25
!"#$%&'( *%+,$'--.%( /,,0.123%( %4 56' 7.('2$ 8%5%$ 9'1.,$%123(& *%+,$'--%$ :789*; June 7, 2016 Buddy Broerman (PI) Jeffery Bennett (Co-PI) Norm Shade Southwest Research Institute ACI Services Project ID: PD108 This presentation does not contain any proprietary, confidential, or otherwise restricted information

0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

!"#$%&'()*%+,$'--.%()/,,0.123%()%4)56')7.('2$)8%5%$)

9'1.,$%123(&)*%+,$'--%$):789*;)

June 7, 2016

Buddy Broerman (PI) Jeffery Bennett (Co-PI) Norm Shade

Southwest Research Institute ACI Services

Project ID: PD108This presentation does not contain any proprietary, confidential, or otherwise restricted information

Page 2: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Timeline Barriers

• ACI ServicesPartners

Overview

• Total Project Budget: $2,284,553• Total Cost Share: $459,160• Total Federal Share:

$1,825,393• Total DOE Funds Spent*:

$624,690* As of 4/6/15, includes ACI’s March 2016 charges

Budget

Barriers TargetsLow CompressorEfficiency

>73% Isentropic Efficiency*

Capital Cost <$240,000 per compressor**

O&M Costs <$4,800 per year**

* DOE Project Target** Targets in the 2012 MYRD&D for 2020

Description Date / TimeframeProject Start Date 9/05/14Project End Date 10/04/17Project Duration 3.0 yearsProject Progress 1.5 years

06/07/2016 SwRI H2 Linear Compressor 2

Page 3: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Relevance• Project Objectives:

– Improve isentropic efficiency above 95% by minimizing aerodynamic losses• Low speed• High valve area ratio

– Reduce capital costs to half that of conventional reciprocating compressors by minimizing part count

– Reduce required maintenance by simplifying the compressor design to eliminate common wear items

• BP1: Analyzed and Designed LMRC to be tested in BP2 & BP3

• This Budget Period (Fiscal Year 2016, BP2):– Detailed Mechanical Design– Estimated Cost Projection for full-scale version– Designed Compressor Test Stand for LP Stage

06/07/2016 SwRI H2 Linear Compressor 3

Page 4: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Approach / Milestones

06/07/2016 SwRI H2 Linear Compressor 4

Fiscal Year 2015 – Design All 3 Stages

Milestone Description(Go/No-Go Decision Criteria)

Stage Sizing Provide cylinder size for each stage and accompanying

calculations.100

Basic Mechanical DesignProvide FEA results and analysis, basic structural design, and

material selection. 100

Linear Motor DesignProvide linear motor design, including required magnet size and

configuration of windings. 100

Bearing and Seal Design and Analysis

Provide selected bearing and seal technology and supporting calculations.

100

Valve Selection Provide the valve type that will be used for the proposed system. 100

Pulsation Control DesignProvide pulsation control design and/or techniques such that the

predicted piping system pulsations are at or below the amplitudes specified in the API Standard 618.

100

Cooling System Design Provide cooler sizes and cylinder cooling specifications 100

Materials and Coatings Selection Deliver material specifications and manufacturer availability 100

Performance Predictions and Comparison

Deliver performance predications and final CFD calculations 100

Task Title % Complete

Page 5: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Approach / Milestones

06/07/2016 SwRI H2 Linear Compressor 5

Fiscal Year 2016 – Fabricate and Test LP Stage

Page 6: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Accomplishments and Progress: Overall Concept & Test Loop

06/07/2016 SwRI H2 Linear Compressor 6

MRCForecourt Hydrogen Compression

CoolingWater

CoolingWater

IntakeManifold Discharge

Manifold

Hydrogen20 bar

Hydrogen875 bar

Stage 1PR = 3.56Pin = 20

Stage 2PR = 3.56Pin = 71

Stage 3PR = 3.56Pin = 248

Compress H2in 3 stages with LMRCs

Stage 1 P&ID

H2

20 bar

H2875 bar

Page 7: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Accomplishments and Progress: 3D Model: Piston Close-up

06/07/2016 SwRI H2 Linear Compressor 7

Ceramic Piston –2.557” OD

Guide Bushing

Seal Seal retainer & Bumper

Piston Retainer

Suction Valve

Discharge Valve

HE/CE Bypass

• Structural design created & FEA performed for each of the 3 stages• Materials selection is complete

3.0” Stroke

Page 8: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Accomplishments and Progress: 3D Model: Magnet/Coil Close-up

06/07/2016 SwRI H2 Linear Compressor 8

Magnets

Coils

Spacers

Central Casing

Piston Rod

Page 9: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

/11%+,0.-6+'(5-)2(#)H$%&$'--T''H21:+%0'G#:;'H#-%Q1JZ1:;2-%-'

06/07/2016 SwRI H2 Linear Compressor 9

Piston Path

Z'8&)'-8#,':1:;2-%-'&:-',#$X)$+#MT'LP! ].':1:;2-%-')X'-#:;'N1M#$'$:1Q#')X'

#b,#08#M',$#--N$#'0)1M%O)1-'8)'M#8#$+%1#'W)&'Q:,'-%U#'":$%#-'B'-#:;'M#X)$+-'

>P! R#21);Mc-'#dN:O)1'0)N,;#M'&%8W'-,$%1Q'$#,$#-#18:O)1')X'-#:;'8)',$#M%08'8W#';#:e:Q#'$:8#'

E$#M%08#M'-#:;';#:e'$:8#'%-':00#,8:S;#T'

kptfe kelgiloy

Finite-Element Model

Reduced Spring Model

I52&' J(#.B.#F20)I'20)7'2K)

925'):&?6$; J(#.B.#F20)I'20)7'2K)925'):E)%4)4F00)L%M;

N LPL @P@L O DP@ @P@D P 5K @P5K

Ceramic seal and tentatively a DLC poly seal are alternatives

Page 10: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Accomplishments and Progress: Valve Selection/Design

06/07/2016 SwRI H2 Linear Compressor 10

• Market search determined that major manufacturers do not have any products that fit the desired operating conditions

• ACI has experience designing and building replacement and custom compressor valves

• The compressor design has a low throughput & tight space constraints therefore a single poppet valve has

• been identified as a solution

• Stages 1, 2, and 3 valves are designed and fine-tuned with performance analysis

Page 11: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Upper Cylinder Head + Piston

Outer Casing

Inner Casing

External Pipe

Magnet + Spacer Assembly

Coil Pack

Lower Cylinder Head + Piston

Annulus

Accomplishments and Progress: LMRC Cooling System Design

Coil cooling• Average value of

560A will be traveling through the coils

• Therefore a conjugate heat transfer model (SINDA/FLUINT) was used to determine conditions required for adequate cooling

06/07/2016 SwRI H2 Linear Compressor 11

Page 12: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Accomplishments and Progress: Performance Prediction/Control Scheme

Original Valve New Valve

Max Force

Scheme(22 cps)

Custom Scheme(6 cps)

Isen. Eff73%

Isen. Eff88%

Isen. Eff89%

1st StageIsen. Eff

99%

Position vs Time

Position vs Time

Target is > 95%

97% 2nd Stage, 97% 3rd Stage06/07/2016 SwRI H2 Linear Compressor 12

Page 13: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Accomplishments and Progress: System Efficiency and Specific Energy

06/07/2016 SwRI H2 Linear Compressor 13

• LMRC predicted efficiency & specific energy: – 20% overall 3 stage (and 20% per stage) – 9.2 kWh/kg overall (2.8 to 3.5 kWh/kg per stage)

• Could be > 90% by implementing design improvements – Move coils to inside of casing.– Locate coils as close as possible to the magnets.– Increase # of rows of coils (predictions indicate this is only

useful after moving coils closer to magnets)– Use superconducting coils. (This may require complex

additional system to keep the coils super cold.)– Further optimization of control scheme.

• ~1.3 kWh/kg is expected with advanced LMRC actuator design & 100 bar inlet pressure (1.6 is 2015 MYRDD target)

Page 14: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Accomplishments and Progress: Full Scale (100 kg/hr) Cost and Life Estimates

06/07/2016 SwRI H2 Linear Compressor 14

Conventional Reciprocating Compressor Technologies LMRC

Seal Life 12-18 months 48 months (ceramic)*

Packing Life 3 years Infinite (NO PACKING)

Valve Life 1-3 years 4 years

Isentropic Efficiency

2015 goal > 73%, 2020 goal > 80% 80% for all 3 stages in series

O&M Cost 2015 goal < $10,000/year, 2020 goal < $4,800 $3,300 / year

Mnfactr Cost 2015 goal < $400,000, 2020 goal < $240,000 $284,000**

2015 and 2020 goals are from the 2012 MYRD&D plan per the goals of the project contract* Assumes operation time is ~1/4 of a 24 hour day** Includes inter-stage piping and coolers. Assumes ~100 units built per year. 2007$ like targetsThe most understood path to 100 kg/hr was used. Larger may be better, but harder to quantify. Also, overall system efficiency gains (design change) should significantly reduce the cost per LMRC.

• 3 LMRCs in parallel per stage = 9 LMRCs total• operating at ~930 cpm with ceramic seals

Page 15: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Accomplishments and Progress: Test Loop Design

06/07/2016 SwRI H2 Linear Compressor 15

• After review of OSHA, Occupancy classification letter filed with City of San Antonio, and SwRI requirements, test stand will be located outside building with required electrical supply

• P&ID• 3D model

Page 16: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Accomplishments and Progress: Responses to Previous Year Reviewers’ Comments

• Cost analysis requested – Described in a previous slide• Flow rate questioned – Calculations described in

quarterly reports• Thermal management questioned– Described in a

previous slide• H2 inside of magnets chamber? – Yes, intentionally• Dynamic seal leak rate questioned – predictions

acceptable per detailed analysis• Control system required to manage power delivery

questioned – power controller from electric automotive industry

06/07/2016 SwRI H2 Linear Compressor 16

Page 17: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Collaborations• DOE – Sponsor, Steering• SwRI – Project lead, design, location for testing• ACI Services – Overall project partner, lead for

mechanical design, fabricator of some parts• Thar Energy – Project partner, seal and ceramic

piston design• Dexter Magnetic Technologies – Neodymium Iron

Magnets• TechniCoil – Coils and winding• Enterprise Power Corp. – Power

Supply/Controller

06/07/2016 SwRI H2 Linear Compressor 17

All major suppliers/manufacturers are in the USA

Page 18: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Remaining Challenges and Barriers

• Challenge: Seal life• Resolution: Ceramic seal and tentatively a DLC

poly seal are alternatives• Challenge: Maintaining budget• Resolution: Weekly budget re-evaluations and

borrow test equipment to leverage benefit of large SwRI testing community

• Challenge: Full scale production cost target • Resolution: Investigate further the possibilities

of increasing the LMRC size instead of speed & numbers

06/07/2016 SwRI H2 Linear Compressor 18

Page 19: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Proposed Future Work

1. Parts Fabrication2. Test Loop Construction3. Commissioning4. Testing5. Data Analysis6. BP3 – Fabricate stages 2 and

3 then test stages 2 and 3 in series with stage 1

06/07/2016 SwRI H2 Linear Compressor 19

Page 20: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

GN++:$2'•! YEL'0)+,;#8#'q'G8:Q#'L')"#$:;;'M#-%Q1'0)+,;#8#'•! ./0%#102',$#M%0O)1-'Q$#:8#$'8W:1'IK6'•! ]:S$%0:O1Q':1M',N$0W:-%1Q',:$8-J0)+,)1#18-'•! *N$$#18;2'1)'8#0W1%0:;J0)++#$0%:;')ta$:+,'%--N#-'%M#1Og#M'

06/07/2016 SwRI H2 Linear Compressor 20

YNMM2'Y$)#$+:1A'G$P'R#-#:$0W'.1Q$P'.Y$)#$+:1u-&$%P)$Q''

>L@aK>>a>KKK'v#t#$2'Y#11#pA'R#-#:$0W'.1Q$P'v#t$#2PY#11#pu-&$%P)$Q''

>L@aK>>a54_L'

h)$+'GW:M#'G#1%)$'*)1-N;8:18A':1M'E$#-%M#18'

.+#$%8N-'hGW:M#u:0%-#$"%0#-%10P0)+'\4?@`'?5Ka@>?@'#b8P'K@?'

84”

wN#-O)1-s'

Page 21: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Technical Backup Slide

06/07/2016 SwRI H2 Linear Compressor 21

Stage Max. InternalOperating Press.

(psig)

Temp. Range

(˚F)Size (in.)

Material Manufacturer Durometer(Shore A)

1 1,125 -15 to 400

3/32 V1238-95Fluorocarbon

Parker Hannifin

95

2 4,101 -15 to 400

3/32 V1238-95Fluorocarbon

Parker Hannifin

95

3 14,069(inner seal**)

-15 to 400

1/8 Inconel 718 w/gold plate

Parker Hannifin

NA

Seal Selection Criteria:1. Face seals with zero gap for all primary & secondary (back-up) seal locations2. Impermeable & resistant to 100% hydrogen gas3. Explosive decompression resistant

Approved by T. Anderson; Application EngineeringParker Hannifin O-Ring Division

** outer seal will be V1238-95 Fluorocarbon due to lower pressures

1st stage (typical)

Central Casing

Page 22: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Technical Backup Slide

06/07/2016 SwRI H2 Linear Compressor 22

Materials selected for each of the compressor components, and the significant mechanical and physical properties for each

Page 23: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Technical Backup Slide: Actuator

Design

06/07/2016 SwRI H2 Linear Compressor 23

R vessel=2.125”

Thk gap=0.04”

Thk vessel=0.36”

No sleeveAny longer

Thk=0

R outer mag=2”

Thk flux Return

(same material as spacers!)

=1/2”

Thk insulation=0.665 mm

Coolant hole diameter=3.1 mm

Coil width=6.5 mm

Each coil pack:12 row x 4 columns

Coil support thk:¼”

Spacer height:0.725”

(adjusted to matchperiodicity of coils)

Magnet height:3”

R shaft(varies)

centerline

R inner flux return=9.3 cm

Page 24: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Technical Backup Slide

06/07/2016 SwRI H2 Linear Compressor 24

Control panel for developing control schemes while simulating LMRC motion and predicting performance

(+ many other system characteristics)

Page 25: 0.123%()%4)56')7.('2$)8%5%$) 9'1.,$%123(&)*%+,$'--%$) :789*;) · 2016-06-17 · material selection. 100 Linear Motor Design Provide linear motor design, including required magnet

Seal-Sapphire COF Determination

It was determined through pin-on-disk testing that the coefficient of friction (COF) for sapphire on PEEK is 0.15

Due to the higher than expected COF, two other seal options are planned for testing

Poly seal with DLC

Sapphire or ceramic seal (~0.0001”-0.0005” clearance)

06/07/2016 SwRI H2 Linear Compressor 25