08-Series 8000 Structures

Embed Size (px)

Citation preview

  • 8/2/2019 08-Series 8000 Structures

    1/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Content

    Ethiopian Roads Authority Page 8000-1

    SERIES 8000: STRUCTURES

    CONTENT

    LIST OF TABLES AND FIGURES ................................................................................................ 11

    DIVISION 8100: FOUNDATIONS FOR STRUCTURES.................................................................12

    8101 Scope ..............................................................................................................................12

    8102 Materials .........................................................................................................................12

    (a) General ..................................................................................................................12

    (b) Rock (for rock fill).................................................................................................12

    (c) Crushed stone ........................................................................................................13

    (d) Granular fill ...........................................................................................................13(e) Sand fill .................................................................................................................13

    (f) Structural steel .......................................................................................................13

    (g) Permanent Pile Casings .........................................................................................13

    (h) Driven Pile Casings ...............................................................................................13

    (i) Sheet Piles .............................................................................................................13

    (j) Grouting.................................................................................................................14

    8103 General............................................................................................................................14

    (a) Subsurface Data.....................................................................................................14

    (b) Channel preservation .............................................................................................14

    8104 Cofferdams, Artificial Islands And Dewatering.............................................................14

    (a) General ..................................................................................................................14

    (b) Access....................................................................................................................15

    (c) Dewatering ............................................................................................................15

    8105 Excavation ......................................................................................................................15

    (a) General ..................................................................................................................15

    (b) Ground surface for excavation ..............................................................................16

    (c) Excavation .............................................................................................................16

    (d) Classification of excavated material......................................................................16

    (e) Blasting..................................................................................................................17

    (f) Deterioration of foundation excavations ...............................................................17

    (g) Excavation safety...................................................................................................17(h) Inspection ..............................................................................................................17

    (i) Excavation by hand ...............................................................................................17

    8106 Foundation......................................................................................................................17

    8107 Utilization Of Excavated Material..................................................................................18

    8108 Backfill And Fill Near Structures...................................................................................18

    (a) General ..................................................................................................................18

    (b) Backfill ..................................................................................................................19

    (c) Fill..........................................................................................................................19

    (d) Select Granular Backfill ........................................................................................19

    (e) Fill within restricted areas .....................................................................................20

    8109 Foundation Fill ...............................................................................................................208110 Grouting Of Rock Fissures .............................................................................................21

    8111 Foundation Dowels.........................................................................................................21

  • 8/2/2019 08-Series 8000 Structures

    2/172

    Series 8000: Structures Standard Technical Specification -2002

    Content

    Page8000-2 Ethiopian Roads Authority

    8112 Foundation Lining.......................................................................................................... 21

    8113 Foundation Piling........................................................................................................... 21

    (a) General.................................................................................................................. 21

    (b) Piling Layout......................................................................................................... 21

    (c) Alternative Designs for Piling and Piling Layouts ............................................... 22

    (d) Details to be furnished by the Contractor ............................................................. 24(e) Pile-installation Frames and Equipment ............................................................... 24

    (f) Piling Platforms..................................................................................................... 24

    (g) Setting Out ............................................................................................................ 24

    (h) Ground Surface of Foundation Piling ................................................................... 25

    (i) Cast in situ concrete piles...................................................................................... 25

    (j) Precast Concrete Piles........................................................................................... 26

    (k) Steel Piles.............................................................................................................. 27

    (l) Driving Piles ........................................................................................................ 27

    (m) Augering and Boring............................................................................................. 29

    (n) Rock Sockets......................................................................................................... 30

    (o) Obstructions .......................................................................................................... 30(p) Determining Pile Lengths ..................................................................................... 31

    (q) Piling Data............................................................................................................. 31

    (r) Stripping the Pile Heads........................................................................................ 32

    (s) Construction of Pile-capping Slab ........................................................................ 32

    (t) Core Drilling ......................................................................................................... 32

    (u) Load Test............................................................................................................... 33

    (v) Defective Piles ...................................................................................................... 34

    (w) Standing Time in Respect of Piles-installation Frames ........................................ 34

    8114 Caissons ......................................................................................................................... 34

    (a) General.................................................................................................................. 34

    (b) Construction and sinking ...................................................................................... 34(c) Founding ............................................................................................................... 35

    (d) Data ....................................................................................................................... 36

    (e) Filling the caissons................................................................................................ 36

    (f) Stripping................................................................................................................ 37

    (g) Concrete screed below the caisson cover slabs..................................................... 37

    8115 Measurement And Payment........................................................................................... 37

    Item 81.01 Additional foundation investigations Provisional Sum .............................. 37

    Item 81.02 Excavation of materials............................................................................... 37

    Item 81.03 Access lump sum ........................................................................................ 38

    Item 81.04 Drainage Lump Sum ................................................................................... 38

    Item 81.05 Backfill to excavations utilizing ................................................................. 38

    Item 81.06 Fill within restricted areas........................................................................... 39

    Item 81.07 Overhaul in excess of 1.0 km, on excavated Material and on material

    imported for backfill, foundation fill and fill for caissons.................................... 39

    Item 81.08 Over break in excavation in hard material .................................................. 39

    Item 81.09 Foundation fill............................................................................................. 39

    Item 81.10 Establishment on site for the grouting of rock fissures............................... 40

    Item 81.11 Move to and set up equipment at each hole to be drilled............................ 40

    Item 81.12 Drilling of holes .......................................................................................... 40

    Item 81.13 Grouting of holes ........................................................................................ 40

    Item 81.14 Doweling into rock...................................................................................... 40Item 81.15 Foundation lining ........................................................................................ 40

    Item 81.16 Establishment on the site for piling............................................................. 41

  • 8/2/2019 08-Series 8000 Structures

    3/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Content

    Ethiopian Roads Authority Page 8000-3

    Item 81.17 Moving to, and setting up the equipment at each position for installing the

    piles........................................................................................................................41

    Item 81.18 Augered or bored holes for piles .................................................................41

    Item 81.19 Driving the temporary casing for driven displacement piling systems for

    forming holes for piles...........................................................................................42

    Item 81.20 Manufacturing, supplying and delivering prefabricated piles .....................42Item 81.21 Installation of prefabricated piles ................................................................42

    Item 81.22 Extra over item 81.18, irrespective of the depth, to form augered and bored

    pile holes through identified obstructions .............................................................43

    Item 81.23 Forming augered and bored pile holes through unidentified obstructions ..43

    Item 81.24 Driving temporary casings for driven displacement piling systems or

    installing prefabricated piles through identified or unidentified obstructions.......43

    Item 81.25 Extra over items 81.18, 81.19 and 81.21 for raking piles............................43

    Item 81.26 Forming under reams for piles.....................................................................43Item 81.27 Forming the bulbous bases for piles............................................................44

    Item 81.28 Socketing piles into rock formation ............................................................44

    Item 81.29 Installing and removing temporary casings in augered holes for piles .......44Item 81.30 Installing permanent pile casing for piles...................................................44

    Item 81.31 Steel reinforcement in cast in situ piles:......................................................44

    Item 81.32 Cast in situ concrete in piles, under reams, bulbous bases and sockets ......44

    Item 81.33 Extra over item 81.32 for concrete cast under water...................................45

    Item 81.34 Splicing/coupling prefabricated piles for lengthening.................................45

    Item 81.35 Stripping/cutting the pile heads ..................................................................45

    Item 81.36 Establishment on the site of the load testing of piles ..................................45

    Item 81.37 Load tests on piles .......................................................................................45

    Item 81.38 Establishment on the site for core drilling...................................................45

    Item 81.39 Moving the equipment to and assembling it at each location where cores are

    to be drilled............................................................................................................45Item 81.40 Drilling the cores .........................................................................................46

    Item 81.41 Standing time for pile-installation frame.....................................................46

    Item 81.42 Establishment on the site for constructing the caisson................................46

    Item 81.43 Formwork for caissons ................................................................................46

    Item 81.44 Steel reinforcement for caissons..................................................................46

    Item 81.45 Cast in situ concrete in caissons and concrete seals ....................................47Item 81.46 Cutting edge for caissons.............................................................................47

    Item 81.47 Sinking caissons through material situated .................................................47

    Item 81.48 Excavation for caissons ...............................................................................47

    Item 81.49 Filling the caissons ......................................................................................48

    Item 81.50 Stripping the caisson heads. ........................................................................48

    Item 81.51 Nuclear integrity testing on bored piles:......................................................48

    DIVISION 8200 FALSEWORK, FORMWORK, AND CONCRETE FINISHES.................................49

    8201 Scope ..............................................................................................................................49

    8202 Dimensions .....................................................................................................................49

    8203 Material Requirements For Falsework And Formwork .................................................49

    (a) Falsework ..............................................................................................................49

    (b) Formwork ..............................................................................................................49

    8204 Design And Construction Requirements ........................................................................51

    (a) Drawings................................................................................................................51

    (b) Design....................................................................................................................52

    (c) Construction ..........................................................................................................53

  • 8/2/2019 08-Series 8000 Structures

    4/172

    Series 8000: Structures Standard Technical Specification -2002

    Content

    Page8000-4 Ethiopian Roads Authority

    (d) Removal of forms and falsework .......................................................................... 57

    8205 Formed Surfaces: Classes Of Finish .............................................................................. 59

    (a) General.................................................................................................................. 59

    (b) Class F1 surface finish .......................................................................................... 59

    (c) Class F2 surface finish .......................................................................................... 59

    (d) Class F3 surface finish .......................................................................................... 59(e) Board surface finish .............................................................................................. 59

    (f) Protecting the surfaces .......................................................................................... 59

    8206 Remedial Treatment Of Formed Surfaces ..................................................................... 60

    (a) General.................................................................................................................. 60

    (b) Repairs to surface defects ..................................................................................... 60

    (c) Rubbing the surfaces............................................................................................. 60

    8207 Unformed Surfaces: Classes Of Finish .......................................................................... 61

    (a) Class U1 surface finish (rough) ............................................................................ 61

    (b) Class U2 surface finish (floated)........................................................................... 61

    (c) Class U3 surface finish (smoothly finished)......................................................... 61

    8208 Measurement And Payment........................................................................................... 61Item 82.01 Formwork for indicated class of finish ....................................................... 61Item 82.02 Vertical formwork for indicated class of finish .......................................... 61

    Item 82.03 Horizontal formwork for indicated class of finish ...................................... 61

    Item 82.04 Inclined formwork for indicated class of finish .......................................... 62

    Item 82.05 Permanent formwork................................................................................... 62

    Item 82.06 Formwork to form open joints .................................................................... 62

    Item 82.07 Establishment on the site for sliding formwork operations ........................ 62

    Item 82.08 Transporting to and setting up the sliding formwork assembly.................. 63

    Item 82.09 Forming the concrete by sliding formwork for structures .......................... 63

    DIVISION 8300: STEEL REINFORCEMENT FOR STRUCTURES ............................................... 64

    8301 Scope.............................................................................................................................. 64

    8302 Materials Requirement................................................................................................... 64

    (a) Steel reinforcement ............................................................................................... 64

    (b) Mechanical couplers ............................................................................................. 64(c) Storage of Materials .............................................................................................. 64

    8303 Construction Requirements............................................................................................ 64

    (a) Equipment ............................................................................................................. 64

    (b) Bending of Reinforcement .................................................................................... 65

    (c) Surface Conditions................................................................................................ 65

    (d) Placing and Fixing ................................................................................................ 65(e) Cover..................................................................................................................... 66

    (f) Laps and Joints...................................................................................................... 67

    (g) Welding................................................................................................................. 67

    8304 Measurement And Payment........................................................................................... 68

    Item 83.01 Steel reinforcement for structure................................................................. 68

    Item 83.02 Mechanical couplers for.............................................................................. 68Item 83.03 Spacer "ladders".......................................................................................... 68

    DIVISION 8400: CONCRETE FOR STRUCTURES ..................................................................... 69

    8401 Scope.............................................................................................................................. 698402 Materials......................................................................................................................... 69

    (a) Cement .................................................................................................................. 69

  • 8/2/2019 08-Series 8000 Structures

    5/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Content

    Ethiopian Roads Authority Page 8000-5

    (b) Admixtures ............................................................................................................69

    (c) Aggregates.............................................................................................................69

    (d) Water .....................................................................................................................71

    8403 Storage Of Materials.......................................................................................................72

    (a) Cement...................................................................................................................72

    (b) Aggregates.............................................................................................................72(c) Storage Capacity....................................................................................................72

    (d) Deteriorated Material.............................................................................................72

    8404 Concrete For Structures ..................................................................................................73

    (a) Concrete Grade and Class .....................................................................................73

    (b) Minimum Cement Content ....................................................................................73

    (c) Maximum Water/Cement Ratio ............................................................................73

    (d) Maximum Cement Content ...................................................................................73

    (e) Design of Concrete Mixes for Structures ..............................................................73

    (f) Prescribed mix .......................................................................................................74

    8405 Construction Requirements ............................................................................................75

    (a) Storage and Handling of Material .........................................................................75(b) Measuring Material. ..............................................................................................76

    (c) Batching Plant, Mixers, and Agitators...................................................................76

    (d) Mixing ...................................................................................................................77

    (e) Delivery .................................................................................................................77

    (f) Batching and Mixing .............................................................................................78

    (g) Trial Mixes ............................................................................................................80

    (h) Consistency and Workability.................................................................................80

    (i) Temperature and Weather Conditions...................................................................80

    8406 Handling, Placing And Compaction Of Concrete ..........................................................82

    (a) General ..................................................................................................................82

    (b) Placing ...................................................................................................................838407 Construction Joints .........................................................................................................87

    (a) General ..................................................................................................................87

    (b) Preparation of Surfaces..........................................................................................87

    (c) Placing Fresh Concrete at Construction Joints ......................................................87

    (d) Bonding .................................................................................................................88

    (e) Bonding and Doweling to Existing Structures ......................................................88

    8408 Expansion And Contraction Joints .................................................................................89

    (a) Open joints.............................................................................................................89

    (b) Filled joints ............................................................................................................89

    (c) Steel joints .............................................................................................................89

    (d) Water stops ............................................................................................................89(e) Compression joint seals.........................................................................................89

    (f) Elastomeric expansion joint seal ...........................................................................90

    8409 Finishing Plastic Concrete..............................................................................................90

    (a) General ..................................................................................................................90

    (b) Striking of Formwork ............................................................................................90

    8410 Curing Concrete..............................................................................................................90

    (a) General ..................................................................................................................90

    (b) Forms inplace method ...........................................................................................91

    (c) Water method ........................................................................................................91

    (d) Liquid membrane curing compound method.........................................................91(e) Steam curing (precast units) ..................................................................................92

    8411 Pipes And Conduits ........................................................................................................92

  • 8/2/2019 08-Series 8000 Structures

    6/172

  • 8/2/2019 08-Series 8000 Structures

    7/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Content

    Ethiopian Roads Authority Page 8000-7

    (f) Positioning of Tendons and Duct Formers for Pre-stressing Tendons................105

    (g) Tendon spacers ....................................................................................................105

    (h) Grout....................................................................................................................105

    (i) Protecting agents for unbonded tendons..............................................................106

    (j) Testing .................................................................................................................106

    8603 Construction Requirements ..........................................................................................106(a) Equipment............................................................................................................106

    (b) Technical Data.....................................................................................................108

    (c) Prestressing System .............................................................................................109

    (d) Drawings Prepared By the Contractor.................................................................109

    (e) Precasting ............................................................................................................110

    (f) Pre-Tensioning ....................................................................................................111

    (g) Post-Tensioning...................................................................................................111

    8604 Loss Of Prestress ..........................................................................................................118

    8605 Measurement And Payment..........................................................................................118

    Item 86.01 Prestressing tendons ..................................................................................118

    Item 86.02 Anchorages and couplers...........................................................................118Item 86.03 Extra over pay item 86.02 for partially tensioning the tendons ................119

    DIVISION 8700 BRIDGE BEARINGS ...................................................................................120

    8701 Scope ............................................................................................................................120

    8702 Bridge Bearings ............................................................................................................120

    (a) Material................................................................................................................120

    (b) Concrete Hinges ..................................................................................................121

    (c) Roofing Felt.........................................................................................................122

    (d) Elastomeric Bearings...........................................................................................122

    (e) Proprietary Bearings............................................................................................123(f) Dowels and Guides..............................................................................................126

    (g) Storage and Handling ..........................................................................................126

    (h) Installation ...........................................................................................................1268703 Bridge Parapets, Railings And Sidewalks ....................................................................127

    (a) Materials ..............................................................................................................127

    (b) Concrete Parapets ................................................................................................127

    (c) Metal Railings .....................................................................................................128

    (d) Bridge Number Plates..........................................................................................128

    (e) Concrete Sidewalks .............................................................................................128

    (f) Concrete Surface Finish Requirements ...............................................................129

    (g) Construction Tolerances......................................................................................1298704 Joints In Structures .......................................................................................................129

    (a) General ................................................................................................................129

    (b) Movement joints ..................................................................................................129

    (c) Materials ..............................................................................................................130

    (d) Filled and unfilled joints......................................................................................132

    (e) Epoxy Mortar Nosings ........................................................................................132

    (f) Concrete Nosings.................................................................................................132

    (g) Plug type expansion joint systems.......................................................................133

    (h) Sealing Of Joints..................................................................................................133

    (i) Proprietary Expansion Joints ...............................................................................135

    (j) Installation Of Expansion Joints..........................................................................135

    8705 No-Fines Concrete........................................................................................................136

    (a) Materials ..............................................................................................................136

  • 8/2/2019 08-Series 8000 Structures

    8/172

    Series 8000: Structures Standard Technical Specification -2002

    Content

    Page8000-8 Ethiopian Roads Authority

    (b) Grades on No-Fines Concrete ............................................................................. 136

    (c) Batching and Mixing........................................................................................... 136

    (d) Placing................................................................................................................. 137

    (e) Protection ............................................................................................................ 137

    8706 Drainage for Structures ................................................................................................ 137

    (a) Weep holes, drainage pipes and channelling ...................................................... 137(b) No-fines concrete blocks..................................................................................... 137

    (c) Synthetic-fibre filter fabric.................................................................................. 137

    (d) Crushed stone in drainage strips behind walls .................................................... 138

    8707 Measurement And Payment......................................................................................... 138

    Item 87.01 Proprietary bearings .................................................................................. 138

    Item 87.02 Installing the proprietary bearings ........................................................... 138

    Item 87.03 Bearings .................................................................................................... 138

    Item 87.04 Concrete hinges ......................................................................................... 138

    Item 87.05 Bearing strips ............................................................................................ 139

    Item 87.06 Dowels/guides........................................................................................... 139

    Item 87.07 Concrete parapets ...................................................................................... 139Item 87.08 Steel railings.............................................................................................. 139

    Item 87.09 End blocks................................................................................................. 139

    Item 87.10 Numbers for structures.............................................................................. 139

    Item 87.11 Proprietary expansion joints...................................................................... 140

    Item 87.12 Installation of proprietary expansion joints .............................................. 140

    Item 87.13 Expansion joints........................................................................................ 140

    Item 87.14 Filled joints: .............................................................................................. 140

    Item 87.15 Unfilled joints ........................................................................................... 141

    Item 87.16 Sealing joints............................................................................................. 141

    Item 87.17 Cast in situ no- fines concrete................................................................... 141

    Item 87.18 Precast no-fines concrete units.................................................................. 141Item 87.19 Drainage pipes and weep holes................................................................. 141

    Item 87. 20 Drainage gulleys ...................................................................................... 142

    Item 87. 21 Synthetic-fiber filter fabric....................................................................... 142

    Item 87. 22 Concrete channeling................................................................................. 142

    Item 87. 23 Crushed stone in drainage strips .............................................................. 142

    Item 87. 24 Nose endings at balustrades ..................................................................... 142

    Item 87.25 Concrete transition blocks......................................................................... 142

    DIVISION 8800:STRUCTURAL STEELWORK ......................................................................... 144

    8801 scope............................................................................................................................. 1448802 Materials....................................................................................................................... 144

    (a) Structural steel..................................................................................................... 144

    (b) Bolts, nuts and washers....................................................................................... 144

    (c) Friction-grip fasteners ......................................................................................... 144

    (d) Welding consumables ......................................................................................... 144

    (e) Test certificates ................................................................................................... 144

    8803 Codes Of Practice......................................................................................................... 145

    8804 Shop Details ................................................................................................................. 145

    8805 Fabrication And Assembly........................................................................................... 145

    (a) General................................................................................................................ 145

    (b) Marking the steel................................................................................................. 145

    (c) Cutting................................................................................................................. 145

    (d) Holes for fasteners .............................................................................................. 145

  • 8/2/2019 08-Series 8000 Structures

    9/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Content

    Ethiopian Roads Authority Page 8000-9

    (e) Joints in compression ..........................................................................................145

    (f) Hollow sections ...................................................................................................145

    (g) Alignment of holes ..............................................................................................146

    (h) Welding ...............................................................................................................146

    (i) Bolting .................................................................................................................146

    (j) Welded Stud Shear Connectors ...........................................................................146(k) Friction-grip fastening .........................................................................................146

    (l) Riveting ...............................................................................................................147

    (m) Trimming .............................................................................................................147

    (n) Corrosion prevention ...........................................................................................147

    8806 Erection.........................................................................................................................147

    (a) General ................................................................................................................147

    (b) Safety during erection..........................................................................................148

    (c) Alignment ............................................................................................................148

    (d) Corrections ..........................................................................................................148

    (e) Grouting...............................................................................................................148

    8807 Testing ..........................................................................................................................149(a) Testing by the engineer .......................................................................................149

    (b) Process control.....................................................................................................149

    8808 Measurement And Payment..........................................................................................149

    Item 88.01 Structural steel ...........................................................................................149

    Item 88.02 Anchor bolts ..............................................................................................150

    Item 88.03 Corrosion protection ..................................................................................150

    DIVISION 8900: STONE MASONRY STRUCTURES .................................................................151

    8901 scope .............................................................................................................................151

    8902 Stone Masonry Walls ...................................................................................................1518903 Classes Of Masonry......................................................................................................151

    8904 Material Requirements For Stone Masonry Structures ................................................152

    (a) Stone ....................................................................................................................152

    (b) Quarry Operations ...............................................................................................154

    (c) Mortar ..................................................................................................................1548905 Construction Requirements ..........................................................................................154

    (a) Excavation and backfill .......................................................................................154

    (b) Falsework ............................................................................................................155

    (c) Selection and Placing ..........................................................................................155

    (d) Beds and Joints ....................................................................................................156

    (e) Headers ................................................................................................................157(f) Backing................................................................................................................157

    (g) Coping .................................................................................................................157

    (h) Parapet walls........................................................................................................157

    (i) Facing for Concrete .............................................................................................157

    (j) Pointing................................................................................................................158

    (k) Weep Holes .........................................................................................................159

    (l) Cleaning Exposed Faces......................................................................................159

    (m) Weather Limitations ............................................................................................159

    8906 Measurement And Payment..........................................................................................159

    Item 89.01 Stone masonry walls..................................................................................159

  • 8/2/2019 08-Series 8000 Structures

    10/172

    Series 8000: Structures Standard Technical Specification -2002

    Content

    Page8000-10 Ethiopian Roads Authority

    DIVISION T8000: CONSTRUCTION TOLERANCES FOR STRUCTURES.................................. 161

    T8001 Scope...................................................................................................................... 161

    T8002 Definitions.............................................................................................................. 161

    T8003 Tolerances .............................................................................................................. 161

    (a) Foundations......................................................................................................... 162

    (b) Footings, pile capping slabs, caisson cover slabs, etc......................................... 163(c) Columns, walls, pier, abutments, etc .................................................................. 163

    (d) Bridge And Culvert Superstructure..................................................................... 164

    (e) Precast Beams ..................................................................................................... 164

    (f) Precast Beams And Panels.................................................................................. 165

    (g) Precast Prestressed Concrete Structural Elements .............................................. 166

    (h) Reinforcing Steel................................................................................................. 167

    (i) Prestressing ......................................................................................................... 168

    (j) Bridge Bearings................................................................................................... 168

    (k) Fabrication And Assembly Tolerances For Structural Steel............................... 169

    (l) Concrete Pavement Slab ..................................................................................... 169

    (m) Miscellaneous...................................................................................................... 172

  • 8/2/2019 08-Series 8000 Structures

    11/172

    Standard Technical Specification - 2002 Series 8000: Structures

    List of Tables and Figures

    Ethiopian Roads Authority Page 8000-11

    LIST OF TABLES AND FIGURES

    Table 8102-1: Rock Classification ..........................................................................................12

    Table 8108-1 Select Granular Backfill Gradation...................................................................20

    Table 8204-1 Minimum Form/Support Release Criteria.........................................................58

    Table 8303-1 Minimum concrete cover over reinforcement...................................................67

    Table 8304-1 Mass of Reinforcing Bars .................................................................................68

    Table 8402-1 Maximum amount of deleterious substances ....................................................70

    Table 8402-2 Grading of Fine Aggregate................................................................................71

    Table 8402-3 Nominal Size and Grading of Coarse Aggregate..............................................71

    Table 8404-1 Grade of Concrete for Structures ......................................................................73

    Table 8404-2 Nominal Mixes..................................................................................................75Table 8406-1 Hand Held Vibratory Requirements..................................................................87

    Table 8409-1 Minimum Period Before Striking Formwork for Concrete for Structures........90

    Table 8700-2 Types of movement joints...............................................................................129

    Table 8700-1 Grades of No-Fines concrete...........................................................................136

  • 8/2/2019 08-Series 8000 Structures

    12/172

    Series 8000: Structures Standard Technical Specification -2002

    Division 8100: Foundations For Structures

    Page8000-12 Ethiopian Roads Authority

    DIVISION 8100: FOUNDATIONS FOR STRUCTURES

    8101 SCOPE

    This Division provides specifications for the construction of foundations for structuresincluding bridges, retaining walls, box and slab culverts etc. It provides in particular

    specifications for excavation, and back filling and for the construction of the foundation it self

    as well as the pile capping slabs or the caisson cover slabs.

    8102 MATERIALS

    (a) General

    Materials used in the permanent foundation work shall comply with the requirements

    specified for the particular material in series 8000 of the Specifications.

    (b) Rock (for rock fill)

    Stones shall be hard, angular, field or quarry stones of such quality that they will not

    disintegrate on exposure to water or weathering.

    The stones shall be free from overburden, shale, and organic material.

    Neither the breadth nor thickness of a single stone shall be less than one-third its length.

    Not more than 10% of the total volume of rock fill shall consist of stones having a mass of

    less than 0.5 of the mass specified and not more than 10% of the total volume of rock fill shall

    consist of stones having a mass more than 5 times the mass specified. Not less than 50% ofthe total volume of rock fill shall consist of stones larger than the specified mass.

    Table 8102-1: Rock Classification

    Class Description Description of HardnessField Indicator Tests

    Unconfined

    Compressive

    Strength

    (MPa)

    R1 Very soft

    rock

    Material crumbles under firm (moderate) blows with a

    sharp end of geological pick and can be peeled offwith a knife; it is too hard to cut a tri-axial sample by

    hand

    0.7 to 3.0

    R2 Soft rock Can just be scraped and peeled with a knife;

    indentations 1 mm to 3 mm show in specimens with

    firm (moderate) blows of the pick point

    3.0 to 10.0

    R3 Hard rock Cannot be scraped or peeled with a knife; handheld

    specimen can be broken with hammer end of a

    geological pick with a single firm (moderate) blow

    10.0 to

    20.0

    R4 Very hard

    rock

    Hand-held specimen Breaks with hammer end of pick

    under more than one below

    20.0 to

    70.0

    R5 Extremely

    hard rock

    Specimen requires many blows with geological pick

    to break through intact material

    More than

    70.0

  • 8/2/2019 08-Series 8000 Structures

    13/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Division 8100: Foundations For Structures

    Ethiopian Roads Authority Page 8000-13

    (c) Crushed stone

    Crushed stone used for the construction of crushed stone fill shall be from sound unweathered

    rock approved by the Engineer.

    (d) Granular fillGranular fill used for the construction of compacted granular fill shall be approved granular

    material of at least gravel sub-base quality.

    Granular back fill required for compacting against earth-retaining structures shall consist of

    well-graded crushed or uncrushed gravel, stone, rock fill, or natural sand or a combination of

    any of these. It shall not contain a soluble sulphate content exceeding 2.5 g per liter as

    determined in accordance with the requirements of AASHTO.

    Not less than 95 per cent of the material shall pass a 125mm BS sieve and at least 90 per cent

    shall pass the 75mm BS sieve but not more than 10 per cent shall pass the 75-micron BS

    sieve.

    (e) Sand fill

    Sand used for filling of caissons shall be clean, hard and free from lumps of clay, organic or

    other deleterious matter.

    (f) Structural steel

    Steel in steel piles shall comply with the requirements of BS 4360 and/or AASHTO M 183 for

    the grade of steel specified on the Drawings.

    I and H sections shall comply with the requirements of BS 4: Part 1.

    Fabricated sections shall comply with the details shown on the Drawings.

    (g) Permanent Pile Casings

    Permanent piles casings shall be sufficiently rigid so as not to deform permanently or damage

    during handing and construction.

    The casings shall be sufficiently dense to prevent the fluid components of the concrete from

    leaking during the placing of the concrete or thereafter.

    Where steel casings contribute to the strength of the pile, the casings shall have a minimum

    wall thickness of 4.5 mm and shall comply with the requirements of ASTM A 252-68. Weldedjoints shall comply with the requirements of Division 8800 of these specifications.

    (h) Driven Pile Casings

    Driven pile casings shall have sufficient strength to permit their being driven and not being

    distorted by the driving of adjacent piles, and they shall be sufficiently watertight to prevent

    water leaking through the casing walls during the placing of concrete.

    (i) Sheet Piles

    For steel sheet piles, conform to AASHTO M 202M or M 223M.

    For all other sheet piles, conform to the requirements prescribed above for the particular

    material specified. Make the joints practically watertight when the piles are in place.

  • 8/2/2019 08-Series 8000 Structures

    14/172

    Series 8000: Structures Standard Technical Specification -2002

    Division 8100: Foundations For Structures

    Page8000-14 Ethiopian Roads Authority

    (j) Grouting

    (i) Cement grout

    Cement grout shall meet the appropriate requirements of sub-clause 8602(h) of these

    specifications.

    (ii) Proprietary-brand grout

    Proprietary brand grout shall be prepared and used strictly in accordance with the instructions

    of the manufacturer.

    8103 GENERAL

    (a) Subsurface Data

    If it is found during the course of excavation that the load bearing strata differs from that

    shown on the Drawings, the Contractor shall immediately notify the Engineer.

    The Engineer shall be entitled, as often as he may deem necessary during the course of

    excavation, to call upon the Contractor to perform additional foundation investigation and/or

    tests at or below the respective foundation levels to establish safe bearing pressures and

    foundation depths.

    (b) Channel preservation

    Stream flow and preservation of marine and freshwater life shall be maintained at all times.

    Access to cofferdams, artificial islands and piling platforms shall be accomplished without

    disrupting the stream flow at the point of crossing unless otherwise specified in the SpecialProvisions.

    On completion of the work surplus excavated materials, including materials excavated from

    caisson compartments and piles, materials used in cofferdams and other temporary works, as

    well as in-situ material, shall be removed and disposed of by the Contractor to the original bed

    level or such lower elevation as agreed to by the Engineer or required for stream

    channelization works.

    8104 COFFERDAMS, ARTIFICIAL ISLANDS AND DEWATERING

    (a) General

    This clause covers the provision of access, including the construction of cofferdams, and

    draining the excavations.

    Where it is unnecessary to provide access in terms of sub-clause 8104(b), the contractor shall

    be paid separately for draining the excavations.

    After Completion of the permanent works, all temporary works shall be completely removed,

    the ground leveled and the site left neat. Where this is impracticable, such portions as have

    not been removed, shall be dealt with in accordance with the engineers instructions.

  • 8/2/2019 08-Series 8000 Structures

    15/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Division 8100: Foundations For Structures

    Ethiopian Roads Authority Page 8000-15

    (b) Access

    Where temporary banks or artificial islands are constructed in view of affording access to the

    location where structural members, piles or caissons are to be constructed, the banks or

    islands shall be adequately compacted in view of supporting any plant and material without

    any undue settling, which may have a harmful effect on the end product.

    The contractor may use any material deemed by him to be suitable for constructing the

    islands, but he shall note that no separate payment will be made in terms of items 81.02(b),

    81.22, 81.24 and 81.48(b) for any obstructions or hard materials occurring in the material

    used for constructing temporary banks or artificial islands.

    Designing and constructing any cofferdams shall comply with the requirements of BS 8004.

    Before starting with construction, the contractor shall submit drawings to the engineer, which

    show details of the cofferdams and the method of construction.

    (c) Dewatering

    The Contractor shall be responsible for preventing the ingress of water into excavations.

    The preventative measures shall include the construction of proper drainage channels,

    diversion channels, sumps, the supply and operation of the necessary bailing and pumping

    equipment and the construction of suitable watertight cofferdams.

    The dewatering measures, with the exception of pumping, shall be maintained until the

    backfilling has been completed.

    Between the various construction stages pumping may be interrupted as agreed by the

    Engineer. Any draining or pumping of water from cofferdams or the interior of any foundation

    enclosure shall be done in such a manner as to preclude the possibility of any portion of the

    concrete materials being carried away.

    8105 EXCAVATION

    (a) General

    This work shall include excavations, not provided for elsewhere in these Specifications,

    required for the foundation of structures as well as for the excavating required for existing

    bridges and culverts where these have to be demolished, extended or modified.

    Excavation required for diverting, channeling or widening streams within 5.0 m of concrete

    structures shall be measured and paid for under item 81.02. Excavations beyond the 5.0 mlimit shall be measured and paid for under the appropriate items of series 3000 and 4000 of

    these specifications.

    The Engineer may require additional excavation, to that described in the Contract, to remove

    any pockets of soft soil or loose rock and the resulting voids and any natural voids shall be

    filled with Grade 20/20 concrete complying with the requirements of clause 8404 of these

    specifications or other material as instructed by the Engineer.

    No trimming of the sides of the excavation shall be carried out within 24 hours of the placing

    of any blinding concrete.

    Any additional excavation below the bottom of foundations, including that resulting from

    removal of material which the Contractor has allowed to deteriorate shall be replaced with

    Grade 20/20 concrete complying with the requirements of Division 8400 A of these

    specifications or other material as instructed by the Engineer.

  • 8/2/2019 08-Series 8000 Structures

    16/172

    Series 8000: Structures Standard Technical Specification -2002

    Division 8100: Foundations For Structures

    Page8000-16 Ethiopian Roads Authority

    The sides of the excavation for foundations for structures shall either be vertically or sloped at

    a safe angle for the material to be excavated. Except in rock, vertical sides shall be adequately

    supported at all times to the satisfaction of the Engineer.

    All practical measures shall be taken to prevent the ingress of surface water into the excavated

    foundations. Any water collecting in the excavated foundation shall be removed as soon as

    possible thereafter.

    (b) Ground surface for excavation

    Prior to commencement of any excavation, the Contractor shall notify the Engineer in good

    time to ensure that measurements, cross sections and levels of the undisturbed ground can be

    taken in order that an average ground surface from which the excavation is to be measured

    can be established and agreed upon between the Engineer and the Contractor.

    (c) Excavation

    Where, in the opinion of the Engineer, the casting of concrete against the excavated earthfaces is not permissible, or where formwork has to be provided, the extremities of the

    excavation, for purposes of measurement and payment, shall be deemed to be the vertical

    planes parallel to and 0.6 m outside the perimeter of the member for which formwork is to be

    provided.

    Where suitable stable material is encountered during excavation, that part of the trench or

    foundation pit shall be excavated to the neat dimensions of the base unless directed otherwise

    by the Engineer.

    Over excavation (over break) in hard material shall be backfield with the same class of

    concrete as that in the base or with mass concrete fill as specified or as directed by the

    Engineer.

    Where blasting is required, the contractor shall complete the entire foundation excavation

    before he commences with the construction of any permanent concrete work, unless otherwise

    approved by the Engineer.

    Boulders, logs, or any other unsuitable material excavated shall be spoiled.

    When hard material suitable for foundation is encountered at the foundation level, it shall be

    cut and trimmed to a firm surface, either level, stepped or serrated, as required.

    Where the material at the foundation level is soft material or hard material that deteriorates

    rapidly on exposure, excavation to final grade and elevation shall not be made until just

    before the blinding layer is placed.

    Where, in the opinion of the Engineer, unsuitable material is encountered at foundation level,

    such material shall be removed and replaced with foundation fill in accordance with Clause

    8109 and as directed by the Engineer.

    (d) Classification of excavated material

    Distinction shall be made for payment purposes between excavation in hard and soft material.

    All excavation for the foundations of structures shall be classified in accordance with the

    following classifications:

  • 8/2/2019 08-Series 8000 Structures

    17/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Division 8100: Foundations For Structures

    Ethiopian Roads Authority Page 8000-17

    (i) Hard material

    Material, which cannot be excavated except by drilling and blasting, or the use of pneumatic

    tools or mechanical breakers shall be classified as hard material.

    (ii) Soft material

    All material not classified as hard material shall be classified as soft material.

    (e) Blasting

    Where blasting is permitted it shall be carried out in accordance with the requirements of the

    Contract.

    (f) Deterioration of foundation excavations

    Where the bottoms or sides of excavations, in which bases are to be cast, are softened due to

    negligence on the part of the Contractor in allowing storm or other water to enter the

    excavations, the softened material shall be removed and replaced with foundation fill asdirected by the Engineer at the Contractor's expense.

    (g) Excavation safety

    The Contractor shall take the necessary precautions to safeguard the stability and safety of the

    excavations and adjacent structures.

    The personal safety of any person shall not be placed in jeopardy nor shall any situation be

    allowed to arise which may result in damage of whatsoever nature.

    (h) Inspection

    No concrete shall be placed before the excavation has been properly cleaned and inspected

    and approved by the Engineer.

    (i) Excavation by hand

    Where circumstances prevent the use of mechanical excavators and material can be removed

    only by hand implements, the Engineer shall authorise the supplementary payment to the

    contractor for such work at the tendered rates for excavation by hand should he be satisfied

    that the contractor had been unable to prevent the necessity for excavation by hand by proper

    planning and precautionary measures.

    The supplementary rate for excavation by hand shall not apply to minor finishing or clearing

    jobs in excavations which are otherwise being done by mass excavation plant.

    8106 FOUNDATION

    In consequence of possible variations of anticipated foundation conditions the dimensions and

    foundation levels specified or shown on the Drawings may have to be varied during

    construction.

    The Engineer has the full and absolute power in terms of this contract to order such variations

    and to specify the actual foundation level for each foundation fill, base, or caisson duringconstruction and his decision shall be final and binding on the Contractor.

  • 8/2/2019 08-Series 8000 Structures

    18/172

    Series 8000: Structures Standard Technical Specification -2002

    Division 8100: Foundations For Structures

    Page8000-18 Ethiopian Roads Authority

    The Contractor shall not be entitled to any additional payment in consequence of any such

    variation in the dimensions or foundation depths over and above that provided for in Clause

    8115 regardless of the stage of construction at which the instruction to vary the dimensions or

    foundation depths is given. However, if in consequence of such variation order the Contractor

    is compelled to substitute machines and equipment with other machines and equipment in

    order to successfully complete the work, the Engineer may, at his discretion, reimburse theContractor for additional expenses incurred provided that the original machines and

    equipment were suited to the work required prior to the variation order being issued.

    No base, caisson, or pile shall be founded unless authorized by the Engineer. Each foundation

    level shall be accurately measured and recorded.

    The term foundation level used in these Specifications shall be deemed to have the

    following meanings in respect of:

    (i) Foundation fill : The surface of the in-situ material that has been prepared to receive

    foundation fills.

    (ii) Bases : The underside of the base.(iii) Piles : The underside of the under ream, bulbous base or rock socket; the tip of the pile

    shoe or lower pile end, as may be relevant.

    8107 UTILIZATION OF EXCAVATED MATERIAL

    Excavated material and material recovered from temporary work shall, so far as it is suitable,

    be utilized for backfill.

    Material unsuitable for use as backfill or in excess of the quantity required to complete the

    backfill shall be spoiled or utilized as directed by the Engineer.

    Excavated material not used for backfill or not taken to spoil but used in the construction of

    embankments or other parts of the work, as directed by the Engineer, will be paid for under

    foundation excavation as well as under the relevant item for the purpose for which it is used.

    The free-haul distance on excavated material and imported material for backfill shall be 1.0

    km.

    Excavated and stockpiled material shall be deposited so as not to endanger the uncompleted

    structure, either by direct pressure or indirectly by overloading the banks contiguous to the

    structure or in any other way.

    8108 BACKFILL AND FILL NEAR STRUCTURES

    (a) General

    In placing backfill and fill, the following precautions shall be taken:

    The material shall be placed simultaneously, in so far as is possible, to approximately the

    same elevation on both sides of an abutment, pier, or wall where appropriate.

    If conditions require placing backfill or fill appreciably higher on one side than on the

    opposite, the additional material on the higher side shall not be placed until authorized by the

    Engineer and preferably not until the concrete has been in place 14 days, or until tests show

    that the concrete has attained sufficient strength to safely withstand any pressure created bythe backfill or fill, or the method of construction.

  • 8/2/2019 08-Series 8000 Structures

    19/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Division 8100: Foundations For Structures

    Ethiopian Roads Authority Page 8000-19

    The material behind abutments restrained at the top by the superstructure. e.g., portal type

    structures, shall be placed as stated on the Drawings or as directed by the Engineer.

    The material behind the walls of concrete culverts shall not be placed until the top slab is

    placed and cured, unless authorized otherwise by the Engineer.

    (b) Backfill

    Excavated areas around structures shall be backfilled with approved material in horizontal

    layers, not exceeding 150 mm in depth after compaction, to the level of the original ground

    surfaces.

    Each layer shall be moistened or dried to optimum moisture content for the material and

    compacted to a density of not less than 93% of Modified AASHTO density.

    (c) Fill

    To prevent wedge action against the structure and bounding slopes, the slopes shall be

    benched or serrated.

    In no case shall the toe of the bounding fill be closer to the concrete face than the height of the

    exposed face of the abutment or wall.

    (d) Select Granular Backfill

    Select granular backfill shall be sound, durable, granular material free from organic matter or

    other deleterious material (such as shale or other soft particles with poor durability).

    Select granular backfill shall conform to the following:

    (i) Quality Requirements

    (1) Gradation according to; Table 8108-1

    (2) Shear angle of internal friction, AASHTO T 236 34o

    min.

    Note:

    Samples shall be compacted as per AASHTO T 236 to 95 percent of the maximum density

    determined according to AASHTO T99 method C or D and corrected for oversized

    material according to AASHTO T 99, Note 7.

    (3) Sodium sulfate soundness loss (5 cycles);15% max. according toAASHTO T 104.

    (4) Los Angeles abrasion, according to AASHTO T96; 50% max.(5) Liquid limit, according to AASHTO T89; 30 max.

    (ii) Electrochemical requirements

    (1) Resistively, AASHTO T 226 3000 cm min.(2) pH, AASHTO T 289; 5.0 to 10.0

    (3) Sulfate content, AASHTO T 290 1000 ppm max.

    (4) Chloride content, AASHTO T 291 200 ppm max.

    Note: Tests for sulfate and chloride content are not required when pH is between 6.0 and 8.0

    and the receptivity is greater than 5000 ohm centimeters.

  • 8/2/2019 08-Series 8000 Structures

    20/172

    Series 8000: Structures Standard Technical Specification -2002

    Division 8100: Foundations For Structures

    Page8000-20 Ethiopian Roads Authority

    Table 8108-1 Select Granular Backfill Gradation

    Sieve Size Percent by Mass Passing Designated Sieve

    (AASHTO T27 and T11)

    100 mm 100

    75 mm 75 10075 m 0 15

    (e) Fill within restricted areas

    The portion of the fill within 3 meters of the concrete faces of the structure and the whole of

    the spill through portion, or the extent shown on the Drawings, shall be termed "fill within

    restricted area".

    Fill within the restricted area shall comply with the requirements of Series 4000 except that it

    shall be compacted to a density of not less than 93% of Modified AASHTO density. In order

    to achieve the specified density, the Contractor shall, where necessary, import material of

    suitable quality.

    Payment in accordance with Pay item 81.06 for the construction of fill within restricted areas

    shall only be made when specifically provided for in the Bill of Quantities.

    8109 FOUNDATION FILL

    If it is found during the course of excavation that the material at the indicated foundation

    depth does not have the required bearing capacity as specified on the Drawings, the

    excavations shall be extended at the discretion of the Engineer until satisfactory foundation

    material is encountered.

    The Engineer reserves the right to order the Contractor to make up the difference in levels

    with foundation fill.

    Where the foundation fill consists of rock or crushed stone fill, it shall be constructed in

    accordance with the requirements of the Special Provisions or as directed by the Engineer.

    Foundation fill consisting of granular material shall be constructed in layers not exceeding

    150 mm in thickness after compaction. Each layer shall be moistened or dried to optimum

    moisture content for the material and compacted to a density of not less than 95% of Modified

    AASHTO density.

    Mass concrete fill to be used shall be of the class or mix as specified or directed by theEngineer.

    Unless specified or directed otherwise by the Engineer, the minimum foundation fill

    consisting of rock fill, crushed stone fill or compacted granular fill to be constructed shall be

    defined by a prism with plan area coinciding with the lower base of a truncated pyramid the

    sides of which slope at an angle of 60o

    with the horizontal from the underside of the footing or

    slab to the foundation level.

    A concrete blinding of 75mm thickness and Grade 15/20 concrete shall be placed underneath

    all bases except where mass concrete fill is used or where authorized by the Engineer.

    Where mass concrete is constructed under a base it shall be constructed accurately to the finallevels of the underside of the base.

  • 8/2/2019 08-Series 8000 Structures

    21/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Division 8100: Foundations For Structures

    Ethiopian Roads Authority Page 8000-21

    8110 GROUTING OF ROCK FISSURES

    Where specified, fissures in the rock below and around the base shall be sealed by pressure

    grouting with a neat cement or sand-cement grout with a water cement ratio as agreed to by

    the Engineer. The extent of fissuring shall be established by water testing under pressure.

    Holes of at least 40 mm diameter shall be drilled in positions ordered by the Engineer andgrout pumped into these holes under suitable pressures.

    Grouting shall be carried out in 3-meter stages to the maximum depth ordered. Care shall be

    taken to avoid further fracturing of the rock strata due to excessive grouting pressures.

    Grouting of rock fissures shall be carried out by specialized operators with adequate

    experience in this class of work.

    8111 FOUNDATION DOWELS

    Where required, foundation dowels of the specified material, diameter and length shall be

    installed at the positions and to the dimensions shown on the Drawings or as directed by theEngineer.

    After exposure, clearing and trimming of the rock formation, holes of not less than 40 mm

    diameter and of specified depth shall be drilled into the rock into which the dowels shall be

    fox-wedged and grouted with a 2:1 sand: cement grout.

    8112 FOUNDATION LINING

    Where specified or directed by the Engineer, foundation lining shall be installed as described

    hereinafter.

    The Engineer shall have the right to order the use of lining against sides of excavations andunderside of bases and slabs in lieu of formwork and concrete building.

    All surfaces to be lined shall be covered with approved sheeting to provide a clean impervious

    layer. The material shall be of sufficient strength to provide a durable working surface and to

    support the concrete and reinforcement without tearing.

    The joints between strips shall have a 150 mm overlap and the lining shall be held firmly in

    position by nails, pegs, etc.

    Polyethylene sheeting of 0.15 mm thickness is generally considered adequate for the use

    under approach (jockey) slabs and bases.

    8113 FOUNDATION PILING

    (a) General

    This section covers the construction of bearing piles of concrete or steel or a combination of

    these materials.

    (b) Piling Layout

    The piling layout, the minimum pile size and/or bearing capacity and type together with the

    steel reinforcement and class of concrete required shall be as detailed and specified on thedrawing unless otherwise specified in the project specifications.

  • 8/2/2019 08-Series 8000 Structures

    22/172

    Series 8000: Structures Standard Technical Specification -2002

    Division 8100: Foundations For Structures

    Page8000-22 Ethiopian Roads Authority

    (c) Alternative Designs for Piling and Piling Layouts

    (i) Submission

    The priced schedule of quantities submitted for alterative designs shall be complied strictly in

    accordance with the relevant measurement and payment clauses of these specifications.

    Where pay items defined in these specifications have been omitted, it shall mean either that

    the items do not apply, or that where the engineer requires work falling under such items to be

    done, it shall be done without any cost to the employer. The inclusion of "rate-only" items will

    not be permitted.

    Where pay items not defined in these specifications are used, the measurement and payment

    requirements for such items shall be specified in detail by the contractor. In the absence of

    such definitions, or in the case of any ambiguity, the interpretation of the engineer shall be

    final and binding.

    Except in piling-only contracts or where otherwise provided in the Project specifications, the

    contractor shall price the schedule of quantities for the original design irrespective of whetheror not an alterative design is offered.

    (ii) Design

    The critical design-load combinations acting upon the underside and the center of gravity of

    the pile-capping slab, the maximum permissible stet of the pile-capping slab, and the technical

    data required for designing alternative piles and/or piling layouts will be indicated on the

    drawings.

    Alternative designs shall comply with the provisions of the Contract and the prescriptions set

    out below.

    For alternative designs submitted the contractor shall submit with his tender a detaileddescription of the method of analysis used in the design of the piles and the pile-group

    layouts.

    The average length of pile and/or of the piles per group on which the quantities in the

    schedule of quantities for the alternative designs are based shall be stated in each case. The

    type of pile offered shall be defined in terms of size, materials, working and breaking load.

    The Contractor shall be responsible for and shall bear the cost for redesigning, drafting and

    submitting the detail drawings for any structural element affected by the alternative pile

    design. Any economy or incidental caused by constructing such element as compared to the

    original design shall be for the account of the contractor.

    The contractor shall, as specified in the Contract, submit to the Engineer at least three months

    prior to work being commenced, drawings detailing the piling-group layout and piles,

    incorporating such amendments to his original design as may be required by the engineer, and

    drawings detailing the amendments required to the pile-capping slab dimensions and

    reinforcement as a result of the layout of the piles, all as applicable.

    No work of whatsoever nature shall be commenced on the piling until the drawings have been

    submitted to and have been approved by the engineer, in writing.

    After approval of the drawings, no departure there from shall be made with out authorization

    by the Engineer.

    Where the alternative piles fail in regard to the load test specified in sub-clause 8113(u) ofthese specifications, the contractor shall be responsible for the cost of the work required for

    improving the piles and pile layout so as to comply with the design requirements.

  • 8/2/2019 08-Series 8000 Structures

    23/172

    Standard Technical Specification - 2002 Series 8000: Structures

    Division 8100: Foundations For Structures

    Ethiopian Roads Authority Page 8000-23

    (iii) Basis of payment

    Where the quantities in the schedule of quantities referred to in sub-clause 8113(c)(i), on the

    one part, differ from the number of piles and the average pile length given in the submission

    for the alternative pile design, on the other part, the Engineer shall accept the sum in the said

    schedule of quantities, correct the quantities, and adjust the rates for the applicable pay items

    accordingly.

    In addition to these corrections, the employer shall be justified in using one of the following

    methods for paying for piles constructed in accordance with the alternative design:

    Method 1

    The employer may check the alternative designs, calculate the quantities and adjust the rates

    as set out in the first paragraph of sub-clause 8113(c)(iii). The employer will then pay for the

    work in accordance with the actually measured quantities.

    Method 2

    The employer may use the following formulae for calculating the quantities under pay items81.17 to 81.35 for payment:

    Np=Nd

    Lp = Nd .Ld + Nb(Lb-Ld)K for Nd > Nb

    and

    Lp = Nd . Ld + Nd(Lb-Ld)K for Nd < Nb

    Ld

    LbK = for Ld > Lb and K =

    Lb

    Ldfor Ld Lb

    Where: P = paid, d = designed and, b = built.

    The term "units" means items of work measured and paid for in the respective pay items such

    as piles, raking piles, casings, underreams, concrete, etc.

    Np = number of "units" measured and finally paid for in a particular pile group.

    Nd =number of "units" provided for in the tender for the alternative design in the same pile

    group.

    Nb = number of approved and accepted "units' finally installed in the same pile group.Lp = the length of the "units" measured and paid for or the length to be used in calculating

    quantities which are a direct function of the length of the "units" for the same pile group.

    Ld = the averag