MICE/Muool Coupling MagnetsMICE/Muool Coupling Magnets ProgressProgress
-2-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
Contents
• Large Coil Test and Plan To be presented by Dr. FengYu Xu
• Fabrication Plan of MICE/MuCool Coupling Magnets
Visits to possible collaborators in China; Request for quotations; and further
technical discussions, preparation for public bidding procedure etc.
• MICE/MuCool Coupling Magnet Updated Design Review Done in ICST/HIT on Dec.06 to Dec.08, 2008, and further improvement has
been carried out after the review according to the Close Out from the review
panel (to be presented by Hong Wu/Heng Pan/XingLong Guo).
-3-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
MICE/MuCool Coupling Magnet Updated Design
The updated engineering design were carried out according to the “A Technical
Agreement on the MICE and MuCool Coupling Solenoid Magnet Fabrication,
Assembly, Test and Shipping” issued in September, 2007 and experience learnt form
test coils’ winding in collaboration with Lawrence Berkeley National Laboratory. The
main differences between the previous design reviewed in May, 2007 and the
updated design reviewed in Dec., 2008 mainly include:
• The inner radius of the coupling coil is changed from 744mm to 750mm considering
very tight space on the inner side of the magnet.
• The coil assembly is designed different from the previous one in terms of winding,
mandrel fabrication, cooling and quench protection assembly.
• A double-band cold mass support system is presented instead of a single-band
system considering the shipping load during long-term transportation and space
limitation.
-4-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
• Two drop-in PTR coolers are to be used for cooling the coupling magnet for the
sake of easy removal from the cryostat during transportation.
• Thermal shields are designed to be supported from the vacuum vessel by four
pairs of G-10 rods instead of being supported onto the cold mass support
assembly as previous design.
• The cooling configuration for the warm end of the HTS leads is designed different
from the previous one.
Further improvement after the review
• To validate:
Stress analyses on final coil cold mass design, mechanical (loads, stress) and thermal analyses on the current design for the coil cold mass support assembly, stress and deflection analyses on the vacuum chamber, etc.
• To update the following engineering design drawings:
Vacuum chamber and interface, coil cold mass assembly, cold mass support assembly, etc.
-5-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
Cryocoolers
Power leads
Cold mass supports
Coil assembly
He cooling pipes
Thermal shields and intercepts
Vacuum vessel
He condenser
Previous design
-6-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
Cryocoolers Power leads
Cold mass supports
Coil assembly
He cooling pipes
Thermal shields and intercepts
Vacuum vessel
He condenser
Updated design
-7-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
Coil assembly and its cooling
Updated designPrevious design
Piping: round tubing instead of type tubing; more cold surface to mount QPAssembly; more space for mounting CMSupport cold end base, etc.
-8-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
Updated designPrevious design
Cold mass support system
Single-band to double-band; space for cold end base and its strength
-9-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
Large Coil Test and Plan
SC splices strength test at LHe temperature
• The strength of SC splices soldering by Sn-Ag solder under LHe
temperature is a major concern presently considering the rigorous stress
state in the coupling coil because all the splices are wound inside the coil
and should be tested before winding the MuCool coil according to Dr. Mike
Green’s advice.
• ICST has performed the strength test for the SC splices at LN2 temperature
and the results show its strength is close to that of the SC wire itself .
• ICST has prepared some of SC splices and to see if they could be tested in
LBNL under LHe temperature.
-10-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
Large test coil
Winding of prototype coil
Cryostat for prototype coil
Cryo-test system
Welding
-11-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
Fabrication Plan of MICE/MuCool Coupling Magnets
Visits to possible vendors in China last December
• CSRDA in Beijing
Experience in: fabrication and assembly of coil mandrel & cooling tubing welding,
heat shields & vacuum chamber for SSM and Ion-removal SC solenoid in BEPCII,
fabrication, assembly, and maintenance of several MRI magnet systems since 1987
(winding coil, cold mass, cryostat, etc.).
• SINAP in Shanghai
Experience in: fabrication, assembly and test of a small SC magnet (EBIT, solenoid
coil ID 100mm) for Shanghai FuDan University, various advanced equipment or
device for alignment, measurement and cryo-test, a set of 600W/4.5K refrigerator
system etc.
Request for quotation• Cold mass assembly: by Jan. 17
• Cryostat assembly: by the middle of February
-12-Wang,Li
The 23rd MICE Collaboration Meeting
2009-01-13 to 17 HIT/CHINA
Possibilities to cause delays• Manpower: skilled technicians and their supervisor, experienced mechanical engineers, etc.
• Funds: available time?
• Request for quotation
Further technical discussions with possible vendors before public bidding for Cryostat
Assembly (after Chinese Spring Festival till Feb. 1st ) are needed.
• Public bidding procedure
At least 3 vendors and 7 days’ workday for publicity, otherwise invalid bidding; if sole source, it
will take a longer time, more paper work and complicated procedure.
• Contract award and sign it after bidding
At least one to two weeks are needed.
• Winter holidays in HIT: Jan. 19 to Feb. 22
No possibility for processing bidding in HIT
Hopefully, to contract the first MuCool coil assembly fabrication out before or
right after the Chinese Spring Festival (at latest by the middle of this February) in
order to avoid more delay!
Plan for Fabrication the MuCool magnet