1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Embed Size (px)

Citation preview

Page 1: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

1

Welcome to the International Right of Way

Association’s

Course 606Project Development and the

Environmental Process

606-PT – Revision 5 – 09.15.10.USA

Page 2: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Introductions

Who we are…What we do…

Where we do it…

How long we’ve been doing it…

Our goals for the course...

2

Page 3: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Objectives (1) After completing this course, you will be able to...

3

Page 4: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Objectives (2) After completing this course, you will be able to...

4

Page 5: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Housekeeping

5

Page 6: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Schedule (1)

6

MODULE I – Morning Session

8:00 – 8:30 Introductions, Etc.

8:30 – 8:45 Overview of Project Development and Environmental Process

8:45 – 9:45 National Environmental Policy Act (NEPA)

BREAK

10:00 – 11:15

Other Environmental Legislation

11:15 – 11:30

Comprehensive Environmental Permit Strategies

11:30 -12:00 Review and Introduction to Case Studies

Page 7: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Schedule (2)

7

MODULE II - Afternoon Session

1:00 – 1:40 Project Conceptualization

1:40 – 2:20 Constraints Analysis and Siting

2:20 – 2:50 Project Planning and Preliminary Design

BREAK

3:00 – 3:30 Project Decision, Detailed Design and Right of Way Acquisition

3:30 – 3:50 Construction

3:50 – 4:10 Operations and Maintenance

4:10 – 4:30 Review

4:30 – 5:00 Exam

Page 8: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Module I

Overview of ProjectDevelopment and Environmental

Compliance Process

8

Page 9: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Project Development Process

9

• Project Conceptualization

• Constraints Analysis and Siting

• Project Planning and Preliminary Design

• Project Decision, Detailed Design and ROW Acquisition

• Construction

• Operations and Maintenance

Page 10: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Environmental Regulation Review (Course 600)

10

Water resourcesWetlands regulationsWildlifeCultural resourcesAir qualityEnvironmental contaminationNational Environmental Policy Act (NEPA)

Page 11: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Environmental Regulation Review (Course 606)

11

National Environmental Policy Act (NEPA)

Endangered Species Act (ESA)

Wetlands Regulations (Clean Water Act, Section 404)

National Historic Preservation Act (NHPA) Section 4 (f)

Page 12: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

NEPA and

State EIA Laws

12

Page 13: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

NEPA Overview (1)

13

Directs all federal agenciesto consider environmental impacts in their

decision making processes for federal proposed actions.

Page 14: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

NEPA Overview (2)

14

NEPA’s three major provisions:

Established national environmental policy.

Created President’s Council on Environmental Quality (CEQ).

Required an EIS (environmental impact statement) as an “action forcing mechanism”.

Page 15: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Agencies Administering NEPA

15

Council on Environmental Quality (CEQ)

Environmental Protection Agency

Page 16: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

What Triggers NEPA?

16

Proposed actions that are:

• Directly carried out or funded by a federal agency.

• Financed or permitted by a federal agency.

• Connected actions.

Page 17: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Levels of NEPA Analysis

17

CEQ statistics indicate that 100 Easare prepared for every EIS.

Page 18: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Categorical Exclusions

18

Categories of actions that do not individuallyor cumulatively have a significant effect

on the human environment.

Proposed action fits within a class of actions listed in regulations.No extraordinary circumstances related to the proposal

that may have significant environmental effects.Action is not connected to any other actions

that may have significant impacts.

Page 19: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

EAs vs. EISs

19

Environmental Assessments (EAs)

Environmental Assessments (EAs)

Environmental Impact Statements (EISs)

Environmental Impact Statements (EISs)

• Significance of effects may be uncertain

• May be developed by an individual or interdisciplinary team

• Can require 2 -18 months to complete

• Can range from concise public documents that meet CEQ requirements to larger documents that are supported by a mitigated FONSI.

• Significant environmental effects

• Are developed by an interdisciplinary team

• Can require from 1 to more than 6 years to complete

• May range from 200 to more than 2,000 pages in length

Page 20: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Other NEPA Documents

20

Page 21: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

When is an Impact Significant?

21

CEQ regulations: context and intensityFactors to consider:

- Public health and safety- Unique characteristics of geographic area- Properties eligible for the National Register of Historic Places (NRHP)- Endangered species or their habitat- Cumulative effects- Federal, state, and local laws and regulations

Page 22: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Steps in EIS Analysis

22

Page 23: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Lead vs. Cooperating Agencies

23

Lead AgencyLead AgencyLead agency determined based on:•Magnitude of agency’s involvement•Project approval/disapproval authority•Expertise concerning the action’s environmental effects•Duration and sequence of agency involvement.

Source: CEQ NEPA regs Section 1501.5(c)

Cooperating AgencyCooperating Agency• Jurisdictional or management

responsibility over impacted resources

• Special expertise with impacted resources

• Geographic proximity to proposed action

• State and local agencies are eligible

• Lead agencies are responsible for designating cooperating agencies– CEQ has issued detailed lead

agency guidance

Page 24: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

NEPA Documentation

24

Administrative Draft EA/EISPublic Draft EA/EIS

Final EA/EISFONSI/ROD

Page 25: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Other NEPA Provisions

25

Public involvement(mandatory and optional)

Coordination with state“mini-NEPAs”

Page 26: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

State EIA Laws

26

Apply to a range of state/local actions, depending on the specific state.

Strongest EIS laws: California, Washington, New York.

FHWA NEPA delegation to states (highway projects).

Page 27: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

NEPA Review

27

Proposed ActionNEPA Document / Analysis Required

Small construction, restoration, or rehabilitation project.

Maintenance of an existing pipeline.

Issuance of a CWA Section 404 permit for a pipeline river

crossing.

Installation of a new pipeline in a new ROW.

Construction of a new highway.

Page 28: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Other Environmental Regulations

28

Page 29: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

29

Endangered Species Act(ESA)

Page 30: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

ESA Overview

30

Prevent extinction and recover of endangered and threatened species and the ecosystems upon which they depend.

Administered by:U.S. Fish and Wildlife Service (USFWS), National Oceanic and Atmospheric Administration (NOAA), National Marine Fisheries Service (NMFS)

Page 31: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

ESA Definitions

31

Endangered: In danger of extinction throughout all or a significant portion of its range.

Threatened: Likely to become an endangered species in the foreseeable future.

Candidate: Can be proposed as endangered or threatened but listing is precluded by other higher priority listing activities.

Page 32: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Major ESA Provisions

32

Page 33: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Section 7 Consultation

33

Prohibits federal agencies from undertaking actions that are likely to:

- Jeopardize the continued existence of a listed species.- Cause destruction or adverse modification of critical habitat.

Federal actions may include funding, permits, leases and other entitlements, and direct federal actions.

Page 34: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Section 7 Process

34

Informal consultation Do listed species exist in project area?Can proposed action affect the species or critical habitat?

Biological Assessment Prepared by federal agency for actions that require an EIS.

Formal consultation USFWS issues Biological Opinion.Determines effects on listed species and critical habitat and offers alternatives/mitigation.

Page 35: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Sections 9 and 10 –Take Prohibition and Authorization (1)

35

Prohibits “take” of listed fish or wildlife species.

“Take” includes harassing, harming,injuring, pursuing, hunting, capturingor killing a species.

Page 36: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Sections 9 and 10 –Take Prohibition and Authorization (2)

36

Incidental take permit (ITP) required when non-Federal activities result in a “take”.

Take must be “incidental to an otherwise lawful activity”.

Page 37: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Sections 9 and 10 – Take Prohibition and Authorization (3)

37

Habitat conservation plans must accompany ITP and outline actions to minimize or mitigate effects of authorized incidental take.

Page 38: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

ESA Review

38

Assume that a proposed new federally funded highway project may affect a listed endangered species.

What steps will you needto take to comply withthe ESA?

Page 39: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Wetland RegulationsClean Water Act

Section 404

39

Page 40: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Clean Water Act Section 404 Overview

40

Requires applicants to obtain a Section 404 permit prior to discharge of dredged or fill material into wetlands or other waters of the U.S.

Requires U.S. Army Corps of Engineers (USACE) and EPA to issue guidelines governing permit programs.

Page 41: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Jurisdictional Waters

41

All waters that are currently used, or were used in the past, or may be susceptible to use in interstate or foreign commerce.

All “other waters” including wetlands that could affect interstate or foreign commerce.

Classification of “isolated” intrastate waters and wetlands is controversial and uncertain.

Page 42: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Nationwide Permits

42

Apply to broad categories of dischargeactivities that will cause only minimaladverse environmental effects on a directand cumulative basis.

NEPA review has been completed and the permit is already issued.

Compliance with other federal environmental legislation required

Page 43: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Individual Permit Process

43

Page 44: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Section 404 Review

44

Assume that a pipeline has been proposed through an area that appears to include jurisdictional wetlands and waters of the U.S.

What steps you would take to comply with the Clean Water Act, Section 404?  

Page 45: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Quiz

45

Is a permit required for ANY project that will discharge dredge or fill into a wetland? 

No. Permits are only required for “waters of the U.S” or jurisdictional wetlands.

Page 46: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Mitigation of Wetland Impacts

46

National goal of no net loss of wetlands function and value is applied to each

permit decision.

Mitigation and monitoring plan should include:Goals/objectivesSite designSuccess criteriaLong term monitoring requirementsMaintenance activities

Page 47: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

National Historic Preservation Act (NHPA)

47

Page 48: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

NHPA Overview

48

Established the National Register of Historic Places.

Created the Advisory Council on Historic Preservation.

Established the Section 106 review process.

Page 49: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

National Register of Historic Places

49

Recognizes districts, sites, buildings, structures and objects.

Must be significant to American history, architecture, archeology, engineering or culture.

Generally, properties younger than 50 years not eligible.

Page 50: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Section 106 Review

50

Applies to federal actions that may affect NHRP listed or eligible properties.

Requires that federalagencies consult with:

- Advisory Council on Historic Preservation State - Historic Preservation Officer (SHPO)- Local agencies- Indian tribes

Page 51: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Section 106 Review Process (1)

51

Page 52: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Section 106 Review Process (2)

52

Page 53: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Question

53

Assume that a pipeline has been proposed through an area that appears to include jurisdictional wetlands and waters of the U.S.

What steps you would take to comply with

the Clean Water Act, Section 404?

Page 54: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Coordination with otherCultural Resource Laws

54

National American Graves Protection and Repatriation Act (NAGPRA)

American Indian Religious Freedom Act (AIRFA)

Archaeological Resources Protection Act (ARPA)

Agency-specific legislation (e.g., Department of Transportation Act, Section 4(f))

Page 55: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

NHPA Review

55

A transmission line is being planned through an area known to have archaeological resources and historic buildings.

What steps would you take to comply with the National Historic Preservation Act (NHPA), Section 106?

Page 56: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Department of Transportation ActSection 4 (f)

56

Page 57: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

4 (f) Overview

57

Requires that transportation projects must avoid historic sites unless there is “no feasible and prudent alternative”.

Project plans must all possible options to avoid or minimize harm to property.

Page 58: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

4 (f) Applicability

58

Applies to any land… Permanently incorporated into a transportation facility.That requires temporary occupancy during the project.Where substantial impairment of the resource may occuras a result of the proposed project.

Projects receiving DOT funds must completea 4(f) evaluation

Evaluation to be included in NEPA documents

Page 59: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Comprehensive Environmental Permit

Strategies

59

Page 60: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Develop Permit Inventory

60

Consider the nature of project activities and affected resources.

Include agency names, regulatory processes, key data and time frames.

Seek project alternatives that avoid or streamline permitting processes.

Page 61: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Develop Permit Strategy

61

Develop preliminary compliance approaches.

Coordinate permitting timelines.

Identify permitting requirements or otherfatal flaws.

Page 62: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Permit Types

62

Page 63: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Implement Permit Strategy

63

Use NEPA and local government permitting as the umbrella for permitting decisions.

Be proactive in the processPre-application consultationSubmit complete and accurate applicationsDocument key permitting meetings and decisions

Page 64: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Review and Recap

64

Page 65: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Module II

Integrating Environmental Compliance into Project

Development

65

Page 66: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Project Development Process

66

• Project Conceptualization• Constraints Analysis and Siting•Project Planning and Preliminary Design•Project Decision, Detailed Design and ROW Acquisition • Construction• Operations and Maintenance

Page 67: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Schedule (2)

67

MODULE II - Afternoon Session

1:00 – 1:40 Project Conceptualization

1:40 – 2:20 Constraints Analysis and Siting

2:20 – 2:50 Project Planning and Preliminary Design

BREAK

3:00 – 3:30 Project Decision, Detailed Design and Rightof Way Acquisition

3:30 – 3:50 Construction

3:50 – 4:10 Operations and Maintenance

4:10 – 4:30 Review

4:30 – 5:00 Exam

Page 68: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Project Conceptualization

68

Page 69: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Identify Purpose of and Need for Action

69

Statement should consider:Proponent’s purpose and need.

Potential NEPA lead agency’s purpose and need.

Page 70: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Develop ConceptualProposed Action

70

• Internal evaluation phase.

• Identify technical and engineering aspects of project.

• Compile list of required materials to develop action

- Text, tables, figures, GIS information- Budget, priority level, potential timeframe

Page 71: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Integrate Factors intoEngineering Plans

71

• Pre-NEPA process.

• Preliminary assessmentEnvironmental engineeringPermitting and compliance evaluationsMitigation opportunitiesPotential siting options

• Identify potential environmental red flags.

Page 72: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Conduct PreliminaryAlternatives Analysis

72

• Pre-NEPA process.

• Internal evaluation of project components and alternatives.

• Develop “options”.

Page 73: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Identify Likely Fields of Study

73

• Identify likely field studies that will address potential environmental and natural resource issues.

• Potential field studies should be incorporated into schedules and budget.

• Delays in field studies can delay NEPA and permitting processes.

Page 74: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Role of Right of Way Professional

74

• Support for project conceptualization.

• Identification of potentially affected land uses and ownership for various project options.

• Preliminary identification of environmental issues and red flags.

• ROW planning and strategies.

• Support for environmental permit strategies.

Page 75: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study: Project Conceptualization

75

Please read the Project Conceptualization in the case study and discuss with your small group.Be ready to report to the entire class, thefollowing project elements. 

• A brief description of the project.

• Project purpose and need.

• Potential environmental red flags.

• Possible field studies that may be required in the future.

Page 76: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study:Project Conceptualization

76

×Ö

#0

Orem

Lehi

Provo

Midvale

Riverton

Salt Lake City

Great Salt Lake

UtahLake

!b

114th & 119th

Printed: 10:14 am 03/23/2004File: F:\6784_158\Maps\Field\I-15.mxd

I-15 SouthExpansion

0 52.5Miles

×Ö Neighborhood Impacts

Project Area

´

Page 77: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Project Development Process

77

• Project Conceptualization

• Constraints Analysis and Siting

• Project Planning and Preliminary Design

• Project Decision, Detailed Design and ROW Acquisition

• Construction

• Operations and Maintenance

Page 78: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Constraint Analysis and Siting

78

Page 79: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Assess Land Ownership and Uses

79

• Public and private landowners may be affected by proposed action.

• Existing and planned future land uses should be evaluated along proposed project route.

• Important for subsequent land acquisition needs and costs, adjacent land use compatibility, plans, and access.

Page 80: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Develop Environmental Permit Strategy

80

• Develop comprehensive permit strategy.

• If necessary, hold pre-permit meetings to discuss special circumstances or uncertainties about specific permits or approval.

• Initiate plans to coordinate permit acquisition efforts with the NEPA process.

• Develop formal permit and approval tracking system.

Page 81: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Assess Available Information

81

• Determine study area boundaries.

• Access and evaluate existing study area data

- Real estate public records- NEPA documents- Existing GIS files

Page 82: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Initiate Field Studies

82

• Revisit field studies that were identified in project conceptualization phase.

• If necessary for process timeline, initiate field studies.

• Results may reveal new constraints or restrictions on a specific project plan or location.

Page 83: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Develop Public Involvement Plan

83

• Identify key stakeholders (individuals and groups).

• Develop pre-NEPA public involvement plan

- Identify issues that may affect public perception of proposed project

- Assess internal options for alleviating or mitigating negative perceptions

Page 84: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Develop Project Schedule

84

• Master schedule- Timeline- Project steps and processes

- Milestones

• Include environmental processes- Permitting

- NEPA

- Public involvement

• Develop critical path for the project

Page 85: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Role of Right of Way Professional

85

• Constraints Analysis and Siting

• Land values and acquisition costs

• Potential for easements and other land use options

• Potential intersections with other linear projects

Page 86: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study:Constraints Analysis and Siting

86

- Please read the Constraints Analysis and Siting in the case study and discuss with your small group. Be ready to report to the entire class, the following project elements. - Think about… Possible land ownership and use constraints. Which permitting agencies will need to be involved in the process.

Page 87: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study:Constraints Analysisand Siting

87

×Ö

#0

Orem

Lehi

Provo

Midvale

Riverton

Salt Lake City

Great Salt Lake

UtahLake

!b

114th & 119th

Printed: 10:14 am 03/23/2004File: F:\6784_158\Maps\Field\I-15.mxd

I-15 SouthExpansion

0 52.5Miles

×Ö Neighborhood Impacts

Project Area

´

Page 88: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Project Development Process

88

• Project Conceptualization

• Constraints Analysis and Siting

• Project Planning and Preliminary Design

• Project Decision, Detailed Design and ROW Acquisition

• Construction

• Operations and Maintenance

Page 89: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Project Planning andPreliminary Design

89

Page 90: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Refine Proposed Action

90

• Review overall project feasibility.

• Determine “scope” of proposed action that will be used in NEPA analysis.

• Should act as a proposal for the lead NEPA and other regulatory agencies to authorize, recommend or implement an action to address a clear purpose and need.

Page 91: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Develop Reasonable Rangeof Alternatives

91

• Identify alternative ways of reaching the project purpose.

• May include alternate location, scope, components, design features and construction/ operations plans.

• Provide alternatives analysis that explains why each option was considered or rejected.

Page 92: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Initiate the NEPA Process

92

Initiated upon formal submittal of refined proposed action to lead NEPA agency.

- Agency will determine level of analysis required.

- Agency will organize and implement plan for carrying out NEPA responsibilities .

Page 93: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Implement Public Involvement Plan

93

• Lead agency implements public involvement plan.

• Should be integrated with proponent’s public involvement plan (if one exists).

Page 94: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Permitting

94

• Refine environmental permit strategy and initiate pre-permit meetings.

• Initiate or continue communication with regulatory agencies.

• Submit formal permit applications if adequate design information is available.

Page 95: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Role of Right of Way Professional

95

• Project Planning and Preliminary Design

• Maintain communication with potentially affected landowners, proponent, and regulatory agencies.

• Ensure that proponent’s plans are properly communicated to interested parties.

Page 96: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study:Project Planning and Preliminary Design

96

Please read the Project Planning and Preliminary Design in the case study and discuss with your small group. Be ready to report to the entire class, the following project elements. Think about… - Reasonable alternatives - Issues will require attention from the right of way team

Page 97: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study:Project Planning andPreliminary Design

97

×Ö

#0

Orem

Lehi

Provo

Midvale

Riverton

Salt Lake City

Great Salt Lake

UtahLake

!b

114th & 119th

Printed: 10:14 am 03/23/2004File: F:\6784_158\Maps\Field\I-15.mxd

I-15 SouthExpansion

0 52.5Miles

×Ö Neighborhood Impacts

Project Area

´

Page 98: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Complete NEPA and Permit Acquisition Process

98

• Two processes should achieve coordinated results

• NEPA document should include:- Environmental commitments- Operating procedures- BMPs and mitigation measures- Construction and operations plans - Related contingency plans

Page 99: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Project Development Process

99

• Project Conceptualization

• Constraints Analysis and Siting

• Project Planning and Preliminary Design

• Project Decision, Detailed Design and ROW Acquisition

• Construction

• Operations and Maintenance

Page 100: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Project Decision, Detailed Design,and Right of Way Acquisition

100

Page 101: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

NEPA Process Completion

101

IMPORTANT!

The NEPA process and other regulatory processes should be completed priorto detailed design and right of way

acquisition.

Page 102: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Develop Adaptive Management Program

102

• Purpose is to improve impact mitigation.

• Plan outlines ways to adjust actions whenthe level of impacts or effectiveness of mitigation measures is highly uncertain

Page 103: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Acquire Right of Way

103

• Right of way acquisition approval allows agency to establish compensation to and grant authority for specific persons to negotiate.

• Land acquisition plan is developed to- Track schedules- Develop cost estimates- Coordinate project alignment variations and adjustments- Define construction procedures and limits

Page 104: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Develop Detailed Construction Plan

104

• All environmental commitments from NEPA and permitting processes must be captured in the construction plan and bid documents.

• Plan should include:- Preconstruction inspections- Site preparation- Mobilization- Groundbreaking

Page 105: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Obtain Necessary ROWClearance Certifications

105

• Payments negotiated and paid to affected property owners.

• Land or rights to land acquired (and vacated if necessary).

• Right of way staff can issues clearance certificate(s).

Page 106: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Role of Right of Way Professional

106

• Title searches and certification of title• Appraisals• Relocation assistance• Acquisitions• Condemnation support• Property management• Community involvement• Project notifications

Page 107: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study: Project Decision,Detailed Design, and Right of Way Acquisition

107

Please read the Project Decision, Detailed Design, and Rightof Way Acquisition in the case study and discuss with your small group. Be ready to report to the entire class, the following project elements. Think about… - Best management practices or environmental commitments that might apply to the construction right of way

- Methods to monitor these commitments

Page 108: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study:Project Decision, Detailed Design, and ROW Acquisition

108

×Ö

#0

Orem

Lehi

Provo

Midvale

Riverton

Salt Lake City

Great Salt Lake

UtahLake

!b

114th & 119th

Printed: 10:14 am 03/23/2004File: F:\6784_158\Maps\Field\I-15.mxd

I-15 SouthExpansion

0 52.5Miles

×Ö Neighborhood Impacts

Project Area

´

Page 109: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Project Development Process

109

• Project Conceptualization

• Constraints Analysis and Siting

• Project Planning and Preliminary Design

• Project Decision, Detailed Design and ROW Acquisition

• Construction

• Operations and Maintenance

Page 110: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Construction

110

Page 111: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Construction Plans

111

On-site environmental and ROW personnel should be present during construction phase to monitor compliance with environmental commitments.

Responsibilities may include:- Schedule

- Staging- Permit compliance- Spoil (waste) sites- Detours / construction routes- Access maintenance- Traffic control- Project restoration activities

Page 112: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Inspection and Monitoring Activities

112

• Ensure that project is being built as designed and in accordance with change orders.

• Coordinate activities with abutting property owners and occupants.

• Monitor construction workforce activities around previously identified impact or environmentally sensitive areas.

Page 113: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Anticipate and Respond to Changes during Construction

113

NEPA documents, permit conditions, and construction plans should be written to anticipate and provide coverage for unforeseen changes

Change may require:- Noting change in monitoring report- Notifying lead agency or permitting agencies- Implementing contingency plans- Reopening NEPA and permit process

Page 114: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Role of Right of Way Professional

114

• Construction

• Maintain communication between public, proponent, landowners, and lead agency

• Maintain up to date knowledge on:- Project needs and justification- Route selection process- Environmental impacts and mitigation measures- Land ownership and use considerations- Facility design and procedures

- Construction methods

- Damage claim and settlement procedures

- Health and safety issues

Page 115: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study: Construction

115

Please read the Construction in the case study and discuss with your small group. Be ready to report tothe entire class, the following project elements. Think about…

- Best management practices to prevent project delays or cost overruns

- Ways to minimize project delays or cost overruns if they should occur

Page 116: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study:Construction

116

×Ö

#0

Orem

Lehi

Provo

Midvale

Riverton

Salt Lake City

Great Salt Lake

UtahLake

!b

114th & 119th

Printed: 10:14 am 03/23/2004File: F:\6784_158\Maps\Field\I-15.mxd

I-15 SouthExpansion

0 52.5Miles

×Ö Neighborhood Impacts

Project Area

´

Page 117: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Project Development Process

117

• Project Conceptualization

• Constraints Analysis and Siting

• Project Planning and Preliminary Design

• Project Decision, Detailed Design and ROW Acquisition

• Construction

• Operations and Maintenance

Page 118: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Operations and Maintenance

118

Page 119: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Maintain and Monitor Environmental Compliance Requirements

119

Inspection, monitoring, compliance, resource management

Life of the project commitment

Page 120: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Implement an AdaptiveManagement Plan

120

If applicable, implement plan during project operations

Ensure that activities are achieving performance standards and make

adjustments, if necessary

Page 121: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Staff Involvement and Changes

121

Ensure that activities are achieving performance standards

Activities include:- Vegetation management and monitoring- Slope stabilization- Debris removal and waste management- Permit license reporting and renewals- Storm water management- Noise control- Maintenance of restored/created habitats- Emergency repairs/response

Page 122: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Role of Right of Way Professional

122

• Operations and Maintenance

• Assist with maintenance and monitoring of proponents environmental responsibilities and commitments

• May include:- Encroachment monitoring- Public awareness programs- Property management programs

Page 123: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study:Operations and Maintenance

123

Please read the Operations and Maintenance in the case study and discuss with your small group. Be ready to report to the entire class, the following project elements. Think about…

- Responsibilities a right of way professional can undertake to ensure that environmental commitments are met

Page 124: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Case Study::Operations andMaintenance

124

×Ö

#0

Orem

Lehi

Provo

Midvale

Riverton

Salt Lake City

Great Salt Lake

UtahLake

!b

114th & 119th

Printed: 10:14 am 03/23/2004File: F:\6784_158\Maps\Field\I-15.mxd

I-15 SouthExpansion

0 52.5Miles

×Ö Neighborhood Impacts

Project Area

´

Page 125: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Objectives (1) Now, you are able to...

125

Page 126: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

Objectives (2) Now, you are able to...

126

Page 127: 1 Welcome to the International Right of Way Association’s Course 606 Project Development and the Environmental Process 606-PT – Revision 5 – 09.15.10.USA

127

Thank you