Upload
darren-james
View
213
Download
0
Tags:
Embed Size (px)
Citation preview
1
ATLAS TileCal Production at UIUC
Maggie Geppert, UIUC
Dr. Steven Errede, project head
July 9th, 2001
2
Overview
• Project Background
• Submodule Production
• Photomultiplier Tube (PMT) Testing
• What’s Next
3
Overview of ATLAS
• Located at Cern in Switzerland, ATLAS will be largest Particle Accelerator in the World
• Five Stories Tall
• Accelerates Protons to 7 trillion eV
• Scheduled to be Completed in 2005
4
Submodule Production
• Submodules are the framework of the detector.
• Hold the detector plates that glow in the presence of radiation from subatomic particles.
5
Submodule Production
• Seven easy steps to a submodule– Washing spacers and masters
– Sanding and drying
– Gluing
– Welding
– Measuring
– Painting
– Banding
7
Photomultiplier Tubes (PMT’s)
• Signals from the detector array are amplified using PMT’s
• Currently testing 3,000 of the 10,000 to be used in ATLAS
• Run the tubes through a series of computer programs
• Right now finishing STEP 1– DC light used during testing process
8
What do We Test?
• Drift– The % change in current over ~30 hrs
– Not to be greater than +/- 2%
• Dark Current– Current through tubes when light isn’t on
– must be < 2 nAmps at 800 Volts
– must be < 4 nAmps at 900 Volts
• These are the 2 most important factors
9
Testing
• Problem– Systematic increase in the Drift of all tubes, including
the reference tubes
• Solution– Look for external causes for the problem
– Check testing setup for flaws in circuits or fiber-optic cable
10
First Look
• Looked at temperature, humidity, and other external factors– Little correlation
Change in Drift vs. Change in Humidity
-3
-2
-1
0
1
2
3
-10 0 10 20 30
Change in Drift
Ch
an
ge
in
Hu
mid
ity
delta #1
delta #2
delta #3
delta #4
Change in Drift vs. Change in Temperature
-3
-2
-1
0
1
2
3
-1.5 -1 -0.5 0 0.5 1 1.5
Change in Temperature (C)
Ch
an
ge
in
Dri
ft
delta #1
delta #2
delta #3
delta #4
11
Next Steps
• Check hardware for internal problems– Currently running diagnostic tests
– Then change the circuit setup in the light source
• After problem is fixed, run STEP 2 tests– Use pulsed light to test PMT’s
• Continue Submodule Production
12
Questions?
• Contact me– [email protected]
• Contact Dr. Errede– 435 Loomis Lab
• UIUC ATLAS Website– http://www.hep.uiuc.edu/atlas/