1 04.04.2007 SB
Cables from PP to calorimetersCabling being done by ITEP-Moscow and IAP-Bucarest teamSummary for cables/connectors list, rack wizard by Robert
2 04.04.2007 SB
Cables routing
PP -> fix point -> ECAL PP -> fix point -> HCAL
HCAL -> fix point -> ECAL
380V + control for power supplies Power for CWs, pin-diods Data and TTC optical cables ECS SPECS Radioactive source for HCAL DSS Water
Trigger cables
3 04.04.2007 SB
4 04.04.2007 SB
Optical cables few problems identified by Patrick:
Trigger-Data fibers are not tagged Colour convention problem
to test before installation ? Trigger cables HCAL -> ECAL
length critical for 6 cables => individual routing Water cooling: water reservoir still to be produced Manpower “sharing” with other activities
Some details
5 04.04.2007 SB
Minimal cabling for common test (ECAL L3B01 + HCAL L3A03)
380 V + control Data + trigger optical Trigger HCAL -> ECAL SPECS for CROCs, voltage and light distribution boards
ECAL+HCAL Power CWs and LEDs (?), backup: keep power supplies on the
calorimeter Turbines for two racks involved Connection of two chillers
problem: guarding/monitoring the power for chillers and turbines
Cabling for common test
6 04.04.2007 SB
C-side rack 1 for ECAL/PS and HCAL rack to be finished on the week of 9/10 (partial DSS, temporary water?)
C-side to be completed on the week of 16/10 (partial DSS, temporary water?)
A-side to start on the week of 16/10 Permanent labels pending
Outlook