25
10 July 2006 ATLAS Plenary 1 Welcome to the ATLAS Overview Week in Stockholm A few words introducing ATLAS to our hosts The new LHC schedule Financial status Implementation of the Operation Model and goals of the ATLAS Week

10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

Embed Size (px)

Citation preview

Page 1: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 1

Welcome to the ATLAS Overview Week in Stockholm

- A few words introducing ATLAS to our hosts- The new LHC schedule- Financial status- Implementation of the Operation Model and goals of the ATLAS Week

Page 2: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 2

Thank you for the friendly welcome to Stockholm !

Professor Kare Bremer Stockholm University,Vice-Chancellor

Professor Anders Flodstroem KTH Stockholm,President

Professor Arne Johansson Swedish Research Council,Secretary GeneralNatural and Engineering Sciences

… but of course also already now to Kerstin Jon-And and Bengt Lund-Jensen for all the careful preparations for the meeting!

Page 3: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 3

ATLAS Collaboration

(As of the March 2006)

35 Countries 158 Institutions 1650 Scientific Authors total(1300 with a PhD, for M&O share)

New application for CB decision in JulyDESY, Humboldt U Berlin (Germany)SLAC, New York U (US)

Albany, Alberta, NIKHEF Amsterdam, Ankara, LAPP Annecy, Argonne NL, Arizona, UT Arlington, Athens, NTU Athens, Baku, IFAE Barcelona, Belgrade, Bergen, Berkeley LBL and UC, Bern, Birmingham, Bologna, Bonn, Boston, Brandeis,

Bratislava/SAS Kosice, Brookhaven NL, Buenos Aires, Bucharest, Cambridge, Carleton, Casablanca/Rabat, CERN, Chinese Cluster, Chicago, Clermont-Ferrand, Columbia, NBI Copenhagen, Cosenza, AGH UST Cracow, IFJ PAN Cracow, Dortmund, TU

Dresden, JINR Dubna, Duke, Frascati, Freiburg, Geneva, Genoa, Giessen, Glasgow, LPSC Grenoble, Technion Haifa, Hampton, Harvard,

Heidelberg, Hiroshima, Hiroshima IT, Indiana, Innsbruck, Iowa SU, Irvine UC, Istanbul Bogazici, KEK, Kobe, Kyoto, Kyoto UE, Lancaster, UN La Plata, Lecce, Lisbon LIP, Liverpool, Ljubljana, QMW London, RHBNC London, UC London, Lund, UA Madrid, Mainz, Manchester, Mannheim, CPPM Marseille, Massachusetts, MIT, Melbourne, Michigan, Michigan SU, Milano, Minsk NAS,

Minsk NCPHEP, Montreal, McGill Montreal, FIAN Moscow, ITEP Moscow, MEPhI Moscow, MSU Moscow, Munich LMU, MPI Munich, Nagasaki IAS, Naples, Naruto UE, New Mexico, Nijmegen, BINP Novosibirsk, Ohio SU, Okayama, Oklahoma,

Oklahoma SU, Oregon, LAL Orsay, Osaka, Oslo, Oxford, Paris VI and VII, Pavia, Pennsylvania, Pisa, Pittsburgh, CAS Prague, CU Prague, TU Prague, IHEP Protvino, Ritsumeikan, UFRJ Rio de Janeiro, Rochester, Rome I, Rome II, Rome III,

Rutherford Appleton Laboratory, DAPNIA Saclay, Santa Cruz UC, Sheffield, Shinshu, Siegen, Simon Fraser Burnaby, Southern Methodist Dallas, NPI Petersburg, Stockholm U, KTH Stockholm, Stony Brook, Sydney, AS Taipei, Tbilisi, Tel Aviv,

Thessaloniki, Tokyo ICEPP, Tokyo MU, Toronto, TRIUMF, Tsukuba, Tufts, Udine, Uppsala, Urbana UI, Valencia, UBC Vancouver, Victoria, Washington, Weizmann Rehovot, Wisconsin, Wuppertal, Yale, Yerevan

Page 4: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 4

Diameter 25 mBarrel toroid length 26 mEnd-cap end-wall chamber span 46 mOverall weight 7000 Tons

The ATLAS detector

ATLAS superimposed tothe 5 floors of building 40

Page 5: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 5

The underground cavern at point-1 forthe ATLAS Detector

Length = 55 mWidth = 32 mHeight = 35 m

Page 6: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 6

An aerial view of point-1

(Across the street from the CERN main entrance)

Page 7: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 7

The ATLAS detector being installed now in the underground cavern

Page 8: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 8

Simulation of a H ee event in ATLAS

Page 9: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 9

The impressive progress on the construction, installation, and commissioning of the detector, as well as on the preparation for the data collection, the distributed analysis and the physics, will be covered over this week

As the details we will be presented all ‘first hand’ by those doing actually the work, there is no point for me to cover any of this now…

Integration work on one of the two SCT end-caps

Page 10: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 10

News from the LHC machine

Page 11: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 11

New LHC machine schedule

A new LHC schedule and turn-on strategy was presented to the CERN SPC and Councilthree weeks ago

The experiments were informed only shortly before, and allowed to communicate it just after the SPC meeting

The main features of the new schedule are:

- The beam pipe closure date will be end of August 2007 (instead of end of June 2007)

- After that there will still be a few weeks of controlled access to the cavern

- This is followed by an LHC commissioning run with collisions at the injection energy (450 + 450 GeV), until the end of 2007

- Then there will be a shut-down (typically 3 months) during which the remaining machine sectors will be commissioned without beam to full energy (7 TeV)

- After that the LHC will be brought into operation for the first physics run at 14 TeV, with the aim to integrate substantial luminosity by the end of 2008

The LHC Machine Advisory Committee (MAC) has strongly endorsed this new start-up strategy asthe most efficient way to reach 14 TeV collisions

The SPC stressed that the goal should be several fb-1 integrated luminosity at the end of 2008

Page 12: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 12

Last magnet delivered October 2006

Last magnet tested December 2006

Last magnet installed March 2007

Machine closed August 2007

First collisions November 2007

Milestones for the machine

- Sectors 7-8 and 8-1 will be fully commissioned up to 7 TeV in 2006-2007. If we

continue to commission the other sectors up to 7 TeV, we will not get circulating

beam in 2007.

- The other sectors will be commissioned up to the field needed for de-Gaussing.

- Initial operation will be at 900 GeV (CM) with a static machine (no ramp, no

squeeze) to debug machine and detectors.

- Full commissioning up to 7 TeV will be done in the winter 2008 shutdown

LHC commissioning

(Presented by CERN to SPC and Council)

Page 13: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 13

Page 14: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 14

LSS installation

Installation activities in a sector

QRL installation

QRL consolidation after pressure test

Cryo-magnet transport

Interconnection phase 1

Pressure test

Cryostat closure – Interconnect consolidation

ELQA at warm Cool-down

Power testsMachine check-out

Beam at 450 GeV/C

Insulation // Interconnect phase 1

Beam pipes & bake-out

End of 1st interconnect activity

Page 15: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 15

Page 16: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 16

We now have enough information to produce a consolidated plan for

commissioning.

Three quarters of the machine has been liberated for magnet

installation and interconnect work is proceeding in 2 octants in

parallel. Magnet installation is now steady at 25/wk . Installation will

finish March 2007. The machine will be closed in August 2007.

Every effort is being made to establish colliding beams before the

end of 2007 at reduced energy. The full commissioning up to 7 TeV

will be done during the 2008 winter shutdown ready for a Physics run

at full energy in spring 2008.

CERN management’s conclusion

(Presented last week by J Engelen at theCracow Physics at LHC conference)

Page 17: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 17

W e Z ee

(Data taking efficiency (machine x detector) of 30% includedEfficiency of all analysis cuts included)

s = 900 GeV, L =1029 cm-2 s-1

Given this new schedule situation, ATLAS stated that the start-up strategy should be such that the useful integrated luminosity at 14 TeV at the end of 2008 will be maximized

This points towards preferring a few weeks of stable running conditions at the injection energyas compared to possibly lengthy attempts to reach the maximum possible beam energy of 1.1 TeVbefore the full commissioning of LHC power components in the winter shut-down

Primarily the run in 2007 will be a detector and computing commissioning run, much more than a physics run

Page 18: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 18

Overall financial situation (more details in the CB)

Main financial framework (a simplified summary)

ATLAS construction budget initial MoU 1995 475 MCHF

updated baseline contributions 468 MCHF

Cost-to-Completion (CtC) evaluation 68 MCHF(in addition to deliverables, accepted by the RRB in October 2002 based on the Completion Plan)

Main funding issues today

There are remaining outstanding contributions to the baseline & Common Fund 9 MCHF

Not all the calculated CtC shares have been pledged, in fact the situation only looksquite good because CERN has committed 5 MCHF more than its calculated share

The following table shows the details

Page 19: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 19

Funding Agency Member New funding (category 1) New funding requestsfee 2004-6 including member fee as prospects (category 2)

Constr. (included in without commitment from FATotal Comp. C&I Constr. Comp.) Total Total

Armenia 66 48 18 38 45Australia 357 242 115 75 140 238Austria 67 52 15 38 67Azerbaijan 43 38 5 38 38Belarus 85 75 10 75 75Brazil 64 47 17 38 41Canada 2090 1528 562 263 2090 0China NSFC+MSTC 141 99 42 38 141Czech Republic 316 196 120 113 316Denmark 422 290 132 38 58 375France IN2P3 5890 4176 1714 225 5890 0France CEA *) 1940 1379 561 38 1334Georgia 42 37 5 38 38Germany BMBF 4531 3250 1281 338 4531 0Germany MPI 1093 761 332 38 1093Greece 261 173 88 113 113 148Israel 739 497 242 113 739Italy 6638 4650 1988 450 6288Japan 4362 3029 1333 563 4362Morocco 57 47 10 38 41Netherlands 1934 1368 566 75 1934Norway 581 391 190 75 581Poland 136 94 42 75 102 34Portugal 446 265 181 38 339 107Romania 140 85 55 38 140Russia 2991 1995 996 263 1759JINR 1066 660 406 38 521Serbia 300Slovak Republic 72 53 19 38 82Slovenia 223 152 71 38 223Spain 1706 1109 597 113 1706Sweden 1691 1121 570 150 1691Switzerland 2372 1701 671 75 2372 0Taipei 445 318 127 38 445Turkey 85 75 10 75 75United Kingdom 4387 3063 1324 450 3133 1254US DOE + NSF 12245 8438 3807 1238 6200CERN 8452 5770 2682 38 13700

Total 68176 47272 20904 5563 62743 2156

*) The commitment shown does not include a 1 MCHF additional engineering contribution provided on the initial BT contract (see MoU Annex 8.A)

Cost to Completion proposed sharing

Status of the Cost to Completion funding (CERN-RRB-2006-027)

Page 20: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 20

Updated Cost to Completion estimates

The RRB was warned in the April 2006 meeting that the ATLAS management is re-evaluating thefinancial situation and evolution since the CtC estimates accepted in October 2002

The situation as we understand it now is that there are new overcosts projected at the level of 4.4 MCHF for the completion, over the 68 MCHF estimated in 2002

Further delays in installation work beyond August 2007 would require additional resources for manpower to be paid (order 200 – 400 kCHF per month)

System Item

Item Over Run

System Over Run

System Total Cost

System Over Cost

    MCHF MCHF MCHF %

Magnet     1.76 158.2 1.1%

Technical Coordination     2.39 49.6 4.8%

  Muon Big Wheels 1.39      

 TCn installation manpower efforts at Point 1. 1.00      

LArCC project     0.25 38.7 0.6%

ATLAS     4.40 536 0.8%

Not initially part of TCn

The following table has been made by the CB Audit Group (see C Oram’s CB presentation)

Largely due to theengineering contracts

Workforce notavailable from CERNand Institutes

Page 21: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 21

Note that these overcosts could still be absorbed within the initial completion plan provided that all FAs would provide the full calculated share of the initial CtC funds, given the extra contribution provided by CERN

Alternative funding schemes have been discussed with the CB Audit Group, and will be discussed in the CB meeting

Restoration of the full TDR detector

The RRB has been reminded regularly that for the standard LHC design-luminosity the ATLASdetector will have to be restored to its approved TDR configuration

At the time of the establishment of the Completion Plan (October 2002), this was estimated tobe in the 20 MCHF range (usual CORE material accounting)

The ATLAS management will have to examine and coordinate plans for reaching the full detectorin the coming months; we are also requested to give first indications about this at the next RRB

Page 22: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 22

Global ATLAS Budget Balance (MCHF)

-25

0

25

50

75

100

125

150

175

200

225

250

275

95-01 2002 2003 2004 2005 2006 2007

Year

MCH

F

Payments

Income

Budget Balance(Cumulative)Cumulative (October2005)

Remaining is also the cash flow problem… (see M Nordberg’s regular presentations for details)

Page 23: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 23

Executive Board

ATLAS management: SP, Deputy SP, RC, TCCollaboration Management, experiment execution, strategy, publications, resources, upgrades, etc.

PublicationCommittee,Speaker Committee

CB

Detector Operation (Run Coordinator)Detector operation during data taking, online data quality, …

Trigger (Trigger Coordinator)Trigger data quality,performance, menu tables, new triggers, ..

Data Preparation (Data Preparation Coordinator)Offline data quality, first reconstruction of physics objects, calibration, alignment (e.g. with Zll data)

Computing (Computing Coordinator)Core Software, operation of offline computing, …

Physics (Physics Coordinator)optimization of algorithms for physics objects, physics channels

(Sub)-systems:Responsible for operation and calibration of their sub-detector and for sub-system specific software

TMB

During this ATLAS Week it will become evident that the ‘Operation Model’ is being implemented in a gradual and pragmatic way

(Details can be found at http://uimon.cern.ch/twiki//bin/view/Main/OperationModel )

Page 24: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 24

Steps on the way to the gradual implementation of the Operation Model (OM)

Setting up of the five activity areas:

Detector operation Will evolve from the present commissioning organization which iswell functional and growing

Trigger Will evolve from the present TDAQ system and physics-relatedtrigger activities, and the TDAQ management changes underway anticipate the reorganization

Computing Basically existing, OM adaptations being implemented

Data Preparation Is being set up now, will regroup many present activities

Physics Basically existing, OM adaptations being implemented

An important step was the introduction of explicit combined Trigger and Physics Weeks driving this central activity for preparing the data taking era

Both the cosmic ray running, gradually starting at Point-1, and the forthcoming large-scale ‘Calibration Data Challenge’ simulations can be seen as important ‘shake-down’ actions for the OM implementation

We have also initiated a major effort (OTSMOU Working Group) to define the fair sharing of all operation tasks between all the Institutions, and to review the M&O sharing for the running phase

This will include a definition of obligations for new Institutions joining ATLAS in this new phase

Page 25: 10 July 2006ATLAS Plenary1 Welcome to the ATLAS Overview Week in Stockholm - A few words introducing ATLAS to our hosts - The new LHC schedule - Financial

10 July 2006 ATLAS Plenary 25

Main goals in very general terms

Get a global view of where we stand in all aspects in the preparations for our experiment

Recall that global aspects concern us all, and that we need to care about much more than just the areas of our own activities

This OW should make us particularly aware of the ongoing transition from construction to operation

The major focal points are clear

- Completion of the construction- Assembly, integration and commissioning of the detector components- Computing and software- Trigger and physics preparation

- Installation- Commissioning

- In general: preparation of the operation phase

Last, but not least, enjoy a stimulating and motivating time together

Recalling the Goals of the Overview Weeks: