13
@ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High-Low Method to Separate Fixed and Variable Costs

@ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Embed Size (px)

Citation preview

Page 1: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

@ 2012, Cengage Learning

Cost Behavior and Cost-Volume-Profit Analysis

LO 1b – Using the High-Low Method to Separate Fixed and Variable Costs

Page 2: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

The high-low method is a cost estimation method that may be used to separate mixed costs into their fixed and variable components.

Mixed CostsLO 1

Page 3: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Mixed CostsLO 1

The number of units produced is the activity base, and the relevant range is the units produced between June and October. The next four slides illustrate how the high-low method is used to determine the fixed and variable costs.

Page 4: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Mixed CostsLO 1

First, select the highest level of

activity.

First, select the highest level of

activity.

Production Total(Units) Cost

June 1,000 $45,550July 1,500 52,000August 2,100 61,500September 1,800 57,500October 750 41,250

Actual costs incurred

Variable Cost per Unit =Difference in Total CostDifference in Production

Page 5: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Mixed CostsLO 1

Second, select the lowest level of

activity.

Second, select the lowest level of

activity.

Production Total(Units) Cost

June 1,000 $45,550July 1,500 52,000August 2,100 61,500September 1,800 57,500October 750 41,250

Actual costs incurred

Variable Cost per Unit =Difference in Total CostDifference in Production

Page 6: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Mixed CostsLO 1

Production Total(Units) Cost

June 1,000 $45,550July 1,500 52,000August 2,100 61,500September 1,800 57,500October 750 41,250

Next, fill in the formula for difference in total cost.

Next, fill in the formula for difference in total cost.

$61,500 41,250

$20,250

Variable Cost per Unit =Difference in Total costDifference in Production

Page 7: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Mixed CostsLO 1

2,100 750

1,350

Then, fill in the formula for difference in production.

Then, fill in the formula for difference in production.

Production Total(Units) Cost

June 1,000 $45,550July 1,500 52,000August 2,100 61,500September 1,800 57,500October 750 41,250

Variable Cost per Unit =$20,250

Difference in Production

Page 8: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Mixed CostsLO 1

Variable cost per unit is $15

Variable cost per unit is $15

Production Total(Units) Cost

June 1,000 $45,550July 1,500 52,000August 2,100 61,500September 1,800 57,500October 750 41,250

= $15Variable Cost per Unit =$20,250

1,350

Page 9: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Mixed CostsLO 1

The fixed cost is estimated by subtracting the total variable costs from the total costs for the units produced as shown below:

Fixed Cost = Total Costs – (Variable Cost per Unit x Units Produced)

Page 10: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Mixed CostsLO 1

The fixed cost is the same at the highest and the lowest levels of production as shown below for Kason Inc.

Fixed Cost = $61,500 – ($15 x 2,100 units)

Fixed Cost = $61,500 – $31,500

Fixed Cost = $30,000

Highest LevelHighest Level

Fixed Cost = Total Costs – (Variable Cost per Unit x Units Produced)

Page 11: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Mixed CostsLO 1

With fixed costs and variable costs estimated at $30,000 plus $15 per unit, a formula is in place to estimate production at any level. If the company is expected to produce 2,000 units in November, the estimated total cost would be calculated as follows:

Total Cost = ($15 x 2,000) + $30,000

Total Cost = $30,000 + $30,000

Total Cost = $60,000

Total Cost = ($15 x Units Produced) + $30,000

Page 12: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Total Variable Costs

Total Units Produced

Unit Variable Costs

Total Units Produced

Per

-Uni

t Cos

t

Total variable costs increase and decrease proportionately with activity level.

Per-unit variable costs remain the same regardless of activity level.

Tot

al C

osts

Summary of Cost Behavior Concepts

LO 1

Page 13: @ 2012, Cengage Learning Cost Behavior and Cost-Volume-Profit Analysis LO 1b – Using the High- Low Method to Separate Fixed and Variable Costs

Total Units Produced

Tot

al C

osts

Total Units Produced

Total fixed costs remain the same regardless of activity level.

Per-unit fixed costs decrease as activity level increases.

Total Fixed Costs

Unit Fixed Costs

Per

-Uni

t Cos

t

Summary of Cost Behavior Concepts

LO 1