Upload
colleen-davis
View
215
Download
0
Embed Size (px)
Citation preview
1© 2003 Six Sigma Academy
Impact and Depth ProjectsGeneral Case Studies
Champion Workshop
2© 2002-2003 Six Sigma Academy
Project Case Studies
The purpose of this section is demonstrate to varying detail the breadth and depth of projects tackled using the Breakthrough Strategy. Included are projects that apply to a variety of industries and processes. The tools used range from simple lean applications to more complex business process Design for Six Sigma. These 8 project examples are not specific to the financial services field, but are intended to broaden your thoughts about the application of this methodology.
Section One – Impact Projects
Focus on Projects and business cases that had a profound effect of evolving the concept of Six Sigma from a manufacturing/back office process improvement tool suite to a business improvement problem solving approach.
Section Two – Depth Projects
Focus on Projects and business cases that show a depth and variation of the tools used to solve business problems through a wide range of processes and industries.
3© 2003 Six Sigma Academy
Impact ProjectsShort Case Studies
4© 2002-2003 Six Sigma Academy
Impact Projects
Focus on Projects and business cases that had a profound effect of evolving the concept of Six Sigma from a manufacturing/back office process improvement tool suite to a business improvement problem solving approach.
The examples chosen:
Pricing
Sales Force Effectiveness
Financial Closing Process
Reduction of Teller Transactions
Adhesive
Delivery Logistics
5© 2002-2003 Six Sigma Academy
Client: GE
Challenge: Gain a 2 –2.5% increase in price of goods and services.
Goal: Negotiate price increases with large clients while maintaining positive relationships
Results: Initially, identified as a huge success… 2.50% price increase year over year. (Equivalent to $4.4MM in margin)… actual results in terms of landed/pocket price a different story.
Pricing
6© 2002-2003 Six Sigma Academy
Pricing
Pricing Waterfall Before
0.39%
0.54%
0.21%0.45%
0.63%
0.47%
0.52%2.50%
0.39%
-1.10%
List Price T erms Extension Addit ional T ermsT aken
Red Arrow Pricing T ransportat ion Field Support Volume Discount Special ContractRates
Concession Landed Price
Initially, the 2.5% price increase was hailed as a big success.However, once the idea of landed price was understood and Calculated, a different story emerged.
7© 2002-2003 Six Sigma Academy
PricingPricing Waterfall After
1.75%
0.05%0.03%0.08% 0.18% 0.40%
0.21%
3.00%
0.30%
List Price T erms Extension Red Arrow Pricing T ransportat ion Field Support Volume Discount Special Contract Rates Concession Landed Price
Six Sigma was a natural way for the organization to deal with the gaps identified by the waterfall… Once the data was collected and verified, each of the waterfall elements were addressed either by policy (pricing changes by sales force) or via green/black belt projects.
The 1999 price increase process netted the business $3.7MM in Contribution Margin.
8© 2002-2003 Six Sigma Academy
Client: Multiple
Challenge: Understand the amount of time spent by the sales force with the decision makers – clients… and increase this time. (In one example the time spent with decision makers was 5% and the other firm found their first quartile sales force spent 14% of their time with decision makers).
Goal: Increase the time spent with the client and specifically increase the time spent with the decision makers at the client.
Results: The first organization increased the time spent with decision makers from 5% to 22%. The second organization is working a current project – current projections show the increasing the time spent from 14% to 30% in trials.
Sales Force Effectiveness
9© 2002-2003 Six Sigma Academy
The sales force effectiveness approach was started in both companies well after the organizations started Six Sigma.
What was typified as the “art of selling,” was not an acceptable reason for why some salespeople met their goals while others did not.
The first example brought the business estimated additional revenue of $39MM (20% increase) with a reduction of sales staff of 15%. The second business identified is still implementing the changes, but expect to drive $500MM in increased sales the first year without adding sales professionals.
Sales Force Effectiveness
10© 2002-2003 Six Sigma Academy
Client: Large conglomerate
Challenge: Reduce the quarterly closing cycle time from 30 days to 5 days. (this included affiliate closing cycles which were never included previously.)
Goal: Reduce the amount of time and associated headcount to accurately close the quarterly books
Results: Multiple projects (typically green belt, though the process was led by a Black Belt)… the results were a 3 day close in 9 months.
Financial Closing Process
11© 2002-2003 Six Sigma Academy
This mega-project dubbed, “Free nights and weekends,” was one of the first finance organizational projects.
The genesis of this project was a CFO who had as her background a MBB certification, asking why the processes of finance took so much time, were fraught with rework and caused as much stress to the finance organization.
The P&L impact of these projects is not readily available, but it can be estimated that over $1MM in cost was removed.
Financial Closing Process
12© 2002-2003 Six Sigma Academy
Client: Large Financial Service Corporation
Challenge: Bank teller transactions are the highest cost and seemingly low value to the client relationship. Nearly 2/3’s of all the teller transactions could be accomplished using an ATM…yet only about 35% of the total are accomplished using the ATM.
Goal: Shift 80% of all transfer-eligible transactions to ATMs and manage the teller workforce to maximize service while minimizing cost.
Results: Through the adoption of waste elimination, variation reduction tools and implementing a queuing model, the results were a 65% transfer of transactions and a reduction of labor costs by 50%.
Reduction of Teller Transactions
13© 2002-2003 Six Sigma Academy
Reduction of Teller Transactions
This mega-project included the use of sophisticated analysis tounderstand time-based forecasting and queuing theory. Determiningthis load and the reasons for the load, specific information technology projects, lean projects, and variability reduction projects were launched.
The P&L impact of these changes to this bank were in the tens of millionsof dollars
14© 2003 Six Sigma Academy
Depth ProjectsLonger Case Studies
15© 2002-2003 Six Sigma Academy
Depth Projects
Focus on Projects and business cases that show a depth and variation of the tools used to solve business problems through a wide range of processes and industries.
The examples chosen:
Branch Office Rework
Increase Market Share
16© 2003 Six Sigma Academy
Branch Office Rework
17© 2002-2003 Six Sigma Academy
Define
Branch Office redundancy and rework result in $7 million of excess expense over a budget of $200 million as well as client dissatisfaction.
Problem Statement
ObjectiveIdentify and reduce the cause for work redundancy and rework by 70% for a savings of > $4.9 million.
Critical to Quality - CTQ• Percentage of redundant and rework expense.• Client satisfaction measured by errors generated
per 100 clients.• Cycle time measured by marketing policy as 14
calendar days.
Current/Goal/Stretch Goal
35,000 DPMO - Current 10,500 DPMO – Goal 10,500 DPMO – Final Actual
Benefits Achieved
$5 million annualized savings80% reduction in branch redundancy and rework expenseNo decrease in cycle time
18© 2002-2003 Six Sigma Academy
High Level Process Map
Start
Stop
No
Yes
Branch i
Branch i+1
Rework
Rework Analysis
• The network consisted of over 200 branches.
• The average branch revenue was ~ $125,000,000.
• The average rework expense per branch was ~ $125,000.
The Focus Was on Representative Branches With the Eventual Goal to Understand Common Operations and
Sources of Redundancy to Create System Wide Mistake Proofing Strategies
The Focus Was on Representative Branches With the Eventual Goal to Understand Common Operations and
Sources of Redundancy to Create System Wide Mistake Proofing Strategies
19© 2002-2003 Six Sigma Academy
Data Collection
Data Collection Focused On The Following Inputs:
(1) Annual Sales (2) Geographical Region (3) Client Affluence Level
Under $10 million $10-25 Million >$25 millionNE SE NW SW Central NE SE NW SW Central NE SE NW SW Central
>$5 MM
$1-5MM
<$500K -$1MM
$100K-$499K
<$100K
Outputs Were Redundant Operations,rework Types, Frequency and Expense As Well As Cycle Time
20© 2002-2003 Six Sigma Academy
Defect Analysis By Branch
Branch Six (Sales Revenue Less Than $10 MM and Located in the Northeast) Had the Most Redundant Operations
89 45 43 34 24 23 21 11
30.7 15.5 14.8 11.7 8.3 7.9 7.2 3.8
30.7 46.2 61.0 72.8 81.0 89.0 96.2 100.0
0
100
200
300
0
20
40
60
80
100
Branch
CountPercentCum %
Per
cen
t
Cou
nt
Redundant Operations By Branch1st Level Pareto Analysis
89 45 43 34 24 23 21 11
30.7 15.5 14.8 11.7 8.3 7.9 7.2 3.8
30.7 46.2 61.0 72.8 81.0 89.0 96.2 100.0
0
100
200
300
0
20
40
60
80
100
Branch
CountPercentCum %
Per
cen
t
Cou
nt
Redundant Operations By Branch1st Level Pareto Analysis
21© 2002-2003 Six Sigma Academy
Defect Analysis By Redundancy For Branch Six
Duplicated Reports Had the Highest Incident Rate
98 45 31 1252.7 24.2 16.7 6.5
52.7 76.9 93.5 100.0
0
50
100
150
0
20
40
60
80
100
Category
CountPercentCum %
Per
cen
t
Cou
nt
Branch Six Work Redundancy2nd Level Pareto For Branch Six
22© 2002-2003 Six Sigma Academy
Analysis Of Redundant Operation By Sales
Several Analyses Were Conducted To Determine The Key Process Input Variables (KPIVs)…Finally, It Was Found Branch Sales Level and Region
Were Significant (East and West Coast As Well As Central United States) …These Were Incorporated Into an Optimization Experiment
0 5 10 15
95% Confidence Intervals for Sigmas
Bartlett's Test
Test Statistic: 0.144
P-Value : 0.931
Levene's Test
Test Statistic: 0.158
P-Value : 0.856
Factor Levels
-1
0
1
Test for Equal Variances for % Redundancy By Branch Sales
Low Sales $<100 K
Intermediate Sales $500K- $1 MM
Sales >$ 5 MM
-1 0 1
1
2
3
4
5
Sales
% R
ed
un
da
ncy
Boxplots of % Redundency by Branch Sales(means are indicated by solid circles)
< $100 K $500K - $1MM >$5 MM
23© 2002-2003 Six Sigma Academy
Building The Optimization Model
Region Is the Most Important Variable
Estimated Regression Coefficients for % Redundancy
Term Coef SE Coef T P
Constant 1.8983 0.1315 14.433 0.000
Sales 0.0167 0.1293 0.129 0.901
Region 1.5833 0.1293 12.244 0.000
Sales*Sales 0.0710 0.1906 0.373 0.720
Region*Region 0.7710 0.1906 4.045 0.005
Sales*Region -0.1000 0.1584 -0.631 0.548
S = 0.3168 R-Sq = 96.1% R-Sq(adj) = 93.3%
24© 2002-2003 Six Sigma Academy
Optimization To Reduce Redundancy
Redundancy Should Be Eliminated By Branch On a Regional Basis Across All Branches
1
0-1
1.0Region
1.5
2.0
2.5
3.0
3.5
4.0
4.5
0
% Redundancy
-11Sales
Percent Redundency Versus Branch Sales and Region
25© 2002-2003 Six Sigma Academy
0 5 10 15 20 25
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
Month
Exp
ense
($
Mill
ion
)
Redundant and Rework Expenses Before Versus After Improvements
Mean=0.1775
2.0SL=0.2628
-2.0SL=0.09220
1 2Before
After
Business Benefits
Redundant Work Was Consolidated by Geographical Region … 40 Branches Were Consolidated Leaving Just 160 in the Network.
• $5 Million Annualized Savings• 80% Reduction in Branch
Redundancy and Rewok• No Decrease in Cycle Time
26© 2003 Six Sigma Academy
Adhesive Project Example
27© 2002-2003 Six Sigma Academy
Problem Statement
The amount of adhesive consumed in the assembly operation is higher than specified by engineering, resulting in significantly higher production expenses, which impact profitability of the product.
Target:
Identify the causes of excessive adhesive consumption and reduce the usage of adhesive in the assembly line operation by 400%.
Critical To Quality - CTQ
Applying the specified amount of adhesive is essential to bond strength.
Applying excessive adhesive causes costs to exceed targets.
Benefits Achieved
$500,000 savings in material costs for adhesive.
28© 2002-2003 Six Sigma Academy
1st Qtr Usage Projected Usage For the Year
Brought in house
14,983 Gal.$174,738
56,479 Gal.$658,689
Usage Per Projected Specification
3,542 Gal.$41,305
13,353 Gal.$155,731
Adhesive Volume/Cost Total Plant
MetricsAdhesive usage and cost
29© 2002-2003 Six Sigma Academy
Purging process Purging process --
--Leaking during Leaking during applicationapplication
-Limit switch set up (too high causesLimit switch set up (too high causes excessive adhesive remaining in drums)excessive adhesive remaining in drums)
Over use Over use of of adhesiveadhesiveduring during assemblyassemblyprocessesprocesses
Cause-Effect DiagramCause-Effect Diagram
MachinesMachines
MethodsMethods
ManpowerManpower MeasuresMeasures
- - Drum’s change over processDrum’s change over process
Nozzles Height Nozzles Height --vs. Panel nestvs. Panel nest -- Needed trainingNeeded training
on spec’s.on spec’s.
Pressure set upPressure set up --
-- In- ProcessIn- ProcessMeasurement Measurement systemsystem
- - Nozzles timingNozzles timing
30© 2002-2003 Six Sigma Academy
Current dimensions data: Base line
Date/Spot 257-1 257-2 257-3 257-4 257-5 257-6 352-1 352-2 352-3 352-4 352-5 352-6 381-1 381-2 381-3 381-4 381-5 381-65/21, 12:30 37 42 38 34 41 38 36 33 33 32 33 36 32 35 38 37 35 375/25, 1:16 35 35 31 31 31 32 41 43 36 45 42 40 40 39 41 40 40 425/29, 10:10 32 34 28 27 34 35 41 43 37 47 42 41 41 40 41 39 39 425/30, 3:10 33 35 33 32 34 27 40 38 35 46 36 42 41 42 42 43 41 425/31, 3:00 39 37.5 33.4 31.6 35.1 33.5 42 41 37 48 38 43 45 44 44 44 43 436/01, 5:00 35 38 34 35 37 36 40 36 33 42 36 41 38 36 39 38 36 39
Diameter (mm)
31© 2002-2003 Six Sigma Academy
50454035302520
USLLSL
Process Capability Analysis for Diameter
PPM Total
PPM > USL
PPM < LSL
PPM Total
PPM > USL
PPM < LSL
Cpm
Ppk
Z.LSL
Z.USL
Z.Bench
StDev (Overall)
Sample N
Mean
LSL
Target
USL
993932.96
993605.73
327.23
981481.48
981481.48
0.00
*
-0.83
3.41
-2.49
-2.51
4.35552
108
37.8435
23.0000
*
27.0000
Expected PerformanceObserved Performance
Overall Capability
Process Data
Current Process not capable- Negative Sigma Level
32© 2002-2003 Six Sigma Academy
"USAGE OPTIMIZATION OF ADHESIVE"TWO LEVEL - TWO FACTORS EXPERIMENT
LINE: 257 / 352 / 381 SHIFT: 2 / 3 DATE: / / Time: ___:___
LEVELS DEFINITION:LEVEL / FACTOR PRESSURE TIMING
HILOW
EXPERIMENT:
RUNS PRESSURE(psi)
TIMING(seconds)
SPOTS DIAMETER(millimeters)
#1 /#2 /#3 /#4 /#5 /#61 HI HI / / / / /2 HI HI / / / / /3 HI HI / / / / /4 HI HI / / / / /1 HI LOW / / / / /2 HI LOW / / / / /3 HI LOW / / / / /4 HI LOW / / / / /1 LOW HI / / / / /2 LOW HI / / / / /3 LOW HI / / / / /4 LOW HI / / / / /1 LOW LOW / / / / /2 LOW LOW / / / / /3 LOW LOW / / / / /4 LOW LOW / / / / /
OBSERVATIONS:______________________________________________________________________________________________________________________________________________________________________________________________________________________
Material: Adhesive (from same drum). Temperature: N/AViscosity: Constant Humidity: Constant
Top of panel
#1 Spots #6
DOE - DOE - Optimize Pressure & Time SettingsOptimize Pressure & Time Settings for the dispensing nozzlesfor the dispensing nozzles
33© 2002-2003 Six Sigma Academy
Regression Analysis: Diameter versus Pressure, Time
The regression equation isDiameter = - 39.0 + 0.740 Pressure + 1.61 Time
Predictor Coef SE Coef T PConstant -38.985 8.038 -4.85 0.000Pressure 0.73956 0.09967 7.42 0.000Time 1.6121 0.2100 7.68 0.000
S = 1.596 R-Sq = 94.0% R-Sq(adj) = 93.5%
Time Pressure
25
29
33
37
41
Dia
met
er
Main Effects Plot - Data Means for Diameter
Results Main Effects Plot Regression Model
Results used to optimize settings for nozzles
34© 2002-2003 Six Sigma Academy
27 mm27 mmUPPER SPEC..UPPER SPEC..
25 mm25 mmTARGETTARGET
23 mm23 mmLOWER LOWER SPEC.SPEC.
WRONGWRONGTOO BIGTOO BIG
WATCH FOR THIS DEFECT
WRONGWRONGTOO SMALLTOO SMALL
Visual Aid
35© 2002-2003 Six Sigma Academy
BEFORE CHANGING ADHESIVE BEFORE CHANGING ADHESIVE DRUMS CHECK FOR:DRUMS CHECK FOR:
1. The drum to be removed from the line is empty. 2. The piston is all the way down to the bottom of the drum.
3. Air pressure closed for drum to be changed4. T-valve closed for the drum to be changed.5. T-valve open for the remaining drum.
AFTER CHANGING ADHESIVE DRUMSAFTER CHANGING ADHESIVE DRUMSCHECK FOR:CHECK FOR:
1. T-valve is open for both drums.2. Air lines open for both drums; if not, if not, one drum will pump Adhesive to the other.one drum will pump Adhesive to the other.
T-valve
To avoid Adhesive spillage…To avoid Adhesive spillage…
LOSSLOSS
$11.7/gallon$11.7/gallon
There is 25% of adhesive remainingin this drum
Piston is herePiston is at bottom
When plate is here
Visual AidsVisual Aids
36© 2002-2003 Six Sigma Academy
Material: PlexiglassMaterial: Plexiglass
23mm23mm 27mm27mm
1000mm1000mm
Measurement tool for Adhesive spotsMeasurement tool for Adhesive spotsPrototype IIPrototype II
Gage type: Go / no goGage type: Go / no go
Higher specification limitHigher specification limit Lower specification limitLower specification limit
60mm60mm
Measurement SystemMeasurement System
37© 2002-2003 Six Sigma Academy
11stst Qtr Cost Improved Process Cost Difference Yearly Savings Qtr Cost Improved Process Cost Difference Yearly Savings
$ 0.58/panel $ 0.58/panel $0.24 /panel $0.34/panel $0.24 /panel $0.34/panel $503,000$503,000
Project Results
Actions:Actions:Material handling ChangesMaterial handling ChangesOptimized Application SettingsOptimized Application Settings
Process Capability for Diameter Improved Ppk= 3.1
38© 2003 Six Sigma Academy
Delivery - Logistics
39© 2002-2003 Six Sigma Academy
Define
• Point one• Point two• Point three• Trailers are not being unloaded in their scheduled window times causing extra inventory to be carried by the plant and costing the plant in switching services. Also impacts ability of plant to build vehicle in station.
Problem Statement
Objective• Improve the live unloading of
scheduled window trailers by 70% in the main plant
• $250 K cost savings to the plant and $250 K to company freight budget
Critical to Quality - CTQ• Inventory and carrying costs
• On-time delivery to line
Metrics (Baseline/Final)
814,000 DPMO - Baseline 18,000 DPMO – Final Actual
Benefits Achieved
$1.27 M in inventory, freight, switching and late line feeds
97% defect reductionTimeframe = 6 months
40© 2002-2003 Six Sigma Academy
Measure
• Process fully mapped• Subjective problem solving tools
used• Operational Definition established• Data collected manually• Process capability measured
Process severely incapable
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
CarrierdeliverstrailerCTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
X
X
XX
X
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
CarrierdeliverstrailerCTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
X
X
XX
X
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
CarrierdeliverstrailerCTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
CarrierdeliverstrailerCTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
X
X
XX
X
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
CarrierdeliverstrailerCTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
X
X
XX
X
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
CarrierdeliverstrailerCTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
X
X
XX
X
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
CarrierdeliverstrailerCTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
CarrierdeliverstrailerCTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
X
X
XX
X
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
CarrierdeliverstrailerCTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
Cause and Effect Diagram
YTrailer LiveUnloaded
Supplier Carrier
Dock Warehouse
Trailer arrives on time
Trailer loaded on time
Trailer has correct stock
Departs on time
TrafficConstruction
Equipment
Door open
Driver
Supervisor/OperatorsPoints on trailer
Condition of trailerUnload time
Set up timeEquipment function
Trailer arrival timeReload time
Bills Cut
Dwell time on dock
Transit time to warehouse
Warehouse inventory levels
Storage space allocation
Storage space dunnage
Dunnage return processSupervisor/Operator
Cause and Effect Diagram
YTrailer LiveUnloaded
Supplier Carrier
Dock Warehouse
Trailer arrives on time
Trailer loaded on time
Trailer has correct stock
Departs on time
TrafficConstruction
Equipment
Door open
Driver
Supervisor/OperatorsPoints on trailer
Condition of trailerUnload time
Set up timeEquipment function
Trailer arrival timeReload time
Bills Cut
Dwell time on dock
Transit time to warehouse
Warehouse inventory levels
Storage space allocation
Storage space dunnage
Dunnage return processSupervisor/Operator
Operational DefinitionLive Unload: Trailer is scheduled on window deliveries managed by the LLP. Trailer is brought to the dock at the scheduled window time on the dock schedule (+/- 15 minutes). Trailer is spotted by the carrier and unloaded/reloaded (as required) within 120 minutes of the window time. Bills are cut and the driver leaves with a reloaded trailer. Drop and swap trailers count as live unload as long as the carrier does the switch and no trailers are added to the yard inventory. Late trailers that are unloaded and taken away by the carrier (without dropping in the yard) will be counted as live unload.
Data Collection Sheet for LCL Dock
Route Commodity TrailerPlan Date Act Date
Plan Time Act Time
Planned Dock Door
Actual Dock Door In Door
Start Unload
Finish Unload
Start Reload
Finish Reload
Time Bills Cut Code
Instructions.
1. Stay out of the way of the receiving checkers unloading (Safety)
2. Fill in each box accurately, Remember to change the date after midnight.
3. Fill out all times using a 24 hour clock.
4. List the most prevent part on the trailer or ODC for commodity. ( ex. Romulus ODC, Bumpers,..)
5. Add comments about specific trailers to clarify reasons for information gathered. (Dropped, Late, Dropped by Carrier, Trailer Damaged,…)
6. Turn in completed document to LLP in Parts Control at the end of the shift.
Arrive Dock Door Process Time
-1.0 -0.5 0.0 0.5 1.0 1.5
LSL USL
Target
Capability Analysis for In-Transit
USL
Target
LSL
Mean
Sample N
StDev (Within)
StDev (Overall)
Cp
CPU
CPL
Cpk
Cpm
Pp
PPU
PPL
Ppk
PPM < LSL
PPM > USL
PPM Total
PPM < LSL
PPM > USL
PPM Total
PPM < LSL
PPM > USL
PPM Total
0.100000
0.000000
-0.100000
0.235433
127
0.166048
0.345609
0.20
-0.27
0.67
-0.27
0.08
0.10
-0.13
0.32
-0.13
23622.05
448818.90
472440.94
21686.35
792643.66
814330.01
165884.68
652422.03
818306.71
Process Data
Potential (Within) Capability
Overall Capability Observed Performance Exp. "Within" Performance Exp. "Overall" Performance
Within
Overall
41© 2002-2003 Six Sigma Academy
Analyze
• Communication was leading cause
• Inconsistent or incomplete information being used
• Delivery times affected by many factors
Data analysis determined multiple causes of defects
4002000-200-400-600-800-1000
USL LSL
Min Deviation Arrive VS Schedule
PPM Total
PPM > USL
PPM < LSL
PPM Total
PPM > USL
PPM < LSL
PPM Total
PPM > USL
PPM < LSL
Ppk
PPL
PPU
Pp
Cpm
Cpk
CPL
CPU
Cp
StDev (Overall)
StDev (Within)
Sample N
Mean
LSL
Target
USL
906340.58
341462.00
564878.57
877585.66
290028.38
587557.28
561983.47
165289.26
396694.21
-0.05
-0.05
0.14
0.04
*
-0.07
-0.07
0.18
0.06
122.386
90.352
121
-34.9917
-15.0000
*
15.0000
Exp. "Overall" PerformanceExp. "Within" PerformanceObserved PerformanceOverall Capability
Potential (Within) Capability
Process Data
Within
Overall
0 100 200 300 400
LSLUSL
Process Capability Analysis for start unloadCalculations Based on Weibull Distribution Model
USL
Target
LSL
Mean
Sample N
Shape
Scale
Pp
PPU
PPL
Ppk
PPM < LSL
PPM > USL
PPM Total
PPM < LSL
PPM > USL
PPM Total
10.000
*
0.000
103.678
121
1.771
116.489
0.03
-0.74
2.40
-0.74
0.00
991735.54
991735.54
0.00
0.00
0.00
Process Data
Overall (LT) Capability
Observed LT Performance
Expected LT Performance
0 100 200 300 400
LSL USL
Total Time to Run Once Started
Calculations Based on Weibull Distribution Model
USL
Target
LSL
Mean
Sample N
Shape
Scale
Pp
PPU
PPL
Ppk
PPM < LSL
PPM > USL
PPM Total
PPM < LSL
PPM > USL
PPM Total
120.000
100.000
30.000
102.580
121
1.787
115.311
0.27
0.14
0.45
0.14
0.00
305785.12
305785.12
0.00
0.00
0.00
Process Data
Overall (LT) Capability
Observed LT Performance
Expected LT PerformanceX1 = YA X2 = YB X3 = YC
XA1= Schedule
XA2= Operators
XA3= Carriers
XA4= Suppliers
XB1= Schedule
XB2= Inventory
XB3= Warehouses
XB4= Operators
XC1= ReloadsXC2= OperatorsXC3= Warehouses
XC4= Bills cut
XC5 = Stock moving off the dock
These were the Xs for the new Ys
Arrival Time Unload Start Time Processing time
X1 = YA X2 = YB X3 = YC
XA1= Schedule
XA2= Operators
XA3= Carriers
XA4= Suppliers
XB1= Schedule
XB2= Inventory
XB3= Warehouses
XB4= Operators
XC1= ReloadsXC2= OperatorsXC3= Warehouses
XC4= Bills cut
XC5 = Stock moving off the dock
These were the Xs for the new Ys
Arrival Time Unload Start Time Processing time
Y=f(X)
X1 = YA X2 = YB X3 = YC
XA1= Schedule
XA2= Operators
XA3= Carriers
XA4= Suppliers
XB1= Schedule
XB2= Inventory
XB3= Warehouses
XB4= Operators
XC1= ReloadsXC2= OperatorsXC3= Warehouses
XC4= Bills cut
XC5 = Stock moving off the dock
These were the Xs for the new Ys
Arrival Time Unload Start Time Processing time
X1 = YA X2 = YB X3 = YC
XA1= Schedule
XA2= Operators
XA3= Carriers
XA4= Suppliers
XB1= Schedule
XB2= Inventory
XB3= Warehouses
XB4= Operators
XC1= ReloadsXC2= OperatorsXC3= Warehouses
XC4= Bills cut
XC5 = Stock moving off the dock
These were the Xs for the new Ys
Arrival Time Unload Start Time Processing time
Y=f(X)
42© 2002-2003 Six Sigma Academy
Improve
• Eliminated unneeded process steps-used hypothesis testing to verify
• Corrected schedule information supplied by carrier
• Built and tested models to re-calculated formulas used for scheduling
• Asked the people why schedules were not being followed!
Improvements implemented to greatly improve communication
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
Carrierdeliverstrailer
CTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
X
X
XX
X
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
Carrierdeliverstrailer
CTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
X
X
XX
X
Revised Process Map
Trailer is loaded at supplier
Carrierdeliverstrailer
Trailer arrives at the plant
Trailer dropped
in yard
Supervisor callstrailer in to dock
Switcher brings
trailer todock
Receiving checker unloads truck
Stock staged onDock
Stocktaken
to mkt. place
Stocktakento line
Stock placedline side
Supv. unloadsor drops
Stock/dunnagewarehousedin mkt. place
Dunnagetaken
to warehouse
Dunnage taken
to dock
Dunnage reloaded/bills cut
Start
Trailer arrivesat supplier
End
Drop
Carrierdeliverstrailer
CTQ
CTQVA
NVA
NVANVA
NVA
Bottle necks reduced
VA
VAVA
Stock loadedon dollies/AGV
NVA
X
X
XX
X
SCAC TLR Route IDSupplier
Code PARTSPlant Arrival
DaysArrival Time
Actual Arrival Time SHIFT Dock DR Unload Status
LIVE UNLD (Y/N)
Rack Return Ratio
OJ TP 022211 A439A Bumpers MTWRF 6:00 2 PL 14 DROP YES
CUOT 26002 PC06A Richfield ODC MTWRF 6:00 2 PL 21 LIVE NO
ADXR 29109 PC09A Detroit ODC MTWRF 6:00 2 PL 21 LIVE NO
RSHQ 24404 PC04A Louisville ODC MTWRF 6:00 2 PL 20 LIVE YES
HJ BT 20980 PC20A Charlotte ODC MTWRF 7:00 2 PL 14 LIVE YES
KCCI 022257 C265C 1/4 PANELS LIVE DROP MTWRF 7:00 2 PL 11 LIVE YES
BTZK 27708 PC07A Romulus ODC MTWRF 7:15 2 PL 20 LIVE NO
RSHQ 24405 PC04A Louisville ODC MTWRF 7:15 2 PL 21 LIVE YES
THMB 024513 T73J B Valences TWRF 8:00 2 PL 14 LIVE YES
ADXR 29106 PC09A Detroit ODC MTWRF 8:15 2 PL 21 LIVE YES
MMDT 021934 M363E ACTU ASY-DR LK SW TWRF 9:00 2 PL 20 LIVE YES
GSD3 029182 W411C WEBASTO MOONROOFS MTWRF 9:30 2 PL 21 DROP NO
CUOT 26003 PC06A Richfield ODC MTWRF 10:00 2 PL 18 LIVE YES
OJ TP 022213 A439A Bumpers MTWRF 10:30 2 PL 11 DROP YES
ADXR 22208 PC02A Norton Shores ODC MTWRF 10:30 2 PL 18 LIVE NO
ADXR 21600 PC01A Chicago ODC MTWRF 12:15 2 PL 14 LIVE YES
ADXR 027716 G519S Batteries MTWRF 13:00 2 PL 20 LIVE YES
2 PL
2 PL
2 PL
2 PL
Shipping and Warehouse Formulas:Over Ship = cumulative ship supplier- cumulative required Storage area Max = (container size X numbers of containers truck ) + (container size X numbers of containers OPRES ) Storage area Min = (container size X numbers of containers OPRES )
Two-sample T for TRANSIT vs OLD TRANSIT
N Mean StDev SE MeanTRANSIT 425 0.711 0.998 0.048OLD TRAN 425 0.89 1.28 0.062
Difference = mu TRANSIT - mu OLD TRANSITEstimate for difference: -0.184095% CI for difference: (-0.3387, -0.0293)T-Test of difference = 0 (vs not =): T-Value = -2.33 P-Value = 0.020 DF = 848Both use Pooled StDev = 1.15
43© 2002-2003 Six Sigma Academy
Control
• Checklists and Control plans established
• Policies and procedures changed
• Charts verify and sustain improvements
Simple job aids and metrics ensure control
Control Plan
Approved
Approved
Dept. P & P’s
Approved
Approved
Yard History Averages
193 187 171 172153
90 78 93 87 73
129107
38 34 25 30 20
412372
302 293
251223
157
18 24 10 0 1 2 0
100759362
0
50
100
150
200
250
300
350
400
450
November December January February March April May
Month
# of
Tra
ilers Inbound
Reloaded
Empties
Totals
Unbilled