1 For the year ending 29 February 2012 Annual results presentation 2012

Embed Size (px)

Citation preview

  • Slide 1
  • 1 For the year ending 29 February 2012 Annual results presentation 2012
  • Slide 2
  • 2
  • Slide 3
  • 3 TABLE OF CONTENTS INTRODUCTION SALIENT FEATURES SUSTAINABILITY ACHIEVEMENTS FINANCIAL REVIEW STRATEGY Short-term challenges & progress Medium to long-term strategy OPERATIONAL REVIEW Products, services & clients Competitors & value proposition Geographical footprint and key contracts RISK MANAGEMENT SEGMENTAL REVIEW ORDERBOOK & OUTLOOK CAPEX CONCLUSION
  • Slide 4
  • 4 INTRODUCTION EVERYTHING I REALLY NEED TO KNOW I LEARNED IN KINDERGARTEN Robert Fulghum
  • Slide 5
  • 5 Everything I really need to know I learned in Kindergarten This passage was written by Robert Fulghum in trying to establish a Credo by which to live and I believe it provides the means for humanity to solve the worlds problems and should form the basis of every Integrated Report. It is entitled: ALL I REALLY NEED TO KNOW I LEARNED IN KINDERGARTEN All I really need to know about how to live and what to do and how to be I learned in Kindergarten. Wisdom was not at the top of the graduate-school mountain, but there in the Sunday School sand-pile. These are the things I learned: Share everything Play fair Dont hit people Put things back where you found them Clean up your own mess
  • Slide 6
  • 6 Everything I really need to know I learned in Kindergarten Dont take things that arent yours Say youre sorry when you hurt somebody Wash your hands before you eat Flush Warm cookies and cold milk are good for you Live a balanced life learn some and think some and draw and paint and sing and dance and play and work every day some. Take a nap every afternoon When you go out into the world, watch out for traffic, hold hands and stick together Be aware of wonder.
  • Slide 7
  • 7 Everything I really need to know I learned in Kindergarten Remember that little seed in the Styrofoam cup the roots go down and the plant goes up and nobody really knows how or why, but we are all like that. Goldfish and hamsters and white mice and even the little seed in the Styrofoam cup they all die. So do we. And then remember the Dick-and- Jane books and the first word you learned the biggest word of all LOOK. Everything you need to know is in there somewhere. The Golden Rule, love, basic sanitation, ecology, politics, equality and sane living. Take any one of these items and extrapolate it into sophisticated adult terms and apply it to your family life or your work or your government or your world and it holds true and clear and firm. Think what a better world it would be if we all the whole world had cookies and milk about three oclock every afternoon and then lay down with our blankets for a nap. Or if all governments had as a basic policy to always put things back where they found them and to clean up their own mess. And it is still true no matter how old you are when you go out into the world, it is best to hold hands, stick together and LOOK. By Robert Fulghum
  • Slide 8
  • 8 SALIENT FEATURES Be aware of wonder.
  • Slide 9
  • 9 Salient Features 29 February 2012 Revenue up 30% to R1.8bn (2011:R1.4bn) EBITDA up 170% to R132.6 m (2011:R49.1m) Headline earnings up 163% to R24m (2011:R37.8m loss) HEPS up 148% to 6.2cents (2011:12.9 cents loss) PAT up 145% to R18.2m (2011:R40.8m loss) EPS up 134% to 4.7cents (2011:13.9 cents loss) Order book up 21% to R1.8b (2011:R1.45b) Operating cash increased by R66.1m to R124.2m
  • Slide 10
  • 10 Sustainability Achievements Put things back where you found them, clean up your own mess. We have had a successful return to profitability in H2 FY 2012 Our rights offer has been completed Acquisition-based debt has been settled We now have a single amalgamated operating entity Our order book has been strengthened We have expanded into Ghana and Uganda ISO 9001 accreditation has been obtained in all divisions Our LTIFR of 0.75 is significantly better than the industry norm of 1.33 Esorfranki Civils capital acquisition programme has been successfully implemented Historical loss-making contracts in all divisions have been concluded Numerous insurance claims impacting cash flows on certain projects have been resolved We have retained key staff
  • Slide 11
  • 11 FINANCIAL REVIEW 29 February 2012 Dont take things that dont belong to you.
  • Slide 12
  • 12 Statement of Financial Position Salient Features as at 29 February 2012: Feb 2011 R 000 Feb 2012 R 000 Assets Non-current assets966 1871 151 181 Current assets498 164665 288 Total assets1 464 3511 816 469 Equities and liabilities Share capital and reserves703 156937 432 Non-current liabilities195 562316 658 Current liabilities565 633562 379 Total equity and liabilities1 464 3511 816 469 Net asset value per share (cents)238,9241.5
  • Slide 13
  • 13 Statement of Financial Position Salient Features (1 March 2011 29 February 2012) Total assets PPE Cash reserves Equity
  • Slide 14
  • 14 Statement of Income Salient Features Feb 2011 R 000 %Feb 2012 R 000 Revenue1 366 43330%1 771 692 EBITDA49 066170%132 656 Profit/(loss) after tax(40 761)145%18 216 Headline earnings/(loss)(37 774)163%24 046 HEPS(12,9)148%6.2
  • Slide 15
  • 15 STRATEGY Live a balanced life learn some and think some and draw and paint and sing and dance and play and work every day some.!
  • Slide 16
  • 16 Short-Term Challenges & Progress CHALLENGE Severe slowdown in public sector infrastructure spend (large scale projects) PROGRESS Management intervention to improve profitability and synergy of divisions by focusing on cost structures, tender submissions and contract execution Expansion into Ghana and Uganda (Esorfranki Geotechnical) Private sector clients targeted and market share grown through efficient project execution, high safety standards and timeous delivery Articles published in major industry journals to enhance brand awareness CHALLENGE B-BBEE focus PROGRESS Level 4 B-BBEE certification maintained
  • Slide 17
  • 17 Short-Term Challenges & Progress CHALLENGE Price competitive environment and increasingly difficult contract terms and conditions PROGRESS Project execution capabilities improved Contract portfolio reviewed and restored to profitability by improving cost reporting standards and standardising policies and procedures across all divisions Civil plant capacity expansion (enhancing efficiency and resource optimisation) Focus on brand awareness Group operations integrated into a single entity to harness cost effectiveness and standardisation Group driven by common values, business philosophies and practices Resources rationalised to enhance shared values and cohesiveness
  • Slide 18
  • 18 Short-Term Challenges & Progress CHALLENGE Organisational development PROGRESS Succession and development plans implemented CHALLENGE The Competition Commission investigation into alleged anti-competitive behaviour in the piling and drilling markets is currently inactive after having the matter referred to a tribunal following a failed settlement offer to the Commissioner. PROGRESS The board has raised an estimated provision in the financial statements for the likely penalty. During the recent fast track settlement process offered to the construction industry Esorfranki Limited filed one marker relating to a prescribed offence Esorfranki was further mistakenly implicated in one other instance relating to Shearwater prior to acquisition Any further developments will be communicated to all stakeholders as they occur.
  • Slide 19
  • 19 Short-Term Challenges & Progress CHALLENGE Delayed payment cycles from government and main contractors PROGRESS Significant advance payments on foreign contracts secured Strict working capital management and reporting enforced Duplicate assets, including business properties realised Short-term working capital facilities secured to accommodate growth and delayed payment cycles Rights issue finalised and acquisition-based debt settled Capital asset expansion programmes secured on the back of long-term contracts, boosting price competitiveness and efficiency and plant resource expansion
  • Slide 20
  • 20 Medium to Long-Term Strategy Harness synergy within the group Expand product offering and grow market share Geographical diversity in Civils and Pipelines Environmental accreditation ISO 14001, safety accreditation ISO 18001 Securing long-term contracts to create future visibility and to underpin sustainability Focus on sustainable growth nodes within government infrastructure programmes Supply chain management will take cognisance of environmental impact and carbon emissions will be measured and managed Addressing Construction Charter requirements to improve BEE scoring by 31 December 2013 Focus on concession and development projects Focus on private sector clients to balance dependency on government contracts
  • Slide 21
  • 21 OPERATIONAL REVIEW 29 February 2012 Wash your hands before you eat flush!
  • Slide 22
  • 22 Products & Services
  • Slide 23
  • 23 Clients
  • Slide 24
  • 24 Competitors and Value Proposition Competitors
  • Slide 25
  • 25 Value Proposition
  • Slide 26
  • 26 Geographical footprint Currently working in Ghana on 3 contracts. New awards in Kenya & Uganda
  • Slide 27
  • 27 Geotechnical - Key Contracts Country & ContractDescription Angola, Kinaxixi MXD complexPhase I 1 150 soil nails, 4 200m of gunite, 310 micropiles and over 370 soldier piles. Phase II comprised the installation of up to five rows of Titan anchors, 7 500m of gunite arches and approximately 90 jet grout columns. Duration: 15 months in progress DRC, Kolwezi soil improvement project Large soil improvement project for a new copper mine processing plant. Duration 6 months: Completed Tanzania, PSPFLateral support and piling to new offices for the Public Services Pension Fund in Dar- es-Salaam Duration: 6 months - completed Botswana, Jwaneng mine cut 8A piling contract consisting of 710 straight-shafted, cast-situ auger piles ranging between 600mm 900mm in diameter and inserted to depths ranging from 16m 25m. Esorfranki also completed the dynamic compaction on the primary stockpile over an area of more than 2 000m. Duration: 10 months - completed South Africa, Argyle storm water outfall (KZN) Design and construction of a temporary jetty and coffer dam with a 5m high protection wall for the construction of the extended concrete shotgun outfall. Duration: 12 months - completed Mozambique, Beira Stacker and Quay Upgrade Deep piling to 28 metres for new coal export facility. Duration: 10 months - completed Mauritius, Dry dock in Port LouisConstruction of a diaphragm wall and piling to the floor slab of the dry dock. Duration: 12 months - completed
  • Slide 28
  • 28 Pipelines - Key Contracts Province & ContractDescription Limpopo, Mooihoek Bulk Water Supply Phase III Installation of 13km of a 660mm diameter steel pipeline. Duration: 11 months in progress Limpopo, Nebo Plateau Bulk Water Pipeline Installation of 32km of a 450mm diameter steel pipeline from Nebo to Jane Furst. Duration: 24 months - completed Gauteng, BG3Delivering water from the Vaal Dam, a distance of 8.6km, in a 3 500mm diameter steel pipe to the canal feeding Zuikerbos Pump Station. Duration: 24 months in progress KwaZulu-Natal, Nsezi Bulk Water Pipeline Installation of 4.5km of a 1 300mm diameter raw water steel pipeline. Duration: 8 months - completed Eastern Cape, Mbizana PipelineInstallation of 13km of a 500mm diameter steel pipeline from the Ludeke dam site to the Nomlaqu treatment works. Duration: 12 months - completed Eastern Cape, Milton SiphonReplacement of approximately 1.1 km of a 1 900mm diameter concrete siphon with new steel pipework. Duration: 6 months - completed
  • Slide 29
  • 29 Civils - Key Contracts Province & ContractDescription North West, Bakwena N4 Toll RoadConstruction of a second 21km carriageway along a section of the N4. Duration: 30 months in progress Mpumalanga, Kusile Power StationUnderground service ducts to completed terraces and general services pipeline Duration: 36 months in progress Gauteng, Sanral R21Upgrade of 12.8km of the R21 national route from the East Rand Mall to Pomona Road. Duration: approximately 28 months - completed Gauteng, K71/R55Phase 1 of the 6.5km R55 from the N14 to the Wierda Road (Kl03) intersection including two road-over-river bridges. Duration: 24 months - completed Final phase comprising 4.2km construction of a dual carriageway from the Kl03 intersection to Laudium and an additional two road-over-river bridges. Duration 24 months in progress Free State, WesselsbronConstruction of a 4.5 mega-litre waste water purification plant in Wesselsbron. Duration: 18 months - completed Northern Cape, KathuConstruction of a 20 mega-litre water reservoir and water tower. Duration: 18 months - completed Construction of infrastructure and housing for Bestwood development Duration 15 months in progress
  • Slide 30
  • 30 RISK MANAGEMENT When you go out into the world, watch out for traffic, hold hands and stick together!
  • Slide 31
  • 31 Matrix of Major Risks Material Risks Mitigation Dependency on government infrastructure spend Product & market diversification, Strategic B-BBEE rating & geographical diversity Working capital managementMonthly cash flow forecast, working capital facilities, tougher on debt collection & KPAs of divisional managers BEEPromotion from within & careful management of transformation process Material shortages material delivery delays Proper planning, qualifying bids, site contracts and manuals & KPAs of divisional managers Credit risk and cost reportingMonthly review at EXCO meeting, monthly review of contract financials & KPAs of divisional managers Bribery and corruptionObtain court interdicts, exposure of corruption through whistle-blowing & enforce Code of Ethics and Conduct CompetitionBuild on reputation through strong brand, be competitive in terms of price and quality, include alternative bids & in-house design Underperforming contractsImmediate identification and response, follow up with possible disciplinary action, ensure accountability, appoint the right people to the right jobs, minimise non-conforming reports & compliance reviews against policies and procedures
  • Slide 32
  • 32 Risk Management Management Contracts
  • Slide 33
  • 33 SEGMENTAL REVIEW
  • Slide 34
  • 34 Segmental Review - Geotechnical GEOTECHNICAL Feb 2011 R 000 Feb 2012 R 000 Segment revenue 706 672734 092 PBIT 18 74750 253 Segment assets 662 228722 746 No of employees 12871 191 Revenue growth (25%)4% Operating margins 3%7% Order book 332 454321 205 Pending awards 263 009150 500 Prospects 454 700468 210 Non-government 60%67% Government 40%33%
  • Slide 35
  • 35 Segmental Review - Pipelines PIPELINES Feb 2011 R 000 Feb 2012 R 000 Segment revenue 169 005227 821 PBIT (3 548) 2 234 Segment assets 87 09284 007 No of employees 434373 Revenue growth (26%) 35% Operating margins (2%) 1% Order book 264 083220 073 Pending awards 631 000260 867 Prospects 5 000 000 3 115 000 Non-government -- Government 100%
  • Slide 36
  • 36 Segmental Review - Civils CIVILS Feb 2011 R 000 Feb 2012 R 000 Segment revenue 518 787824 051 PBIT (3 113)25 377 Segment assets 454 761583 537 No of employees 1 4531 820 Revenue growth (27%)59% Operating margins(1%)3% Order book 860 267 1 215 762 Pending awards 511 5001 613 000 Prospects2 482 0003 788 500 Non-government 30%23% Government 70%77%
  • Slide 37
  • 37 ORDER BOOK AND OUTLOOK Cookies and warm milk are good for you!
  • Slide 38
  • 38 Order book as at 29 February 2012 Business Unit Order Book (R millions) Secured Revenue FY 2013 (R millions) Secured Revenue FY 2014+ (R millions) Geotechnical 32128932 Civils 1 216843373 Pipelines 22017842 Total 1 7571 310447
  • Slide 39
  • 39 Geotechnical Outlook as at 29 Feb 2012 Johannesburg Cape Town (including Ghana) Angola Durban, Mozambique, Tanzania & East Coast Mauritius
  • Slide 40
  • 40 Pipelines Outlook as at 29 Feb 2012 Current contracts Pending & potential awards Key contracts
  • Slide 41
  • 41 Civils Outlook as at 29 Feb 2012 Roads Kusile Mine work at Xstrata & Anglo Coal Current contracts rolled over from last year as at 29 Feb 2012 Building General
  • Slide 42
  • 42 Civils Outlook as at 29 Feb 2012 Roads Kusile Mine work at Anglo Coal Pending awards and targeted key contracts Building General
  • Slide 43
  • 43 General Outlook 2013FY and beyond Gautrain Private Development Spinoff Resource Arena General
  • Slide 44
  • 44 General Outlook 2013FY and beyond Energy sector Sanral & other roads Other parastatals
  • Slide 45
  • 45 CAPEX Share everything!
  • Slide 46
  • 46 Capex Segments (R 000s) Financial years 2013 Total (L+H) 2013 High (H) 2013 Low (L) 20122011 Geotechnical50 00025 000 51 10011 793 Civils328 000190 000138 000205 31717 964 Pipelines30 00015 000 6206 104 Corporate6 0004 0002 00068514 512 Total414 000234 000180 000257 72250 373 Revenue2 800 000400 0002 400 0001 727 0001 366 433
  • Slide 47
  • 47 CONCLUSION Having successfully turned the corner, we find ourselves leaner, meaner, happier, more focused and realistically bullish for the future of Esorfranki Limited and all its stakeholders! THANK YOU
  • Slide 48
  • 48 Disclaimer Forward-looking statements This presentation contains forward-looking statements that, unless otherwise indicated, reflect the companys expectations as at 29 February 2012. Actual results may differ materially from the companys expectations if known and unknown risks or uncertainties affect its business or if estimates or assumptions prove inaccurate. The company cannot guarantee that any forward-looking statement will materialise and, accordingly, readers are cautioned not to place undue reliance on these forward-looking statements. The company disclaims any intention and assumes no obligation to update or revise any forward-looking statement even if new information becomes available as a result of future events or for any other reason.
  • Slide 49
  • 49 www.esorfranki.co.za Esorfranki Limited | 30 Activia Road Activia Park Germiston 1401 PO Box 6478 Dunswart 1508 South Africa + 27 83 259 2584 +27 11 776 8700 +27 11 822 1158 [email protected] Bernie Krone| CEO + 27 84 556 2486 +27 11 776 8700 +27 11 822 1158 [email protected] Wayne van Houten| CFO