10.1.1.547.795

Embed Size (px)

Citation preview

  • 7/25/2019 10.1.1.547.795

    1/16

    The Use of IT in Commercial management of Construction Projects

    M.Sarshar1, A.Connolly2

    Abstract

    The construction industry uses standard off the shelf software packages for

    many of its major activities such as, drawing packages, accounting packages

    and project management packages. Yet standard packages are not used for

    commercial and commercial management aspects of operations, in a similar

    manner.

    The existing packages on the market are diverse and lack functional integrity.

    Some implementations of new commercial software in major companies have

    resulted in grave challenges and risks to the business.

    In order to investigate the reasons, a literature search on the use of IT in the

    construction industry was undertaken. It was found that commercial systems

    have received very little attention and focus from the construction IT research

    community.

    This paper reviews some of the existing literature, in order to emphasise this

    gap in research. It urges further research in this critical aspect of managing

    major projects.

    Key Words: Construction IT, commercial management software, construction

    contract management

    Background

    Commercial management packages within the construction industry are wide-

    ranging and complicated to use. The current packages do not support many

    of the important aspects of the detailed commercial processes. The problem

    1School of Built Environment, Liverpool John Moores University, Byrom Street, Liverpool L3 3AF.

    Tel- 00 44 151 231 2871 Email [email protected]. Bailey,

  • 7/25/2019 10.1.1.547.795

    2/16

    magnifies when companies attempt to implement new systems, where

    companies face significant challenges during the delivery phase of new

    software. Commonly the requirements have been poorly understood and a

    coherent plan for change over has not been devised.

    Commercial management systems appear to vary in design from company to

    company, with the absence of a commonly used IT package that is suitable

    for use in the construction industry as a whole. For the administration of

    construction contracts, much of the administration tasks are standard practice

    with the basic contract administration being governed by The Housing Grants,

    Construction and Regeneration Act 1996. Standard IT packages are greatly

    used in many other industries. The construction industry has adopted some

    standard off the shelf software successfully, such as drawing packages,

    accounting packages and project management packages. Yet, is there

    something significantly different about each construction firm that means IT

    systems can not be developed for commercial management in a similar way?

    Can the systems that are in use be improved further so that time and money

    can be saved? Could the different construction professions and parties to the

    contract integrate their IT systems to save time and money and reduce human

    error? If these systems can be developed why has this not happened yet?

    Faithful & Gould Ltd, a medium sized Quantity Surveying (QS) firm in the UK

    attempted to implement a new commercial management software package for

    the UK wide cost consultancy. A catalogue of errors occurred in the

    implementation of this system leading to dramatic consequences. Faithful &

    Gould Ltd rolled out a new management accounting IT system in circa 1999

    that was to improve their commercial billing and commercial management

    systems and bring about great change and benefits to the company and

    clients alike but, the system roll out was a complete failure. The poor

    implementation strategy that was to manage the change over to the new

    system, meant huge amounts of data was lost and the company struggled to

    bill clients and receive monies into the company accounts as a result. As a

    direct consequence of the failed implementation, Faithful & Gould Ltd came

  • 7/25/2019 10.1.1.547.795

    3/16

    close to bankruptcy. They were subsequently bought by WS Atkins group

    which secured the companys future.

    Walmsley (2007) reports on a catalogue of errors in developing and

    implementing a tailor made commercial system for a major contractor in the

    UK. These errors have led to significant financial impact on the company,

    during the transition. Due to confidentiality issues, many of these problems

    have not been widely reported.

    A literature search into construction IT research reveals that there is little work

    specifically on commercial contract management. This is perturbing as there

    are enough difficulties and disputes in the UK construction industry without

    further hindrance. Many disputes are documented as being caused by poor

    commercial management and administration (Furmston 1996). Many of the

    commercial processes required in construction companies are repetitive and

    the processes are documented in the standard types of construction contracts

    adopted in the UK (Sun 2003). Can basic failures in contract administration

    such as: late payment to suppliers and sub-contractors, lack of payment

    notices, poor change control and lack of final account information be improved

    upon if the IT systems are improved?

    This paper searches the existing literature for some direction and guidelines.

    There are little guidelines. Furthermore some of the few existing suggestions

    appear impracticable. The paper provides an elementary high level

    requirements map for commercial management systems and appeals for

    more research in this critical area.

    ICT in the Construction Industry

    Globalisation of economies brought about by the IT revolution has produced

    large changes in most industries (Baldwin 1998)and led to advanced

    industrial nations trading together is a virtual environment (Brandon 1995).

    Many industries boomed, telecommunications for example, yet others have

    stalled or contracted (Sun 2004).

  • 7/25/2019 10.1.1.547.795

    4/16

    It has been stated that the UK construction industry is seriously lagging

    behind the aerospace, finance and telecommunications industries in the

    development and use of IT (Latham 1999). However, most of the business

    processes and work that surround any construction projects now rely on IT

    systems and tools to design, inform, manufacture, process and communicate

    information and like any other industry where these processes are required, IT

    appears to be utilised (Alshawi 1999).

    In terms of future directions for ICT in the construction industry, Construct IT

    in the UK developed a vision for the use of ICT in the next ten years(Sarshar

    2000 and 2002). This vision was further adopted by CIB Working Commission

    78 (Amor et al 2002). This vision was based on extensive literature search

    and discussions amongst experts and academics. It consists of seven major

    themes:

    1. Model driven as opposed to document driven information management

    on projects.

    2. Life cycle thinking and seamless transition of information and

    processes between life cycle phases.

    3. Use of past project knowledge (/ information) in new developments.

    4. Dramatic changes in procurement philosophies, as a result of the

    internet.

    5. Improved communications at all life cycle phases, through

    visualisation.

    6. Increased opportunities for simulation and what if analysis.

    7. Increased capabilities for change management and process

    improvement.

    These themes do not include any intention to research into the key legal

    aspects the standard contracts and the constraints these impose on the use

    of IT in the construction industry (Amor et al2002). This clearly has a bearing

    on the research directions of the construction ICT community.

    Another key researcher in this area, Alshawai (1999), has provided a review

    of the application and use of IT in the construction management of projects

  • 7/25/2019 10.1.1.547.795

    5/16

    from an industry and research perspective. He gave an overview of major

    functions and impact of IT to the general performance. It was recognized that

    post contract functions are highly dependent on gathering and presenting

    information; this is costly and time-consuming and the processes that are

    undertaken to fill these functions are usually unstructured. Manipulation of

    information can not be done manually it needs to be managed electronically

    and presented with the correct level of detail. Alshawi (1999) mentions

    producing reports in the study varied in structure from one site to another and

    that information sent to head office was in different formats and he suggested

    process re-engineering is required before successful implementing patient of

    IT.

    Alshawi (1999) suggests deregulation of professional roles and organisational

    systems in order to increase competition between professions. The authors

    question if this suggestion, as deregulation of professional roles and

    organisational systems will result in people being unsure of their job roles

    limits and where their boundaries are. Another suggestion was that clients

    should demand a better service. The authors are in full support of this

    proposal, however Alshawi (1999) continues to claim that the client should be

    more aware of the industry's failings. The author questions if this is a positive

    step. This study also stated that the industry must realise that they were

    facing long-term recession and overcapacity. However RICS indicates that

    quantity surveyors are in great demand (RICS 2000).

    In short advances in ICT are not likely to be a key driver in imposing major

    change in the current structures of the industry. ICT systems need to respond

    support current structures and professions, reducing the barriers between

    professional communication, rather than eliminating professions altogether.

    Carter conducted an EU funded research (titled eLEGAL) on the use of ICT in

    construction contracts. His findings demonstrate that Paper is still used in for

    the use of large quantities for the administration of contracts but this is not

    due to an unwilling construction industry, simply the failure to establish legal

    qualification within contracts (Carter et al2001). Carter et all(2001)

  • 7/25/2019 10.1.1.547.795

    6/16

    recognised that advances in IT could be used to enable the construction

    industry to manage large construction and engineering projects by way of

    assisting the co-ordination of the virtual enterprises that often are used.

    Carter et al(2001) also recognised that that there were several areas of legal

    uncertainty that threatened the adoption of such advances for the

    management of contracts and undertook a study called eLEGAL. Carter et al

    (2001) was aware that without some acceptance of and a move towards

    defining IT as legally admissible then many areas that could benefit from the

    use of IT would not be able to gain from such assistance. Legislation is now

    able to support the use of IT in business throughout the EU but, the standard

    forms of contract adopted in the UK Construction Industry do not make

    provision for the use of IT as yet and therefore, the eLEGAL project concluded

    that the use of IT to support contract practices may not be admissible (Carter

    et al2001). According to Carter et al (2001) the construction industry is failing

    to adopt IT for the management and administration of contracts.

    Since Carter et al(2001) wrote the Industry failing to adopt IT for the

    administration of documents the, JCT 2005 has been published and the new

    suite of contracts does make some provision for IT to be included within the

    contract (JCT 2005). Claus 18.1 allows the parties to agree the medium for

    which communication and general administration of the contract can be

    undertaken. However, in the guide notes to the JCT 2005 suite of contracts it

    is mentioned that the contracts did not go further to adopt and supports the

    use of IT for the management of contracts as there remains much

    disagreement within the Construction Industry to its legality and authority.

    Managing Change, Implementing New Systems

    Another premise of this paper is that several construction companies have

    faced critical challenges in implementing new commercial management

    systems. For this reason some literature in change management during the

    introduction of new systems were examined to establish if this problem is only

    limited to commercial management systems. This was certainly not the case,

  • 7/25/2019 10.1.1.547.795

    7/16

    and there is much to learn from change management literature.

    In a study of a large project, the new Terminal 5 at Heathrow Airport, two

    types of innovation were identified, bounded and unbounded (Harty 2005).

    The research team aimed to explain an alternative way to understanding the

    unbounded innovations within the construction industry using sociology of

    technology concepts. The study was seen as an exciting opportunity as there

    was to be 500 or more contractors on site and was known as one of the

    biggest construction projects in the world at that time. Harty (2005) explains

    that the employer (BAA) for the project was keen to role out a new system of

    3D Auto CAD. The study was undertaken over an 18 month period on site.

    One of the findings of the study was that the system to be implemented was

    not actually capable of delivering the ideas or visions of BAA. The 3D

    AutoCAD system did not have the functionality to carry out the tasks required

    of the engineers and drafters and the system could not be used for drafting

    design as well as manufacture (Harty 2005).

    The system integration methods in the study of Heathrows Terminal 5

    alienated some users and break out systems developed as the staff were

    determined to carry out their duties and get the project completed successfully

    (Harty 2005). The break off systems developed to enable actors to work

    rather than wait for further development of the software systems (Harty 2005).

    Harty (2005) did not investigate attitudes to change and adoption of the vision

    and there were no references to the attitudes of the employees and sub-

    contractors to the adoption of the vision. These factors are interdependent to

    the success of any change (Hazzan 2004).

    Harty (2005) Quotes:

    The focus groups were an attempt at alignment. Efforts were being made to

    engineer a built victory generously a system of 3-D CAD software and

    practices but crucially with more than one system builder and with a number

    of ideas and visions informing its assembly none of which had the ability to

    override others or persuade them to change.

  • 7/25/2019 10.1.1.547.795

    8/16

    Harty (2005) did not mention if the rank structure was in place, if any prior

    discussions had been undertaken with the team members or if focus groups

    were set up. Similar research was carried out to explore the problems with

    introducing any form of management led change; aimed at understanding

    change within project-based organisations (Bresnen 2005). Bresnen (2005)

    explains that the research was conducted by applying a framework to two

    case studies on two separate UK companies that were applying management

    led change in the form of new IT Systems. The study also analysed the

    reaction by the project centralised team to resist the change. The author

    questions why they only investigated the resistance to change and not items

    or issues that inhibited the change in order to understand any resistance

    found. Bresnen (2005) also found that the diversity of the project managers

    systems throughout each company, as well as their attitudes, had

    considerable influence on whether the systems were accepted and therefore

    successful adopted by the firm as a whole (Bresnen 2005).

    The difference between project-based organisations compared with other de-

    centralised organisations is the practices of each and, therefore the spread of

    power of each are different (Bresnen 2005).

    Bresnen (2005) states that this results in the implementation of change

    throughout a company is more difficult as a result and will vary across the

    regions.

    There needs to be a sharing of interest between the project teams and head

    office management (Bresnen 2005). Implementation is more successful when

    management are selective to who can be included in planning and

    implementing change within an organisation (Hazzan 2004). Those

    considered as best of breed should be chosen to help implement the

    changes they will have greater knowledge of what is required (Katranuschkov

    2006). Least resistance is encountered from those who have the power and

    knowledge of the new systems, if they are able to put this knowledge to use

    (Hazzan 2004). Alpha project managers remained outside the system in a 'not

  • 7/25/2019 10.1.1.547.795

    9/16

    broken doesn't need fixing' attitude to what was seen as a redundant system.

    When involving project managers, those who were respected by their peers

    the resistance to change was influenced by these individuals (Bresen 2005).

    Project Managers that didn't meet regularly could not share their opinions or

    knowledge to influence change positively. However; they also couldn't gain

    solidarity to resist the changes being implemented (Fernie 2006). Successful

    change reinforces and does not undermine existing systems (Hazzan 2004).

    Project Managers have admitted fictitious reporting to show head office only

    the successful results (Bresnen 2005). Bresnan (2005) identifies that it is

    important for the senior management and the project managers at regional

    level to have the same goals to overcome this. However, Bresnan (2005) did

    not mention if that those who implemented the change first improved the

    processes or if there was an incentive to succeed, such as the bonus scheme.

    Woodward et al (1994) studied change management during the

    implementation of a cost management system. The purpose of the study was

    to describe the philosophy behind the need for change (Woodward et al

    1994). However, there is no mention of whether the study was a success.

    The findings of Woodwards study are inconclusive and the research

    methodology questionable. Woodward et al(1994) claims that the traditional

    role of a quantity surveyor cannot adequately cover the cost management

    discipline in today's construction industry and that this adds to the cause of a

    budget overspend. The authors questions this finding as the role of the

    quantity surveyor is dependent upon the work given to the quantity surveyor

    from the employer. It is too simplistic to rule out the role of the quantity

    surveyor.

    Procuring Commercial management Software

    There are various software solutions on the UK market that are developed to

    aid the management of contracts. Many software suppliers to the construction

    industry now offer impressive solutions that are delivered as modules or

    packages that can be bolted together to form a fully integrated business IT

  • 7/25/2019 10.1.1.547.795

    10/16

    system. The quantity of suppliers that produce and sell such products and

    services in the UK are so vast nowadays, it is not possible to list all of the

    products on the open market. On the whole the IT suppliers advertise their

    products as standard package software that is already designed and

    developed specifically for the construction industry, which can be tailored

    upon delivery to meet the customers individual requirements. This is a

    credible way of ensuring their construction company customers are satisfied

    with the product they have purchased and is aimed at delivering products that

    will meet the individual business requirements of the construction orientated

    customer at a cost much less than that of the bespoke software. (McConnell

    1997).

    It is therefore critical for construction companies to fully capture the

    requirements of their systems before they embark on purchasing new

    software, and test their software against these requirements. The range of

    task within the management of contracts is extensive and contracts are

    stipulated in many areas by the constraints of timetables and stipulated dates

    within a contract. It is important that the procedures and tasks to be carried

    out are done so in an efficient manner if the required documents and

    information is to be presented and the tasks are to be completed satisfactorily

    by these deadlines. Failure to meet these deadlines can incur financial

    penalties imposed by the contract and, result in a breach of the law pertaining

    to the administration and government of construction contracts (Brandon

    1995).

    The administration and management of the construction contracts are not the

    only procedures and tasks a construction company has to undertake. There

    are many other business management procedures that are required for the

    firm to function successfully. These processes are required for a department

    to function. Fig 1 illustrates an overview of the departments generally

    required within a construction firm, although this can differ from company to

    company. There is a need for some level of integration between the activities

    of some of these departments.

  • 7/25/2019 10.1.1.547.795

    11/16

    Fig 1 Typical departments within a construction company

    Focusing only on the management of contracts, a summary of the common

    processes involved is shown in Fig. 2. This figure highlights the range of

    tasks expected as a minimum, although some variance to this is probable,

    dependant on the stipulations within a particular contract.

    CompanyDepartments

    Marketing and Business

    Development

    HumanResources

    ProjectManagement

    QualityAssurance

    Health and

    Safety

    IT Management

    Accounts andFinance

    CommercialManagement

  • 7/25/2019 10.1.1.547.795

    12/16

    Fig 2 Range of tasks within a contract.

    Each of the above procedures can consequently been expanded into more

    detail. Figure 3 provides an example:

    Receipt & LegallyChecking Documents

    ReturningDocuments

    Set UpOn System

    PracticalCompletion

    Purchasing

    Sub-contracting

    Cost ReportingCVR

    Contract

    Applications

    Labour

    Management

    FinalAccounts

  • 7/25/2019 10.1.1.547.795

    13/16

    Fig 3 Description of ideal variation management system

    In order to capture the requirements adequately, and be able to test and

    implement the eventual system effectively, there is a body of knowledge in the

    software industry, termed the Systems Development Life Cycle. In this

    approach the development of an IT system is divided into several stages

    (Tomayko et al2004). These stages together called the development

    lifecycle (Maher 2006). The management of an ideal development project is

    extremely complicated and therefore the stages are broken down into

    manageable chunks (Sommerville 2007).

    The construction industry needs to utilize such approaches in order to reduce

    the risk of introduction of new commercial management software within the

    business.

    Future Directions

    MaterialDepartment

    CostReporting

    CVRSub-contractor costs

    Labour info

    VO costs

    SOR info

    Variation submissionVariation description

    Material description

    Material cost

    QuantitySurveyor

    ProjectManagement Files

  • 7/25/2019 10.1.1.547.795

    14/16

    This paper explored set out to explore the construction IT literature, in order to

    explore how to improve the procurement and implementation of commercial

    management systems in the construction industry.

    It became obvious that the main body of construction IT literature has paid

    little attention to commercial and legal aspects of managing projects. When

    there are references, on several occasions the role of the QS has been

    questioned and dismissed. This is contrary to real-life evidence that there is a

    shortage of QSs in the UK and the demand for this profession is increasing,

    even though the role is becoming more strategic.

    Many companies have had problems in implementing new commercial

    management systems. Here the picture is different and there is a large body

    of literature which the industry can learn form. In particular the literature on

    change management and also in software development address similar

    problems and can add value.

    There are still many unresolved questions, which researchers need to

    investigate. For example:

    What does the construction industry require of a commercial

    management system?

    Do these requirements remain the same for each construction

    company or can there be a standard solution?

    Do the current commercial management systems used in large

    construction firms deliver their key requirements?

    How do construction companies monitor their systems effectiveness

    and further develop their IT systems to meet the needs of the

    company?

    How will commercial management systems integrate with other key

    construction applications, such as drawings and accounting?

    There is a critical need to shift the focus of the construction IT research to

    include this all important topic.

  • 7/25/2019 10.1.1.547.795

    15/16

    References

    Alshawi, M., Underwood, J. (1999) The Application of Information Technology

    in the Management of Construction.The Royal Institution of Chartered

    Surveyors. This reference is incomplete. You need to identify which RICS

    publication.

    (Amor 2002) This reference is missing

    Baldwin, A., Betts, M., Blundell, D., Hansen, K., Thorpe, T. (1998) Measuring

    the Benefits of IT Innovation.Construct IT Centre of Excellence.

    Brandon, P., Betts, M. (1995) Integrated Construction Information.Padstow,

    T.J. Press (Padstow) Ltd, 1st Ed.

    Bresnen, M., Implementing change in construction project organisations,

    Building Research & Information, Volume 33 NO 6, p547-560.

    Carter, C., Hassan, T., Merz, M., White, E. (2001) The Elegal Project

    Specifying Legal Terms of Contract in ICT Environment.

    http//www.itcon.org/2001/12/

    Furmston, M, 1996. Contract, Tort and Construction Disputes. Construction

    Law, 5 (3), pp. 81-82.

    Harty, c., A sociology of technology approach, Building Research &

    Information, Volume 33 NO 6, 512-522.

    Hazzan, O., Tomayko, J.E. (2004) Human Aspects of Software Engineering.

    United States of America, Charles River Media, 1st Ed.

    Katranuschkov, P., (2006) Process Modelling, Process Management and

    Collaboration.http//www.itcon.org/33/

    Latham, M. (1994), Constructing The Team: Final Report, HMSO, London.

  • 7/25/2019 10.1.1.547.795

    16/16

    McConnell, S. (1998) Software Project Survival Guide.United States of

    America, Microsoft, 1st Ed.

    RICS 2000).This reference is missing

    Sarshar, M., Abbott, C., Aouad, G., A Vision for Construction IT 2005-2010,

    RICS (Royal Institute of Chartered Surveyors) Research Series, Dec 2000.

    Sarshar, M., Tanyer, A., Aouad, G., Underwood, J., A Vision for Construction

    IT 2005-2010: Two Case Studies, Engineering, Construction & Architectural

    Management, Issue 2, April, 2002.

    Sommerville, I. (1982) Software Engineering.Harlow, Pearson Education

    Limited, 8th Ed.

    Sun,M. Howard,R. (2003) Understanding I.T. in Construction.London: Spon

    Press.

    Tomayko 2004 This reference is missing

    Walmsley, M., (2007), Critical analysis of the implementation of a major

    commercial system, within a large contractor, UG dissertation, Liverpool John

    Moores University, April 2007.

    Woodward et al(1994) This reference is missing