OCEAN PARK MASTER REDEVELOPMENT PROJECT Contract No. CS01 – Vet Hospital

SUBMISSION REVIEW RECORD

CSF Ref. No.: OPE-DBJV-PRPJ-QSE-0073 Rev. A & A1 ~ Drainage Management Plan Title of Submission: Permit Condition 2.13: Submission of Drainage Proposal

EPD’S COMMENTS PMR’S RESPONSE STATUS ITEM NO.

REVIEWER

REF. SECTION Description of Comment Response

Action due date

(C-closed; blank-open) (COMPLETED

BY PMR)

10 EPD General We observed that there will be an access road and a vet pool on Nam Long Shan. Please also pay attention to control/minimize the surface run-off arising from the associated construction activities.

Noted. Temporary Drainage system and wastewater treatment facility for the surface runoff will be installed at the access road and the vet pool on Nam Long Shan under the contractual requirements. Discharge License has been applied at vet pool area and the requirement under Water Pollution Control Ordinance will be fully followed.

- End -