1

Project management in SE

Basic principles of software projects

Peeter Normak

12.11.2015

Page 2: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

2

Plan

1. General requirements for software

2. Specifics of software projects

3. Critical success factors of software projects

4. Preliminary planning of a software project

5. Software project staffing

6. Requirements development

7. Quality, risk and change management

8. Co-operation with upper management

9. Software projects costs estimation

10. Release of software

11. Software process best practices

Page 3: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

3

General requirements for software

Page 4: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

4

Development trends of modern economy and society

The structure and type of economical activities are changing:

1. The share of services compared to manufacturing sector is constantly increasing (1970 – 1:1; 2010 – 3:1; IBM: 1995…2005 – 28% 55%).

2. Internet is becoming the major environment for providing services.

3. Services are becoming more and more individualized (mass customization, co-creation).

Page 5: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

5

ICT influences the whole society

The business models of enterprises and organizations are changing:

• Production ecosystems emerge. Example: Opel (seat belts)

• Economy globalizes.

• Economic processes are more standardized and automated.

ICT has decisive role in implementing changes:

• about half of the productivity increase is due to ICT implementations.

• The potential yearly contribution to European GDP from achieving a fully functioning Digital Single Market has been estimated at EUR 415 billion.

E-skills are becoming ultimately important.

Page 6: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

6

Discussion

What are the most general requirements for

modern software that makes its development complicated?

Page 7: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

7

General requirements for software

Modern software should:

1. Operate on different platforms and with different hardware.

2. Be interoperable with a wide variety of other software.

3. Satisfy the needs of a wide – and non-homogeneous – user group.

4. Be easily adaptable to specific needs and changing environments (for example changing legislation and institutional regulations).

General requirements for software projects are determined by the general requirements for software.

Page 8: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

8

Specifics of software projects

Page 9: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

9

Specifics of software projects – implications from general requirements

Software should:

• confirm to the standards,

• be user friendly both visually (graphical design) and logically (correspond to the activity patterns of users),

• be easily expandable,

• support the main processes of application areas,

• adequately react to deliberate (for example attacks) and inadvertent (for example power failure) disruptions.

Page 10: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

10

Specificity of software projects – high failure rate

Successful Problematic Failed

1994 16 53 31

1996 27 33 40

1998 26 46 28

2000 28 49 23

2004 29 53 18

2006 35 46 19

2009 32 44 24

2012-waterfall 14 57 29

2012-agile 42 49 9

Standish Group (figures are in percentage):

Page 11: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

11

Action lines for responding to the problems

The main reason for emerging severe problems in software development – massive introduction of local and wide area networks in 1980-ies and 1990-ies.

Action lines:

1. Systematic analysis of software development process and development of a variety of software development methodologies and tools.

2. Development of ICT related specifications and standards.

3. Development of different frameworks (for example, SWEBOK) and capability maturity models (for example, CMM-SW).

4. Development of curricula recommendations.

5. Development of e-skills certificates and certifying institutions.

6. Professionalization of ICT (project) management.

Page 12: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

12

Current policies in Europe responding to the problems

1. DIGITALEUROPE’s Vision 2020 (http://www.digitaleurope.org/DesktopModules/Bring2mind/DMX/Download.aspx?Command=Core_Download&EntryId=157&PortalId=0&TabId=353).

2. Digital Agenda for Europe (https://ec.europa.eu/digital-agenda/en/digital-agenda-europe-2020-strategy).

3. A Digital Single Market Strategy for Europe (http://ec.europa.eu/priorities/digital-single-market/docs/dsm-communication_en.pdf).

4. Future-proofing eGovernment for a Digital Single Market.

5. Opening up Education: Innovative teaching for all through new Technologies and Open Educational Resources (http://eur-lex.europa.eu/legal-content/EN/TXT/PDF/?uri=CELEX:52013DC0654&from=EN).

Page 13: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

13

Critical success factors of software projects

Page 14: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

14

Critical success factors of software projects

Fundamental: optimize (minimize) rework in software development.

The role of initial phase in planning where the most important decisions are made – the 10% indicator.

Critical success factors are to a great extent determined by the requirements for software on the one hand and on the available resources on the other hand.

Examples: Dippler (lack of resources).

NB! Some more process management during the initial phase of a project can avoid huge overspendings for correcting mistakes in a final phase of a project; problems should be solved immediately!

Page 15: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

15

Critical success factors of software projects

Examples (for another study, see Appendix 2 of the Lecture Notes – Aspects of ICT Project Management):

1. User involvement during the whole project.

2. Effective change management.

3. Quality assurance.

4. Timely integration of components.

5. Adequate corrections of time-table.

6. Following a suitable process model.

7. Support of the upper management.

Page 16: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

16

Preliminary planning of a software project

Page 17: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

17

The three main questions (view of a developer)

Planning costs of a project are normally 5-10% of the total costs of a project.

Before making the bid decision, answer the following questions:

• Our bid will win because … (allows to stress on the strengths),

• If our bid will not win, it will be because … (allows to eliminate the possible weaknesses),

• The top three risks are … (allows to mitigate the risks).

Page 18: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

18

Discussion

What aspects for making the bid/no bid decisions would you consider?

Page 19: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

19

Making the bid/no bid decision (Smith, 2001)

1. Clarity of requirements.

2. Consistency with the strategy of the applicant.

3. Previous cooperation with the customer.

4. Existence of modules that are suitable to use in the project.

5. Existence of staff with necessary skills.

6. Availability of time resource for composing a high level bid.

7. Readiness of the customer to pay an adequate prise.

8. Prospects to win depending on the number of competitors and their quality.

9. The rate of differentiation from the competitors.

10. Ability to offer cheaper solutions compared to the competitors.

11. Opportunities to discuss the requirements, priorities, possibilities evaluation criteria and possible solutions with the customer.

Page 20: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

20

The phases of a software process

The simplest model : ADDIE (Analyse, Design, Development, Implementation, Evaluation) or,

in more common terms in software development:

Requirements, Design, Construction, Testing, Implementation.

SWEBOK (The Guide to the SoftWare Engineering Body Of Knowledge): 15 knowledge areas + sub-areas (topics).

For example, Software Requirements has the following subareas among the 10 topics:

1) Requirements elicitation

2) Requirements analysis

3) Requirements specification

4) Requirements validation

Page 21: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

21

Preliminary planning of a software project

The outcome of preliminary planning: a Charter.

The Charter should contain:

• The vision of the project

• The main authority/decision maker

• The objectives of the project

• The main risks

• Needs in personnel

• Estimated duration of the project.

Page 22: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

22

Uncertainty coefficients for duration of a SW project

If the objectives of a project are concretized during the project then duration should be adjusted as well.

Example: uncertainty coefficients (according to NASA SEL): c 1/c

•After specification of requirements 2,0 0,5•After requirements analysis 1,75 0,57•After general design 1,4 0,71•After detailed design 1,25 0,80•After coding 1,1 0,91•After testing 1.05 0,95

Page 23: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

23

Software project staffing

Page 24: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

24

Software project staffing – the work distribution

Need for a staff depends on the development model. Requirements analysis requires usually more time and higher qualification some models do not include this phase, considering it separately.

Fred Brooks suggestion (distribution of man months): 1/3 planning, 1/6 coding, 1/4 component test, 1/4 system test.

Brooks’ law: “adding manpower to a late software project makes it later”.

Replacement of a developer during a software project is very costly forming and keeping the staff is one of the quality indicators of project managers.

Problem: non-compliance of knowledge, skills and practices. Example: GP master thesis – quality assurance.

Page 25: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

25

Software project staffing – the roles

Different development models consider different roles of software project team members.

Example (Belbin’s role model, http://www.belbin.com/about/belbin-team-roles/):

• Co-ordinator

• Shaper

• Plant

• Monitor Evaluator

• Implementer

• Teamworker

• Resource investigator

• Specialist

• Completer Finisher

Page 26: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

26

Software project staffing – recommendations

1. Plan only up to 75% of available resources (including personnel).

2. Invest rather to an expert than to a “cheap” beginner and hope in his training and development (difference 10x in productivity, 5x in speed).

3. Harmony of the project team is more important than individual knowledge/skills; insufficient handling of tensions is the most often complaint of staff members. Belbin: balance – not intellect – enables a team to succeed.

4. Personality characteristics are more important than knowledge/skills: the latter are easier to form (Roger Woolfe, 10:6).

5. Project manager should be free in forming the project team; pressure should be avoided.

6. The roles that are formed in some other context should not inhibit the roles distribution in the project.

Example: student projects in Victoria University (Melbourne).

Page 27: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

27

Requirements development

Page 28: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

28

Requirements development

A software requirements: a description of a software system to be developed (may include also some use cases that describe interactions the users will have with the software).

Requirements are divided into functional and non-functional requirements.

Standish Group: The quality of requirements is in importance the 3rd success factor, and the 3rd failure factor.

Fundamental: user involvement (and therefore, identification of the key end users). Recommendations: http://www.mitre.org/publications/systems-engineering-guide/se-lifecycle-building-blocks/requirements-engineering/eliciting-collecting-and-developing-requirements

Page 29: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

29

Requirements development – possible problems

1. The objective of a project is formulated in very general terms. Possible activities (PA): definition of related processes and concrete specification of requirements; composition of user stories.

2. Definition of users that will be involved in development. All important profiles should be represented. Example: registration to the courses.

3. Finding common language with the users. PA: training, seminars.

4. User awareness of their needs. PA: interviews, composition of user stories.

5. Ensuring effective usability. PA: style guide, prototypes, user manual.

6. Requirements change during the project. PA: using agile methodologies, effective change management.

Page 30: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

30

Quality, risk and change management

Page 31: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

31

Quality assurance

The influence of quality extends far beyond the End of a project quality is much more important than time overruns.

Some important aspects:

1. The tests of an integrated system should be performed by people not belonging to the developers team.

2. Pareto rule (80:20) normally applies. Problematic modules should be found as early as possible.

3. Determine when to stop testing (for example, by the timely distribution of errors or by the formula N*M/L).

4. Procedures for correcting errors should be established (corrections should not cause new errors, automated testing etc).

Page 32: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

32

Risk management

Risk management can be considered as solving of some kind of optimization exercise; in average 5-10% of the costs.

Follows general risk management schemes. The specific IT risk management activities include: 1) risk monitoring, 2) pricing of security measures, 3) monitoring of IT processes, 4) information security incident management, 5) log analysis and evidence handling.

Standard: ISO/IEC 27005:2011  Information technology — Security techniques — Information security risk management.

Framework (example): Risk IT – A Risk Management Framework by Information Technology Governance Institute (ITGI).

Analysis (example): http://www.isaca.org/SiteCollectionDocuments/2015-risk-reward-survey/2015-it-risk-reward-barometer-report.pdf

Page 33: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

33

Change management – the procedure

Project plan and other documents need continuous updating/adaptation.

An agreed scheme is necessary. Example:

1. Initiators of a change will compose and submit Proposal for a Change that describes the reasons why changes are needed and what are the expected results when changes will be implemented.

2. The board forwards the proposal for acceptance and improvement suggestions to the parties concerned.

3. The parties concerned will estimate the possible costs and benefits from their point of view.

4. Based on the feedback the board will make a conclusion and informs about it the parties involved.

NB! All important document (risks, tests, style guide, delivery check list etc) should be the subject of change management.

Page 34: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

34

Change management – topics to be considered

“Compulsory” topics:

1. Influence to the project plan: time-table, resource distribution (for example, increases the work load of busy people), quality etc.

2. Timing: are the changes timely (or should be postponed)?

3. Risks: affecting existing and emerging new risks.

The advantages of well organised change management:

1. Solutions used for software development are more broadly discussed and motivated.

2. The project is documented more completely.

3. The parties are better informed about each other activities.

Page 35: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

35

Co-operation with the upper management

Page 36: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

36

Co-operation with upper management – the need

Standish Group: Co-operation with upper management is in importance the 2nd success factor, and the 4th failure factor.

Effective co-operation assumes that the members of upper management are: 1) informed and 2) involved (the managers should get the feeling of ownership).

The following situations should be prevented:

1) Suspicions of the managers that the project is planned not quite adequately. Solution: all important aspects should thoroughly grounded and discussed with the managers.

2) The managers may make decisions that inhibit the project activities because they are not informed about the project’ needs (agreements of third parties, assigning important resources to other needs etc).

Page 37: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

37

The aim of cooperation – getting support when needed

1. For doing a particular project or initiative.

2. For getting support in solving unexpected or serious problems (or even solving the problems).

3. For getting input from other projects or activities.

4. For launching cooperation with other institutions/stakeholders.

5. For getting involved/offering participation in new initiatives.

6. For focusing and speeding up processes (implementing bottom-up initiatives are normally time-consuming).

Page 38: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

38

Co-operation with upper management – example

“Alcohol test”: the manager asks unexpectedly questions about important aspects of the project.

The objective of the test: to make sure that the team members have understood the project and their role within it.

Preventive actions are needed for successful passing the test: asking himself the possible questions, finding answers and discussion with the team members.

Page 39: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

39

Software projects’ costs estimation

Page 40: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

40

Software projects costs estimation

The model: Workload = SizeProcess × Staff Environment Quality

Size unit: 1000 lines of code or a function. Practices: reuse of components/code, automatic code generation.

Process. Practices: optimizing human work, reducing unnecessary work.

Staff: balanced team is better than individualistic high level experts. • Use less and better people.• Adjust the tasks to competences and motivation of the staff members. • Chose each other complementing and harmonizing people.• Help people to achieve self-realization.

Environment: development and other tools, techniques etc.

Quality: • Using suitable indicators/metrics.• Adapting mutually supportive work culture.

Page 41: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

41

Release of software

Page 42: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

42

Release of software

Procedures:

1. The distribution of errors has reached acceptable level.

2. All fatal errors are found and corrected.

3. Going through the release checklist.

4. Agree on the procedure for correcting the errors that are found after the project finishes.

5. Compose and discuss the history document.

Example. Release Management on Data Warehouses (Ronald Konings, http://www.konings.biz/thesis/Release%20Management%20%20Master%20Thesis%20v10.pdf).

Problem: rationality of beta-testing.

Page 43: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

43

Release – recommendations

1. Forrester Research (2011):

• Improve pre-build process (check the quality before the release; many problems have their root cause in early stages),

• Expand release management throughput (use parallelism and intelligent testing processes);

• Optimize release pipelines (implement virtualization, compress release cycles);

• Design software for rapid change (improve system modularity);

• Create common release portals (managers, developers and testers are informed about the updates).

2. Gartner (2013): release management process is insufficient or even completely missing in 95% of IT organizations.

Page 44: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

44

Software process best practices

Page 45: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

45

Recommendations I – Software process best practice

1. Present software to the customers as early as possible. No matter how much will you co-operate on the requirements analysis phase, practical work with the software is much more effective.

2. Use suitable process model. The model depends on the organizational culture of the institution, competence, elaboration of requirements, willingness to take risks etc.

3. Minimize the intellectual distance (between problem and solution, as well between the parties of the development). Structure of software should correspond to real world structures.

4. Make the program right before making it fast. It is easier to make working program simpler than a fast program correct

Page 46: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

46

Recommendations II – Software process best practice

5. Good management is more important than good technology. Good technology does not compensate bad management. Good manager attracts good people and forms a devoted team.

6. Understand and follow the customers priorities. The customer agrees to get 90% functionality delayed if only the most important 10% will be delivered on time.

7. Software should allow changes. This applies both to the structure and components.

8. Software development should be self-documenting. The code must have a clear and clean structure, the names reflect their meaning etc.

Page 47: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

47

Home assignment No 5

1. Formulate three words of wisdom based on the article “Why Software Fails” (http://spectrum.ieee.org/computing/software/why-software-fails/).

2. Find at least five myths of software development.

3. What do you have learned at most from NASA SEL experience (http://www.cs.umd.edu/~basili/publications/proceedings/P94.pdf)?

Page 48: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

48

Next lecture:

Thursday, 26. November

at 12:00

Topics:

- Methodologies and models of

software processes

- Concluding discussions

Page 49: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

49

Curricula recommendations

• Association for Computing Machinery (ACM) and IEEE-Computer Society: http://www.acm.org/education/curricula-recommendations

• The European Centre for the Development of Vocational Training (CEDEFOP): www.cedefop.europa.eu/etv/Upload/Information_resources/Bookshop/50/2204_en.pdf

• European Quality Assurance Network for Informatics Education (EQANIE): http://www.eqanie.eu/pages/quality-label/framework-standards-criteria.php

Page 50: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

50

E-skills development

EU policy (“Technology for innovation/ICT industries and e-business”):

NB! Directorate General Enterprise and Industry.

European e-Skills 2006 Conference in Thessaloniki:

“the success of the Lisbon strategy, the competitiveness of European industry and social cohesion are dependent on the effective use of ICT and the knowledge, skills, competencies and inventiveness of the European workforce and its ICT practitioners.”

Developers Customers

Users/stakeholders

Page 51: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

51

Development of e-skills

Communication of European Commission 7.9.2007 “E-skills for the 21st century: fostering competitiveness, growth and jobs”).

The key components of the long-term e-skills agenda:

1.Longer term cooperation: strengthening cooperation between public authorities and the private sector through the promotion of multi- stakeholder partnerships and joint initiatives.

2.Human resources investment: ensuring sufficient public and private investment in human resources and e-skills.

3.Attractiveness: promoting science, maths, ICT, e-skills, job profiles, role models, and career perspectives with a particular focus on young people.

4.Employability and e-inclusion: developing digital literacy and e-competence actions.

5.Lifelong acquisition of e-skills: ensuring that workers can regularly update their e-skills.

Page 52: 1 Project management in SE Basic principles of software projects Peeter Normak 12.11.2015

52

Estonia – institutions supporting ICT higher education

Tallinn (www.tlu.ee) and Tartu (www.ut.ee) Universities and Tallinn University of Technology (www.ttu.ee), The Estonian IT College (www.itcollege.ee).

Estonian IT Foundation for Education (www.hitsa.ee/en/) – supports ICT innovations and implementation in the universities.

Archimedes Foundation (http://archimedes.ee/en/foundation/) – implements international and national programmes and projects in the field of education and research.

Estonian National program in IT – supports R&D projects.

Association of Information Technology and Telecommunications (www.itl.ee, universities are associated members) – supports cooperation with the industry, promotes ICT professions.

Estonian Development Fund – composes foresights etc (http://www.arengufond.ee/en/).