07_Dynamic_Plant_Simulation_T.pdf

Embed Size (px)

Citation preview

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    1/29

    1 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Dynamic Plant Simulation

    Tehran, September 26th 2005

    Dieter Krenz

    Linde Engineering

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    2/29

    2 D. Krenz / HDB / z3641.ppt

    Linde EngineeringThe plant control system, plant tuning,operator training and the plant operatingpoint influences the overall plant result

    HYCO plants have different topology

    Several feeds, fuel gases, parallel trains etc. A control system shouldmeet the special plant topology

    The operator knowledge is the key for a smooth plant operation

    Training of the operator is a precondition for a good plant operation

    A plant consists of many valves and controller

    Tuning of these control loops have a great impact on the dynamicplant behavior

    The plant operating point is responsible for the plant profit

    Changing feed situations can lead to different best plant operatingpoints

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    3/29

    3 D. Krenz / HDB / z3641.ppt

    Linde EngineeringLinde applies simulation for training,control system design, tuning andoptimization

    Simulation models are used for

    Training

    Control system design

    Tuning of PID controller and plant units

    Automatic plant start up

    Best plant operation

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    4/29

    4 D. Krenz / HDB / z3641.ppt

    Linde EngineeringDynamic simulation reducescommissioning time andminimizes trail and error

    Advantages

    tests and demonstration of plant behavior already before plantstart-up

    time consuming tests with the real plant can be done much

    faster with a dynamic simulation model

    reduced test activities with the real plant during commissioning

    Overall Benefit

    reduced commissioning time less trail and error

    Best operation point

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    5/29

    5 D. Krenz / HDB / z3641.ppt

    Linde EngineeringLinde uses commercially availablesimulation as well ascustomized simulations in Excel

    The purpose of the simulation defines the simulation tool

    Excel for simulations of HYCO plants (reformer, shift reaction,simplified cold box, etc.)

    Commercially available simulation packages such as HYSYSare used for studies

    Lindes simulation tool OPTISIM when the accuracy of

    property data is significant (Cold Box)

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    6/29

    6 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Linde set up the simulation in orderto give the customer a easy to use tool

    The simulation set up with EXCEL is flexible and user friendly

    The simulation model is tailored to the actual plant and includesonly the major mass and energy balance. No special knowledge

    necessary to use the simulation model

    Easy to use simulation model with a comprehensive user interfacewhich can be modified in the look and feel

    Both dynamic and steady state models are available

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    7/29

    7 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Simulation set up in HYSYS

    5m3

    6m3

    6m3

    60m3

    5m3

    5m3

    320m3

    5m3

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    8/29

    8 D. Krenz / HDB / z3641.ppt

    Linde EngineeringA dynamic simulation showsthe expected plant behaviorbefore commissioning

    Feed

    H2/CO

    in OXO

    OXO

    H2

    to Shift

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    9/29

    9 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Simulation set up in EXCEL (partly)

    13797.2kg/h 38.0bar

    13788 kg/h 1.0bar

    4415.6kg/h

    50.0% 4413 kg/h 1.30bar

    76.3%

    3.56mol% ch4

    6803.4kg/h 15.8% 29.55mol% H2O

    6800 kg/h 1.36mol% 1.30bar 44.16mol% h2

    2.75mol% 1025.9cel 14.67mol% CO

    7.92mol% CO2

    0.15mol% N2 875 cel

    40.0bar 67.2% 28.6bar 26.6bar 874.0cel

    600 cel

    0.94828 ch4 397 cel 100.0% 9.03MW

    0 H2O 29 bar co2 ref 1.0bar 250 cel

    0.0291 h2 7959 kg/h

    0 CO

    0.000485 CO2 2.0kg/h

    0 C2H4 7959 kg/h 70000.0kg/h

    0.009457 C2H6 70000 kg/h

    0.0006 C3H6 51.8% 60.7% 81.3% 0.0% 0.0% 0.0%

    0.003301 C3H8

    0 C4H8

    0.000641 i-C4H100.000621 n-C4H10 0.0% 1452.3kg/h 757.3kg/h 1090.6kg/h 0.0kg/h 0.0kg/h 0.0kg/h

    0.000214 C5H12 1463 kg/h 758 kg/h 1072 kg/h 0 kg/h 0 kg/h 0 kg/h

    0.0000388 C6H14

    0.007864 N2 0.0kg/h

    -21 kg/h

    40.0bar

    v

    Feed

    1

    v

    v

    reformer

    steam

    co2imp

    v ng v pg v tg v h2 v co v co2

    v

    air

    co2rec

    mp

    tc

    v pcbox

    prereformer

    v st. pref

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    10/29

    10 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Well trained operator makeless errors in plant operation

    Class room training is organized in the steps

    Definition of the training goals

    Explanation and demonstration of the process basics

    Group work with the aid of a training simulator

    discussion

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    11/29

    11 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Example of Linde class room trainingwith dynamic simulation

    1const30000.0kg/h flow in

    periode100.0sec 30000.0kg/h

    amplitude FIN2500.0kg/h 50.0% SP3

    29500.79950.0%

    2 KP PV3 FOUT2

    360 TI 30000.2kg/h0 TD

    44.7% OP3

    0

    10

    20

    30

    40

    50

    60

    0 100 200 300 400

    time

    PV3,SP3andOP3

    PV3

    OP3

    SP3

    drum MAN

    AUTO

    LC1

    v

    LC1

    const

    sinus

    flow in

    27000

    27500

    28000

    28500

    29000

    29500

    30000

    30500

    31000

    0 100 200 300 400

    time

    FIN2andFOUT2

    FIN2

    FOUT2

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    12/29

    12 D. Krenz / HDB / z3641.ppt

    Linde EngineeringOur HYCO plant control systemsare successfully used indifferent plant topologies

    The frequent operation of a plant load change is done totally automaticby Lindes control system

    The control system calculates all setpoints (flows, O2, steam,

    feed etc.) based on simplified or rigorus models

    The operator has only to enter the target values for the products

    If one plant unit trips the rest of the plant remains running

    Changes of heating values are compensated for in a special heatvalue loop

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    13/29

    13 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    RemoteSP =

    33000 kg/h

    RemoteSP =

    132000 kg/h

    TC

    Reformer

    FC

    FC

    PC

    FCFC

    NG = 1500 kg/hFeed =

    15000 kg/h

    RemoteSP =

    45000 kg/h

    RemoteSP =

    15000 kg/h

    SP

    Load

    Steam

    Feed

    Min

    Steam

    FC

    Air = 132000 kg/h

    RemoteSP =

    1500 kg/h

    air /

    purge

    air /

    gas

    Reformer Load And Fuel Gas Control Training

    820.5 celInternalSP =

    45000 kg/h

    InternalSP =

    15000 kg/h

    Internal SP =1500 kg/h

    Internal SP =33000 kg/h

    Internal SP =132000 kg/h

    START

    Simulation

    STOP

    Simulation

    AUTO

    AUTO

    AUTO AUTOAUTO

    MAN

    AI O2 = 2.4 %

    Excess

    Air

    Min

    Air

    Purge = 33000 kg/h

    Steam =

    45000 kg/h

    InternalSP =

    45000 kg/h

    InternalSP =

    15000 kg/h

    InternalSP =1500 kg/h

    InternalSP =33000 kg/h

    InternalSP =132000 kg/h

    InternalSP =820.5 cel

    Load

    controldetails

    Air/temp

    control

    details 14 3 1.10000 75000

    80 3 25000

    Feedforward

    8

    +

    TC-Out =

    0 kg/h

    Init OFFHOLD

    Simulation

    help on

    Example of a reformer control systemfor demonstration of principle controlsystem features

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    14/29

    14 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Control and simulationof a standard H2 plant

    Reformer CO shift PSAH2 ProductFeed

    Plant topology:

    Control system:Based on the target value for the H2 product the setpoints for steam,

    feed, temperatures, O2 etc are calculated via feedforward andfeedback

    Simulation:

    Based on a simplified energy and mass balance there are steady stateand dynamic simulation available

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    15/29

    15 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Control and simulation of a HYCO Plant

    Reformer MDEA Adsorber Cold Box

    PSA

    CO Product

    H2 Product

    Feed

    Plant topology:

    Control system:

    Based on the target values for the products H2 and COthe setpoints for steam, feed, temperatures, O2 aswell as the flows and temperature setpoints in thecold box are calculated via feedforward andfeedback

    Simulation:Based on a simplified energy and mass balancethere are steady state and dynamic simulationavailable

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    16/29

    16 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Plant topology:

    Control system:

    Based on the target values for the products H2and OXO the setpoints for steam, feed,temperatures, O2 MDEA cycle flows,membrane pressure etc are calculated via

    feedforward and feedback

    Simulation:

    Load changes have been simulated in HYSYS

    POX CO-Shift MDEA Membrane

    PSA Compressor

    cooling

    OXO Product

    H2 Product

    Feed

    Control and simulation of aHYCO Plant with POX and membrane

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    17/29

    17 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Plant topology:

    Control system:

    Based on the target values for the products H2 and CO the load is automaticallydistributed to CO shift and cold box. The setpoints for steam, feed,temperatures and O2 as well as the flow and temperature setpoints in the

    cold box are calculated via feedforward and feedback.

    Simulation:

    Steady state simulation

    Reformer CO-Shift PSA

    MDEA

    CO Product

    H2 ProductFeed

    Cold Box

    Control and simulation of aHYCO Plant with POX and membrane

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    18/29

    18 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    ProductsPlant

    FI

    Controller

    for correction

    +Calculation

    of

    Setpoints

    for the

    Plant

    Setpoint

    Products

    MeasurementSetpoint

    Feedforward

    Independent Plant

    inputs such as

    Reformer Load

    CO2 Recycle etc

    Calculation of independent plant inputs such as reformer load etc. basedon operator setpoint for the products

    adjustment of all significant controller as a function of plant load byfeedforward

    deviations between setpoints for products and actual measured productsare compensated by a controller

    A General load control conceptis applied to all plant topologies

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    19/29

    19 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    setpoint

    syngas temperature

    Controller settings are responsiblefor the plant dynamic

    step response isunstable

    step response isexcellent

    step response is tooslow

    Reformer

    TC

    Fuel gas

    control

    TimeTime Time

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    20/29

    20 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    setpoint

    syngastemperature

    A dynamic simulation of thecontrol loop leads to anexcellent behavior in a short time

    step response isexcellent

    Reformer

    TC

    Fuel gascontrolTime

    dynamic simulation based onmeasurements

    Leads to the best overallresponse with minimum workin the real plant and minimum

    trail and error

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    21/29

    21 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Model Identification by setting V, TS, TOT and/or KI

    Model EquationY_MOD = V*(1 - exp(-(t-TOT)/TS)) + KI*(t-TOT)

    V TS TZ KI Delta_U Abtastzeit

    20 1250 240 0 1000 50

    0

    5

    10

    15

    20

    -10 -1 450 950 1450 1950 2450

    0

    200

    400

    600

    800

    1000

    1200

    Y_MES

    Y_MOD

    Delta_U

    Go To Control Hilfe Einblenden

    A two step procedure with Lindestuning programm leads to bestcontroller settings in minimum time

    PID-CONTROLLER TUNING

    Setpoint DisIn DisOut

    10 PID-Controller Periodend.1000 Plant Periodend.100

    KP = 1 Amplitude200.0 Vertrkung 20 Amplitude0.0

    TN = 800 Anstiegszeit 1250

    SP TD = 0 PlantIN= Totzeit 240 PlantOut

    PID_OUT+DisIN Integrations. 0

    PID_OUT HIGH / LOW PV HIGH LOW SCALING PV=PlantOut+DisOUT

    MH=50000.0 -ML=50000.0 PVH=1000.0 PVL=0.0

    Sim.-zeit

    3600.0 sec

    Abtastzei t

    1.0 sec

    Zufallssignal

    -ZinMin=0.1

    ZinMax=0.1

    Kin=0.0

    ZouMin=0.0

    ZouMax=0.0

    Kou=0.0

    0

    2

    4

    6

    8

    10

    12

    14

    0 494.2 988.5 1482.7 1976.9 2471.2 2965.4 3459.6

    -500

    0

    500

    1000

    1500

    PlantOut

    SP

    DisOut

    PlantIn

    DisIn

    Input PlantInput Plant Model

    Hilfe Einblenden

    Model identification based onplant measuremnts

    Dynamic simulation of theclosed loop

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    22/29

    22 D. Krenz / HDB / z3641.ppt

    Linde EngineeringDynamic Simulation is usedfor tuning of complex systemssuch as a steam system

    PC-hh

    SGTCOND

    SGTEXTR:

    cond

    HP Header

    MP Header

    LP Header

    HP-steamreformer.

    HP-steamsyngas cooler.

    MP-steam

    co shift.

    FC

    Dilution steamreformer PC

    PC-h

    Auxilaryboiler

    SGC

    loadcontrol

    FC

    LP export

    PC-h

    TG

    COND

    TG

    EXTR:

    cond

    PC

    G

    Power

    PC-hh

    PC-hh PC

    FI

    FI

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    23/29

    23 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Simulation set up of asteam system simulation

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    24/29

    24 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    An automatic plant start up / shut-down with the aid of a sequence.

    A sequence itself will perform valve and/or controller open/close/rampingin the same way as described in the operating manual and

    is organized in steps such as purging, heating, feed in etc.

    Before the next step will be executed the previous one must be finishedsuccessfully. This is checked by comparing actual with expected operatingconditions.

    In case of an error (failed check) the sequence will hold. The operator will fixthe problem and resume the sequence.

    The operator can hold and resume the sequence at any time.

    Automatic Plant Start Up

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    25/29

    25 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    A PFD serves as visualization of all stepsvalve open/close is indicated by green/red

    actions are yellow with a descriptiontransitions are blue with a description

    Automatic Plant Start Up

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    26/29

    26 D. Krenz / HDB / z3641.ppt

    Linde EngineeringA plant model enables the plant operatorto change major plant variables andverify the best operating point

    Independent plantinputs such as feed

    composition

    Plant Model

    Observation of thepredicted products and

    selection of theoperating point which

    promises the best plantresult

    Variation of plantvariables such as

    steam/feed, reformeroutlet temperature etc.

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    27/29

    27 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Example for a HYCO plant modelfor the operating point calculation

    O2 0.00%

    AC2104 O2-SP

    1.22mol% 1.22mol% 0.00%

    0.00% 0 kg/h

    0 kg/h flue gas H2-Product

    steam T2118 0 kg/h

    FC2106 987 cel 0 Nm3/h

    0 kg/h 0.00% F. 0.0kmol/h

    D/C 28.6bar 0 kg/h

    3.00kg/kg 855 cel 330 cel 0.00%

    reformer 0.00% 0.00% shift 0.0kmol/h psa

    co2=0.00mol% co2=0.00mol%580 cel co2=0.00mol% co2=0.00mol%

    0.00% co2=0.00mol% co2=0.00mol% purge gas

    feed co2=0.00mol% T co2=0.00mol% 0 kg/h

    0.0kmol/h 855 cel dry ch4 0.000mol

    FC2103 dry h2o 0.000mol

    0 kg/h 0.00% h2 0.000mol0 kg/h 0.00% co 0.000mol

    0.00% air co2 0.000mol

    0 kg/h n2 0.000mol

    Einsatzzusammensetzung 250 cel

    0 ch4 0 49.22MJ/kg 9.73MJ /k g FC2115

    0 H2O 0 Erdgas DWA Restg 0 kg/h

    0 h2 0 0 kg/h

    0 CO 0

    0 CO2 0 0 kg/h 0 kg/h

    0 C2H4 0 FC2119 FC24030 C2H6 0 0 kg/h 0 kg/h

    0 C3H6 0 0.00% 0.00%

    0 C3H8 0

    0 C4H8 00 i-C4H10 0

    0 n-C4H10 0

    0 C5H12 0

    0 C6H14 0

    0 N2 0.0082

    1.00 1.00

    combustion

    steam

    D/C

    Steam or D/C

    feed

    Production

    feed / Producti

    ON (to flar)

    OFF (no flare

    purge gas to flare

    Man Auto

    o2

    Man Auto

    temperatur

    NSG

    RUG

    Einsatztyp

    M1

    M2

    M3 HG1 HG2

    Heizgastyp

    HG3 HG4 HG5

    wie Einsatz

    aus HG-Typ

    Heizgaswahl

    Man Auto

    ch2.sp

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    28/29

    28 D. Krenz / HDB / z3641.ppt

    Linde EngineeringLindes simulation models are easyto use and lead always to a improvedand smooth plant operation

    Simulation models are tailored to your plant can run on normal PChardware and can be used immediately without any programmingwork

    The operator can learn with simulation models the process behaviorwithout endangering the real plant. The Excel models are especiallygood because of their user interface (similar to the DCS) and the lowinvestment coasts

    The plant tuning is done with simulation models in order to reduce

    trail and error. This results in best plant operation under changingplant conditions.

  • 7/29/2019 07_Dynamic_Plant_Simulation_T.pdf

    29/29

    29 D. Krenz / HDB / z3641.ppt

    Linde Engineering

    Thank you for your Attention.