24 July 1986
FINAL REPORT
EVALUATION REPORT
TRAINING AND DEVELOPMENT ISSUES PROJECT AID Loan No 492-V-069 AID Project No 492-0340
Evaluation Team
Harry Pasimio - Team Leader Paul Deuster- Member
WP0627P
TABLE OF CONTENTS
PageEXECUTIVE SUMMARY i-iv
I BACKGROUND 1
II PROJECT STATUS 2
Financial Status 2- 4 Activity Status 4
III NON-TRAINING EL-MENTS OF TDI 5
A Divergence of Views on Approach 6 - 7 to Project Implementation
B Communication Problems - 108
C Component Management II
D Implementation Procedures 12
IV TRAINING 13
A Pace of implementation 13
B Objectives of Training Activities 14
C Overall Consistency with Priorities 15 - 17
0 Areas for Improvement 18 - 19
E Usefulness of Training 20
V PROJECT SIGNIFICANCE AND OLTLOOK 21 - 23
Vi RECOMMENDATIONS 23 - 29
LIST OF TABLES
Table I Financial Analysis Loans and Grants
Table 2 Financial Analysis Training and Non-Training
Table 3 Training Funded Under TDI Distribution by Agency
Table 4 Training Funded Under TDI Distribution by Field of Study
A N NE X E S
A Financial Analysis Table
B Prioritization Scheme for Training
C Training Funded Under TDI
D Status of On-going TDI Research Projects
APPENDICES
1 Scope of Work for Evaluation
2 List of Persons interviewed
3 Key Documents Reviewed
BASIC PROJECT IDENTIFICATION DATA
1 Country Philippines
2 Poject Title Training and Development issues
3 Project Number AID Project No 492-0340 AID Loan No 492-V-069
4 Project Dates
a First Project Agreement July 29 1983 b Final Obligation FY 84 c Project Assistance Completion Date (PACD) December 31 1988
5 Project Funding
a AID Bilateral Funding Grant $1200000
b Other Major Donors None Loan $3300000
c Host Country Counterpart Funds $1300000
T 0 T A L $6000000
6 Mode of Implementation Host Country
7 Project Design USAID Philippines and the Govt of the Philippines
8 Responsible Mission Officials (For the full life of the project)
a Mission Director(s) Frederick W Schieck (FY 84 - Present) Anthony M Schwarzwalder (FY 83 - 84)b Project Officer(s) Dominic A DAntonio (FY 86 - present) Richard E Rhoda (FY 83 - 86)
9 Previous Evaluation(s) None
10 Cost of Present Evaluation
Person Days Dollar Costs a Direct Hire
(1) AIDN TDY (2) USAID staff 28b Contract 28 $2800
c Other
--
-aa~a~a-~a~a4-- lta -~ a-a- A- a a -~ a-aaaai ~a ~a
- - - - a-a a-r a-a-~ -i-a ~ ~ -Y -~- - - - aaflt( a-aA~~ ~ 7~j Aa-~ ~a-aa~v
aa-~a~a~a-a~a1gtQ ~ --~A-i~ ~a2aaap ~-aaa a a~--a~ aa ~ ~ a~ a~ja-~aa a~~aa-A~aa ~ - - -~
- ~ a - - -4---a -~ -lta-a ~iaa -~-~ ~ a ~a -4~~ ~ 4---a-a-~a~- a-~a~~ jfla -~ 4~
OF ACRONYf IS ~ -
~a-a-r- - ~ -~a-aaa --- ~a-Y - ~ ~V~a a4a--a~4 ~a-4-aa-lt~-~a~a- a~~aaaaa-V~Y~7--7 ~~~a-a- -gt a -- - ~ ~ a-a-iaA~ ~-a-a-a4~4a 4-aa~i a-aaaaaaa- 4- TIO~ REPORT -
- a~~Ai~W~ a-a- - a-~ a- ~ ~ ~ -4- -~ 4 aia-a -- - a-a~lt ~a~~~-i ~a-~a- ~a-aa-a a~-a -~- a-a -aj-a---~a- - -A$a-akaJ --- ~ a-
~ ~a--~a a-a aa a ~a4a-~A~-~Qj ~ ~ lt a-a-~ ashya a-lt a a- -~ ~ ~4~ a~14~a~a- a7 2aa~ ~f~a ~ a- -- I
a--~a-a-a-a- -a- ~ ~aa--~aa~a a aa~-a-a--------~ aj
Economic Plunning a-and Reseat chaStaff7a aa-~--a-a - a--~ ~-a- 4 ~a--ja-j~ --a-- a-
a a- a-- - a--4~a- a-a-ES I-A Daaaaa-~a E-ononft ~nd SociaL impact AnalysaisWomen din lti~---- -shy- a a- ~a- 4L P a-a
---i--a - aaaaa -~~a- ~ ~ a a- ashy
-~
aaa a- a a-~a -a- a--aa- - ar4 - --ashyaa-aa-- -~
~I~-GPT General ParticipanC T~dlning a ---r- ~ aj~aa~~ - ~ a a aa- a- a- a 4aaa~ a ~a a-ta~ ashy
a- a a a- ~gt -~ a- ~a-aa- aa- a shy~ a-agt shy
aThEa~A agt flational Economic and D6velopment Authority a- a- gt -agt~4 Waa-arV P a-Wja - shy
a ~a-a-a gt~lt-a-ashyp1io Tra - aa- a aaaa a4~a a Aa shy
ashy~a-a-PAGOa-~ Project Assistance Completion Da~e ~
aa
Th~~a a-aa-a~a a413a ~~Ya ~
a-- -- ~j~5 Philippin~~Insatitute for Development ~ a a a ~a-~ a- a a a a a a a a
-- -~a - aa-ga- aaa-paa-~ a-i ~ ~~ ~ Letterr~ a ~ a a a- ~a-arrOJecL plusmnmpmementau on
a a 4aa- a- a a a a a a- ~ ~~~aa~aaaaagta 4ashya --~ashya a-aa---~a-a aa- -a~a aAl~ a- a aaa4A~aa shy
a ininganci ueveiopment Isues Projectagta-a-a- - ~a - -
a -- gtaaUa a A aa-~a a a- aaa aaaa a~~aa r
a ining andaDevelopment ~ aa a~ alaa-a a a a a-a a~ a a -A- a- a
-a- a- aa ffice a -a-a a a O ~-h 4aa4 a a ~~a-a- a-a-a
a-a a a a-a aaa- aa a a a a-a a
-a- USAID 7 U nited Stat a- a-a a a ~ a~ a a a-a - a-a ~aa a-aaashy
es - aa-a- a-a~gencyfora aX ~ Internatjonal~- aa-a- aa Oevemopmenta a- ~a- a~ a aa-aa-aa-- a a a aa -----------4 a- a a a
Aa a aa-ashy-a--ar
a a- a a a a aa a- a-a-aa -~ agt ~a a-a-a-aaa- aa- a a- a- a-a- a a - a - a -a ~a a-a-aa4aaaaaaaaa-aaa4 a a- a-- - a- a-~ ~a- a- a a 2 a aaa--a aaaa~-aaJ-aa-aa--Kaa-aaa--a-~aaaa-aa-aashy Paaa- 4 a a a - a-- a-a--a-a-a-a-a-ashyaaaa- a-a-a a a a-a a-aaa-a a- shya- a-a a
a a a- a a- a a-a~ a a a ~ - -- a a a - -a- -a
-- 4a~a-~ -a-a~aa-- ashya- a a- a a-a- aa
a- a a - a ~-aaa a- a- 1 a-a-ashy
- a-a- a-a aaa- a ashy
lta a a -a a~ a a a a-a-~ a-ashy
aaJ-a-J alt~aa- a-- a aT a 2 a-a a aa a-a- a a a-a a-a~ a-a4-ia-a-- a-a-~a-a-~a aa- a-a-a a a- a-a-ashya aaa aa-~
a-a a- a-a a- -a a - a- a- ala aa a-a a- a- aa- ~a a- a a- aa-aa a a- a- a a ashy
a-a---ia--a--- a-a-aa-a-~ a-a-aaaa
a- a-a-aaaa-~a-a a a - a- a a- a- aaaa-a-aa-~ a a a- a la-a-a aaa- a a-a- aa aa-aa-a-lta ~-aa~a a a -a- a a a - a- a a- aa- a-~ a-agt 4aa-a-aa4-a-a-a-a a-aa a-a- a a 4 ~a-a- a-a a a aashya a-a a-a- a-ashya~a $aa-a-a~a-a-a4- a~ a- a-aJ a aaa- a- aa a- a- a-aa a-a a-a aa a a-a-a-
aaaIaaaa-a-a-a-a~a a-a- a-a-
a
a- ~a a-a-
a- a a- a-a- a- a a-a-ashya a-a- a- a a a- a-a-44aalt a- a-- a-aa-~ a a-a- aa-~24a4aaaa~aa
a-a- a a- a a- a- a a - a a
~a a~a-a-a-aa-a-a-a aa-a-a a- - ~-a-a a ~ a- a-a a a-a- a- aa~a a-aaa-a a a- aa-aa-a-aashy~a-a-~- a-- aaaa- -aa a 4a a-~a-~a- aaaAa a a-a- a- a-a-a- --- a-a-ashyaa-a-a-~aa-a a~~a- a-a aa-a-aa~aa~a~aaa a- a-a-a-4~a- a a a-a-a-ashya-a-2 a-aaa-gtaa-al a a- aaa~A a-a-a-a-a- a
a-a a-ashya-a-a-a-a a- Jaa-a- a-aa- agt a- aaa aa-a- a a a-3a-a- ~a a-a-a- ~gta-~~~a- 4- 4aa-Aa--------------------a--a- a-a- ~~ a-a- a~~a-Pa-a-a-a-~ 2--a-a- a ~a-aaaa-a4aa-aa-aa- a-a-a-agtaa-aa2aa~a-C-i-a-a a- a-a-- aa-a- - a
- a a-a- a-a----a-a a-a-- - ~aa-~aaa4a a a-a-a- a-gt -a-~ a--4a-a-a-~a-~a- a-a-a- a--a-a---aaa-aaaa--a-aaaa--aa-a--a a-a--a-aa-~a-4a-a-a-~--a--~aaaa--- a a-~a-~ a- a- a-a-a a-a-a4 ashy-- aa-- -aa-a- a-a~--~a-~aa--a-~a- aa-- a~-a- a-aaaaaa-a--a-a-a-a-aaa-a-a-aa-a-a-aa-a-a-a- ~a~a-aSaaa-a4-ashya-~a-a-aa-~aa-la-~a-a~ 2 -a--a-shy
a-a-a aaaaa-a- a-a-a-i aa---a- a-a--a--a aa-a~~-a- aaa-a-a-aaa-a-a-a- -- a- agt a-a-a-a-a-a-a-a-~ a a---- aaa~a-~aaa---aa-Xaa--aa-a-aa-a-a-a-a -shy
- a a ~ ------------shy aaa -------------- a-a-- -a -a-- - a-a-a-a a-a-aa-a-a-a- aa-~
gt7gt a-a-aaa-~aa-aa-a-aa a-- a- la-a a a-a- aaa-aaa- a-a-
4 a-2a- aa~a- -~aa-a a-a-a-a--a- a-a-a-Yaaa-~a-~-aa-3a-aa4yaaa~a-aaaaaaa-a-aa-aa- a-Va-a--a- a- -~ -a-a- a- ~a- 4~ a-a- -a-~ - - - a-4a-aa- aa--a-aa a-a-~ a-a-a-a-a-a-a aa-aa~ -a-
~ a-j-~a-a7~24 a-a- -a-a-a-~a-a-a a-- a-aa-4a-a-4a-4a-a 1
44aaaa- a-a-4- a-~a-a~a-a-aa a-aK ~a~Ca-a-~a-a-Aa-P~aa-a~-a-a-aaa-a-aa-~Aa-ltaa-a(a-aampa-Aa-a-a-aa-a-A aa-aa a a-aa4a-a-44a-aaa-a-gtashy
a-a-a- - ~ lta-a~aa-~a-(a-a--aCpaa-a~ aa~a-~-a-a-a-aaa-aa4-aa-aa~a-aia-a-a-a~a
---- ~ 4 aa~aii4~a~a-iAa-a-aaaaa-a-aaaaa-aaaaa-Aaaaaaa-ia-aa-a-aaa aa-aaa-aa-a-a-Va-P4a4~~aaa-aa-~aa-
a-i a-a a-
-a- ~ a a-~ - a--a- a a-a-a-a--- ~a-a-a-aa-a- a-a-a- a- a
~a-a~a~~a-a- 4-a-a-i a-a- aa-a-a-~~aa-a-~ a-a-~a4aa 4 ~a--a-a- a-Aa-~aVia-aa~a 4- 2- 4- a-a-a~ 4a-a-igt~4~-~a4 4- -shy4a-a-a-ia-a- aa4a-~a4a-a-a2a-a -a-a--aaa-a a-a-a-a a-a--a- a-a-ashy
a -a-4Va--~a-C~a-~a-aa-a-a-4a-aa-4~a-4iaa ~ a-a-a ~a-~ w a-a- -a a-~ a a a-a-a-i a-a-a a~-a-aa-a- a~ taa~a-a-~a4~aa-a-a-aa-a-~-aaaaaa---a-a- aaa-~~a 4 Aa-a- a-a-ashya- a-~ aaa-a-a-a~~Ta-a4~aa a-a-a a- -a--a aa-a-a-a-a -aa-a-aa-~a a-a ashy~ a-~ a-a-aaa~~ a~- a-~aIa- ~ - aa~ia-~a4 a-a-ashy -z~
a- ~ a-Aa-~~ a- -- aa-a-a~aa-aa-a- aAa- a aa-a- a-
XEC IUT VE SU INARy
A PURPOSE OF EVALUATIO The purpose of hi s eulu aci)n s to assess t ie proqess of implementation
of the Traininj and Devel opinent Issues (TDI ) Project identify probl ems andissues that nay have hamsered project progress and recommend measures tomaximize project impact on the develornent effor of the new government
B PROJECT PURPOSE o zJC 2The purpose TheT iS tO ]uoroe t2e apaolit oT the
Philippine Government anl ctiher instI tutions to analyze develoument issues andto make sound and timely C-lont-reiated Jechions
C CONCLUSIONS AND - gt
1 Overall project progress has been relatively slow While training(Participant Trainin2 Corsnent and the training element of the Development n s by and larje on schedule progress ofthe non-trainine nns (rsearch fora teiuicai and management assistanceand equiprne nt Depeloum+n t componentd c mlo o)f h) Dhe s isses has been
painfully slow
This notwi t htanaid nr ci current eviidence supports the continueduserulness of rothie ear + its expressed obiective of buildinq uoinsttut0ional caciies foreen poliiv analysis and relateddecision-makinc The pot2ntial v Iue of the project is further enhanced by
de-isions TD t+- woul - toto nono u pace of project implementation buz aiso expand project benefits and impactand (b) the positive climate under the new government
(a) recent - o the a t o onl yy i rove - e
The slow proress o thO proj It to v-- unI i kelydat e renders the full inmpleImentation of the projec within the curren PACD
Accordingly the follow ing maijor recommend- ~i are herein made
Recomend ation 1
The priject shoul d be toc ninued and the -eeded by t1io years Decenber I 9J
Recornmendati-l 2
Should fo two-yearthe rcn a elttnsin of the PACD beaproved] rti~er evaluat ion of the project - id e underzahen i the first half 191
~Recommen dtioni32
an cosdrtopesing of th ot etsrvcn iffclte and i osdrtoof theidi Fffsed social beneits of the project theS~entire unearmar ed loan allocation to the projetshoul d be converted to
-771-2-Thes-Ioi-prog ress-of tb4e- non training-eImn shs-be-rotd-a in n_7basic int Iretti onai differences bet e te-TDI _PMvOad the USAID Mjsion~ on the~aproach-toproject imletto and the-e lted isueof extraScompensatioqn for gvernmienitpersonnell This i n r slnialeorpolmin the cornrunication process jbetwen the two 4parties~At thejdesign stage ~ more extensive discussions werepreVented bamptimersue-bo happroaching US bu dgetary deadl ines At the im~lernentE tibon st ge ffective~
specifically Vwlth respect to USAIDs merbership-in thrieitSernlt Commi-ttee and (b) the fact that 4 both the USAID Miss ion and1he TDI Pon Sendscompeting claims on staff time rendered it difficultgtfor closerattenti on to bedevoted -to project concerns~~
Inlight of the foregoing the followingrecommendations~are made J j Recommendation 4 4
To enhance smooth and timely implementation~o fthe p-oject as awoead in particular ofthe non-training~e ementsor the Devel4opment Issues~
- component acl1ear resol ution of the problem issues_should be 1made and 4agreements
shyreached clearly set out44in projqc~t imp emetation letter iilt7iAlso to the extentTneeded to resolve uncertainiies 4or ambiguitiesyconcerning administrative aspectsofpoet imlemnain - Isisampulbe issued 4that clearly set-out USAID gu(inclns and proexemptions that -may be6greeudtupon)1 y d pon - V 4e4-
Recommendation 5 Tthe extet eded for4 smooth impjlementain I cenewJf~il
managementof the pr jct at-1both the TDI-T 4 ad -theUSAID ends shoul d ~ -devote miore timne to the- ranagement of the-project Mor 1etiMLe is clearly4--needed in the immeidiate fut-ure to resoIveba sic is sues clarify 4if~
-4shy
regulations and establ ish4 ruie procedres~I4~4
Recommendation 6 4
In the specific case of te non taning eImnsoFthe Devel opment Aigtises comnponent it ils t hat arecommended t eias a porton 0 ~ ~~management dutiles be transferred to the Phlppine Institute for 4-4----~shy
shy_ ~ z Developmient Studies(PIDS) which hasexperience in the4 maaeeto4researchi and iiS1 procedures
11i Il iw4
0ctob~ b3 Te p98 7Wrso nteTD saar- has ~Produced veryencouraging ejiysbiss Ifls1ronsto e yejeer Proposal Sane the TDI PMO hpas decifded to convene s-Imilar workshopsi h~tre ona regul ar bsspss-by wc a y 1rZgtTI- ecision is stronglyendorsed 4 ~gtosbjtc
InI addtinoever parallel acinwl ndtob taken in othei ctimpa
pr je
~~ The six areas tha~t ha-ve been selcted7 as prioriti - -h anarrtrelated actfitij s fo0 stanpcl ~id
iare deme so broad th~at pro1 ect acriis n Mact would tend -to be too di~~Afft-- Ac4nq5
finer fouigof the Research Agenda should b unetkn uhtaproject activities are limited toa smal inumber of development issues~------- ~deemedcriticalunder the new governImentttetnl~2PThrey
resources of a larger numbwer ofinsti ucions can be applied to a-particular~issue produce more extensive as well1 as more iidepthiigt -- analysis fnd altogethier maximize project impDactjb)While curirenit iplementation procedures
- ~ elements1of the eel opment coverinoIssues Component are- design9edthe o-traininto~ ngmtehcompetitiv~e niature of a~ad~encourage broad participationandensure cons istency witi-pojc purpiose thei rj tie-consumi ng character tends to4plusmn4v effecti Yely rule out use of the proj ect for urgnt shor$t-termpohi -ity44 issues and their rigidity limits the~ability of project managmnt
444 -- iitiate quickI relevant coiisul tancies Accordingly gmn Recommendat ion Gi4 Impl ementa tion procedureN
)444shld be difi ei toal1owgeae Aiscretionary powers4 to the TDI-PM0 Specjif44 cally the TDI -PMObe authiorized to approvewithout furthj should Commi ttee or ned of eitherSt44ering~USAID approval 4 proposals ridcotas ontpista 444have4 been previous y cleared 1e~as4 ela on ~lvant topics thatshy
445a44--y be of Jimmediate urgency 111This 4a~thio~ity howeershul bpshy4~-~4444- imited both a~s4I to the- amount of any-indifdual contract
4 and to the total amount of all such contractsJora say $150001given yearsay~i it
~44444-~4$1 00000 vii 4 4
74 4 ~4i While raining activities have bee proce ding argel on- ched
exit~ coe for improvement in component operation~s ~o enlarge trainingshybee1isand -broaden the i r di stribut ion i 4~4 - 4
7~
-44444 - -
h4~4~-444444
7a) ~Whul sc he ifor io riti Zing9 benefic ary ins~tttons ard fiel ds ojjstudy Ahas been diia n up and Va rgeIy f I Io eld ~he absenceof dei1ed prog ram of t rainingactiY1ti - resu1Ited inh certan i l~neidistribyton ~ among agenc 1es wi th~i npri or ity groupsKa
~of 5studiy~ and~bewe I eta nregionai o fijce s 4is also en b eEthe accomodation of agenc Ie ht
s as 4eI I Id ludy~ th1at wef- as fiL f ltt) out(seoK~f establ i sp priorities
As earl ier noted nowever theTDI-PM~O has recentlyKapproved speci fi c - xcproposals to correct4 these jrnibalaance These inclu~de 1i)forniu1 ationof a oedea e prog ram for trlnnf iers of the project d~ration
WioselmDremenedtation t1p m arograts S partial-shifting of the trainin6g budget -from overseastKo local traTi n in
i)th upadadjustments in stpnrae )OIafllwances and Kvjyresea rch LiesiS al IOwahces urider Iocdl11 tvilo fiijgrants to enhance theirSVKatt ractiveness expansion off6nding-support underthpoeto
include training insuitable ~fields ihn selected isitt teinlsof~learning in-the country~and iv) broadening institutionial and regionalparti~cipation in the~trann 0opo~amp -riig compnent
$AlI of the fore_goi ng recommendati ns are hereinK endorsed In addi tion Re ot meond 1
KKK K
K ~ cobnatinthIUKK If somdnr-sise prjcs not KK K shiftingKKK
A)Whie ssesetof henodistributon fo1ields)toi o finininpcif K beween thegenraenvK i antd egn oel setortesse asytt es
~KKK~KKo enbl csounb andertaken to fl~ Kthexentto4hjit7tprojyectfne Khe Kriig objctve foispoen hisr acivd the K~KK K
KKAnito Kg Kine eficedmediatelyV~KKKKKsytm eniioe tpe beprojectsshould KKKestablished KKK a c~K v a d
K KK
I BACKGROUND
The Training and Development Issues (TD) Project was designed to improve
the capability of the Philippine Government and other institutions to analyze
development issues and to make sound and timely development related
decisions This objective was sought to be achieved mainly through training
and the conduct of research and related activities on a small number of issues
deemed critical to the sustained pursuit of Philippine development
The project was conceived to address perceii gips in the USAID
assistance program to the Philippines First most previous research
activities had not focused on developing the information needed for effective
decision-making and policy review Second general participant training
projects had lacked specific focus and supporting activities thereby limiting
their impact And third sectorally focused institutional development
projects often could not fully a-hieve their development objectives because
many key policy related factors affecting project success were beyond the
control of the implementing agency
Under the Project Agreement vwhich was signed on 29 July 1983 USAID
committed to provide a total of $42 million in loans ($33 million) and
grants ($09 million) Of this amount $25 million was allocated to the
Development Issues Component and $16 million to the Training Conponent with
$100000 set aside for evaluation USAID funding for the project was
subsequently raised by a $3U0000 grant that brought the total USAID
commi tnent to $45 million Government counterpart funding amounted to $15
million PACD aas set at 31 December 1938
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
TABLE OF CONTENTS
PageEXECUTIVE SUMMARY i-iv
I BACKGROUND 1
II PROJECT STATUS 2
Financial Status 2- 4 Activity Status 4
III NON-TRAINING EL-MENTS OF TDI 5
A Divergence of Views on Approach 6 - 7 to Project Implementation
B Communication Problems - 108
C Component Management II
D Implementation Procedures 12
IV TRAINING 13
A Pace of implementation 13
B Objectives of Training Activities 14
C Overall Consistency with Priorities 15 - 17
0 Areas for Improvement 18 - 19
E Usefulness of Training 20
V PROJECT SIGNIFICANCE AND OLTLOOK 21 - 23
Vi RECOMMENDATIONS 23 - 29
LIST OF TABLES
Table I Financial Analysis Loans and Grants
Table 2 Financial Analysis Training and Non-Training
Table 3 Training Funded Under TDI Distribution by Agency
Table 4 Training Funded Under TDI Distribution by Field of Study
A N NE X E S
A Financial Analysis Table
B Prioritization Scheme for Training
C Training Funded Under TDI
D Status of On-going TDI Research Projects
APPENDICES
1 Scope of Work for Evaluation
2 List of Persons interviewed
3 Key Documents Reviewed
BASIC PROJECT IDENTIFICATION DATA
1 Country Philippines
2 Poject Title Training and Development issues
3 Project Number AID Project No 492-0340 AID Loan No 492-V-069
4 Project Dates
a First Project Agreement July 29 1983 b Final Obligation FY 84 c Project Assistance Completion Date (PACD) December 31 1988
5 Project Funding
a AID Bilateral Funding Grant $1200000
b Other Major Donors None Loan $3300000
c Host Country Counterpart Funds $1300000
T 0 T A L $6000000
6 Mode of Implementation Host Country
7 Project Design USAID Philippines and the Govt of the Philippines
8 Responsible Mission Officials (For the full life of the project)
a Mission Director(s) Frederick W Schieck (FY 84 - Present) Anthony M Schwarzwalder (FY 83 - 84)b Project Officer(s) Dominic A DAntonio (FY 86 - present) Richard E Rhoda (FY 83 - 86)
9 Previous Evaluation(s) None
10 Cost of Present Evaluation
Person Days Dollar Costs a Direct Hire
(1) AIDN TDY (2) USAID staff 28b Contract 28 $2800
c Other
--
-aa~a~a-~a~a4-- lta -~ a-a- A- a a -~ a-aaaai ~a ~a
- - - - a-a a-r a-a-~ -i-a ~ ~ -Y -~- - - - aaflt( a-aA~~ ~ 7~j Aa-~ ~a-aa~v
aa-~a~a~a-a~a1gtQ ~ --~A-i~ ~a2aaap ~-aaa a a~--a~ aa ~ ~ a~ a~ja-~aa a~~aa-A~aa ~ - - -~
- ~ a - - -4---a -~ -lta-a ~iaa -~-~ ~ a ~a -4~~ ~ 4---a-a-~a~- a-~a~~ jfla -~ 4~
OF ACRONYf IS ~ -
~a-a-r- - ~ -~a-aaa --- ~a-Y - ~ ~V~a a4a--a~4 ~a-4-aa-lt~-~a~a- a~~aaaaa-V~Y~7--7 ~~~a-a- -gt a -- - ~ ~ a-a-iaA~ ~-a-a-a4~4a 4-aa~i a-aaaaaaa- 4- TIO~ REPORT -
- a~~Ai~W~ a-a- - a-~ a- ~ ~ ~ -4- -~ 4 aia-a -- - a-a~lt ~a~~~-i ~a-~a- ~a-aa-a a~-a -~- a-a -aj-a---~a- - -A$a-akaJ --- ~ a-
~ ~a--~a a-a aa a ~a4a-~A~-~Qj ~ ~ lt a-a-~ ashya a-lt a a- -~ ~ ~4~ a~14~a~a- a7 2aa~ ~f~a ~ a- -- I
a--~a-a-a-a- -a- ~ ~aa--~aa~a a aa~-a-a--------~ aj
Economic Plunning a-and Reseat chaStaff7a aa-~--a-a - a--~ ~-a- 4 ~a--ja-j~ --a-- a-
a a- a-- - a--4~a- a-a-ES I-A Daaaaa-~a E-ononft ~nd SociaL impact AnalysaisWomen din lti~---- -shy- a a- ~a- 4L P a-a
---i--a - aaaaa -~~a- ~ ~ a a- ashy
-~
aaa a- a a-~a -a- a--aa- - ar4 - --ashyaa-aa-- -~
~I~-GPT General ParticipanC T~dlning a ---r- ~ aj~aa~~ - ~ a a aa- a- a- a 4aaa~ a ~a a-ta~ ashy
a- a a a- ~gt -~ a- ~a-aa- aa- a shy~ a-agt shy
aThEa~A agt flational Economic and D6velopment Authority a- a- gt -agt~4 Waa-arV P a-Wja - shy
a ~a-a-a gt~lt-a-ashyp1io Tra - aa- a aaaa a4~a a Aa shy
ashy~a-a-PAGOa-~ Project Assistance Completion Da~e ~
aa
Th~~a a-aa-a~a a413a ~~Ya ~
a-- -- ~j~5 Philippin~~Insatitute for Development ~ a a a ~a-~ a- a a a a a a a a
-- -~a - aa-ga- aaa-paa-~ a-i ~ ~~ ~ Letterr~ a ~ a a a- ~a-arrOJecL plusmnmpmementau on
a a 4aa- a- a a a a a a- ~ ~~~aa~aaaaagta 4ashya --~ashya a-aa---~a-a aa- -a~a aAl~ a- a aaa4A~aa shy
a ininganci ueveiopment Isues Projectagta-a-a- - ~a - -
a -- gtaaUa a A aa-~a a a- aaa aaaa a~~aa r
a ining andaDevelopment ~ aa a~ alaa-a a a a a-a a~ a a -A- a- a
-a- a- aa ffice a -a-a a a O ~-h 4aa4 a a ~~a-a- a-a-a
a-a a a a-a aaa- aa a a a a-a a
-a- USAID 7 U nited Stat a- a-a a a ~ a~ a a a-a - a-a ~aa a-aaashy
es - aa-a- a-a~gencyfora aX ~ Internatjonal~- aa-a- aa Oevemopmenta a- ~a- a~ a aa-aa-aa-- a a a aa -----------4 a- a a a
Aa a aa-ashy-a--ar
a a- a a a a aa a- a-a-aa -~ agt ~a a-a-a-aaa- aa- a a- a- a-a- a a - a - a -a ~a a-a-aa4aaaaaaaaa-aaa4 a a- a-- - a- a-~ ~a- a- a a 2 a aaa--a aaaa~-aaJ-aa-aa--Kaa-aaa--a-~aaaa-aa-aashy Paaa- 4 a a a - a-- a-a--a-a-a-a-a-ashyaaaa- a-a-a a a a-a a-aaa-a a- shya- a-a a
a a a- a a- a a-a~ a a a ~ - -- a a a - -a- -a
-- 4a~a-~ -a-a~aa-- ashya- a a- a a-a- aa
a- a a - a ~-aaa a- a- 1 a-a-ashy
- a-a- a-a aaa- a ashy
lta a a -a a~ a a a a-a-~ a-ashy
aaJ-a-J alt~aa- a-- a aT a 2 a-a a aa a-a- a a a-a a-a~ a-a4-ia-a-- a-a-~a-a-~a aa- a-a-a a a- a-a-ashya aaa aa-~
a-a a- a-a a- -a a - a- a- ala aa a-a a- a- aa- ~a a- a a- aa-aa a a- a- a a ashy
a-a---ia--a--- a-a-aa-a-~ a-a-aaaa
a- a-a-aaaa-~a-a a a - a- a a- a- aaaa-a-aa-~ a a a- a la-a-a aaa- a a-a- aa aa-aa-a-lta ~-aa~a a a -a- a a a - a- a a- aa- a-~ a-agt 4aa-a-aa4-a-a-a-a a-aa a-a- a a 4 ~a-a- a-a a a aashya a-a a-a- a-ashya~a $aa-a-a~a-a-a4- a~ a- a-aJ a aaa- a- aa a- a- a-aa a-a a-a aa a a-a-a-
aaaIaaaa-a-a-a-a~a a-a- a-a-
a
a- ~a a-a-
a- a a- a-a- a- a a-a-ashya a-a- a- a a a- a-a-44aalt a- a-- a-aa-~ a a-a- aa-~24a4aaaa~aa
a-a- a a- a a- a- a a - a a
~a a~a-a-a-aa-a-a-a aa-a-a a- - ~-a-a a ~ a- a-a a a-a- a- aa~a a-aaa-a a a- aa-aa-a-aashy~a-a-~- a-- aaaa- -aa a 4a a-~a-~a- aaaAa a a-a- a- a-a-a- --- a-a-ashyaa-a-a-~aa-a a~~a- a-a aa-a-aa~aa~a~aaa a- a-a-a-4~a- a a a-a-a-ashya-a-2 a-aaa-gtaa-al a a- aaa~A a-a-a-a-a- a
a-a a-ashya-a-a-a-a a- Jaa-a- a-aa- agt a- aaa aa-a- a a a-3a-a- ~a a-a-a- ~gta-~~~a- 4- 4aa-Aa--------------------a--a- a-a- ~~ a-a- a~~a-Pa-a-a-a-~ 2--a-a- a ~a-aaaa-a4aa-aa-aa- a-a-a-agtaa-aa2aa~a-C-i-a-a a- a-a-- aa-a- - a
- a a-a- a-a----a-a a-a-- - ~aa-~aaa4a a a-a-a- a-gt -a-~ a--4a-a-a-~a-~a- a-a-a- a--a-a---aaa-aaaa--a-aaaa--aa-a--a a-a--a-aa-~a-4a-a-a-~--a--~aaaa--- a a-~a-~ a- a- a-a-a a-a-a4 ashy-- aa-- -aa-a- a-a~--~a-~aa--a-~a- aa-- a~-a- a-aaaaaa-a--a-a-a-a-aaa-a-a-aa-a-a-aa-a-a-a- ~a~a-aSaaa-a4-ashya-~a-a-aa-~aa-la-~a-a~ 2 -a--a-shy
a-a-a aaaaa-a- a-a-a-i aa---a- a-a--a--a aa-a~~-a- aaa-a-a-aaa-a-a-a- -- a- agt a-a-a-a-a-a-a-a-~ a a---- aaa~a-~aaa---aa-Xaa--aa-a-aa-a-a-a-a -shy
- a a ~ ------------shy aaa -------------- a-a-- -a -a-- - a-a-a-a a-a-aa-a-a-a- aa-~
gt7gt a-a-aaa-~aa-aa-a-aa a-- a- la-a a a-a- aaa-aaa- a-a-
4 a-2a- aa~a- -~aa-a a-a-a-a--a- a-a-a-Yaaa-~a-~-aa-3a-aa4yaaa~a-aaaaaaa-a-aa-aa- a-Va-a--a- a- -~ -a-a- a- ~a- 4~ a-a- -a-~ - - - a-4a-aa- aa--a-aa a-a-~ a-a-a-a-a-a-a aa-aa~ -a-
~ a-j-~a-a7~24 a-a- -a-a-a-~a-a-a a-- a-aa-4a-a-4a-4a-a 1
44aaaa- a-a-4- a-~a-a~a-a-aa a-aK ~a~Ca-a-~a-a-Aa-P~aa-a~-a-a-aaa-a-aa-~Aa-ltaa-a(a-aampa-Aa-a-a-aa-a-A aa-aa a a-aa4a-a-44a-aaa-a-gtashy
a-a-a- - ~ lta-a~aa-~a-(a-a--aCpaa-a~ aa~a-~-a-a-a-aaa-aa4-aa-aa~a-aia-a-a-a~a
---- ~ 4 aa~aii4~a~a-iAa-a-aaaaa-a-aaaaa-aaaaa-Aaaaaaa-ia-aa-a-aaa aa-aaa-aa-a-a-Va-P4a4~~aaa-aa-~aa-
a-i a-a a-
-a- ~ a a-~ - a--a- a a-a-a-a--- ~a-a-a-aa-a- a-a-a- a- a
~a-a~a~~a-a- 4-a-a-i a-a- aa-a-a-~~aa-a-~ a-a-~a4aa 4 ~a--a-a- a-Aa-~aVia-aa~a 4- 2- 4- a-a-a~ 4a-a-igt~4~-~a4 4- -shy4a-a-a-ia-a- aa4a-~a4a-a-a2a-a -a-a--aaa-a a-a-a-a a-a--a- a-a-ashy
a -a-4Va--~a-C~a-~a-aa-a-a-4a-aa-4~a-4iaa ~ a-a-a ~a-~ w a-a- -a a-~ a a a-a-a-i a-a-a a~-a-aa-a- a~ taa~a-a-~a4~aa-a-a-aa-a-~-aaaaaa---a-a- aaa-~~a 4 Aa-a- a-a-ashya- a-~ aaa-a-a-a~~Ta-a4~aa a-a-a a- -a--a aa-a-a-a-a -aa-a-aa-~a a-a ashy~ a-~ a-a-aaa~~ a~- a-~aIa- ~ - aa~ia-~a4 a-a-ashy -z~
a- ~ a-Aa-~~ a- -- aa-a-a~aa-aa-a- aAa- a aa-a- a-
XEC IUT VE SU INARy
A PURPOSE OF EVALUATIO The purpose of hi s eulu aci)n s to assess t ie proqess of implementation
of the Traininj and Devel opinent Issues (TDI ) Project identify probl ems andissues that nay have hamsered project progress and recommend measures tomaximize project impact on the develornent effor of the new government
B PROJECT PURPOSE o zJC 2The purpose TheT iS tO ]uoroe t2e apaolit oT the
Philippine Government anl ctiher instI tutions to analyze develoument issues andto make sound and timely C-lont-reiated Jechions
C CONCLUSIONS AND - gt
1 Overall project progress has been relatively slow While training(Participant Trainin2 Corsnent and the training element of the Development n s by and larje on schedule progress ofthe non-trainine nns (rsearch fora teiuicai and management assistanceand equiprne nt Depeloum+n t componentd c mlo o)f h) Dhe s isses has been
painfully slow
This notwi t htanaid nr ci current eviidence supports the continueduserulness of rothie ear + its expressed obiective of buildinq uoinsttut0ional caciies foreen poliiv analysis and relateddecision-makinc The pot2ntial v Iue of the project is further enhanced by
de-isions TD t+- woul - toto nono u pace of project implementation buz aiso expand project benefits and impactand (b) the positive climate under the new government
(a) recent - o the a t o onl yy i rove - e
The slow proress o thO proj It to v-- unI i kelydat e renders the full inmpleImentation of the projec within the curren PACD
Accordingly the follow ing maijor recommend- ~i are herein made
Recomend ation 1
The priject shoul d be toc ninued and the -eeded by t1io years Decenber I 9J
Recornmendati-l 2
Should fo two-yearthe rcn a elttnsin of the PACD beaproved] rti~er evaluat ion of the project - id e underzahen i the first half 191
~Recommen dtioni32
an cosdrtopesing of th ot etsrvcn iffclte and i osdrtoof theidi Fffsed social beneits of the project theS~entire unearmar ed loan allocation to the projetshoul d be converted to
-771-2-Thes-Ioi-prog ress-of tb4e- non training-eImn shs-be-rotd-a in n_7basic int Iretti onai differences bet e te-TDI _PMvOad the USAID Mjsion~ on the~aproach-toproject imletto and the-e lted isueof extraScompensatioqn for gvernmienitpersonnell This i n r slnialeorpolmin the cornrunication process jbetwen the two 4parties~At thejdesign stage ~ more extensive discussions werepreVented bamptimersue-bo happroaching US bu dgetary deadl ines At the im~lernentE tibon st ge ffective~
specifically Vwlth respect to USAIDs merbership-in thrieitSernlt Commi-ttee and (b) the fact that 4 both the USAID Miss ion and1he TDI Pon Sendscompeting claims on staff time rendered it difficultgtfor closerattenti on to bedevoted -to project concerns~~
Inlight of the foregoing the followingrecommendations~are made J j Recommendation 4 4
To enhance smooth and timely implementation~o fthe p-oject as awoead in particular ofthe non-training~e ementsor the Devel4opment Issues~
- component acl1ear resol ution of the problem issues_should be 1made and 4agreements
shyreached clearly set out44in projqc~t imp emetation letter iilt7iAlso to the extentTneeded to resolve uncertainiies 4or ambiguitiesyconcerning administrative aspectsofpoet imlemnain - Isisampulbe issued 4that clearly set-out USAID gu(inclns and proexemptions that -may be6greeudtupon)1 y d pon - V 4e4-
Recommendation 5 Tthe extet eded for4 smooth impjlementain I cenewJf~il
managementof the pr jct at-1both the TDI-T 4 ad -theUSAID ends shoul d ~ -devote miore timne to the- ranagement of the-project Mor 1etiMLe is clearly4--needed in the immeidiate fut-ure to resoIveba sic is sues clarify 4if~
-4shy
regulations and establ ish4 ruie procedres~I4~4
Recommendation 6 4
In the specific case of te non taning eImnsoFthe Devel opment Aigtises comnponent it ils t hat arecommended t eias a porton 0 ~ ~~management dutiles be transferred to the Phlppine Institute for 4-4----~shy
shy_ ~ z Developmient Studies(PIDS) which hasexperience in the4 maaeeto4researchi and iiS1 procedures
11i Il iw4
0ctob~ b3 Te p98 7Wrso nteTD saar- has ~Produced veryencouraging ejiysbiss Ifls1ronsto e yejeer Proposal Sane the TDI PMO hpas decifded to convene s-Imilar workshopsi h~tre ona regul ar bsspss-by wc a y 1rZgtTI- ecision is stronglyendorsed 4 ~gtosbjtc
InI addtinoever parallel acinwl ndtob taken in othei ctimpa
pr je
~~ The six areas tha~t ha-ve been selcted7 as prioriti - -h anarrtrelated actfitij s fo0 stanpcl ~id
iare deme so broad th~at pro1 ect acriis n Mact would tend -to be too di~~Afft-- Ac4nq5
finer fouigof the Research Agenda should b unetkn uhtaproject activities are limited toa smal inumber of development issues~------- ~deemedcriticalunder the new governImentttetnl~2PThrey
resources of a larger numbwer ofinsti ucions can be applied to a-particular~issue produce more extensive as well1 as more iidepthiigt -- analysis fnd altogethier maximize project impDactjb)While curirenit iplementation procedures
- ~ elements1of the eel opment coverinoIssues Component are- design9edthe o-traininto~ ngmtehcompetitiv~e niature of a~ad~encourage broad participationandensure cons istency witi-pojc purpiose thei rj tie-consumi ng character tends to4plusmn4v effecti Yely rule out use of the proj ect for urgnt shor$t-termpohi -ity44 issues and their rigidity limits the~ability of project managmnt
444 -- iitiate quickI relevant coiisul tancies Accordingly gmn Recommendat ion Gi4 Impl ementa tion procedureN
)444shld be difi ei toal1owgeae Aiscretionary powers4 to the TDI-PM0 Specjif44 cally the TDI -PMObe authiorized to approvewithout furthj should Commi ttee or ned of eitherSt44ering~USAID approval 4 proposals ridcotas ontpista 444have4 been previous y cleared 1e~as4 ela on ~lvant topics thatshy
445a44--y be of Jimmediate urgency 111This 4a~thio~ity howeershul bpshy4~-~4444- imited both a~s4I to the- amount of any-indifdual contract
4 and to the total amount of all such contractsJora say $150001given yearsay~i it
~44444-~4$1 00000 vii 4 4
74 4 ~4i While raining activities have bee proce ding argel on- ched
exit~ coe for improvement in component operation~s ~o enlarge trainingshybee1isand -broaden the i r di stribut ion i 4~4 - 4
7~
-44444 - -
h4~4~-444444
7a) ~Whul sc he ifor io riti Zing9 benefic ary ins~tttons ard fiel ds ojjstudy Ahas been diia n up and Va rgeIy f I Io eld ~he absenceof dei1ed prog ram of t rainingactiY1ti - resu1Ited inh certan i l~neidistribyton ~ among agenc 1es wi th~i npri or ity groupsKa
~of 5studiy~ and~bewe I eta nregionai o fijce s 4is also en b eEthe accomodation of agenc Ie ht
s as 4eI I Id ludy~ th1at wef- as fiL f ltt) out(seoK~f establ i sp priorities
As earl ier noted nowever theTDI-PM~O has recentlyKapproved speci fi c - xcproposals to correct4 these jrnibalaance These inclu~de 1i)forniu1 ationof a oedea e prog ram for trlnnf iers of the project d~ration
WioselmDremenedtation t1p m arograts S partial-shifting of the trainin6g budget -from overseastKo local traTi n in
i)th upadadjustments in stpnrae )OIafllwances and Kvjyresea rch LiesiS al IOwahces urider Iocdl11 tvilo fiijgrants to enhance theirSVKatt ractiveness expansion off6nding-support underthpoeto
include training insuitable ~fields ihn selected isitt teinlsof~learning in-the country~and iv) broadening institutionial and regionalparti~cipation in the~trann 0opo~amp -riig compnent
$AlI of the fore_goi ng recommendati ns are hereinK endorsed In addi tion Re ot meond 1
KKK K
K ~ cobnatinthIUKK If somdnr-sise prjcs not KK K shiftingKKK
A)Whie ssesetof henodistributon fo1ields)toi o finininpcif K beween thegenraenvK i antd egn oel setortesse asytt es
~KKK~KKo enbl csounb andertaken to fl~ Kthexentto4hjit7tprojyectfne Khe Kriig objctve foispoen hisr acivd the K~KK K
KKAnito Kg Kine eficedmediatelyV~KKKKKsytm eniioe tpe beprojectsshould KKKestablished KKK a c~K v a d
K KK
I BACKGROUND
The Training and Development Issues (TD) Project was designed to improve
the capability of the Philippine Government and other institutions to analyze
development issues and to make sound and timely development related
decisions This objective was sought to be achieved mainly through training
and the conduct of research and related activities on a small number of issues
deemed critical to the sustained pursuit of Philippine development
The project was conceived to address perceii gips in the USAID
assistance program to the Philippines First most previous research
activities had not focused on developing the information needed for effective
decision-making and policy review Second general participant training
projects had lacked specific focus and supporting activities thereby limiting
their impact And third sectorally focused institutional development
projects often could not fully a-hieve their development objectives because
many key policy related factors affecting project success were beyond the
control of the implementing agency
Under the Project Agreement vwhich was signed on 29 July 1983 USAID
committed to provide a total of $42 million in loans ($33 million) and
grants ($09 million) Of this amount $25 million was allocated to the
Development Issues Component and $16 million to the Training Conponent with
$100000 set aside for evaluation USAID funding for the project was
subsequently raised by a $3U0000 grant that brought the total USAID
commi tnent to $45 million Government counterpart funding amounted to $15
million PACD aas set at 31 December 1938
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
A N NE X E S
A Financial Analysis Table
B Prioritization Scheme for Training
C Training Funded Under TDI
D Status of On-going TDI Research Projects
APPENDICES
1 Scope of Work for Evaluation
2 List of Persons interviewed
3 Key Documents Reviewed
BASIC PROJECT IDENTIFICATION DATA
1 Country Philippines
2 Poject Title Training and Development issues
3 Project Number AID Project No 492-0340 AID Loan No 492-V-069
4 Project Dates
a First Project Agreement July 29 1983 b Final Obligation FY 84 c Project Assistance Completion Date (PACD) December 31 1988
5 Project Funding
a AID Bilateral Funding Grant $1200000
b Other Major Donors None Loan $3300000
c Host Country Counterpart Funds $1300000
T 0 T A L $6000000
6 Mode of Implementation Host Country
7 Project Design USAID Philippines and the Govt of the Philippines
8 Responsible Mission Officials (For the full life of the project)
a Mission Director(s) Frederick W Schieck (FY 84 - Present) Anthony M Schwarzwalder (FY 83 - 84)b Project Officer(s) Dominic A DAntonio (FY 86 - present) Richard E Rhoda (FY 83 - 86)
9 Previous Evaluation(s) None
10 Cost of Present Evaluation
Person Days Dollar Costs a Direct Hire
(1) AIDN TDY (2) USAID staff 28b Contract 28 $2800
c Other
--
-aa~a~a-~a~a4-- lta -~ a-a- A- a a -~ a-aaaai ~a ~a
- - - - a-a a-r a-a-~ -i-a ~ ~ -Y -~- - - - aaflt( a-aA~~ ~ 7~j Aa-~ ~a-aa~v
aa-~a~a~a-a~a1gtQ ~ --~A-i~ ~a2aaap ~-aaa a a~--a~ aa ~ ~ a~ a~ja-~aa a~~aa-A~aa ~ - - -~
- ~ a - - -4---a -~ -lta-a ~iaa -~-~ ~ a ~a -4~~ ~ 4---a-a-~a~- a-~a~~ jfla -~ 4~
OF ACRONYf IS ~ -
~a-a-r- - ~ -~a-aaa --- ~a-Y - ~ ~V~a a4a--a~4 ~a-4-aa-lt~-~a~a- a~~aaaaa-V~Y~7--7 ~~~a-a- -gt a -- - ~ ~ a-a-iaA~ ~-a-a-a4~4a 4-aa~i a-aaaaaaa- 4- TIO~ REPORT -
- a~~Ai~W~ a-a- - a-~ a- ~ ~ ~ -4- -~ 4 aia-a -- - a-a~lt ~a~~~-i ~a-~a- ~a-aa-a a~-a -~- a-a -aj-a---~a- - -A$a-akaJ --- ~ a-
~ ~a--~a a-a aa a ~a4a-~A~-~Qj ~ ~ lt a-a-~ ashya a-lt a a- -~ ~ ~4~ a~14~a~a- a7 2aa~ ~f~a ~ a- -- I
a--~a-a-a-a- -a- ~ ~aa--~aa~a a aa~-a-a--------~ aj
Economic Plunning a-and Reseat chaStaff7a aa-~--a-a - a--~ ~-a- 4 ~a--ja-j~ --a-- a-
a a- a-- - a--4~a- a-a-ES I-A Daaaaa-~a E-ononft ~nd SociaL impact AnalysaisWomen din lti~---- -shy- a a- ~a- 4L P a-a
---i--a - aaaaa -~~a- ~ ~ a a- ashy
-~
aaa a- a a-~a -a- a--aa- - ar4 - --ashyaa-aa-- -~
~I~-GPT General ParticipanC T~dlning a ---r- ~ aj~aa~~ - ~ a a aa- a- a- a 4aaa~ a ~a a-ta~ ashy
a- a a a- ~gt -~ a- ~a-aa- aa- a shy~ a-agt shy
aThEa~A agt flational Economic and D6velopment Authority a- a- gt -agt~4 Waa-arV P a-Wja - shy
a ~a-a-a gt~lt-a-ashyp1io Tra - aa- a aaaa a4~a a Aa shy
ashy~a-a-PAGOa-~ Project Assistance Completion Da~e ~
aa
Th~~a a-aa-a~a a413a ~~Ya ~
a-- -- ~j~5 Philippin~~Insatitute for Development ~ a a a ~a-~ a- a a a a a a a a
-- -~a - aa-ga- aaa-paa-~ a-i ~ ~~ ~ Letterr~ a ~ a a a- ~a-arrOJecL plusmnmpmementau on
a a 4aa- a- a a a a a a- ~ ~~~aa~aaaaagta 4ashya --~ashya a-aa---~a-a aa- -a~a aAl~ a- a aaa4A~aa shy
a ininganci ueveiopment Isues Projectagta-a-a- - ~a - -
a -- gtaaUa a A aa-~a a a- aaa aaaa a~~aa r
a ining andaDevelopment ~ aa a~ alaa-a a a a a-a a~ a a -A- a- a
-a- a- aa ffice a -a-a a a O ~-h 4aa4 a a ~~a-a- a-a-a
a-a a a a-a aaa- aa a a a a-a a
-a- USAID 7 U nited Stat a- a-a a a ~ a~ a a a-a - a-a ~aa a-aaashy
es - aa-a- a-a~gencyfora aX ~ Internatjonal~- aa-a- aa Oevemopmenta a- ~a- a~ a aa-aa-aa-- a a a aa -----------4 a- a a a
Aa a aa-ashy-a--ar
a a- a a a a aa a- a-a-aa -~ agt ~a a-a-a-aaa- aa- a a- a- a-a- a a - a - a -a ~a a-a-aa4aaaaaaaaa-aaa4 a a- a-- - a- a-~ ~a- a- a a 2 a aaa--a aaaa~-aaJ-aa-aa--Kaa-aaa--a-~aaaa-aa-aashy Paaa- 4 a a a - a-- a-a--a-a-a-a-a-ashyaaaa- a-a-a a a a-a a-aaa-a a- shya- a-a a
a a a- a a- a a-a~ a a a ~ - -- a a a - -a- -a
-- 4a~a-~ -a-a~aa-- ashya- a a- a a-a- aa
a- a a - a ~-aaa a- a- 1 a-a-ashy
- a-a- a-a aaa- a ashy
lta a a -a a~ a a a a-a-~ a-ashy
aaJ-a-J alt~aa- a-- a aT a 2 a-a a aa a-a- a a a-a a-a~ a-a4-ia-a-- a-a-~a-a-~a aa- a-a-a a a- a-a-ashya aaa aa-~
a-a a- a-a a- -a a - a- a- ala aa a-a a- a- aa- ~a a- a a- aa-aa a a- a- a a ashy
a-a---ia--a--- a-a-aa-a-~ a-a-aaaa
a- a-a-aaaa-~a-a a a - a- a a- a- aaaa-a-aa-~ a a a- a la-a-a aaa- a a-a- aa aa-aa-a-lta ~-aa~a a a -a- a a a - a- a a- aa- a-~ a-agt 4aa-a-aa4-a-a-a-a a-aa a-a- a a 4 ~a-a- a-a a a aashya a-a a-a- a-ashya~a $aa-a-a~a-a-a4- a~ a- a-aJ a aaa- a- aa a- a- a-aa a-a a-a aa a a-a-a-
aaaIaaaa-a-a-a-a~a a-a- a-a-
a
a- ~a a-a-
a- a a- a-a- a- a a-a-ashya a-a- a- a a a- a-a-44aalt a- a-- a-aa-~ a a-a- aa-~24a4aaaa~aa
a-a- a a- a a- a- a a - a a
~a a~a-a-a-aa-a-a-a aa-a-a a- - ~-a-a a ~ a- a-a a a-a- a- aa~a a-aaa-a a a- aa-aa-a-aashy~a-a-~- a-- aaaa- -aa a 4a a-~a-~a- aaaAa a a-a- a- a-a-a- --- a-a-ashyaa-a-a-~aa-a a~~a- a-a aa-a-aa~aa~a~aaa a- a-a-a-4~a- a a a-a-a-ashya-a-2 a-aaa-gtaa-al a a- aaa~A a-a-a-a-a- a
a-a a-ashya-a-a-a-a a- Jaa-a- a-aa- agt a- aaa aa-a- a a a-3a-a- ~a a-a-a- ~gta-~~~a- 4- 4aa-Aa--------------------a--a- a-a- ~~ a-a- a~~a-Pa-a-a-a-~ 2--a-a- a ~a-aaaa-a4aa-aa-aa- a-a-a-agtaa-aa2aa~a-C-i-a-a a- a-a-- aa-a- - a
- a a-a- a-a----a-a a-a-- - ~aa-~aaa4a a a-a-a- a-gt -a-~ a--4a-a-a-~a-~a- a-a-a- a--a-a---aaa-aaaa--a-aaaa--aa-a--a a-a--a-aa-~a-4a-a-a-~--a--~aaaa--- a a-~a-~ a- a- a-a-a a-a-a4 ashy-- aa-- -aa-a- a-a~--~a-~aa--a-~a- aa-- a~-a- a-aaaaaa-a--a-a-a-a-aaa-a-a-aa-a-a-aa-a-a-a- ~a~a-aSaaa-a4-ashya-~a-a-aa-~aa-la-~a-a~ 2 -a--a-shy
a-a-a aaaaa-a- a-a-a-i aa---a- a-a--a--a aa-a~~-a- aaa-a-a-aaa-a-a-a- -- a- agt a-a-a-a-a-a-a-a-~ a a---- aaa~a-~aaa---aa-Xaa--aa-a-aa-a-a-a-a -shy
- a a ~ ------------shy aaa -------------- a-a-- -a -a-- - a-a-a-a a-a-aa-a-a-a- aa-~
gt7gt a-a-aaa-~aa-aa-a-aa a-- a- la-a a a-a- aaa-aaa- a-a-
4 a-2a- aa~a- -~aa-a a-a-a-a--a- a-a-a-Yaaa-~a-~-aa-3a-aa4yaaa~a-aaaaaaa-a-aa-aa- a-Va-a--a- a- -~ -a-a- a- ~a- 4~ a-a- -a-~ - - - a-4a-aa- aa--a-aa a-a-~ a-a-a-a-a-a-a aa-aa~ -a-
~ a-j-~a-a7~24 a-a- -a-a-a-~a-a-a a-- a-aa-4a-a-4a-4a-a 1
44aaaa- a-a-4- a-~a-a~a-a-aa a-aK ~a~Ca-a-~a-a-Aa-P~aa-a~-a-a-aaa-a-aa-~Aa-ltaa-a(a-aampa-Aa-a-a-aa-a-A aa-aa a a-aa4a-a-44a-aaa-a-gtashy
a-a-a- - ~ lta-a~aa-~a-(a-a--aCpaa-a~ aa~a-~-a-a-a-aaa-aa4-aa-aa~a-aia-a-a-a~a
---- ~ 4 aa~aii4~a~a-iAa-a-aaaaa-a-aaaaa-aaaaa-Aaaaaaa-ia-aa-a-aaa aa-aaa-aa-a-a-Va-P4a4~~aaa-aa-~aa-
a-i a-a a-
-a- ~ a a-~ - a--a- a a-a-a-a--- ~a-a-a-aa-a- a-a-a- a- a
~a-a~a~~a-a- 4-a-a-i a-a- aa-a-a-~~aa-a-~ a-a-~a4aa 4 ~a--a-a- a-Aa-~aVia-aa~a 4- 2- 4- a-a-a~ 4a-a-igt~4~-~a4 4- -shy4a-a-a-ia-a- aa4a-~a4a-a-a2a-a -a-a--aaa-a a-a-a-a a-a--a- a-a-ashy
a -a-4Va--~a-C~a-~a-aa-a-a-4a-aa-4~a-4iaa ~ a-a-a ~a-~ w a-a- -a a-~ a a a-a-a-i a-a-a a~-a-aa-a- a~ taa~a-a-~a4~aa-a-a-aa-a-~-aaaaaa---a-a- aaa-~~a 4 Aa-a- a-a-ashya- a-~ aaa-a-a-a~~Ta-a4~aa a-a-a a- -a--a aa-a-a-a-a -aa-a-aa-~a a-a ashy~ a-~ a-a-aaa~~ a~- a-~aIa- ~ - aa~ia-~a4 a-a-ashy -z~
a- ~ a-Aa-~~ a- -- aa-a-a~aa-aa-a- aAa- a aa-a- a-
XEC IUT VE SU INARy
A PURPOSE OF EVALUATIO The purpose of hi s eulu aci)n s to assess t ie proqess of implementation
of the Traininj and Devel opinent Issues (TDI ) Project identify probl ems andissues that nay have hamsered project progress and recommend measures tomaximize project impact on the develornent effor of the new government
B PROJECT PURPOSE o zJC 2The purpose TheT iS tO ]uoroe t2e apaolit oT the
Philippine Government anl ctiher instI tutions to analyze develoument issues andto make sound and timely C-lont-reiated Jechions
C CONCLUSIONS AND - gt
1 Overall project progress has been relatively slow While training(Participant Trainin2 Corsnent and the training element of the Development n s by and larje on schedule progress ofthe non-trainine nns (rsearch fora teiuicai and management assistanceand equiprne nt Depeloum+n t componentd c mlo o)f h) Dhe s isses has been
painfully slow
This notwi t htanaid nr ci current eviidence supports the continueduserulness of rothie ear + its expressed obiective of buildinq uoinsttut0ional caciies foreen poliiv analysis and relateddecision-makinc The pot2ntial v Iue of the project is further enhanced by
de-isions TD t+- woul - toto nono u pace of project implementation buz aiso expand project benefits and impactand (b) the positive climate under the new government
(a) recent - o the a t o onl yy i rove - e
The slow proress o thO proj It to v-- unI i kelydat e renders the full inmpleImentation of the projec within the curren PACD
Accordingly the follow ing maijor recommend- ~i are herein made
Recomend ation 1
The priject shoul d be toc ninued and the -eeded by t1io years Decenber I 9J
Recornmendati-l 2
Should fo two-yearthe rcn a elttnsin of the PACD beaproved] rti~er evaluat ion of the project - id e underzahen i the first half 191
~Recommen dtioni32
an cosdrtopesing of th ot etsrvcn iffclte and i osdrtoof theidi Fffsed social beneits of the project theS~entire unearmar ed loan allocation to the projetshoul d be converted to
-771-2-Thes-Ioi-prog ress-of tb4e- non training-eImn shs-be-rotd-a in n_7basic int Iretti onai differences bet e te-TDI _PMvOad the USAID Mjsion~ on the~aproach-toproject imletto and the-e lted isueof extraScompensatioqn for gvernmienitpersonnell This i n r slnialeorpolmin the cornrunication process jbetwen the two 4parties~At thejdesign stage ~ more extensive discussions werepreVented bamptimersue-bo happroaching US bu dgetary deadl ines At the im~lernentE tibon st ge ffective~
specifically Vwlth respect to USAIDs merbership-in thrieitSernlt Commi-ttee and (b) the fact that 4 both the USAID Miss ion and1he TDI Pon Sendscompeting claims on staff time rendered it difficultgtfor closerattenti on to bedevoted -to project concerns~~
Inlight of the foregoing the followingrecommendations~are made J j Recommendation 4 4
To enhance smooth and timely implementation~o fthe p-oject as awoead in particular ofthe non-training~e ementsor the Devel4opment Issues~
- component acl1ear resol ution of the problem issues_should be 1made and 4agreements
shyreached clearly set out44in projqc~t imp emetation letter iilt7iAlso to the extentTneeded to resolve uncertainiies 4or ambiguitiesyconcerning administrative aspectsofpoet imlemnain - Isisampulbe issued 4that clearly set-out USAID gu(inclns and proexemptions that -may be6greeudtupon)1 y d pon - V 4e4-
Recommendation 5 Tthe extet eded for4 smooth impjlementain I cenewJf~il
managementof the pr jct at-1both the TDI-T 4 ad -theUSAID ends shoul d ~ -devote miore timne to the- ranagement of the-project Mor 1etiMLe is clearly4--needed in the immeidiate fut-ure to resoIveba sic is sues clarify 4if~
-4shy
regulations and establ ish4 ruie procedres~I4~4
Recommendation 6 4
In the specific case of te non taning eImnsoFthe Devel opment Aigtises comnponent it ils t hat arecommended t eias a porton 0 ~ ~~management dutiles be transferred to the Phlppine Institute for 4-4----~shy
shy_ ~ z Developmient Studies(PIDS) which hasexperience in the4 maaeeto4researchi and iiS1 procedures
11i Il iw4
0ctob~ b3 Te p98 7Wrso nteTD saar- has ~Produced veryencouraging ejiysbiss Ifls1ronsto e yejeer Proposal Sane the TDI PMO hpas decifded to convene s-Imilar workshopsi h~tre ona regul ar bsspss-by wc a y 1rZgtTI- ecision is stronglyendorsed 4 ~gtosbjtc
InI addtinoever parallel acinwl ndtob taken in othei ctimpa
pr je
~~ The six areas tha~t ha-ve been selcted7 as prioriti - -h anarrtrelated actfitij s fo0 stanpcl ~id
iare deme so broad th~at pro1 ect acriis n Mact would tend -to be too di~~Afft-- Ac4nq5
finer fouigof the Research Agenda should b unetkn uhtaproject activities are limited toa smal inumber of development issues~------- ~deemedcriticalunder the new governImentttetnl~2PThrey
resources of a larger numbwer ofinsti ucions can be applied to a-particular~issue produce more extensive as well1 as more iidepthiigt -- analysis fnd altogethier maximize project impDactjb)While curirenit iplementation procedures
- ~ elements1of the eel opment coverinoIssues Component are- design9edthe o-traininto~ ngmtehcompetitiv~e niature of a~ad~encourage broad participationandensure cons istency witi-pojc purpiose thei rj tie-consumi ng character tends to4plusmn4v effecti Yely rule out use of the proj ect for urgnt shor$t-termpohi -ity44 issues and their rigidity limits the~ability of project managmnt
444 -- iitiate quickI relevant coiisul tancies Accordingly gmn Recommendat ion Gi4 Impl ementa tion procedureN
)444shld be difi ei toal1owgeae Aiscretionary powers4 to the TDI-PM0 Specjif44 cally the TDI -PMObe authiorized to approvewithout furthj should Commi ttee or ned of eitherSt44ering~USAID approval 4 proposals ridcotas ontpista 444have4 been previous y cleared 1e~as4 ela on ~lvant topics thatshy
445a44--y be of Jimmediate urgency 111This 4a~thio~ity howeershul bpshy4~-~4444- imited both a~s4I to the- amount of any-indifdual contract
4 and to the total amount of all such contractsJora say $150001given yearsay~i it
~44444-~4$1 00000 vii 4 4
74 4 ~4i While raining activities have bee proce ding argel on- ched
exit~ coe for improvement in component operation~s ~o enlarge trainingshybee1isand -broaden the i r di stribut ion i 4~4 - 4
7~
-44444 - -
h4~4~-444444
7a) ~Whul sc he ifor io riti Zing9 benefic ary ins~tttons ard fiel ds ojjstudy Ahas been diia n up and Va rgeIy f I Io eld ~he absenceof dei1ed prog ram of t rainingactiY1ti - resu1Ited inh certan i l~neidistribyton ~ among agenc 1es wi th~i npri or ity groupsKa
~of 5studiy~ and~bewe I eta nregionai o fijce s 4is also en b eEthe accomodation of agenc Ie ht
s as 4eI I Id ludy~ th1at wef- as fiL f ltt) out(seoK~f establ i sp priorities
As earl ier noted nowever theTDI-PM~O has recentlyKapproved speci fi c - xcproposals to correct4 these jrnibalaance These inclu~de 1i)forniu1 ationof a oedea e prog ram for trlnnf iers of the project d~ration
WioselmDremenedtation t1p m arograts S partial-shifting of the trainin6g budget -from overseastKo local traTi n in
i)th upadadjustments in stpnrae )OIafllwances and Kvjyresea rch LiesiS al IOwahces urider Iocdl11 tvilo fiijgrants to enhance theirSVKatt ractiveness expansion off6nding-support underthpoeto
include training insuitable ~fields ihn selected isitt teinlsof~learning in-the country~and iv) broadening institutionial and regionalparti~cipation in the~trann 0opo~amp -riig compnent
$AlI of the fore_goi ng recommendati ns are hereinK endorsed In addi tion Re ot meond 1
KKK K
K ~ cobnatinthIUKK If somdnr-sise prjcs not KK K shiftingKKK
A)Whie ssesetof henodistributon fo1ields)toi o finininpcif K beween thegenraenvK i antd egn oel setortesse asytt es
~KKK~KKo enbl csounb andertaken to fl~ Kthexentto4hjit7tprojyectfne Khe Kriig objctve foispoen hisr acivd the K~KK K
KKAnito Kg Kine eficedmediatelyV~KKKKKsytm eniioe tpe beprojectsshould KKKestablished KKK a c~K v a d
K KK
I BACKGROUND
The Training and Development Issues (TD) Project was designed to improve
the capability of the Philippine Government and other institutions to analyze
development issues and to make sound and timely development related
decisions This objective was sought to be achieved mainly through training
and the conduct of research and related activities on a small number of issues
deemed critical to the sustained pursuit of Philippine development
The project was conceived to address perceii gips in the USAID
assistance program to the Philippines First most previous research
activities had not focused on developing the information needed for effective
decision-making and policy review Second general participant training
projects had lacked specific focus and supporting activities thereby limiting
their impact And third sectorally focused institutional development
projects often could not fully a-hieve their development objectives because
many key policy related factors affecting project success were beyond the
control of the implementing agency
Under the Project Agreement vwhich was signed on 29 July 1983 USAID
committed to provide a total of $42 million in loans ($33 million) and
grants ($09 million) Of this amount $25 million was allocated to the
Development Issues Component and $16 million to the Training Conponent with
$100000 set aside for evaluation USAID funding for the project was
subsequently raised by a $3U0000 grant that brought the total USAID
commi tnent to $45 million Government counterpart funding amounted to $15
million PACD aas set at 31 December 1938
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
BASIC PROJECT IDENTIFICATION DATA
1 Country Philippines
2 Poject Title Training and Development issues
3 Project Number AID Project No 492-0340 AID Loan No 492-V-069
4 Project Dates
a First Project Agreement July 29 1983 b Final Obligation FY 84 c Project Assistance Completion Date (PACD) December 31 1988
5 Project Funding
a AID Bilateral Funding Grant $1200000
b Other Major Donors None Loan $3300000
c Host Country Counterpart Funds $1300000
T 0 T A L $6000000
6 Mode of Implementation Host Country
7 Project Design USAID Philippines and the Govt of the Philippines
8 Responsible Mission Officials (For the full life of the project)
a Mission Director(s) Frederick W Schieck (FY 84 - Present) Anthony M Schwarzwalder (FY 83 - 84)b Project Officer(s) Dominic A DAntonio (FY 86 - present) Richard E Rhoda (FY 83 - 86)
9 Previous Evaluation(s) None
10 Cost of Present Evaluation
Person Days Dollar Costs a Direct Hire
(1) AIDN TDY (2) USAID staff 28b Contract 28 $2800
c Other
--
-aa~a~a-~a~a4-- lta -~ a-a- A- a a -~ a-aaaai ~a ~a
- - - - a-a a-r a-a-~ -i-a ~ ~ -Y -~- - - - aaflt( a-aA~~ ~ 7~j Aa-~ ~a-aa~v
aa-~a~a~a-a~a1gtQ ~ --~A-i~ ~a2aaap ~-aaa a a~--a~ aa ~ ~ a~ a~ja-~aa a~~aa-A~aa ~ - - -~
- ~ a - - -4---a -~ -lta-a ~iaa -~-~ ~ a ~a -4~~ ~ 4---a-a-~a~- a-~a~~ jfla -~ 4~
OF ACRONYf IS ~ -
~a-a-r- - ~ -~a-aaa --- ~a-Y - ~ ~V~a a4a--a~4 ~a-4-aa-lt~-~a~a- a~~aaaaa-V~Y~7--7 ~~~a-a- -gt a -- - ~ ~ a-a-iaA~ ~-a-a-a4~4a 4-aa~i a-aaaaaaa- 4- TIO~ REPORT -
- a~~Ai~W~ a-a- - a-~ a- ~ ~ ~ -4- -~ 4 aia-a -- - a-a~lt ~a~~~-i ~a-~a- ~a-aa-a a~-a -~- a-a -aj-a---~a- - -A$a-akaJ --- ~ a-
~ ~a--~a a-a aa a ~a4a-~A~-~Qj ~ ~ lt a-a-~ ashya a-lt a a- -~ ~ ~4~ a~14~a~a- a7 2aa~ ~f~a ~ a- -- I
a--~a-a-a-a- -a- ~ ~aa--~aa~a a aa~-a-a--------~ aj
Economic Plunning a-and Reseat chaStaff7a aa-~--a-a - a--~ ~-a- 4 ~a--ja-j~ --a-- a-
a a- a-- - a--4~a- a-a-ES I-A Daaaaa-~a E-ononft ~nd SociaL impact AnalysaisWomen din lti~---- -shy- a a- ~a- 4L P a-a
---i--a - aaaaa -~~a- ~ ~ a a- ashy
-~
aaa a- a a-~a -a- a--aa- - ar4 - --ashyaa-aa-- -~
~I~-GPT General ParticipanC T~dlning a ---r- ~ aj~aa~~ - ~ a a aa- a- a- a 4aaa~ a ~a a-ta~ ashy
a- a a a- ~gt -~ a- ~a-aa- aa- a shy~ a-agt shy
aThEa~A agt flational Economic and D6velopment Authority a- a- gt -agt~4 Waa-arV P a-Wja - shy
a ~a-a-a gt~lt-a-ashyp1io Tra - aa- a aaaa a4~a a Aa shy
ashy~a-a-PAGOa-~ Project Assistance Completion Da~e ~
aa
Th~~a a-aa-a~a a413a ~~Ya ~
a-- -- ~j~5 Philippin~~Insatitute for Development ~ a a a ~a-~ a- a a a a a a a a
-- -~a - aa-ga- aaa-paa-~ a-i ~ ~~ ~ Letterr~ a ~ a a a- ~a-arrOJecL plusmnmpmementau on
a a 4aa- a- a a a a a a- ~ ~~~aa~aaaaagta 4ashya --~ashya a-aa---~a-a aa- -a~a aAl~ a- a aaa4A~aa shy
a ininganci ueveiopment Isues Projectagta-a-a- - ~a - -
a -- gtaaUa a A aa-~a a a- aaa aaaa a~~aa r
a ining andaDevelopment ~ aa a~ alaa-a a a a a-a a~ a a -A- a- a
-a- a- aa ffice a -a-a a a O ~-h 4aa4 a a ~~a-a- a-a-a
a-a a a a-a aaa- aa a a a a-a a
-a- USAID 7 U nited Stat a- a-a a a ~ a~ a a a-a - a-a ~aa a-aaashy
es - aa-a- a-a~gencyfora aX ~ Internatjonal~- aa-a- aa Oevemopmenta a- ~a- a~ a aa-aa-aa-- a a a aa -----------4 a- a a a
Aa a aa-ashy-a--ar
a a- a a a a aa a- a-a-aa -~ agt ~a a-a-a-aaa- aa- a a- a- a-a- a a - a - a -a ~a a-a-aa4aaaaaaaaa-aaa4 a a- a-- - a- a-~ ~a- a- a a 2 a aaa--a aaaa~-aaJ-aa-aa--Kaa-aaa--a-~aaaa-aa-aashy Paaa- 4 a a a - a-- a-a--a-a-a-a-a-ashyaaaa- a-a-a a a a-a a-aaa-a a- shya- a-a a
a a a- a a- a a-a~ a a a ~ - -- a a a - -a- -a
-- 4a~a-~ -a-a~aa-- ashya- a a- a a-a- aa
a- a a - a ~-aaa a- a- 1 a-a-ashy
- a-a- a-a aaa- a ashy
lta a a -a a~ a a a a-a-~ a-ashy
aaJ-a-J alt~aa- a-- a aT a 2 a-a a aa a-a- a a a-a a-a~ a-a4-ia-a-- a-a-~a-a-~a aa- a-a-a a a- a-a-ashya aaa aa-~
a-a a- a-a a- -a a - a- a- ala aa a-a a- a- aa- ~a a- a a- aa-aa a a- a- a a ashy
a-a---ia--a--- a-a-aa-a-~ a-a-aaaa
a- a-a-aaaa-~a-a a a - a- a a- a- aaaa-a-aa-~ a a a- a la-a-a aaa- a a-a- aa aa-aa-a-lta ~-aa~a a a -a- a a a - a- a a- aa- a-~ a-agt 4aa-a-aa4-a-a-a-a a-aa a-a- a a 4 ~a-a- a-a a a aashya a-a a-a- a-ashya~a $aa-a-a~a-a-a4- a~ a- a-aJ a aaa- a- aa a- a- a-aa a-a a-a aa a a-a-a-
aaaIaaaa-a-a-a-a~a a-a- a-a-
a
a- ~a a-a-
a- a a- a-a- a- a a-a-ashya a-a- a- a a a- a-a-44aalt a- a-- a-aa-~ a a-a- aa-~24a4aaaa~aa
a-a- a a- a a- a- a a - a a
~a a~a-a-a-aa-a-a-a aa-a-a a- - ~-a-a a ~ a- a-a a a-a- a- aa~a a-aaa-a a a- aa-aa-a-aashy~a-a-~- a-- aaaa- -aa a 4a a-~a-~a- aaaAa a a-a- a- a-a-a- --- a-a-ashyaa-a-a-~aa-a a~~a- a-a aa-a-aa~aa~a~aaa a- a-a-a-4~a- a a a-a-a-ashya-a-2 a-aaa-gtaa-al a a- aaa~A a-a-a-a-a- a
a-a a-ashya-a-a-a-a a- Jaa-a- a-aa- agt a- aaa aa-a- a a a-3a-a- ~a a-a-a- ~gta-~~~a- 4- 4aa-Aa--------------------a--a- a-a- ~~ a-a- a~~a-Pa-a-a-a-~ 2--a-a- a ~a-aaaa-a4aa-aa-aa- a-a-a-agtaa-aa2aa~a-C-i-a-a a- a-a-- aa-a- - a
- a a-a- a-a----a-a a-a-- - ~aa-~aaa4a a a-a-a- a-gt -a-~ a--4a-a-a-~a-~a- a-a-a- a--a-a---aaa-aaaa--a-aaaa--aa-a--a a-a--a-aa-~a-4a-a-a-~--a--~aaaa--- a a-~a-~ a- a- a-a-a a-a-a4 ashy-- aa-- -aa-a- a-a~--~a-~aa--a-~a- aa-- a~-a- a-aaaaaa-a--a-a-a-a-aaa-a-a-aa-a-a-aa-a-a-a- ~a~a-aSaaa-a4-ashya-~a-a-aa-~aa-la-~a-a~ 2 -a--a-shy
a-a-a aaaaa-a- a-a-a-i aa---a- a-a--a--a aa-a~~-a- aaa-a-a-aaa-a-a-a- -- a- agt a-a-a-a-a-a-a-a-~ a a---- aaa~a-~aaa---aa-Xaa--aa-a-aa-a-a-a-a -shy
- a a ~ ------------shy aaa -------------- a-a-- -a -a-- - a-a-a-a a-a-aa-a-a-a- aa-~
gt7gt a-a-aaa-~aa-aa-a-aa a-- a- la-a a a-a- aaa-aaa- a-a-
4 a-2a- aa~a- -~aa-a a-a-a-a--a- a-a-a-Yaaa-~a-~-aa-3a-aa4yaaa~a-aaaaaaa-a-aa-aa- a-Va-a--a- a- -~ -a-a- a- ~a- 4~ a-a- -a-~ - - - a-4a-aa- aa--a-aa a-a-~ a-a-a-a-a-a-a aa-aa~ -a-
~ a-j-~a-a7~24 a-a- -a-a-a-~a-a-a a-- a-aa-4a-a-4a-4a-a 1
44aaaa- a-a-4- a-~a-a~a-a-aa a-aK ~a~Ca-a-~a-a-Aa-P~aa-a~-a-a-aaa-a-aa-~Aa-ltaa-a(a-aampa-Aa-a-a-aa-a-A aa-aa a a-aa4a-a-44a-aaa-a-gtashy
a-a-a- - ~ lta-a~aa-~a-(a-a--aCpaa-a~ aa~a-~-a-a-a-aaa-aa4-aa-aa~a-aia-a-a-a~a
---- ~ 4 aa~aii4~a~a-iAa-a-aaaaa-a-aaaaa-aaaaa-Aaaaaaa-ia-aa-a-aaa aa-aaa-aa-a-a-Va-P4a4~~aaa-aa-~aa-
a-i a-a a-
-a- ~ a a-~ - a--a- a a-a-a-a--- ~a-a-a-aa-a- a-a-a- a- a
~a-a~a~~a-a- 4-a-a-i a-a- aa-a-a-~~aa-a-~ a-a-~a4aa 4 ~a--a-a- a-Aa-~aVia-aa~a 4- 2- 4- a-a-a~ 4a-a-igt~4~-~a4 4- -shy4a-a-a-ia-a- aa4a-~a4a-a-a2a-a -a-a--aaa-a a-a-a-a a-a--a- a-a-ashy
a -a-4Va--~a-C~a-~a-aa-a-a-4a-aa-4~a-4iaa ~ a-a-a ~a-~ w a-a- -a a-~ a a a-a-a-i a-a-a a~-a-aa-a- a~ taa~a-a-~a4~aa-a-a-aa-a-~-aaaaaa---a-a- aaa-~~a 4 Aa-a- a-a-ashya- a-~ aaa-a-a-a~~Ta-a4~aa a-a-a a- -a--a aa-a-a-a-a -aa-a-aa-~a a-a ashy~ a-~ a-a-aaa~~ a~- a-~aIa- ~ - aa~ia-~a4 a-a-ashy -z~
a- ~ a-Aa-~~ a- -- aa-a-a~aa-aa-a- aAa- a aa-a- a-
XEC IUT VE SU INARy
A PURPOSE OF EVALUATIO The purpose of hi s eulu aci)n s to assess t ie proqess of implementation
of the Traininj and Devel opinent Issues (TDI ) Project identify probl ems andissues that nay have hamsered project progress and recommend measures tomaximize project impact on the develornent effor of the new government
B PROJECT PURPOSE o zJC 2The purpose TheT iS tO ]uoroe t2e apaolit oT the
Philippine Government anl ctiher instI tutions to analyze develoument issues andto make sound and timely C-lont-reiated Jechions
C CONCLUSIONS AND - gt
1 Overall project progress has been relatively slow While training(Participant Trainin2 Corsnent and the training element of the Development n s by and larje on schedule progress ofthe non-trainine nns (rsearch fora teiuicai and management assistanceand equiprne nt Depeloum+n t componentd c mlo o)f h) Dhe s isses has been
painfully slow
This notwi t htanaid nr ci current eviidence supports the continueduserulness of rothie ear + its expressed obiective of buildinq uoinsttut0ional caciies foreen poliiv analysis and relateddecision-makinc The pot2ntial v Iue of the project is further enhanced by
de-isions TD t+- woul - toto nono u pace of project implementation buz aiso expand project benefits and impactand (b) the positive climate under the new government
(a) recent - o the a t o onl yy i rove - e
The slow proress o thO proj It to v-- unI i kelydat e renders the full inmpleImentation of the projec within the curren PACD
Accordingly the follow ing maijor recommend- ~i are herein made
Recomend ation 1
The priject shoul d be toc ninued and the -eeded by t1io years Decenber I 9J
Recornmendati-l 2
Should fo two-yearthe rcn a elttnsin of the PACD beaproved] rti~er evaluat ion of the project - id e underzahen i the first half 191
~Recommen dtioni32
an cosdrtopesing of th ot etsrvcn iffclte and i osdrtoof theidi Fffsed social beneits of the project theS~entire unearmar ed loan allocation to the projetshoul d be converted to
-771-2-Thes-Ioi-prog ress-of tb4e- non training-eImn shs-be-rotd-a in n_7basic int Iretti onai differences bet e te-TDI _PMvOad the USAID Mjsion~ on the~aproach-toproject imletto and the-e lted isueof extraScompensatioqn for gvernmienitpersonnell This i n r slnialeorpolmin the cornrunication process jbetwen the two 4parties~At thejdesign stage ~ more extensive discussions werepreVented bamptimersue-bo happroaching US bu dgetary deadl ines At the im~lernentE tibon st ge ffective~
specifically Vwlth respect to USAIDs merbership-in thrieitSernlt Commi-ttee and (b) the fact that 4 both the USAID Miss ion and1he TDI Pon Sendscompeting claims on staff time rendered it difficultgtfor closerattenti on to bedevoted -to project concerns~~
Inlight of the foregoing the followingrecommendations~are made J j Recommendation 4 4
To enhance smooth and timely implementation~o fthe p-oject as awoead in particular ofthe non-training~e ementsor the Devel4opment Issues~
- component acl1ear resol ution of the problem issues_should be 1made and 4agreements
shyreached clearly set out44in projqc~t imp emetation letter iilt7iAlso to the extentTneeded to resolve uncertainiies 4or ambiguitiesyconcerning administrative aspectsofpoet imlemnain - Isisampulbe issued 4that clearly set-out USAID gu(inclns and proexemptions that -may be6greeudtupon)1 y d pon - V 4e4-
Recommendation 5 Tthe extet eded for4 smooth impjlementain I cenewJf~il
managementof the pr jct at-1both the TDI-T 4 ad -theUSAID ends shoul d ~ -devote miore timne to the- ranagement of the-project Mor 1etiMLe is clearly4--needed in the immeidiate fut-ure to resoIveba sic is sues clarify 4if~
-4shy
regulations and establ ish4 ruie procedres~I4~4
Recommendation 6 4
In the specific case of te non taning eImnsoFthe Devel opment Aigtises comnponent it ils t hat arecommended t eias a porton 0 ~ ~~management dutiles be transferred to the Phlppine Institute for 4-4----~shy
shy_ ~ z Developmient Studies(PIDS) which hasexperience in the4 maaeeto4researchi and iiS1 procedures
11i Il iw4
0ctob~ b3 Te p98 7Wrso nteTD saar- has ~Produced veryencouraging ejiysbiss Ifls1ronsto e yejeer Proposal Sane the TDI PMO hpas decifded to convene s-Imilar workshopsi h~tre ona regul ar bsspss-by wc a y 1rZgtTI- ecision is stronglyendorsed 4 ~gtosbjtc
InI addtinoever parallel acinwl ndtob taken in othei ctimpa
pr je
~~ The six areas tha~t ha-ve been selcted7 as prioriti - -h anarrtrelated actfitij s fo0 stanpcl ~id
iare deme so broad th~at pro1 ect acriis n Mact would tend -to be too di~~Afft-- Ac4nq5
finer fouigof the Research Agenda should b unetkn uhtaproject activities are limited toa smal inumber of development issues~------- ~deemedcriticalunder the new governImentttetnl~2PThrey
resources of a larger numbwer ofinsti ucions can be applied to a-particular~issue produce more extensive as well1 as more iidepthiigt -- analysis fnd altogethier maximize project impDactjb)While curirenit iplementation procedures
- ~ elements1of the eel opment coverinoIssues Component are- design9edthe o-traininto~ ngmtehcompetitiv~e niature of a~ad~encourage broad participationandensure cons istency witi-pojc purpiose thei rj tie-consumi ng character tends to4plusmn4v effecti Yely rule out use of the proj ect for urgnt shor$t-termpohi -ity44 issues and their rigidity limits the~ability of project managmnt
444 -- iitiate quickI relevant coiisul tancies Accordingly gmn Recommendat ion Gi4 Impl ementa tion procedureN
)444shld be difi ei toal1owgeae Aiscretionary powers4 to the TDI-PM0 Specjif44 cally the TDI -PMObe authiorized to approvewithout furthj should Commi ttee or ned of eitherSt44ering~USAID approval 4 proposals ridcotas ontpista 444have4 been previous y cleared 1e~as4 ela on ~lvant topics thatshy
445a44--y be of Jimmediate urgency 111This 4a~thio~ity howeershul bpshy4~-~4444- imited both a~s4I to the- amount of any-indifdual contract
4 and to the total amount of all such contractsJora say $150001given yearsay~i it
~44444-~4$1 00000 vii 4 4
74 4 ~4i While raining activities have bee proce ding argel on- ched
exit~ coe for improvement in component operation~s ~o enlarge trainingshybee1isand -broaden the i r di stribut ion i 4~4 - 4
7~
-44444 - -
h4~4~-444444
7a) ~Whul sc he ifor io riti Zing9 benefic ary ins~tttons ard fiel ds ojjstudy Ahas been diia n up and Va rgeIy f I Io eld ~he absenceof dei1ed prog ram of t rainingactiY1ti - resu1Ited inh certan i l~neidistribyton ~ among agenc 1es wi th~i npri or ity groupsKa
~of 5studiy~ and~bewe I eta nregionai o fijce s 4is also en b eEthe accomodation of agenc Ie ht
s as 4eI I Id ludy~ th1at wef- as fiL f ltt) out(seoK~f establ i sp priorities
As earl ier noted nowever theTDI-PM~O has recentlyKapproved speci fi c - xcproposals to correct4 these jrnibalaance These inclu~de 1i)forniu1 ationof a oedea e prog ram for trlnnf iers of the project d~ration
WioselmDremenedtation t1p m arograts S partial-shifting of the trainin6g budget -from overseastKo local traTi n in
i)th upadadjustments in stpnrae )OIafllwances and Kvjyresea rch LiesiS al IOwahces urider Iocdl11 tvilo fiijgrants to enhance theirSVKatt ractiveness expansion off6nding-support underthpoeto
include training insuitable ~fields ihn selected isitt teinlsof~learning in-the country~and iv) broadening institutionial and regionalparti~cipation in the~trann 0opo~amp -riig compnent
$AlI of the fore_goi ng recommendati ns are hereinK endorsed In addi tion Re ot meond 1
KKK K
K ~ cobnatinthIUKK If somdnr-sise prjcs not KK K shiftingKKK
A)Whie ssesetof henodistributon fo1ields)toi o finininpcif K beween thegenraenvK i antd egn oel setortesse asytt es
~KKK~KKo enbl csounb andertaken to fl~ Kthexentto4hjit7tprojyectfne Khe Kriig objctve foispoen hisr acivd the K~KK K
KKAnito Kg Kine eficedmediatelyV~KKKKKsytm eniioe tpe beprojectsshould KKKestablished KKK a c~K v a d
K KK
I BACKGROUND
The Training and Development Issues (TD) Project was designed to improve
the capability of the Philippine Government and other institutions to analyze
development issues and to make sound and timely development related
decisions This objective was sought to be achieved mainly through training
and the conduct of research and related activities on a small number of issues
deemed critical to the sustained pursuit of Philippine development
The project was conceived to address perceii gips in the USAID
assistance program to the Philippines First most previous research
activities had not focused on developing the information needed for effective
decision-making and policy review Second general participant training
projects had lacked specific focus and supporting activities thereby limiting
their impact And third sectorally focused institutional development
projects often could not fully a-hieve their development objectives because
many key policy related factors affecting project success were beyond the
control of the implementing agency
Under the Project Agreement vwhich was signed on 29 July 1983 USAID
committed to provide a total of $42 million in loans ($33 million) and
grants ($09 million) Of this amount $25 million was allocated to the
Development Issues Component and $16 million to the Training Conponent with
$100000 set aside for evaluation USAID funding for the project was
subsequently raised by a $3U0000 grant that brought the total USAID
commi tnent to $45 million Government counterpart funding amounted to $15
million PACD aas set at 31 December 1938
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
--
-aa~a~a-~a~a4-- lta -~ a-a- A- a a -~ a-aaaai ~a ~a
- - - - a-a a-r a-a-~ -i-a ~ ~ -Y -~- - - - aaflt( a-aA~~ ~ 7~j Aa-~ ~a-aa~v
aa-~a~a~a-a~a1gtQ ~ --~A-i~ ~a2aaap ~-aaa a a~--a~ aa ~ ~ a~ a~ja-~aa a~~aa-A~aa ~ - - -~
- ~ a - - -4---a -~ -lta-a ~iaa -~-~ ~ a ~a -4~~ ~ 4---a-a-~a~- a-~a~~ jfla -~ 4~
OF ACRONYf IS ~ -
~a-a-r- - ~ -~a-aaa --- ~a-Y - ~ ~V~a a4a--a~4 ~a-4-aa-lt~-~a~a- a~~aaaaa-V~Y~7--7 ~~~a-a- -gt a -- - ~ ~ a-a-iaA~ ~-a-a-a4~4a 4-aa~i a-aaaaaaa- 4- TIO~ REPORT -
- a~~Ai~W~ a-a- - a-~ a- ~ ~ ~ -4- -~ 4 aia-a -- - a-a~lt ~a~~~-i ~a-~a- ~a-aa-a a~-a -~- a-a -aj-a---~a- - -A$a-akaJ --- ~ a-
~ ~a--~a a-a aa a ~a4a-~A~-~Qj ~ ~ lt a-a-~ ashya a-lt a a- -~ ~ ~4~ a~14~a~a- a7 2aa~ ~f~a ~ a- -- I
a--~a-a-a-a- -a- ~ ~aa--~aa~a a aa~-a-a--------~ aj
Economic Plunning a-and Reseat chaStaff7a aa-~--a-a - a--~ ~-a- 4 ~a--ja-j~ --a-- a-
a a- a-- - a--4~a- a-a-ES I-A Daaaaa-~a E-ononft ~nd SociaL impact AnalysaisWomen din lti~---- -shy- a a- ~a- 4L P a-a
---i--a - aaaaa -~~a- ~ ~ a a- ashy
-~
aaa a- a a-~a -a- a--aa- - ar4 - --ashyaa-aa-- -~
~I~-GPT General ParticipanC T~dlning a ---r- ~ aj~aa~~ - ~ a a aa- a- a- a 4aaa~ a ~a a-ta~ ashy
a- a a a- ~gt -~ a- ~a-aa- aa- a shy~ a-agt shy
aThEa~A agt flational Economic and D6velopment Authority a- a- gt -agt~4 Waa-arV P a-Wja - shy
a ~a-a-a gt~lt-a-ashyp1io Tra - aa- a aaaa a4~a a Aa shy
ashy~a-a-PAGOa-~ Project Assistance Completion Da~e ~
aa
Th~~a a-aa-a~a a413a ~~Ya ~
a-- -- ~j~5 Philippin~~Insatitute for Development ~ a a a ~a-~ a- a a a a a a a a
-- -~a - aa-ga- aaa-paa-~ a-i ~ ~~ ~ Letterr~ a ~ a a a- ~a-arrOJecL plusmnmpmementau on
a a 4aa- a- a a a a a a- ~ ~~~aa~aaaaagta 4ashya --~ashya a-aa---~a-a aa- -a~a aAl~ a- a aaa4A~aa shy
a ininganci ueveiopment Isues Projectagta-a-a- - ~a - -
a -- gtaaUa a A aa-~a a a- aaa aaaa a~~aa r
a ining andaDevelopment ~ aa a~ alaa-a a a a a-a a~ a a -A- a- a
-a- a- aa ffice a -a-a a a O ~-h 4aa4 a a ~~a-a- a-a-a
a-a a a a-a aaa- aa a a a a-a a
-a- USAID 7 U nited Stat a- a-a a a ~ a~ a a a-a - a-a ~aa a-aaashy
es - aa-a- a-a~gencyfora aX ~ Internatjonal~- aa-a- aa Oevemopmenta a- ~a- a~ a aa-aa-aa-- a a a aa -----------4 a- a a a
Aa a aa-ashy-a--ar
a a- a a a a aa a- a-a-aa -~ agt ~a a-a-a-aaa- aa- a a- a- a-a- a a - a - a -a ~a a-a-aa4aaaaaaaaa-aaa4 a a- a-- - a- a-~ ~a- a- a a 2 a aaa--a aaaa~-aaJ-aa-aa--Kaa-aaa--a-~aaaa-aa-aashy Paaa- 4 a a a - a-- a-a--a-a-a-a-a-ashyaaaa- a-a-a a a a-a a-aaa-a a- shya- a-a a
a a a- a a- a a-a~ a a a ~ - -- a a a - -a- -a
-- 4a~a-~ -a-a~aa-- ashya- a a- a a-a- aa
a- a a - a ~-aaa a- a- 1 a-a-ashy
- a-a- a-a aaa- a ashy
lta a a -a a~ a a a a-a-~ a-ashy
aaJ-a-J alt~aa- a-- a aT a 2 a-a a aa a-a- a a a-a a-a~ a-a4-ia-a-- a-a-~a-a-~a aa- a-a-a a a- a-a-ashya aaa aa-~
a-a a- a-a a- -a a - a- a- ala aa a-a a- a- aa- ~a a- a a- aa-aa a a- a- a a ashy
a-a---ia--a--- a-a-aa-a-~ a-a-aaaa
a- a-a-aaaa-~a-a a a - a- a a- a- aaaa-a-aa-~ a a a- a la-a-a aaa- a a-a- aa aa-aa-a-lta ~-aa~a a a -a- a a a - a- a a- aa- a-~ a-agt 4aa-a-aa4-a-a-a-a a-aa a-a- a a 4 ~a-a- a-a a a aashya a-a a-a- a-ashya~a $aa-a-a~a-a-a4- a~ a- a-aJ a aaa- a- aa a- a- a-aa a-a a-a aa a a-a-a-
aaaIaaaa-a-a-a-a~a a-a- a-a-
a
a- ~a a-a-
a- a a- a-a- a- a a-a-ashya a-a- a- a a a- a-a-44aalt a- a-- a-aa-~ a a-a- aa-~24a4aaaa~aa
a-a- a a- a a- a- a a - a a
~a a~a-a-a-aa-a-a-a aa-a-a a- - ~-a-a a ~ a- a-a a a-a- a- aa~a a-aaa-a a a- aa-aa-a-aashy~a-a-~- a-- aaaa- -aa a 4a a-~a-~a- aaaAa a a-a- a- a-a-a- --- a-a-ashyaa-a-a-~aa-a a~~a- a-a aa-a-aa~aa~a~aaa a- a-a-a-4~a- a a a-a-a-ashya-a-2 a-aaa-gtaa-al a a- aaa~A a-a-a-a-a- a
a-a a-ashya-a-a-a-a a- Jaa-a- a-aa- agt a- aaa aa-a- a a a-3a-a- ~a a-a-a- ~gta-~~~a- 4- 4aa-Aa--------------------a--a- a-a- ~~ a-a- a~~a-Pa-a-a-a-~ 2--a-a- a ~a-aaaa-a4aa-aa-aa- a-a-a-agtaa-aa2aa~a-C-i-a-a a- a-a-- aa-a- - a
- a a-a- a-a----a-a a-a-- - ~aa-~aaa4a a a-a-a- a-gt -a-~ a--4a-a-a-~a-~a- a-a-a- a--a-a---aaa-aaaa--a-aaaa--aa-a--a a-a--a-aa-~a-4a-a-a-~--a--~aaaa--- a a-~a-~ a- a- a-a-a a-a-a4 ashy-- aa-- -aa-a- a-a~--~a-~aa--a-~a- aa-- a~-a- a-aaaaaa-a--a-a-a-a-aaa-a-a-aa-a-a-aa-a-a-a- ~a~a-aSaaa-a4-ashya-~a-a-aa-~aa-la-~a-a~ 2 -a--a-shy
a-a-a aaaaa-a- a-a-a-i aa---a- a-a--a--a aa-a~~-a- aaa-a-a-aaa-a-a-a- -- a- agt a-a-a-a-a-a-a-a-~ a a---- aaa~a-~aaa---aa-Xaa--aa-a-aa-a-a-a-a -shy
- a a ~ ------------shy aaa -------------- a-a-- -a -a-- - a-a-a-a a-a-aa-a-a-a- aa-~
gt7gt a-a-aaa-~aa-aa-a-aa a-- a- la-a a a-a- aaa-aaa- a-a-
4 a-2a- aa~a- -~aa-a a-a-a-a--a- a-a-a-Yaaa-~a-~-aa-3a-aa4yaaa~a-aaaaaaa-a-aa-aa- a-Va-a--a- a- -~ -a-a- a- ~a- 4~ a-a- -a-~ - - - a-4a-aa- aa--a-aa a-a-~ a-a-a-a-a-a-a aa-aa~ -a-
~ a-j-~a-a7~24 a-a- -a-a-a-~a-a-a a-- a-aa-4a-a-4a-4a-a 1
44aaaa- a-a-4- a-~a-a~a-a-aa a-aK ~a~Ca-a-~a-a-Aa-P~aa-a~-a-a-aaa-a-aa-~Aa-ltaa-a(a-aampa-Aa-a-a-aa-a-A aa-aa a a-aa4a-a-44a-aaa-a-gtashy
a-a-a- - ~ lta-a~aa-~a-(a-a--aCpaa-a~ aa~a-~-a-a-a-aaa-aa4-aa-aa~a-aia-a-a-a~a
---- ~ 4 aa~aii4~a~a-iAa-a-aaaaa-a-aaaaa-aaaaa-Aaaaaaa-ia-aa-a-aaa aa-aaa-aa-a-a-Va-P4a4~~aaa-aa-~aa-
a-i a-a a-
-a- ~ a a-~ - a--a- a a-a-a-a--- ~a-a-a-aa-a- a-a-a- a- a
~a-a~a~~a-a- 4-a-a-i a-a- aa-a-a-~~aa-a-~ a-a-~a4aa 4 ~a--a-a- a-Aa-~aVia-aa~a 4- 2- 4- a-a-a~ 4a-a-igt~4~-~a4 4- -shy4a-a-a-ia-a- aa4a-~a4a-a-a2a-a -a-a--aaa-a a-a-a-a a-a--a- a-a-ashy
a -a-4Va--~a-C~a-~a-aa-a-a-4a-aa-4~a-4iaa ~ a-a-a ~a-~ w a-a- -a a-~ a a a-a-a-i a-a-a a~-a-aa-a- a~ taa~a-a-~a4~aa-a-a-aa-a-~-aaaaaa---a-a- aaa-~~a 4 Aa-a- a-a-ashya- a-~ aaa-a-a-a~~Ta-a4~aa a-a-a a- -a--a aa-a-a-a-a -aa-a-aa-~a a-a ashy~ a-~ a-a-aaa~~ a~- a-~aIa- ~ - aa~ia-~a4 a-a-ashy -z~
a- ~ a-Aa-~~ a- -- aa-a-a~aa-aa-a- aAa- a aa-a- a-
XEC IUT VE SU INARy
A PURPOSE OF EVALUATIO The purpose of hi s eulu aci)n s to assess t ie proqess of implementation
of the Traininj and Devel opinent Issues (TDI ) Project identify probl ems andissues that nay have hamsered project progress and recommend measures tomaximize project impact on the develornent effor of the new government
B PROJECT PURPOSE o zJC 2The purpose TheT iS tO ]uoroe t2e apaolit oT the
Philippine Government anl ctiher instI tutions to analyze develoument issues andto make sound and timely C-lont-reiated Jechions
C CONCLUSIONS AND - gt
1 Overall project progress has been relatively slow While training(Participant Trainin2 Corsnent and the training element of the Development n s by and larje on schedule progress ofthe non-trainine nns (rsearch fora teiuicai and management assistanceand equiprne nt Depeloum+n t componentd c mlo o)f h) Dhe s isses has been
painfully slow
This notwi t htanaid nr ci current eviidence supports the continueduserulness of rothie ear + its expressed obiective of buildinq uoinsttut0ional caciies foreen poliiv analysis and relateddecision-makinc The pot2ntial v Iue of the project is further enhanced by
de-isions TD t+- woul - toto nono u pace of project implementation buz aiso expand project benefits and impactand (b) the positive climate under the new government
(a) recent - o the a t o onl yy i rove - e
The slow proress o thO proj It to v-- unI i kelydat e renders the full inmpleImentation of the projec within the curren PACD
Accordingly the follow ing maijor recommend- ~i are herein made
Recomend ation 1
The priject shoul d be toc ninued and the -eeded by t1io years Decenber I 9J
Recornmendati-l 2
Should fo two-yearthe rcn a elttnsin of the PACD beaproved] rti~er evaluat ion of the project - id e underzahen i the first half 191
~Recommen dtioni32
an cosdrtopesing of th ot etsrvcn iffclte and i osdrtoof theidi Fffsed social beneits of the project theS~entire unearmar ed loan allocation to the projetshoul d be converted to
-771-2-Thes-Ioi-prog ress-of tb4e- non training-eImn shs-be-rotd-a in n_7basic int Iretti onai differences bet e te-TDI _PMvOad the USAID Mjsion~ on the~aproach-toproject imletto and the-e lted isueof extraScompensatioqn for gvernmienitpersonnell This i n r slnialeorpolmin the cornrunication process jbetwen the two 4parties~At thejdesign stage ~ more extensive discussions werepreVented bamptimersue-bo happroaching US bu dgetary deadl ines At the im~lernentE tibon st ge ffective~
specifically Vwlth respect to USAIDs merbership-in thrieitSernlt Commi-ttee and (b) the fact that 4 both the USAID Miss ion and1he TDI Pon Sendscompeting claims on staff time rendered it difficultgtfor closerattenti on to bedevoted -to project concerns~~
Inlight of the foregoing the followingrecommendations~are made J j Recommendation 4 4
To enhance smooth and timely implementation~o fthe p-oject as awoead in particular ofthe non-training~e ementsor the Devel4opment Issues~
- component acl1ear resol ution of the problem issues_should be 1made and 4agreements
shyreached clearly set out44in projqc~t imp emetation letter iilt7iAlso to the extentTneeded to resolve uncertainiies 4or ambiguitiesyconcerning administrative aspectsofpoet imlemnain - Isisampulbe issued 4that clearly set-out USAID gu(inclns and proexemptions that -may be6greeudtupon)1 y d pon - V 4e4-
Recommendation 5 Tthe extet eded for4 smooth impjlementain I cenewJf~il
managementof the pr jct at-1both the TDI-T 4 ad -theUSAID ends shoul d ~ -devote miore timne to the- ranagement of the-project Mor 1etiMLe is clearly4--needed in the immeidiate fut-ure to resoIveba sic is sues clarify 4if~
-4shy
regulations and establ ish4 ruie procedres~I4~4
Recommendation 6 4
In the specific case of te non taning eImnsoFthe Devel opment Aigtises comnponent it ils t hat arecommended t eias a porton 0 ~ ~~management dutiles be transferred to the Phlppine Institute for 4-4----~shy
shy_ ~ z Developmient Studies(PIDS) which hasexperience in the4 maaeeto4researchi and iiS1 procedures
11i Il iw4
0ctob~ b3 Te p98 7Wrso nteTD saar- has ~Produced veryencouraging ejiysbiss Ifls1ronsto e yejeer Proposal Sane the TDI PMO hpas decifded to convene s-Imilar workshopsi h~tre ona regul ar bsspss-by wc a y 1rZgtTI- ecision is stronglyendorsed 4 ~gtosbjtc
InI addtinoever parallel acinwl ndtob taken in othei ctimpa
pr je
~~ The six areas tha~t ha-ve been selcted7 as prioriti - -h anarrtrelated actfitij s fo0 stanpcl ~id
iare deme so broad th~at pro1 ect acriis n Mact would tend -to be too di~~Afft-- Ac4nq5
finer fouigof the Research Agenda should b unetkn uhtaproject activities are limited toa smal inumber of development issues~------- ~deemedcriticalunder the new governImentttetnl~2PThrey
resources of a larger numbwer ofinsti ucions can be applied to a-particular~issue produce more extensive as well1 as more iidepthiigt -- analysis fnd altogethier maximize project impDactjb)While curirenit iplementation procedures
- ~ elements1of the eel opment coverinoIssues Component are- design9edthe o-traininto~ ngmtehcompetitiv~e niature of a~ad~encourage broad participationandensure cons istency witi-pojc purpiose thei rj tie-consumi ng character tends to4plusmn4v effecti Yely rule out use of the proj ect for urgnt shor$t-termpohi -ity44 issues and their rigidity limits the~ability of project managmnt
444 -- iitiate quickI relevant coiisul tancies Accordingly gmn Recommendat ion Gi4 Impl ementa tion procedureN
)444shld be difi ei toal1owgeae Aiscretionary powers4 to the TDI-PM0 Specjif44 cally the TDI -PMObe authiorized to approvewithout furthj should Commi ttee or ned of eitherSt44ering~USAID approval 4 proposals ridcotas ontpista 444have4 been previous y cleared 1e~as4 ela on ~lvant topics thatshy
445a44--y be of Jimmediate urgency 111This 4a~thio~ity howeershul bpshy4~-~4444- imited both a~s4I to the- amount of any-indifdual contract
4 and to the total amount of all such contractsJora say $150001given yearsay~i it
~44444-~4$1 00000 vii 4 4
74 4 ~4i While raining activities have bee proce ding argel on- ched
exit~ coe for improvement in component operation~s ~o enlarge trainingshybee1isand -broaden the i r di stribut ion i 4~4 - 4
7~
-44444 - -
h4~4~-444444
7a) ~Whul sc he ifor io riti Zing9 benefic ary ins~tttons ard fiel ds ojjstudy Ahas been diia n up and Va rgeIy f I Io eld ~he absenceof dei1ed prog ram of t rainingactiY1ti - resu1Ited inh certan i l~neidistribyton ~ among agenc 1es wi th~i npri or ity groupsKa
~of 5studiy~ and~bewe I eta nregionai o fijce s 4is also en b eEthe accomodation of agenc Ie ht
s as 4eI I Id ludy~ th1at wef- as fiL f ltt) out(seoK~f establ i sp priorities
As earl ier noted nowever theTDI-PM~O has recentlyKapproved speci fi c - xcproposals to correct4 these jrnibalaance These inclu~de 1i)forniu1 ationof a oedea e prog ram for trlnnf iers of the project d~ration
WioselmDremenedtation t1p m arograts S partial-shifting of the trainin6g budget -from overseastKo local traTi n in
i)th upadadjustments in stpnrae )OIafllwances and Kvjyresea rch LiesiS al IOwahces urider Iocdl11 tvilo fiijgrants to enhance theirSVKatt ractiveness expansion off6nding-support underthpoeto
include training insuitable ~fields ihn selected isitt teinlsof~learning in-the country~and iv) broadening institutionial and regionalparti~cipation in the~trann 0opo~amp -riig compnent
$AlI of the fore_goi ng recommendati ns are hereinK endorsed In addi tion Re ot meond 1
KKK K
K ~ cobnatinthIUKK If somdnr-sise prjcs not KK K shiftingKKK
A)Whie ssesetof henodistributon fo1ields)toi o finininpcif K beween thegenraenvK i antd egn oel setortesse asytt es
~KKK~KKo enbl csounb andertaken to fl~ Kthexentto4hjit7tprojyectfne Khe Kriig objctve foispoen hisr acivd the K~KK K
KKAnito Kg Kine eficedmediatelyV~KKKKKsytm eniioe tpe beprojectsshould KKKestablished KKK a c~K v a d
K KK
I BACKGROUND
The Training and Development Issues (TD) Project was designed to improve
the capability of the Philippine Government and other institutions to analyze
development issues and to make sound and timely development related
decisions This objective was sought to be achieved mainly through training
and the conduct of research and related activities on a small number of issues
deemed critical to the sustained pursuit of Philippine development
The project was conceived to address perceii gips in the USAID
assistance program to the Philippines First most previous research
activities had not focused on developing the information needed for effective
decision-making and policy review Second general participant training
projects had lacked specific focus and supporting activities thereby limiting
their impact And third sectorally focused institutional development
projects often could not fully a-hieve their development objectives because
many key policy related factors affecting project success were beyond the
control of the implementing agency
Under the Project Agreement vwhich was signed on 29 July 1983 USAID
committed to provide a total of $42 million in loans ($33 million) and
grants ($09 million) Of this amount $25 million was allocated to the
Development Issues Component and $16 million to the Training Conponent with
$100000 set aside for evaluation USAID funding for the project was
subsequently raised by a $3U0000 grant that brought the total USAID
commi tnent to $45 million Government counterpart funding amounted to $15
million PACD aas set at 31 December 1938
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
XEC IUT VE SU INARy
A PURPOSE OF EVALUATIO The purpose of hi s eulu aci)n s to assess t ie proqess of implementation
of the Traininj and Devel opinent Issues (TDI ) Project identify probl ems andissues that nay have hamsered project progress and recommend measures tomaximize project impact on the develornent effor of the new government
B PROJECT PURPOSE o zJC 2The purpose TheT iS tO ]uoroe t2e apaolit oT the
Philippine Government anl ctiher instI tutions to analyze develoument issues andto make sound and timely C-lont-reiated Jechions
C CONCLUSIONS AND - gt
1 Overall project progress has been relatively slow While training(Participant Trainin2 Corsnent and the training element of the Development n s by and larje on schedule progress ofthe non-trainine nns (rsearch fora teiuicai and management assistanceand equiprne nt Depeloum+n t componentd c mlo o)f h) Dhe s isses has been
painfully slow
This notwi t htanaid nr ci current eviidence supports the continueduserulness of rothie ear + its expressed obiective of buildinq uoinsttut0ional caciies foreen poliiv analysis and relateddecision-makinc The pot2ntial v Iue of the project is further enhanced by
de-isions TD t+- woul - toto nono u pace of project implementation buz aiso expand project benefits and impactand (b) the positive climate under the new government
(a) recent - o the a t o onl yy i rove - e
The slow proress o thO proj It to v-- unI i kelydat e renders the full inmpleImentation of the projec within the curren PACD
Accordingly the follow ing maijor recommend- ~i are herein made
Recomend ation 1
The priject shoul d be toc ninued and the -eeded by t1io years Decenber I 9J
Recornmendati-l 2
Should fo two-yearthe rcn a elttnsin of the PACD beaproved] rti~er evaluat ion of the project - id e underzahen i the first half 191
~Recommen dtioni32
an cosdrtopesing of th ot etsrvcn iffclte and i osdrtoof theidi Fffsed social beneits of the project theS~entire unearmar ed loan allocation to the projetshoul d be converted to
-771-2-Thes-Ioi-prog ress-of tb4e- non training-eImn shs-be-rotd-a in n_7basic int Iretti onai differences bet e te-TDI _PMvOad the USAID Mjsion~ on the~aproach-toproject imletto and the-e lted isueof extraScompensatioqn for gvernmienitpersonnell This i n r slnialeorpolmin the cornrunication process jbetwen the two 4parties~At thejdesign stage ~ more extensive discussions werepreVented bamptimersue-bo happroaching US bu dgetary deadl ines At the im~lernentE tibon st ge ffective~
specifically Vwlth respect to USAIDs merbership-in thrieitSernlt Commi-ttee and (b) the fact that 4 both the USAID Miss ion and1he TDI Pon Sendscompeting claims on staff time rendered it difficultgtfor closerattenti on to bedevoted -to project concerns~~
Inlight of the foregoing the followingrecommendations~are made J j Recommendation 4 4
To enhance smooth and timely implementation~o fthe p-oject as awoead in particular ofthe non-training~e ementsor the Devel4opment Issues~
- component acl1ear resol ution of the problem issues_should be 1made and 4agreements
shyreached clearly set out44in projqc~t imp emetation letter iilt7iAlso to the extentTneeded to resolve uncertainiies 4or ambiguitiesyconcerning administrative aspectsofpoet imlemnain - Isisampulbe issued 4that clearly set-out USAID gu(inclns and proexemptions that -may be6greeudtupon)1 y d pon - V 4e4-
Recommendation 5 Tthe extet eded for4 smooth impjlementain I cenewJf~il
managementof the pr jct at-1both the TDI-T 4 ad -theUSAID ends shoul d ~ -devote miore timne to the- ranagement of the-project Mor 1etiMLe is clearly4--needed in the immeidiate fut-ure to resoIveba sic is sues clarify 4if~
-4shy
regulations and establ ish4 ruie procedres~I4~4
Recommendation 6 4
In the specific case of te non taning eImnsoFthe Devel opment Aigtises comnponent it ils t hat arecommended t eias a porton 0 ~ ~~management dutiles be transferred to the Phlppine Institute for 4-4----~shy
shy_ ~ z Developmient Studies(PIDS) which hasexperience in the4 maaeeto4researchi and iiS1 procedures
11i Il iw4
0ctob~ b3 Te p98 7Wrso nteTD saar- has ~Produced veryencouraging ejiysbiss Ifls1ronsto e yejeer Proposal Sane the TDI PMO hpas decifded to convene s-Imilar workshopsi h~tre ona regul ar bsspss-by wc a y 1rZgtTI- ecision is stronglyendorsed 4 ~gtosbjtc
InI addtinoever parallel acinwl ndtob taken in othei ctimpa
pr je
~~ The six areas tha~t ha-ve been selcted7 as prioriti - -h anarrtrelated actfitij s fo0 stanpcl ~id
iare deme so broad th~at pro1 ect acriis n Mact would tend -to be too di~~Afft-- Ac4nq5
finer fouigof the Research Agenda should b unetkn uhtaproject activities are limited toa smal inumber of development issues~------- ~deemedcriticalunder the new governImentttetnl~2PThrey
resources of a larger numbwer ofinsti ucions can be applied to a-particular~issue produce more extensive as well1 as more iidepthiigt -- analysis fnd altogethier maximize project impDactjb)While curirenit iplementation procedures
- ~ elements1of the eel opment coverinoIssues Component are- design9edthe o-traininto~ ngmtehcompetitiv~e niature of a~ad~encourage broad participationandensure cons istency witi-pojc purpiose thei rj tie-consumi ng character tends to4plusmn4v effecti Yely rule out use of the proj ect for urgnt shor$t-termpohi -ity44 issues and their rigidity limits the~ability of project managmnt
444 -- iitiate quickI relevant coiisul tancies Accordingly gmn Recommendat ion Gi4 Impl ementa tion procedureN
)444shld be difi ei toal1owgeae Aiscretionary powers4 to the TDI-PM0 Specjif44 cally the TDI -PMObe authiorized to approvewithout furthj should Commi ttee or ned of eitherSt44ering~USAID approval 4 proposals ridcotas ontpista 444have4 been previous y cleared 1e~as4 ela on ~lvant topics thatshy
445a44--y be of Jimmediate urgency 111This 4a~thio~ity howeershul bpshy4~-~4444- imited both a~s4I to the- amount of any-indifdual contract
4 and to the total amount of all such contractsJora say $150001given yearsay~i it
~44444-~4$1 00000 vii 4 4
74 4 ~4i While raining activities have bee proce ding argel on- ched
exit~ coe for improvement in component operation~s ~o enlarge trainingshybee1isand -broaden the i r di stribut ion i 4~4 - 4
7~
-44444 - -
h4~4~-444444
7a) ~Whul sc he ifor io riti Zing9 benefic ary ins~tttons ard fiel ds ojjstudy Ahas been diia n up and Va rgeIy f I Io eld ~he absenceof dei1ed prog ram of t rainingactiY1ti - resu1Ited inh certan i l~neidistribyton ~ among agenc 1es wi th~i npri or ity groupsKa
~of 5studiy~ and~bewe I eta nregionai o fijce s 4is also en b eEthe accomodation of agenc Ie ht
s as 4eI I Id ludy~ th1at wef- as fiL f ltt) out(seoK~f establ i sp priorities
As earl ier noted nowever theTDI-PM~O has recentlyKapproved speci fi c - xcproposals to correct4 these jrnibalaance These inclu~de 1i)forniu1 ationof a oedea e prog ram for trlnnf iers of the project d~ration
WioselmDremenedtation t1p m arograts S partial-shifting of the trainin6g budget -from overseastKo local traTi n in
i)th upadadjustments in stpnrae )OIafllwances and Kvjyresea rch LiesiS al IOwahces urider Iocdl11 tvilo fiijgrants to enhance theirSVKatt ractiveness expansion off6nding-support underthpoeto
include training insuitable ~fields ihn selected isitt teinlsof~learning in-the country~and iv) broadening institutionial and regionalparti~cipation in the~trann 0opo~amp -riig compnent
$AlI of the fore_goi ng recommendati ns are hereinK endorsed In addi tion Re ot meond 1
KKK K
K ~ cobnatinthIUKK If somdnr-sise prjcs not KK K shiftingKKK
A)Whie ssesetof henodistributon fo1ields)toi o finininpcif K beween thegenraenvK i antd egn oel setortesse asytt es
~KKK~KKo enbl csounb andertaken to fl~ Kthexentto4hjit7tprojyectfne Khe Kriig objctve foispoen hisr acivd the K~KK K
KKAnito Kg Kine eficedmediatelyV~KKKKKsytm eniioe tpe beprojectsshould KKKestablished KKK a c~K v a d
K KK
I BACKGROUND
The Training and Development Issues (TD) Project was designed to improve
the capability of the Philippine Government and other institutions to analyze
development issues and to make sound and timely development related
decisions This objective was sought to be achieved mainly through training
and the conduct of research and related activities on a small number of issues
deemed critical to the sustained pursuit of Philippine development
The project was conceived to address perceii gips in the USAID
assistance program to the Philippines First most previous research
activities had not focused on developing the information needed for effective
decision-making and policy review Second general participant training
projects had lacked specific focus and supporting activities thereby limiting
their impact And third sectorally focused institutional development
projects often could not fully a-hieve their development objectives because
many key policy related factors affecting project success were beyond the
control of the implementing agency
Under the Project Agreement vwhich was signed on 29 July 1983 USAID
committed to provide a total of $42 million in loans ($33 million) and
grants ($09 million) Of this amount $25 million was allocated to the
Development Issues Component and $16 million to the Training Conponent with
$100000 set aside for evaluation USAID funding for the project was
subsequently raised by a $3U0000 grant that brought the total USAID
commi tnent to $45 million Government counterpart funding amounted to $15
million PACD aas set at 31 December 1938
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
~Recommen dtioni32
an cosdrtopesing of th ot etsrvcn iffclte and i osdrtoof theidi Fffsed social beneits of the project theS~entire unearmar ed loan allocation to the projetshoul d be converted to
-771-2-Thes-Ioi-prog ress-of tb4e- non training-eImn shs-be-rotd-a in n_7basic int Iretti onai differences bet e te-TDI _PMvOad the USAID Mjsion~ on the~aproach-toproject imletto and the-e lted isueof extraScompensatioqn for gvernmienitpersonnell This i n r slnialeorpolmin the cornrunication process jbetwen the two 4parties~At thejdesign stage ~ more extensive discussions werepreVented bamptimersue-bo happroaching US bu dgetary deadl ines At the im~lernentE tibon st ge ffective~
specifically Vwlth respect to USAIDs merbership-in thrieitSernlt Commi-ttee and (b) the fact that 4 both the USAID Miss ion and1he TDI Pon Sendscompeting claims on staff time rendered it difficultgtfor closerattenti on to bedevoted -to project concerns~~
Inlight of the foregoing the followingrecommendations~are made J j Recommendation 4 4
To enhance smooth and timely implementation~o fthe p-oject as awoead in particular ofthe non-training~e ementsor the Devel4opment Issues~
- component acl1ear resol ution of the problem issues_should be 1made and 4agreements
shyreached clearly set out44in projqc~t imp emetation letter iilt7iAlso to the extentTneeded to resolve uncertainiies 4or ambiguitiesyconcerning administrative aspectsofpoet imlemnain - Isisampulbe issued 4that clearly set-out USAID gu(inclns and proexemptions that -may be6greeudtupon)1 y d pon - V 4e4-
Recommendation 5 Tthe extet eded for4 smooth impjlementain I cenewJf~il
managementof the pr jct at-1both the TDI-T 4 ad -theUSAID ends shoul d ~ -devote miore timne to the- ranagement of the-project Mor 1etiMLe is clearly4--needed in the immeidiate fut-ure to resoIveba sic is sues clarify 4if~
-4shy
regulations and establ ish4 ruie procedres~I4~4
Recommendation 6 4
In the specific case of te non taning eImnsoFthe Devel opment Aigtises comnponent it ils t hat arecommended t eias a porton 0 ~ ~~management dutiles be transferred to the Phlppine Institute for 4-4----~shy
shy_ ~ z Developmient Studies(PIDS) which hasexperience in the4 maaeeto4researchi and iiS1 procedures
11i Il iw4
0ctob~ b3 Te p98 7Wrso nteTD saar- has ~Produced veryencouraging ejiysbiss Ifls1ronsto e yejeer Proposal Sane the TDI PMO hpas decifded to convene s-Imilar workshopsi h~tre ona regul ar bsspss-by wc a y 1rZgtTI- ecision is stronglyendorsed 4 ~gtosbjtc
InI addtinoever parallel acinwl ndtob taken in othei ctimpa
pr je
~~ The six areas tha~t ha-ve been selcted7 as prioriti - -h anarrtrelated actfitij s fo0 stanpcl ~id
iare deme so broad th~at pro1 ect acriis n Mact would tend -to be too di~~Afft-- Ac4nq5
finer fouigof the Research Agenda should b unetkn uhtaproject activities are limited toa smal inumber of development issues~------- ~deemedcriticalunder the new governImentttetnl~2PThrey
resources of a larger numbwer ofinsti ucions can be applied to a-particular~issue produce more extensive as well1 as more iidepthiigt -- analysis fnd altogethier maximize project impDactjb)While curirenit iplementation procedures
- ~ elements1of the eel opment coverinoIssues Component are- design9edthe o-traininto~ ngmtehcompetitiv~e niature of a~ad~encourage broad participationandensure cons istency witi-pojc purpiose thei rj tie-consumi ng character tends to4plusmn4v effecti Yely rule out use of the proj ect for urgnt shor$t-termpohi -ity44 issues and their rigidity limits the~ability of project managmnt
444 -- iitiate quickI relevant coiisul tancies Accordingly gmn Recommendat ion Gi4 Impl ementa tion procedureN
)444shld be difi ei toal1owgeae Aiscretionary powers4 to the TDI-PM0 Specjif44 cally the TDI -PMObe authiorized to approvewithout furthj should Commi ttee or ned of eitherSt44ering~USAID approval 4 proposals ridcotas ontpista 444have4 been previous y cleared 1e~as4 ela on ~lvant topics thatshy
445a44--y be of Jimmediate urgency 111This 4a~thio~ity howeershul bpshy4~-~4444- imited both a~s4I to the- amount of any-indifdual contract
4 and to the total amount of all such contractsJora say $150001given yearsay~i it
~44444-~4$1 00000 vii 4 4
74 4 ~4i While raining activities have bee proce ding argel on- ched
exit~ coe for improvement in component operation~s ~o enlarge trainingshybee1isand -broaden the i r di stribut ion i 4~4 - 4
7~
-44444 - -
h4~4~-444444
7a) ~Whul sc he ifor io riti Zing9 benefic ary ins~tttons ard fiel ds ojjstudy Ahas been diia n up and Va rgeIy f I Io eld ~he absenceof dei1ed prog ram of t rainingactiY1ti - resu1Ited inh certan i l~neidistribyton ~ among agenc 1es wi th~i npri or ity groupsKa
~of 5studiy~ and~bewe I eta nregionai o fijce s 4is also en b eEthe accomodation of agenc Ie ht
s as 4eI I Id ludy~ th1at wef- as fiL f ltt) out(seoK~f establ i sp priorities
As earl ier noted nowever theTDI-PM~O has recentlyKapproved speci fi c - xcproposals to correct4 these jrnibalaance These inclu~de 1i)forniu1 ationof a oedea e prog ram for trlnnf iers of the project d~ration
WioselmDremenedtation t1p m arograts S partial-shifting of the trainin6g budget -from overseastKo local traTi n in
i)th upadadjustments in stpnrae )OIafllwances and Kvjyresea rch LiesiS al IOwahces urider Iocdl11 tvilo fiijgrants to enhance theirSVKatt ractiveness expansion off6nding-support underthpoeto
include training insuitable ~fields ihn selected isitt teinlsof~learning in-the country~and iv) broadening institutionial and regionalparti~cipation in the~trann 0opo~amp -riig compnent
$AlI of the fore_goi ng recommendati ns are hereinK endorsed In addi tion Re ot meond 1
KKK K
K ~ cobnatinthIUKK If somdnr-sise prjcs not KK K shiftingKKK
A)Whie ssesetof henodistributon fo1ields)toi o finininpcif K beween thegenraenvK i antd egn oel setortesse asytt es
~KKK~KKo enbl csounb andertaken to fl~ Kthexentto4hjit7tprojyectfne Khe Kriig objctve foispoen hisr acivd the K~KK K
KKAnito Kg Kine eficedmediatelyV~KKKKKsytm eniioe tpe beprojectsshould KKKestablished KKK a c~K v a d
K KK
I BACKGROUND
The Training and Development Issues (TD) Project was designed to improve
the capability of the Philippine Government and other institutions to analyze
development issues and to make sound and timely development related
decisions This objective was sought to be achieved mainly through training
and the conduct of research and related activities on a small number of issues
deemed critical to the sustained pursuit of Philippine development
The project was conceived to address perceii gips in the USAID
assistance program to the Philippines First most previous research
activities had not focused on developing the information needed for effective
decision-making and policy review Second general participant training
projects had lacked specific focus and supporting activities thereby limiting
their impact And third sectorally focused institutional development
projects often could not fully a-hieve their development objectives because
many key policy related factors affecting project success were beyond the
control of the implementing agency
Under the Project Agreement vwhich was signed on 29 July 1983 USAID
committed to provide a total of $42 million in loans ($33 million) and
grants ($09 million) Of this amount $25 million was allocated to the
Development Issues Component and $16 million to the Training Conponent with
$100000 set aside for evaluation USAID funding for the project was
subsequently raised by a $3U0000 grant that brought the total USAID
commi tnent to $45 million Government counterpart funding amounted to $15
million PACD aas set at 31 December 1938
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
11i Il iw4
0ctob~ b3 Te p98 7Wrso nteTD saar- has ~Produced veryencouraging ejiysbiss Ifls1ronsto e yejeer Proposal Sane the TDI PMO hpas decifded to convene s-Imilar workshopsi h~tre ona regul ar bsspss-by wc a y 1rZgtTI- ecision is stronglyendorsed 4 ~gtosbjtc
InI addtinoever parallel acinwl ndtob taken in othei ctimpa
pr je
~~ The six areas tha~t ha-ve been selcted7 as prioriti - -h anarrtrelated actfitij s fo0 stanpcl ~id
iare deme so broad th~at pro1 ect acriis n Mact would tend -to be too di~~Afft-- Ac4nq5
finer fouigof the Research Agenda should b unetkn uhtaproject activities are limited toa smal inumber of development issues~------- ~deemedcriticalunder the new governImentttetnl~2PThrey
resources of a larger numbwer ofinsti ucions can be applied to a-particular~issue produce more extensive as well1 as more iidepthiigt -- analysis fnd altogethier maximize project impDactjb)While curirenit iplementation procedures
- ~ elements1of the eel opment coverinoIssues Component are- design9edthe o-traininto~ ngmtehcompetitiv~e niature of a~ad~encourage broad participationandensure cons istency witi-pojc purpiose thei rj tie-consumi ng character tends to4plusmn4v effecti Yely rule out use of the proj ect for urgnt shor$t-termpohi -ity44 issues and their rigidity limits the~ability of project managmnt
444 -- iitiate quickI relevant coiisul tancies Accordingly gmn Recommendat ion Gi4 Impl ementa tion procedureN
)444shld be difi ei toal1owgeae Aiscretionary powers4 to the TDI-PM0 Specjif44 cally the TDI -PMObe authiorized to approvewithout furthj should Commi ttee or ned of eitherSt44ering~USAID approval 4 proposals ridcotas ontpista 444have4 been previous y cleared 1e~as4 ela on ~lvant topics thatshy
445a44--y be of Jimmediate urgency 111This 4a~thio~ity howeershul bpshy4~-~4444- imited both a~s4I to the- amount of any-indifdual contract
4 and to the total amount of all such contractsJora say $150001given yearsay~i it
~44444-~4$1 00000 vii 4 4
74 4 ~4i While raining activities have bee proce ding argel on- ched
exit~ coe for improvement in component operation~s ~o enlarge trainingshybee1isand -broaden the i r di stribut ion i 4~4 - 4
7~
-44444 - -
h4~4~-444444
7a) ~Whul sc he ifor io riti Zing9 benefic ary ins~tttons ard fiel ds ojjstudy Ahas been diia n up and Va rgeIy f I Io eld ~he absenceof dei1ed prog ram of t rainingactiY1ti - resu1Ited inh certan i l~neidistribyton ~ among agenc 1es wi th~i npri or ity groupsKa
~of 5studiy~ and~bewe I eta nregionai o fijce s 4is also en b eEthe accomodation of agenc Ie ht
s as 4eI I Id ludy~ th1at wef- as fiL f ltt) out(seoK~f establ i sp priorities
As earl ier noted nowever theTDI-PM~O has recentlyKapproved speci fi c - xcproposals to correct4 these jrnibalaance These inclu~de 1i)forniu1 ationof a oedea e prog ram for trlnnf iers of the project d~ration
WioselmDremenedtation t1p m arograts S partial-shifting of the trainin6g budget -from overseastKo local traTi n in
i)th upadadjustments in stpnrae )OIafllwances and Kvjyresea rch LiesiS al IOwahces urider Iocdl11 tvilo fiijgrants to enhance theirSVKatt ractiveness expansion off6nding-support underthpoeto
include training insuitable ~fields ihn selected isitt teinlsof~learning in-the country~and iv) broadening institutionial and regionalparti~cipation in the~trann 0opo~amp -riig compnent
$AlI of the fore_goi ng recommendati ns are hereinK endorsed In addi tion Re ot meond 1
KKK K
K ~ cobnatinthIUKK If somdnr-sise prjcs not KK K shiftingKKK
A)Whie ssesetof henodistributon fo1ields)toi o finininpcif K beween thegenraenvK i antd egn oel setortesse asytt es
~KKK~KKo enbl csounb andertaken to fl~ Kthexentto4hjit7tprojyectfne Khe Kriig objctve foispoen hisr acivd the K~KK K
KKAnito Kg Kine eficedmediatelyV~KKKKKsytm eniioe tpe beprojectsshould KKKestablished KKK a c~K v a d
K KK
I BACKGROUND
The Training and Development Issues (TD) Project was designed to improve
the capability of the Philippine Government and other institutions to analyze
development issues and to make sound and timely development related
decisions This objective was sought to be achieved mainly through training
and the conduct of research and related activities on a small number of issues
deemed critical to the sustained pursuit of Philippine development
The project was conceived to address perceii gips in the USAID
assistance program to the Philippines First most previous research
activities had not focused on developing the information needed for effective
decision-making and policy review Second general participant training
projects had lacked specific focus and supporting activities thereby limiting
their impact And third sectorally focused institutional development
projects often could not fully a-hieve their development objectives because
many key policy related factors affecting project success were beyond the
control of the implementing agency
Under the Project Agreement vwhich was signed on 29 July 1983 USAID
committed to provide a total of $42 million in loans ($33 million) and
grants ($09 million) Of this amount $25 million was allocated to the
Development Issues Component and $16 million to the Training Conponent with
$100000 set aside for evaluation USAID funding for the project was
subsequently raised by a $3U0000 grant that brought the total USAID
commi tnent to $45 million Government counterpart funding amounted to $15
million PACD aas set at 31 December 1938
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
7a) ~Whul sc he ifor io riti Zing9 benefic ary ins~tttons ard fiel ds ojjstudy Ahas been diia n up and Va rgeIy f I Io eld ~he absenceof dei1ed prog ram of t rainingactiY1ti - resu1Ited inh certan i l~neidistribyton ~ among agenc 1es wi th~i npri or ity groupsKa
~of 5studiy~ and~bewe I eta nregionai o fijce s 4is also en b eEthe accomodation of agenc Ie ht
s as 4eI I Id ludy~ th1at wef- as fiL f ltt) out(seoK~f establ i sp priorities
As earl ier noted nowever theTDI-PM~O has recentlyKapproved speci fi c - xcproposals to correct4 these jrnibalaance These inclu~de 1i)forniu1 ationof a oedea e prog ram for trlnnf iers of the project d~ration
WioselmDremenedtation t1p m arograts S partial-shifting of the trainin6g budget -from overseastKo local traTi n in
i)th upadadjustments in stpnrae )OIafllwances and Kvjyresea rch LiesiS al IOwahces urider Iocdl11 tvilo fiijgrants to enhance theirSVKatt ractiveness expansion off6nding-support underthpoeto
include training insuitable ~fields ihn selected isitt teinlsof~learning in-the country~and iv) broadening institutionial and regionalparti~cipation in the~trann 0opo~amp -riig compnent
$AlI of the fore_goi ng recommendati ns are hereinK endorsed In addi tion Re ot meond 1
KKK K
K ~ cobnatinthIUKK If somdnr-sise prjcs not KK K shiftingKKK
A)Whie ssesetof henodistributon fo1ields)toi o finininpcif K beween thegenraenvK i antd egn oel setortesse asytt es
~KKK~KKo enbl csounb andertaken to fl~ Kthexentto4hjit7tprojyectfne Khe Kriig objctve foispoen hisr acivd the K~KK K
KKAnito Kg Kine eficedmediatelyV~KKKKKsytm eniioe tpe beprojectsshould KKKestablished KKK a c~K v a d
K KK
I BACKGROUND
The Training and Development Issues (TD) Project was designed to improve
the capability of the Philippine Government and other institutions to analyze
development issues and to make sound and timely development related
decisions This objective was sought to be achieved mainly through training
and the conduct of research and related activities on a small number of issues
deemed critical to the sustained pursuit of Philippine development
The project was conceived to address perceii gips in the USAID
assistance program to the Philippines First most previous research
activities had not focused on developing the information needed for effective
decision-making and policy review Second general participant training
projects had lacked specific focus and supporting activities thereby limiting
their impact And third sectorally focused institutional development
projects often could not fully a-hieve their development objectives because
many key policy related factors affecting project success were beyond the
control of the implementing agency
Under the Project Agreement vwhich was signed on 29 July 1983 USAID
committed to provide a total of $42 million in loans ($33 million) and
grants ($09 million) Of this amount $25 million was allocated to the
Development Issues Component and $16 million to the Training Conponent with
$100000 set aside for evaluation USAID funding for the project was
subsequently raised by a $3U0000 grant that brought the total USAID
commi tnent to $45 million Government counterpart funding amounted to $15
million PACD aas set at 31 December 1938
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
I BACKGROUND
The Training and Development Issues (TD) Project was designed to improve
the capability of the Philippine Government and other institutions to analyze
development issues and to make sound and timely development related
decisions This objective was sought to be achieved mainly through training
and the conduct of research and related activities on a small number of issues
deemed critical to the sustained pursuit of Philippine development
The project was conceived to address perceii gips in the USAID
assistance program to the Philippines First most previous research
activities had not focused on developing the information needed for effective
decision-making and policy review Second general participant training
projects had lacked specific focus and supporting activities thereby limiting
their impact And third sectorally focused institutional development
projects often could not fully a-hieve their development objectives because
many key policy related factors affecting project success were beyond the
control of the implementing agency
Under the Project Agreement vwhich was signed on 29 July 1983 USAID
committed to provide a total of $42 million in loans ($33 million) and
grants ($09 million) Of this amount $25 million was allocated to the
Development Issues Component and $16 million to the Training Conponent with
$100000 set aside for evaluation USAID funding for the project was
subsequently raised by a $3U0000 grant that brought the total USAID
commi tnent to $45 million Government counterpart funding amounted to $15
million PACD aas set at 31 December 1938
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
--- Th e Na ona on oi ceydDe eopment AutoiU EDA) the central
~coordi nating authori ty for~the p~l anning andimp mentation of Philippine
socio0 ec onomi c devel opment serv~ed as th e Gov ernment 1 gnc oI44nt1ng
The dei gn f the proectrovided f~or 4 the4 conduct f possibly4two
- v al~ai on s~on e t proxi mately mid -t erm of1i mpl ement ati o ad fi na
~-~-ev aluati on at4 th n sb to mutual amptb the eshyagea both parti es -on 4ltfor4it Ths report
-4 n represeints th e resul t oF4 tLId-ietrmi eval uati on th e
44444ltScope of Work for vfii ch 1 s Ap x4444 lt444attach ed as en I444444444444 44 4444444444
444~4444444I I44P4OJECT STATUS
4 4 4 A4444444 l44 444a 44t4t4s
444~4444444As 443 Ma c 1986 fund444444444444 thatgt had~ bee earmarked for 4444
44444444
~4- 42 -4 es 44444444444t 9 5 0 0 r p e e t n 1 pe -J e t o h o a
4Pre4e ent411ov i r1 I~ ape 4gt~444 of 31PROJEC STTU M-ar-h -19-6 was 29 motso
4444-~ 47 per- cen of the 4 ba444 444 of444-44444444the p o durat on o 62 m nths 44444444 4t
444F o44 A4444et ai 1 s s oe Annex A
44444444444444444444444 44~44144 4
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
34J~cye 000)oculj a 96yI Y
Pe r1 1
obi tiOtis IA011t 01i tonsj A o 51igationsbt I TO TAL UJSAl 0 r zi5Q 20 6 3 3
Grant 1200 04I- 337 2881
Loan 3300J 505 15 1gt 50 5 Ii~KiiAs may bDe expec ted par tAcul arly i n Ii 9h FtLLin sf~hua I1y tight
bal ance- I -paymen ts situatio of1nteeono 1 tI dtho ofolocono~i~r~ ~gant
the project has been m- gI po Po oni IfasCerKthanth ~pin i Priono
loanortion W -I
Sl 11 i2 o1 mVgr n lI1at n $ 3 0 a b e a~ir-i e r r
36arm erk ento cenJ 151 perh o hetot on31cto)ams l - a
trinn- rersetn 82 pe ceto 11sad - ae 1pr ~n
ante of tie w1 ctII athe loa iof I~oodf f3all oca OnIV shy- 14
earkarked (1d seinrs)and anda1o oo quipmen com~oditieslos~1 iic
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
- 4-
Table 2
Financial Analysis Training and Non-Training (Cumulative $000)
As of 31 March 1986
I EARMARKED -- COMMITTEDI Percent of I Percent of
IOliaationslImount Obligations JAmount Obliaationsl
TOTAL USAID 4500 935 208 839 186
Training 2530 766 277 763 296
Non-Training 1820 169 93 77 42
Evaluation 100 - shy - -
B Activity Status
The activities for which commitment of project funds had been made as of
31 March 186 are as follows
1 Participation of a total of fifty-nine (59) Filipino scholars in
various educational programs in the US (34) and in the Philippines
(25) 3 Of these 34 have been or are in programs of one year or longer and 25 in programs of shorter duration in addition the
project funded a special training on micro-computers for TDI-PMO staff
2 Research undertakin~s covering
a Evaluation of Ten Years of r5ilingual Education in the Philippines
(2 sets of studies)
3 Detailed List attached as Annex C See also Tables 3 and 4 below forbreakdown by agency-beneficiary and by field of training
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
~41
oaen l] -
Devl 0f 3-- 1 foi- tiieSeL-toraamp Ciassf tjcatio)n of--~~x-
-I -4-- s --t od -g --s 4 -- 4 of o- itr
-141l2 1I-d4 o--r sho n co Y
3 One workshopon thr~-Le~-23 peearAgna anTD roc u- ren e n t o f-htc p in m c ie
The peceding sectionu~ cla4- ory Show tbht progress i-le nton-traV i ng- d--gt -
eleent of--- t--e TD rje t llo hih Fl n er te prjc sDv --p e t
project- tonterksho ontrt orresea rch tgnaki~ng plc ny h-ad
Pri4-r to Puocuresmenumeoff popoopyn rnadni Deele
Issues-4~fo erfnunds fndsfaoa acte on otdfnacn
- WhtheFaLilyu sncmSandexpendfithesPhi~ poin--4 fo th-nsiutoaPr-ile Compone-t 4
ofth Ealatonofth P r o g r a
hi1 p pi e ili g a1 du atom -4
4 4 4
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
-0-
A Diveraence ofZiews on ADproach to Project imlementation
The slow start of the non-training elements of the Development Issues
Component of the TDI Project and its relatively slow progress to-date is
reflective of a fundamental divergence of views between the USAID Mission and the PhiliDDine Governmen implementin aqency for the proh EDA on~ _mni aec o h rject hNEDo
the approach to project implementaticn Specifically while both agree on
(a) the project objective of building up institutional capacities for the
analysis of and subsequent decision-making on key development issues and
(b) on the conduct of research undertakings (including conferences and fora)
to bring this about they dsagree on tne matter of payment for those involved
in the conduct of such research undertakings reflecting a difference in
approach to the at ainment o1 the project s objective
Tile USAID lissions exoectation was that the object-ive would be approached
by focusins goverment personnel attention on particular issues within the
context of their normal functions and thus without additional compensation as
well as by opening up the policy formulation process to a broad spectrum of
participants from outside government thereby enriching the process itself and
the policy recommendations that subsequently emanate from it The outputs
being d dist-illation of hopefully some of the best minds in (and as
necessary out of the country policy-makers ould be better-equipped for
decision-makinQ on zritical issues This would be supplemented by funding
provisions for training in issue-related fields From the foregoing the
Mission lxpectationthat government personnelwas would be actively involved
in te project without extra compensation so that much if not most of the
funds for non-training Development Issue Component activities would be paid
out to non-governmental institutions
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
7
eeA
GQiTe but -a aitiona tier oa ti exto herej app a
ng
c luc h o tl~h pcfcrbem Aha -ave~- sl-~ d prges howed n
i e Pro ecteSawho omptitiv roc ren contattinsw t l
iacn ipenta-ions aod Ith fundamentalu diegicup i n vigt 4- i tiand expfo atins -
four~-res-eard nureactvte t1yyisgong have~ inole TD td-e f
- uctheth dife t iabascci renc haexplettin ijogrstf to ----onect implemefntio the hae epenth rssuessfnaetl nd es
prolemti isses A t have pa tl th ---geerllit--ted~t slo progthess A-A
sp-- rProje c asa rcholeieiti~sca P_undrocuk en icondt ri -shy~In g ernrfliet ~
A71 Ashy
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
-8-
B Communication Problems
The fact that the projects principal problems are rooted in basic
interpretational differences would seem to indicate problems in the
communication process between the USAID Mission and the Philippine Government
throuch its implementing agency the NEDA concerning the project indeed
for various reasons this appears to have been the case from the design stage
to at least the early stages of project implementation
1 Project design stage
Because of pressures brought on by approaching US budgetary deadlines in
mid-1983 there was little opportunity for any extensive discussion between
the ilission and the INEDA on the Project Paper which was prepared by the
Mission Staff Indications of the basic differences in expectations with
respect to the approach to project implementation thus began to surface only
in the course of implementation itself as the TDI-PMO based at NEDA began to
endorse for the Missions clearanceapproval specific proposals to use project
funds for non-training activities including equipment procurement
On this particular issue it may be pointed out that the language of the
Project Pap-- was by no means unequivocal in thie discussion of Submission
of Issue Proposals and Selection of issue Activities paragraphs 1 and 2 of
p 11 state that
A wide variety of organizations are expected to submit proposals and
thus be eligible for implementing ac-ivities These include (a) units
within NEDA (b)GOP agencies (c) Local governments (d)Government
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
corotinsfe)Reseaich an deducati oil insti tutions) (f Pci ate
or iUo 3t1 and~joilntr yentuI-es alni1on any ofPr~an J~2Combif~t ion
thelfl2~On fl ~
i~~t ne$ o rgmdt gtl roosaIne o ed -i e 4Z4 -- 4-Nt ls-b lE D t-- I am a-n-~a4t4~4o n F 4 op c mp-- t-NN ap1e -a lt o
E e eO 1epaoven-apropol t -fo1A
muc i fO11o t mto ie fundsa Ivoirtie icsh reold e ciiisu epi-
aand ptyrsonnelpr1heIva001 reserc jon ~taboutri prayng gzt insm t nsui ons -
-~- pr bs I s
cnra isu thamot 1 neef cleryseled-ct and agreeyd be paidthrds torttl
tv o prtes-in heuouseonsrjc imnplemenothriond theysdowereo~d bas-sugt-gt-lte toii ov annm rnsl ieCti tan ngt isustat oldo h -eahi~e ln
Oresc anyroundher tani-s 4-icutoo 4tergdemndth o sheofmof tepati
F -n2 --- cus n n Lhis p o 7 VV4-
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
- 10 -
TWo soecific situations contributed to the insufficiency of
communia-ions rirstly the NJEDA TDI-Project -lanagement and the USAID
Ilission differed on the particular issue of USAID representation in the
Project Steering Committee The Mission had expected to be an ex-officio
member of the Committee the TDI-Project Managements position on the other
hand vias that since the USAIDs role in the Steering Committee as specified
in the Project Agreement was advisory USAID participation in Steering
Committee meetinQs would be strictly on a need basis
Secondly neither the USAID nor more importantly even the NEDA TDI-PM1O
was devoting much time to the project
For example Project Impl ementation Letters setting out pertinent USAID
implementing guidelines and procedures were not issued early on The only
issuance of this nature (PIL NJo 3) came in January 1985 seventeen (17)
months after signing of the Project Agreement setting out the mechanism for
financing the Develoomen- Tssues Component (This represents a sharp contrast
to the Economic and Social Impact Analysis-Women in Development (ESIA-WID)
project in which within a little over three (3)months of the date of signing
of the Project Agreement at least five (5) PILs had been issued setting out
among other things criteria for satisfactory compliance with conditions
precedent guidelines for contracting and exemptions thereto and procedures
and documentation for requesting and liquidating AID Peso advances) Perhaps
this was due to USAID presumpions as to the extent of the project personnels
awareness of USAID rules and procedures
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
C j
1 L~ (J O eZ
C~CrpnnvIaaeret7 iil n -c mP 1opmnise oio
USIDgudl ne an i-a 4 apocduraeen opude by tencoprativelymp1n
coom nngtandoitsel c77S t-Eh e)EoR S ntheDee tiyFr 4P off o mhaag oadnt
UndeZer which th-enanagenglUAsiD sancedStaff (whse~ Diectoe athe a
better Jnf thdlatte sutflureha eentolacI orIfactar ibftmay e rSltuethd
7- ~ t cui 7dlinof hwavlomn sus compon eyt praifielyevt -e77~774774
no( tranin Iaof ths soff AseOeioloa a comonnshouldntD have beet astigned stne1E
to bg-ent adresd preerabl ones dut a e tenass 7-oropri nc i
From thsise Onele thed t thne tePR Deoe opnanthprojecoits therof choice f
Deeon fromeviwesubrs staandpin the logca Assues Component as tntiva
the7gtuangmt strucDttue is rsosbe thnialforojhet mardnaemen ofuttelt 74- J77747
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
- 12 -
Philippine development panning it is in a particular vantage point to assess
an prioritize poi cy research issues and proposals that bear on Philippine
devel opment
0 Implementation Procedures
Following from the USAID premise of the broadest possible participation in
the policy formulation process the implementation procedures set out in the
Project Paper envisioned extensive use of seminars and conferences (about 30
to 40) in the entire course of project implementation from issue selection to
the presenta-ion of research findings and recommendations These procedures
were adopted in the implementation Plan of the DeveloDMnt issues Component
in the implementation o- zite project to-date however only one such
workshop-conFerence- has been nel d and this in October more tiian1985 two
years from the daze of signing of tne Project Agreemnt The purpose of this
workshop attended by representatives of various research institutions was to
publicize generate interest in and hopefully speed up research formulation
under the Development Issues Component of TDI
Significantly post-orkshop response to the project has been encouraging
wit~is aditionalproposals having already been received on topics in the
Research Agenca as ail as -n others related to it Still others are
currently under preparation From clnis standpoint much improvement may be
expected in the pace of mpement3ation of at least the research element of the
5Development -ssues Component within the coming monthsshy
5 The Steering Committee was scheduled to meet on 14 July 1986 at which approval of research proposals 4ith a total cost of just under $200000 is expected
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
134
Ri 2 i~s1e +ciohana~pp O~iPI-O(echfL~eand iequl E1i tsl aI o c a u5s
de 1a s 4n 1117 -i ioii fz s opnn ~docn i aDIb Iduc d thceiei~
S I S j f ~t 2DrQ ocedures mndat2a SbI91 SiOll Of DI OPOSai SuunesS~~
tehn Ve YeS SZC eeaDPr0 o f p 1 ISC0so t ng oveA
1 and-US ID approval olf a I po10s a s regaId] o3 7f CosS c h7000003
bri d part icipati on ~and eisur2cdnsi s e[iy t poj orps 3S SUC
ormdi -l a l1Ong teri devel opmenlt iSSLueS Such ieconSumII ng PrcCIesKi ate~ acceptable roM val they also effle ti vel1y ru le outlteueoute
pr ojec t for short-term pol iy issues and 1-rit the ability of pr oject manage~rs
lt~~ to A itijate quickIy relevant consul ta ncies lt-~lt~ gt7
77 VTRAINING
A2 P 8 e of amp- in 1o 7mo
kser e ntd7ot lle arltrinsan om ten rU7ADf d
p7777hs or etr le ta n n (2 cntan 9 pr en
respective~~~~ 7~rt ta reuns-am n on -- s o 11a c 9 T
$280)0007a 9 n t al o a7 t ng
as74 in-- bee4ac a mo ni4v(9
~~~e cen r e l n ll e7am 4in 777444
t~~~~~~~~~~~~7 a dteIa heesusataloain
7IV TrgRANUat 37 million has bee 7724 andV co ii ony77mi-e t e e te to
~77727 27 e c e n t 7 ~ 7 7y 7~7 7~ 77 7 47 7 - 7 74 7 4 7 4 7
7~~7I 77 of be e i e trr 7ub i r of in 777n unde 7 the-7 Project77 have77~47~777
7e2as Of he San date nu be e fi t - i - (59 Of th -1 nb thiri4 to U I747477
34 h a7 e7 in ovsea nin t7ny fi 2tra and4 e lt~ ) n74n 7e
7747777 ~ ~ ~ ~ ~ ~ 74 ~ lt ~ 7 7 4 77 7 4 ~ ~ ~ ~ ~ ~4 ~ J ~ 7
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
- 14 -
Coincidentally thirty-four j34) have been in long-term (one-year or more)
pr rams and twenty-five (25) in shorter programs
Based on the foregoing the training component of the TDI Project has to
date been proceeding by and large on schedule This notwithstanding however
it needs to be asked whether the component (including the training element of
the Development issues Component) has been operating in a manner consistent
with the training objectives of the project
B Objectives of Training Activities
As designed the training component of the TDI project was not only to
build upon but to improve on the General Participant Training (GPT) Program of
the 1970s Specifically whiie the GPT Program was observed to have lacked
focus on particular development issues or on specific human resource and
institutional development objectives that thereby limited its overall impact
training activities under the TDI project would support the institutional
objectives of requesting organizations contribute to improving manpower
skills critical to national and regional development and enhance capacities
related to the issues selected under the Development issues Component
Towards this end a survey of training needs of socio-economic
development-related government institutions was undertaken in the early stages
of the project On the basis of criteria approved by the project Steering
Committee survey responses were analyzed to come up with a prioritization of
agencies and of fields of study for funding under the projectshy
6 Attached as Annex B
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
- - -
---------------------------------------------------------------------------------------------------------------------------------------
----------
f-~i 4j ~ j ~-
~ ~ 1lt shy
~kgt shy~ ~ C
~ A-
~-C Ove~iai~1fon~iencY~ith ~Pvid~Yt-1~6s ~ ~4A ~ A A
~- T~~- ~- ~ A- ~
Interms-~ of~~ag~ ies~th j~eampjjfted~trj~1n1ngC su1 p~J r A ~
r1npV~mei~~at1on n~s been la5ge$y co ~ ~ establi sned~ ~
--A-A-~
~( ~A--~ ~ IC-he P -gli t~e n~ 1C8gt ih~ ~ itift1o~i~ t$iaCth~VPCIece1 ye amp f~jidf -g - --A- ~1 A- ~C C~ C -~- -Th - -~~gtA~4A -~ - - shy
~--C--- ~ C- shy~-~si-sfipport ~o ~da1t~ ~n all U~id~Kthe ~~stitutThns -- ~ --- -~--~ - 14 -- ~ ~ate-gory or--f1~--~-~p) ~~or~i~Y lr ~AC C~ ~--(-A-A-Ci~C-
S - ~~A -A-----~C ~ ~C~ ~ C~- --7
~ -r 1~A-C-
-~ 4 ~ ~ -A--- - ---A- - - C -3 - -shy
~eiei~~iVai1~b1e Four (A) others were~ih the second p~ ion ~y14st--C~ A4~~- -~-shy
-~ -~
S-~-A-- ~ r - --Ashyccoun~jng-~oc-~seven 17) of the s1o~s -~
-~- -~ C C- ~ ~1CCC~w -~ -C -~-- A-A- --C
K- In teins of Fields of studf-p i~ ities ae~e i~ke i-se 2-~Cf~6~A-r~A-~
C 22W- C- C - C -A 4 ~
A-lt-C -~ -Cshy-A ~ -- ~ -~-~---r--~- VA- -C- ---A--shy
ob s~iv~d~Tab1 e 4) CCth Ec~hii~s Plaijning and Piib11ampPb1-~c~ Ana1ys~is ~ - - -f
-~ C 4hr1 ---shy
~ fTeVd 128 ro111owed~VA-~ ~-~P~bU-c~ - ~
----- C ~--~--~A~ CL~~ 4 A~ rC - -- ~C-~~A-A
~C4~A-CCCAC 2ihAdipini s ~ ~t1OflC and~S c~ti sti LS ~ 16)- Studf~gru6t~ n~i ~i~1yzed--~a~ltA-A- -- -
A-- C---C-----Q-~CfA~ ---C- -A-A-~~ ~- - -C- -- ~ ~ -C - -C~ -
S C -- of C--~ a6ii~id C-~~Cparticular1p~-nlt~he ated socialjJeveioyrnent~ fo the balance ~(f5-)~)~- -C-~C-~
SCC ~C- C~~~CA-CA- -~A-kCC 2CCA~A -shy- - ~ - - -lt-A- C- - C-A- A-CC-A-A-A--CC-C-A- -- gt i~4 A-~---~ A- --- -
C-A-A-C-ltC-C~y1 - - ~-- ~ A- -- ~ 4-A -gt ----shyltC - CC~Cjgt~C~CCC- C-C-~
A-Cl- C -- ~CCC~CC-CC-ACC-A-A~-~C-CC~4--1ltCAC-A-- - - C-C-u ~A-A-- C- - C CC-C-C- - C-CAshy- -- C CC CA-C-~ A--A-IA--A-A-i-CC--C-CA-C-S-~C-~4 C-A-C-A -C--CC l-C------A-C AC-C A-C~-lt-A- -l---A--A
1AltCA-lt4ltA-A-A-C-C-1 - C- --- A-C C-~A A -A--C-~C A-A-C C -C ICC-~~ A-1~A-A--ampC-C fC-C-C-A-ltAC-C-CC~~ C-~C-C-- -A-CC-CA-C-C-
C I- A-- C- CC ~ ~C CC-CC - A-CC-C S-------------
C-C-~CA-lfC-C~CC-~ CA--C C-C-~- A J--C-----A-v CC-C- A-rCCCCA-~CCs lt- C if-C-C-A-- C -~ A-C~ CClt CCC- A-
S------------CC-C-CCC ~ C C C-CC-C C-C- CC-C- ---- C-C-A- 4C-CA-C-A-A-C-A-C-CCC-- C-C- --A-C C-
CCA- A- CCA-C- C-- CCC-C-C-A-CC-A- C~CVCA-A-CC-Cfl~C-4IA-A-A-CC-~lt~CAC-C-AC~-~C-- A--A - --- A-C-C-C-C- CC~iA-C- C-C C-CC-ICC-C-C-AC-- 4 ~ ---A A-A- AC- -~- ~A-C-C-A-A-~-C-C-A-- ---- C-CC
CC-CC-- CA- - C--C-C--C-C C-CCC-C-A-~AA-C-A- ~ --C-C- C- - -~~-~4C~A C-A-AC-~-kC-C- -VA-C-CC- -A-C-~ C -A
C-C-C-C-C - lt-~CCCCC-C C~C-~CCCC-C C-A-C-C-A- C-C-A- ~ lt--A-Cshy- -- C-C A C-C-CC-CA-C CASC ~ A-C CA ~C-C-C- A- C-- -~-- CC- ~CCC- - -- C-C-A- - - CCgt C CC-C-A- C-CC-A-C-CC-CC- CC-CCCCC-CC-CC-CClt--A A-~jC--A-C-C -LA C--A C-CCC C~A-C~ C- ICC- CCC~~-C-C ~ C-- -A- lt-C-AC -- A- -ltCltA-C C-V ifCC~CCLCCC-C-C-C-A-C-CCAC-C-A-C-CC - C-A-CC-A-C--C- -- - C-C-A-CC-~- A-C-A-CA-A-C~ltC C-C-A- -~~--~ - CC-A-CC-C-CC-CCCC-CCC ~ C-CC-C- C-- C- - ICC- CC-C-C-C-C-CC- shy-ltC CC-~C~C~~ C-C CCC -- -4A- --~-CC--C~ - ltA CshyA-C-- -C-C-CC~C-C CC C-- A-C- C-C- A-CC- -- CCCC-C-C-C-C-CAC-A1CA-A-ACA-C-CCC-C-A-~C-XC-CCCCC-CA-A-C-C-A-CC-C-C-AC-CC-C- - -C C-A-A-C-CCCA-C-CC-C-CA C-CC-A CshyCC~7C-~~A-A-~ C---------------shy
CC-C- CC-CA- CCA-CC-C-C-CC -CA-C-- - - - -C--C- - - - - - -A-C-CA-A-i4~CC-A-A-~A-A-A-A- C C-CC Cshy- A- A-CC-A-CC -A C-A- A- C- CC-~C- ~- - - - - -C-C-C-CCC-C-C-A-CC -- - A-C-C- - - -~A-AA-CjC-A-A-A-C-CA-CC-AC-C-4CI~14-~~- - - - C- Ar- - - - - - -C-C- C- A-C-- 4C-4--C-C-- C-CA----C-- C-C-C------------CA- A-A-A- -C-A--CA--C- CA-~A-CC-C-~ A-C-C-X~C~4C-C CC---CC- C- -C-CCC-~CCC -A-----------CC-CC-C--CA-C-C-------------CC-CC-CA- C-CC-C-A-C C
4 ---------------------------------- CC------CC-C- --C-A-- CC-- ~C- ~ - -AC-C- C A-CCC-C-C-A-C-ltC- C-~ C-AC-C-A-C-C-A-A-~~A-CCC-C - C-A- ~C-C-- - - - -CA- - C-Cshy
CA-C--------------A--CC-C--~-~C- ~A---A-C-C- --C--C-------C-C---------A------------A-C-~C~C CC-CCC-C-CC-CA-ACC-C-C-A-CCA--C- CCCCltC-C-A-C-CC-CA-CA-CC-CC-C-CA-A-CC-A- C 7Clt- A AC-A-A-C-C-A-A- C-Ik4-KA- -~- - ---- - CC-C-C---gt- CC- 4j WA-CA-- - CC-C--C- - -- CC--C-C- -CC K ~C--~A-C-- -C-A-~- CC
-A- --- - AC-C-C- CAA-AA-C-C-C-~A-~CC-C ~A- C1~A-C-CA-CC-C-C-CC-CCC4CC-C--C- rshyfCyCC-A-C-C-A-C-CCC-C-C-C-C~C-CC- 44 A-C-A---
---- -C-
- - - - - - - - -~ CC- -A-CC A- C C--CC-----
CA- -~--C-C-C--- - - - - - -C-C-- A-C-gt 1- --- ~-- 4
C-C-C-C-~A-C- C- C-- --- ~-- A ~C -C-- A- -AC--C- 4CtC--~C-4A-C-C--C CC-C- C- C-- A-A-C-A-C~~ltC- 4~C-C- CC-C-C-C-C-A-C-C-A-C-C-AA-A- ~---------C-~ -C-C C-CA-CC A-A-C CC-CA-AC-C- C -- C-C-CC-C- - - ---- -CC -- C-C-CC-CCC
-- C-C- -C-- - C CC~A----AC- C--C C ~ C--~4 C-C-A C-C- C~C-~C-A-- - - - C- - C-CC-A-C A~A-~j~-~~
4 ~ -- C--A-j C~C C-C-C-CCC--~ lt--C-CC--C -A--CC-CC-A-----C-C ~C- -C-~~C- CA-CC-CC-C-C-C---- C- A-C-C------ C-Cshy1 - 1A-A-C-A-C-- C~C- C-- ~ C-C-C-C-A-1 C-C-C-C ~C-A-CC-ltC- C A- ~ - C-CC- - - - - - shy-- A-A-gt ~ - - shy - -C-C-A CC-~C-CC-C--CC C-C ltC-~-~C-gt----- CCC-CCCCA- A-A---C- C-A-C-C-CC-CC- CCCC- C- C --- C C-C
A-C-~C-A-CAC4~~C-C-AC-C-C~CCA-C-CC-I A--- CC-C C- CC-C-CC-CC-A-C-C-~C-C- -C-C-~A------------C CCAC VIC--ltA- -~A~ A-~--A------C-A--A- C-C-A- C- -yC -- C-C ~ C- C-A-CC-C-C4C- C- A-CA-A-C-CC- A -C---C--C-C--------------C-- A-C~A-C-C-A-CC-A-A-CCA-4CCCCA- A-C-C-C---~ A-C- - CCCCCCiA- - A- CC~A-C-A-CCA- C-C-A-A-SC-~--------CC--~ - C- A-CCshy- A -A-A-A-- CC~A-A--~ C-C--C-C-~A-C-C-~A-C-A-C-A-~C-A-CC-CC--A-A-CC-C-A-- ~C-lt-C-C--~-gt ~ ~ C-A-CA-C-C-------------------CCCC-VA-ACCC-C-C-CC-C-C- C-AC-CC---- - - -C-C-C- A-C-A-C-A-C-C--~lt4- C- C--CC-CA-C-CC--CC-CC-A-~ C-A-A-A-AC-CCC-CC-C-C- - - A-~CC-C C-
A- - -C- ~ - C~ CifCC - A- CA--------A
C-~~A-C-~ -- C C-CC-C--CC- C C-C-CC-CC-CC-A-A-C-C-C-CA--C-CC-- -C C- -C C-CC-C A- C-C-CC-CA-A-CA-C C-C- - shy- CA-SC-C-A-
CCC-CC-C-CC-C-CC-C-CCC- C A- C-A- - C-C A-C-
C-- - CI CCC- C- AC-C- C---- - C-~~~A-C-C--- - - - - - -shy~ - C-A-CC-C-C CC-C A-C-C-A- CCC-C-C C-CIshy
~~C--A--A-C--C--C-C-C -- I--C---~
C-C-n - C -- A- A-C-C-C--C-CC-A--A-A-C-AC-~lC-C-- - -- - - ~CC
C-jA-C- ~~CCC-C- C-C-A-CA-C-C-
-- - A-C-CA-CCCCA-CC-C-C-C-~C-~C-~ - C-A-~CAv~~A----------------------------~~~CA- C-C-AC C- -C-C-CC-C- C-C-A- C-Cshy
A-~A-A-A-~A-KC-4C-C-C-4) C~- C CA- ---~ C-A-A-A- - CC-A- -- - CC-C-C A- CC-C-C-C-CC- -- -C-A-~C A-A-A-LA-----------------C-A-C- C C-A-C C-A-~~A-C- C-~ A- ~C-A-A-~ ~4CC
A-C CA-A-~C-~C-AC
)~ C-C-A-C-C- ~C-A-~4 C-A- - A-
C-A-C-~ CC-C- CA-C
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
TABLE 3
TRAINING FUIDED UNDER TDI
Distribution by Agency
(Earmarked as of 31 March 1986)
Overseas
T 0 T A L 34
Fi st Priority 26
NEDA 01M MOF MTI EducationalResearch Institutions (6)
11 3 3 3 6
Second Pr oritv 3
MOLE MHS MECS MSSD
3 -
-
Third Priority 1
MLG Non-Pri ority
1 4
C1 DBP Regional Trial Courts
1 2
Local
25
17
11 2 -3
3 1
4
1 1 1 1
4
4 -
-
-
-
Total
59
43
22 5
6 7
7
4 1 1 1
5
5 4
1 1 2
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
lj~~
~ 4 -~ -~ shy4 i V
- - V -~ -- - - ~ -- V
-- 1~ A -~ -~Ta 4-bTh 4 ~
shy
~j~T~A1[ING FI4~ DED f1DE~~PI -~ ~gt j A
~2 ~ SJ3i8~2iTih3Y~IELD4~OF STUDY -~ gt - --gt ~
~ ~ -- -~a ~ cn i9~6~ gt~~
- -~
VV4-I~ V- gt2 gtgt~VVgt~~VV~V V 4gt - ~ gt~v~ VV - gt- shy
-~A- ~lt~~OF STUDY- ~-~-
~ 4~Vampk4- I-V~----~--4 ~gtgt~VVA~gt~ 4 lt~4~V gt4 ND gtjji gt~ I
4S~gt-gt-~ gt-k4V~-- 4 VV~VVgtV VVVltV Y~~-gtgtgtgtgt4 ~lt~ 1~ 4 V shy
~-- VV VV gt- - -V--p--V gtOlt eamp Total ~ gt7~__________ ~~~ V
-~- -~~- - 4 ~ VV~
4 shy
4 4-gt -~-V-V-- - 4-gt~4-gt-gtgt~4-gt-gtVV- 4 4VVV gtV gt
4 - Vlt ~ 4
-- ~v-V - VV- fl---VV~-V~V~ gt4V - ~ - -4-- 4~4-4J-V-VV--V-V~V4-- gt-- gt -- 4
~---gtA4-----------~
4 shy44gt V44 V4- -~
~~ -gt--V--gt Economcs ~ -~Th~---j-~-~ ~ Vgt-Vgt- V444-VVVVgt-gt~V 3 V~I~ ~-21plusmn4 - -~ 4 f - 4- V4V 4 4 V~
--~-- -Y VVVgt -shyV~2 VV~VV -3-3Igt -VVVVV~- - shy
-~~ 22y~-4~4~4 - V~~~4-V4 -- gt~ P J a~ning 3 4 ~ 4-
I - V-VTgt -shygt-~--- Pub Vi C VVPOl 1 Cy~ V V - ~~~-~-4----- ~V ~- ~plt- -V- - VV - - - ~~ jlt~~ 1 --shy~ shy
4 4 -
V 4
- V VV4 4-VTV4 - YVVVVV VV~4-LVV OgtA VVjfVV
SV
4- - V~V ~V gt~gt -V -V -~ - 4gt 4----~ Vgt4-VVgt~ gtVgtV 4V~V~- V-V V gtV gtgt V amp~y-v4V4gtp-~4J4~VVV- 4 ~ ~V~Vgt-V
4-gt 4gt3gt V gt3 -gtlt VV gt~VV~4 4 3- -shyiIan42eI~~n~gtruoI 4
V 4 4 V Vl 3V~~ 4-~ 4-V VVVltV-- ~ 4-44YVVV gt-----4-V
V 4 V V V VV 2 V ~vV ~4444~~V4-gtVVgtVVV44VVV4-1 4V4gt4V-~VV gt--8-~---~Vp V -- - - C 4V VV V Vgt V ~gt V V 4 VVAVVVVV~VVV44VVV-44IA4~gt4 gtV4-gtV4 4 VV ~VVVV4gt V----- V VVV
- I~V3~ VVVV V V- V
S a ~i s -i-c~ V 4- VV V Vgt4 ~V V 3 4 4 V VVVV3V-VV- gt~gt ~ -gtVVshy
4----- ~ 4-V Vgt V 4-V gtVV-4 ~ VVV~-4-~~ -V4I--V
4-V V V VV-~
4 VgtVVgt~VVV gt3 sgt24TV V gtVVgt ~gt~~44VV4-~V 4-4--~~jgt444VsectVTV3-4-2-V-A4~A43~
444~gt4V4J4444- - - gtVVVVYIgtV VVV gt4-VgtV~VgtV4-gt-V V gt~gt-~VgtVgtVV4V4V V - VV 4 i4- V gt V-V 4 S- - ~VV- -VV44~ V-V
V4VV 2 -- 1 V lt7 V VV~ Vgtgt-S -Science amp Tec ino1ogy~ ~
VgtV-VVVVVgt- 4---~-4
---4-~- -V 4-V-- 4 44- V V ~gt gt-VV shy-V----Vgt V -Vgt--- gt
4 A-VV- -4 4~ -4-V -VgtV V V 4
- V~--4 T3ltVgtVV4VltVV~44VgtV4V33Vltgt4~444V4V 4ltV gt 4 - -V-7gt )~V4V~4 -~ 4444VV~3 V 4gt34-I- VV Vgt -~ V - VgtVVVVlt 4144ltV4 V
-~ VV--V~V ncl - 4neeMng)-~-V-- -VgtgtVV4 V~ 3 V~VV4gtI 3VVV-VgtVV IgtV~3ifVY4-~
VVVV VVV~ ~~V~-V4-VV~4 VI--- 4~ V 4
VV~-- yVgt-V~gt~ V 3 34~~4V~~44-Vgt34 V -4-V - V--V
VV44- gtV VVVVgtVVIVV~VVV- -- V3gt4- ~4- V4shygtV~gtgtV-V-VVgt3V4 V S V~VVV~VV ~gtV~V
V 4 7gt 4 4 4 44 V - ~-4- gt -- 4--4V-~--- -- -VV
~iVVVV V ~- 4 - 4~ 4 4- gt4gt VV -~ -- gtVV4-4V---4-VVVVVVV V--V ThVVVVV- VVVVVVVVVVgt - -- 4-- gtA4 ---------- 4-VV V-V V~VV~-VVVgt~4-VVVVV -~V - -- 444-4--~gtV-V --gt44- Labor --- - V~ VV
VVV --4~-gt 4- I gt~ VVV-V 4- gt -4-A- -gt gt VVI shy
-gt~44444gtVV44[44-V -VVVV4 -4- V~ 4- -- V 4-- V 4gtgt-- 4 3 ~ shy4 4igt~ 4V-V44gt4-~lt- - V-44-4~gt~VVV --gt-gt4~---~---4-- I I- -gt~ - - 4-V
4V~j4-VVVV4V ~VdVgtVgtlt7
4 V27V7 - V- - -4i-3V I-~Q 4-34-VV 4-VV4~VV~
V V ---3- 4-1-VT-- ~V2VVV
4VV-VV4 gt4 gt44-44444 V~-VV~~ 44gt4-74-~ 4--V ce -- -- --gt44-ampgt4 V - -ISL alV V
~VJ--~I~ -gt4-VVVV-V gt-gt gt~V-VVVVV334-4 4
gt gt-VV 4 4
414Vgt4---4V - 4-V- V 4 gt44gt44-V-V --- - - - iV ~V~44jVi~2gt4-gth V- --V~ gtVV4--VV4 V-VV-----shy-gt4-V V74gt4- gtVVgtV ~
- - gt V V ~ VV3Vj gt4444k2-444gt-- -gt-~- V- 44- -4fgt4-- VV44~~- VV444VgtV4-V-t-VV VV~- VV~VgtV gt 4 gt
~Vgtgt V 4 Vgt4-V-~2 ~ ~ 44-V ~
gt44gt44VVj VVV~4 4-V V~ VV3VVltVgt4-VVgt pV4VVVV- V- gtVgtVI ~~~gt
gt~ 4- V VVVV2V Vgt4 44-gt ~4-4--Vi44VV-4gt444KV2 4
gt~V V -- - - 4gt44ViVV V VV-VgtV 474~gt 4-~4 4-~- ~VVV
gt -~VVV~VVVV-V -V-V V Vgt V ~ltgtgt---3gtgt- ~44 -4gt--~Vgt~gtltgt-Vgt--44gtV4-------V4V4-VV V-V--------4-V 4 V~VgtgtVi4 ----- VVV-VV-VV-4----V4-VVgt VVVVVVV~VVV4-gtV 4gt 4- VV V
4 V~VVVVVgt4--VgtV-V----- gt-gtVVVVV4-gt-4-Vgt 44 V VVVVgtV-~p-VgtV-VA - VVVVV-VgtV~gt~V-VV4V~Vgt4V--~V-444V44VV44gt4gt- V ---- ~- VV V-~
----------- ~-~V V -----------------shy ~ -V ~gt V -shy
4 4 gt 3 -4- - V - - - VVVV-- pV--~ 4 44gtVV4-44VVVVVgtV4gtVV ~ gt~shy- -- - gt44-V-VVV--VV-V- - 4gtgt -ltY-VVV4~V~42Vgt~4V V-- V1 shy
7 4 - ~ 4 4 gt 4-~ ~Vgt4-V 3-VV -~-VU -- 24 T Q T A~-4gtV - VAVVi 4 4 4 gt
9 ~V~4-~-- -V -- ~ gt4-4-~ V4VV4-4-V~V44-4--V4-4-4 -V -V- 4- ~ - V 4-- - - - - - VVgt --V VV gtVV gt-4~ -
Vgt- -V- -VPgt Vgtgt--- - VVV--gt4- lt 4-gt-gtgt~4---VV -VgtV 4--~4-Igt34VCVVVV4---4gt-----4444V~---4-gt4--- 4
V-VI4----~ -Vgt-V 44VV----~ -a---------4-4 gti 4 ~-V-4
V-gt4Vgt ~ gt 4
VgtVgt 4gt gtgt 4-shy4 4Vlt4444VV~Vgt---VPVVltgt~ -shy
4 4VgtV~V 44gt~gt--------------------------44V44444Y434
ltVgt4-VV VV- -3- gt~ 4
4gtVVTT-4444-gt4gtK~44- 444 gt - ~4- V4-gt- gt44ltgt 4gtgt- - - - -V - gt gtltI---- 4--V~VV -V-VPVIgtltgt4-gtV-gt~4-VV-VVgtVgt~-------- V~ gt -44- V
V 4--VVgt44 ----------------------------------VVgt-4V--V44V4---gt-i4 gt~ gt~
4 VV V-------VVV
gt4- 4gt-gtgtgt 44-gt4--V-rV4-I-~4~ V
gt4gt~-gtgt4gt4-- 4V4 3~V-V-gtV---I-gtV~-4--ltV~ - -- 4 4 gt ~ ~ -gt~-~44 4gt- 4- V gtgt4- gt~4-V4-gtV4- -V4444 2shy---- V gtVVVVgt-V-VgtgtVgt--------V
4 4 gtI4W4V~VV ~VVVVV gt~4-gtV- gt4gtVV- -V-~gt-V~-~VV~VVVV - V - -4-444gt3- gt - 33---4Vjv- 3 ------------ VVV44gt-gt~V 4W gt~4-~gt~)~4VgtVVVV gtVgt
4 3~-lt-44gtVVV-V4V4-V4444-~gt4-V4-4~ VV gt-4gt4 44V4V2V-V4-V ~gt- - - - V V ~- ~4-3V -~ 4V3VVI4VV-VVV 4-V4~4-VVP~4-VVV~V-lt7- gt
4gt~-3~ -gtV4-V~~PV- V V - V -gt - 4 4 -4- 4
4 -~ V 4344 44gt444V-gt4- V - gtV 4shy
- 4 VVV44VgtVVgtVltgt$ -~ V--- VgtVgt4-VVV~~Vgt4---~4- Vgt4-V-VV V--VV-V-V-44shy4
4 - 4 gt
-- 4 4V gtV j4-4 c-- -4- ---~---gt- ---- 4- --~ ~-- gt--4~ - gt--gt ~gt--Vgt~-~ 444 V-V4~V 3V gtgt4 4
4- ~----- 3 4 4 - 4 4
-------------V- gtV-V-V~V~V-Vgt------ gt~VV -V - - V 4 V V
4V gt444 4-gt--4 ~ ---------- 4gtVV~VV gt ~gt~~-4-44 V4-Vgt4~ 4-gt7I~4-Vgt4--Vgt 444~4-4gt4-gt4T 4gt gt4shy
~ - p VgtV44VVVVgt4-4-lt gt4-I-gt gt~------V 4 4
4gt~37WJ3-~- 4-gt--V-- V - -lt~ 4-4- VV44 - gt~ ~ 4- A-- gt-- V44 4 4
-gt4- - -gt 4444-4 4-gtP ~V34-VV44VA44-4-4-~-gtV-4--444- gtV 4[(3gt4gtV V ~ VP- 4gt gt 4 -34-i3
-4-~ gt~3 - 4~34-gtV4--~shy- -4gt shy
gt444--4 4 shy
kgtgtshy~ 4V4~V -~ 4-gt VVV 4gtVV V - ~ 1 3 4
------ 4-V~444V----gt~---44 V4VV t4~I4V4gtV 44V~ltgtV33gtgtWgt4~ lt734-4V 444gt4444fr4-4444444 -4 gt4- VVVYVV ~gt - 44-4 V~V
-------------------------------------- 4 4
~44iV VVlgt444-V4VV4VV -gt4-- -~VV~ 1-V ~gt~ ~ -i~V gt4 4-gt4JVV V 4gtVgt4
4gt 4-V~V~ 444-4-~-44gt _gtV4~ VVV44~- 4 4 ~ 4
- V Igt - gt~ 4- ~44gt gtP VVVgt4V 4gt V~gt4
3 VV~VVV4~ VVVV4gt~gt 4- gt4-4-- V44gt- - 4 VVgtVgt4 shyV--4VV-4V-VV4
4 -gt V gt4- -gt ~ ~ ltgt4V-VAVVV ~I -- -Vgt - gt ~ 4
V4~j ~ ---------- V ~Vgt ~4gt~ --4--V4--V
~4f - V V4
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
13 -
D Areas for gtnorovein
The foregoing general observations notwi thstanding however there are
definite areas for improvement in the operation and implementation of training
activities
o e-n viith the priorit zation scheme adopted while useful in guiding
the evaluation of specific requests fo training assistance leaves too much
room for flexibility in decision-making While the need for and the value of
flexibility in a program of this nature recognized too much it couldis of
easily lead to distortions in Program results That this has tended to be the
case is evident from the folloino
a) The predominance of gtEDA itself as recipient institution of the
training grants Of the fifty-nine (59) slots that had been made
available twen-y-two 2) or more thian a thi -d went to IEDA official s
and employees Relative to the slots that went to institutions in the
first priority list (43) the proportion is even higher at slightly
over half While a large proportion of project training funds going
to NEDA staff may be justifiable in terms of the institutions central
role in Philippine development plannin and policy-formulation such a
high proportion of resources going to a single agency is rather
excessive
b) Relatedly the predominance of fields of a general development nature
ie Economics Planning IMlanagement and Public Acimnistration and
Statistics in the fields of training supported under the project
These acounted for forty-four (44) of the fifty nne (59) slots
Again whlle the value of a broad perspective in policy-formulation is
recognized threo-fourtihs of the training allocation going into thi3
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
19shy
type of general zraining wou d seem to unduly undervalue tiie ieed for
more specza~ized types of poli cy anal vsis called for in many areas of
Phiippine development T is of course Dossble that these needs are
already being addressed tirou-gh projects other than the underone
consideration if so then - e present ellocation under the TDI
Project may well be jusified Unfortunately time constraints have
7 no- enabled -i-oser nvesiation of this mattershy
c) Funding of pr-grans in Law and Justice which though related to
socio economic development policy formulation is at best only
distantly so ParLicipation for instance in programs on American amp
internat-ional a as well as -n the US Legal System by members of
the Regional Trial Courts is to say the least difficult to justify
under tiis project However support towards laster s degrees in
Engineering of which rhere are two probably is justifiable as these
may be classified among the manpower skills critical to national and
regional development
d) Relative imbalance in the distribution of training slots between
participants from central offices and those from the regions Of the
fifty-nine (59) slots made available less than ten have gone to participants from the reg-onai offices Considering the thrust of the
present government towards genuine regionalzation including NEDAs
own interests improvements in this regard are especially called for
For instance the nei government is strengthening the role of the
Regional Development Council- and therefore these may be additional
training needs
_ According to the Hanager of the Participant Training Component this was in fact the case
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
The seconc road a-ea for improvemert is in monit-ori ng The establ i shment
of a sstem for monitoring of zrain n oarticioants both during and more
importantly after traind1n Was envsioned in thne project design The first
batch or tra nees iho went through one year programs in SY 1934 have been back
on the job for a ear and tiose wiho underwenr shorter programs have been back
for a longe period To cate hovever no back to office monitoring has been
undertken rendr in- di-ficut the assssent of traininc imDact relative to
obj ectives
E Usefulness of Training
Towards this end however limited interviews of immediate supervisors of
returned trai nees wiere carried out in this evaluation to obtain some feel for
the usefulness o1 training to the sponsoring institutions
in general the assessment of training impact has been very positive with
significant improvements observed in the overall depth and breadth of
analytical outputs of returned trainees in one instance however even
before the outset of tne training program the participant was transferred to
another unit to which immediate applicabilit of the training eventua1y
received was minimal thoh nonethelss potentially useful
On the transfer of knowledgeskills acquired to other personnel of the
sponsoring Insitutions the general approach has been through informal
discussions on the j o
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
- 21 -
V PRQ ECT SGJ I IT AND OUTLOOK
Implementation problems notwithstanding current evidence supports the
continued usefulness off the project towards the objective of building up
institutional capacities for policy analysis and decision-making in the
PhiliPPine bureaucracy The Tax Administration and Compliance Study for
instance thouqh still in the process of finalization has already contributed
siqnificant inputs to the recent formulation of a new Tax Reform Package
Outputs of the on-going research on Sectoral Classification of Trade and
Inve ment Data are already being programmed for use in the current drafting
of the Philippine Development Plan for 1987-1992 Limited interviews have
also established the positive contributions of training supported under the
project in terms of improved overall quality of analytical work of returned
trainees
The potential impact of the project is further considerably enhanced by
the fact of a new government which is seriously engaged in a broad-ranging
effort to review and as needed recast the whole gamut of policies
structures and procedures that intimately affect both the current and the
future life of the nation
In terms of project operations recent developments augur well for
improvements not only in the pace of project implementation but also in terms
of broadening the projects overall impact In the case of the Development
Issues Component mention has already been made of positive expectations
resultina from the workshop on the Research Agenda conducted in late 1935
Significantly because of the materially improved response that resulted from
thc workshop the TDI-PMO has decided to convene similar workshops on a
regular basis possibly twice a year
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
2) 2
ng wo-dO t h se inIud
z 4
agences ithapriua 5 vP eFv o broadeing insi njttioal acss~ bon th
Patal ohftin ofiote etrainn budge fro-rea 4olo
localh prjectng athe~~i prpsdmve i gandsg t nlreprjc
a trac ti-4es ovvf-lc lt ann te sie drts okalw ne
thi7111jre paatona prori wj taf l needpse to bfsleNcfuprddto1e s tna tj1
are g oe tffatlatcoprb en to en rduntser ther( donor proramsat~ ncsw wpartheu fregig brodein~a nvi
aIe Ii ew too ro dn to-e h
C fh tronn bdgt~rinin inselsctod fieldsin~~
3ns teContra Luzng Sthel-siniicanty cost Ndiffential Metwend no~y~e~n
Unvrit1lso -the -osb~ltiso agai prtnd n dtoeelopment of~c a Naster
iNI e r t3 c hN e pt 4 ~r i n appea
progeiss byrtclal intecs fntraining ativ it ede- hghl
N - ~ - - ~ N N Ni N4 N 4
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
23 shy
unlikely the full ip1ementation of The project within the current PACD
Furthermore the Pr o- ed mod ficiDns in the operating scheme of the
training component ioulc also take some time to work out Accordingly the
7oTDI-P1O is exoected put forard to USAID a request for a two-year extension
of the current PASD f the project is extended then there will be need for
another evaiua-ion in two years
VI RECOMME IDATI OS
in light of all of the foregoing the following recommendations are herein
made with respect to the TDI project
1 The project should continue and the PACD extended by two years to
December 1990
2 Should the Precedinig reccmmendation be approved another evaluation of
the project should be schedule- in thc first half of 1988
3 To contribute to the easing of the countrys debt servicing
difficulties and in consideration of the diffused social benefits of the
project the entire unearmarked loan allocation to the project should be
converted to outright grant
4 To enhance smooth and timely implementation of the project as a whole
and in particular of the non-training elements of the Development issues
Component a clear resolution of the issues that have herein been identified
as having largely held back proect progress should be made and agreements
reached should be clearly set out in project implementation letters
Critical items in this regard are the whole apProach to project
implementation and the related question of compensation for government
personnel and the issue of USAID membership in the Project Steering
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
2 AAA
ona I~AY ~n87 t
M71 I d di t i rel a i vel 1 a - i ge P L ho l bA
s su a ed s OU - 1D g uA~fVSAA~ is d tAc -- e in ia e A d e a r d
ieAtOn i1 tA A-IIFIU Ua1 Y e a9 r e dA~A co c r i g e m r 4n
dminstrt e asPctso Prje em e tI n s spr m I~ n 4d4A o4A~ u -Aacur
dib reen ec about ~ uc AAA a or im ig ~V stlany wAi r Aties ~ ite exist
FA- co ib t n oA t hgtek ftent t reslutiAAs teo lw n
nsue sJ suc dcoes not~uuwarnt egt-T
the Gvernent tseluthrughi agencies and- i nLru ngt e sore d ss~
fo the purose Wha tepo ctdes st make vilbefnsto nbe
pers one pi je ip astosss ittv owa s natiatr on ut~f eacivti
-t-Aisureet)oee nt~ reerh-ntttoswih huhgvrmn-wnd
noexlrzhiosiiht urrnctei tresarch aciiis nhci to
woldbeaitional t (utnof rpegu~lar gio ovrmet aencises the lthuo ~ wou aAAAAgtAAshy
jutf cmestin eerh nt bae ingvrmn ed aioa
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
institutions woul d clearly all under this categor Persons working for such
institutions either on full-time or part-time detail would hence be eligible
for sal ary compensation Drovl ded tNere was no doubl e payment
(ii) The enoagemen- of iovernment of fi cials and personnel for such
discrete activities that produce specific tangible outPuts such as the
preoaration of conceptissue -aDer which a-ivities thou h fall ing within
the particul ar areas of eoert i se of the officials and personnel concerned
clearly fall outside of their normal terms of reference and involve additional
workload outside of regular work hours
(iii) The participation of government officials and personnel in
conferences workshoos and uch other fora as be convened undermay the
project For this purpose epnses notrmal ly incurreo (ie transport and
room and board) in such Dari--icati on can be funded out of project re2sourcesiv)Re4 1b urS--I- -o0 lC 7
nto diem miscellaneous
costs even where he government oi-l is no eligible for pesonai
v u rav per and research
compensation under the project provided the costs were not otherwise
reimbursed and were directly related to a specific research task
b) On the issue of USAID membership in the Project Steering Committee it
is our view that the Project would stand to benefit from regular
particioai of JSAD person- in n2 se 7of topi cs and Suchici on prcposals
Partici o3-ion wouId i-roduce yet 3not7er poi n or vi ew on substan i ve
del iberations as ell as provide a conduit cear and early ofor r--Sorse
admini strati ve questions However alternazive r--are pssI - to
the inclusion of a USAID person in the del iLerationS - the Projec t Steering
Committee One possibility aould b the iormuaticn a joAn 1f- USALD coitte aov -he Steering Committee Yhere policycommittee above theSteeringaCommitte
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
mipiementation issues and prpoal could~ beformially disused Sti I
another ~ autl teai1PrCie _ens i S to incorporate nta tlraiwihtP
~the Solection pr ocess fo rproposaIscnu tatios wi th and Sol ic t bi of
oponsrro1SA 10--1eespo -~ssem~of-Ler ihe-TD I-P10 iaas---shy-a
~done- Drelininayi evalI ua on~oF propisa sbut be fore theampy are formjal ly
5 G e ED eta role in Philippine deeomn planin an
gtlt-policy~formul ation~2 NEDA shoul d reta inovea~l Imanagement of the jproject~~
Underith v al Idi rnction Of a project di rector- the two broad elenients of- -
the prjc training and non-training should cont~inue to be managed---shy
-sepa rately given -the di ffere ex4eri (P-ne requirmens an proces si ngWVo4shy
4
VV ~procedures involved in manaemn of the t-o- bra lseo ciiis
4j ltBecaus~e of thiese~di ferences h riigapc fteDvlpetIse houd b hadle nit
CornotSinenen a io ineone
Cop~nnt bythemangemn of the Participant Traininshyesniicat pooe training is~- oadrs
--- corenstin betuee thepnt management unt shouldKbe maintained-Kshy6Gieni o nito theon-yar xprin o ranstraton
shudcninueloberhneds (emngeetuito h PtticipantTrinn c oK~( m p Iiou1dn n lde tan n le et fte K Keeom n
--4gtV27 Com one t) Some-- ex a o te us f i
exetd significantxaso inpoga ariiato
Since ~onpnen aJ~uuILuIIKui~u~r1r~y~pK AK
t--
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
27 shy
7 For reasons that have already been indicated elsewhere in this
report at of part ofleast the management the procedures of the Development
Issues component (which now excludes training) should be transferred or
subcontracted to the Philippine Institute for Development Studies (PIDS) which
has consideraile experience with managing research and working with USAID
8 To improve the implementation of the development issues component
(a) The Steering Committee especially in light of the priorities of
the new GOP administration should focus and prioritize the Agenda of Areas of
Research This should be done with the intent of selecting only a limited
number of development issues in order to concentrate efforts involve more
institutions in the same topic and culminate through a series of activities
in concrete policy recommendations
(b) TDI-PI0 should implement present plans for more frequent workshops
and advertisements to solicit research proposals and to broaden participation
(c) In addition high level NEDA officials should continue to endeavor
to involve directly other ministers and deputy ministers in the selection of
development issue topics research assignments and discussions of results
NEDA should continue to make readily available TDI resources to other
ministries
(d) The regular selection process should be made simpler and quicker
through such steps as greater discretionary power to the NEDA-TDI Project
Manager to approve proposals on already cleared topics without further
approval of the Steering Committee or USAIO up to a limit of say $15000
per proposal
(e) An alternative formechanism selecting consultants should be
designed to meet immediate short-term needs The NEDA-TDI project manager
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
should have greater authority to initiate on his own within topic guidelines
approved by the Steering Committee and USAID consultancy contracts This
authority snould be limited both as to amount of any individual contract say
$15000 and to the total amount of all such contracts for the year say
$100000
9 The Evaluation Team endorses the TDI-PMO proposals for improving the
overall effectiveness and impact of training activities Specifically
(a)A more detailed training plan for the balance of the project
duration should be prepared based on an updated assessment of institutional
training needs The team feels that in this assessment special attention
should be given to the needs of regional offices Further while maximum
adherence to the formulated plan is desirable provision for some degree of
flexibility should also be allowed to enable the project to respond to
unforeseen but urgent training requirements that may arise in the course of
implemfentation For this purpose ten (10) per cent of the uncommitted
balance of the training allocation could remain unprogrammed and availed of
largely on a need basis
(b) Institutional participation in the training component should be
broadened not so much however by increasing the number of participating
institutions (although possibly that too) but more through the provision of
proportionately more slots to institutions that have been determined to rank
high in the institutional prioritization scheme
(c) Participation from the regional levels should be increased and
perhaps even given priority
(d) Extension of funding support to training in suitable fields in
selected regional training institutions in the country should be undertaken
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
n this reard full consi deration should be given toi nci uding training
ororms 7 rv ate -c--nal insi tutions The proposal to explore the
devloomnt of a aster s roram in DcveloDment Economics at the UP in
Diliman is siMilarlI endorsed
10 7n add-isn to the forejoing a reassessment of the distribution of
ii-s is-ai r 1 ly t iclh general and te more
setor-soecifiPopo1 cy analysi s stud prcgrams should be unde rtaken to ensure
th t the latter type of neecs is indeed being adequately addressed through
thi-s rojett in comb na tion i - othr d or-assi sted training programs If
not tIen soe shi ftng in proportions should be effected
11 Finally to enable continuini assessment of the extent to which project ojectives for the training component are being achieved the
otng system envisaged nder the project should immediately be
establisned and activated
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
ANNEX A
Financial Analysis Table as of 31 March 1986 (Cumulative $000)
EARMARKED I COMMI1TTEDofoI I I of lObligationsi Amount IOblig Amount 1Oblig1
TOTAL USAiD 4500 935 208 339 136
GRANT 1200 430 358 337 281
Training 230 261 932 261 932
Fora 200 2 210 10
Tech amp Mat Assistance 220 89 405 10 45
Research 330 73 22] 60 182
EquipmentCommodities 70 5 71 5 71
Evalualion 100 0 0 0 0
LOAN 3300 505 153 502 152
Training 2300 505 220 502 218
Tech amp Mgt Assistance 300 0 0 0 0
Research 500 0 0 0 0
EquipmentCommodities 200 0 0 0 0
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
ANN1EX B
TRAINING AND DEVELOPMENT ISSUES PROJw Participant Training Component
TRAINING HICH MAY POSSIBLY BE SUPPORTED
I FIRST PRIORITY
A NATIONAL SCIENCE AND TECHNOLOGY AUTHORITY
1 Science Policy Formulation and Administration 2 nformation Science 3 Technology AssessmentEv~iuation 4 industrial Project Feasibility Study5 Research Program Development Evaluation and Management
Economicsc 7 Public Administration 8 Development Planning and Administration
B MINISTRY OF FINANCE
1 Public Fi nan- 2 E c o n o mi c s3 Public Administration
4 TaxRevenue Admi ni stration 5 Development Planning and Administration
C OFFICE OF BUDGET AND MANIAGEMENT
1 Public Finance 2 Public Administration 3 Government 2udgeting 4 Government Accounting5 Project Planning Implementation Monitoring and Evaluation 6 Developmer- Planning and Administration
D MINISTRY OF TRADE AND INDUSTRY
D1 Bureau o in-ustri 3l Devel opment
I industrial Development and Management 2 7 c 9 n o I _pound5 3 S t a t i s t i s 4 Price Stabilization Policy Analysis and Formulation5 Tdentification and Promotion of Industrial Investment Projects6 Development Planning and Administration
1 Prioritized in accordance with the approved criteria for the evaluation of training needs v
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
D2 Bureau of Domestic Trade
1 Economics 2 Public Adminiszra-ion 3 S ta c i s z i c s 4 Development Planning and Administration5 Project Planning implementation Monitoring and Evaluation6 Price Stabilization Policy Analysis and Formulation
D3 Bureau of Forein Trade
1 Economics 2 Statistics 3 Public Administration 4 Development Planning and Administration 5 Trade Negotiation Techniques 6 Trade Facilitation Fundamentals
D4 Bureau of Small and Medium Industries
1 Industrial IManacement 2 Economics 3 Policy Analysis and Formulation 4 Project Planning ImplementationManagement Monitoring
and Evaluation 5 Market Research 6 Public Administration
E NATIONAL ECOO1IC AND DEVELOPMENT AUTHORITY
1 Development Planning and Administration 2 Public Administration 3 Economics 4 Statistics 5 Public Finance 6 Industrial Development and Management7 Public Policy Analysis and Formulation 8 Project Planning Implementation Monitoring
and Evaluation 9 Urban and Regional Planning
F jMINSTRY OF ENERGY
1 Project Planning and Management2 Development Planning and Administration 3 Public Administration
G RESEARCH 1ST TUO S
H TRAINING INSTiTUT1ONS 2 2 Specific institutions and priority training needs to be determined
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
-3-
II SECOND PRIORITY A MINISTRY OF TRANSPORTION AD COMMUNICATION
I Policy Analysis and Formulation 2 Urban Transportation Development 3 Transport Economios 4 Transport Ilanagemen5 Project Planning implemenzation Monitoring
and Evaluation 6 Communications Engineering 7 Public Acminis-ration
8 MIISTRY CF PU3LIC ORKS AND HIGHWAYS
1 Infrastructure Project Management2 Equipment IManagement3 Labor Intensive Highway Maintenance 4 Construction lanagement5 Materials Engineering and Quality Control 6 Financial Manaaement and Control 7 Civil Engine ring
C MINISTRY OF SOCIAL SERVICES AND DEVELOPMENT
1 S o c ial o g y2 D e m o g r a o h Y 3 Human Resources DeveloDment 4 Manpower PlanningiForecasting5 Development Planninr and Administration 6 Public Administration
D MINISTRY OF HUMAN SETTLEMENTS
1 Urban and Regioral Planning2 Strategic Planning3 ShelterHousing Project Development Management4 Project Planning Imolementation Monitoring and Evaluation5 Lnvironmental Science and Technology o Information Systems7 Agribusiness tManaement
E MINISTRY CF EDUCATiON4 CULTURE AND SPORTS
1 Education Planning2 S ta t is tic s 3 Development Planning and Administration 4 Management Information Systems5 Project Planning Implementation Monitoring and Evaluation6 Management information System
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
F MINISTRY OF LABOR AND EMPLOYMENT
1 Economics 2 S t a t i s t i c s 3 Public Adinistraion 4 Development Planning and Administration 5 Management Information System6 Project Planning implementation Monitoring and
Evaluation
G MINISTRY OF AGRARIAN REFORM
1 Agrarian Studiesanagement 2 Rural Sociology 3 Agricultural Project Planning Implementation
Monitoring and Evaluation 4 Rural Development and Settlement M11anagement5 Management Information SystemsLand Records
Management System6 Irrigation Project Development and Ianage-ent7 Agricultural Land and Water Resources Development
H OFFICE OF THE PrME-INISTER
1 Economics 2 Development Planning and Administration 3 Public Policy Analysis and Formulation 4 Foreign Policy Analysis and Formulation 5 Project Planning implementation Monitoring
and Evaluation 6 Management Information System
III THIRD PRIORITY
A MINISTRY OF LOCAL GOVERNMENT
1 Development Planning and Administration 2 Project Planning implementation Monitoring
and Evaluation 3 Management Information Systems 4 Financial Management5 Urban and Regional Planning 6 Rural and Community Development
B MINISTRY OF AGRICULTURE AND FOOD
1 Project Planning Analysis and Implementationfor Agricultural Development
2 Strategic Planning and Management3 Policy Formulation and Analysis for Agricultural Development
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
- 5-
CMINISTRY OF NATURAL RESOURCES
1 Forest Resource Management 2 Resource Development and Management3 Ecological Analysis for Natural Resource Management
D MINISTRY OF HEALTH
1 Health ProgramProject Development Implementation Monitoring and Evaluation
2 Stati stics 3 Management Information Systems
E OTHER AGENCIES
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
ANNEX C
TRAINING FUNDED UNDER TDI (earmarked as of 31 arch 1936)
Date of
Agency Field of Study Training
I COMPLETED
A Overseas Long-Term
1 Julio Ragragio DBP MS Public Policy and 62884-72885 Management
2 Adelfo Gaffud OBM MA Development Econ 6684-6685
3 Veronica Guzman NEDA MA Development Econ 6684-5685
4 Elisa Agomaa OBM MS Public Policy 62484-62385 amp Management
5 Ofelia Bulaong BOi MS Public Policy 62484-62385
amp Management
6 Gilda Reyes OBM MA Development Econ 53085-53086
7 Theresa Coronel NEDA MA Development Econ 53035-53086
8 Camilo Jose Lim NJEDA MA Development Econ 53085-53086
9 Edmundo Martinez Ateneo U MS Public Policy amp 7185-6286 Management
10 Antonio Basilio MTI MS Public Policy amp 7186-6286 Management
B Overseas Short-Term
1 Paz Suarez BIR Intl Tax Admin 101-11984
2 Regino Veridiano RTC Br Americin and Intl 63-61384 XXXI Law
3 Cita Angeles BOI Investment Negotiation 610-72484
4 Filemon Uriarte NIIST RampD institute gt 64-62984
5 Luz Mier NEDA Public Enterprise 71-81884 Pol icy As of end of SY 1985-86
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
-2 shy
6 Joseph AlabanZa IEDA Popularion and Dev 71-71484
7 Lydia de Villa 1iMC Executive Management 52-61585
8 Teresita Ianipon NEDA Statistical Packages 530-71585 for Microcomputers
9 Lermy Concepcion NEDA Price index Construct- 626-8285 ion and Analysis
10 Antonio Roman Jr MOF Intl Loan Negotiation lO -1185 and Renegotiation
11 Cecilia Tanchoco NEDA Economic Growth Income 513-62885 Distribution amp Poverty
12 Daniel Pabellon NEDA Advanced Management 728-92185
13 Gaudioso Sosmena Jr MLG Neighborhood Justice 98-10985
14 Jasmin Centina MOLE Development Project 916-92785 Evaluation
15 Rafdel Espiritu MOLE Development Project 916-92785 Evaluation
16 San-iaQo Ranada Jr TRC Br US Legal System 716-81085
17 Miguel Chavez Jr MOLE Labor Sta-istics 1015-12685 Analysis for Policy Formulation
18 Flordeliza Javier UPLB Plant Biotechnology 9285-22186
C Local Long-Term
1 Presentacion Gonzales Ph D Education SY 1985-86 (Dissertation only)
D Local Short-Term
1 Sismundo Cater MTI Development Economics 884-485
2 Elena Lardizabal MTI Development Economics 884-485
3 Tim Fernandez NEDA Development Economics 884-485
4 Rose Nepomuceno NEDA Development Economics 384-485
Ottomama Benito Prov Board Development Management 217-31486 Lanao Sur
6 Moises Dalisay Jr Prov Board Dev Management 217-31486 Lanao Norte
5
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
-3shy
-A Oversems Lo 0shy
o 13s1 Edd ]3 TA Ph D 2ubl ic Pol icy 712610 --720127
3 Li rio Abu1n0KWr1a an UA 0PhD JUrban-4 i A Sisana 1 35-1505811 ci1-1240
5 Celia Reyos NDS PhD Economics SY 1235 - 11
1 Gil 3e1 tran MOF Public Enterprisa 61 6-72586
C Local L-c 7-
1 aii NEWv1 D3 )3
2 Cecilia Celestino FNRI PhD Nutriticn 1935-83
3 Sixo Toiantino NEDA nTPhD Urban A 19353 Nannin g
4 Teresa Wiz NEDA PhD jbl f~ia 3815-23
5 Anecita Castillo 03NM M Public d 1935-87
6 Rosana NLG Public
Lucentales cu MA Social
rtista MA Adv 1935-31
7 Ruel MSSO ~ri 18 l Work 1935-37
3 Dante _A a 1c 193Qundo gt1 Pb Ani r 35--17
3 Agnes Car 3nto WYDA NA jr n a n1l 1335-37
15 Acaro Ai EDM A Public Aon 195-17
11 Yel ito Al imanw MOLE XA Lahor Hcorio-7cs 12 133 _3
12 Eul ito Wismark VH~S MS 3tatistics 1935-37
13 Jul ita de K Cruz I MA Pual i 1985-37
14 Oscar Xi 3 zDA MiA uan5 2Wii 1935-37
N1 anni nn 15 Ruth Paul-Cruz EA 11A Economics 1985-37
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
-4 shy
16 Honorina Tanhueco JEDA A Economics 1985-87
17 Winfred Vilamil IEDA MA Economics 1985-87
18 Corazon Sarcia MIEDA S Engineering 1986-87 (Completion only)
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
Appendix I
TRAINING AiND DEVELOPENT ISSUES PROJECT EVALUATION SCOPE OF CRK FOR EVAUTION
I THE PROJECT
Title Training and Development Issues Project (492-0340) Project Start July 29 1983 PACD December 31 1983 Funding $6000000 (TOTAL)
$4500000 (AID-funded) $1200000 (Grant) $3300000 (Loan) $1500000 (GOP)
Purpose The purpose of the project is to improve the capability of Philippine Government and other institutions to analyze development issues and to make sound and timely development-related decisions
Current Status The above-mentioned purpose is pursued through the implementation of two project components namely (1)Participant Training Component and (2) Development Issues Comoonent As of 31 December 1985 a total of 29 overseas and 15 local training participants nave been supported by the Participant Training Component Meanwhile the Development Issues Component has directed efforts toward the development of the technical base for effective policy analysis Through the conduct of three researches under the broad develoPment issues identified for project attention preparation of concept papers on development planningand policy issues and provision of support for 4 overseas the same
and 34 local training participants As of date the Participant Training Component has
obligated 609 p-r cent of the total loan appropriation it has received so far and 967 per cent of its total grant budget The Developmeit Issues Component on the other hand has obligated 437 per cent of the total loan appropriations and 164 per cent of its total grant budget
I PURPOSE AND TIING OF THE EVALUATION
This evaluation will assess the progress of the implementation of the TDI Project and make reccmmendations for maximizing the projects impact on the development efforts of the Aquino Government It will identify the successful project activities and attempt to explain the advantages these have over ess successful activities It plans to investigate the problems and issues which appear to have hampered or delayedimplementation of the less successful and to determine mechanisms to avoid or resolve them The evaluation also will identiFy and assess new approaches for using project resources to achieve project objectives
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
More soecifically it will focus on five general areas
a the current status of project implementationb exIec7ations and Perceptions of TDI project by NEDA and USAID and c factors affecting project implementation d selection of DI componenT issues and Training component participants
and e opportunities and mechanisms for improving the project
As scheduled in the project paper the first evaluation will be conducted in FY 86
Based on tne findings the evaluation should recommend whether basicchannes in theproject design and implementation Procedures are necessary The recommendatiors should indicate the advantages and disadvantages of the design and procedural changes advocated
III QUESTIONS FOR THE EVALUATION TEAM
A Current Status
7S imDlementation of the TDI Project proceeding as planned What are thevariances between projected and observed schedules for implementing the training and development issues components of the project If such variances exist what are their probable impact on the overall impIlmentation Plan Is it likely that the project purpose will be achieved by the PACD
B Expectations and Perceotions
What are NEDAs and AIDs expectations and perceptions regarding the project design implementation procedures factors hinderingimplementation beneficiary groups etc What are AIDs expectations of the NEDA TDI-Project Management Office (TDI-PMO) regarding the latters implementation procedures What are TDI-PMO expectations of USAID regarding project supportbackstopping How do NEDAs and AIDs percepticns compare with actual implementation procedures Are both sidessatisfied with the manner by which the implementation process is proceeding 1f not what are the areas and reasons for dissatisfaction
C Factors Affectino Project Imolementation
What factors explain the progress or lack of progress of both the trainingand development issues components What are the major factors contributing to delays in project implmentation Are the delays a function of project design How were the guidelines in the PP and other ooverning documents applied Are the assumptions underlying the projectdesign and iMPlementation plans valid How can the NEDA TDi-ProjectManagement Office (TDI-PMO) further raise its institutional capability eg staff availability and appropriate organizational structure to implement the plan as scheduled How can USAID further improve itsbackstopping for the project Are there external factors eg lack of interest in potential participant organizations affectingimplementation Are there budget-related problems such provision ofas
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
- 3 -
AAs and Ds hamering immlementation Are GOP or AID regulations oroperating procedures hampering implementation What have NEDA and AID done to resolve the known problems thus facilitating projectimplementaion successfuliw were the solutions
0 Selection Proesses
Do TDi-PMO and AID agree on the general issues selected for DI componentfocus and on the process used to select these issues Do TDI-PMO and AID agree on the more sDecific interpretation of these issues and the procedures for eiiciting research proposals and choosing projectprODonents _7fthere are contrasting interpreta ions do these dif f erenc-s a- iPlemen ation- of the D1 component Is access to theDI component widely known to potential individualinstitutional participant-s Do TDI-PMO and AID agree on the process used to select training particiDsants 11hatfactors are the most imoor-ant in theparticipant selection process Does TDI financed training focus on the development issues facing the country
E Mechanism for mrovina the Project
What basic chances in projet design or IEDA and AID procedures are required to achieve project objectives What changes are needed to improve implementaion Should the project improve the process of ientifvin- sub-issues for research identifying research institutionssoliciting proposais for ssues research and trainingi or selectingtraining activi ti Should project resources be shi fed between components Are additional grant or loan funds required Should theproject be coninued 11hat alternative project approaches could be used to better achieve project objectives
IV TEAM COMIPOSITION
The evaluation team must exhibit a thorough understanding of the following subject areas
1 Operations of the GOP specifically of NEDA and OEM2 Philippine develoDment issues and how these relate to policies3 IMechanics of Ai0 and USAIDPhilippines and4 The nature of the relationshio between USAID and N-DA5 The develooment priorities and opportunities of the Aquino government
The teams comPosition should represent expertise in the fields of organizational planning and management policy-making evaluation and management of research and training activities Given the sensitivities surrounding this project and the importance of this evaluation the teamshould not only be experts in the subject areas above they should also bewell known and respected by both INEDA and AID A team is expected to becomposed of a mix of Philippine and US consulrants or MissionAIDWashington personnel
The team will not have to collect and analyze a great deal of information because there have been very few implementation actions to date Thus asmall team of perhaps three or maybe four highly qualified persons should be sufficient
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
- 4-
METHCDOLCOOY A[D PROCEDURES
The team will complee all evaluation-related activities in four weeksThe following cihart includes a list of activities the timetable and teammembers expeCted participation in eacn of the activities Althouah the list is illustrative nonetheless the evaluation team is expected toadhere to the 4-week constraint the use of project documents andinterviews with GOP USATD and project recipients as primary sources of data and to the requirement to discuss preliminary findings with 4EDA-USAID Drior to finalizing the report
Activity Week 1 Week 2 Week 3 Week 4 Team Day No Day [o Day No Day No Members
123456 123456 123456 123456 Involved
A Preparatory Activities
1 Team Org XXX All 2 Redesign of
Eval scope XXXXX All3 Review of doc XXXXXXXXX All
B Data Collection
Interview USAID XXXXX All Project Staff Program Officer Directors Office
2 Interview GOP XXX XXXXXXXXAXX All NEDA Senior Managemeit NEDA-TDI-PMO EAS EPRS PDS OBt1
3 Interview Recipients XXX XXXXXXXXXXX All
C Cata Analysis and XXXXX XXXXXXXXXXX All Report Writing
D Submission of draft report and xx discussion of findings with All NEDA and USAID
E Draft Revision XXXXXXXXX All
F Submission of final report XX TL to NEDA and USAID
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
Vi FUI JDIG
An estimated $6100 in project funds will be used for the evaluation The estimated budget is presented in Annex B
VII REPORTING REQUIREMENTS
A The final report which is to be submitted at the end of the fourth week will use the regular format for AID evaluations It will contain the following sections
1 Executive Summary - a two-page single-spaced summary whichincludes tne projects statement of purpose and the objectives of the evaluation
2 Basic Project Identification Data Face Sheet - (the format will be provided juringtne evaluation)
3 Statement of Conclusions and Recommendations - the conclusions should be concise and topics identified by subhead while recommendations should correspond to the conclusions mentioningwhich agencyies have responsibility for recommended action
4 Body of Report - should include a description of the countrycontext in which the project was developed and provide theinformation on which conclusions and recommendations are based
5 Appendices as necessary (including the evaluations scope of workDrer description of methodology list of persons interviewed and key documents reviewed list of acronyms)
B The Preliminary Report which is to be presented to and discussed withNEDA and USAiD after the third week consists of a draft of the findings and recommendations
C The evaluation team leader is responsible for furnishing NEDA andUSAID with draft copies of the preliminary report prior to its presentation and discussion with the two agencies In like manner heis responsible for the submission to NEDA and USAID of the final report as scheduled and in a format acceptable to USAID
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
Appendix 2
LIST OF PERSONS INTERVIEWED
A PhilioDPine Government Officials
NE DA
1 Mr Florian Alburc Chairman Steerina Committee TDI
2 Mr Filologo Pante Jr roject Manager TDI
3 Mr Wil fredo Nuqui Manager Develooment issues Component 4 Mr Romeo Reyes Manager Participant Training Component
5 Ms Julieta Legaspi Assistant Manager Development
Issues Component
6 Mr Vicente Salazar Assistant Manager Participant
Training Component
7 Ms Remedios de Leon Director Industry and Utilities Staff
8 Ms Carol Guina Assistant Director Policy Coordination Staff
9 Ms Luz Bautista TDI Project Staff
10 Ms Flordeliza Dizon TDI Project Staff
11 Ms Ciosena Ungson TDI Project Staff
-12 Ms Carmen Viray TDI Project Staff
13 Ms Guida Capellan Officer-in-charge NEDA
MIS-Data Bank Unit
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
OBM
Mr Romeo de Vera Director Financial Planning Staff
PIDS
Mr Mario Feranil Director
USAID
1 Mr William T Oliver Chief Program Office
2 Mr Richard E Rhoda Dep Chief Program Office
3 Mr Sulpicio Roco Sr Program Specialist Program Office
4 Mr Sibley Kawi Trainirg Officer Informa-ion amp
Training Division
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II
Appendix 3
KEY DOCUMENTS REVIEWED
1 TDI Project Paper
2 Project Loan and Grant Agreement for the TDI Project
3 Detailed Implementation Plans for Development issues and for
Participant Training Components
4 Project Implementation Letters
5 USAID Quarterly Progress Reports on TDI Project
6 TDI-PIO Periodic Status ReDorts
7 MinutesAgenda Folders for Steering Committee Mleetings
8 TDI-Pgt 0 esearch A enda
9 Training and Financial Plans for Participant Training
10 Folder of Communications on TDi between USAID and TDI-PMO
11 Pertinent ESIA-WID Project Implementation Letters
12 Evaluation Report on General Participant Training II