Upload
alisha-york
View
214
Download
0
Tags:
Embed Size (px)
Citation preview
1
LHC-DFBX
Fabrication Oversight Plan
Joseph Rasson
LBNL
Presented at the
DFBX Production Readiness Review
23-24 October 2002, LBNL
Brookhaven - Fermilab - Berkeley
US LHC ACCELERATOR PROJECT
2
Outline
Production Oversight Fabrication Oversight Plan Vendor Monitoring Oversight Level of Effort Change Control Procedures Summary
3
Production Oversight
Project oversight tasks: Manage fabrication activities at LBNL Manage current leads procurement Transfer GFM to cryogenic vendor Monitor fabrication, assembly and acceptance tests at
cryogenic vendor Manage Change Control Process Update engineering drawings to include as-built modifications Update Interface Specifications Manage hardware and document transfer to CERN Report status to LHC-PMO
4
Fabrication Oversight Plan
Fabrication oversight is critical to delivering a quality product on schedule
Vendor is requested to provide detailed fabrication and assembly milestones to track progress
Implement a Change Control Procedures Plan constant monitoring of vendor performance to:
Assist in resolving fabrication issues Insure that DFBX is given the appropriate scheduling priority Supervise the transfer GFM to the vendor Witness critical assembly processes Witness inspection tests Manage change control process
5
Vendor Monitoring
Frequent visits to vendor fabrication facility MTM is within a driving distance to FNAL Will consider retaining professional QA support from local
firms if PHPK wins the award LBNL representative will have unrestricted access to the
Subcontractor facility during normal working hours Subcontractor will provide office space to LBNL
representative
6
Vendor Monitoring (cont.)
Request Reports and Scheduled Meetings Post Award Conference to kick-off DFBX production Monthly Progress reports Monthly meetings at the vendor’s facility to review Progress Weekly phone or video conference meetings to review status Meetings to be attended by Subcontractor’s Project Manager
and lead engineer
7
Oversight Level of Effort
Fabrication oversight will be made up of LBNL and FNAL staff The balance between LBNL and FNAL will depend on who the
location of the vendor DFBX Project Engineer is committed to stay with project
throughout the production phase On the average 2 FTE’s are available for project management
and production oversight
8
DFBX Oversight Level of Effort
-
0.20
0.40
0.60
0.80
1.00
1.20O
ct-0
2
No
v-0
2
De
c-0
2
Jan
-03
Fe
b-0
3
Ma
r-0
3
Ap
r-0
3
Ma
y-0
3
Jun
-03
Jul-
03
Au
g-0
3
Se
p-0
3
Oct
-03
No
v-0
3
De
c-0
3
Jan
-04
Fe
b-0
4
Ma
r-0
4
Ap
r-0
4
Ma
y-0
4
Jun
-04
Jul-
04
Au
g-0
4
Se
p-0
4
Oct
-04
No
v-0
4
De
c-0
4
Jan
-05
Fe
b-0
5
Ma
r-0
5
Ap
r-0
5
Ma
y-0
5
Jun
-05
Jul-
05
Au
g-0
5
Se
p-0
5
FY2003 FY2004 FY2005
FTE
Jon Zbasnik Joseph Rasson Ray Hafalia or equivalent Peterson, Tom
9
Change Control Procedures
Established project change control procedures to manage production cost and schedule
Change Control Procedures is a supplemental document to LBNL-LHC QA Plan
Procedures apply to LBNL or vendor generated change requests Procedures insure that documents and drawings are updated and
archived in the Document Control Center Change requests that impact cost or schedule will be
communicated to the vendor by LBNL Procurement Officer Process flow charts and forms are available and being reviewed
10
LBNL Generated Changes
Engineering Design Change initiated at LBNL or FNAL
DesignChange Notice
Form submitted to DFBX Project Engineer for
approval
No furtheraction taken
Doeschange affectan in-house or
an outsidefab?
Project Engineer issues an RFI to vendor to determine
cost and/or schedule impact
Project Engineer negotiates technical issues of change
with fabrication vendor
Is costchange more than
$5k?
Project Engineer makes changes to drawings and/or specifications
Submittedto FNAL PM Office
for approval
Project Engineer requests Procurement Officer to issue contract mods (outside only)
No furtheraction taken
Revised drawings and/or specifications filed in the Document Control Center
Hardware is fabricated based on new prints and/or specifications
Accepted RejectedIn-house
Outside
>$5k
<$5k
Accepted
Rejected
11
Vendor Generated Changes (1)
Vendor identifies inconsistencies in LBNL
drawings or specifications
Vendor issues a Corrective Action Report
Project Engineer makes changes to drawings and/or specifications
Project Engineer requests Procurement Officer to issue
contract modifications
Revised drawings and/or specifications filed in the Document Control Center
Hardware is fabricated based on new prints and/or specifications
Reportreviewed by LBNL
Project Engineer forapproval
Is costchange more than
$5k?
Submittedto FNAL PM Office
for approval
AcceptedRejected >$5k
<$5k
Accepted
Rejected
No furtheraction taken
No furtheraction taken
12
Vendor Generated Changes (2)
Vendor identifies potential changes to simplify a
fabrication or assembly
Vendor issues a Deviation Request
Project Engineer makes changes to drawings and/or specifications
Project Engineer requests Procurement Officer to issue
contract modifications
Revised drawings and/or specifications filed in the Document Control Center
Hardware is fabricated based on new prints and/or specifications
Requestreviewed by LBNL
Project Engineer forapproval
Is costchange more than
$5k?
Submittedto FNAL PM Office
for approval
AcceptedRejected >$5k
<$5k
Accepted
Rejected
No furtheraction taken
No furtheraction taken
13
Vendor Generated Changes (3)
Inspected parts or assemblies do not conform to drawings
and/or specifications
Vendor issues a Nonconformance Report
Project Engineer makes changes to drawings and/or specifications
Project Engineer requests Procurement Officer to issue
contract modifications
Revised drawings and/or specifications filed in the Document Control Center
Hardware is reworked based on new prints and/or specifications
ProjectEngineer & Material
Review Board determine necessary action
Isthere a cost
impact?
Use as isScrap No
Yes
Reject and scrap parts
No furtheraction taken
Rework
Project Engineer requests Procurement Officer to issue
contract modifications
14
LBNL Design Change Notice Form
DFBX Design Change Notice Form
LHC-DFBX DCN No. DFBX-
Requester: Date: Affected Document: Short Title of Change: Description of Proposed Change: Justification for Proposed Change: Impact on Cost/Schedule: Impact on other subsystems or the Interface Specifications: Reviewed by Lead Engineer: Reviewed by Project Engineer Concurrence: Approval Date: Rejection and reason for rejection:
15
Deviation Report D e v i a t i o n R e q u e s t
L H C -D F B X P O . N o . D e v i a t i o n R e q u e s t
R o u t i n e ? U r g e n t ? E m e r g e n c y ?
D R -
D a t e : T o L B N L D F B X P r o j e c t M a n a g e r :
S u p p l i e r N a m e , A d d r e s s , P h o n e , e t c :
T y p e : M a t e r i a l ? P a r t ? S u b a s s e m b l y ? F i n a l A s s e m b l y ? P r o c e d u r e ? D e s i g n C o n f l i c t ? S p e c C o n f l i c t ? I t e m N a m e a n d S e r i a l N u m b e r
D W G # o r S p e c # Q T Y N o n c o n f o r m i n g I t e m s
D e s c r i p t i o n o f D e v i a t i o n S e e a t t a c h e d ?
R e q u i r e m e n t s V i o l a t e d S e e a t t a c h e d ?
O r i g i n a t o r
D a t e P r i n c i p a l S u p p l i e r P l a n n e r D a t e
R e m e d i a l A c t i o n / J u s t i f i c a t i o n S e e a t t a c h e d ?
C a u s e a n d C o r r e c t i v e A c t i o n S e e a t t a c h e d ?
P r i m e C o n t r a c t o r A p p r o v a l s R e c o m m e n d e d D i s p o s i t i o n A c c e p t ? R e d e s i g n ? R e j e c t ? R e p a i r ?
C o s t / S c h e d u l e I m p a c t
D a t e D a t e
L B N L A p p r o v a l s
C u s t o m e r D i s p o s i t i o n : A c c e p t R e q u e s t ? D e n y R e q u e s t ? S e e a t t a c h e d ?
16
Summary
Fabrication oversight plan has been developed and being reviewed LBNL and Fermilab will play active roles in oversight activities Change Control Procedures and forms have been developed Tailor fabrication oversight plan to vendor Changes that impact cost or schedule will be communicated to
vendor through LBNL Procurement Officer