Upload
benjamin-jackson
View
214
Download
0
Embed Size (px)
Citation preview
03/22/07 ACC Open Meeting Summer Preparedness 2007 1
SRP
Summer Preparedness 2007
Mike HummelManager – Supply & Trading
andGary Harper
Manager - System Operations
ACC Summer Preparedness HearingMarch 22, 2007
03/22/07 ACC Open Meeting Summer Preparedness 2007 2
Eastern Mining Area
Phoenix
Peoria
Glendale
Scottsdale
Mesa
Tempe
Gilbert
Chandler
Tolleson
LitchfieldPark
Surprise
Goodyear
Avondale
ApacheJunction
QueenCreek
FountainHills
ParadiseValley
SRP Electric Service Territory
03/22/07 ACC Open Meeting Summer Preparedness 2007 3
Summary
• Peak demand is expected to be higher than last year due to continued growth.
• Adequate resources have been secured to meet the anticipated demand.
• The risk of potential wildfires is a continuing concern.
03/22/07 ACC Open Meeting Summer Preparedness 2007 4
Peak Load Forecast
6590 MW6627 MW
2006 Actual 2007 Forecast
03/22/07 ACC Open Meeting Summer Preparedness 2007 5
Summer 2006 Retail System Peak ‘Needle Peak’
• Summer 2006 new peak – 6590 MW
• Exceeded Base Forecast of 6210 MW by 380 MW
– 16 hours
• Exceeded High Risk Forecast of 6448 MW by 150 MW (1:10 occurrence)
– 3 hours
• 118 degree Peak Temperature (1:10 occurrence)
03/22/07 ACC Open Meeting Summer Preparedness 2007 6
Summer 2007 Outlook
SRPSRPGenerationGeneration
PurchasedPurchasedPowerPower
SRPSRPForecastForecast
Peak LoadPeak Load
ReservesReserves
5690 MW
1849 MW
Expected Need
6627 MW
912 MW
Total 7539 MW
Expected Capability
Total 7539 MW
03/22/07 ACC Open Meeting Summer Preparedness 2007 7
Reserves• Respond to load extremes above base
forecast.• Provide an immediate response to forced
outages.• Quantity is based on NERC and WECC
operating criteria and contractual arrangements.
• A portfolio of resources is utilized to meet the reserve requirements.– Balances “reliability” and “low cost” objectives.
03/22/07 ACC Open Meeting Summer Preparedness 2007 8
SRP Owned Generation – 2007
Coal1791 MW
Nuclear 672 MW
Gas2951 MW
Hydro & Renewables 276 MW
Total Capacity: 5690 MW
03/22/07 ACC Open Meeting Summer Preparedness 2007 9
Purchased Power
• Purchased power portfolio is in place to meet demand.
• Additional purchases may be needed to respond to forced unit outages.
• Regional market conditions suggest that there will be sufficient capacity to meet the Arizona demand.
03/22/07 ACC Open Meeting Summer Preparedness 2007 10
Fuel Status
• Nuclear – Full requirements under contract
• Coal– Plants expected to be at or above target
inventories by summer season– Full requirements under contract
• Natural Gas– Full transportation requirements under contract– In process of securing retail commodity
requirements – Distillate fuel back-up
03/22/07 ACC Open Meeting Summer Preparedness 2007 11
Generation Maintenance Completed By Summer 2007
UnitsAgua Fria 1,2,3,4,5,6Craig 2Desert Basin 1,2Hayden 2Horse Mesa 1,2,4Kyrene 7Mormon Flat 1,2Navajo 2Palo Verde 1,2,3Roosevelt 1Santan 1,2,3,4,5Stewart Mountain 1
03/22/07 ACC Open Meeting Summer Preparedness 2007 12
NEW NUMBER
- Distribution Substations 5
- 28MVA 69/12kV Transformers 9
- 230kV Breakers 12
- 69kV Breakers 43
- 69kV Capacitors 48 MVAR
-230/69kV Transformers 2
-500/230kV Transformers 1
System AdditionsStations
03/22/07 ACC Open Meeting Summer Preparedness 2007 13
System AdditionsLines
ADDITIONS NUMBER
- Pole Replacements 620
- Rebuilt/Upgrade 69kV Lines 6.1 Miles
- New Circuit Miles of 69kV Line 20.6 Miles
- Rebuilt/Upgrade 230kV Lines 17.5 Miles
- New Circuit Miles of 230kV Line 9 Miles
03/22/07 ACC Open Meeting Summer Preparedness 2007 14
System Preparation
Transmission and substation maintenance Transmission and substation maintenance and training will be complete by summer. and training will be complete by summer. This includes:This includes:
– Line patrols/inspections– Preventative maintenance– Pole re-enforcement– Pole change-outs/
upgrades– Wildfire coordination
– Tree trimming– Cable replacement – Storm planning– Emergency
procedure training– Blackstart training
03/22/07 ACC Open Meeting Summer Preparedness 2007 15
• Facilities identification and location
• Direct communication between SRP and Agencies
• SRP Advisor Representative on-site
• Firefighting safety information
• Participate in State Drill and Southwest Mutual Assistance Committee
SRP/Wildland Fire CoordinationSRP/Wildland Fire Coordination
03/22/07 ACC Open Meeting Summer Preparedness 2007 16
SRP Electric Facility Firefighting
• Support development of Pre-Plan Information for each facility.
• Provide Emergency Contact Information for each facility and responding firefighters.
• Integrate SRP representatives into Incident Command System management.
• Provide firefighter electrical safety awareness and facility orientation training.
03/22/07 ACC Open Meeting Summer Preparedness 2007 17
Arizona EHV Transmission Systems
Glen CanyonGlen Canyon
ParkerParker
DavisDavis
Phil Young Phil Young (Greenlee)(Greenlee)
HaydenHaydenCraigCraig
PaloPaloVerdeVerde
ChollaCholla
MohaveMohave
CoronadoCoronado
SpringervilleSpringerville
KyreneKyrene
Four CornersFour Corners
NavajoNavajo San JuanSan Juan
ToToMiguelMiguel
ToToDeversDevers
Silver KingSilver King
North GilaNorth GilaSaguaroSaguaro
MeadMead
MoenkopiMoenkopi
WestwingWestwing
El DoradoEl DoradoMc CulloughMc CulloughMarketplaceMarketplace
PinnaclePinnaclePeakPeakLibertyLiberty
ShiprockShiprock
SouthSouth VailVail
TONEVADA
TOCALIFORNIA
TOUTAH
TONEW
MEXICO
TO COLORADO
TOPHOENIX AREA
TO TUCSONAREA
TONEW
MEXICO
TONEW
MEXICO
TOUTAH
NEW MEXICONEW MEXICOARIZONAARIZONAMEXICOMEXICO
COLORADOCOLORADOUTAHUTAHNEVADANEVADA
CALIFORNIA
NorthNorthNorthNorth
BrowningBrowningHassayampaHassayampa JojobaJojoba
RuddRudd
Electrical SubstationsElectrical Substations
Coal GenerationCoal Generation
Hydro GenerationHydro Generation
New Gas GenerationNew Gas Generation
03/22/07 ACC Open Meeting Summer Preparedness 2007 18
Distribution• Summer operating procedures reviewed
and refresher training provided to O&M personnel.
• Six mobile substation transformers are available for service if needed.
• If required, the process for implementing rotating outages has been automated.
– The planned sequence of substation outages and the duration of each outage is the same as in the past.
03/22/07 ACC Open Meeting Summer Preparedness 2007 19
Summary of Year 2007Projected Conditions
• Transmission, SRP generation and planned energy purchases are adequate to serve the forecasted year 2007 demand.
• Wildfires are our biggest concern.
• Contingency plans are in place to handle emergency events.
03/22/07 ACC Open Meeting Summer Preparedness 2007 20