28
1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

Embed Size (px)

Citation preview

Page 1: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

1

Decay Solenoid Report– 2nd June 2009

Decay Solenoid Status

MJD CourtholdMJ Hills

JH Rochford

Page 2: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

2

Decay Solenoid Report– 2nd June 2009

Important Fact

The Decay Solenoid now works !!

And has been tested to 5 Tesla

Page 3: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

3

Decay Solenoid Report– 2nd June 2009

Main Decay Solenoid Parameters

Parameters:

• Central field 5T

• Open inner Radius 60mm

• Coil inner Radius 65mm

• Coil length 8m

• Stored Energy 1.5MJ

• Max. Current 1000A

• Cu:NbTi ratio 3.5

• Current density 220 Amm-2

Page 4: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

4

Decay Solenoid Report– 2nd June 2009

Initial Decay Solenoid Powering Tests and Review -1

• Initial powering tests showed that the Decay Solenoid could not be powered beyond ~290 Amps, whereas 870 Amps is required for normal running at 5 Tesla.

• Investigations showed that coil #10 was always slightly ohmic, and caused the magnet to go normal at currents in excess of ~290 Amps

• Discussions with PSI revealed that essential MLI was missing from the 4.5K and 77K apertures at each end of the DS, allowing 300K radiation shine directly into the bore of the DS, which then had to pass through the coil windings before it could be removed by the cooling circuit

• Further analysis of the data and modelling confirmed the importance of the missing MLI

Page 5: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

5

Decay Solenoid Report– 2nd June 2009

Initial Decay Solenoid Powering Tests and Review -2

• Five layers of MLI were fitted over the 4.5K & 77K apertures at the DS exit-end, after which the DS was cooled-down and powering tests repeated.

• NB: The entry-end could not be treated at the same time, due to lack of access to the synchrotron vault until the ISIS shutdown in April.

• Test results confirmed that the additional MLI had fixed the problem at the exit-end, shifting the problem to the entry-end (coil #1 was still ohmic, although initial results were ambiguous, due to a data-logging error).

• The DS was reviewed on 3Mar09. The review board accepted that 300K radiation shine was the most likely cause of powering problems, and accepted the DS team’s repair plans & schedule, but remained concerned that other problems might be revealed once the identified problem had been fixed.

Page 6: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

6

Decay Solenoid Report– 2nd June 2009

Additional MLI

Additional Multi-Layer Insulation (MLI) was fitted in two locations at the exit end of the solenoid:

– Over the cold mass bore aperture (5 layers)

– Over the radiation shield aperture (5 layers)

Rad Shield MLI

Cold Mass MLI

Page 7: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

7

Decay Solenoid Report– 2nd June 2009

Additional Temperature Measurement

Page 8: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

8

Decay Solenoid Report– 2nd June 2009

Conclusions from January Tests

Quench always originated in coil 10The problem appeared to be thermal rather than an inherent

fault in the coil(s)– Measured temperatures of coil 10 (~7K), the iron tube (8-9K)

and the iron endplate (11-12K) were high – even before powering.

– Raising the temperature of the iron reduced the current needed to cause a quench - i.e the temperature margin of the superconductor had been reduced.

– The exit temperature of the coil cooling circuits was higher than seen at PSI for the same flow, suggesting a greater than expected heat load on the coils.

No evidence of a thermal stability problem– Temperatures all remained stable until after onset of quench– There was no indication of a blockage – the measured flow was

consistent with that measured at PSI

Page 9: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

9

Decay Solenoid Report– 2nd June 2009

Measured heat loads

•From the enthalpy of the fluid and the flow we calculated the measured heats loads on the system. •Flow is only measured into the magnet. Flow out is assumed to be the same as flow in, but this might not be true if the liquid level in the cryostat is fluctuating. Filling the cryostat may also contribute to the unaccounted for heat loads.•The flow meter measurement is limited to mass flows below 5g/s.

Page 10: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

10

Decay Solenoid Report– 2nd June 2009

Comparison of Measured Heat Loads

  T (K) P(b) Ent' In J/g T (K) P(b) Ent out j/g Flow g/s watts

Iron yoke TI2=4.39 PI2=7.95 3.4 TI3=4.67 PI3=7.82 4.4 5.0 5.0

Coils 1-5 TI2=4.39 PI4=7.49 3.2 TI5=4.68 PI5=7.07 4.1 5.0 4.5

Coils 6-10 TI2=4.39 PI3=7.82 3.3 TI4=4.78 PI4=7.49 4.6 5.0 6.5

Heater             23.0

Unaccounted for loads             2.2

complete system TI1=6.42 PI1=7.69 12.9 TI0=4.4 PI0=1.17 21.2 5.0 41.2

Before MLI

After MLI  T (K) P(b) Ent' In J/g T (K) P(b) Ent' out J/g Flow g/s watts

Iron yoke TI2=4.40 PI2=6.11 2.5 TI3=4.68 PI3=5.97 3.5 4.3 4.3

Coils 1-5 TI2=4.40 PI4=5.61 2.3 TI5=4.69 PI5=5.21 3.3 4.3 4.2

Coils 6-10 TI2=4.40 PI3=5.97 2.4 TI4=4.68 PI4=5.61 3.4 4.3 4.0

Heater             9.5

Unaccounted for loads             9.7

complete system TI1=6.36 PI1=6.04 13.5 TI0=4.42 PI0=1.18 20.9 4.3 31.7

Page 11: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

11

Decay Solenoid Report– 2nd June 2009

Radiative Load on CoilsSimplified Comsol model• Radiative exchange between

surfaces• Correct geometry exit and entry

ends• Assume simple cylindrical vessel• 3 cases

• No MLI windows• MLI windows at exit end• MLI windows at both ends

iron

Oxidised aluminium E~0.1Multi Layer Insulation (n>20)

E~0.001Glass Fibre E~0.2Conductivity of Coils worst case

assume conductivity of resin ~0.05W/mK

Vac ves, 300K, E=0.1 Rad shld, 77K, E=0.001

Coil K=0.05W/mK outer surface 4.4K heat sink Inner surface GRP tube E=0.2

Page 12: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

12

Decay Solenoid Report– 2nd June 2009

Coil peak 8.74KCoil peak 10.31K

Coil inner surface ~0.2m2

~1.1W coil 10~0.8W coil 1

Power crossing coil surfaces

No MLI windows present

Page 13: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

13

Decay Solenoid Report– 2nd June 2009

Coil peak 8.74KCoil peak 4.5K

Coil inner surface ~0.2m2

<0.1W coil 10

~0.8W coil 1

Power crossing coil surfaces

MLI windows at exit end only

Page 14: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

14

Decay Solenoid Report– 2nd June 2009

Coil peak 4.43KCoil peak 4.5K

Coil inner surface ~0.2m2

<0.014W coil 10

~0.004W coil 5

Power crossing coil surfaces

MLI windows at both ends

Page 15: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

15

Decay Solenoid Report– 2nd June 2009

Summary of Radiative Analysis

•Heat deposition in the coils due to lack of intermediate MLI windows on the 77K radiation shield would be significant.•This heat would be dissipated in the outer coils.•The predicted temperatures indicate that a significant portion of the coils would not be superconducting, or sitting very close to the critical surface.

Page 16: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

16

Decay Solenoid Report– 2nd June 2009

•Using quench data from solenoid runs• VF model of magnet can estimate Ic and Bp during runs

Superconductor margins

VF model;Peak field in conductor at nominal current - 870A is 5.1T(Consistent with PSI data)

Page 17: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

17

Decay Solenoid Report– 2nd June 2009

Margins

Jden Temp margin Temp

current Scon' winding Bp margin w.r.t 4.4K quench origin

A A/mm2 A/mm3 T % K K

300 234 47 2.3 66 ~3.4 7.8

870 680 136 5.1 17 ~1.1 5.5

1000 781 156 5.9 0 0 4.4

Page 18: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

18

Decay Solenoid Report– 2nd June 2009

Conclusions of thermal modelling•The predicted radiation loads gave temperatures that were consistent with those estimated for the temperature of the quenching conductor.

•Bit of hand waving here •for emissivities•and fitted a curve to the observed critical current in the conductor to estimate the margin

•Actual conductor data would have improved on these estimates •Strong evidence that radiative load on the coils was the culprit

Tq=Quench

estimate

1st coil to quench

Tq= Radiation

model

1st coil to quench

No windows ~8 Num 10 10.3 Num 10

One window ~8 Num 1 8.7 Num 1

Page 19: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

19

Decay Solenoid Report– 2nd June 2009

ConclusionsI. Before fitting additional MLI, source of magnet quench was clearly

coil#10.II. After fitting additional MLI, source of quench moved to coil #1 (although

an error in data-logging gave ambiguous results at the time).III. Enthalpy calculations showed that extra MLI had reduced heat load on

cold mass, particularly coils 6-10.IV. Additional MLI had also changed temperature distribution at exit end - iron

tube was colder and heating appeared to come from within magnet bore.V. Modelling of radiative heat loads predicted a significant heat load due to

direct shine from 300K window surface.VI. Coil temperatures predicted from thermal modelling were broadly

consistent with observed currents at quench.VII. Results suggested that the magnet was not cold enough to operate at full

current, due to radiation from 300K thin windows, but other unknown heat loads could not be ruled out.

Page 20: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

20

Decay Solenoid Report– 2nd June 2009

Repairs to Decay SolenoidDuring ISIS April Shutdown

•The entry-end window was removed, and 10 layers of MLI were fitted over the 4.5K and 77K apertures.•The exit-end window was also removed, and a further 10 layers of MLI added to the 5 layers of MLI previously fitted to the 77K aperture, as 10+ layers were now considered more prudent.•The vacuum system was purged continually with dry N2 whilst the system was open, to prevent the ingress of moisture, as this had previously created significant problems when pumping down the insulating vacuum.

Page 21: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

21

Decay Solenoid Report– 2nd June 2009

Additional Task Performed Whilst Decay Solenoid Open

•Two turbo-pump stacks fitted to Decay Solenoid vacuum system via electro-pneumatically operated gate-valves

• Water-vapour had been difficult to remove with previous pumping system via long DN40 hoses

• The two identical pumping systems, with short DN100 pipe-work, are now very efficient, and can individually pump down the system in less than 24 hours

• Access to the restricted DSA is an issue• The twin systems are now remotely controlled, and provide full

redundancy in the event of malfunction

Page 22: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

22

Decay Solenoid Report– 2nd June 2009

Rerun of Powering Testsand Analysis

•Rerun of powering tests• It was necessary to perform these tests initially with Quench Detector

active, but its action disabled, as in previous tests, up to ~300 Amps.•Investigation of Quench Detector issues

• Quench Detector is a modular design, so it was possible to check the individual comparator and relay boards by substitution.

• By elimination, it was discovered that all QD problems (during closure of PSU circuit-breakers, and during ramping) were due to a broken wire in the internal cable loom, which was repaired.

• During testing it was found that the QD PSU and Battery Backup PSU create significant quantities of noise, suggesting that the PSUs are in need of refurbishment.

•Rerun of powering tests following QD repairs• Powering tests were repeated without an further issues, and with the

QD fully active.• The Decay Solenoid was powered to 870 Amps for one hour, and

briefly to 900 Amps.

Page 23: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

23

Decay Solenoid Report– 2nd June 2009

Issues: open / in hand / closed

Mechanical

•Significant leak in transfer line at turret.•Fit strain-relieving collar around transfer line, with load taken by neighbouring support column (following slide).•A strengthening collar may also be necessary.•If leak persists it will be necessary to replace existing vacuum flange with a more substantial one.

•Smaller leaks in Decay Solenoid insulating vacuum.•Live with these.

•Vacuum system upgrade.•Complete

Page 24: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

24

Decay Solenoid Report– 2nd June 2009

Issues: open / in hand / closed

Page 25: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

25

Decay Solenoid Report– 2nd June 2009

Issues: open / in hand / closedOperational

•Refrigerator transition at 60K still an issue•Some work required on control system. Linde to attend and analyse next cool-down in July, and complete the implementation of a fully automatic & reliable control program, including recovery from interruptions. Linde requested this visit, and I would anticipate them bearing the cost

•Quench system now functioning normally, but refurbishment or replacement is required to ensure future reliability.

•DL staff are addressing this issue.•Aim is to make system almost turnkey and increase the number of experienced operators. Reconsider the consequences of having separated the DS control from the refrigerator control

•Need to produce comprehensive documentation, and identify operators.

Page 26: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

26

Decay Solenoid Report– 2nd June 2009

Typical cool-down - with interventionstill some issues around 60K, when refrigerator goes into

normal operation, that require addressing

Page 27: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

27

Decay Solenoid Report– 2nd June 2009Typical cool-down - without intervention

improved control required for radiation shields – presently very sensitive to mass flow variations into cold mass

Page 28: 1 Decay Solenoid Report– 2 nd June 2009 Decay Solenoid Status MJD Courthold MJ Hills JH Rochford

28

Decay Solenoid Report– 2nd June 2009

Issues: open / in hand / closedFinal testing phase

•The Decay Solenoid will be cooled down in the presence of Linde•This is aniticipated to take longer than usual, due to potential interruptions by Linde.

•Linde will consider modifications to the control programme whilst powering tests are under way.•The DS will be powered to 5 Tesla, and soak-tested for at least 24 hours.•The DS must be signed off by 7/8/09, in order to allow the TB to make the final decision to remove the synchrotron-hall beam-stop.•The DS will be warmed up, to allow Linde to implement final modifications to the control programme, and then retest the cool-down process.