Kempsey Shire Council10 Year Works Program

2016-2025

KEMPSEYShire Council ksc

Page 2: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

2 | P a g e

Contents

What infrastructure assets does Council maintain? ................................................................ 3

How does Council prioritise Assets? ......................................................................................... 3

How does Council assess the asset condition? ........................................................................ 3

Why have a ten year works program? ..................................................................................... 4

Sealed Roads ............................................................................................................................ 5

Unsealed Roads...................................................................................................................... 12

Kerb and Gutter ..................................................................................................................... 15

Footpaths ............................................................................................................................... 18

Bridges ................................................................................................................................... 20

Public Toilets .......................................................................................................................... 23

Open Spaces & Facilities ........................................................................................................ 24

Page 3: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

3 | P a g e

What infrastructure assets does Council maintain? Community infrastructure assets include roads (both sealed and unsealed), bridges (both concrete and timber), rural culverts, footpaths, kerb and gutter, guardrails, bus shelters, car parking facilities, stormwater drainage (including pits, pipes, head walls and open drains), flood mitigating structures, buildings, parks (sports fields, playgrounds and cemeteries), airport and waste management facilities.

Council’s transport network comprises 603km of sealed roads, 578km of unsealed roads, 168 bridges (concrete and timber), 62km of footpaths, 156km of kerb and gutter. Council modelling shows that aapproximately $17 million is required per annum for both sealed and unsealed roads for renewals.

Further information on Council’s management of Community Infrastructure can be found at http://www.kempsey.nsw.gov.au/corporate/policies/procedure-3-04-03-asset-management-plan-general-2013.html .

The road network is the largest asset group maintained by Council in terms of size and value and is also one of the most frequently used and vital asset groups to the community and business operators.

How does Council prioritise Assets? Council uses the same system of assessing its asset management priorities as it uses to assess its service provision, ensuring that the decisions of where resources are allocated are done in an equitable and efficient way.

Within the asset classes there are a number of factors taken into account in relation to the assessment protocols. These will vary for asset classes and within each asset class there will be a discussion of how the various aspects of the asset will relate to the overall methodology.

The system is based on assessment of the following factors:

Risk The level of change in Council’s risk profile generated by the action. There is a recognition that Council cannot fund all of the work that would be required at any one time and therefore the limited resources must be used or applied in a way that most effectively manages the inherent risks that this situation creates.

Nuisance The level of change in the nuisance impact to the community of using the asset/service. Serviceability The change in the level of service provided to the community by the asset/service. Level of benefit The frequency with which the asset or service is used and the level of use overall.

A current example of this would be the bridges included on school bus routes. These bridges are considered a higher priority than others as any failure or limit on the bridge would result in disruption to the school bus route. Unlike residents, the alternative route may introduce significant additional time and backtracking.

How does Council assess the asset condition? In most cases some form of condition assessment is undertaken or updated periodically. For small asset classes such as bus stop shelters, this process is done manually. For large classes like roads, footpaths and kerb and

Page 4: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

4 | P a g e

gutter, automated survey vehicles equipped with sensors, data loggers and high definition video cameras is used to collect information about these assets and their condition.

Council uses “Lifecycle Management Plans” (LMP) to manage and operate assets at agreed levels of service whilst optimising life cycle costs.

Each asset has a LMP that includes the following information:

• Levels of Service – Customer Charter • Infrastructure Risk Management Plans • Routine Operations and Maintenance Plans • Renewal/Replacement Plans • Creation/Acquisition/Upgrade Plans • Disposal Plans • Service consequence and risks

Why have a ten year works program? Out of the lifecycle management plan for each asset a proposed works program has been developed to identify the specific locations or assets nominated to be renewed or refurbished over the next ten years. This program is centred around Council’s Long Term Financial Plan (LTFP) that gives the budget amounts expected to be available in future years based on numerous assumptions of what will happen in regard to income and operating costs over the same period.

Having a listing will give the community an opportunity to know if works are listed within the foreseeable future. It should be noted that the plan is revised each year to take into account more detailed investigations of projects prior to commencement and that changes may be made. In general, works listed for the following year are set and already under investigation for works to proceed. Works listed in the first four years of the program are fairly firm; however, some priorities may alter from year to year depending upon the individual circumstances. Works listed out beyond four years have initially been identified to go into the program; however, changes may occur as the program is formally revised in line with updated condition data every three years.

Works that are not on the program may be warranted in terms of the asset conditions; however, the priority may not be as high as other items. Works on lower traffic local roads are being considered where there is an unreasonable maintenance impact or where the community risk is escalating.

When undertaking works on the roadway, other asset groups such as the kerb and guttering as well as the footpaths are fixed at

the same time. This gives economies of scale to reduce overall costs and allows the job to look finished

Page 5: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

5 | P a g e

Sealed Roads Council is responsible for managing the Shire’s network of 603km sealed and 578km unsealed roads including regional roads and the former Pacific Highway Corridor.

Both sealed and unsealed road types are built upon layers formed of compacted gravel known as the road base. The road base provides strength to compensate for the underlying soil weakness. Sealed roads also have a sealed surface that is constructed of bitumen and aggregate, asphalt or concrete. The seal adds strength to the road formation and reduces the ingress of water from the surface into the base. If water is allowed to saturate the road base, potholes tend to form during rainfall and deterioration of the road is greatly accelerated.

Road traffic and environmental factors cause roads to deteriorate over time creating the need for maintenance. Between 2008 & 2013, several main stream flooding events and extended periods of above average rainfall have contributed to a deterioration of the road network. The graph below shows this deterioration based on the condition assessment data from 2008 & 2013 for sealed roads. The graph shows that many roads that were in good to fair condition have deteriorated with a large increase in the roads that are considered “failed”. A condition assessment is due to be undertaken in 2016 and this will provide better information upon which to observe the decline in condition of the network over time. In theory, if the road network condition is not significantly changed between condition audits then Council would be providing sufficient resources to maintain the current condition of the assets.

-5.00%0.00%5.00%

10.00%15.00%20.00%25.00%30.00%35.00%40.00%

0 1 2 3 4 5 6 7 8 9 10 11 12

% o

f Net

wor

k

Condition

Sealed Road Network Condition 2008 2013

This figure shows that the condition of the sealed road network deteriorated significantly in the 5 years to 2013. In 2008, 84.89% of the road network was rated as fair or better condition but in 2013 that percentage had dropped to 47.93%

Recycling of existing gravel pavement via in-situ stabilisation with the addition of lime and/or cement. The old gravel and additional materials are mixed by a pulveriser and

then re-compacted to reform the roadway

Page 6: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

6 | P a g e

Crescent Head Road at corduroy

Edge widening for safety and alignment improvement using specialised machinery for good placement on the formed shoulder.

After Before

Bissett Street, East Kempsey

After Before

Page 7: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

7 | P a g e

The following lists the prioritised works program for sealed roads over the next 10 years:

Sealed Road Section Estimated Cost Year Airport Road, Aldavilla (Sherwood Road to Airport entrance) $250,000 2017

Arakoon Road (Bullocks Quarry Road to Cabbage Tree Lane) $400,000 2019

Arakoon Road (Cabbage Tree Lane to Phillip Drive – 1.132km) $551,000 2019

Arakoon Road (South West Rocks Road to Chainage 1000 – 1km) $484,000 2022

Armidale Road (East Street Bellbrook to Cemetery Road – 0.854km) $500,000 2022

Armidale Road (Elbow Street) – (Tozer Street to River Street – 0.219km) $250,000 2016

Armidale Road (Ferrier Drive to Link Road – 2.965km) $1,200,000 2020

Armidale Road (from Hickeys Creek Bridge to 2.0km west) $740,000 2018

Armidale Road (North Street to Sherwood Road) $1,000,000 2021

Armidale Road (River Street) – (Elbow Street to North Street – 2.494km) $1,100,000 2016

Armidale Road (Turners Flat Road to Deep Creek) $450,000 2017

Arthur Street, South West Rocks (Bruce Field Street to Mitchell Street – 0.395km) $200,000 2020

Arthur Street, South West Rocks (Mitchell Street to Cook Drive – 0.181km) $178,000 2025

Austral Eden Outer Road $200,000 2025

Becke Street, West Kempsey (Broughton Street to Polwood Street) $120,000 2021

Belgrave Street, Kempsey (full length concrete rejuvenation) $600,000 2025

Belmore River Left Bank Road (Chainage 3020 to Chainage 4060) $350,000 2019

Belmore River Right Bank Road (from 4.0km from South West Rocks Road for 4.0km) $1,620,000 2023

Belmore River Right Bank Road (from 8.0km from South West Rocks Road to Loftus Road) $2,500,000 2024

Belmore River Right Bank Road (from South West Rocks Road for 4.0km) $1,600,000 2020

Belmore Street, Crescent Head (Pacific Street to Allman Place – 0.208km) $100,000 2020

Belmore Street, Smithtown (Park Street to end – 0.133km) $88,000 2021

Beranghi Street, Crescent Head (Pacific Street to Main Street – 0.204km) $143,000 2022

Betts Street, East Kempsey (Bissett Street to Gill Street) $350,000 2019

Bloomfield Street, South Kempsey (Prince Street to Naiooka Street) $200,000 2018

Bloomfield Street, South Kempsey (West Street to Railway Street) $150,000 2018

Broughton Street, West Kempsey (Tozer Street to Sea Street – 0.312km) $206,000 2021

Buchanan Drive, South West Rocks (Gregory Street to end – 0.431km) $254,000 2021

Cameron Street, West Kempsey (Sea Street to Cochrane Street) $403,000 2022

Cardwell Street, South West Rocks (end to Martin Street – 0.108km) $72,000 2021

Carri Street, South Kempsey (Goonbi Street to Lachlan Street) $60,000 2018

Clarence Ryan Avenue, West Kempsey (Douglas Fentiman Street to Cochrane Street) $400,000 2025

Clyde Street, Kempsey (Mall to Stuart Street – 0.28km) $400,000 2017

Cochrane Street, West Kempsey (Kemp Street to North Street – 1.308km) $600,000 2016

Collin Tait Avenue, West Kempsey (Douglas Fentiman Street to end) $100,000 2024

Page 8: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

8 | P a g e

Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way to Spooners Avenue) $1,800,000 2024

Collombatti Road (Spooners Avenue for 2km west) $1,000,000 2025

Crescent Head Road (Adventist School entry to East Street – includes new bridge) $989,900 2019

Crescent Head Road (Beranghi Road to Berrys Lane) $500,000 2021

Crescent Head Road (from Bypass work to Teague Drive) $500,000 2017

Crescent Head Road (from east of Berrys Lane to Dulconghi Hill) $300,000 2021

Crescent Head Road (Macleay Valley Way to East Street) $400,000 2019

Crescent Head Road (reseal Teague Drive to Seale Road) $180,000 2024

Crescent Head Road (Willow Street to East Street – 0.193km) $100,000 2020

Dangar Street, West Kempsey (Kemp Street to end) $35,000 2023

Douglas Fentiman Street, West Kempsey (Dangar Street to Broughton Street) $200,000 2025

East Street, Crescent Head (Main Street to Korogora Street – 0.257km) $150,000 2016

East Street, South Kempsey (Boral Lane to Angus McNeil Crescent – 0.09km) $63,000 2025

Eden Street, Kempsey (Kemp Street to Sydney Street) $500,000 2025

Edgar Street, Frederickton (full length) $1,000,000 2025

Edinburgh Street, South West Rocks (High Street to Landsborough Street – 0.077km) $80,000 2016

Elizabeth Street, South West Rocks (Gregory Street to McIntyre Street – 0.311km) $160,000 2016

Entrance Street, South West Rocks (Rudder Street to Quarry Street – 0.212km) $150,000 2016

Forth Street, Kempsey (Gladstone Street to Stuart Street) $200,000 2019

Fourth Avenue, Stuarts Point (Ocean Avenue to Walter Conn Road – 0.333km) $160,000 2020

Frank Cooper Street, South West Rocks (Bruce Field Street to Everglades Place – 0.088km) $62,000 2022

Fraser Lane, South Kempsey (Carri Street to Bloomfield Street – 0.113km) $65,000 2019

Gamacks Lane , West Kempsey (Tozer Street to end – 0.08km) $80,000 2016

Geoffrey Debenham Street, Kempsey (Smith Street to end – 0.132km) $100,000 2018

Gladstone Street, Kempsey (Forth Street to Kemp Street) $521,919 2023

Goonbi Street, South Kempsey (Nicholson Street to Bloomfield Street) $80,000 2018

Gordon Rees Street, South Kempsey (Lachlan Street to Naiooka Street) $50,000 2018

Gowings Hill Road, South Kempsey (Burnt Bridge to Marys Bay Road) $556,878 2022

Harold Walker Avenue, West Kempsey (Elbow Street to Marsh Street – 0.246km) $145,000 2025

Haven Crescent, Aldavilla (Full Length – 0.5km) $380,000 2022

Hickeys Creek Road, Millbank (Toms Gully Road to Powicks Bridge) $650,000 2019

High Street, Crescent Head (Baker Drive to Main Street – 0.213km) $150,000 2022

Hillview Drive, Aldavilla (Haven Crescent to Park Road – 0.196km) $137,000 2022

Hodgson Street, Crescent Head (East Street to Hill Street – 0.11km) $77,000 2022

Hopetoun Street, Kempsey (Forth Street to end) $150,000 2025

Innes Street, East Kempsey (Bissett Street to Gill Street) $350,000 2019

John Street, Kempsey (Belgrave Street to Eden Street – 0.211km) $125,000 2021

Page 9: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

9 | P a g e

Sealed Road Section Estimated Cost Year Jubilee Street, South West Rocks (Ocean Drive to North end – 0.14km) $110,000 2025

Kemp Street, West Kempsey (Thompson Street to North Street) $300,000 2016

Lanes Lane, Kempsey (Clyde Street to end – 0.076km) $40,000 2018

Laurels Avenue, East Kempsey (Union Lane to end – 0.109km) $51,000 2016

Leith Street, West Kempsey (River Street to Sea Street) $400,000 2025

Leith Street, West Kempsey (Sea Street to Cochrane Street) $311,162 2023

Little Rudder Street, East Kempsey (Lord Street to end – 0.118km) $80,000 2022

Macquarie Street, South kempsey (Middleton Street to Bloomfield Street) $200,000 2018

Main Street, Crescent Head (Hill Street to Beranghi Street – 0.384km) $270,000 2022

Marine Parade, Stuarts Point (Nineteenth Avenue to Kimpton Street – 0.998km) $400,000 2017

Marsh Street, West Kempsey (River Street to Tozer Street) $300,000 2017

Marsh Street, West Kempsey (Sea Street to Kemp Street) $120,000 2025

McIntyre Street, South West Rocks (Gregory Street to end – 0.797km) $528,000 2022

Memorial Avenue, South West Rocks (McIntyre Street to Landsborough Street) $82,000 2021

Middleton Street, South Kempsey (Macquarie Street to Lachlan Street – 0.273km) $150,000 2016

Middleton Street, South Kempsey (Vernon Street to Railway Street) $300,000 2020

Mitchell Street, South West Rocks (Simpson Street to McIntyre Street – 0.933km) $486,000 2022

Nance Road, South Kempsey (South Street to Queen Street – 0.501km) $300,000 2017

New Entrance Road, South West Rocks (Quarry Street to Chainage 2088 – 2.08km) $1,100,000 2022

Nicholson Street, South Kempsey (Macquarie Street to end) $60,000 2018

North Street, West Kempsey (River Street to Sea Street) $150,000 2016

North Street, West Kempsey (Sea Street to Cochrane Street) $571,841 2025

Ocean Drive (Livingstone Street to end – 0.08km) $70,000 2025

Old Station Road (Belle Rio Close to Inches Road – 0.243km) $170,000 2025

Park Avenue, West Kempsey (River Street to end – 0.224km) $140,000 2021

Phillip Drive, South West Rocks (McIntyre Street roundabout to end – 3.014km) $1,404,000 2021

Pipers Creek Road (Old Pipers Creek Road to Marys Bay Road – 1.422km) $650,000 2021

Plummers Lane (from 1.0km from Macleay Valley Way to Summer Island Road) $1,500,000 2023

Plummers Lane (from 600m south of Suez Road to South West Rocks Road – 1.5km) $500,000 2022

Plummers Lane (Macleay Valley Way to 1km east) $431,000 2016

Plummers Lane (Rainbow Reach Road 1.5km east) $600,000 2016

Plummers Lane (Summer Island Road to 2015 work) $480,000 2018

Prince Street, South Kempsey (Middleton Street to end) $50,000 2018

Queen Street, Greenhills (Fern Lane to Forest Lane – 0.123km) $70,000 2020

Queen Street, South Kempsey (South Street to Nance Road – extend to causeway – 0.207km) $250,000 2018

Railway Street, South Kempsey (Middleton Street to Druitt Street – 0.285km) $158,790 2020

Rankine Street, Crescent Head (East Street to May Street – 0.375km) $263,000 2022

Page 10: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

10 | P a g e

Sealed Road Section Estimated Cost Year Regent Street, Kempsey (Forth Street to end) $150,000 2025

Rudder Street, East Kempsey (Bissett Street to Wharf Street) $93,620 2019

Sea Street, West Kempsey (Kemp Street to North Street) $1,500,000 2024

Second Lane (reseal Macleay Valley Way to Kemp Street} $80,000 2022

Sherwood Road (Chainage 5284 to Chainage 6284 – 1km) $500,000 2021

Sherwood Road (Chainage 6284 to Gowings Hill Road – 0.289km) $210,000 2017

Sherwood Road , Aldavilla (Ronella Drive to Hillview Drive) $150,000 2017

Short Street, West Kempsey (end to Tozer Street) $250,000 2016

Short Street, West Kempsey (Tozer Street to Sea Street – 0.3km) $150,000 2022

Smithtown Road (Church Lane to South West Rocks Road – 0.942km) $573,000 2025

Smithtown Road (Macleay Valley Way to 1.7km east) $550,000 2018

South Street, South Kempsey (Macleay Valley Way to bridge) $664,597 2019

South West Rocks Road (from 1.0km east of Smithtown Road to Kinchela Creek Bridge) $1,800,000 2023

South West Rocks Road (from 4.6km east of Back Creek Road to 7.6km east) $1,140,000 2018

South West Rocks Road (from 7.6km east of Back Creek Road to Perret's Bridge) $1,000,000 2020

South West Rocks Road (from end 2015 work to Old Station Road) $1,200,000 2020

South West Rocks Road (from Smithtown Road to 1.0km east) $350,000 2019

South West Rocks Road (Kinchela Creek Bridge to Riverside Drive) $300,000 2019

South West Rocks Road (Pola Creek Road to Red Hill Lane) $300,000 2017

South West Rocks Road (reseal Red Hill Lane to McKays Lane) $150,000 2025

Spooners Avenue, Collombatti (from Chain O Ponds for 1.1km) $500,000 2023

Stuart Street, Kempsey (Belgrave Street to Forth Street) $250,000 2018 Stuart Street, Kempsey (Forth Street to end – 0.432km) $250,000 2016

Stuarts Point Road (Browns Road to Barbers Lane) $1,000,000 2018

Stuarts Point Road (Lukes Lane to Browns Road) $650,000 2016

Stuarts Point Road (reseal Barbers Lane to Grassy Head Road) $170,000 2024

Tabrett Street, West Kempsey (Becke Street to Bestic Street – 0.182km) $114,000 2021

Tabrett Street, West Kempsey (Tozer Street to Bestic Street – 0.493km) $308,000 2021

Tozer Street, West Kempsey (Kemp Street to North Street – 2.708km) $1,500,000 2017

Trial Bay Gaol Access Road (Cardwell Street to Gaol) $640,020 2016

Union Lane, East Kempsey (Rudder Street to Laurels Lane – 0.034km) $29,000 2016

Verge Lane, Kempsey (Sydney Street to Elringtons Lane – 0.677km) $300,000 2017

Verge Street, Kempsey (Belgrave Street to Vincent Street) $200,000 2018

Verge Street, Kempsey (Sydney Street to John Street) $150,000 2017

Vernon Street, South Kempsey (Bloomfield Street to Taylor Street – 0.118km) $70,000 2024

Vincent Street, Kempsey (Belgrave Street to Verge Street) $60,000 2018

Wentworth Avenue, South West Rocks (Arthur Street to end – 0.108km) $80,000 2016

Page 11: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

11 | P a g e

Sealed Road Section Estimated Cost Year Wharf Street, East Kempsey (Rudder Street to end – 0.076km) $50,000 2022

Wide Street, West Kempsey (Tozer Street to Kemp Street) $280,000 2019

William Street, East Kempsey (Sullivan Street to Stanley Dyson Place – 0.056km) $40,000 2022

Yaelwood Street, Kempsey (Forth Street to end) $150,000 2024

Yarrabandini Road, Frederickton (Great North Road to Golf Course) $200,000 2019

Yarravel Street, South Kempsey (Prince Street to Lachlan Street) $180,000 2018

York Lane, Kempsey (Belgrave Street to Forth Street – 0.187km) $150,000 2021

Kemp Street, West Kempsey – Stage 1 rehabilitation, construct kerb ramps, construct footpath to Marsh Street kerb line

Page 12: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

12 | P a g e

Unsealed Roads The unsealed roads program aims to replenish the gravel surface on Council’s network of 578km of unsealed roads at regular intervals. Gravel is lost over time through erosion and dust. Without sufficient gravel on the road, the effectiveness of maintenance grading is reduced as we are reluctant to disturb the natural clay material below the roads. This would lead to a worse result in terms of the rate of deterioration in road conditions following maintenance grading. Priority is given to the main feeder roads as these tend to have higher traffic loadings hence deteriorate faster and have higher vehicle speeds. Priority is also given to ensuring all roads are reasonably trafficable during wet weather. The following lists the prioritised unsealed road works for the next 10 years:

Unsealed Road Section Estimated Cost Year

Aldavilla Road (Belgrave Falls Road to Old Aerodrome Road – 0.386km) $125,000.00 2019 Armidale Road (end of bitumen to top of Pee Dee Hill – km) $220,000.00 2017

Back Beach Road Crescent Head (Point Plomer Road to end – 0.5km) $25,000.00 2021

Back Creek Branch Road (Back Creek Road to end – 0.4km) $20,000.00 2024

Back Creek Road Kinchela (South West Rocks Road to Back Creek Branch Road – 0.6km)

$30,000.00 2024

Back Creek Road, Kinchela (Back Creek Branch Road to end – 2km) $100,000.00 2024

Ballengara Road (Pipers Creek Road to end – 2.7km) $135,000.00 2025

Balls Road (Toose Road to Fifes Creek Road – 0.9km) $45,000.00 2018

Bannermans Access (Nagles Falls Road to end – 0.8km) $40,000.00 2021

Barbers Lane (Rogers Lane to end – 1.775km) $88,750.00 2020

Belgrave Falls Road (Aldavilla Road to Wards Road – 1.1km) $55,000.00 2021

Belgrave Falls Road (Wards Road to end – 0.1km) $5,000.00 2021

Belmore River Right Bank Road (Upper Belmore River Road to Seale Road – 2.653km)

$132,650.00 2019

Beranghi Road (Wortley Drive to end – 6.101km) $305,050.00 2017

Billybyang Creek Road (Hickeys Creek Road to Sundowner Road – 1.7km) $85,000.00 2021

Billybyang Creek Road (Sundowner Road to end – 3.4km) $170,000.00 2021

Bottletree Lane (Pipers Creek Road to end – 0.7km) $35,000.00 2018

Brassils Creek Road (Warbro Brook Road to end – 5.2km) $260,000.00 2022

Browns Road (Stuarts Point Road to end – 1.4km) $90,000.00 2023

Carrai Road (Willi Willi Road to end – 5.6km) $280,000.00 2025

Collombatti Road (Swan Lane to Hughes Access – 4.872km) $243,600.00 2017

Collombatti Road (Hughes Access to Chain O Ponds Road – 2.7km) $135,000.00 2017

Collombatti Road (Chain O Ponds Road to Bastows Lane – 0.2km) $10,000.00 2020

Collombatti Road (Bastows Lane to Wybalena Avenue – 0.7km) $28,000.00 2020

Collombatti Road (Cedar Crossing to Roses Road – 1.6km) $64,000.00 2023

Collombatti Road (Roses Road to Johnstons Access – 0.7km) $28,000.00 2023

Collombatti Road (Johnstons Access to Ptolemys Access – 3.2km) $160,000.00 2018

Corangula Road (Armidale Road to Fischers Road – 1.047km) $41,880.00 2025

Page 13: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

13 | P a g e

Unsealed Road Section Estimated Cost Year Corangula Road (Fischers Road to end – 1.3km) $52,000.00 2025

Davy Lane (Battles Outlet Road to end – 0.4km) $20,000.00 2025

Dennis Road (Mungay Creek Road to end – 4.7km) $235,000.00 2021

Dondingalong Road (Wirrang Drive to Adelaide Brook Road – 0.617km) $30,850.00 2021

Dondingalong Road (Adelaide Brook Road to Battles Outlet Road – 0.4km) $16,000.00 2025

Dungay Creek Road (Gills Gully to Eight Mile Creek Road – 3.6km) $245,000.00 2023

East Street Gladstone (Macleay Street to end – 0.3km) $12,000.00 2025

First Lane, Kempsey (Glastone Street to Smith Street – 1.1km) $55,000.00 2020

Five Day Creek Road (Armidale Road to Dews Access – 8.8km) $352,000.00 2025

Goulds Lane (Old Mill Lane to end – 1.357km) $60,000.00 2019

Hickeys Creek Road (Billybyang Creek Road to Dykes Access – 1km) $190,000.00 2018

Hickeys Creek Road (Dykes Access to end – 8.9km) $500,000.00 2019

Jacks Crossing (Armidale Road to Chain O Ponds Road – 6.331km) $253,240.00 2023

Kawana Lane (Pacific Highway to end – 1.3km) $60,000.00 2017

Kemps Road (Pacific Highway to end – 3km) $180,000.00 2024

Kemps Access (Quarry Road to end – 4km) $200,000.00 2024

Kinchela Creek Left Bank Road (Bridge to end – 2.583km) $103,320.00 2023

Kinchela Creek Right Bank Road (Kinchela Creek Left Bank Road to end – 2.452km)

$98,080.00 2023

Lukes Lane (Stuarts Point Road to end – 1.8km) $80,000.00 2016

Maineys Road (Turners Flat Road to end – 1.5km) $75,000.00 2023

Maria River Road (Crescent Head Road to Shire boundary – 12km) $600,000.00 2019

Mines Road (Armidale Road to Mungay Creek Road – 8.534km) $400,000.00 2020

Mooneba Road (Armidale Road to Ducats Lane – 7.572km) $150,000.00 2018

Moparrabah Road (Coggies Access to Willi Willi Road – 4.75km) $190,000.00 2021

Mungay Creek Road (Dennis Road to Mines Road – 1.861km) $93,050.00 2019

Mungay Creek Road (Mines Road to end – 5.2km) $208,000.00 2022

Nelsons Wharf Road (Old Aerodrome Road to end – 1.3km) $62,000.00 2017

Nook Creek Road (Armidale Road to end – 1.5km) $60,000.00 2024

Nulla Nulla Creek Road (Mitchells Access to Ryans Access – 8.374km) $400,000.00 2020

Nulla Nulla Creek Road (end of bitumen to Nurse Kilpatrick Bridge) $180,000.00 2018

Old Coast Road (Smiths Creek Road to State Forest – 3.6km) $240,000.00 2024

Old Station Road (Verges Creek Road to Friths Lane – 4.35km) $250,000.00 2020

Pipers Creek Road (Wirrang Drive to Ballengara Road – 3.8km) $190,000.00 2016

Point Plomer Road (Back Beach Road to end – 6km) $315,000.00 2018

Point Plomer Road (Back Beach Road to end – 6km) $315,000.00 2023

Rainbow Reach Road (Plummers Lane to Suez Road – 2.8km) $140,000.00 2016

Rainbow Reach Road (Suez Road to end – 2.8km) $112,000.00 2017

Page 14: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

14 | P a g e

Unsealed Road Section Estimated Cost Year Rainbows End Road (Pipers Creek Road to end – 1km) $50,000.00 2021

Ranch Road (Crescent Head Road to end – 1.738km) $90,000.00 2024

Rogers Lane (Barbers Lane to end – 2.284km) $91,360.00 2020

Saleyards Road (North Street to end – 5.69km) $284,500.00 2022

Seale Road (Crescent Head Road to Verges Creek Road – 3.6km) $180,000.00 2024

Seale Road (Verges Creek Road to Belmore River Right Bank Road Se – 4.1km) $205,000.00 2024

Seven Hills Road (Tamban Road to end – 5.753km) $287,650.00 2025

Smiths Creek Road (Crowther Drive to Crowther Drive – 2.6km) $130,000.00 2022

Smiths Creek Road (Crowther Drive to Old Coast Road – 0.341km) $13,640.00 2021

Smiths Creek Road (Old Coast Road to end – 5.6km) $280,000.00 2021

Spooners Avenue (Chain O Ponds Road to Sauls Cowbails Road – 1.145km) $60,000.00 2016

Spooners Avenue (Sauls Cowbails Road to Railway – 3.3km) $170,000.00 2016

Suez Road (Rainbow Reach Road to end bitumen) $32,000.00 2016

Sundowner Road (from Shire boundary back 2km) $100,000.00 2016

Toorumbee Road (Willi Willi Road to end – 3.2km) $128,000.00 2025

Turners Flat Road (Maineys Road to Lovelocks Creek Road – 2.9km) $145,000.00 2022

Turners Flat Road (Lovelocks Creek Road to Willi Willi Road – 2.4km) $84,000.00 2023

Upper Smith Creek Road (Pacific Highway to end – 4.165km) $208,250.00 2021

Warbro Brook Road (Brassils Creek Road to Lemon Tree Gully) $100,000.00 2018

Wharf Road (Pacific Highway to end – 0.962km) $20,000.00 2021

Willi Willi Road (Turners Flat Road to Temagog Road – 10.2km) $550,000.00 2016

Willi Willi Road (Temagog Road to Stony Creek Lane – 1.5km) $85,000.00 2017

Willi Willi Road (Stony Creek Lane to Moparrabah Road – 4.6km) $250,000.00 2017

Willi Willi Road (Moparrabah Road to Toorumbee Road – 2.9km) $160,000.00 2018

Winstead Road (Kundabung Road to end – 2.6km) $75,000.00 2021

Wrights Lane (Washington Street to James Grimwade Place – 0.078km) $3,900.00 2017

Yabsleys Lane (Blewitts Lane to end - 0.4km) $25,000.00 2021

Yarrabandini Road (Great North Road to end – 2.018km) $80,720.00 2022

Page 15: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

15 | P a g e

Kerb and Gutter Council manages almost 157 kilometres of kerbs and guttering.

The kerb and guttering within the Kempsey Shire Council catchment mainly consists of concrete, with some paving. Approximately 30% of the kerb guttering is listed in poor condition with Council’s defects register identifying over 6km of completely failed kerb and gutter (or around 4.5%).

Where the kerb and gutter has failed completely, there is a much greater potential for water to damage the road pavement. It is also likely to affect property access and increase the risk of injury to the community. Using the prioritisation matrix in the asset management plan replacing failed kerb and gutter generally provides a better outcome than most other actions. Whilst defects in kerb and guttering are being fixed over time as the condition of the adjoining road is rectified. There are numerous smaller sections of failed kerb and gutter that required replacement outside of the normal road program.

The table following lists the prioritised works program for kerbs and guttering over the next 10 years:

Kerb and Gutter – Street Length (m) Year Akubra Place 13 2025

Albert Street 169.5 2020

Angus McNeil Crescent 34 2021

Becke Street 47 2019

Belgrave Street 9 2021

Belmore Street Smithtown 20 2022

Betts Street 62.3 2020

Bloomfield Street 183 2018

Broughton Street 85.35 2021

Bruce Field Street 12 2019

Carri Street Kempsey 28.2 2018

Carrington Street 1 2025

Chifley Place 10 2018

Clyde Street 1.5 2016

Cochrane Street 135.1 2016

Dangar Street 104 2024

Dorshae Close 4 2018

Douglas Fentiman Street 40 2016

Druitt Street 13 2018

Dudley Street 16 2018

Edgar Street 64.4 2024

Elrington Avenue 77 2016

Emmanuel Crescent 2.5 2024

Eric Kennedy Street 45.5 2016

Geoffrey O’Hea Street

After Before

Page 16: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

16 | P a g e

Kerb and Gutter – Street Length (m) Year Ferry Street 3.3 2018

Forth Street 20 2019

Frank Archibald Street 64.2 2016

Frank Cooper Street 33 2024

George Hardiman Avenue 77.9 2016

Gladstone Street, Kempsey 16.5 2021

Goonbi Street 32.6 2018

Gordon Nixon Avenue 115.9 2019

Government Road 6 2025

Great North Road 157 2019

Greenfields Avenue 67.2 2016

Harold Coutman Street 44.3 2016

Harry Boyes Avenue 91.1 2019

Hennessy Street 79 2020

Hill Street Crescent Head 10 2021

Hillview Drive (in road rehab program) 132

Hopetoun Street 3.5 2019

Hughes Place 47.5 2016

Innes Street 3 2022

Jack Bond Crescent 78 2018

Jack Williams Crescent 28 2018

James Carney Crescent 43 2017

Jersey Street 22 2019

Keith Dunn Street 10 2018

Keith Moses Crescent 64 2019

Kemp Street 49 2021

Killuke Crescent 1 2018

Lachlan Street 17 2021

Lawson Street South West Rocks 74 2016

Leith Street 223 2020

Lindsay Place 12.5 2018

Little Rudder Street 5 2025

Lord Street 162 2021

Macleay Street, Frederickton 15 2021

Macleay Street, Kempsey 56.4 2021

Macquarie Street 57 2018

Main Street Smithtown 29.5 2019

Marine Parade 51.4 2020

Marsh Street 22 2017

McIntyre Street 75 2019

Memorial Avenue, Kempsey 24 2017

Page 17: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

17 | P a g e

Kerb and Gutter – Street Length (m) Year Middleton Street 119.9 2021

Milton Barnett Street 18 2024

Mitchell Avenue 15 2024

Nance Road 44.9 2018

New Street 38 2016

Nicholson Street 51 2018

North Street Kempsey 78 2016

Panorama Avenue 177 2024

Park Road 10 2018

Polwood Street 92 2021

Prince Street 28 2018

Queen Street, South Kempsey 57 2018

Regent Street 2 2021

River Street 72.5 2021

Robert Eggins Street 45.5 2016

Ronald Robinson Place 10.6 2017

Roscoe Turner Avenue 6 2017

Rudder Street, East Kempsey 4 2021

Sea Street 17 2021

Seventeenth Avenue 5 2017

Short Street, West Kempsey 121.1 2018

Smith Street 28 2021

South Street 145 2019

Stanley Dyson Place 1.5 2022

Tabrett Street 91 2020

Taylor Street 56 2016

Thirteenth Avenue 21 2017

Thomas Hennessy Crescent 0.5 2022

Tozer Street 585 2017

Verge Street, Kempsey 29 2017

Vincent Street, Kempsey 5 2018

Walker Street 5 2018

Walter Conn Road 4 2024

Warne Drive 266.9 2020

Warwick Avenue 42 2016

Wide Street 7 2022

Yabsleys Lane 148 2022

Yarravel Street 132 2018

York Lane 1.75 2016

Page 18: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

18 | P a g e

Footpaths Council manages almost 62 kilometres of footpaths and cycleways. The majority of the footpaths are located in Kempsey, although footpaths have been established at South West Rocks, Crescent Head, Stuart Point, Frederickton, Bellbrook, Smithtown and Gladstone. Most of the footpaths are constructed as concrete, with some being asphalt, paving or gravel.

Around 73% of footpaths are identified as being in satisfactory or better condition. These footpaths require little maintenance. This leaves 27% of the network in poor or failed condition with slipperiness, uneven joints and cracking/spalling identified as the most common defects. Footpaths in poor condition attract a greatly increased maintenance effort to reduce the risk of injury.

During 2016 Council will complete a review of the Pedestrian Access & Mobility Plan (PAMP) that will introduce a new level for the prioritisations of renewals. The report will identify non–conforming infrastructure and in particular where ramps are not mobility access compliant. There is also likely to be a renewed focus on completing the footpath network so that it joins the high demand pedestrian locations in an effective manner. The annual program will be reviewed once the PAMP is completed.

In order to address the current asset condition, the following lists the prioritised works program for footpaths over the next 10 years:

Location Cost Year

Bissett Street (Rudder Street to Innes Street – 134m) $48,300 2018

Forth Street (Gladstone Street to Hopetoun Street – 112m) $38,700 2020

Frank Archibald Street (Dunghutti Place to end – 45m) $14,850 2017

Gladstone Street Kempsey (Belgrave Street to Forth Street – 203m) $70,050 2023

Gregory Lane (Paragon Avenue to end – 12m) $1,500 2018

Lachlan Street (Bloomfield Street to Druitt Street – 114m) $29,100 2016

Lachlan Street (Carri Street to Bloomfield Street – 98m) $29,400 2020

Lord Street (Little Rudder Street to Lord Street – 60m) $18,000 2017

Lord Street (Lord Street (Macleay Valley Way) to Herborne Avenue – 135m) $58,800 2016

After

Crescent Head Reserve Foreshore Walkway

Before

Page 19: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

19 | P a g e

Location Cost Year

Regent Street (Forth Street to end – 193m) TBC 2020

River Street (Angus Avenue to Short Street – 115m) $24,150 2023

River Street (Elbow Street to Marsh Street – 231m) $83,100 2022

Rudder Street Kempsey (Ferry Street to Bissett Street – 219m) $62,400 2019

Sea Street (Elbow Street to Marsh Street – 159m) $119,250 2021

Sea Street (Elbow Street to Marsh Street – 44m) $33,000 2017

Sea Street (Leith Street to Elrington Avenue – 18m) $7,800 2018

Smith Street (Forth Street to Stuart Street – 27m) $22,350 2018

South West Rocks Horseshoe Bay Reserve (36m) $9,750 2017

Tozer Street (Elbow Street to Marsh Street – 19m) $16,200 2018

Page 20: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

20 | P a g e

Bridges Council manages 39 concrete bridges and 104 timber bridges as part of the road transport infrastructure network. Timber bridges constitute 73% of the total bridge assets with 28% being identified in poor condition.

Bridges either provide a single access route or an alternative route to a destination. Where alternative routes are available there is a cost resulting from the greater amount of travel required.

Often bridges provide for direct and quick access. It is therefore necessary to manage bridge assets to ensure that they are maintained in a safe condition with cost efficient use of resources. If bridges were closed there would be a cost and inconvenience caused to the community needing to use the alternative route.

The timber bridge program includes, in general, replacement of 2–4 timber bridges per year and refurbishment of a similar number to extend their effective lives. It is projected that over the next 25 years all timber bridges will be replaced with concrete/composite structures or reinforced concrete box culverts. There are presently no load limits on any of Council’s road bridge structures. The following lists the prioritised works program for bridge replacements over the next 10 years:

Location Cost Year

Austral Eden Inner Road – Barnett’s Drain $100,000 2020

Austral Eden Outer Road – Anderson’s Bridge $160,000 2016

Back Creek Footbridge $450,000 2016

Barbers Lane – King Creek $135,000 2018

Belmore River Left Bank Road – Buchanan’s Bridge $300,000 2016

Belmore River Right Bank Road – Scott’s Drain $140,000 2019

Billybyang Creek Road – Griffith’s Bridge $120,000 2023

Billybyang Creek Road – Kyle’s Bridge $140,000 2022

Billybyang Creek Road – Sundowner $140,000 2024

Billybyang Creek Road – Wicks $120,000 2022

Boyters Lane – Boyters $200,000 2018

Brassils Creek Road – Warbro Brook $140,000 2023

Chain O Ponds Road $250,000 2021

Collombatti Road – Brenton’s Dam Bridge $160,000 2023

Dowlings Falls Road – Mainey’s Bridge $200,000 2018

Five Day Creek Road – No. 1 $100,000 2025

Five Day Creek Road – No .2 $100,000 2025

Formwork to the base of a multi cell culvert to replace a timber bridge. The use of precast box culverts greatly increases the speed that small bridges can be replaced and provides the lowest life cycle cost for the community.

Page 21: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

21 | P a g e

Location Cost Year

Five Day Creek Road – No. 3 $200,000 2025

Hickeys Creek Road – Billybyang Creek $300,000 2024

Hickeys Creek Road – Holberton $120,000 2022

Kinchela Creek Left Bank Road – Knauers Bridge $165,000 2016

Kinchela Creek Left Bank Road – Lee’s Drain $250,000 2024

Mines Road – Deep Creek $200,000 2024

Mines Road – Bococka $200,000 2024

Mooneba Road – Barking Dog Bridge $200,000 2017

Nulla Creek Road – O’Neill’s $600,000 2025

Nulla Creek Road – McIntyre’s Bridge $300,000 2016

Nulla Creek Road – Rose’s Bridge $350,000 2020

Old Station Road – Frogmore $120,000 2021

Saleyards Road – Christmas Creek $180,000 2023

Schmidts Access Road – Schmidt’s Bridge $295,000 2017

Secombs Lane – Powicks Access $100,000 2020

Smiths Creek Bridge – Duck Creek $140,000 2023

Smiths Creek Bridge – Nursery Gully $120,000 2021

Sundowner Road – Petersen’s Bridge $120,000 2024

Tamban Road – No. 1 $160,000 2020

Tamban Road – Weisenbucca $120,000 2020

Toose Road – McKenzies $165,000 2020

Toms Gully Road – Kyle’s Bridge $150,000 2017

Toms Gully Road – Toms Gully $150,000 2025

Turners Flat Road – Anderberg $550,000 2019

Verges Creek Road $120,000 2021

Warbro Brook Road – Butler’s Bridge $140,000 2018

Warbro Brook Road – Harry’s Gully $140,000 2022

Warbro Brook Road – McIver $300,000 2022

Willi Willi Road – Oaky Creek $160,000 2021

Page 22: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

22 | P a g e

Smiths Creek Bridge, Kundabung

In addition, some of these bridges and some other lower priority bridges will require refurbishment to extend their life for up to 10 years before replacement is required. The selection of a refurbishment treatment is based upon a comprehensive condition and load capacity assessment. Often several of the bridge components such as piles, capwales, headstocks and/or girders are replaced in addition to a new deck. This can be a cost effective means to defer replacement so that higher priority bridges can be replaced.

Before After

Detailed investigation and assessment of our timber bridges helps to prioritise those requiring replacement and those where refurbishment will extend the life of the existing structure. Where possible bridges are refurbished in order to delay the costs of replacement

Page 23: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

23 | P a g e

Public Toilets Council manages 23 public toilets. These are toilets that are constantly open to the public or generally open only during daylight hours for public use. Facilities that form part of a sporting complex or that are not normally open to the public during the day are not included in this program. The community satisfaction survey undertaken in February 2016 identified the condition of public toilets in the Shire as a priority for our community. It was evident that greater levels of community satisfaction could be achieved through and increase in investment in the condition of our public toilets. An example of this is the work done during 2015 to refurbish the existing toilet within Riverside Park. The following lists the prioritised works program for public toilet replacements/refurbishment over the next four years. Toilets within the coastal reserves have not been included unless funding has already been secured as a review of the management of Council caravan park management is in progress and a further program of works will be developed once this review is completed.

Location Cost Year

Clyde Street Mall, Kempsey – refurbishment $300,000 2016

Crescent Head Foreshore Reserve – replacement $484,000 2016

Riverside Park, Gladstone – refurbishment $200,000 2017

Belgrave Street Park – refurbishment $100,000 2017

Gregory Street Carpark – replacement $300,000 2018

Rudder Park, East Kempsey – replacement $200,000 2019

Yakka Watson Park, Smithtown – refurbishment $100,000 2019

Kempsey Riverside Park amenities during refurbishments

Page 24: 10 Year Works Program 2016-2025 - Kempsey Shire€¦ · 10 Year Works Program 2016 – 2025. 8 | Page Sealed Road Section Estimated Cost Year Collombatti Road (Macleay Valley Way

10 Year Works Program 2016 – 2025

24 | P a g e

Open Spaces & Facilities Council manages 333 hectares of open spaces (including cemeteries, airport and saleyards) 14 sports fields, 26 playgrounds and 32 other buildings. These are facilities that are highly valued by the community and currently well serviced. The community satisfaction survey undertaken in February 2016 identified open spaces and facilities as an area of significance to the community. There is significant opportunity to improve community satisfaction through the refurbishment of recreational assets and facilities. An example of this is the work done during 2015 to refurbish the playground within Riverside Park. In particular, there are excellent opportunities for Council to be supported by the community to deliver benefits at a reduced cost. There is also an opportunity to undertake a program for asset renewal replacement under the Work For The Dole Scheme, which will require council to fund materials and some supervision costs. Whilst some works have been funded in the immediate future, there are a number of strategic projects occurring at present that will provide information upon which to review the current works program, with a view to increasing the level of asset renewals in this area. These projects include the Macleay Valley Sporting Infrastructure Strategy, the open spaces & civic maintenance service level review and condition audits across all assets in this group. The following lists the prioritised works program for replacements/refurbishments that have already been funded. Asset replacements/refurbishments within the coastal reserves have not been included as a review of the management of Council caravan park management is in progress and a further program of works for the coastal reserves will be developed once this review is completed.

Location Cost Year

Horseshoe Bay Reserve Playground – refurbishment $250,000 2016

South Kempsey Park – refurbishment and reorganisation of existing infrastructure $70,000 2016

Rudder Park – replacement of fencing with plantings & refurbishment of park $40,000 2016 Replacement of pedestrian barrier fencing on approaches to the Kempsey Traffic Bridge $40,000 2016

Kempsey Riverside Park refurbishments