010-158-42395 Flood Risk Assessment

Embed Size (px)

Citation preview

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    1/48

    GEOENVIRONMENTAL

    CONSULTING ENGINEERS clarkebond

    Completed by: Andrew Crewdson Page 1of 8 Date: 01 October 2007

    FLOOD RISK ASSESSMENT

    SITE: H17 Newtown Road, Highbridge Project No: EE00431NGR: 331400, 147350 Revision: C

    CLIENT: Gaia Partnership Date of Revision: 01/10/07

    AREA LIABLE TO FLOODING

    The site lies within the Environment Agencys indicative flood risk areas for Zone 2 and 3.

    The proposed site is part of the H17 residential allocation included in Sedgemoor DistrictCouncils development framework. The site lays approximately 100m to the north of the tidalestuary of the River Brue. The Brue reaches the sea at Highbridge, 1500m to the west. Thecourse of the Brue has been altered and straightened over the years upstream of the site.The current tidal limit is immediately to the south of the site at the sluices at New ClyceBridge.

    To the north and east of the site are residential properties. To the south is a boat buildingyard and housing, to the west is a wastewater treatment works with the Apex Leisure Parkcontaining several lakes and a caravan park on land further to the west. The Brue catchmenthas an area of approximately 259km2 and is predominantly wetland within the SomersetLevels.

    The existing site varies in level from 5.6 to 6.8mAOD. The existing topographical survey hasbeen tied into Ordnance Datum from the benchmark on New Clyce Bridge. The total sitearea is approximately 27120m2. The site falls away from the River Brue towards theresidential dwellings alongside the northern boundary.

    An earth bank tidal defence, which runs along the southern and western boundaries, defendsparts of the area, such as the Sewage works to a level varying between 8.45m and 8.60mAOD. On the southern boundary of the site there is a raised parcel of land that reaches8.00mAOD.

    To the east of the site on Huntspill Moor the River Brue is linked to the manmade HuntspillRiver, dug in the 1940s, and to the south by an artificial channel known as Cripps River. TheHuntspill and Cripps rivers were built to improve drainage of the area.

    The attached drawing EE00431/Fig01 shows the site location.

    The attached drawing EE00431/Fig02 shows the existing site topographical survey, andpredicted flood extents.

    The drawings are included in Appendix A.

    A copy of the EA flood map is included in Appendix B.

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    2/48

    GEOENVIRONMENTAL

    CONSULTING ENGINEERS clarkebond

    Completed by: Andrew Crewdson Page 2of 8 Date: 01 October 2007

    FLOOD RISK ASSESSMENT

    SITE: H17 Newtown Road, Highbridge Project No: EE00431NGR: 331400, 147350 Revision: C

    CLIENT: Gaia Partnership Date of Revision: 01/10/07

    PROBABILITY OF FLOODING AND POTENTIAL CHANGE

    The impact of urban development and land use change on the River Brue is likely to beminimal, particularly in view of recent policies such as PPG and PPS25 aimed at reducingsuch impacts.

    The Environment Agency have stated that there is a maximum fluvial 1 in 100 year level of5.0mAOD for the River Brue because of the interlinked watercourses and wetland areasupstream of Highbridge. Due to the Highbridge Sluice there is no tidal influence on the Brueupstream of Clyce Bridge. The River Brue is therefore highly unlikely to have any majorflood influence on the site but will need to be considered if any surface water drainageoutfalls are considered to the Brue.

    EXTENT AND STANDARD OF FLOOD DEFENCES

    An earth bank currently defends western parts of the site, which is part of the EnvironmentAgencys tidal defence scheme for Highbridge. The bank varies in level between 8.60 and8.54mAOD over a distance of approximately 290m.

    An additional bank running along the southern boundary provides some further defence at alevel of 8.14m AOD.

    The lowest point in the area exposed to tidal influence is at 7.81m AOD, or 50mm short ofthe 1 in 200 year predicted flood level.

    This defence level of 7.81m equates to an approximate return period of 1 in 150 years fortidal flooding.

    LIKELY DEPTH OF FLOODING

    1 in 200 Year EventThe 1 in 200 year still water level in the tidal Brue for Highbridge has been agreed with theEnvironment Agency as 7.86mAOD.

    Behind the existing defence at 7.81m the ground drops away to a low-dished area with aninvert of approximately 7.20m. The perimeter of the dished area has a level of 7.59m and aplan area of 2347m2.

    Any flows overtopping the 7.81m level would flow east into this dished area and impound upto a level of 7.59m, before then flowing north, east and south into existing areas ofdevelopment. This dished area has an approximate storage volume of 445m3.

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    3/48

    GEOENVIRONMENTAL

    CONSULTING ENGINEERS clarkebond

    Completed by: Andrew Crewdson Page 3of 8 Date: 01 October 2007

    FLOOD RISK ASSESSMENT

    SITE: H17 Newtown Road, Highbridge Project No: EE00431NGR: 331400, 147350 Revision: C

    CLIENT: Gaia Partnership Date of Revision: 01/10/07

    Using the design flood level of 7.86m and the existing defence level of 7.81m a tide wouldspill over the low spot for just under 14 minutes based on tide curves derived from HinkleyPoint gauging station. The width of the spill is between 4.5 and 5.0m with cross sectionalflow area varying between 0.0m2 and 0.14m2. Assuming the tide is travelling at a rate of0.5m/s calculates out as a total volume of 28.3m3 travelling through the lowest point.

    From this it can be seen that no flood water would enter this site, part of the H17 allocation,

    during a 1 in 200 year tide event. The full tidal overtopping calculations are included inAppendix C.

    1 in 200 Year + 30% Climate Change EventTo allow for potential rises in tide levels initially an additional 0.40m was added to the 1 in200 year tidal level and a further 0.30m for freeboard giving a 1 in 200 year + climate tidelevel of 8.56m AOD for any earth flood defences.

    Further work to revise the climate change allowances following publication of PPS25 hasnow been undertaken. We have calculated a revised tidal design level of 8.87mAOD for2110 to cover a development life span of 100 years.

    We have carried out an assessment of existing ground levels within the Highbridge /Burnham area to create some contouring of the surrounding area. These contours areshown on EE00431/Fig5 and Fig6. We have then assumed that we will construct the Phase1 development including our flood alleviation proposals and that the land to the south ofPhase 1 (Boatyard site) will be raised to 8.90m. Any overtopping floodwater passing alongthe south side of the site, will still run through Smith Way, Sparks Way and out into NewtownRoad before heading north toward Newtown Lake.

    To assess the maximum volume of flood water that the tide could generate we have drawnup a series of spill profiles to match the predicted tide curve level and calculated the possibleflow area available through each cross sectional area of the spill.

    If tide levels were to reach the level of 8.87m, spilling through the area with the lowestground levels between 8.11 and 7.81mAOD there would be approximately 150,000m3 ofwater entering into the Highbridge area over the spill length of 70m. This tidal volume isbased on a single tide cycle in just over 1 hours of flow between 0.76 and 1.06m deep.

    We have considered 3 tide cycles passing over this spillway and a total volume of floodwaterof 450,000m3 dispersed in the Highbridge/Burnham area.

    The lowest areas immediately to the north of the site are at 5.2m, rising to 5.5m. At 5.5mfloodwater would start to enter the northern side of the site, as the low-lying areas below5.5m will have filled. Therefore using the 5.5m contour area as a storage pond level (less a20% allowance for buildings) we have calculated the maximum impounding level of 3 tide

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    4/48

    GEOENVIRONMENTAL

    CONSULTING ENGINEERS clarkebond

    Completed by: Andrew Crewdson Page 4of 8 Date: 01 October 2007

    FLOOD RISK ASSESSMENT

    SITE: H17 Newtown Road, Highbridge Project No: EE00431NGR: 331400, 147350 Revision: C

    CLIENT: Gaia Partnership Date of Revision: 01/10/07

    cycles by dividing the total flood volume in 3 tide cycles (450,000m3) by the potential storagearea (221.04ha). This equates to a total water depth of 200mm, or a level of 5.70mAODwithout any allowances for draw down by the highway and surface water drainage network orthe volume of storage available below the 5.5m contour.

    At the entrance to the site off Newtown Road the existing ground level is at 6.40m, wepropose to raise the access road up to a level of 7.65m as soon as highway designstandards permit (approx 15m distance). This will be 1.25m above the existing ground level

    to the south of the site where flood flow depths would be up to 1.1m deep based on our flowpath/depth analysis. Then the access road or site level would rise up further to a level of8.90m along the southern site frontage to provide an engineered flood defence at point 3 onour development option layout. Alternatively if the access road follows a more northerlyroute along the old railway line then the site frontage levels will be raised to a similar profile.This raised defence area would be constructed, as a minimum width of 5m to ensuresurcharging by floodwater did not cause a breach failure.

    The width of flow available through the housing area varies between 40 and 70m and weestimate that the flow depth through this area would vary between 1.0 and 1.3m because ofthe housing layout. By adopting the proposed levels on the southern boundary shown ondrawing EE00431/Fig4C we would ensure that the proposed site frontage is always at least1.4m above the existing ground levels along the boundary with Smith Way / Sparks Wayhousing area.

    On this basis if the remainder of the Phase 1 site area to the rear of the proposeddevelopment option defences were raised to a minimum of 6.5m, floodwater would not enterthe Phase 1 development area.

    MHWS tide is approximately 5.80m AOD.

    The site is generally not at risk from waves or storm surges due to its distance inland, butshould it occur there is 300mm freeboard above the 1 in 200 year + climate change tidallevel.

    EFFECTS OF CLIMATE CHANGE

    The impacts of climate change on the hydrological regime of the River Brue are not fullyknown. In general climate change in the west of England is expected to result in an increasein rainfall intensity and higher rainfall totals during the winter period. This might be expectedto lead to an increase in heavy rainfall events such as occurred in October and December2000 and July 2005.

    An additional 30% flow above the 1 in 100 year flow should be considered for climatechange, however the main flood risk in this location is tidal.

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    5/48

    GEOENVIRONMENTAL

    CONSULTING ENGINEERS clarkebond

    Completed by: Andrew Crewdson Page 5of 8 Date: 01 October 2007

    FLOOD RISK ASSESSMENT

    SITE: H17 Newtown Road, Highbridge Project No: EE00431NGR: 331400, 147350 Revision: C

    CLIENT: Gaia Partnership Date of Revision: 01/10/07

    Tide levels are predicted to increase due to climate change. Generally it is believed that tidelevels in the southwest will increase by 4mm a year. When combined with the rate thesouthwest peninsula is sinking a value of 5mm is used.

    Tide 1 in 200 year design tide level has been increased in line with Annex B of PPS 25 tocover a life span of 100 years.

    In a higher flood level tidal event flows would travel through the site north, east and south

    towards the existing development areas once the low ponding area was full.

    NATURE AND LIFETIME OF DEVELOPMENTAND EXTENT OF FLOOD PROOFING

    The site is currently defended to a 1 in 150 year return period tidal event, or 50mm short ofthe current 1 in 200 year design standard. It has been proven earlier that this part of the H17site would not flood in a 1 in 200 year tide event.

    The site defence only becomes substandard when climate change and freeboard allowancesare added onto the predicted still water tide levels, i.e. development could proceed as longas the defences were improved within the timescale of the development of the whole of the

    H17 allocation. Each landowner would need to deliver part of the defence scheme as part oftheir planning permission. To provide adequate flood protection to the whole of this sitewhen considering climate change the Environment Agency have agreed to the developmentoption as shown on Fig04. Refer to Fig04 for the reference locations:

    Phased Development OptionDue to land ownership constraints the H17 site will proceed in two phases, phase 1 being thenorthern part, phase 2 being the boatyard site. Phase 1 will provide a raised flood defence to8.90m between the existing EA defences at point 1, through point 2 finishing at point 3,currently at 6.85m within the site. To the east of point 3 ground levels would be rampeddown to the site entrance at a level of 6.40m. Closing of the gap through the boat yard wouldoccur when the boatyard is developed within the next 5 years.

    General Design Features

    The raised land on the southern boundary between points 1 and 3 could be used as part of aresidential unit or garden area. A typical sketch showing how this could work is included onFigure 4 as section A - A.

    Typically a minimum width of 5m of raised land is required as a defence before any buildingcan be located.

    If no buildings are to be used to back onto the earth defence then a width of 8m earthbanking should be used.

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    6/48

    GEOENVIRONMENTAL

    CONSULTING ENGINEERS clarkebond

    Completed by: Andrew Crewdson Page 6of 8 Date: 01 October 2007

    FLOOD RISK ASSESSMENT

    SITE: H17 Newtown Road, Highbridge Project No: EE00431NGR: 331400, 147350 Revision: C

    CLIENT: Gaia Partnership Date of Revision: 01/10/07

    Finished floor levels on the properties fronting the tidal defences in the west and southshould be set at 9.05m AOD. Other property in the north and eastern parts of the site shouldhave minimum floor levels 300mm above the local ground level.

    The proposed site access road from the east will have a landscape buffer on the south side,this will be shaped to form a dished channel to store and convey flood water to the eastalong the existing flood route in a climate change event. The road and landscape buffer

    design can be detailed to mirror the existing flood regime where flows travel to the easttoward the existing development if Option 2 is promoted. Once the boatyard is developedthis potential climate change flood route would be closed off.

    The attached drawing EE00431/Fig03 shows the proposed site layout.

    The attached drawing EE00431/Fig04 shows the flood proposals for Phase 1 of thedevelopment.

    Surface Water Run-off

    Greenfield and Brownfield run-off for the existing site was calculated using the IH124 andWallingford methods. Run-off was calculated as the following:

    Return Period Greenfield(l/s)

    Brownfield(l/s)

    1 in 2 year 1.9 195Mean Annual Flood 2.1 221.6

    1 in 100 year 5.2 471.9

    The maximum proposed site peak run-off based on the illustrative masterplan has beencalculated as follows:

    Return Period Developed site(l/s)

    1 in 2 year 196.9Mean Annual Flood 223.7

    1 in 100 year 477.1Climate Change 620.2

    Surface water run-off from the proposed development should be disposed of using SUDSTechniques if previous site use and ground levels permit. If a direct discharge to a

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    7/48

    GEOENVIRONMENTAL

    CONSULTING ENGINEERS clarkebond

    Completed by: Andrew Crewdson Page 7of 8 Date: 01 October 2007

    FLOOD RISK ASSESSMENT

    SITE: H17 Newtown Road, Highbridge Project No: EE00431NGR: 331400, 147350 Revision: C

    CLIENT: Gaia Partnership Date of Revision: 01/10/07

    than the existing run-off rate.

    There is sufficient capacity to connect into the existing Wessex Water surface water sewer tothe west of the site to achieve a direct tidal outfall. The land needed to complete theconnection is under the control of Gaia Partnership. A copy of the Wessex Water sewerrecords is included in Appendix B.

    If a direct discharge to the tidal estuary can be achieved then no reduction in the existingpeak flow or attenuation would be needed. Any outfalls through the existing / proposed tidal

    defence wall should be fitted with a flap valve and adequate storage provided within the siteshould the outfall become hydraulically locked during a tidal event.

    Pipe System

    Due to the location of the proposed development there will be issues with the outfall to theestuary becoming tide locked. Using the tidal curves in Appendix D it has been calculatedthat during the climate change event the system would be tide locked for a total of up to 360minutes.

    Using WinDes a maximum volume of 882.3m3 would be required to sufficiently store theflows from a 6 hour storm during a 100 year climate change event without flooding the site.

    This can be delivered by using a 1.2m x 260m Pipe with a 225mm orifice plate or pipecontrolling the outflow.

    The discharges from the proposed system are as follows:

    Pipe SystemReturn period Allowable

    run-off(l/s)

    Proposed post developmentpeak site run-off (l/s) and

    critical storm duration

    Control Measures

    2 year 196.9 65.3 (30min winter)30 year 374.6 82.3 (30min winter)

    100 year 477.1 91.3 (60min winter)Climate change 620.2 101.8 (60min winter)

    1.2m x 260m Pipewith 225mm Orifice

    Plate or Pipe

    We have therefore created a system with adequate storage in the event of a climate changetide locking event happening. Once the flows are able to discharge to the estuary, thesystem would be completely emptied within 150 minutes i.e. half the period of free flowingoutfall between tide lock. Discharge rates from the development have also been improved;with the 2-year event peak site run-off having been reduced by two thirds.

    All flap valves should be subject to regular maintenance to prevent floodwaters entering thesystem.

    See Appendix C for the IH124, existing Brownfield and proposed run-off calculations.

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    8/48

    GEOENVIRONMENTAL

    CONSULTING ENGINEERS clarkebond

    Completed by: Andrew Crewdson Page 8of 8 Date: 01 October 2007

    FLOOD RISK ASSESSMENT

    SITE: H17 Newtown Road, Highbridge Project No: EE00431NGR: 331400, 147350 Revision: C

    CLIENT: Gaia Partnership Date of Revision: 01/10/07

    OVERALL ASSESSMENT OF FLOOD RISK AND RECOMMENDATIONS

    The site does lie within the 1 in 200 year tidal zone.

    To mitigate the flood risk to the property and the occupiers the following should be put inplace as part of the planning proposals:

    Surface water run-off should be disposed of using SUDS Techniques includingpre-treatment of surface water run-off where ground conditions and ground waterlevels permit. After initial treatment a direct discharge to the tidal estuary can beachieved by connecting to a Wessex Water manhole to the west of the study areain land under control of the Gaia Partnership;

    A flood defence embankment wall is required to a level of 8.90m to alleviate tidalflooding on the site. This can be delivered in two parts linked to phased planningapplications given the current level of flood defence is so close to the 1 in 200year design event;

    Minimum finished floor levels to be 9.05m AOD in the south and west on the topof the flood defence bund and 300mm above ground levels locally in the northand east. Site ground level / parking behind the frontage tidal defences canremain at the existing ground levels.

    Any proposed outfalls are to be fitted with flap valves or similar to prevent theingress of flood waters, and should the valves become hydraulically locked duringtimes of high water, adequate storage should be provided to prevent the systemsurcharging. All flap valves should be subject to regular maintenance to preventfloodwaters entering the system.

    We recommend that the phased development option be constructed and that theplanning authority and EA use their powers to enforce delivery of the defencebetween points 1 and 8 on drawing EE00431/Fig4 when a planning application islodged on the boatyard site.

    Reviewed by Date RevisionN A Smith 03/11/06 Original issueN A Smith 06/11/06 AN A Smith 14/11/06 BN A Smith 01/10/07 C

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    9/48

    Appendix A

    Drawings

    Fig. 1 Site Location PlanFig. 2 Existing Site Layout, Topographical Survey and Existing Flood RegimeFig. 3 Proposed Site LayoutFig. 4 Proposed Flood Alleviation OptionsFig. 5 Flood Flows and StorageFig. 6 Enlarged Flow Regime at Site

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    10/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    11/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    12/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    13/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    14/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    15/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    16/48

    Appendix B

    Third Party Records

    EA Flood Risk MapWessex Water Sewer Records

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    17/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    18/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    19/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    20/48

    EE00431 - Newtown Road, Highbridge September 2007

    IoH 124 Greenfield & Existing Brownfield run-off

    IoH 124 Greenfield

    QBARrural = 0.00108 AREA0.89

    SAAR1.17

    SOIL2.17

    AREA (km

    2

    ) = 0.50SAAR* = 750

    SOIL* = 0.3

    Catchment area = 50.000 ha

    Total Site area = 2.039 ha

    Brownfield area = 0.958

    Greenfield area = 1.081

    MAF / QBAR Greenfield = 0.099 m3/s for 50 ha

    Windes Wallingford Procedure Brownfield flow

    0.958 ha - 2yr storm 195 l/s

    Summary

    Return Periods Growth factors Greenfield

    1.081ha Site

    area flow

    (m3/s)

    Brownfield

    0.958 ha

    site area

    flow (m3/s)

    Total

    existing site

    run-off

    (m3/s)

    Mean Annual Flood (MAF) 1.00 = 0.099 m3/s 0.0021 0.2216 0.2237

    1 yr 0.78 = 0.077 m3/s 0.0017 0.1521 0.1538

    2 yr 0.88 = 0.087 m3/s 0.0019 0.1950 0.19695 yr 1.23 = 0.122 m

    3/s 0.0026 0.2399 0.2425

    10 yr 1.49 = 0.147 m3/s 0.0032 0.2906 0.2937

    25 yr 1.84 = 0.182 m3/s 0.0039 0.3588 0.3627

    30 yr 1.90 = 0.188 m3/s 0.0041 0.3705 0.3746

    50 yr 2.12 = 0.209 m3/s 0.0045 0.4134 0.4179

    100 yr 2.42 = 0.239 m3/s 0.0052 0.4719 0.4771

    Climate Change 100yr+ 30% = 0.311 m3/s 0.0067 0.6135 0.6202

    Greenfield

    50 ha flow

    (m3/s)

    plus

    EE00431\IoH 124 Somerset.xls\IoH 124

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    21/48

    H17 Newtown Road, Highbridge

    Impermeable Area Impermeable Area Impe

    Proposed Site All Proposed Site Brownfield Pro

    Total site area = 27121 m2 Total site area = 8602 m2 Tota

    2.712 ha (Not all positively drained) 0.860 ha

    Roof Area 4710 m2 Roof Area 1228 m2 Roof

    0.471 ha 0.123 ha

    Imp % = 90 0.424 ha Imp % = 90 0.111 ha Imp %

    Block Paving 1442 m2 Block Paving 301 m2 Block

    0.144 ha 0.030 ha

    Imp % = 70 0.115 ha Imp % = 70 0.024 ha Imp %

    Access Road & Footpath 7496 m2 Access Road & Footpath 2136 m2 Acce

    0.750 ha 0.214 ha

    Imp % = 100 0.750 ha Imp % = 100 0.214 ha Imp %

    Greenfield contribution = 13473 m2 Greenfield contribution = 4937 m2 Gree

    1.347 ha 0.494 ha

    Imp % = 20 0.269 ha Imp % = 20 0.099 ha Imp %

    Total = 1.289 ha For Windes Design Total = 0.348 ha For Windes Design

    + 30% climate change = 1.547 ha For Windes Design + 30% c limate change = 0.418 ha For Windes Design

    Current Site Total Current Site Brownfield Cur

    Total site area = 27121 m2 Total site area = 19344 m2 Tota

    2.712 ha 1.934 ha

    Roof Area 4032 m2 Roof Area 1203 m2 Roof

    0.403 ha 0.120 ha

    Imp % = 90 0.363 ha Imp % = 90 0.108 ha Imp %

    Concrete 3605 m2 Concrete 3277 m2 Conc

    0.361 ha 0.328 ha

    Imp % = 90 0.324 ha Imp % = 90 0.295 ha Imp %

    Access Road + Parking 13514 m2 Access Road + Parking 11087 m2 Acce

    1.351 ha (50% Positively Drained) 1.109 ha (+50

    Imp % = 100 1.351 ha Imp % = 50 0.554 ha Imp %

    Greenfield contribution = 5970 m2 Greenfield contribution = 3777 m2 Gree

    0.597 ha 0.378 ha

    Imp % = 20 0.119 ha Imp % = 20 0.076 ha Imp %

    Total = 2.039 ha For Windes Design Total = 0.958 ha For Windes Design

    + 30% climate change = 2.446 ha For Windes Design + 30% c limate change = 1.149 ha For Windes Design

    AREAS Rev A.xls\AC Data

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    22/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 1

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB Brownfield 2yr Flow

    Date 28 September 07 Designed By AMC

    File Brownfield.sws Checked By

    Micro Drainage System1 W.10.4

    STORM SEWER DESIGN by the Modified Rational Method

    Network Design Table

    PN

    Length

    (m)

    Fall

    (m)

    Slope

    (1:X)

    Area

    (ha)

    T.E.

    (mins)

    DWF

    (l/s)

    k

    (mm)

    HYD

    SECT

    DIA

    (mm)

    1.000 10.00 0.100 100.0 0.958 2.00 0.0 0.600 o 375

    Network Results Table

    PN

    Rain

    (mm/hr)

    T.C.

    (mins)

    US/IL

    (m)

    E.Area

    (ha)

    E.DWF

    (l/s)

    Foul

    (l/s)

    Infil.

    (l/s)

    Vel

    (m/s)

    CAP

    (l/s)

    Flow

    (l/s)

    1.000 75.0 2.1 5.000 0.958 0 0 0 1.81 200 195

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    23/48

    Appendix D

    Tidal Calculations

    Hinkley Tidal Calculations 1 in 200 year eventTidal Inflow -1 in 200 year eventTidal Curve 1 in 200 year + 30% Climate ChangeTidal Inflow -1 in 200 year event + 30% Climate Change

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    24/48

    EE00431 - H17 Newtown Road, Highbridge FRA September 2007

    Date Time ACD ODN 1 in 200 year

    Peak of 7.86m

    10/03/01 00:15:00 1.464 -4.34

    10/03/01 00:30:00 1.173 -4.63

    10/03/01 00:45:00 0.928 -4.87

    10/03/01 01:00:00 0.706 -5.09

    10/03/01 01:15:00 0.644 -5.16 LP -5.156

    10/03/01 01:30:00 0.742 -5.06 -5.077

    10/03/01 01:45:00 0.972 -4.83 -4.864

    10/03/01 02:00:00 1.334 -4.47 -4.516

    10/03/01 02:15:00 1.764 -4.04 -4.097

    10/03/01 02:30:00 2.22 -3.58 -3.647

    10/03/01 02:45:00 2.72 -3.08 -3.149

    10/03/01 03:00:00 3.302 -2.50 -2.564

    10/03/01 03:15:00 3.943 -1.86 -1.913

    10/03/01 03:30:00 4.611 -1.19 -1.229

    10/03/01 03:45:00 5.324 -0.48 -0.494

    10/03/01 04:00:00 6.069 0.27 0.280

    10/03/01 04:15:00 6.83 1.03 1.076

    10/03/01 04:30:00 7.603 1.80 1.891

    10/03/01 04:45:00 8.373 2.57 2.708

    10/03/01 05:00:00 9.095 3.30 3.481

    10/03/01 05:15:00 9.792 3.99 4.232

    10/03/01 05:30:00 10.448 4.65 4.945

    10/03/01 05:45:00 11.058 5.26 5.614

    10/03/01 06:00:00 11.604 5.80 6.218

    10/03/01 06:15:00 12.08 6.28 6.752

    10/03/01 06:30:00 12.468 6.67 7.194

    10/03/01 06:45:00 12.756 6.96 7.531

    10/03/01 07:00:00 12.942 7.14 7.759

    10/03/01 07:15:00 13.01 7.21 HP 7.860

    10/03/01 07:30:00 12.919 7.12 7.736

    10/03/01 07:45:00 12.69 6.89 7.463

    10/03/01 08:00:00 12.348 6.55 7.070

    10/03/01 08:15:00 11.882 6.08 6.546

    10/03/01 08:30:00 11.354 5.55 5.958

    10/03/01 08:45:00 10.782 4.98 5.327

    10/03/01 09:00:00 10.144 4.34 4.630

    10/03/01 09:15:00 9.465 3.67 3.894

    10/03/01 09:30:00 8.782 2.98 3.158

    10/03/01 09:45:00 8.102 2.30 2.430

    10/03/01 10:00:00 7.412 1.61 1.696

    10/03/01 10:15:00 6.705 0.91 0.949

    10/03/01 10:30:00 6.025 0.23 0.235

    10/03/01 10:45:00 5.37 -0.43 -0.448

    10/03/01 11:00:00 4.74 -1.06 -1.100

    10/03/01 11:15:00 4.132 -1.67 -1.726

    10/03/01 11:30:00 3.563 -2.24 -2.307

    10/03/01 11:45:00 3.025 -2.78 -2.852

    10/03/01 12:00:00 2.527 -3.27 -3.352

    10/03/01 12:15:00 2.062 -3.74 -3.816

    10/03/01 12:30:00 1.634 -4.17 -4.238

    10/03/01 12:45:00 1.286 -4.51 -4.577

    10/03/01 13:00:00 1.011 -4.79 -4.839

    10/03/01 13:15:00 0.709 -5.09 -5.126

    10/03/01 13:30:00 0.555 -5.25 -5.263

    10/03/01 13:45:00 0.518 -5.28 LP -5.28

    Hinkley 2001 data.xls\10-03 2001 extrap to 7.86

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    25/48

    EE00431 - Site H17 - Highbridge, FRA September 2007

    1 in 200 Tidal Inflow

    Time mAOD

    mAOD Time

    Spill Level 7.81 07:07

    Tidal peak 7.86 07:15

    Ponding Invert level 7.22

    Width of breach = 4.63 m

    Cross sectional flow area = 0.139 m2

    Distance from defence to Low Spot = 0.00 m2

    Area of ponding "A" below 7.59m = 2347.00 m

    m

    Max depth based on total volume over area = 0.012 m

    or = 7.232

    * Assumed velocity = 0.5 m/s

    Flow Volume

    (m3/s)* (m

    3)

    07:07:25 7.810 0.0000

    07:15:00 7.860 0.0694 15.7

    07:21:03 7.810 0.0000 12.6

    Total volume = 28.3

    Flow Calcs Highbridge 1in200.xls\Tidal Inflow - 1 in 200

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    26/48

    EE00431 - H17 Newtown Road, Highbridge FRA

    Flow Calcs Highbridge 1in2

    -8.000

    -6.000

    -4.000

    -2.000

    0.000

    2.000

    4.000

    6.000

    8.000

    10.000

    00:00:00 01:00:00 02:00:00 03:00:00 04:00:00 05:00:00 06:00:00 07:00:00 08:00:00 09:00:00 10:00:00 11:00:00

    Spill Level (7.81mAOD)

    1 in 200 + CC tide curvederived from Hinkley

    Peak 8.874mAOD

    Tidal Lock (1.70mAOD)

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    27/48

    EE00431 - H17 Newtown Road, Highbridge FRA September 2007

    1 in 200 + CC Tidal Inflow

    Time mAOD Width of breach = 70.00 m

    01:15:00 -5.156 mAOD Time

    01:30:00 -5.107 Marsh level 7.81 08:35 Cross sectional flow area 7.810 = 6.670 m2

    01:45:00 -4.921 Tidal peak 8.874 09:30 Cross sectional flow area 8.015 = 16.661 m2

    02:00:00 -4.595 Marsh level 5.5 10:25 Cross sectional flow area 8.428 = 47.617 m2

    02:15:00 -4.191 Cross sectional flow area 8.722 = 71.681 m2

    02:30:00 -3.752 Cross sectional flow area 8.874 = 84.139 m2

    02:45:00 -3.258 Cross sectional flow area 8.699 = 69.797 m2

    03:00:00 -2.666 Cross sectional flow area 8.358 = 41.894 m2

    03:15:00 -2.000 Cross sectional flow area 7.885 = 9.983 m2

    03:30:00 -1.292 Cross sectional flow area 7.810 = 6.670 m2

    03:45:00 -0.522

    04:00:00 0.297 Distance from defence to Low Spot = 0.00

    04:15:00 1.149 Area of ponding at 5.5mAOD = 2762979 m

    04:22:39 1.638 Outfall Area considered deducting buildings at 20% = 2210383 m

    04:30:00 2.028

    04:45:00 2.919 Max depth based on total volume over area = 0.068 m

    05:00:00 3.770 or = 5.568 m

    05:15:00 4.606

    05:30:00 5.408 Flow Volume Level after 3 tide cycles = 5.70 m

    05:45:00 6.168 (m3/s) (m

    3)

    06:00:00 6.864 * Assumed velocity = 0.5 m/s

    06:15:00 7.488

    06:24:11 7.810 0.0 0.0

    06:30:00 8.015 8.3 1453.8

    06:45:00 8.428 23.8 14462.607:00:00 8.722 35.8 26842.1

    07:15:00 8.874 42.1 35059.5

    07:30:00 8.699 34.9 34635.6

    07:45:00 8.358 20.9 25130.5

    08:00:00 7.885 5.0 11672.3

    08:01:50 7.810 0.0 274.5

    08:15:00 7.270

    08:30:00 6.589

    08:45:00 5.866 Total volume = 149531

    09:00:00 5.077

    09:15:00 4.251

    09:30:00 3.432

    09:45:00 2.629

    10:00:00 1.827

    10:26:30 1.638 Outfall

    10:15:00 1.017

    10:30:00 0.251

    10:45:00 -0.476

    11:00:00 -1.164

    11:15:00 -1.816

    11:30:00 -2.416

    11:45:00 -2.972

    12:00:00 -3.476

    12:15:00 -3.937

    12:30:00 -4.351

    12:45:00 -4.674

    13:00:00 -4.917

    13:15:00 -5.181

    13:30:00 -5.292

    13:45:00 -5.28

    Flow Calcs Highbridge 1in200 CC.xls/Tidal Inflow - 1 in 200 CC

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    28/48

    Appendix E

    WinDes Calculations

    WinDes Result File Pipe System 100yr + 30% CC under Tide Lock ConditionsWinDes Result File Pipe System 2yrWinDes Result File Pipe System 30yr

    WinDes Result File Pipe System 100yrWinDes Result File Pipe System 100yr + 30% Climate Change

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    29/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 1

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB CC Tide Lock Pipe SystemDate September 07 Designed By AMC

    File CC Test Tide Lock.src Checked By

    Micro Drainage Source Control W.10.4

    Summary of Results for 100 year Return Period (+30%)

    Storm

    Duration(mins)

    Maximum

    Control(l/s)

    Maximum

    Outflow(l/s)

    Maximum

    Water Level(m OD)

    Maximum

    Depth(m)

    Maximum

    Volume(m)

    Status

    15 Summer 0.2 0.2 3.9868 0.9868 279.5 O K30 Summer 0.2 0.2 4.1693 1.1693 375.7 O K60 Summer 0.2 0.2 4.3662 1.3662 482.1 O K120 Summer 0.3 0.3 4.5817 1.5817 597.1 O K180 Summer 0.3 0.3 4.7182 1.7182 666.5 O K240 Summer 0.3 0.3 4.8187 1.8187 715.3 O K

    360 Summer 0.3 0.3 4.9822 1.9822 787.4 O K480 Summer 0.3 0.3 5.1342 2.1342 842.4 O K

    600 Summer 0.3 0.3 5.3342 2.3342 886.5 O K720 Summer 0.0 0.0 3.0000 0.0000 0.0 O K960 Summer 0.0 0.0 3.0000 0.0000 0.0 O K

    1440 Summer 0.0 0.0 3.0000 0.0000 0.0 O K2160 Summer 0.0 0.0 3.0000 0.0000 0.0 O K2880 Summer 0.0 0.0 3.0000 0.0000 0.0 O K4320 Summer 0.0 0.0 3.0000 0.0000 0.0 O K5760 Summer 0.0 0.0 3.0000 0.0000 0.0 O K7200 Summer 0.0 0.0 3.0000 0.0000 0.0 O K8640 Summer 0.0 0.0 3.0000 0.0000 0.0 O K

    10080 Summer 0.0 0.0 3.0000 0.0000 0.0 O K15 Winter 0.2 0.2 4.0513 1.0513 313.1 O K30 Winter 0.2 0.2 4.2533 1.2533 420.9 O K60 Winter 0.3 0.3 4.4742 1.4742 540.0 O K120 Winter 0.3 0.3 4.7227 1.7227 668.9 O K180 Winter 0.3 0.3 4.8872 1.8872 746.7 O K

    240 Winter 0.3 0.3 5.0177 2.0177 801.4 O K360 Winter 0.3 0.3 5.3067 2.3067 882.3 O K

    480 Winter 0.0 0.0 3.0000 0.0000 0.0 O K600 Winter 0.0 0.0 3.0000 0.0000 0.0 O K720 Winter 0.0 0.0 3.0000 0.0000 0.0 O K960 Winter 0.0 0.0 3.0000 0.0000 0.0 O K

    1440 Winter 0.0 0.0 3.0000 0.0000 0.0 O K

    Storm

    Duration(mins)

    Rain

    (mm/hr)

    Time-Peak

    (mins)

    15 Summer 89.02 1930 Summer 59.85 3460 Summer 38.41 64120 Summer 23.81 124180 Summer 17.74 184240 Summer 14.29 244360 Summer 10.50 364480 Summer 8.44 484600 Summer 7.12 604720 Summer 0.00 0960 Summer 0.00 0

    1440 Summer 0.00 02160 Summer 0.00 02880 Summer 0.00 04320 Summer 0.00 05760 Summer 0.00 07200 Summer 0.00 08640 Summer 0.00 0

    10080 Summer 0.00 015 Winter 89.02 1930 Winter 59.85 3460 Winter 38.41 64120 Winter 23.81 124180 Winter 17.74 184240 Winter 14.29 244360 Winter 10.50 364480 Winter 0.00 0600 Winter 0.00 0720 Winter 0.00 0960 Winter 0.00 0

    1440 Winter 0.00 0

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    30/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    31/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    32/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 4

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB CC Tide Lock Pipe SystemDate September 07 Designed By AMC

    File CC Test Tide Lock.src Checked By

    Micro Drainage Source Control W.10.4

    Circular Pipe Details

    Diameter (m) 2.100 Length (m) 260.000 Cover Level (m) 6.400

    Slope (1:x) 500.0 Invert Level (m) 3.000

    Orifice Outflow Control

    Diameter (m) 0.010 Discharge Coefficient 0.600 Invert Level (m) 3.000

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    33/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 1

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 2yr Pipe SystemDate September 07 Designed By AMC

    File 2yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Summary of Results for 2 year Return Period

    Storm

    Duration(mins)

    Maximum

    Control(l/s)

    Maximum

    Outflow(l/s)

    Maximum

    Water Level(m OD)

    Maximum

    Depth(m)

    Maximum

    Volume(m)

    Status

    15 Summer 62.3 62.3 3.4597 0.4597 53.2 O K30 Summer 63.5 63.5 3.4737 0.4737 57.2 O K60 Summer 62.1 62.1 3.4577 0.4577 52.6 O K120 Summer 57.7 57.7 3.4107 0.4107 40.4 O K180 Summer 53.4 53.4 3.3682 0.3682 30.9 O K240 Summer 49.8 49.8 3.3342 0.3342 24.4 O K

    360 Summer 41.9 41.9 3.2902 0.2902 17.3 O K480 Summer 35.8 35.8 3.2607 0.2607 13.3 O K

    600 Summer 31.5 31.5 3.2397 0.2397 10.9 O K720 Summer 28.1 28.1 3.2233 0.2232 9.1 O K960 Summer 23.3 23.3 3.1993 0.1992 6.9 O K

    1440 Summer 17.6 17.6 3.1673 0.1673 4.5 O K2160 Summer 13.3 13.3 3.1368 0.1368 2.8 O K2880 Summer 10.8 10.8 3.1228 0.1228 2.1 O K4320 Summer 8.1 8.1 3.1088 0.1088 1.6 O K5760 Summer 6.6 6.6 3.0988 0.0988 1.3 O K7200 Summer 5.7 5.7 3.0903 0.0903 1.0 O K8640 Summer 5.0 5.0 3.0838 0.0838 0.9 O K

    10080 Summer 4.5 4.5 3.0793 0.0793 0.8 O K15 Winter 64.5 64.5 3.4852 0.4852 60.6 O K30 Winter 65.3 65.3 3.4942 0.4942 63.5 O K60 Winter 62.6 62.6 3.4632 0.4632 54.2 O K120 Winter 55.5 55.5 3.3887 0.3887 35.3 O K180 Winter 49.2 49.2 3.3292 0.3292 23.6 O K

    240 Winter 42.6 42.6 3.2937 0.2937 17.8 O K360 Winter 33.2 33.2 3.2482 0.2482 11.8 O K

    480 Winter 27.5 27.5 3.2202 0.2202 8.8 O K600 Winter 23.6 23.6 3.2008 0.2007 7.0 O K720 Winter 20.8 20.8 3.1863 0.1862 5.9 O K960 Winter 17.0 17.0 3.1628 0.1628 4.2 O K

    1440 Winter 12.7 12.7 3.1333 0.1333 2.6 O K

    Storm

    Duration

    (mins)

    Rain

    (mm/hr)

    Time-Peak

    (mins)

    15 Summer 36.37 1330 Summer 24.05 2260 Summer 15.35 38120 Summer 9.61 70180 Summer 7.27 100240 Summer 5.95 130

    360 Summer 4.48 188480 Summer 3.66 248

    600 Summer 3.12 308720 Summer 2.74 368960 Summer 2.24 490

    1440 Summer 1.68 7342160 Summer 1.26 10802880 Summer 1.03 14684320 Summer 0.77 21925760 Summer 0.63 29367200 Summer 0.54 36328640 Summer 0.47 4312

    10080 Summer 0.42 504015 Winter 36.37 1430 Winter 24.05 2360 Winter 15.35 40120 Winter 9.61 72180 Winter 7.27 102

    240 Winter 5.95 130360 Winter 4.48 190

    480 Winter 3.66 248600 Winter 3.12 308720 Winter 2.74 368960 Winter 2.24 490

    1440 Winter 1.68 734

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    34/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 2

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 2yr Pipe SystemDate September 07 Designed By AMC

    File 2yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Summary of Results for 2 year Return Period

    Storm

    Duration(mins)

    Maximum

    Control(l/s)

    Maximum

    Outflow(l/s)

    Maximum

    Water Level(m OD)

    Maximum

    Depth(m)

    Maximum

    Volume(m)

    Status

    2160 Winter 9.6 9.6 3.1163 0.1163 1.9 O K2880 Winter 7.8 7.8 3.1073 0.1073 1.5 O K4320 Winter 5.9 5.9 3.0918 0.0918 1.1 O K5760 Winter 4.8 4.8 3.0823 0.0823 0.8 O K7200 Winter 4.1 4.1 3.0763 0.0763 0.7 O K8640 Winter 3.6 3.6 3.0718 0.0718 0.6 O K

    10080 Winter 3.2 3.2 3.0678 0.0678 0.5 O K

    StormDuration

    (mins)

    Rain

    (mm/hr)

    Time-Peak

    (mins)

    2160 Winter 1.26 1100

    2880 Winter 1.03 14604320 Winter 0.77 2128

    5760 Winter 0.63 29127200 Winter 0.54 35928640 Winter 0.47 4352

    10080 Winter 0.42 5024

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    35/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 3

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 2yr Pipe SystemDate September 07 Designed By AMC

    File 2yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Rainfall Details

    Region ENG+WAL Cv (Summer) 0.750 Summer Storms Yes

    Return Period (years) 2 Cv (Winter) 0.840 Winter Storms YesM5-60 (mm) 19.000 Shortest Storm (mins) 15 Climate Change % +0Ratio-R 0.350 Longest Storm (mins) 10080

    Time / Area Diagram

    Total Area (ha) = 1.289

    Timefrom:

    (mins)to:

    Area(ha)

    0 4 1.289

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    36/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 4

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 2yr Pipe SystemDate September 07 Designed By AMC

    File 2yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Circular Pipe Details

    Diameter (m) 2.100 Length (m) 260.000 Cover Level (m) 6.400

    Slope (1:x) 500.0 Invert Level (m) 3.000

    Orifice Outflow Control

    Diameter (m) 0.225 Discharge Coefficient 0.600 Invert Level (m) 3.000

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    37/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 1

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 30yr Pipe SystemDate September 07 Designed By AMC

    File 30yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Summary of Results for 30 year Return Period

    Storm

    Duration(mins)

    Maximum

    Control(l/s)

    Maximum

    Outflow(l/s)

    Maximum

    Water Level(m OD)

    Maximum

    Depth(m)

    Maximum

    Volume(m)

    Status

    15 Summer 76.8 76.8 3.6403 0.6403 116.8 O K30 Summer 79.3 79.3 3.6763 0.6763 131.9 O K60 Summer 79.3 79.3 3.6763 0.6763 131.7 O K120 Summer 76.2 76.2 3.6328 0.6328 113.7 O K180 Summer 72.5 72.5 3.5827 0.5827 94.2 O K240 Summer 68.8 68.8 3.5362 0.5362 77.3 O K

    360 Summer 62.2 62.2 3.4592 0.4592 53.0 O K480 Summer 56.5 56.5 3.3987 0.3987 37.6 O K

    600 Summer 51.8 51.8 3.3527 0.3527 27.9 O K720 Summer 48.0 48.0 3.3197 0.3197 21.9 O K960 Summer 39.9 39.9 3.2807 0.2807 16.0 O K

    1440 Summer 30.0 30.0 3.2328 0.2328 10.1 O K2160 Summer 22.1 22.1 3.1933 0.1932 6.4 O K2880 Summer 17.9 17.9 3.1688 0.1688 4.6 O K4320 Summer 13.1 13.1 3.1358 0.1358 2.7 O K5760 Summer 10.5 10.5 3.1213 0.1213 2.1 O K7200 Summer 8.9 8.9 3.1128 0.1128 1.7 O K8640 Summer 7.8 7.8 3.1068 0.1068 1.5 O K

    10080 Summer 6.9 6.9 3.1008 0.1008 1.3 O K15 Winter 79.7 79.7 3.6818 0.6818 134.1 O K30 Winter 82.3 82.3 3.7198 0.7198 150.7 O K60 Winter 81.7 81.7 3.7103 0.7103 146.5 O K120 Winter 76.5 76.5 3.6368 0.6368 115.5 O K180 Winter 70.9 70.9 3.5622 0.5622 86.6 O K

    240 Winter 65.5 65.5 3.4962 0.4962 64.0 O K360 Winter 55.8 55.8 3.3912 0.3912 35.8 O K

    480 Winter 48.4 48.4 3.3217 0.3217 22.3 O K600 Winter 41.6 41.6 3.2887 0.2887 17.0 O K720 Winter 36.4 36.4 3.2637 0.2637 13.7 O K960 Winter 29.5 29.5 3.2303 0.2302 9.8 O K

    1440 Winter 21.9 21.9 3.1918 0.1918 6.3 O K

    Storm

    Duration

    (mins)

    Rain

    (mm/hr)

    Time-Peak

    (mins)

    15 Summer 68.84 1530 Summer 45.83 2460 Summer 29.24 40120 Summer 18.11 74180 Summer 13.53 106240 Summer 10.95 136

    360 Summer 8.11 196480 Summer 6.54 256

    600 Summer 5.54 314720 Summer 4.83 370960 Summer 3.89 490

    1440 Summer 2.87 7342160 Summer 2.11 11002880 Summer 1.69 14564320 Summer 1.24 21565760 Summer 1.00 29367200 Summer 0.84 36648640 Summer 0.73 4320

    10080 Summer 0.65 507215 Winter 68.84 1530 Winter 45.83 2560 Winter 29.24 44120 Winter 18.11 80180 Winter 13.53 112

    240 Winter 10.95 142360 Winter 8.11 200

    480 Winter 6.54 252600 Winter 5.54 312720 Winter 4.83 370960 Winter 3.89 490

    1440 Winter 2.87 728

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    38/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 2

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 30yr Pipe SystemDate September 07 Designed By AMC

    File 30yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Summary of Results for 30 year Return Period

    Storm

    Duration(mins)

    Maximum

    Control(l/s)

    Maximum

    Outflow(l/s)

    Maximum

    Water Level(m OD)

    Maximum

    Depth(m)

    Maximum

    Volume(m)

    Status

    2160 Winter 16.1 16.1 3.1563 0.1563 3.8 O K2880 Winter 12.9 12.9 3.1343 0.1343 2.6 O K4320 Winter 9.5 9.5 3.1158 0.1158 1.9 O K5760 Winter 7.7 7.7 3.1063 0.1063 1.5 O K7200 Winter 6.4 6.4 3.0968 0.0968 1.2 O K8640 Winter 5.6 5.6 3.0893 0.0893 1.0 O K

    10080 Winter 5.0 5.0 3.0838 0.0838 0.9 O K

    StormDuration

    (mins)

    Rain

    (mm/hr)

    Time-Peak

    (mins)

    2160 Winter 2.11 1096

    2880 Winter 1.69 14644320 Winter 1.24 2136

    5760 Winter 1.00 29127200 Winter 0.84 36408640 Winter 0.73 4352

    10080 Winter 0.65 5008

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    39/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 3

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 30yr Pipe SystemDate September 07 Designed By AMC

    File 30yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Rainfall Details

    Region ENG+WAL Cv (Summer) 0.750 Summer Storms Yes

    Return Period (years) 30 Cv (Winter) 0.840 Winter Storms YesM5-60 (mm) 19.000 Shortest Storm (mins) 15 Climate Change % +0Ratio-R 0.350 Longest Storm (mins) 10080

    Time / Area Diagram

    Total Area (ha) = 1.289

    Timefrom:

    (mins)to:

    Area(ha)

    0 4 1.289

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    40/48

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    41/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 1

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 100yr Pipe SystemDate September 07 Designed By AMC

    File 100yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Summary of Results for 100 year Return Period

    Storm

    Duration(mins)

    Maximum

    Control(l/s)

    Maximum

    Outflow(l/s)

    Maximum

    Water Level(m OD)

    Maximum

    Depth(m)

    Maximum

    Volume(m)

    Status

    15 Summer 83.6 83.6 3.7383 0.7383 158.9 O K30 Summer 87.2 87.2 3.7933 0.7933 184.2 O K60 Summer 88.1 88.1 3.8073 0.8073 190.8 O K120 Summer 85.5 85.5 3.7678 0.7678 172.4 O K180 Summer 82.0 82.0 3.7143 0.7143 148.3 O K240 Summer 78.3 78.3 3.6618 0.6618 125.8 O K

    360 Summer 71.7 71.7 3.5732 0.5732 90.6 O K480 Summer 66.1 66.1 3.5032 0.5032 66.3 O K

    600 Summer 61.0 61.0 3.4462 0.4462 49.5 O K720 Summer 56.6 56.6 3.3997 0.3997 37.8 O K960 Summer 49.5 49.5 3.3322 0.3322 24.1 O K

    1440 Summer 37.8 37.8 3.2707 0.2707 14.6 O K2160 Summer 27.8 27.8 3.2218 0.2217 9.0 O K2880 Summer 22.2 22.2 3.1938 0.1937 6.4 O K4320 Summer 16.1 16.1 3.1568 0.1568 3.8 O K5760 Summer 12.8 12.8 3.1338 0.1338 2.6 O K7200 Summer 10.8 10.8 3.1228 0.1228 2.1 O K8640 Summer 9.4 9.4 3.1153 0.1153 1.8 O K

    10080 Summer 8.3 8.3 3.1098 0.1098 1.6 O K15 Winter 86.9 86.9 3.7893 0.7893 182.2 O K30 Winter 90.8 90.8 3.8508 0.8508 211.6 O K60 Winter 91.3 91.3 3.8588 0.8588 215.3 O K120 Winter 87.0 87.0 3.7903 0.7903 182.8 O K180 Winter 81.6 81.6 3.7093 0.7093 145.9 O K

    240 Winter 76.3 76.3 3.6333 0.6333 114.0 O K360 Winter 66.8 66.8 3.5117 0.5117 69.0 O K

    480 Winter 58.7 58.7 3.4207 0.4207 42.9 O K600 Winter 51.9 51.9 3.3537 0.3537 28.1 O K720 Winter 46.4 46.4 3.3122 0.3122 20.7 O K960 Winter 37.5 37.5 3.2692 0.2692 14.4 O K

    1440 Winter 27.6 27.6 3.2208 0.2207 8.8 O K

    Storm

    Duration

    (mins)

    Rain

    (mm/hr)

    Time-Peak

    (mins)

    15 Summer 89.02 1530 Summer 59.85 2560 Summer 38.41 42120 Summer 23.81 76180 Summer 17.74 108240 Summer 14.29 140

    360 Summer 10.50 202480 Summer 8.44 260

    600 Summer 7.12 320720 Summer 6.19 376960 Summer 4.96 492

    1440 Summer 3.62 7342160 Summer 2.64 11002880 Summer 2.11 14564320 Summer 1.53 21965760 Summer 1.22 29047200 Summer 1.02 35688640 Summer 0.88 4392

    10080 Summer 0.78 499215 Winter 89.02 1630 Winter 59.85 2660 Winter 38.41 46120 Winter 23.81 82180 Winter 17.74 116

    240 Winter 14.29 148360 Winter 10.50 208

    480 Winter 8.44 264600 Winter 7.12 320720 Winter 6.19 374960 Winter 4.96 492

    1440 Winter 3.62 730

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    42/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 2

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 100yr Pipe SystemDate September 07 Designed By AMC

    File 100yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Summary of Results for 100 year Return Period

    Storm

    Duration(mins)

    Maximum

    Control(l/s)

    Maximum

    Outflow(l/s)

    Maximum

    Water Level(m OD)

    Maximum

    Depth(m)

    Maximum

    Volume(m)

    Status

    2160 Winter 20.1 20.1 3.1828 0.1828 5.6 O K2880 Winter 16.1 16.1 3.1563 0.1563 3.8 O K4320 Winter 11.7 11.7 3.1273 0.1273 2.3 O K5760 Winter 9.3 9.3 3.1148 0.1148 1.8 O K7200 Winter 7.8 7.8 3.1073 0.1073 1.5 O K8640 Winter 6.7 6.7 3.0998 0.0998 1.3 O K

    10080 Winter 6.0 6.0 3.0928 0.0928 1.1 O K

    StormDuration

    (mins)

    Rain

    (mm/hr)

    Time-Peak

    (mins)

    2160 Winter 2.64 1100

    2880 Winter 2.11 14684320 Winter 1.53 2136

    5760 Winter 1.22 29367200 Winter 1.02 36408640 Winter 0.88 4368

    10080 Winter 0.78 5072

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    43/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 3

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 100yr Pipe SystemDate September 07 Designed By AMC

    File 100yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Rainfall Details

    Region ENG+WAL Cv (Summer) 0.750 Summer Storms Yes

    Return Period (years) 100 Cv (Winter) 0.840 Winter Storms YesM5-60 (mm) 19.000 Shortest Storm (mins) 15 Climate Change % +0Ratio-R 0.350 Longest Storm (mins) 10080

    Time / Area Diagram

    Total Area (ha) = 1.289

    Timefrom:

    (mins)to:

    Area(ha)

    0 4 1.289

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    44/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 4

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB 100yr Pipe SystemDate September 07 Designed By AMC

    File 100yr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Circular Pipe Details

    Diameter (m) 2.100 Length (m) 260.000 Cover Level (m) 6.400

    Slope (1:x) 500.0 Invert Level (m) 3.000

    Orifice Outflow Control

    Diameter (m) 0.225 Discharge Coefficient 0.600 Invert Level (m) 3.000

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    45/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 1

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB CC Pipe SystemDate September 07 Designed By AMC

    File CCyr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Summary of Results for 100 year Return Period (+30%)

    Storm

    Duration(mins)

    Maximum

    Control(l/s)

    Maximum

    Outflow(l/s)

    Maximum

    Water Level(m OD)

    Maximum

    Depth(m)

    Maximum

    Volume(m)

    Status

    15 Summer 91.4 91.4 3.8608 0.8608 216.5 O K30 Summer 96.0 96.0 3.9378 0.9378 254.5 O K60 Summer 97.6 97.6 3.9663 0.9663 269.1 O K120 Summer 95.7 95.7 3.9328 0.9328 252.1 O K180 Summer 92.4 92.4 3.8778 0.8778 224.7 O K240 Summer 89.0 89.0 3.8213 0.8213 197.2 O K

    360 Summer 82.4 82.4 3.7208 0.7208 151.2 O K480 Summer 76.8 76.8 3.6403 0.6403 116.8 O K

    600 Summer 71.8 71.8 3.5737 0.5737 90.8 O K720 Summer 67.4 67.4 3.5187 0.5187 71.3 O K960 Summer 59.7 59.7 3.4317 0.4317 45.6 O K

    1440 Summer 48.6 48.6 3.3237 0.3237 22.6 O K2160 Summer 36.1 36.1 3.2622 0.2622 13.5 O K2880 Summer 28.8 28.8 3.2268 0.2267 9.5 O K4320 Summer 21.0 21.0 3.1873 0.1873 5.9 O K5760 Summer 16.7 16.7 3.1608 0.1608 4.1 O K7200 Summer 14.0 14.0 3.1418 0.1418 3.0 O K8640 Summer 12.1 12.1 3.1298 0.1298 2.4 O K

    10080 Summer 10.7 10.7 3.1223 0.1223 2.1 O K15 Winter 95.2 95.2 3.9238 0.9238 247.4 O K30 Winter 100.3 100.3 4.0133 1.0133 293.1 O K60 Winter 101.8 101.8 4.0398 1.0398 307.1 O K120 Winter 98.4 98.4 3.9788 0.9788 275.4 O K180 Winter 93.3 93.3 3.8928 0.8928 232.0 O K

    240 Winter 88.2 88.2 3.8093 0.8093 191.6 O K360 Winter 78.8 78.8 3.6688 0.6688 128.7 O K

    480 Winter 70.8 70.8 3.5617 0.5617 86.4 O K600 Winter 64.0 64.0 3.4787 0.4787 58.6 O K720 Winter 57.9 57.9 3.4127 0.4127 40.9 O K960 Winter 48.5 48.5 3.3232 0.3232 22.5 O K

    1440 Winter 35.8 35.8 3.2607 0.2607 13.3 O K

    Storm

    Duration

    (mins)

    Rain

    (mm/hr)

    Time-Peak

    (mins)

    15 Summer 89.02 1630 Summer 59.85 2660 Summer 38.41 44120 Summer 23.81 78180 Summer 17.74 112240 Summer 14.29 144

    360 Summer 10.50 206480 Summer 8.44 266

    600 Summer 7.12 326720 Summer 6.19 384960 Summer 4.96 500

    1440 Summer 3.62 7362160 Summer 2.64 11002880 Summer 2.11 14684320 Summer 1.53 21565760 Summer 1.22 28727200 Summer 1.02 35608640 Summer 0.88 4392

    10080 Summer 0.78 496015 Winter 89.02 1630 Winter 59.85 2860 Winter 38.41 46120 Winter 23.81 84180 Winter 17.74 118

    240 Winter 14.29 152360 Winter 10.50 214

    480 Winter 8.44 274600 Winter 7.12 332720 Winter 6.19 386960 Winter 4.96 492

    1440 Winter 3.62 734

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    46/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 2

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB CC Pipe SystemDate September 07 Designed By AMC

    File CCyr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Summary of Results for 100 year Return Period (+30%)

    Storm

    Duration(mins)

    Maximum

    Control(l/s)

    Maximum

    Outflow(l/s)

    Maximum

    Water Level(m OD)

    Maximum

    Depth(m)

    Maximum

    Volume(m)

    Status

    2160 Winter 26.1 26.1 3.2133 0.2132 8.2 O K2880 Winter 20.9 20.9 3.1868 0.1868 5.9 O K4320 Winter 15.1 15.1 3.1498 0.1498 3.5 O K5760 Winter 12.0 12.0 3.1293 0.1293 2.4 O K7200 Winter 10.1 10.1 3.1193 0.1193 2.0 O K8640 Winter 8.8 8.8 3.1123 0.1123 1.7 O K

    10080 Winter 7.8 7.8 3.1068 0.1068 1.5 O K

    StormDuration

    (mins)

    Rain

    (mm/hr)

    Time-Peak

    (mins)

    2160 Winter 2.64 1100

    2880 Winter 2.11 14684320 Winter 1.53 2200

    5760 Winter 1.22 28327200 Winter 1.02 35848640 Winter 0.88 4408

    10080 Winter 0.78 5048

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    47/48

    (c)1982-2006 Micro Drainage

    Clarke Bond Structures Ltd Page 3

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB CC Pipe SystemDate September 07 Designed By AMC

    File CCyr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Rainfall Details

    Region ENG+WAL Cv (Summer) 0.750 Summer Storms Yes

    Return Period (years) 100 Cv (Winter) 0.840 Winter Storms YesM5-60 (mm) 19.000 Shortest Storm (mins) 15 Climate Change % +30Ratio-R 0.350 Longest Storm (mins) 10080

    Time / Area Diagram

    Total Area (ha) = 1.289

    Timefrom:

    (mins)to:

    Area(ha)

    0 4 1.289

  • 7/30/2019 010-158-42395 Flood Risk Assessment

    48/48

    Clarke Bond Structures Ltd Page 4

    Malvern House Newtown Road

    Yeoford Way Highbridge

    Exeter EX2 8LB CC Pipe SystemDate September 07 Designed By AMC

    File CCyr New Pipe.src Checked By

    Micro Drainage Source Control W.10.4

    Circular Pipe Details

    Diameter (m) 2.100 Length (m) 260.000 Cover Level (m) 6.400

    Slope (1:x) 500.0 Invert Level (m) 3.000

    Orifice Outflow Control

    Diameter (m) 0.225 Discharge Coefficient 0.600 Invert Level (m) 3.000