62
Rock bolting Uwe Wyink Global Technical Manager Injection Ludwigshafen, 13.09.-14.09.2018

02 BASF Uwe Wyink · 2018-11-13 · Underground logistics longer transport ways to tunnel headings Cost pressure – per linear meter tunnel Higher development rate m/d General lack

Embed Size (px)

Citation preview

Rock boltingUwe WyinkGlobal Technical Manager Injection

Ludwigshafen, 13.09.-14.09.2018

Agenda

10/17/182

Motivation

Current situation for rock support

Alternative solution

Customer benefit

Motivation

3 10/17/18

4 10/17/18

Challenges in tunnel development in mining

10/17/185

Deeper mining results in:higher rock stressmore difficult ground conditions in combination with moving groundneed for improved quality and efficiency of installed ground support

higher rock temperaturesBigger tunnel dimensions (higher, wider)

Requirement to improve safetyKeep miners away from unsupported roof and face

Underground logistics longer transport ways to tunnel headings

Cost pressure – per linear meter tunnel Higher development rate m/d

General lack of skilled workforce in the industry

Higher degree of automatization in tunnel development needed

Current challenges in tunnel development in miningIndirect cost

10/17/186

Insufficient tunnel support is leading toRoadway deformation

Rock falls

Ground collapse

Additional cost for support refurbishment3 times the cost per m for total reconstruction

Hindered transport in narrow tunnels

Higher maintenance cost for equipment

Tunnel face/roof collapse

10/17/187

Current situation for rock support

8 10/17/18

Rock reinforcement principlesTheory

10/17/189

“Similar” principles as for a stone bridge

Ground support reinforces the selfcarryingproperties of the strata

Rocks near open space are held/locked together

Sprayed applied

Rock bolts

Standing support

Existing ground support methodsConventional

10/17/1810

Standing support (yielding & stiff)Steel archesWood

Sprayed concrete wet & dryWith and without fibers

RockboltsMechanical anchorsFriction boltsGrouted bolts

Resin cartridgesCementitious cartridgesCementitious grouts

Rock bolting and Cable bolting In Mining & Tunneling

10/17/1811

Rock bolts and Cable bolts are used extensively in ground support regimes in both hard rock and coal mines

This ground support or rock reinforcement is seen as active support

Rockbolts are used in combination:With and without meshSpray applied concreteSteel arches

The degree of mechanization and automatization in the mines is growing

Roof bolting theory

10/17/1812

Mechanical rockbolts

Friction bolts

Full barsPoint groutedFully encapsulated

Self drilling anchors

Cable bolts

Areas of application

17.10.1813

Resin grouted rockbolts

10/17/1814

Resin cartridgesVarious diametersVarious lengthsVarious speeds

Used for Point groutingFull encapsulation

Rockbolt installation (cartridges)

10/17/1815

Rockbolt installation (cartridges)

10/17/18 | Optionale Zusatzinformationen16

Rockbolt installation (cartridges)Feed rate – too fast

10/17/1817

Rockbolt installation (cartridges)Feed rate – too slow

10/17/1818

Rockbolt installation (cartridges)Mixing – too long

10/17/1819

Rockbolt installation (cartridges)Mixing – low rotation

10/17/1820

Rockbolt installation (cartridges)

10/17/1821

Rockbolt installation (cartridges)Storing & application temperature

10/17/1822

Rockbolt installation (cartridges)Resin volume - borehole

10/17/1823

Rockbolt installation (cartridges)Resin volume - strata

10/17/1824

Rockbolt installation (cartridges)Resin volume – weak rock strata

10/17/1825

17.10.18 | Optionale Zusatzinformationen26

Rockbolt installation

Rockbolt installation (cartridges)Summary

10/17/18 | Optionale Zusatzinformationen27

Mixing qualitySeveral mixing issues with cartridgesMixing takes place in the borehole and can’t be controlled 100%To much or to less bolt rotation leads to insufficient mixingCorrect bolt feed rate and rotation is neededBigger borehole diameter leads to finger glove effect or no mixing of resin and hardenerLimited shelf life of cartridges compared to pumpable resinsMixing of cartridges is highly depending on the surrounding application temperature

Rockbolt installation (cement grout)

10/17/18 | Optionale Zusatzinformationen28

SummaryCementitious grouts

17.10.18 | Optionale Zusatzinformationen29

Enough volume = full encapsulated

Controlled mixing outside the borehole

Suitable for cable and long bolts

Long setting and curing time = long re-entry time

Wider borehole diameter = longer drilling time per meter

Could lead to problems in water sensitive strata

Comparison

17.10.18 | Optionale Zusatzinformationen30

Alternative solution

17.10.1831

Requirements for a pumpable & fast reacting resin

10/17/1832

ApplicationEasy and robust mixingGood pumping and penetration behaviorThixotropic effectFull rockbolt encapsulationAdjustable to varying installation requirements

PerformanceFast strength developmentAdequate final strengthComply with existing EHS regulations

MasterRoc MP 368 compact PUS for consolidation with very fast strength developmentAreas of application

Reinforcement of fractured coal and rock strata

Consolidation of fractured rock, debris and tunnel faces

Sealing against gas and water

Features and key benefits

Very fast reacting

High bond strength

Fire-resistant and low reaction temperature

For temporary and permanent application

Works under water (no reaction with water)

Cured material remains flexible

The needs

Resin cartridge based anchor system

• Inconsistent quality due to challenging installation and mixing

method

• Limited resin quantity

• Not suited for broken and friable rock

Weakness

• “Simple” installation

• No additional equipment needed

• Pre tensioning possible

Strength

Thixotropic rock bolting resin

• Low viscosity for easy mixing and consistent grout quality

• Thixotropic performance for roof bolting

• Fast strength development to provide immediate support

• Suitable for competent and broken rock strata

• Always fully encapsulated rockbolt (better load transfer)

• Existing cracks in the strata are filled and consolidated

• Automated application possible

Features and benefits

R&D Shanghai

First pumping trials with different formulations

Rockbolt resin approval testing @ DMT Germany

Testing & resultsRockbolt pull test – bolt failure 350 kN

TestingFast reacting pumpable resin

Extensive testing @ Trostberg 2017/2018

MasterRoc RBA 380Thixotropic rockbolt resin

17.10.1841

Rockbolt installationFast reacting pumpable resin

10/17/18 | Optionale Zusatzinformationen42

Rockbolt installationFast reacting pumpable resin

10/17/18 | Optionale Zusatzinformationen43

Mixing of pumpable resin QC check possible by operatorAlways sufficient mixing is leading to improved load transfer between bolt and strataVarying borehole diameter & length and cracks don’t have an impact on the encapsulationOptimal ratio between borehole & rockbolt diameter = fast drilling possibleThixotropic behavior of resin = no borehole sealing neededFully encapsulated rockbolt

Ideal load transfer between rockbolt and strataImproved corrosion protection

Fast curing allows fast reentry timeCuring time adjustableWorks in temperature ranges between 5°C and 35°CShelf life 12 month if stored between 0° - 30°CNo aging of the cured product

Rockbolt installationVarying conditions

10/17/18 | Optionale Zusatzinformationen44

Rock & underground temperatureRock strata

Crack distributionSurface frictionStrength

Borehole diameter and lengthRockbolt

LengthDiameterSurface

MasterRoc RBA 38X

17.10.18 | Optionale Zusatzinformationen45

Features and benefits

Highly reactive, fire resistant thixotropic polyurea silicate injection resin for rock bolting

Secure and precise injection due to its thixotropic properties

Flexibility in application due to its unique thixotropic properties and long distance pumping capacity

Increased reliability due to its full-size grouting

Mixes easily even in low temperatures > 5°C

High structural strength combined with flexibility

Neither expands its volume with water, nor absorbs water

Keep people safe during bolting due to its fast curing and strength development

17.10.18 | Optionale Zusatzinformationen46

One-step vs. two-step

17.10.18 | Optionale Zusatzinformationen47

Customer benefit

17.10.18 | Optionale Zusatzinformationen48

Comparison pumpable resin vs. cartridgesRockbolt installation

10/17/18 | Optionale Zusatzinformationen49

Installation speed 2,50 m bolt (bolt installation only, without drilling)

CartridgesTo insert cartridges 30 sec – 10,0 min

bolt installation and mixing 45 sec

Curing time fast cartridge 45 – 60 sec

Total = 2 – 5 min

Pumpable resinAutomated bolt installation 30 sec – 1 min possible

Cartridges vs. Pumpable resins corosion

10/17/1850

Why to change?Cartridges vs. pumpable resin

17.10.18 | Optionale Zusatzinformationen51

Increase in tunnel development rateFaster reentry timeMore efficient use of equipmentLess mine personal

Higher mine productivityTunnel development = bottle neck forproduction

Improved strata controlLess cost for maintenanceMore efficient use of support

Rockbolt installationFast reacting pumpable resin

10/17/18 | Optionale Zusatzinformationen52

Mixing of pumpable resin QC check possible by operatorAlways sufficient mixing is leading to improved load transfer between bolt and strataVarying borehole diameter & length and cracks don’t have an impact on the encapsulationOptimal ratio between borehole & rockbolt diameter = fast drilling possibleThixotropic behavior of resin = no borehole sealing neededFully encapsulated rockbolt

Ideal load transfer between rockbolt and strataImproved corrosion protection

Fast curing allows fast reentry timeCuring time adjustableWorks in temperature ranges between 5°C and 35°CShelf life 12 month if stored between 0° - 30°CNo aging of the cured product

Rockbolt installationVarying conditions

10/17/18 | Optionale Zusatzinformationen53

Rock & underground temperatureRock strata

Crack distributionSurface frictionStrength

Borehole diameter and lengthRockbolt

LengthDiameterSurface

Current challenges in tunnel development in miningDirect cost

10/17/18 | Optionale Zusatzinformationen54

Times in a development cycleBlast hole drilling x minBlast hole charging x minBlasting x minScaling x minBolt drilling & installation (+mesh) x min (>50%)Muck haulage x minSprayed concrete (optional secondary support)

Customer statementEpiroc/BASF workshop

17.10.18 | Optionale Zusatzinformationen55

Hello gentlemen,

I'd like to thank you once again for providing such a top notch experience detailing the advancements you've made to the Boltec product line.

The resin grout system you created will be a game changer in terms of this rigs ability to operate in ALL types of ground conditions. I've been waiting many years for this solution. You continually seek to improve what is already a stellar rig making it safer and more productive. ……..Looking forward to continue changing the way the mining industry looks at the bolting process. You ll probably need to get more space to build more rigs!! Take care.

Bernie WhitmellMOB [email protected]

Solving your Challenges in Tunneling and Mining

Partiell vs. fully encapsulated rockboltsRockbolt corosion

10/17/18 | Optionale Zusatzinformationen66

10/17/18 | Optionale Zusatzinformationen67

Field trialsGosowong Kencana mine

10/17/18 | Optionale Zusatzinformationen69

Field trialsGosowong Kencana mine

10/17/18 | Optionale Zusatzinformationen70

Field trialsGosowong Kencana mine

10/17/18 | Optionale Zusatzinformationen71