27-Apr-2004 AstroGrid Consortium Meeting - PL talk 1
Agenda Tuesday
status review / goals / scienceLunch + AGLIItn-05 reviewDinner at Coton 20.00 (share rides)
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 2
Agenda Wednesday
0900 start Deployment, ArchitectureEGSO and AVO talksItn 06/07 plansBreakouts (Presntn, Data, Integn)1300 lunch1400 breakout reports1600 close
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 3
Goals for this meeting
understand progress to datescope to completionItn-06 plans
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 7
Where are we ?
16 months into Phase Busing 23ish FTEsspent 2.7M (three-quarters of budget)
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 8
achievements : research
political visibilitytechnology evaluationseveral impressive reportscontributions to standards
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 9
achievements : engineering
bulk of engine room components portal, myspace, community, data access, workflow most of these being done by no other VO projects
contributions to working demossome released software
but few toolsand integration hard
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 10
achievements : deployment
no real data deploymentprimitive working systemno users
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 11
news
new Finance Officer (John Pye)Astrogrid2 funded SSVO joined forces Total AG2+ = 4.0M 2005-2007
VOTECH proposal submitted to FP6 may fund +6 staff
AVO demo January : first science
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 12
AstroGrid-2 plans
Design study underway : May 15Project Plan : early JunePPARC review : July-August ?Design Reference Architecture : OctoberStart : Jan 2005
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 14
the eightfold path
develop standards for data, metadata, data exchange and provenancedevelop a software infrastructure for data servicesestablish a physical grid of resources construct and maintain a Service and Resource Registryimplement a working VO system of real scientific use to astronomersprovide a user interface to that VO systemprovide or adapt a set of science user tools to work with the VOestablish a leading position for the UK in VO work
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 15
progress (1-4)
develop standards for data, metadata, data exchange and provenanceon track through IVOA
develop a software infrastructure for data servicesgood progress
establish a physical grid of resources hardly started; needs DC co-operation
construct and maintain a Service and Resource Registrygood progress
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 16
progress (5-8)
implement a working VO system of real scientific use to astronomersnot seriously attempted yet
provide a user interface to that VO systembasic technical components : gooduser friendly skin : thou jesteth
provide or adapt a set of science user tools to work with the VOprovide : officially abandoned due to lack of resourceadapt : good progress
establish a leading position for the UK in VO workexcellent but could still go backwards !
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 18
Delivery Philosophy
AstroGrid-1 will deliverAstroGrid-2 is not an excuse not a continuous programme
Descope if necessary : NOW
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 19
Key tasks
finish componentspush IVOA standardsdeploy to UK data centres (July)deploy to AVO (Jan)publicise worldwide
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 20
components
nothing newintegratemake robust and easy to installdocument
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 21
Two Projects
AstroGrid-A : 70% done generic VO s/w suite contributions to standards programme
AstroGrid-B : 10% done working implementation for UK
astronomers physical grid of resources
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 22
Deploymentcan't wait for Itn-08 : start nowneed to work with Data Centresneeds real data, real machinesneeds stable s/wneeds different mentality
special WGuse Itn-05 software
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 23
Releases
distinguish types of release internal s/w suite releases : I external s/w suite releases : E physical deployments : D
AGSAG see only D-typesworld VO projects see E-typesdata centres see E-types
27-Apr-2004 AstroGrid Consortium Meeting - PL talk 24
Whats involved ?
code tidyingcomponent installation at DCsweb page design and build no new portal technology
real data : DCA installationreal machines : provided by DCsnetwork tuningtool integrationdocumentation and user guide