AcornPip 1.0 Intro AcornPip (a) M (b) W (c) A (d) E Original Each Ac configur AcornPip Material (MGSP) Choosin only the autolabo etc.) It d is handle labor. 2.0 Mate Material priced in reached Control b Tools/Jo as show Tools/In The unit factored Once the drawing pe Material oduction to pe can be u Materials P Welds Auto Labor Extra Labor System or cornPipe job red to use e pe Pricing S l Group Spe ) system. ng the MGS pricing of w or (cuts, bev does not affe ed for items erials Pip ls such as p n the invent d from Fabri by selecting ob Inventory wn. You may nventory Up t price for e d by Factor e unit price is simply a l and Labor o Pricing u used to calc Pipe, fitting cuts, beve MGSP Sys b can be either the or System, or ecific Pricin SP option af welds and vels, end ca ect how pri s or for extr pe, Fittings pipe and fitt tory view, w ication Mate g y/Pricing/Ite y need to fi pdate only to each item is 1, which wi es and Facto a matter of d r Pricing using Acor culate pricin gs, and misc els, tig root stem: riginal the ng ffects aps icing ra s, and Misc tings are which is erial ems irst select o bring the s entered in ill be 1.00 if or 1 values displaying t 1 rnPipe ng for: cellaneous t, end prote cellaneous inventory v the Unit Pr f no discou s have been the drawing items. ectors, hand s Items view up to d rice column unt nor prem n entered, p g and then s dling etc. date. n. The price mium applie pricing the m selecting V 2017-0 e used is es. materials o View/Pricing 04-07 on a g.

1.0 Introduction to Pricing using AcornPipe Files/Pricing Information in...hydrotest, preheat, as described in section 1 and select 2017-0 end protectors e 4-07 . AcornPip 5.0 Extra

  • Upload
    dominh

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

AcornPip

1.0 Introduction to Pricing

AcornPipe can be used to calculate pricing for:

(a) Materials

(b) Welds

(c) Auto Labor

(d) Extra Labor

Original System or MGSP

Each AcornPipe job can be

configured to use either the original

AcornPipe Pricing System, or the

Material Group Specific Pricing

(MGSP) system.

Choosing the MGSP option affects

only the pricing of welds and

autolabor (cuts, bevels, end caps

etc.) It does not affect how pricing

is handled for items or for extra

labor.

2.0 Materials

Materials such as pipe and fittings are

priced in the inventory view, which is

reached from Fabrication Material

Control by se

Tools/Job Inventory/Pricing/Items

as shown.

Tools/Inventory Update only

The unit price for each item is entered in the Unit Price column. The price used is

factored by Factor 1

Once the unit prices and Factor 1 values have been entered, pricing the materials on a

drawing is simply a matter of displaying the drawing and then selecting View/Pricing.

AcornPipe Material and Labor Pricing

1.0 Introduction to Pricing

AcornPipe can be used to calculate pricing for:

Materials – Pipe, fittings, and miscellaneous items.

Welds

Auto Labor –

Extra Labor

Original System or MGSP

Each AcornPipe job can be

configured to use either the original

AcornPipe Pricing System, or the

Material Group Specific Pricing

(MGSP) system.

Choosing the MGSP option affects

only the pricing of welds and

autolabor (cuts, bevels, end caps

It does not affect how pricing

is handled for items or for extra

Materials – Pipe, Fittings, and Miscellaneous Items

Materials such as pipe and fittings are

priced in the inventory view, which is

reached from Fabrication Material

Control by selecting

Tools/Job Inventory/Pricing/Items

as shown. You may need to first select

Tools/Inventory Update only

The unit price for each item is entered in the Unit Price column. The price used is

factored by Factor 1

Once the unit prices and Factor 1 values have been entered, pricing the materials on a

drawing is simply a matter of displaying the drawing and then selecting View/Pricing.

e Material and Labor Pricing

1.0 Introduction to Pricing using AcornPipe

AcornPipe can be used to calculate pricing for:

Pipe, fittings, and miscellaneous items.

– cuts, bevels, tig root, end protectors, handling etc.

Original System or MGSP System:

Each AcornPipe job can be

configured to use either the original

AcornPipe Pricing System, or the

Material Group Specific Pricing

Choosing the MGSP option affects

only the pricing of welds and

autolabor (cuts, bevels, end caps

It does not affect how pricing

is handled for items or for extra

Pipe, Fittings, and Miscellaneous Items

Materials such as pipe and fittings are

priced in the inventory view, which is

reached from Fabrication Material

lecting

Tools/Job Inventory/Pricing/Items

You may need to first select

Tools/Inventory Update only to bring the inventory view up to date.

The unit price for each item is entered in the Unit Price column. The price used is

factored by Factor 1, which will be

Once the unit prices and Factor 1 values have been entered, pricing the materials on a

drawing is simply a matter of displaying the drawing and then selecting View/Pricing.

e Material and Labor Pricing

using AcornPipe

AcornPipe can be used to calculate pricing for:

Pipe, fittings, and miscellaneous items.

cuts, bevels, tig root, end protectors, handling etc.

System:

configured to use either the original

AcornPipe Pricing System, or the

Material Group Specific Pricing

Choosing the MGSP option affects

autolabor (cuts, bevels, end caps

It does not affect how pricing

is handled for items or for extra

Pipe, Fittings, and Miscellaneous Items

Materials such as pipe and fittings are

priced in the inventory view, which is

reached from Fabrication Material

Tools/Job Inventory/Pricing/Items

You may need to first select

to bring the inventory view up to date.

The unit price for each item is entered in the Unit Price column. The price used is

which will be 1.00 if no discount nor premium applies

Once the unit prices and Factor 1 values have been entered, pricing the materials on a

drawing is simply a matter of displaying the drawing and then selecting View/Pricing.

1

using AcornPipe

AcornPipe can be used to calculate pricing for:

Pipe, fittings, and miscellaneous items.

cuts, bevels, tig root, end protectors, handling etc.

Pipe, Fittings, and Miscellaneous Items

to bring the inventory view up to date.

The unit price for each item is entered in the Unit Price column. The price used is

if no discount nor premium applies

Once the unit prices and Factor 1 values have been entered, pricing the materials on a

drawing is simply a matter of displaying the drawing and then selecting View/Pricing.

Pipe, fittings, and miscellaneous items.

cuts, bevels, tig root, end protectors, handling etc.

Pipe, Fittings, and Miscellaneous Items

to bring the inventory view up to date.

The unit price for each item is entered in the Unit Price column. The price used is

if no discount nor premium applies

Once the unit prices and Factor 1 values have been entered, pricing the materials on a

drawing is simply a matter of displaying the drawing and then selecting View/Pricing.

cuts, bevels, tig root, end protectors, handling etc.

to bring the inventory view up to date.

The unit price for each item is entered in the Unit Price column. The price used is

if no discount nor premium applies

Once the unit prices and Factor 1 values have been entered, pricing the materials on a

drawing is simply a matter of displaying the drawing and then selecting View/Pricing.

2017-0

The unit price for each item is entered in the Unit Price column. The price used is

if no discount nor premium applies.

Once the unit prices and Factor 1 values have been entered, pricing the materials on a

drawing is simply a matter of displaying the drawing and then selecting View/Pricing.

04-07

Once the unit prices and Factor 1 values have been entered, pricing the materials on a

drawing is simply a matter of displaying the drawing and then selecting View/Pricing.

AcornPip

3.0 Welds

The following

section 1.0 above. Otherwise,

which describes the original weld pricing system.

To enter weld prices, you need to have saved at least one drawing since turning on

MGSP. If you have just turned on MGSP, batch resave all drawings so as to create a

complete pricing table. Then get to Fabrication Material Control and select

Tools/Job In

and type of weld used on the job. Welds of different material groups are listed

separately.

Fill in the Price and Factor columns. For example, a Factor of 0.9 represents a 10%

discount. If many lines have the same Factor, select all the relevant cells in that column

and enter the desired value. It will then be propagated to all the selected lines.

If weld prices do not appear on the drawing when

you switch to pricing view, go to

frame in the Job Options window and make sure the

Fab Welds box is checked as shown.

AcornPipe Material and Labor Pricing

.0 Welds

The following assumes you have opted to use the MGSP system as described

section 1.0 above. Otherwise,

which describes the original weld pricing system.

To enter weld prices, you need to have saved at least one drawing since turning on

MGSP. If you have just turned on MGSP, batch resave all drawings so as to create a

complete pricing table. Then get to Fabrication Material Control and select

Tools/Job Inventory/Pricing/ Welds. This brings up a table listing each size, schedule

and type of weld used on the job. Welds of different material groups are listed

separately.

Fill in the Price and Factor columns. For example, a Factor of 0.9 represents a 10%

count. If many lines have the same Factor, select all the relevant cells in that column

and enter the desired value. It will then be propagated to all the selected lines.

If weld prices do not appear on the drawing when

you switch to pricing view, go to

frame in the Job Options window and make sure the

Fab Welds box is checked as shown.

e Material and Labor Pricing

assumes you have opted to use the MGSP system as described

section 1.0 above. Otherwise,

which describes the original weld pricing system.

To enter weld prices, you need to have saved at least one drawing since turning on

MGSP. If you have just turned on MGSP, batch resave all drawings so as to create a

complete pricing table. Then get to Fabrication Material Control and select

ventory/Pricing/ Welds. This brings up a table listing each size, schedule

and type of weld used on the job. Welds of different material groups are listed

Fill in the Price and Factor columns. For example, a Factor of 0.9 represents a 10%

count. If many lines have the same Factor, select all the relevant cells in that column

and enter the desired value. It will then be propagated to all the selected lines.

If weld prices do not appear on the drawing when

you switch to pricing view, go to

frame in the Job Options window and make sure the

Fab Welds box is checked as shown.

e Material and Labor Pricing

assumes you have opted to use the MGSP system as described

section 1.0 above. Otherwise, see the document

which describes the original weld pricing system.

To enter weld prices, you need to have saved at least one drawing since turning on

MGSP. If you have just turned on MGSP, batch resave all drawings so as to create a

complete pricing table. Then get to Fabrication Material Control and select

ventory/Pricing/ Welds. This brings up a table listing each size, schedule

and type of weld used on the job. Welds of different material groups are listed

Fill in the Price and Factor columns. For example, a Factor of 0.9 represents a 10%

count. If many lines have the same Factor, select all the relevant cells in that column

and enter the desired value. It will then be propagated to all the selected lines.

If weld prices do not appear on the drawing when

you switch to pricing view, go to the Labor Pricing

frame in the Job Options window and make sure the

Fab Welds box is checked as shown.

2

assumes you have opted to use the MGSP system as described

the document Weld

which describes the original weld pricing system.

To enter weld prices, you need to have saved at least one drawing since turning on

MGSP. If you have just turned on MGSP, batch resave all drawings so as to create a

complete pricing table. Then get to Fabrication Material Control and select

ventory/Pricing/ Welds. This brings up a table listing each size, schedule

and type of weld used on the job. Welds of different material groups are listed

Fill in the Price and Factor columns. For example, a Factor of 0.9 represents a 10%

count. If many lines have the same Factor, select all the relevant cells in that column

and enter the desired value. It will then be propagated to all the selected lines.

If weld prices do not appear on the drawing when

the Labor Pricing

frame in the Job Options window and make sure the

assumes you have opted to use the MGSP system as described

Weld-Labor-Pricing

To enter weld prices, you need to have saved at least one drawing since turning on

MGSP. If you have just turned on MGSP, batch resave all drawings so as to create a

complete pricing table. Then get to Fabrication Material Control and select

ventory/Pricing/ Welds. This brings up a table listing each size, schedule

and type of weld used on the job. Welds of different material groups are listed

Fill in the Price and Factor columns. For example, a Factor of 0.9 represents a 10%

count. If many lines have the same Factor, select all the relevant cells in that column

and enter the desired value. It will then be propagated to all the selected lines.

frame in the Job Options window and make sure the

assumes you have opted to use the MGSP system as described

Pricing-in-AcornPipe.

To enter weld prices, you need to have saved at least one drawing since turning on

MGSP. If you have just turned on MGSP, batch resave all drawings so as to create a

complete pricing table. Then get to Fabrication Material Control and select

ventory/Pricing/ Welds. This brings up a table listing each size, schedule

and type of weld used on the job. Welds of different material groups are listed

Fill in the Price and Factor columns. For example, a Factor of 0.9 represents a 10%

count. If many lines have the same Factor, select all the relevant cells in that column

and enter the desired value. It will then be propagated to all the selected lines.

2017-0

assumes you have opted to use the MGSP system as described in

AcornPipe.pdf

To enter weld prices, you need to have saved at least one drawing since turning on

MGSP. If you have just turned on MGSP, batch resave all drawings so as to create a

complete pricing table. Then get to Fabrication Material Control and select

ventory/Pricing/ Welds. This brings up a table listing each size, schedule

and type of weld used on the job. Welds of different material groups are listed

Fill in the Price and Factor columns. For example, a Factor of 0.9 represents a 10%

count. If many lines have the same Factor, select all the relevant cells in that column

and enter the desired value. It will then be propagated to all the selected lines.

04-07

pdf,

To enter weld prices, you need to have saved at least one drawing since turning on

MGSP. If you have just turned on MGSP, batch resave all drawings so as to create a

ventory/Pricing/ Welds. This brings up a table listing each size, schedule

Fill in the Price and Factor columns. For example, a Factor of 0.9 represents a 10%

count. If many lines have the same Factor, select all the relevant cells in that column

AcornPip

4.0 AutoLabor

AutoLabor includes cuts, bevels, tig root

and handling. Handling can be by length,

following

To enter AutoLabor

Tools/Job Inventory/Pricing/Auto Labor.

Note that while the costs

group (and each combination of size and schedule), preheats and end protector costs

are independent of material group.

AcornPipe Material and Labor Pricing

4.0 AutoLabor

AutoLabor includes cuts, bevels, tig root

and handling. Handling can be by length,

following assumes that the MGSP option has been selected

To enter AutoLabor

Tools/Job Inventory/Pricing/Auto Labor.

Note that while the costs

group (and each combination of size and schedule), preheats and end protector costs

are independent of material group.

e Material and Labor Pricing

AutoLabor includes cuts, bevels, tig root

and handling. Handling can be by length,

assumes that the MGSP option has been selected

To enter AutoLabor pricing, get to

Tools/Job Inventory/Pricing/Auto Labor.

Note that while the costs for cuts and bevels are specified separately for each material

group (and each combination of size and schedule), preheats and end protector costs

are independent of material group.

e Material and Labor Pricing

AutoLabor includes cuts, bevels, tig root/

and handling. Handling can be by length,

assumes that the MGSP option has been selected

, get to Fabrication Control

Tools/Job Inventory/Pricing/Auto Labor.

for cuts and bevels are specified separately for each material

group (and each combination of size and schedule), preheats and end protector costs

are independent of material group.

3

/argon purge,

and handling. Handling can be by length, size, and schedule or by weight. Th

assumes that the MGSP option has been selected

Fabrication Control

for cuts and bevels are specified separately for each material

group (and each combination of size and schedule), preheats and end protector costs

argon purge, hydrotest, preheat,

size, and schedule or by weight. Th

assumes that the MGSP option has been selected as described in section 1

Fabrication Control and select

for cuts and bevels are specified separately for each material

group (and each combination of size and schedule), preheats and end protector costs

hydrotest, preheat,

size, and schedule or by weight. Th

as described in section 1

select

for cuts and bevels are specified separately for each material

group (and each combination of size and schedule), preheats and end protector costs

2017-0

hydrotest, preheat, end protectors

size, and schedule or by weight. The

as described in section 1

for cuts and bevels are specified separately for each material

group (and each combination of size and schedule), preheats and end protector costs

04-07

end protectors

as described in section 1.

for cuts and bevels are specified separately for each material

group (and each combination of size and schedule), preheats and end protector costs

AcornPip

5.0 Extra Labor

Labor items such as documentation, bird screens, counte

that cannot conveniently be included under AutoLabor are handled as Extra Labor.

To enter extra labor pricing for the current job, select

Tools/Job Inventory Pricing/Extra Labor and edit the table as shown below.

If adjace

multiple lines before entering the price.

AcornPipe keeps track of extra labor based on the size (if any) and on the description

you supply, so you need to be systematic with your de

It is recommended you omit the size from the description if at all possible. For example,

if you have different charges for radiographs depending on size, enter simply “X

Std ” or “

make your prices much easier to manage.

The value applied by AcornPipe is the Price times the Factor. There is no MatGroup or

other factor involved.

AcornPipe Material and Labor Pricing

5.0 Extra Labor

Labor items such as documentation, bird screens, counte

that cannot conveniently be included under AutoLabor are handled as Extra Labor.

To enter extra labor pricing for the current job, select

Tools/Job Inventory Pricing/Extra Labor and edit the table as shown below.

If adjacent prices or factors are the same, you can enter them faster by selecting

multiple lines before entering the price.

cornPipe keeps track of extra labor based on the size (if any) and on the description

you supply, so you need to be systematic with your de

It is recommended you omit the size from the description if at all possible. For example,

if you have different charges for radiographs depending on size, enter simply “X

” or “X-Ray Sch 160

make your prices much easier to manage.

The value applied by AcornPipe is the Price times the Factor. There is no MatGroup or

other factor involved.

e Material and Labor Pricing

Labor items such as documentation, bird screens, counte

that cannot conveniently be included under AutoLabor are handled as Extra Labor.

To enter extra labor pricing for the current job, select

Tools/Job Inventory Pricing/Extra Labor and edit the table as shown below.

nt prices or factors are the same, you can enter them faster by selecting

multiple lines before entering the price.

cornPipe keeps track of extra labor based on the size (if any) and on the description

you supply, so you need to be systematic with your de

It is recommended you omit the size from the description if at all possible. For example,

if you have different charges for radiographs depending on size, enter simply “X

Ray Sch 160” for the description and be consistent over

make your prices much easier to manage.

The value applied by AcornPipe is the Price times the Factor. There is no MatGroup or

other factor involved.

e Material and Labor Pricing

Labor items such as documentation, bird screens, counte

that cannot conveniently be included under AutoLabor are handled as Extra Labor.

To enter extra labor pricing for the current job, select

Tools/Job Inventory Pricing/Extra Labor and edit the table as shown below.

nt prices or factors are the same, you can enter them faster by selecting

multiple lines before entering the price.

cornPipe keeps track of extra labor based on the size (if any) and on the description

you supply, so you need to be systematic with your de

It is recommended you omit the size from the description if at all possible. For example,

if you have different charges for radiographs depending on size, enter simply “X

” for the description and be consistent over

make your prices much easier to manage.

The value applied by AcornPipe is the Price times the Factor. There is no MatGroup or

4

Labor items such as documentation, bird screens, counte

that cannot conveniently be included under AutoLabor are handled as Extra Labor.

To enter extra labor pricing for the current job, select

Tools/Job Inventory Pricing/Extra Labor and edit the table as shown below.

nt prices or factors are the same, you can enter them faster by selecting

cornPipe keeps track of extra labor based on the size (if any) and on the description

you supply, so you need to be systematic with your de

It is recommended you omit the size from the description if at all possible. For example,

if you have different charges for radiographs depending on size, enter simply “X

” for the description and be consistent over

make your prices much easier to manage.

The value applied by AcornPipe is the Price times the Factor. There is no MatGroup or

Labor items such as documentation, bird screens, counterbores, bolt

that cannot conveniently be included under AutoLabor are handled as Extra Labor.

To enter extra labor pricing for the current job, select

Tools/Job Inventory Pricing/Extra Labor and edit the table as shown below.

nt prices or factors are the same, you can enter them faster by selecting

cornPipe keeps track of extra labor based on the size (if any) and on the description

you supply, so you need to be systematic with your descriptions.

It is recommended you omit the size from the description if at all possible. For example,

if you have different charges for radiographs depending on size, enter simply “X

” for the description and be consistent over

The value applied by AcornPipe is the Price times the Factor. There is no MatGroup or

rbores, bolt-ups, x

that cannot conveniently be included under AutoLabor are handled as Extra Labor.

Tools/Job Inventory Pricing/Extra Labor and edit the table as shown below.

nt prices or factors are the same, you can enter them faster by selecting

cornPipe keeps track of extra labor based on the size (if any) and on the description

scriptions.

It is recommended you omit the size from the description if at all possible. For example,

if you have different charges for radiographs depending on size, enter simply “X

” for the description and be consistent over all sizes. This will

The value applied by AcornPipe is the Price times the Factor. There is no MatGroup or

2017-0

ups, x-rays etc.

that cannot conveniently be included under AutoLabor are handled as Extra Labor.

Tools/Job Inventory Pricing/Extra Labor and edit the table as shown below.

nt prices or factors are the same, you can enter them faster by selecting

cornPipe keeps track of extra labor based on the size (if any) and on the description

It is recommended you omit the size from the description if at all possible. For example,

if you have different charges for radiographs depending on size, enter simply “X-Ray

all sizes. This will

The value applied by AcornPipe is the Price times the Factor. There is no MatGroup or

04-07

rays etc.

cornPipe keeps track of extra labor based on the size (if any) and on the description

It is recommended you omit the size from the description if at all possible. For example,

Ray

all sizes. This will

The value applied by AcornPipe is the Price times the Factor. There is no MatGroup or

AcornPipe Material and Labor Pricing 5 2017-04-07

6.0 Technical Details about Pricing

Table 1 below shows where the pricing information is stored under both the original

pricing scheme and the MGSP option.

Table 1

Files holding Pricing Information for job HYD

Original Pricing MGSP File Location

Items HYD_Inventory.dbf AcornClients

Welds FabWeldPricingHYD.dbf MGSP_FabWeldPricingHYD.dbf Job Folder

Auto Labor

FabALPricingHYD.dbf MGSP_FabALPricingHYD.dbf Job Folder

Extra Labor FabXLPriceHYD.dbf

Job Folder

Each .dbf file has an corresponding index file which has the extension .cdx.

Switching to MGSP does not affect item prices because they are for specific materials

already, and it does not affect extra labor prices because they are indpendent of

material group. Only weld pricing and autolabor pricing are affected by the MGSP

selection.