    HIGHWAY MATERIALSPart 2

    Compaction and CBR

    Mr Che Ros Ismail| Dr Norhidayah Abdul Hassan

    Faculty of Civil Engineering

  • 8/18/2019 02-Highway Materials - Compaction CBR

    2/20

      How to determine the

    strength or bearingcapacity of soil?

    2

  • 8/18/2019 02-Highway Materials - Compaction CBR

    3/20

    3

    Two major processes

    Compaction test

    (determine Maximum DryDensity, MDD and Optimum

    Moisture Content, OMC)

    California Bearing Ratio test

    (determine CBR value)

  • 8/18/2019 02-Highway Materials - Compaction CBR

    4/20

    Compact ion

    4

    Data and analysis

    Calculate dry density andmoisture content (plot DD vs. MC)

    Determine MDD and OMC

    Compaction of sample

    Tools: mold 2.3L, hammer 4.5 kgProcedures: compacted for 5

    layers, 62 blows/layer

    Sample preparation

    dry soil (particle size ≤ 20mm) 5 different moisture contents

  • 8/18/2019 02-Highway Materials - Compaction CBR

    5/20

    5

    1

    2

    Compaction steps

  • 8/18/2019 02-Highway Materials - Compaction CBR

    6/20

    Compaction steps

    6

    3

    4

  • 8/18/2019 02-Highway Materials - Compaction CBR

    7/20

    7

    4

    5

    Compaction steps

  • 8/18/2019 02-Highway Materials - Compaction CBR

    8/20

    Example Data:

    Compaction data:

    Moisture content data:

    Sample1

    Sample2

    Sample3

    Sample4

    Sample5

    Mass of mould (g)

    Mass of mould + compacted sample (g)

    Mass of compacted sample (g)

    Bulk Density (Mg/m3)

    Dry density (Mg/m3)

    Sample

    1

    Sample

    2

    Sample

    3

    Sample

    4

    Sample

    5

    Mass of container (g)

    Mass of container + wet sample (g)

    Mass of container + dry sample (g)

    Moisture content (%)

  • 8/18/2019 02-Highway Materials - Compaction CBR

    9/20

    Dry Density vs. Moisture Content

    Moisture Content

    Dry Density

    Compaction

    CurveMDD

    OMC

  • 8/18/2019 02-Highway Materials - Compaction CBR

    10/20

    CBR Test

    Data and analysisDetermine dry density, Plot Load (kN)

    vs. Penetration of Plunger (mm)Determine Top and bottom CBR

    values at 2.5 and 5 mm pen.

    Compaction of sampleTools: mold 2.3L, hammer 4.5

    kgProcedures: 3 samples, compacted for 5 layers,65, 35, 15 blows/layer, soaked in water for 4 days

    Sample preparation

    dry soil (particle size ≤ 20mm) optimum moisture content

  • 8/18/2019 02-Highway Materials - Compaction CBR

    11/20

    11

    Top

    Bottom

    Soaked CBR

  • 8/18/2019 02-Highway Materials - Compaction CBR

    12/20

    12

    CBR Testing

    Sample

    Penetration

    dial gauge

    Loading

    dial gauge

  • 8/18/2019 02-Highway Materials - Compaction CBR

    13/20

    13

    CBR 1

    0 2 4 6 8

    0

    2

    4

    6

    8

    10

    12

    Penetration, mm

        L   o   a    d ,    k

        N

    2.5 5.0

  • 8/18/2019 02-Highway Materials - Compaction CBR

    14/20

    14

    CBR 2

    0 2 4 6 8

    0

    2

    4

    6

    8

    10

    12

    Penetration, mm

        L   o   a    d ,

        k    N

    2.5 5.0

  • 8/18/2019 02-Highway Materials - Compaction CBR

    15/20

    15

    CBR 3

    0 2 4 6 8

    0

    2

    4

    6

    8

    10

    12

    Penetration, mm

        L   o   a    d ,    k

        N

    0 2.5mm 5.0mm

    Tangent line

  • 8/18/2019 02-Highway Materials - Compaction CBR

    16/20

    CBR analysis

    1. Calculate CBR values of top and bottom @ 2.5 and 5.0mm:

    [email protected] = load at 2.5mm/13.24 x100

    [email protected] = load at 5.0mm/19.96 x100

    2. Report the highest CBR values for top and bottom and dry

    density for all 3 samples

    3. Plot CBR values versus dry density and determine CBR at

    95% compaction (95% MDD)

    16

  • 8/18/2019 02-Highway Materials - Compaction CBR

    17/20

    CBR vs . DD Data

    17

  • 8/18/2019 02-Highway Materials - Compaction CBR

    18/20

    18

    CBR vs. DD

    95% compaction = 95% MDD

  • 8/18/2019 02-Highway Materials - Compaction CBR

    19/20

    19

    I n-situ CBR

  • 8/18/2019 02-Highway Materials - Compaction CBR

    20/20

    THANK YOU