Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 1
1.0 EXECUTIVE SUMMARY
1.1 Name of the Project Proponent: : SKS ISPAT & POWEER LTD.
1.2 Location : 18th Mile Stone, Bilaspur Road, Village: Siltara, Tehsil: Dharsiva Raipur (C.G.) - 493 111
1.3 Office (Regd.) : 501-B, Elegant Business Plaza J.B. Nagar, Andheri-Kurla Road Andheri (E), MUMBAI – 400 059
1.4 Name of Promoters : Mr. Pankaj K Jha (Whole Time Director)
1.5 Existing, Proposed and Total Capacity of SMS Division
Existing Production capacity & configuration
Proposed Change/ configuration
Total production capacity & configuration
Remarks
SMS – 3,31,500 TPA 3 x 12T Induction Furnace & 3 x 15T Induction Furnace
SMS – 3,31,500 TPA (No change in approved capacity) 4 x 15T Induction Furnace
SMS – 3,31,500 TPA (Initially approved capacity) 3 x 12T Induction Furnace 7 x 15T Induction Furnace
Four more Induction Furnace of (15T each) to be installed to achieve approved rated production
1.6 Total Project Area : Total project 225 Acres (91.05 Ha.) including proposed
land 02 acres (0.809 ha) within existing premises
1.7 Number of Shift : Round the Clock (4 Shift)
1.8 No. of Working Days : 320 Days
1.9 Cost of Project : Existing: Rs. 1000.00Cr; Proposed: Rs. 25.00Cr.
Total Cost: 1025 Cr(Rs.)
1.10 Man Power Utilization : Employment (SMS Division)
Existing = 122, Proposed = 70, Total = 192
1.11 Water Requirement Existing water requirement is 4,764 m3/d, No additional water required (Source: Kharun River)
Drawl of water 4800m3/day, permission already obtained from WRD, CG.
1.12 Power Requirement : Existing 85 MW (No additional power requirement) Source: Captive generation (CPP)
1.12 Greenbelt : 33% green belt already developed within existing plant premises (52,000 Nos.)
1.12 Project Implementation Period : 06 Months
1.13 Environment Consulting Organization
: Anacon Laboratories Pvt. Ltd. Head Office: 60, Bajiprabhu Nagar,Nagpur-440 033, Lab. : FP-34, 35, Food Park, MIDC, Butibori, Nagpur – 441122 MS Ph. : (0712) 2242077, 9373287475 Fax: (0712) 2242077 Email: [email protected], [email protected] website: www.anaconlaboratories.com
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 2
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 Identification of project and project proponent:
SKS Ispat and Power Limited, is an ISO 9001-2008, ISO 14001-2004 certified Steel conglomerate,
having 6 Lakh tons per annum Integrated Steel Plant in Raipur, Chhattisgarh. The company has Rich
experience of 40 years in the Steel Industry enables to understand and serve valuable customers in a
highly professional and cost effective manner.
SKS Ispat & Power Limited, presently have various facilities in their existing integrated steel plant in
Siltara, Raipur. Some of them are sponge Iron Plant having capacity of 2,70,000 TPA (2x100 TPD
and 2x350 TPD), 85 MW power plant (25 MW Waste Heat Recovery Boilers (WHRB) and 2x30 MW
CFBC & AFBC boilers) and other interrelated units with investment of Rs. 1000 crores. SKSIPL are
committed to be part of Chhattisgarh State for industrialization progress undertaken by the
Government of Chhattisgarh for optimum utilization of natural and human resources available in the
state. The SKS group is establishing a 1200 MW IPP in District Raigarh of Chhattisgarh State with an
investment of Rs. 7000 crores (of which around 3500 cores spent) as well as an integrated Cement
Plant of 3.0 MTPA at District- Bilaspur with an estimated investment of Rs.700 crores.
At the existing integrated steel plant company has proposed to add the following
modification/enhancement with existing SMS project only details are presented in Table 1.
TABEL 1: PRODUCTION/ GENERATION CAPACITY EXPANSION AND CHANGE IN
CONFIGURATION
Existing Production capacity & configuration
Proposed Change/ configuration
Total production capacity& configuration
Remarks
SMS – 3,31,500 TPA 3 x 12T Induction Furnace & 3 x 15T Induction Furnace
SMS – 3,31,500 TPA (No change in approved capacity) 4 x 15T Induction Furnace
SMS – 3,31,500 TPA (Initially approved capacity) 3 x 12T Induction Furnace 7 x 15T Induction Furnace
Four more Induction Furnaces of (15T each) to be installed to achieve approved rated production
Sponge Iron - 2,70,000 TPA 2 x 100 TPD & 350 x 2 TPD Kiln
- Sponge Iron - 2,70,000 TPA 2 x 100 TPD & 350 x 2 TPD Kiln
No change at present
Rolling Mill (4 Nos.) - 3,84,000 TPA
- Rolling Mill (4 Nos.) - 3,84,000 TPA
No change at present
Ferro Alloy – 29,400 TPA
- Ferro Alloy – 29,400 TPA No change at present
Power Plant – Total 85 MW 25 MW WHRB and 2 X 30 MW CFBC & AFBC CPP.
- Power Plant – Total 85 MW 25 MW WHRB and 2 X 30 MW CFBC & AFBC CPP.
No change at present
Gasifire (5 Nos.) 5 x 8000 Nm3/Hr.
- Gasifire (5 Nos.) 5 x 8000 Nm3/Hr
No change at present
Oxygen/Nitrogen Plant – 170 NM3/Hr.
- Oxygen/Nitrogen Plant – 170 NM3/Hr.
No change at present
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 3
2.2 Brief Description of Nature of the Project:
The project already has existing integrated steel plant having the sponge iron plant 2,70,000 TPA (2x100 TPD and 2x350 TPD), 85 MW Captive power plant (25 MW Waste Heat Recovery Boilers (WHRB) and 2x30 MW CFBC & AFBC boilers), Ferro Alloy plant 29,400 TPA, Rolling Mill (4 Nos.) - 3,84,000 TPA, Gasifire (5 Nos.) 5 x 8000 Nm3/Hr, Oxygen/Nitrogen Plant – 170 NM3/Hr and Steel Melting Shop (SMS) having capacity of SMS – 3,31,500 TPA(3 x 12T IF & 3 x 15T IF with investment of Rs. 1500 crores at Siltara, Tehsil Dharsiwa, Raipur, Chhattisgarh.
Now, said proposal is only modification/ enhancement in the existing configuration of furnaces at
existing steel division with additional 4nos x 15T capacity induction furnace with 6/11 CCM without
change in the existing capacity of the issued environmental clearance.
Justification for Modification/Enhancement of SMS Division:
• M/s. SKSIPL going to increase the unachieved capacity of Steel melting shop by adding the 4
Nos. of induction furnace hence all initially approved estimated parameters will be the same.
PRODUCTION IN (MT)
2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15
124485.413 113660.245 92762.146 153408.089 183253.225 159145.11 186874 172607
PERCENTAGE CAPACITY UTILIZATION (3,31,500 TPA)
37.5% 34.2% 27.9% 46.2% 55.2% 48.0% 56.37% 52.06%
• There will be no use of fossil fuels (Coal and Diesel).
• Presently sponge production and ferro alloys are not fully utilized hence company have to sale in
open market. After proposed adding of 4 nos. of IF’s,its internal consumption of sponge will be
increased which results in reduction in outgoing number of vehicles.
• After this arrangement, companies internal consumption will be increased which results in
reduction in outgoing number of vehicles which further result in reduction of fugitive emission on
road
• It is further clarified that the technology of low frequency induction furnaces has improved a lot
and it runs under high efficiency. The electricity consumption is less as compared to old
technology.
Existing Project Details:
The details of existing production profile is mentioned in Table 2
TABEL 2: EXISTING PRODUCT PROFILE
Product Total Quantity Remarks
Sponge Iron - 2,70,000 TPA
EC granted by MoEF dated. August 25,2006 (F.No. J-11011/99/2006 – IA II(I)
Steel Billets production Unit (SMS) -
3,31,500 TPA
Palletization Plant – 3,00,000 TPA
Structural/re-rolled products
3,84,000 TPA
Captive Power Plant (Total 85 MW)
WHRB – 25 MW&2 X 30 MW CFBC & AFBC CPP.
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 4
Product Total Quantity Remarks
Gasifire (5 Nos.) 5 x 8000 Nm3/Hr Consent to establish was obtained vide order no.1689/TS/CECB/2013 dated 01/07/2013. Renewal of Consent was obtained vide order No.307/TS/CECB/2015dtd. 21.04.2015 valid till 31/01/2018
Oxygen/Nitrogen Plant 170 NM3/Hr.
Proposed Project Details:
The company now proposes only modification/enhancement in the existing configuration of furnaces
at existing steel division with additional 4nos x 15T capacity induction furnace with 6/11 CCM without
change in the existing capacity of the issued environmental clearance. The proposed details of
capacity are mentioned in Table 3.
TABEL 3: DETAILS OF MODIFICATION/ENHANCEMENT OF SMS PROJECT
Existing Production capacity & configuration
Proposed Change/ configuration
Total production capacity & configuration
Remarks
SMS – 3,31,500 TPA 3 x 12T Induction Furnace & 3 x 15T Induction Furnace
SMS – 3,31,500 TPA (No change in approved capacity) 4 x 15T Induction Furnace
SMS – 3,31,500 TPA (Initially approved capacity) 3 x 12T Induction Furnace 7 x 15T Induction Furnace
Four more Induction Furnace of (15T each) to be installed to achieve approved rated production
2.3 Need for the project and its importance to the country and/or region:
Steel is one of the most important products of the modern world and is of strategic importance for
any industrial nation. Historically, all nations during their industrialization phase have been
supported by a strong steel industry of their own. From construction, industrial machinery to
consumer products, steel finds a wide variety of applications. It is also an industry with diverse
technologies based on the nature and extent of use of raw materials.
India is the 4th largest producer of steel in the world accounting for production of 81.54 million tons
of crude steel in 2013-14. It also holds the third position in consumption of steel. Thus there is
great potential of steel industry in India.
Four more Induction Furnaces of (15T each) to be installed to achieve approved rated production
i.e. 3,31,500 TPA also in order to meet the in-house demand of raw material for MS rounds and
CTD bars and to meet the market requirement in timely manner, the proposed project is
undertaken.
Advantages of the project
- Improved productivity of the existing process. - Reduced operation cost due to sharing of infrastructures and manpower with existing unit
reducing overhead by almost 30% - Since the materials handling will be similar to existing operation, synergy of activities will bring
economies to the unit. - Dedicated and experienced workforce is available. - Ready market for the supply of finished products. Easy accessibility to the thriving markets of
Chhattisgarh, Madhya Pradesh, Bihar, UP and Odisha form another major locational advantage factor.
- Technology has already been successfully tried in existing plant.
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 5
2.4 Demand-Supply Gap
Steel production of India accounted for 14.33 million tons in 1990-91, which gradually increased to
36.12 million tons in 2003-04. Rapid rise in production has resulted in India becoming the 3 rd largest
producer of crude steel in 2015 and the country continues to be the largest producer of sponge iron
or DRI in the world. As per the report of the Working Group on Steel for the 12th Five Year Plan,
there exist many factors which carry the potential of raising the per capita steel consumption in the
country. These include among others, an estimated infrastructure investment of nearly a trillion
dollars, a projected growth of manufacturing from current 8% to 11-12%, increase in urban population
to 600 million by 2030 from the current level of 400 million, emergence of the rural market for steel
currently consuming around 10 kg per annum. At the time of its release, the National Steel Policy
2005 had envisaged steel production to reach 110 million tonnes (mt) by 2019-20. However, based
on the assessment of the current ongoing projects, both in greenfield and brownfield, the Working
Group on Steel for the 12th Five Year Plan has projected that domestic crude steel capacity in the
country is likely to be 140 MT by 2016-17 and has the potential to reach 149 MT if all requirements
are adequately met. The National Steel Policy 2005 is currently being reviewed keeping in mind the
rapid developments in the domestic steel industry (both on the supply and demand sides) as well as
the stable growth of the Indian economy since the release of the Policy in 2005.India is expected to
become the world's second largest producer of crude steel in the next 10 years, moving up from the
third position, as its capacity is projected to increase to about 300 MT by 2025. Huge scope for
growth is offered by India’s comparatively low per capita steel consumption and the expected rise in
consumption due to increased infrastructure construction and the thriving automobile and railways
sectors.
The National Steel Policy 2005 is currently being reviewed keeping in mind the rapid developments in
the domestic steel industry (both on the supply and demand sides) as well as the stable growth of the
Indian economy since the release of the Policy in 2005.
2.5 Imports vs. Indigenous production
The Indian infrastructure sector is likely see a massive growth due to increasing economic status thus
in order to keep the supply ready to match the demand of construction steel in India and to achieve
the rated production by modification/enhancement of SMS becomes important for M/s. SKS Ispat and
Power Ltd.
2.6 Export possibility
Export of Steel is always possible, the Government of India is also encouraging export of steel,
however proposed quantity will be domestically consumed. The world steel market is for about 1500
Million Tonnes, out of which about 50% is being produced by China, the global demand even if
increased by 2% per annum then it requires addition of 30 Million Tonnes additional production
capacity. Since China has already reach to saturation level of increasing the production therefore
India has better chance to share the world market by increasing its production in an energy efficient
manner. The unit being located in the eastern sector can export the steel to Bangladesh; Bhutan; and
Burma and Nepal also.
2.7 Domestic/ Export Markets
Domestic market with real estate, infrastructure projects, industrial projects are available for purchase
of steel which is estimated to be around 80 million tonnes per annum. The estimated growth in
infrastructure is likely to increase the demand of steel to more than 150 million tonnes by the year
2025. In view of this, it is required to make advance planning for creating the facility and infrastructure
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 6
to meet this demand. The domestic market as well as export market both will require good quality
steel, produced with minimum energy consumption and minimum cost of production.
The project has potential to cater to the domestic demand as well as export demand of steel to
domestic as well as export oriented steel plants.
2.8 Employment Generation (Direct and Indirect) due to the project:
The total employment generated by the existing integrated steel plant is about 1000 employees.
However, the existing and likely proposed employment generation in SMS division due to project is
given in Table 4.
TABLE 4: EMPLOYMENT GENERATION
Particulars Existing Proposed
Admin Staff : 08 05
Production staff : 114 65
Sub-Total : 122 70
Total : 192 Nos.
3.0 PROJECT DESCRIPTIONS
3.1 Type of project
SKS Ispat & Power Limited, was granted Environment Clearance vide letter no. J-11011/99/2006-IA.II(I) dated 25.08.2006 and presently operating various facilities in their existing integrated steel plant with an investment of around Rs.1000 Crores in Siltara, Raipur. The company now proposes only modification/enhancement in the existing configuration of furnaces at existing steel division with additional 4nos x 15T capacity induction furnace with 6/11 CCM without change in the existing capacity (3,31,000 TPA) of the issued environmental clearance. As the existing induction furnaces are not running efficiently (as per the present designed capacity). Thus, to achieve the rated production M/s. SKSIPL have to make addition of IF’s without change in total capacity of existing steel division. The proposed addition of IF’s will be established in the existing plant premises only no additional land required outside the plant side. Project falls under Category A (secondary metallurgical processing) Item 3(a) of the schedule of EIA notification of Sept 14, 2006 issued by MOEF & CC. 3.2 Location
Details about the Project area are presented in Table 5.
TABLE 5: DETAILS ABOUT THE PROJECT AREA
State Chhattisgarh
District/ Tehsil Tehsil- Dharsiwa, District- Raipur
Village Siltara
Khasara No. Private Industrial Land: Khasra No. 102/1-9
Area 225 Acres
Toposheet No. 64G/11
Geo-coordinates Latitude : 21023’29”N
Longitude : 81°38’46”E
The index map and location is presented in Annexure-I, Location map showing 10 km radius of study
area shown in Annexure-II
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 7
Annexure – I
INDEX MAP
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 8
Annexure – II
STUDY ARA MAP
(10 KM RADIAL DISTANCE FROM THE PROJECT SITE)
3.3 Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted.
Proposed modification/enhancement of SMS will be within the existing plant premises; hence,
alternative sites are not examined.
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 9
3.4 Size or Magnitude of Project
The existing and proposed production capacity with details regarding configuration are presented in
Table 6
TABLE 6: PROPOSED MODIFICATION/ENHANCEMENT OF SMS PROJECT
Existing Production capacity & configuration
Proposed Change/ configuration
Total production capacity & configuration after expansion
Remarks
SMS – 3,31,500 TPA 3 x 12T Induction Furnace & 3 x 15T Induction Furnace
SMS – 3,31,500 TPA (No change in approved capacity) 4 x 15T Induction Furnace
SMS – 3,31,500 TPA (Initially approved capacity) 3 x 12T Induction Furnace 7 x 15T Induction Furnace
Four more Induction Furnaces of (15T each) to be installed to achieve approved rated production
3.5 Project description with process details:
Induction Furnaces (proposed 4 x 15 Ton Induction Furnaces)
M/s. SKS Ispat and Power Limited is having following in the steel melting shop:
The various types of Induction Furnaces used for Steel making are medium frequency and high
frequency. Mild steel, Stainless Steel and low and high alloy Steel can be made from these furnaces.
Raw materials used are Steel melting Scrap and Direct Reduced Iron. Alloying elements added as
per requirement
Manufacturing Process
The induction furnace continuous casting route is adopted for steel melting. The induction furnace -
continuous casting route is proposed to be adopted for additional steel melting.
DRI from the DR plant will be conveyed to the overhead storage bins, which shall be located in the
melt shop. DRI will be discharged onto traveling vibratory feeders for charging into the furnaces.
Plant return scraps from various generating points and purchased scrap is transported to the scrap
bay of steel melting shop. One crane is provided in the scrap bay for unloading and loading of scrap
and pig iron in scrap buckets. These are transported to the furnace bay by electrically driven scrap
bucket transfer car. The scrap buckets are weighed in the scrap bay. Scrap is stored on furnace
working platform near the furnace for charging.
The scrap is charged into the crucibles for generating the hot heel for DRI charging. Necessary
carbon in the form of pig iron/ petroleum coke is added into the crucibles to ensure the availability of
necessary carbon in the bath. Once the molten bath has been formed and minimum temperature of
the bath has been achieved, sponge iron is charged in small batches and the slag formed is removed
periodically. After the completion of charging of sponge iron, a sample is drawn to determine the
composition of the bath. After achieving the desired melt analysis, the temperature is raised to the
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 10
tapping temperature taking into account additions of predetermined amount of ferroalloys to achieve
the required tapping composition of the melt.
Continuous Casting
The continuous casting technology has gained worldwide acceptance because of high yield,
economics of operation and better product quality. Hence this technology is chosen for our steel
plant casting the liquid steel into billets. The existing continuous caster will be utilized for producing
steel billets, which is equipped with moulds, mould oscillating mechanism, secondary cooling
segments, withdrawals and straightening unit, gas cutting unit, dummy bar insertion system, run out
roller tables, cross transfer mechanism and cooling bed. The caster is controlled from the pendant
control panels and also from main control room located on the casting platform and the auxiliary
control room near the gas-cutting unit. The tap-to-tap time of the induction furnaces is matched with
the casting cycle time so as to have maximum number of sequential cast.
Ladle
The ladle is picked up by ladle handling crane and placed on the ladle stand. A refractory lined
Tundish, fully dried and fitted with preheated nozzles mounted on Tundish car is moved from the
reserve position to the casting posit
Pictorial View of Billets formation Pictorial View of Ladle
Prior to the start of the casting operation, the dummy bars will be introduced into the mould. The gap between the dummy bar and mould walls is sealed with asbestos cords and small pieces of steel scraps are placed over the dummy bar head for chilling of initial metal. Water supply to mould, secondary cooling zone and machine cooling is switched on at this stage. When the liquid steel level in the Tundish reaches a predetermined level, the tundish nozzles are opened. When the metal level in the mould reaches about 100-150 mm from its top the drive of the mould oscillating mechanism as well as withdrawal and straitening unit is switched on. The withdrawal of dummy bar begins at the minimum speed and gradually increased to normal speed within few minutes. The mould is lubricated with liquid lubricant. During casting operation the metal level in the mould is maintained within predetermined limits by adjusting flow of metal into the mould or by adjusting the withdrawal speed.
The liquid metal level in Tundish is also kept within permissible range by adjusting theopening of ladle slide gate. The partially solidified billets after leaving the mould pass through strand guide roller segment where intensive but controlled cooling of billets is affected by water spray nozzles. The
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 11
solidified billets are guided through withdrawal and straightening units before entering the gas cutting zone. The dummy bar is separated from the billet for the gas cutting unit and is stored till its introduction is required for the next hit. The cast billet is cut to predetermine length by gas cutting torches. The size billets are delivered to the cooling bed through run out roller table and cross transfer mechanism. The billets are marked on cooling bed by the marking unit for identification/tracking.
ASSUMPTIONS
Some of the important assumptions relating to the production of billet is as under: No. of Working days 320 Days Furnace Capacity
No. of Furnace -4 Nos.
Capacity per Charges -15 MT
Total heats per day -10 nos.
Total capacity -600 tons per day
(140 minutes per heat)
Capacity Utilization
1st year of operation - 80 %
From 2nd year and ahead - 90 to 100 %
For uninterrupted operation of the plant the raw material to be kept in the raw material yard is as
given under, these holdings period is suggested taking into account the availability, transit period and
any unforeseen interruptions in the supply channel.
Sponge iron - 2 Months
Pig Iron - 2 Months
Scrap - 2 Months
Ferro Alloys - 2 Months
Work in Progress - 15 Days
Finished Outputs - 22 Days
Stores and Spares - 3 Months
The above holding periods have been specified taking into account the activity in stand alone basis.
RAW MATERIAL SPECIFICATIONS
Sponge Iron - + 3 to – 20 mm\
Pig Iron - + 100 to - 150 mm
Scrap - + 20 mm to – 150 mm
Ferro Alloys - +20 to – 70 mm
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 12
CONTINUOUS CASTING M/C
Continuous casting is the process to solidify molten steel into a semi finished billet, bloom, or slab for
subsequent rolling. Prior to the introduction of the continuous casting in 1950s, steel was poured into
stationary molds to form ingots. But continuous casting has substantially added to improved yield,
quality, productivity and cost efficiency.
Steel from the electric arc furnace is tapped into a ladle and taken to the continuous casting machine.
The ladle is raised onto a turret that rotates the ladle into the casting position above the tundish.
Liquid steel flows out of the ladle into the tundish and then into water-cooled copper mold.
Solidification begins in the mold, and continues through the first zone and strand guide. In this
configuration, the strand is straightened, torch-cut and then discharged for intermediate storage or
hot charged for finished rolling. The melting /casting/ rolling processes are linked while casting a
shape that substantially conforms to the finished product. The complete chain from liquid metal to
finished rolling can be achieved within two hours.
The Product end-use dictates the quality, grade and shape of the cast product (billet, bloom, slab,
beam blank, and/or round).
To start a cast, the mold bottom is sealed with a dummy bar head attached to dummy bar. The
dummy bar is held in place hydraulically by Straightener Withdrawal units. This head prevents
liquid steel from flowing out of the mold. The steel poured into the mold is partially solidified,
producing a steel strand with a solid outer shell and a liquid core. In this primary cooling area, once
the steel shell has sufficient thickness, about 10–20 mm, the staightener withdrawal units are started.
The moving dummy bar starts to withdraw the partially solidified strand out of the mold along with the
dummy bar.
Liquid steel continues to pour into mold to replenish the withdrawn steel at an equal rate. The
withdrawal rate depends upon the cross-section, grade and quality of steel being produced, and may
vary widely depending upon section, quality and machine design parameters
Casting times are typically matched with the EAF tap-to-tap time. Upon exiting the mold, the strand
enters a roller containment section and secondary cooling chamber in which the solidifying strand is
sprayed with water to promote solidification. This area preserves cast shape integrity and product
quality. Larger cross-sections require extended roller containment. Once the strand is fully solidified
and passed through the staightener withdrawal units, the dummy bar is disconnected, removed and
stored. Following the Straightener, the strand is cut into individual pieces of required length and
discharged for further processing by rolling.
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 13
Main Features:
Production capacity - 300,000 tons/year
Remains same (Existing Capacity)
Days of liquid steel supply/year - 320
Grades of steel to cost - Low, Medium, and high carbon steels
Heat size - 15 t
Source of liquid metal - 15 t Induction Furnace
Type of ladle - Bottom pouring with slide gate system and
porous plug
Billet size - 140x140,150x150 and 125 x 125 mm.
Billet quality -- Internationally acceptable for size surface
Quality, mechanical and metallurgical
Properties
MACHINE PARAMETERS
Type of machine - 2/3 strand, curved mould, bow type
Machine Radius - 6 / 11 m billet.
Method of ladle placement - Rotating turret with independent lifting and
lowering if the arms along with facilities for
Weighment
Strand cooling - air / mist
EMS - to be provided
Tundish - of adequate size capacity to facilitate
Sequence casting & inclusion removal
Mould level control - to be provided with the mould
Billet cutting - to be provided along with auto operation
Method of discharge - on horizontal discharge roller table
Dummy bar - flexible / rigid with replaceable heads for
different sizes
Casting speed - variable for various grades
Mould oscillation - short lever arm, variable frequency and
variable stroke of oscillation. The frequency of
oscillation to be coupled with the casting
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 14
speed to maintain a constant negative strip
time
Tundish car - With lift lower and centering device
Withdrawal system - hydraulically pressurized withdrawal machine
with Individual driven rolls for maintaining
straightness of the cast strand while casting
Drive - DC or VVVF Drives for withdrawal
straightener, Mould oscillation with perfect
synchronization between withdrawal
straightener & oscillation
Figure 1 Process Flow Chart
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 15
Source of water:
Raw water requirement is been met from the Kharun river for which WRD department Govt. of CG
has allotted 1.8 MCM (4800 KLD) of water. The Kharun river is at a distance of about 4 km from the
existing plant location. Anicut has been constructed on the river and an intake well along with the
pump house is constructed by SKSIPL at downstream of the Anicut and about 4 km long cross-
country piping system for transportation of river water. The river water is stored at 2 nos. of common
reservoir within the station boundary.
3.6 Raw materials required along with estimated quantity, likely source, marketing area of
final product/s, Mode of transport of raw Materials and Finished Products.
Estimated raw materials quantity likely to be sourced from outside, mode of transportation is given in
Table 7.
TABLE 7: ESTIMATED RAW MATERIAL CONSUMPTION
Sl. Description Quantity (MTPA) Source
1 Sponge Iron 323213 From Captive generation/Open market.
2 Pig Iron 51343 Open Market
3 Scrap 18218 Open Market
4 Ferro Alloys 3643 Captive Generation
Total= 3,96,417
Note: 1. Existing requirement of Raw materials as we are not increasing the existing approved Capacity. 2. All Types of Raw materials are being transported through Road by covered truck and final product will be charged directly to the Existing Rolling Mills
TABLE 8: MATERIAL BALANCE
STEEL MELTING SHOP (Capacity- 3, 31,500 TPA)
MATERIAL BALANCE (T/T OF PRODUCT) – BILLET PRODUCTION
(A) INPUT (B) OUTPUT
Sponge Iron 0.975 Total liquid metal 1.043
Pig Iron 0.155 Slag 0.131
Scrap 0.055 Total 1.174
Ferro Alloys 0.011 (C) LOSSES
Total 1.196 Burning losses (A-B) 1.196-1.174=0.022
(D) MATERIAL BALANCE D=A-(B+C) = 1.196- (1.174+0.022)=0
3.7 Resource optimization/ recycling and reuse envisaged in the project, if any, should be
briefly outlined.
During the process, marginal water will be used and will be recovered and recycled for process use; hence no waste water generation are envisaged.
The effluent generated from the operation is utilized for water sprinkling on roads & yards.
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 16
The source of domestic wastewater is only from the office toilets of the plant are being completely disposed off into the soak pit via septic tank. Soak pit overflows used in horticulture
activities.
3.8 Availability of water, its source, Energy/ Power requirement and source:
Availability of water and its source:
Raw water requirement is met from the Kharun River for which WRD, Govt. of CG has allotted 1.8
MCM of water. The Kharun river is at a distance of about 4 km from the existing plant location. Anicut
has been constructed on the river and an intake well along with the pump house is constructed by
SKSIPL at downstream of the Anicut and about 4 km long cross- country piping system for
transportation of River water. The river water is stored at 2 nos. of common reservoir within the
station boundary. No water will be abstracted from groundwater and no further water is required for
the project
Energy/ Power requirement and source:
The electric power requirement for the project will be fulfilled from captive power plant. The detail of
captive Power plants are as follows (Table 9):
TABLE 9: ENERGY/POWER REQUIREMENT AND SOURCE
Sr. No. Existing capacity of CPP
1. AFBC– 30 MW
2. CFBC – 30
3. WHRB -25
Total = 85 MW
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
Management/disposal:
Slag generated is being crushed for metal recovery and dust generated is used for area
development as filling material. As there is no additional capacity increase than already approved
capacity, the waste disposals would be within norms.
100% of wastewater will be recycled and Zero discharge condition will be maintained.
100% Mill scale is used for captive consumption in SMS Plant as raw material.
Miss-Roll and End Cuts 100% are used in captive consumption in Steel Melting Shop as raw
materials.
The fly ash generated shall be utilized in our own Fly Ash Bricks Plant and remaining if any, shall
be supplied to other Bricks manufacturing Units and Cement Plant.
The liquid steel produced will be used in a manner to produce hot billet suitable for Re Rolling,
thus online hot Re Rolling practice will be adopted.
Mill scale generated in the Rolling mill will be100% used in SMS plant.
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 17
TABLE 10: QUANTITY OF WASTES TO BE GENERATED
Description Quantity of Waste generated Method of Collection Method of Disposal
Billet Scale (Existing) (5.17 TPD) 0.5 % OF PRODUCTION
Manual Used In Furnaces
Billet Scale (Proposed) (4.14 TPD) 0.4 % OF PRODUCTION
Manual Used In Furnaces
Slag (Existing)
186 TPD (18 % OF TOTAL CHARGE MIX) At full capacity
Manual Slag Crush/Metal Recycle
Slag (Proposed) Manual Slag Crush/Metal Recycle
3.10 Schematic representations of the feasibility drawing which give information of EIA
purpose.
S. No. Particulars Impacts Remediation Proposed
1. Change in
land use.
Permanent change in land use
related to:
Installation of machineries
Plantation in and around the plant
Recharge potential development
The project is already an Industrial
area and the proposed expansion
will be within plant premises, devoid
of vegetative tree cover and having
only the grass cover. Part of the
land will be covered by tree
plantation to the extent of 33% of
area being brought under industrial
activity. The greenery will be taken
up within the plant boundary and
additionally outside the plant
boundary.
Water will be sourced from River
Kharun, no groundwater will be
abstracted for the project activities
hence, natural recharge of
groundwater level will not be
affected through proposed project
activities.
2. Transportation
of material
The existing network of
transport gets reduced (+ve
impact)
• Presently sponge production and ferro alloys are not fully utilized hence company have to sale in open market. After proposed adding of 4 nos. of IFs its internal consumption of sponge will be increased which results in reduction in outgoing number of vehicles.
• After this arrangement companies internal consumption will be increased which results in reduction in outgoing number of vehicles which further result in reduction of fugitive emission on road
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 18
S. No. Particulars Impacts Remediation Proposed
3. Gaseous and
Particulate
Emission to
The atmosphere
Air quality All necessary steps will be followed to
minimize the emission from point
sources as well as line sources. Thus
the standards of Stack Emission and
Ambient Air quality will be maintained
as per prescribed limits.
4. Discharge of
effluent
Impact of water quality. Zero discharge is already being
implemented at existing ISP and in will
be continued further.
5. Withdrawal of
ground /
surface water
Availability of ground/surface
water is affected.
Water will be sourced from River
Kharun, no groundwater will be
abstracted for the project activities
hence, natural recharge of ground
water level is not affected through
project activities. Permission
regarding drawl of river water is
granted from water resource
department.
6. Operation of
equipment
and vehicles
likely to
generate
noise.
Impact on human health due
to excess noise level beyond
permissible level.
All the process equipment will be
installed on anti-vibration pad with
sufficient provisions to minimize
generation of noise. The high noise
generating equipment like turbine and
generator will be enclosed with noise
suppressing enclosures.
The buildings as well as boundary wall
and green belt will ensure the
attenuation of noise outside the
boundary within the prescribed limits.
7. Fire Hazard
due to storage
of fuel etc.
Risk to the surrounding
habitation.
Necessary precautions to prevent fire
and all the provisions to control fire
shall be provided.
8. Employment
to outsiders
Socio-economic disparity with
local community
Priority of employment will be given to
local people, as already sufficient
qualified and trained local youth are
available.
9. Cultural impact Local population feels isolated The promoters proposed to employ
local masses in the project, hence no
such impact on cultural diversity is
likely to take place.
10. Disposal of solid
and hazardous
wastes
Create odorous problem,
nuisance condition related to
the disposal of solid wastes.
Deterioration of soil,
productivity pollution in ground
water/surface water due to
leaching and surface runoff.
Domestic wastes will be segregated
for organics and Inorganics. Organic
wastes will be used for composting
and inorganics for approved vendors.
Disposal of hazardous wastes will be
done as per hazardous wastes
handling and disposal rule.
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 19
4.0 SITE ANALYSIS
4.1 Connectivity.
The proposed project is situated at Siltara village, Tehsil Dharsiva, Raipur district of Chhattisgarh
state. The site is well connected with Road/Rail. The existing road network will be used for
transportation activities. The details are as follows:
Nearest Road: Raipur-Bilaspur-Kolkata Highway (NH-200)about 1.89 km, E
Nearest railway station- Mandhar, 08 km (Railway Station) (SE) & Raipur, 12 km (E)
Nearest airport- Raipur 24.28 Km, SE
4.2 Land Form, Land use and Land ownership.
The proposed activities will be within the existing integrated steel complex. SKSIPL is already having
existing 225 Acres (91.05 Ha.) of land at village Siltara at Raipur District. The proposed land identified
for the modification/enhancement of SMS will be 02 acres (0.809 ha) within existing plant premises. It
is Private Land already developed for industrial activities.
4.3 Topography (along with map)
The project area located at Siltara village in Raipur District of Chhattisgarh state. General topography
of the region was observed to be flat with low undulating plain and the plant site having gentle slope
toward West. Dominant features of the land are being the lateritic, sandy loamy plain and broad
alluvial plain of River Kharun. The project located at 21023’29”North Latitude and 81°38’46”East
longitude on the Topo sheet No. 64, G/11. The site specific Topography map is given in Figure 2.
FIGURE 2: SNAPSHOT OF GOOGLE SATELLITE IMAGERY SHOWING FLAT TOPOGRAPHY
Geology
The project area falls in Raipur District. It mainly covers the rocks of Chandi Formation, Raipur Group
of Chhattisgarh Super Group.
Raipur Formation: It is represented by Chandi Formation of Raipur group which is part of
Chhattisgarh Super group of Meso to Neoproterozoic age. Lithological it comprises of limestone and
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 20
dolomite: reddish brown, fine to medium grained, hard and compact. Clay pockets are also observed
in area which are Green to olive green, soft to moderately hard, occurs as pockets and lenses and
patches of chert of green, buff, red, massive and compact rock are observed in area.
HYDROGEOLOGY
The study area comes under Mahandi River Basin. The principal Aquifer system within study area is
Sedimentary rocks. The Pre- monsoon ground water level observed within the study area is 3-5m
while the post monsoon water level observed in the area is 2-3m. Water table contour observed in the
study area is from 250m amsl. As per CGWB, 2013 data the study area falls in safe category of
groundwater development with observed groundwater development of 64%. However, No Ground
water will be utilized for project related activity. The yield of aquifer observed within the area is 1-8
lps. Dendritic type of drainage pattern is observed in study area which follows the regional slope.
4.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies
(distance from HFL to the river), CRZ. In case of notified industrial area, a copy of Gazette
Notification should be given:-
Existing land use is a private industrial land. The land is being used for Industrial Purpose.
5.0 PLANNING BRIEF
5.1 Planning concept (type of industries, facilities transportation Town and Country
Planning Development authority Classification.
Project concept:
Steel Melting Shop (SMS): Sponge iron, ferro alloys, pig iron and imported stainless steel scrap are
being charged from the top of Induction Furnace. Arcing melt the contents. Oxygen blowing is done.
Steel is tapped and chemistry correction is done in ladel refining furnace. Liquid steel is casted into
billets in continuous casting machine. Slag is taken out from slag tap hole.
Town and Country Planning Development authority Classification:
The project falls within Siltara village near to Siltara Industrial Area surrounded by a various
Industries. Town and country planning department has already classified land as industrial. Adequate
road facilities are already developed and available for transportation of raw materials as well as
finished products.
5.2 Population Projection.
The existing industry is providing employment to about 1000 people including 192 people for SMS division. During construction phase, about 60 workmen i.e labors and workers will be hired from nearby villages. After modification/enhancement in SMS division (operation phase) total workforce will be around 70. Since the plant is located in the Raipur district in which trained manpower are already available therefore the employment will be mostly given to local people therefore there will not be any substantial increase in the population of local villages. However, due to increase economic growth, the local youth will be benefited and employment. 5.3 Land use planning (breakup along with green belt etc.).
The proposed activities will be within the existing integrated steel complex. SKSIPL is already having
existing 225 Acres (91.05 Ha.) of land at village Siltara at Raipur District. The land for the
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 21
modification/enhancement of SMS will be 02 acres (0.809 ha) within existing plant premises. It is a
private land already developed for industrial activities. The plantation details within the plant premises
in given in Table 11.The breakup of the land for the various activities is presented in Table 12.The
layout map showing proposed project site is depicted in Figure. 3.
TABLE 11-PLANTATION DETAILS
1 Total area of Plant 91.05 Hec (225 Acres)
2 Area reserved for plantation 33% of the total plant area
3 Total no of plants planted 80,000
4 Total alive plant 52,000
5 Survival rate 65%
6 Places at plantation done Inside the plant premises, labour colony,Bacholers Hostel,Bana Village,nearby villages,approch road from Bilaspur-Raipur road to SKS plant etc.
7 Types of Plant Neam, Chatim, Gulmohar, Peltophorum, Karanj, Teak
etc.Including ornamental plants at gardens/lawns.
TABLE 12: LAND BREAKUP
Sl. No. Details Area (In Acres.) Area (In Ha.)
1 Sponge Iron Plant 5.56 2.25
2 WHRB CPP 3.5 1.41
3 Billet Production unit 3.2 1.29
4 Rolling Mill 6.2 2.50
5 Coal based Power Plant 5.5 2.22
6 Ferro Alloys 3.2 1.29
7 Oxygen Plant 2.6 1.05
Central QC Lab 3.2 1.29
Fly Ash Bricks Plant 1.0 0.404
8 Automobile 3.2 1.29
8 Roads 12.56 5.08
9 Other Buildings (Canteen,ADM etc.) 8.42 3.40
10 Reserved for Green Belt 74.25 30.04
11 Water Reservoir 18.5 7.48
12 Raw Material Storage Yards 10.3 4.16
13 Dispatch Yard 8.5 3.43
14 Slag Crusher 2.5 1.01
15 Residential Area 9.5 3.84
16 Reservoir for Rain water Harvesting 9.5 3.84
17 Temples 3.3 1.33
Truck & Other Parking 8.5 3.43
18 Hazardous Waste storage area 1.5 0.60
18 Vacant Land 20.52 8.30
Total 225 91.05
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 22
FIGURE 3: LAYOUT OF EXISTING INTIGRATED STEEL PLANT OF M/s. SKSIPL SHOWING
PROPOSED SITE WITHIN EXISTING PREMISES
Proposed site for installation of 4 nos. of
IF’s having capacity of 15T each
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 23
5.4 Assessment of Infrastructure Demand:
No substantial additional infrastructure is required for the proposed activities. The available road
network and natural sources of water supply and drainage system are adequate. However in order to
have smooth transport of men and materials the existing approach road of existing steel complex will
be extended to proposed project within plant premises. Water will be sourced from river Kharun.
There is no other major infrastructural requirement for the project.
9.1 Amenities/Facilities:
The project modification/enhancement of SMS division does not require additional large amenities or
facilities. As it already has necessary arrangement for the project for meeting water supply for
drinking purposes, toilet facilities for workers as well as inward/outward transport operators, parking
facilities, as well as canteen for workers and guests. The septic tank has been built for disposal of
domestic effluent generated. A canteen with rest room is also available for the supply of tea; snacks;
food to the workers, drivers and visitors etc. Sufficient parking space is already created for the
parking of trucks, cars, etc.
6.0 PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
About 0.809 Ha land will be used for the construction of induction furnaces for SMS division out of the
total 91.05 Ha. The proposed site is well connected with concrete road; remaining area will be used
for open space and green belt development, parking bay, etc. as given in land use statement.
6.2 Residential Area (Non Processing Area)
There is no residential area proposed in the plant area; as the existing villages have adequate
facilities to accommodate the additional manpower residential requirements. Most of the local people
will only be employed so the need of the additional residential colony in the plant is not required.
6.3 Green Belt
Greenbelt in an around 30.04 Ha. (33%) is already developed, having local species with broad leaves
and higher canopy. The ever green as well as native plants species will be selected for the purposed
of green belt. The existing plantation is around 52, 000 within plant premises of M/s. SKSIPL.
6.4 Social Infrastructure:
The project area lies within the district of Raipur. There is no requirement to build any social
infrastructure within the plant area, however, a small temple already exists and the infrastructure for
amenities to the workers such as kitchen, canteen, rest room etc. is already provided which will be
further augmented with the expansion of the project.
6.5 Connectivity (Traffic and Transportation Road, Rail/Metro/Waterways etc.).
The proposed project is situated at Siltara village, Tehsil Dharsiva, Raipur district of Chhattisgarh
state. The site is well connected with Road/Rail. The existing road network will be used for
transportation activities. The details are as follows:
Nearest Road: Raipur-Bilaspur-Kolkata Highway (NH-200)about 1.89 km, E
Nearest railway station- Mandhar, 08 km (Railway Station) (SE) & Raipur, 12 km (E)
Nearest airport- Raipur 24.28 Km, SE
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 24
6.6 Drinking Water Management (Source & Supply of water)
There will be no additional water requirement for proposed modification/enhancement of SMS
division. The water requirement will be fulfilled through existing available water. SKSIPL has already
obtained consent for drawl of water through Kharun river (1.08 MCM) from water Resources
Department, Govt. of Chhattisgarh, vide letter No. 5425/315/JS/TS/AJP/03-D-4 dated 06/11/2004. No
groundwater will be abstracted.
6.7 Sewerage system
Infra-structural services including water supply, sewage, drainage facilities and electrification will be
made. The existing toilet facilities will be available to the workers to allow proper standards of
hygiene. These facilities are connected to a septic tank and soak pits. Waste water drainage system
of the plant is well connected to the sewerage channel facilities to ensure minimum impact on the
environment.
6.8 Industrial Waste/ Solid Waste Management.
100% of Industrial Solid waste will be used in the following manner:
6.9 Solid Waste Management
Slag as generated is crushed for metal recovery and dust generated is used for area development as filling material .As there is no addition capacity, the waste disposals would be within norms.
Thick green belt will be developed all around the periphery of the plant and vacant places within
the premises so as to reduce the pollution load and improve the aesthetics of the area.
TABLE 13: DISPOSAL OF SOLID WASTE
Description Quantity of Waste generated Method of Collection Method of Disposal
Billet Scale (Existing) (5.17 TPD) 0.5 % OF PRODUCTION
Manual Used In Furnaces
Billet Scale (Proposed) (4.14 TPD) 0.4 % OF PRODUCTION
Manual Used In Furnaces
Slag (Existing)
186 TPD (18 % OF TOTAL CHARGE MIX) At full capacity
Manual Slag Crush/Metal Recycle
Slag (Proposed) Manual Slag Crush/Metal Recycle
6.10 Power Requirement & Supply/source.
The electric power requirement for the project will be fulfilled from 85MW Captive Power plant.
7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN
7.1 Policy to be adopted (Central/ State) in respect of the project affected persons
including home oustees, land oustees and landless laborers (a brief outline to be
given):
The proposed project does not have any directly displaced persons, due to acquisition of land. There
are also no land oustees or project affected persons or home oustees, thus R&R plan is not
applicable here. However, the priority for employment will be given to local persons living in the
adjoining villages. In addition to this, promoter will also contribute for the welfare of the people of local
surrounding.
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 25
7.1.1 Details of Corporate Social Responsibility by M/s. SKS Ispat and Power Ltd.
The company is actively involved in CSR activities for the welfare of the surrounding areas and
budgetary provision is made every year. In 2013-14, company has spent Rs. 19,04,058 for different
activities as a part of CSR activities. For the year 2014-15 company had spent Rs. 24,01,584 for
different CSR activities and for the year 2015-16 company has made the provision of Rs. 8,36,052
has been made available by the company Table 14-16.
TABLE 14: CSR ACTIVITIES DURING THE YEAR 2013-14
Sr. No. Particulars Cost (In Rs.)
1 Beatification and cleaning of village pond, disposal of solid waste generated from plant, construction/repairing of pond bank and chabutraghat, etc. at Gram Parastari.
5,00,000
2 Expenditure for religions programme at village murathi,Charoda, Dharsiwa and Siltatara
33,401
3 Expenses under Chief Minister KanyadanYojana 1,00,000
4 Cooperation fund towards the Times of India Corporate Cricket 25,000
5 Expenses towards environment conservation 8,21,965
6 Expenses towards distribution of Medicine and providing medical facilities, organizing Health check-up camps in nearby villages surrounding the plant area.
4,23,692
Total 19,04,058
TABLE 15: CSR ACTIVITIES DURING THE YEAR 2014-15
Sr. No. Particulars Cost (In Rs.)
1 Organizing free Health check-up camps at village Parastari 500,00
2 Organizing Eye check-up camps at village Murraithi 40,000
3 Expenses under Chief Minister Kanyadan Yojana 1,00,000
4 Plantation/Greenbelt and beautification along SKS approach road, approach road of industrial area and nearby villages.
1,00,000
5 Expenditure towards religious programme at village murathi,Charoda, Dharsiwa and Siltatara
1,00,000
6 Expenses towards environment conservation 6,55,556
7. Expenses towards distribution of Medicine and providing medical facilities, organizing Health check-up camps in surrounding industrial area and nearby villages.
13,56,028
Total 24,01,584
TABLE 16: CSR ACTIVITIES DURING THE YEAR 2015-16
Sr. No. Particulars Cost (In Rs.)
1 Provision made towards organizing various activities 1,00,000
2 Plantation/Greenbelt and beautification along approach road of SKS and industrial area and nearby villages.
1,00,000
3 Expenditure towards religious programme at village 1,00,000
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 26
Sr. No. Particulars Cost (In Rs.)
muraithi,Charoda, Dharsiwa and Siltatara
4 Provision towards environment conservation 4,36,052
5 Provision towards distribution of Medicine and providing medical facilities, organizing Health check-up camps in surrounding industrial area and nearby villages.
1,00,000
Total 8,36,052
8.0 PROJECT SCHEDULE & COST ESTIMATES
8.1 Likely date of start of construction and likely date of completion:
SCHEDULE FOR APPROVAL AND IMPLEMENTATION
Proposed Project
Activities at the site will be carried out after grant of Environmental clearance from Ministry of
Environment & Forests and Consent to establish from Chhattisgarh Environment Conservation Board
(CECB). The schedule for implementing the proposed project is given in Table 17.
TABLE 17: PROJECT IMPLEMENTATION SCHEDULE
Particulars Implementation Date/Time Period
Start of Construction After Receipt of Environmental Clearance &
Permission of Establishment.
Construction Period
Installation of additional of Induction Furnaces at
SMS,
03 Months
Commercial Production Period
Commercial Production will be started After 03 Months
8.2 Estimated project cost along with analysis in terms of economic viability of the project.
The estimated project cost will be Rs. 25.00 crores for installation and operation. The project is
economically viable
TABLE 18: PROJECT COST
Existing Project Cost (Rs. In Crores)
Proposed expansion cost (Rs. In Crores)
Total Cost (Rs. In Crores)
1000 25 1025
9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
9.1 Financial and social befits with special emphasis on the benefit to the local People
Including Tribal Population, If Any, in The Area.
• M/s. SKSIPL going to increase the unachieved capacity of Steel melting shop by adding 4 Nos. of
induction furnaces hence all initially approved estimated parameters will be the same.
• There will be no use of fossil fuels (Coal and Diesel).
• Presently sponge production and ferro alloys are not fully utilized hence company have to sale in
open market. After proposed adding of 4 nos. of IF’s its internal consumption of sponge will be
increased which results in reduction in outgoing number of vehicles.
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 27
• After this arrangement companies internal consumption will be increased which will result in
reduction in outgoing number of vehicles and further reduction in fugitive emission on road
• It is further clarified that the technology of low frequency induction furnaces has improved a lot
and it runs under high efficiency. The electricity consumption is less as compared to old
technology.
• Further, M/s. SKSIPL has already decided to give topmost priority for employment to local people
within the plant, and outside the plant in direct and indirect employment. Out of over 70
people to be employed from the proposed project activities, the company would be employing
more than 40 people from local area, which would naturally involve tribal people also who are
more than 60% in population and also are now well qualified as well as competent to take the
employment in the proposed industry. The local population is likely to be benefited by payment of
salary and wages to the local community employed.
On overall assessment of the project with technical and financial aspects, it is concluded that the
proposed modification/enhancement of SMS division of integrated steel plant is technically highly
feasible and financially profitable.
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 28
Appendix I
APPROVAL LETTER FROM WATER RESOURCES DEPARTMENT
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 29
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 30
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 31
Appendix II
EXISTING ENVIRONMENTAL CLEARANCE LETTER, MoEF, NEW DELHI
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 32
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 33
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 34
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 35
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 36
Appendix III
EXISTING CONSENT LETTER
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 37
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 38
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 39
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 40
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 41
Pre-Feasibility Report (PFR)
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 42