Upload
coleman-ficken
View
216
Download
0
Tags:
Embed Size (px)
Citation preview
1
MICE CM31
• Key schedule drivers for Step IV• Schedule table• Milestone summary• Comment on Step V• Step VI
Andy Nichols, STFC, 3/11/11
Key Schedule drivers for Step IV
• Spectrometer solenoids:• Very encouraging progress; reassembly is coming on well• We have a realistic and achievable delivery schedule• All major technical issues appear to be closed• MAP and MICE reviews have been signed off• Injection of manpower is clearly paying dividends
• AFC modules:• AFC #1 is in final stages of manufacture at Tesla Eng• Pressure point is the OVC (outer vacuum can assembly)• Coils for both modules wound, experts agree they are very high quality• But delivery date has slipped to end February, 2012• This date urgently needs to be reviewed very carefully with Tesla
Key Schedule drivers for Step IV
• Hall Infrastructure:• Floor plates will be complete in Early December, 2011
• AFC moving platform is complete and being tested
• Much work to be done on South Mezzanine, but not critical to Step IV
• Liquid hydrogen system:• Mechanical, civil and electrical installation of system A is essentially
complete
• Major pre-hydrogen operation safety review on October 4th
• Went well, formal feedback expected soon
• This should be the ‘green-light’ for hydrogen testing
• Stop-press: report received yesterday – looks like it will force the Departmental ‘ownership’ of MICE issue – good news!
MICE Top-Level Project Schedule
• Step IV• Step V
• Revision date: 30th October, 2011
• Note: items in red text are key schedule drivers• Items in orange text are high risk items• Items in Green text are complete
4
STEP IV
Subsystem DateSpectrometer solenoid #1 + #2 June’12Fibre tracker #1 + #2 ReadyFocus coil #1 Feb’12
LH2 system A Dec ‘11
Solid absorber(s) June ‘12Liquid absorber ReadyDiffuser Aug’12Virostek plate Feb. ‘12Substation upgrade ReadyEMR installation May’12Radiation shutter June ‘12AFC Moving platform #1 Ready
Step IV ready...Q4, 2012
STEP V
Subsystem DateStep IV data-taking complete Q1 2013Absorber Focus Coil #2 Q3 2012LH2 system B Q1 2013RF Amplifiers Q3 2013RF Infrastructure Q3 2013Successful test of first CC coil Q3 2012RFCC delivery plan completeAFC Moving platform #2 Q4 2012RFCC Moving platform #1 Q4 2012ISIS Long shutdown start Aug
2014ISIS Long shutdown end Feb 2015
Step V ready...see later....
7
Milestones prepared by Alan Grant with all latest known dataOnly look at Step IV pleaseSteps V & VI cannot be predicted until RFCC delivery plan is known
MICE CM31 wrap-up Alain Blondel
MICE SCHEDULE update October 2011 V1
STEP I
STEP IV Q4 2012 and 2013
STEP V
STEP VI
aim: 2016
Run date:
EMR run Q2 2012
Comment on Step V
• First coupling magnet is a key component:• First coil has been shipped to US, test plan is taking shape• Should be tested by Summer 2012• Represents a major decision point• Cryostat and other part drawings should be ready for production readiness review
at LBNL in January 2012• Fabrication of cryostat(s) with US vendors is being explored• Discussion in early stages of sharing the MICE CC assembly somehow• A CC delivery plan, including the above points, is a vital milestone• Early guidance on the first magnet’s destination – MuCool or MICE is required
before we can plan• Until we know the above two questions, we cannot make any firm statement about
the delivery of Step V
10
Step VI
• Important news: the experiment is now approved financially to Step VI– But it has to fit within a flat-cash profile that implies an extended
timescale, for example the third FC arrives in 2017-18
– However, we have an opportunity to review the situation at the completion of Step IV and to request a more aggressive funding profile
– As with Step V, it is unwise at this point to publicise any delivery dates that we might not be able to meet
What can TD do?
• ................• Take an active part in the coupling magnet construction
• Norbert Collomb and AN are working on that plan
• It will be presented strongly at the post Step IV review
• Locally in TD, we must build local expertise in the following:• RF engineering• Electrical engineering• Accelerator engineering• Cryogenic support• This expertise has to reside at RAL in ASD/TD at Group level
somewhere
• This is an opportunity for TD to get the best out of MICE if it really wishes to
• It should complement and reinforce the PPD MICE Group
• We might like to take advantage of any local re-structuring
12