4
. Condition Assessment of Railway Condition Assessment of Railway Bridges Bridges

Condition Assessment of Railway Bridges Condition Assessment of Railway Bridges

Embed Size (px)

Citation preview

Page 1: Condition Assessment of Railway Bridges Condition Assessment of Railway Bridges

.

Condition Assessment of Railway BridgesCondition Assessment of Railway Bridges

Page 2: Condition Assessment of Railway Bridges Condition Assessment of Railway Bridges

Most of the railway bridges in the Indian Railway (IR) system that have been built several decades ago have deteriorated both in terms of strength and stiffness due to a variety of reasons. These bridges have been designed for live loads and service conditions that have changed drastically with time. Increased axle loads and traffic density have necessitated bridge owners to get their condition assessed in order to determine their residual structural strength and identify strengthening measures to be taken for safe performance.

Condition assessment provides information regarding the intensity and extent of observed defects, the cause for these defects and possible deterioration processes that have strong impact on the safety and service life of structures. Further, these information forms the basis for estimating the residual structural capacity and possible remedial works that need to be undertaken.

Five bridges out of which two were steel plate girder bridges, one steel truss bridge and remaining two were arch bridges made of brick masonry and concrete have been examined.

The bridges were instrumented with LVDT (spring and capacitance type), Electrical resistance strain gages, Vibrating wire strain gages, Uni-axial and tri-axial accelerometers, Acoustic emission sensors, Tiltmeter and Temperature sensor.

Condition Assessment of Railway BridgesCondition Assessment of Railway Bridges

Investigators: Investigators: J.M. Chandra Kishen, Ananth Ramaswamy, J.M. Chandra Kishen, Ananth Ramaswamy, C.S. Manohar and D. RoyC.S. Manohar and D. Roy

Page 3: Condition Assessment of Railway Bridges Condition Assessment of Railway Bridges

The following four loading tests were carried out:

1. Static Load Test: Two BRN wagons loaded with 200 (approx. 20.75 T axle load), 184, 168 and 152 prestressed concrete sleepers were placed on the bridge structure at a fixed position. The two wagons could apply a static load on both the spans of the bridge. Displacements and strains were measured at various locations on the bridge for each load level of this test.

2. Test to obtain Influence Line diagram: A train formation consisting of two locomotive engines (WDG4), two BRN wagons with 152 sleepers in each, two goods wagon filled with 25 tonnes axle load with four axles each (BOXNEL), followed by two locomotive engines (WDG3A), was positioned on the bridge at different pre-determined location and measurements were taken. At the start of the test, the first wheel of WDG4 wagon was placed on the left springing position of span 1. The test progressed with subsequent wheels of the formation occupying this first reference point. Since the formation had forty wheels, the same number of measurements was taken. This test was performed to obtain the variations in deflections and strains for different positions of the load to obtain some kind of an influence line diagram, although strictly not.

3. Speed Test: In this test, the same formation as used in the test for influence line was made to run at speeds of 5, 10, 20, 30 and 40 kmph in both the directions. The objectives of this test were to obtain the dynamic amplifications, natural frequencies and mode shapes of the structure.

4. Longitudinal Load Test: For this test a formation consisting of 54 goods wagons (BOXNEL), each loaded with 25 tonne/axle load and five locomotive engines (WDG4) two at one end and three at the other was used.

Page 4: Condition Assessment of Railway Bridges Condition Assessment of Railway Bridges

0 20 40 60 80 100 120 140 160 180 20018.2

18.4

18.6

18.8

19

19.2

19.4

Time s

Dis

plac

emen

t

0 10 20 30 40 50 60 7017.6

17.7

17.8

17.9

18

18.1

18.2

18.3

18.4

18.5

Time s

Dis

plac

emen

t

Typical time histories of displacement measured at the crown of the masonry arch bridge (in mm) are presented for two load cases; (a) data from passage of goods train; (b) data from passage of passenger train. The initial and final larger spikes correspond to passage of locomotives and the peaks in the middle regions correspond to passage of wagons/compartments;

(a) (b)