Briefing on Materials Standards Plan/Schedule: ConcreteS. K. GhoshS. K. Ghosh Associates Inc.Palatine, IL and Aliso Viejo, CA

www.skghoshassociates.com- # -ACI 318-08

- # -2009 International Building Code

- # -33The 2009 IBC came out in March 2009.

It is scheduled to become effective in the State of California Jan 1 2011.

Changes between the 2006 IBC and the 2009 IBC are shown with black bars in the margin. An arrow indicates a deletion.

Ask how many people have the 2009 IBC; typically we get a response that 90% have not purchased.ACI 318-11

- # -

2009 International Building Code- # -

ASCE 7-10Supplement No. 1being processed now.- # -Adoption of ACI 318-11ACI 318-11 adopted into the 2012 IBC sight-unseenUnderstanding was that it would be removed by errata if it did not come out in print by a certain dateA number of other standards was adopted by the same administrative maneuver- # -

- # -Significant changes from ACI 318-08 to ACI 318-11Rules for deformed bar types are updated. Grade 80 deformed bars per ASTM A615 and A706 are allowed for non-seismic applications. Zinc and epoxy dual-coated reinforcing bars per ASTM A1055 are now recognized.- # -Significant changes from ACI 318-08 to ACI 318-11New test methods for sulfate resistance are included. ASTM D516 and D4130 are identified as tests for sulfate ions in water, brackish water, or seawater, and ASTM C1580 is identified as a test for water-soluble sulfate in soil.- # -Significant changes from ACI 318-08 to ACI 318-11Test records for determining standard deviation for a mixture design may now be up to 24 months old. Also, testing agencies performing acceptance testing of concrete are now required to comply with ASTM C1077.- # -Significant changes from ACI 318-08 to ACI 318-11New requirements for detailing of circular column ties, design and detailing of temperature and shrinkage reinforcement for post-tensioned slabs, and minimum reinforcement for deep beams have been added. Also, development length for headed bars has been revised.- # -Significant changes from ACI 318-08 to ACI 318-11Factored load combinations have been revised to conform to ASCE 7-10.- # -Significant changes from ACI 318-08 to ACI 318-11Reinforcement detailing requirements for seismic applications have been enhanced. These enhancements include rules for detailing of horizontal bars at special boundary elements of special shear walls, and confinement of beam flexural hinge regions.- # -Significant changes from ACI 318-08 to ACI 318-11Door and window openings in shear walls often lead to narrow vertical wall segments, many of which have been defined as wall piers in the IBC and in the UBC before it. Wall pier provisions are now included in ACI 318-11. The dimensions defining wall piers are given. Detailing is prescribed, which would result in flexural failure preceding shear failure in wall piers. - # -Significant changes from ACI 318-08 to ACI 318-11Design requirements for adhesive anchors are now included.Failure modes and corresponding nominal strengths are defined, as are requirements for testing and evaluation of adhesive anchors for use in cracked concrete or subject to sustained loads.- # -Significant changes from ACI 318-08 to ACI 318-11The new provisions also include criteria for overhead adhesive anchors, seismic requirements for anchoring to concrete, installation and inspection of adhesive anchors, and certification of adhesive anchor installers.- # -Reorganization of ACI 318-11ACI 318-11:CHAPTER 1GENERAL REQUIREMENTSCHAPTER 2NOTATION AND DEFINITIONSCHAPTER 3MATERIALCHAPTER 4DURABILITY REQUIREMENTSCHAPTER 5CONCRETE QUALITY, MIXING, AND PLACINGCHAPTER 6FORMWORK, EMBEDMENTS, AND CONSTRUCTION JOINTS- # -Reorganization of ACI 318-11ACI 318-11 (Contd.):CHAPTER 7DETAILS OF REINFORCEMENTCHAPTER 8ANALYSIS AND DESIGNGENERAL CONSIDERATIONSCHAPTER 9STRENGTH AND SERVICEABILITY REQUIREMENTSCHAPTER 10FLEXURE AND AXIAL LOADSCHAPTER 11SHEAR AND TORSION- # -Reorganization of ACI 318-11ACI 318-11 (Contd.):CHAPTER 12DEVELOPMENT AND SPLICES OF REINFORCEMENTCHAPTER 13TWO-WAY SLAB SYSTEMSCHAPTER 14WALLSCHAPTER 15FOOTINGSCHAPTER 16PRECAST CONCRETECHAPTER 17COMPOSITE CONCRETE FLEXURAL MEMBERS- # -Reorganization of ACI 318-11ACI 318-11 (Contd.):CHAPTER 18PRESTRESSED CONCRETECHAPTER 19SHELLS AND FOLDED PLATE MEMBERSCHAPTER 20STRENGTH EVALUATION OF EXISTING STRUCTURESCHAPTER 21EARTHQUAKE-RESISTANT STRUCTURESCHAPTER 22STRUCTURAL PLAIN CONCRETE- # -Reorganization of ACI 318-11ACI 318-11 (Contd.):APPENDIX ASTRUT-AND-TIE MODELSAPPENDIX BALTERNATIVE PROVISIONS FOR REINFORCED AND PRESTRESSED CONCRETE FLEXURAL AND COMPRESSION MEMBERSAPPENDIX CALTERNATIVE LOAD AND STRENGTH REDUCTION FACTORSAPPENDIX DANCHORING TO CONCRETE- # -Reorganization of ACI 318-14ACI 318-14:CHAPTER 1GENERALCHAPTER 2NOTATION AND TERMINOLOGYCHAPTER 3REFERENCED STANDARDSCHAPTER 4PERFORMANCE REQUIREMENTS FOR STRUCTURAL MEMBERS AND STRUCTURAL SYSTEMSCHAPTER 5CONCRETE: DESIGN AND DURABILITY REQUIREMENTS - # -Reorganization of ACI 318-14ACI 318-14 (Contd.):CHAPTER 6STEEL REINFORCEMENT MATERIAL AND DURABILITYCHAPTER 7LOADSCHAPTER 8STRUCTURAL ANALYSISCHAPTER 9SECTIONAL STRENGTHCHAPTER 10SERVICEABILITYCHAPTER 11ONE-WAY SLABS- # -Reorganization of ACI 318-14ACI 318-14 (Contd.):CHAPTER 12TWO-WAY SLABSCHAPTER 13BEAMSCHAPTER 14COLUMNSCHAPTER 15WALLSCHAPTER 16FOUNDATIONSCHAPTER 17JOINTS AND CONNECTIONSCHAPTER 18DISCONTINUITY REGIONS

- # -Reorganization of ACI 318-14ACI 318-14 (Contd.):CHAPTER 19ANCHORING TO CONCRETECHAPTER 20EARTHQUAKE-RESISTANT STRUCTURESCHAPTER 21REINFORCEMENT DETAILSCHAPTER 22REQUIREMENTS FOR CONCRETE AND GROUT

- # -Reorganization of ACI 318-14ACI 318-14 (Contd.):CHAPTER 23FORMs, SHORES, AND RESHORESCHAPTER 24STRENGTH EVALUATION OF EXISTING STRUCTURESCHAPTER 25PLAIN CONCRETE318.1CODE REQUIREMENTS FOR THIN SHELLS AND COMMENTARY- # -Reorganization of ACI 318-14REORGANIZATION OBJECTIVESMake Designers Work EasierUser Assured That All Appropriate Code Sections are AddressedAllow for Future InnovationSimplified Methods Provide Quick, Safe Solutions- # -Your input soughtwww.concrete.org/COMMITTEES/318Public.htmA Submit Questions/Comments button facilitates communication with the committee. Questions and comments will be reviewed, and the FAQ section will be periodically updated with answers to commonly asked questions. ACI Committee 318 may also conduct surveys to solicit specific input and feedback from users of the Code.- # -ACI 318-14 scheduleACI 318 balloting schedule shows the last letter ballot in January 2012. The committee will meet in the 2012 Spring Convention in Dallas (March 18-22). The committee will probably meet in the summer of 2012 also to resolve issues. TAC review comes next, followed by public review.The Standard (minus the Commentary) is expected be finalized at the Spring 2013 convention (mid April) in Minneapolis.- # -IBC Adoption of ACI 318-14A submissions will be prepared for the January 3, 2012 code change deadline for the 2015 IBC.The submission will assume 318-14 will be at a stage to print a few "final" copies for ICC review by late September 2013, in which case 318-14 will be referenced in Chapter 19 of the 2015 IBC.If review copies cannot be printed in time, 318-11 will remain the reference standard in the 2015 IBC. ACI 318-14 will then be adopted by 2018 IBC.

- # -IBC Adoption of ACI 318-14The process to include 318-11 in the 2012 IBC occurred before 318-11 was finalized. So all exceptions and additions in IBC Chapter 19 to ACI 318 are based on 318-08. This creates some problems and inconsistencies.A second code change is being prepared to remove these inconsistencies and will also be submitted by the January 3, 2012 deadline.

- # -Developments since ACI Convention, Fall 2011, CincinnatiAt the last convention, the plan was to maintain the 318-11 reference in the 2015 IBC, because the 318 steering committee agreed that more time was needed to finish 318-14 than was previously available.Dan Falconer, ACI

- # -Developments since ACI Convention, Fall 2011, Cincinnati the ICC timetable has since changed and now approximately matches up with what the steering committee thought was needed to finish 318-14. ACI will therefore propose inclusion of 318-14, and not 318-11, in the 2015 IBC. At this time, I can't provide a revised detailed 318 schedule, but this is the big picture.Dan Falconer, ACI- # -Developments since ACI Convention, Fall 2011, CincinnatiI can tell you that CP 28 was revised such that for the 2012/13 cycle and beyond, updates to currently referenced [standards] will still be processed via the IADMIN committee (Group B with a code change deadline of Jan 3, 2013) and that the updated standard needs to be available by 12/1/14. Mike Pfeiffer, ICC

- # -Developments since ACI Convention, Fall 2011, CincinnatiIn effect, the Board has made permanent the 09/10 cycle provision for updating standards....Mike Pfeiffer, ICC- # -Developments since ACI Convention, Fall 2011, CincinnatiFirst, the referenced standards revised through the administrative process need to be available for purchase by December 1, 2014. Second, new referenced standards must be submitted with the code change proposal. The status of such new standards is currently defined as "an official draft," which is somewhat unclear. Matt asked if the draft after the final committee ballot was acceptable and Mike answered that such a draft is OK.Dan Falconer, ACI

- # -318-14 Completion Schedule

Regarding a schedule for completion of 318-14, it takes about 2 months from completion of committee responses to public comments to be available for purchase; therefore, the fall 2014 meeting can't be part of the schedule. My guess is that the committee has about 30 months [until Summer 2014] to finish in order to be referenced.Dan Falconer, ACI

- # -Thank You!!

For more informationwww.skghoshassociates.comChicago Main Office334 East Colfax Street, Unit EPalatine, IL 60067Phone: (847) 991-2700Fax: (847) 991-2702Email: [email protected] Southern California Office43 Vantis DriveAliso Viejo, CA 92656 Phone: (949) 215-6560Fax: (847) 991-2702Email: [email protected] - # -