Upload
paola-yarbough
View
214
Download
1
Embed Size (px)
Citation preview
1
Engr . Jonathan U. NdiagwalukweExecutive Director (S/O), TCN
STRATEGIES FOR MITIGATING INCIDENCE OF SYSTEM COLLAPSE
By
Enugu Power Summit 11th -12th May, 2012
● Introduction
OUTLINE
2
● The Grid System
● System Frequency Management
● System Collapses in Retrospect
● System Collapse Mitigation Strategies
● Concluding Remarks
● Causes of System Collapse
● Grid Instability
● A system is an inter-related set of components that work together within an identifiable boundary, as a coherent whole, to achieve an overall goal.
INTRODUCTION
3
● In the case of a power system, when all or some of the functional components have failed as a result of perturbations,System Collapse is said to have occurred.
● The scope of failure determines whether the collapse is total or partial.
● System Operation States
INTRODUCTION (CONT’D)
4
► Normal State:
The power system operates in normal state when system
frequency and voltages are close to their nominal values.
There is adequate generation to cope with load demand. ► Alert State:
It is the state of an electric power system in which an event will result in
loss of load, stressing of system components beyond their ratings, bus
voltages and system frequency outside tolerances, cascading voltage
instability etc.
The Grid Code stipulates that the grid has to be in the normal state
at least 90% of the time, This is hardly the case with our grid
● An electric power grid is a system of power
generation plants, transmission substations and lines
interconnected in a mesh for efficient delivery of
electricity
The Grid System
5
TO SAKETE
ONITSHA
KAINJI
JEBBA/GS
JEBBA/TS
SHIRORO
Ikeja
Akure
Uyo
BirninKebbi
Minna
Kaduna
Abuja
Jos
Bauchi
Gombe
Damaturu
MaiduguriKano
IIorin
AdoEkiti
EnuguAkwa
Ibadan
Sokoto
Gusau
Katsina
Hadejia
Jalingo
Yola
Abakaliki
Calabar
JIGAWA
KANO
KATSINA
SOKOTO
ZAMFARA
KEBBI
KWARA
KADUNA
NIGER
NASSARAWA
TARABA
YOBE
PLATEAU
EBONYI
CROSSRIVER
OSUN
BAYELSA
EDO
DELTA
ONDO
OYO
IMO
ADAMAWA
BORNO
GOMBE
BAUCHI
EKITI
LAGOS
ATLANTIC OCEAN
NIGER
REPUBLICOF BENIN
REPUBLICOF CAMEROON
REPUBLICOF
CHAD
SAPELEP/ST.
DELTAPOWER ST.
OGUN
Osogbo
NIGERIA
Potiskum
Niamey
132 kV
Mambila
Bali
AFAM POWER ST.
AsabaBenin
EGBINP/ST.
Lokoja
ABUJA
AJAOKUTA
Lafia
Makurdi
MAKURDI
BENUEKOGI
ENUGU
Aliade
ABIA
AKWAIBOM
Owerri
AN AMBRA
PortHarcourt
RIVERS
Umuahia
2
2
2
22 2
2
4
3
TRANSMISSION LINE LEGEND
BULK SUPPLY POINT
HYDROELECTRIC POWER STATION
THERMAL POWER STATIONS
330 KV
H
330KV LINES (EXISTING) – MULTIPLE CIRCUITS
330KV LINES - EXISTING
2
2
2
330KV LINES (FGN) – MULTIPLE CIRCUITS
330KV LINES (PROPOSED PROJECT) – MULTIPLE CIRCUITS
330KV LINES (NIPP) – MULTIPLE CIRCUITS
330KV LINES - FGN
330KV LINES - NIPP
330KV LINES - PROPOSED PROJECT
2
Nigerian Power Grid: Existing 330KV Lines Network
ALAGBADO
Abeokuta
Olorunsogo
B1T
T4A
An electric power grid can be rendered unstable by
the following:• System faults at busbar sections or on Transmission
lines
• Loss of generation
• Loss of large loads
• Switching of large loads
A power system is therefore considered
stable if in the event of any or a
combination of the above factors, the
entire network is able to remain in
synchronism. This is hardly the case with
the Nigerian grid. Any of the above events
can throw the system out of synchronism
and result in the shutdown of the grid.
Grid Instability
7
SYSTEM FREQUENCY MANAGEMENT
8
● A nominal frequency of 50Hz is achieved when active power generation in the system equals the total demand.
● In practice, we seek to achieve this balance through manual load shedding/generation scheduling or by the appropriate application of under-frequency relays.
● The SCADA/EMS facility, through its Load Frequency Control (LFC) function, offers an automated means for frequency management.
SYSTEM COLLAPSES IN RETROSPECT
9
YEAR GENERATION TRANSMISSION
INDERTERMINATE
2000 2 9 02001 9 10 02002 19 22 02003 14 39 02004 20 32 02005 15 21 02006 8 22 02007 3 24 02008 8 32 22009 8 31 02010 9 29 42011 0 17 2
10
20002001
20022003
20042005
20062007
20082009
20102011
0
5
10
15
20
25
30
35
40
45
GENERATION TRANSMISSION INDERTERMINATE
SYSTEM COLLAPSES IN RETROSPECT………
2012 SYSTEM COLLAPSES TO DATE
SUMMARY OF MAJOR SYSTEM DISTURBANCES IN 2012
S/NoDATE/ MONTH
TYPE OF DISTURBANCE IN
THE GRID IMMIDIATE CAUSE/REMARKS
TOTAL PARTIAL
116/03/201
2X
The tripping of Benin/Onitsha 330KV line (CCT B1T) at both ends
223/03/201
2 X
(1) Explosion of the red phase CT of the primary side of 150MVA 330/132/33kV transformer at Benin TS.
325/03/201
2 X Bus Zone protective relay operation at Benin T/S
428/03/201
2X The tripping of Benin/Onitsha line (cct B1T)
502/04/201
2 X Tripping of Benin - Onitsha line (CCT B1T) at both ends.
603/04/201
2 X Tripping of Benin - Onitsha line (CCT B1T) at both ends.
712/04/201
2X
The simultaneous tripping of Benin/Onitsha 330kV line (cct B1T) and Onitsha /Alaoji 330kV line (cct T4A)
8 30/04/12
X The tripping of Onitsha/Alaoji 330kV line (cct T4A)
907/05/201
2X (1) Tripping of Jebba Units (2G1 & 3) on fault
1009/05/201
2X Indeterminate
1110/05/201
2X Indeterminate
Graphical representation of 2012 system collapses to Date
12
Transmission Generation Indeterminate0
1
2
3
4
5
6
7
8
9
No.
Causes of system collapse
System collapse can result from: • Generation• Transmission• Load Management
GENERATION:• Grossly inadequate generation• Sudden loss of generation • Absence of/or inadequate operating reserveTRANSMISSION:• Tripping of critical 330KV lines (especially the single circuit lines)• Indiscriminate operation of line protection relays• Transmission equipment failure
13
Causes of system collapse........contd.
• LOAD MANAGEMENT– Grid indiscipline - Reluctance to adhere to load
allocation– Lack of a functional SCADA/EMS system,
necessitating manual operation which is fraught with human error
14
Generation Profile (Mar’11 – April’12)
15
MONTH AVERAGE ACTUAL GEN. CAPABILITY
(MW)
PEAK GEN.(MW)
AVERAGE GEN.(MW)
MAR 2011 4450.14 3851.60 3324.62APR 2011 4627.51 3943.60 3501.11MAY 2011 4195.03 3635.90 2945.25JUN 2011 4359.04 3354.00 2790.33JUL 2011 4571.53 3607.00 2970.51AUG 2011 4421.46 3839.70 3363.06SEPT 2011 4684.33 4003.80 3352.65OCT 2011 4899.55 4054.20 3078.07NOV 2011 5039.38 3627.77 3280.36DEC 2011 4768.91 4089.30 3338.36JAN 2012 4788.26 4162.20 3531.69FEB 2012 4959.01 4086.20 3465.29MAR 2012 5171.00 3744.20 3096.49APR 2012 5338.68 3698.30 2936.67
Collapse Free Months with average Spinning Reserve of 280MW
System Collapse Mitigation Strategies
16
● Elimination of all encumbrances on all Transmission lines.
► Short Term Strategies:
● Review of the operation of Under-frequency Load Disconnection scheme.
● Procurement of additional operating reserve capability for effective frequency management.
● Timely completion of on-going SCADA/EMS reactivation project for real-time Grid management and supervisory control.● Review of the entire system protection scheme is required to ensure proper and reliable operation
● Manpower shortage in system operations is now acute needs to addressed.
System Collapse Mitigation Strategies (Cont’d)
17
● It is imperative to strengthen the Grid to satisfy N-1 reliability assessment criteria.
► Long Term Strategies:
● Increased generation is an absolute necessity for stable grid operation.
● Creation of closed loops in the network.
● Network compensating devices, such as the Static Var Compensators (SVC) should be deployed for efficient voltage control.
Nigerian Power Grid: Existing, On-going and Proposed 330KV Lines Network
TO SAKETE
ONITSHA
KAINJI
JEBBA/GS
JEBBA/TS
SHIRORO
Ikeja
Akure
Uyo
BirninKebbi
Minna
Kaduna
Abuja
Jos
Bauchi
Gombe
Damaturu
MaiduguriKano
IIorin
AdoEkiti
EnuguAkwa
Ibadan
Sokoto
Gusau
Katsina
Hadejia
Jalingo
Yola
Abakaliki
Calabar
JIGAWA
KANO
KATSINA
SOKOTO
ZAMFARA
KEBBI
KWARA
KADUNA
NIGER
NASSARAWA
TARABA
YOBE
PLATEAU
EBONYI
CROSSRIVER
OSUN
BAYELSA
EDO
DELTA
ONDO
OYO
IMO
ADAMAWA
BORNO
GOMBE
BAUCHI
EKITI
LAGOS
ATLANTIC OCEAN
NIGER
REPUBLICOF BENIN
REPUBLICOF CAMEROON
REPUBLICOF
CHAD
SAPELEP/ST.
DELTAPOWER ST.
OGUN
Osogbo
NIGERIA
Potiskum
Niamey
132 kV
Mambila
Bali
AFAM POWER ST.
AsabaBenin
EGBINP/ST.
Lokoja
ABUJA
AJAOKUTA
Lafia
Makurdi
MAKURDI
BENUEKOGI
ENUGU
Aliade
ABIA
AKWAIBOM
Owerri
AN AMBRA
PortHarcourt
RIVERS
Umuahia
2
2
2
2
2
2
2
2
2
22
2
2
2
2
2
2
2
2
2
1
11
4
22
22
2
2
2
2
2
2
2
2
2
2
22 2
2
4
3
ALAGBADO
Abeokuta2
Olorunsogo
TRANSMISSION LINE LEGEND
BULK SUPPLY POINT
HYDROELECTRIC POWER STATION
THERMAL POWER STATIONS
330 KV
H
330KV LINES (EXISTING) – MULTIPLE CIRCUITS
330KV LINES - EXISTING
2
2
2
330KV LINES (FGN) – MULTIPLE CIRCUITS
330KV LINES (PROPOSED PROJECT) – MULTIPLE CIRCUITS
330KV LINES (NIPP) – MULTIPLE CIRCUITS
330KV LINES - FGN
330KV LINES - NIPP
330KV LINES - PROPOSED PROJECT
2
CONCLUDING REMARKS
Increased Generation,expanded grid network with redundancies and functional grid management tools will launch the system into an era of stability and a collapse free operation.
19