Upload
khangminh22
View
0
Download
0
Embed Size (px)
Citation preview
© USM_REDAC_2009
CONTENTS
• Background • Sediment Transport Concept • Existing Sediment Transport Equations • Sediment Data Collection • Development of Sediment Rating Curve
Using Sediment Transport Equations • River Modelling
© USM_REDAC_2009
Figure 3.3 Typical Meandering RiverTypical Meandering River
Channel Pattern
Point Bar (Connected to banks)
© USM_REDAC_2009
This is the flow at which water begins to leave the channel and move onto the floodplain.
Bank full discharge
© USM_REDAC_2009
Natural River Characteristics
Sungai Sedim, Kulim
Sungai Ulu Paip, Kulim
Sungai Kampar @ Kg Jahang,
Gopeng
Sungai Kulim, Kedah
© USM_REDAC_2009
Nuki River (Kitakyushu City, Fukuoka Prefecture)
Before construction ( October 1991 )
23 months after construction (July 1995) Sediment was deposited on which vegetation grew,
Creating a natural water space.
River Rehabilitation Example: Japan
Immediately after construction (August 1993)
© USM_REDAC_2009
(a) Pembinaan Siap Pada 30 Januari 2003 (b) 4 Bulan Selepas Pembinaan
Aliran Rendah (22 Mei 2003)
Aliran Tinggi (19 Mei 2003)
Constructed River: Kampus Kejuruteraan USM
© USM_REDAC_2009
Dr. Hans Albert Einstein (1972)
If we change a river we usually do some good somewhere and “good” in quotation marks. That means we achieve some kind of a result that we are aiming at but sometimes forget that the same change which we are introducing may have widespread influences somewhere else. I think if, out of today's emphasis of the environment, anything results for us it is that it emphasizes the fact that we must look at a river or a drainage basin or whatever we are talking about as a big unit with many facets. We should not concentrate only on a little piece of that river unless we have some good reason to decide that we can do that.
© USM_REDAC_2009
River Equilibrium
4 Factors affecting river equilibrium
Flow discharge Sediment discharge
© USM_REDAC_2009
River straightening
Most popular option for a flood mitigation project
Banks unstable and collapse
© USM_REDAC_2009
Dam construction
Raising base level in main channel
Clear water release below a dam
© USM_REDAC_2009
Bed Material
Bed Load
Suspended Load
Wash Load
Total Bed Material Load
Total Load
Modes of Sediment Transport
© USM_REDAC_2009
Wash Load (silt/clay)
Bed-Material Load
(sand/gravel)
Suspended Bed-Material Load
(sand)
Bed-Material Load (sand and/or gravel)
Suspended Load as Normally Reported
Modes of Sediment Transport
Total Sediment
Load
© USM_REDAC_2009
Incipient Motion - Shields Diagram (Nalluri & Featherstone 2001)
τo = τc
τo = τc
τo = ρgRSo
© USM_REDAC_2009
Particle Size Distribution of River Bed Material
Stesen SP7 Sg. Pari
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
0.01 0.10 1.00 10.00 100.00
Sampel 1 Sampel 2 Sampel 3 PurataSaiz Partikel (mm)
Peratus Telus (%)
d90
d65
d10
d35
d50
d60
© USM_REDAC_2009
2/13/21 SRn
V =
Manning’s n for River Design
1.216/1
50dn=
266/1
90dn=
Uniform Sediment
(Cu = d60 / d10 ≤ 3)
Non -Uniform Sediment
(Cu = d60 / d10 > 3)
© USM_REDAC_2009
Transport Modes Equation Range of Data
Bed Load
Shields 1.56 < d50(mm) < 2.47 Meyer-Peter-Muller 3.17 < d50(mm) < 28.6 Einstein – Brown ψ < 10 Einstein 0.785 < d50(mm) < 28.6
Total Bed Material Load
Graf 0.09 < d50(mm) < 2.78 Engelund & Hansen 0.19 < d50(mm) < 0.93
Yang 0.137 < d50(mm) < 1.71 yo(m) < 1.0 m
Ackers & White 0.04 < d50(mm) < 4.94
Existing Sediment Transport Equations
© USM_REDAC_2009
Definition of Sediment Rating Curve
A relationship between flow discharge (Q) and the corresponding sediment transport rate (Tj)
© USM_REDAC_2009
River Equilibrium
4 Factors affecting river equilibrium
Flow discharge Sediment discharge
© USM_REDAC_2009
Flow Discharge
Model Neyrflux Type 80 Universal Current Meter
Electromagnetic Current Meter
© USM_REDAC_2009
Water Surface Slope, So
Distance = 100 – 250 m
Electronic Digital Measurement (EDM)
© USM_REDAC_2009
Bed Load Rate for a Cross Section, Tb
Tb = gb1 + gb2 + gb3 + gb4 + gb5 + gb6 + gb7+ gb8 = 0.0165 + 0.0388 + 0.0600 + 0.0641 + 0.0678 + 0.0469 + 0.0157 + 0.0102 = 0.3200 kg/s
Lokasi : Sungai Langat @ Jenderam Bridge, Hilir Sepang
Tarikh : 8/10/2008 T = 600 s B = 25.2 m W3 = 1093.65 g W4 = 762.5 g hs = 7.6 cm n = 8 gb1 = = 0.0641 kg/s
( )
×
×+
82.25
076.06002/50.76265.1093
© USM_REDAC_2009
Suspended Load
Low Flow High Flow
DH-59 Sampler DH-48 Sampler
“Depth Integrating Method”
© USM_REDAC_2009
Suspended Load, Tt
Cv =
= = 7.91x10-5
Calculation
65.210210 6−×
s
m
SC Qt = Cv x Q
= 7.91x10-5 x 14.394 = 1.14x10-3m3/s Tt = Qtx ρs = 1.14x10-3 x 2650 = 3.018 kg/s
Location : Sungai Langat @
Jenderam Bridge, Hilir Sepang
Date : 8/10/2008 (Q=14.394m3/s)
Date No. Weight of Weight of Weight of Weight of Weight of Weight ofSampel Filter Paper Filter Paper Filter Paper Filter Paper Filter Paper Filter Paper
LA1/S1 LA1/S2 LA1/S3 + + +Dry Suspended Dry Suspended Dry Suspended
Solid Solid SolidLA1/S1 LA1/S2 LA1/S3
(g) (g) (g) (g) (g) (g)10-Aug-08 LA2/03 0.3207 0.3192 0.3171 0.3424 0.3389 0.3386
Weight Weight Weight Weight Sample Suspended Cv Q Qt Tt
of Dry of Dry of Dry of Dry Volume Solid Suspended Suspended Suspended Suspended Concentration
Solids Solids Solid Solid Cm
LA1/S1 LA1/S2 LA1/S3 Average (g) (g) (g) (g) (ml) (x10-6) (m3/s) (kg/s)
0.0217 0.0197 0.0215 0.0210 100 210 7.91E-05 14.394 1.14E-03 3.0179
© USM_REDAC_2009 Jambatan Kg Dusun Nanding(28 August 2008)
d50=2.50 mm
0.0000.0100.0200.0300.0400.0500.0600.0700.0800.090
0 1 2 3 4 5 6 7 8 9
River Width (m)
Susp
ende
d Lo
ad R
ate
(kg/
s)
0.00
0.01
0.02
0.03
0.04
0.05
0.06
0 1 2 3 4 5 6 7 8 9River Width (m)
Sect
iona
l Bed
Loa
d Ra
te (k
g/s)
0.00
1.00
2.00
3.00
0 1 2 3 4 5 6 7 8 9River Width (m)
Elev
atio
n (m
)
Jambatan Nami (03 August 2008)
Q=3.47 m3/s
Lateral Distribution of Bed Load and Suspended Load
Bed Load
Suspended Load
Sungai Muda
d50=2.50 mm
0.00
5.00
10.00
15.00
20.00
25.00
0 2 4 6 8 10 12 14 16 18River Width (m)
Susp
ende
d Lo
ad R
ate
(kg/
s)
0.000
0.005
0.010
0.015
0.020
0.025
0.030
0.035
0.040
0 2 4 6 8 10 12 14 16 18River Width (m)
Sect
iona
l Bed
Loa
d R
ate
(kg/
s)
1.00
1.50
2.00
2.50
3.00
3.50
0 2 4 6 8 10 12 14 16 18River Width (m)
Elev
atio
n (m
)
Q=20.95 m3/s
Bed Load
Suspended Load
Sungai Langat
© USM_REDAC_2009
Nama Nombor Tarikh Masa Q V B Yo A P R S0 Tb Tt Tj d50
Sungai Sampel ( m3/s ) ( m/s ) ( m ) ( m ) ( m2 ) ( m ) ( m ) ( kg/s ) ( kg/s ) ( kg/s ) ( mm )
(LA1) LA1/01 23-Aug-08 9.00 am 17.564 0.225 35.00 3.34 78.045 36.500 2.14 0.000700 0.0275 4.0647 4.0921 1.10(Dengkil) LA1/02 23-Aug-08 12.00 pm 18.896 0.238 35.00 3.33 79.475 36.634 2.17 0.000700 0.0282 4.7188 4.7470 1.70
LA1/03 25-Aug-08 9.00 am 45.456 0.482 36.60 3.97 94.348 38.679 2.44 0.000750 0.0422 8.5146 8.5568 2.00LA1/04 25-Aug-08 11.00 am 44.294 0.462 36.40 3.78 95.964 38.227 2.51 0.000750 0.0406 12.0473 12.0879 1.40LA1/05 26-Aug-08 12.00 pm 91.769 0.757 37.40 4.85 121.290 40.424 3.00 0.000900 0.0469 99.3514 99.3983 3.00LA1/06 26-Aug-08 2.00 pm 96.104 0.794 37.27 4.80 121.098 40.354 3.00 0.000900 0.0468 82.4151 82.4619 2.00LA1/07 27-Aug-08 12.00 pm 34.647 0.387 36.10 3.89 89.620 37.732 2.38 0.000700 0.0384 21.9241 21.9624 1.00LA1/08 27-Aug-08 2.00 pm 35.866 0.399 35.79 3.80 89.961 37.419 2.40 0.001000 0.0420 22.9553 22.9973 1.30LA1/09 28-Aug-08 3.00 pm 120.763 0.786 37.60 5.70 153.569 42.228 3.64 0.000650 0.0571 67.2329 67.2900 0.31LA1/10 28-Aug-08 6.00 pm 118.261 0.774 37.15 5.77 152.849 42.250 3.62 0.000650 0.0571 62.6461 62.7031 0.65
LA2 LA2/01 5-Aug-08 2.30 pm 7.503 0.262 24.00 2.34 28.660 25.101 1.14 0.001250 0.2069 1.0825 1.2894 0.38(Jenderam) LA2/02 5-Aug-08 5.00 pm 6.856 0.254 23.74 2.15 26.976 24.799 1.09 0.001250 0.2060 0.7935 0.9994 0.40
LA2/03 10-Aug-08 9.00 am 14.270 0.366 25.20 2.74 38.986 26.546 1.47 0.001850 0.3200 3.0179 3.3379 0.40LA2/04 10-Aug-08 12.00 pm 16.128 0.416 24.96 2.71 38.798 26.412 1.47 0.001850 0.3008 3.0286 3.3294 0.40LA2/05 13-Aug-08 9.00 am 9.764 0.260 24.92 2.74 37.594 26.120 1.44 0.001000 0.2056 2.1018 2.3074 0.55LA2/06 13-Aug-08 12.00 pm 9.923 0.262 24.81 2.57 37.811 26.126 1.45 0.001000 0.2181 1.1658 1.3839 0.47LA2/07 23-Aug-08 2.00 pm 10.862 0.268 26.04 2.80 40.485 27.252 1.49 0.001150 0.2600 4.8538 5.1139 0.38LA2/08 23-Aug-08 5.00 pm 10.534 0.268 25.86 2.77 39.359 27.023 1.46 0.001150 0.2310 4.7036 4.9345 0.40LA2/09 26-Aug-08 4.00 pm 45.063 0.668 32.93 3.74 67.443 34.859 1.93 0.001250 0.2917 18.8618 19.1535 0.33LA2/10 26-Aug-08 6.00 pm 44.983 0.692 32.93 3.62 65.009 34.841 1.87 0.001250 0.2890 21.0956 21.3847 0.38
LA3 LA3/01 5-Aug-08 10.00 am 8.321 0.607 22.26 1.05 13.714 22.861 0.60 0.001150 0.3656 1.6716 2.0372 0.90(UKM) LA3/02 5-Aug-08 1.00 pm 7.899 0.571 22.09 1.20 13.825 22.961 0.60 0.001150 0.4595 1.4453 1.9048 0.80
LA3/03 11-Aug-08 9.00 am 11.378 0.443 21.80 1.89 25.675 23.123 1.11 0.001150 0.2765 2.7927 3.0692 0.70LA3/04 11-Aug-08 12.00 pm 11.034 0.427 21.62 1.88 25.867 22.943 1.13 0.001150 0.2986 2.3107 2.6093 0.73LA3/05 14-Aug-08 9.00 am 6.247 0.293 21.50 1.69 21.313 22.418 0.95 0.001150 0.2654 0.6704 0.9358 0.73LA3/06 14-Aug-08 12.00 pm 6.112 0.296 21.50 1.68 20.673 22.443 0.92 0.001150 0.2465 0.7695 1.0160 0.70LA3/07 25-Aug-08 5.00 pm 19.024 0.578 23.50 2.64 32.890 25.108 1.31 0.001150 0.3300 3.8780 4.2080 1.00LA3/08 25-Aug-08 7.00 am 18.749 0.568 23.26 2.69 33.002 24.900 1.33 0.001150 0.2982 4.8088 5.1070 1.10LA3/09 27-Aug-08 9.00 am 19.390 0.542 23.50 2.39 35.808 25.174 1.42 0.001150 0.3350 9.3189 9.6539 1.10LA3/10 27-Aug-08 11.00 am 19.070 0.542 23.30 2.31 35.203 24.912 1.41 0.001150 0.3197 8.4722 8.7919 1.00
Sungai Langat
Data summary
© USM_REDAC_2009
0.1
1
10
100
1000
1 10 100 1000
Tota
l Bed
Mat
eria
l Loa
d, T
j(K
g/s)
Discharge, Q (m3/s)
Dengkil
Jemderam
Jalan Tangkas
Kg Dusun Nanding
Jambatan Bt 14 Cheras
Jambatan Kg Rinching, Semenyih
Present Study
Sediment Rating Curve for Dengkil Reach
Sungai Langat
© USM_REDAC_2009
Yang Equation
Sediment Transport Equation Assessment
Location Total of Data Discrepancy Ratio between 0.5-2.0
No. of data %
LA1 (Dengkil) 10 1 20.00
LA2 (Jenderam) 10 6 60.00
LA3 (UKM) 10 6 60.00
LA4 (Kg Dusun Nanding) 10 3 30.00
LA5 (Cheras) 10 4 40.00
LA6 (Semenyih) 10 10 100.00
Overall 60 30 50.00
Location Total of Data Discrepancy Ratio between 0.5-2.0
No. of data %
LA1 (Dengkil) 10 3 30.00
LA2 (Jenderam) 10 3 30.00
LA3 (UKM) 10 10 100.00
LA4 (Kg Dusun Nanding) 10 4 40.00
LA5 (Cheras) 10 3 40.00
LA6 (Semenyih) 10 8 80.00
Overall 60 31 51.67
Engelund-Hansen Equation
© USM_REDAC_2009
0.1
1
10
100
1000
1 10 100 1000
Tota
l Bed
Mat
eria
l Loa
d, T
j(K
g/s)
Discharge, Q (m3/s)
Present Study Data
Engelund-Hansen
Yang
Sungai Langat
Assessment of Yang and Engelund-Hansen Equations
© USM_REDAC_2009
0.01
0.1
1
10
1 10 100 1000
Tota
l Bed
Mat
eria
l Loa
d, T
j(K
g/s)
Discharge, Q (m3/s)
Present Study Data
Engelund-Hansen
Yang
Sungai Muda
Assessment of Yang and Engelund-Hansen Equations
© USM_REDAC_2009
Computation Steps
• Obtain Cross Section Data • Compute flow discharge for each flow
depth using Manning’s equation • Compute sediment transport rate using
chosen sediment transport equation • Plot flow disharge vs. sediment transport
rate
© USM_REDAC_2009
Flow Discharge Computation yo B A P R So n V Q
(m) (m) (m2) (m) (m) (m/s) (m3/s)
0.50 6.82 1.6708 6.95 0.241 0.0012 0.051 0.26 0.44
1.00 18.49 7.9038 18.99 0.416 0.0012 0.051 0.38 2.99
1.50 19.41 17.3804 18.36 0.947 0.0012 0.051 0.65 11.38
2.00 20.33 27.3168 21.73 1.257 0.0012 0.051 0.79 21.61
2.50 21.35 37.6990 23.16 1.627 0.0012 0.051 0.94 35.43
3.00 22.62 48.6969 24.78 1.965 0.0012 0.051 1.07 51.89
3.50 24.22 60.4067 26.68 2.264 0.0012 0.051 1.17 70.75
4.19 27.64 78.0204 30.46 2.561 0.0012 0.051 1.27 99.21
5.00 39.28 107.8882 42.38 2.546 0.0012 0.051 1.27 136.64
5.50 47.45 126.0745 50.79 2.482 0.0012 0.051 1.25 157.00
6.00 50.64 155.4999 54.26 2.866 0.0012 0.051 1.37 213.11
6.50 52.97 181.3358 56.73 3.196 0.0012 0.051 1.47 267.27
7.00 55.56 208.4767 59.31 3.515 0.0012 0.051 1.57 327.37
7.39 57.47 230.4973 61.58 3.743 0.0012 0.051 1.64 377.43
© USM_REDAC_2009
Sediment Transport Rate Computation
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
0.01 0.1 1 10 100
Perc
enta
ge pa
ssin
g (%
)
Particle size (mm)
d50 = 1.20 mm
Sediment Distribution Curve on 26 August 2008
© USM_REDAC_2009
Computed Sediment Transport Rate yo d50 τ τ 3/2 V 2 Qs Qs Gw CT Cv Qj Tj
(m) (mm) ( N/s ) ( Kg/s ) ( Kg/s ) (= Qs / Gw) ( Ct / 2.65 ) (m3/s) (kg/s)
0.50 1.20 2.831 4.764 0.069 0.293 0.030 430.7 0.0001 2.6E-05 0.00001 0.03044
1.00 1.20 4.900 10.848 0.143 3.762 0.383 2915.3 0.0001 5E-05 0.00015 0.39367
1.50 1.20 11.145 37.207 0.429 40.506 4.129 12036.6 0.0003 0.00013 0.00147 3.9046
2.00 1.20 14.799 56.932 0.626 94.741 9.658 20223.2 0.0005 0.00018 0.00389 10.3211
2.50 1.20 19.158 83.855 0.883 206.771 21.078 32658.8 0.0006 0.00024 0.00863 22.8650
3.00 1.20 23.130 111.242 1.135 373.530 38.076 47355.7 0.0008 0.00030 0.0157 41.7214
3.50 1.20 26.656 137.623 1.372 597.872 60.945 64234.8 0.0009 0.00036 0.0253 67.1279
4.19 1.20 30.152 165.564 1.617 967.485 98.622 90026.5 0.0011 0.00041 0.0410 108.678
5.00 1.20 29.971 164.080 1.604 1351.68 137.785 1.3E+05 0.0011 0.00041 0.0561 148.638
5.50 1.20 29.222 157.968 1.551 1519.84 154.928 1.5E+05 0.0011 0.00040 0.0626 165.818
6.00 1.20 33.739 195.971 1.878 2437.12 248.432 2.0E+05 0.0012 0.00047 0.1004 266.171
6.50 1.20 37.628 230.817 2.172 3472.79 354.005 2.5E+05 0.0014 0.00054 0.1431 379.128
7.00 1.20 41.381 266.196 2.466 4768.16 486.051 3.1E+05 0.0016 0.00060 0.1958 518.867
7.39 1.20 44.062 292.483 2.681 5893.07 600.721 3.5E+05 0.0017 0.00064 0.2429 643.654
Total Bed Material Load Computation using Engelund-Hansen Equation
© USM_REDAC_2009
Computed Sediment Rating Curve
Jambatan Bt 14, Cheras (LA5), Sungai Langat
0.00
0.05
0.10
0.15
0.20
0.25
0.30
0 50 100 150 200 250 300 350 400
Qj (
m3 /s
)
Q (m3/s)
Engelund-Hansen Equation
Measured (August 2008)
© USM_REDAC_2009
Computed Sediment Transport Rate
Total Bed Material Load Computation using Yang Equation
yo d50 Ws Wsd50/ν U* = U*/Ws Re*= VS/Ws Vc/Ws VcS/Ws Log CT CT Cv Qj Tj
(m) (mm) ( m/s ) (gRSo)1/2 U*d50/ν (ppm) (ppm) (m3/s) (kg/s)
0.50 1.20 0.15 180 0.0532 0.3547 63.854 0.0021 1.4925 0.00179 1.4250 0.00003 0.00001 4.4E-06 0.0117
1.00 1.20 0.15 180 0.0700 0.4667 84.004 0.0030 2.05 0.00246 1.7599 0.00006 0.00002 0.0001 0.1722
1.50 1.20 0.15 180 0.1056 0.7038 126.685 0.0052 2.05 0.00246 2.4966 0.00031 0.00012 0.0013 3.5716
2.00 1.20 0.15 180 0.1217 0.8110 145.982 0.0063 2.05 0.00246 2.6480 0.00044 0.00017 0.0036 9.6098
2.50 1.20 0.15 180 0.1384 0.9228 166.095 0.0075 2.05 0.00246 2.7681 0.00059 0.00022 0.0078 20.7712
3.00 1.20 0.15 180 0.1521 1.0139 182.503 0.0085 2.05 0.00246 2.8478 0.00070 0.00027 0.0138 36.5515
3.50 1.20 0.15 180 0.1633 1.0884 195.920 0.0094 2.05 0.00246 2.9042 0.00080 0.00030 0.0214 56.7512
4.19 1.20 0.15 180 0.1736 1.1576 208.371 0.0102 2.05 0.00246 2.9510 0.00089 0.00034 0.0334 88.6267
5.00 1.20 0.15 180 0.1731 1.1541 207.746 0.0101 2.05 0.00246 2.9488 0.00089 0.00034 0.0458 121.439
5.50 1.20 0.15 180 0.1709 1.1396 205.134 0.0100 2.05 0.00246 2.9393 0.00087 0.00033 0.0515 136.525
6.00 1.20 0.15 180 0.1837 1.2245 220.417 0.0110 2.05 0.00246 2.9921 0.00098 0.00037 0.0790 209.264
6.50 1.20 0.15 180 0.1940 1.2932 232.775 0.0118 2.05 0.00246 3.0306 0.00107 0.00040 0.1082 286.774
7.00 1.20 0.15 180 0.2034 1.3562 244.108 0.0126 2.05 0.00246 3.0631 0.00116 0.00044 0.1429 378.595
7.39 1.20 0.15 180 0.2099 1.3994 251.892 0.0131 2.05 0.00246 3.0841 0.00121 0.00046 0.1729 458.097
© USM_REDAC_2009
Computed Sediment Rating Curve
Jambatan Bt 14, Cheras (LA5), Sungai Langat
0.00
0.02
0.04
0.06
0.08
0.10
0.12
0.14
0.16
0.18
0.20
0 50 100 150 200 250 300 350 400
Qj (
m3 /s
)
Q (m3/s)
Yang Equation Measured (August 2008)
© USM_REDAC_2009
Channel Cross Sections
Ch. 3020 ( 21 Oktober 2002) Jambatan Manjoi, Ch. 3380 ( 21 Oktober 2002)
Taman Merdeka, Ch. 2475 ( 21 Oktober 2002) Alor Limpah Batu, Ch. 1220 ( 25 Julai 2001)
© USM_REDAC_2009
Channel Cross Sections
Jambatan Silibin, Ch. 4540 ( 21 Oktober 2002)
Tokong Buddha, Ch. 4160 ( 21 Oktober 2002) Ch. 3600 ( 21 Oktober 2002)
Kuala Sungai Pari ( 22 Julai 2001 )
© USM_REDAC_2009
Observed Flow Profiles
Measured Data
Water Surface Profiles
Perbezaan Paras Air Sungai Pari
34.00
35.00
36.00
37.00
38.00
39.00
2000 2500 3000 3500 4000 4500 5000Keratan Rentas, m
Para
s, m
P. Air 7/10/2002 (35.00 Cumecs) P. Air 8/10/2002 (34.70 Cumecs)P. Air 9/10/2002 (47.80 Cumecs) P. Air 10/10/2002 (14.15 Cumecs)P. Air 21/10/2002 (7.05 Cumecs)
Paras Air Cerapan Sungai Pari Paras Air Cerapan
© USM_REDAC_2009
Hydrological Data
2000 Flood Hydrograph
Puncak Hidrograf Tahun 2000 Sungai Pari
0
20
40
60
80
100
120
2390 2400 2410 2420 2430 2440 2450Masa, jam
Kada
ralir
, m3 /s
© USM_REDAC_2009
River Data
Taburan Purata Saiz Endapan Bahan
Dasar Untuk Sungai Pari
0.00
10.00
20.00
30.0040.00
50.00
60.0070.00
80.00
90.00
100.00
0.01 0.10 1.00 10.00 100.00
Saiz Partikel, mm
Pera
tus
Telu
s, %
Cerapan Dasar Hil ir Cerapan Dasar Hulu
d50 = 2.50 mm
d50 = 1.80 mm
Bed material Bank material
Sediment rating curve
© USM_REDAC_2009
FLUVIAL-12 Model
Predicted Flow Profiles
Profil Paras Air Sungai Pari Bagi Kadaralir Q=48 m3/s
Profil Paras Air Sungai Pari Bagi Kadaralir Q=15 m3/s
2000 Flood
34.5035.0035.5036.0036.5037.0037.5038.00
2000 2500 3000 3500 4000 4500 5000Keratan Rentas, m
Par
as, m
Paras air simulasi (FL-12) Paras air cerapan
35.50
36.00
36.50
37.00
37.50
38.00
38.50
2000 2500 3000 3500 4000 4500 5000Keratan Rentas, m
Para
s, m
Paras air simulasi (FL-12) Paras air cerapan
© USM_REDAC_2009
Predicted Cross Section Changes
Ch. 2475 Taman Merdeka
Ch. 3020
36.00
37.00
38.00
39.00
40.00
41.00
0.00 10.00 20.00 30.00 40.00 50.00Jarak Dari Tebing Kiri, m
Par
as, m
P. Dasar Awal P. Air AwalP. Dasar Simulasi FL-12 P. Air Simulasi FL-12P. Dasar Simulasi FL-14 P. Air Simulasi FL-14
35.00
36.00
37.00
38.00
39.00
40.00
41.00
0.00 10.00 20.00 30.00 40.00 50.00Jarak Dari Tebing Kiri, m
Par
as, m
P. Dasar Awal P. Air AwalP. Dasar Simulasi FL-12 P. Air Simulasi FL-12P. Dasar Simulasi FL-14 P. Air Simulasi FL-14
© USM_REDAC_2009
Ch. 3380 Jambatan Manjoi
Ch. 3600
34.00
35.00
36.00
37.00
38.00
39.00
40.00
0.00 10.00 20.00 30.00 40.00 50.00Jarak Dari Tebing Kiri, m
Para
s, m
P. Dasar Awal P. Air AwalP. Dasar Simulasi FL-12 P. Air Simulasi FL-12P. Dasar Simulasi FL-14 P. Air Simulasi FL-14
34.00
35.00
36.00
37.00
38.00
39.00
40.00
0.00 10.00 20.00 30.00 40.00 50.00Jarak Dari Tebing Kiri, m
Par
as, m
P. Dasar Awal P. Air AwalP. Dasar Simulasi FL-12 P. Air Simulasi FL-12P. Dasar Simulasi FL-14 P. Air Simulasi FL-14
Predicted Cross Section Changes
© USM_REDAC_2009
What Is a Bund?
• The U.S. Federal Emergency Management Agency (FEMA) defines a bund or levee as a “man-made structure, usually an earthen embankment, designed and constructed in accordance with sound engineering practices to contain, control, or divert the flow of water so as to provide protection from temporary flooding.”
© USM_REDAC_2009
Sediment Deposition after Channel Widening
Sungai Muda 2003 Hydrograph (50-yr ARI)
Deposition
Original Bed Level
© USM_REDAC_2009
River Sand Mining Envelopes
• The suitable sand mining reaches can be determined by drawing the predetermined bed level based on HEC-RAS modelling.
• The minimum envelope level or “redline” adopted for the sand extraction is 1.0 m above the datum bed levels.
• The maximum envelope level is taken as 1.5 m from the top of deposition level as stated in the existing DID’s guideline.
© USM_REDAC_2009
Stock Pile
Stock Pile
Main Bank
30 m
Mining Setback (Minimum)
‘redline’
Deposition Thalweg
Maximum Allowable Mining Depth = 1.5 m ELEV. 98.5m
ELEV. 100m
1.0 m
10m
30 m
Mining Setback (Minimum)
10m
Allowable Section for Sand Mining
Setback, “redline” and Maximum Allowable Mining Depth for In-Stream Mining
Figure 1.2: River Sand Mining Management Guideline
© USM_REDAC_2009
-6.00
-4.00
-2.00
0.00
2.00
4.00
6.00
200 240 280 320 360 400 440 480
Initial Cross Section
Simulated Cross Section
Minimum Mining Level
Allowable mining depth = 1.5m"redline"
1m
CH 9700 (Deposition Level = 2.8m)
Minimum and Maximum Envelope Lines
Sungai Muda Extra Replenishment Level
© USM_REDAC_2009
Sustainable In stream Extraction
• Reduced number of extraction sites by increasing extracted volume for each site
• Allowing replenishment to occur along the river
• Extraction only from large rivers having the main channel width wider than 20 m
© USM_REDAC_2009
Appropriate Extraction Sites
An extraction site can be determined after setting the 1 m “redline”.
© USM_REDAC_2009
Minimum and Maximum Envelope Lines
1.5 m Extraction Level
1.0 m “Redline”
Sungai Muda
© USM_REDAC_2009
Appropriate Extraction Sites
Recommended areas for sand mining (based on 2003 flood hydrograph):
• CH 17254.06 to CH 19454.46 • CH 20056.20 to CH 20690.80 • CH 20970.17 to CH 21399.46 • CH 21865.41 to CH 23556.37 • CH 23960.61 • CH 24454.94 to CH 26133.94 • CH 26467.28 • CH 27042.74 to CH 28146.99
• CH 28907.23 • CH 30046.23 to CH 30484.41 • CH 30978.42 • CH 31426.28 • CH 32061.49 to CH 32360.40 • CH 33433.75 • CH 33650.64 • CH 33939.03
2003 Hydrograph (50-yr ARI flood)
© USM_REDAC_2009
Extraction Volume Determination
Setback = 50 m Setback = 20 m
toe
toe 1m “redline”
1.5m
© USM_REDAC_2009
Chainage Area (m2)
Average Area (m2)
Distance (m)
Mining Volume
(m3) 23556.37 275
253 1598 404,294 25454.42 231
Extraction Volume Determination
Chainage Area (m2)
Average Area (m2)
Distance (m)
Mining Volume
(m3) 23556.37 210
196.5 1598 314,007 25454.42 183
Total deposition volume
Total extraction volume
** 314,007 m3 / 12 months = 26,000 m3 /month
** middle-third mining volume = 404,294 m3 / 3 = 134,765m3
X 2.3
© USM_REDAC_2009