03- Process Analysis

Embed Size (px)

Citation preview

  • 8/9/2019 03- Process Analysis

    1/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Process Analysis

    OPERATIONS MANAGEMENT -1

    Term 2, B2014-16, Oct-Dec 2014

  • 8/9/2019 03- Process Analysis

    2/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    West

    converts iron ores into iron briquettes to supply steel

  • 8/9/2019 03- Process Analysis

    3/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    ~ 160 m

    IronOreFines

    CFBPreheater

    InclinedBucket Elevator

    1st StageCFB Reactor

    2nd StageFB Reactor

    HBI Produc

    ProcessGas

    HeatExchanger Process GasCompressor

    Fired Gas Heaters

    ElectricalSubstation&ControlRoom

    Engineering drawing

    To Create a Process Flow Chart (Diagram)

  • 8/9/2019 03- Process Analysis

    4/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Elements of a Process

    Inventory / Buffers

    Do NOT have a capacity; however,

    there might be a limited number of

    flow units that can be put in this

    inventory space at any moment of time

    Multiple flow unit types possible

    Arrows

    Indicate the flow of the flow unit

    Multiple flow unit types possible

    Activities

    Carried out by resources

    Add value and are required

    for completion of the flow unit

    May or may not carry inventory Have a capacity (maximum number

    of flow units that can flow through

    the activity within a unit of time)

  • 8/9/2019 03- Process Analysis

    5/30OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Pre-Heater

    Pile of Iron ore fines

    Process flow diagram, first step

  • 8/9/2019 03- Process Analysis

    6/30OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    LockHoppers

    1st Reactor 2ndPre-Heater

    Pile of Iron ore fines

    Process flow diagram, to be continued

  • 8/9/2019 03- Process Analysis

    7/30OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    FlaHe

    DischargeBriquetting

    Lock

    Hoppers1st Reactor 2nd RPre-Heater

    Pile of Iron ore fines

    Finished Goods

    Completed process flow Process flow di

  • 8/9/2019 03- Process Analysis

    8/30OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Completed PFD for the Circored process

    Pile of Iron

    ore fines

    Pre-Heater

    Bri

    tinFlash

    heater

    Dis-

    charge

    Fini

    goo

    Lock

    Hoppers1st

    Reactor

    2nd

    Reactor

  • 8/9/2019 03- Process Analysis

    9/30OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    FlasHeaDischargeBriquetting

    LockHoppers

    1st Reactor 2ndRePre-Heater

    Pile of Iron ore fines

    Finished Goods

    7.5% Outflow 15% Outflow 1

    FlasHeaBriquetting

    LockHoppers

    1st 2ndPre-Heater

    Pile of Iron ore fines

    Finished Goods

    Process flow diagram accounting for mass

  • 8/9/2019 03- Process Analysis

    10/30OPM 1 Term 2, B2014-16, Oct-Dec 2014

    Session 03 Process Analysis

    Process Concepts

    Important

    Process capacity

    Flow rate

    Cycle Time

    Manufacturing Lead Time (MLT) /Throughput T Bottleneck

    Process utilization and capacity utilization

    Workload and implied utilization

    Additional

    Lot Size/Batch Size

    Setup time Run time

    Waiting time

    Idle time

    Buffer

  • 8/9/2019 03- Process Analysis

    11/30OPM 1 Term 2, B2014-16, Oct-Dec 2014

    Session 03 Process Analysis

    Bottleneck and process capacity Capacity: Number (amount) of units that can be processed pe

    Each briquetting machine has a capacity of 55 tons per hour

    Overall capacity of a sequence of processes is determined by

    process, i.e. the resource with the smallest capacity.

    Process capacity=Min{Capacity of Res 1, ., Capacity of Res

    Incorporating available input rate and demand rate,

    Throughput=Min{Input rate, Process capacity, Demand rate

    Demand

    InputBottleneckCapacity

    Excesscapacity

    Flow Rate

    Demand

    InputBottleneckCapacity

    Excesscapacity

    Flow Rate

    Demand constrained

    Flow Rate Flow Rate

    Supply constrained

  • 8/9/2019 03- Process Analysis

    12/30OPM 1 Term 2, B2014-16, Oct-Dec 2014

    Session 03 Process Analysis

    Capacity Related Terminology

    Setup time : thetime that a part

    spends waiting for aresource to be set

    up to work on thissame part

    Process time/runtime is the timethat the part is

    being processed

    Queue titime th

    waits for while the

    is bussometh

  • 8/9/2019 03- Process Analysis

    13/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Time Components of Production Cycle (C

    Wait time is the time that apart waits not for a resourcebut for another part so that

    they can be assembledtogether

    Idle time is the unuthat represents thtime less the sum

    setup time, processqueue time, and w

    i d i f

  • 8/9/2019 03- Process Analysis

    14/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Time to Produce a Certain Amount of Su

    Assuming the process is already producing output.

    How long does it take for the Trininad plant to prod10,000 tons?

    A restaurant has 40 tables. Average flow time = 60 m

    long is the wait time if you are sixth on the waiting l

  • 8/9/2019 03- Process Analysis

    15/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Throughput Time = Work-in-Process /Throughput rate

    Operations management (OM) covers a large arena of practice.

    Littles Law is discussed in several current OM texts, including Hopp a(2000), Cachon and Terwiesch (2004).

    Queuing theory and OM generally use different notations for Littles Law

    and so we introduce that issue first. In a desire to get close to people wh

    using LL to support decision making,

    Littles Law

    Average Inventory = Average Flow Rate X Average Flow Tim

    ( Cachon and Terweiesch

    ( Hopp amd Spearman, 2000

    Li l L

  • 8/9/2019 03- Process Analysis

    16/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Littles Law

    7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00

    Cumulative In-flow and Out-flow

    11

    10

    98

    7

    6

    5

    4

    3

    2

    1

    0

    Flow Time

    Inventory

    Inventory=Cumulative Inflow Cumulative Outflow

    Cumulative

    Inflow

    Cumulative

    Outflow

    Patients

  • 8/9/2019 03- Process Analysis

    17/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    The process capacity of Circored plant in Trini

    Capacities

    Preheater 120 tons/hour

    Lock Hoppers 110 tons/hour

    1st (cfb) Reactor 112 tons/hour. Processes 28 tons every 15 minutes

    2nd (fb) Reactor 100 tons/hour. Processes 400 tons every 4 hours

    Flash heater 135 tons/hour

    Discharge 118 tons/hour

    Briquetting 165 tons/hour

    Pre-

    Heater DischaFlash

    heater

    Lock

    Hoppers 1st (cfb) Reactor

    2nd (fb)

    Reactor

    Process Capac

    = min{120,110,112,100,

    = 100 tons/ho

  • 8/9/2019 03- Process Analysis

    18/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    The cycle time of circored plant in Trinidad

    Cycle time: Amount of time taken to process 1 unit in a repetitive

    Since different units can be processed in parallel, cycle time is not the flow tim

    Cycle time (designed) = 1 / Process Capacity

    How long does it take to process 1 ton of iron ore?

    Since 1 hour is required for 100 tons, 1/100 hour suffices for 1 ton.

    That is, the cycle time is 0.01 hour = 0.6 min = 36 seconds

    Every 36 seconds 1 ton of iron briquette is completed.

    Pre-

    Heater DischaFlash

    heater

    Lock

    Hoppers 1st (cfb) Reactor

    2nd (fb)

    Reactor

    P tili ti d C it tili ti

  • 8/9/2019 03- Process Analysis

    19/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Process utilization and Capacity utilizatio

    The objective of most businesses is to increase profi

    increase utilization.

    A service process should not pursue 100% utilization

    Utili ation of limited demand

  • 8/9/2019 03- Process Analysis

    20/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Utilization of limited demand Assume the demand is only 657,000 tons

    Design capacity = (100 tons/hr X 24 hours/day X 365 days/ yr)

    tons

    The bottleneck is the resource with the highest utilization.

    Utilization Profile

  • 8/9/2019 03- Process Analysis

    21/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Preheater LockHoppers

    CFB StationaryReactor

    Flashheater

    Pressurelet-downsystem

    Briquma

    Imbalance relativeTo bottleneck

    Mismatch between demand andsupply at the process level

    Preheater LockHoppers

    CFB StationaryReactor

    Flashheater

    Pressurelet-downsystem

    Briquma

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Imbalance relativeTo bottleneck

    Mismatch between demand andsupply at the process level

    Bottleneck

    Utilization

    Utilization Profile

    Workload and implied utilization

  • 8/9/2019 03- Process Analysis

    22/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Workload and implied utilization

    Utilization only carries information about excess ca

    Implied utilization captures the mismatch when the

    exceeds the capacity.

    The utilization with demand of 1 095 000

  • 8/9/2019 03- Process Analysis

    23/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    The utilization with demand of 1,095,000

    Bottleneck

    Implied (requested) Utilization of a resource = Demand / Capacity

    Preheater LockHoppers

    CFB FB FlashHeater

    Briquett0%

    50%

    75%

    100%

    Utilization

    Discharge

    125%

    STEPS FOR BASIC PROCESS ANALYSIS WITH ON

  • 8/9/2019 03- Process Analysis

    24/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    STEPS FOR BASIC PROCESS ANALYSIS WITH ON

    OF FLOW UNIT

    Find the capacity of everyresource, if there are

    multiple resourcesperforming the same

    activity add their capacitiestogether.

    The resource with thelowest capacity is called the

    bottleneck. Its capacitydetermines the capacity ofthe entire process (Process

    Capacity).

    The flow on Flow(Availab

    Pro

    We find the Utilization oSimilarly we find the utilization of eachresource as Flow rate

    Different units flowing in the same syste

  • 8/9/2019 03- Process Analysis

    25/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    File

    Contact faculty/

    other persons

    Contact prior

    employers

    Benchmark

    grades

    Confirmation

    letter

    Internship

    Staff

    Consulting

    File

    Contact faculty/

    other persons

    Contact prior

    employers

    Benchmark

    grades

    Confirmation

    letter

    Different units flowing in the same syste Outsourcing business processes is common

    Billing, Recruiting, Maintenance, Customer call centers, etc

    The company which handles the outsourced process is likely to deal w

    kinds of units

    Case in point: A company that provides resume validation service:

    Demand is 180 applications per day ( 30 for consulting, 110 for staff and remaining f

    STEPS FOR BASIC PROCESS ANALYSIS WITH M

  • 8/9/2019 03- Process Analysis

    26/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    STEPS FOR BASIC PROCESS ANALYSIS WITH M

    TYPES OF FLOW UNITS1. For each resource, compute the number of minutes that the resource can produce; this is 6

    Number of resources within the resource pool.

    2. Create a process flow diagram, indicating how the flow units go through the process; use m

    indicate the flow of the different flow units.

    3. Create a table indicating how much workload each flow unit is consuming at each resource

    The rows of the table correspond to the resources in the process.

    The columns of the table correspond to the different types of flow units.

    Each cell of the table should contain one of the following:

    1. If flow unit does not visit the corresponding resource, ;

    2. Otherwise, demand per hour of the corresponding flow unit activity time.4. Add up the workload of each resource across all flow units.

    5. Compute the implied utilization of each resource as

    Implied utilization = Result of Step 3

    Result of Step 1

    The resource with the highest implied utilization is the bottleneck.

    An application as a unit

  • 8/9/2019 03- Process Analysis

    27/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    An application as a unit

    Activity

    Time (min)

    Per applct

    Number

    of workers

    Available

    Capacity

    Applct/hr

    Consulting

    Workload

    Per hour

    Staff

    Workload

    Per hour

    Intern

    Workload

    Per hour

    T

    File 3 1 20 3 11 4

    Contact Persons 20 2 6 3 0 0

    Contact

    Employers

    15 3 12 3 11 0

    Benchmark

    Grades

    8 2 15 0 0 4

    Confirmation

    Letter

    2 1 30 3 11 4

    Demand per hour for validation: 3 for consulting; 11 for staff; 4 for inter

    Using One minute of work as the flow unit to find the

  • 8/9/2019 03- Process Analysis

    28/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    g

    Activity

    Time (min)

    Per applct

    Number

    of workers

    Available

    Capacity

    Consulting

    Workload

    Minutes Per

    hour

    Staff

    Workload

    Minutes Per

    hour

    Intern

    Workload

    Minutes Per

    hour

    File 3 1 60 3 X 3 11 X 3 4 X 3

    Contact Persons 20 2 120 3 X 20 0 0

    Contact

    Employers

    15 3 180 3 X 15 11 X15 0

    Benchmark

    Grades

    8 2 120 0 0 4 X 8

    Confirmation

    Letter

    2 1 60 3 X 2 11 4 X 2

    Demand per hour for validation: 3 for consulting; 11 for staff; 4 for inter

    A li ti it

  • 8/9/2019 03- Process Analysis

    29/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    An application as a unit

    What is the minimum number of people to hire simplied utilization of contact employers is below 100%

    What happens to implied utilizations when staff ap

    decrease to 8 per hour? Compute the new utilization

    Summary of process analysis

  • 8/9/2019 03- Process Analysis

    30/30

    OPM 1 Term 2, B2014-16, Oct-Dec 2014 Session 03 Process Analysis

    Compute the

    Capacity for

    each of the

    Resources

    Use demand to

    compute the

    implied utilization

    levels

    Identify the

    Bottleneck

    Prepare a

    Process Flow

    Diagram

    Use different

    Colors to mark

    Flow units

    Note that capacity

    levels may differ

    depending on

    product type

    Compute the work-

    load across all

    product types

    Step with highest

    implied utilizationExtensions required

    for working with

    multiple flow units

    Extensions required

    for working with

    multiple flow units

    Compute the

    Capacity for

    each of the

    Resources

    Use demand to

    compute the

    implied utilization

    levels

    Identify the

    Bottleneck

    Prepare a

    Process Flow

    Diagram

    Compute the

    Capacity for

    each of the

    Resources

    Use demand to

    compute the

    implied utilization

    levels

    Identify the

    Bottleneck

    Prepare a

    Process Flow

    Diagram

    Use different

    Colors to mark

    Flow units

    Note that capacity

    levels may differ

    depending on

    product type

    Compute the work-

    load across all

    product types

    Step with highest

    implied utilization

    Summary of process analysis

    World class enterprises excel at the speedy and flexible integthe business processes.

    Finding the bottleneck allows us to compute a variety of perf

    measures.

    You Can't Manage What You Don't Measure