1 BROOKHAVEN SCIENCE ASSOCIATES

Ring Building Overview

Marty Fallier, Conventional Facilities DirectorASAC Meeting July 18, 2008

Page 2: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

2 BROOKHAVEN SCIENCE ASSOCIATES

Outline

• Design & Construction Approach• Site Plan • Ring Building Design

• Overall Floor Plan• Architectural Program• Building Section• Injection Building• RF Building• Accommodating Long Beamlines

• Utilities

Page 3: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

3 BROOKHAVEN SCIENCE ASSOCIATES

Design & Construction Approach

• Design is by HDR Architects & Engineers• Vibration and Acoustic Consultant – Colin Gordon Associates• Cost Estimating Consultant – VJ Associates• Geotechnical Consultants – GEI Associates• Fire Protection Consultant – NIKA Technologies

• Design Phase Construction Management - LiRo/Gilbane• Construction Management will be by NSLS-II Team• Construction will be competitive Lump-sum contracts to general

contractors (see construction package list)• Main Ring Building Contract out for bid – 9/26/08• Start Construction – Spring 09• Turnover Ring Bldg to ASD – 2/11 thru 4/12

Page 4: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

4 BROOKHAVEN SCIENCE ASSOCIATES

Construction Packages & InterfacesConstruction Package Purpose Interface

Site Preparation

Prepares site for Ring Building contractor, isolates & reroutes utilities, clears trees, closes monitoring wells, verifies no environmental liabilities

Will be done prior to start of Ring Building Contract

Ring Building Main contract, provides all buildings and on-site utilities

Interfaces to all packages except CHW Plant

Electrical Substation & PowerIncreases capacity of BNL substation for NSLS II, brings 20 MW at 13.8 kV to site

Connect to power 13.8kV at construction site boundary

Chilled Water PipingBrings Central Chilled Water piping to construction site boundary

Connect to chilled water at construction site boundary

Chilled Water Plant ExpansionExpands capacity of Central Chilled Water Plant

No interface with Ring Building Contract

Future Lab Office BuildingsProvides lab and office space for research teams and staff

Added to exterior of Ring Building at each Pentant after Pentant is accepted from Ring Building contractor FY 2012-13

Page 5: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

5 BROOKHAVEN SCIENCE ASSOCIATES

NSLS II Siteplan

Vehicle Access Tunnel

Possible JPSI Locations

NSLS

CFN

Injection Bldg

NSLS II

Service Bldgs (1 of 5)

CHW Plant

Bldg 603 Substation

Future LOB’s & Parking

RF Bldg

HDR Preparing new graphicPaving in Base Scope

Future Paving (w/LOB’s)

LOB’s in Base Scope (2nd pkg)

Page 6: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

6 BROOKHAVEN SCIENCE ASSOCIATES

Ring Building Overview

Page 7: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

7 BROOKHAVEN SCIENCE ASSOCIATES

View of Entry Lobby

Page 8: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

8 BROOKHAVEN SCIENCE ASSOCIATES

Key Performance Parameters

• Designed to achieve key CF-Accelerator Parameters• Storage Ring Tunnel vibration• Storage Ring Tunnel temperature stability• Primary Process DI Water load and temperature stability• Process Chilled Water load and temperature stability• Provide supporting utilities & required capacities

– Electrical– Chilled water– LN2 & GN2– Potable Water & Fire Protection– Data and Communication

• Assure overall beam availability >95%

Page 9: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

9 BROOKHAVEN SCIENCE ASSOCIATES

Overall Floor Plan

Storage Ring & Booster Tunnel

Experimental Floor

Access Corridor

Service Buildings

LOB’s 1, 5, & 4 Base Scope

Future LOB’s

Earth Berm

RF

Injection

Lobby

LOB 1

Vehicle Tunnel

LOB

5

LOB 4LOB 3

LOB 2

Process Cooling Water Bldg

Page 10: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

10 BROOKHAVEN SCIENCE ASSOCIATES

Ring Building Section

Page 11: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

11 BROOKHAVEN SCIENCE ASSOCIATES

Injection Building

Page 12: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

12 BROOKHAVEN SCIENCE ASSOCIATES

RF Building

Page 13: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

13 BROOKHAVEN SCIENCE ASSOCIATES

By-pass Corridor

By-pass Corridor

Extended Experimental Floor

Std Access Corridor

Stair, ADA Lift and Material Lift

Ramp

Page 14: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

14 BROOKHAVEN SCIENCE ASSOCIATES

Section Through Access Corridor at Beamline

Section Through Corridor At Beamline

2’-6”

7’-1”

Beam Tube

Page 15: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

15 BROOKHAVEN SCIENCE ASSOCIATES

Overall Utilities Plan

Page 16: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

16 BROOKHAVEN SCIENCE ASSOCIATES

Central Process DI Water Plant

Tower Water Treatment Area

Process DI Water Treatment Area

Process DI Water Supply & Return

Process DI Water Pumps

Cooling Tower Pumps

Chilled Water Supply & Return

Page 17: 1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008

17 BROOKHAVEN SCIENCE ASSOCIATES

Summary

• CF & ASD effectively coordinating requirements to assure design meets performance goals• Regular & frequent coordination meetings• Active ASD interaction with CF A/E (HDR)

• CF design on track for completion in late August to support bid and award for Spring 09 construction start

• Development of detailed commissioning plan for CF facilities to enable hand-off for ASD installation & commissioning is underway (CFAC Recommendation)