162
SPECIFICATION 0803 HYDRAULIC SERVICES for UQ ADVANCED ENGINEERING BUILDING AEB

0803 Hydraulic Services Specification-Construction Issue

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

SPECIFICATION

0803 HYDRAULIC SERVICES

for

UQ ADVANCED ENGINEERING BUILDING

AEB

0803 – HYDRAULIC SERVICES March 2011 AEB Construction Issue

THIS PAGE NOT USED

Document Status Record - Page 1

DOCUMENT STATUS RECORD

This sheet records the Revision Code and Date Approval of the document.

For convenience, the nature of the revision is briefly noted under „remarks‟, but these remarks are not part of the document.

Revision Code

Date Revised

Section / Page Revised plus any remarks

P1 12/10/10 Preliminary

P2 05/11/10 Preliminary – QS Issue

P3 11/11/10 Preliminary – Pre Tender Issue

A 6/12/10 Tender Issue

1 15/3/11 Construction Issue

Advanced Engineering Building Hydraulic Services

Hydraulic Specification – Preface

Preface- Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue C

onst

ructio

n

PREFACE

P.1 STATUS

a) This Preface to the Hydraulic Services Specification is provided to assist tenderers gain an appreciation of the specification structure, objectives and expectations of the Sub-Contractor.

P.2 SCOPE

a) This Specification details the engineering and quality assurance requirements for the supply, installation, testing, commissioning, and placing into service, maintenance and warranty of the Hydraulic Services installation for the project.

b) The scope is set out in “Section 2 – Description and Extent of Works” and includes the extent of works, interfacing and co-ordination with other trades and services.

P.3 CONTRACT/SUB-CONTRACT CONDITIONS

a) This Specification does not include any details of the form or conditions of contract/sub-contract.

b) Determine the applicable contract conditions to The Works and make all due allowance.

P.4 CONDITIONS OF TENDERING

a) Refer to the Invitation to Tender and Tender Documentation for tender requirements and make all due allowance.

P.5 SPECIFICATION OBJECTIVES

a) The intent of this Specification is to:

I. Define the extent of works including interfacing and co-ordination to be provided by the Hydraulic Sub-Contractor.

II. Define the scope of services including project management, installation engineering, testing commissioning, maintenance and documentation to be provided by the Hydraulic Sub-Contractor.

III. Specify the technical requirements of the Hydraulic Installation.

IV. Provide documentation required by Authorities to demonstrate design compliance with statutory requirements and for issue of relevant Building Permits.

V. Specify design and installation requirements against which compliance can be assessed.

VI. Provide a basis for competitive tendering for suitably qualified tenderers.

a) The Specification relies upon the Hydraulic Sub-Contractor having the necessary resources to complete the detailed design, testing and commissioning of the installation in accordance with the design intent and the requirements of the specification.

P.6 NOMINATED SPECIALIST SERVICE PROVIDERS

The following specialist suppliers and firms have been nominated for aspects of the works as follows:

Siphonic Drainage Company: Syfon Systems

Contact Details: Chris Blake (07 – 3208 7500)

Concrete Curing Bath Company: Geo-Con Products Pty Ltd

Advanced Engineering Building Hydraulic Services

Hydraulic Specification – Preface

Preface- Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue C

onst

ructio

n

Contact Details: Russell Barry (07 – 3265 4952)

Advanced Engineering Building Hydraulic Services

Hydraulic Specification– Table of Contents

Table of Contents- Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

DOCUMENT STATUS RECORD 1

PREFACE 1

PROJECT INFORMATION 1 1.

1.1 GENERAL INFORMATION 1 1.2 ROLES, OBJECTIVES & EXPECTATIONS 2 1.3 ASSOCIATED DOCUMENTS 3 1.4 ALTERNATIVE PRODUCTS 4 1.5 REQUIRED SUBMISSIONS 5 1.6 TECHNICAL DATA SUBMISSIONS 8 1.7 SAMPLES FOR REVIEW 8 1.8 QUALITY ASSURANCE 9

DESCRIPTION AND EXTENT OF WORKS 1 2.

2.1 EXTENT OF WORKS 1 2.2 ASSOCIATED WORKS 3 2.3 PERFORATIONS IN STRUCTURE 5

DESIGN AND COMPLETION CRITERIA 1 3.

3.1 DESIGN CRITERIA 1 3.2 CERTIFICATION 4 3.3 ACCEPTANCE CRITERIA 4

SERVICES INFRASTRUCTURE 1 4.

4.1 HOUSE DRAINAGE 1 4.2 WATER 1 4.3 STORMWATER 1 4.4 NATURAL GAS 1

SANITARY DRAINAGE SYSTEMS 1 5.

5.1 GENERALLY 1 5.2 SANITARY DRAINAGE CONNECTION 1 5.3 MATERIALS 1 5.4 EXCAVATION 1 5.5 BACKFILLING 1 5.6 GRADIENTS 1 5.7 FILLED GROUND 1 5.8 OVERFLOW GULLY 2 5.9 TESTING 2 5.10 ACCESS / INSPECTION PITS 2 5.11 CLEAR OUTS / INSPECTION OPENINGS 2 5.12 PIPELAYING 2 5.13 CONCRETE ENCASING 2 5.14 REFLUX VALVES 2 5.15 BASKET TRAPS 2 5.16 BEDDING MATERIALS 2 5.17 USE OF CONCRETE 3 5.18 GREASE ARRESTOR 3

Advanced Engineering Building Hydraulic Services

Hydraulic Specification– Table of Contents

Table of Contents- Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

5.19 GENERAL PURPOSE PIT 3 5.20 SEWER PUMPOUT PIT SUCTION PIPELINE 3 5.21 SEWER PUMPS 3

SANITARY PLUMBING SYSTEM 1 6.

6.1 GENERALLY 1 6.2 SUPPORTING AND FIXING PIPES 1 6.3 FIXTURE TRAPS 1 6.4 VENT PIPES 1 6.5 INSPECTION OPENINGS & GATES 1 6.6 JOINTS 2 6.7 EXPANSION JOINTS 2 6.8 BRANCHES 2 6.9 OFFSETS 2 6.10 TRAPS 2 6.11 PAN COLLARS 2 6.12 TUNDISHES 2 6.13 TESTING 2 6.14 FIRE STOPPING / FIRE STOP COLLARS 2 6.15 FLOOR WASTES 2 6.16 THERMAL INSULATION 3

STORMWATER DRAINAGE & DOWNPIPE SYSTEMS 1 7.

7.1 GENERALLY 1 7.2 STORMWATER CONNECTION 1 7.3 MATERIALS 1 7.4 EXCAVATION 1 7.5 BACK-FILLING 1 7.6 GRADIENTS 1 7.7 FILLED GROUND 1 7.8 TESTING 1 7.9 ACCESS / INSPECTION PITS 2 7.10 GRATINGS AND OUTLETS 2 7.11 PLANTERS 2 7.12 PIPE LAYING 2 7.13 CONCRETE ENCASING 2 7.14 SAND FOR BEDDING 2 7.15 USE OF CONCRETE 2 7.16 SUB SOIL DRAINS 2 7.17 PITS 3 7.18 ROOF OUTLETS 3 7.19 DRAINAGE TURN UPS (D.T.U.) 3 7.20 DOWNPIPES 3

DOWNPIPES AND OVERFLOWS 1 8.

8.1 GENERALLY 1 8.2 PIPEWORK 1 8.3 PIPE JOINTING 1 8.4 RAINWATER OUTLET 1 8.5 TESTING 1

Advanced Engineering Building Hydraulic Services

Hydraulic Specification– Table of Contents

Table of Contents- Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

8.6 BRANCHES 1

SIPHONIC DRAINAGE SYSTEM 1 9.

9.1 GENERAL 1 9.2 DESIGN 1 9.3 OUTLETS 1 9.4 PIPES AND FITTINGS 2 9.5 INSTALLATION 2 9.6 WARRANTY 3 9.7 TESTING PROCEDURE 3 9.8 MAINTENANCE 3

DOMESTIC COLD WATER SYSTEMS 1 10.

10.1 GENERALLY 1 10.2 WATER MAIN CONNECTION 1 10.3 VALVES (IN-LINE) 1 10.4 CONNECTION TO FIXTURES 1 10.5 THRUST BLOCKS 1 10.6 TESTING 1 10.7 TAPS AND FAUCETS 1 10.8 FLUSHING & CLEANING OF WATER SUPPLY SERVICES 2 10.9 BACKFLOW PREVENTION 2 10.10 HOSE TAPS 2 10.11 FIRE SPRINKLER SUPPLY 2

DOMESTIC HOT WATER & WARM WATER SERVICES 1 11.

11.1 GENERALLY 1 11.2 TESTING 1 11.3 CONNECTIONS TO FIXTURES 1 11.4 CONTROL VALVES 1 11.5 EXPANSION AND CONTRACTION 1 11.6 VALVES 1 11.7 THERMOSTATIC MIXING VALVE 1 11.8 HOT WATER HEATERS 2 11.9 HOT WATER CIRCULATING PUMP 2 11.10 THERMAL INSULATION 2

NATURAL GAS 1 12.

12.1 GENERALLY 1 12.2 AUTHORITIES‟ APPROVALS 1 12.3 INSPECTION 1 12.4 GAS SERVICE SYSTEM 1 12.5 MATERIALS 1 12.6 REGULATORS 1 12.7 TESTING 1 12.8 COMPLETION 2 12.9 ACCESSIBILITY 2 12.10 INSTALLATION 2 12.11 GAS – SYSTEMS SHUT OFF 2 12.12 CONNECTION TO GAS HEATERS, APPLIANCES, EQUIPMENT AND OUTLETS 2

Advanced Engineering Building Hydraulic Services

Hydraulic Specification– Table of Contents

Table of Contents- Page 4

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

12.13 UNDERGROUND INSTALLATION 3 12.14 VALVE BOXES 3 12.15 PIPING 3 12.16 PITS 3

FIRE HYDRANT SERVICE 1 13.

13.1 GENERALLY 1 13.2 FIRE BRIGADE BOOSTER CONNECTION 1 13.3 INTERNAL HYDRANTS 1 13.4 EXTERNAL FIRE HYDRANTS 1 13.5 MATERIALS 2 13.6 TESTING OF PIPEWORK 2 13.7 TEMPORARY FIRE PROTECTION (DURING CONSTRUCTION) 2 13.8 THRUST BLOCKS 2 13.9 VALVES 2 13.10 FIRE HYDRANT TEST DRAIN 2

HOSE REEL SERVICE 1 14.

14.1 GENERALLY 1 14.2 MATERIALS 1 14.3 FIRE HOSE REELS 1

RAINWATER RE-USE SYSTEM 1 15.

15.1 GENERALLY 1 15.2 TESTING 1 15.3 CONNECTIONS TO FIXTURES 1 15.4 EXPANSION AND CONTRACTION 1 15.5 MATERIALS 1 15.6 VALVES 1

HYDRAULIC LABORATORY FLUME RETICULATION AND PUMPS 2 16.

16.1 GENERALLY 2 16.2 MATERIALS 2 16.3 TESTING 2 16.4 VALVES 3 16.5 IDENTIFICATION OF PIPEWORK 3 16.6 HEADER TANK LINING 3 16.7 PUMP CONTROL PHILOSOPHY 3

CONCRETE CURING LABORATORY 4 17.

17.1 GENERALLY 4 17.2 INSTALLATION 4 17.3 PROCUREMENT 4 17.4 SCHEDULE OF EQUIPMENT 4

REVERSE OSMOSIS WATER SYSTEM 5 18.

18.1 GENERALLY 5 18.2 WATER CONNECTIONS 5 18.3 WATER METERS 5

Advanced Engineering Building Hydraulic Services

Hydraulic Specification– Table of Contents

Table of Contents- Page 5

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

18.4 PIPEWORK 5 18.5 VALVES (IN-LINE) 5 18.6 CONNECTION TO FIXTURES 5 18.7 TESTING 5 18.8 TAPS & FAUCETS 5 18.9 FLUSHING & CLEANING OF REVERSE OSMOSIS WATER SUPPLY SERVICES 6 18.10 SANITATION 6 18.11 REVERSE OSMOSIS PLANT 6 18.12 SYSTEMS 7 18.13 MONITORING 7

HYDRAULIC SERVICES GENERAL CONDITIONS 8 19.

19.1 PROTECTION OF PLANT AND MATERIALS 8 19.2 CO-ORDINATION 8 19.3 NUISANCE 8 19.4 MAKING GOOD 8 19.5 DIMENSIONS ON SITE 8 19.6 PROTECTION OF PROPERTY 8 19.7 DAMAGE TO FINISHES 9 19.8 TESTS 9 19.9 OCCUPATION 11 19.10 NOTICE OF PRACTICAL COMPLETION 11 19.11 FIXTURE AND FIXTURE POINTS 11 19.12 PIPES IN SLAB 11 19.13 SETTING OUT 11 19.14 CLEANING UP AND FINISHING 13 19.15 GENERAL PIPING INSTALLATION REQUIREMENTS 13 19.16 SUPPORT AND FIXING OF PIPEWORK 13 19.17 BUILDING EXPANSION JOINTS 14 19.18 JOINTS IN COPPER PIPING 14 19.19 CHASING AND DRILLING 14 19.20 CONCEALING 15 19.21 GRADES 15 19.22 COVER PLATES 15 19.23 CAPPING OFF 15 19.24 FIRE RATING 16 19.25 CLEANING OUT OF PIPING 16 19.26 CHROME PLATING 16 19.27 PREFABRICATION 16 19.28 CORROSION PROTECTION 16 19.29 SETTING TO WORK 16 19.30 NOISE AND VIBRATION 17 19.31 INSPECTION OPENINGS 17 19.32 IDENTIFICATION 17 19.33 EXISTING SERVICES 17 19.34 DEMOLITION OF SERVICES 18 19.35 REDUNDANT SERVICES EXTERNAL TO PROPERTY 18

REFERENCED DOCUMENTS 1 20.

EXCAVATION 1 21.

Advanced Engineering Building Hydraulic Services

Hydraulic Specification– Table of Contents

Table of Contents- Page 6

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

21.1 GENERAL 1

MATERIALS 1 22.

22.1 MATERIALS AND WORKMANSHIP 1 22.2 SAMPLES 1 22.3 CONCRETE 1 22.4 COVERS AND FRAMES 1 22.5 TRENCH GRATES AND SUMPS 2 22.6 PAINTS AND SEALANTS 2 22.7 FIXINGS 4 22.8 FLEXIBLE CONNECTIONS 4 22.9 FLANGES 4 22.10 GALVANISING 4 22.11 UNIONS 4 22.12 VALVES 4 22.13 BUTTERFLY VALVES 5 22.14 REFLUX VALVES 5 22.15 BALANCING VALVES 5 22.16 PRESSURE LIMITING / REDUCING VALVES 5 22.17 BALL VALVES 5 22.18 THERMOSTATIC MIXING VALVES 5 22.19 SLUICE VALVES 5 22.20 STRAINERS 6 22.21 COPPER AND BRASS TUBES AND FITTINGS 6 22.22 CAST IRON PIPES AND FITTINGS 6 22.23 FIBRE REINFORCED CEMENT PIPES 6 22.24 CONCRETE PIPES 6 22.25 VITRIFIED CLAY PIPES 6 22.26 UPVC AND PVC PIPES AND FITTINGS 6 22.27 HDPE PIPES AND FITTINGS 7 22.28 POLYPROPYLENE PIPES AND FITTINGS 7 22.29 JOINTING MATERIALS 7 22.30 EXPANSION 8 22.31 TEMPERATURE GAUGES 8 22.32 PRESSURE GAUGES 8 22.33 INSULATION MATERIALS 8 22.34 HOSE REELS 9 22.35 HYDRANT LANDING VALVES 9 22.36 HYDRANT BOOSTER ASSEMBLY 9 22.37 ACOUSTIC TREATMENT TO PIPEWORK 10 22.38 VALVE IDENTIFICATION 10 22.39 PROTECTIVE PIPE WRAPPING/COATING 10 22.40 WARNING TAPES 10 22.41 ROOF PENETRATION FLASHINGS 10 22.42 WATER SUB METERS 11 22.43 POLYETHYLENE PIPES AND FITTINGS 11 22.44 UNPLASTICISED POLY VINYL CHLORIDE PRESSURE PIPE 11 22.45 VALVE BOXES 11 22.46 CONCRETE THRUST BLOCKS 11 22.47 BACKFLOW PREVENTION VALVES 11

Advanced Engineering Building Hydraulic Services

Hydraulic Specification– Table of Contents

Table of Contents- Page 7

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

PUMPS 1 23.

23.1 SEWAGE PUMPS 1 23.2 DUAL RAINWATER PRESSURE PUMPS 1 23.3 HOT WATER CIRCULATING PUMPS 2 23.4 HYDRAULIC LABORATORY FLUME PUMPS 2 23.5 PUMP CONTROL PANELS 3 23.6 FLEXIBLE PUMP COUPLINGS 3 23.7 PUMP MOUNTINGS 3

PIPING, VALVES AND FITTINGS 1 24.

24.1 PIPING 1 24.2 VALVES & FITTINGS 1 24.3 GAUGES & INSTRUMENT FITTINGS 3 24.4 INSTALLATION 4 24.5 TESTING OF PIPEWORK 6

NOISE AND VIBRATION 1 25.

25.1 GENERAL REQUIREMENTS 1 25.2 VIBRATION CONTROL 1 25.3 NOISE MEASUREMENTS 2 25.4 VIBRATION MEASUREMENTS 2

PAINTING AND IDENTIFICATION 1 26.

26.1 GENERAL 1 26.2 DESIGN 1 26.3 AUTHORITY STANDARDS AND CODES 1 26.4 SUBMISSIONS 1 26.5 GENERAL REQUIREMENTS 2 26.6 PAINTING 2 26.7 IDENTIFICATION AND LABELLING 2

TESTING, COMMISSIONING AND HANDOVER 1 27.

27.1 GENERAL 1 27.2 RECTIFICATION OF DEFECTS 1 27.3 PRE-COMMISSIONING PROCEDURES 1 27.4 COMMISSIONING MANAGEMENT 2 27.5 COMMISSIONING 2 27.6 CONTROLS, GAUGES AND INSTRUMENTATION 3 27.7 TEST RECORDS 4 27.8 TEST AND INSTALLATION INSTRUMENTS 4 27.9 TESTING 4 27.10 PERFORMANCE TESTS 5 27.11 COMMISSIONING AND PERFORMANCE DATA 5 27.12 HANDING OVER 5 27.13 INDEPENDENT COMMISSIONING AGENT 5 27.14 FINAL COMMISSIONING 5 27.15 POST CONTRACT DRAWINGS 6 27.16 INSTALLATION MANUALS 7 27.17 REQUIRED OPERATING INSTRUCTIONS 10

Advanced Engineering Building Hydraulic Services

Hydraulic Specification– Table of Contents

Table of Contents- Page 8

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

27.18 OWNER INSTRUCTION 10 27.19 ADDITIONAL GREEN STAR REQUIREMENTS 10

ROUTINE MAINTENANCE AND SERVICING 1 28.

28.1 SCOPE 1 28.2 MAINTENANCE AND SERVICING REQUIREMENTS 1 28.3 GENERAL REQUIREMENTS 2 28.4 PREVENTATIVE MAINTENANCE AND TESTING 3 28.5 MAINTENANCE RECORDS 3 28.6 DEFECTS, LIABILITY AND WARRANTY PERIOD 4 28.7 MAINTENANCE PROPOSAL 4 28.8 FINAL COMPLETION 4 28.9 BUILDING TUNING 4

SCHEDULES 5 29.

29.1 GENERAL 5 29.2 SCHEDULE OF EQUIPMENT 6 29.3 SCHEDULE OF VALVES 13 29.4 SCHEDULE OF STORMWATER PITS AND OUTLETS 17 29.5 SCHEDULE OF FLOOR DRAINS 20 29.6 SCHEDULE OF INSULATION 20 29.7 SCHEDULE OF WATERPROOFING 21 29.9 SCHEDULE OF PIPE MATERIALS 22 SCHEDULE OF TAPWARE AND FIXTURES 24 29.10 SCHEDULE OF BOILING WATER UNITS 27 29.11 SCHEDULE OF BMS POINTS 28

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

PROJECT INFORMATION 1.

1.1 GENERAL INFORMATION

1.1.1 Definitions

Principal / Superintendent -University of Queensland

Consulting Engineer -WSP Lincolne Scott

Architect -RKAH

Certifier -McKenzie Group

Fire Engineer -AECOM

Mechanical Engineer -WSP Lincolne Scott

Fire Protection Engineer -WSP Lincolne Scott

Electrical Engineer -Aurecon

Structural Engineer -Aurecon

Civil Engineer -Aurecon

Works -As described in Section 2

Contractor -TBA

Sub-Contractor / Installer -Successful Tenderer

1.1.2 The Project

The proposed development at the University of Queensland, St Lucia is called the Advanced Engineering Building (AEB). The building is seven storeys with levels 1 to 6 comprising of laboratory, teaching, office and research space for engineering staff and students. Level 7 is the services plantroom. Building GFA is approx 24,000m².

This project is subject to fire engineering.

1.1.3 ESD Initiatives

Forming part of the design concept, all parties of the design team including architects and builders and project management team have committed themselves to achieve a 5 Star Green Star Education (v1.0). This is both a design and as-built rating. The hydraulic sub-cotractor will have specific obligations in relation to providing written documentation as part of the A-Built submission. Items will include copies of receipt of goods, material data sheets, commissioning and testing data in an approved format. The project is also targeting 5 star NABERS.

To achieve this, a variety of items have to be fulfilled and have to be demonstrated during an assessment process by the Green Building Council of Australia (GBCA). These measures include but are not limited to the following items:

a) The inclusion of high water efficiency rated tap ware

b) The installation of water meters for all major water uses throughout the building with a link to the Building Management System.

c) Rainwater harvesting and re use of water to serve toilet flushing and irrigation requirements.

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

d) Reduction of PVC – Typically all hydraulic services related PVC materials shall be replaced with HDPE or PPR where an alternative product to PVC exists.

e) All insulation shall be free of ozone depleting gases in manufacture and composition.

f) All adhesives and sealants will be low VOC.

g) All painted services are to be painted with low VOC paints

h) Undertaking building tuning during the first 12 months of building operation

i) Preparation and implementation of commissioning in accordance with CIBSE requirements.

j) Preparation of relevant services clauses for inclusion in a Building Users Guide.

k) Undertake Principal instruction on hydraulic services operation.

l) Conform to the Contractors Waste Management plan in specifically relation to recycling.

It is within the sub - contractor‟s responsibility to comply with and achieve the abovementioned keystones, as part of the ESD initiatives.

1.2 ROLES, OBJECTIVES & EXPECTATIONS

1.2.1 Obligations of the Sub-Contractor

In writing this Specification the Principal expects and relies upon the tenderers‟ possessing specialist trade expertise necessary to complete the works in accordance with documentation.

In addition, the tenderer has the following obligations:

a) To raise in good time, issues requiring design input or clarification from the Superintendent, particularly in respect to:

I. Interpretation of the Specification or drawings.

II. Problems in complying with the Specification.

III. Omissions from the tender documents.

IV. Suggested alternatives/substitutions.

b) To allow the design verification costs of the Superintendent when suggesting alternatives and departures from the Specification.

c) To certify compliance with Contract documents, including all variation instructions, at Practical Completion as required by this Specification.

d) To comply with the Quality Assurance requirements of this document and the project contract documentation

e) To certify compliance with Authority requirements.

f) To pay all fees applicable to the works.

g) Arrange for specialist suppliers to provide on site inspections, installation supervision and commissioning.

h) To obtain all Authority permits and certificates to allow the progress of the works.

i) To provide manufacturer‟s and workshop drawings in sufficient detail to allow proper fabrication, coordination and installation of the works.

j) To provide samples and prototypes where specified.

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

1.3 ASSOCIATED DOCUMENTS

This specification is to be read in conjunction with the following documents:

a) Hydraulic service design drawings (refer schedule below)

b) Contractors staging plans detailing separable portions of work

c) Structural, architectural and other trade services drawings for coordination purposes

d) Survey Drawings

e) Civil stormwater management plan

f) All other documents forming the main contract of works

Hydraulic Drawing Number and Revision

(prefixed with BNE0911900-****)

Drawing Title

H001 Cover Sheet, Legend and Drawing Schedule

H002 Site Plan

H003 External Works

H101 Sanitary, Trade Waste and Stormwater Drainage – Level 1 (Sheet 1 of 2)

H102 Sanitary, Trade Waste and Stormwater Drainage – Level 1 (Sheet 2 of 2)

H103 Sanitary, Trade Waste and Stormwater Drainage – Level 2 (Sheet 1 of 2)

H104 Sanitary, Trade Waste and Stormwater Drainage – Level 2 (Sheet 2 of 2)

H105 Sanitary, Trade Waste and Stormwater Drainage – Level 3 (Sheet 1 of 2)

H106 Sanitary, Trade Waste and Stormwater Drainage – Level 3 (Sheet 2 of 2)

H107 Sanitary, Trade Waste and Stormwater Drainage – Level 4 (Sheet 1 of 2)

H108 Sanitary, Trade Waste and Stormwater Drainage – Level 4 (Sheet 2 of 2)

H109 Sanitary, Trade Waste and Stormwater Drainage – Level 5 (Sheet 1 of 2)

H110 Sanitary, Trade Waste and Stormwater Drainage – Level 5 (Sheet 2 of 2)

H111 Sanitary, Trade Waste and Stormwater Drainage – Level 6 (Sheet 1 of 2)

H112 Sanitary, Trade Waste and Stormwater Drainage – Level 6 (Sheet 2 of 2)

H113 Sanitary, Trade Waste and Stormwater Drainage – Level 7 (Sheet 1 of 2)

H114 Sanitary, Trade Waste and Stormwater Drainage – Level 7 (Sheet 2 of 2)

H115 Sanitary, Trade Waste and Stormwater Drainage – Roof (Sheet 1 of 2)

H116 Sanitary, Trade Waste and Stormwater Drainage – Roof (Sheet 2 of 2)

H200 Water, Gas, Fire Hydrants and Hose Reels – Level 1 (Sheet 1 of 2)

H201 Water, Gas, Fire Hydrants and Hose Reels – Level 1 (Sheet 2 of 2)

H202 Water, Gas, Fire Hydrants and Hose Reels – Level 2 (Sheet 1 of 2)

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 4

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

H203 Water, Gas, Fire Hydrants and Hose Reels – Level 2 (Sheet 2 of 2)

H204 Water, Gas, Fire Hydrants and Hose Reels – Level 3 (Sheet 1 of 2)

H205 Water, Gas, Fire Hydrants and Hose Reels – Level 3 (Sheet 2 of 2)

H206 Water, Gas, Fire Hydrants and Hose Reels – Level 4 (Sheet 1 of 2)

H207 Water, Gas, Fire Hydrants and Hose Reels – Level 4 (Sheet 2 of 2)

H208 Water, Gas, Fire Hydrants and Hose Reels – Level 5 (Sheet 1 of 2)

H209 Water, Gas, Fire Hydrants and Hose Reels – Level 5 (Sheet 2 of 2)

H210 Water, Gas, Fire Hydrants and Hose Reels – Level 6 (Sheet 1 of 2)

H211 Water, Gas, Fire Hydrants and Hose Reels – Level 6 (Sheet 2 of 2)

H212 Water, Gas, Fire Hydrants and Hose Reels – Level 7 (Sheet 1 of 2)

H213 Water, Gas, Fire Hydrants and Hose Reels – Level 7 (Sheet 2 of 2)

H301 Water Circulation – Hydraulic Lab – Level 1

H401 Sanitary and Trade Waste Schematic – Sheet 1

H402 Sanitary and Trade Waste Schematic – Sheet 2

H403 Cold Water Schematic

H404 Non-Potable Cold Water Schematic

H405 Hot Water Schematic

H406 Non-Potable Hot Water Schematic

H407 Stormwater Schematic

H408 Rainwater Re-use, Gas and Fire Schematic

H409 Reverse Osmosis Water Schematic

H501 Detail Sheet 1

H502 Detail Sheet 2

H601 Axonometric Views – Sheet 1

H602 Axonometric views – Sheet 2

H603 Axonometric views – Sheet 3

H701 Sections – Sheet 1

1.4 ALTERNATIVE PRODUCTS

It shall be noted that where a specific brand or model of equipment is specified this is intended to define a benchmark quality and performance standard. Should the Sub-Contractor offer equal or equivalent equipment it shall be the responsibility of the Sub-Contractor to submit a detailed comparison matrix with the tender submission. Failure to comply with this shall imply that the Sub-Contractor has verified the suitability of the equipment to the installation as being in compliance with the functional requirements and specifications and will make use of the brands defined in the specification.

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 5

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

The Sub-Contractor is responsible for all additional work resulting from the utilisation of an approved alternative product, including additional or revised statutory approvals, changes to adjacent work, re-submission of shop drawings and any costs incurred by the Consultants in assessing such alternative products.

Proposals for substitution must include details of:

a) Changes to adjacent work.

b) Cost differences.

c) Quality differences advantage to the Principal.

d) Lead time and program changes.

e) Certificate of compliance.

Any alternate offer shall be considered only if accompanied by a fully conforming tender submission. The Principal reserves their right not to accept alternate product offers.

All alternate offers are subject to prior approval and acceptance in writing by the Principal.

1.5 REQUIRED SUBMISSIONS

Provide in good time to allow review without impediment to the programme:

a) Copies of correspondence with Authorities.

b) Certified schedule of compliance for all plant and equipment, prior to placing orders.

c) Certified schedule of competency for all tradesmen intended to work on the project.

d) Factory test results where applicable.

e) All product data, performance test and commissioning results required by this Specification.

f) Shop drawings for fabrication of all equipment and items supplied.

g) Inspection, test and commissioning plans for every section of the works including:

I. The procedure of how to complete the task.

II. The skill or competency of the person undertaking the works.

III. The review or testing procedure to assure satisfactory completion of the task.

IV. The detailed documentation to record the process.

V. The Sub-Contractors representative authorised to sign-off the task as accepted Principal handover / training proposals.

h) Record and installation drawings. Record all changes to equipment and services layouts, wiring and any other items during the construction period, which may have been incorporated into these works. Include these changes in the As Installed documentation. The final installation is to be represented in a Revit as part of a building information model (BIM) with architecture and all other services. As-Installed Drawings to be exported from Revit and presented in Autocad dwg format.

i) Operating and Maintenance manuals.

j) Maintenance/service records during the defects liability period.

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 6

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

1.5.1 Shop Drawings

Submit for approval dimensioned shop drawings, showing details of the fabrication, layout and installation of all plant and equipment, including relationship to building structure and other services.

The term shop drawings shall mean complete drawings showing all details of fabrication assembly, installation and fixing of the items concerned, and shall include any necessary explanatory notes or specifications.

Fabrication or installation shall not proceed until the associated shop drawings have been reviewed and accepted.

Show all dimensions and notes which are based on site measurement. Confirm dimensions on site prior to preparation of drawings. Co-ordinate work shown diagrammatically in the contract documents, and submit dimensioned set-out drawings. Allow for adjustments and fitting on site. Indicate whether site dimensions have been verified. Confirm site dimensions prior to fabrication. No extra charge or compensation will be considered for differences between actual dimensions and dimensions indicated on Contract Documents. Do not delay job progress.

Where plant and equipment is to be located within or above the structure, submit sketch plans at an early stage of the project to demonstrate that the spatial allocations are sufficient for effective installation, testing, commissioning and lifetime maintenance or replacement.

Prepare shop drawings using Autodesk Revit 2010 or version compatible with the Contractor‟s choice for the BIM.

Provide the following information on the title block:

a) Project identification.

b) Sub-Contractor‟s name.

c) Date of preparation of submission, and all revisions, if applicable.

d) Shop drawing number and title of item to which the shop drawing refers.

e) Sub-contractor‟s name, if submission is prepared by a sub-contractor.

f) Contractor‟s name, if submission is prepared by a sub-contractor, including the names of person or firm preparing the shop drawings, if different from Sub-Contractor.

g) Statement or stamp of approval by the Sub-Contractor, which shall signify that he has seen and examined the shop drawing as conforming to Specification.

h) Submit minimum 2 prints in A0 size (final number and size to be agreed).

Show the following information where appropriate as a minimum requirement:

a) Plantroom layout plant 1:50 scale, with sections and details at 1:20 scale.

b) Floor plans at 1:100 scale, with detailed sections.

c) Access to and removal of all plant including locations and sizes of access doors to be installed in finished building surfaces.

d) Schematic and layout drawings of piping, conduits, and controls.

e) Schedule of electrical loadings.

f) Switchboard and control panel layouts and schematics with terminal numbering.

g) Cable type, size and marking details.

h) Location and identifier for all equipment.

i) Locations of all control sensors, valves and actuators.

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 7

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

j) Detailed information including make, model and curves for installed pumps.

k) Details of all interfaces with other services and utilities.

l) Services co-ordination drawings for spatial co-ordination with building structure and other services with details for restricted locations.

m) Control logic diagrams with settings.

n) Foundations, plinths, chases, ducts, pits and penetrations through structure.

o) Layout and details of services cast in concrete.

p) Structural loadings and earthquake forces due to plant.

q) Structural support details and methods of fixing to structure.

r) Construction loadings.

s) Lifting point loads.

t) Label schedules.

Where clashes occur submit drawings showing coordination of all the services at the locations including dimensions and sizes of other trades, e.g:

a) Electrical Services including Communications and Security.

b) Fire Protection Services.

c) Lift Services.

d) Mechanical.

If amendments are required, drawings are to be revised and resubmitted for approval. This process shall continue until the shop drawings are deemed satisfactory. Review of shop drawings by the Consulting Engineer refers to general design only and does not relieve the Sub-Contractor of responsibility for contract requirements, or dimensional accuracy of the information presented in the shop drawings.

Once a shop drawing is accepted, provide 2 prints (final number and size to be agreed) of the final drawings.

Allow 3 weeks for review of shop drawings after delivery to the Superintendent for appraisal.

Any costs resulting from a failure to submit drawings for any purpose will not be accepted.

Keep current, approved copies of shop drawings on site for review at all times.

The Mechanical trade is responsible for preparing 3 dimensional co-ordinated shop drawings for all service trades, and shall liaise with other trades during preparation to ensure services are co-ordinated. Provide all necessary advice during the preparation of these drawings to ensure that the drawings accurately represent what will be installed including any proposed changes to the design drawings. The shop drawings are to highlight any clashes between services to allow resolution prior to commencing construction.

At the end of the process the Mechanical trade is responsible not only for mechanical drawings but also co-ordinating and producing fully dimensioned set out drawings for all relevant trades including cable trays, bus ducts, pipework, items on ceiling and penetration drawings

Modify the 3D drawings to As-Constructed status on completion for inclusion within As-Constructed submissions.

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 8

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

1.5.2 Penetrations and Building in Drawings

Prepare and submit drawings of penetrations and “built-in” components in the same form and manner as described for the processing of shop drawings. All penetration measures shall relate to grid lines, co-ordinates or relative levels.

The Sub-Contractor is responsible for the location of all sleeves, blockouts and penetrations and for sealing of the penetrations to match required FRL of the building element.

The Sub-Contractor must obtain penetration requirements from all sub-contractors and co-ordinate fully all penetration requirements, with particular attention to adjustments in penetration locations made necessary by crossing of ducts, pipes, conduits, etc.

The Sub-Contractor shall submit co-ordinated penetration drawings in sufficient time for review. Any failure to submit requirements within sufficient time for revision of structural drawings, resulting in re-working of the structure or re-ordering of structural components shall be solely at the expense of the Sub-Contractor and shall not constitute any claim for variation or delay.

Drawings of penetrations and “built-in” components shall be submitted for review in the same form and manner as described for the processing of shop drawings. All penetration measures shall relate to grid lines, co-ordinates or relative levels.

The Sub-Contractor is responsible for the location of all sleeves, blockouts and penetrations required for the works in accordance with dimensions and set out tolerances indicated on the drawings, including sealing of the penetrations.

Penetrations through fire rated, smoke rated, air tight, water tight or acoustic barriers must be sealed in accordance with the requirements of the Authority having jurisdiction.

1.6 TECHNICAL DATA SUBMISSIONS

Provide technical data submissions for items of equipment and plant proposed, for review and comment by the Superintendent.

Where the manufacturer‟s technical data and information forwarded by the contractor (technical data submission) does not cover all the specification requirements, a schedule of items which are different from the tender specification

Apart from the non conforming details/items listed in the submission it would be assumed that the equipment proposed meets with all other specified requirements.

Review of plant/equipment proposed will be undertaken on the above basis.

Failure to identify any deviation from the specified requirements at the proposal stage could result in equipment having to be replaced after installation. It is therefore important that all tenderers and equipment suppliers are made aware of this requirement.

The technical review will be undertaken on the basis that non complying equipment may be rejected at any time.

1.7 SAMPLES FOR REVIEW

Submission of samples of at least the following shall be provided.

a) Basins – amenity and laboratory

b) Basin bottle traps

c) Water Closets

d) Urinals

e) Tapware – amenity and laboratory

f) Safety Showers

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 9

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

g) Eyewashers

h) Lab sink wastes

i) Longitudinal Trench grates.

j) Rainwater outlets

k) Inspection point covers

l) Floor grates – amenity and laboratory only.

m) Acoustic and Thermal insulation along with appropriate ESD certification.

n) In wall tundishes

1.7.1 Timing

Coordinate submissions of related samples. Do not cause delays by making late submissions or submitting inadequate samples.

1.7.2 Quantity

Submit a sample of each designated item and an electronic copy of updated manufacturers technical details. Provide 2 copies of all supporting documentation. Include ancillary items such as fasteners, flashings and seals.

1.7.3 Identification

Identify the project, Contractor, Subcontractor or supplier, manufacturer, applicable product, model number and options, as appropriate and include pertinent Contract document references.

Include service connection requirements and product certification.

Identify any non-compliances with project requirements, and characteristics which may be detrimental to successful performance of the completed work.

1.7.4 Approval

Do not commence work affected by samples until the samples have been accepted. Submit further samples as necessary.

1.7.5 Sample Acceptance and Retention

Keep approved samples in good condition on site, until practical completion.

Do not incorporate in the works Samples which have been approved for incorporation. Hand approved samples over to the Principal at the end of the project.

Installed items will match accepted samples throughout the works.

1.8 QUALITY ASSURANCE

Provide a Quality Assurance plan in order to propose, establish, maintain, monitor and document a quality assurance system covering all aspects of the design, purchase, fabrication, installation and completion of the works. The plan shall be in accordance with ISO 9001./.2 (as appropriate).

Designate a Project Quality Inspector to discharge the quality plan, which must include the following minimum:

a) Check all shop drawings for conformance to requirements prior to submission.

b) Check equipment compliance schedule against the particular specification requirements and equipment schedules prior to submission.

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 10

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

c) Check all samples for conformance to requirements prior to submission.

d) Check all tests required for proper manufacturing of the equipment.

e) Check all manufactured items for compliance prior to dispatch to site.

f) Check installation of all items under this Specification.

g) Check all materials, welding, joining, terminations, fixing and finishes.

h) Check all on-site tests required to commission the works.

i) Check operating and maintenance manuals to ensure they contain adequate information to permit systems to be operated by the Principal at the end of defects liability period. (Including adequate training and tuition of the Principal‟s representative).

Submit the following documentation:

a) Quality System third party certification, if any, to the Standards specified by the Joint Accreditation System of Australia and New Zealand.

b) Quality manual detailing corporate Q.A. policy statement, system element description, register of procedures and project specific ITPs.

c) Typical inspection sheets to be used during construction.

d) Typical inspection sheets to be used pre commissioning.

e) Typical inspection and test process sheets.

1.8.1 Authorities requirement

It is the hydraulic service Sub-Contractor's responsibility to be aware and fulfil all obligations resulting from the standard and job specific published and received requirements of the Authorities.

All direct approaches to the Authorities will be coordinated by the Contractor and will not be made without their presence and consent.

1.8.2 Applicable Australian Standards

All Australian Standards and Codes, be they recommendations or statutory requirements, current at the date of this brief and specification along with the reference codes and standards listed in the prefaces to those Standards and Codes are applicable to these works in respect of all materials and workmanship.

1.8.3 Materials and Workmanship

All materials and workmanship provided by the Sub-Contractor will be of good and industry standard quality. The materials and workmanship will be to the approval of the Principal and all defective materials and work when directed in writing will be rectified and/or removed from the Works at the Sub-Contractors expense and without any delay to the construction program.

1.8.4 Coordination with Others

Throughout the process of execution of the Works the Sub-Contractor will be responsible for the coordination of his design and installation with other designers, trades and the Contractor. Under no circumstances will deficiency in the coordination with others give rise to any Sub-Contract variations or claims.

The Sub-Contractor will provide adequate openings (including making good and fire rating) in floors, slabs, walls and ceiling tiles and/or plinths for all Works of this Sub-Contract. All brackets, bolts, hooks which are required to be built will be supplied and installed by the Sub-Contractor.

Advanced Engineering Building Hydraulic Services

Project Information – Section 1

Section 1 - Page 11

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

1.8.5 Considerations for Materials Engineering

Consideration for proposed materials, used to convey, support and fix services are an essential part of the engineering design process for this project. Materials used for conveying of services could possibly be subjected to accelerated surface corrosion from the sea water spray, high humidity and exposure of Ultra-Violet radiation, if inappropriate materials and or surface treatments are selected.

All materials selected & installed for this project will be suitable for their location and environment. All materials used for conveying of services will have a minimum replacement (life) period of 20 years. All materials used for supporting & fixing of service materials will have a minimum replacement (life) period of 15 years.

Advanced Engineering Building Hydraulic Services

Description and Extent of Works – Section 2

Section 2 - Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

DESCRIPTION AND EXTENT OF WORKS 2.

2.1 EXTENT OF WORKS

2.1.1 General Works

a) Provision of planning and preparation for the works.

b) Provision for coordination with other disciplines.

c) Advise of any discrepancies between services specification and services drawings by way of RFI, during the tender period and during construction.

d) Provision for installation of all outlets, equipment and fittings in accordance with architects details. Advise of any discrepancies between hydraulic services documentation and architects documentation by way of RFI.

e) Provision of general penetrations other than the major service core riser penetrations and horizontal penetrations from service core to the building areas. Fire sealing of penetrations. Provision of sleeves on band beams as noted.

f) Provision of clear and comprehensive labelling of all pipework and equipment.

g) Provision of product data sheets.

h) Provision of samples.

i) Provision of Acceptance Test Procedures.

j) Provision of test results for each item of plant and equipment and for all systems.

k) Provision of Quality Assurance manuals for approval prior to commencement of the works, customised to this project.

l) Provision of testing and commissioning of the complete installation and preparation of commissioning report.

m) Provision of detailed “Shop Drawings”, fully coordinated with all services and Architectural drawings, schedules and schematics for the complete project in compliance with this specification, the BCA and the relevant standards. The Mechanical Contractor shall be the lead contractor in relation to providing a co-ordinated Revit Model.

n) Provision of 12 month warranty and preventative maintenance for the complete installation.

o) Provision of building systems tuning on a monthly basis during the 12 month warranty period and report on a quarterly basis.

p) Provision for training of building staff on the usage and maintenance of equipment and systems where applicable.

q) Documentation of the “ As Installed” hydraulic services in a project building information model (BIM) in Autodesk Revit software. The model shall be established and managed by the Contractor.

r) Provision of “As Installed” documentation and manuals in both pdf and dwg format, with all drawings updated to reflect revisions and variations issued as instructions during the course of the project.

2.1.2 Hydraulics Works

The Hydraulic services will generally comprise of the installation, commissioning, testing, placing into service maintenance and defects warranty of the following:

a) Sanitary Plumbing and Drainage

Advanced Engineering Building Hydraulic Services

Description and Extent of Works – Section 2

Section 2 - Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

b) Trade waste Drainage

c) Stormwater Drainage and Internal Downpipes (conventional and siphonic)

d) Rainwater Harvesting and reuse for toilet flushing and provision for irrigation supply.

e) Rainwater storage tanks (other than cast insitu)

f) Waterproofing of Level 7 rainwater tank

g) Rainwater reticulation

h) Potable hot and cold water reticulation

i) Non-potable hot and cold water reticulation

j) Water sub-metering of major water uses linked to BMS with leak detection protocol

k) Hot water heat exchangers – heat supplied from mechanical plant

l) Natural gas reticulation

m) Sub-soil drainage

n) Fire Hydrants and Fire Hose Reels including test drains.

o) Connections to site infrastructure

p) Acoustic and thermal insulation of pipework as required.

q) Sanitary fixtures and tapware

r) Laboratory fixtures and tapware

s) Plug and waste to all integral bench sinks and troughs

t) Reconfiguration of water supply to fire systems for buildings within the University adjacent project site.

u) Installation of house drainage pipework to accommodate the house drainage diversion around the building. Inground works associated with the diversion is part of civil scope.

In addition to the above scope of Hydraulic services the following items will also be included:

a) Project Management of installation

b) Preliminaries

c) Negotiations with all authorities.

d) All associated authority applications, fees and charges.

e) Preparation and submission of detailed workshop drawings

f) All co-ordination between Hydraulic Services and other services trades and building structure.

g) Documentation of hydraulic services in the project BIM using Autodesk Revit 2010 software.

h) Preparation and submission of Manuals and As-Installed drawings.

i) Maintenance and Defects Liability for a period of 12 month from date of practical completion.

j) Training staff in the operation of all systems.

k) Staged handover to suit the building program.

Advanced Engineering Building Hydraulic Services

Description and Extent of Works – Section 2

Section 2 - Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

l) Preparation and submission of documentation to aid in the Greenstar Submission for an AS-Built rating under the Education v1 rating tool.

2.2 ASSOCIATED WORKS

2.2.1 Contractor

a) Provide all hydraulic ducts and form large hydraulic penetrations as shown on structural drawings only. All other penetrations by Hydraulics Sub-Contractor.

b) Temporary electrical supply for use during construction.

c) Access panels to all ducts and ceilings, inspection openings and fire hose reel/hydrant housings, including fire hydrant booster valve cabinet.

d) Cut all holes in finished surfaces, timber, cupboards, false ceilings, vanity units, shelves, etc, as required by the Hydraulics Sub-Contractor.

e) 25mm thick waterproof ply supports for sanitary fixtures on dry wall construction.

f) Access doors and hatches for access to hydraulic equipment.

g) Bollards and mechanical protection to pipework, stacks and equipment.

h) Roof, gutters, gutter sumps, gutter outlet and external downpipes.

i) Supply and installation of waterproof membranes in all wet areas – amenity, laboratory, terrace and roof areas.

j) Set out of building grids to allow set out of core holes.

k) Supply and installation of all roof under flashing to external penetrations.

l) Supply and install all roof/parapet/terrace overflows.

m) All in-situ concrete sumps and grated drains (grates and frames to be supplied and installed by the Hydraulics Sub-Contractor) that form part of the structural slab.

n) Concrete pump plinths to the dimensions supplied by the Hydraulics Sub-Contractor. Note: Metal forms to be supplied and installed by the Hydraulics Sub-Contractor.

o) Fire hydrant and fire hose reel cupboards and necessary signs.

p) Fire service booster valve cupboards and signage.

q) Labeling of all hydraulic equipment enclosures.

I. Cast insitu water storage tanks

r) Rainwater storage tank (approx 70,000 litres). Note: Waterproofing, pipework to and from tank, valves, levels, access ladders, fill valves, float switches etc are to be by the hydraulic sub-contractor.

s) Hydraulics lab header tank (Level 2). Note: Waterproofing, pipework to and from tank, levels and sensors are to be by the hydraulic subcontractor.

t) Inground flume sumps in Hydraulics Lab (level 1). Note: pipework to and from sumps, pump fixings, rails, conduits, access covers etc are to be by the hydraulic sub-contractor.

u) Structural form for the stepped spillway flume fiberglass shell (level 1)

v) Spoon drains or dish drains with falls to the outlets provided by the Hydraulics Sub-Contractor.

w) Chasing, coring, cutting and making good.

x) Pipe penetration guards for pipes.

Advanced Engineering Building Hydraulic Services

Description and Extent of Works – Section 2

Section 2 - Page 4

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

y) Excavation and de-watering for sewer pump station (level 1)

2.2.2 Mechanical Services

a) Condensate drainage from mechanical plant to tundish.

a) Extension of cold water service from control valve provided for mechanical services requirements.

b) Extension of natural gas service from control valve provided for mechanical services requirements.

c) Provide wiring from terminals of electrical control equipment and control panels of hydraulic equipment to Building Management System for monitoring of hydraulic services equipment.

2.2.3 Electrical Services

Provision of permanent electrical power for various hydraulics components. The Hydraulics Sub-Contractor shall be responsible for contacting the Electrical Sub-Contractor to coordinate the location that the electrical power is required to be run to and for coordinating the time that the electrical power is to be connected to the hydraulic components. The power is required for but not limited to the following:

a) Electrical supply (looped, un-terminated tails) to sewer drainage pumps control panel.

b) Electrical supply (looped, un-terminated tails) to rainwater pumps control panel

c) Electrical supply (looped, un-terminated tails) to stepped spillway pumps control panel (Level 1)

d) Electrical supply (looped, un-terminated tails) to flume sump pumps control panel (Level 1)

e) Electrical supply (looped, un-terminated tails) to tilting flume pumps control panel (Level 1)

f) Electrical supply (looped, un-terminated tails) to plunging jet flume pump control panel (Level 1)

g) Electrical supply (looped, un-terminated tails) to control panel for hot water circulating pumps.

h) Electrical wiring to the gas automatic safety shutdown valve from the emergency power supply.

i) Electrical supply to urinal flushing devices.

j) Electrical supply to auto flushing devices in laboratory and plantroom areas.

k) Electrical supply to the boiling / chilled water units.

Note the Hydraulics Sub-Contractor is to supply all control panels for hydraulic plant and the connection from the control panel to the equipment where required.

2.2.4 Fire Services

a) Extension of fire services from flanged supply in sprinkler valve room.

2.2.5 Building Management System (BMS) Sub-Contractor

Provision of BMS points for the monitoring of various hydraulics components.

Advanced Engineering Building Hydraulic Services

Description and Extent of Works – Section 2

Section 2 - Page 5

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

The Hydraulics Sub-Contractor shall be responsible for contacting the BMS Sub-Contractor to coordinate the location of the required BMS connection points.

The Hydraulics Sub-Contractor shall also be responsible for determining in conjunction with the BMS Sub-Contractor the state of the points to be provided.

The Hydraulics Sub-Contractor shall provide voltage free contacts in the control panel for all points requiring BMS monitoring for continuation by the BMS Sub-Contractor.

Further, the Hydraulics Sub-Contractor is to provide the required access to his plant and equipment for the BMS Sub-Contractor to complete his work.

The BMS Sub-Contractor works shall include points and electrical wiring from hydraulic plant as required. Refer “Schedules” section for list of BMS points associated with hydraulic services.

2.2.6 Landscape Services

a) Extension of irrigation water service from control valve provided for irrigation system.

2.2.7 Civil Services

a) Valved and capped potable water supply from precinct water main

b) Valved and capped fire water connection to precinct fire main.

c) House drainage connection branch for new pumped house drainage discharge

d) House drainage connection branch for new gravity house drainage discharge

e) House drainage connection branch for diverted house drainage

f) Stormwater connection stub for overflow from rainwater harvesting tank

g) Stormwater connection stub for stormwater discharge (western end of building).

2.3 PERFORATIONS IN STRUCTURE

2.3.1 General

Provide all openings throughout the building and structure for the passage of pipework, conduits, cable trays, flues, ducts etc. in accordance with dimensional details provided. Penetrations through structural beams shall not be varied from those shown on the Tender Drawings without written approval from the Builder and Structural Engineer.

2.3.2 Minor Penetrations

Minor penetrations such as conduits, flues, pipes and ducts shall be provided in positions nominated on fully dimensioned shop drawings.

Supply a sleeve for each individual penetration and place the sleeve in accordance with the dimensions on the shop drawing. Maintain separation between penetrations in accordance with BCA requirements.

2.3.3 Sealing of Penetrations

Seal all penetrations namely:

a) Sealing around pipes and conduits, etc. which pass through acoustic or fire barriers.

b) Sealing between pipework and sleeves, where movement is to occur.

c) Sealing watertight around penetration which leads outside the building and are located below the ground surface.

Advanced Engineering Building Hydraulic Services

Description and Extent of Works – Section 2

Section 2 - Page 6

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

d) Sealing around penetrations through chambers which are subject to suction or pressurisation.

e) Materials used for sealing penetrations shall be suitable for the purpose and shall comply with the requirements of the Local Authority.

2.3.4 Perforations in Roofs

Provide flashed holes in roofs, including kerbs as necessary, to accommodate this installation of conduits, flues, pipes etc.

Provide over-flashing of each penetration to ensure a fully waterproof installation. Any trimmer beams between purlins or other reinforcement to accommodate large equipment shall be supplied and installed to suit plant and equipment.

Co-ordinate locations of vent terminations with architectural drawings and mechanical services supply and exhaust ductwork.

Advanced Engineering Building Hydraulic Services

Design and Completion Criteria – Section 3

Section 3 - Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

DESIGN AND COMPLETION CRITERIA 3.

3.1 DESIGN CRITERIA

Design criteria presented herein form the basis for the design of the works and for any alternative proposals submitted.

3.1.1 Trade Waste and Sanitary Plumbing

Trade waste and sanitary plumbing systems: Designed in accordance with AS/NZ 3500 and Local Authority and Sewer Plumbing Regulations.

3.1.2 Stormwater

Designed in accordance with local authority regulatory requirements & AS/NS 3500.

3.1.3 Items and Design Criteria

Item Design Criteria

Pipe sizing design criteria Australian Standard 2200 – Design charts for Water Supply and Sewerage and The Institute of Plumbing Australia – selection and sizing of copper tubes for water piping systems.

Water supply – mains water Mains water supplied from private precinct mains water network. Average supply temperature 15°C.

Electromagnetic emission In accordance with Australian/New Zealand Standard 4251 Part 1 – Electromagnetic compatibility – Generic immunity standard – residential, commercial and light industry.

Electromagnetic immunity In accordance with Australian/New Zealand Standard 4252 Part 1 – Electromagnetic compatibility – Generic immunity standard – residential, commercial and light industry.

Disability access In accordance with the Building Code of Australia and Australian Standard 1428.1 1993 – Design for Access and Mobility.

Faucets, cocks and outlets To requirements of Australian Standard 1718, de-zincification resistant copper alloy, pressure tested to 2.0 Mpa.

Water conservation measures In accordance with AS 6400 – Water Efficient Rating and Labelling.

Heated water temperature control

To requirements of Australian/New Zealand Standard 3500.4.1 – Heated water supply systems – Performance requirements.

Test procedures for fire rating products

To requirements of Australian Standard 1530.4 – and Australian Standard 4072.1-1992.

Gas supply Natural gas calorific value 39.2 MJ/m³

Specific gravity 0.6

Supply pressure at consumer side of meter:

3kPa for all

Advanced Engineering Building Hydraulic Services

Design and Completion Criteria – Section 3

Section 3 - Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

3.1.4 Cold Water – Potable and non-potable

The cold water service shall provide the necessary quantity of water to each area or fixture. A system shall be designed with acceptable water velocity and pressure drops to deliver water at the minimum required flows and pressures as mentioned.

The design shall comply with the latest Australian Standards AS 3500.1 to satisfy local authority requirements.

Extend domestic water to private (University of Queensland) water meter assembly, complete with site containment. Provide pressure limiting / reduction valves downstream of water meter where required.

Supply cold water to all fixtures, fittings and equipment within the project except WCs and urinals.

Design Criteria

The cold water system shall meet the following minimum operational and design criteria:

a) working velocities in pipes shall be limited to a maximum of 1.5 m/s

b) maximum operational pressure 500 kPa

c) minimum operational pressure 250 kPa

The following minimum flow rates shall be provided to fixtures:

Fixture Flowrate

Wash hand basins 4.5 l/min (maximum combined flow)

Kitchen Sinks 6.0 l/min (maximum combined flow)

Hose taps 9.0 l/min (maximum combined flow)

Shower 7.5 l/min (maximum combined flow)

Laboratory Sinks 6.0 l/min unless stated otherwise

Safety Showers / eyewashers 60 l/min and 12 l/min

Provide backflow prevention devices to all incoming water supplies and all outlets with potential cross connections to AS 3500.1 and local authority requirements. Backflow devices shall dual and in parallel with isolation valves on each side of each valve assembly.

Provide isolation valves to each fixture and each group of fixtures located within the same room and level.

Provide a water meter assembly, complete with volt free contacts for connection by BMS contractor to each building zone and major equipment item and as shown on drawings.

3.1.5 Heated Water – Potable and non-potable

The water heating system shall be connected to and receive heat from the mechanical hot water generation plant.

The design shall comply with the latest of Australian Standards AS3500.4. The heated water service shall comprise of centralised plant heat exchangers, heated water flow, heated water return, dual circulating pumps, balancing valves and insulation for both potable and non-potable hot water.

Supply domestic heated water at minimum to the following:

a) Base building amenity showers (cold water only to handbasins in amenities)

Advanced Engineering Building Hydraulic Services

Design and Completion Criteria – Section 3

Section 3 - Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

b) Cleaners rooms

c) Handbasins in laboratories

d) Sinks in tea rooms / breakout spaces / staff rooms.

Supply non-potable heated water at a minimum to the following:

a) Laboratory sinks and tapware as nominated

Maximum inlet supply pressure to all heated water heaters is to be 650 kPa.

Maximum temperature shall be 70°C.

Insulation will have a zero flame and smoke index and be 20mm thick (min) with a K value of 0.04 w/m K for all heated water flow and return pipework including all dead legs.

Dead legs in the heated water system shall be avoided and every heated water outlet shall have full temperature within 10 seconds.

All heated pipework in wall chases to be lagged.

Heated water circulating pumps to be dual in operation with “duty pump” –“stand by” principle with pump run and pump fail. Pump sized to limit heat loss from system to 5°C. Pumps shall incorporate a variable speed drive unit, and be set to operate upon notable temperature drop in return line.

Provide control valves to each group of fixtures located within the same room and level.

Provide self balancing valves on all heated water return lines.

Make provision for expansion and contraction on all heated water pipework.

Air release valves to be provided at highest point of main circuit complete with drain.

Design Criteria

The heated water system shall meet the following operational and design criteria:

a) Working velocities in pipes shall be limited to a maximum of 1.8 m/sec

b) Maximum operational pressure 500 kPa

c) Minimum operational pressure 250 kPa

d) The maximum flow rates shall be provided as per cold water section.

e) Provide water hammer arrestors where necessary.

f) Provide thermostatic mixing valves to all disabled amenities, parents rooms and public amenities set at 43° C and all other areas to be set at 50° C.

3.1.6 Gas Service

A natural gas system shall be designed providing gas to all gas appliances including gas fired electrical generator and mechanical hot water heaters.

The whole of the system shall be designed to comply with AS 5601 and local authorities requirements.

The gas service system shall commence from the point of connection to the gas meter.

Extend the gas service to the plant rooms and connect to the water heaters. Extend the gas service into the laboratories as shown on the drawings.

Provide provisional gas supply (pipework only) to level 2 cafe.

Provide pressure regulators to authority requirements.

Advanced Engineering Building Hydraulic Services

Design and Completion Criteria – Section 3

Section 3 - Page 4

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Allow to install flame failure device on each appliance connected to the gas supply.

Where required, provide vents from regulator sets and terminate to atmosphere.

Provide gas supply to satisfy mechanical services requirements. Terminate gas valve within 1m of equipment.

3.1.7 Trade Waste

Trade waste installations shall be in accordance local authority Trade Waste policies.

Complete systems shall be installed in accordance with sanitary plumbing and drainage sections.

3.1.8 Stormwater (Roof)

Roof drainage systems: Designed in accordance with AS 3500 based on an average rainfall recurrence interval of 100 years for box gutters and high risk areas, interval of 20 years for eave gutters.

3.1.9 Sanitary Fixtures and Tapware

Supply and install fixtures, including showers, basins, sinks, WC‟s, urinals and the like.

Supply and fix accessories, including bolts, brackets, putty, mastic, mortar and the like, necessary for the correct installation for the fixtures.

All fixtures and tap ware to be as scheduled, installed to manufacturer‟s recommendations.

3.1.10 Laboratory Fixtures and Tapware

Supply and install fixtures, including safety showers, basins, sinks, eyewashers, hose taps and the like. Provide 316 stainless steel trap and waste only for lab sinks where sink is integral to the bench.

Supply and fix accessories, including bolts, brackets, putty, mastic, mortar and the like, necessary for the correct installation for the fixtures.

All fixtures and tap ware to be as scheduled, installed to manufacturer‟s recommendations.

3.1.11 Building Details

Architectural drawings showing the nature of construction of the building, together with structural ductwork, lighting and other services layouts, are available for inspection upon request.

Thoroughly inspect existing conditions, the building plans and be fully conversant with, and allow in the tender price, all items necessary for the successful completion of the project to the intent of this Specification.

All slab works shall be reinstated to match original surface finish and original structural integrity maintained.

3.2 CERTIFICATION

Subject all procedures, recording, testing and commissioning of each plumbing system as provided and installed by the Hydraulics Sub-Contractor to a quality assurance programme which records all actions undertaken and achieved during each installation process.

3.3 ACCEPTANCE CRITERIA

3.3.1 Practical Completion

Minimum requirements for granting of Practical Completion will be:

Advanced Engineering Building Hydraulic Services

Design and Completion Criteria – Section 3

Section 3 - Page 5

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

a) Stable and reliable system performance;

b) Certification of compliance with Statutory Authority requirements;

c) Authority Approvals obtained as required;

d) Equipment manufacturer‟s Acceptance Certificates;

e) Contractor‟s listing of minor corrective and outstanding work items to complete the works;

f) Approved Maintenance Management Plan including maintenance programme, OH&S risk assessment and risk management procedures, specialist service providers, maintenance task sheets;

g) Draft copies of the as-installed documentation;

h) Within 30 days of Practical Completion; the following shall be provided:

I. Completed As-Installed and Maintenance and Operating Documentation.

II. BIM Revit model

3.3.2 Final Completion

Minimum requirements for granting of Final Completion will be:

a) Submission of final system documentation.

b) Fully completed Maintenance Records.

c) Completion of all items noted on the Final Inspection Report.

d) Copy of Certificate of Compliance.

Advanced Engineering Building Hydraulic Services

Services Infrastructure – Section 4

Section 4 - Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

SERVICES INFRASTRUCTURE 4.

4.1 HOUSE DRAINAGE

The site is located in a network of private house drains.

The site will utilize two (2) connections to the private infrastructure:

I. A 150mm connection in within the loading dock area for gravity drainage from Level 2 to Level 7

II. A 100mm connection from a new lifting pump station on level 1 adjacent the lake boardwalk.

4.2 WATER

The site has frontage to a 150mm private water main in Staff house Rd. The main is metered at the boundary to the University and is supplied from the Queensland Urban Utilities infrastructure.

The site will utilize one connection to the private infrastructure:

I. 150mm fire / domestic water connection extending from the capped and valved branch line provided under civil scope of works.

4.3 STORMWATER

The site is located in a network of private stormwater drains which all discharge to the adjacent lake.

The site will utilize the following connections to the private infrastructure:

I. 300mm connection to the civil stormwater system from the rainwater tanks within the loading dock areas

II. 225mm connection to the civil stormwater manhole at the south western end of the building.

III. 300mm connection into a new civil kerb entry pit in Jocks Rd.

IV. 300mm connection from the hydraulics lab (Level 1) through to an existing headwall into the lake

V. 225mm connection from the auditorium roof stormwater drainage through to an existing discharge point into the lake.

4.4 NATURAL GAS

The site has frontage to the following gas mains:

a) 50mm medium pressure main in Staff House Rd.

Application shall be made to the Authority for supply to the site.

Meter locations for base building, tenancy provision and co-gen plant shall be on the western end of the building accessed from Level 2.

Advanced Engineering Building Hydraulic Services

Sanitary Drainage Systems – Section 5

Section 5 - Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

SANITARY DRAINAGE SYSTEMS 5.

5.1 GENERALLY

Supply, install, test and commission all house drainage from soil and wastes and fixures to the sewer connection. Provide all necessary pipes, junctions, bends, pits, floor wastes, excavation, supports, backfilling, testing and sundry equipment required for the installation. Pipeline positions shall be determined on site in conjunction with all other disciplines to ensure adequate coordination of all services and elements. Coordination shall be carried out prior to any setting out, excavation and pipe installation taking place.

Execute the works, using only materials and structures as approved by the local authority and to the satisfaction of the Contractor.

5.2 SANITARY DRAINAGE CONNECTION

Make the connection to the private infrastructure connection branch in an approved manner and to University of Queensland requirements.

Liaise with the civil contractor to confirm depth and position of new sanitary drainage connection points. Ascertain the depth, position and suitability of the existing sanitary drainage connection points prior to the commencement of any work and incorporate any adjustments required to execute the work. No claims for redundant work will be considered due to failure to comply with this requirement. Make connection to the sanitary drainage connection branches.

5.3 MATERIALS

Refer “Schedules” section and as specified for Pipes and fittings for sanitary drainage. Joints shall comply with relevant clauses under “Jointing”.

5.4 EXCAVATION

Carry out all necessary excavation as specified under “Excavation & Pipework Requirements” section.

5.5 BACKFILLING

Supply all necessary material and carry out backfilling as specified under “Excavation & Pipework Requirements” section.

5.6 GRADIENTS

Pipelines shall be laid true to line and bore from point to point.

Unless otherwise indicated on the drawings pipelines shall be graded in accordance with the Authorities requirements and as specified under “Excavation & Pipework Requirements” section.

5.7 FILLED GROUND

The entire level 1 slab is on ground however, the eastern portion of the Level 1 slab will be structurally designed as a suspended slab. Therefore, all drainage under that portion of the slab shall be suspended from the slab.

Where indicated on the structural drawings and/or encountered on site, pipelines shall be supported as directed and as previously specified under “Excavation & Pipework Requirements” section.

Advanced Engineering Building Hydraulic Services

Sanitary Drainage Systems – Section 5

Section 5 - Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

5.8 OVERFLOW GULLY

Supply and install an overflow gully for each connection to the house drainage network to provide a safe release from the connection point. Gully shall be constructed of 100mm diameter “P” trap and 100mm riser. Top of riser shall incorporate 200mm cast iron grate with concrete surround. Terminate gully top to comply with current authorities‟ regulations.

5.9 TESTING

Provide a hydrostatic test to choke level for a minimum period of 15 minutes and as required by the testing authority and the Contractor.

5.10 ACCESS / INSPECTION PITS

Supply and install inspection pits as shown on the drawings. Refer “Schedules” section for schedule of pits and chambers.

Pits, covers and frames shall be as specified under “Schedules” section.

5.11 CLEAR OUTS / INSPECTION OPENINGS

Provide and install clear-out inspection fittings to provide rodding access to all lines.

Riser from pipeline shall extend vertically to finished floor level and terminate with a brass screw out and frame.

5.12 PIPELAYING

Carry out necessary pipelaying as specified in “Excavation & Pipework Requirements” section.

5.13 CONCRETE ENCASING

Carry out all necessary concrete encasing as specified in “Excavation & Pipework Requirements” section and as shown on drawings.

5.14 REFLUX VALVES

Supply and install all reflux valves in the locations indicated and as specified in the “Schedules” section.

5.15 BASKET TRAPS

Supply and install all basket traps in the locations indicated on the drawings or as required by the local authority and as specified in the “Schedules” section.

5.16 BEDDING MATERIALS

Shall be approved and conform with the following: -

a) Crushed rock or gravel screenings of nominal sizes 7-10mm.

b) Loss of weight after thoroughly washing with water shall not exceed 10%.

c) Not less that 25% by weight shall be retained on Tyler 28 mesh sieve.

d) Shall be free of organic or foreign matter.

Advanced Engineering Building Hydraulic Services

Sanitary Drainage Systems – Section 5

Section 5 - Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

5.17 USE OF CONCRETE

Provide 20 MPa concrete not less than 100 mm thick with exposed surfaces cement rendered as follows:

a) Around pipes and fittings wherever required by appropriate authority.

b) Around and under disconnection traps, gullies, gully risers and sink stones.

c) Around pipes and fittings pass under footing beams to the invert of the footing beam.

d) Under and around bases of inclined junction and bends.

e) Under Bases of traps.

f) Under roadways and footpaths / stabilised sand 10 MPa only.

Where regulation cover cannot be provided over drains, surround pipes with 150 mm of 20 MPa concrete.

Provide 150mm thick pads under all vertical bends and on the outside of all changes in direction.

5.18 GREASE ARRESTOR

Supply and install a new grease arrestor with concrete infill gas tight gatic lids as indicated on drawings. The arrestor shall comply with the requirements in the “Schedules” section.

5.19 GENERAL PURPOSE PIT

Supply and install a new general purpose pit with concrete infill gas tight gatic lids as indicated on drawings. The GPP shall comply with the requirements in the “Schedules” section.

5.20 SEWER PUMPOUT PIT SUCTION PIPELINE

Provide a suction pipeline from the sewer pumpout pit fitted with a bend and „KAMLOK‟ fitting adjacent the pit and terminating on Level 2 loading dock. Refer drawings for location.

5.21 SEWER PUMPS

Supply and install sewer pumping station as specified in the “Schedules” section.

Advanced Engineering Building Hydraulic Services

Sanitary Plumbing System – Section 6

Section 6 - Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

SANITARY PLUMBING SYSTEM 6.

6.1 GENERALLY

Sanitary plumbing works above ground shall include all those works generally considered by authorities and trade practice to be soil, waste, vent above ground as distinct from drainer's work.

The sanitary plumbing system shall comprise of a dual stack system – namely blackwater and greywater. The blackwater stack system shall drain all urinals and WC‟s. The greywater stack system shall drain handbasins and showers. Both systems shall combine just prior to connection to the house drainage connection branch to the network infrastructure.

Plumbing as defined in this Section shall comprise plumbing waste, condensate and vent pipes above ground. Plumbing shall be the connection of the above floor fixtures and vents to the drainage system.

The sub contractor shall provide for protection of all fittings and pipework after installation and secure them against damage and shall be completely responsible for the replacement of any damaged or disfigured fitting, pipe or fixture at his own cost.

All non-metallic pipes penetrating floor slabs, fire and smoke walls and any fire rated element shall be provided with an approved fire stop collar to match the required FRL of that element.

6.2 SUPPORTING AND FIXING PIPES

All pipes shall be adequately supported and securely fixed in accordance with the drawings and to the satisfaction of the Contractor. Such supporting and fixing to be carried out without causing any distortion, damage or stress on the pipes or pipe joints. Pipes shall be supported at each collar and at spacing as listed in the appropriate Australian Standard.

6.3 FIXTURE TRAPS

25mm water seal traps shall be provided for the following fixtures:

a) Tea Sinks 50 mm two part universal pattern.

b) Amenity Basin 40mm chrome plated (CP) bottle trap

c) Laboratory Basin 40 mm CP copper two part S or P-trap with 40 mm CP extension riser.

d) Laboratory Sinks 50 mm two part universal pattern

Note: 75mm water seal traps are required for fixtures in PC2 laboratories as noted on drawings.

6.4 VENT PIPES

Terminate all vents through roof with a cowl. Finish vents 3 metres above ground and pedestrian trafficable levels, 300mm above roof level and 6 metres clear of openings and fresh air intakes as required by the local authority and as indicated on the drawings. Flashing of vents, which penetrate the roof, shall be carried out within the hydraulics scope of works.

The roof areas containing services equipment are considered trafficable and vents are to terminate 3m above the FFL of these areas.

6.5 INSPECTION OPENINGS & GATES

Install inspection openings in accessible locations so that each section of pipework can be cleaned. Inspection opening sizes shall be in accordance with authorities‟ requirements. Install testing gates on all stacks at every floor level and at the base of each stack.

Advanced Engineering Building Hydraulic Services

Sanitary Plumbing System – Section 6

Section 6 - Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

6.6 JOINTS

All joints shall be in conformity with that specified under the relevant “Materials” clause.

6.7 EXPANSION JOINTS

Supply and install approved expansion joints to all soil, waste, relief and main vent lines. Expansion joints shall be installed on each line at intervals not exceeding 3000mm on both vertical and horizontal pipelines and on either side of building expansion joints.

6.8 BRANCHES

When a branch line enters a vertical pipe the branch fitting must be wholly outside the vertical pipe such that the internal bore of the pipe is maintained at all times. For vertical branches of up to and including 80mm a radius of at least 25mm must be maintained on the throat of the bend and a radius of 50mm for larger junctions.

All horizontal branches shall connect to the main branch line through a 45° or sweep type junction.

6.9 OFFSETS

Use sweep bends of 300mm radius (or alternatively 2off 45° bend), and provide maximum fall between bends.

6.10 TRAPS

Traps shall be of the same material as the branch drainage except traps in visible locations shall be chrome plated. Refer “Schedules” section for specified pipework.

6.11 PAN COLLARS

Unless otherwise noted all pan collars to soil type fixtures shall be of approved materials and pattern. Collar shall incorporate an approved neoprene rubber ring joint.

6.12 TUNDISHES

Supply and install tundishes in areas required for mechanical / plant drainage. Tundishes shall be chrome plated where exposed.

6.13 TESTING

Provide a hydrostatic test to maximum choke level to the satisfaction of the authority and the Contractor.

6.14 FIRE STOPPING / FIRE STOP COLLARS

Where pipes pass through any fire rated element they shall be surrounded by a sealant of intumescent material capable of completely sealing the pipe penetration under fire conditions.

Approved fire stop collars fixed to formwork and incorporated within the concrete slab or as fire stop strip wrapped around the pipe and inserted into a pre-formed core hole to be installed to comply with relevant standards and codes.

6.15 FLOOR WASTES

Use trap with 100mm riser and 65mm or 100mm outlet of self-cleansing pattern. Grate to be as specified in the “Schedules” section.

Advanced Engineering Building Hydraulic Services

Sanitary Plumbing System – Section 6

Section 6 - Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

6.16 THERMAL INSULATION

Supply and install insulation to all tundishes and pipework receiving air conditioning condensate. Insulation is to extend along the length of the drainage line back to the point of connection to the stack.

Insulation shall not be installed until all relevant tests and inspections have been carried out.

Insulation shall be as specified in the “Schedules” section.

The pipe insulation shall comprise closed cell polymer foam and shall be installed around the pipework surface as tightly as possible without gaps, with the edges and ends tightly butted together.

All joints shall be taped using a 75mm adhesive backed tape. Where necessary the preformed sections shall be cut (using a sharp knife or scissors) and mitred, to ensure a tight fit around bends and at tees. Joints in insulation and at brackets, bends, along longitudinal joints and elsewhere at 500mm centres shall all be taped as described above.

Apply insulation in accordance with manufacturer‟s instructions in a neat and workmanlike manner so as to present a smooth even finish.

Insulations shall have no Ozone Depleting Potential (ODP) in either its composition or its manufacture.

Advanced Engineering Building Hydraulic Services

Stormwater Drainage & Downpipe Systems – Section 7

Section 7 - Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

STORMWATER DRAINAGE & DOWNPIPE SYSTEMS 7.

7.1 GENERALLY

Supply, install, test and commission all stormwater drainage to the stormwater connection. Provide all necessary pipes, junctions, bends, pits, floor wastes, excavation, supports, backfilling, testing and sundry equipment required for the installation. Pipeline positions shall be determined on site in conjunction with all other disciplines to ensure adequate coordination of all services and elements. Coordination shall be carried out prior to any setting out, excavation and pipe installation taking place.

Execute the works, using only materials and structures as approved by the local authority and to the satisfaction of the Contractor.

7.2 STORMWATER CONNECTION

Make the connection to the private infrastructure stormwater connections in an approved manner and to University of Queensland requirements.

Liaise with the civil contractor to confirm depth and position of new stormwater drainage connection points. Ascertain the depth, position and suitability of the stormwater connection points prior to the commencement of any work and incorporate any adjustments required to execute the work. No claims for redundant work will be considered due to failure to comply with this requirement.

7.3 MATERIALS

Refer “Schedules” section and as scheduled.

7.4 EXCAVATION

Carry out all necessary excavation as specified under “Excavation & Pipework Requirements” section.

7.5 BACK-FILLING

Supply all necessary material and carry out back-filling as specified under “Excavation & Pipework Requirements” section.

7.6 GRADIENTS

Pipelines shall be laid true to line and bore from point to point.

Unless otherwise indicated on the drawings pipelines shall be graded in accordance with the Authorities requirements and as specified under “Excavation & Pipework Requirements” section.

7.7 FILLED GROUND

The entire level 1 slab is on ground however, the eastern portion of the Level 1 slab will be structurally designed as a suspended slab. Therefore, all drainage under that portion of the slab shall be suspended from the slab.

Where indicated on the structural drawings and/or encountered on site pipelines shall be supported as directed and as previously specified under “Excavation & Pipework Requirements” section.

7.8 TESTING

Provide a hydrostatic test to choke level for a minimum period of 15 minutes and as required by the testing authority and the Contractor and as specified under “Preliminaries” section.

Advanced Engineering Building Hydraulic Services

Stormwater Drainage & Downpipe Systems – Section 7

Section 7 - Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

7.9 ACCESS / INSPECTION PITS

Supply and install inspection pits at changes of direction. Pits to be reinforced concrete of appropriate dimensions to Code with depths to match invert levels of pipeline and as specified in “Materials” section.

Pits, covers and frames shall be as specified under “Schedules” section.

7.10 GRATINGS AND OUTLETS

Supply and install all pits, gratings and outlets as specified in “Schedules” section.

7.11 PLANTERS

Supply and install 50mm drainage cell with a geotextile fabric to all planters over the entire area of the planter.

7.12 PIPE LAYING

Carry out necessary pipe laying as specified in “Excavation & Pipework Requirements” section.

7.13 CONCRETE ENCASING

Carry out all necessary concrete encasing as specified in “Excavation & Pipework Requirements” section.

7.14 SAND FOR BEDDING

Shall be approved and conform to the following: -

Loss of weight after thoroughly washing with water shall not exceed 10%.

Not less that 25% by weight shall be retained on Tyler 28 mesh sieve.

Shall be free of organic or any foreign matter.

7.15 USE OF CONCRETE

Provide 20 MPa concrete not less than 100 mm thick with exposed surfaces cement rendered as follows:

Around pipes and fittings wherever required by appropriate authority.

Around pipes and fittings pass under footing beams to the invert of the footing beam.

Under and around bases of inclined junction and bends.

Under roadways and footpaths / stabilised sand 10 MPa only.

Where regulation cover cannot be provided over drains, surround pipes with 150 mm of 20 MPa concrete.

Provide 150mm thick pads under all vertical bends and on the outside of all changes in direction.

7.16 SUB SOIL DRAINS

Provide subsoil drains to intercept groundwater seepage and prevent water build-up behind walls and under floors, pavements and landscape beds. Connect subsoil drains to surface drains or to the stormwater drainage system as applicable.

Advanced Engineering Building Hydraulic Services

Stormwater Drainage & Downpipe Systems – Section 7

Section 7 - Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Follow the minimum clear depths, measured to the crown of the pipe, where the pipe passes below the following elements:

a) 100mm below formation level of the pavement, kerb or channel

b) 100mm below the average gradient of the bottom of footings.

c) Below the finished surface of unpaved ground, levels as indicated on drawings.

d) Minimum trench width to be 300 mm.

Bed piping on a continuous underlay of bedding material, at least 75 mm thick after compaction. Lay the pipe with one line of perforations at the bottom.

If necessary, form chases to prevent projections such as sockets and flanges from bearing on the trench bottom or underlay.

Place the material in the pipe surround in 200mm layers loose thickness, and compact without damaging or displacing the piping.

Provide polyester permeable filter socks capable of retaining particles of 0.25 mm size. Securely fit or join the sock at each joint.

7.17 PITS

Provide a smooth, seamless finish, using steel trowelled render or concrete cast in steel forms and as specified in the “Schedules” section.

Cove or splay internal corners with metal access covers and grates to AS3996..

The top of cover or grate, including frame in paved areas shall be flush with the paving surface.

In landscaped areas 25 mm above finished surface and gratings taking surface water runoff located to receive runoff without ponding.

7.18 ROOF OUTLETS

Supply and install roof and balcony drainage outlets in the positions indicated on the drawings and as scheduled.

New roof outlets shall be as specified in “Schedules” section complete with grate and extension ring in locations as shown on the drawings.

Support each sump during construction with wire ties, set level both ways, to suit roof falls.

7.19 DRAINAGE TURN UPS (D.T.U.)

Install drainage turn up in spoon drains by terminating pipe collar at the invert of the spoon drain. Grates are only required if specifically noted on the drawings.

Encase drainage turn up riser in 150mm thickness concrete surround.

7.20 DOWNPIPES

Install internal conventional downpipes from all roof outlets, gutters, terrace outlets and the like and connect into the stormwater system. Downpipes shall be vertical and secured to the structure.

External conventional downpipes are not part of this scope.

Refer “Schedules” section as specified.

Advanced Engineering Building Hydraulic Services

Downpipes and Overflows – Section 8

Section 8 - Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

DOWNPIPES AND OVERFLOWS 8.

8.1 GENERALLY

The work under this part comprises the complete supply and installation of the internal downpipes from the roof outlets and sumps to the stormwater drainage system indicated on the drawings.

Allow for the supply and fixing of all bends, tees, junctions, roof drainage outlets piping and sundry equipment necessary to complete the installation as shown on the drawings and specified.

The overflow system shall either directly discharge through the external walls or interconnect via a piping system then discharge independently of the main stormwater runs.

8.2 PIPEWORK

Refer to 'Schedules' section of the specification.

Flexible rubber ring joints are to be provided where the downpipe connects to the box gutter outlet.

8.3 PIPE JOINTING

Refer to 'Materials' section of the specification. Jointing of dissimilar metals, where corrosion may occur, shall be made with neutral materials, or gasket type joints.

8.4 RAINWATER OUTLET

Supply and fix approved, flat or domed type roof drainage outlets cast in the concrete roof structure in positions indicated on the drawings. Set grates, flush and matching with adjoining surfaces. Grates shall have puddle flange and membrane clamp.

8.5 TESTING

On completion all work shall be hydrostatically tested under expected maximum choke condition including box gutter sump and box gutter for a period of two (2) hours.

Any defects shall be remedied and the test re-applied. Provide all testing gates and apparatus necessary for the test. Testing is to be witnessed by the Hydraulic Consultant's representatives.

8.6 BRANCHES

Where a branch line enters a vertical pipe, the branch fitting must be wholly outside the vertical and horizontal pipe, such that the internal bore of the pipe is maintained at all times. All horizontal and vertical branches shall be made at 45° to the main line.

Advanced Engineering Building Hydraulic Services

Siphonic Drainage System – Section 9

Section 9 - Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

SIPHONIC DRAINAGE SYSTEM 9.

9.1 GENERAL

This section specifies the requirements for design, installation and usage in accordance with the provisions of ISO and EN Standards. The system will convey rainwater from the roof to a below ground drainage system.

The underground drainage system must be capable to accepting without surcharge the rate of flow of water discharged by the siphonic drainage system in addition to other discharges which may be received. All material shall be manufactured in compliance with and certified by ISO 9001 and ISO 14000.

9.2 DESIGN

a) The design calculation software should be dedicated in accordance to the pipe and fittings and other items (e.g. outlets) used within the system. The software should be strictly based upon multi-phase modeling of the flow conditions and incorporate standard hydraulic principles. The software must further be able to generate a detailed material list of all individual components used in the calculation.

b) Hydraulic calculations must provide the following information within the set limit specified:

I. Pipe Size 40 to 315mm dia.

II. Negative Pressure Withstand 800 mbar on pipe ø up to 160mm and 450 mbar on pipe ø 200mm and above (SDR33) 800m bar on pipe ø 200mm and above (SDR26)

III. Filling Ratio Not below 60% water

IV. Water Velocity Not below 0.7 m/sec

a) Calculations should allow for rainfall intensity in accordance with relevant Australian Standard. For gutter installations, no reducing factor (e.g. run–off delay) shall be applied under normal conditions.

b) The pipework directly after the siphonic system should be designed to cope with the maximum discharge volume and high velocity from the siphonic system, using conventional gravity drainage formula.

c) The operation of the siphonic system shall be warranted by the manufacturer of the software calculation package.

d) The software must cater for each type/model of outlet specifically. Use of any other outlets than those listed in the calculation program is prohibited.

e) Overflows must be provided in order to operate in the event of an emergency and must discharge above maximum flood level on the outside of the building.

9.3 OUTLETS

The siphonic outlet shall be of the following type:

a) Consists of Polypropylene functional element and leaf guard with integrated stainless steel inlet plate with maximum capacity 14l/s.

b) Consists of aluminium cast, functional element, stainless steel inlet plate and HDPE connection with maximum capacity 25l/s.

c) The outlet shall be supplied with mounting plates suitable for the roof construction and compatible with the waterproofing membrane being used for the roof.

Advanced Engineering Building Hydraulic Services

Siphonic Drainage System – Section 9

Section 9 - Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

d) All roof outlets shall operate at the maximum capacity with a retained water head not exceeding 55mm in accordance with EN Standard.

e) Under maximum design rainfall conditions, the minimum capacity the roof outlet must receive to function siphonically at 1 litre per second for 14l or 8 litres per second for 25l model.

f) The use of outlets >25l/s is prohibited for any gutter installation due to increased risk (as per EN Standard).

9.4 PIPES AND FITTINGS

a) All pipes and fittings to be of High Density Polyethylene, HDPE (Density 951 – 955 kg/m

3) to DIN 19537, DIN 8074, DIN 8075 and carry a BBA agreement certificate.

b) All materials should be manufactured under a BS 5750/ISO 9000 approved scheme.

c) All component parts of the system including the outlets, pipes and fittings shall be from one source of manufacturer and shall be covered by manufacturer‟s warranty.

d) All pipes and fittings must be capable of withstanding the negative pressure produced by the siphonic action and certified suitable for this purpose by the manufacturer.

e) HDPE pipes must be annealed in order to reduce the mechanical stress on joints and fixations.

f) All HDPE pipes must be manufactured in accordance to the material specification by the manufacturer.

g) All HDPE materials must be warranted by the manufacturer.

h) Only injection moulded fittings must be used. For large bore fittings, exceptions might be approved under condition that segments are manufactured and welded in the production plant under the same stringent manufacturing certifications (ISO 9000, ISO 14000).

i) All fastening system materials to be galvanized mild steel and must be capable of withstanding all stress produced by thermal expansion, contraction, weight and vibration.

9.5 INSTALLATION

a) All pipe and fitting joints including the joint to the outlet to be fusion welded by electro weld-sleeve coupling.

b) All bends, throughout the system, to be of 45°, except for the first bend after the outlet, which has to be of 90°.

c) Anchor brackets (or fixed point) must be provided at each section when the pipeline changes orientation. The anchor bracket must be stronger than the expected expansion or contraction forces.

d) Intermediate guide brackets must be provided at the following intervals.

I. Vertical installation – max. 15 times pipe ø

II. Horizontal installation - max. 10 times pipe ø

III. Lateral fixation at reasonable intervals to prevent vibration

a) Connection of underground pipe directly into the open or closed surface drain must be above the critical water level designed for the maximum rainfall intensity.

b) Where pipes penetrate through fire compartments, built in fire sleeves must be provided in accordance with local standards and Building Regulations.

c) The installation can only be performed by the manufacturer‟s approved installers.

Advanced Engineering Building Hydraulic Services

Siphonic Drainage System – Section 9

Section 9 - Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

9.6 WARRANTY

a) The contractor shall provide a Warranty certificate for the completed installation against any defects of materials and workmanship. The contractor shall rectify any defects discovered during this warranty period at no cost to the owner.

b) The warranty certificate issued for the completed installation shall be valid for a period of 10 years commencing upon the Certificate of Practical Completion of the project.

9.7 TESTING PROCEDURE

All work that is to be concealed should be tested before it is finally enclosed. Test for soundness should be applied to all internal pipework. The internal rainwater pipes should be tested with the system connected to the conventional drain and then plugged off at the access pipe on the base of the stack. The system should then be filled with water and left to stand for 5 minutes after which time the system should be checked visually for evidence of leaks.

When access pipes and expansion sockets are part of the system to be tested then care should be taken not to exceed an internal static head pressure of 2 bar.

9.8 MAINTENANCE

Rainwater installations should be maintained regularly in accordance with the manufacturer‟s recommendations and in compliance with Australian Standards Code of Practice.

Rainwater pipes, outlets, and gratings should be inspected and thoroughly cleaned twice a year, or more often if the building is in or near industrial area, or is near trees, or may be subjected to extremes of temperature.

Advanced Engineering Building Hydraulic Services

Domestic Cold Water Systems – Section 10

Section 10 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

DOMESTIC COLD WATER SYSTEMS 10.

10.1 GENERALLY

Supply, install, test and commission all domestic cold water pipes from the branch connection off the private main to all fixtures, fittings and faucets requiring domestic cold water. Include for all pipework, bends, offsets, brackets, pumps, taps and faucets and sundry equipment required for the installation.

Supply all meters on site, complete with all valves and fittings as required.

10.2 WATER MAIN CONNECTION

A capped and valved branch connection shall be provided under the civil scope. Excavate, locate and connect to the new branch connection off the water mains for the services as required and extend to the reticulation.

10.3 VALVES (IN-LINE)

To pipelines supplying cold water to each group of fixtures, supply and install valves for the purpose of shutting down the system for isolation and maintenance purposes as specified in “Materials” and “Schedules” sections.

Locate valves behind access panels or within accessible ducts. Valves located in ground shall be provided with valve pit and galvanised infill lid.

10.4 CONNECTION TO FIXTURES

Provide isolation valves and unions at wall or floor surface and at all fixtures and appliances to allow removal and replacement without the need to adjust connections.

10.5 THRUST BLOCKS

To all changes of direction on rubber ring jointed pipelines below ground install concrete thrust blocks to restrain the internal operating pressures of the pipeline under all conditions. Concrete mass shall be poured around and behind fittings and bear against virgin soil material. A minimum of 0.75 cubic metres of concrete shall be used at each position.

10.6 TESTING

Provide a water pressure test of 1500 kPa for a period of two hours. Disconnect any equipment connected to the service not rated to the test pressure, before testing commences.

10.7 TAPS AND FAUCETS

Supply and fix the taps and faucets specified in the “Schedule” section. All taps and faucets shall have Watermark approval.

Unless indicated otherwise taps and faucets shall be all brass construction. All connections and cover plates shall be bright chromium plated finish. Taps shall be fitted with anti-splash nozzles, except for hose taps and/or where otherwise specified.

Advanced Engineering Building Hydraulic Services

Domestic Cold Water Systems – Section 10

Section 10 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

10.8 FLUSHING & CLEANING OF WATER SUPPLY SERVICES

Immediately after the satisfactory completion of the sectional/first fix and the whole system/final fix hydraulic pressure tests the Hydraulics Sub-contractor shall flush out, remove all foreign matter and clean all the systems. Water systems shall be flushed out with clean water. Whenever possible the flushing medium shall be fed into the system at high points and flushed out at low points on the system via suitably sized valve or plugged wash-out points. The flushing and cleaning medium shall be fed into the system at the highest pressure that the system will safely withstand and be carried out for a sufficient period of time to ensure that all foreign matter is removed. The flushing shall be witnessed by the Superintendent for the duration of the flushing of each service and shall be recorded by the Hydraulics Sub-contractor and certified by the Contractor.

10.9 BACKFLOW PREVENTION

Supply and install approved, dual RPZDs in parallel, in the domestic cold water supply as specified in the “Schedules” section.

Sub-Contractor is to maintain device for a period of 12 months and will include maintenance instructions in as-built manuals to be supplied at end of project establishing an authorised maintenance programme including registration and certification of all installed devices.

Provide isolation valves (gate) upstream and downstream of valve.

Flush piping before installing device and test device after installation and prior to operation in service.

10.10 HOSE TAPS

Provide and install hose taps with anti-vandal heads.

Each tap shall consist of a 20mm diameter copper riser with a back plated elbow and a 20mm diameter brass finish hose tap. The tap shall be 450mm above the floor unless otherwise directed.

10.11 FIRE SPRINKLER SUPPLY

Allow to provide a water supply connection from the cold water service in size as nominated on the drawings and terminate with a blank Table E flange at the sprinkler control valve room.

Advanced Engineering Building Hydraulic Services

Domestic Hot Water & Warm Water Services – Section 11

Section 11 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

DOMESTIC HOT WATER & WARM WATER SERVICES 11.

11.1 GENERALLY

Supply, install, test and commission the domestic hot water service and warm water service from the hot water heaters to the fixtures and appliances. Include for all piping, fittings, supports, insulation, hot water heat exchangers, valves, circulating pumps and other sundry items of equipment required for the installation.

The new hot water system shall consist of a flow and return system from the hot water plant where indicated on the drawings. The hot water is to be circulated at 65°C. Thermostatic mixing valves will be located in all other areas to maintain the water at 50°C or 43°C.

All pipes shall be insulated as specified in “Schedules” section.

11.2 TESTING

Provide a water pressure test of 1500 kPa for a period of two hours. Disconnect any equipment connected to the service not rated to the test pressure before testing commences.

11.3 CONNECTIONS TO FIXTURES

Provide unions at wall or floor surface and at appliances to allow removal and replacement without the need to adjust connections.

11.4 CONTROL VALVES

Supply and install control valves to each group of fixtures. Locate behind access panels or within accessible ducts.

11.5 EXPANSION AND CONTRACTION

Make adequate provision for expansion and contraction by the provision of clips/brackets with wooden expansion blocks so that under all working conditions no strain is imposed on pipework or fittings, Pipes located in walls and floors shall be provided with sufficient insulation so that expansion and contraction does not impose a strain on the pipework or finished surfaces. No joints will be allowed within or under concrete slabs where slab is on ground.

Branch pipes off straight lengths of unrestrained supply pipes shall incorporate a minimum of 3 long radius pipe bends and a straight length of pipe not less than 1000mm long between the branch connection and the first branch pipe restraint to facilitate movement of the supply pipe without imposing strain on the pipe connections and fittings.

11.6 VALVES

Refer to “Schedules” section for valves.

11.7 THERMOSTATIC MIXING VALVE

Supply and install thermostatic mixing valves to all personal hygiene fixtures to manufacturers requirements and in accordance with the local authorities requirements. Valves shall be set to 43°C.

TMV to be installed for all laboratory handbasins and wash troughs, PWD handbasins and showers and cyclist showers.

All valves to comply with those specified in “Schedules” section.

Advanced Engineering Building Hydraulic Services

Domestic Hot Water & Warm Water Services – Section 11

Section 11 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

11.8 HOT WATER HEATERS

Supply and fix the hot water heat exchangers in the locations indicated on the drawings. Heat exchangers shall receive heat from the mechanical heating plant via a set of flow and return pipes. Circulation pumps, controls and boosting of the heating system shall be part of the mechanical scope.

Heat exchangers shall have dual stainless steel hot water coils within the heat exchangers – one potable and one non-potable system.

Provide heaters with dial thermometers on the cold water inlet, hot water outlet as well as the flow and return lines from the mechanical plant.

Heat exchangers shall be manifolded such that balanced flow across all exchangers is achieved.

Heater sizes and duties are to comply with the “Schedules” sections.

11.9 HOT WATER CIRCULATING PUMP

Supply and install a hot water circulating pump to the requirements as specified in the “Pumping” and “Schedules” sections.

11.10 THERMAL INSULATION

Provide all necessary insulation to hot water piping to prevent heat loss.

Insulation shall not be installed until all relevant tests and inspections have been carried out.

Insulation shall be as specified in the “Schedules” section.

The pipe insulation shall comprise closed cell polymer foam and shall be installed around the pipework surface as tightly as possible without gaps, with the edges and ends tightly butted together.

All joints shall be taped using a 75mm adhesive backed tape or, if faced with aluminium foil, joints shall be taped using a 75mm pressure sensitive aluminium tape. Where necessary the preformed sections shall be cut (using a sharp knife or scissors) and mitred, to ensure a tight fit around bends and at tees. Joints in insulation and at brackets, bends, along longitudinal joints and elsewhere at 500mm centres shall all be taped as described above.

At union flanges, valves and strainers, or any areas share access is required for maintenance; insulation shall incorporate the press seal fastener system.

Where supports and spacer blocks are used to support the pipework, the pipe insulation shall be butted tightly up to the spacer blocks and sealed using a silicon sealant.

Apply insulation in accordance with manufacturer‟s instructions in a neat and workmanlike manner so as to present a smooth even finish.

Provide timber blocks at brackets to ensure even support without affecting insulation.

Insulation to piping chased into walls to be 10mm Ableflex or approved equal. Ensure that such insulation permits adequate expansion and contraction.

Advanced Engineering Building Hydraulic Services

Natural Gas – Section 12

Section 12 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

NATURAL GAS 12.

12.1 GENERALLY

Supply, install, test and commission the gas service from the point of connection to all gas points. Extend as specified supplying all regulators, filters, pipework and sundry items to complete the system to comply to the local gas authorities regulations.

Carry out the gas installation in accordance with the requirements of the regulatory authorities and relevant codes.

12.2 AUTHORITIES’ APPROVALS

Provide documents evidencing approval of regulatory authorities before Practical Completion.

If the responsible authority is required to or, pursuant to the powers vested in it, elects to perform or supply part of the Works, make the necessary arrangements with the authority and pay and bear the fees payable in connection therewith.

12.3 INSPECTION

Give sufficient notice so that inspection may be made at the following stages, where applicable:

a) Works ready for specified testing.

b) Enclosed work ready to be covered up or concealed.

12.4 GAS SERVICE SYSTEM

Provide a system of piping to supply both medium and low pressure (30.0 / 3.0 kPa) natural gas from the authority meter location, and reticulate through the building to the mechanical hot water heaters, laboratories (low pressure) and the gas fired electrical generators (medium pressure). The system shall be complete with all connections, filters, regulators required to form a fully functional authority approved system, and as further specified under this part and as generally shown on the drawings.

12.5 MATERIALS

Pipework, valves and regulators shall be as specified in the “Schedules” section.

12.6 REGULATORS

Provide over-pressure shut off (OPSO) regulators as indicated on drawings and in accordance with associated standards.

Regulators shall be capable of passing the required megajoules and delivering the required supply pressure.

12.7 TESTING

Carry out the required tests in the presence of the Contractor and an authorised representative of the relevant authority. Supply the apparatus and materials necessary. Submit the test results in writing. Replace and retest components, if any, which fail the required test.

Seal off items of equipment not designed to withstand the test pressure. Securely anchor pipes and fittings in position to prevent movement during the tests.

Do not cover or conceal work until it has been tested. Leave pipe joints exposed to enable observation during the tests.

Advanced Engineering Building Hydraulic Services

Natural Gas – Section 12

Section 12 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

12.8 COMPLETION

On completion of installation and testing, turn on isolating and control valves, and purge and charge the installation.

Hand over the installation fully charged with gas.

12.9 ACCESSIBILITY

Locate pipe fittings requiring maintenance or servicing, including control valves, joints designed to enable removal of pipes, and the like, in accessible positions with adequate clearance and ventilation.

As far as practicable install components such as pipe fittings so that they are removable without damage either to themselves or to the building structure or finishes.

12.10 INSTALLATION

Connect to authorities gas meter in an approved manner in accordance with relevant standards.

Provide adequate ventilation to all areas where gas appliances are installed to AS 5601.

Install regulators in the positions indicated on the drawings an under and over pressure shut-off regulator with the capacity to pass the required amount of gas reducing the pressure from 210 kPa to 5kPa or 2.75 kPa.

Regulators are to be the OPSO type and be capable of delivering the required megajoule rating and be vented to the requirements of the Gas Authority.

Allow to purge the pipework in accordance with standards and local authorities.

Gas pipework shall maintain a gradient of 1:230 unless otherwise indicated or directed by the gas authority. The graded pipes are to grade to low points terminating in a tail pipe with a 20mm capped valve in an approved easily located and nominated position.

12.11 GAS – SYSTEMS SHUT OFF

Supply and fix automatic shutdown control with bypass, as approved by the local Authority and the QFRS, to shut down the gas supply if any automatic fire sprinkler or thermal alarm is activated.

Automatic shutdown equipment shall incorporate valves, motorised valves, pressure switch, flanges and other items of equipment necessary to suit the requirements of the QFRS. The Electrical Contractor will connect control wiring from the emergency power supply for power operation of motorised valve. The whole equipment shall shut down the gas supply on the operation of the automatic over protection system and must be reset manually before gas supply can be stored.

Provide a set of voltage free alarm contacts to the Gas Service Automatic Shutdown valve for connection to the Building Maintenance System by the BMS Contractor. The Shut-Off system is to be similar to those manufactured by SCE Systems 3.

12.12 CONNECTION TO GAS HEATERS, APPLIANCES, EQUIPMENT AND OUTLETS

Provide and install all gas piping, appliance or equipment gas control valves, gas appliance regulators, stainless steel flexible pipe connections, gas unions and ancillary fittings for all gas burning appliances and other equipment or machines wherever located in the building to ensure the full operation of these items of equipment.

Advanced Engineering Building Hydraulic Services

Natural Gas – Section 12

Section 12 – Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Before connecting gas to gas heaters, appliances and equipment ensure that the appliance is approved in accordance with the requirements of the Qld Gas Examiner and is correctly installed and that all supports, flues, connections, flame failure devices comply with the regulations.

12.13 UNDERGROUND INSTALLATION

During backfilling lay warning tape 300 mm above, and for the full length of, buried gas pipes.

Warning tape: Minimum 100 mm width, of durable plastic material with 316 stainless steel tracer wire , colour to AS 1345, with "GAS PIPE UNDER" marked continuously.

Marker plates are required. Provide brass marker plates at ground level at each change of direction in the underground pipeline, engraved to show the direction of the line and name of the service. Inset the marker in a 150 x 150 x 150 mm concrete block, with the top set flush with ground level.

Reinstate the ground surface to the original condition and to match adjacent surfaces.

12.14 VALVE BOXES

Supply and install valve boxes for access to underground valves. The boxes shall be standard cast iron boxes with hinged covers. Set tops flush with pavement surfaces, or 15 mm above unpaved surfaces. Provide an in situ concrete surround 150 mm thick, to the top, bottom and sides of the box, with exposed surface steel trowelled. Set a shaft of pipe beneath each box to give access to the valve. Stamp the box cover with the word "GAS".

12.15 PIPING

If practicable, install piping so that it is concealed within service ducts or non-habitable enclosed spaces and does not appear on external walls. Otherwise, provide metal piping mounted on metal brackets and provide metal cover plates at penetrations. For piping embedded in concrete, install in continuous lengths without fittings. Do not lay across joints between adjoining sections of concrete through which reinforcement does not extend.

12.16 PITS

For below ground, house control valves in concrete access pits with removable pit covers.

Pits to be constructed to give 300mm clear space all around the fittings in the pit.

Use Grade N20 concrete to AS 1379, 100mm thick, reinforced with F82 fabric with concrete covers to AS3996. Mark pit covers with the work „GAS‟.

Grade floor to a point on one side and provide a gravity drain to remove water from the pit. Do not connect the drain to other substructures or drains. Carry the pit walls up to 50mm above finished ground level. Cast in the pit cover frame flush with the top. Trowel the top smooth.

Advanced Engineering Building Hydraulic Services

Fire Hydrant Service – Section 13

Section 13 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

FIRE HYDRANT SERVICE 13.

13.1 GENERALLY

Supply, install, test and commission the Fire Hydrant Service from the incoming water main to all fire hydrants required.

Include for all piping, fittings, valves, hydrant valves, pumps, control equipment electrical wiring and other sundry items of equipment as required for the installation in accordance with the Building Code of Australia and AS 2419. Provide a flow test to comply with AS2419.1.

After commissioning of the installation submit a Form 16 certificate to the Contractor certifying the installation.

To all changes of direction below ground where DICL fillings are used, supply and construct concrete thrust blocks of sufficient size, design and location to prevent movement of the pipeline by means of the internal pressure. Thrust blocks shall be as specified under “Domestic Cold Water”.

All gate valves installed on the fire hydrant piping system shall be “remotely monitored” gate valves with electronic anti-tamper devices. Fire trip wiring to the FIP to be by the fire services contractor.

13.2 FIRE BRIGADE BOOSTER CONNECTION

Supply and install an approved bronze hydrant booster valve complete with:

a) Pressure gauge

b) Main isolating valve

c) Full way non-return valve

d) Fire Brigade supply and discharge connection points

e) Connections to be to QFRS requirements with threads protected by loose brass screwed caps fitted with brass security chains.

f) Block plan of the system as specified in AS 2419.

g) Notice of pressures

h) Bleed valves

i) Direction of flow arrow welded to pipe surface.

The booster assembly is a precinct booster. The booster is to connect back into the precinct fire main.

13.3 INTERNAL HYDRANTS

Supply and install internal landing valve hydrants in approved locations in accordance with the requirements in AS2419. Install hydrants clear of fire egress path.

13.4 EXTERNAL FIRE HYDRANTS

Install each external hydrant on a 100mm riser complete with a 450 x 450 x 100 thick concrete base finished 25mm above ground level. Locate hydrants at least 10m away from building unless protected by a fire rated surround. Two hydrant valves shall be provided on each hydrant riser. Hydrant outlets to be 750mm above ground, fitted with a brass cap and chain and angled down at 35° to the horizontal.

Advanced Engineering Building Hydraulic Services

Fire Hydrant Service – Section 13

Section 13 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

13.5 MATERIALS

All pipework and valves shall be as specified in “Schedules” section.

13.6 TESTING OF PIPEWORK

Test all pipework 1700 kPa for a period of two hours. On completion, test the installation under full supply conditions all to the satisfaction of the QFRS and the Contractor. Record pressure and flow results and advise, in writing, to the Contractor.

13.7 TEMPORARY FIRE PROTECTION (DURING CONSTRUCTION)

Provide fire extinguishers and an operational fire hydrant system in accordance with the BCA Part E.

13.8 THRUST BLOCKS

To all changes of direction on rubber ring jointed pipelines below ground install concrete thrust blocks to restrain the internal operating pressures of the pipeline under all conditions. Concrete mass shall be poured around and behind fittings and bear against virgin soil material. A minimum of 0.75 cubic metres of concrete shall be used at each position.

13.9 VALVES

Supply and install all valves as specified in the „“Schedules” section.

13.10 FIRE HYDRANT TEST DRAIN

Supply and install pipework, couplings and connections as required for the fire hydrant test drain as shown on the drawings and in accordance with QFRS requirements.

Advanced Engineering Building Hydraulic Services

Hose Reel Service – Section 14

Section 14 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

HOSE REEL SERVICE 14.

14.1 GENERALLY

Supply, install, test and commission the hose reel service from the point of connection to all fire hose reels all in accordance with the BCA, AS 1221 and AS 2441.

Extend as specified, supplying all fittings, valves, brackets, pumps and sundry items to complete the installation including the hose reels to the approval of the Queensland Fire and Rescue Service, the local Council and the Contractor.

After commissioning of the installation submit a Form 16 certificate to the Contractor certifying the installation. Provide a flow test certificate to comply with AS1221 section 3.2.4.

14.2 MATERIALS

Pipework shall be as specified in the “Schedules” section.

14.3 FIRE HOSE REELS

Hose reels shall be wall mounted containing 36m of 20mm internal diameter fabric reinforced non-kinking rubber hose with adjustable nozzle. The reels shall be fitted with a gunmetal hub, red baked enamel mild steel side plates and stainless steel spacing rods and shall be in accordance with AS 1221

The hose shall be led off by a fair lead to give a completely free withdrawal in any direction by one person and mounted 1500mm AFFL to the centre of the hub.

The hose shall be supplied with water from the water service through a 25mm screw down loose jumper type valve fitted with a union between valve and reel for maintenance purposes. The nozzle shall be attached to the valve by a device so that it cannot be removed until water supply is turned on.

The hose shall operate with a minimum running pressure of 200 kPa at the outlet of the nozzle when the hose is fully extended.

Fire hose reels shall be provided in accordance with the BCA requirements. The system shall also be approved for use by the certifying authority.

Advanced Engineering Building Hydraulic Services

Rainwater Re-use System – Section 15

Section 15 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

RAINWATER RE-USE SYSTEM 15.

15.1 GENERALLY

Supply, install, test and commission the rainwater re-use service from the rainwater harvesting tank to the fixtures. Include for all piping, fittings, supports, filters, treatment devices, valves, pumps and other sundry items of equipment required for the installation.

The rainwater re-use system shall consist of a storage tank and pumps where indicated on the drawings. The rainwater is to be circulated through the building. Rainwater shall be provided only to WC cisterns and urinals throughout the building.

Supply, install and commission a main‟s water bypass via solenoid valve operated by the pump control pressure sensor to ensure sufficient water in the rainwater tank to supply the system. The main‟s water top-up shall be metered separately.

15.2 TESTING

Provide a water pressure test of 1500 kPa for a period of two hours. Disconnect any equipment connected to the service not rated to the test pressure before testing commences.

15.3 CONNECTIONS TO FIXTURES

Provide unions at wall or floor surface and at appliances to allow removal and replacement without the need to adjust connections.

15.4 EXPANSION AND CONTRACTION

Make adequate provision for expansion and contraction by the provision of clips/brackets with wooden expansion blocks so that under all working conditions no strain is imposed on pipework or fittings, Pipes located in walls and floors shall be provided with sufficient insulation so that expansion and contraction does not impose a strain on the pipework or finished surfaces. No joints will be allowed within or under concrete slabs where slab is on ground.

Branch pipes off straight lengths of unrestrained supply pipes shall incorporate a minimum of 3 long radius pipe bends and a straight length of pipe not less than 1000mm long between the branch connection and the first branch pipe restraint to facilitate movement of the supply pipe without imposing strain on the pipe connections and fittings.

15.5 MATERIALS

Pipework shall be as specified in the “Schedules” section.

15.6 VALVES

Refer to “Schedules” section for valves.

Advanced Engineering Building Hydraulic Services

Hydraulic Laboratory Flume Reticulation and Pumps – Section 16

Section 16 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

HYDRAULIC LABORATORY FLUME RETICULATION AND PUMPS 16.

16.1 GENERALLY

Supply, install, test and commission Hydraulic Laboratory Flume Reticulation System, to supply flumes with water from sumps and/or header tank. Include for all piping, fittings, supports, thrust-bracketry, valves, pumps, electrical control panels and other sundry items of equipment required for the installation.

The following flumes shall be supplied under gravity from the Header Tank [40,000 litres] which is located on Level 2 :

(a) Broad Crested Weir Flumes [3 no]

(b) Culvert Flumes [3 no]

(c) Hydraulic Jump Flumes [3 no]

(d) Channel Flumes [3 no]

(e) Plunging-Jet Flume

These flumes drain to a central in-ground sump [100,000 litres], from where water is pumped back to the Header Tank via three delivery mains.

Water shall be supplied to a Large Tilting Flume from the central in-ground sump, via submersible pumps. This flume shall drain back to the sump.

Water shall be supplied to the Plunging-Jet Flume from the central in-ground sump [as well as from the Header Tank], via a submersible pump. This flume shall drain back to the sump.

Water shall be supplied to the Large Stepped-Spillway Flume, from its own dedicated in-ground sump, via submersible pumps. This flume shall drain back to its own sump.

Supply, install and commission a main‟s water top-up to each in-ground sump.

All pump status, and sump water levels associated with the Hydraulics Laboratory shall be monitored and communicated to a central Control Office in the Laboratory/.

16.2 MATERIALS

Pipework to and from flumes and pumps shall be PVC pressure pipe rated PN 6, with solvent-welded joints. Adequate allowance should be made for pipe bracketry, ensuring pipes are secure and supported in accordance with the manufacturer‟s specifications. In particular, pipe bends and changes in direction shall be secured with adequate thrust brackets. Where pipes are installed vertically, from high level to flume inlets or sumps, they shall be supported securely along the vertical length, and restrained adequately against all thrust and movement, caused by flow within pipework.

Where indicated in the drawings, pipework fittings cast into concrete shall be grade 316 stainless steel. Flanged connections shall be provided between steel and PVC pipe fittings.

The Stepped Spillway Flume includes a stainless-steel diffuser, through which the pumped delivery discharges. This diffuser was used in the previous Hydraulics Laboratory, and has been retained for use in the new facility. The Contractor shall liaise with UQ and take possession of the diffuser, which shall be built into the works.

16.3 TESTING

Flume pipework and pumps shall be tested, and compliance with the specified delivery rates shall be demonstrated [see pump duties in Section 21].

In addition, flume pipework shall be tested hydrostatically to 1,5 times the working pressure for at least 30 minutes to confirm integrity of pipe joints and flange gasket seals.

Advanced Engineering Building Hydraulic Services

Hydraulic Laboratory Flume Reticulation and Pumps – Section 16

Section 16 – Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

16.4 VALVES

Valves to flume delivery pipework shall be flanged butterfly valves. Valves to be pointing downwards and at 2100mmm AFFL.

16.5 IDENTIFICATION OF PIPEWORK

In addition to the requirements of Section 17.32, all flume pipework shall be clearly labelled, with direction of flow and flume name, or Header Tank overflow, as necessary.

16.6 HEADER TANK LINING

After the installation of all pipework, penetrations and the like, apply a liquid rubber waterproof membrane to the tank. Lining to extend to 300mm above top water mark.

Lining shall be non PVC based and comply with the requirements for VOC content and ODP emissions.

16.7 PUMP CONTROL PHILOSOPHY

The following philosophy shall be applied to flume pump operation:

a) Main In-Ground Sump Pumps

On manual start-up, these pumps shall deliver a low flow of 10L/s, to intitiate an overflow condition in the Header Tank. As flume valves are opened and flows from the Header Tank to the Flumes increase, the delivery of the pumps shall increase automatically to ensure that the top water level in the Header tank remains constant, and conversely as Flume valves are closed, the delivery shall decrease accordingly, until to the low flow condition is achieved. The pumps shall therefore be controlled from the top water level in the tank. The Control Panel housing the pump controls and VSD‟s shall be located on Level 1 at the Sump. The Control Panel shall include an emergency stop button.

b) Stepped-Spillway Flume Sump Pumps

On manual start-up, these pumps shall deliver a low flow of 25L/s down the stepped spillway of the Flume. The Control Panel housing the pump controls and VSD‟s shall be located on Level 1 at the Sump. A remote control panel shall be located on the Flume, to allow for adjustment of pump speed and therefore flow, by way of a dial or touch sensor, up to the maximum flow. The remote panel shall include an emergency stop button.

c) Large Tilting Flume Sump Pumps

These pumps shall be located in the large in-ground sump, at the Tilting Flume. On manual start-up, these pumps shall deliver a low flow of 5L/s down the Tilting Flume. The Control Panel housing the pump controls and VSD‟s shall be located on Level 1 near the Tilting Flume. A remote control panel shall be located on the Flume, to allow for adjustment of pump speed and therefore flow, by way of a dial or touch sensor, up to the maximum flow. The remote panel shall include an emergency stop button.

d) Plunging Jet Flume Pump

This pump shall be located in the large in-ground sump, at the Tilting Flume. On manual start-up, the pump shall deliver a low flow of 5L/s to the Plunging Jet Flume. The pump controls and VSD shall be located in the same Control Panel as those of the Tilting Flume pumps, on Level 1 near the Tilting Flume. A remote control panel shall be located on the Plunging Jet Flume, to allow for adjustment of pump speed and therefore flow, by way of a dial or touch sensor, up to the maximum flow. The remote panel shall include an emergency stop button.

Advanced Engineering Building Hydraulic Services

CONCRETE CURING LABORATORY – Section 17

Section 17 – Page 4

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

CONCRETE CURING LABORATORY 17.

17.1 GENERALLY

Supply, install, test and commission Concrete Curing Tanks, Heating and Recirculation System. Include for all piping, fittings, supports, thrust-bracketry, valves, pumps, electrical control panels and other sundry items of equipment required for the installation.

The entire installation shall comply with AS 1012.13-1992 : Methods of testing concrete - Determination of the drying shrinkage of concrete for samples prepared in the field or in the laboratory. The contractor shall provide a certificate of compliance in accordance with the abovementioned standard for the system operation.

17.2 INSTALLATION

The Concrete Curing Laboratory on Level 2 shall contain two tanks, which will be used for the immersion and curing of concrete samples in lime-saturated water. The tanks shall accommodate 2 layers of concrete cylinders 150mm diameter and 300mm high, with adequate racking and clearance space between layers. The installation shall comprise the following :

a) Two GMS curing tanks of nominal internal dimensions 1,9m long x 0,8m wide x 0,6m deep. Each tank shall have a drain and overflow. A grating shall be provided 50mm above each tank floor, to support fully laden sample racks, of total mass 350kg.

b) Each tank shall include a heating element and tank-mounted control panel, to maintain a constant water temperature of 27°C.

c) Water circulation pumps, .

d) An automatic pH monitoring system. pH and temperature controls shall be provided inside the Laboratory, with digital read-out of tank pH and water temperatures. In addition, a digital readout of tank water temperatures shall be provided outside the Laboratory. Audible and visible alarms shall be mounted on the outside of the room to alert operators to deviation in pH or temperature. pH and temperature data shall be logged electronically on a an hourly basis for a 7-day cycle. The monitoring system shall be linked back to the BMS for “out of range” alarm on both temperature and pH.

e) Eight immersible and stackable sample racks per tank, each of approximate dimensions 450mm x 900mm. Three spare racks shall be provided.

f) Suitable frame with which to raise racks from floor level and into each tank, by means of overhead electric hoist [supplied by others]. The frame and racks must all accommodate a fully laden load of 350kg.

g) A drainage rack on rails shall be provided to the top of each tank.

h) Polystyrene sheets, 80mm thick, to float on tank water surface, providing thermal insulation, over entire water surface.

17.3 PROCUREMENT

The above installation shall be procured from, and installed by, Geo-con Products (Pty) Ltd, through the Hydraulics scope of work.

17.4 SCHEDULE OF EQUIPMENT

Refer section 29.2 for details.

Advanced Engineering Building Hydraulic Services

REVERSE OSMOSIS WATER SYSTEM – Section 18

Section 18 – Page 5

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

REVERSE OSMOSIS WATER SYSTEM 18.

18.1 GENERALLY

Supply, install, test, commission and sanitize all reverse osmosis water pipes from the reverse osmosis plant as indicated on the drawings, to all fixtures, fittings and faucets requiring reverse osmosis water. Include for all pipework, bends, offsets, brackets, pumps, tanks, taps and faucets and sundry equipment required for the installation.

Supply, install and commission reverse osmosis plant, pretreatment and storage to provide analytical grade Type II water.

18.2 WATER CONNECTIONS

At the point of connection to the potable water supply install an RPZD.

18.3 WATER METERS

At the point of connection to the potable water supply install a water meter.

The meter shall have pulse output and be connected to the BMS.

18.4 PIPEWORK

All pipework shall be fusion-welded. No bonding agents or solvents shall be used to effect connections.

18.5 VALVES (IN-LINE)

To pipelines supplying reverse osmosis water to each group of fixtures, fittings or equipment, supply and install valves for the purpose of shutting down the system for isolation, maintenance and disinfection purposes.

Locate valves behind access panels or within accessible ducts.

Valves normally closed shall be diaphragm valves, with no dead-leg.

Valves normally open shall be ball valves.

18.6 CONNECTION TO FIXTURES

Provide unions at fixtures and appliances to allow removal and replacement without the need to adjust connections.

Provide check valves at dishwasher connections to prevent backflow contamination of the loop.

18.7 TESTING

Provide a water pressure test of 1500 kPa for a period of two hours. Prior to testing, disconnect any equipment connected to the service that is not rated to the test pressure. Conform to testing requirements set out in “Preliminaries” section.

18.8 TAPS & FAUCETS

Supply and fix the taps and faucets specified in the “Schedules” section or as selected by the Architect. Unless indicated otherwise, taps and faucets shall be epoxy coated brass construction. All connections and cover plates shall be bright chromium plated finish. Taps shall be fitted with barbed nozzles and handles at the outlet otherwise specified. Material in contact with reverse osmosis water shall be limited to PP, PVDF or EP316 SS.

Taps shall comply with the following:

Advanced Engineering Building Hydraulic Services

REVERSE OSMOSIS WATER SYSTEM – Section 18

Section 18 – Page 6

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

a) Specific for use in reverse osmosis water systems

b) Incorporate an internal flow and return system with no dead legs

18.9 FLUSHING & CLEANING OF REVERSE OSMOSIS WATER SUPPLY SERVICES

Immediately after the satisfactory completion of the sectional/first fix and the whole system/final fix hydraulic pressure tests the Hydraulics Installer shall flush out, remove all foreign matter and clean all the systems. Water systems shall be flushed out with clean water. Whenever possible the flushing medium shall be fed into the system at high points and flushed out at low points on the system via suitably sized valve or plugged wash-out points. The flushing and cleaning medium shall be fed into the system at the highest pressure that the system will safely withstand and be carried out for a sufficient period of time to ensure that all foreign matter is removed.

18.10 SANITATION

Allow for all valves and fittings in the loop system. Complete sanitization of the pipework systems and allow for all labour, chemical and equipment as necessary. Allow to purge and dispose of chemically treated water. Test and confirm that no sanitant remains on the pipework once completed.

18.11 REVERSE OSMOSIS PLANT

a) Provide, install and commission a central Reverse Osmosis plant on Level 6.

b) The plant shall be a Millipore Elix water purification system, or equivalent, to provide ASTM Type II water, and must provide water > 1MΩ.cm @ 25°C.

The Hydraulics installer is to co-ordinate with the Supplier to provide a complete and satisfactory system.

The plant will comprise a skid mounted system complete with :

I. Elix Water Purification System

II. Pre-filters with carbon and filtration to 1 micron

III. Grundfos distribution pumps of CRN or CHI type only, with duty/standby configuration

IV. U.V. Tank Sterilization

V. 0.22um Loop filters appropriately sized to flow rate/pressure

VI. Back pressure relief valves

VII. BMS connection

VIII. R.O. water storage tank with overflow facility and vent filter

IX. Check valves

c) Provide in addition to plant and equipment :

I. Towns mains water supply with RPZD

II. Drains and tundishes

III. All Electrical supplies

IV. Tank support system

V. RO water plant and point of use outlets

Advanced Engineering Building Hydraulic Services

REVERSE OSMOSIS WATER SYSTEM – Section 18

Section 18 – Page 7

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

18.12 SYSTEMS

The system design parameters are.

a) Velocity 0.95m/s to 1.5m/s

b) Pressure 250-600kPa

18.13 MONITORING

Water quality shall be monitored at the return of the loop to the tank, and must be ASTM Type II grade or higher. Water quality in the loop shall not exceed 15MΩ.cm @ 25°C.

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 8

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

HYDRAULIC SERVICES GENERAL CONDITIONS 19.

19.1 PROTECTION OF PLANT AND MATERIALS

The Sub-Contractor shall be entirely responsible for all apparatus, equipment and appurtenances furnished by him or Sub-Contractors in connection with the works. Special care shall be taken to protect all such goods in a suitable manner.

The protection shall include covers to prevent moisture, grit, plaster or other foreign substances from entering the working part of plant and equipment. Seal and protect all open ends of piping and conduit (as applicable) whilst in storage and during course of installation, and to protect adequately all electrical and control equipment.

All materials, goods and equipment forming part of this Contract must be completed, intact and in new order when the Proprietor takes over the responsibility for the works, and it shall be the liability of the Sub-Contractor to safeguard such materials, goods and equipment until then.

19.2 CO-ORDINATION

Be responsible for co-ordination of all aspects of the work under the contract including but not limited to work associated with the preparation and submission of shop drawings, installation and commissioning of the hydraulic system, job progress schedule, and follow up all other trades without delay.

Immediately give notice of any dispute with other trades or problems anticipated in relation to the co-ordination of the work.

19.3 NUISANCE

No work shall be carried out or materials handled in such a manner as to cause nuisance on the site or to other Sub-Contractors or to occupants of adjacent buildings.

All work causing inconveniences to others shall have safety barriers, lights, warning signs etc in accordance with all relevant codes, standards, regulations etc.

19.4 MAKING GOOD

Be responsible for and make good any damage to building and surfaces generally and any other works that may be disturbed or injured by cartage, work generally or other operations. The reinstatement shall be with equal quality materials to the same standards of construction and expected life as existed prior to commencement of works.

19.5 DIMENSIONS ON SITE

Be responsible for taking all dimensions on site. The dimensions must be checked before work is commenced or prefabricated. All levels and dimensions of existing services must be confirmed before commencing work. The invert levels shown on the drawings are recommended only, and must be checked on site before excavation or installation of pipe work to ensure connection to supply sources and fall to pipe work etc. is correct.

19.6 PROTECTION OF PROPERTY

The Sub-Contractor shall be responsible for any damage to existing work on the site caused by the execution of the work of this Contract and shall pay all rectification costs involved.

Rectification of damage to the works of other trades shall not be undertaken by this trade but will be arranged by the Sub-Contractor to be carried out by the appropriate person, firm or Authority at the expense of this trade.

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 9

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

19.7 DAMAGE TO FINISHES

The Sub-Contractor shall be responsible for the refinishing or replacement of any part of this installation damaged prior to the installation being taken over by the Building Owner.

19.8 TESTS

The Contractor may at any time during the progress of the works, test and examine any materials used and inspect the workmanship employed, and may reject any materials and workmanship that are not in accordance with the specification and drawings.

The Sub-Contractor shall provide such assistance as may be required by the Contractor to carry out these tests, including facilities for inspection of works.

On completion the installations shall be tested in the presence of the Contractor and passed by all Authorities having jurisdiction over the works. Two (2) copies of all approvals and test certificates issued by the Authorities shall be submitted to the Contractor.

The Sub-Contractor shall provide all fees, labour, materials, power and instruments required for the purpose of carrying out tests, and shall make good at his own expense any defects disclosed during tests.

Tests shall generally be as follows:

a) During Manufacture

I. Every facility is to be afforded the Authorities and/or Contractor for the inspection of any part of the work or apparatus during the course of manufacture, and upon completion, testing is to be undertaken in the manufacturer's workshop as directed by the Contractor.

b) Hydrostatic Tests

I. All cold water piping shall be hydrostatically tested to a head of one and a half times the working head. Hydraulic (testing) pumps shall be disconnected immediately after pressurisation and all test heads shall be maintained until the Contractor has satisfied himself as to the soundness of the pipe work and equipment.

II. In no case shall the period of test be less than 30 minutes.

III. Before applying specified test head, all air shall be expelled from the piping being tested. If necessary, supply and install approved air relief valves for this purpose.

IV. Equipment is not to be connected to the respective services while hydrostatic tests are being carried out.

V. Provide a suitable pump and gauge and do all necessary work for carrying out the tests.

VI. All testing of cold water piping is to be carried out before:

1. Finishing trades have commenced their work;

2. Ceilings are installed;

3. Insulation of pipe work.

I. At completion of testing, all cold water lines shall be kept charged full of water at all times.

c) Choke Tests

I. All sanitary drains, stormwater drains, sanitary plumbing, rainwater pipes, shall be choke (water) tested by plugging at the lowest, or other approved positions and filling with water to the overflow level.

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 10

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

II. Choke tests shall be maintained until the Contractor and/or Authorities have satisfied themselves as to the soundness of the pipe work.

III. In no case shall be period of test be less than one hour.

IV. Fixtures are not to be connected to the respective services while choke tests are being carried out.

V. Provide all necessary plugs and do all necessary work for the carrying out of the tests.

VI. All testing of the above system shall be carried out before:

1. Finishing trades have commenced their work,

2. Ceilings are installed,

3. Backfilling has commenced,

4. Absorption into pipe wall is complete.

d) Fixtures

Fixtures shall be filled to spill level with water after installation and visually checked for leaks.

e) Test of Completion

Upon completion the Hydraulic works shall be tested under normal working conditions and as directed by the Contractor; such tests shall continue until the Contractor is satisfied that the terms of this specification has been compiled with and that the Hydraulic works are capable of meeting all requirements.

All defects disclosed during the tests shall be remedied immediately and, if required by the Contractor fresh tests shall be carried out.

The duration of the tests will be decided by the Contractor. The maximum duration of any one test will not exceed eight hours.

f) Generally

The Contractor shall be given seven (7) days clear notice that any system is ready for test.

Provide all equipment and technical, artisan and unskilled labour required for tests.

The Contractor reserves the right to check any aspect with his own equipment.

All tests shall be carried out in the presence of, and to the satisfaction of all local Authorities, as well as the Contractor.

g) Essential Services

Upon completion of the works, provide Essential Services Certification to the requirements of the Building Code of Australia for the following:

I. Fire mains and pumps.

II. Fire hydrants.

III. Fire hose reels.

IV. Fire extinguishers (where applicable).

The Sub-Contractor shall engage a competent and approved person to inspect and certify all essential services installed under their sub-contract and shall pay all associated fees and costs.

Inspections shall be carried out as follows:

I. At preparation of working drawings; and

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 11

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

II. Upon completion of system.

Notification shall be made to enable testing, certification and approval by the Local Fire Authority. Allow paying any associated fees.

A certificate of compliance for each essential service installed under their contract as per requirements of the BCA is to be obtained and forwarded to the Contractor upon completion of the works.

19.9 OCCUPATION

The Contractor reserves the right to take over any completed portion of the works for the purpose of installing equipment and fittings or for occupation and the Sub-Contractor shall co-operate with the Contractor and shall arrange his works to this end as required.

Such entry and occupation shall not constitute acceptance, shall not provide grounds for extension of time or for compensation and shall not relieve the Sub-Contractor of his responsibility to complete the Contract.

Where partial occupation occurs, the guarantee, warranty and defects liability period for the relevant sections of the services installations will operate from the date of such occupation.

19.10 NOTICE OF PRACTICAL COMPLETION

When, in the opinion of the Contractor the works are practically completed, the Contractor will issue to the Proprietor a "notice of practical completion", stating the date upon which the works were practically completed.

This date shall be the date from which the guarantee, warranty and defects liability periods as defined shall operate.

This notice will not be issued until the systems have been properly commissioned and until the Sub-Contractor has supplied operating instructions and "As Executed" drawings.

19.11 FIXTURE AND FIXTURE POINTS

Install and supply all materials, backing plate and noggins necessary to make all fixtures and fixture outlet points rigid (i.e. sanitary fixtures and tap fittings etc.). All fixtures shall be connected via a service pipe and union type fitting. Nut and olive connection is not acceptable. Direct connection of pipe work to the fixture will not be accepted.

19.12 PIPES IN SLAB

Under no circumstances shall any pipe work be cast in slabs, unless clearly noted on the drawings. Any hot and cold water pipes noted as being 'in slab' shall be contained in UPVC/polyethylene conduits and these pipes shall be totally retrievable.

The HDPE cast in concrete sanitary plumbing system shall be cast in without any sleeving or wrapping in accordance with AS 2033 and the manufacturer‟s requirements.

19.13 SETTING OUT

Set out and identify all trenches, pits, pipelines and plant equipment positions so that the Contractor may readily observe the location works.

Gain approval for the proposed location of the works from the Contractor prior to commencement of any excavation.

Larger scale drawings are to be used in preference to small scale where no dimensions are shown.

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 12

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Architectural dimensioned drawings are to be used in preference to scaled drawings regardless of their relative scale.

a) Trenches

Interpret all levels and grades to determine correct falls to pits and street connections. Advise the Contractor if grades cannot be met so that he may determine revised locations or grades for the works.

The set out of piping, pits and covers shall be arranged in conjunction with other trades so as to be readily accessible for operating, servicing, maintaining and repairing of it.

Under no circumstance shall the Authorities and/or the Contractor conceal any drainage pipes etc. before inspection and approval.

Piping, pits, etc. which are installed in unsuitable locations shall be removed and relocated as directed by the Contractor. All expenses caused by this action shall be made good without extra charge.

b) Core Holes

Set out all core holes and openings as required and necessary for the passage of pipes and/or conduits throughout the existing structure. Arrange for approval from the Structural Engineer to drill such holes or openings and pay all cost involved where required in existing slabs.

Core holes within "in situ" slabs shall be formed using "Gatic" preformed units installed in accordance with the manufacturer's instructions.

Do not cut any holes, openings, and chases or otherwise interfere with the work of other trades without the specific approval of the Contractor. Any damage done to other trades shall be made good without extra charge.

c) Cutting of Concrete Floor Slabs and concrete reinstatement

Set out lines of trenches and gain structural engineers approval before cutting slabs. Cut slabs to a minimum depth of 100 mm. Break out slabs and remove spoil form site.

Demolish slabs as required to enable excavation and installation of all hydraulic services.

Saw cut topping and structural slab in straight lines. The hydraulic service Sub-Contractor shall backfill and compact trenches etc, as specified. Reinstatement of slab will be by concreting Sub-Contractors.

The Hydraulic Services Sub-Contractor shall remove and dispose of demolished and excavated materials from demolition of topping, slab and trench excavations.

d) Accessibility

The set out of piping, valves and equipment shall be arranged in conjunction with other trades so as to be readily accessible for operating, servicing, maintaining and repairing of it.

In no circumstances shall the Authorities and/or the Contractor conceal any pipes, valves, etc. before inspection and approval.

Piping, valves, etc. which are installed in unsuitable locations shall be removed and relocated as directed by the Contractor. All expense caused by this action shall be made good without extra charge.

If neither the specification nor plans contain any mention of minor parts, which in the opinion of the Contractor are reasonably and obviously necessary for the satisfactory completion of the Hydraulic works, and then such parts are to be provided without extra charge.

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 13

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

19.14 CLEANING UP AND FINISHING

The site and precincts must be kept clean and tidy and all rubbish removed daily, or at the request of the Contractor to a location on each floor as nominated by the Contractor. At the conclusion of the work covered by this specification clear away and remove to the nominated locations all debris and rubbish and leave the complete installation thoroughly clean and capable of efficiently operating, to the entire satisfaction of the Contractor.

19.15 GENERAL PIPING INSTALLATION REQUIREMENTS

a) All screwed joints shall be made with the best quality pipe joint compound, carefully placed on the threads of the pipe and not through the fittings.

b) After cutting, all piping, burrs and sharp edges shall be reamed out.

c) Care should be taken when erecting piping; any marked, dented or otherwise damaged piping shall be replaced in a satisfactory manner.

d) Piping shall be installed as direct as possible between connecting points and parallel to walls.

e) Unless otherwise noted, all piping shall be kept as high as possible to beams, slabs, so as to maintain maximum headroom.

f) Obtain approved ceiling heights and install work to clear obstructions and co-ordinate with work of other trades.

g) Connections between pipe, fittings, hangers and equipment of dissimilar metals shall be avoided where possible.

h) Provide a minimum 3 mm thick extruded flexible PVC insulation between supports and service pipe of dissimilar materials and PVC piping. TAPE WILL NOT BE ACCEPTABLE.

i) Piping shall be carefully installed to provide for proper alignment, slope and expansion, guided and supported in such a manner so that piping will not sag, buckle or cause water hammer.

j) Provide unions or flanges at connections to each piece of equipment, etc. for easy dismantling and at such other points to facilitate installation.

k) All fittings and connections at pumps, tanks or other major equipment, 65 mm and over shall be assembled with flanged joints.

l) All unnecessary lengths of male threads located in exposed pipe work within exposed areas/rooms shall be trimmed to the minimum necessary lengths.

m) The Sub-Contractor shall allow for all necessary trimming and machining of threads to obtain the requirements of this clause.

n) Provide special (and approved) threaded sections where necessary.

o) Remove all unnecessary hemp or other jointing materials from joints.

p) Except where otherwise specified, mitred joints shall not be permitted.

q) The arrangement of all piping shall be generally as shown on the drawings.

19.16 SUPPORT AND FIXING OF PIPEWORK

REFER ACOUSTIC REPORT FOR REFERENCE TO SECUING OF PIPEWORK IN NOISE SENSITIVE AREAS.

Pipes shall be adequately supported and secured in an approved manner.

Pipes shall not be fixed to, supported by, or welded to other pipes.

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 14

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Pipe work must be free to move without causing stresses in the pipe work or pipe joints. Where provision has been made for movement in mains, the branch lines shall be unrestrained and in the case of copper tube, annealed for a minimum of 1500 mm from the main. Where this is not achievable, some other approved provision for movement shall be made.

Vertical pipes passing through floors shall be supported at maximum 2400 mm centres. Support horizontal pipes at maximum 1800 mm centres.

Support all pipes except sheet metal gutters and downpipes with galvanised concrete inserts, channels, and pipe clamps, and pipe hangers, etc. in accordance with the manufacturer's instructions and complying with the catalogue regarding spans and loads.

Secure all supports and necessary sanitary fixtures with approved "Rawlock" metallic anchors or equal.

Power-driven fixings, wooden plugs or screw-ins shall NOT be used.

19.17 BUILDING EXPANSION JOINTS

Crossing building expansion joints with pipelines shall be avoided where possible. Where this is not possible, lines adjacent to a building expansion joint shall be located in a readily accessible position and fitted with an approved expansion joint.

19.18 JOINTS IN COPPER PIPING

All joints in copper pipe work shall be made by brazing with low temperature silver brazing alloy containing not less than 5% silver (15% for gas piping). Use oxy-acetylene heating for all low temperature brazing.

Flux shall be as recommended by brazing alloy manufacturer.

Slip joints shall be permitted to join lengths of copper pipes and shall be made by annealing and expanding ends with a proper tool to form a slip (capillary) joint.

Fabricated tees or junctions in copper pipe will not be permitted.

Valves shall not be brazed direct onto pipes. Valves shall be indirectly joined to pipes by the use of flanged or screwed adaptors, which shall be silver brazed onto the pipe and then screwed to the valve. Care shall be taken to prevent distortion to the valve and/or valve seat.

19.19 CHASING AND DRILLING

Provide all the necessary chasing, cutting and drilling of brick walls, ceiling, etc. to allow the fixing and passage of pipes through the structure.

Chases to be saw cut before breaking-out or be cut with approved mechanical saws.

Set out in ample time all positions required after having established the position of the pipes and obtained approval for same from the Contractor.

After installation of piping within chases ensure that piping is properly fixed with copper or brass clips (ferrous fixing shall not be used) and chases made good with cement mortar. Ensure that adequate allowance is made for expansion and contraction by piping within chases.

Chasing shall be carried out as follows:

a) Brickwork shall have been built a minimum of 7 days prior to chasing.

b) Chasing shall be carried out using a machine specifically designed for the purpose. Do not use hand tools.

c) Chasing shall be on the same side of the wall and vertically above the outlet it serves.

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 15

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

d) Minimise horizontal chasing.

e) No chase shall be deeper than 35 mm or wider than 80 mm or 3 conduit pipes. Pipes shall be installed so they are approximately 5 mm below the surface of the bricks. Pipe sizes larger than 25 mm shall be provided with block outs in walls.

f) Where two or more chases are necessary in close proximity they shall be at least 100 mm apart.

g) No chases on opposite sides of a wall shall be within 150 mm of each other.

h) No notching or drilling through lintels, wall stiffeners, control joints or the like shall be made without the approval of the Superintendent.

i) All voids in chases shall be filled with sand/cement mortar prior to cement rendering. This work is the responsibility of the services Sub-Contractor.

j) All chases wider than 35 mm or serving 2 or 3 pipes shall be done without the approval of the Contractor.

k) No chasing shall be done in walls that are proposed to remain unrendered. These areas can be identified from the schedule of finishes. Where a wall is to remain unrendered, surface mount services to a configuration approved by the Contractor.

l) Do not chase Reinforced Concrete walls without the prior approval of the Contractor.

Where the above conditions cannot be complied with, immediately notify the Contractor and await instruction before proceeding.

Provide approved fire stop collars to all horizontal and vertical surfaces as necessary to equal the fire rating of the surrounding structure and comply with BCA and QFRS requirements. Use approved fire stop collars for “dry wall” construction and install strictly to the manufacturer‟s instructions.

19.20 CONCEALING

Generally, all piping is to be concealed by chasing or building-in and generally as indicated on the drawings.

19.21 GRADES

All grades and inverts indicated on the drawings shall be established with the use of approved surveying instruments.

Check the topography and finished floor elevations before commencing any excavation work.

The setting of all inverts, etc. at correct elevations is a prime and definite requirement of this specification.

Grades to drains shall generally be as shown on the drawings and as required by the relevant Authorities.

All water piping shall be graded to facilitate draining at a low-level drainage point.

19.22 COVER PLATES

Where exposed pipes pass through a floor, wall or ceiling, the joint shall be finished with an approved Chrome-Plated spun metal cover plate. The cover plate is to be flush with the wall.

19.23 CAPPING OFF

Throughout the installation of all piping, special care shall be continuously exercised to protect all openings to prevent the admission of dirt, stones or other foreign substances that would subsequently obstruct the system.

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 16

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

During the construction of the job and where directed by the Contractor, seal off all open ends of pipe work in an approved manner.

19.24 FIRE RATING

Maintain fire rating to meet BCA and fire engineering requirements. Fire stop collars shall be approved for their purpose, pipe work material, pipe size and installation location.

19.25 CLEANING OUT OF PIPING

After installation and before hydrostatic tests are carried out, the piping shall be thoroughly cleaned and flushed.

All piping shall be thoroughly washed out and the systems operated in this manner until all foreign matter is removed. Pipe work shall be disinfected in accordance with AS3500.

The cleaning out of the piping shall be carried out in the presence and to the satisfaction of the Contractor.

19.26 CHROME PLATING

Waste pipes, flush pipes, water and gas branches, between walls and individual fixtures shall be chrome-plated and fitted with approved cover plates at walls.

Chrome plating shall be carried out in the best manner; steel or wrought iron shall be heavily coppered, heavily nickelled and finally chromium plated.

19.27 PREFABRICATION

Where practical, prefabrication work shall be carried out off the site so that site work is minimised and is confined generally to the joining of straight lengths.

At no time will excessive amounts of unfixed prefabricated Hydraulic materials be maintained on the site.

19.28 CORROSION PROTECTION

In general, all equipment, piping, hangers and fixings shall be finished with corrosion-resistant coatings. Make good any scratches or other marks likely to permit corrosion.

All mild steel to be galvanised or finished with other approved corrosion-resistant coating.

Should any corrosion become apparent to any material during the maintenance period the defective part shall be removed and re-treated in an approved manner to prevent further corrosion.

19.29 SETTING TO WORK

On completion of all Hydraulic works proceed in setting the plant into operation.

Where required, make all necessary adjustments to the systems.

All components of the system shall be systematically checked for correct operation, and operational control points etc. for all equipment, set to control the plant so as to provide operation as specified.

Upon completion of the above works, provide all necessary skilled labour for a period of time, as designated by the Contractor, to instruct his representative fully in the operation, adjustment and maintenance of the plant, equipment and control system.

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 17

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

19.30 NOISE AND VIBRATION

Provide every precaution to eliminate noise and vibration in the operation of all parts of the installation. In the event of excessive noise being generated, make all necessary alterations to correct the condition to the satisfaction of the Contractor. Allow to comply in all respects to the Acoustic Consultant‟s Report and requirements as directed. The acoustic consultant‟s report, where available, will be provided upon request. Where a report is not available, allow to comply with BCA standards.

19.31 INSPECTION OPENINGS

Inspection openings and testing gates shall be installed in sanitary plumbing pipes at each change of direction, before each fixture and elsewhere as directed by the local Authorities, Contractor, and/or required for maintenance.

Every section of piping shall be accessible from at least one inspection opening or testing gate. Sizes of inspection openings shall be to the Local Authorities' requirements.

Test gates shall be provided at the base of stacks and at junctions servicing WC's.

19.32 IDENTIFICATION

All pipe work shall be identified according to AS 1345, "The Identification of Piping, Conduits and Ducts".

Identification markings shall be installed at distances not exceeding 5000 mm and shall be on either side of walls etc. to enable instant recognition.

Identification signs shall be as manufactured by Safetyman Pty Ltd or approved equal.

Provide and fix all signage associated with the Hydraulic services under this contract to comply with relevant Australian Standards. Signage shall include, but not be limited to storage tanks, safety showers, fire hydrant booster and suction manifolds, valves, pumps, gas shut off valves, TMV‟s, etc.

19.33 EXISTING SERVICES

It is the Sub-Contractor's responsibility to obtain full information regarding all existing services, including, but not limited to, water, gas, sewer, stormwater, electrical and telephone - wherever new piping is to be installed.

The Sub-Contractor shall pay any and all costs involved in making good any service damage while excavating, installing or backfilling for any service noted herein.

Should any existing service be damaged, the Contractor and relevant Authority shall be notified immediately.

The Sub-Contractor shall investigate for exact location, depth and size of all existing services prior to any installation being carried out.

Existing services shall be maintained and operational until new works are installed. Allow tracing services as necessary to determine if services shown or found are „live‟ and performing connection to new services with the minimum of downtime. All disconnections and shut downs shall be approved by the Contractor prior to work being commenced.

Where existing branch lines are located and are not shown on the drawings or „As Constructed‟ drawing (available at request from the Superintendent) allow to trace and make connection to new services or cap off as appropriate.

Refer to staging documentation for programming of works.

Advanced Engineering Building Hydraulic Services

Hydraulic Services General Conditions – Section 19

Section 19 – Page 18

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

19.34 DEMOLITION OF SERVICES

Demolition shall be by the hydraulic sub-contractor. Remove all redundant pipe work as far as practicable to code requirements.

Allow identifying services to be removed and cap off as necessary.

Temporary services to remain include - fire hydrant and hose reel, cold water and sanitary plumbing and drainage required during building works.

Allow disconnecting and removing when temporary services are no longer required.

All disconnections and capping of services to be carried out in strict accordance with Authorities' requirements.

19.35 REDUNDANT SERVICES EXTERNAL TO PROPERTY

Allow to investigate all existing services where connected to Authority mains, including water, fire services, gas, sewer, and stormwater.

Disconnect and cap off each service to AS3500 and to Authority requirements. Each service shall be capped off at the Authority main and inspected by the relevant Authority. Pay all associated Authority fees and charges and restoration costs.

Allow investigating site authority records thoroughly to determine the extent of disconnections and refer to hydraulic services drawings for inclusions.

Advanced Engineering Building Hydraulic Services

REFERENCED DOCUMENTS – Section 20

Section 20 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

REFERENCED DOCUMENTS 20.

Details of documents referenced and applicable to this specification are, but not limited to the following:

Australian/New Zealand Standards

AS/NZS 4859.1-2002 Mineral wool thermal insulation–Batt and blanket

AS 1366.3-1992/Amdt 1-1993 Rigid cellular plastics sheets for thermal insulation - Rigid cellular polystyrene - Moulded (RC/PS - M)

AS/NZS 1530.3-1999 Methods for fire tests on building materials, components and structures - Simultaneous determination of ignitability, flame propagation, heat release and smoke release

AS/NS 3500 (all parts) Plumbing and Drainage

AS5601 Gas Installations

AS 1851 Maintenance of Fire Protection Systems and Equipment

AS5200 Technical Specification for Plumbing and Drainage Products

AS6400 Water Efficient Products – Rating and Labelling

AS2419.1 Fire Hydrant Installations – System Design, Installations and Commissioning

State and Local Authorities

Queensland Development Code

Brisbane City Council Water Supply Code

Project Specific Reports and Documents

Acoustic Report Prepared by Arup

Fire Engineering Report Prepared by AECOM

Advanced Engineering Building Hydraulic Services

Excavation – Section 21

Section 21 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

EXCAVATION 21.

21.1 GENERAL

All excavations necessary for the installation of hydraulic services, pits, sumps, chambers and the like shall be undertaken by the Contractor. Activities associated with excavation include :

a) Confirmation of existing and design levels

b) Soil testing

c) Excavation, spoiling and disposal of material

d) Dewatering

e) Shoring and making safe, including lighting and barrier erection

f) Bedding of pipework

g) Filling and compaction

h) Maintenance and reinstatement

i) Erosion control

The Sub-Contractor shall ensure that the installation of hydraulic services, associated with excavation, is undertaken in compliance with the Workplace Health and Safety Act, as amended.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

MATERIALS 22.

22.1 MATERIALS AND WORKMANSHIP

All materials are to be new and the best of their respective kind. All labour shall be skilled in its particular craft and all shall be in accordance with best practices for works of this kind. The items shall include all labour, equipment, materials and transportation necessary to construct and complete the work.

All pipes and fittings must carry an Australian Standards approval, and watermark approval numbers.

All materials and workmanship not of the stated quality may be rejected.

Make written requests to the Contractor for approval before proceeding with the substitution of any materials or constructions. Where a material is described as “similar to” or “equal to” a nominated material then the material nominated is to be allowed for by tenderers in compiling their tenders.

The substitution of goods, materials, workmanship, methods and equipment may be approved by the Contractor on the written request giving technical information, certifying that it is of equal or better quality and effectiveness and quoting an appropriate price adjustment. Any variation in cost resulting from such substitution will be added to or deducted from the Contract Sum as the case may require.

Orders for material are to be made as soon as practicable to ensure delivery on time and building components manufactured, stored or stockpiled off site are to be properly maintained.

All defective materials and work are to be rectified and/or removed from the works as and where directed. Certificates may be withheld while such defects remain unremedied or on site provided sufficient time has elapsed to comply with the order for removal.

No approval of the Contractor shall be deemed an acceptance of materials on workmanship not complying with the provisions of this Contract.

The installation throughout shall comply in every respect with the various codes set out by the Standards Association of Australia together with such additional requirements as may be specified herein.

22.2 SAMPLES

Submit to the Contractor identified duplicate samples of any materials or items specified to be used in the works. One each of the approved samples shall be signed by the Contractor and returned and the other shall be kept on the works in a safe place and available for inspection.

22.3 CONCRETE

Concrete shall be of 25 Mpa strength, or as directed by the structural engineer. All site mixed concrete shall be of 4:2:1 mix. Mortar shall be 2:1 cement mix. Waterproof render shall be 3:1 mortar waterproofed, with approved brand of waterproofing compound used directly in accordance with the manufacturer's direction.

22.4 COVERS AND FRAMES

Covers and frames shall be manufactured in accordance with AS3996 and be 'ACO' or approved equal cast iron covers and frames with all edges machine fitted and have removable plastic lifting hole plugs. Each cover shall have a brass or stainless steel plate bearing the name of the service.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

The covers and frames shall be set to the level of the finished surface and filled in with the same material as used for the surrounding path or roadways, lawned areas shall be infilled with concrete. Brass edge trimmed covers and frames shall be used in areas where tile, paver or carpet finish is required. All covers and frames shall have the manufacturers recommended lubricant applied prior to installation.

All internal covers shall be lock down type.

Cover duties selected may not be appropriate for construction type traffic. Allow protecting installed covers during the construction phase. All covers damaged shall be replaced without incurring additional costs to the contract.

22.5 TRENCH GRATES AND SUMPS

All trench grates, roof sumps and outlets, sump grates and frames used, shall be manufactured in accordance with AS3996 and be of the required strength to carry the vehicular or pedestrian traffic. The trench grates used shall be longitudinal bar gratings suitable for vehicle and cyclist traffic, set flush with surrounding finished levels. Trench grates in pedestrian areas shall be of the “heelguard” type.

Grates and frames may not be of appropriate duties to withstand construction traffic. Allow to protect installed grates and frames during the construction phase. All grates damaged shall be replaced without incurring additional costs to the contract.

22.6 PAINTS AND SEALANTS

Maximum TVOC Content Limits for Paints, Varnishes and Protective Coatings

Product Type/Sub Category Max TVOC content (g/L of ready-to-use product)

Walls and ceilings - interior gloss 75

Walls and ceilings - interior semi gloss 16

Walls and ceilings - interior low sheen 16

Walls and ceilings - interior flat washable 16

Ceilings - interior flat 14

Trim - gloss, semi gloss, satin, varnishes and woodstains 75

Timber and binding primers* 30

Latex primer for galvanized iron and zincalume 60

Interior latex undercoat 65

Interior sealer 65

One and two pack performance coatings for floors* 140

Any solvent-based coatings whose purpose is not covered in table 200

Obtain the approval of the design team or client before substituting the finishes listed in the schedule.

Undertake a final audit at the end of construction works to ensure the correct products have been used.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Maximum TVOC limits for Adhesives and Sealants

Ensure that 95% of all adhesives and sealants meet the TVOC Content Limits outlined in the following table

Product Type Maximum TVOC content*

(g/L of product)

Dry wall and panel adhesive 50

Construction adhesive* 70

Structural glazing adhesive 100

Architectural sealants* 250

* Sealants used to enhance the fire- and water-proofing properties are included

Obtain the approval of the design team or client before substituting the finishes listed in the schedule.

Undertake a final audit at the end of construction works to ensure the correct products have been used.

Volatile Organic Compounds (VOC) As-Built Requirements

Confirmation from the Supplier

Confirmation from the Supplier(s) of the type and quantity of each product supplied to AEB Voc Datasheet(s) provided by Manufacturer/Supplier:

a) For each compliant product nominated

b) For every datasheet provided, the compliant VOC levels must be highlighted and referenced

c) State the calculation method followed to determine TVOC levels of each specified product

d) The datasheets must come from a NATA or ISO/IEC17025 registered laboratory quoting the TVOC level of each specified product

Or

a) - The Manufacturer documenting the calculation method followed to determine TVOC levels of each specified product

Confirmation from the Contractor

a) - That compliant low-VOC products were used by ALL subcontractors and relevant trades wherever specified, to meet the Credit Criteria by describing the application, amount, type and supplier used throughout AEB.

The sub-contractor shall utilise only paints and sealants that have low Volatile Organic Compound (VOC) content.

For solvent-based coatings, the paint shall not contain VOC‟s in excess of 200g/litre

For multi-purpose construction adhesives, the VOC content shall not exceed 70 g/litre.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 4

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

The sub-contractor is required to conform to these limits. The sub-contractor is responsible for determining compliance of all paints and sealants used under the hydraulic sub-contract. A comprehensive list of paints and sealants to be used on site shall be compiled by the Contractor prior to use on site. The sub-contractor is to select and utilise only products from the approved list.

Any alternative to those paints and sealants listed must be presented and approved by the Contractor prior to substitution.

22.7 FIXINGS

Fixings shall be 'Dynabolts', 'Dynasets' or equal approved rawl expansion type and shall be installed in direct accordance with the manufacturer's instructions. Plastic or nylon type fixing or anchors will not be accepted.

Sure drive metal expansion anchors will be accepted on small-bore pipes up to 20mm diameter.

22.8 FLEXIBLE CONNECTIONS

Flexible connections or anti-vibration couplings shall be fitted to all pumping equipment and be 'S' flex flexible couplings installed in accordance with the manufacturer's instructions. Flexible connections shall be the same size as the pipe work, not the equipment.

Flexible connections shall be installed with the aid of adjustable threaded spacers and shall be adjusted correctly to dimensions recommended by the manufacturer prior to fixing of the pipe work, the maximum angular deflection allowed on the flexible connection shall not exceed five (5) degrees and shall be installed only where indicated on the drawings.

Flexible connections on submersible pumps shall be jointed to pump/s and pipe work with male and female 'Kamlok' quick release 'cam type' couplings.

22.9 FLANGES

Flanges shall conform to AS 2129, AS 2528 and AS 4087. Use brass flanges for copper tubing, galvanised mild steel flanges screwed type for galvanised mild steel, cast iron flanges for cast iron pipes and PVC flanges for PVC piping.

22.10 GALVANISING

All galvanising of steel work shall be hot dip process in accordance with AS 1650 to give 0.1mm minimum thickness coating.

22.11 UNIONS

Unions shall be four (4) piece compression type unions (2 part cones) or three (3) piece brass, bull nose taper type unions. Brass and copper type union connections shall not be used under any circumstances, in concealed or inaccessible locations.

Unions shall be located on the outlet side of all control valves.

22.12 VALVES

All valves used shall be in accordance with AS1628. All valves shall be of one type and of one manufacturer. All valves shall be placed in easily accessible positions for operation and repair. Valves in ducts shall be positioned at 600mm from the finished floor level, unless noted otherwise on the drawings.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 5

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Control valves to main branch lines and outlet positions shall be of the gate or ball valve pattern. Elsewhere the control valves shall be of the loose jumper pattern where required by code. All valves shall be tested to a pressure of 1700 kPa and marked by an approved Testing Authority.

Valves up to and including 50mm shall be screwed. Valves above that size shall be flanged with Table E flanges. All valves shall be suitable for temperatures up to 90°C.

Spindles shall be non-rising type and must not project into the bore of the valve when the valve is in the fully open position. The bore must be clear and unobstructed when in this position.

22.13 BUTTERFLY VALVES

All valves shall be manufactured in accordance with AS4795, be fully approved and tested to a pressure of 2000 kPa and marked by an approved Testing Authority.

22.14 REFLUX VALVES

All valves shall be manufactured in accordance with AS1628, be fully approved and tested to a pressure of 2000 kPa and marked by an approved Testing Authority. Valve shall be generally constructed of bronze, have replaceable valve discs and be suitable for temperatures up to 90°.

22.15 BALANCING VALVES

Balancing valves shall be Tour and Andersson Therm valves with screwed connections.

22.16 PRESSURE LIMITING / REDUCING VALVES

Pressure limiting valves shall be "RMC” or equal approved. Pressure limiting valves shall maintain the desired outlet pressure under no flow conditions. The valves shall be suitable for operation under the pressures and flows it shall be subjected to. The valves shall be adjustable and the outlet and inlet ranges to be approved by the Hydraulic Consultant.

22.17 BALL VALVES

Ball valves shall be manufactured in accordance with AS1628, be fully dezincification resistant, watermarked to AS5200, full bore, and screwed BSP connection.

Ball valves may be used in preference to loose jumper type valves where approved.

22.18 THERMOSTATIC MIXING VALVES

The valve must have a wax element which gives complete fail-safe and have built in stop valves for serviceability.

All valves shall have their temperature set to code requirements and tested following completion of works and all test results shall be recorded and included within the Instruction and Maintenance Manual. Testing shall include failsafe testing with isolation of cold-water service. Provide signage where valves are concealed.

Temperature limiting (tempering) valves shall not be used.

22.19 SLUICE VALVES

All sluice valves shall be manufactured in accordance with AS2638 and be fully approved.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 6

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

22.20 STRAINERS

„Y‟ strains shall be fitted upstream of all back flow prevention devices, solenoid and similar valves. „Y‟ strainers shall be approved by the local authority and be as manufactured by RMC or equal.

22.21 COPPER AND BRASS TUBES AND FITTINGS

Copper tubes shall be solid drawn in accordance with the following standards: -

Water Service Pipe AS 1432 Type A and B.

Waste pipes shall be as AS1432 Type D and Type B for fabrication of junctions, fittings to AS1589.

Brass tubes shall be solid drawn with minimum wall thickness of 1.6mm. Fittings for copper and brass pipes shall be a minimum 60/40 gunmetal or brass and stamped by the approved Authority.

22.22 CAST IRON PIPES AND FITTINGS

All cast iron pipes and fittings shall be soil weight in accordance with AS 1631. The entire cast iron pipe work system shall be equal in all aspects to the “Crevet” manufactured system, including fittings and connections

22.23 FIBRE REINFORCED CEMENT PIPES

Shall be manufactured in accordance with AS4139 and be “Hardies” or approved equal.

22.24 CONCRETE PIPES

Concrete pipes shall be in accordance with AS 4058 as approved by the local Authority.

22.25 VITRIFIED CLAY PIPES

Vitrified clay drainage pipes and fittings for underground drainage shall be first quality.

Jointing shall be made with push fit polypropylene flexible couplings with EPDM (ethylene propylene) sealing rings.

The system shall be equal in all respects to the SUPERSLEVE gravity drainage system manufactured by HEPWORTH BUILDING PRODUCTS.

22.26 UPVC AND PVC PIPES AND FITTINGS

PVC pipes and fittings: - for underground drainage shall be 'Unplasticated Poly Vinyl Chloride' in accordance with AS 1273 stormwater, AS 1260 drainage, waste and vent. Solvent welded jointed for 100mm and 150mm diameter. Install in accordance with AS 2032. Sub-soil drains shall be 100mm solvent welded joints and fittings.

The system shall be equal in all respects to the Hardie Iplex Plastics.

Markings - all pipes and fittings shall bear the approved stamp of the local Authority and all care shall be taken to ensure that the stamp is not erased during installation. Pipes and fittings not bearing the approved stamp will not be accepted.

Expansions - expansion joints for sewer shall be used on long straight runs between fixed points at 12 metre centre and shall be in accordance with AS 2032 and the local Authority requirements.

Where a ring seal adaptor is fitted to the socket of the fittings, care must be taken to leave the required gap between the end of the pipe and the shoulder of the socket of the fittings.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 7

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

22.27 HDPE PIPES AND FITTINGS

All pipes and fittings must carry an Australian Standards approval, and watermark approval numbers.

All HDPE pipe work and fitting joints shall be butt-welded or fused, utilising approved butt fusion welding equipment under factory controlled conditions. Butt welds shall be used only on stormwater systems, vertical plumbing stacks and vents. All sanitary and trade waste drainage (horizontal) shall have joints made with electro fusion couplings. All site welds may be either butt or fusion, utilising approved butt fusion welding equipment or electro fusion sleeves installed strictly in accordance with the manufacturer's direction. No other jointing methods are to be used.

All persons carrying out the jointing procedure shall complete the installation course and be accredited by the manufacturer prior to commencing works.

Confirmation of accreditation numbers of all personnel intending to install the HDPE system shall be provided prior to commencement of works.

22.28 POLYPROPYLENE PIPES AND FITTINGS

All pipes and fittings must carry an Australian Standards approval, and watermark approval numbers.

All PP pipe work and fitting joints shall be butt-welded or fused, utilising approved butt fusion welding equipment under factory controlled conditions. All site welds may be either butt or fusion, utilising approved butt fusion welding equipment or electro fusion sleeves installed strictly in accordance with the manufacturer's direction. No other jointing methods are to be used.

All persons carrying out the jointing procedure shall complete the installation course and be accredited by the manufacturer prior to commencing works.

Confirmation of accreditation numbers of all personnel intending to install the PP system shall be provided prior to commencement of works.

22.29 JOINTING MATERIALS

All joints shall be cleaned free of any foreign material, dirt, and grease etc., before any attempt is made to do the joints.

Joints shall be cut true and square, remove all burrs and swarfs, etc. and grind or file a chamfer lightly around the pipe.

Poly Vinyl Chloride (PVC or UPVC) pipes shall be jointed by solvent welding of the type recommended by the manufacturer. Clean joints with approved solvent cleaning fluid. Apply an even, liberal layer of the approved solvent cement to both surfaces of the joint and allow standing to become touch dry. Push the joints together and remove all surplus solvent with a clean, dry cloth in accordance with AS 2032.

Silver Brazing Alloy shall contain not less than 15% silver; verification of the silver content shall be given in writing to the Hydraulic Consultant. Care shall be taken not to overheat the joint. Apply the correct flux as recommended by the manufacturer slightly carbonising flame shall be used. Failure to use 15% silver brazing alloy will result in rectification of all joints.

Steel Pipe Welding (Fusion Welding). The joint shall be properly prepared before commencement and will be made in accordance with AS CB15.

Bronze Welding the joint shall be chamfered and the filler rod and flux shall be of the type recommended by the manufacturer.

Cement shall be Portland cement Type 'A' and respective to AS 3972 stored in a dry and moisture free state and mixed as required to a consistency of 2:1.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 8

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Sewer Drainage - Rubber Ring Joints shall be in accordance with AS 1646 and installed in accordance with AS 1260.4, AS 2032. All rubber rings shall be of the type recommended by the manufacturer and approved by the local Authority.

Stormwater shall be rubber ring jointed in accordance with the AS 1646 and the local Authority, and to be of the type and size recommended by the manufacturer. Where the pipe connecting is of a different material - a varying size ring as supplied by the manufacturer shall be used.

Flange type gaskets shall be material canvas or fibre reinforced rubber of 3 mm minimum thickness.

Lubricant for lubricating the rubber ring and insertion type gaskets and the outside surfaces of the spigot ends or pipes shall be of an approved non-toxic vegetable based type and shall be applied in accordance with the manufacturer's instructions.

Nuts and Bolts generally shall conform to AS 2451 and be heavily galvanised by the hot dip process. Where galvanised iron to cast iron and cast iron to cast flanges butt, brass bolts shall be used.

Epoxy Resin for cast iron pipes shall be thixotropic epoxy resin paste equal to Davis Fuller's type 603 as approved by the manufacturer.

Silicone shall be Selleys or approved equal, have low VOC content and used as recommended by the manufacturer, white shall be used around vitreous china sanitary ware and clear for seal under fixing taps stainless steel etc.

22.30 EXPANSION

Expansion for pressure type services where expansion shall be allowed for because of either excessively long runs exposed to temperature variations (i.e. in excess or 20m), shall be allowed for by means of expansion loops or approved mechanical expansion device.

They shall be of the type, material and manufacture approved by the Authority governing the works, and installed in such a manner that the axial movement of adjacent sections of the pipe and to the extent that the pipe work is above to extend to its possible maximum expansion in both directions without any restrictions.

Expansion joints shall be installed at intervals of no more than 20m and between fixed points exceeding three metres (3m) on all horizontal lines and branches that experience temperature variations and pipes crossing structural expansion joints.

22.31 TEMPERATURE GAUGES

Provide 100mm diameter waterproof temperature gauges on both the inlet and outlet side of central hot water plant.

22.32 PRESSURE GAUGES

The face on the gauge shall be minimum of 100mm diameter and gauges shall be waterproof and oriented so that the guage can be read at a height of 1600mm above floor level.

Each gauge shall be complete with approved gunmetal stopcock and copper piping connected to the relevant pipe work. Provide pressure gauges upstream and down stream of all pumping or pressure reduction devices and plant.

22.33 INSULATION MATERIALS

Pipes shall be lagged to the manufacturer's standards or as specified in hot water insulation section. Where joints, fittings, bends, branches and valves etc, the lagging shall be cut and trimmed to fit around the section and then taped over.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 9

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Insulation shall be close celled polymer. Insulations shall have no Ozone Depleting Potential (ODP) in either its composition or its manufacture.

Where insulated pipes are exposed, ie not contained within service shafts, ducts or ceiling voids, insulation shall be sheathed with metal cladding, painted and labelled to specification.

Metal cladding shall comprise 0.55mm thick mild steel sheeting.

Cut and roll sheeting to the required sizes with beaded transfer joints and 25mm overlapping circumferential joints, with longitudinal joints facing away from view. Seal joints with sealing compound for piping exposed to weather or moisture.

Fix with steel straps for low temperature piping and either straps or self-tapping screws for medium temperature piping. Do not violate vapour barrier.

22.34 HOSE REELS

Wall mounted fire hose reels shall be 36 metres with copolymer centre, brass stop valve, complete with nozzle interlock, roller hose guide arm, 25mm galvanised iron disconnection union and 20mm twist jet/spray brass nozzle.

All fire hose reels shall comply with AS 1221, AS 2441 and BCA.

Hose reels, unless otherwise stated, shall be installed with the centre of the hub 1.5m above the floor level.

Secure reel hub to floor by means of a steel post fixed to floor. Additional operating instruction sheet shall be procured and secured in a position adjacent to the reel in a permanently upright position.

Fire hose reels are not to be used as a water supply source during construction. All damaged fire hose reels shall be replaced without incurring additional costs to the contract.

22.35 HYDRANT LANDING VALVES

Landing valves shall be approved all brass valve, 65mm diameter thread, fitted with a wheel type handle and shall be of an approved pattern.

The outlet of each valve shall be fitted with a brass cap and chain. Plastic caps are not approved. All externally installed landing valves shall have an anchor block at the base.

All external hydrants to be Fire master twin outlet pillar hydrant. Supply signage as required under AS 2419.1 or by local Authority.

22.36 HYDRANT BOOSTER ASSEMBLY

Shall be in accordance with the drawings and shall be submitted for approval prior to manufacture.

The valve shall be installed above the ground in a position approved by the Contractor and the local Fire Brigade, strictly in accordance with AS 2419. All jointing within the booster valve assembly shall be flanged. The use of roll grooved jointing is not permitted.

The entire hydrant booster valve assembly shall be contained within a purpose made cabinet of dimensions to suit the assembly and in a colour approved by the Architect.

The hydrant booster assembly shall include a double check valve in the H pattern separating the suction and booster points. All materials upstream of the double check valve shall be AS5200 compliant for contact with the drinking water supply.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 10

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

22.37 ACOUSTIC TREATMENT TO PIPEWORK

Acoustic treatment, where necessary, shall be supplied and fixed as required to comply with BCA standards, and the acoustic report.

As a minimum, acoustic treatment shall be required for all drainage pipework (sanitary, trade waste and stormwater) located above office, teaching and laboratory areas.

Refer “Schedules” section for material details.

22.38 VALVE IDENTIFICATION

All control valves shall be identified by 1.0mm thick aluminium/melamine plate minimum dimensions of 65mm x 40mm, with the purpose stamped into the plate in minimum 5mm high letters.

Example: STAFF TOILETS MALE No.27

Allow recording valve numbers and purposing in the operation and maintenance manual.

22.39 PROTECTIVE PIPE WRAPPING/COATING

All in ground metal pipes 80mm diameter and greater shall be protected by a polyethylene continuous sleeve (green sock) sealed with a waterproof duct tape. The sleeving shall be fitted to affect a smooth, closely contoured envelope with minimum barrel and socket gaps. There should be sufficient slack in contouring to allow the sleeving to follow the profile of the spigot-socket interface to prevent damage during backfill.

Sleeving shall be equal to MAC-WRAP protective sleeving as distributed by CHARMAC INDUSTRIES PTY. LTD.

All in ground metal pipes smaller than 80mm diameter shall be wrapped with a layer of petrolatum impregnated fully synthetic woven carrier tape.

All clean pipes and fittings shall be primed with a compatible priming paste prior to wrapping of the tape.

All pipes and fittings shall be covered with a minimum overlap of 30 millimetres.

Tape shall be equal in all respects to DENSO.

22.40 WARNING TAPES

All buried gas, water and fire services shall be identified with a 150mm wide high strength coloured rot resistant homopolymer polypropylene plastic mesh incorporating a 0.7mm AISI 316 grade stainless steel tracer wire and laminated with a printed warning tape on the top surface. Warning tape to be placed min 300mm above the top of the service.

The strip shall be a continuous length coil and colour coded to international standards, in addition to naming the service. e.g. BLUE - water supply.

The warning tape shall be equal in all respects to “Boddingtons Detectamesh”

22.41 ROOF PENETRATION FLASHINGS

All service pipes penetrating the roof shall be made watertight by use of a flexible pipe flashing prior to fitting a cowl.

The pipe flashing shall be designed and installed to conform closely to the roof profile.

Seal the flashing by use of a neutral cure silicone sealant prior to fixing the flashing with zinc plated self-drilling steel screws, or equal approved.

Advanced Engineering Building Hydraulic Services

Materials – Section 22

Section 22 – Page 11

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Pipe flashings shall be equal in all respects to the standard round 'DEKTITE' roof flashings manufactured from ethylene propylene dilne monomer polymer (E.P.M.D.) and distributed by DEKS INDUSTRIES PTY. LTD.

22.42 WATER SUB METERS

Hot, cold and rainwater services shall be fitted with a low friction turbine meter with integral line strainer, modular meter insert and non-return valve.

All meters shall be fitted with upstream and downstream unions and an upstream control valve, and comply in total with AS 3565.

Industrial cold water services shall be fitted with an impact resistant heavy-duty turbine meter.

All meters shall be fitted with upstream and downstream flanges and an upstream control valve.

All meters shall have provision for pulse output to future connection to BMS system. Pulse output shall be 1 pulse per 10 litres. BMS shall include leak detection protocol using data from water sub-meters.

22.43 POLYETHYLENE PIPES AND FITTINGS

Polyethylene pipe for potable water and/or irrigation services shall be Class 12 industrial polyethylene compatible with black polypropylene compression fittings with integral white acetal split rings and nitrile rubber "O" rings.

22.44 UNPLASTICISED POLY VINYL CHLORIDE PRESSURE PIPE

UPVC pressure pipe for pumped transfer of fluids shall be Class 16 unplasticised poly vinyl chloride tube, with solvent welded jointing of injection moulded fittings.

The system shall be equal in all respects to the pressure pipe system manufactured by IPLEX PIPELINE SYSTEMS.

22.45 VALVE BOXES

Shall be "Havestock" or approved equal cast iron with an identification mark stamped on top.

22.46 CONCRETE THRUST BLOCKS

Concrete thrust blocks shall be constructed at all stop ends, fittings, changes of direction and on every fourth straight and continuous length of pipe and where indicated on the drawings.

Thrust blocks shall be constructed for a minimum length of 500mm along the pipe and 300mm over the barrel of the pipe, the trench shall be under cut for a depth of 150mm into both sides and the bottom of the trench, reinforcing steel F82 shall be installed to tie the concrete around the pipe and into the rebates at the sides of the trenches.

The thrust blocks shall be supported or backed during the pour with approved formwork and the quantity of concrete shall be not less than 0.5 cubic metres, concrete to be as previously specified, all joints in the pipe work shall be left exposed.

22.47 BACKFLOW PREVENTION VALVES

Supply and install backflow prevention valves in accordance with AS/NZS 3500. All valves shall comply with AS 2845.1. Allow all costs to register each valve with the local regulatory Authority and provide certification.

Advanced Engineering Building Hydraulic Services

Pumps – Section 23

Section 23 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

PUMPS 23.

23.1 SEWAGE PUMPS

Provide a sewage pumping system, generally comprising:

a) Two identical submersible pumps

b) Controls and wiring

c) Rising main

d) Chamber vent

e) Holding well and covers.

All to form a complete and approved installation as indicated on the drawings.

Refer “Materials” section for details.

Provide a rising main to comply with the following:

a) Provide unions, non-return and gate valve on rising main within pump chamber

b) Provide supports, excavation, bedding, backfill, fixings, brackets etc for rising mains and sewage pumping line – as before specified.

c) Connect to main gravity drainage junction to local authorities requirements.

23.2 DUAL RAINWATER PRESSURE PUMPS

Supply and install one only dual pumpset system.

Refer “Schedules” section for details.

Pumpset is to incorporate the following:

a) 2 variable speed pumps.

b) Separate distribution board mounted on same base frame fitted with main power supply isolating switch with separate circuit breakers for each unit.

c) Inlet side of each pump pre-plumbed with an isolating valve and non-return valve, connected to a common inlet manifold with a neoprene vibration eliminator.

d) Discharge side of each pump fitted with an isolation valve and a common manifold is to be provided with a separate main isolating valve, neoprene vibration eliminator and a full flow bypass. On the discharge manifold a 0/1600KPA- 65mm pressure gauge is provided together with a single pressure tank in accordance with the manufacturers specification. This system will maintain a set pressure with a maximum variation of 2.0%.

e) The total system is mounted on a mild steel galvanised base plate frame.

f) Site commissioning by trained Service Personnel after installation by others.

Attached pump control panel is to incorporate the following features:

a) Main isolating switch

b) Duty selector switch

c) Manual/off/auto selector switch for each pump.

d) Motor and control circuit breakers

e) DOL contractors with hand reset thermal overloads

Advanced Engineering Building Hydraulic Services

Pumps – Section 23

Section 23 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

f) Automatic alternation

g) Lights for:

I. power on 1 off

II. pump run 1 off per pump

III. Pump fail 1 off per pump

h) Volt free contacts

i) Run on timers

j) Audible alarm with mute button

k) All mounted on a sheet metal non-weatherproof cabinet.

Pumpset shall be capable to receive non-potable make-up water when pressure switch signals no flow from tank. Pumpset is to comply with AS5200 and local authority requirements.

23.3 HOT WATER CIRCULATING PUMPS

Supply and install at each hot water return pump set vertical support frames comprising galvanised steel unistrut channel. Fix the hot water return pumps associated pipework and electrical control panels to the vertical support frames.

Dual Pumps shall be mounted in the vertical position with interconnecting pipework and valves.

Refer “Schedules” section for details.

Provide and install pressure gauges and gauge control valves on the inlet and outlet of each pump.

Provide and install temperature gauges on inlet side of each pump.

Fit a “Gate” valve on the inlet of each pump and a balancing valve on the outlet of each pump.

Provide stainless steel flanged vibration eliminators on the suction and delivery connection to each pump. Provide stainless steel vibration eliminators on the pipework connection to and from the pump set group.

Provide air eliminators on each side of the pump.

Provide and install anti-vibration mounts as required.

Provide electrical power, control and alarm wiring with conduits from the pumps electrical control panels to pump motors. Pumps to have thermal overload protection auto/off/manual selector for each pump, auto/change-over selection switch, motor, circuit breakers, AC on light, pump run lights, pump fail lights, alarm button and mute button.

Electrical wire each pump for 24 hours running with an automatic change over to the second pump after each 24 hour duty.

23.4 HYDRAULIC LABORATORY FLUME PUMPS

Supply and install submersible sump pumps for flume operation. Pumps shall be mounted on guide rails, fixed to sump floor and roof slab.

Refer Section 30.2 for details, and Section 17.7 for pump control philosophy.

Fit a non-return valve on the outlet of each pump.

Advanced Engineering Building Hydraulic Services

Pumps – Section 23

Section 23 – Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Provide electrical power, control and alarm wiring with conduits from the pumps electrical control panels to pump motors. Pumps to have thermal overload protection auto/off/manual selector for each pump, auto/change-over selection switch, motor, circuit breakers, AC on light, pump run lights, pump fail lights, alarm button and mute button.

Electrical wire each pump for 24 hours running with an automatic change over to the second pump after each 24 hour duty.

23.5 PUMP CONTROL PANELS

Supply and install all equipment necessary to operate the pumps specified under hydraulic services.

Allow for all control cabinets, mounting brackets, contactors, isolating and control switches, auxiliary switches, alarms, wiring between pump and panel, panel and level controls, and other associated equipment necessary for the safe and effective operation of the pumps as required for the installation and in accordance with statutory requirements to AS 3000.

Provide a complete specification and drawings of pumps and control equipment prior to installation.

All control panels to be rated IP54.

23.5.1 Labelling

a) All control panels and equipment shall be labeled with engraved laminated type labels. Labels shall be black and white lettering. Size of lettering shall match importance and location. Labels shall be screw fixed.

a) Cabinets shall be labeled to indicate function, eg: “Rainwater Pump No. 1”

b) Equipment shall be labeled to indicate function and to identify any associated equipment, eg:

I. “PUMP CONTROL SELECTOR”

II. AUTO/OFF/MANUAL

23.5.2 Testing

Test the system on completion. Furnish two copies of the manufacturer‟s test certificate.

23.6 FLEXIBLE PUMP COUPLINGS

Flexible connections or anti-vibration couplings similar to „S‟ flex flexible couplings installed on the suction and discharge side of each pump in accordance with the manufacturer‟s instructions. Each flexible connector shall have a hose length of not less than four (4) times the pipe diameter installed with a maximum angular deflection not exceeding five (5) degrees.

23.7 PUMP MOUNTINGS

Pump mountings (except submersible pumps) shall be Silentbloc or approved equal spring isolating mountings on an appropriate size to provide a minimum 95% vibration absorption.

Advanced Engineering Building Hydraulic Services

Piping, Valves and Fittings – Section 24

Section 24 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

PIPING, VALVES AND FITTINGS 24.

24.1 PIPING

a) Supply piping in clean, full standard, straight lengths, free from any defects, mill scale, rust, burns, dents and kinks and protected against mechanical damage.

b) Refer to the “Schedules” section for systems permitted pipe materials and joining methods.

24.2 VALVES & FITTINGS

24.2.1 General Requirements

a) Use valves suitably sized for the application and at least line size unless used for control when a smaller size may be necessary.

b) Select valves and fittings to meet the operating pressures and operating characteristics of the relevant systems and to meet higher test pressures where applicable.

c) Design pressure of valves and fittings not less than the system design pressure.

d) All isolating valves and throttling valves shall be rated for full shut-off pressure.

e) All valves and fittings shall be installed in accordance with manufacturer‟s recommendations and with valve shafts installed on or above the horizontal plane and with all tapping points a minimum of 45 degrees off the vertical downwards plane.

f) Provide extended shafts or bodies for insulated valves to allow full thickness of insulation.

g) Valves up to 50mm diameter; screwed connections to AS 1722.1–1975.

h) Valves over 50mm diameter; flanged connections to AS 2129–2000 Type E minimum or Victaulic rolled groove.

i) Handwheels and handles to be removable with the direction of closing to be marked clearly.

j) Select valves to water supply authority approval where applicable; valves to be stamped with approval details.

k) For each type of valve and fitting, valves and fittings to be supplied from one manufacturer throughout the project.

l) Where copper alloy valves used, select valves of dezincification resistant type.

24.2.2 Water Services Valves & Fittings

24.2.2.1 Isolating Valves (up to 50mm)

a) Ball Valves

I. Full bore pattern with handle parallel to direction of flow when fully open.

II. Bronze bodied with hard chromed brass or stainless steel ball, stainless steel stem and PTFE seat.

III. Screwed connections.

24.2.2.2 Isolating Valves (over 50mm)

I. Straight through flow, solid wedge type.

II. Bronze bodied to AS 1628–1999 or cast iron to AS 3579–1993 or cast steel with zinc free, non rising inside screw type spindles.

Advanced Engineering Building Hydraulic Services

Piping, Valves and Fittings – Section 24

Section 24 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

III. Resilient seated.

IV. Medium pattern.

V. Replaceable bronze seat.

VI. Flanged connections.

24.2.2.3 Non Return Valves (up to 50mm)

I. Bronze body swing check type to AS 1628–1999 with stainless steel trim.

II. Screwed connections.

III. To be completely free of hammering under all operating conditions.

24.2.2.4 Non Return Valves (over 50mm)

I. Cast iron spring loaded dual flap type to AS 3578–1993 with stainless steel spring and pin, stainless steel plates, integral nitrile rubber seat.

II. Flanged connections or rolled groove connections.

III. Victaulic Style 716 Type.

24.2.2.5 Pressure Relief Valves

I. Direct acting, spring loaded, side outlet type with adjustable setting to AS 1271–1997.

II. Designed to discharge at full capacity at a pressure not greater than 10% higher than set point pressure.

III. Bronze bodied with renewable stainless steel disc and seat with springs protected from working fluid.

IV. Provide easing gear.

V. Lockable shield to prevent unauthorised alteration to setting.

VI. Valve drained to waste.

24.2.2.6 Strainers

I. Y type or Victaulic Style 731 suction diffusers complete with pre-filter 16 mesh for pressures up to 2065kPA.

II. Screwed bronze body on all lines up to and including 50mm and flanged cast iron body above 50mm with easily removed perforated stainless steel or brass strainer basket.

III. Select mesh for 15kPa maximum pressure drop.

IV. Fit ball valve and drain line to waste for strainers over 50mm as follows:

V. 65, 80 and 100mm strainer – 25mm drain; 125mm – 32mm drain; 150 and 200mm – 40mm drain; 250, 300 and 350 – 50mm drain.

24.2.2.7 Automatic Air Vents

I. Float operated with cast iron or copper alloy body and stainless steel or solid plastic floats and mechanisms.

II. Air vents are to be fully rates for the system operating conditions; minimum acceptable is 1,000kPa and 120°C.

III. All vents are to be fitted with separate isolation valve on the inlet to allow servicing of the vent without draining the system.

Advanced Engineering Building Hydraulic Services

Piping, Valves and Fittings – Section 24

Section 24 – Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

IV. Combined air vent discharge capacity of any section of the system being filled must exceed the flow rate at the fast fill system.

V. Flamco Flexvent, Flexvent Super or equal.

24.2.2.8 Expansion Joints

I. Flanged type of high grade neoprene.

II. Powersorb type REJ or equal.

24.2.2.9 Flexible Pipework Connections

I. Flanged type of high grade EPDM and spirally wound wire and reinforcing having a nominal length of 6 times nominal pipe diameter.

II. Hyflo C-Flex or equal approved.

24.2.3 Natural Gas Towns Gas and LPG Valves

a) Isolating Valves

I. Full bore, dezincification resistant.

II. Ball valves operable by one quarter turn.

III. Permanently fixed handle indicating direction of gas flow.

IV. Comply with Gas Supply Authority requirements and AGA / ALGA Standards as appropriate.

24.3 GAUGES & INSTRUMENT FITTINGS

a) Universal Test Points

I. Binder Twinlock type.

II. Test points to be installed a minimum of 45o above the vertical downwards plane and as required to provide access.

b) Thermometers

I. 100mm dial type mercury in steel thermometers matching pressure gauges and calibrated in Deg. C.

II. Dial range twice operating temperature range.

III. Accuracy 1% of scale range.

IV. Bulb type 316 stainless steel.

c) Thermometer Pockets

I. Locate thermometer pockets in positions where no adverse flow conditions exist.

II. Use thermometer pockets of removable screwed stainless steel type in steel lines, inserted through screwed type boss welded to the pipe.

III. Use thermometer pockets of fixed copper tube type brazed into copper piping lines.

IV. Length of pockets and depth of insertion in pipe adequate to ensure accurate headings.

V. Fill pockets with heat conducting fluid to a minimum depth of 50mm and fit caps to each pocket.

VI. Enlarge pipes smaller than 65mm so as to retain free area.

Advanced Engineering Building Hydraulic Services

Piping, Valves and Fittings – Section 24

Section 24 – Page 4

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

VII. Install pockets vertically or at an angle to retain heat conducting fluid.

d) Pressure Gauges

I. Oil filled 100mm dial Bourdon pipe type to AS 1349–1986.

II. Fit with ball valve.

III. Manually adjustable set point needle incorporated on face of gauge.

IV. Chrome plated escutcheon and suitable for recessed mounting.

V. Select compound type gauges for pump suctions graduated in mm of mercury on vacuum side and kPa on the pressure side.

VI. Bourdon pipe material stainless steel for hot water and steam, phosphor bronze for other services.

VII. Bosses for pressure gauges, standard internally screwed type welded or brazed to side of piping.

e) Gauge Panels

I. Folded sheet metal of adequate stiffness, painted or powder coated with gauges logically grouped and mounted to approval.

24.4 INSTALLATION

24.4.1 Arrangement

a) Layout piping with adequate provision for expansion, contraction, grading, alignment and access for maintenance with not less than 50mm clearance (including insulation) between pipes and all other surfaces and services.

b) Co-ordinate and detail offsets and bends required for co-ordination between trades and integration with building structure and architectural finishes.

24.4.2 Pipework Supports and Anchors

a) General Requirements

I. Design supports for all static and dynamic load and reactions.

II. Install seismic bracing to all pipework as required by AS 1170.4–1993.

III. Comply with all Statutory and Code requirements.

IV. Locate valves and fittings as close as possible to points of support and separately support valves in line sizes 200mm and larger.

b) Support Spacing

I. Non ferrous pipe to AS 3500.1 Table 5.2.

II. Steel pipe to AS 4041–1998 Table 3.28.2.

III. ABS to manufacturer‟s recommendations.

c) Pipe Clamps, Spacers and Saddles

I. Individually hung pipes - bolted, two-piece type clamps with clevis or welded yokes of 'Millstrut' PC7 or PC10 series or equivalent. One-piece type clamps with clevis similar to 'Millstrut' PC2 series may be used for pipe sizes DN65 or less. Clamps rated for the full load of pipe plus its fluid contents, insulation and fittings.

Advanced Engineering Building Hydraulic Services

Piping, Valves and Fittings – Section 24

Section 24 – Page 5

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

II. Spacers – High temperature insulated pipes - fully vapour sealed hardwood spacers located between clamps and pipes. Spacers wedge shaped hardwood blocks arranged to form circular collars of the same thickness as the insulation and projecting a minimum of 10mm on either side of the clamps.

III. Firmly attach clamps and collars to pipework and/or insulating spacers without applying undue pressure to the pipe walls.

d) Hanger Rods

I. Fabricate hanger rods and associated fittings from hot dip galvanised or zinc plated mild steel bar of not less than the following diameters:

Nominal Pipe Size mm Rod Diameter mm

Up to 50 (inclusive) 8

65 & 80 10

100 to 150 12

200 to 250 16

300 to 450 20

500 & above 24

e) Fixed Supports

I. Fix hanger rods direct to structure unless moving supports required to cater for expansion, contraction and vibration.

II. Support two or more pipes on common channel section bracket or trapeze type support:

Pipe sizes up to 100mm Millstrut P1000 Series

Pipe sizes over 1000mm Standard rolled sections

f) Moving Supports

I. Where hanger rods used to take up movement ratio of effective length to pipe movement to be not less than 6:1.

II. Provide 'V' shaped brackets with oversize holes for rods. Similarly, clevis or welded yokes on pipe clamps to have oversize holes for rods. Secure rods at each end using spherical washers and locknuts and do not use any nuts between brackets and clevis or welded yoke.

g) Anchors

I. Design, supply and install anchors where shown on drawings and where required to accommodate pipework weight, thrust forces and expansion and contraction.

II. Submit detailed design and installation details for the project structural engineer‟s approval and confirmation that the building structure can resist the anchor forces imposed by the system design.

III. Anchor connections to the pipework shall be:

Steel pipe: Fully welded to pipe.

Copper pipe: Anchors comprising bronze flanges fully brazed to pipe and bolted to galvanised steel anchor plates. Use non conductive bushes and washers.

Advanced Engineering Building Hydraulic Services

Piping, Valves and Fittings – Section 24

Section 24 – Page 6

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

IV. Anchor shall comprise steel plates and/or rolled steel sections designed to transfer the weight of pipework, pipe and thrust forces exerted by the system to the structure.

24.4.3 Vibration Isolators

a) Rubber bellows are not to be used to absorb piping movement due to expansion in the system.

b) Rubber bellows should NOT be installed extended, compressed or offset to make up for deficiencies in pipe length or alignment.

c) Pipework must be properly anchored around the unit, to avoid the bellows bearing the weight of the piping system.

d) Units must be rated for the system operation pressure and temperature.

e) The Sub-Contractor should note the allowable bellows movement in their submission of products.

f) Construction to include flanged connections, bellows to be nylon cord and wire reinforced EPDM rubber suitable for a working temperature of up to 95°C.

g) Hyflo C-Flex or equal approved.

24.4.4 Pipe Expansion and Contraction

a) Provide means to accommodate piping expansion and contraction in pipe runs longer than 30m from anchor points which may be a series of full radius bends and diversions, expansion loops or bellows.

24.4.5 Pipe Penetrations

a) Supply 1.6mm galvanised steel sleeves for placement and casting in penetrations. Sleeves to extend a minimum of 100mm above floors.

b) Pipe penetrations in fire rated structures to comply with BCA Clause C3.15 Fire Resistance – Openings for service installations where applicable – refer to architectural and structural drawings for required fire ratings.

c) Pipe penetration fire rating system to comply with approved type tested installation.

d) Where required provide 100mm guard around fire rated penetrations to ensure no combustible material comes within 100mm of pipe penetration and pipe.

e) Non fire rated wall penetrations to be sealed with mineral fibre insulation to maintain acoustic rating.

f) Where packing material is mineral fibre material enclose in sisalation.

g) Where exposed to view provide galvanised sheet metal collar.

24.5 TESTING OF PIPEWORK

a) Pressure test all sections of pipework prior to lagging or painting using calibrated pressure gauges. Provide signed test reports for each pressure test.

b) Isolate any equipment that will not withstand test pressures prior to testing.

c) Remake any leaking joint and retest.

Advanced Engineering Building Hydraulic Services

Noise and Vibration – Section 25

Section 25 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

NOISE AND VIBRATION 25.

25.1 GENERAL REQUIREMENTS

a) Acoustically seal pipe and cable penetrations through noise rated walls and acoustic enclosures.

b) Statically and dynamically balance rotating machinery.

c) Support rotating and reciprocating equipment on anti-vibration/vibration absorbing mounts on hangers.

d) All static equipment in plantrooms with suspended floors to be separated from the structure with double thickness neoprene pads or equal.

e) All connections to rotating equipment or assemblies containing rotating equipment shall be rendered flexible by anti-vibration hangers supporting pipework and/or by flexible connections as specified.

f) Plinths for all floor mounted equipment.

25.2 VIBRATION CONTROL

25.2.1 Acceptance Criteria

a) Complete systems including individual components not to exceed satisfactory levels as set out in AS 1359 and AS 2625.

b) Select anti-vibration mounts/hangers for life cycle of building and install in accordance with the requirements of the Earthquake Code AS 1170.4–1993.

c) Select and install anti-vibration mounts and hangers in locations to prevent transmission of vibration to adjoining areas and to prevent undue vibration, distortion or fatigue of equipment and connecting piping and cabling.

d) Select vibration isolation mounts/hangers to allow for deflections of building structures and finishes and for minimum static deflection as specified.

25.2.2 Spring Mounts

a) Free standing and positioned for uniform deflection of all springs.

b) Spring mounting plates and frames hot dip galvanised.

c) Ratio of mean coil diameter to compressed length at specified static deflection of 0.8.

d) Minimum additional travel to solid of 50%.

e) Holding down bolts to be provided.

f) Surge frequency to be beyond 30% of predominant machine frequency of vibration.

25.2.3 Neoprene Pads

a) Use up to 9mm static deflection.

b) Loading not greater than 400kPa.

25.2.4 Anti-Vibration Hangers

a) Spring and double neoprene cup type in series.

b) Total hanger deflection 25mm minimum.

c) Provide secondary adjustment to transfer load to spring.

Advanced Engineering Building Hydraulic Services

Noise and Vibration – Section 25

Section 25 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

25.3 NOISE MEASUREMENTS

a) Measure and submit noise measurements in areas nominated above using sound level meter complying with AS 1259 during the noisiest operating condition.

b) Where noise measurements exceed specified criteria, take additional noise readings in each octave band (125Hz to 4000Hz inclusive) in selected locations with reference to AS 1045-1988, AS 1055, AS 1081, AS 1089, AS 1217 and AS 1469–1983.

25.4 VIBRATION MEASUREMENTS

a) Where a noise hazard exists and all practicable noise attenuation has been carried out, hazardous areas shall be defined by the erection of signs reading:

NOTICE

HEARING PROTECTION MUST BE WORN

IN THIS AREA

or

NOTICE

HEARING PROTECTION MUST BE WORN

WHEN THIS MACHINE IS RUNNING

b) Signs shall be 'Brady' Indoor/Outdoor, Personal Hazard Warnings or approved equivalent.

Advanced Engineering Building Hydraulic Services

Painting and Identification – Section 26

Section 26 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

PAINTING AND IDENTIFICATION 26.

26.1 GENERAL

This section sets out the technical and quality assurance requirements for the painting, identification and labelling of the Hydraulic Services installation.

a) Paint the complete installation, except normally bright and polished metal components, bearing surfaces, adjusting screws and similar items:

I. Pipework, valves, fittings and supports exposed to view and in ceiling spaces within laboratories and workshops.

II. Pipework, valves, fittings and supports within plant rooms exposed to view.

III. Pipework, valves, fittings and supports located in walk-in ducts.

IV. All plant and equipment

V. Machine bases and plinths

VI. Switchboards, control panels, conduits, cable trays, and electrical ducts throughout.

b) Provide identification and labelling of all equipment, valves, and control items exposed to view or concealed including:

I. System and equipment designations,

II. Critical Systems labelling

III. Essential Services labelling

IV. Plant maintenance and operating and emergency signage,

V. Statutory signage, including occupational health and safety signage, hazardous chemical signage;

26.2 DESIGN

Select painting and finishes in accordance with the architectural requirements.

Review the risk assessment and statutory and authority requirements completed as part of the system testing, commissioning and handover requirements and provide labelling and signage as determined.

26.3 AUTHORITY STANDARDS AND CODES

a) Comply with applicable Federal, State and Territory Authority design guidelines and codes of practice and requirements, including those relating to

I. BCA essential services

II. Pressure Vessels

III. Occupational Health and Safety

IV. Hazardous Materials

V. Environment Protection.

26.4 SUBMISSIONS

Provide the following submissions:

Advanced Engineering Building Hydraulic Services

Painting and Identification – Section 26

Section 26 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

a) Paint Systems and colour schedule to be used.

b) Labeling Systems.

c) Valve identification.

d) Schedule of statutory, maintenance and operating signage.

26.5 GENERAL REQUIREMENTS

a) Comply with AS/NZS 2311, AS/NZS 2312 and AS 1345.

b) Fabricated pipe and steelwork shall be delivered to site prime coated.

c) All black steel surfaces and surfaces subject to corrosion shall be protected.

d) Concealed pipe work to be prime coated.

e) Protect all items of work during dispatch and whilst on site during progress of installation.

26.6 PAINTING

Refer architectural specification in relation to painting of services (including pipework, supports, trays etc)

26.7 IDENTIFICATION AND LABELLING

26.7.1 General

a) Mark all systems and equipment including wiring, piping and fittings to that they are readily identifiable.

b) Locate labels so that they are easily seen and either attached to, below or next to item referred.

c) Labeling to match installation documentation schedules.

d) Equipment and Service labels shall be in accordance with the Legend of Symbols nomenclature for the respective service.

26.7.2 Labels

a) Labels shall be permanent.

b) Type: select from the following:

I. Engraved and black filled lettering on stainless steel plate, minimum 1mm thick mechanically fixed.

II. Photo etched aluminium.

III. Engraved two-colour laminated plastic mechanically fixed.

IV. Adhesive labeling.

V. Painted.

c) Adhesive labels and laminated plastic labels shall not be used where exposed to the environment.

d) Painted labels shall be in the same finish paint type as the installation.

26.7.3 Pipework

a) Provide painted or adhesive labeling in accordance with AS 1345

Advanced Engineering Building Hydraulic Services

Painting and Identification – Section 26

Section 26 – Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

b) For systems containing hazardous materials provide labeling in accordance with AS 1318

c) Labeling shall indicate system, contents and direction of flow.

d) Where a pipe passes through a wall, slab or partition provide labeling each side.

e) Spacing of pipe bands: 3m plant areas, 8m elsewhere and at each level vertically at all branches.

f) Provide marker adjacent to tee, valve, outlets and pumps.

g) Provide marker on both directions on bends.

h) Lettering size 32mm minimum.

26.7.4 Equipment

a) All items of equipment such as pumps, hot water units, filters and similar items shall be labeled in accordance with the specification abbreviations, symbols and acronyms scheduled or otherwise approved.

b) Label all equipment, instruments, indicators, gauges switches and valves.

c) Equipment requiring special maintenance procedures or presenting occupational health and safety hazards: provide permanent labels complying with statutory requirements.

d) Equipment requiring consumables including replacement belts, oils, filters and strainers: provide labels indicating consumable component details and quantities and corrective maintenance trigger point.

e) Valves: Labels shall be colour coded laminated labels indicating service, function and normal position, and attached to hand wheels or spindles using a vandal resistant permanent chain/ring.

f) Lettering size: 32mm minimum.

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

TESTING, COMMISSIONING AND HANDOVER 27.

27.1 GENERAL

a) This Section of the Specification covers the testing and commissioning requirements for the various hydraulic services.

b) Provide all necessary competent personnel and equipment to carry out testing and commissioning of the installations covered by this Specification.

c) Carefully pre-plan and schedule all tests to ensure that they are co-ordinated with the work of other Contractors and Sub-Contractors involved and that they are carried out in a safe and efficient manner with the minimum of inconvenience to all concerned. Where the work is being carried out in an occupied or partially occupied building, take responsibility to advise the owners and/or management of the building regarding the nature of the tests and co-ordinate with them to minimise any possible hazards or inconvenience that may arise due to the tests. In addition, give notification at least three (3) days in advance of carrying out any tests so that a representative may observe the test.

d) Carried out all tests required by statutory authorities to prove that the systems operate to their satisfaction and in accordance with the appropriate Codes and Regulations.

e) Undertake comprehensive pre-commissioning, commissioning and quality monitoring in accordance with CIBSE commissioning codes related to the hydraulic services installation including but not limited to the following:

I. Code B - Boilers

II. Code M – Commissioning Management

III. Code W – Water distribution systems

f) Post all pre-commissioning, allow 1 full day site testing to demonstrate the interface testing of the different services disciplines (these will need to have been tested prior to this event to ensure a smooth witnessing process), attendance will be required by all relevant contactors, consultants and the Independent Commissioning Agent

27.2 RECTIFICATION OF DEFECTS

Promptly rectify all defects.

27.3 PRE-COMMISSIONING PROCEDURES

Prior to commencement of the commissioning of the systems, carry out the following procedures:

a) Progressively during the construction phase regularly discharge cold water from all systems to ensure that stagnation shall not occur.

b) Pressure test all water systems as outlined in Specification.

c) Thoroughly clean out and flush out all water systems to ensure only clean water is within the systems.

d) Pressure and leak test all water systems as outlined in Section „Pipework, Valves & Fittings„.

e) Thoroughly clean and flush out all water systems including package pressure system.

f) Commission the water treatment plant. Protect the filtered and treated water systems by the complete flushing out of the system prior to commissioning and installation of the filters.

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

g) Provide manufacturers test certificates for all proprietary manufactured items including pumps, water filters, backflow preventers, thermostatic valves and trace heating system. Mount test certificates for pressure vessels in glazed frames adjacent the equipment. Fix to pressure relief valves the manufacturers tags indicating the set pressure of the valves and stamp all pressure valves with the manufacturer's design and test pressure ratings.

h) Overhaul all installed backflow preventers including full commissioning of same by manufacturers representative

27.4 COMMISSIONING MANAGEMENT

Management of commissioning to include:

a) Programming and scheduling of commissioning and handover activities in conjunction with the Head Contractor and in consultation with other relevant parties.

b) Liaison with other services, trades and co-ordination of commissioning activities associated with system interfaces and interaction between systems.

c) Liaison with and briefing of Authorities to ensure that the commissioning procedures and resultant data provided for their approval is consistent with their requirements and records.

d) Taking a lead role for the Hydraulic Services testing and commissioning including attending meetings with Contractor, other services trades with consultants and Authorities as necessary.

e) Preparation of progress reports on testing and commissioning.

All commissioning result forms shall be completed, including the following:

Tested By: ………………..…….. Please print Witnessed By: ……………………………

Signed: …………………………………… Signed: ……………………………………

Date: ……………………………………… Date: ………………………………………

Test Device used: ……………………………………………………………………………….

Serial Number: …………………………………………………………………………………..

Date of Calibration: ……………………………………………………………………………..

Method of Testing: ……………………………………………………………………………...

27.5 COMMISSIONING

The commissioning of the hydraulic services shall adopt the recommendations listed in the Chartered Institution of Building Services Engineers England (CIBSE) Commissioning Code M, Commissioning Code W and Commissioning Code B (where related to hot water heaters). Specifically, the hydraulic sub-contractor shall comply with the following sections:

a) B1 – Safety Issues

b) B4 – Commissioning project management

c) B5 – Sequence of commissioning

d) B9 – Operation and calibration

e) M2 – General Considerations

f) M4 – Programming and Co-ordination of the Commissioning Process

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

g) M5 – Installation Quality Assurance

h) M6 – Pre-commissioning

i) M7 – Commissioning

j) M8 – Witness Compliance

k) M9 – Building Log Book

l) M10 – System Handover

m) W1 – Safety Issues

n) W5 – Pre-commissioning

o) W6 – Setting pumps to work

p) W7 – Balancing and regulating water flow rates

q) W8 – Evaluation and witnessing of commissioned systems

Carry out all commissioning tests necessary to put the systems into commercial use and to approval before Practical Completion is granted. Check and adjust each item of equipment individually, each service individually and each complete system as a whole to the design duties and generally as follows.

27.5.1 Hot, Cold and Re-use Water Systems & Storage

a) Check and prove all pressure and flow actuated controls, relief devices, bleeds, vents and drains to approval.

b) Fully open all control valves during balancing of water flows. Permanently mark final settings of all regulating valves in an appropriate manner.

c) Installed thermostatic mixing valves, back flow preventers and trap primers shall be checked and set by the manufacturers representative.

d) All Backflow prevention devices shall be tested, recorded and submitted to the appropriate authorities in accordance with manufactures and local authorities requirements.

e) Level indicators on rainwater and greywater storage tanks to be monitored by the BMS. High and low level alarms to be generated.

27.6 CONTROLS, GAUGES AND INSTRUMENTATION

Adjust period controls and activate by competent personnel provided by the manufacturer or his authorised agent. Maintain a complete log of the settings and readings of all controls, gauges and instruments throughout the Commissioning period.

27.6.1 Water meters

All water meters to be commissioned and monitored via the BMS. Maintain a complete log of the settings and readings throughout the Commissioning period.

27.6.2 Sewer pump station

Adjust level sensors and commission pumps as required. Pumps controlled by controller provided as part of the packaged pump station. BMS to monitor high and low level alarms.

27.6.3 Pumps

Commission all pumps as required and ensure they are operational and working within to the required duties.

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 4

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

BMS to monitor pump failures (all pumps) and temperature on hot water return lines.

27.6.4 Hot Water Plant

a) Top up levels within heat exchangers

b) Commission hot water system as required and ensure plant is operational and working within to the required peak hourly flow rate of 1000L/hr

c) BMS to monitor water meter located on cold water inlet of hot water plant

27.6.5 Electrical Control Panels and Switchboards

Prove the operation of all indicating and recording instruments and associated equipment and the indicating lights and associated flashers and relays under full working conditions.

27.7 TEST RECORDS

Submit test log sheets proposed to be used during the performance tests for approval at least 4 weeks prior to the commencement of the tests for all commissioning and testing items listed within this specification.

27.8 TEST AND INSTALLATION INSTRUMENTS

a) Supply all instruments and appliances necessary to complete the performance tests specified for the duration of the tests.

b) Use gauges, instruments and materials provided as permanent parts of the installation during performance testing.

c) Check test instruments proposed for use during performance testing for accuracy by the manufacturer or an approved laboratory.

d) Provide calibration certificates for each of the instruments to be used prior to the commencement of tests.

e) Check and calibrate all instruments provided as part of the installation as specified above and again after 6 months of normal operation. Replace any instrument which will not hold calibration.

27.9 TESTING

27.9.1 Piping

a) After installation and before any piping is concealed, the Sub Contractor must provide all necessary equipment for pressure testing of services as specified and/or as directed.

27.9.2 Sewerage and Stormwater

a) Arrange for all testing of work as required by the Authority and in accordance with the Quality Assurance Program.

b) On completion of all work, lodge the Authorities‟ certificate of approval with the Contractor.

27.9.3 Water Services

a) As pipework proceeds and on completion of each section, test the work to withstand a hydrostatic pressure of a minimum of twice the working pressure of the various service lines, but in no case less than 2,100 kPa as specified.

b) Maintain the pressure of each section under pressure test for a period of 4 hours.

c) Subject all pipework fabricated off site to pressure test prior to delivery on site.

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 5

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

d) Subject all pipework in inaccessible locations to water test prior to construction of surrounding walls.

27.10 PERFORMANCE TESTS

Carry out in addition to the commissioning requirements to the above, performance tests and any necessary final adjustments arising thereof, at a time to be nominated during the maintenance and guarantee period or, in the event of failure of the installation to meet the minimum requirements of the Specification, such extended period as may be permitted.

27.11 COMMISSIONING AND PERFORMANCE DATA

Provide copies of all data recorded during commissioning of the installation as detailed for performance tests together with all necessary inspection certificates from local authorities and appropriate manufacturer's pressure test certificates and performance curves or tables for the following items.

a) All pumps (including Q-H, NPSH and BKW curves applicable to the diameters and speeds of the installed impellers together with details of the installed, minimum and maximum impeller diameters).

b) Manufacturing guarantees in respect of motors, filters, pressure vessels, pumps and other items requiring performance.

c) Data covering all other specific items of equipment installed.

d) Noise level tests as appropriate.

When all data, certificates and performance curves referred to above have been received and approved, then practical completion is granted.

27.12 HANDING OVER

Adopt the following procedure prior to handing over the installation:

a) Carry out all preliminary testing, checking, adjusting and inspection of the installation before forwarding notification that the installation is considered to have reached Practical Completion.

b) After inspection, and when the approving authority is satisfied and agrees that the installation is ready for handing over to the Purchaser, commissioning of the systems is required and providing with installation manuals together with post contract drawings as specified.

After the installation has been inspected and approved and the above requirements fulfilled, practical completion is certified.

27.13 INDEPENDENT COMMISSIONING AGENT

The Testing and commissioning of this project is to be done in accordance with Green Star requirements and an Independent Commissioning Agent as engaged by the building owner. The section below is to be used as a guide for the organisation and management and then liaised with the sub contractors so as to test and verify the operation of individual items of plant and equipment, sub-systems, systems and the overall installation including the interfaces with other building services systems provided by others.

27.14 FINAL COMMISSIONING

Undertake final commissioning in 3 stages:

a) Major items of plant and equipment and components.

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 6

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

b) Systems and sub-systems.

c) Inter-system operation and interfaces.

Final commissioning to include:

a) Testing of performance of individual plant items and components.

b) Testing of operating sequences, interlocks and safeties.

c) Final water balancing.

d) Electrical testing and verification to AS/NZS 3000.

e) Final controls calibration.

f) System operation under all operating modes and under all conditions of load.

g) Inter-system operation and correct interfacing connections under all operating conditions and under simulated fire conditions.

h) Thermographic survey of hydraulic switchboards.

i) Water treatment tests and water analysis.

j) Environmental audit (if required).

k) Rectification and correction of any defects and deficiencies.

l) Cleaning of plant room, switchboards and all hydraulic services equipment and devices.

27.15 POST CONTRACT DRAWINGS

All as installed documents submitted shall have a stamp with similar words to the following and be signed prior to submission for review.

AS INSTALLED DRAWING

a) We certify that this drawing is an accurate record of the work installed by our company under the terms of our contract.

b) Sub-Contractor‟s Name………………………………………………………………........

c) Sub-Contractor‟s Address…………………………………………………………………

d) ……………………………………………………………………………………….

e) Signed…………………………………………….Date…………………………...

f) Printed………………………………………………………………………………

a) Maintain current sets of contract drawings and shop drawings on-site.

b) Progressively record changes to form a record of work as installed.

c) Prepare and submit for approval as-built drawings covering all aspects of the work.

d) Show dimensions, types and locations of equipment, cables, piping, ductwork pits and markers in relation to permanent site features and other underground services.

e) Show the „as-installed‟ locations of building elements, plant and equipment with particular emphasis on items requiring maintenance or clearing.

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 7

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

f) Show off-the-grid dimensions where applicable. Include relationship to building structure street features and other services and changes made during commissioning.

27.16 INSTALLATION MANUALS

Both electronic and hard copy manuals are required as noted in the scope of works

Supply 1 hard copy and 3 electronic copies of Operation and Maintenance Manuals prior to Practical Completion.

27.16.1 Hard Copy – 1 off

First draft manuals: Submit a first draft manual 8 weeks before the date for practical completion for review and to enable the Principal‟s staff to familiarise themselves with the installation. Include provisional record drawings and preliminary performance data. Format to be as for the final manuals, with temporary insertions for items which cannot be finalised until the installation is commissioned and tested.

Second drafts: Following receipt of comment on the first draft and not later than 2 weeks before the date for practical completion submit a completed second draft for review. If available, include certificates from authorities, warranties and commissioning test reports. These drafts are required to enable the Principal to safely operate the plant after handover.

Final copies: Submit final volumes within 2 weeks after practical completion. Incorporate feedback from review and from training of Principal‟s staff, including preparation and insertion of additional data. Include a section containing commissioning test reports.

Revisions: Prior to final completion, submit 1 section sets of loose leaf amendments for insertion in the manuals, incorporating feedback from the maintenance period.

Aim: To provide a detailed understanding of the plant and its operation, an aid for training of operators, a reference for fault diagnosis and a framework for preventative and breakdown maintenance.

Authors and compilers: Use personnel experienced in the maintenance and operation of equipment and systems installed and with editorial ability. Avoid use of “jargon”.

Warning and Cautions: Include to emphasise conditions hazardous to personnel or equipment, giving instructions to avoid the hazard. Format to be:

WARNING: An examining or testing procedure or practice which must be observed or risk loss of life or injury to personnel.

CAUTION: An examining or testing procedure or practice which must be followed or risk damage to equipment.

a) The manual shall be neatly prepared and bound in one, or a series of, vinyl hard-back folder with lettering on the front and the spine including the following information:

OPERATION AND MAINTENANCE MANUAL VOLUME NUMBER

PROJECT NAME DATE OF ISSUE

HYDRAULIC SERVICES CONTRACTOR

CONSULTING ENGINEERS – WSP LINCOLNE SCOTT

SUB CONTRACTOR

b) Co-ordinate with Contractor to ensure the correct stamping is provided.

c) Pagination: Number pages consecutively. Double sided on A4 size (minimum 50%) recycled white (minimum CIE whiteness of 140) paper, with reinforced binder perforations.

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 8

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

d) Ring size: 50mm maximum, with compressor bars. Not to be overloaded.

e) Dividers: Durable divider for each separate element, with typed description of system and major equipment components. Clearly print short titles under laminated plastic tabs.

f) Drawings: Fold illustrative drawings to A4 size and accommodate them in plastic pockets in the binder.

g) All aspects of the style and quality of the manual, including folders and contents shall be submitted for approval prior to completion.

h) After the draft copy has been approved, supply 1 copies of the manuals to the Contractor for issue to the Proprietor and the Superintendent.

27.16.2 Installation Manual Format

a) Section 1 - Index

I. Index all sub-divisions of each section including lists of drawings, equipment, etc. for quick reference.

II. Include index in every volume of the manuals.

b) Section 2 - General Description and Capacities of Installations:

I. Divide into sub-sections for general items and for each individual plumbing system as

II. Include a directory: Names, addresses and telephone and facsimile numbers of Principal Consultant, Sub-Consultants, Contractor, Sub-Contractors and names of responsible parties.

III. Include a scope of works: Statement of scope of services and interfacing with other Contracts.

IV. Include an installation description: General description of installation.

V. Systems description: Technical description of the systems installed, written to ensure that the Principal‟s staff fully understand the scope and facilities provided. Identify function, normal operating characteristics and limiting conditions. Include schematic diagrams.

VI. System performance: Technical description of the modes of operation of the systems installed.

c) Section 3 – Equipment:

I. Sub-divide as for Section 2 and list all major items of equipment installed complete with manufacturer's name, agent's name, contact details, model and/or type No., serial No., size, design ratings and including all relevant data necessary for re-ordering or replacing the equipment or components of same. As far as practicable, all equipment should be broken down to individually identifiable items such as, pump stations, hot water plant etc.

II. Provide manufacturers‟ technical literature for equipment installed, assembled specifically for the project, excluding irrelevant matter. Mark each product data sheet to clearly identify specific products and component parts used in the installation and data applicable to the installation. Do not include advertising literature.

d) Section 4 - Installation, Maintenance and Operating Instructions:

I. Sub-divide as for Section 2 and include manufacturer's installation, maintenance and operating instructions for each item of equipment such as sanitary and tapware, hot water plant, UV treatment, etc.

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 9

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

II. Emergency maintenance procedures, including telephone numbers for emergency services and after hour‟s contact for suppliers and Contractors and procedures for fault finding.

III. Manufacturer‟s technical literature as appropriate. Register with manufacturer as necessary. Retain copies delivered with equipment.

IV. Detailed recommendations for preventative maintenance frequency and procedures which should be adopted by the Principal to ensure the most efficient operation of the systems installed. Include inspection, testing and maintenance programme in tabular form showing frequency and level of routine checks for each item.

V. Safe trouble shooting, disassembly, repair and reassembly, cleaning, alignment and adjustment, balancing and checking procedures. Provide logical step-by-step sequence of instructions for each procedure. Include calibration and recommissioning of controls.

VI. Schedule of spares recommended to be held on site, being those items subject to wear or deterioration and which may involve the Principal in extended deliveries when replacements are required. Include complete nomenclature and model numbers, and local sources of supply. Include sectionalised diagrams of machines identifying component parts.

VII. Schedule of normal consumable items, local sources of supply and expected replacement intervals up to a running time of 40,000 hours. Include lubricant and lubrication schedules for equipment.

e) Section 5 - Plant Operating Instructions:

I. Sub-divide as for Section 2 and provide a complete description and correct sequence of all actions necessary to start-up, operate and shut-down all plant including procedures for seasonal changeovers. These instructions shall include full information on such items as normal and abnormal gauge readings, instrument settings and control points, differentials, time delays, oil levels, water temperatures, and all similar relevant variable and adjustable items, to permit checking and adjustments where practicable and identification of hazardous conditions or malfunction of plant. In addition the instructions shall include information on the immediate action to be taken in the event of hazardous conditions arising.

f) Section 6 - Performance Test Results:

I. This section shall be sub-divided as for Section 2 and shall include all performance test results as outlined in previous Clauses.

g) Section 7 – Certificates

Statutory Certificates of Compliance for:

I. Electrical Work.

II. Plumbing drainage or gas-fitting work.

III. Copies of manufacturers‟ warranties.

IV. Certificates from authorities and utilities.

V. Production certification.

VI. Copies of test certificates for the mechanical installation and equipment used in the installation, e.g. pressure vessels.

h) Section 8 – Drawings

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 10

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

I. Drawings and technical data: As necessary for the efficient operation and maintenance of the installation, and as specified elsewhere.

27.16.3 General Requirements

Documentation is required in electronic and hard copy format. Electronic documentation shall be supplied on the latest Microsoft and AutoCAD Software versions at the time of Practical Completion.

Scope of the documentation and format requirements comprise:

Document Format Sets

Operating and Maintenance Manuals Electronic installed on BMS File Server 1

CD ROM – Microsoft Office Latest Version

3

Hardcopy 3

As Built Drawings DVD – Revit Model 3

Hardcopy – Full Size 1

A3 Size 2

OH&S Safety Signage Permanent 1

27.17 REQUIRED OPERATING INSTRUCTIONS

Provide operating instructions and schematic diagrams mounted alongside equipment to meet statutory requirements, e.g. Fire Brigade. Diagrams to be colour-coded, colour-fast, laminated and mounted.

27.18 OWNER INSTRUCTION

The service of a fully knowledgeable Commissioning Engineer shall be required for a period of 2 full working weeks to instruct the Owner's nominated representatives including Consultants in all details of the plant operation.

27.19 ADDITIONAL GREEN STAR REQUIREMENTS

The following additional requirements are to be met if required by the Green Star Schedule in Schedules.

a) Comprehensive pre-commissioning, commissioning and quality monitoring are to be performed in accordance with ASHRAE Guideline 1 or CIBSE Commissioning Codes.

b) Provide a complete commissioning report which confirms that all commissioning is in compliance with the contract documents. The report must also include a list of outstanding commissioning issues, records of all functional/commissioning testing undertaken and list any seasonal testing required in the future.

c) Owner instruction to be spread over at least two sessions separated by at least two months. Issues covered must include:

I. Energy and environmental features of the design.

II. Review of the controls set-up, programming, alarms and trouble shooting.

III. Operating and Maintenance manuals.

IV. Building operation including start-up, normal operation, unoccupied operation, seasonal changeover and shutdown.

Advanced Engineering Building Hydraulic Services

Testing, Commissioning and handover – Section 27

Section 27 – Page 11

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

V. Interactions with other systems.

VI. Optimising energy efficiency.

VII. OH&S issues.

VIII. Maintenance requirements and sourcing replacements.

IX. Occupant satisfaction feedback.

d) Allow to coordinate the above with electrical and hydraulics Sub-Contractors so that a whole-building approach is achieved.

e) Separately from the routine maintenance and servicing, provide detailed formal monthly reviews of the Hydraulic Services provide written reports to the building owner quarterly detailing the status of the system, changes made, etc. As a minimum, each review shall include:

I. All system set points and timers.

II. Rectification of all BMS alarms and other faults.

III. Full load commissioning tests.

IV. Minor adjustments to BMS programmes, set points, water flows, etc. as found necessary from operating experience or as advised by the Superintendent to time the system for optimum performance and energy efficiency.

f) Provide a formal final re-commissioning of the hydraulic services in the final month before Final Completion (12 months after Practical Completion). As a minimum this is to include:

I. A written report to the building owner as per the quarterly review.

II. All quarterly issues.

g) Engagement of an Independent Commissioning Agent (ICA) as per Green Star requirements whose role will be to provide commissioning advice to the design team and to the Building Owner and to monitor and verify the commissioning of the HVAC and building control systems. The independent commissioning agent will report directly to the Building Owner and the primary goal of the agent is to independently identify system deficiencies as early in the project as possible and track their status until corrected. The ICA‟s role and responsibilities include:

I. Be an objective advocate of the Building Owner.

II. Review basis of design and design intent as well as preliminary working drawings.

III. Create a commissioning plan and direct the commissioning process that covers the following (if present): grey water treatment plant, hot water plant, thermostatic mixing valves, automatic controls, hot and cold water systems, air admittance valves.

IV. Introduce standards and strategies early in the design process.

V. Set target requirements in the contract documents to ensure implementation of selected measures.

VI. Coordinate with the Building Owner, design team and contractor throughout the commissioning, testing and adjustment phases.

VII. Observe all testing, review and approve contractor test results.

h) Prepare final commissioning report including recommendations to the Building Owner regarding the performance of commissioned building system.

Advanced Engineering Building Hydraulic Services

Routine Maintenance and Servicing – Section 28

Section 28 – Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

ROUTINE MAINTENANCE AND SERVICING 28.

28.1 SCOPE

a) Maintenance services shall include:

I. Preparation of a maintenance management plan which includes a detailed maintenance program, equipment schedules, statutory and preventative maintenance schedules, OH&S risk assessment, inspection and testing schedules, breakdown rectification management and reporting systems.

II. Preventative and corrective maintenance and testing services to assure specified system reliability and availability.

III. Statutory maintenance and testing required by the Building Regulations.

IV. Breakdown responses.

V. Annual full system fire and life safety system control and performance verification test to be carried out after hours.

VI. Comply with Building and Occupational Health and Safety Regulations.

VII. Comply with AS/NZS 3666.2:1995; AS/NZS 3666.3:2000; AS/NZS 1677.2:1998.

VIII. Comply with manufacturer‟s recommended maintenance program and schedules.

IX. Submit maintenance plan and schedules prior to Practical Completion.

a) Routine maintenance and servicing is to be carried out on a monthly basis for a period of 12 months from the date of Practical Completion to the end of the Maintenance and Defects Liability Period.

28.2 MAINTENANCE AND SERVICING REQUIREMENTS

a) Carry out routine testing, servicing and maintenance from date of Practical Completion to the end of Maintenance and Defects Liability Period.

b) Use maintenance procedures as appropriate to ensure the safe and proper operation of all systems in accordance with items outlined in „Testing & Commissioning' Section of this Specification, and pursuant to the scope of installation as set out in „Description and Extent of Work„ Section of this Specification.

c) Carry out routine testing and maintenance at monthly intervals and carry out emergency service on a 24 hour call out basis.

d) Include the following in testing of installation:

I. Pump installation working to capacity and operational

II. Domestic hot water plant is operational.

III. Backflow prevention devices have been commissioned and operational

IV. All pump controls and interface are operational

V. BMS interface has been confirmed and operational

VI. Hot water return pumps are operational.

VII. Water meters are interfacing with the BMS system.

VIII. Thermostatic valves are operating at set temperature.

IX. Tapware operating satisfactorily.

Advanced Engineering Building Hydraulic Services

Routine Maintenance and Servicing – Section 28

Section 28 – Page 2

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

X. Downpipe/overflow, planter drains, waste and drain systems clear of blockage.

XI. Siphonic stormwater outlets clear of blockage.

XII. Plastic inspection opening covers have been replaced with final chrome plated covers.

e) At the conclusion of each maintenance visit complete a check list of items tested and serviced, sign and submit the test record and service books check list to a responsible person on site. Within 7 days of the date of the service visit, forward a report together with a copy of the check list to the Contractor.

f) Advise the Contractor of the proposed date and service program for the last major visit not less than 7 days prior to the date of the proposed last visit so that a representative may be present to inspect the equipment and records.

g) Include recommendations on the tender submission for any further testing, maintenance and servicing procedures required for the particular equipment offered and include such services for in the tender price.

h) Do not release retention moneys or bank guarantee until correctly dated and completed reports covering the warranty period have been received at the appropriate times and approved. Should these inspections not be completed within the Maintenance and Defects Liability Period, then that period, including all equipment warranties will be extended until the inspections have been completed.

i) An emergency call out of service must provide the following:

I. Be available and able to be contacted by telephone 24 hours per day, 7 days a week.

II. Immediately investigate within two (2) hours on site when notified of the occurrence of any blockages, false alarms or fault from the installation.

III. Notify in writing to the Contractor the circumstances surrounding each call out. Notification shall be forwarded on the first working day after the call out.

IV. Replace and/or repair any malfunctioning equipment at his cost. Negotiate replacement costs associated with equipment malfunctioning due to blockages and/or vandalism with the Contractor.

V. Cost call-outs as a result of vandalism at current period Contract rates - labour and material.

VI. Provide a log sheet, detailing the labour and material used on each call.

VII. Pay out the total costs incurred at the end of the defects liability period.

28.3 GENERAL REQUIREMENTS

a) Monthly maintenance and servicing in accordance with maintenance schedules recommended by equipment manufacturers.

b) Maintenance, testing and inspections in accordance with regulatory requirements and relevant Australian Standards.

c) Rectification of defects at Sub-Contractors cost.

d) Operation and verification in conjunction with other services trades, of all fire and life safety systems. Such testing to be undertaken at 6 monthly intervals.

e) Replacement of consumables (e.g. filter media, chemicals) at Sub-Contractors cost.

f) Submission of monthly reports to Principal and Superintendent on maintenance activities performed.

Advanced Engineering Building Hydraulic Services

Routine Maintenance and Servicing – Section 28

Section 28 – Page 3

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

g) Provision and filling out log book which must be kept on site, detailing all visits.

h) Service personnel to be available for call out on a 24 hour per day, 7 day per week basis. Response time for emergency and corrective maintenance must not exceed 4 hours.

28.4 PREVENTATIVE MAINTENANCE AND TESTING

As a minimum, regular maintenance and servicing tasks to include.

28.4.1 Monthly

a) Check and adjust all belt drives and couplings.

b) Check and report on necessity for replacement of filter media.

c) Oil and grease all bearings.

d) Clean as necessary drip trays, strainers and other sediment collecting items, which may become fouled.

e) Adjust and repack as appropriate, glands of all pumps and valves.

f) Check, test and report on chemical treatment as required.

g) Dose chemicals as necessary.

28.4.2 Quarterly

a) Check operation, setting and calibration of all controls.

b) Check all motors for temperature rise, operating current and leakage.

c) Check and adjust boilers, burners and water levels in water heaters.

28.4.3 Six Monthly

a) Check internal and external vibration isolation.

b) Check operation of all electrical switchgear including setting and operation of motor overloads.

28.4.4 Last Maintenance Visit

a) Check all motor starters and relay controls.

b) Check all electric motors and check overloads.

c) Undertake thermal scanning of switchboards and report thereon.

d) Check all system safeties.

e) Replace all filter media and disposable filters.

f) Check test and report on the building rainwater re-use system including inspection of the rainwater tank.

g) The date for the final maintenance visit to be advised 7 days prior to the proposed visit so that a representative may be present to inspect the equipment when end covers are removed.

28.5 MAINTENANCE RECORDS

a) Mandatory maintenance records to include monthly maintenance and service reports, including water treatment reports, reports on all defects and their rectification, certification of the correct operation of essential services and a maintenance log book.

Advanced Engineering Building Hydraulic Services

Routine Maintenance and Servicing – Section 28

Section 28 – Page 4

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

b) Monthly Maintenance and Service Reports to include:

I. Check list of all items serviced and inspected.

II. Description of maintenance performed.

III. Notes on supplementary maintenance required.

c) Maintenance Log Book to include:

I. Schedule of all equipment.

II. Register of maintenance visits and cross reference to service reports.

III. Register of work performed under headings of preventive maintenance, corrective and emergency maintenance and defects rectification.

d) The Maintenance Log Book is to be kept in a locked cabinet provided for the purpose in an agreed location on site.

e) At the conclusion of each maintenance visit the log book is to be duly completed and signed off by an authorised representative of the Building Owner and service records are to be forwarded to the Building Owner or his representative within 7 days of each monthly visit.

28.6 DEFECTS, LIABILITY AND WARRANTY PERIOD

a) Defects liability and warranty period covers the same time frame as the Maintenance period, normally 12 months from the date for Practical Completion.

b) Where plant, equipment and systems are delivered to site, or installed, or made operational in advance of the date for Practical Completion, the warranty on such equipment and liability for defects on such equipment and systems, shall be extended to cover the whole of the time to 12 months from the date for Practical Completion.

c) Without exception, the whole of the works covered by this Specification shall be under warranty and subject to rectification of defects, until 12 months from the date for Practical Completion.

28.7 MAINTENANCE PROPOSAL

At least 6 weeks prior to the end of the Maintenance and Defects Liability Period submit a proposal to carry out on going preventive maintenance and corrective breakdown maintenance for a period of 2 years giving details of the maintenance procedures to be carried out including any overhauls or additional levels of service required.

28.8 FINAL COMPLETION

a) Final Completion will not be granted until maintenance records are complete and signed off and until all defects have been rectified and inspected.

b) The Maintenance and Defects Liability Period may be extended unless 12 monthly maintenance and servicing visits have been made and reported as specified.

28.9 BUILDING TUNING

Undertake a commissioning process over a period of at least 12 months which includes no less than monthly monitoring, quarterly reviews and reporting and a full re-commissioning service carried out 12 months after practical completion.

Generate a Building Tuning Report for the building owner.

List the roles and responsibilities of the various parties to be involved during this period.

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 5

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

SCHEDULES 29.

29.1 GENERAL

The following schedules have been prepared for tendering purposes and to convey design intent. They form a summary of the preceding Clauses in the Specification and must be read in conjunction with these Clauses and the Project Drawings.

Where reference Clauses are referred to, they shall be taken as the major Clause, but equipment shall also comply with all other relevant Clauses in the Specification.

Water quantities and temperatures may be changed slightly to suit the particular manufacturer‟s equipment, however full details shall be submitted for review. Changes shall not be in conflict with any By-Laws, Statutory Requirements (including BCA Section J where applicable), Public Health Requirements or the overall design in general including achievement of any energy compliance and Green Star criteria.

Pump duties have been calculated from typical equipment and have been given as a guide only.

The following schedules show details of hydraulic equipment only.

THE EQUIPMENT PAGES OF This schedule must be submitted with the tender offer in the current tabulated form with „tender‟ columns and rows completed.

Schedule of equipment submitted on alternate forms, manufacturers‟ data sheets, contractor work sheets, etc. will not be accepted.

Completion of the technical schedule for tender review does not constitute approval of proposed equipment nor does it absolve the requirement to satisfy the requirements of the specification.

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 6

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

29.2 SCHEDULE OF EQUIPMENT

SEWER SUBMERSIBLE PUMP STATION

Location Level 1 South East

Well Capacity 1500 litres (effective)

Pump Flow rate 1.7 l/s (each)

Head 5m

Operation / Rating 3 Phase: 1.5kW

Type Submersible sewage pump with Cutter system in pump inlet

System 2 Pumps (100%)

Accessories High Level Alarm to BMS

Light Duty GATIC access cover

Make / Model Aquatec Environmental packaged sewer pump station AFPS-OGP – STD – 002

Ph: (03) 1800 852 782

IRRIGATION TANK

Location Level 1 tank room

Capacity 70,000 litres (min effective)

Dimensions 3 x ø 3600 tanks 2800 high at apex

System Multiple polyethylene tanks with interconnecting pipework. Inlets and outlets manifolded together.

Mosquito proof stainless steel mesh on all inlets and outlets.

Mounted on slab

Accessories 1 x ø150 inlet (each tank)

1 x ø150 outlet (overflow – each tank)

1 x ø25 valved outlet (ball valve – each tank)

1 x ø50 drain (each tank)

Make / Model Action Tanks RPT5200 (23,600 litres each)

Ph: (07) 5442 4242

GREASE ARRESTOR

Location Level 3 – North

Treatment rate 1000 litres / hr

Dimensions 2000 length x 1000 width

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 7

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

System Concrete inground with 2 part infill galvanised mild steel GATIC cover and frame and 300mm risers to suit depth.

Make / Model Icon Septec 303C6121D

SILT ARRESTOR

Location Level 2 – South

Capacity 1000 litres

Dimensions 2140 length x 800 width

System Concrete inground with 3 part Class D cast iron cover and frame and 300mm risers to suit depth.

Make / Model Icon Septec 303C6121D

GROSS POLLUTANT TRAP

Location Level 1 – Hydraulics Lab

Treatment Rate Up to 150 l/s

Dimensions 1050 diameter x 2400 deep

System Polyethylene inground with Class D cast iron cover.

Make / Model CDS Technologies – Little Nipper – CDS0506 (part of Rocla group of companies)

GENERAL PURPOSE PIT

Location Level 1 – Geo-Mechanics Lab

Capacity 2000 litres

Dimensions 2050 length x 860 width

System Concrete inground with 3 part Class C cast iron cover and frame.

Make / Model Mascot Engineering TT100 without internal trash screens and fitting.

RAINWATER PRESSURE PUMPS

Location Level 7 Plantroom

No off 2 off

Flow rate 1.5 l/s

Head 20m

Operation / Rating 3 Phase: 1,1 kW/10,5A

Type Variable speed drive

System Duty / standyby packaged pump set with potable cold water bypass.

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 8

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Make / Model Grundfos, HYDRO MPC-E 2xCRIE5-8 415V 50Hz +PT80

FLUME SUMP PUMPS

Location Large In-Ground Sump, Level 1

No off 3

Flow rate 2 x 100 l/s + 1 x 45 l/s

Head 8 m

Operation / Rating 2 x 16 kW/160 A + 4,5 kW/83 A

Type Submersible, channel impeller

Make / Model 2 x Grundfos S1.100.200.135.4.54L.S.261.G.N.D

1 x Grundfos SE1.100.150.55.A.4.50B

Controller 1 x Hydro MPC 2 x VSD with emergency stop

STEPPED SPILLWAY FLUME PUMPS

Location Stepped Spillway Flume Sump, Level 1

No off 3

Flow rate 2 x 80 l/s + 1 x 200 l/s

Head 15m

Operation / Rating 2 x 20 kW/161 A + 46 kW/437 A

Type Submersible, channel impeller

Make / Model 2 x GrundfosS1.100.200.170.4.54L.S.285.G.N.D

1 x GrundfosS2.100.200.400.4.62L.S.285.G.N.D

Controller 1 x Hydro MPC + 1 x remote panel with VSD adjustment by dial or touch sensor, emergency stop on remote panel

LONG TILTING FLUME PUMPS

Location Large In-Ground Sump, Level 1, at Tilting Flume

No off 2

Flow rate 2 x 45 l/s

Head 5,5 m

Operation / Rating 2 x 4,9 kW/64A

Type Submersible, channel impeller

Make / Model 2 x Grundfos SE1.100.150.40.A.4.50B

Controller 1 x Hydro MPC + 1 x remote panel with VSD adjustment by dial or touch sensor, emergency stop on remote panel

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 9

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

PLUNGING JET FLUME PUMP

Location Large In-Ground Sump, Level 1, at Tilting Flume

No off 1

Flow rate 45 l/s

Head 5,5 m

Operation / Rating 4,9 kW/64A

Type Submersible, channel impeller

Make / Model Grundfos SE1.100.150.40.A.4.50B

Controller 1 x Hydro MPC + 1 x remote panel with VSD adjustment by dial or touch sensor, emergency stop on remote panel

REVERSE OSMOSIS WATER CIRCULATING PUMPS

Location Level 6 plantroom

No off 2 off

Flow rate 1,5 l/s

Head 25 m

Operation / Rating 0,3 kW

Type Vertical Multistage centrifugal, end suction

Make / Model 2 x Grundfos CRN 5-4

HOT WATER CIRCULATING PUMP STATION – Potable

Location Plantroom L14

No off 2 0ff

Flow rate 0.2 l/s

Head 7m

Operation / Rating Single Phase: 10 AMP

Type Centrifugal, canned rotor type

System 2 Pumps (100% flow rate each) duty / standby

Make / Model Grundfos UPS 25-60B

HOT WATER CIRCULATING PUMP STATION – Non Potable

Location Plantroom L14

No off 2 0ff

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 10

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Flow rate 0.2 l/s

Head 7m

Operation / Rating Single Phase: 10 AMP

Type Centrifugal, canned rotor type

System 2 Pumps (100% flow rate each) duty / standby

Make / Model Grundfos UPS 25-60B

HOT WATER PLANT

Location Level 7 Plantroom

No off 3 off

First hour delivery 1000 L

System Polyethylene heat exchangers with dual stainless steel coils – potable and non-potable coil – with valved connections to mechanical heating plant.

Make / Model Rotex Sanicube

WATER METERS up to 50mm – Cold Water

Type Positive displacement volumetric rotary - pulse capable

Pulse 1 pulse / 10 litres

Model / Make Elster V100 (PSM-T) inline

Accessories Isolation valves (ball) upstream and downstream

Barrel union downstream

WATER METERS up to 50mm – Water over 50°C

Type Multi-jet - pulse capable

Pulse 1 pulse / 10 litres

Model / Make Elster M150 inline with pulse output

Accessories Isolation valves (ball) upstream and downstream

Barrel union downstream

WATER METERS 50mm and over

Type Single jet turbine – pulse capable

Pulse 1 pulse / 10 litres

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 11

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Model / Make Elster S2000

Accessories Isolation valves (gate) upstream and downstream

Flanged connections

SILT TRAPS – UNDER SINK

Location As shown on drawings

System 50 litre polyethylene silt trap with internal baffles and mounted stainless steel frame with castors.

Make / Model Halgan PTUS/PE/5

SILT TRAPS – FLOOR

Location Concrete Lab and Geo Mechanics Lab

System 450 x 450 316 Stainless steel tray with perforated basket – 200mm deep. No holes in the bottom 100mm. Fixed grate at base of tray. Heavy duty grate for forklift access.

Make / Model Stainless Metal Craft AT-9

REVERSE OSMOSIS PLANT

Location Level 6 Plantroom

No off 1 off

Flow rate 55 l/min

Water Quality Type 2

System Membrane filter package unit with 500 litre storage tank.

Make / Model Millipore Elix 35 with storage tank.

FIRE HOSE REELS

Location All

Make / Model Wormalds model HR3691P

CONCRETE CURING - TANKS

Location Level 2 Concrete Curing lab

No off 2 off

Dimensions 1900 (L) x 800 (W) x 600 (D) – internal

Accessories Stands

Heater element and control panel

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 12

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Circulating pump

Raised base rack

50mm drain

Overflow

Make / Model Geo-Con model 55-C0190/CON.

CONCRETE CURING – ROLLING DRAINAGE RACK

Location Level 2 Concrete Curing lab

No off 2 off

Make / Model Geo-Con model 55-C0190/1. CON.

CONCRETE CURING – SPECIMEN BASKETS

Location Level 2 Concrete Curing lab

No off 19 off

Dimensions 900 (L) x 450 (W) x 250 (D) – overall

Make / Model Geo-Con model 55-C0190/2. CON.

CONCRETE CURING – DATA LOGGER

Location Level 2 Concrete Curing lab

No off 2 off

Accessories Dual pH and temperature logger

Simultaneous display of pH and temperature

7-day rolling data logger set at hourly intervals

Audible and visible alarms located outside lab

Waterproof

All cables and probes

Interface with BMS or computer for data logging / alarm.

Make / Model Geo-Con model 55-C0195/1.

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 13

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

29.3 SCHEDULE OF VALVES

PRESSURE LIMITING VALVE

Location As shown

Size Up to 32mm

Accessories Isolation valve upstream

Operation Preset to max 350 kPa or 500 kPa as shown on schematics

Make / Model RMC PS50 (15mm), PS75 (20mm), PS100 (25mm)

PRESSURE REDUCING VALVES

Location As shown

Size 32mm and over

Accessories Isolation valve upstream

Operation Preset to max 350 kPa or 500 kPa as shown on schematics

Make / Model RMC PRV2532 (32mm), PRV2540 (40mm), PRV2550(50mm), PRV80 (80mm), PRV100 (100mm)

THERMOSTATIC MIXING VALVE

Location Amenities, first aid room and parents room

Accessories Isolation valve (ball) on inlet to hot and cold water

Model / Make Enware Aquablend 1000

THERMOSTATIC MIXING VALVE

Location Laboratory hand washing basins (under)

Accessories Isolation valve (ball) on inlet to hot and cold water

Model / Make Broen Stabitherm

ISOLATION VALVE – up to 65mm

Location As shown on drawings

Accessories Brass body with stainless steel ball - quarter turn and lockable handle.

Barrel union downstream.

Model / Make Isis Valves

ISOLATION VALVE – 65mm and over

Location As shown on drawings

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 14

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Accessories Ductile iron body gate valve with non rising stem.

Resilient seated.

Flanged joints with fibre gasket.

Galvanised steel bolts and nuts

Model / Make Tyco valves with Rilsan nylon 11 polymeric coating.

HOT WATER BALANCING VALVE

Location End of all hot water flow lines

Accessories Isolation valve upstream and barrel union downstream.

Model / Make Tour Anderson (TA) Therm

SINGLE CHECK VALVE

Location All

Model / Make Tyco

Accessories Isolation valves upstream and downstream

Strainer upstream

Barrel unions upstream and downstream

DOUBLE CHECK VALVE up to 50mm

Location All

Model / Make Tyco

Accessories Isolation valves upstream and downstream

Strainer upstream

Barrel unions upstream and downstream

DOUBLE CHECK VALVE 50mm and over

Location All

Model / Make Tyco

Accessories Isolation valves upstream and downstream

Strainer upstream

Flanged joints

REDUCED PRESSURE ZONE DEVICE (RPZD) VALVE up to 100mm

Location All

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 15

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Model / Make Watts/RMC009 series

Accessories Isolation valves upstream and downstream

Strainer upstream

Barrel unions upstream and downstream for 50mm and smaller

Flanged joints for 65mm and over

REDUCED PRESSURE ZONE DEVICE (RPZD) VALVE 100mm and over

Location All

Model / Make Watts / RMC 909 series

Accessories Isolation valves upstream and downstream

Strainer upstream

Flanged joints

AUTO FLUSHING VALVE

Location Laboratories and plantrooms

System Valve to flush every 12 hours and discharge over tundishes to charge traps. Duration of flush to be set to between 5 and 10 seconds.

PIR sensor to be concealed to avoid activation from movement.

Model / Make Zip Flushmaster Standard

ISOLATION VALVE – Flume pipework – Level 1

Location Level 1 Hydraulics Lab – Flume pipework

Accessories Butterfly valve, with manually operated quarter-turn handle and notched plate for valve setting

Flanged connections with fibre gaskets.

ISOLATION VALVE – Reverse Osmosis pipework

Location Laboratories and Plantrooms

Model / Make Asahi diaphragm valves (type 14) – poly propylene with EPDM diaphragm

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 16

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 17

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

29.4 SCHEDULE OF STORMWATER PITS AND OUTLETS

29.4.1 GRATED DRAINS

Location LEVEL 1 HYDRAULICS LAB : MAIN FLUME SUMP

Dimension 709mm wide, in 995mm lengths along each edge

Make / Model Webforge galvanised mild steel Class D MTG60D Trench Grate (07) 3859 8300

Location LEVEL 2 and LEVEL 5 TERRACE

Dimension 200mm wide

Make / Model ACO polycrete drain K200S series with lockable stainless steel heelguard grate (07) 3267 8700

Location DOOR THRESHOLDS (ALL)

Dimension 100mm wide

Make / Model ACO polycrete drain K100S series with lockable stainless steel heelguard grate (07) 3267 8700

29.4.2 ACCESS COVERS

Location LEVEL 1 HYDRAULICS LAB MAIN FLUME PUMP SUMP

Dimension 6-part cover and removable frame (2,550 x 1,570mm), plus

4-part cover and removable frame (1,350 x 970mm)

Make / Model Class D Recessed Ductile Iron Access Cover and Frame

ACO Rhinocast

(07) 3267 8700

Location LEVEL 1 HYDRAULICS LAB TILTING FLUME PUMP SUMP

Dimension 6-part cover and removable frame (2,550 x 1,570mm), plus

8-part cover and removable frame (3,300 x 1,270mm)

Make / Model Class D Recessed Ductile Iron Access Cover and Frame

ACO Rhinocast

(07) 3267 8700

Location LEVEL 1 HYDRAULICS LAB STEPPED SPILLWAY FLUME PUMP SUMP

Dimension 8-part cover and removable frame (3,000 x 1,570mm), plus

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 18

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

600 x 600mm cover and removable frame

Make / Model Class D Recessed Ductile Iron Access Cover and Frame

ACO Rhinocast

(07) 3267 8700

29.4.3 STORMWATER PITS

PIT PIT LOCATION

SIZE MATERIAL COVER TYPE DEPTH

(mm)

MAKE/MODEL

SWP1 Level 1 – adjacent stepped spillway flume.

900 x 900

Polycrete Grated - Galvanised mild steel Class D

900 ACO

GO Level 1 - Base of downpipes

300 x 300

Polycrete Grated - Galvanised mild steel Class D

300 ACO

29.4.4 STORMWATER OUTLETS

OUTLET CODE

OUTLET NAME LOCATION SPECIFICATION

GO Grated Outlet Level 5 terrace

Level 6 terrace

150 Square Floor Drain with no grate to drain membrane – trench drain to discharge into outlet.

200 Square Retro-fit floor drain to drain tiles

SPS Q150 C (body only)

SPS Q200S/Q

GO Grated Outlet Top of level 3 entry awning (west and north)

SPS truflo dome grate with membrane clamping ring

TIB 100D2

GO Grated Outlet Roof SPS Superflo dome grate with membrane clamping ring

TIB 150D2

PBO Planter Box Outlet

All 150 Square Floor Drain with no grate to drain planter base

200 Square Retro-fit floor drain to drain tiles

SPS Q150 C (body only)

SPS Q200S/Q

SDO Spoon Drain Outlet

Level 1 dry wall SPS 100mm round Vertical Drain

R100B/C

PO Parapet Outlet Top of Level 3 entry awning (west) and Jocks Rd awning.

SPS PD100CG

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 19

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

SO Siphonic Outlet Roof As supplied by Syfon

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 20

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

29.5 SCHEDULE OF FLOOR DRAINS

OUTLET CODE

OUTLET NAME LOCATION SPECIFICATION

FW Floorwaste Safety shower / lab handbasin stations

100 chrome plated brass grate with 100mm riser

FW Floorwaste Amenities Refer architectural schedule (Appendix A)

PFW Plantroom Floorwaste

All SPS 150mm round floor drain with brass grate and cast iron body

Model: R150G/C

BFW Basket Floorwaste

All SPS 150mm round basket floor drain with 316 stainless steel grate and cast iron body. Include sediment basket.

SHR Shower Waste All Refer architectural schedule (Appendix A)

IOS Inspection opening to surface

Internal Areas - Amenity

Stainless steel body and cover

Galvin Engineering model: 67736SS

IOS Inspection opening to surface

Internal Areas - Labs

Stainless steel body and cover suitable for forklift loads

Galvin Engineering model: 67736SS

IOS Inspection opening to surface

External Nickel / bronze cover and body suitable for forklift loads

Galvin Engineering model: 67736

29.6 SCHEDULE OF INSULATION

TYPE LOCATION DESCRIPTION SPECIFICATION

Thermal All hot water pipework (flow return and deadlegs)

Close celled elastomer – 25mm thick

Thermotec Zero 4 – 25mm thick

Thermal All air conditioning condensate drainage lines back to stack

Close celled elstomer – 19mm thick

Armaflex

Acoustic All sanitary and stormwater drainage lines above office areas

5.0 kg/ flexible loaded vinyl bonded to 25mm thick flexible convoluted foam in lieu of Geberit Silent pipework.

Soundlag 4525C

Note: Alternative insulations must satisfy the stricter of the BCA Section J requirements and the above WSP Lincolne Scott requirements. In addition, alternatives must have zero ODP in both product and manufacture.

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 21

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Where exposed, insulation shall be sheathed with mild steel sheet, painted and labelled to specification.

29.7 SCHEDULE OF WATERPROOFING

LOCATION DESCRIPTION SPECIFICATION

Level 7 Rainwater Tank Elastomeric polymer applied in liquid form.

Daclar from Liquid Rubber Australia Pty Ltd

Ph 07 5568 0544

Level 2 Header tank Elastomeric polymer applied in liquid form.

Daclar from Liquid Rubber Australia Pty Ltd

Ph 07 5568 0544

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 22

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

29.9 SCHEDULE OF PIPE MATERIALS

Note – all exposed pipework and pipework located above lab areas to be painted. Pipework requiring insulation shall be metal sheathed prior to painting.

SERVICE LOCATION MATERIAL NOMINAL PIPE SIZE

Stormwater Above + Below ground HDPE with butt weld, acoustic specification where designated

100- 300

Stormwater Below ground FRC 300-600

Siphonic Stormwater Above + below ground HDPE and Stainless Steel (horizontal above tenancy areas) – refer Syfon specification for materials of specific locations, acoustic specification where designated

50- 350

Sewer Drainage Below ground PPR 100-225

Sewer Drainage from high temperature discharge

All HDPE with fusion welded joints or PPR

50-100

Sanitary stack Above ground HDPE with fusion welded joints, acoustic specification where designated

50-150

Vent pipes Above ground HDPE with fusion welded joints

40 - 150

Sewer rising main Above and below ground

HDPE – pressure PN 6 32–100

Trade waste drainage

Above ground HDPE with fusion welded joints equal to Geberit Silent.

50-150

Trade waste drainage

Lab sink trap and waste above slab (under sink)

Chrome plated copper 50

Trade waste stack Above ground HDPE with fusion welded joints equal to Geberit Silent.

100-150

Trade waste vent Above ground HDPE with butt welds 50-100

Sanitary Plumbing Above ground HDPE with fusion welded joints equal to Geberit Silent.

40-150

Condensate drain Above ground HDPE with fusion welded joints

Horizontal lines to be lagged.

25 - 100

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 23

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Cold water mains Below ground Ductile Iron, cement lined with polyethylene sleeve.

50-150

Cold water service Above ground Copper tubes to AS 1432-1990 Type B

Chrome plated where exposed in labs and public spaces.

Painted in plantrooms.

15-150

Hot water service Above ground Copper tubes to AS 1432-1990 Type B

15-100

Hot and cold water rough-ins

Above ground Copper tubes to AS 1432-1990 Type B

15-25

Hot and cold water rough-ins

Surface (wall) mounted below 2700 AFFL in labs and public spaces

Chrome plated copper (Type B) with chrome plated brackets.

15-25

Rainwater reticulation and rough ins

Above and below ground

Polypropylene pipe 25-100

Fire hydrant service Above ground Galvanized mild steel tube with rolled grove joints. (Light weight pipe not permitted without prior approval)

100 - 150

Fire hydrant service Below ground Ductile Iron, cement lined with polyethylene sleeve.

100-150

Fire hose reel service

Above and below ground

Galvanized mild steel tube 25-65

Natural and LP gas service

Above ground Copper tubes to AS 1432-1990 Type B

15-150

Natural and LP gas service

Below ground Medium Density Polyethylene

20-150

Fire Hydrant Test Drain

All HDPE with fusion welded joints

150

Sewer pumpout line Above ground Galvanised mild steel 50

Flume Supply Pipework

Header tank to flumes uPVC Class 6 pressure pipe, with solvent welded joints

150 – 200

Flume Overflow Pipework

Header tanks to sump uPVC Class 6 pressure pipe, with solvent welded joints

200

Flume pumped rising main pipework

Sump pumps to header tank

uPVC Class 6 pressure pipe, with solvent welded joints

250

Reverse Osmosis pipework

All Polypropylene, with thermally welded joints – George Fischer Piping

40

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 24

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Systems

SCHEDULE OF TAPWARE AND FIXTURES

29.9.1 AMENITY

Refer Appendix A plus the following additions.

FIXTURE CODE

DESCRIPTION LOCATION SPECIFICATION

SK Staff tea sinks All SINK PLUG AND BASKET WASTE

Manufacturer: Clark

Product Ref: A0182

Description: 304 stainless steel plug and medium basket waste

Finish: Stainless steel

Trap and expose pipework to be chrome plated copper.

29.9.2 LABORATORY

FIXTURE CODE

DESCRIPTION LOCATION SPECIFICATION

SS/EW SAFETY SHOWER / EYEWASH COMBINATION

As shown on drawings

Manufacturer: Broen

Product Ref: 17 968.004 VVS:766172 300 Stainless-steel, free standing

Description: Disability-friendly body shower with eye/face shower and bow

HB Handwashing basin in labs

As shown on drawings

FIXTURE

Manufacturer: Britex

Product Ref: HBVR

Description: Wall-mounted, with 300mm high Stainless steel splashback. Bowl to be 400mm diameter.

Finish: Stainless Steel

TAPSET

Manufacturer: Hansa

Product Ref: Medica Prado Basin Mixer #014222460037

Finish: Stainless steel

TAPSET (PC2 designated rooms – Environmental lab on

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 25

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Level 4 and AMCP lab on Level 5

Manufacturer: Enware

Product: Enmatic 5000 – model ENM5021

Finish: Chrome

CS Cleaners Sink In labs only FIXTURE

Manufacturer: Caroma

Product Ref: 811592, 811594 and 811593.

Description: Wall mounted vitreous china with heavy chrome plated grate.

Finish: White

TAPSET

Manufacturer: Reece

Product Ref: Posh Solus sink mixer with extended lever

Finish: Chrome

LS Laboratory Sinks

All LABORATORY SINK PLUG AND WASTE

Manufacturer: Stainless Metal Craft

Product Ref: P&WSS316

Description: stainless steel plug and waste

Finish: Stainless steel

LST1 Lab sinks As shown on drawings

LABORATORY SINK TAPSET

Manufacturer: Broen

Product Ref: 15 264.009 with Ballofix shut-off valve

Finish: White

LST2 Lab sinks (cold water only)

As shown on drawings

LABORATORY SINK TAPSET (cold only)

Manufacturer: Broen

Product Ref: 15 277.009 with Ballofix shut-off valve

Finish: White

LST3 Lab Sinks – RO water

As shown on drawings

LABORATORY SINK RO TAPSET

Manufacturer: Broen

Product Ref: 15 410.009 with Ballofix shut-off valve

Finish: White

LTS4 Lab Sink As shown on drawings

SPRAY RINSE ARM

Manufacturer: Enware

Product Ref: FWS131

Finish: Chrome

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 26

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

FCT1 Fume cupboard water tapset – hot and cold

As shown on drawings

Terminate with isolation valve. Braided hoses and tapware supplied with Fume Cupboard. Supply and install trap and waste to Fume Cupboard sink.

FCT2 Fume cupboard RO water tapset

As shown on drawings

Terminate with isolation valve. Braided hoses and tapware supplied with Fume Cupboard. Connect hose to isolation valve after installation of fume cupboard.

FCT3 Fume cupboard gas turret

As shown on drawings

Terminate with isolation valve. Braided hoses and tapware supplied with Fume Cupboard. Connect hose to isolation valve after installation of fume cupboard.

HT Hose tap In labs and amenities

Wall mounted 20mm chrome plated brass tap

HT Hose tap In plantrooms Wall mounted 20mm brass tap

WMTSS 1,800mm Long Wall-mounted Trough

Undergrads. Lab

FIXTURE

Manufacturer: Britex

Product Ref: TP3 with 300mm high Stainless steel splashback

TAPSET

Manufacturer: Broen

Product Ref: 15 264.009 with Ballofix shut-off valve

Finish: White

GT Gas Turret In Labs GAS TURRET

Manufacturer: Broen

Product Ref: 15 013.909

Finish: White

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 27

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

29.10 SCHEDULE OF BOILING WATER UNITS

FIXTURE CODE

DESCRIPTION LOCATION SPECIFICATION

BCWU Boiling / Chilled Water unit

All tea sinks / staff cafes

Manufacturer: ZIP

Product Ref: BC125/100

Description: Under bench chilled boiling water unit – GPO connection

DFS / DFP Drinking Fountain

All and as shown on drawings.

Manufacturer: ZIP

Product Ref: Chill Fountain CFB 140FAW 37096

Description: Wall mounted drinking fountain – Adult / Wheelchair suitable.

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 28

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

29.11 SCHEDULE OF BMS POINTS

Item Location Signal type Input / Output Number

Cold Water Meter – Amenities

Level 1 Pulse (digital) Output 1

Cold Water Meter – Amenities

Level 2 Pulse (digital) Output 1

Cold Water Meter – Cyclist Facilities

Level 2 Pulse (digital) Output 1

Cold Water Meter – Amenities

Level 3 Pulse (digital) Output 1

Cold Water Meter – Amenities

Level 4 Pulse (digital) Output 1

Cold Water Meter – Amenities

Level 5 Pulse (digital) Output 1

Cold Water Meter – Amenities

Level 6 Pulse (digital) Output 1

Hot Water Meter – Amenities

Level 1 Pulse (digital) Output 1

Hot Water Meter – Amenities

Level 2 Pulse (digital) Output 1

Hot Water Meter – Cyclist Facilities

Level 2 Pulse (digital) Output 1

Hot Water Meter – Amenities

Level 3 Pulse (digital) Output 1

Hot Water Meter – Amenities

Level 4 Pulse (digital) Output 1

Hot Water Meter – Amenities

Level 5 Pulse (digital) Output 1

Hot Water Meter – Amenities

Level 6 Pulse (digital) Output 1

Non-Potable Cold Water Meter – Labs

Level 1 Pulse (digital) Output 1

Non-Potable Cold Water Meter – Labs

Level 2 Pulse (digital) Output 1

Non-Potable Cold Water Meter – Labs

Level 4 Pulse (digital) Output 1

Non-Potable Cold Water Meter – Labs

Level 5 Pulse (digital) Output 1

Non-Potable Cold Water Meter – Labs

Level 6 Pulse (digital) Output 1

Water Meter – Master Level 2 Pulse (digital) Output 1

Water Meter – Retail Level 2 Pulse (digital) Output 1

Advanced Engineering Building Hydraulic Services

Schedules – Section 29

Section 29 – Page 29

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

Water Meter – Flumes Level 1 Pulse (digital) Output 1

Water Meter – Wave basin, stepped spillway, Tsunami, Ocean

Level 1 Pulse (digital) Output 1

Water Meter – Cold water to hot water plant

Level 7 Pulse (digital) Output 1

Water Meter – Non Potable cold water to non-potable hot water plant

Level 7 Pulse (digital) Output 1

Water Meter – Cold water to mechanical plant

Level 7 Pulse (digital) Output 1

Water Meter – Cold water to cooling towers

Level 7 Pulse (digital) Output 1

Water Meter – Cold water make-up for toilet flushing

Level 7 Pulse (digital) Output 1

Water Meter – Rainwater tank outlet

Level 7 Pulse (digital) Output 1

Water Meter – Cold water to RO plant

Level 6 plantroom

Pulse (digital) Output 1

Gas Meter – Mechanical Heating Water Plant

Level 7 Pulse (digital) Output 1

Gas Meter – Co-generation gas engine

Level 7 Pulse (digital) Output 1

RO plant – Pump 1 Level 6 plantroom

Failure (digital)

Output 1

RO plant – Pump 2 Level 6 plantroom

Failure (digital)

Output 1

Sewer Pump Station– pump 1

Level 1 Failure (digital)

Output 1

Sewer Pump Station– pump 2

Level 1 Failure (digital)

Output 1

Sewer Pump Station Level 1 High level alarm (digital)

Output 1

Rainwater pressure pump – pump 1

Level 7 Failure (digital)

Output 1

Rainwater pressure pump – pump 2

Level 7 Failure (digital)

Output 1

Spare 5

Advanced Engineering Building Hydraulic Services

Appendix A

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

APPENDIX A – ARCHITECTURAL FIXTURE AND TAPWARE SCHEDULE

ret: F:\400 Documentation\430 Schedules\Fixtures And Equipment Schedule\101208_AEB_Fixtures And Equipment Schedules_Tender.Doc

400

FIXTURES + EQUIPMENT SCHEDULE – DETAILED DESIGN ISSUE

AEB UNIVERSITY OF QUEENSLAND

Status: Tender Date: 08/12/2010 Revision:

ret: F:\400 Documentation\430 Schedules\Fixtures And Equipment Schedule\101208_AEB_Fixtures And Equipment Schedules_Tender.Doc

SCHEDULE 1: FIXTURES + EQUIPMENT

Code G Code

Item Description and Finish Supplier Contact Details

Image

3in1_R G1 Paper Towel Dispenser / Hand Dryer / Bin, Recessed

RBA Recessed 3-in-1 (Paper Towel, Waste & Dryer), in Stainless Steel finish #B815969

RBA 1300 788 778

3in1_S G1 Paper Towel Dispenser / Hand Dryer / Bin, Surface Mounted

RBA Surface Mounted 3-in-1 (Paper Towel, Waste & Dryer), in Stainless Steel finish #B8159699

RBA 1300 788 778

AD G1 Height Adjustable System

Hafele Adjus Table System with Panel Attachement and wind up mechanism. Refer joinery drawings for height adjustment and furtherdetail.

Hafele Mark Iselin 0412953046 [email protected]

BC G1 Baby Change Table

JD Macdonald Surface Mounted Parallel Baby Change Station with Full Stainless Steel, 956 W x 103 D x 552mm H #BCP-SSC-SM

JD Macdonald 07 3363 6400

BIN_1 G3 Wheelie Bin Paper Recycling

120L Wheelie Bin. 440-480 W x 560 D x 930 H. Waste Contractor collects twice weekly.

By client

BIN_2 G3 Wheelie Bin Comingled Waste

120L Wheelie bin. 440-480 W x 560 D x 930 H. Co-mingled (Glass, Bottles, Cans) – cleaners empty daily into 240L bins.

By client

BIN_3 G3 Wheelie Bin Secure Paper Recycling

240L Wheelie Bin. CCCCCollected by contractors

By client

BIN_4 G3 Wheelie Bin General Waste

120L Wheelis Bin. 440-480 W x 560 D x 930 H. Cleaners empty daily into 240L bins.

By Client

BIN_5 G3 Wheelie Bin Cardboard Recycling

1100L bin. Kept in central location. By Client

ret: F:\400 Documentation\430 Schedules\Fixtures And Equipment Schedule\101208_AEB_Fixtures And Equipment Schedules_Tender.Doc

Code G Code

Item Description and Finish Supplier Contact Details

Image

BSN G1 Vanity Basin Caroma Cube Wall Basin with 0 tapholes #683505W with Caroma Modina Bottle Trap in chrome finish #687290C

Source 22 Jackie Hooper 07 3131 1154 [email protected]

BSN_PWD G1 PWD Vanity Basin

Caroma Cube Care Wall Basin with 1 taphole #683515W with Caroma Modina Bottle Trap in chrome finish #687290C Mounting height and bottle trap location to comply with AS1428.2.

Source 22 Jackie Hooper 07 3131 1154 [email protected]

BK G1 Sliding Baskets

Hafele Wire Basket pull-outs, internal mounting for open carcass. Provide runners, nuts and bolts as required. Basket types to suit 450mm carcass width, drawer runner 400mm L. Basket dimension 375mm W x 425mm D. 2 x baskets at 235mm H #541.74.722 and 1 x basket at 105mm H #541.74.702 White powdercoat finish. Refer Joinery JU56 for detail.

Hafele Mark Iselin 0412953046 [email protected]

CH1 G1 Auditorium Chair – Permanent

Civic WMR Convention Chair with integrated foldaway tablet. High back, tilt up seat with perforations to the underside of seat. Seat and back outer to be plywood with upholstered inner in Sustainable Living Chelsea 100% Ecowool fabric. Fabric colour to be confirmed, allow for 10 x colour types. Seat and back pads to be removable. Armrests have solid Blackbutt top with matching veneered sides. Tablet to be 10mm compact laminate. Floor fixing as per manufacturer’s recommendations. Refer Acoustic report for required acoustic performance of seating.

Civic Project Seating Bruce Rowland 5483 7011 [email protected]

CH2 G1 Auditorium Chair - Removable

Civic WMR REMOVABLE Convention Chair with integrated foldaway tablet. As per ‘CH1’ but with floor fixed mechanism for easy removal of complete seat.

Civic Project Seating Bruce Rowland 5483 7011 [email protected]

CT G1 Cutlery Tray Insert

Hafele white plastic cutlery tray sized to suit drawer internals

Hafele Mark Iselin 0412953046 [email protected]

ret: F:\400 Documentation\430 Schedules\Fixtures And Equipment Schedule\101208_AEB_Fixtures And Equipment Schedules_Tender.Doc

Code G Code

Item Description and Finish Supplier Contact Details

Image

CTR G1 Furniture Castors

Hafele heavy duty castor. Provide fixings as required. 75mm dia Wheel with brake and swivelling mounting plate, steel galvanised, 60 x 60mm. #663.16.920.

Hafele Mark Iselin 0412953046 [email protected]

CM G3 Coffee Machine

By Client

CPU G1 CPU Holder Humanscale CPU 600 white/polished aluminium

Schiavello Michelle Fuery 0417 756 331

DFP G1 Drinking Fountain_PWD

Refer Hydraulic Engineer’s specification

DFS G1 Drinking Fountain

Refer Hydraulic Engineer’s specification

DS1 G2 Display Screen

46” screen and bracket, portrait mounted. Outlets to be mounted directly behind screen. To be recessed in concrete walls.

Refer Paul Matthews (UQ)

DS2 G2 Display Screen

52” screen and bracket, landscape mounted. Outlets to be mounted directly behind screen.

Refer Paul Matthews (UQ)

DW G1 Dishwasher Fisher & Paykel One Touch 5 star WELS rating, in Brushed Stainless Steel finish #DW60DOX1 H 820 (min) 900 (max) x W 598 x D 570

Harvey Norman Commercial P_07 3297 3700

FT1 G1 Foldaway Tablet

Disabled Foldaway and adjustable writing tablet system. Armrest to be solid timber to match Blackbutt. Veneer sides to be AFS certified and plywood substrate to be E0. Tablet to be 10mm compact laminate. Tablet to be electronically height adjustable, integrate with electrical services. Floor fixing as per suppliers recommendations.

Civic Project Seating Bruce Rowland 5483 7011 [email protected]

FW1 G1 Floor Waste Rogerseller Grata Square floor waste 115x115mm #233542, with #233545 Puddle flange and adaptor kit when installed in shower areas. Installed as per Manufacturer’s instructions.

Rogerseller P_3251 4333

GR_WC G1 PWD Toilet Grab Rail Suite

Bobrick 40degree angled Grab Bar to suit exposed cistern toilet suite, satin stainless steel finish, 32mm dia, concealed fixings and clearances to comply with AS 1428.2. To be used in conjunction with 300mm Straight Grab Rail with clearances to suit AS 1428.2.

Barben Industries Cameron Kenny 0417753038 [email protected]

ret: F:\400 Documentation\430 Schedules\Fixtures And Equipment Schedule\101208_AEB_Fixtures And Equipment Schedules_Tender.Doc

Code G Code

Item Description and Finish Supplier Contact Details

Image

GR_AWC G1 Ambulant Disabled Toilet Grab Rail Suite

RBA 90degree angled Grab Bar for both left and right hand side of toilet cubicle, 450x450mm, satin stainless steel finish, 32mm dia, concealed fixings and clearances to comply with AS 1428.1. #RBA4090-400 and #RBA4090-410

GR_SHW G1 PWD Shower Grab Rail Suite

Bobrick Shower Grab Bar Straight 600mm, satin stainless steel finish, 32mm dia, 60mm clearance, concealed fixings #GS60 To be used in conjunction with Bobrick 90 degree grab bar 450x450mm To be used in conjunction with SHR_PWD shower rail with clearances to suit AS1428.2.

Barben Industries Cameron Kenny 0417753038 [email protected]

HD G1 PWD Sensor Air Hand Dryer

Bobrick Surface Mounted ADA Dryer with white painted cover #B-7120

Barben Industries Cameron Kenny 0417753038 [email protected]

HR G1 Hanging Rail - Lockers

20mm dia hanging rail, with end supports as required. Refer Joinery for rail length. Chrome finish.

Hafele or similar

LK2 G1 Joinery Lock Hafele SYMO 3000 sytem Hafele Mark Iselin 0412953046 [email protected]

LK3 G1 Locker Lock Hafele Safe-O-Tronic LS300 RFID/NFC cabinet lock with timer function options. Include individual number signage per locker, refer joinery drawing?

Hafele Mark Iselin 0412953046 [email protected]

MFD G3 Multi Function Device

By client

MW G1 Microwave Panasonic 32L Invertor Microwave NN-ST657S. 301Hx518Wx404mmD

Harvey Norman Commercial P_07 3297 3700

MXR_1 G1 Sink Mixer

Reece Ram Luka sink mixer, chrome finish. 5 star WELS rating

Reece Paul Rochford 0418326633 [email protected]

MXR_2 G1 Basin Mixer Reece Ram Luka wall basin set, chrome finish with 200mm reach. Note: Contractor to install cold tap and spout only, refer drawings. 6 star WELS rating

Reece Paul Rochford 0418326633 [email protected]

ret: F:\400 Documentation\430 Schedules\Fixtures And Equipment Schedule\101208_AEB_Fixtures And Equipment Schedules_Tender.Doc

Code G Code

Item Description and Finish Supplier Contact Details

Image

MXR_3 G1 Cleaner’s Sink Mixer

Reece Posh Solus sink mixer with extended lever handle 4 star WELS rating

Reece Paul Rochford 0418326633 [email protected]

MXR_4 G1 Shower Mixer

Reece Teknobili Live built in shower mixer #LV00108 CR

Reece Paul Rochford 0418326633 [email protected]

MXR_5 G1 SSW2 Basin Tapware.

Refer to Hydraulics Documentation to Hydraulic Engineer’s Documentation

MXR_6 G1 Lab Basin Tapware

Refer to Hydraulics Documentation to Hydraulic Engineer’s Documentation

MRX_7 G1 Lab Sink Tapware

Refer to Hydraulics Documentation to Hydraulic Engineer’s Documentation

MXR_PWD G1 PWD Basin Mixer

Hansa Medica Prado Neu Basin Mixer #0142 2246 0037 WELS 6 star rating (with 4.5lpm normal flow rate).

Source 22 Jackie Hooper 07 3131 1154 [email protected]

PT_1 G1 Paper Towel Dispenser

JD Macdonald Surface Mounted Paper Towel Dispenser 525 Multi-Fold Stainless Steel finish, 280W x 370H x 102mm D, #0210.

JD Macdonald 07 3363 6400

RACK G1 Mop and Broom Rack

Bradley Surface Mounted Mope and Broom Holder #9954 in Stainless Steel Finish. Overall 900L x102W x70D (248mm between each holder).

Bradley Australia 02 9774 3755

RF_1 G1 Refrigerator Fisher & Paykel Vertical Refrigerator E450R 451 litre in White finish. Overall 1695H x635W x694D (allow minimum air clearance). Handing as per Joinery drawings.

Harvey Norman Commercial P_07 3297 3700

ret: F:\400 Documentation\430 Schedules\Fixtures And Equipment Schedule\101208_AEB_Fixtures And Equipment Schedules_Tender.Doc

Code G Code

Item Description and Finish Supplier Contact Details

Image

RF_3 G1 Underbench Refrigerator – 1 Door

Fisher & Paykel Bar Refrigerator P120RW 115L litre in White finish. Overall 819H x 525W x 570D (allow minimum air clearance). Handing as per Joinery drawings.

Harvey Norman Commercial P_07 3297 3700

SD_1 G1 Soap Dispenser - Amenities

Airtowel Industrial Soap Dispenser, in Stainless Steel finish 225 H x 60 W x 95mm D, 450ml capacity #SDAI-LD1

Airtowel Hygiene Systems 07 3355 9400

SD_2 G1 Soap Dispenser – Kitchen

Airtowel Industrial Soap Dispenser in Stainless Steel finsh, 70mm spout #SDAI-BS20-316

Airtowel Hygiene Systems 07 3355 9400

SD_3 G1 PWD Soap Dispenser - Labs

JD Macdonald Surface Mounted Disposable Cartridge Soap Dispenser, Satin Stainless Steel finish, 110 W x 280 H x 100mm D #5001-SS

JD Macdonald 07 3363 6400

SD_PWD G1 PWD Soap Dispenser

JD Macdonald Surface Mounted Disposable Cartridge Soap Dispenser, Satin Stainless Steel finish, 110 W x 280 H x 100mm D #5001-SS

JD Macdonald 07 3363 6400

SH_1 G1 Shelf Barben Axis Shelf, in Satin Stainless Steel #A-9994

Barben Industries Cameron Kenny 0417753038 [email protected]

SHC G1 Shower Curtain/Rail/Hooks

Barben Heavy Duty Shower Curtain Rod, concealed fixed. 25mm dia stainless steel, sized to suit PWD shower. #B-207 With Barben Stainless Steel Shower Curtain Hooks, quantity to suit PWD Shower. #204-1 With custom made Shower Curtain, contractor to allow for manufacture. Fabric to be Kvadrat Zeze 196

Barben Industries Cameron Kenny 0417753038 [email protected] Kvadrat Renee Henderson 0409222819

ret: F:\400 Documentation\430 Schedules\Fixtures And Equipment Schedule\101208_AEB_Fixtures And Equipment Schedules_Tender.Doc

Code G Code

Item Description and Finish Supplier Contact Details

Image

[email protected]

SH_PWD G1 PWD Shelf Barben Axis Shelf custom size 120x400mm, in Satin Stainless Steel #A-9994

Barben Industries Cameron Kenny 0417753038 [email protected]

SHR_1 G1 Shower Rose

Gessi 200mm R ound Goose Neck Shower Head 3 Star WELS rating #ROGS1

Abey 07 3805 7000

SHR_PWD G1 Shower Rail_PWD

ABEY ABS2 Hamme Hand Shower Set Single Flow. Hammer Hand Shower Set Single Flow 3.star flor rate. 7.5L/min

Abey 07 3805 7000

SNK_1 G1 Integrated Single Square Bowl Sink

400mm x 400mm x 150mm deep custom stainless steel sink, with integrated waste. To be integrated into stainless steel benchtop. Refer to Joinery Specification for details on gague etc.

By Joiner

SNK_2 G1 Cleaner’s Sink

Caroma Cleaner’s Sink #811592W with CP Grate, Fixing Brackets and Waste Outlet

Source 22 Jackie Hooper 07 3131 1154 [email protected]

SNK_3 G1 Single Square Bowl Sink_Sick Room

Reece Kado Arc vanity basin with 1 x taphole, overmount to benchtop.

Reece Paul Rochford 0418326633 [email protected]

SNK_4 G1 Lab Sink_hand basin

Refer Hydraulics specification

SNK_5 G1 Lab Sink_large

Refer Hydraulics specification

SSH_PWD G1 PWD Soap Shelf

Barben Axis Soap Dish, in Satin Stainless Steel, 150 L x 110 D x 20mm thick #A-107

Barben Industries Cameron Kenny 0417753038 [email protected]

ret: F:\400 Documentation\430 Schedules\Fixtures And Equipment Schedule\101208_AEB_Fixtures And Equipment Schedules_Tender.Doc

Code G Code

Item Description and Finish Supplier Contact Details

Image

ST_PWD G1 PWD Shower Seat

Bobrick #B-5181 Reversible Folding Shower Seat 840x565mm, maximum 163kg limit, mounted 430-485mm from top of seat to floor. With collapsible legs to support seat when folded down.

Barben Industries Cameron Kenny 0417753038 [email protected]

TR G1 Tea Towel Rail

Hafele Towel Rail 1 arm, extendable, silver anodised finish #510.54.912

Hafele Mark Iselin 0412953046 [email protected]

TRD G1 Toilet Roll Dispenser

Airtowel Jumbo Toilet Roll Holder, Aluminium 269 W x 316 H x 128 D #TRHJM-455000

Airtowel Hygiene Systems 07 3355 9400

UR G1 Urinal Caroma Cube 0.8L Electronic Urinal Suite WELS 6 star rating #678660W

Source 22 Jackie Hooper 07 3131 1154 [email protected]

VG G1 Ventilation Grille

Hafele Ventilation Grille, aluminium angled louvre grille 56mm high x 480mm wide. #575.08.924 Contractor to powdercoat black.

Hafele Mark Iselin 0412953046 [email protected]

WC G1 Toilet Suite Caroma Metro wall faced toilet suite Back entry, 4 Star WELS Rated #904639

Source 22 Jackie Hooper 07 3131 1154 [email protected]

WC_P G1 Toilet / Shower Partitions

TPI Custom ceiling suspended 13mm compact laminate partition system with exposed structural works to be concealed behind a brushed stainless steel surround. Suspended system to be utilised for cubicle runs up to 4 cubicles, for cubicle runs above 4 cubicles provide TP1 Eco Float system. Including TP1 Series 600 hardware. TPI to supply and install all partitions and hardware.

TPI Michael Sloan Ph 02 9709 5601

ret: F:\400 Documentation\430 Schedules\Fixtures And Equipment Schedule\101208_AEB_Fixtures And Equipment Schedules_Tender.Doc

Code G Code

Item Description and Finish Supplier Contact Details

Image

WC_PWD G1 PWD Toilet Suite

Caroma Care 800 Wall Faced Toilet Suite, with Colani double flap seat 4 Star WELS Rated #900800W

Source 22 Jackie Hooper 07 3131 1154 [email protected]

WU G1 Billi Tap + Underbench Unit

Refer to Hydraulics Documentation Refer to Hydraulic Engineer’s Documentation

Advanced Engineering Building Hydraulic Services

Appendix B

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

APPENDIX B – CONCRETE CURING BATHS DRAWING

Advanced Engineering Building Hydraulic Services

Appendix C

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

APPENDIX C – DETAILS OF ACOUSTIC TREATMENT OF WALL PENETRATIONS

(refer Acoustic Report for full extent and requirements of acoustic treatment for hydraulic services)

Advanced Engineering Building Hydraulic Services

Appendix C

Tender Form - Page 1

BN

E0911900.0

.8 K

S 1

00809 H

ydra

ulic

Specifi

catio

n -

Const

ructio

n M

arc

h 2

011 W

SP L

incoln

e S

cott ©

2011

R

evi

sion 1

/ Iss

ue

Const

ructio

n

APPENDIX D – ARCHITECTURAL FINISHES SCHEDULE – REFER DOWNPIPES SECTION

(Not available at time of issue. Please obtain copy directly from Architect / Contractor)