32
Contract Number: P1007 File Reference 1007-DISQ-0-E-SS-27011-Rev.2 Page 1 of 32 RWE Dea Disouq Field Development FEED Specification for Power Generators GEN-01, GEN-02 and GEN-03 1007-DISQ-0-E-SS-27011 2 29.03.12 Issued for Design A Saleh A Fawzi A Hamdan RWE 1 11.03.12 Issued for Client Approval A Saleh A Fawzi A Hamdan RWE 0 26.10.11 Issued for Client Review A Saleh A Fawzi A Hamdan RWE Rev Date Description Issued By Checked By Approved By Client Approval

1007 DISQ 0 E SS 27011 Specification for Power Generators (GEN 01, GEN 02 and GEN 03)

Embed Size (px)

DESCRIPTION

lkmlml

Citation preview

Contract

Number: P1007

File Reference

1007-DISQ-0-E-SS-27011-Rev.2

Page

1 of 32

RWE Dea

Disouq Field Development

FEED

Specification for Power Generators

GEN-01, GEN-02 and GEN-03

1007-DISQ-0-E-SS-27011

2 29.03.12 Issued for Design A Saleh A Fawzi A Hamdan RWE

1 11.03.12 Issued for Client Approval A Saleh A Fawzi A Hamdan RWE

0 26.10.11 Issued for Client Review A Saleh A Fawzi A Hamdan RWE

Rev Date Description Issued By Checked By Approved By

Client Approval

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 2 of 32

Table of Contents

1 Introduction ............................................................................................................... 5

1.1 Background .............................................................................................................. 5

1.2 Objective .................................................................................................................. 6

1.3 Definitions ................................................................................................................. 7

1.4 Abbreviations ............................................................................................................ 8

2 Codes and Standards ............................................................................................. 10

2.1 General ................................................................................................................... 10

2.2 Order of Precedence .............................................................................................. 10

2.3 EC Directives .......................................................................................................... 10

2.4 Project Documents ................................................................................................. 11

2.5 International Codes and Standards ......................................................................... 11

3 Scope of Supply ..................................................................................................... 13

4 Equipment Operating Conditions ............................................................................ 14

4.1 Electrical Equipment Location ................................................................................. 14

4.2 Environmental Design Data .................................................................................... 14

5 Design Requirements ............................................................................................. 15

5.1 General ................................................................................................................... 15

5.2 Operational Requirements ...................................................................................... 15

5.3 Design Features ..................................................................................................... 16

5.4 Excitation System ................................................................................................... 16

5.5 Enclosures and Materials ........................................................................................ 16

5.6 Cooling System ...................................................................................................... 17

5.7 Bearings ................................................................................................................. 17

5.8 Terminal Boxes ....................................................................................................... 17

5.9 Noise Levels ........................................................................................................... 18

5.10 Emission Levels ...................................................................................................... 18

5.11 Generator Protection and Control Panel ................................................................. 18

5.12 Annunciation, Alarm and Shutdown ........................................................................ 19

5.13 Manual/Auto Start ................................................................................................... 19

5.14 Secondary Wiring ................................................................................................... 20

5.15 Cable Terminations ................................................................................................. 20

5.16 Electric System Metering ........................................................................................ 20

5.17 Contacts ................................................................................................................. 21

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 3 of 32

5.18 Synchronizing System ............................................................................................ 21

5.19 Governor ................................................................................................................ 22

5.20 Requirements for Parallel Operation ....................................................................... 22

5.21 Current Transformers ............................................................................................. 22

5.22 Voltage Transformers ............................................................................................. 22

5.23 Battery and Charger Assemblies ............................................................................ 23

5.24 Accessories ............................................................................................................ 24

5.25 Nameplates ............................................................................................................ 24

5.26 Electrical Immunity .................................................................................................. 24

5.27 Disturbance Immunity ............................................................................................. 24

6 Painting .................................................................................................................. 25

7 QC Inspection and Testing ..................................................................................... 25

7.1 General ................................................................................................................... 25

7.2 Generator QC Tests ............................................................................................... 25

7.3 Battery and Charger QC Inspection and Testing ..................................................... 26

7.4 Generator Control Panel QC Test ........................................................................... 27

7.5 Package String QC Test ......................................................................................... 27

7.6 Site Acceptance QC Test ........................................................................................ 27

8 Documentation ....................................................................................................... 28

9 Preparation for Shipment ........................................................................................ 29

10 Storage Locally and Shipping ................................................................................. 29

10.1 Weight .................................................................................................................... 29

11 Vendor's Responsibility and Guarantees ................................................................ 29

12 Site Installation Assistance, Commissioning and Start-Up ...................................... 30

13 Spare Parts............................................................................................................. 31

12.1 Pre-commissioning and Commissioning Spare Parts .............................................. 31

12.2 Two Years Spare Parts ........................................................................................... 31

14 Health, Safety and Environmental Management ..................................................... 31

15 Quality Assurance................................................................................................... 32

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 4 of 32

Changes List

Rev. Date

prepared (DD.MM.YYYY)

Prepared by Description

1 06.03.12 ASaleh Incorporated client comments

2 29.03.12 ASaleh Incorporated client comments

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 5 of 32

1 Introduction

1.1 Background

RWE Dea Egypt has discovered seven natural gas reserves in the Disouq Concession within the onshore Nile Delta, starting in 2008, as shown on the concession map below. Further exploration in the concession is ongoing. RWE Dea Egypt is the operator of the Concession with EGAS as a partner.

The selected development comprises a central gas treatment plant near NSG-1x, where the gas is collected, treated by means of Low Temperature Separation utilizing the Joule Thomson effect to achieve gas quality, and compressed for export. Treated gas is transferred via a 16” pipeline directly into the GASCO NTS pipeline. The well fluids are gathered and fed to a common inlet separator at the central plant. All gases and liquids will be separated and processed on the central treatment plant into sales gas, stabilized condensate and free production water. Treatment of gas is carried out in two trains, while treatment of condensate is in a single train. Three trains of sales gas compression shall be installed. Fuel gas for the gas engine drive power generators will be taken from the suction of the sales gas compressors.

Main Electrical power shall be generated and supplied by two Gas driven generators 400 Volt, 3-phase, 4 wire, 50 Hz, 2000kVA each, with one generator running and one in standby. Both Gas driven generators will be connected to the 400 Volt AC, 50Hz Low Voltage Power Motor Control Centre (PMCC). One Emergency Diesel Generator 400Volt, 3-phase, 4 wire, 50Hz, 500kVA shall feed the emergency loads via the Low Voltage Emergency Power Motor Control Centre (EPMCC) in case of a loss of gas production.

One gas driven generator shall feed all plant loads with the second gas driven generator on stand by. Main electrical power with one gas driven generator running will be distributed via

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 6 of 32

the Power Motor Control Centre (PMCC) and the Emergency Power Motor Control Centre (EPMCC).

All generators (Gas driven and Diesel driven) shall have the ability to synchronize for maintenance purposes.

The PMCC and EPMCC shall be designed for the parallel operation of one gas driven and one diesel driven generator but not for continuously parallel operation of the two gas driven generators. Synchronisation of the both gas driven generators is purely required in case of maintenance of one gas driven generator set to prevent a production stop and to bring the second gas driven generator online before shutting down the one driven generator set.

A manual and fully automatic synchronization unit shall be installed on each power generation skid. Central Treatment Process Plant loads will be connected with the Power Motor Control Centre, the Emergency Power Motor Control Centre and the UPS distribution panel as shown on the Single Line Diagrams MCC, PMCC, EPMCC and UPS (1007-DISQ-0-G-DW-30089).

Preliminary Process Plant loads as result of the FEED are shown on Electrical Load List (1007-DISQ-0-G-LL-30090).

One gas driven generator as main and normal power supply will feed process plant loads such as:

Motors.

Package units.

Buildings normal lighting distribution panels and welding socket outlets in the

Workshop, Warehouse, Control building, Fire pump station, Substation

building and chemical storage building.

External lighting distribution panels.

Control building UPS. (located in Control Building)

Compressors UPS. (located on Compressor Skid)

Flare UPS (Located near the Flare)

Plant loads are preliminary estimations as result of FEED design and will be finally determined during detail design by the detail design contractor and the vendors of packages..

In Normal operation with the one gas driven generator running the emergency loads shall be fed via the PMCC and EPMCC. In case of loss of this normal supply, the emergency diesel generator shall start automatically to feed the emergency loads of the process plant only without black out.

The Emergency power motor control centre shall feed the emergency plant loads as shown on the single line diagrams“1007-DISQ-0-E-DW-30089”.

Preliminary Emergency plant loads are shown on electrical load list “1007-DISQ-0-G-LL-30090”.

1.2 Objective

This specification defines the minimum requirements for the design, construction, painting, inspection, testing, documentation, preparation for shipment, pre-commissioning and commissioning and start-up of Gas and Diesel generator(s)and associated control panel(s) to

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 7 of 32

be used for main and emergency power generation (as specified in data sheet). These generator(s) shall be coupled to two Gas driver(s) and one Diesel driver to form uniform packages as generating sets with fully automated and manual synchronization panels, control panel with small UPS, main CB, switchboard, F&G detection, Automated Fire Extinguishing and ESD system and independent starting system for engines with batteries and electronically controlled charger.

Each Power Gen set package to be fully functional stand alone as well as integrated into the power and control system architecture of the Central Treatment Plant as shown on the single line diagrams and control system architecture drawing.

Each package to be configured and equipped with all required control equipment and protection systems for single as well as parallel operation and load sharing with automatic and manual start locally as well as remotely.

Each Package control system shall communicate with the central treatment plant control system via redundant communications link and if required via internal packages communications link between all three packages (to be confirmed by vendor).

On board ESD system shall be designed as standalone SIL rated safety system (vendor shall confirm SIL level in accordance to package HAZOP) which can receive SIL rated hardwired ESD signal from ICSS for package shut down in case of ESD plant shut down.

The package F&G system shall be designed as standalone SIL rated safety system, shall activate the package Fire fighting system and report its status to the plant F&G system as part of the ICSS.

Interfaces and utilities are to be minimised for each package as follows:

1. Electrical Power output ( 400 Volt, 3-phase and Neutral , 50 Hz ) 2000kVA each gas

engine and 500kVA diesel engine

2. One Auxiliary Power input ( 400 Volt, 3-phase, Neutral, Earth, 50 Hz ) for each

package for all auxiliary circuits for control and power circuits on the package

3. Hardwired ESD signal from ESD system of ICSS to each Package Control ESD

system

4. Hardwired F&G status signals from each package to F&G system of central ICSS

5. Redundant Communications link for data transfer to/from the central DCS

6. Instrument Air as required

7. Interconnecting communications and shutdown links between the three genset

packages as required

For an overview of the Electrical System refer to Single Line Diagrams for MCC, PMCC, EPMCC and UPS (1007-DISQ-0-G-DW-30089). For an overview of the Control system refers to Control System Architecture Central Treatment Plant (1007-DISQ-0-G-DW-30036).

For the Electrical System Design Philosophy utilised throughout the project refer to document number (1007-DISQ-0-G-MA-30088) and for the Control system Philosophy refer to document number (1007-DISQ-0-G-MA-30092).

1.3 Definitions

The following definitions are generic to the Disouq Field Development Project and may be referred to in this document:

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 8 of 32

Company RWE Dea Nile Branch

FEED Engineer ONSPEC

Detail Design Contractor Contractor appointed by the Company for the detail engineering and construction phase of the project.

Purchaser Company.

Supplier/Vendor The manufacturer, seller or supplier of equipment.

Project Disouq Field Development Project

Independent Verification Body Inspection Body or Authority appointed by the Company

1.4 Abbreviations

A Ampere A.C. Alternating Current ATEX Directive for the supply and use of equipment in potentially explosive

atmospheres (Atmosphere EXplosive) AVR Automatic Voltage Regulator BS British Standard CB Circuit Breaker CT Current Transformer D.C. Direct current DCS Distributed Control System EC European Commission EGAS Egyptian Natural Gas Holding Company EMC Electromagnetic Compatibility ESD Emergency Shut Down FEED Front End Engineering and Design F&G Fire and Gas GASCO Egyptian Natural Gas Company HAZOP Hazard and Operability Study HBCF High Breaking Capacity Fuse HMI Human Machine Interface HRCF High Rupturing Capacity Fuse ICSS Integrated Control and Safety System IEC International Electrotechnical Commission I / O Input / Output IDC Inter Discipline Check IP Ingress Protection ISO International Organisation for Standardisation ITP Inspection and Test Plan

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 9 of 32

kVA kilovolt Ampere ( apparent power ) kVar kilovolt Ampere reactive ( reactive power ) kW kilowatt (active power ) LCU Local Control Unit LED Light Emitting Diode L.V. Low Voltage (≤1000V A.C.) MCC Motor Control Centre MCCB Moulded Case Circuit Breaker mm millimetre NTS National Transmission System PE Protective Earth p.f. power factor QA Quality Assurance QC Quality Control QP Quality Plan RTD Resistance Temperature Detector RWE Dea Rheinisch Westfaelisches Elektrizitaetswerk Deutsche Erdoel

Aktiengesellschaft SIL Safety Integrity Level TTA Type Tested Assembly UCP Unit Control Panel Ue Rated Operational Voltage Ui Standard Insulation Voltage Un Nominal Voltage C.T. Current Transformer V.T. Voltage Transformer

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 10 of 32

2 Codes and Standards

2.1 General

The design, construction and supply of the equipment shall be in accordance with the relevant sections of the latest editions, including addendums, of the international codes and standards and shall comply with the latest revisions of project documentation detailed below. In general, the electrical work shall be in accordance with the IEC standards. Where no appropriate IEC standard exists, British Standards shall be used. Electrical components for incorporation into the installation shall comply with the relevant IEC standards. These shall be selected to exclude readily combustible insulating and constructional material and excessive heat generation. Electrical and mechanical reliability is of the utmost importance. All electrical components shall be tested to the relevant IEC standards.

2.2 Order of Precedence

In the event of any conflict between this specification and the documents listed herein, the decreasing order of precedence shall be:

1. Purchase Order and amendments thereto 2. Data Sheets 3. This Package Specification 4. Other Referenced Project Specifications 5. Egyptian National/Local Codes and Standards 6. International Codes and Standards

2.3 EC Directives

The equipment shall be supplied in accordance with all applicable European Community Directives. Particular attention shall be paid to:

Electromagnetic Directive 2004/108/EC & 89/336/EC

Low voltage Directive 2006/95/EC

General Product Safety Directive 2001/59/EC

CE marking 93/68/EC

ATEX 95 Equipment Directive 94/9/EC

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 11 of 32

2.4 Project Documents

Project Documents consist of the following:

Document Number Description

1007-DISQ-0-G-DW-30089 1007-DISQ-0-E-RT-27013 1007-DISQ-0-E-SS-27027 1007-DISQ-0-E-DS-27029 1007-DISQ-0-G-MA-30088 1007-DISQ-0-E-DS-27031 1007-DISQ-0-E-DS-27032 1007-DISQ-0-J-SS-33054 1007-DISQ-0-F-G-SP-10014 1007-DISQ-0-P-RT-48138 1007-DISQ-0-G-DW-30036 1007-DISQ-0-G-MA-30092 1007-DISQ-0- G-LL-30090 1007-DISQ-0-E-SS-27023

1007-DISQ-0-P-PH-48071 1007-DISQ-0-F-DW-10012 1007-DISQ-0-M-SS-42008 1007-DISQ-00-QP--1008 1007-DISQ-00-F-QA-1007 1007-DISQ-0-L-DW-39000 1007-DISQ-0-F-SS-10018 1007-DISQ-0-L-SS-39004

Single Line Diagrams for MCC,PMCC,EPMCC and UPS Short Circuit Calculation Report Motor Control Centre Specification PMCC and EPMCC Motor Control Centre Data Sheet Electrical System Design Philosophy Gas Engine Synchronous Generators Data Sheet Diesel Engine Synchronous Generator Data Sheet PLC Specification for Packages F&G Requirement Specification Fire & Gas Cause & Effect Control System Architecture Central Treatment Plant Control System Philosophy Electrical Load List Electrical Specifications for Packaged Equipment Shutdown Philosophy Hazardous Area Classification Layout Gas /Diesel Engine Specification Project Quality Plan QA Plan Plot Plan - CTP Specification for Equipment Noise Control Specification for Painting and Protective Coatings

2.5 International Codes and Standards

As a minimum, the equipment shall be designed, manufactured, tested and delivered in accordance with the relevant sections of the latest editions of the international codes and standards. Codes and standards used for this project shall be the latest revisions including all addenda available at the time of purchase order placement and shall include but not be limited to the following:

Document Number Description IEC 60034 Rotating Electrical Machines. IEC 60034-1 Combined Frequency and Voltage Variations IEC 60051 Direct-acting Indicating Analogue Electrical Measuring

Instruments and Their Accessories. IEC 60038 IEC Standard Voltages IEC 60044-1 Instrument Transformers. Part 1: Current Transformers IEC 60044-2 Instrument Transformers. Part 2: Inductive Voltage

Transformers IEC 60050 International Electrotechnical Vocabulary IEC 60072 Dimensions and Output Series for Rotating Machines. IEC 60085 Thermal Evaluation and Classes of Electrical Insulation. IEC 60185 Current transformers Characteristics IEC 60186 Voltage Transformers. IEC 60255 Electrical Relays. IEC 60529 Classification of Degrees of Protection Provided by

Enclosures.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 12 of 32

IEC 60947 Low Voltage Switchgear and Control Gear. IEC 61000 Electromagnetic Compatibility (EMC). ISO 8528 Reciprocating Internal Combustion Engine Driven

Alternating Current Generation ISO3046 Reciprocating Internal Combustion Engines BS5000 Specification for Rotating Electrical Machines of Particular

Types or for Particular Applications BS7626 Specification for current transformers NEMA MG-1/22 Motors and Generators

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 13 of 32

3 Scope of Supply

The scope of work includes, but is not limited to, the following items:

The detail design, manufacture and supply of three power generators as detailed in this specification, referenced Data Sheets and Single Line Diagrams

The detail design, manufacture and supply of all necessary ancillary equipment, special tools and spare parts for pre-commissioning and commissioning/start-up, whether specified or not, to provide a complete, functional system at Disouq CTP site.

The preparation and supply of all documents so that detail design contractor can easily incorporate such information and related components (e.g. generator control panel) into the overall design of the Project

The factory inspection QC and testing of all equipment and items. The System integration test with all power generator packages and the ICSS and a final Site Acceptance Test inclusive performance test. This includes the provision of appropriate test certification and procedures (Factory Acceptance- , System integration- and Site Acceptance - Test procedures).

Preparation for transport and shipping. All items shall be securely packed and fully protected against damage

Site supervision during installation and hook up.

Pre commissioning, commissioning, start-up and performance test of UPS system on site

The coordination and integration of all parts which interface mechanically, electrically or electronically with Vendor system. Also, the Vendor shall ensure the transfer of data between himself and the Vendor of the ICSS package(s) as required and shall attend interface meetings and system integration tests with ICSS Vendor.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 14 of 32

4 Equipment Operating Conditions

4.1 Electrical Equipment Location

The generator(s) shall be suitable for outdoor installation in the Central Treatment plant as shown on the Plot Plan (1007-DISQ-0-L-DW-39000). The Vendor shall provide each generator engine combination as a standalone Skid or containerized if this is the standard solution preferred by vendor. The generator control panel(s) shall be suitable for installation in an air-conditioned switchgear and control room or within the package container as per supplier standards. In all cases the control panel must be designed for safe and reliable operation in the absence or failure of air conditioning system.

4.2 Environmental Design Data

The local climate conditions are as stated below: Location: Egypt Lower Nile Delta Elevation: +/- 5 m Ambient Temperatures 0°C to 35 °C, max. 50 °C Av. Air Humidity 60 to 75% Average Rainfall app. 200 mm/ year with possible showers

during Nov-March Seismic Zone moderate risk, 10% probability to exceed

0,8 m/s² ground acceleration in 50 years Wind Speed & Direction

Earthquake Zone

Predominant NW direction; max. 39-44 m/s Zone 2

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 15 of 32

5 Design Requirements

5.1 General

The generator shall be a brushless 400 Volt A.C., 50 Hz synchronous type, self-air cooled, with direct connected, shaft mounted and permanent magnet exciter.

The alternator shall be rated for continuous duty in accordance with ISO8528, ISO3046, IEC60034, BS5000 and MG-1/22 at the engine’s rated output and a power factor of 0.8. The stator windings shall be provided with class F insulation while the operating temperature shall be designed to be 120 °C at the maximum output and site conditions. Rotor windings shall be provided with class H insulation. The alternator and exciter shall be air cooled.

The set shall be provided with electronic governor and AVR systems.

The generator shall be designed for remote start / stop and status monitoring from the central control room.

The set shall contain its own starting system and be suitable for black start.

Under all condition the voltage and frequency shall be maintained within limits as specified on the data sheet of 1.0 per unit (i.e. 400V load and 50Hz) by the generator control system.

Load share, load management and synchronization between the generator sets when in parallel operation, shall be provided by the generator Unit Control Panels (UCP’s).

Full load voltage levels for Disouq field development project system shall be as follows: -

400V, 3 phase, 4-wire, 50 Hz, neutral point solidly earthed at the PMCC & EPMCC

230V, 1 phase, 50Hz, single phase & neutral derived from phase to neutral at sub distribution boards.

Embedded RTD's (3 per generator, one in each winding) with alarm and shutdown signals shall be provided for stator temperature measurement, another set of spare RTD (3 per generator, one in each winding) shall be embedded and wired to spare terminal box ready for connection in case of any RTD failure of used one.

The generator shall be equipped with anti-condensation space heaters for operation on 230 Volts, single phase, 50 Hz. The space heaters shall be suitable for the area classification and shall be provided with a separate terminal box.

Vendor shall provide two diagonally opposite earthing copper bars to receive all the package Electrical equipment earthing wires by Vendor. The copper bars should be ready to receive external earthing connections suitable for 95 mm2 earthing cable of the main earthing plant grid.

5.2 Operational Requirements

The rated power output of the generator, rated voltage and frequency shall be as shown on data sheet. The generator shall deliver the specified output at the maximum derating conditions (maximum ambient temperature and full load) without exceeding 120 deg C.

The generators and associated equipment expected lifetime duration shall be minimum 25 years. The generator should deliver the rated power output specified on the data sheet on a continuous basis of 24 hours per day, for a period of at least 4 years without maintenance and a minimum of 2000 hours without minor service required.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 16 of 32

5.3 Design Features

Generator shall be able to operate withstand an over speed of at least 25% of rated speed. An over speed time of two minutes is an acceptable design and test figure.

Generator shall be designed to withstand without exceeding the maximum allowable temperature limits:

- A stator current of 110% of rated current for one hour every 12 hour operation

period at rated voltage, rated frequency and rated power factor.

- A stator current of 150% of rated current for at least 30 seconds with the voltage

being maintained within +/-5%.

The generator control panel shall have an integrated automatic voltage regulator (AVR) with +10% voltage adjustment range by means of a rheostat. Voltage regulation shall be within +/-0.5% maximum at steady state and 15% maximum voltage dip at maximum load start (Instantaneous) as specified in data sheet.

In the case of 3-phase symmetrical short circuit is applied at the generator terminals, the generator regulator and exciter system should be able to sustain at least 300% of rated generator current for 10 seconds.

The distortion factor of waveform (at no load) shall be ideally 0% and the total harmonic content LL/LN shall not exceed 2.5%.

The combined generator, exciter and regulator efficiency at full load shall not be less than the following with power factor 0.8:

50-100 KVA 90% efficiency.

125-300 KVA 91% efficiency.

330-600 KVA 92% efficiency.

630-2000 KVA 93% efficiency.

The emergency diesel generator should have the capability of being online at rated voltage, speed and frequency, within 10 seconds. The time required for the gas generator to be online shall be advised by Vendor.

5.4 Excitation System

The excitation system shall be of the brushless type with hermetically sealed rectifiers, including A.C. main exciter, a rotating rectifier and a permanent magnet pilot exciter. Reliable operation of the system must be secured in case of any rectifier failure.

The rated excitation current should not be less than 110% of the excitation current at the rated output of the generator under full load and maximum ambient temperature.

The excitation system shall be able to handle the start up of all motors indicated on the Single line diagram “1007-DISQ-0-E-DW-30089”. The system shall allow adequately relay settings for system fault current protection.

5.5 Enclosures and Materials

The generator stator frame shall be of cast steel or fabricated steel with 3 mm minimum thickness. The frame shall have sufficient strength and rigidity to withstand handling, transport, or due to short circuit.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 17 of 32

Mechanical degree of protection for the generator, exciter, terminal boxes and bearing houses for Indoor installation and outdoor installation shall be IP55 (IEC).

All generators shall be marked clearly and permanently with the direction of shaft rotation.

Each generator shall be equipped with certified lifting devices and lifting procedure to enable lifting of a generator for maintenance or after breakdown.

5.6 Cooling System

Generators shall be frame-surface or air-to-air, self-cooled. Cooling method shall be specified as per IEC 60034-6. Accepted cooling methods are as follows:

Frame surface, self cooled, open circuit, cooling method IC 01.

Air to air, self cooled, closed circuit, and cooling method IC 411.

Air to air, self cooled, closed circuit, and cooling method IC 511.

Air to air, self cooled, closed circuit, and cooling method IC 611.

Air to Water, self cooled, closed circuit, cooling method IC 71W.

Air to Water, self cooled, closed circuit, cooling method IC 81W.

For generators 1250 KVA and above, exciter cooling method shall be IC 31 unless a higher cooling method is required.

Vendor shall indicate the selected cooling method in data sheet.

5.7 Bearings

Bearing and bearing housings shall be designed to minimize contamination of lubricant and lubricant leaking into the winding. Lubricant shall be grease type and shall be defined by Vendor. Two-bearing machine shall be preferred.

RTD's (2 per bearing) with alarm and shutdown signals shall be provided for bearing temperature measurement; the RTD'S shall be wired via terminal box (if required) directly into the package control system. Bearing shall be insulated to prevent shaft and bearing surface damages due to shaft current circulation and shall have provisions for testing of vibration. Sleeve Bearings type are preferred. Roller bearings type if recommended by Vendor may be accepted subject to Company approval.

5.8 Terminal Boxes

The terminal boxes enclosure of main windings, control / measurement circuitry and auxiliary electrical supplies shall meet or exceed the generator enclosure requirements (IP55).

Terminal boxes must be able to accommodate without deterioration the maximum through fault current available at the terminals and should be able to contain without external effect the consequence of any internal box fault.

The terminal boxes shall be of ample dimension for accepting the number, type and size of line and neutral cables and cable terminations as specified on the data sheet or the single line diagram.

For neutral point earthing of star connected generators, a separate neutral cable box shall be provided with adequate space to accommodate current transformers.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 18 of 32

On four wire systems (low voltage 3 phase systems) the neutral shall be brought out to the main cable box as well as to neutral cable box.

The main and neutral cable boxes shall include internal bus bars for cable connection and current transformers installation. Cables are not accepted.

Auxiliary equipment terminal boxes shall be mounted on the side of the generator opposite to that of the main terminal box.

Separate cable boxes shall be provided for the following:

Main terminals.

Neutral terminal.

Space heater terminals.

Resistance temperature detectors terminals.

Other auxiliaries if any.

5.9 Noise Levels

Maximum noise levels for equipment shall not exceed 80 DB(A ) at 1 meter from the source and shall be in accordance with document Noise Control Specification “1007-DISQ-0-F-SS-10018”

5.10 Emission Levels

All emissions from the generators must comply with Egyptian Law 4 for the Environment as described in Prime Minister’s Decree 1095 for 2011.

5.11 Generator Protection and Control Panel

The design, layout, dimensions and configuration of the panel(s) shall be proposed by Vendor and approved by Company before delivery.

Generator control panel enclosure shall be as follows:

IP 41 (IEC) for indoor installation.

IP 55 (IEC) for outdoor installation.

The generator control panel shall be a free-standing, non-ventilated type with removable side and top cover. Space heater shall be provided to prevent moisture. The heaters shall be thermostatically controlled.

Generator control panel shall be provided with facilities to monitor status, protective relays, and alarm and trip signals in accordance with PLC Specification for Packages Document No. 1007-DISQ-0-J-SS-33054.

Protective relays shall be multifunction microprocessor based relay .Protective relays shall be for operation from instrument transformers having nominal 5 ampere, or 1 ampere for secondary current relays or 110 Volt secondary for voltage relays. Control Voltage supply shall be 24V DC from AC/DC system supplied by generator Vendor and derived from 400 Volt AC, 3-phase, Neutral and Earth auxiliary power supply of the package which will be provided by others. The relays manufacturer shall be subject for Company approval. Relay test facilities shall be provided on the panels such as sockets and plugs to enable testing the relay without disconnecting the relay terminals unless the relay is with built -in test facilities.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 19 of 32

The protective relay shall contain the following functions unless otherwise shown on the single line diagram:

Fast lock-out relay for generator circuit breaker tripping.

Fast lock-out relay for prime mover shut down.

Under/over voltage relay.

Winding and Bearing RTD relay.

Under/over frequency relay.

Field failure relay.

Negative phase sequence relay for generators 500kW and greater.

Diode failure relay.

Reverse power relay.

Voltage restrained over current.

Differential relay.

Earth fault over current relay (Back up & stator earth fault protection).

Instantaneous Over current relay.

Generator/Engine Trip circuit supervision relay.

5.12 Annunciation, Alarm and Shutdown

The annunciation for shutdown and alarm signals shall be displayed on each generator/engine control panel section. Vendor shall provide a list of all annunciation shut down and alarm for the engine to Company for review and approval. Annunciators shall be mounted on the panel face and shall have reset facilities and test lamps.

Each alarm or shutdown shall be associated by:

Horn signal.

Flashing lamps.

The fault can be acknowledged by push button which shall stop the horn signal.

5.13 Manual/Auto Start

Manual/or auto start shall be selected via an auto-off-manual key type selector switch in the Generator control panel. The operation feature shall be as follows:

a. Manual Operation

The engine shall start manually using the start Push Button.

b. Automatic operation

The engine shall start automatically in the event of loss voltage due to failure of the duty unit(s).

In both cases the closure of main circuit breaker shall be selected either manual or automatic by auto/manual circuit breaker selector switch in the Generator control panel.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 20 of 32

5.14 Secondary Wiring

Secondary wiring shall be flexible stranded copper conductor, PVC or XLPE insulated 600/1000V, flame retardant.

Minimum wire size for control wiring shall be 1.5 mm2 and for current transformer wiring 2.5 mm2.

All low voltage wires shall be neatly arranged and clipped in groups and protected by flexible conduit or channels with covers.

Each conductor and its terminations are to be identified and marked with numbered and/or lettered ferrules of flame resistant material.

All live terminals are to be equipped with removable covers (with tools only).

As far as practicable, signal conductors shall be segregated from power wiring and AC wiring shall be segregated from DC wiring.

Wiring to equipment mounted on doors or hinged panels shall be carried through flexible conduits or spiral wraps.

5.15 Cable Terminations

Cable gland plate’s metallic, non-magnetic material shall be readily removable for the drilling and fitting of glands.

Wiring and terminals shall be identified in accordance with the related wiring diagrams.

Positioning of cable termination shall avoid obstruction of other cable terminations, removable covers and shall provide easy access for terminating cables.

Cable supports shall be provided by the Vendor to avoid undue strain on the cable termination.

All 400/230 Volt AC terminal blocks shall be provided with transparent covers.

5.16 Electric System Metering

Each generator shall have the following meters with reading provided to the local control panel:

Engine elapsed time meter - digital type (ETM).

Generator active power (kW)

Generator apparent power (kVA)

Generator reactive power (KVAR)

Generator power factor (PF)

Generator load in percent

Generator voltmeter with selector switch (VS) seven positions.

Generator current with selector switch (AS) four positions.

Generator frequency (Hz)

Generator temperature monitor for both winding and bearing RTD.

Exciter ammeter

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 21 of 32

Exciter voltmeter

5.17 Contacts

Each generator to be provided with volt free contacts for remote signals as follows:

Power generator(s) running.

Power generator(s) common alarm.

Power generator(s) common shutdown.

Power generator(s) trip circuit faulty.

Power generator(s) incoming circuit breaker trip (if applicable).

Power generator(s) incoming circuit breaker close (if applicable).

Engine(s) common alarm.

Engine(s) summary fault trip.

5.18 Synchronizing System

Each generator shall have manual and automatic start-up, synchronization and dead bus closure. In addition, facilities for synchronizing across the bus section Circuit Breaker on the PMCC and EPMCC shall be provided (Bus section breaker are always closed until a maintenance or abnormal condition requires them to opened). Each synchronizing attempt, whether auto or manual shall be subject to a permissive signal from a check synchronising relay.

The synchronizing panel shall contain as minimum:

Synchroscope.

Synchronizing lamps.

Double frequency meter.

Double voltmeter.

Circuit breaker(s) switch trip-neutral-close.

Bus voltmeters.

Synchronizing selector.

Mode of operation.

Synchronizer relay.

Check synchronising relay with indication of permissive state, incorporating dead bus

Closing facility.

AVR (raise/lower) switches.

Governor (raise/lower) switches.

Active, apparent and reactive load sharing.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 22 of 32

5.19 Governor

The governor shall be of the electronic type or microprocessor based type. The requirements for isochronous or speed droop or single operation shall be specified on data sheet. Facilities shall be provided to allow remote control of the Governor. This system will provide load sharing between generators sets running in parallel. The Governor shall be provided with a manual control facility.

5.20 Requirements for Parallel Operation

Generators shall be equipped with a damper winding on the rotor. If more than one star point of paralleling operation generators will be earthed the Vendor shall ensure that third harmonic currents circulating through the star point connections are minimized. As generators are operating in parallel the reactive power generated shall be controlled by an automatic power factor controller. A droop current transformer and droop rheostat shall be provided.

5.21 Current Transformers

Current transformers shall comply with the requirements of IEC 60044 and IEC 60185.Current transformers of the bushing type shall not be used.

Metering current transformers shall be with an accuracy class 0.5. Protective relay current transformers shall have an accuracy of 5P10 (IEC class). Accuracy shall be as necessary as is satisfactory to operate the relays over their design range. Differential Protection current transformers shall have an accuracy class X in accordance with IEC 60185 or equivalent.

The secondary output current shall be 5 amperes, except in the following cases:

Secondary output shall be 1 ampere for differential protection and earth leakage protection.

Connections for remote ammeters shall be from 1 ampere interposing current transformers.

Current transformers shall be designed to mechanically and thermally withstand the specified switchboard short circuit capacity. Current transformers short time thermal current shall be as specified on data sheet. Current transformer secondary circuits shall be furnished with terminal blocks having short circuiting provisions. All current transformers to be connected to current test block.

Current transformer shall have the following specification:

Dynamic current shall not be less than 2.5 times the rated short time thermal current.

Maximum continuous current shall be equal to 120% of the rated primary current.

Vendor shall be responsible for design of the current transformers such that to carry the relay burden and avoid CT saturation during normal operation, overload and short circuit conditions.

5.22 Voltage Transformers

Voltage transformers shall comply with the requirements of IEC 60186.Voltage transformers shall be with an accuracy class 0.5 (IEC class).

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 23 of 32

Voltage transformers shall be mounted in isolated compartments with draw out facilities. Voltage transformers shall be equipped with withdrawable primary fuses with an interrupting capacity not less than rated interrupting capacity of the incoming circuit breakers.

Voltage transformers secondary protection shall be by miniature circuit breakers which shall be mounted in a compartment separate from the transformers and primary fuses. All voltage transformers to be connected to voltage test block.

5.23 Battery and Charger Assemblies

The battery & charger assemblies shall be a standard product proven performance type of assembly and shall comply with IEC requirements and data sheet.

DC system power capacity shall cover all the DC power requirements for the engine driven generator set. The DC power requirements for the package and DC system capacity shall be specified by Vendor during quotation.

Nickel/Cadmium batteries in a plastic container with ample capacity for supplying the DC loads for eight (8) hours with the battery charger off shall be provided. The system shall have dual set of battery charger and one battery set.

Each charger shall be sized to supply the DC load and re-charge the complete discharged battery bank in approximately 8 hours.

Sizing of battery and charger shall be based on:

D.C feed power to control panel 8 hours.

D.C feed power to D.C starting motor.

D.C feed power to all other control & auxiliaries.

20 % spare power.

Two separate DC systems shall be supplied. One DC system for the generator control panel and engine controls, the second DC system for engine starting. Starter Batteries shall be installed in the engine generator enclosure.

Provisions should be taken to prevent batteries discharging into charger on charger fault. The DC required for the package shall be from the battery and charger system through D.C. distribution panel integral with the chargers.

The D.C. distribution panel shall include main incoming circuit breaker moulded case current limiting type and branch miniature circuit breaker 2-poles. All circuit breakers shall be provided with over current and short circuit protection.

Batteries shall be in a separate ventilating battery room or battery case, while the charger and relevant D.C panel shall be located in control room of the package. Batteries shall be in a separate enclosure and free standing. Battery charger case should be equipped with ventilating thermostatically controlled fan(s).

DC output shall be 24V DC (or Vendor standard) to suit the required DC voltage for starting the engine and feed the generator control/protection panel & other engine auxiliaries.

AC input to the battery charger shall be 400/230 Volt (4 wire), 3 phase, 50 Hz, derived by vendor from package auxiliary circuit provided by Company. Moulded case circuit breaker shall be provided by Vendor at the incomer(s) of the battery charger system.

Each charger shall be provided with but not limited to the following alarms and indicating lights:

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 24 of 32

Failure of input power to the battery charger.

Failure of the output power from the battery charger.

D.C. system earth fault.

AC power "ON".

High rate charge.

Indicating instruments of switchboard quality shall be provided as follows:

A.C input voltage, with phase selector switch.

D.C output voltage.

D.C output current.

D.C charging current.

5.24 Accessories

Each battery system shall be supplied with all standard accessories, tools and spares required for the installation, including the following:

Inter-cell connections and shrouds.

Two terminal connection lugs.

One thermometer with vent plug and wall-mount holder.

One syringe hydrometer with wall mount holder.

Cell bridging connection.

Cell Testing voltmeter 3-0-3V.

One single cell lifting sling (or other suitable handling provisions).

Insulated spanners.

Acid resistant and insulating floor if containerized solution

First Aid and Safety kit for battery rooms including Eye flush bottle station

5.25 Nameplates

Stainless steel nameplates with information listed in IEC-60034 clause 27 shall be provided in English language.

5.26 Electrical Immunity

All Equipment shall be able to generally withstand the impact of the imposed electrical tests as defined in referenced IEC.

5.27 Disturbance Immunity

The package shall be suitably screened to optimize electromagnetic compatibility (EMC).The package shall be type tested in accordance with IEC 61000 part 4, level 3 - typical industrial environments, as detailed below:

IEC 61000-4-2- Electrostatic Discharge - level 3 - 8 kV air discharge.

IEC 61000-4-3-Radiated Electromagnetic Field (RFI) - level 3-10 V/m.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 25 of 32

IEC 61000-4-4-Electrical Fast Transient - level 3 - 4 kV common mode.

IEC 61000-4-5-Surge - 2 kV line - earth and 1 kV line – line.

The manufacturer shall provide type test certificates from a recognized testing authority to verify that the whole equipment is effectively screened against EMC in line with the applicable IEC standards.

6 Painting

All equipment shall be finish painted or coated in accordance with Protective Coating Specification (1007-DISQ-0-L-SS-39004).

A sufficient quantity of touch-up paint (10%) shall be supplied with the equipment to repair minor damage to the paint finish after site installation.

7 QC Inspection and Testing

The Vendor is to co-operate with Company Inspection Representative to carry out the tests as specified by IEC60034. The Vendor shall perform QC inspection and testing at Factory Acceptance Tests, System QC Integration Tests with ICSS System connected and Site Acceptance Tests in the presence of Company Representative and/or Independent Verification Service Company. These are to include, but not limited to, the following:

7.1 General

Physical check of general appearance, finish, mechanical assembly including good welding, full nuts on bolted parts, undamaged condition and general worthiness.

Dimensional check, particularly overall length, breadth, height and fixing centres against the Vendor's certified drawings.

Check of cable termination locations, direction, type and materials against specification and

Vendor's certified drawings.

QC Inspection and Testing shall be carried out in general in accordance to audited Quality Control Inspection and Test plan, additional Factory Acceptance Test, System Integration Test and Site Acceptance Tests shall be carried out in accordance to QC Test Procedures and QC plan which will be prepared by vendor and reviewed and approved in advance by company

7.2 Generator QC Tests

Measurement of winding resistance (cold).

Full-Load Heat Run Test With Zero Power Factor Method or Equivalent

o 1/2 load test (1 hour minimum at 0 p.f)

o 3/4 load test (1 hour minimum at 0 p.f)

o Full load test (1 hour minimum at 0 p.f)

o Over load test (110% full load for 1 hour at 0 p.f).

Temperature rise test and calculating winding temperature rise.

Measurement of winding resistance (hot).

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 26 of 32

Bearing inspection and temperature rise.

Vibration Test.

Noise level test.

Waveform test.

Engine Test

Insulation Resistance On

o Generator windings (before heat run and after heat run & dielectric test).

o Exciter windings (before heat run and after heat run & dielectric test).

o Heater

o Built in temperature detectors

o Bearing insulation

Dielectric Test On

o Generator windings.

o Exciter windings.

o Heater.

Built in temperature detectors.

7.3 Battery and Charger QC Inspection and Testing

The Vendor is to carry out the complete range of routine tests as specified by IEC 60034 These are to include, but not limited to the following:

Insulation resistance measurement.

Dielectric test.

Proper mechanical and electrical operation of all functional parts including auxiliaries, meters, indicators, relays, etc.

Load Test: The battery chargers shall be operated at full load and ambient temperature of 40 degrees Centigrade for a period of 24 hours, to ensure that no overheating of any component occurs.

Output Characteristics: The Vendor shall demonstrate the output characteristics of the equipment by recording input voltage, frequency, current and power factor, and output voltage, current and ripple at the following output loads:

o No load.

o 25 % full load.

o 50 % full load.

o 100 % full load.

o 110 % full load.

o 150 % full load for 5 seconds

Battery cells shall undergo standard QC factory tests.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 27 of 32

7.4 Generator Control Panel QC Test

The generator control panel and auxiliaries equipment shall be subjected for the following tests

Insulation tests.

Full functional test.

Temperature rise test.

Factory Acceptance Test, System Integration Test with ICSS and Site Acceptance Test

7.5 Package String QC Test

The Vendor shall perform string test including, but not limited to, the following:

Engine start-up system including measurement of the starting time. A minimum of two start and stop tests shall be performed.

Automatic start-up system if provided.

For emergency generator sets verification of the time between initiation of a start command and acceptance of the nominal load for a cold start.

All engine alarm and shutdown functions.

All generator alarm and trip functions, including the verification of protection relay operation.

Operation of the battery charger.

The status/ alarm / trip/ shutdown indication of the control panels.

Local manual start/ stop/ emergency stop functions.

Remote start/stop/emergency stop functions (input signals).

Operation of the AVR.

Operation of the AVR automatic transfer system.

Operation of the automatic power factor controller.

Operation of the synchronizing equipment.

Calibration of measuring and protective devices.

7.6 Site Acceptance QC Test

During running each generator set the following inspections to be performed:

Check for leaks.

Check for loose fasteners.

Activate and test the safety devices.

Oil level check.

Water level check.

Engine to control interconnects check.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 28 of 32

Check of direction of rotation.

Control panel tests.

Check of the adjustment of all safety devices & protective relay.

Check of excitation & voltage regulator.

Load test - 8 hours operation after one hour stabilization period.

Engine shutdown & safety devices shall be demonstrated.

Parallel operation test and complete function test.

System Integration Test with ICSS

8 Documentation

Vendor shall provide as a minimum the following documentation:

Outline and Equipment arrangement drawings

Layout drawings of all systems

P&ID’s, Cause and Effect diagrams including ESD and F&G

Power and Instrument Cable list

Single line diagram

Electrical schematics and wiring diagram

Interconnection wiring diagrams

Termination diagrams

Earthing Diagrams

Relays and circuit breakers characteristics

Current and potential transformers curve.

Equipment Data Sheets and Equipment List

Data sheets for panels, generators, relays and all auxiliaries

Nameplates configuration

List of sub-Vendors

Installation, pre-commissioning and commissioning and start-up, operating and maintenance manuals

Acceptance/performance QC test procedure

Surface preparation and painting procedure

Shipping, handling, packing and storage procedure

QC Test reports and certificates

Spare parts lists for pre-commissioning and commissioning and two years operation turn over methodology

List of settings of protective relays

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 29 of 32

Interface List, Interface data and all details ( Hard- and Software )

Factory Acceptance Test Procedure

System Integration Test Procedure

Site Acceptance Test Procedure

ATEX 95 Certificates for equipment installed in classified areas

HAZOP study and report

Safety Integrity Level report(SIL)

9 Preparation for Shipment

The Vendor shall take all measures to avoid any risk of damage or deterioration during shipping. When shipment is by sea, engine/generator set must be adequately protected against knock and salt-water spray etc.. In every case, consideration must be taken of the fact that engine/generator set will remain at site exposed in open air, in damp, tropical, high sandstorm and dusty location. Suitable bracing shall be provided to support heavy components during shipment.

The generator control panel shall be complete for service with all small wiring terminal boards, fuses, links, labels, foundation bolts, test and earth connections and all necessary items.

Wires for energizing space heaters during storage shall be brought out and tagged "Space Heaters" with the voltage and connected wattage shown.

10 Storage Locally and Shipping

Equipment shall be packed in such a way that it can be stored locally, at the various sites for a period of up to 12 months without suffering any damage or ill effect that would affect its performance or operational life. Silica gel bags shall be included and/or electric anti-condensation heaters, with terminals readily accessible from outside the packaging shall be provided to prevent condensation damage.

10.1 Weight

All the dimensions of the equipment including the weight (via a weight certificate) shall be provided, as access to the site is limited to road transport. Package may have to be split into smaller shipping sections than is normal because of the limitations in access, and the weight of each section may prove a critical item in transportation to site.

Shipping, installation and maintenance weights (including locating the centre of gravity) shall be provided.

11 Vendor's Responsibility and Guarantees

The data sheet shall be completed by the Vendor and submitted with his quotation within the tolerances specified in the relevant IEC 60034 codes. These values shall be the basis of a performance guarantee.

The Vendor is responsible for complying with all codes which apply to the equipment. Any special certification requirements or inspections by other authorities arising from the above shall be arranged by the Vendor and the costs for the same shall be included in his quotation.

The equipment to be provided by Vendor must be in complete compliance with this specification and references codes. Any exception or deviations, if any, must be listed

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 30 of 32

separately with the quotation for Company approval. Any exception which is not listed shall not be considered.

A complete set of tools for service and maintenance shall be supplied in a suitable box with service and maintenance manual guides.

12 Site Installation Assistance, Commissioning and Start-Up

Manufacturer shall provide a specialist with approved C.V. & certificates for site installation supervision assistance, start-up and pre-commissioning and commissioning supervision.

Installation supervision shall include but not limited to the following:

Visual QC inspection.

Check and supervision of mechanical installation.

Check and supervision of Electrical installation.

Check of alignment, assembly, interwiring connections of the various units shipped separately in order to assure that the Generator Package ready for connection of incoming and outgoing power and control cables and ready for operation.

During the pre-commissioning and commissioning and start-up stage, manufacturer specialist shall carry-out, but not limited to the following:

Check of the correct execution of the connections between assembled units.

Insulation test of all power, control auxiliary circuits and equipment.

Dielectric withstand test of all power, control, auxiliary circuits and equipment.

Batteries shall be fully charged and subjected to discharge tests to prove their electrical characteristics and capacity at site.

Test of functioning of all equipment + full load test.

Test and calibrations of all protective relays on site by relays sub-supplier himself.

Site Acceptance Test inclusive System integration test on site.

Implementations of all recommendations specified in pre-commissioning and commissioning and start up manual.

Each skid shall include adequate lifting and maintenance provisions. This shall include sufficient lifting lugs, pad eyes, pulling rings and runway beams to assist with lifting and handling of all components where access is restricted or where component maintenance weights exceed 25kg and which may need to be removed or replaced during the design life of the package. Permanent facilities shall only be provided in the case of components weighing 1 tonne or more and which will require frequent maintenance at least once every 12 months or where access for temporary lifting gear is restricted.

The Vendor shall ensure that adequate access and withdrawal space is provided to permit access for maintenance.

Permanent lifting davits, runway beams, pad eyes or other suitable lifting aids shall be provided above filter covers and for all other components weighing 1 tonne or more or which will require frequent maintenance at least once every 12 months. Permanent overhead

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 31 of 32

runway beams and/or lifting pad eyes shall also be provided above equipment where access restrictions and/or location of equipment components preclude the use of portable lifting gear.

The supplied equipment shall be provided with an appropriate number of suitably rated lifting lugs to enable lifting and installation at site. All pad eyes furnished by the Vendor shall be designed in accordance with API RP2A with a factor of safety of at least two (2) based on the maximum static weight of the complete package. Pad eyes shall be designed for a lateral load of at least 1.5 times the design load, to be applied simultaneously with the sling load.

Suitable, dedicated and certified lifting beams and/or spreader bars, slings and shackles shall also be provided to enable installation of the equipment.

13 Spare Parts

The following specified spare parts shall be included in Vendor's quotation:

12.1 Pre-commissioning and Commissioning Spare Parts

Pre-commissioning and Commissioning spare parts shall be Vendor responsibility but Vendor shall submit a detailed list with his quotation, the spare parts, shall be left for the purchaser storage.

12.2 Two Years Spare Parts

The Vendor shall submit for each Generator set a detailed list of two years spare parts with his quotation with wearing, turn over and replacement rate data.

14 Health, Safety and Environmental Management

The Vendor shall consider the impact on environment because of his products during different process (e.g. designs, manufacturing, …. etc.), and shall develop environment friendly products and manufacturing processes such that the supplied equipment will be safe, efficient and made in way that it conserve energy and other natural resources.

The electrical equipment and products shall cover (in design, engineering, manufacturing and testing processes) any emergency, abnormal and upset conditions which would be met during equipment operation to prevent the following:

Environmental damages.

Equipment or product damages.

Plant operation losses.

Health effects.

Loss of public & customer trust.

The electrical equipment and products shall be designed to comply with all legal requirements and relevant international standards (in design, engineering, manufacturing and testing processes) under any emergency, abnormal and upset conditions.

Onspec Engineering Solutions

Disouq Field Development Project

Specification for Power Generators

Page: 32 of 32

15 Quality Assurance

The Vendor and major sub-suppliers shall comply with ISO 9001,2008 International Standard, “Quality Management Systems – Requirements” and shall be adopted by the Vendor and his sub-suppliers throughout the various phases of the project (Management, Engineering, fabrication, assembly, QC testing and Inspection, Pre-commissioning and commissioning).

The Vendor’s Quality Management System Manual and concerned operating system documents, quality internal audit reports, QA/QC Plan, Inspection and Test Plan (ITP), management review minutes of meeting and ISO9001:2008 valid active certificate with the right certificate scope will be subject to the Purchaser’s approval prior to issue of a Purchase Order. Major sub-suppliers will be subject to the same approvals.

The Purchaser reserves the right to conduct a Quality Surveillance Audit at the Vendor’s /sub suppliers facilities at any stage during manufacture according to the Disouq Project Quality Plan. The responsibility for QC inspection rests with the Vendor.

The approval of any work by the Purchaser or the release of equipment for shipment shall in no way relieve the Vendor of his responsibility for meeting the requirements of this specification. QC Inspection and testing shall be carried out in accordance with the approved ITP.

The Vendor shall furnish a representative ITP detailing his normal scope of QC inspection and testing with the bid in the form of his Quality Control Plan of similar projects done before. In the event of an order, the Vendor shall submit a detailed project specific ITP for the Purchaser’s approval. The ITP shall identify all QC inspection and test activities in accordance with Requisition and its various attachments, their acceptance criteria, and observed or witness hold points.

The Purchaser reserves the right to carry out its own QC inspection during design and manufacture according to the project quality plan with QA plan and the project contracting documents, Purchase Order requirements and agreements. The Vendor shall provide free access to his works, and to that of all sub-suppliers, for the Purchaser and Purchaser’s representative. All necessary QC certification documents relating to materials, QC shop test data, etc. shall be made available to verify that the requirements of the Purchase Order are being met.