01338525

Embed Size (px)

Citation preview

  • 8/11/2019 01338525

    1/5

    2004

    IEEE Intemational Conference on

    Electric

    Utility Deregulation, Restructuring and Power Technologies (DRPT2004)

    April

    2004 Hong Kong

    Generate new relay settings

    Intelligent Method for Protection Coordination

    C.W.

    So,

    Member,

    IEEE,

    K.K. Li, Senior Member, IEEE

    Abstract:

    This paper presents the application of

    Artificial Intelligence in protection coordination. It can

    substantially improve the coordination of protection

    relay operations. The relay settings and coordination

    requirements are formulated into a set of constraint

    equations and an objective function is developed to

    manage the relay settings by the Time Coordination

    Method TCM). Modified Evolutionary Programming

    MEP) is employed to search for the optimum relay

    settings with maximum satisfaction of coordination

    constraints. The results show that the intelligent

    method for protection coordination can optimize the

    protection relay settings, reduce relay mis-coordinated

    operations, and increase supply reliability. The

    efficiency of TCM taking the fault current changes

    into consideration is also discussed in this paper.

    Index Terms - Protection Relay Coordination, Time

    Coordination Method, Power System Reliability.

    I. INTRODUCTION

    A modem protection system consists of various types

    of protective relays, which functions

    to

    detect and isolate

    system abnormalities swiftly. For various voltage level,

    the various combinations of main and backup relays are

    installed to provide complete protection to various power

    apparatus. The main protection relay works in unit

    protection principle and removes in-zone fault instantly.

    The backup protection relay is designed to backup the

    main protection relay in case it fails. The overcurrent relay

    is

    a major type of backup protection relay. As it is non-

    unit protection, it is discriminated by their operating time,

    which forms a sequence of backup relay operations for the

    unclear system fault. Any incorrect operation of the

    backup relays will result in a large area of supply

    interruption

    [11

    as well as decreasing the supply reliability.

    The backup protection relay coordination is thus necessary.

    It ensures that the fault clearance actions are in correct

    sequence and minimizes the supply interruption. As the

    power system is changing from time to time, the

    coordination work should be carried out upon any

    significant change in power system configurations [2].

    Based on the communication ability equipped in modem

    digital relay, the coordinated relay settings can be

    downloaded through the communication network. The

    Time Coordination Method (TCM), which formulates the

    coordination of relay settings into a set of constraint

    equations and an objective function, is proposed in [3] to

    The authors would like to thank The Hong Kong Polytechnic

    University for supporting the research and publishing this work.

    C.W.

    So (e-mail: paulsot~~comnuter.or~)s currently working in

    a PhD project with the Hong Kong Polytechnic University. Dr. K.K.

    Li

    (e-mail: [email protected],hk) is with the Dcpartment of Electrical

    Engineering, Hong Kong Polytechnic University, Hong Kong.

    manage the relay settings. In distribution network, the

    major backup protections are Inverse Definite Minimum

    Time Lag (LDMTL) overcurrent and earth fault relays.

    Their operations depend on the fault current magnitude.

    Thus, the relay operation is affected by the change

    of

    fault

    current magnitude [7]. In fact, any unclear fault will be

    cleared by the backup relay operations. Any circuit

    breaker operation will result in changes in fault current

    distribution and magnitude experienced by backup relays.

    In order to boost the performance, the TCM must be able

    to handle a reasonable number of fault current changes.

    This paper shows how the TCM can significantly improve

    the supply reliability and reduce relay mal-operations.

    11. PRINCIPLES

    OF

    TIMECOORDINATION METHOD

    (TCM)

    Initialize relay settings

    Objective value calculation I

    E No

    Fig. 1

    Time Coordination Method

    The process flow chart of the TCM is shown in Fig 1.

    It formulates the power network and protection system

    into an objective function and a set of constraint equations.

    The objective function in the TCM is shown in equation

    (1).

    where

    Ri

    is each relay operation time and regulated by a

    scale factor

    a.

    C y s the operation time difference for each pair of

    relays and regulated by a scale factor p

    CV,

    is the number of coordination constraint

    violations and regulated by scale factor

    x

    nd 6

    Note: Variable

    i,

    j and

    k

    are iterated for all possible

    system configurations.

    0-7803-8237-4/04/ 17.0002004IEEE

    378

  • 8/11/2019 01338525

    2/5

  • 8/11/2019 01338525

    3/5

    2004 E E E International Conference on Electric Utility Deregulation, Restructuring

    and

    Power Technologies (DRPT2004) April 2004 Hong Kong

    which will caused fault current changes. In the result

    section, the efficiency of the TCM with different number

    of fault current changes will be examined. The more

    number of fault current changes to be handled, the larger

    number of system configurations should be considered.

    The possible system configurations are considered as

    follows:

    For a fault in a particular busbar, the number of

    system configurations C to be studied due to the number

    of linesN in the system is:

    C=2N

    The number of system configurations C' if r out of N

    circuits will trip to isolate the fault is shown in equation

    (4).

    (3)

    i O

    In the sample system as shown in Fig 2, although the

    number of configurations is C=2 =256, but some rare

    system configurations may be ignored. If the maximum

    allowable circuit outages

    =

    3, the number of system

    configurations to process C' = C: +

    C:

    +C: +C:

    =

    93

    The processing time reduction due to the minimized

    system configurations is equal to 6 3 -36,3 . The

    effect of the reduced number of system configuration in

    constraint checking will be discussed in the result section.

    C 256

    During the constraint checking, the constraint

    violations are checked against whether the operation time

    difference between the upstream and downstream relays is

    smaller than the coordination margin [3,4]. The objective

    value is also calculated during constraint checking. One of

    the major objective of the TCM is the minimization of the

    number of constraint violations.

    V . RELIABILITYVALUATION

    The benefits of the TCM may be measured by the

    supply reliability indices. The basic principle of the supply

    reliability is presented by Billinton and Allan [9,10]. The

    effectiveness of protection relay operations contributed to

    the supply reliability [I

    11

    may be computed by the three

    classic calculations. The first class of reliability

    calculation is the stuck breaker and is shown in equations

    4) and 5).

    us b )

    = b rb

    4)

    (b)

    =

    b 5)

    Where

    A

    is the failure rate of stuck breaker.

    rb is the switching time to restore system due to stuck

    (b) is the supply b failure rate due to stuck breaker.

    Uv(b) s the supply b restoring time.

    The second class of reliability calculation is the

    breaker.

    busbar fault and is shown in equations 6) and (7).

    Where

    Afis the failure rate of busbar.

    rf

    is the repair time of busbar.

    (b) is the supply b failure rate due to busbar fault.

    Ub(b) is the supply

    b

    repair time.

    The third class of reliability calculation is the

    protection fault and is shown in equations

    8)

    and (9).

    U ,

    b)= f , r , 8)

    (9)

    Where

    A s the failure rate of the cable.

    r is the switching time of the cable.

    f

    s the probability of protection failure.

    AJb) is the supply b failure rate due to protection

    U,(b) is the supply

    b

    restoring time.

    fault.

    The resultant reliability of the supply b due to

    protection operation is shown in equations (lo),

    1 1)

    and

    (12).

    A b) = As@ + + ,(b) (10)

    [E]

    @)= Us@) Ub(b>4 Up@)

    r(b) =

    U(b)/A (b)

    Where

    (b)

    is the failure rate of supply

    b.

    U(b) is the repair time of supply b.

    r(b) is the mean duration of supply b interruption.

    The supply reliability for every supply busbar may be

    evaluated by simulating the busbar fault, stuck breaker

    and protection failure in each busbar. For instance, a

    single-phase-to-earth fault occurs at busbar bi, the

    protection relay operates according to the fault current

    distribution and resulting in busbar

    bj

    loss of supply

    (bifbj). The supply reliability of busbar bj should be

    updated according to equations (6) and (7).The protection

    failure and stuck breaker cases are also simulated by

    applying busbar fault on the circuit connected

    to

    the

    busbar and update the reliability indices by equations

    (4),

    9, 8) and 91). The resultant reliability indices will be

    the sum of all individual simulated reliability indices

    according to equations

    lo),

    (1 1) and

    (12).

    VI. SIMULATION RESULT N D DISCUSSION

    The relay information and system parameters of the

    sample distribution system are shown in Table

    1

    and 2

    respectively.

    380

  • 8/11/2019 01338525

    4/5

    2004

    IEEE

    Intemational Conference on

    Electric Utility

    Deregulation, Restructuring

    and Power

    Technologies DRPT2004)

    April

    2004

    Hong Kong

    Note: All per-unit (pu) values are based on 100MVA.

    Table 3: Si1

    The TCM can be set of different population size,

    number of generations and number of fault current

    changes. The results shown

    in

    Table

    3

    are used to

    determine the case for the best TCM performance.

    The contribution of constraint violations in objective

    value is proportional to the number of system

    configurations. Moreover, from the results, the number of

    constraint violations depends on the number of fault

    current changes, the comparison of the objective value is

    only valid for those cases with the same number of fault

    current changes, i.e. case 1 to 3 , 4 to 6, 7 to 9, 10 to 12, 13

    to 15 and 16 to 18. For cases 1 to 3, they have been

    checked based on no fault current change. The TCM then

    only checks the relay operations with single and three

    phase busbar faults at E31 to B7, i.e. 12 fault cases are

    being studied. In cases 16 to 18, the number of system

    configurations based on equation (2) for a fault in either

    busbar is

    c

    =

    2 c

    p

    = 219

    As there are six

    busbars in the system and two types of fault are simulated,

    a total of 219 x

    6

    x

    2

    = 2628 fault cases are to be studied.

    Thus, the number of constraint violations for cases 16 to

    18 are considerable larger than cases 1 to 13.

    When a busbar fault occurred, two or more tripping

    should be carried out by OC relay to isolate the fault

    completely. For cases 1 to 6, since the number

    of

    fault

    current changes is less than 2, they are impractical to

    implement. The number of constraint violations and the

    processing time per generation

    of

    cases 7 to 9 are less than

    cases 10 to 18. Case

    8

    has the smallest number of

    constraint violations. Case 14 has better reliability indices

    with 0.6160 f/yr and 1.2016 hr/yr. It implies that case 13

    to 15 has less chance in loss of supply due to relay mis-

    coordination. As the roll of distribution

    is

    to provide a

    reliable power network

    to

    customers, relay settings of case

    14 should be the best for retaining the supply reliability.

    The performance of MEP depends on the population

    size, the number of generations and the number of fault

    current changes. For cases 13

    to

    15, a better objective

    value occurs in case 14 for population size of 50 rather

    than case 13 or 15, similar behaviors occur in every three

    consecutive cases. It implies that population size of 100

    may be over-crowed, in which better protection settings

    are not easily to be selected to survive during the selection

    process in

    MEP.

    VII. CONCLUSION

    r O

    The TCM can make relays more intelligent and adapt

    to the system configuration. The supply reliability can be

    improved by reducing the number of mis-coordinated

    relay operations. The setting of the TCM with different

    number of fault current changes is examined. The result

    shows that better improvement of supply reliability do not

    occur in larger number of fault current changes. It implies

    that the unrealistic number of fault current changes will

    cause the TCM to over-test the system and the TCM force

    the protection relays to handle those unrealistic system

    configurations.

    VIII. REFERENCE

    [l ]

    R.P.

    Graziano,

    V.J.

    Kruse, G.L. Rankin,

    Systems Analysis of Protection System Coordination:

    A

    Strategic Problem for Transmission and Distribution

    38

  • 8/11/2019 01338525

    5/5

    2 0 0 4 IEEE I n t e ma t i ona l Conf e r e nc e o n E l e c tr i c U t il i t y D e re gu l a ti on , Re s t r uct u r i ng a nd P ow e r T e c hn o l og i e s ( D RP T 2 004)

    April

    2 0 0 4 H o n g K o n g

    Reliability, IEEE Transactions on Power Delivery, Vol.

    7, NO. 2, pp 720-724, April 1992.

    [2] William J. Ackerman, Substation Automation

    nd the EMS, I999 IEEE Transmission and Distribution

    Conference, April 1999,

    Los

    Angeles, USA, Vol.

    1,

    pp.

    [3] C.W.

    So,

    K.K. Li, Time Coordination Method

    for Power System Protection by Evolutionary Algorithm,

    IEEE Transactions in Industry Application,

    Vol. 36, No. 5,

    [4] C.W. So, K.K. Li, K.T. Lai, K.Y. Fung,

    Application of Genetic Algorithm for Overcurrent Relay

    Coordination, IEE Ih International Conference on

    Developments in Power System Protection, Nottingham,

    UK, March 1997, pp. 66-69.

    [5 ]

    R. Salomon, Evolutionary Algorithms and

    Gradient Search

    :

    Similarities and Differences, IEEE

    Transactions on Evolutionary Computation,Volume 2, pp

    [6] C.W.

    So,

    K.K. Li, K.T. Lai, K.Y. Fung,

    Overcurrent Relay Grading Coordination Using Genetic

    Algorithm, IEE APSCOM-9 7 International Conference,

    Hong Kong, Vol.

    1,

    pp. 283-287, November 11-14, 1997.

    [7] C W

    So,

    K K Li, Overcurrent Relay

    Coordination by Evolutionary Programming, Journal of

    Electric Power System Research,

    Volume 53, pp 83-90,

    2000.

    [8] A. E. Eiben, R. Hinterding, and

    Z.

    michalewicz,

    Parameter Control in Evolutionary Algorithms,

    IEEE

    Transactions on Evolutionary Computation,Volume

    3 ,

    pp

    [9] R. Billinton, and R.N. Allan, Reliability

    Evaluation of Engineering Systems: Concepts and

    Techniques, Plenum Press, New York, USA, 2dEdition,

    1992.

    [101R. Billinton, and R.N. Allan, Reliability

    Evaluation of Power Systems, Plenum Press, New York,

    USA,

    2d

    Edition, 1996.

    274-279.

    Sqt/ Oc t 2000, pp. 1235-1240.

    45-55, July 1998.

    124-141, July 1999.

    C11lJ.J. Meeuwsen,

    W.L

    Kling, S.P.J. Rombouts

    The influence of protective relay schemes on the

    reliability indices of load points in meshed operated mv

    networks,

    I rH International Conference and Exhibition

    on Electricity Distribution, Part

    1:

    Contributions, Congres

    International des RCseaux Electriques de Distribution

    (CIRED), June 1997, IEE Publication

    No.

    438, Vol;. 4, pp.

    14/1-14/5.

    IX.

    BIOGRAPHIES

    C.W.

    So

    rcceived the BEng and PhD degree from

    the Hong Kong Polytechnic University in 1996

    and

    2001

    respectively. He is working as an

    Engineer in CLP Power Ltd. in Hong Kong,

    responsible for Protection and Substation

    Automation. His rescarch interest is power

    system protection, the applicahon of artificial

    intelligent, substation automation and power

    system computer programming

    K. K. Li received the M.Sc. and the Ph.D degree

    from the University of Manchester Institute of

    Science and Technology, Manchester, U.K., and

    City University, London, U.K. He is currently an

    Associate Professor in the Department of

    Electrical Engineering, Hong Kong Polytechnic

    University, Hong Kong. His research interests

    are power systcm protection and I applications

    in power systems.

    382