Upload
khangminh22
View
0
Download
0
Embed Size (px)
Citation preview
THE REPUBLIC OF UGANDA
OFFICE OF THE AUDITOR GENERAL
ANNUAL REPORT OF THE AUDITOR GENERAL FOR THE YEAR
ENDED 30TH JUNE 2014
VOLUME 2
CENTRAL GOVERNMENT
iii
Table Of Contents
List Of Acronyms And Abreviations ................................................................................................ viii
1.0 Introduction .......................................................................................................................... 1
2.0 Report And Opinion Of The Auditor General On The Government Of Uganda
Consolidated Financial Statements For The Year Ended 30th June, 2014 ....................... 38
Accountability Sector................................................................................................................... 55
3.0 Treasury Operations .......................................................................................................... 55
4.0 Ministry Of Finance, Planning And Economic Development ............................................. 62
5.0 Department Of Ethics And Integrity ................................................................................... 87
Works And Transport Sector ...................................................................................................... 90
6.0 Ministry Of Works And Transport ....................................................................................... 90
Justice Law And Order Sector .................................................................................................. 120
7.0 Ministry Of Justice And Constitutional Affairs .................................................................. 120
8.0 Jlos, Law And Order Sector Secretariat .......................................................................... 140
9.0 Ministry Of Internal Affairs ................................................................................................ 177
10.0 Uganda Police Force ....................................................................................................... 188
11.0 Uganda Prisons Services ................................................................................................. 214
12.0 Judiciary Department ....................................................................................................... 223
13.0 Department Of Public Prosecutions ................................................................................. 240
14.0 National Citizenship And Immigration Control ................................................................. 242
Public Sector Management ....................................................................................................... 268
15.0 Ministry Of Local Government ......................................................................................... 268
16.0 Office Of The Prime Minister............................................................................................ 332
17.0 Ministry Of Public Service ................................................................................................ 349
Security Sector ........................................................................................................................... 355
18.0 Ministry Of Defence.......................................................................................................... 355
19.0 Office Of The President ................................................................................................... 366
20.0 State House ..................................................................................................................... 369
iv
Agriculture Sector ...................................................................................................................... 371
21.0 Ministry Of Agriculture, Animal Industry And Fisheries ................................................... 371
22.0 Nationalagricultural Advisory Services (Naads) .............................................................. 406
23.0 National Agricultural Research Organisation (Naro) ....................................................... 422
Energy Sector ............................................................................................................................. 441
24.0 Ministry Of Energy And Mineral Development ................................................................. 441
Health Sector............................................................................................................................... 472
25.0 Ministry Of Health ............................................................................................................. 472
26.0 Uganda Blood Transfusion Services ............................................................................... 509
27.0 Butabika Mental Referral Hospital ................................................................................... 516
28.0 Uganda Cancer Institute .................................................................................................. 518
29.0 Uganda Heart Institute ..................................................................................................... 524
30.0 Mulago Referral Hospital Complex .................................................................................. 526
31.0 Arua Regional Referral Hospital ...................................................................................... 544
32.0 Mbale Regional Referral Hospital .................................................................................... 546
33.0 Kabale Regional Referral Hospital ................................................................................... 549
34.0 Lira Regional Referral Hospital ........................................................................................ 551
35.0 Gulu Regional Referral Hospital ...................................................................................... 552
36.0 Mbarara Regional Referral Hospital ................................................................................ 554
37.0 Fort Portal Regional Referral Hospital ............................................................................. 555
38.0 Jinja Regional Referral Hospital ...................................................................................... 557
39.0 Soroti Regional Referral Hospital .................................................................................... 560
40.0 Masaka Regional Referral Hospital ................................................................................. 561
41.0 Mubende Regional Referral Hospital ............................................................................... 563
42.0 Moroto Regional Referral Hospital ................................................................................... 564
43.0 Hoima Regional Referral Hospital ................................................................................... 566
44.0 China-Uganda Friendship Hospital Naguru ..................................................................... 568
v
Education Sector ........................................................................................................................ 573
45.0 Ministry Of Education And Sports .................................................................................... 573
46.0 Makerere University ......................................................................................................... 591
47.0 Makerere University Business School ............................................................................. 612
48.0 Uganda Management Institute ......................................................................................... 615
49.0 Mbarara University Of Science And Technology ............................................................. 618
50.0 Kyambogo University ....................................................................................................... 622
51.0 Busitema University ......................................................................................................... 650
52.0 Gulu University ................................................................................................................. 653
Gender And Labour Sector ....................................................................................................... 658
53.0 Ministry Of Gender, Labour And Social Development ..................................................... 658
Water And Environment Sector ................................................................................................ 672
54.0 Ministry Of Water And Enviroment .................................................................................. 672
55.0 Ministry Of Trade, Industry And Cooperatives ................................................................. 705
56.0 Ministry Of Tourism Wildlife And Antiquities .................................................................... 716
Land Sector ................................................................................................................................. 721
57.0 Ministry Of Lands, Housing And Urban Development ..................................................... 721
Information And Communication Sector ................................................................................. 745
58.0 Ministry Of Information And Communications Technology ............................................. 745
Public Administration Sector .................................................................................................... 749
59.0 Ministry Of Foreign Affairs ............................................................................................... 749
60.0 East African Community Affairs ....................................................................................... 752
Social Sector ............................................................................................................................... 753
61.0 Ministry Of Gender, Labour And Social Development ..................................................... 753
Missions ...................................................................................................................................... 762
62.0 Uganda Embassy, Abu Dhabi .......................................................................................... 762
63.0 Uganda High Commission, Abuja .................................................................................... 762
vi
64.0 Uganda, Embassy Addis Ababa ...................................................................................... 768
65.0 Ankara Embassy .............................................................................................................. 771
66.0 Uganda, Embassy Beijing ................................................................................................ 772
67.0 Uganda Embassy, Berlin ................................................................................................. 773
68.0 Uganda Embassy Brussels .............................................................................................. 776
69.0 Uganda High Commission, Bujumbura............................................................................ 782
70.0 Uganda Embassy, Cairo .................................................................................................. 784
71.0 Uganda High Commission, Canberra .............................................................................. 802
72.0 Uganda Embassy, Copenhagen ...................................................................................... 806
73.0 Uganda High Commission, Dar Es Salaam ..................................................................... 808
74.0 Uganda High Commission, Washington .......................................................................... 810
75.0 The Permanent Mission Of The Republic Of Uganda To The United Nations And Other
International Organizations In Geneva ............................................................................ 812
76.0 Uganda Permanent Mission To The United Nations, New York ..................................... 819
77.0 Uganda Consulate, Guangzhou, China ........................................................................... 820
78.0 Uganda Embassy Juba .................................................................................................... 821
79.0 Uganda Embassy, Khartoum ........................................................................................... 823
80.0 Uganda High Commission, Kigali .................................................................................... 824
81.0 Uganda Embassy, Kinshasa ............................................................................................ 828
82.0 Uganda High Commission, London ................................................................................. 836
83.0 Uganda Embassy, Moscow ............................................................................................. 838
84.0 Uganda High Commission, Nairobi .................................................................................. 840
85.0 Uganda High Commission, New Delhi ............................................................................. 842
86.0 Uganda High Commission, Ottawa .................................................................................. 843
87.0 Uganda Embassy, Paris .................................................................................................. 845
88.0 Uganda High Commission, Pretoria ................................................................................ 850
89.0 Uganda Embassy, Rome ................................................................................................. 853
vii
90.0 Uganda Embassy Tokyo .................................................................................................. 859
91.0 Uganda Embassy, Tripoli ................................................................................................. 861
92.0 Uganda High Commission, Tehran .................................................................................. 862
93.0 Uganda Embassy In Riyadh ............................................................................................ 864
94.0 Uganda Embassy In Mogadishu ...................................................................................... 865
viii
LIST OF ACRONYMS AND ABREVIATIONS
AIDS Acquired Immune Deficiency Syndrome
ART Anti-Retroviral Therapy
BFP Budget Framework Paper
BOU Bank of Uganda
BTC Belgium Technical Cooperation
CAES College of Agriculture and Environment Sciences
CAO Chief Administrative Officer
CDC Center for Disease Control
CEDAT College of Engineering Design Art and Technology
CEES College of Education and External Studies
CEMAS Computerized Education Management and Accounting System
CHOGM Commonwealth Heads of Governments Meeting
CHS College of Health Sciences
CHUSS College of Humanities and Social Sciences
CIID Criminal Intelligence and Investigations Department
COBAMS College of Business and Management Sciences
COCIS College of Computing and Information Sciences
COMESA Common Market for Eastern & Southern Africa
CONAS College of Natural Sciences
COVAB College of Veterinary Medicine and BioSecurity
CUFH China Uganda Friendship Hospital
DHO District Health Officer
DSCs District Service Commissions
EAC East African Community
ED Executive Director
ix
EFT Electronic Funds Transfer
ESAAG East and Southern African Association of Accountant Generals
ESC Education Service Commission
FAR Fixed Asset Register
FIEFOC Farm Income Enhancement and Forest Conservation
FOC Faculty of Commerce
FY Financial Year
GoU Government of Uganda
HC Health Centre
HIV Human Immunodeficiency Virus
HSC Health Service Commission
HSC Health Service Commission
IAS International Accounting Standards
IAS International Accounting Standards
ICGR International Conference for Great Lakes Region
ICT Information and Communications Technology
ICT Information Communication Technology
IFMS Integrated Financial Management System
ITFC Institute of Tropical Forest Conservation
JCRC Joint Clinical Research Center
JLOS Justice, Law and Order Sector
JMS Joint Medical stores
KCCA Kampala Capital City Authority
KYU Kyambogo University
L.T.C ward Lymphoma Treatment Centre
LANs Local Area Networks
LC Letter of Credit
LCs Letters Of Credit
M&E/MIS Monitoring & Evaluation/Management Information System
x
MDAs Ministries, Departments and Agencies
MEACA Ministry of East African Affairs
MFPED Ministry of Finance Planning And Economic Development
MICT Ministry of Information and Communications Technology
MKCCAP Mulago Kampala Capital City Authority Project
MNRH Mulago National Referral Hospital
MoES Ministry of Education and Sports
MoFA Ministry of Foreign Affairs
MoFPED Ministry of Finance, Planning and Economic Development
MoGLSD Ministry of Gender, Labour & Social Development
MoH Ministry of Health
MoLHUD Ministry of Lands, Housing and Urban Development
MoTWA Ministry of Tourism Wildlife and Antiquities
MOU Memorandum of Understanding
MTIC Ministry of Trade, Industry and Cooperatives
MUBS Makerere University Business School
MUECCA (A) Makerere University Establishment of Constituent College Order Amended
MUK Makerere University
MUST Mbarara University of Science and Technology
MWE Ministry of Water and Environment
NBI National Backbone Infrastructure
NCBS National College of Business Studies
NDA National Drug Authority
NHIS National Health Insurance Scheme
NMS National Medical Stores
NTC National Teachers College
NTR Non Tax Revenue
NWSC National Water and Sewerage Corporation
OAG Office of the Auditor General
xi
OPD Out Patients Departments
PAC Public Accounts Committee
PAYE Pay As You Earn
PFAA Public Finance and Accountability Act
PFAR Public Finance and Accountability Regulation
PIC Planning Investment Committee
PPDA Public Procurement & Disposal of Assets
PPS Private Patients Services
PS Permanent Secretary
PS/ST Permanent Secretary/Secretary to the treasury
PSC Public Service Commission
PSU Pharmaceutical Society of Uganda
PWD People With Disability
S.T.C ward Solid Tumor Centre ward
TAI Treasury Accounting Instruction
UAC Uganda AIDS Commission
UBTS Uganda Blood Transfusion Services
UCI Uganda Cancer Institute
UGX Uganda Shillings
UHI Uganda Heart Institute
ULC Uganda Land Commission
ULC Uganda Land Commission
UNHRO Uganda National Health Research Organisation
UNICEF United Nations International Children's Emergency Fund
URA Uganda Revenue Authority
USD United States Dollar
WAN Wide Area Network
WRS Warehouse Receipt System
1
1.0 INTRODUCTION
I am required by Article 163(3) of the Constitution of the Republic of Uganda and Section
13 and 19 of the National Audit Act 2008 to audit and report on the Public Accounts of
Uganda and of all public offices including the Courts, the Central and Local Government
Administrations, Universities and Public Institutions of like nature and any Public
Corporations or other bodies established by an Act of Parliament.
Under Article 163 (4) of the Constitution, I am also required to submit to Parliament by
31st March annually a Report of the Accounts audited by me for the year immediately
preceding. I am therefore, issuing this report in accordance with the above provisions.
This is Volume two of my Annual Report to Parliament and it covers financial audits
carried out on Central Government Ministries, Departments, Agencies, Universities and
Uganda Missions abroad.
In this introduction, I give an overview of the financial audit work carried out, status of
completion of the audits, summary of the audit opinions issued on the financial
statements of the entities audited and a summary of the key audit findings arising from
the audit.
Section 2 presents my findings and audit opinion on Government of Uganda Consolidated
Financial Statements including major observations.
Section 3 contains the detailed audit findings on each entity audited.
STATUS OF COMPLETION OF AUDITS
Financial Audits
A total of 107 entities comprising of Ministries, Agencies, Commissions, Departments,
Uganda Missions abroad, Public Universities, Referral Hospitals and the Consolidated
Government of Uganda Financial Statements, were audited during the year ended 30th
June 2014. Accordingly, separate audit reports were issued for each of them.
2
Out of the 107 entities audited, 75 entities had unqualified opinions, and 32 had qualified
opinions. Included in 107 are 17 entities that are contained in Volume 6. The basis used
to arrive at the audit opinion is described in the separate reports issued on individual
entities. The table below summarises the types of audit opinions issued on each of the
entities audited:-
No Entity Category Sector Opinion
1 Uganda Consolidated Fund MDA Accountability Qualified
2 Treasury Operations MDA Accountability Qualified
3 Directorate Of Ethics and
Integrity
MDA Accountability Qualified
4 Ministry of Education And
Sports
MDA Education Qualified
5 Makerere University MDA Education Qualified
6 Kyambogo University MDA Education Qualified
7 Gulu University MDA Education Qualified
8 Ministry Of Energy And
Mineral Development
MDA Energy Qualified
9 Ministry of Health MDA Health Qualified
10 Arua Regional Referral
Hospital
MDA Health Qualified
11 Lira Regional Referral
Hospital
MDA Health Qualified
12 Gulu Regional Referral
Hospital
MDA Health Qualified
13 China-Uganda Friendship
Hospital Naguru
MDA Health Qualified
14 Uganda Cancer Institute MDA Health Qualified
15 Ministry of Information And
Communications
Technology
MDA ICT Qualified
3
No Entity Category Sector Opinion
16 Ministry of Justice and
Constitutional Affairs
MDA JLOS Qualified
17 Ministry of Internal Affairs MDA JLOS Qualified
18 Uganda Prisons Services MDA JLOS Qualified
19 Directorate of Public
Prosecutions
MDA JLOS Qualified
20 National Citizenship and
Immigration Control
MDA JLOS Qualified
21 Office of the Prime Minister MDA PSM Qualified
22 Ministry of Public Service MDA PSM Qualified
23 Ministry of Lands, Housing
And Urban Development
MDA Lands & Housing Qualified
24 Ministry of Local
Government
MDA PSM Qualified
25 Ministry of Foreign Affairs MDA Public Sec Admin Qualified
26 Uganda Embassy,
Khartoum
MDA Public Sec Admin Qualified
27 Ministry of Trade, Industry
And Cooperatives
MDA Trade & Tourism Qualified
28 Ministry of Water And
Environment
MDA Water & Environment Qualified
29 Electoral Commission Commission Administration Qualified
30 Public Service Commission Commission PSM Qualified
31 Local Government Finance
Commission
Commission PSM Qualified
32 Uganda National Roads
Authority
SA / SE Works Qualified
33 Ministry Of Finance,
Planning and Economic
Development
MDA Accountability Unqualified
4
No Entity Category Sector Opinion
34 Ministry Of Agriculture,
Animal Industry And
Fisheries
MDA Agriculture Unqualified
35 National Agricultural
Research Organisation
(NARO)
MDA Agriculture Unqualified
36 Makerere University
Business School
MDA Education Unqualified
37 Uganda Management
Institute
MDA Education Unqualified
38 Mbarara University of
Science And Technology
MDA Education Unqualified
39 Busitema University MDA Education Unqualified
40 Ministry of Gender Labour
and Social Development
MDA Social Development Unqualified
41 Butabika Mental Referral
Hospital
MDA Health Unqualified
42 Mulago Referral Hospital
Complex
MDA Health Unqualified
43 Mbale Regional Referral
Hospital
MDA Health Unqualified
44 Kabale Regional Referral
Hospital
MDA Health Unqualified
45 Mbarara Regional Referral
Hospital
MDA Health Unqualified
46 Fort Portal Regional
Referral Hospital
MDA Health Unqualified
47 Jinja Regional Referral
Hospital
MDA Health Unqualified
5
No Entity Category Sector Opinion
48 Soroti Regional Referral
Hospital
MDA Health Unqualified
49 Masaka Regional Referral
Hospital
MDA Health Unqualified
50 Mubende Regional Referral
Hospital
MDA Health Unqualified
51 Moroto Regional Referral
Hospital
MDA Health Unqualified
52 Hoima Regional Referral
Hospital
MDA Health Unqualified
53 Uganda Blood Transfusion
Services
MDA Health Unqualified
54 Uganda Heart Institute MDA Health Unqualified
55 Uganda Police Force MDA JLOS Unqualified
56 Judiciary Department MDA JLOS Unqualified
57 East African Community
Affairs
MDA Public Sec Admin Unqualified
58 Uganda Embassy, ABU
DHABI
MDA Public Sec Admin Unqualified
59 Uganda High Commission,
Abuja
MDA Public Sec Admin Unqualified
60 Uganda, Embassy Addis
Ababa
MDA Public Sec Admin Unqualified
61 Ankara Embassy MDA Public Sec Admin Unqualified
62 Ganda, Embassy Beijing MDA Public Sec Admin Unqualified
63 Uganda Embassy, Berlin MDA Public Sec Admin Unqualified
64 Uganda Embassy Brussels MDA Public Sec Admin Unqualified
65 Uganda High Commission,
Bujumbura
MDA Public Sec Admin Unqualified
6
No Entity Category Sector Opinion
66 Uganda Embassy, Cairo MDA Public Sec Admin Unqualified
67 Uganda High Commission,
Canberra
MDA Public Sec Admin Unqualified
68 Uganda Embassy,
Copenhagen
MDA Public Sec Admin Unqualified
69 Uganda High Commission,
Washington
MDA Public Sec Admin Unqualified
70 Uganda Embassy Tehran MDA Public Sec Admin Unqualified
71 Uganda Embassy Dar-salam MDA Public Sec Admin Unqualified
72 The Permanent Mission Of
The Republic Of Uganda To
UN
MDA Public Sec Admin Unqualified
73 Nations and Other
International Organizations
In
MDA Public Sec Admin Unqualified
74 Uganda Consulate,
Guangzhou, China
MDA Public Sec Admin Unqualified
75 Uganda Embassy Juba MDA Public Sec Admin Unqualified
76 Uganda High Commission,
Kigali
MDA Public Sec Admin Unqualified
77 Uganda Embassy, Kinshasa MDA Public Sec Admin Unqualified
78 Uganda High Commission,
London
MDA Public Sec Admin Unqualified
79 Uganda Embassy, Moscow MDA Public Sec Admin Unqualified
80 Uganda High Commission,
Nairobi
MDA Public Sec Admin Unqualified
81 Uganda High Commission,
New Delhi
MDA Public Sec Admin Unqualified
82 Uganda High Commission,
Ottawa
MDA Public Sec Admin Unqualified
7
No Entity Category Sector Opinion
83 Uganda Embassy, Paris MDA Public Sec Admin Unqualified
84 Uganda High Commission,
Pretoria
MDA Public Sec Admin Unqualified
85 Uganda Embassy, Rome MDA Public Sec Admin Unqualified
86 Uganda Embassy Tokyo MDA Public Sec Admin Unqualified
87 Uganda Embassy, Tripoli MDA Public Sec Admin Unqualified
88 Ministry of Defence MDA Security Unqualified
89 Office of the President MDA Security Unqualified
90 State House MDA Security Unqualified
91 Ministry of Tourism Wildlife
And Antiquities
MDA Trade & Tourism Unqualified
92 Ministry of Works And
Transport
MDA Works & Transport Unqualified
93 Equal Opportunities
Commission
SA/SE Accountability Unqualified
94 Education Service
Commission
Commission Education Unqualified
95 Uganda Aids Commission Commission Health Unqualified
96 Health Service Commission Commission Health Unqualified
97 Uganda Human Rights
Commission
Commission JLOS Unqualified
98 Judicial Service Commission Commission JLOS Unqualified
99 Uganda Law Reform
Commission
Commission JLOS Unqualified
100 Uganda Registration
Services Bureau
SA /SE JLOS Unqualified
101 Uganda Land Commission Commission Lands & Housing Unqualified
102 Parliamentary Commission Commission Legislature Unqualified
8
No Entity Category Sector Opinion
103 Parliamentary Pension
Scheme
SA / SE Legislature Unqualified
104 Kampala Capital City
Authority
SA / SE PSM Unqualified
105 The Uganda Road Fund SA /SE Works Unqualified
106 Embassy of Uganda in
Mogadishu
MDA Public Sec Admin Unqualified
107 Uganda Embassy In Riyadh MDA Public Sec Admin Unqualified
The table and graphs below provide a breakdown of the types of opinions issued:-
Types of Opinions issued since 2010 by numbers and percentage:-
Types of
Opinions
Year ending 30th June
2010 % 2011 % 2012 % 2013 % 2014 %
Unqualified 40 40 61 59 47 45 60 58 75 70
Qualified 58 57 41 40 51 47 39 38 32 30
Disclaimer 3 3 1 1 7 7 4 4 0 0
Adverse 0 0 0 0 0 1 0 0 0 0
Figure showing the types of opinions issued for 2013/2014:-
9
Figure showing Trends of Types of Opinions Issued since 30th June 2010:-
Figure showing comparision of types of opinions issued since 30th June 2010:-
Special Audits
10
During the period under review, I undertook two special Audits of; Kyambogo University
and Uganda Government Payroll, which were completed and the highlights of these
reports have been included in this Volume.
1.2 KEY FINDINGS CENTRAL GOVERNMENT ONE
CENTRAL GOVERNMENT ISSUES
Government has undertaken various PFM reforms which have led to
improvements in public financial management notably the management
of the payroll and the Treasury Single Account among others. However,
Government continues to have challenges which require attention. The
key findings below indicate selected areas of concern which require
Government intervention.
1.2.1 Contingency Provisions for court awards
During the year, contingent liabilities in respect of cases before court
under the Ministry of Justice and Constitutional Affairs rose from
UGX.2.2 trillion in the previous year to UGX.4.3 trillion during the year
under review implying an increase of 95%. Besides, the Accounting
Officers explained that the provision excludes those that intend to sue
Government. This situation is untenable and likely to create an
additional burden on the public resources. There is need for Government
to examine the issue further with a view to establishing the likely causes
in order to facilitate Government to arrive at a sustainable solution.
1.2.2 Court Awards and Compensations
Unsettled Court awards and compensations have continued to
accumulate over the years rising from 54bn in 2012 to 164bn in July
2013 and 442Bn in 2014 and yet Government does not seem to have
adequate budget provision for these obligations. For the period 2012 to
2014 only UGX.13bn was budgeted for. The consequence of this state of
affairs has led to interest payments for non-settlement amounting to
11
UGX.60bn. The Accounting Officer attributes this to inadequate
provision of funds to clear the arrears. I advised management to
continue liaising with Parliament and Ministry of Finance, Planning and
Economic Development to ensure that these accumulated arrears of
compensation are cleared.
1.2.3. Irregular Payments – Loss, Likely loss and Nugatory Expenditure
A review of payment certificates revealed irregularities related to
payments for works not executed, payments for defective works and
payments that could have been avoided with better procurement
planning and contract management. The likely losses will crystallize into
losses unless management takes measures to have them recovered. The
irregular payments noted for the projects were likely losses
(UGX.45,315,967,993, USD.1,848,205 and Euro.68,558), losses (
UGX.300,279,163 and Euro.66,698) and nugatory expenditure
(UGX.2,464,934,174 and USD.3,663,761).
1.2.4. Under absorption of Government Funds
Projects failed to absorb funds totaling to UGX.217,393,823,773 and
Government entities returned unspent balances of UGX.9,412,704,745
to the Consolidated Fund indicating partial service delivery. Most
affected service delivery areas were road constructions, agro
processing, household income improvement, health and education
services. The low absorption capacity was attributed to inefficiencies in
the management of procurements, delayed accountability,
incompetence by contractors, inadequate planning among others. In the
circumstances, service delivery is undermined.
I advised management to review the causes and develop strategies to
ensure timely implementation of projects and programs.
1.2.5 Pension liabilities
12
Outstanding Pension liabilities under the Ministry of Public Service
increased by UGX.81,245,706,749 (326.2%) during the year under
review. This is an indication that the ministry‟s rate of accumulation of
pension arrears is significantly high, which might not be sustained by
Government.
Further, it was noted that a total of 19,135 pensioners who had attained
the maximum pensionable period of 15 years were still on the ministry‟s
payroll and earning monthly pension yet they had not furnished the
ministry with life certificates. As such, a total of UGX.12,727,686,849
paid in respect of their monthly pensions during the year under review
could not be supported in the absence of life certificates.
1.2.6 Comprehensive payroll verification
On the request of Accounting Officers, a total of 15,021 records were
deleted from the payroll for various reasons which included: death,
retirement and/or abscondment. Government incurred a total of
UGX.39,183,937,122 on these employees in respect of the wage bill
from July, 2013 up to the respective periods the individual employees
were deleted from the payroll in the FY 2013/14 alone.
It was also noted that, as a result of the mandatory validation and
biometric data capture exercise for government employees, a total of
8,589 employees have not been accounted for by 130 entities/votes,
although they remain on the government payroll. These employees are
being paid a monthly total of UGX.4,563,318,131 which translates into
UGX.54,759,817,572 per annum. There is need for Government to make
a follow up on the matter to ensure the affected employees are verified
or deleted.
1.2.7 Congested Prisons
Uganda Prisons Services has experienced an increase in the prisoners‟
population since the merger and takeover of 174 Local Administrations
13
Prisons in 2006, from a daily average of 19,179 prisoners in 2006 to
41,516 by June 2014. According to management, the available capacity
is only 16,040 prisoners. As a consequence, some of the prisons had
capacities of over 500%. With the current prisoner numbers, there has
been a strain on the facilities, staff and food. The Accounting Officer
attributes this to failure to match the growing prisoner population to the
facilities. These facilities have not been increased to match the
numbers. There is need for government to look into the matter with a
view to providing additional resources to support the Uganda Prisons.
1.2.8 Inadequate Facilitation of Government Analytical Labs
The Directorate of Government Analytical Laboratories is mandated to
provide scientific advisory and analytical services to government
departments responsible for administration of Justice and the general
public. However, the directorate is inadequately facilitated as evidenced
with inadequate infrastructure, limited funding and under staffing. As
such, the department was only able to respond to 52.5% of court
sermons and resolved 35% of the cases received. Not only does the
government stand to lose cases as a result but also the inadequacies
delay timely justice. There is need to facilitate the government facility
with adequate resources.
1.2.9 Settlement of Electricity Bills
Government entered into an agreement with UMEME in which the latter
was required to offset Government bills that remained outstanding for a
period of more than 60 days. Total Government debt as at 31st January
2013 amounts to UGX.62.7bn. I noted that there are no regular
reconciliations on the escrow account taking into account moneys that
MDAs have paid. The Accounting Officers attributed this to lack of
information regarding payments from the Escrow Account to enable
them undertake the reconciliations. There is need for Government to
undertake reconciliation to avoid any eventual over payments.
14
1.2.10 Land Matters
As reported in my previous year audit findings, land matters have again
remained an issue featuring in my current year audit report. A number
of instances have been noted where Government entities have
continued to lose out on land to encroachers.
This is notably seen with NARO, Ministry of Agriculture and Fisheries
Uganda Police and Universities. The challenge these entities are facing
result from inadequate resources to have their land surveyed, titled and
secured. Further, I noted that the Uganda Land Commission which is
mandated to hold Government Land in trust does not have an updated
register of all the land it holds in trust for Government. There is a need
to address land issues in Government Institutions.
1.2.11 Redundant Teachers SACCO Fund
During the year, the Government offered to contribute UGX.25bn to the
teachers‟ SACCO fund over a five year period with the objective of
enabling teachers access affordable credit financing. UGX.4,317,423,564
was released to Micro Finance Support Centre during the year under
review. The funds have not been accessed by the intended beneficiary
teachers because the fund management had become a source of conflict
between UNATU and the Ministry. Unless the disagreement surrounding
the fund management is resolved, the intended objective will not be
achieved.
1.2.12 Non-Retention of NTR by UCIC
According to section 3 of the Uganda Citizenship and Immigration
Control Act, NTR collected by the entity should be retained and treated
as appropriation in Aid. To the contrary, UGX.68,778,391,313 collected
in respect was automatically remitted to the Consolidated Fund contrary
to the UCIC Act. It is noted that due to inadequate funding the entity
has not been able to operate as envisaged. Due to these inadequacies,
the processing of passports takes on average 30 days as opposed to an
15
ideal time of 8 days. Further, it was observed that one officer handles
80 passport applications per day instead of 50 applications in an ideal
situation.
Management attributed this to inadequate staffing, lack of
interconnectivity passport issuing system and infrastructure. There is
need for Government to consider additional resources for the entity.
1.2.13 Delayed Contracts
It was observed that a number of Government contracts/projects for a
total of UGX.39,642,990,522, Us$.1,930,524 and Euros.512,288 that had
been ongoing or were started during the financial year lagged behind
schedule or demonstrated signs of failure. It was also noted that a
number of these contracts/projects had exceeded their completion
dates while others had been abandoned. These delays ranged between
three months and three years. The delays in contract execution were
attributed to insufficient funding and inadequate supervision of contract
implementation by the responsible entities. This may have resulted into
losses to Government and failure to achieve the intended objectives of
the procurements/contracts.
There is need for closer supervision of these projects to ensure timely
service delivery.
1.2.14 Payables/domestic arrears
The total value of payables/domestic arrears increased by UGX.138.166
billion (approximately 12%) from UGX.1.127 trillion in the financial year
2012/2013 to UGX.1.265 trillion in the year 2013/2014. The trend
shows a steady increase in the payables figures, which indicates that the
current approaches to address the problem are not effectively working.
The debt figure may become unmanageable as it appears to be spiralling
out of control.
16
There is need to revisit the current approaches of arrears management
with a view to reducing the growth in domestic arrears.
1.2.15 Mining/Exploration Licences
Section 105 of the Mining act 203 provides for payment of any royalty
assessed to be settled within 30 days. It was observed that 174
companies whose licences had expired defaulted on arrears of royalties
amounting to UGX.850,240,000. Further, 17 licence holders had not
provided the required records and audited financial statements to the
Ministry of Energy. There was no follow up by management on
defaulters for purposes of compliance. There is need for the Ministry to
closely follow up licence holders to avoid losses to government.
1.2.16 Audit of Kyambogo University
A special audit was undertaken for the University and it was noted
among other findings that a total of 10,486 students were admitted by
Kyambogo University without making applications. This was found to be
irregular. The University needs to strengthen controls relating to
administration of students to the University.
1.3.0 GENERAL FINDINGS
1.3.1 DELAYED CONTRACTS
It was observed that a number of Government contracts/projects for a total of
UGX. 39,642,990,522, Us$.1,930,524 and Euros 512,288 that had been ongoing or
were started during the financial year lagged behind schedule or demonstrated
signs of failure. It was noted that a number of these contracts/projects had
exceeded their completion dates while others had been abandoned. The delays
were between 3 months and 3 years. The delays in contract execution were
attributed to insufficient funding and inadequate supervision of contract
17
implementation by the responsible entities. This may have resulted into losses to
Government and failure to achieve the intended objectives of the
procurements/contracts. Table 1 below refers.
Table 1 Delayed contracts
Entity Contract (UGX) USD $s Euros Time
delayed
Justice Law
and Order Sector
projects
Construction of the Law
Development Centre Auditorium
3,977,880,902 0 0 over 15
months
Construction works of regional laboratory in
Gulu
436,445,468 0 0 Over 6years
Construction Regional Laboratory in Mbarara
535,191,985 0 0 Over 3 years
Procurement of Liquid
Chromatography Tandem Mass Spectrometer
(LCTMS)
0 786,595 0 Over
9months
Construction of Makindye Family Court
910,209,442 0 0 Over 2 and ½
years
Uganda Police
Force
Construction of Nateete divisional headquarters
2,358,000,000 0 0 Over 3years
Construction of Buliisa Police station
450,000,000 0 0 Over 1 year
Construction of 4 storeyed classroom block
,Kabalye Police Training
School
4,324,964,501 0 0 Over 3years
Uganda
Prisons Services
Construction of a twin
ward at Ruimi Prisons Farm
618,909,737 0 0 6months
construction of a cotton
store at Mubuku prison
farm
149,982,339 0 0 Delayed
2months
even after the
extension date of
January
2015
18
Entity Contract (UGX) USD $s Euros Time delayed
Community
Agriculture Infrastruct
ure Improveme
nt Prog.I
construct Agro Processing
facilities in the three sub-counties of; Nagongera (2
rice hullers), Merikit (2 rice hullers) and
Nabuyoga (1 maize mill
and 2 rice hullers) all in Tororo District
227,594,063 0 0 Delayed
by over 3years
and the project
closed in
December 2014.
CAIIP Prog.II
Community access road under Batch B Agwata
Atidi-Kachung road in Agwata Sub County in
Dokolo District
428,915,399 0 0 The works were
abandoned after
12months delay
Ministry Of
Agriculture, Animal
Industry
And Fisheries
Renovation of Ministry's
premises in Entebbe
144,214,834 0 0 Over
1year
supply of tractors 0 34,336
0
ATAAS
(Grant) EU, WB and
Danida
delivery of project
vehicles
0
1,109,593
0 Over 1
and ½ years
Uganda Manageme
nt Institute
Construction of new classroom block and
office block.
21,324,058,054 0
0 Over 1 and ½
years
Rehabilitation of hostel 2,543,323,798 0 0 Over 1 and ½
years
Ministry of Water And
Environme
nt
Consultancy Services for Feasibility Studies,
Detailed Designs and
Construction Supervision of Water Supply Systems
Under Lot3: for Namulonge-Kiwenda-
Busiika and Kiwoko, Butalanga and
Rehabilitation of Katuugo
and Improvement of Kakooge and Migeera
Water Supply Systems
1,213,300,000 0 0 Over 3months
19
Entity Contract (UGX) USD $s Euros Time delayed
Consultancy Services for
Feasibility Studies and Detailed Designs Under
Lot2: for Busaana Kayunga,Kabembe-Kalagi-
Naggalama and Kakunyu-
Kiyindi and Construction Supervision for
Rehabilitation of Buvuma
0 0 512,288 Over
3months
TOTAL 39,642,990,522 1,930,524 512,288
1.3.2 Mischarged Expenditure
Expenditures from various entities totalling to UGX. 51,728,901,102 were charged
on items which do not reflect the nature of the expenditure. Such a practice
impacts on the credibility of the financial statements, since the figures reported
therein do not reflect true amounts expended on the affected expenditure items. I
however noted an improvement over the last three years where mischarged
expenditures have been reducing from UGX.256,976,089,113 in the FY 2011/2012
to UGX.97,896,448,777 in 2012/2013 and UGX. 51,728,901,102 in 2013/2014.
Over the three years, the mischarges have reduced by 86%. There is still need for
accounting officers to enforce strict adherence to the provisions regarding
reallocation of funds. Table 2 and 3 below refers.
Table 2 Mischarged Expenditure
2011/2012 2012/2013 2013/2014
Mischarged Expenditures 256,976,089,113 97,896,448,777 51,728,901,102
Percentages Reduction
From 2011/12
0 % 62 % 86 %
20
-
50,000,000,000
100,000,000,000
150,000,000,000
200,000,000,000
250,000,000,000
300,000,000,000
2011/2012 2012/2013 2013/2014
Mischarged Expenditure for the last three Financial years
Amount (shs)
Table 3 Mischarged Expenditures
Entity Amount Mischarged –
UGX
Accountability Sector
Ministry Of Finance, Planning and Economic Development 2,208,201,055
Department Of Ethics and Integrity 275,372,736
Works and Transport Sector
Ministry of Works And Transport 48,153,093
Uganda National Roads Authority 3,501,412,812
Ministry of Justice and Constitutional Affairs 615,047,805
Ministry of Internal Affairs 421,104,192
Uganda Police Force 132,090,477
Uganda Prisons Services 637,537,384
JLOS SECTOR
Judiciary Department 423,909,500
Judicial Service Commission 86,527,567
Uganda Law Reform Commission 77,415,412
DPP 454,431,122
Uganda Registration Services Bureau - Operations 239,197,478
National Citizenship And Immigration Control 5,906,786,217
Public Sector Management
Ministry of Local Government 2,497,433,465
Office of the Prime Minister 5,564,282,629
21
Entity Amount Mischarged –
UGX
Ministry of Public Service 1,721,329,414
Public Service Commission 512,592,443
Local Government Finance Commission 241,919,355
Ministry of Gender, Labour and Social Development 66,982,475
Expanding Social Protection (2013) 11,976,000
Agriculture Sector
National Agricultural Research Organisation (NARO) 206,704,980
Energy Sector
Ministry of Energy And Mineral Development 3,038,506,327
Land Sector
Ministry of Lands, Housing And Urban Development 543,519,621
Ministry of Trade, Industry And Cooperatives 592,962,823
Ministry of Tourism Wildlife And Antiquities 115,112,418
WATER SECTOR
Ministry of Water and Environment 1,545,058,115
NEMA 942,053,402
MISSIONS
Uganda Embassy Brussels 150,514,718
HEALTH SECTOR
Ministry of Health 2,644,401,389
Uganda Blood Transfusion Services 27,880,704
Uganda Cancer Institute 656,275,672
Butabika Hospital 74,863,427
Mulago Hospital Complex 1,756,710,500
Education Sector
Ministry of Education and Sports 11,841,989,175
Makerere University 969,917,237
Kyambogo University 978,727,963
Total 51,728,901,102
1.3.3 UNACCOUNTED FOR FUNDS
A total of UGX.85,785,457,670, US$.530,861, EURO137,327 inform of advances to
staff, payments to service providers, cash withdrawals, imprest, remittances to
Districts, borrowings for carrying out activities in various entities remained un-
accounted for by the time of audit contrary to the Public Finance and Accounting
Regulations. Table 4 below refers.Delays in accounting for funds may encourage
22
falsification of documents. I advised management to adhere to the provisions in
the Public Finance and Accountability Regulations.
Table 4 Unaccounted for Funds
Entity UGX US$ EURO
Ministry Of Finance, Planning and Economic Development
1,619,879,097
Strengthening Evidence Based Decision Making II-MOFPED
74,903,000
Transport Sector Development
Project SDR 120,000,000
23,632,667
Judicial Service Commission 95,350,296
Uganda Law Reform
Commission
63,000,000
Ministry of Local Government 137,542,000
District lively hood support Programme
183,219,506
Northern Uganda Social Action
Fund
58,826,655,271
Uganda Good Governance
(UGOGO) Programme
109,402,538
Public Service Commission 21,760,585
Kampala Capital City Authority 74,547,100
Parliamentary Commission 27,401,000
NAADS secretariat 8,460,120,471
Ministry Of Energy And Mineral
Development
122,889,501
Energy for Rural Transformation II Project –
Private Sector Foundation
Uganda (PSFU) Component
455,000
Ministry of Gender, Labour and
Social Development
25,000,000
Ministry of Health 121,360,800
East African Public Health Laboratories Networking
Project (EAPHLNP)
31,377,000
Uganda Health Systems
Strengthening Project (UHSSP)
27,007,487
Uganda Global Fund to Fight Aids, Tuberculosis and
Malaria Project - MALARIA
COMPONENT ROUND 7
518,614
Arua Regional Referral Hospital 359,130,640
Mbale Regional Referral
Hospital
23,526,000
Lira Regional Referral Hospital 106,394,580
Gulu Regional Referral Hospital 219,224,118
23
Entity UGX US$ EURO
Mbarara Regional Referral Hospital
10,164,220
Soroti Regional Referral
Hospital
23,466,678
Hoima Regional Referral
Hospital
12,520,753
China-Uganda Friendship Hospital Naguru
1,500,129,768
Ministry of Education And
Sports
873,759,757
Ministry of Public service 302,018,445
Ministry of Education and
Sports Universal Post Primary Education and Training
(UPPET) Project
10,008,317,486
Makerere University 308,857,850
Economic Policy Research Centre (EPRC)
62,020,000
Norwegian Programme for
Capacity Development in Higher Education and Research
for Development (NORHED) Funded Projects
12,247
Adaptation of small scale biogas
digesters for use in rural households in sub-
Saharan Africa Project
137,327
Mbarara University of Science And Technology
17,407,000
Kyambogo University 588,454,804
Gulu University 728,758,584
Ministry of Water And Environment
202,890,333
Lake Victoria Environmental
Management Project Phase II (LVEMP II)
30,758,200
Water and Sanitation
Development Facility - East (WSDF-E)
19,417,500
Ministry of Trade, Industry And
Cooperatives
215,110,206
Uganda High Commission,
Bujumbura
13,748,041
Uganda Embassy, Cairo 52,625,621
Uganda Embassy, Kinshasa 61,253,767
85,785,457,670 530,861 137,327
24
1.3.4 Un-Accounted for Taxes
During the year under review, seven MDAs did not account for taxes amounting to
UGX.2,524,676,637 contrary to the requirements of the Income Tax Act 1997 (as
amended). These un-accounted for taxes included UGX.1,965,825,158 relating to
un-remitted tax deductions from payments made to suppliers and
UGX.558,851,479 un-deducted tax from eligible payments. Table 5 and 6 refer.
The failure to deduct and remit taxes directly impacts on collections by the
Uganda Revenue Authority. I advised Accounting Officers to comply with the tax
law.
Table 5 Un-remitted taxes Entity Amount
Health Service Commission 17,945,553
Mulago Referral Hospital Complex 1,867,853,563
Makerere University 43,131,990
Busitema University 36,894,052
Total 1,965,825,158
Table 6 Un-Deducted taxes Entity Amount
Local Government Finance
Commission
72,542,866
Lira Regional Referral Hospital 29,094,551
Makerere University 457,214,062
Total 558,851,479
Grand Total 2,524,676,637
1.3.5 Outstanding Commitments
It was noted that a number of government entities have continued to enter into
commitments beyond the available funds. This is contrary to the commitment
control system which requires the accounting officer to commit Government within
the provided funds. The total amount of domestic arrears has continued to
increase over the years to UGX.1.274 trillion, as illustrated in the table 7 and
graph below:-
25
Table 7: domestic arrears for the last three years
Details Amounts (UGX)
2011/2012 2012/2013 2013/14
Domestic
arrears
763,186,161,377 1,127,241,181,530 1,274,539,269,438
Graph 1: showing the increase in domestic arrears
I have advised that Treasury needs to come up with a strategy on how it intends
to address the problem of the increasing domestic arrears.
Table Domestic arrears details Ministry/Department Amount
Office of the President 11,182,915,772
State House 529,849,725
Office of the Prime Minister 28,666,752
Ministry of Defence 81,928,017,200
Ministry of Public Service 1,187,512,043
Ministry of Foreign Affairs 32,395,526,489
Ministry of Justice and Constitutional Affairs 442,173,233,469
Ministry of Finance, Planning and Economic 74,273,703,301
Ministry of Internal Affairs 1,347,504,072
26
Ministry/Department Amount
Ministry of Agriculture, Animal Industry and Fisheries
13,412,965
Ministry of Local Government 26,491,610
Ministry of Lands, and Environment 9,786,954,419
Ministry of Education and Sports 1,608,017,001
Ministry of Health 10,815,916,944
Ministry of Trade, Industry and Cooperatives 4,373,220,288
Ministry of Works, Housing and Communication 137,149,140
Ministry of Energy and Minerals 11,369,575,619
Ministry of Gender, Labour and Social Development 4,773,792,282
Ministry of Water & Environment 3,002,380,703
Ministry of Communication & ICT 1,251,589,543
Ministry of East African Affairs 3,104,636,201
Judiciary 7,884,204,435
Electoral Commission 8,139,451,273
Inspectorate of Government 66,789,517
Law Reform Commission 486,899,069
Uganda Human Rights Commission 10,398,832
Uganda Aids Commission 231,162,155
Uganda Industrial Research Institution 10,495,093
Directorate of Ethics & Integrity 269,736,264
Uganda National Roads Authority 376,619,216,212
Uganda Heart Institute 405,417,044
Uganda Tourism Board 252,420
Uganda Road Fund 113,721,073
UGANDA REGISTRATION SERVICES BURREAU 14,894,636,149
NATIONAL CITIZENSHIP & IMM CTRL 39,750,123,409
KCCA 9,806,247,065
EQUAL OPPORTUNITIES COMMISSION 2,948,596
Accountant Generals office 49,732,652
Education Service Commission 18,489,607
Directorate of Public Prosecutions 898,836,756
Health Service Commission 75,489,633
National Agricultural Research Organisation 743,038,883
Uganda Police 46,702,959,156
Uganda Prisons 46,597,708,858
Public Service Commission 73,540,596
Local Government Finance Commission 17,525,048
National Environment Management Institute 446,656
27
Ministry/Department Amount
Uganda Blood Transfusion Service 35,195,800
NAADS 450,484,312
UNBS 514,191
Uganda Lands Commission 7,163,296,958
ESO 3,072,785,870
Mulago Hospital Complex 8,901,380,582
Butabika Hospital 2,689,244
Arua Hospital 42,038,550
Gulu Hospital 1,478,683,569
Hoima Hospital 24,198,822
Jinja Hospital 821,384,282
Kabale Hospital 13,329,254
Masaka Hospital 88,937,450
Mbale Hospital 266,412,236
Soroti Hospital 164,195,808
Lira Hospital 3,144,629
Mbarara Regional Hospital 979,056,740
Naguru Referral hospital 15,440,299
Uganda Mission , New York 372,744,046
Uganda High Commission in the United Kingdom 22,343,922
Uganda High Commission in India 136,735,355
Uganda High Commission in Egypt 156,458,196
Uganda High Commission in Kenya 41,344,046
Uganda High Commission in Nigeria 1,963,510
Uganda High Commission in South Africa 34,456,347
Uganda Embassy in the United States 35,737,665
Uganda Embassy in Ethiopia 437,876,327
Uganda Embassy in China 398,313,217
Uganda Embassy in Rwanda 1,035,112
Uganda Embassy in Belgium 37,729,811
Uganda Embassy in Italy 7,367,626
Uganda Embassy in DRC 131,225,090
Uganda Embassy in France 1,441,784
Uganda Embassy in Russia 8,599,658
Uganda Embassy in Australia 11,197,141
GRAND TOTAL 1,274,539,269,438
28
1.3.6 Budget performance
Budget shortfall
I noted that sixteen MDAs budgeted to receive UGX.1,945,157,932,133, out of
which UGX.750,336,029,473 was received translating into a 39% out-turn for the
financial year. This left a funding gap of UGX.1,194,926,969,786 (61%). Details
are in the table 8 below: Failure to release the budgeted funds to the MDAs
affected implementation of the planned activities which affects fulfilment of their
mandates in the long run. I advised Accounting Officers to take up this matter
with the relevant authorities to ensure all the budgeted funds are released so as to
accomplish planned activities.
Table 8 Budget shortfall Entity Budget
(UGX)
Received (UGX) Shortfall (UGX) %age of
shortfall
Department of Ethics and integrity
5,404,295,598 5,219,309,500 184,986,098 3.4
Ministry of Internal
Affairs
10,916,219,910 10,734,020,200 182,199,710 1.6
National Agriculture
Research
Organization
41,867,739,709 35,027,197,017 6,840,542,692 16.3
Statements of
Quality Infrastructure and
Standards
Programme (QUISP)
9,737,388,600 3,136,178,649 6,601,209,951 67.7
Vegetable Oil
Development
Project (VODP), Phase II
35,215,199,674 22,737,879,128 12,477,320,546 35.4
Inspectorate Of Government- IGG
34,209,254,859 34,128,691,768 80,563,091 0.23
Ministry of Lands,
Housing and Urban Development
17,277,762,153 15,256,559,842 2,021,202,311 11.7
Ministry of Energy
And Mineral Development
1,305,566,104,201 189,656,857,225 1,115,909,246,976 85
President‟s Office 73,619,648,221 73,561,071,202 58,577,019 0.079
Ministry of Tourism, Wildlife and
Antiquities
13,612,395,000 12,309,697,806 1,302,697,194 9.5
Uganda Export Promotions Board
5,916,691,307 1,459,163,507 4,457,527,800 73.3
China-Uganda 9,548,296,000 7,187,921,785 2,360,374,215 24.7
29
Entity Budget (UGX)
Received (UGX) Shortfall (UGX) %age of shortfall
Friendship Hospital,
Naguru
Ministry of Justice
and Constitutional
Affairs
60,643,372,903 57,225,590,343 3,417,782,560 5.6
Ministry of Work
and Transport
119,061,202,859 91,677,910,743 27,383,292,116 23
Ministry Of Education And
Sports
197,562,361,139 186,558,729,377 11,003,631,762 6
Ministry Of Education And
Sports- Muni University
5,000,000,000 4,459,251,381 540,748,619 10.4
Totals. 1,945,157,932,133 750,336,029,473 1,194,821,902,660
1.3.7 Under absorption of Government Funds
Government entities returned unspent balances of UGX.9,412,704,745 to the
consolidated Fund and Projects failed to absorb funds totalling to
UGX.217,393,823,773 indicating partial service delivery. Most affected service
delivery areas were road constructions, agro processing, household income
improvement, and health and education services. The low absorption was
attributed to inefficiencies in the management of procurements, delayed
accountability, incompetence by contractors, poor planning among others. In the
circumstances, service delivery is undermined.
I advised management to review the causes and develop strategies to ensure
these Projects/Programmes are implemented timely. The table 9 below refers.
Table 9: Under absorption of Government Funds Entity Amount (UGX)
Ministry Of Finance, Planning and Economic Development 4,279,076,501
SIDA support to Competitiveness Investment climate project 46,176,200
Rural Financial Services Project 25,871,247
FINMAP 9,245,168,202
DFID/DANIDA Support IGG 397,123,848
Directorate Of Ethics and Integrity 16,141,555
30
Entity Amount (UGX)
Justice Law and Order Sector 31,311,690,369
Ministry of Justice and Constitutional Affairs 626,612,306
Judicial Service Commission 11,686,514
Ministry of Local Government 206,455,619
CAIIP Prog. II 49,863,220,272
CAIIP Prog. III 42,765,790,733
Market and Agriculture Trade Improvement project 20,900,695,536
District lively hood support programme 661,108,818
Office of the Prime Minister 1,598,871,722
Ministry of Public Service 1,019,906,494
PUBLI SECTOR REFORM PROGRAMME 262,479,735
Public Service Commission 22,834,248
Parliamentary Commission 283,243,030
State House 166,980,339
Ministry Of Agriculture, Animal Industry And Fisheries 83,070,501
NAADS secretariat 374,488,912
Vegetable Oil Development Project 2 6,240,584,580
East African Agricultural Productivity program (EAAPP) 9,426,703,017
ATAAS (Grant) EU, WB and Danida 26,287,401,192
Electricity Sector Development Project (ESDP) 758,679,600
Ministry of Health 112,014,076
Global Fund HSS 1,106,657,333
Global Fund Malaria Round 4 119,652,304
Uganda Blood Transfusion Services 503,763
Health Service Commission 45,460,306
Butabika Mental Referral Hospital 323,725,696
Uganda Cancer Institute 13,001,287
Uganda Heart Institute 1,621,796
Mbale Regional Referral Hospital 2,737,071
Fort Portal Regional Referral Hospital 124,615,088
Education Service Commission 47,607,960
Lake Victoria Environmental Management-Project Phase II 3,533,295,929
District Commercial Officers Services Support Project 3,804,561,600
TRACE 101,446,800
Ministry of Lands, Housing And Urban Development 50,123,067
Leveraging Municipal Infrastructure Improvement
Investments( LMIII) Project
315,127,600
Transforming Settlements of the Urban Poor in Uganda
(TSUPU)
433,195,201
Uganda Land Commission 995,000
Ministry of Information And Communications Technology 60,509,764
Ministry of Foreign Affairs 65,593,054
East African Community Affairs 11,425,154
31
Entity Amount (UGX)
National council of Children 124,449,360
Ministry of Tourism, Wildlife and Antiquities 20,929,857
Uganda High Commission, Washington 10,248,222
Uganda Consulate, Guangzhou, China 66,487,046
Uganda Embassy, Tripoli 15,778,349
TOTAL 217,393,823,773
1.3.8 WASTEFUL/NUGATORY EXPENDITURE
Good practice requires Accounting officers to reduce cases of apparent waste,
extravagant administration or failure to achieve value for money due to
management‟s laxity in the conduct of operations, however I noted wasteful
expenditure to the tune of UGX 7,478,849,806.and USD 3,663,761. These arose as
a result of interest on late payments, parking fees for grounded vehicles, delayed
handover of sites, court settlements among others. Table 10 below refers. This
affected the implementation of activities in the MDA‟s and on the overall service
delivery.
I advised management to adhere to the contract arrangements with a view of
avoiding such expenses.
Table 10 Wasteful/Nugatory Expenditure Entity Amount (UGX) USD
Ministry of Works And Transport 726,882,420
Uganda National Roads Authority 2,464,934,174 3,663,761
Ministry of Health 2,143,173,980
Uganda Aids Commission 12,766,000
Uganda Cancer Institute 448,408,158
China-Uganda Friendship Hospital, Naguru 8,054,900
Ministry of Water And Environment 1,120,908,971
Uganda Embassy, ABU DHABI 2,048,822
Ministry of Local Government 404,788,822
Mbale Regional Referral Hospital 146,883,559
TOTAL 7,478,849,806 3,663,761
32
1.3.9 ADVANCES TO STAFF PERSONAL ACCOUNTS:
A number of accounting officers advanced a total sum of UGX.12,014,225,502 to
their staff, through their individual personal accounts. Table 11 below refers. I
noted a reduction of 26% as compared to the previous year amount of
UGX.16,284,144,090. Although there has been an improvement/decline in
absolute terms, I advised the accounting officers to avoid the practice as it is
contrary to regulations, highly risky and exposes government funds to loss since
accounting officers have no control over individual‟s bank accounts. Management
was advised to adhere to the regulations.
Table 11 Advances to Staff Personal Accounts Entity Amount
Directorate Of Public Prosecutions 68,730,000
Office of the Prime Minister 3,607,259,014
Local Government Finance Commission 241,922,320
Parliamentary Commission 3,429,105,022
Ministry of Health 15,644,667
Ministry of Local Government 4,623,642,146
Uganda Health Systems Strengthening Project (UHSSP) 10,515,333
Mbarara University of Science And Technology 17,407,000
TOTAL 12,014,225,502
1.3.10 UN-AUTHORISED/EXCESS EXPENDITURE
An analysis of budget estimates and the actual expenditure of ministries,
departments and agencies revealed unauthorized/excess expenditure to the tune
of UGX. 24,946,031,342 mostly by foreign missions, universities and the energy
fund contrary to Section 17 and section 9 (5) of the PFAA, 2003. Table 12 below
refers. There was no authority in form of approved re-allocation or Virement
warrants obtained to incur over expenditure. Management was advised to adhere
to the relevant sections of the law.
Table 12 Un-Authorised/Excess Expenditure Entity Amount
Energy Fund 10,432,195,553
Makerere University 4,037,303,551
Makerere University Business School 1,936,187,681
33
Entity Amount
Mbarara University of Science And Technology 713,736,286
Kyambogo University 5,135,749,119
National Youth Council 51,750,000
Uganda, Embassy Addis Ababa 142,915,235
Uganda Embassy Brussels 390,437,807
Uganda High Commission, Canberra 41,160,736
Uganda Embassy Juba 1,282,122,285
Uganda High Commission, London 461,037,361
Uganda Embassy New York 321,435,728
TOTAL 24,946,031,342
1.3.11IRREGULARITIES IN PROCUREMENTS
I noted that a number of entities conducted procurements worth
UGX.7,404,413,312 and US$.34,336 that violated the provisions of the
procurement law and its regulations. Table 13 below refers. The violations were
mainly in form of delays, un-planned procurements, use of non-prequalified
suppliers, un-accomplished procurements, un-authorised direct procurements,
non-delivery of four tractors and insufficient procurement records.
I advised Accounting Officer to always adhere to the provisions of the
procurement laws and regulations.
Table 13 Procurement Irregularity Entity Procurement
Irregularity Amount
Ministry of Works And Transport
Delays in the procurement evaluation process Nil
Ministry of Local Government
Pre-qualified framework contracts Nil
Ministry of Gender, Labour and Social Development
Non-Disposal of Obsolete Assets Nil
Office of the President Procurements not in the entity`s procurement plan
64,037,000
Ministry Of Trade, Industry And Cooperatives
Un implemented activities in the procurement plan
Un supported procurement
1,866,080,000
45,900,000
Ministry Of Agriculture, Animal Industry And Fisheries
Un planned procurement Incomplete renovation works Delayed Supply of 4 tractors
59,659,384 144,214,834 US$.34,336
Butabika Mental Referral Hospital
Un authorised additional funding above contractual figures
83,169,990
34
Entity Procurement Irregularity
Amount
Uganda Cancer Institute
Irregular Amendment of contract 2,197,609,659
Mulago Referral Hospital Complex
Direct Procurements ( Non Use of Prequalified Service providers)
Irregular Procurements Procurement of Parking Management Services
(unplanned and No records)
504,358,000
128,956,377
Ministry of Education And Sports
Delayed Procurement Process Nil
Makerere University Business School
Contract not cleared by the Solicitor General 152,707,104
Gulu University Direct Procurements 34,444,000
Ministry of Water And Environment
Delays in the procurement evaluation process Nil
Ministry of Trade, Industry And
Cooperatives
Un implemented activities in the procurement plan
Un supported procurement
1,866,080,000
45,900,000
Ministry of Foreign Affairs
Failure to submit progress Reports on Waivers and Deviations Given by PPDA
Nil
Uganda High Commission, Abuja
Non Compliance with the PPDA Act regulations Nil
Uganda Embassy, Cairo
Absence of a Procurement Plan Absence of Evaluation Committee Botched Renovation of the Official Residence Procurement of Office Laptops ( lack of technical
specification and evaluation report) Redesigning of the Chancery Reception ( lack of
evaluation committee report)
Nil
Nil Nil
Nil
Uganda High Commission, Canberra
Lack of procurement files 62,567,529
Uganda Embassy, Copenhagen
Lack of a procurement plan Nil
Uganda Embassy, Darla salaam
Irregular Procurements 116,645,135
Uganda Embassy, Tehran
Lack of a list of prequalified suppliers 32,084,300
1.3.12 Outstanding Receivables UGX. 136,620,085,336
During the review, it was noted that receivables worth UGX. 136,620,085,336 had
not been received by the various Ministries, Departments and Agencies and were
therefore still outstanding as at 30th June 2014 as summarized in table 14 below:
There is a risk that the activities for which these receivables were appropriated
were not carried out and this could have affected the implementation of planned
activities. I explained to the Accounting Officers that there seems to be laxity in
following up of the receivables and ensuring their recovery. I advised management
to expedite the recovery process and have all the receivables recovered.
Table 14 Outstanding Receivables
35
ENTITY AMOUNT
Butabika Hospital 41,705,859
CAIIP Prog.II 672,139,959
CAIIP Prog.III 599,242,578
F/ Portal Hospital 7,775,000
Inspectorate of Government 62,170,000
Judiciary Department 203,791,671
Masaka Hospital 67,000,000
Mbale Hospital 2,625,000
Ministry of Energy And Mineral Development 3,968,646,755
Ministry of Foreign Affairs 3,343,140,729
Ministry of Health 696,865,456
Ministry of Information and Communications Technology 3,452,442
Ministry of Internal Affairs 9,600,417
Ministry of Public Service 18,600,628
Ministry of Water & Environment 7,464,502,592
Ministry of Works & Transport 6,283,365,438
Moroto Regional Hospital 1,000,000
Mubende Regional Hospital 215,408,183
Naguru Hospital 62,039,827
National Citizenship and Immigration 8,628,412,000
National Planning Authority 3,648,966
Public Procurement and Disposal of Assets Authority 181,348,048
State House 590,200,000
Uganda Blood Transfusion Service 124,356,004
Uganda Embassy in Belgium 82,653,340
Uganda Embassy in Berlin 233,199,891
Uganda Embassy in Burundi 3,966,456
Uganda Embassy in Canberra 13,366,531
Uganda Embassy in China 5,776,157
Uganda Embassy in Denmark 76,729,177
Uganda Embassy in Guangzhou 43,187,644
Uganda Embassy in Japan 274,164
Uganda Embassy in Moscow 46,827,823
Uganda Embassy in Rwanda 116,929,199
Uganda Embassy in Saudi Arabia 3,676,677
Uganda Embassy in The Us 327,593,565
Uganda Embassy in UAE Dubai 420,133,538
Uganda Heart Institute 4,169,069
Uganda High Commission In India 14,203,221
Uganda High Commission In Kenya 44,644,765
Uganda High Commission In South Africa 7,585,007
Uganda Investment Authority 7,415,815,646
Uganda Mission At The Un, New York 646,745,100
Uganda Police 3,759,853,523
Uganda Prisons 2,437,182,189
Kampala Capital City Authority 72,258,023,654
Local Government Finance Commission 52,575,575
Uganda Aids Commission 2,178,305
36
ENTITY AMOUNT
Uganda Human Rights Commission 162,418,338
Uganda Land Commission 150,000,000
Uganda National Roads Authority 4,945,982,553
Uganda Registration Services Bureau - Liquidation Acc‟t 8,177,490,354
Uganda Registration Services Bureau - Operations 2,998,910
Uganda Road Fund 1,860,291,838
Local Government Finance Commission 52,575,575
TOTAL 136,620,085,336
1.3.13 Staff shortages
Section 15(9) of the Standing Orders, 2010 mandates the Ministry of Public
Service to determine the structure, terms and conditions of service in Government
entities. Good strategic planning also requires an entity to carry out human
resource planning to ensure that an adequate number of qualified staff is in place
to carry out the operational activities of an entity so as to enable her achieve
strategic objectives. A review of the staffing structures of various MDAs however
revealed a number of vacant posts in a number of entities. The Table 15 below
refers: Inadequate staffing affects the timely implementation of the Ministry's
activities. It may adversely impact on the entities in the achievement of its
strategic objectives.
I advised Accounting Officers to make concerted efforts in liaising with all
stakeholders to ensure that vacant posts are filled to enable the Ministry
adequately deliver on its mandate.
Table 15 Staff shortages
Entity Approved Filled Vacant % shortfall
Min of Ethics and Integrity
59 46 14 24
Min of ICT 93 76 17 18
Min of Internal Affairs 35
Min of Lands 839 343 486 59
Min of Gender Labour
and Social Development
609 276 333 55
Mulago Hospital 1477 1290 187 12
DPP - - 31 -
Judiciary - - 297 -
Min of Tourism 43
Uganda Management Institute.
219 182 37 17
Makerere University. 2780 1484 1296 46
37
Entity Approved Filled Vacant % shortfall
MAAIF:-Department of Crop Protection
21
Min of Justice and Constitutional Affairs.
10
Min of Works
East African Civil
Aviation Academy.
Kireka Division of
Material Testing
76
70
54
46
22
25
29
32
Arua Regional Referral Hospital
354 301 53 15
Moroto Regional Referral
Hospital
386 153 233 60
Soroti Regional Referral
Hospital
344 259 85 25
Fort Portal Regional Referral Hospital
421 310 111 26
Hoima Regional Referral
Hospital
401 209 192 45
Jinja Regional Referral
Hospital
417 364 47 11
Kabale Regional Referral Hospital
350 227 123 35
Mbale Regional Referral
Hospital (PDU)
2
Mbarara Regional
Referral Hospital
620 437 183 30
Butabika Hospital 433 346 87 20
Uganda Blood
Transfusion Service
116 98 16 14
Kyambogo University 1550 830 720 46
Judicial Service Commission.
10
Uganda Road Fund 31 22 9 29
Parliamentary Commission.
485 403 80 16.5
Uganda Aids Commission 84 56 28 33
Health Service Commission
63 51 12 19
38
2.0 REPORT AND OPINION OF THE AUDITOR GENERAL ON THE
GOVERNMENT OF UGANDA CONSOLIDATED FINANCIAL
STATEMENTS FOR THE YEAR ENDED 30TH JUNE, 2014
THE RT. HON. SPEAKER OF PARLIAMENT
I am mandated by Article 163 (3) of the Constitution of the Republic of Uganda, 1995 (as
amended), to audit and report on the public accounts of Uganda and of all public offices,
including the courts, the central and local government administrations, universities and
public institutions of like nature, and any public corporation or other bodies or
organizations established by an Act of Parliament.
I have audited the accompanying consolidated financial statements of Government of
Uganda for the year ended 30th June 2014. These financial statements comprise of the
Statement of Financial Position as at 30th June 2014, Statement of Financial Performance,
Statement of Changes in Equity, Cash flow Statement together with other accompanying
statements, notes and accounting policies.
Management‟s Responsibility for the Financial Statements
Under Article 164 of the Constitution of the Republic of Uganda, 1995 (as amended) and
Section 8 of the Public Finance and Accountability Act (PFAA), 2003, the Accounting
Officers are accountable to Parliament for the funds and resources of the Votes/Entities
under their control. The Accountant General is also responsible for the preparation and
fair presentation of Consolidated Financial Statements in accordance with the
requirements of the Financial Reporting Guide, 2008, and for such internal control as
management determines necessary to enable the preparation of financial statements that
are free from material misstatement whether due to fraud or error.
Auditor‟s Responsibility
39
My responsibility as required by Article 163 of the Constitution of the Republic of Uganda,
1995 (as amended) and Sections 13 and 19 of the National Audit Act, 2008 is to express
an opinion on these statements based on my audit. I conducted the audit in accordance
with International Standards of Supreme Audit Institutions (ISSAIs). Those standards
require that I comply with the ethical requirements and plan and perform the audit to
obtain reasonable assurance about whether the financial statements are free from
material misstatement.
An audit involves performing audit procedures to obtain audit evidence about the
amounts and disclosures in the financial statements as well as evidence supporting
compliance with relevant laws and regulations. The procedures selected depend on the
Auditor‟s judgment, including the assessment of risks of material misstatement of the
financial statements whether due to fraud or error. In making those risk assessments, the
Auditor considers internal controls relevant to the entity‟s preparation of financial
statements in order to design audit procedures that are appropriate in the circumstances
but not for purposes of expressing an opinion on the effectiveness of the entity‟s internal
control. An audit also includes evaluating the appropriateness of accounting policies used
and the reasonableness of accounting estimates made by management, as well as
evaluating the overall presentation of the financial statements.
I believe that the audit evidence I have obtained is sufficient and appropriate to provide a
basis for my qualified audit opinion.
Part „„A‟‟ of this report sets out my opinion on the financial statements. Part “B” which
forms an integral part of this report presents in detail all the significant audit findings
made during the audit which have been brought to the attention of management.
PART “A”
Basis for Qualified Opinion
Un supported budget movement - UGX.264,546,614,000
In the Ministerial Policy Statement, management of Treasury Operations requested for
UGX.224billion to cater for external debt principal payments. However, this figure was
revised upwards to UGX.470,546,614,000 in the approved budget estimates. I was not
40
provided with the required documentation to provide justification and basis for the
upward revision of UGX.264,546,614,000.
Mischarge of Expenditure – UGX.49,972,190,602
A review of the expenditures revealed that various entities charged wrong expenditure
codes to the tune of UGX.49,972,190,602. This practice undermines the budgeting
process and the intentions of the appropriating authority as funds are not fully utilised for
the intended purposes. The practice also leads to financial misreporting.
Unaccounted for Advances
A total of UGX.84,323,243,109, advanced to staff to carry out activities in various entities
remained un-accounted for by the time of audit, contrary to the Public Finance and
Accounting Regulations. Delays in accounting for funds may encourage misappropriation.
Qualified Opinion
In my opinion, except for the possible effects of the matters described in the Basis for
Qualified Opinion paragraph, the consolidated financial statements of Government of
Uganda for the year ended 30th June 2014 are prepared, in all material respects, in
accordance with the Financial Reporting Guide, 2008 and section 31(6) of the Public
Finance and Accountability Act, 2003, of the Laws of Uganda.
Emphasis of Matter
Without qualifying my opinion further, attention is drawn to the following additional
matters which are also included in part B of this report and my annual report to
Parliament.
Contingent Liabilities - UGX.4,384,339,987,635
As disclosed in in the statement of contingent liabilities, Government contingent liabilities
are reported at UGX.4,384,339,987,635 up from UGX.2,275,442,213,858 the previous
year. The trend appears unsustainable in the event that a significant percentage
crystallizes into liabilities.
Classified Expenditure
41
As disclosed in note 7, a total of UGX.426,439,648,203 relates to classified expenditure.
In compliance with Regulation 12 of the Public Finance and Accountability (Classified
Expenditure) Regulations 2003, this expenditure was audited separately and a separate
audit report issued.
John F.S. Muwanga
AUDITOR GENERAL
KAMPALA
27th March, 2015
42
PART "B"
DETAILED REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL
STATEMENTS OF THE UGANDA CONSOLIDATED FUND ACCOUNT FOR THE
FINANCIAL YEAR ENDED 30TH JUNE 2014
This Section outlines the detailed audit findings, management responses, and my
recommendations in respect thereof.
2.1 INTRODUCTION
Article 163 (3) of the Constitution of the Republic of Uganda, 1995 (as amended)
requires me to audit and report on the public accounts of Uganda and all public
offices including the courts, the central and local government administrations,
universities, and public institutions of the like nature and any public corporation or
other bodies or organizations established by an Act of Parliament. Accordingly, I
carried out the audit of the Government of Uganda Consolidated Financial
Statements to enable me report to Parliament.
2.2 BACKGROUND INFORMATION
Under Article 164 of the Constitution of the Republic of Uganda, 1995 (as
amended) and Section 8 of the Public Finance and Accountability Act, 2003, the
Accounting Officers are accountable to Parliament for the funds and resources of
the Votes/Entities under their control. The Accountant General is appointed as the
Accounting Officer and Receiver of Revenue for the Consolidated Fund. He is
responsible for establishing and maintaining a system of Internal Controls
designed to provide reasonable assurance that the transactions recorded are
within the authority and properly record the use of all public funds by the
Government of the Republic of Uganda. Accordingly, the Accountant General is
responsible for the preparation and fair presentation of Consolidated Financial
Statements in accordance with the requirements of the Public Finance and
Accountability Act, 2003, and the modified cash basis of accounting.
The accompanying Government of Uganda consolidated financial statements
provide a record of the Governments‟ financial performance for the year 2013/14
43
and the financial position of the consolidated fund as at 30th June 2014, in
accordance with the Public Finance and Accountability Act, 2003.
2.3 AUDIT SCOPE
The audit was carried out in accordance with International Standards of Supreme
Audit Institutions (ISSAIs) and accordingly included a review of the accounting
records and agreed procedures as was considered necessary. In conducting my
reviews, special attention was paid to establish whether;
a. The consolidated financial statements have been prepared in accordance
with consistently applied Accounting Policies and fairly present the
revenues and expenditures of government for the year and of the
consolidated financial position of the Consolidated Fund as at the end of
the year.
b. All funds were utilized with due attention to economy and efficiency and
only for the purposes for which the funds were provided.
c. Management was in compliance with the Government of Uganda financial
regulations.
d. To evaluate and obtain a sufficient understanding of the internal control
structure of the department, assess control risk and identify reportable
conditions, including material internal control weaknesses.
e. All necessary supporting documents, records and accounts have been kept
in respect of all activities, and are in agreement with the consolidated
financial statements presented.
2.4 AUDIT PROCEDURES PERFORMED
The following audit procedures were undertaken:-
a. Revenue
Obtained schedules of all revenues collected and reconciled the amounts to the
entity‟s cashbooks and bank statements.
44
b. Expenditure
The entity payment vouchers were examined for proper authorization, eligibility
and budgetary provision, accountability and support documentation.
c. Internal Control System
Reviewed the internal control system and its operations to establish whether
sound controls were applied throughout the period audited.
d. Entity Financial Statements
Examined, on a test basis, evidence supporting the amounts and disclosures in the
financial statements; assessed the accounting principles used and significant
estimates made by management; as well as evaluating the overall financial
statement presentation.
2.5 FINDINGS
2.5.1 Budget Performance
During the year under review, government realised domestic revenue amounting
to UGX.8,558,164,372,769 out of the projected amount of
UGX.8,760,700,000,000, representing a 98% performance. A total of
UGX.468,539,890,855 was also realised from grants.
Further noted was that although a total of UGX.11,909,327,199,837 was
appropriated for utilization by MDAs, government released a sum of
UGX.9,951,405,146,965 to the MDAs to cater for their planned activities. This
represents 84% of the approved budget as summarized in the table below.
Table showing Budget Performance by Classification
Summary Approved Estimates (Ugx)
Actual Released (Ugx) Performance Percen
tage
Ministries 4,082,118,540,426 2,829,005,115,553 69%
Agencies 5,600,222,403,447 4,965,527,511,837 89%
Referral Hospitals 128,334,797,129 110,399,214,895 86%
Embassies abroad 89,508,388,833 88,628,155,914 99%
District Councils 1,885,871,113,747 1,837,334,896,715 97%
45
2.6 SUPPLEMENTARY EXPENDITURE - UGX.56,133,336,950
Article 156(2) of the Constitution of the Republic Government 1995 (as amended)
prescribes that if in respect of any financial year it is found that the amount
appropriated for any purpose under the Appropriation Act is insufficient or that a
need has arisen for expenditure for a purpose for which no amount has been
appropriated by the Act, a supplementary estimate showing the sums required or
spent shall be laid down before Parliament and in the case of excess expenditure,
within four months after the money is spent.
Section 12 (1) of the Budget Act 2001 stipulates that total supplementary
expenditure that requires additional resources over and above what is
appropriated by Parliament shall not exceed 3% of the total approved budget for
that financial year without prior approval of Parliament.
I noted during a detailed analysis of the supplementary expenditure that an excess
of UGX.56,133,336,950, which is 0.4% above the approved 3% as per the Budget
Act, was spent without prior approval by parliament. However, the provision in the
Budget Act appears not to be in harmony with the provision in the Constitution
with regard to approval of a supplementary expenditure. I have accordingly
advised government to seek a legal interpretation of the above provisions so as to
have them harmonised.
2.7 Payment of Gross Tax for Ineligible Items
In a letter dated 25th June, 2013, referenced TPD 167/238/19 from the Minister of
State for Finance to the Commissioner General, Uganda Revenue Authority (URA),
Government committed itself to support the Agriculture Sector, in particular the
textile sub sector, by paying Value Added Tax (VAT) and Import duty on raw
materials imported for manufacturing textiles, and VAT on the supply of
manufactured textiles. This was subject to the condition that the raw materials
Urban/municipal
Councils
123,271,956,255 120,510,252,051 98%
Totals
11,909,327,199,837
9,951,405,146,965 84%
46
would exclusively be used to manufacture textiles. The interventions would make
locally manufactured textiles cheaper and, thus promoting the growing of crops
that provide fiber.
I noted that the Ministry of Finance, Planning, and Economic Development paid a
sum of UGX.653,893,113 in taxes, on behalf of private companies in relation to
the goods which were not raw materials used in the manufacturing of textiles.
These included items such as already woven and printed Polyester bed sheet
materials. This practice undermines the intentions of Government, due to the fact
that imported textile materials eventually become cheaper and suffocate the
demand for locally manufactured textiles. This negatively impacts on the demand
for agriculture produce.
I advised Management to always keenly observe the conditions set by Government
before approving such tax payments, and to consider initiating recovery measures
of the amounts irregularly expended.
2.8 Contingent liabilities - UGX.4,384,339,987,635
A contingent liability is a possible cash outflow whose occurrence is dependent on
an event which is not in the control of an organization. Including figures as
contingent liabilities implies that management‟s assessment shows a possibility of
a cash outflow in a near future.
During the year under review, the balance for contingent liabilities increased from
UGX.2,275,442,213,858 as at 30th June, 2013, to UGX.4,384,339,987,635 as at
30th June, 2014, representing a 93% increment. This is an equivalent of 54% of
the tax revenue collected by URA during the year under review. It was further
noted that out of the reported amount, 98% was arising from legal proceedings
against Government under the Ministry of Justice and Constitutional Affairs. In the
event that all these liabilities crystalize, Government will be required to use close
to 50% of its annual budget to meet these liabilities, which is likely to adversely
affect implementation of other government programmes.
47
In response, management explained that mitigation against accumulation of such
contingent liabilities requires Government wide responsibility and effort. I
concurred with this explanation and accordingly advised Government to look into
this matter so as to arrive at a sustainable solution.
2.9 Payroll Management
The Government of Uganda has been implementing a centralized payroll payment
process which has been characterized by numerous weaknesses. Under this
process, most Accounting Officers perceived their role within the payroll payment
process as implementing the assignment on behalf of Ministry of Public Service
(MoPS), but without full responsibility and accountability on what happens in the
process. In addition, MoPS did not have adequate resources to manage a
centralized payroll process. This resulted into delayed payments, inclusion of ghost
employees on the payroll, delays in staff accessing the Government payroll and
repeated removal and reinstatement of staff on the payroll. Details of these
findings are contained in my report on the comprehensive audit of the
Government payroll issued in February 2015.
During the year under review, a reform to decentralize the payroll payment
process was initiated. Under the new decentralized salary payment process,
individual votes are required to upload, process and pay salaries from their votes‟
respective salary accounts in BoU. The Accounting Officers are therefore fully
responsible for their payrolls including the timing of monthly salary payments. The
new arrangement has had significant improvements in the management of the
payroll payment process, especially in the areas of timely payment, exclusion of
ghosts, prompt inclusion on the payroll of newly appointed staff and fully
assigning payroll responsibility to Accounting Officers.
While the principle of decentralised management has had its merits, the lack of
adequate controls supported by a strengthened payroll monitoring system, poses
a risk to the management of the decentralised model. The decentralised payroll
process without clear controls at the different Votes may in the long run just
transfer the same payroll challenges to the Votes. Besides, at the time of the
48
audit, each Accounting Officer processed payroll data using the IPPS from which a
payroll was generated monthly. This was then transferred to the IFMS, IPPS
interface in „plain text format‟ and then manually uploaded into the IFMS for
payment. However, the „plain text format‟ used in this process is not a secure
format and is open to uncontrolled modification, which, if changes were made,
could go undetected due to the absence of any form of change log.
In response, management acknowledged that upload of files is open to
modifications but the Accounting Officers are required to run an invoice register
and reconcile it with the payroll before approval of invoices. I advised Treasury
and MoPS management, to implement a software mechanism, which enables the
movement of encrypted payment related data from the IPPS to the IFMS.
2.10 Unauthorized Receipt of grants by MDAs
Section 57 of the Public Finance and Accountability Act, 2003, states that, “Any
grants made to the Government shall be received by the Minister (Minister for
Finance) on behalf of Government and shall be paid into and form part of the
Consolidated Fund or a special fund established for a specific purpose”. Ideally,
the Ministries, Departments and Agencies (MDA‟s) are expected to identify project
needs for donor support and come up with proposals through the Sector Working
Groups. The development committee at MOFPED then conducts a feasibility study
of the project proposal and thereafter identifies Development Partners for funding.
Once the source of funding is identified, an MoU between the Minister for Finance
and the Development partner is signed. The grants are then entered in the
Ministry of Finance‟s Debt Management and Financial analysis System (DMFAS) for
onward monitoring and reporting.
Comparison of notifications from Bank of Uganda sent to MOFPED relating to
funds received from Development Partners and total grants reported in the DMFAS
revealed that grants worth USD.15,322,575 received in Bank of Uganda by various
government Ministries, Departments and Agencies were not in the DMFAS. In
addition, grants worth USD.98,052,299 received from various Development
49
Partners for various research initiatives by Makerere University over a three year
period were not found on the system.
Management explained that they did not have any documentation pertaining to
the said funds and that only grants with agreements or MoUs that involved
MoFPED were included in the system. This may imply that funds were solicited on
behalf of GoU without involvement of the Minister responsible for Finance, and are
therefore unknown to the Ministry. This creates risks of: double financing by both
GoU and donors; abuse of funds by recipients; uninformed allocation of GoU funds
and the risk of using GoU funded activities to account for donor funds and/or vice
versa. It also implies that the total of Grants reported in the consolidated financial
statements is understated and misleading. I advised government to put in place a
mechanism to track all grants received on its behalf and accordingly monitor their
performance.
2.11 The Treasury Single Account
With effect from 1st October 2013, Government of Uganda (GoU) introduced a
Treasury Single Account (TSA) in which all government cash balances are
aggregated into a set of linked accounts. The primary objective of the TSA was to
ensure management of GoU aggregate cash balances in order to: Minimize
transaction costs during budget execution; Ensure efficient control and monitoring
of funds released to various Government agencies; and better coordination
between fiscal and monetary policy implementation initiatives of government.
The operations of the TSA over the period under review were analysed, and it was
noted that despite having challenges in the transition period, the implementation
has been largely successful. It was noted that: the arrangement has led to the
closure of a number of redundant accounts, which could have been avenues for
misuse of funds; it has greatly improved treasury cash management; as at 30th
June, 2014, cash is only available to entities which can absorb it; and it is
envisaged that in subsequent years, borrowing from the domestic market will be
greatly reduced.
50
However, I noted that the TSA is heavily dependent on strong budget controls on
the IFMS given that invoice funding is from a basket. At the moment, paid
transactions can still be presented as voided on the system and this creates extra
budgetary funds. In addition, budget journals can still be used to bypass all other
controls available in the budget revision process. I advised the Accountant General
to further strengthen the system and manual controls regarding budget revision so
as to harness all the benefits of a Treasury Single Account.
2.12 Payables
Audit reviewed the status of payables (domestic arrears) as at 30th June, 2014 and
noted that despite adopting the commitment control system, the total value of
payables increased by UGX.138.166 billion (approximately 12%) from UGX.1.127
trillion in the financial year 2012/2013 to UGX.1.265 trillion in the year 2013/2014.
This is further illustrated in the table and graph below;
Table 1: domestic arrears for the last four years
Financial Year
2010/2011 2011/2012 2012/2013 2013/2014
Amounts (Ugx)
473,654,629,150 763,186,161,377 1,127,241,181,530 1,265,406,925,415
0
200,000,000
400,000,000
600,000,000
800,000,000
1,000,000,000
1,200,000,000
1,400,000,000
2010/2011 2011/2012 2012/2013 2013/2014
Am
ou
nt
-U
gx (
'00
0)
Financial Year
Trend of Payables Position
Amounts - Ugx ('000)
51
The current status shows a steady increase in the payables figures, which
indicates that the current approaches to address the problem are not effectively
working. The debt figure may become unmanageable as it appears to be spiraling
out of control.
In response, various Accounting Officers explained that the Commitment Control
System cannot control certain types of expenditures such as the contractual
obligations of rent, wage and contributions to International Organizations. This is
further complicated by the budget credibility issues whereby certain Accounting
Officers may not budget adequately for some of the known expenditures.
Sometimes even when they budget adequately, in cases where budgets are cut to
finance supplementary budgets, arrears can be created.
I have advised that Treasury needs to evaluate the current approach that is being
utilized to control domestic arrears and consider making improvements in order to
reverse the spiraling trend.
2.13 Mischarge of Expenditure - UGX.49,972,190,602
Expenditure amounting UGX.49,972,190,602 by several votes in respect of various
activities was charged wrongly to item codes meant for other activities resulting in
misstatement of amounts expended on the affected item codes. These were done
without authority from Permanent Secretary/Secretary to Treasury (PS/ST).
Mischarges impact on the credibility of the financial statements, since the figures
reported therein do not reflect true amounts expended on the affected
expenditure items.
There is need for Accounting Officers to streamline budgeting processes and to
enforce strict adherence to the provisions regarding reallocation of funds.
Table showing entities that had mischarged expenditure
Entity AMOUNT MISCHARGED -
UGX
Accountability Sector
Ministry Of Finance, Planning and Economic Development 2,208,201,055
52
Department Of Ethics and Integrity 275,372,736
Works and Transport Sector
Ministry of Works And Transport 48,153,093
Uganda National Roads Authority 3,501,412,812
Ministry of Justice and Constitutional Affairs 615,047,805
Ministry of Internal Affairs 421,104,192
Uganda Police Force 132,090,477
Uganda Prisons Services 637,537,384
JLOS SECTOR
Judiciary Department 423,909,500
Judicial Service Commission 86,527,567
Uganda Law Reform Commission 77,415,412
DPP 454,431,122
Uganda Registration Services Bureau - Operations 239,197,478
National Citizenship And Immigration Control 5,906,786,217
Public Sector Management
Ministry of Local Government 2,497,433,465
Office of the Prime Minister 5,564,282,629
Ministry of Public Service 1,721,329,414
Public Service Commission 512,592,443
Local Government Finance Commission 241,919,355
Ministry of Gender, Labour and Social Development 66,982,475
Expanding Social Protection (2013) 11,976,000
Agriculture Sector
National Agricultural Research Organisation (NARO) 206,704,980
Energy Sector
Ministry of Energy And Mineral Development 3,038,506,327
Land Sector
Ministry of Lands, Housing And Urban Development 543,519,621
Ministry of Trade, Industry And Cooperatives 592,962,823
Ministry of Tourism Wildlife And Antiquities 115,112,418
WATER SECTOR
Ministry of Water and Environment 1,545,058,115
NEMA 942,053,402
MISSIONS
Uganda Embassy Brussels 150,514,718
HEALTH SECTOR
Ministry of Health 2,644,401,389
53
Uganda Blood Transfusion Services 27,880,704
Uganda Cancer Institute 656,275,672
Butabika Hospital 74,863,427
Education Sector
Ministry of Education and Sports 11,841,989,175
Makerere University 969,917,237
Kyambogo University 978,727,963
Total 49,972,190,602
2.14 Unaccounted for Funds
A sum of UGX.84,323,243,109, remained unaccounted for at the end of the year.
This comprised of funds advanced to staff to carry out various activities in various
Ministries, Departments and Agencies. This is contrary to the Public Finance and
Accountability Regulations which require all such advances to be accounted for
within 60 days on completion of the related activity. Delayed accountability for
funds may lead to falsification of accountability documents.
I advised the Accounting Officers to adhere to Regulations by ensuring that before
another amount is advanced, a previous one ought to be fully accounted for.
Table showing unaccounted for advances
Entity AMOUNT - UGX
Ministry Of Finance, Planning and Economic Development 1,619,879,097
Strengthening Evidence Based Decision Making II-MOFPED 74,903,000
Transport Sector Development Project SDR 120,000,000 23,632,667
Judicial Service Commission 95,350,296
Uganda Law Reform Commission 63,000,000
Ministry of Local Government 137,542,000
District lively hood support Programme 183,219,506
Northern Uganda Social Action Fund 58,826,655,271
Uganda Good Governance (UGOGO) Programme 109,402,538
Public Service Commission 21,760,585
Kampala Capital City Authority 74,547,100
Parliamentary Commission 27,401,000
NAADS secretariat 8,460,120,471
Ministry Of Energy And Mineral Development 122,889,501
Energy for Rural Transformation II Project – Private Sector Foundation Uganda (PSFU) Component
455,000
54
Entity AMOUNT - UGX
Ministry of Gender, Labour and Social Development 25,000,000
Ministry of Health 121,360,800
East African Public Health Laboratories Networking Project (EAPHLNP)
31,377,000
Uganda Health Systems Strengthening Project (UHSSP) 27,007,487
Arua Regional Referral Hospital 359,130,640
Mbale Regional Referral Hospital 23,526,000
Lira Regional Referral Hospital 106,394,580
Gulu Regional Referral Hospital 219,224,118
Mbarara Regional Referral Hospital 10,164,220
Soroti Regional Referral Hospital 23,466,678
Hoima Regional Referral Hospital 12,520,753
China-Uganda Friendship Hospital Naguru 1,500,129,768
Ministry of Education and Sports 873,759,757
Ministry of Education and Sports Universal Post Primary
Education and Training (UPPET) Project
10,008,317,486
Makerere University 308,857,850
Economic Policy Research Centre (EPRC) 62,020,000
Mbarara University of Science And Technology 17,407,000
Kyambogo University 570,497,304
Gulu University 728,758,584
Ministry of Water And Environment 202,890,333
Lake Victoria Environmental Management Project Phase II (LVEMP II)
30,758,200
Water and Sanitation Development Facility - East (WSDF-E) 19,417,500
Ministry of Trade, Industry And Cooperatives 215,110,206
Uganda High Commission, Bujumbura 13,748,041
Uganda Embassy, Cairo 52,625,621
Uganda Embassy, Kinshasa 61,253,767
Ministry of Public Service 302,018,445
TOTAL 84,323,243,109
55
ACCOUNTABILITY SECTOR
3.0 TREASURY OPERATIONS
3.1 Un supported budget movement
It was noted that in the ministerial policy statement submitted to Parliament for
the year under review, management requested for UGX.224billion to cater for
External Debt Principal Payments. It was however noted that, in the approved
budget estimates, a total of UGX.470,546,614,000 was allocated for external debt
principal repayments. I was not provided with the required documentation to
support the upward revision of UGX.264,546,614,000.
It was further noted that of the approved amount, a total of UGX.329,197,200,187
representing 70% of the external debt budget, was vired to other expenditure
items. Management explained that while it is true that external debt amortization
was UGX.224bn, they had factored in domestic debt interest to allow for any
interest shortfall. However, it should be noted that domestic debt interest was
budgeted for elsewhere to a tune of UGX.860bn. This is an indicator of
weaknesses in the budget formulation which undermines the credibility of the
budgeting processes.
I have advised Management to strengthen its budgeting processes so as to arrive
at realistic estimates. Management is further requested to provide the basis for the
above budget revisions as well as virements.
3.2 Payments in respect of Mandamus Orders
It was noted that Parliament did not appropriate funds for expenditure on item
282104, in respect to payments for third party compensations under the Treasury
Operations Vote. However, management made virements from external debt
payments to the tune of UGX.87,992,164,680 to cater for third party
compensations. The following observations have been noted;
a) The force of Mandamus orders
I noted that the mandate to settle court awards is vested with the Ministry of
Justice and Constitutional Affairs and the line item was provided for as a statutory
56
charge on the Consolidated Fund. During the year under review, the Ministry of
Justice and Constitutional Affairs paid domestic arrears amounting to
UGX.8,561,690,269 in respect of Court Awards and compensations. The payment
of UGX.87,628,710,396 to several beneficiaries by the Ministry of Finance Planning
and Economic Development under mandamas orders creates a distortion within
the established payment frameworks.
The Accounting Officer explained that authority to effect the payments was
communicated in a letter Ref. MA/57/012/M and dated 13th June 2013 by the
Attorney General to the Minister of Finance, Planning and Economic Development.
I advised management that the issue of mandate be resolved to ensure
conformance with set laws.
b) Disregard of MoUs
Due to cash flow constraints, Memoranda of Understanding (MoUs) were entered
by MOFPED with the representatives of the would-be beneficiaries to spread the
payments over a longer period without attracting extra interest. However, there
were instances of payments by the Ministry of Finance, Planning and Economic
Development, beyond the agreed installments. This trend needs to be checked if
any benefits are to be reaped from signing the MOU‟s.
Table showing payments not in in line with payment plans as per MoUs
Court case Amount agreed on in MoU - Ugx
Amount paid - Ugx
Amounts that could have been paid in
later years - Ugx
C/S No.22/2001 4,808,185,200 8,488,185,200 3,680,000,000
C/S No.16/2009 10,349,786,849 15,700,289,135 5,350,502,286
C/S No.469/2004 618,610,131 1,136,370,000 517,759,869
Total 15,776,582,180 25,324,844,335 9,548,262,155
c) Unreliable balances
As a result of uncoordinated operations/payments, the balances being reported by
the Solicitor General have not fully taken into account payments made by the
57
Ministry of Finance, Planning and Economic Development; details of variances are
shown below;
Table showing reported balances Court case Amount
Awarded - Ugx
Amount Paid by
MOFPED - Ugx
Expected Balan
ce - Ugx
Balance per MOJCA
- Ugx
Over statement - Ugx
C/S No.22/2001
21,294,000,000 8,488,185,200 12,805,814,800 21,294,000,000 8,488,185,200
C/S No.98/2008
6,018,427,774 3,171,794,441 2,846,633,333 4,200,000,000 1,353,366,667
C/S No.16/2009
44,760,128,000 15,700,289,135 29,059,838,865 35,000,000,000 5,940,161,135
Total 15,781,7
13,002 Under the circumstances, the cross vote payments will affect the validity of the
reported outstanding balances of court awards and compensations and may
eventually lead to overpayments. Besides, the reported payables both under
MOJCA and in the Consolidated Accounts were overstated by Ugx.15,781,713,002,
as a result of failure to reconcile the payments in question.
Non deduction of taxes
In accordance with Section 61 of the Income Tax Act, Cap.340 a compensation
payment derived by a person takes the character of the item that is compensated.
I noted that except for payments to one law firm, no taxes from interest earned,
legal fees, and compensation for loss of business were withheld from the other
payments as required by Sections 118 and 120 of the Income Tax Act. This could
be attributed to the fact that the Ministry of Finance did not have details of the
breakdown of outstanding amounts.
I have advised that whereas the letter from the Solicitor General sets out
responsibility, it is imperative that accounting mechanisms are put in place to
ensure that transactions are captured in both entities to reflect the correct
position. In addition, the Accounting Officer is advised to ensure compliance with
the provisions under the Income Tax Act, with regard to deduction of withholding
taxes, while effecting such payments.
3.3 Domestic Investment
A sum of UGX.1,928,989,607,673 is reported as the net worth for domestic
investments. I reviewed the accompanying schedule and noted that Entities with a
58
total net worth of UGX.249,298,051,082, had their net worth unchanged for the
financial years ending 30th June, 2013 and 30th June, 2014 as shown in the table
below. However I was not provided with evidence to confirm this position. It is
highly unlikely that such investments remained static for the two years. In the
absence of evidence to support this position, there is a risk that the balance for
domestic investments is misstated.
Table showing entities with unchanged Net worth
ENTERPRISE HISTORICAL COST - UGX
Net worth as at - UGX
30/6/2013 30/6/2014
GOVT. PARASTATALS ( 100 % HOLDING)
Post Bank Uganda Ltd 7,999,998,200 13,972,130,667 13,972,130,667
Uganda Electricity Transmission Co Ltd
61,229,404,597
(8,998,569,000)
(8,998,569,000)
Amber House 5,000,000,000 22,898,824,358 22,898,824,358
Uganda Printing and Publishing Corporation
3,542,271,000
7,305,996,584
7,305,996,584
Posta Uganda 19,487,176,000 22,428,287,000 22,428,287,000
National Medical Stores 12,932,830,091 22,447,283,000 22,447,283,000
Uganda Railways Corporation
39,989,832,000
73,721,730,000
73,721,730,000
National Enterprises Corp
42,336,083 21,507,069,815 21,507,069,815
Uganda Crane Industries
Ltd.
16,280,574,639
247,363,838
247,363,838
175,530,116,262 175,530,116,262
MINORITY SHAREHOLDING (LESS THAN 50% HOLDING )
Phoenix logistics (31/07/08)
5,097,599,190
2,333,706,820
2,333,706,820
Kinyara Sugar Works Ltd 3,000,456,160 66,818,850,000 66,818,850,000
LAP textiles Limited 2,405,378,000 2,405,378,000 2,405,378,000
71,557,934,820 71,557,934,820
PREFERENCE SHARES
Good Africa Coffee (20/06/08)
2,210,000,000
2,210,000,000
2,210,000,000
2,210,000,000 2,210,000,000
249,298,051,082 249,298,051,082
3.4 Un recognized Investment in M/S Victoria International Airways Ltd
In a letter dated 12th July, 2006 referenced EDP.73/100/01, the then Minister for
Finance requested the Solicitor General to make a capital injection of USD.250,000
59
into M/S Victoria International Airways Ltd (VIA Uganda) for purchase of shares in
the same company by the Government of Uganda. The funds were to be obtained
from the proceeds from the liquidation of the defunct Uganda Airlines Corporation,
in which the Registrar General was appointed as the official receiver. The Solicitor
General accordingly effected this payment, as per his letter to the Minister,
referenced ADM/11/158/01, dated 25th July 2006.
However, I noted that this investment is not reflected in the Treasury books of
account. There is no information pertaining to dividends (if any) that have been
remitted to GoU ever since the investment was undertaken and no record of
government representation on the Board of Directors. In the circumstances, there
is risk of Government losing this investment to the private owners of the airline.
Besides, the decision to acquire shares in a private company doing the same
business from which the Government was divesting at the time appears not to
have been properly evaluated.
In response, management explained that they did not have any information
pertaining to this investment. I have advised management to follow up this matter
and secure a share certificate for the investment, recognize it in the books of
account and obtain board representation.
3.5 Performance of loans
A review of the loan disbursements revealed that several loans appeared to be
performing poorly, with some nearing expiry, while others reached the closing
date without fully disbursing. Details are shown below;
Table showing performance of some loans Creditor Project Name Curren
cy Loan Amount
Disbursed % Disbursed
Date Signed Closing Date
ADF Road Sector Support project 4
AFU 72,940,000 - 0% 11/12/13 30/6/18
BADEA Urban Markets & Agric Products
USD 10,000,000 44,645 0% 16-Jul-09 30-Mar-15
GOVT. OF GERMANY
132 KV Double Circuit Tr. Line
EUR 15,000,000 -
0% 24-Oct-13 24-Oct-17
IDB CAIIP III IDI 5,210,000 0% 14-Jun-12 31-Dec-16
OPEC FUND Energy Dev't & Acces Expansion
USD 10,000,000 -
0% 29-Jan-13 31-Dec-16
SAUDI ARABIA
Rural Electrification
SAR 41,250,000 -
0% 13-Oct-11 30-Oct-14
60
Creditor Project Name Currency
Loan Amount
Disbursed % Disbursed
Date Signed Closing Date
FUND Project
ADF Supp. to Higher Education(HEST
AFU 67,000,000 882,987.25 1% 5-Jul-13 30-Jun-18
BADEA Rural Electrification Project
USD 10,000,000 51,770 1% 22-Jul-10 30-Sep-14
BADEA Nakaseke Technical Institute
USD 5,000,000 101,723 2% 28-Jun-11 30-Jun-14
IDB Specialized Mater. & Neonatal
IDI 14,080,000 321,843.84 2% 4-Apr-12 30-Jun-16
IDB National Educ Sup. Phase II
IDI 9,010,000 225,285.04 3% 30-Jun-11 31-Dec-15
IDB Rural Income & Employment
IDI 6,600,000 310,045.00 5% 22-Feb-10 30-Jun-14
IDB IDB-SMALL BRIDGES IN N.&NE UGA
IDI 7,000,000 391,999.32 6% 22-Dec-08 31-Dec-14
IDA Water Mgt & Dev't Project
SDR 87,100,000 6,425,496.65 7% 22-May-13 31-Dec-18
BADEA Line Of Credit-UDBL
USD 4,500,000 615,523.70 14% 12-May-09 31-Mar-15
JICA Electric Grids of Nile Equator
JPY 5,406,000,000
890,333,539 16% 26-Mar-10 1-Dec-17
ADF 3rd Community Agric Infrastruc
AFU 40,000,000 6,978,800.48 17% 10-Jun-11 31-Dec-16
BADEA N.NE Bridges USD 7,000,000 1,177,910.09 17% 20-Oct-05 31-Dec-14
KUWAIT FUND
KUWAIT FUND FOR UDBL
KWD 3,000,000 816,785.78 27% 22-Sep-10 30-Jun-15
IDB National Education Support
IDI 8,660,000 2,437,451.14 28% 24-Jun-10 31-Dec-14
OPEC FUND Vocational Education Project
USD 22,950,000 6,611,023.34 29% 23-Mar-10 31-Dec-14
ADF Kampala Sanitation Program 1
AFU 35,000,000 10,587,456.20 30% 11-May-09 31-Dec-14
ADF Interconnect Nile Elect Grids
AFU 7,590,000 2,362,395.70 31% 13-May-09 31-Dec-14
IDA 2nd L.Victoria Enviro Mgt Proj
SDR 17,600,000 8,571,811.09 49% 29-Oct-09 31-Dec-14
ADF Mbarara Nkenda Power Lines
AFU 52,510,000 29,767,184.98 57% 13-May-09 31-Dec-14
JICA Bujagali Interconnection Proj.
JPY 3,484,000,000
1,990,709.71 57% 30-Oct-07 21-Mar-15
Such low levels of performance undermine the attainment of planned development
targets and renders commitment charges paid in respect of undisbursed funds
nugatory.
Management explained that poor Loan performance is attributed to both internal
(GoU) and External (Creditor) factors. The major internal factors include
61
procurement challenges, compensation of third parties and lack of Land titles for
Large Infrastructure Projects. The main external factor is lack of legal and
regulatory framework to enable implementation of some Loans from the Islamic
development Bank. Government is fast tracking the Financial Institutions Act
amendment, to enable Islamic/Shariah Banking to operate. I have advised
government to identify and resolve any bottlenecks hindering the smooth
implementation of the above projects as well as explore ways of expediting the
processes so as to improve on service delivery.
62
4.0 MINISTRY OF FINANCE, PLANNING AND ECONOMIC
DEVELOPMENT
4.1 Mischarge of expenditure
The Government Chart of Accounts defines the nature of expenditures for each
item code. The intention is to facilitate better and consistent classification of
financial transactions and also track budget performance per item. A review of
records for the year under audit revealed that UGX.2,208,201,055 was charged on
items which do not reflect the nature of the expenditure incurred. This constituted
of 0.9% total expenditure for the Ministry. Mischarge of expenditure impacts on
the credibility of the financial statements since the figures reported therein do not
reflect true amounts expended on the respective items. It further impacts on the
appropriateness of the future budgets since the reported actual figures are
misleading.
Management explained that this was a result of the difference between Chart of
Accounts classification of expenditure items and Output Budgeting Tool (OBT).
While the newly passed Public Finance Act is based on outputs, the chart of
accounts has not been aligned to the new budgeting methodology.
I advised management to liaise with Treasury to align the chart of accounts to the
budgeting tool for appropriate reporting.
4.2 Un-supported Gross Tax payments
Gross tax payments made to URA are expected to be made against commitment
forms properly supported with import documentation and tax assessments. A
review of the underlying documentations revealed that UGX.1,114,667,735 was
not supported with import taxation documentation and URA tax assessments. In
the above circumstances, I was unable to confirm that the gross tax payments
were eligible.
63
I advised management to always ensure that payments from the gross tax
account are properly supported, otherwise funds are recoverable.
4.3 Gross Tax Payments for Non-Qualifying Items
As part of Government support to the Agriculture Sector value chain and in
particular the Textile sub-sector, Government was meant to pay VAT on imported
raw materials for the manufacturers of textiles. A review of a sample of payments
for import taxes on behalf of the textile beneficiary companies revealed that the
beneficiary company imported finished textiles (Bales 100 % polyester printed
fabric) worth UGX.1,659,611,200 and UGX.144 million was for goods described as
polyester bed sheets. This is contrary to the purpose for which the incentive was
established. Importation of printed fabric and bed sheets materials will not benefit
the local cotton farmers as had been intended. Ideally, to support the agricultural
sector, beneficiary companies ought to have been procuring all the cotton
ginned/produced in the country and not bringing in printed fabric. It was therefore
irregular for the Ministry to make such payments on these finished products
without carrying out due diligence.
I advised management to restrict tax payments to only raw materials as per
Government policy for the textile sub-sector. Management should initiate recovery
measures for all payments made in respect of semi and finished products (bed
sheets and printed fabric).
4.4 Un-supported tax payments for clearance of textile materials
According to the circular ref: EDP 81/137/05 by the Accounting Officer it was
indicated that for a company to qualify for the incentive of exemption of VAT
/import duty in the textile industry, they needed to present PAYE and NSSF returns
for verification of the minimal number of employees required, an investment
license from Uganda Investment Authority, among other requirements. However,
it was noted that UGX.980,735,024 was paid to URA in relation to taxes for textile
imports without proof that the above requirements had been fulfilled.
64
There is a risk that the objective of setting the above conditions was not achieved
and that the beneficiaries did not qualify.
I advised management to ensure that all beneficiary companies always provide the
required information as verified and cleared prior to making payments for the
incentives.
4.5 AGRICULTURE CREDIT FACILITY (ACF)
The Agricultural Credit Facility (ACF) was set up in 2009 by Government in
partnership with commercial banks, Credit Institutions and Uganda Development
Bank (the Participating Financial Institutions (PFIs) with the aim of providing
medium and long term loans to projects engaged in agriculture and agro-
processing on more favourable terms than usually available from Financial
Institutions. During the year, a sum of UGX.30bn was deposited by the Ministry of
Finance, Planning and Economic Development onto the ACF Escrow account for
onward remittance to the Bank of Uganda Capital Account. The memorandum of
Understanding (MOU) and progress report for the period ending September 2014
from Bank of Uganda were reviewed and the following noted:
a) Non-utilization of Agricultural Credit Facility
The escrow account held by the Accountant General‟s office in BoU closed with the
UGX.30 billion because these funds had not been transferred to the ACF capital
account as at 30th June 2014. The ACF capital account is an account where funds
released are held for onward disbursement to the Participating Financial
Institutions (PFIs). It was noted that a sum of UGX.16,507 million was held on the
ACF capital account un-utilized at the year-end. This implies that a total of
UGX.46.507 billion released for the ACF activities remained idle on the two
accounts during the year. The objective for which the funds were appropriated
and released may not be achieved.
Management explained that Bank of Uganda (BoU) disburses funds to the
Participating Financial Institutions (PFIs) with respect to only approved eligible
projects whose pace of flow depends on the PFIs. This project conception had
little input from BOU as a stakeholder but during implementation a number of
65
challenges existed that required a revision of the implementation policy and MOU
to ensure that there is adequate absorption of the funds.
I advised management to expedite the revision of the policy and MoU to address
the implementation challenges.
b) ACF GoU contribution
According to the financing MoU, Government was supposed to contribute UGX.30
billion annually and the Participating Financial Institutions (PFIs) were to match
the GoU contribution thereby creating a revolving pool of loanable fund amounting
to UGX.60 billion for eight years.
A review of Bank of Uganda Report for the period ending September 2014
revealed that capitalization of the fund by Government should have grown to
UGX.150 billion to date. However, government has to date remitted only
UGX.93bn to cover disbursements and commitments made since inception leaving
a shortfall of UGX.57 billion. Since Government is not fully meeting its stated
requirements as per the MoU sustainability of the facility may be tampered.
Management explained that although Government has not fully remitted the
budgetary allocations, BoU has not run out of funds for onward disbursement to
PFIs in respect of eligible borrowers. The slow pace of disbursements was due to
low absorption caused by failure by beneficiaries to meet the criteria for obtaining
the loan i.e. the criteria‟s put in place for one to obtain the loan were marked as
stringent for the targeted/potential borrowers as opposed to the currently
benefiting high level farmers.
I advised the Accounting Officer to renew the criteria in place and ensure that the
pace of absorption is improved. In the meantime GoU contributions should be
matched with the MoU for implementation as agreed.
c) Potential Loss of ACF borrowed funds
66
BoU report revealed that six projects that accessed farmer and agro processors
loans amounting to UGX.2,122,193,576 were classified as delinquent and been
forwarded to Bank of Uganda for writing off. Table below refers:
PFI Project Amount (UGX)
KCB Formula Feeds Ltd 1,314,411,429
KCB Pearl Mixed Farm 392,857,142
Tropical Bank Ltd Tom O‟lalobo 325,000,000
Centenary Rural Dev‟t Soroti Diary Ltd 48,019,341
DFCU Lira Integrated School 23,654,500
DFCU Bunya SACCO 18,251,164
Total 2,122,193,576
Unless adequate recovery measures are taken, Government risks losing the above
funds or even more if the current low recovery rate continues. It appears that the
appraisal by PFIs to ascertain viability, feasibility and eligibility by PFIs as one of
their roles was not properly undertaken.
Management should liaise with BoU to compel the PFIs to ensure proper due
diligence is done prior to issuing loans to save Government from losing money due
to the poor loan portfolio management on the part of the PFIs.
4.6 Un-supported utility payments
Section 181 of the TAI requires all vouchers to contain full particulars of each
service or goods and be accompanied by such supporting documents as may be
required so as to enable them to be checked without reference to any other
documents. However, it was noted that UGX.415,192,655 paid to National Water
and Sewerage Corporation was not supported with tax invoices and
acknowledgement receipts. I was therefore unable to ascertain that the payments
were actually made to the utility company.
I advised management to make a follow up of the acknowledgements with NWSC.
4.7 Budget Performance Review
Analysis of budget performance indicated that some planned activities were not
fully performed despite the entity receiving 97% of its budget.
67
Output 140301 – Accounting and Financial Management Policy,
coordination and monitoring
Under this activity, it had been planned to conduct (12) audits of foreign missions
and (2) IT audits. However, only one mission audit was achieved and no IT
reviews were conducted.
Management explained that because of resource constraints, this activity was
dropped. The IT audits were not carried out because of inadequate capacity. The
Ministry is now undergoing restructuring to provide for IT auditing.
I advised management to expedite capacity building undertakings and have the
audits carried out.
Output 140156 Lottery Services
It had been planned to collect UGX.2bn from the National Lottery as government
share on the Lottery collections. However, it was noted that only UGX.0.08bn was
collected leading to a shortfall of UGX.1.92bn. It had also been planned to procure
an electronic monitoring system to monitor Lotteries, Gaming and Pool Betting for
enhanced monitoring of revenue generation by URA and the Lottery Board. This
too was not achieved.
Management explained that this was due to loopholes in the prevailing law that
illegal operators exploited to set up illegal lotteries that were in direct competition
with the National Lottery (NL). This curtailed the National Lottery collection.
Regulations have since been put in place to strengthen the weak law. Meanwhile
illegal Lotteries are being phased out.
Funds for the electronic monitoring system were not provided and the system
could not be procured. This procurement had been budgeted for UGX.400m. The
procurement has been included among unfunded activities for the Ministry BFP of
2015/16.
68
I advised management to secure the resources and have the electronic Monitoring
System in place. I also advised management to address the weaknesses in the
current law to guide the operations of National Lottery Board.
Output: 140103 - Capitalization of Financial Institutions
The Ministry had planned to disburse a total of UGX.16 billion as Graduate Venture
Capital during the year however no disbursements were made. Failure to achieve
all planned activities may negatively affect the Ministry performance and
achievement of its strategic objectives.
Management explained that the funding for Graduate Venture Capital was
transferred to Ministry of Gender by Parliament when approving the final budget
for FY 2013/14.
4.8 ENTERPRISE UGANDA: Funding gap
Enterprise Uganda (EU) is a public entity duly registered and constituted according
to the Laws of Uganda with the objectives among others to work with Government
to promote Government policies, directives and programmes. EU envisages Micro,
Small and Medium Scale Enterprises (MSMEs) as important vehicles for expanding
production, providing self-employment and generally enhancing economic growth
in the country. This is in line with the government objective of enhancing the
quality and availability of gainful employment and uplifting the standards of living
in households.
During the year, EU had budgeted to receive Government support of
UGX.2,410,000,000 but only UGX.2,199,375,000 was released which is 91.26%
leading to a budget shortfall of UGX.210,625,000. Despite the shortfall in
Government releases, audit appreciates that most of the planned activities were
achieved. I noted that during the year, EU had planned to train a total of 5,000
participants both rural and urban households and equip them with skills to
start small enterprises. However, it was noted that 4,768 (95.36%) were
trained in the districts of Wakiso, Tororo, Kayunga and Kiruhura. 322
intended participants were not trained. I urged management to liaise with the
69
Ministry of Finance, Planning and Economic Development to source for sufficient
funding to meet its budget plans. This was attributed to the funding gap.
4.9 RURAL FINANCIAL SERVICES PROGRAMME
The Rural Financial Services Programme (RFSP) supports the Rural Financial
Services Strategy (RFSS) which is one of the pillars of the Prosperity for All (PFA)
vision of government, which aims at ensuring that every economically active
Ugandan earns some basic income, through production, marketing and agro-
processing of products. This programme ended in December, 2014 and a review
of the activities for the financial year 2013/2014, revealed the following:
a) Lack of proof of ownership of motor cycles
The Government through RFSP put in place rural development strategy and
availed funds to be used to equip SACCOs with kits which include money safes,
filing cabinets, bicycles, salaries for staff and office rent. Under this arrangement
through a grant, 188 motor cycles were distributed to SACCOs to facilitate them in
form of transport. Accordingly, RFSP officials were paid allowances worth
UGX.10,480,000 to enable verification of transfer of ownership of these motor
cycles from UCSCU to beneficiary SACCOS. However, it was noted that by the time
of audit (December, 2014), only (36) motor cycles had been transferred to the
SACCOS leaving with the balance still in the names of UCSCU. Delay in transfer of
ownership may result in costs to UCSCU in case accidents or other eventualities
happen.
Management attributed the delay to lack of Tax Identification Numbers by SACCOS
but RFSP has guided them on how to register with URA.
I advised RFSP management to expedite the transfer process. b) Assets - Verification of assets provided to support SACCOs
During the closure of the project, management of RFSP carried out verification of
the assets register to validate data for update. At the end of the exercise, a
verification report was produced. The following was observed from the report:
70
Oribicin SACCO
Oribicin SACCO had been reportedly closed because of failure to pay back loans
worth UGX.78,000,000 which was borrowed by the former SACCO Chairman who
also later passed on. However, it was noted that there was no documentation to
indicate the status of the assets such as money safe, filing cabinets and bicycles.
The possibility of recovery of these assets appears remote.
Gulu Municipal and Bufunjo SACCOs
The asset verifications report also indicates that Gulu and Bufunjo SACCOs had
been closed because of mismanagement of funds by their respective Boards and
management; although this was not quantified. It was noted that the where about
of the motor cycle for Bufunjo and the kits for Gulu municipal SACCO were yet to
be established. There is a possibility that they could have been stolen or being
used for non-SACCO related activities.
Management explained that both cases have been forwarded to the department of
Cooperatives, and the respective District Cooperative offices to revamp or turn
around the activities of the SACCOs. It is only after the turnaround activities have
failed that the SACCOs will be liquidated.
I advised management of RFSP to provide a clear status report regarding the
assets of the above SACCOs.
c) Un-sustainable strategy of strengthening of the Apex Institutions
By the closure of the RFSP project, Uganda Cooperative Savings and Credit Union
Limited UCSCU), the implementing partner had established (15) regional offices in
the four regions of the country as had been targeted. However, it was noted that
with the project support coming to an end, UCSCU downscaled the regional offices
from (15) to (4) (Northern, Western, Eastern and Central). Only a few field liaison
officers were employed in the rest of the regions for increased efficiency in the
utilization of resources.
Under this arrangement, there is a risk that UCSCU may not provide services to
the SACCOs on a sustainable basis.
71
Management explained that Government has made provisions for providing
additional technical and financial support to UCSCU in order to ensure that UCSCU
becomes sustainable in the next five years, as per the revised UCSCU business
plan. This commitment is contained in the Loan agreement and Aide Memoirs
signed between IFAD/GOU.
The outcome of the above commitment is awaited.
4.10 THE POPULATION SECRETARIAT (POPSEC)
The population secretariat (POPSEC) is a semi-autonomous department under
Ministry of Finance Planning and Economic Development (MOFPED) established
under The National Population Act, 2014 responsible for the implementation of the
policy decisions of the National Population Council and promote the integration of
population factors in development planning at the national and lower levels in
accordance with the agreed frame work under the National Development Plan.
The following observations were made.
a) Lack of National Population Council
The population Secretariat (POPSEC) developed a five year National Population
Action Plan (NPAP) in 2010 giving National Population Council the key role of
providing strategic direction. Consequently, Parliament passed the National
Population Council Act on July 23rd 2013 and assented by H.E. the President on
January, 6th 2014. However, it was noted that the National Population Council had
not been established at the time of writing this report. This may negatively affect
policy formulation and strategic guide on the implementation of the objectives of
POPSEC.
Management explained that POPSEC was advised by the First Parliamentary
Counsel that the Act will be operational after full registration.
I urged management to liaise with the responsible authorities to ensure that the
National Population Council is urgently established.
72
4.11 TAX APPEAL TRIBUNAL
a) Un-resolved tax disputes
The tribunal had planned to resolve 100 tax disputes countrywide during the year
but only 90 cases were resolved leaving a balance of 10 tax disputes outstanding
at the year-end.
The registrar Tax Tribunal explained that the 10 outstanding disputes were filed
towards the end of the financial year and could not be completed before the year
end. These cases have however been carried forward.
I urged management to always ensure that planned targets are attained and
timely.
b) Failure to conduct planned circuit sessions
According to the annual budget performance, the tribunal had planned to conduct
circuit sessions (regional case hearings) in the regions of Mbale, Gulu, Mbarara
and Arua. The objective of conducting circuit sessions was to take tribunal sittings
to the regional offices to encourage and enable up-country tax payers lodge and
have their cases arbitrated upon within the respective localities. The circuit
sessions were not conducted.
Management explained that full circuits could not be held due to a shortfall in
funding. The outstanding upcountry disputes were carried forward.
I advised management to ensure that the implications for failure to conduct the
above activity are properly highlighted in the next budget to enable its funding.
4.12 NON-PERFORMING ASSETS RECOVERY TRUST (NPART)
a) Stalling of the Winding up Bill
The Non-Performing Assets Recovery Trust Act (NPART) was enacted on 10th
October 1994 and was to run for a period of (3) years. However, it was noted that
73
the NPART Act has been extended by Parliamentary resolutions for a number of
times, the last extension being the period ending 9th October 2007.
In view of the above, it was noted that the Act has served its purpose and it was
time to wind-up the trust and repeal the Act. However, it was noted that passing
of the bill (winding up) appears to have stalled since October, 2007.
This in turn has delayed the achievement of the winding-up bill of repealing of the
NPART Act, winding up of the affairs of the Trust, The Sinking Fund and the
Tribunal and transfer to Government of all assets.
Government continues to spend money on NPART without any legal basis as its
mandate has long expired without any further renewals. For instance, a total of
UGX.249,999,999 was released during the year out of which UGX.141,905,060
(56.76%) was spent on employee costs alone.
Management explained that the bill was presented to the committee of the cabinet
which made recommendation for the Ministry‟s action. The Act has been edited
and ready for submission to the cabinet.
I urged management to continue liaising with the relevant authorities to expedite
the passing of the bill.
b) Un-spent balance not returned to Treasury
Section 19(1) of the Public Finance and Accountability Act provides that any
unspent balance at the close of the year shall be repaid to the consolidated fund.
According to the cashbook presented for audit, NPART had un-spent balance of
UGX.20,032,804 at the year-end which was not returned to the UCF as required
by the regulation.
Management explained that the instruction to transfer the funds was bounced by
BoU and the matter has been forwarded to Accountant General to direct BoU to
return the money to the UCF.
The outcome of the above management action is awaited.
74
4.13 PRESIDENTIAL INITIATIVE ON BANANA INDUSTRIAL DEVELOPMENT
(PIBID)
a) Failure to return un-spent funds to the Consolidated Fund
According to the Internal Audit and Inspectorate report for financial year
2013/2014, PIBID project had un-spent funds to a tune of UGX.4,259,043,697 as
at 30th June, 2014. However, the amount was not returned to the Consolidated
Fund account as required. The funds were retained and utilized during the year
without authority from the Accountant General and the Permanent
Secretary/Secretary to the Treasury.
Management explained that the funds were meant to pay for machinery for the
Banana Plant from an International Company based on Germany whose contract
had not been finalised by close of the year. The contract was only signed on 10th
July 2014 and request to hold money was made to PS/ST on 11th July, 2014.
However, no response was received. The funds were finally spent in the
subsequent year 2014/15.
b) Doubtful fuel consumption
UGX. 90,018,707 spent on fuel was not supported by fuel requisition vouchers
indicating the purpose, motor vehicle movement log book justifying fuel usage and
activity reports confirming occurrence. In the above circumstances, the
expenditures appear doubtful.
Management explained that all payments for fuel are effected through a fuel
company. Noted variances during the reconciliation are effectively adjusted and
reflected in the subsequent remittances.
As a way forward, management explained that it will always ensure that the
reconciliations are regularly and timely done as this will easily enable identification
of discrepancies and allow a fast correction of anomalies.
75
4.14 IRISH AID SUPPORT TO GENDER & EQUITY BUDGETING (EDUCATION
SECTOR AND KARAMOJA SUB-REGION)
(a) General Standards of Accounting and Internal Control Systems
It was noted that management had complied in all material respects with the
financing agreement and GoU financial regulations except for the following matter:
i) Retention and expenditure of funds after suspension of the project
As at 17th July 2013, the project had total available funds of UGX.65,571,546
composed of un-spent project funds worth UGX.30,384,506 and UGX.35,187,040
refunded to the bank account being funds for activities not undertaken.
In July 2013 the donors suspended project funding following the financial scandal
at Office of the Prime Minister. It was noted that the funds were retained and
spent after the suspension period. The authority from the development partners to
retain and spend these funds was not sought.
Although management explained that the funds were spent because the
development partners did not object to the continued payment of project staff
salaries from the available balance, I was not provided with communication to this
effect.
I advised management to always seek authority prior to spending project balances
after closure of the projects.
4.15 FINANCIAL MANAGEMENT AND ACCOUNTABILITY PROGRAMME
(FINMAP)
(a) Compliance with programme financing agreement and government
financial regulations
The Programme complied with the covenants with Programme agreement and
Government Financial Regulations except for the following matters;
i) Statutory Deductions
76
It was noted that there were instances where withholding taxes were not
deducted from some payments made to suppliers of goods and services yet these
suppliers were not exempted from withholding tax. Examples of such payments
were as follows;
Company Name Amount
UGX
Withholding Tax
UGX
Comments
Inline Print
Services
9,524,567 571,474 Tax not withheld
Hotel Brovad 70,692,000 4,241,520 Tax not withheld
Com Events
Coalition
34,080,000
2,044,800
“
Adventcity Ltd 7,265,440 435,926 “
Innovative
Furniture Ltd
10,576,001
634,560
“
Kabu General
Agencies
18,940,000
1,136,400
“
Total 9,064,680
Non compliance with all the provisions of the Income Tax Act could lead to heavy
penalties and interest being imposed on the project by the relevant authorities.
Management explained that there was an oversight especially because the IFMS
did not deduct automatically. The providers in question were still working with
FINMAP and the taxes would be recovered from the next payments.
I advised management to ensure that all the provisions of the tax laws were
complied with in order to avoid associated penalties and interest.
ii) Delayed project activities
My review of the project budget for the year indicated a number of project
activities that were not carried out as planned by the end of the year. These
include the following:
77
Code Activity
Delayed activities‟
Budget ( UGX)
Management response
1.1.1.2 Training of users of
IMEM
55,323,360 The IMEM was not yet
finalized and hence training
could not be programmed.
1.2.1.2 Conduct consultative
stakeholder
workshops and
disseminate final
report analyzing
national revenue
base
91,310,400
A more comprehensive
internal study to analyze the
current tax system with a
view towards generating
revenue enhancement
measures for FY 14/15 was
conducted instead, and a
report has been compiled
and disseminated.
2.1.1.1 Undertake
consultancy for the
automation of the
system
107,424,000
The procurement process for
the consultancy to develop
the OBT was delayed
following a decision to fund
and procure the activity
through the mainstream GoU
budget and procurement
modalities respectively
2.3.1.1 Undertake
consultancy for the
review of the
GoU/MTEF
134,280,000
The review of the GoU/MTEF
was placed on hold pending
further policy guidance by
top management on how to
proceed
3.1.1.3 Procure IFMIS audit
tools and conduct
security related
training
1,074,240,000 The procurement was held
back by the delays in the
finalization of the security
audit and its attendant
recommendations.
78
Code Activity
Delayed activities‟
Budget ( UGX)
Management response
3.1.4.1 Undertake a
consultancy to
develop noncurrent
assets module of
IFMIS: conduct
related user training
and change
management
sessions
174,606,970 It was resolved that the
development of the non-
current assets module be
included in a (subsequent)
contract with Oracle for post
IFMS upgrade technical
support.
3.1.5.1 Set up the system
application: conduct
ICT trainings, and
procure licenses
268,560,000 The activity was put on hold
pending the successful
upgrade of the IFMS to
version 12.
3.1.6.6 Disaster recovery site
set up and tested
18,595,094 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
4.1.1.2 Conduct monitoring
of implementation of
RAM, hot and cold
reviews
27,574,000 This was due to operational
delays in the
commencement of the RAM
training.
4.1.1.1 Acquire forensic tools
for the Unit‟s lab
490,226,738 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
4.1.4.1 Acquire ERA licenses
for 30 staff
136,294,200 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
79
Code Activity
Delayed activities‟
Budget ( UGX)
Management response
4.1.5.1 Conduct training for
30 internal audit
staff
14,502,240 Un-anticipated delays in the
procurement of the
software.
4.1.6.1 Conduct hands on
training for IA staff
in Quality Assurance
120,852,000 The activity was re-
programmed to the next FY.
4.1.7.1 Undertake Quality
Assurance reviews
and specialized
training for
supervision and
inspection staff.
120,852,000 The activity was re-
programmed to the next FY.
5.1.1.2 Conduct pilot of
Alternative Energy
Sources for IFMIS in
LGs
268,560,000 None of the bidders were
identified to have the
requisite experience and
competence for the activity,
which has now been
postponed to next FY.
5.1.1.8 Conduct post
implementation
change management
sessions at 26 Tier 2
sites +6 Tier 1
rollout undertaken
338,385,600 Un-anticipated delays in the
processing of the funds for
the activity.
5.1.1.9 Conduct basic ICT
trainings for new
users at the IFMIS
LG sites at 26 Tier 2
sites +6 Tier 1
rollout
295,416,000 Un-anticipated delays in the
processing of the funds for
the activity.
80
Code Activity
Delayed activities‟
Budget ( UGX)
Management response
5.1.3.1 Engage consultancy
to roll out IFMIS Tier
2 solution to 13 LG
sites
4,748,140,800 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
5.1.4.1 Review the LG Act to
clarify the
jurisdiction of
parliament and the
LGPAC
40,284,000 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
5.1.4.2 Conduct capacity
building for
members of the
LGPACs and their
support staff on
LGPAC
67,140,000 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
5.1.4.3a Conduct capacity
assessment for the
LGPACs targeting
committee members
and support staff,
Design capacity
building programme
123,537,600 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
81
Code Activity
Delayed activities‟
Budget ( UGX)
Management response
5.1.4.3b Conduct capacity
assessment for
LGPACs targeting
Conduct capacity
assessment for the
LGPACs targeting
committee members
and support staff,
Design capacity
building programme
(task force)
24,170,400 Un-anticipated delays in the
processing of the funds for
the activity arising in large
part from delayed
disbursement of funds by
development partners..
6.1.2.3A PFM Advisor
recruited (by 1 Jan
2014)
241,704,000 A decision was taken not to
proceed until further notice.
6.1.3.1 Undertake take
consultancy for the
road map for the
integration of
Accounting and
Budgeting systems.
107,424,000 This activity was placed on
hold following a policy
directive that this activity
would be led (under FINMAP
III) by the new department
of MIS in the Accountant
General's Office (AGO), in
collaboration with NITAU.
6.1.2.2 Acquire and
disseminate IEC
materials to enhance
staff capacity and
public awareness on
accountability.
61,768,800
There were no related
activities that were initiated
by the component
6.1.3.1 Commission studies,
benchmarks and
reviews of PFM
implementation
93,996,000
There were no related
activities that were initiated
by the component
Total
9,245,168,202
82
Code Activity
Delayed activities‟
Budget ( UGX)
Management response
3.1.5.1 Set up the system
application: conduct
ICT trainings, and
procure licenses
268,560,000 The activity was put on hold
pending the successful
upgrade of the IFMS to
version 12.
3.1.6.6 Disaster recovery site
set up and tested
18,595,094 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
4.1.1.2
Conduct monitoring
of implementation of
RAM, hot and cold
reviews
27,574,000 This was due to operational
delays in the
commencement of the RAM
training.
4.1.1.1 Acquire forensic tools
for the Unit‟s lab
490,226,738 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
4.1.4.1 Acquire ERA licenses
for 30 staff
136,294,200 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
4.1.5.1
Conduct training for
30 internal audit
staff
14,502,240 Un-anticipated delays in the
procurement of the
software.
4.1.6.1
Conduct hands on
training for IA staff
in Quality Assurance
120,852,000 The activity was re-
programmed to the next FY.
83
Code Activity
Delayed activities‟
Budget ( UGX)
Management response
4.1.7.1 Undertake Quality
Assurance reviews
and specialized
training for
supervision and
inspection staff.
120,852,000 The activity was re-
programmed to the next FY.
5.1.1.2 Conduct pilot of
Alternative Energy
Sources for IFMIS in
LGs
268,560,000 None of the bidders were
identified to have the
requisite experience and
competence for the activity,
which has now been
postponed to next FY.
5.1.1.8 Conduct post
implementation
change management
sessions at 26 Tier 2
sites +6 Tier 1
rollout undertaken
338,385,600 Un-anticipated delays in the
processing of the funds for
the activity.
5.1.1.9 Conduct basic ICT
trainings for new
users at the IFMIS
LG sites at 26 Tier 2
sites +6 Tier 1
rollout
295,416,000 Un-anticipated delays in the
processing of the funds for
the activity.
5.1.3.1 Engage consultancy
to roll out IFMIS Tier
2 solution to 13 LG
sites
4,748,140,800 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
84
Code Activity
Delayed activities‟
Budget ( UGX)
Management response
5.1.4.1 Review the LG Act to
clarify the
jurisdiction of
parliament and the
LGPAC
40,284,000 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
5.1.4.2 Conduct capacity
building for
members of the
LGPACs and their
support staff on
LGPAC
67,140,000 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
5.1.4.3a Conduct capacity
assessment for the
LGPACs targeting
committee members
and support staff,
Design capacity
building programme
123,537,600 Un-anticipated delays in the
procurement process, arising
in large part from delayed
disbursement of funds by
development partners.
5.1.4.3b Conduct capacity
assessment for
LGPACs targeting
Conduct capacity
assessment for the
LGPACs targeting
committee members
and support staff,
Design capacity
building programme
(task force)
24,170,400 Un-anticipated delays in the
processing of the funds for
the activity arising in large
part from delayed
disbursement of funds by
development partners..
6.1.2.3A PFM Advisor
recruited (by 1 Jan
2014)
241,704,000 A decision was taken not to
proceed until further notice.
85
Code Activity
Delayed activities‟
Budget ( UGX)
Management response
6.1.3.1 Undertake take
consultancy for the
road map for the
integration of
Accounting and
Budgeting systems.
107,424,000 This activity was placed on
hold following a policy
directive that this activity
would be led (under FINMAP
III) by the new department
of MIS in the Accountant
General's Office (AGO), in
collaboration with NITAU.
6.1.2.2 Acquire and
disseminate IEC
materials to enhance
staff capacity and
public awareness on
accountability.
61,768,800
There were no related
activities that were initiated
by the component
6.1.3.1 Commission studies,
benchmarks and
reviews of PFM
implementation
93,996,000 There were no related
activities that were initiated
by the component
Total 9,245,168,202
Unless project activities are carried out as planned, the intended purpose of the
project may not be achieved.
I advised management to endeavor to set project milestone and deliverables for
specific periods so as to track project performance and progress.
(b) General Standard of Accounting and Internal Control
A review was carried out on the programme system of financial management and
it was noted that management had instituted adequate controls to manage
programme resources.
86
4.16 SIDA SUPPORT TO COMPETITIVENESS INVESTMENT CLIMATE
STRATEGY (CICS) PROJECT
(a) Compliance with the SIDA/GOU Financing Agreement Provisions
and GOU Financial Regulations
It was noted that management complied with the covenants contained in the
financing agreement and Government of Uganda Financial Regulations except for
the following instance:
i) Lack of authorization to spend UGX.47,010,645
Article 4 Section 5 of the agreement required that funds transferred to Uganda for
purposes of a project and not utilized by 30th June 2013 shall be repaid to Sweden
within three months of that date. It was noted that out of the balance carried
forward from the previous (UGX.47,010,645) UGX.46,176,200 was spent without
seeking for authority/objection from donors contrary to the financing agreement. I
explained to management that this was a deviation that may result in poor donor
relations in case there is need to engage in other future financing agreements.
Management explained that the funds were already committed towards SIDA –
CICS Secretariat activities. After payment of the activities a balance of
UGX.834,445 was left on the account which balance will be returned to the
development partners as per the agreement.
I advised the project coordinator to ensure compliance with financing agreement
with regard to authority for retention and expenditure of un-spent balance after
the project closure.
(b) General Standard of Accounting and Internal Control
A review of the following areas was carried out:-
Accounting system and policies.
Book keeping.
Management and control of both bank and cash accounts.
Purchases and payments.
Fixed assets management.
87
It was noted that management‟s control structure environment, accounting system
and policies and control procedures were generally adequate to ensure prudent
use of, and accountability in the project.
4.17 RURAL FINANCIAL SERVICES PROJECT
(a) Delayed implementation of field activities
While the annual work plan and budget for the closure period activities was
finalised on 14 June 2013 and approval for the same obtained from IFAD through
a no –objection notice on 4 July 2013, the program closure activities were
scheduled to have been completed and paid for by 31 December 2013. I noted
that there were some program activities totalling UGX.25,871,247 that were not
fully completed by the end of the year and were therefore carried forward to 2014.
These include external audit costs, vehicle maintenance costs, validation and field
work costs.
The delay in completing project activities had a spill over effect on other closure
activities like the finalisation of program reports. This may have resulted into a
diversion of funds to other uses other than those for which the funds were
approved.
Management explained that almost all programme activities were carried out and
closed off. Those that were not closed off were contractual in nature and were
not settled in time due to the shortcoming in the system.
I advised management to ensure that in future program activities are implemented
on a timely basis.
5.0 DIRECTORATE OF ETHICS AND INTEGRITY
5.1 Mischarged Expenditure-UGX.275,372,736
The Parliament of Uganda appropriates funds in accordance with the needs of the
country and this appropriation is implemented through the budget in which funds
are tagged to particular activities and outputs using account codes and MTEF
codes. A review of the Directorate‟s expenditures revealed that the entity charged
88
wrong expenditure codes to a tune of UGX.275,372,736. The practice is contrary to
the intentions of the appropriating authority and leads to incorrect financial
reporting.
The Accounting Officer attributed this to inadequate budget on some codes and
yet work had to proceed. Management also attributed the problem to the de-
linkage between IFMS and output budgeting.
I advised management to undertake realistic budget and whenever necessary
request for reallocations or virements, as provided for under the TAI. I also
advised management to contact the Accountant General to resolve the de-linkage.
5.2 Funding gap-UGX.181,598,834
According to the statement of appropriation account based on services voted by
Parliament, the Directorate had budgeted to receive transfers from treasury worth
UGX.5,404,295,598 however, UGX.5,219,309,500 was received, creating a funding
gap of UGX.184,986,098. The shortfall directly affected the settlement of
outstanding commitments of UGX.265,071,856 brought forward from the prior
year.
The Accounting Officer explained that the PS/ST had been requested to provide
explanation for the funding gap but no response had been received.
I advised management to continue liaising with Treasury for purposes of ensuring
that the appropriated resources are released.
5.3 Vacant positions
A review of the Directorate approved structure/establishment indicated that
whereas 59 posts were approved, only 46 had been filled by the year-end leaving
14 vacant posts unfilled. The most affected departments were the information
center and the legal department as indicated in the table below.
Post Tile Approved Filled Vacant Salary
Legal Department
89
Commissioner Legal Services 1 0 1 UIE
Legal Officer 2 0 2 U4
Information Center
Principal Information Scientist 1 0 1 U2
Communications Officer 1 0 1 U3
Information Scientist 3 2 1 U4
Lack of such essential staff may negatively impact on the entity's service delivery.
The Accounting Officer explained that the delay in recruitments was caused by
lack of the Public Service Commission in place, but the requests have now been
submitted to the commission for action.
I advised management to liaise with the responsible authorities and ensure that
the key vacant posts are urgently filled.
90
WORKS AND TRANSPORT SECTOR
6.0 MINISTRY OF WORKS AND TRANSPORT
6.1 Payment of Consolidated allowances- UGX.2,444,859,353
During the year, a total of UGX.2,444,859,353 was paid out in gross consolidated
allowances to staff contrary to the requirements of Public Service Standing Orders.
I noted that there was no authority to pay such allowances on top of salary
already paid. In the circumstances, I could not confirm the regularity of the
quarterly consolidated allowances.
In response, the accounting officer explained that payments were effected to
motivate staff since their salaries were considered very low.
I advised the accounting officer to seek authority from ministry of public service or
have if officially regularized.
6.2 Mischarge of Expenditure
Expenditure totaling to UGX.48,153,093 was inappropriately charged on budget
lines to fund activities that were not planned and without authority. I explained to
management that mischarge of expenditure translates into misrepresentation of
expenditure balances in the financial statements. The practice is also not in line
with the intentions of the appropriating authority.
In response, the Accounting Officer acknowledged that challenges exist in
matching GoU budgeting principles that are driven by Output Based objectives,
Public Finance Management best practices and generally acceptable accounting
principles.
I advised management to liaise with the Accountant General with a view of
streamlining the budget process and also ensure that sufficient funds are allocated
to key account areas. Should there be need for reallocation, authority for the
virement should be sought before any reallocations are undertaken.
91
6.3 Budget Performance
a) Funding Gap
During the review, I noted that the Ministry budgeted to receive
UGX.119,061,202,859 out of which a sum of UGX.91,677,910,743 was received
translating into a 77% out-turn for the financial year. This left a funding gap of
UGX.27,383,292,116. The gap affected the implementation of planned activities
for year as summarized below;
Departments
/Directorate
Planned activities not completed
Transport
Regulation
32 bus operator licenses not processed; 10% Bus routes not monitored.
Coordination office for aircraft accident investigations not
established.
Capacity of the Air Transport Regulation division to regulate the aviation not developed.
Transport
services and
infrastructure
Procurement of rehabilitation and upgrade of railway wagon ferry MV Pamba not done;
Progress on the upgrade Kampala Kasese railway line delayed. No progress on the New Ferry to replace Kabalega –Opening
Southern Route.
92
Departments
/Directorate
Planned activities not completed
Construction
standards and
quality
assurance
9 reports on materials testing, quality control and research on construction materials not produced.
Compliance to set engineering standards 49 MDAs not fully
monitored.
Environment and social impact assessment reports on two Development projects prepared not done;
The National Building Review Board (NBRB) was not appointed
and the secretariat not established.
Contractor for the outstanding Phase 2 works at Kyabazinga‟s Palace not fully paid.
Procurement of Moisture testing filed equipment and Mobile
Lab testing equipment not done.
Environmental Audits on on-going projects not conducted.
Training of 40 Local Government staff in RAMPS not conducted.
District, urban
and
community
access roads
Computerized Vehicle Maintenance management system (CVMMS) not developed.
85 drivers not tested and certified.
4 supervision vehicles for the Regional Mechanical Workshops of Bugembe, Mbarara, Gulu, including Chief Mechanical workshop not procured.
Rehabilitation of selected office blocks and workshop facilities of Gulu, Mbarara, and Bugembe Regional Mechanical Workshops not achieved.
Policy,
planning and
support
services
The planned 127 staff were not recruited. Monitor the 20,000 km of the National Roads network in 72
Districts not accomplished.
Consultant to carry out a study for the establishment of a Maritime was not achieved;
Consultant to develop boat building standards not procured.
93
Failure to release the budgeted funds to the Ministry affected implementation of
the planned activities which affects fulfilment of the ministry‟s mandate in the long
run.
I advised management to ensure that the matter is always followed up during the
year with the Ministry of Finance, Planning and Economic Development to ensure
all the budgeted funds are released to the Ministry.
6.4 Grounded motor vehicles
Inspection of Works premises revealed that the Ministry had 105 grounded motor
vehicles in different locations. Out of the 105; ten (10) vehicles were in private
locations as shown below;
S/No. Reg. No Make / Type Location
1 UR0182 14oktober Wheel Loader Bwanda Covent Masaka
2 UG0822W Caterpillar Wheel Loader Kapchorwa T.C
3 UG790W Mitsubishi Dumper Truck Kira T.C
4 UG791W Mitsubishi Dumper Truck Kira T.C
5 UG0805W Sakai Pneumatic Roller Kira T.C
6 UG0836W Bomag Vibro Roller Kira T.C
7 UW0865 Bomag Pneumatic Roller Kira T.C
8 UW0173 Ford Bitumen Truck Kira T.C
9 UG0787W Caterpillar Wheel Loader Sunset Garage- Mengo
10 UG0035W Nissan Pick Up URRU
I noted that most of the vehicles have been grounded for more than 4 years and
some were in a very bad shape as reflected in the sample pictures taken in the
photographs below;
94
Grounded Vehicle at MELTEC-
Mbale
Other vehicle Parts loaded
on a grounded vehicle at
Kireka Materials testing
A grounded car packed
under a shade of a
building at transport
Licensing Board grounds.
The grounded vehicles continue to deteriorate in their economic value due to
depreciation arising from the long stay without maintenance. In response, the
Accounting Officer explained that vehicles were relocated and lined for boarding
off.
I advised management to expedite the boarding process with a view to avoiding
further deterioration of the vehicles.
6.5 Inspection
As part of the audit, inspection and audit of the Ministry upcountry stations and
other operational areas including the Institutions under the control of the Ministry
were carried out and below are the findings;
a) Mbarara Regional Mechanical Workshop i. Grounded Tractors
Physical inspection of the mechanical workshop showed that there were three
tractors belonging to different districts as shown in the table and picture below;
Tractor Details Date received in
workshop
Owner district
LG0002-42 Tractor Massey Ferguson 28/07/2010 Rukungiri District
LG0020-21 Tractor Massey Ferguson 04/02/2010 Kisoro District
LG0045-62 Tractor Massey Ferguson 01/06/2011 Isingiro District
95
The three tractors in the workshop belonging to the 3 districts stated above.
I noted that the tractors have been in the garage for over three years and their
long stay in the garage could have hampered the work at the districts. Besides,
there was no proper explanation why the tractors were not repaired and taken
back to their respective districts. Some parts of the tractors were found
disjointed.
In response, management explained that the tractors have been in the garage for
over 3 years but this arose from Uganda Road Fund (URF) failure to fund the
Regional Mechanical Workshops (RMWs). Some repairs have been done but once
the necessary funds are secured, the major repairs will be carried out.
I advised management to expeditiously repair the tractors and have them taken
back to the respective districts for use.
ii. Office sharing
I noted that the Mbarara Mechanical Workshop regional offices were housed in
two office blocks that belong to Ministry of Works. The block has four office rooms
of which two are occupied by Ministry of works and the other two by Ministry of
Local Government. The lower office block has 12 office rooms. 5 rooms were
occupied by Ministry of works; Diary Development Authority occupied 4 rooms
while Ministry of Agriculture occupied 3 office rooms. The following was noted;
There was no evidence of Memorandum of Understanding or tenancy
agreements signed between the Ministry of Works and other Government
Agencies/ Ministries. I could therefore not get the terms and conditions of
occupancy which translates into loss of NTR to Government.
96
It was not clear how other services in the blocks such as power, water,
security, office cleaning and compound maintenance were handled among the
occupants.
Interview with Workshop management showed that the building was renovated
by the Ministry of Local Government under un-clear terms. I could not establish
how much was paid for the service and under what terms the Ministry of Local
Government did the repairs.
In the circumstances, I could not rule out the possibility of loss of revenue.
In response, the Accounting officer explained that the arrangement of sharing
between MAAIF, MoLG and MoWT has been in place since 1989. The Ministry is
formalizing the relationship with the two entities through a memorandum of
understanding. This will cover extensively on sharing and payment of power,
water, security, office cleaning and compound maintenance.
I advised the accounting officer to ensure the terms of occupancy are clearly
defined. Management was also advised to expedite the MoU arrangements
streamlining use of government structure.
b) East African Civil Aviation Academy
i. The Academy Legal Status
The East African Civil Aviation Academy (EACAA) is a centre of excellence in
aviation training for the region that was revived by the East African community
whose awards are recognized by the education regulations all over the world.
EACAA was established in September 1971 as the East Africa Civil Aviation Flying
School of excellence under the Directorate of Civil Aviation (DCA) of the East
African Community (EAC), with Government of Uganda, EAC and the United
Nations Development Programme and the International Civil Aviation Organization
UNDP/ICAO as the main contributors. While GoU upgraded the Soroti Airfield
runway from grass surface to asphalt, EAC financed the construction of the school
buildings, staff housing and navigation facilities as well as providing the
administration staff and some technical personnel like counterpart instructors, Air
97
traffic controllers and Meteorologists. East African Airways provided the bulk of
counterpart flying and engineering instructors.
During the audit, it was observed that the Institution operates more like a
department under MoWT, headed by a director who reports to the Permanent
Secretary. I noted there was no legal framework that supports the operations of
the Academy under Ministry of Works.
The academy did not produce final accounts. I noted that there is no reporting
frame work/basis that is well defined for independent preparation of final accounts
as the legal frame work is no clear. In the circumstances, I could not appraise fully
the operational results of the Academy.
In response; the Accounting Officer explained that the Ministry is discussing with
Public Service to operationalize the Academy operations and its possibilities of
becoming autonomous.
The outcome of the above commitment is awaited.
ii. Staffing gaps
A review of the Academy staffing structure as at 1st November 2014 revealed that
the Academy had 76 approved positions. However, out of the approved posts, only
54 (71%) positions were filled leaving 22 posts (29%) not filled. Specifically, I
noted the following issues under the two departments.
iii. Flying School Department
The three top most positions of Chief Flying Instructor, Principal Flying Instructor
and the Senior Flying Instructor were not filled which puts the operations of the
school at risk of failing to achieve its mandate.
iv. Works and Estates Section
The Position of Senior Assistant Engineering Officer (Civil) was not filled. The
unfilled post is too critical that a gap could have negative effects on the entity‟s
service delivery.
98
In response, management explained that the existence of vacancies in the
technical posts was mainly due to challenges in attracting suitable candidates
owing to the poor remuneration offered by the Academy compared to the market.
The low salary was also a cause for the high turnover however effective 1st July
2014, the salaries of the technical staff were enhanced and a new salary structure
for the technical staff of the academy was issued.
I advised management to continue following up the matter with the relevant
authorities to ensure the posts are filled for improved service delivery as the legal
status of the academy is being resolved.
v. Grounded aeroplanes
Inspection of the aeroplanes revealed that out of eight aeroplanes that the
academy had only two (5X-UAN and 5x LWE) were operational. The other six were
grounded as shown as in the table below;
S/N Registration number Reason for being grounded.
1 5X-ELG Engine overhaul.
2 5X –CEA Engine overhaul
3 5X-UWD Major Frame overhaul.
4 5X –VIC Accident that damaged the tail part
5 5X-KYO Engine problem and propeller.
6 5X-SRI As a result of getting an accident.
I explained to management that the grounded aeroplanes negatively impact on
the operations of the Academy. There is a risk that if maintenance of these planes
is not given priority assets may deteriorate further.
I advised management to plan and have all the aeroplanes repaired so that they
are put back to use.
c) Gulu Regional Mechanical Work Shop
99
The following was noted during the inspection of the workshop;
i. Shared offices and Workshop Yard between Gulu Regional
Mechanical Workshop and UNRA - Gulu Station
During the review, I noted that the Gulu regional mechanical office premises are
shared by both Gulu Regional Mechanical Workshop and UNRA-Gulu Station and
the following anomalies were noted;
There was no evidence of Memorandum of understanding signed between the
two entities for co-existence in the same premises.
Although the two entities each had its own water meters and electricity
meters, the service bay and the parking yard were still shared. I explained to
management that the shared service bay could cause inconvenience in case
both entities have repair works at the same time.
Both of the two entities‟ grounded and running vehicles were mixed up in the
parking yard with no demarcations and as a result the park yard space was
getting congested.
It was not clear as to which entity was responsible for maintenance of the
shared parking yard and the security of the premises.
I explained to management that there is a possibility of duplicate payments for the
same services leading to loss of Government funds.
In response, management explained that a draft Memorandum of Understanding
to clear the misunderstanding was prepared and forwarded to Solicitor General for
advised.
The outcome of management effort is awaited.
d) Kireka Division of Materials Testing And Research
The Division of Materials Testing and research falls under the department of
Construction Standards and Quality Management in the Directorate of Engineering
and Works, in the Ministry. The division is mandated to provide technical
(engineering) services to the entire Construction Industry in the Country; through
among others testing of construction materials to ascertain their suitability and
100
compliance to standards, offering advisory services on quality of construction
materials, and conducting research on construction materials and technologies.
Inspection of the division premises revealed the following;
i. Inadequate Funding
During the year, the division had budget estimates of UGX.4,275,651,000 for both
wages and non- wages, however, a review of the Ministry‟s performance for year,
showed that UGX.2,805,233,000 (66%) was spent on wages and official activities
of the Division. Funds totalling to UGX.1,470,418,000 were not released to the
division hence crippling the activities of the division. I noted that this affected
mainly monitoring and development of policies, guidelines and strategies. I
explained to management that in view of the growing construction industry in
Uganda, there is need for increased monitoring and development of standard
guidelines/policies to enhance quality of construction materials.
In response, the accounting officer explained that during the year, the budget was
partially funded by MOFPED and recurrent activities were therefore scaled down to
fit within the funds released.
I advised the Accounting Officer to liaise with Ministry of Finance Planning and
Economic Development and ensure funds releases are improved to allow the entity
to enforce monitoring for enhanced quality of standards.
ii. Staffing Gaps
At the time of inspection (December 2014), the division had 46 (68%) vacancies
filled and 25 (32%) unfilled against the approved establishment of the division of
70 vacancies. I noted that some of the unfilled vacancies were senior positions
that included the two Principal Engineers. I explained to management that staffing
gaps of this magnitude impacts negatively on the operations and activities of the
Ministry. There is a risk that the Unit could fail to attain its mandate.
In response, management explained that all the posts were cleared by Ministry of
Public Service for filling; and the vacant posts were finally advertised.
101
Management anticipates that in 2015 the ten (10) Civil Engineers will be recruited
and absorbed in the division.
I await the outcome of management‟s commitment.
iii. Lack of Essential Laboratory Facilities/Equipment
I noted that at the division, vital equipment and chemicals were lacking for its
effective laboratory and field operations. Interview with management showed that
the unavailable equipment and chemicals included;
Set of drilling rig for geotechnical investigations;
Digital steel testing equipment for testing steel products;
Geo- physical soil testing equipment for foundation soil investigations;
Assorted structural integrity testing equipment (non – destructive tests)
Road pavement condition survey equipment and
Assorted chemical reagents.
I explained to management that lack of essential equipment and chemicals is a
serious hindrance to the attainment of the Ministry mandate and its objectives.
In response, management explained that the procurement of essential laboratory
equipment and chemicals is always limited by lack of adequate funds in the
budget. Once the funds are available, the position will improve. Other possible
means of re-tooling the laboratories is being pursued e.g. through support from
Development Partner.
I advised management to take up the matter with Ministry of Finance for adequate
funding so as to purchase the necessary equipment and chemicals. I urge
management to continue pursuing the development partners for funding.
iv. Inadequate transport equipment
The division has got six upcountry laboratories at Arua, Gulu, Mbale, Jinja,
Mbarara, and Fort portal. However, inspection of the four (4) available vehicles
allocated to the division showed that only one pickup was in fair running condition
while the others were constantly breaking down and grounded. I explained to
102
management that inadequate transport could affect execution of field activities of
the division.
In response, the accounting officer explained that the Ministry acquired new
Vehicles from which one was allocated to the Department and indicated that the
process of rationalizing the usage of the available fleet of Vehicles is on-going.
I await the outcome of the above commitment.
v. Lack of Monitoring and Supervision from the Ministry Head
quarter
During the review, I noted that the Division hardly receives any team from head
Office to carry out supervision and monitoring of the division activities. I explained
to management that frequent monitoring and supervision of the activities carried
out at the division would enhance productivity of the division.
In response, the accounting officer explained that monitoring and supervision
mechanisms have been put in place to ensure proper coordination of all activities
in the Ministry which include holding regular meetings, reporting, and spot
checking of departmental activities and operations.
I advised management to implement the supervision and monitoring mechanisms
put in place for effective service delivery.
vi. Laboratory equipment not labeled
Physical inspection of the division laboratories revealed that the chemical
containers and laboratory apparatus and equipment were not labelled for quick
identification, safe custody and to avoid a mix up of materials. There is a risk of
using a wrong chemical on an experiment that could easily produce inaccurate and
unproductive test results. Besides, the equipment may easily get lost through
theft.
In their response, management explained that all laboratory equipment have serial
numbers and the equipment details are usually recorded and kept as part of the
store‟s records at the time of receipt/acquisition. Chemicals and Reagents normally
103
have labels on their containers for ease of identification. However management
acknowledged that unique marking of the laboratory facilities would reinforce the
record keeping system which is hoped to be undertaken when funds are secured.
I await the outcome of management‟s commitment.
e) Inspection of Okokorio And Agule Ferry Landing Sites on Lake
Bisina
Okokorio and Agule Ferry Landing sites are located on Lake Bisina in Katakwi and
in Kumi Districts respectively. MOWT contracted two (2) Local companies to
construct the Landing sites. A consultant was also procured to supervise the
construction of both sites on behalf of the Ministry.
The funding for the above works was from the Prime Minister‟s office in 2008. In
last year‟s audit; it was noted that while the Pontoon ferry was delivered at CME
(Ministry or Works and Transport) at a cost of Euros.1,502,000 and a consultant
engaged, the construction works for the landing sites and approach roads had not
commenced by end of the year and this resulted in UGX.5,245,466,352 to lie idle
on the deposit account.
During the financial year under review; a total of UGX.2,844,237,389 was paid for
the construction of landing sites and UGX.2,401,228,963 was committed awaiting
the consultants advise. Below is a summary of inspection findings;
f) Inspection of Okokorio ferry landing site - Katakwi district
The contract price for the construction works was agreed at UGX.2,230,878,835.
The contract commencement date was 3rd April 2013 and at the close of the
Financial Year, the Ministry had paid three (3) Interim Payment Certificates
totalling to UGX.1,094,248,185. During inspection of the landing site on the 17th of
October, 2014 I noted the following;
(i) The project was behind schedule as the scheduled completion date had been
set for 2nd January 2014. There was no evidence that the liquidated
damages was being charged.
104
(ii) The contract conditions require that the site Engineer prepares the Site Diary
which details the dairy activities carried out on the site. The site Diary is
signed by the Site Engineer and is certified by the Resident Engineer who is
a permanent representative of the Ministry of Works and Transport on Site.
However, I noted that the hard copy of the site Diary that is required to be
certified by the Resident Engineer was not prepared. This short coming
raised doubt on the Interim Payment Certificates (IPC) that were raised by
the Resident Engineer and eventually paid by the Ministry.
(iii) The Consulting firm that is responsible for supervision of the construction did
not have a permanent staff on site.
(iv) The site Engineer confirmed that whenever he comes up with technical
challenges or technical issues to consult, he rings the Resident Engineer who
is based in Kampala and who sends the Clerk of Works that issue out
instructions to the site Engineer on site. The Clerk of Works last issued
instructions to the Site Engineer on the 6th October, 2014 a sign of
inadequate supervision.
There is a risk that the contractor could do shoddy work due to inadequate
supervision and works may be delayed. Delayed works come with challenges that
range from increased costs and supervision.
In response, management explained that the delay was due to flooding in the
project area which necessitated the review of the design to cater for low and high
level docking. These are compensation events which will be evaluated when the
final account is prepared and if found necessary liquidated damages will be
charged. Management further explained that the poor performance of the
consultant led to shoddy works and accordingly the Ministry has withheld payment
to the consultant pending further evaluation. The Ministry instructed the contractor
to correct defects at his own cost. Management has also constituted an in-house
team to complete the works.
105
I advised management to increase its supervision role and ensure that the defects
are corrected within the agreed timelines.
g) Inspection of the landing site- General findings:
i. The Docking area
Inspection of the docking areas showed that the activity was coming to a
completion except for the access road to the docking area that was not yet
completed as per the picture below:
Incomplete access road to the docking area
The construction of the ferry has delayed.
In response, management explained that the Ministry team has been constituted
to complete the outstanding works and the assembling of the ferry has already
been directed to begin at the Site.
I urged management to monitor the construction works closely and ensure the
works are concluded.
ii. Poorly constructed sideways of access road to the docking area
The sideways of the access road to the docking area were not dug to the bed of
the Lake. The work was on-going and the sideways were being supported by the
installed Gabions. There is a possibility that the Access road will be washed away.
See the pictures below;
106
Poorly constructed sideways of access Road
Incomplete parking yard above. The parking yard should be covered with
stabilized Mar rum
Completed passengers shade.
In response, management explained that the contractor has been instructed to
correct all the observed defects. On the issue of covering the parking area, the
Ministry has put in place the team to complete outstanding works which will
include laying of pavers on the stabilized surface, fencing of the area, gabion
works and handrails. The outcome of the above commitment is awaited.
iii. Failure to implement the original plan of the Okokorio ferry
landing site
Review of the plan of the Okokorio Ferry Landing site showed that some activities
included in the original plan were excluded from the contract. These included; the
servants‟ quarters residence, the Administration Block and the Water treatment
Plant which were all not built. I explained to management in case the above
essential activities are not done, this will affect operations of the ferry services in
future.
In response, management explained that at the time of contract packaging, the
items were found non-essential and were not included in the Bills of Quantities.
However the passenger shade has been re-modelled to include an office as well as
residence. Furthermore; it was explained that rain water harvesting facility was
put in place to provide adequate water for domestic use.
107
I advised Management to revisit the contract and ensure that the activities agreed
on be undertaken.
h) Inspection of Agule Ferry Landing Site on Lake Bisina in Kumi
district
The MOWT contracted a Local company to construct Agule Ferry Landing site at a
contract price of UGX.1,653,530,183. The contract commencement date was 1st
Sept.2012 and the planned completion date was set for 31st May 2013. At the
close of the Financial year, the Ministry had paid five (5) Interim Payment
Certificates totaling to UGX.1,452,564,020.The Landing site was inspected on 17th
Oct, 2014 and below are the findings;
(i) The contractor is behind schedule by more than 2 years and at the time of
audit; there was no evidence that liquidated damages were being charged.
(ii) The construction procedures and guidelines require that the site Engineer
should prepare the Site Diary which details the dairy activities carried out on
site. The site Diary is signed by the Site Engineer and is certified by the
Resident Engineer who is a permanent representative of the Ministry on Site.
However, the Site Manager never had a copy of the site Diary that should
have been certified by the Resident Engineer. He claimed it was with the
Site Engineer who was not at the site. This short coming raised doubt on the
Interim Payment Certificates (IPC) that were raised by the Resident Engineer
and eventually paid by the Ministry.
(iii) A review of the Visitors book and interview with the Site Manager revealed
that the Resident Engineer representing the consultant last visited the Site
on 02nd November 2013, in the presence of an Engineer representing the
Ministry of Works. There was no evidence that the contract for the
supervising consultant was terminated. There is a risk that the resident
engineer could have abandoned the site and hence shoddy work could easily
go undetected and the contractor paid all his dues.
108
In response, management acknowledged that the project was behind schedule
mainly due to flooding in the project area which necessitated the review of the
design to cater for low and high level docking. These are compensation events
which will be evaluated when the final account is prepared and if found necessary,
liquidated damages will be charged. Management admitted that the performance
of a Consultant was not satisfactory and stated that the Ministry has withheld
payment to the consultant pending further evaluation. An in-house team to
complete the works has now been constituted.
I await the outcome of management‟s commitment.
i) Inspection of the landing site - General Findings;
i. Lack of a sign post
The Contractor has not yet installed a sign post as evidence that it is the company
constructing the site, and indicating that the Consulting firm and the Ministry are
funding the construction.
ii. Lack of an office at the construction site
The contractor does not have an office at the site.
iii. Completed Docking Area
Inside view of the completed passenger shade.
The inside part of the passenger shade was
completed but seats in the middle of the
shade were not constructed.
Completed six stances latrine
The six stance latrine was completed but
lacked the handles along the carriage
way to the latrine.
109
Incomplete parking yard.
The parking yard is supposed to be
covered with stabilized mar rum that is
not yet done
In response management explained that the seats in the middle of the shade and
the handles along the carriage way will be fixed as extra works.
I advised management to ensure the remaining works is completed to ensure
safety of passengers.
iv. Failure to implement the original plan of the ferry landing site.
A review of the plan of the Agule Ferry Landing site showed that some activities
included in the original Plan were excluded from the Contract. These included the
servants‟ quarters residence, the Administration Block and the Water treatment
Plant that had not been constructed. There is a risk that the essential activities not
undertaken may affect operations of the ferry services when it begins operations.
In response, management explained that at the time of contract packaging, the
items were found non-essential and were not included in the Bills of Quantities.
However the passenger shade has been re-modelled to include an office as well as
residence. Furthermore; rain water harvesting facility was put in place to provide
adequate water for domestic use.
I advised management to ensure all the above issues are handled to avoid ferry
service interruptions.
6.6 Transport Licensing Board (TLB) Operations
a) Review of Performance - In land water Transport Vessels
110
One of the functions of the transport licensing Board (TLB) is to carry out
Inspection and licensing of Inland Water Transport Vessels under the Inland Water
Control Act (1939) and to conduct periodic Inland Water Transport Vessel
inspection and licensing at the various landing sites on the lakes and navigable
sections of River Nile. A review of this function showed that a smaller number of
vessels were licensed compared to the available operating vessels during the year
which translates into failure to collect revenue from the operating vessels. There
was no evidence that all the vessels were licensed as there was no data base for
all the operating vessels.
There is a possibility that unworthy vessels may continue plying water routes
endangering the lives and properties of sailors.
In response, management explained that the number of vessels inspected and
licensed was lower than those plying different inland waterways. This has been
caused by a number of factors listed below;
Capacity gaps due to ceiling of required personnel; the Ministry has engaged
Ministry of Public Service to address the gap during the restructuring exercise.
The e-Tax platform is not very convenient for boat owners to pay for their
licences. Most landing sites where these boats are found have no banking
facilities or reliable internet.
Most of these landing sites are remote areas with poor network coverage
which makes it hard to use the e-tax platform.
Management further explained that though enforcement by use of patrol is
sometimes insufficient; this option will be improved through coordination.
I advised management to ensure all the functions of the TLB are implemented.
b) Limited Storage Space for Important Data
Traffic and Road Safety Act section 71 (2) requires that; the Board shall furnish to
the Minister once in every year a list of routes and packages of routes covering the
whole of Uganda, selected and assembled so as to provide transport services to
meet reasonable passenger demand and which will be reasonably efficient and
111
economic either as listed singly or otherwise for both large and small prospective
operators. However during the review, I noted that the Board has data relating to
statistics for granted routes for buses that is manually stored and bulky but has
got limited storage space. I explained to management that there is a possibility of
data getting misplaced and or mixed up causing unnecessary delays in retrieving
of data needed for operations.
In their response, management acknowledged that most data on granted routes
for buses is still manually kept but indicated the Ministry will initiate a procurement
for a consultant to design a software package that stores all these records
including records for all Passenger Vehicles Inspected and Licensed. Procurement
of computers to be used by this software is in advanced stages. The Ministry has
also put in place a Transport Data Management System to store all the data for
the sector.
I await the outcome of management‟s commitment.
c) Lack of adequate Office space for Operations
Physical inspection of the TLB offices showed that the Board has limited space
compared to the nature of operations that requires attending to the general public
most of the time. I noted that the Board has various sections each carrying out a
specific activity however; there is limited space for operations such as inspection
of long vehicles like Buses. Below is a picture of clients waiting to be served and
TLB offices clearly reflecting the shortage of space.
TLB clients waiting outside due to limited
space inside the assessment office
Main Block Office at TLB which
accommodates office of the Secretary to
the Board, Accounts Section, and the
reception.
112
Despite the challenge; I noted that the Office of the Prime Minister (OPM) stores
some food relief in one of the oldest structures behind the TLB offices that further
congests the premises occupying the limited space where other vehicles for
inspection would be packed. It was not clear under which terms the OPM uses
such a store and besides, the structure is too old and does not seem to be fit for
storing food and or valuables. I explained to management that limited space for
buses creates a bad image and doubt as to whether thorough tests are carried
out. I also explained to management that Limited space may easily accelerate
inefficiencies.
Management responded that indeed the office space at TLB was insufficient
however, construction is on-going for a new office block which will also act as a
Maritime Administration block. The Ministry has also written to the OPM to relocate
their store in order to provide more space for vehicle inspection. The procurement
of a firm to provide motor vehicle inspection services is in advanced stages which
will also relieve the problem of lack of space for vehicle inspection.
I advised management to plan and address the above challenge for enhanced
efficiency.
d) Lack of reliable vehicles for field activities
Physical inspection of vehicles used by TLB while carrying out field operations
revealed that the current fleet of vehicles used by the Board was not mechanically
sound and this hinders the major field activities such as inspection and licensing of
passenger Service Vehicles (PSVs), monitoring bus operations and safety
sensitization campaigns for both water and road transport. There is a risk that
such poorly maintained vehicles could cause accidents while carrying out field
work.
Management explained that that at the time of audit inspection, vehicles allocated
to TLB were in a bad condition hindering TLB activities however, the Ministry has
113
since allocated a brand new pick up as part of the general pool and also initiated
procurement for the repair of the existing vehicles.
Management action on the matter is awaited.
e) Review of Computerized Driving Permits operations
As part of the review, the computerized driving permits project was inspected
focusing on the effectiveness of the process of acquiring a driving permit and the
control environment. One activity of Printing and Issuing of Driving Permits to
establish the effectiveness of internal controls regarding printing and issuing was
sampled and the following limitations were noted;
a) Lack of Data Recovery Center
b) Lack of Computerized Archive
c) Lack of an efficient interface between URA and Face Technologies Ltd.
There is a risk that in case of fire or any disaster the available data could get
destroyed. The ministry has not backed up the data to date.
In response, management explained that the Ministry has finalized the
procurement to establish a Data Recovery Centre and the related works have
commenced. For the computerized archive, it was explained this was due to the
fact that partly some functions both administration and management of driving
permits were done by URA. The files were therefore sent from URA to MoWT and
thereby forming a backlog at the registry. The process of computerizing the
archives has been budgeted for in the financial year 2015/16.
I advised management to work out modalities of establishing a Data Recovery
Center to ensure issuance of driving permits is not hugely interrupted due to
unforeseen challenges at the main facility.
f) Lack of Water Transport Standards/operational guidelines/policy
The Inland Water Control Act (1939) Section 3 requires that every person applying
for a license for the carriage of passengers or goods by ship shall submit to the
Board; particulars of the type or types and numbers of ships to be used,
114
particulars of the construction, motive power and cargo capacity of every such
ship, the total number of crew to be carried in every such ship, the number of
passengers every such ship is intended to carry, the places between which the
ships are intended to be navigated and the services to be provided by the ships.
However during the review; I noted that the Ministry has no standards/guidelines
in place to guide the operations of the water transport. I explained to
management that lack of standards could lead to unforeseeable challenges
including loss of lives and revenue to Government.
Management explained that Uganda is a member of the International Maritime
Organization (IMO) and as such is required to follow standards and guidelines
issued by the IMO such as the International Convention on the Safety of Life at
Sea (SOLAS) and the International Convention on Marine Pollution. Management
indicated that it will come up with standards and guidelines to guide the user.
I advised management to ensure standards/policy guidelines are put in place to
guide transport operations on water.
6.7 EAST AFRICA TRADE AND TRANSPORT FACILITATION PROJECT (EATTFP)
(a) Compliance With The Financing Agreement And Government Of
Uganda Provisions
Project Management complied in all material respects with the provisions in the
agreement and GoU regulations except in the following matter;
(i) Unreleased Budgeted Project Funds (IDA & GOU)
Analysis of budget for the year showed that the Project expected funding from IDA
and GOU to a tune UGX.894,846,000 and UGX.11,910,000,000 respectively.
However, I noted that only UGX.14,227,175,761 was received from IDA and
UGX.2,357,076,832 from GOU translating into 45% performance of the total
budgeted funds for the year as summarised in the schedule below;
Details Budgeted
Amount
Actual Receipts Variance Remarks
115
IDA Funds 24,894,846,000 14,227,175,761 10,667,670,239 43% of funds not
applied for
due to the
low rate of
absorption.
GOU funds 11,910,000,000 2,357,076,832 9,552,923,168 80% of the budget
not funded.
Total 36,759,845,000 16,584,252,593 20,220,593,407
Funds totalling to UGX.9,552,923,168 (26 % of the total budget) from GOU was
not released to the project. Low absorption capacity coupled with the non-release
of funds from GOU affects implementation of the planned activities and could lead
to unnecessary project extension costs.
Management explained that the unreleased funds from GOU had been budgeted
for taxes that were finally waived by Ministry of Finance as at 30th June 2014 while
the slow disbursement of funds from IDA was a result of delayed completion of
works for Malaba OSBP and Mukono Railway ICD (Inland customs Department).
I advised management to take up the matter with appropriate authorities for
purposes of obtaining adequate funding and enforce monitoring to ensure project
activities are completed as scheduled.
(b) General Standard Of Accounting And Internal Control
A review of the project financial management system was carried out and it was
observed that management had instituted adequate controls to manage project
resources.
(c) Project Implementation
(i) Inspection of construction works at One Stop Border Posts
(OSBP)
I inspected four OSBPs at Katuna, Mutukula, Mirama, Busia, Malaba and Mukono
ICD was carried out between the 24th August and 5th September 2014.
It was noted that works at all the OSBPs and Mukono Railway ICD were behind
schedule despite several requests to have the project extended.
116
Specific observations at each inspection site are as below:
BUSIA OSBP
The construction of Busia OSBP at a contract sum of UGX.15,898,641,294 was for
a period of 12 months. Works commenced on 29th August 2013 and was to be
completed on 28th August, 2014. At the time of inspection, the agreed time period
had expired and the construction works were far behind schedule. At the time of
reporting, the progress of works was estimated at 60% and the contractor had
provisionally been given the extension up to end of December 2014. Such delays
have an effect on project performance.
In response, management explained that some major works could not commence
due to the need to keep the border operational. Management further indicated
that there was a funding challenge for extra works which were omitted at the
bidding stage yet the works were essential for OSBP operations. These include
purchase and installation of fire-fighting equipment, Generator and Stabilizer,
borehole, relocation of the national fiber optic cable, and extension of truck
parking yard. The cost variation to cater for the above extra works was estimated
at about UGX.2 billion and that TMEA was soliciting for the funds.
I advised management to liaise with the PS/ST and IDA on the matter and have
the extra works urgently funded to avoid any delays and costs associated with
project extension.
MALABA OSBP
The construction of Malaba OSBP was agreed at a contract sum of
UGX.15,708,759,579 to be completed within 12 months effective 29th August
2013. The expected date of completion was scheduled to 28th August, 2014
however, this period had expired before completion of works. At the time of
inspection, works were estimated at 75% completion. As at the time of reporting,
I noted that management had not secured a “No Objection” for the project
extension from the IDA. Non completion is likely to extend the project life further.
117
In their response, management explained that the Contractor‟s performance was
affected by delayed relocation of URA customs office and delayed construction of
exit road by UNRA. The Ministry applied for an extension of the IDA credit in
March 2014 however, the extension has not been secured. Management has
continued to work with the contractor to achieve practical completion of major
works by the credit closure date of 30th September 2014. Presently, the average
physical progress of works at Malaba is estimated at 94% and full completion will
be achieved by end of November 2014.
I advised management to seek for an extension and have the construction
finalized.
MUTUKULA OSBP
The construction of Mutukula OSBP commenced on 6th September 2013 at a
contract sum of UGX.18,793,900,201. The expected date of completion was 5th
September 2014, however, at the time of inspection, the expected date had
expired yet a substantial amount of work had not been done. Delayed completion
of works has greatly affected the performance of the project.
Management explained that the contractor‟s underperformance was a result of
partial site possession by the contractor due to land disputes with Project Affected
Persons which caused a design review/alteration in the project area; delayed
relocation of Government border agencies (Immigration and Police); additional
excavations due to marshy soil; and less mobilization by the contractor.
However, the above issues have been resolved and the average physical progress
of works was presently at 60% completion. The contract was also extended to 2nd
December 2014 to enable the contractor complete all outstanding works.
I advised management to monitor the contractor closely and ensure that the
works are completed within the extended timelines.
KATUNA OSBP
The construction of Katuna OSBP at a contract sum of UGX.8,951,277,750
commencement on 13th June 2014 and was estimated to be completed on 13th
118
June, 2015. At the time of inspection, the contractor had completed demolishing
of the existing structures preparing the site for construction works to commence.
It was evident that works may not be completed at the set period.
I advised management to ensure close monitoring so that the project is completed
on schedule.
MIRAMA HILLS OSBP
The Construction of OSBP at Mirama Hills at a contract sum of US $ 7,817,703.32
commenced on 4th July 2013 and the revised completion date had been set for
19th September 2014. At the time of inspection, the extension had expired and
the physical progress of works achieved was estimated at 70%. Delayed
completion of works affects border post operations and could lead to unnecessary
project extension costs.
Management explained that the slow progress was attributed to the Supervision
Consultant who is based in Nairobi where decisions and instructions are taken;
contract administration differences with former Project Architect which caused
delays in procurement of materials and processing of documents/payments;
additional scope due to demolitions and bulk excavations; heavy rains in South
Western Uganda and low mobilization by the Contractor. Management indicated
that the above issues have now been resolved and the average physical progress
of works had reached 80%. Consequently, the contractor was given up to end of
December to complete all outstanding works. The contractor has also been served
a notice to charge liquidated damages.
I advised management to enforce the provisions of the contracts and ensure that
the contractor speeds up the works at the border posts to avoid escalation of
contract costs.
MUKONO ICD
The Construction of proposed Railway Inland Container Depot (ICD) at Mukono by
an international construction company at a contract sum of US $ 8,688,120,112
commenced on 10th December 2012 and was expected to be completed on 10th
December 2013 but was later revised to 9th June 2014. At the time of inspection,
119
the constructions were estimated at 50% completion way below expected
performance. As explained earlier, delays are likely to affect the project
performance and time extensions.
Management explained that the contractor‟s underperformance was caused by
among others; partial site possession due to disputes between Uganda Railways
Corporation (URC) and Mukono District Council over the ownership of existing
warehouses that was later resolved in July 2014; death of the Contractor`s site
engineer in December 2013; and increased scope of works on the office block and
container platform.
However, all the above challenges were resolved and extension sought from the
financiers to the end of December 2014 and the average physical progress of ICD
works was presently estimated at 85% completion. It was further indicated that
the contractor has been served with a notice to charge liquidated damages.
I advised management to increase suspension and monitoring with a view of
having the construction completed within the extended time period.
120
JUSTICE LAW AND ORDER SECTOR
7.0 MINISTRY OF JUSTICE AND CONSTITUTIONAL AFFAIRS
7.1 Mischarge of Expenditure – UGX.615,047,805
The Parliament of Uganda appropriates funds annually in accordance with the
needs of each MDA. This appropriation is implemented through the budget in
which funds are tagged to particular activities and outputs using account and
MTEF codes.
A review of the Ministry‟s payments revealed that there were mischarges under
various codes during the year under review, totalling to UGX.615,047,805. These
payments were made without requisite authority. The practice undermines the
budgeting process and the intentions of the appropriating authority. The practice
also leads to financial misreporting.
The Accounting Officer explained that the practice is regrettable, and they are
working towards eliminating it.
I advised the Accounting Officer to streamline the budgeting process and ensure
that funds are allocated to budget lines in accordance with priorities. Any
reallocations should be undertaken in accordance with the regulations.
7.2 Outstanding Commitments – UGX.442,173,233,469
The Ministry of Justice and Constitutional Affairs had accumulated outstanding
commitments totaling UGX.442,173,233,469 as at 30th June 2014. The outstanding
commitments comprised of court awards and compensations UGX
440,484,898,505, unpaid rent, UGX 976,958,385, withholding tax UGX 11,998,536
and other obligations UGX 699,378,043.
The outstanding commitments position rose from UGX.164,163,005,576 at the end
of the previous year to UGX.442,173,233,469 at the end of the current financial
year, (169% increase). It is important that government examines the causes of
these losses with an objective of minimizing them.
121
It was further noted that there are delays in settling claims which are likely to lead
to the accumulation of unpaid Court awards and compensations and other claims
to unmanageable amounts. The delayed payments may also lead to penalties in
interest and other related charges.
The Accounting Officer explained that the cause of the accumulation is due to
inadequate funding and lack of instructions from line Ministries when they have
committed the offence. The Accounting Officer promised to meet the Ministry of
Finance, Planning and Economic Development to discuss the minimization of
accumulation of Court awards and also avoid delays in payment. The Accounting
Officer also suggested other alternatives such as devising means of settling court
awards, holding meetings and conducting workshops with some of the entities
concerning their obligations, as well as advocating for transfer of settlement of
liabilities to the responsible MDAs.
I urged the Accounting Officer to continue with dialoguing with a view of
minimizing court awards and compensations.
7.3 Court awards and compensations
a) Rise in Contingent Liabilities – UGX.4,295,304,082,625
During the year, contingent liabilities rose from UGX.541,554,003,100 to
UGX.4,295,304,082,625 as per the Statement of Contingent Liabilities as at 30th
June 2014. This indicates a 693% increase in this category of liabilities. This
situation is untenable and likely to create an additional burden on the public
resources.
The Accounting Officer explained that the contingent liabilities include only the
filed suits and excludes intentions to sue. He further explained that the figure of
UGX.4,295,304,082,625 provided in the contingent liabilities is for the most
probable cases that may be lost.
There is need for Government to examine the issue further with a view to
establishing the likely causes in order to facilitate Government to arrive at a
sustainable solution.
122
b) Budgeting for Court Awards and Compensations
I noted that whereas the Court awards and compensations have continued to
accumulate over the years, budget allocations and releases have not improved to
cover the obligations. The table below shows the Court awards and compensations
at the end of each year, subsequent budgets and releases made to settle the
obligations:
No Financial
Year From
Outstanding
Amount at start
of Year (UGX.)
Approved
Budgeted
Amount Year
(UGX.)
Amount Paid
(UGX.)
1 1st July 2012 54,009,997,832 4,346,998,000 20,746,165,234
2 1st July 2013 82,342,100,818 4,346,998,000 5,361,160,000
3 1st July 2014 164,163,101,576 4,347,324,000 8,500,551,991
From the analysis, it is clear that insufficient funds have been budgeted and
released to cover the outstanding amount over the years. This has partly caused
the accumulation of the arrears.
The Accounting Officer explained that this matter has remained a relentless
challenge to the Ministry, as the Ministry of Finance, Planning and Economic
Development over years has not taken into consideration the existence of two
distinct provisions in MTEF ceiling of Court Awards and Compensations that is
current and the arrears. He further explained that the unsettled amounts will
continue to accumulate if sufficient provisions are not made.
I advised that in the budget preparation process and provisions in MTEF ceilings
on Court Awards and Compensations, consideration should be made to provide for
Current and Arrears of Court Awards and Compensations. I also advised that
Management should continue liaising with Parliament and MoFPED to ensure that
these cumulative arrears of compensations are cleared.
c) Accumulation of interest on Court awards and compensations –
UGX.60,396,783,924
123
According to Section 26(2) of the Civil Procedures Act Cap 71, court may in the
decree order interest at such rate as the court deems reasonable to be paid on the
principal sum adjudged from the date of the suit.
I noted that in several court cases ruled against Government, court awarded
interest ranging from 6%-25% and even up to 40% in some cases, per annum on
the court awards.
It was observed that as a result of government‟s failure to pay these court awards
on time, interest of UGX.60,396,783,924 has accumulated over time and in some
of the cases interest is now greater that the principal award. At the current rate of
payment it would be difficult for government to extinguish the total outstanding
debt in court awards.
The Accounting Officer explained that budget ceilings are set and no amount of
negotiations with MOFPED have borne additional funds.
I advised the Accounting Officer to ensure that adequate planning is made to
promptly settle payments related to these cases to avoid interest charges and
other related charges that may arise therefrom.
d) Failure to document guidelines for payment of court awards and
compensations
An interview with management and a review of documentation revealed that the
Ministry established a committee on compensations, out of court settlement and
court awards. The Committee sits every quarter to determine which cases to
prioritize for payment.
I noted that whereas the Committee has been in existence for some years now, it
is not supported by any documentation or clear approval from management. I also
noted that there are no documented guidelines on the payment of Court awards
and compensations.
In the absence of documented guidelines it becomes difficult to establish whether
the settlements were done in a transparent manner.
124
I further noted that the criteria for priority of payment of court awards and
compensations are not documented. As a result of undocumented payment
guidelines, there is a payment backlog and aging out of claims is becoming
difficult. For instance, there are claimants who have never received any payment
dating as early as year 1999, yet those awarded by court in recent years are being
cleared.
The Accounting Officer explained that the committee to manage court awards and
compensations looks at the funds available and distributes them accordingly. The
criteria used include; First in first out, Mandamus cases, High interest rates,
Human rights cases, and Medical grounds.
I advised the Accounting Officer that the internal guidelines for management of
court awards and compensations should be documented and followed.
e) Management of Court Awards and Compensation Files
(i) Inadequate Records Management
It was observed that the records management of Court awards and compensations
is inadequate because the Ministry‟s case management filling system is still a
manual one. MoJCA works with case and advice request files that require tracing,
quick movement and action which is not possible in the manual system. For
example it is not possible to identify cases with high interest charges. It was also
noted that MOJCA cannot easily ascertain the number of claims that have been
cleared and those outstanding at a given time. As the Directorate of Civil litigation
has pending cases for a long time, tracing the documentation from manual records
can be cumbersome and subject to abuse.
The Accounting Officer explained that the Ministry is in the process of securing a
service provider to computerize the system.
I advised the Accounting Officer to expedite the process of computerizing records
so as to improve information flow and protection.
(ii) Ledger Card Management:
125
During the audit of court awards and compensations, a sample of files was
reviewed to ascertain whether the amounts reported on the ledger cards actually
tallied with the outstanding amounts awarded in the cases. The following were
observed about the ledger cards;
(a) Lack of ledger cards:
It was observed that certain files lacked ledger cards contrary to best practice.
This is risky because one cannot easily ascertain how much money has been paid
and how much is outstanding. It also raises questions of figures raised in the final
accounts as payments made and outstanding balances. Examples of the cases
with missing cards are; Benon Turyamureeba & 132 Others Vs Attorney General
Misc. Application 440/2005 and Capt. Samuel Nsubuga & Others Vs. AG CS.
547/2007.
The Accounting Officer explained that some files do not have ledger cards because
some of the required information is not readily available on the file.
I advised the Accounting officer to ensure that the files are updated and the ledger
cards opened.
(b) Ledger cards are not properly updated:
Best practice dictates that while maintaining a ledger card, it should be opened on
the date of award and the amounts awarded indicated, subsequently, when
payments are made, they should be entered onto the card with their
corresponding dates indicated and at the end of the year. The ledger cards should
be updated to get the figure outstanding as at the close of the year. During the
audit of the files, it was observed that the ledger cards were not properly updated.
On some files, when payments were made, they were not reflected on the ledger
cards. It was further noted that all the cards were not updated at each year end
while on other cards, the opening figure was not that awarded but a figure
“brought forward”. This raises doubt about the figures reported in the final
accounts as outstanding especially for awards that earn interest.
126
Furthermore, computations were carried out on some files and outstanding figures
compared to what was reported on the ledger cards and major differences were
observed. Of the five files sampled the total difference was UGX.1,769,667,605.
There is a risk of failure to track payments made on various cases.
The Accounting Officer explained that they are constantly improving the use of
Ledger cards and ensuring that they are updated. He also explained that they will
be phasing them out as they move towards computerization.
I wait the result of management efforts on improving the custody of the
information.
(c) Ledger cards lacking serial numbers:
It was also observed that certain ledger cards were not serially numbered. This is
risky because a ledger card can be plucked out and replaced with another without
anyone noticing. Furthermore, it was observed that there are two types of ledger
cards that are used. This is risky too because having two sets of source
documents can be misleading as they can be tampered with or manipulated.
The Accounting Officer explained that the ledger cards that are not serially
numbered (ledger sheets) were first used when the Ministry had just embarked
on opening up ledgers on every compensation/ court awards file but management
later realized that this type of ledger cards were not appropriate as they seemed
to be weak and also lacked numbers. Management stopped their use and resolved
that serialized ledger cards instead be procured and the ledgers sheets which were
already on files be phased out slowly as the files continue to be updated by
replacing them with serialized ledger cards which is ongoing.
I advised the Accounting Officer to ensure that the ledger cards are serialized.
(iii) Inadequate filing and mix up of records
For every case handled by MOJCA, a file is opened on which all documentation
related to the case is kept. I observed however that some files contained
127
documents relating to other cases, and some files were missing key documents.
For example the documents of Mugwere Yekosofati Vs. AG HCCS 28/2007 were
misfiled in Administrator General Vs. Bwanika James & Others SCCA No.7/2003.
Improper filing of documents may lead to loss of cases.
The Ministry should ensure that all documents are properly filed on their
respective files.
(iv) Poor information flow
To maintain and enhance internal operations of an organization, information must
flow both vertically and horizontally, hence the need to maintain designated places
for easy access and retrieval.
However, it was observed that many files are kept in state attorneys‟ offices
instead of the Civil Registry and in many instances; they are not well protected
from outsiders. Furthermore, files relating to completed cases are delayed to be
approved, thus resulting into understatement of payables in financial Statements.
Failure to get hold of the pertinent information will mean that the liabilities in the
Financial Statements will be understated.
Management appreciated the observation.
I advised that all concluded cases should be forwarded to the Director, Civil
Litigation who in turn forwards them to higher authorities for approval and for
capture in the database.
(v) Access to Registries
The Ministry of Justice operates both security and open registries. Inside the said
registries, important and confidential records are kept. It is in this regard that
access to these registries should be restricted to authorized personnel to avoid any
likely compromise on the information contained in the files (being accessed by
unauthorized people).
However, observation indicates that any person can easily access the registries,
particularly the Civil Litigation Registry. This statement is confirmed by people we
128
found seated on the chairs where the staff who man the registry are supposed to
be. Worse still, there are times when the registry is left open without a single staff
with outsiders standing by the entrance. There is danger in leaving the registry
unattended by staff because the non-staff can easily access information on the
files which could result into loss of cases wince the other party‟s lawyers may
access information that may disadvantage the Government‟s defence.
The Accounting Officer noted the observation and pledged to ensure that the
registries are properly manned and a circular to this effect has been issued.
I advised the Accounting Officer that the Ministry‟s registries should be manned in
such a way that no unauthorized person is allowed to have access to them. I also
advised that no registry should be left open when all the staff in charge are out so
as to avoid strangers getting access to vital information. Staff manning the
registries should ensure that the registry is not left unattended.
f) Lack of Follow up on Cases Won by Government
A review of the sampled cases revealed that a total of over 50 cases have been
won by Government, with an estimated claimable amount of UGX.32,101,000,000.
The Attorney General is commended for this achievement and for a saving of
UGX.100,892,976,730 on the cases won.
However, I also noted cases where the Attorney General was awarded costs and
other payments by court, the costs had not been recovered, by the time of the
audit.
Management attributed the failure to recover/enforce court awards to lack of
resources for initiating recovery/execution proceedings. Government continues to
lose non-tax revenue in the won cases which could be used to offset outstanding
court awards.
The Accounting Officer responded that they followed up on cases won and some
money has been sent to the Treasury. The Accounting Officer further explained
that in the case of costs, Courts have said they are not entitled to instruction fees.
129
In the near future, they intend to engage executioners/court bailiffs with authority
from the Chief Registrar and MOFPED.
I advised the Accounting Officer to put in place a clear follow up mechanism to
ensure recovery of monies due to Government.
7.4 Staffing Gaps in the Directorate of Civil Litigation
It was noted that the Directorate has thirty technical staff under the director.
Three Commissioners, Seven Principal State Attorneys, five Senior State Attorneys
and fifteen State Attorneys. However, as per the staffing structure, the Directorate
is supposed to have a total number of forty lawyers. The available number of staff
is inadequate to handle over five thousand existing files and the ever increasing
number of cases arising out of continued litigation against Government.
The understaffing causes fatigue and deteriorating morale for the current staff and
creates case backlogs.
The Accounting Officer explained that the approved structure for Directorate of
Civil Litigation provides for twenty five Legal Staff and twenty one are filled. A
submission was made to Public Service Commission on 27th November, 2014 for
filling of the three vacant posts of Senior State Attorney. The Accounting Officer
further explained that they expect the number of staff to increase when the
proposed structure is approved.
I advised the Accounting Officer to follow up with the relevant authorities to
ensure adequate staffing of the Directorate.
7.5 Failure by the Attorney General to file a defence
I observed that in some cases, the Attorney General did not file a defence or failed
to appear and defend cases filed against Government. The Government loses
funds in these cases that have not been defended by the Attorney General.
Failure to defend Government leads to loss of cases and eventually loss of public
funds.
130
The Accounting Officer explained that they sometimes delay to get instructions, for
example, in the case of Fuelex (U) Ltd Vs AG HCCS 825 of 2007. He also explained
in some instances they are unable to go to Court because of matters beyond their
control.
I advised the Accounting Officer to ensure adequate planning and scheduling of
available staff resources to ensure that cases are attended to.
7.6 Payment of procurement claims arising from breach of contracts by
other Line Ministries
According to Section 59 (2) of the Public Procurement and Disposal of Public
Assets Act, 2003, a procurement or disposal shall only be initiated or continued on
the confirmation that funding, in the full amount over the required period, is
available or will be made available at the time the contract commitment is made.
However, I observed that some Ministries enter into contracts and later breach the
terms of the contract by failing to pay the contractors or service providers who sue
the Attorney General in his representative capacity as the chief legal officer of
government. These Ministries are unresponsive when called upon to assist the
Attorney General to defend their actions and as a result the Attorney Generals
loses these cases which escalates the outstanding payments on court awards. The
table below contains sampled cases:
Case File
Judgment
Date
Decratal
Sum
(UGX.)
Interest
Outstanding
(UGX.)
Balance
(UGX.)
Ministry
New World
Services Ltd vs
AG CS 650/2013
23/7/2014 147,200,000 147,200,000 Ministry of
Defense
Prime
Constructors Ltd
Vs. AG HCCS
55/08
07/06/2010 1,322,098,06
2
718,454,817 1,967,851,47
6
Ministry of
Water
131
Case File
Judgment
Date
Decratal
Sum
(UGX.)
Interest
Outstanding
(UGX.)
Balance
(UGX.)
Ministry
Combined
Services Limited
Vs. Attorney
General HCCS
657 of 2003
20/03/2009 176,791,511 176,791,511 Ministry of
Water
There is laxity by Government Ministries in aiding the Attorney General‟s chambers
to efficiently perform his role.
The Accounting Officer agreed with the observation, and explained that the
Ministry has communicated to MDAs about the consequences of not meeting their
obligations.
I advised that each Ministry should bear the legal costs arising from breach of
contract to reduce laxity in providing Defence in cases against Government.
7.7 Irregular Compensation to Lowi Roadways Ltd
Whenever the Ministry receives any compensation issues, be it relating to movable
chattels or land, the final decision arrived at as to how much should be paid to the
complainant, should be based on the advice of experts in pertinent fields. As far as
land is concerned, the advice of the Chief Government Valuer is paramount while
that of the Chief Mechanical Engineer (Ministry of Works) comes into play
concerning motor vehicles.
It was noted that a payment of UGX.1,959,485,948 was made to a Law Firm on
behalf of a client for loss of Buses destroyed in an ambush by Kony rebels and the
attendant loss of earnings. Instead of soliciting competent advice and assistance
of pertinent experts in the areas mentioned, the Ministry went ahead and paid the
sum of money based on the advice of a Principal State Attorney who lacks the
knowledge and skills of the Chief Mechanical Engineer. The resulting amount
arrived at is likely to have been misstated and probably caused financial loss to
Government.
132
The Accounting Officer responded that the vehicles were bombed and the Attorney
General used his discretion to determine the values for compensation.
I advised that determination of the amount payable to claimants in compensation
issues should be arrived at by involving Government technical officers.
7.8 Fuelex (U) Limited vs. AG HCCS 825 of 2007
The Plaintiffs sued the Attorney General for recovery of UGX.59,801,899 being
amounts wrongly deducted as Withholding Tax (WHT) from the payments for fuel
supplied to the Ministry of defence, interest thereon, general damages and costs
of the suit. Court entered a default judgment and awarded 59,801,899 as WHT
wrongly withheld, costs at the rate of 25% from 24th October 2007 until full
payment and costs of the suit.
A detailed review of the case noted the following:-
The Attorney General did not appear and defend and as a result Government
was not effectively represented.
The court ordered that the defendant may recover the monies paid to the
plaintiff from URA in lieu of the monies refunded. The money has not yet
been recovered from URA.
To date, the decree has not been satisfied yet the decretal sum and costs
continue to accrue interest which as at 30/6/2014 had accumulated to the
tune of about UGX.114,261,333. The outstanding balance as reflected on the
ledger card now stands at UGX.182,218,133.
There is a risk that Government will lose more funds in interest in case the amount
remains outstanding.
The Accounting Officer responded that efforts will be made to contact MOFPED for
necessary funding and as soon as it releases the funds, they will have the amount
settled.
I advised the Accounting Officer to follow up with MOFPED to have the amount
settled expeditiously.
133
7.9 Delays by the Chief Government Valuer to issue valuation reports
In the process of handling compensations and court awards, MOJCA is required to
determine the value of property for which the claimant seeks compensation. In
doing this, the Ministry calls and relies on Government agencies such as the Chief
Government valuer or Chief Mechanical Engineer with the relevant expertise in the
matter. I however observed that in some of the cases, the Chief Government
valuer delayed to provide the Attorney General with a valuation report, despite
constant reminders. Details are shown in the table below:
S/No. Case File No Date when the
request was made
Date when
valuation report
was issued
2. Metropolitan properties Ltd Vs.
Attorney General CS 102/2009.
12th August 2013 13th Dec 2013
3. Mbuya Blocks Limited Vs. AG
and 2 Ors HCCS No. 293/2005
11th May 2010 25th March 2011
There is a risk that a delay by the Chief Government Valuer to issue valuation
reports can result into reliance by court on the plaintiff‟s valuation which can
inevitably lead to loss of colossal sums of money by Government.
The Accounting Officer suggested that the Chief Government Valuer be advised to
make timely valuations and send the reports.
I advised the Accounting Officer to make regular follow up with the Chief
Government Valuer.
7.10 Human Resource and Strategic management issues
a) Delayed restructuring processes
Good strategic planning requires an entity to carry out human resource planning to
ensure that adequate number of qualified staff is in place to carry out the
operational activities of an entity so as to enable her achieve strategic objectives.
Section15(A-a) of the Standing Orders, 2010 mandates the Ministry of Public
134
Service to determine the structure, terms and conditions of service in Government
entities.
A review of the Ministry‟s Strategic Investment Plan (2012/13-2016/17) revealed
that management of the Ministry came up with a proposed macro organization
structure that would enable her to fulfil its mandate. The Ministry of Public Service
has in the past few years been restructuring MDAs including MoJCA. The process
has however been slow implying that the proposed macro organization structure is
not yet approved by the Ministry of Public Service. Consequently, all MoJCA
Directorates are operating below the required staffing levels and this has been
rated as a high risk in the Ministry‟s Strategic Investment Plan. As noted in the
previous year audit report, unless the proposed macro organization structure is
approved and operationalized, implementation of Ministry‟s strategic plan may be
negatively affected.
The Accounting Officer explained that the restructuring exercise is awaiting the
issue of a certificate of financial implications from the Ministry of Finance, Planning
and Economic Development.
I advised the Accounting Officer to follow up the approval of the proposed macro
organization structure by dialoguing with the Ministry of Public Service, Cabinet
and Ministry of Finance Planning and Economic Development, to enable the
Ministry deliver on her mandate.
b) Staffing gaps in the existing organization structure
Despite the fact that the proposed macro organization structure has not been
approved as noted in para.7.4.1 above, various posts in the existing organization
structure have remained vacant. These include key posts of: Commissioner Civil
Litigation (Institutions); Commissioner Legal Drafting (LG); Administrator General,
Principal Personal Secretaries, Principal State Attorney and Principal Accountant.
A review of the Ministry‟s ministerial policy statement revealed that this situation
was mainly attributed to the current freeze on recruitment and the wage bill
constraints which prevented the recruitment of more staff. Lack of staff in vital
135
positions of the organization affects the performance and overall achievement of
organization‟s goals and objectives. The existing members of staff may be
overworked leading to staff demotivation and staff turnover.
The Accounting Officer explained that they are in the process of filling the vacant
posts.
I advised the Accounting Officer to continue liaising with the Ministries responsible
and have the gaps filled.
c) Failure to Approve Centre for Alternative Dispute Resolution
(CADRE) by Ministry of Public Service
The Arbitration and Conciliation Act, 2000 (Cap.4) is an amendment of the laws
relating to Domestic Arbitration, International Commercial Arbitration,
Enforcement of Foreign arbitral awards and to define the law relating to
conciliation. The Act establishes the Centre for Arbitration and Dispute Resolution
(CADRE). The role of CADRE is to promote arbitration and alternative dispute
resolution to decongest the Commercial Court and to create a conducive business
environment for promotion of business to attract investments.
The Ministry of Justice together with the JLOS Sector Secretariat and the Ministry
of Public Service (MoPS) finalized the institutional arrangements of establishing
CADRE in accordance with the Arbitration and Reconciliation Act Cap. 4 and this
was approved by the CADRE Council. The organizational structure was then
submitted to the MoPS for approval but to date nothing has been done. Failure to
approve CADRE body defeats the good intention of formulating it and loss of the
intended benefits.
The Accounting Officer responded that the Hon. Attorney General wrote to the 1st
Deputy Prime Minister and the Minister of Public Service requesting for his
intervention to have this matter finally resolved.
I advised management to continue liaising with the responsible authorities and
ensure that CADRE is approved to allow its operation.
136
7.11 Delays in Settlement of Commitments
Best practice requires that once a commitment is entered into, there is need to
ensure that funds are available to settle the commitment upon delivery of goods
and services. Regulation 105(1) of the PPDA Regulations, 2003 also requires a
procuring and disposal entity not to initiate any procurement proceedings or
activities for which funds are neither available nor adequate.
A review of the accounting records revealed that commitments totaling to
UGX.629,235,292 settled during the year were prompted by notices of intention to
sue or signing consent agreements between the Ministry and the service providers
as a result of delayed settlement. It was further noted that some of the payments
related to the previous years.
Delayed settlement of creditors can result into the following:
Double payments as a result of failure to differentiate paid invoices from un-
paid ones over time.
Budgetary indiscipline as a result of incurring expenditure in the periods to
which it does not relate.
Legal suits against the Ministry and loss of trust by the service providers.
The Accounting Officer explained that delays in settlement of commitments are
occasioned by the inadequate budget received by the Ministry and emergencies
that the Ministry is bound to comply with.
I advised the Accounting Officer to always liaise with the relevant authorities for
adequate funding.
7.12 Land and Fleet management
a) Lack of Land titles for Regional Offices
While the Ministry has made improvements by acquiring regional Offices in
Mbarara, Gulu, Mbale and Arua, at the time of writing of this report, there was no
evidence of ownership of this property in form of land titles. There is a risk of loss
137
of valuable property to other claimants or encroachers. Karamoja office which is
opening soon faces a similar problem.
The Accounting Officer responded that Ministry is in advanced stages of securing
the said land titles.
I await the results of management efforts.
b) Un-disposed of vehicles
Treasury Accounting Instructions Section 816 requires a Government entity to
maintain an operating records/register for each vehicle to record its history,
performance, servicing, overheads and repairs among other things, in sufficient
details for periodic assessments to be made of its performance compared to its
cost of up keep. Once the vehicle is not cost effective, it should be boarded off.
A review of the Board of Survey Report dated 18th July, 2013, revealed that an
adhoc Board of Survey which sat on 14th June 2013 and resolved to boarded off 8
unserviceable vehicles. However, by the time of writing this report, the said
vehicles had not been disposed off. Most of the vehicles are parked in the
Ministry‟s parking yard thus wasting the valuable space. Failure to dispose of the
grounded vehicles can also result into:
storage costs especially those vehicles kept in garages;
Loss in value of the vehicles due to depreciation;
Theft of vehicle parts and vandalism of idle vehicles in the garages.
The Accounting Officer explained that the process of disposal delayed due to the
need to ensure that the process was transparently done. The process is now on
course and the vehicles are expected to be boarded off soon.
I advised management to expedite this disposal process to prevent the vehicles
from further deterioration.
c) Vehicle repairs and maintenance
The Ministry sends its fleet to prequalified garages for routine repairs and
maintenance. Under normal circumstances, each vehicle is supposed to have a
138
ledger maintained for it by the transport officer and another by accounts section
for the purpose of knowing which vehicle frequents the garage. Similarly, all the
repairs invoices should be endorsed by the transport officer indicating that the
repairs were actually carried out. On the contrary, during the year the procedures
indicated above were not undertaken.
I advised the Accounting Officer to increase the vehicle monitoring and supervision
roles and have the required process started and finally implemented.
7.13 Budget performance
The Ministry‟s approved recurrent budget for the year amounted to
UGX.60,643,372,903. However, by the close of the financial year,
UGX.57,225,590,343 had been received (representing about 94.4% of the budget)
leading to a shortfall of UGX.3,384,225,686. The shortfall in the releases partly
affected implementation of planned activities. While some planned activities were
partially implemented or others were not implemented at all. The table below
refers:
Planned Key Activity
Expected Output Actual output Variance
Administrator General-Estates Registration and Inspection
Issuing 350 land
transfers
350 land transfers
to be issued.
159 land transfers
to be issued.
241 land transfers not
issued. (68%) under performance
Apply to Court to
grant 25 letters of administration
25 letters of
administration applied for
1 letters of
administration applied for
24 letters of
administration not applied for (96%) under
performance
200 Estates to be filed for winding up
200 Estates filed for winding up
34 Estates filed for winding up
166 Estates not filed for winding up. (83%) under
absorption.
wind up 80 Estates 80 Estates wound up
34 Estates wound up
46 Estates not wound up (57.5%) under
performance
Law Council
Holding 60
disciplinary committee meetings
and conclude at least
150 cases
60 disciplinary
committee meetings held and
150 cases
concluded.
53 disciplinary
committee meetings held
and 60 cases
concluded.
07 meetings not held
(12%) under performance and 90 cases not
concluded (60%) under
absorption.
139
The Accounting Officer explained that there were several reasons why the
institution failed to achieve the targets. Among these were the irreconcilable
differences among land and property beneficiaries who were disagreeing on the
distribution, missing land titles and bureaucracies in the land office. There were
also numerous adjournments due to absence of parties in respect of cases
handled by the law Council.
I advised the Accounting Officer to plan adequately and ensure that all planned
activities for which funds are released are completed to enable the Ministry deliver
its mandate.
7.14 Capital Development Budget
During the process of budgeting, the Ministry is supposed to make estimates of
financial resources to be expended in carrying out planned activities in a given
period (a financial year in case of MDAs). The budgeted expenditure includes both
Recurrent and Development.
It was noted that the Ministry of Justice has no provision for Capital Development
budget. The lack of the said budget has rendered the Ministry unable to meet its
Capital Development obligations. It was noted that what appears as an approved
budget under Capital Development are donor funds which are channeled through
MOJCA to JLOS. Lack of Capital Development has forced the Ministry to use some
of its meager resources to purchase fixed assets such as office equipment and
furniture, which results into mischarge since no money is provided in the budget
estimates.
The Accounting Officer explained that they have raised this concern severally but
are still awaiting the Ministry of Finance, Planning and Economic Development to
provide the required funding.
I urged management to keep liaising with the relevant stakeholders for funding.
140
8.0 JLOS, LAW AND ORDER SECTOR SECRETARIAT
8.1 JLOS SECRETARIAT AND GENERAL OBSERVATIONS
(a) Budget performance
During the year, the Justice, Law and Order Sector (JLOS) Secretariat received a
total of UGX.62,359,810,419 to facilitate operations of the various JLOS
components. At the beginning of the year, the Secretariat also had unspent
balance totaling UGX.19,603,254,264. The total available funds for spending for
the year amounted to UGX.81,841,588,727.
UGX.50,529,898,358 was subsequently spent during the year by the various
implementing agencies leaving a balance of UGX.31,311,690,369 unspent. The
table below shows the opening and closing balances as well as expenditures by
various entities during the year.
No Institution Opening
Balance (JLOS)
Adjustment
to Opening
Balance
Receipts Total Funding
Available
Expenditure
UGX
Closing Bal.
UGX
1 Uganda Law
Society 124,450 - 605,520,100 605,584,600 305,551,600 300,033,000
2 Uganda Law
Reform Comm. 17,490,404 0 1,772,605,000 1,790,094,000 1,549,207,000 240,887,000
3 Local Government 26,197,000 70,969,000 412,825,000 509,991,000 412,050,000 97,941,000
4 Law Development
Centre 3,925,472 - 1,944,560,000 1,948,485,472 1,763,562,885 184,922,587
5 Tax Appeals
Tribunal 88,727,706 - 367,403,000 456,130,706 388,755,095 67,375,611
5 Directorate of
Public Prosecution 14,119,108 - 3,611,000,000 3,625,119,108 3,172,618,418 452,500,690
7 Uganda Reg.
Serv. Bureau 648,436,381 7,837,000 932,300,000 1,588,573,381 743,215,955 845,357,426
8 Ministry of
Internal Affairs 362,268,010 - 3,571,787,034 3,934,055,044 3,880,839,977 53,215,067
9 Uganda Police
Force 1,742,461,000 80,538,000 4,155,067,000 5,978,066,000 3,683,370,000 2,294,696,000
10 Uganda Prisons
Services 1,727,128,658 - 5,827,765,000 7,554,893,658 5,529,465,894 2,025,427,764
11 Judicial Service
Commission 3,154 1,387,596,000 1,387,599,000 1,212,374,000 175,225,000
141
No Institution Opening
Balance (JLOS)
Adjustment
to Opening
Balance
Receipts Total Funding
Available
Expenditure
UGX
Closing Bal.
UGX
12
Min. of Gender,
Labour & Social
Dev‟t
566,746,713 - 759,832,000 1,326,578,713 1,184,326,000 142,252,713
13 Judiciary 977,014,855 -9,855 9,651,325,400 10,628,330,400 7,175,472,474 3,452,857,926
14
Administrator
General Public
Trustee
121,221,795 - 576,644,000 697,865,795 572,142,768 125,723,027
15
Uganda Human
Rights
Commission
70,422,757 1,010,000 963,007,243 1,034,440,000 548,060,000 486,380,000
16 Min. of Justice &
Const. Affairs 1,917,431 -1,917,431 1,372,000,000 1,372,000,000 1,365,596,545 6,403,455
17 Secretariat
(Donner) 6,405,083,230 268,162,485 9,306,938,190 15,443,858,935 9,234,376,101 6,209,482,834
18 Secretariat (IFMS) 3,392,177 -3,392,177 3,072,075,970 3,072,075,970 3,044,601,261 27,474,709
19
Nat Citizenship &
Immigration
Control
1,630,547,244 - 1,616,293,756 3,246,841,000 1,372,042,000 1,874,799,000
20 MOJCA (CBL) 205,301,589 -8,286,500 1,943,010,174 2,140,025,263 2,112,837,544 27,187,719
21 JLOS House Acc 4,990,725,130 - 8,092,000,000 13,082,725,130 861,177,289 12,221,547,841
22
Taxes on
Machinery,
Furniture & Veh.
- - 418,255,552 418,255,552 418,255,552 -
Grand Total 19,603,254,264 -
121,412,890 62,359,810,419 81,841,588,727 50,529,898,358 31,311,690,369
I explained to management that failure to utilize the available funds implies that
planned activities were partially or not implemented. This may lead to failure by
the management to attain the programme objectives.
Management explained that the out of the unspent balance, UGX.12,221,547,841
was earmarked for the construction of the JLOS House and the balance was
committed to on-going construction works both at the JLOS headquarters, and at
the participating JLOS institutions.
I advised Management to properly supervise the on-going works with a view of
concluding the activities within the agreed timelines.
(b) Shortfall in the Budget Releases
142
A comparison of the approved JLOS budget and work plan for the 2013/14 with
funds released for the financial year revealed shortfalls in funding to the tune of
UGX.1,222,161,000. The table below shows funding shortfalls for the three
participating JLOS institutions:
No Institution Budget (UGX) Releases (UGX) Shortfall (UGX)
1 Uganda
Human Rights
Commission
1,186,465,000 963,007,000 223,458,000
2 Uganda Police 4,530,385,000 4,154,917,000 375,468,000
3 Uganda Prisons
Services
6,451,000,000 5,827,765,000 623,235,000
Total 12,167,850,000 10,945,689,000 1,222,161,000
Shortfall in funding impacts negatively on the implementation of planned activities
under Programme.
Management explained that the Sector experienced the shortfall because the
Secretariat did not receive the fourth quarter funding planned for the year.
Management was advised to liaise with the relevant stakeholders to ensure
adequate funding for implementation of planned activities.
(c) Delayed implementation of activities
The Secretariat had a total of UGX.18,557,638,979 available for implementation of
activities, out of which UGX.11,124,870,437 (60%) was spent, leaving a balance of
UGX.7,432,768,542. A review of Secretariat records indicated that some planned
and funded activities were partially or not implemented at all. These include
among others; construction of new Justice Centers; procurement and supply of
furniture to up country Justice Centers and electronic media outreach
programmes.
143
I explained to management that non-implementation of the activities also hinders
the Programme from achieving its intended objectives.
Management explained that most of the activities referred to are now on-going the
delay was due to the need to adhere to the government commitment control
guidelines and ensure that procurement processes are adhered to as per the PPDA
law.
Management is advised to make plans and budgets cautiously and realistically and
ensure that activities are implemented in accordance with the approved plans.
(d) Field inspections at Bulambuli Police Station
Field inspections were carried out in the district of Bulambuli to verify the
construction works that were on-going. The findings are below:
Construction of police station
A contract for construction of Bulambuli Police Station was awarded to a local
company at a contract price of UGX.474,426,916. Out of the contracted amount,
UGX.191,938,718 had been paid at the time of audit. The contract period was
agreed to be two years and completion date was scheduled at the end of the
2012/2013 financial year. Field inspections revealed that the works were still
incomplete (approximately up to 70% of the works had been completed). The
building had stayed for one and a half years without any progress in construction
works, implying that the works had been abandoned. The inspection also revealed
the following;
There was no furniture supplied yet furniture had been budgeted for in the
year under review.
Cracked and wet ceiling was observed at the balcony due to inadequately
placed gutter outlets thus damaging the walls and ceiling.
Perforated walls were noted due to capillarity. According the BOQ, damp proof
course known as Pluvex or other equally and approved damp proof course
weighing not less than 0.5 Kg per meter was to be used to avoid wet
environment that weakens the walls due to capillarity.
144
Poor quality flush doors of which one for juvenile cell is already damaged.
According to the BOQ, 45mm thick solid flush doors overall sizes 850x2075mm
were to be fitted. However, low quality thin solid flush doors were installed.
Male cell copings had not been completed.
The team observed that the Police Station waiting room was already serving
as store for produce-maize, questioning its use for the intended purpose.
See pictures below:
Front and rear views of Bulambuli Police Headquarter
Perforated wall due to capillarity
Waiting room used for store purposes Water tank not installed, weak tank stands
noted
145
Spoilt poor quality flush door Rusting sink in the wash room
The delays in completion of the Project and the related defects deny beneficiaries
of the intended services.
Management explained that the completion of the Project is behind schedule, and
that on a number of occasions the contractor had been warned of the slow pace of
completion. Several meetings have been held with the contractor but with little
progress seen. Right now options for sourcing a sub-contractor to finish the
remaining works are being explored. The defects observed in Bulambuli will be
corrected by the contractor before handing over.
I await the results of management commitment on the matter.
8.2 MINISTRY OF GENDER, LABOUR AND SOCIAL DEVELOPMENT (MOGLSD)
(a) Budget performance
During the year, a total of UGX. 759,832,000 was released for the implementation
of the MoGLSD-JLOS activities against the approved budget of UGX.906,600,000.
A total of UGX.1,326,578,713 was available for JLOS activities under the Ministry
for the financial year 2013/2014 (UGX 566,746,713 brought forward from the
previous year and UGX.759,832,000 released in the current year).
UGX.1,184,326,000 was utilized leaving a balance of UGX.142,252,713 at the end
of the financial year, indicating an absorption capacity of 89%. The planned
activities not implemented included the review of Probation function/Probation Act
and the development of management guidelines for remand homes and
rehabilitation centres.
146
The slow implementation of the planned activities has a negative effect on the
objectives of the project.
Management explained that the funds were committed and the activities were on-
going. The draft reports for the two consultancy works have been submitted to
the Ministry and were being reviewed by senior stake holders for in-depth input.
I advised Management to expedite the implementation of activities to enable
finalisation of the activities within the agreed timelines.
8.3 LAW DEVELOPMENT CENTRE (LDC)
(a) Budget performance
During the year, a total of UGX.1,948,485,472 was available for approved JLOS
activities. Out of this amount, UGX.1,763,562,885 (77%) was expensed leaving a
balance of UGX.184,922,587. It was noted that some planned activities were not
implemented. The table below refers:
Code Activity/Planned
Out Put
Actual out Puts Variance Budgeted/
Released
Funds
000‟s
Amount
Spent
000‟s
Remarks
2.1.1.26 Complete
construction of LDC
Auditorium
Auditorium has been
roofed. Internal works
of tiling, Air
conditioning are still
on going.
700,000 700,000 Not achieved
although
funds had
been released
2.1.1.51 1 Recording
equipment
Procurement process
has been completed
waiting for delivery of
the recording
equipment
I recording
equipment not
procured
80,000 0 Not achieved
2.5.2.2 Women cell Procurement process
completed, contract
signed , work slated
to begin by 1st Sept
2014
Not achieved 100,000 0 Not achieved
147
Under absorption of funds in the period in which they are planned does not only
lead to overspill of activities to the next planning periods but also the
implementation of the activities may be affected due to increased prices.
Management explained that the unspent balance of UGX.184,922,587 was meant
for activities that had not yet been done but whose procurement process had
already been completed. The activities were still on-going and are about to be
completed.
I advised management to ensure follow up of project activities to enable timely
attainment of Programme objectives.
(b) Stalled Construction of the Law Development Centre Auditorium
In a bid to alleviate the shortage of lecture rooms at the Centre, management with
funding from the Justice Law and Order sector, the Ministry of Finance (GOU) and
the Centre‟s non tax revenue, contracted a local company to construct a befitting
auditorium at the centre at a contract sum of UGX.3,977,880,902. It was
envisaged that the auditorium would accommodate up to 1000 students as well as
provide office space for some staff. The Contract period was agreed to start on
30th May 2012 and end on 11th June 2013.
It was however noted that the completion of the auditorium has delayed by over
15 months (as of 6th October 2014). It was also noted that the auditorium was
commissioned for use on 4th April 2014, despite it being incomplete.
The pictures below show the current state of the auditorium:
148
Ceiling without Gypsum Plaster Board
Un-tiled floor without seats and other fittings
Figure 1 Uninstalled electrical fittings
149
Unfinished compound
The delay in the completion of the auditorium has led to the failure by
management to address the issue of shortage of lecture rooms at the Centre. The
delay may also lead to increased construction costs due to inflation and other
related costs.
Management explained that the contractor submitted variations in respect of air
conditioning, auditorium chairs, and extra works in respect of the pagolar and
landscaping in 2013. The variations and extra works were referred to Ministry of
Works and Transport for a technical opinion. The report from the Ministry is being
awaited.
I advised Management to follow up with Ministry of Works and ensure that the
auditorium is completed.
8.4 MINISTRY OF INTERNAL AFFAIRS (MOIA)
(a) Budget performance
During the year, a total of UUGX.3,571,787,034 was released for the
implementation of JLOS activities under the Ministry against the approved budget
of UGX.3,361,660,000. A total of UGX.3,934,055,044 was available for JLOS
activities for the financial year 2013/2014 (UGX.362,268,010 brought forward from
the previous year and UGX.3,571,787,034 released in the year under review).
Records availed indicate that almost all the funds were utilized, leaving only a
150
balance of UGX.53,000,000. It was however noted that some activities worth
UGX.963,000,000 were not implemented, as shown in the table below:
Specific Activities Total Release
(UGX)
Study on implementation of community service and its impact
in Uganda - 12 years after inception
50,000,000
Set up wide area network to link departments 21,000,000
Consultancy to design a database for storage of data on vital
government installations / information and management of
explosives
5,000,000
Specialized Camera 5,000,000
Laptops for field data capture 6,000,000
Heavy duty Photocopier (multi-purpose) - to reduce Cs
forms/photocopying costs
15,000,000
LCD projector 7,000,000
Vehicle for Monitoring and inspection 120,000,000
Procure saloon motor vehicle for transporting Forensic experts
to attend courts outside Kampala
120,000,000
Procure LC/MS to increase success rate of analytical forensic
examinations in explosives, chemical war agents, food
additives, plant and animal poisons
400,000,000
Carry out counter terrorism awareness programs by GSO 50,000,000
Benchmark on international best practices in Namibia on
managing recidivism by NCS
29,000,000
Procure personal protective equipment for incidence response 30,000,000
Finalization of the Client Charter (MIA/F&A) 50,000,000
Motorcycles for NFP (2012/13) 55,000,000
Total 963,000,000
Failure to implement planned activities has a negative effect on the objectives of
the programme.
151
Management explained that by the time of audit, the activities were still under
implementation.
I advised Management to ensure that planned activities are implemented timely in
accordance with approved work plans.
(b) Delayed construction works of regional laboratory in Gulu
During the year, the Ministry paid UGX.30,409,733 to a local company for the
construction of Gulu Regional Government Laboratory. This was a 4th payment to
the contractor bringing the total payments to UGX.236.330,768 out the contract
sum of UGX.436,445,468. A contract signed between the Ministry and the
contractor was not availed for audit and there was no proof that the Ministry owns
the land on which the laboratory is being constructed. Scanty information obtained
indicated the following:
The contract was entered into on 28th January 2008 and was to be executed
within 22 calendar weeks commencing on 22nd February, 2008. The
completion date was scheduled for 28th July, 2008.
The scope of works comprised construction of a single block laboratory
building including associated electro-mechanical installations and external
works.
The Ministry was to appoint a project manager responsible for monitoring and
supervising the works.
On 16th April 2012, three years and nine month after the expected completion
date, MOWT staff visited the construction site and made the following
observations:
Construction works had not been completed 277 weeks past the date of
completion.
The contractor had submitted a claim of UGX.104,651,368 which included
items of work not fully completed like the ceiling, painting of internal walls,
doors and windows, electrical installations and external walls.
The amount due to the contractor according to the Ministry‟s
assessment/valuation report (valuation No.3) was UGX.30,409,733. This
152
however could not be substantiated as the valuation certificate was not on file
and besides, a contract management file was not availed for review.
The contractor carried out extra works without any authorization as required
by the contact.
There was no evidence that the title had been secured.
On inquiry about the status of the laboratory, I was informed that the laboratory
had been plastered but the contractor abandoned the site. Instead of terminating
the contract due to failure to complete the project, the Ministry went ahead and
paid UGX.30,409,733 to the contractor on 30th October 2013.
Failure to complete the project impacts on the service delivery and undermines the
objectives of the project. It is likely that by the time the contract is resumed, the
cost to completion will have increased leading to loss of public funds.
Management explained that this contract met a lot of challenges and the work
could not continue. The contract is now under review following the approval by
PPDA. Management is in the process of securing another contactor.
Management was advised to establish the loss as a result of abandonment of the
site by the former contractor and accordingly evoke the necessary provisions in
the contract. Management was also advised to expedite the process of securing
another contractor in accordance with the PPDA Act.
(c) Delayed completion of the Regional Laboratory in Mbarara
On 31st May 2009, the Ministry entered into a contract with a local company for
the construction of a regional laboratory in Mbarara at a contract price of
UGX.454,015,728. The contract price was revised twice upwards by
UGX.81,176,257 (which is 17.9%) to arrive at UGX.535,191,985 (first by
UGX.16,705,437 and then by UGX. 64,470,820). To date the Ministry has paid a
total of UGX.514,775,133 to the contractor leaving a balance of only
UGX.20,416,852. The project management file was not availed, however, review
of the scanty information available revealed the following:
153
The construction which begun on 21st May 2011 was to take a duration of 22
calendar weeks to be completed by 19th November 2011. Despite the project
completion date having been extended twice to 31st December 2012, the
construction was completed on 16th October 2013, 4 years and 5 months of
signing the contract, and it took nearly a year for the building to be handed
over to the Ministry.
The land title for the land on which the laboratory was constructed was not
availed for audit review.
The project objectives have not been achieved in this regard and this could have
also led to extra costs on supervision and material price changes.
Management explained that the Regional Laboratory construction was
subsequently completed and the building was handed over to the Ministry. They
further explained that the Land Title is being processed and the Ministry is in touch
with Uganda Land Commission and Mbarara District Land Board.
I advised Management to ensure that projects are closely monitored and
completed in a timely manner to achieve the intended objectives and avoid
nugatory expenditure associated with implementation delays.
(d) Delayed Procurement of Liquid Chromatography Tandem Mass
Spectrometer (LCTMS)
On 12th June, 2014, the Ministry entered into a contract with a local company to
supply Liquid Chromatography Tandem Mass Spectrometer, for use by the
Directorate of Government Analytical Laboratory at contract sum of USD
786,594.66. I noted that the equipment which had been budgeted for at
UGX.500,000,000 was estimated to cost UGX.1,600,000,000 when initiating the
procurement.
Subsequently the contract was awarded at USD.786,594.66 (approximately
UGX.2,084,475,849) which was above the estimated price. According to the
payment terms, 80% (approximately UGX.1,667,580,679) of the contract price
was to be paid on delivery but only UGX.400, 000,000 was released for the
procurement. It was not explained why the Ministry entered into a contract when
154
it did not have enough funds contrary to PPDA regulations, and how it would raise
the total 80% of the contract price in case the equipment is delivered. Under the
circumstances, there is a likelihood of breach of contract by the Ministry which
may attract penalties.
In addition to the entity entering into a contract with limited funds the contract did
not contain a time frame. There was no evidence that the estimated value of the
equipment was based on the market price or on results of enquiry from the
manufacturers of the equipment. Lack of this analysis posed a risk of exaggeration
of the estimated price.
Management explained that the Ministry entered into the contract when they did
not have enough funds, but JLOS headquarters made a commitment to avail the
funds in the financial years 2014/15 and 2015/16.
I advised management to always carry out market surveys to make more accurate
cost estimates, and to always make a commitment when funds are available to
settle the resultant obligation. I also urged management to ensure that the
contractual agreements are finalised and supply is undertaken as agreed.
(e) Electronic Data Management System for the NGO Board
During the year, a local company was contracted by the Ministry to develop of an
Electronic Data Management System (EDMS) for the NGO Board at a contract price
of UGX.237,048,420. According to the terms of payment, 15% of the contract
price was to be paid to the company upon submission of an acceptable inception
report and 20% on submission of an acceptable design of an EDMS with
appropriate security architecture.
The Ministry subsequently paid the contractor UGX.35,557,263 being 15% of the
contract price upon submission of the inception report. However, I was not
provided with evidence that the inception report was discussed and found
acceptable to warrant the payment as provided for in the contract. Similarly, 20%
of the contract price worth UGX.47,409,684 was paid for the design of the EDMS,
but there was no evidence that the design was submitted and found appropriate
155
before payment would be effected. I was also not provided with approval as
granted by NITAU.
In the absence of the inception report and the design of the EDMS, I could not
verify that the payments were appropriately made. In the circumstance, the
system may not have been sufficiently developed to serve the intended purpose.
I advised management to review the agreed contractual terms and follow the
terms to conclusion. I also advised management to follow up with NITAU to
ascertain whether the EDMS is appropriate to serve the intended purpose.
8.5 UGANDA LAW SOCIETY (ULS)
(a) Budget performance
During the year, a total of UGX.605,584,600 was available to ULS to finance
planned JLOS activities against the budgeted amount of UGX.580,000,000. Out of
the releases, only UGX.305,551,600 was utilized while UGX.300,033,000 remained
unutilized at the close of the year. The funds remained on account even after the
close of the year. The delay or failure to implement planned activities denies
beneficiaries of the intended benefits. Non-implementation of the activities also
hinders the Programme from achieving its intended objectives.
Management explained that the unspent funds were a contribution towards the
construction of the ULS Resource Centre. The activity was not undertaken because
a number of steps needed to be completed before construction could begin. The
steps included but were not limited to retaining services of a Consulting Firm and
Project Manager to carry out the pre-construction, actual construction and post
construction process, preparation of detailed designs and site plans, and ground
plans.
I advised Management to make plans and budgets cautiously and realistically and
ensure that activities are implemented in accordance with the approved plans.
156
8.6 MINISTRY OF LOCAL GOVERNMENT (MOLG)
(a) Budget performance
A total of UGX.509,991,000 was available for approved JLOS activities for the
2013/14 financial year. However, only UGX.412,050,000 was utilized (representing
81% absorption) leaving unutilized balance of UGX.97,941,000. A review of the
project's performance as per the performance report revealed that some planned
activities had not been done, while others remained incomplete. The table below
refers:
Planned Key Activity
Approved Budget (UGX 000)
Actual amount Released (UGX 000)
Actual Expenditure
(UGX 000)
Expected Output
Actual output Remarks
OUTCOME 2. ACCESS TO JLOS SERVICES ENHANCED
2.3.3.5 Printing and distribution 6000 copies of LCC Regulations
42,000 41,500 16,460 6,000 copies of LCC Regulations Printed and distributed.
1,071 copies of LCC Regulations Printed and 294 copies distributed.
There was 17.8% absorption capacity to print and 27% to distribute the printed copies.
2.3.3.6 Printing and distribution 6000 copies of Module on Local Administration of Justice.
20,000 20,000 14,718 6000 copies of Module on Local Administration of Justice Printed and distributed.
1100 copies of Module on Local Administration of Justice Printed and 128 distributed.
There was 18.3% absorption capacity to print and 11.6% to distribute the printed copies.
Sub Total 62,000 61,500 31,178
The slow implementation of the planned activities indicates that there is no proper
coordination between those responsible for approval of the activities and the
implementers.
Management explained that the cause was due to delayed procurements which
have now been concluded. I advised Management to carry out adequate planning
and to requisition for only those funds that can be put to proper use during the
financial year. Funds should be released to the entity based on realistic plans and
budgets.
157
8.7 UGANDA HUMAN RIGHTS COMMISSION (UHRC)
(a) Budget Performance
The Commission had budgeted for UGX.1,186,465,000 to be able to implement the
outlined activities under JLOS Programme. However, only UGX.963,007,000 was
received resulting into a budget shortfall of UGX.223,458,000. Further, during the
year, a total of UGX.1,034,440,000 was available for implementation of approved
JLOS activities (including the balance brought forward from the previous year of
UGX.70,422,000 and a refunded amount of UGX.1,011,000) but, only
UGX.548,060,000 was spent resulting into an absorption of only 53%.
UGX.486,380,000 remained unutilized by year end. As a consequence some
planned and funded activities were partially or not implemented at all. These
included; printing of popular version of universal periodic review of Uganda which
was rolled over from the previous year registered only 30.8% performance,
conducting a documentation of human rights violations in the country particularly
in the Acholi Sub region and, the procurement and delivery of the civic education
van intended for conducting Constitutional education.
Management acknowledged the slow implementation of activities and pledged to
make improvements in the future.
I advised management to prepare realistic budgets for Programme activities and
ensure commitment in execution of activities to enable attainment of Programme
objectives.
8.8 JUDICIAL SERVICE COMMISSION (JSC)
(a) Budget Performance
The approved work plan and budget for the period 2013/14 indicated funding for
the JSC of UGX.1,464,606,000, out of which UGX.1,387,599,000 was received. Out
of UGX.1,387,599,000 received, UGX.1,212,374,000 was utilized (representing
87.4% of the funds received) leaving unspent balance UGX.175,225,000. A review
of the Programme‟s performance revealed that execution of various key planned
activities for which funds had been released remained incomplete or were not fully
achieved. These included; investigation trips; Disciplinary Committee Meetings,
158
Development of an automated data base management system and development
of recruitment, discipline and training of judicial officers. Inadequate
implementation of the planned activities, affects the timely achievement of the
programme objectives.
Management explained that the above mentioned activities were still on-going by
the time of audit since all the related funds were earlier committed.
I advised Management to ensure that there is commitment in execution of
Programme activities to enable timely attainment of its objectives.
8.9 UGANDA REGISTRATION SERVICES BUREAU (URSB)
(a) Budget Performance
The Bureau had budgeted for UGX.847,286,000 to implement activities under JLOS
Programme and UGX.845,425,000 was received. The entity also received an
additional 86,875,000 from the Secretariat. Out of the total amount received only
UGX.179,823,000 was utilized, resulting into only 21% absorption. A comparison
of the entity‟s performance with the previous year also showed that the Bureau
has not been performing well and little improvement has been realized. The table
below refers:
Year Budgeted amount
Released
(UGX)
Funds Spent (UGX) Absorption Rate
2012/2013 855,250,000 360,354,000 42%
2013/2014 845,425,000 179,823,000 21%
This does not only lead to spill-overs of activities of the preceding periods which in
turn affect the implementation of future work plans but also the implementation of
the activities may be affected due to increase in prices and other factors beyond
management control.
Management explained that delayed procurements and adjustments in the work
plans affected the planned activities which were not anticipated yet they were
159
inevitable. Management regretted the position and indicated that they have since
stepped up the Policy Planning Unit and Procurement and Disposal Unit (PDU) to
ensure adequate coordination of work plan activities so that funds are utilized on
the planned activities in a timely manner.
I await the results of management efforts.
8.10 UGANDA POLICE FORCE (UPF)
(a) Budget performance
During the year, UUGX.4,155,067,000 (92%) was released to the Uganda Police
Force to finance planned JLOS activities against the approved budget of
UGX.4,530,385,000. The entity also had a balance of UGX.1,742,461,000 brought
forward from the previous year and UGX.80,538,000 refunds bringing total funds
available for expenditure to UGX.5,978,066,000. Out of the available funds,
UGX.3,683,370,000 was utilized leaving the balance of UGX..2,294,696,000. Out of
the un utilized funds, UGX.1,259,250,000 (78%) represents the planned activities
which were not implemented at all. Details of activities that were not implemented
are shown below:
Planned activity Amount released (UGX)
Construct a police station at Koboko 500,000,000
Provide support to forensics service (SOCO) with
50sets
250,000,000
Procure heavy duty photocopier 10,000,000
Induct 500PPCs into CID 15,000,000
Train 50 personnel (SOCO) in scenes of crime
management
30,000,000
Train 200 officers in first responders course 30,000,000
Train 100 officers in Homicide Investigations 40,000,000
Procure 50 speed guns 80,000,000
Induct 50 dog handlers 7,200,000
Stationery (50 counter books, 50 pens, 30 cm rulers,
50 canine officers manuals, 5 reams of paper
3,500,000
160
Planned activity Amount released (UGX)
Protective clothing 3,250,000
Basic trainee handling equipment (1metre leash and
choke)
66,000,000
Construct 10 canine units 65,000,000
Establish Human Rights committees in 5 regions
(Mbarara, Gulu, Hoima, Jinja & Masaka)
38,000,000
Procure motor vehicles for use in Democratic
policing and human rights observance in 5 Regions
120,000,000
Glass Door filing cabinet 1,300,000
Total 1,259,250,000
Delayed or non-implementation of planned activities may lead to failure by the
management to attain the programme objectives.
Management explained that the activities were not implemented due to various
reasons including; change of plan from construction of Police station at Koboko to
Kyenjojo, failure of supplier to deliver the forensics equipment, and shortage of
training space to train 500 PPCs into CIDs. The authority to divert some of the
funds into other activities also partly caused the delay to implement the planned
activities on time.
I advised Management to ensure that adequate planning is undertaken to allow
utilization of funds and in a timely manner.
(b) Under-utilization of un spent balances brought forward
At the beginning of the financial year under review, UPF had unspent balance of
UGX.1,742,461,000 which was brought forward from the previous years. During
the year, only UGX.1,140,987,000 representing 65% was spent leaving a balance
of UGX.601,474,000 unutilized. Details are below:
161
Period Amount b/f
(Opening
balance)
Amount spent
during 2013/14
Closing Balance
(UGX.)
2011/2012 924,478,000 595,579,000 328,899,000
2012/2013 817,983,000 545,408,000 272,575,000
Total 1,742,461,000 1,140,987,000 601,474,000
A further review of the records revealed that vital activities such as the
procurement of the Automated Fingerprint Information System (AFIS) machine for
forensic investigations, and the training of 2,500 police officers which activities
relate to the previous period were not implemented. Details for brought forward
activities not implemented at all are as indicated in the table below:
Activity Amount (UGX)
Procurement AFIS machine 167,397,000
Recruit 2500 police officers 100,000,000
Procure patrol vehicles (balance
remained)
83,424,375
Refund of letter of credit 80,000,000
Total 430,821,375
The delay or failure to implement planned activities denies beneficiaries of the
intended services. Non-implementation of the activities also hinders the
Programme from achieving its intended objectives.
Management explained that the Automated Finger Print Information System (AFIS)
was initially budgeted for at UGX 3.0bn and JLOS Secretariat agreed to fund it in 3
years with an approved budget of UGX 1.0bn in the FY 2012/2013. However, only
UGX.500m was released to fund the first component of the AFIS (i.e Crime
Records Management System (CRMS)). The system was procured at UGX.343m
leaving a balance of UGX.167m. Because of the need to create linkages and widen
coverage to the entire country, another feasibility study was conducted which was
162
costed at UGX.18bn. This was presented to the JLOS technical committee for
funding but was declined considering the small Sector budget.
I advised Management to make realistic plans and budgets cautiously and
realistically and ensure that activities are implemented in accordance with the
approved plans. Management was further advised to engage the various
stakeholders to plan for the funding of the AFIS.
(c) Use of Force Account
During the audit, it was established that Force Account was used in the completion
of Kira Police Station at UGX.158,215,376, fencing Nagalama Dog Breeding Center
at UGX.49,337,235 and erecting of uniports at Busunju Police Barracks at
UGX.291,120,239 among others. Although the supplies used were procured in
accordance with the PPDA Act, there was no evidence that the direct, indirect and
overhead costs of using Force account were determined to be less than what a
contractor would demand, or that these were emergency situations and as such
there was no contractor willing to execute the assignment to warrant use of Force
account. In the absence of proper costing of the works to be carried out, I could
not ascertain whether the use of Force account was necessary and cost effective.
Management regretted the omission of not carrying out the cost benefit analysis
on a case by case basis. They further explained that the decision for in-house
construction has always been educated by cost comparisons based on unit rates
obtained from similar projects that were tendered out. They also explained that
UPF has come up with a new construction policy to address amongst others the
issue of in-house construction.
I await the results of management efforts.
8.11 UGANDA PRISONS SERVICES (UPS)
(a) Budget performance
During the year, a total of UGX.5,827,765,000 (90.3%) was released for the
implementation of Uganda Prisons Service JLOS activities against the approved
budget of UGX.6,451,000,000. The entity had a balance of UGX.1,727,128,658
163
brought forward from last year bringing the total amount available for expenditure
to UGX.7,554,893,658. A review of the project's performance revealed that out of
the available funds, only UGX.5,529,465,894 was utilized leaving the balance of
UGX.2,025,427,764 unutilized. Various planned activities were not implemented,
while others remained incomplete, implying inadequate performance. The table
below shows some of the activities that were not implemented:
Specific activities
Approved
Budget
Funds
Released FY
2013/14
Funds
Spent
Un spent
Balance
%
Performance
Construction of
reception center at
Isingiro. 400,000,000
370,000,000
76,779,640
293,220,360
21
Construction of
reception center at
Kalong. 400,000,000
380,000,000
3,800,000
376,200,000
1
Construction of
reception center at
Amuru. 400,000,000
360,000,000
-
360,000,000
NIL
Reconstruction,
expansion and
modification of
Ndorwa Prison and
staff quarters 500,000,000
440,000,000 3,260,000
436,740,000
1
Renovation at
Tororo Prison 320,000,000
320,000,000
-
320,000,000
NIL
Total 2,020,000,000 1,870,000,000 83,839,640
1,786,160,360
Slow activity implementation was exhibited mostly in construction works. By the
time of inspection (August 2014), construction especially of UPS prisons at Tororo,
Ndorwa, Kabong and Isingiro was either far behind schedule or had not started at
all.
The slow implementation of the planned activities is an indication of lack of
coordination between those responsible for approval of the activities, and the
164
implementers. The delay or failure to implement planned activities denies
beneficiaries of the intended services.
Management explained that the activities were not implemented due to various
reasons including; change in allocation of construction sites by the district
authority for example in Amuru and Kaabong, inaccessibility of some locations for
example Isingiro situated on a hill top and the works being undertaken in prisons
limiting contractor working time for example; Tororo.
I advised Management to carry out adequate planning to requisition for only those
funds that can be put to proper use during the financial year. Funds should be
released to the entity based on realistic plans and budgets.
8.12 JUDICIARY
(a) Budget performance
During the year, a total of UGX.9,651,325,400 was released for the
implementation of the Judiciary JLOS activities against the approved budget of
UGX.9,222,000,000 (inclusive of a special release of UGX.810,000,000). A review
of the project's performance revealed that out of the available funds for
expenditure amounting to UGX.10,628,330,400 (including the brought forward
amount of UGX.977,005,000), only UGX.7,175,472,474 was spent (68%) leaving
the balance of UGX.3,452,857,926 unutilized. Various planned activities were not
implemented, while others remained incomplete, a sign of inadequate
performance. It was also noted that in some instances, the awarded contract
values exceeded the available funding. The table below refers:
Planned Key Activity Available
funding
Contractor Contract
Value
(UGX)
Remarks
2.1.1.1
Completion of
construction works,
equipping and furnishing
of Kabale and Mitiyana
courts
2,057,965,000 BMK
Hebron
Investment
1,479,014,000
1,089,776,000
Activity
delayed
Double cabins to
facilitate Chief
240,000,000 Victoria
Motors
240,000,000 Activity
delayed
165
Planned Key Activity Available
funding
Contractor Contract
Value
(UGX)
Remarks
Magistrates for locus
visiting
Double cabins for
selected G1 Magistrates
in hard to reach areas
(Bundibugyo, Kisoro,
Buhweju, Buliisa and
Bukwo [choose 2])
240,000,000 Victoria
Motors
240,000,000 Activity
delayed
2.1.1.44
Acquire Court Recording
equipment for Kabale,
Soroti and Masaka High
Courts, Civil Divisions
(2) and one (1) for each
of the Chief Magistrates
Court at the High Court
Circuit Headquarters
230,000,000 International
Business
Solutions
230,000,000 Activity
delayed
2,815,465,000 3,278,790,000
The slow implementation of the planned activities is an indication of lack of
coordination between those responsible for approval of the activities, and the
implementers. Non-implementation of activities in the planned periods does not
only affect the performance of preceding work plans but also leads to increased
costs due to increases in prices.
Management explained that the implementation period of the activities mentioned
did not proceed according to the stipulated time and that the delay was due to the
long procurement procedures. Management further indicated that they have put in
efforts to expedite the implementation of the activities.
I await the results of the management efforts.
(b) Case Backlog performance
The Judiciary undertook to reduce a proportion of case backlogs at various levels.
A total of UGX.2,200,000,000 was budgeted under JLOS for the reduction of case
backlog of which UGX.1,890,000,000 was released for the activity during the year.
It was also noted that the sector has been allocating funds in the past years for
166
the reduction of back log cases in the judicial system. In the past two years a total
of UGX.4,555,569,754 was spent on this item. However, it has been noted that
case backlogs are instead increasing rather than going down. Even with the
appointment of over 20 Judges to the Supreme Court, Court of appeal and the
High Court this has helped little to reduce the case backlog. Details of the trend
are in the table below:
Court Cases b/f Filed Disposed Pending Backlog Growth
Rate
2012/2013
Supreme Court 45 40 12 73 62.2% Increase
Court of appeal 3,622 1,060 226 4,456 23.0% Increase
High Court 33,492 20,758 13,640 40,610 21.3% Increase
Chief Magistrate Court 81,360 67,717 62,717 85,963 5.7% Increase
Magistrate Grade 1
23,677
48,985
47,171
25,888
7.7% Increase
Magistrate Grade 11 4,978
10,982
10,558
5,402
8.5% Increase
OVERALL 147,174 149,542 134,324 162,392 10.3 Increase
2013/2014
Supreme Court 73 74 82 65 11% Reducing
Court of appeal 4,456 1,251 891 4,816 8.1% Increase
High Court 40,610 24,739 17,485 47,864 17.9% Increase
Chief Magistrate Court 85,963 64,511 65,676 84,798 1.4 Reducing
Magistrate Grade 1 25,888 48,645 46,481 28,052 8.4% Increase
Magistrate Grade 11 5,402 13,204 12,979 5,627 4.2% Increase
Overall 162,392 152,424 143,594 5,627 5.4% Increase
The objective of reducing case backlog in the judicial system is therefore not being
achieved.
Management explained that the recruitment of more Judges and additional
funding has increased case disposal. However due to increased sensitization and
awareness of the public, the Judicial system has realized increased case filing.
This has led to an increase in the number of cases filed and the need for increased
funding and manpower.
167
I advised management to liaise with the relevant authority with a view of soliciting
for more funding and manpower in the Judiciary.
(c) Delayed construction of Makindye Family Court
In the period 2010/2011, the Judiciary undertook to construct Makindye Family
Court and a contract of UGX.910,209,442 was signed with a local company in
August 2012. In accordance with the terms of the contract, work was to start
within 14 days after the signing of the contract and was to be completed within a
year after the start of the project. A visit to the site in September 2013, one year
after contract commencement revealed that works had not been completed as
shown in the picture below:
Stalled Makindye Court civil works in September 2013
A subsequent field inspection to the site on 12th September 2014 (one year later)
revealed that the works were still incomplete and behind schedule. A few workers
were at site fixing tiles and face bricks and doors. The structure is shown in the
picture below:
Delayed Construction at Makindye Court as at 12-09-2014
168
Review of records revealed that a total of UGX.300,000,000 was allocated by the
JLOS Secretariat in the period 2010/2011 for the construction of the Family Court
and no further funds have been provided in the work plans for completion of the
court in subsequent years. It was however noted that a total of UGX.694,892,782
has been paid to the contractor from JLOS funds to complete the Court leaving an
outstanding amount of UGX.215,316,660.
Failure to include spill-over works in work plans and budgets of the subsequent
periods causes difficulty in securing funds for the pending works, and may lead to
diversions or incomplete works. The work is now behind schedule by over 12
months. The works should have been completed by August 2013. Delays in
construction works affect achievement of Project objectives.
Management explained that the performance of the contractor has been below
expectations and on several occasions the Judiciary has been warning the
contractor to finish the project on agreed time. Currently, the building is at
finishing level with a few electrical and final fittings work remaining for the
building to be completed. Due to the delay the contractor extended the
performance bond for one year and has also provided a new work schedule to
have the building completed by March 2015.
I advised Management to ensure that spill-over constructions and other works in
progress are catered for in the subsequent budgeting period for appropriate
allocation of funds.
8.13 DIRECTORATE OF CITIZENSHIP AND IMMIGRATION CONTROL (DCIC)
(a) Budget performance
During the year, a total of UGX.1,626,293,756 was provided for the
implementation of the DCIC-JLOS activities against the approved budget of
UGX.1,728,008,000. A total of UGX.3,256,841,000 was available for spending
(including UGX.1,630,547,244 brought forward from the previous year). However,
only UGX.1,372,042,000 (42%) was utilized leaving a balance of
169
UGX.1,884,799,000 unutilized at the end of the financial year. Several planned
and funded activities were not implemented as indicated in the table below:
No Planned activity Amount
released
(UGX)
Amount
spent
(UGX)
Remarks
1 Automate and link work processes
153,000,000
0 No work done
2 Interconnect borders with headquarter and
regional offices (PISCES)
69,960,000
0 No work done
3 Procure security equipment(fraud
detectors, security stamps)
100,000,000
0 No work done
4 Construct Ngom Oromo and Ntoroko border
posts
420,000,000
0 No work done
5 Construct staff accommodation at Mpondwe
and Oraba
140,000,000
0 No work done
6 Build ramps & modify counters at border
posts
46,472,000
0 No work done
7 Procure 3 Electronic billboards for
immigration information at Entebbe Airport
30,000,000
0 No work done
8 Not identified
30,000,000
0 No work done
9 Construction of Goli Border post
39,550,000
0 No work done
10 Decongest Registries
81,550,000
0 No work done
11 Construction of Atiak Border post
50,000,000
0 No work done
12 Automation of business processes
241,000,000
16,195 7% works
done
13 Develop and print operating procedures
manual
15,350
0 No work done
14 Ethics code in place, complaints system
established
70,000 0 No work done
The slow implementation of the planned activities has negative effect on the
achievement of the objectives of the project. Failure to implement the brought
170
forward activities may imply that such activities are no longer vital to Project
objectives and the unspent balances should be returned to the Secretariat and
appropriated for other urgent activities.
Management acknowledged the observation and explained that the delay was
caused by the vigorous procurement process. Most of the procurements are at the
level of contract award.
I advised management to ensure that the procurement process is expeditiously
concluded and have the activities implemented in accordance with work plans.
(b) Delayed production of the Directorate Strategic plan
UGX.49,739,700 was paid to a local company towards producing an inception
report on the preparation of the Directorate Strategic Investment plan and its
associated Information Communication Technology (ICT) and Monitoring and
Evaluation (M & E) frameworks. According to the agreement signed in December,
2013 between the Directorate and the consultant, the execution of the contract
was to commence on 4th March, 2014 and end on 14th June, 2014.
However, by the time of audit (five months after the end of the contract period),
the consultant had not furnished the directorate with the deliverables specified in
the agreement. The delayed completion of the plan inhibits the smooth
implementation of the Directorate strategic objectives.
Management responded that the Directorate stopped the consultant from
executing the contract after the contractor had produced an inception report
because management had wanted to review the composition of the committee
first. However, after the composition of the committee had been reviewed and
the work on the SIP has now resumed.
I await the results of the management efforts.
(c) Field inspections
(i) Lack of Land Titles for border posts
171
I carried out field inspections at the border posts and noted that management did
not obtain land titles for the land before commencing the construction of the
border posts. The affected posts include Bunagana, Kizinga and Kyanika. There is
a risk that the ownership of the land on which the border posts are constructed
can be contested.
I advised Management to follow up the ownership of the land.
(ii) Inadequate workmanship at Bunagana Border Post
The regional offices were constructed under a contract signed on 11th July, 2011
for a sum of UGX.188,845,241. The contract was to be executed within six months
with effect from 18th July 2011. The building was completed and handed over to
the directorate for occupation. The audit inspection carried out on 14th August
2014 revealed that although the construction had been done and completed, there
was evidence of inadequate workmanship and use of inferior materials, as detailed
below:
The toilet seat (water closet) and cistern were not properly installed leading to
flooding of the toilet room and those adjoining it during the flushing of the
toilet.
Whereas the agreement required the contractor to fix seven thick flash doors,
the contractor instead fixed semi-solid flash doors which are weaker and
cheaper than thick flash doors specified in the contract. Semi-solid flash door
which are easily damaged by both water and sunshine, were fixed both inside
and at the behind entrances (exterior) of the building where they are exposed
to rain and sunshine. It was not explained how the contractor could be allowed
to fix inferior doors when the project was managed by an engineer who also
worked as a project manager.
The doors were fitted without fixing a mosquito mesh on the ventilator. The
immigration officer had improvised for a mosquito mesh by fixing a steel vent
grill which is ideally meant for metallic (steel casement) windows and doors.
The improvised mosquito mesh (steel grill) has not served the purpose of a
mosquito mesh as mosquitoes freely pass through the grills.
172
It was observed that the plaster on the walls was failing. The cause of this
could be use of lower ratios of cement: lime: sand than those specified in the
bill of quantities of 1:2:9 for the first coat and 1:1:6 for the second coat. This
depicts inadequate supervision by the contract manager.
The photos below refer:
Figure 2: Bunagana Border Post office block.
Figure-2: Door without mosquito mesh. Figure-3: Improvised mosquito mesh.
Figure-4: Swollen and peeling Plaster off the walls
Under the circumstances, the building may not last the intended life period.
173
Management regretted the error and indicated that a plan is under way to rectify
the defects when funds are made available.
I advised management to always monitor/supervise the works before and after the
handover to avoid such uncalled for eventualities. In the meantime, I await
management efforts in rectifying the defects.
8.14 DIRECTORATE OF PUBLIC PROSECUTIONS (DPP)
(a) Budget Performance
During the year, a total of UGX.3,611,000,000 was released by the Ministry of
Justice as budgeted to finance planned JLOS activities. Out of UGX.3,611,000,000
released, UGX.3,172,618,418 was utilized leaving a balance of UGX.452,500,690
unspent (including UGX.14,119,108 brought forward from the previous year). As a
result, various planned activities were not implemented as detailed in the table
below:
No Specific activities Total
releases
Remarks
1 Open and resource 8 new DEPP
stations
200,000,000
Not implemented
2 Carry out major renovation of 3 DPP
buildings in F/Portal, Mbale and Masaka
(Lira)
200,000,000
Not implemented
3 Construct Guard house and toilets in 3
existing DPP offices in Paidha Moyo
and Adjumani
60,000,000
Not implemented
4 Construct and furnish 1new DPP office
in Kapchorwa
400,000,000
Not implemented
5 Procure & install solar equipment in 3
stations in Nakapiripirit, Arua and
Paidha
123,000,000
Not implemented
6 Preparation of anti-corruption
witnesses
100,000,000
Not implemented
174
The failure to implement planned activities is an indication of lack of
Management‟s commitment to Programme implementation, which hinders the
programme from achieving its intended objectives.
Management explained that the activities were not implemented due to various
reasons including; lack of adequate staff and accommodation to resource the
proposed opening of the new offices, procurement challenges for example on
construction of guards houses and toilets of offices in Paidha, Moyo and Adjumani,
and interruption from external parties for example the court order of the anti-
corruption court on preparation of anti-corruption witnesses.
I advised Management to carry out adequate planning and to requisition for only
those funds that can be put to proper use during the financial year. Funds should
be released to the entity based on realistic plans and budgets.
8.15 UGANDA LAW REFORM COMMISSION (ULRC)
(a) Budget Performance
The approved work plan and revised budget for the period 2013/14 indicated
funding for the Uganda Law Reform Commission activities of UGX.1,790,094,000.
During the year, UGX.1,772,605,000 was received by the entity for funding of the
JLOS activities. However, although the Commission got almost all the required
funds, only UGX.1,549,207,000 was utilized representing 87% leaving an unspent
balance of UGX.240,887,000 (including a brought forward balance of
UGX.17,490,404 from the previous year). A review of the Commission‟s
performance report revealed that execution of some key activities for which funds
had been released remained incomplete. Details are as in the table below:
Planned Key
Activity
Approved
Budget
(UGX
Actual
amount
Released
(UGX)
Funds un-
utilized
(UGX)
Expected
Output
Actual
output
Remarks
OUTCOME 2. ACCESS TO JLOS SERVICES ENHANCED
175
Planned Key
Activity
Approved
Budget
(UGX
Actual
amount
Released
(UGX)
Funds un-
utilized
(UGX)
Expected
Output
Actual
output
Remarks
Study to
review the
Prisons Act,
1.1.1.17 Publish
the study report
5,000,000 5,000,000 5,000,000 Printed
published
report on
Prisons Act.
Nil
Though funds
were released
there was
100% under
absorption
1.5.1.9 Printing
of 200 statutory
hard copies of
the Revised
Edition
100,000,000 100,000,000 72,816,000 The funds are
not sufficient
and not
economically
feasible to
print only 200
copies.
No
Copies
printed.
Copies not
printed yet
100M was
released on
this item as
planned. 72%
under
absorption
1.5.1.11
Print the
Drafting Manual
15,000,000 15,000,000 15,000,000 Draft Manual Nil Nil absorption
as the money
was released
but not
expensed on
this item
Failure to implement planned activities affects the timely achievement of the
programme objectives.
Management explained that the activities were not implemented due to various
reasons, for example; printing could not be done because the principal laws had
not been finalized. In the course of revision, it was discovered that many issues,
including conversion of fines and penalties into currency points needed more
consultation. Additionally the enabling law to authorize publication of the revised
laws of Uganda has not yet been passed by Parliament. It was realized that the
Commission was not the competent authority to issue the legislative drafting
manual. Accordingly there are consultations with the 1st Parliamentary Counsel on
176
the way forward. Those issues affected timely implementation of the planned
activities.
I advised Management to carry out adequate planning and to requisition for only
those funds that can be put to proper use during the financial year. Funds should
be released to the entity based on realistic plans and budgets.
8.16 MINISTRY OF JUSTICE AND CONSTITUTIONAL AFFAIRS
(a) Construction of Mini-JLOS Centre Moroto
JLOS Center/House Moroto was constructed and completed and commissioned on
14/02/2014 by Hon. Justice Steven Kavuma then Ag. Chief Justice and H.E.
Alphans Hennekens, Ambassador, Royal Netherlands Embassy. Refer to photos
below:
Mini JLOS centre Moroto
It was however noted on inspection that the House has remained un-occupied. It
has not been occupied apart from Prisons department with inadequately furnished
office of the Resident Prisons Officer (RPO). It has electricity and running water
without furniture and curtains. Offices for JLOS Secretariat were still empty. The
House also has an extension for Directorate of Citizenship and Immigration and
Government Analytical Laboratory and Community Service but all this remained
unoccupied with no furniture and curtains.
Underutilization of the building undermines the intensions of the Programme.
177
Management explained that efforts are underway to have all JLOS institutions
occupy the building. The delay was caused by lack of funds to procure the
required furniture and other office equipment.
Management efforts on the matter are awaited.
9.0 MINISTRY OF INTERNAL AFFAIRS
9.1 Mischarged expenditure
The Parliament of Uganda appropriates funds in accordance with the needs of the
country and this appropriation is implemented through the budget in which funds
are tagged to particular activities and outputs using account codes and MTEF
codes. However, it was noted that the Ministry charged wrong expenditure codes
to a tune of UGX.421,104,192 without authority from PS/ST. This constituted 15%
of the entity total expenditure. The practice of mischarge of expenditure
undermines the importance of the budgeting process and leads to misreporting.
The Accounting Officer attributed this to lack of sufficient funds on the respective
budget items/account codes as well as the emergencies that come at short notice.
He further explained that they will continue to request MoFPED for adequate
funding as well as increased ceilings for consumptive arrears in accordance with
Ministry operational experiences.
I advised the Accounting Officer to continue liaising with MOFPED to streamline
the budget process and ensure that sufficient funds are allocated to each account.
Authority should be sought before any reallocations are made.
9.2 Outstanding Payables
UGX.1,356,915,300 remained outstanding in payables at the end of the financial
year. The outstanding payables comprised of grants payable to RESCA of
UGX.1,317,292,748 and Umeme bills worth UGX.39,622,552. I explained to
178
management that accumulation of domestic arrears is in contravention of the
commitment control system.
Management attributed the outstanding payables to inadequate funding.
I advised Management to adhere to the commitment control system and liaise with
the relevant stakeholders to solicit for funding and have the outstanding
obligations settled.
9.3 Lack of certificates of title for Government land
The Ministry possesses various pieces of land in different parts of the country in
which Government has invested as shown in the table below. I was however not
availed with certificates of land title to verify ownership. Lack of ownership poses
a risk of loss of the land and developments thereon.
Location Plot No. Occupied by
Jinja Road Plot 75 Ministry Headquarters
Lourdel Road; Kampala Plot 2-4 Directorate of Government
Analytical Laboratories
Lyadda Road; Mbale Plot 15-35 Regional Government Laboratory -
Mbale
Kitunzi Road; Mbarara Plot 7 Regional Government Laboratory in
Mbarara
Princess road; Gulu Plot 4 C Regional laboratory-Gulu (Under
construction)
The Accounting Officer responded that efforts of pursuing Titles for all Ministry
land from Uganda Land Commission are in the process.
I advised the Accounting Officer to prioritize surveying of the Ministry land and
secure the titles to avoid any loss.
9.4 Staffing gaps
179
It was noted that the Ministry has 35 vacant posts. These include key posts of:
Principal Internal Auditor, two members of Amnesty Commission, DRT Member,
Commissioner-DGAL, Assistant Commissioner-DGAL, Principal Government
Analysts-DGAL, Senior Government Analysts-DGAL, Senior Lab. Technicians-DGAL,
and the Probation and Welfare Officer. The Table below refers:
PROGRAMME AFFECTED
POST/TITLE
APPROVED VACANT
POSTS
Finance &
Administration
(F&A)
Principal Internal
Auditor
1 1
Drivers 7 1
Amnesty
Commission (AC)
Members of
Commission
6 2
DRT Member 7 1
Accounts Assistant 1 1
Stores Assistant 1 1
Drivers 12 2
Office Attendants 2 1
Directorate of
Government
Analytical
Laboratories
(DGAL)
Commissioners 2 1
Asst. Commissioner 2 1
Principal Govt.
Analyst
8 4
Senior Govt.
Analyst
11 6
Senior. Lab.
Technicians
5 4
Personal Secretary 3 1
Steno. Secretary 2 1
Laboratory Assistant 9 1
Stores Assistant 2 1
Office Attendant 9 1
National Probation & Welfare 9 3
180
PROGRAMME AFFECTED
POST/TITLE
APPROVED VACANT
POSTS
Community Service
(NCS)
Officer
Non-Governmental
Organization Board
(NGO)
Stenographer 1 1
GRAND TOTAL 35
According to the Ministerial Policy Statement 2014/15, management plans to
recruit only three staff to fill the posts of one Laboratory Assistant and three
Probation Officers without considering the most affected and technical Directorate
of Government Analytical Laboratories. Inadequate staffing affects the timely
implementation of the Ministry's activities.
The Accounting Officer explained that the recruitment process could not be
undertaken because of the limited resources availed by the Ministry of Finance,
Planning and Economic Development. It has therefore become difficult to recruit
when the wage for the un-filled positions is not provided for in the budget.
I advised the Accounting Officer to make concerted efforts in liaising with all
stakeholders to ensure that vacant posts are filled to enable the Ministry
adequately deliver on its mandate.
9.5 Lack of an IT strategic plan
The Ministry has made substantial investment in IT Equipment including
procurement of computers, Laptops, Servers, Network racks etc. However, the
Ministry does not have an IT Strategy/Plan to ensure that these facilities and data
captured therein are safeguarded and protected and also to ensure continuity in
operation in case any disaster strikes. It was further noted that the Ministry has
an internal backup drive in the server room which cannot be put to use due to lack
of the IT Strategy/ Policy. This exposes the Ministry to a risk of losing all the
information stored on the computers in case of virus attack and theft of the
equipment or fire breakout.
181
Management explained that there is a running strategic plan but in draft form.
I advised the Accounting Officer to have the IT strategy approved and
commissioned.
9.6 Directorate of Government Analytical Laboratories - DGAL
The Directorate of Government Analytical Laboratories is mandated to provide
scientific advisory and analytical services to government departments responsible
for the administration of Justice (Police, DPP, Judiciary); Statutory Regulatory
Bodies (NEMA, UNBS, URA, NDA); the Private Sector (UMA, PSF) and the public in
general (individuals, scientific researchers).
A review of the operating environment of the DGAL revealed the following:
a) Poor infrastructure and working environment at DGAL
Headquarters
The headquarters of the directorate are located at Wandegeya Kampala. A visit of
the offices revealed that the building housing the directorate was built way back in
1927 and is currently in a dilapidated state and needs urgent renovations. The
directorate looks abandoned and yet it plays an important role of providing
scientific and analytical evidence in administration of justice. The building which
houses eight scientific laboratories with expensive and sensitive equipment as well
as information is roofed with corrugated iron sheets which are old and require
replacement; and in some areas there are leakages. The drive ways and parking
area has potholes. DGAL headquarters photos are indicated below:
Main entrance of the directorate headquarters: Falling facial boards; Stairs in a sorry state; Building
looks abandoned
182
Rear view of the building: Left is behind the Commissioner‟s office; pothole with water visible. Right
is the window one of the laboratories, wall needs renovations.
Leaking ceiling that needs urgent repairs/renovations
Left: Front parking with big potholes filled with water. Right: Drive way with pot holes
Parking on the sides that needs re-tarmacking
183
With this state of infrastructure, the directorate may find it difficult to meet
adequately its mandate.
The Accounting Officer explained that management is cognizant of this appalling
situation and has always engaged MoFPED to increase the Ministry development
budget but with limited success. The Ministry gets a Paltry 103 Million as its
development Budget which cannot do much because of other pending capital
commitments.
I advised the Accounting Officer to engage all stakeholders including JLOS Swap
Programme to ensure that the Ministry secures funds to renovate the
infrastructure.
b) Case backlogs and Performance of the Directorate
The Directorate provides forensic expertise to back up police in complicated cases
such as mass murders and fire out breaks, and also provides expert evidence in
courts of law. During the year, the Directorate responded to only 42 (52.5%) of
the 80 court sermons received from Kampala and upcountry, and analyzed and
disposed of 518 (35%) of the 1480 cases received. The pending cases have
accumulated leading to case backlog mainly due to shortage of chemicals and
reagents to do forensic analysis. This has in many cases caused delays in
providing expertise evidence and government could be losing very important cases
due to lack of evidence to guide prosecution.
It was also noted that no funding was provided to facilitate the movement of
experts to crime scenes and courts of law. In 2013/14, the directorate only
managed to send experts to crime scenes and courts around Kampala being
unable to handle upcountry areas. This has greatly affected the level of crime
investigations and delivery of justice. With increasing levels of sophisticated crimes
and emerging issues in the Oil and Gas Sector, terrorism, bio terrorism and
poisons, it is apparent that the directorate is inadequately funded to execute its
mandate.
184
The Accounting Officer explained that the Ministry has consistently experienced
underfunding to most of the critical areas especially in analysing disposing off
emergency cases and procuring chemicals and reagents. Management therefore
has to rationalize the meagre resources to carry out very critical activities and this
has greatly affected performance.
I advised that Accounting Officer to engage all stakeholders to ensure that the
Ministry secures enough funding for the directorate.
c) Lack of Maintenance contracts for DGAL Equipment
The Directorate has a number of scientific equipment for analyzing forensic and
DNA specimens, checking water and waste water samples and analyzing
proficiency testing samples, etc. The equipment in question include, but not
limited to Genetic Analyiser, PCR Machine, RT- PCR, Vortex Mixer/Mini shaker,
Thermal Shaker, Electrophorus Machine, Autoclave sterilizer, Comparison
Microscope and Electrostatic Detection Apparatus.
The Directorate however does not have maintenance contracts for these key
equipment. Lack of maintenance contracts limits routine and timely maintenance
of the equipment. In the circumstances, the efficiency and effectiveness of the
equipment is compromised most especially during crisis and peak periods. As a
result, the life span of the equipment is shortened or threatened, yet the Ministry
may not have capacity to procure and replace with new equipment.
The Accounting Officer explained that there was inadequate allocation of funds for
servicing and maintenance of the equipment, calibration of GC/MS, HPLC, AAS and
UV-VIS. During the year under review, only UGX.19,037,000 was allocated
against required 13,000 US Dollars. Servicing and calibration of DNA and real-
time PCR, required UGX.20,000,000 against the allocated 35,000 US Dollars. The
budget is still too low to commit service contracts maintenance as the equipment
service providers are based abroad.
185
I advised that Accounting Officer to continue engaging all stakeholders to ensure
that the Ministry secures enough funding to undertake this critical activity.
9.7 Mbale Regional Laboratories
Mbale regional laboratory is a well-equipped laboratory supposed to cover the
eastern region by collecting, testing and analyzing samples for suspects. The
laboratory however lacks reagents to carry out tests and has become more of a
collection centre for the samples than a testing and analysis laboratory. Despite
the Government injecting a lot of money for constructing and equipping the
Laboratory, it cannot be fully utilized due to lack of chemicals, reagents and other
consumables. The samples collected are instead sent to the Kampala headquarters
for testing and analysis which greatly affects the timely crime investigations and
delivery of justice; and also non achievement of the overall objective of having a
regional centre.
In addition, the laboratory is run by a skeleton staff of two government analysts,
one cleaner/ receptionist, one Shamba boy and four police guards. The station has
a motor cycle as a means of transport which is not provided with fuel. The station
receives imprest of only four million to run the office for a quarter which is not
enough and not received in time. The last imprest was received in the second
quarter of the year.
Under the circumstances, it is evident that the Mbale Regional Laboratory may not
achieve its objective of contributing to timely administration of justice in the
Eastern Region through testing and analysis of various samples to be used for
testifying in courts of law.
The Accounting Officer responded that Management of the Ministry recognizes the
need with concern and will continue engaging MoFPED to avail funding.
I await the results of management commitment.
9.8 Budget Performance
186
During the year, the Ministry of Internal Affairs received UGX.10,734,020,200
against the approved budget of UGX.10,916,219,910. The grants revenue
constituted 98.5% of the approved budget estimates. Subsequently, the Ministry
spent a total of UGX.10,358,868,929 which represented 96.5% of the amount
released.
However, a review of the Ministry‟s performance as per the annual physical
performance report indicated that some planned activities were not implemented,
while others remained incomplete despite release of 98.5% of the approved
budget. The table below refers:
Planned key activity Expected output Actual output Variance
Manage Amnesty
commission offices, six
Demobilization
Resettlement Teams
(DRTs) (Gulu, Kitgum.
Arua, Kasese, Central
and Mbale) and Beni
liaison office in DR
Congo
Amnesty
Commission offices,
six DRTs and the
liaison office in Beni
in the Democratic
Republic of Congo
well managed
The Amnesty
commission office,
the DRTs and the
liaison office in Beni
in the Democratic
Republic of Congo
were not well
managed.
Amnesty
commission had
accumulated arrears
of rent Amounting
to UGX.200,127,100
by the end of the
year. UGX 637m
due to the
Commission was not
released to the
Commission by the
Ministry.
Procurement of a
double-cabin pickup
for Amnesty
Commission
Motor vehicles and
other transport
equipment
The vehicle was not
purchased.
100% under
performance
Procure computer
supplies, Glassware,
chemicals and
laboratory
consumables for Mbale
Regional Laboratory;
Analyze and conclude
40% of received cases
at Mbale Regional
laboratory
Increased analytical
scope of the
laboratory
Computer supplies,
Glassware,
chemicals and
laboratory
consumables were
not procured; Only
20% of cases
received were
analyzed.
20% of cases not
analyzed
187
Planned key activity Expected output Actual output Variance
Conclude testing and
analysis within 9
months
Timely forensic
investigation
undertaken in
administration of
justice.
Out of 1,215
forensic cases
received only 444
were analyzed and
reported on
63.5% under
performance
Training Poison
Information Centre
operatives and
procurement of intox
data (a diagnostic
software) among other
requirements)
Strengthened Poison
Information Centre.
Activity was not
done
100% under
performance
Carry out forensic
study on oil and gas
industry contaminants
in water found in
Albertine region
(Bulisa District)
Oil and Gas industry
contaminants in
waters of Albertine
region monitored
Activity was not
done
100% under
performance
Procurement and
installation of
biometric access
control system at
DGAL
Electronic access
control system
installed at D/GAL
Activity was not
done
100% under
performance
Undertake District
study visits for best
practices in the
management of
Community Service
Orders.
Best practices in
community service
orders adopted and
applied
Activity was not
done
100%
underperformance
Continue with the
development of
National policy on
Community service
National policy on
Community service
Started the process
of developing the
Draft Policy on
corrections (National
corrections policy (in
place of National
Policy on
Community Service
only one
consultative meeting
was held.
The development of
the National
corrections
policy/National
policy on
Community service
was not given
priority.
Carry out Semi-annual
Monitoring and
Evaluation (M & E)
visits of Community
Service offenders
country wide.
Increased
supervision and
monitoring of
community service
offenders across the
country.
Monitored only
10% of the
community service
offenders.
90%
underperformance.
188
Planned key activity Expected output Actual output Variance
Setting up
rehabilitative projects
in 4 districts of Arua,
Bulambuli, Kapchorwa
and Kyenjojo
Rehabilitative
projects in 4 districts
of Arua, Bulambuli,
Kapchorwa and
Kyenjojo set up
The rehabilitative
projects were not
set up.
100%
underperformance
Monitoring 200
selected Non-
Governmental
Organizations (NGOs)
for Compliance with
the Law and the terms
and conditions of their
permits
200 NGOs
monitored
Only 90 NGOs were
monitored.
55%
underperformance
Renovation of two
residential buildings
for UNAFRI.
Two buildings for
UNAFRI renovated
The buildings were
not renovated.
100%
underperformance
Management‟s failure to implement activities as planned negatively affected the
Ministry performance and delivery on its mandate.
The Accounting Officer attributed the underperformance to inadequate funding.
I advised the Accounting Officer to liaise with all relevant stakeholders to solicit for
adequate funding and have the activities undertaken as planned.
10.0 UGANDA POLICE FORCE
10.1 Payables
Included in payables of UGX.46,702,959,156 are bills in respect of; water,
UGX.3,653,659,427; Umeme, UGX.14,443,914,497 and garages, UGX.736,243,151
which have been outstanding for more than a year. The opening balance on these
items was again reflected as closing balance indicating no movement in these
expenditure items. It is evident that management has not put in place sufficient
mechanisms to monitor and control these items. There is a risk of loss of
reputation and litigation by creditors. There is also a risk of power and water
disconnections by the utility companies.
189
Management attributed accumulation and non-clearance of domestic arrears to
underfunding of utility expenses which has been brought to the attention of
Ministry of Finance, Planning and Economic Development through various
communications. Management has in the meantime consulted with the Director
Internal Audit to have the electricity and water arrears verified with a view of
providing an adequate budget in FY 2015/16.
I reminded management that accumulation of domestic arrears is in contravention
of the commitment control systems and advised that the Accounting Officer
continue liaising with the responsible authorities for extra funding to clear the
outstanding arrears.
10.2 Mischarged expenditure
A review of the entity expenditures revealed that wrong expenditure codes were
charged to a tune of UGX.132,090,477 without authority contrary to chapter IV
section 156 of the TAIs. This practice does not only distort the intentions of
appropriating authority but also results into misreporting of the financial
statements balances.
Management explained that the Police budget is underfunded and as such it
cannot support the level of services that are required to fulfill its mandate. It was
therefore inevitable that certain items were used to fund critical activities resulting
into mischarges.
I advised management to streamline the budget process to ensure that sufficient
funds are allocated to each account code and to seek for authority before any
reallocations are made.
10.3 Unpaid assessment under Express Penalty Scheme recorded by URA –
UGX.672,130,000
The Express Penalty Scheme (EPS) was a policy introduced by Management where
traffic offenders were instantly apprehended, fined or cautioned. It was noted that
UGX.672,130,000 remained unpaid from Express Penalty Scheme assessment
190
captured on the URA portal as at 18th November 2014. The Police and URA have
not established any mechanism to follow up offenders for payment of the fines. It
was further noted that there is no consolidated record of offenders who are issued
tickets but do not report to URA for assessment. Under the circumstances, it was
difficult to enforce collection of all the revenue from the scheme.
Management explained that the Traffic and Road Safety(TRS) Directorate has
established mechanisms to follow up EPS defaulters. Such mechanisms include
daily tracking of EPS defaulters by EPS Tracking Unit on all major roads in Uganda.
Some traffic officers from stations that have internet connectivity have been
trained to track EPS defaulters. The World Bank is also supporting the TRS
Directorate through Ministry of Works and Transport to establish a Road Crash
Data Base System together with the computers and other necessary logistics that
will be used during the implementation and final rollout.
I advised management to implement the mechanisms in place to ensure that all
the revenue assessed is tracked and collected.
10.4 Land matters
a) Land titles and Land Fencing
Uganda Police Force has 665 pieces of land in the 106 Districts however; most of
them did not have titles as shown in the summary below. While 145 pieces of land
had been surveyed pending deed plans, 418 pieces of land were pending surveys.
Total No. of districts
where land is
located
Titled land Surveyed land
with deed plans
Pending surveys
and titling
process
665
Pieces
106 102 145 418
15% 21% 64%
Most of the land had not been fenced. Police was losing its land to rampant
encroachment due to lack of land titles and fencing. Some of the barracks affected
include the following:-
191
In Arua, 8 acres of land located south of the barracks that originally belonged
to the Police Special Force are now being used by the army. Also another
piece of land of about an acre is being claimed by a business man in town.
In Kiboga, the DPC was only able to show us the blue print of the area which
was also being claimed by a local politician.
It was difficult to establish the actual land area in Hoima Police station and
barracks as there was a claim of a two acre piece of land by the Municipal
authority.
In Masindi Police station and Barracks, there was encroachment of the 3 acre
piece of land behind the police station by the staff from water department.
Other stations and barracks without land titles include Nebbi, Yumbe, Atiak,
Gulu, Jinja, Kamuli, Iganga, Tororo, Lwakhakha, Mbale, Soroti, Serere,
Moroto, Kotido, Mityana, Mubende, Kyenjojo, Fort-portal, Kasese and
Kamengo.
Management explained that UPF lands department has extensively conducted
surveys and boundary openings of Police land but funding is inadequate to provide
fencing for the entire UPF stock.
I advised management to expedite surveying with a view of obtaining land titles in
order to protect the land from encroachers, and also source for funding to fence
off all police land across the country.
b) Encroachment of land at Nateete Police Station
Nateete land is titled on Plot 146 Kibuga, Block 18 measuring 3.252 hectares
registered under Uganda Land Commission on 5th July 2010 with user restricted to
Police Department (Police Station). However, the Force has not opened up
boundaries and fenced off the land to safeguard it from encroachers. The land has
since been encroached on and the Force has not used its Land Protection Unit
under CIID to recover the land. The extent of encroachment is shown in the
photos below:
192
Left: The trench that boarders with Police land, the rear view of encroachers
Right: The front view of the encroachers just overlooking the Station‟s park yard
Left: One of the permanent buildings built on Police land. The boundary of Police land is
slightly behind the building
Right: Some building belonging to encroachers. Inset is the Natete Police Station being
constructed.
Police land just adjacent to the Police station building under construction. The
encroachers have just sold it off to a private developer.
Management explained that the Nateete land was already encroached upon at the
time of titling. Boundaries were opened and the extent of the encroachment was
193
identified. Discussions have since been held with the encroachers and other
stakeholders and the Land Protection Unit was notified to take appropriate action.
The land that was not encroached upon is properly secured and occupied by
Police.
I advised management to continue using the services of its Local Protection Unit to
recover the land encroached on or take other actions which may involve legal
means.
10.5 Construction of Nateete Divisional Police Headquarters – Delayed
completion
The works at Nateete Divisional Police Headquarter were initiated after the station
was burnt down by rioters in 2010. The construction of the “roofed frame
structure” commenced in October 2011 and was supposed to be completed by
October 2014. The project under force account mechanism was originally
estimated to cost UGX.1.648bn but was later revised to UGX.2.358bn.
However, by February 2015, four months after the estimated completion date, the
works completed were estimated at only 75% according to the Project Manager.
By the time of inspection, there was no activity taking place and yet the condition
of the offices at the station was alarming. Although there were some building
materials on site, I was informed that funds for cement and labour to complete
casting the second floor slab were lacking. At this rate of progress, the building
might not be completed within the coming six years and the intended objectives of
the construction may not be achieved.
The photos below show the level of completion and the current structure used as
an office:
194
Above: Rear view of the building Front view of the building
Above: Materials at site (iron bars and timber)
Above: Current offices of the station
Management attributed the delays to inadequate funding. Although the completion
of the super structure required UGX.2.3bn, only UGX.1.8bn has been released and
spent on the Project. The balance of the funds to complete the Project was
budgeted but has not yet been released by MoFPED.
I advised management to continue engaging the MoFPED for adequate funds to
complete the building. Management was also advised to look into an option of
contracting out the remaining works to completion in order to solve the Station‟s
office accommodation problems and achieve the intended objectives of putting up
a model Divisional Police Headquarters.
10.6 Lack of staff accommodation at Nateete Police Station
195
Nateete Police Station has staff accommodation problems that need to be urgently
addressed. Police officers have no official accommodation but rather improvise for
their accommodation at the Police station themselves. The security of police
officers is at stake as they share accommodation with civilians who encroached on
Police land. The situation is made worse because the station is located in a
lowland which is more or less a wetland with full of mosquitoes and with poor
drainage. The poor living conditions impact on police officer‟s morale and
performance.
The physical situation can be observed from the photographs below:
Above: Self improvised accommodation for police officers.
Above left: A newly improvised shelter, on its left with poles, another officer trying to
put up his accommodation.
Above right: A police officer washing his clothes in front of his “house”. Inset is the
Police station building under construction
196
Above left: The old pit latrine and bath rooms. Officers still use the bathrooms for
bathing.
Above right: The new pit latrine police officers use.
In their response, management explained that due to inadequate budget, no funds
have been provided for construction of staff accommodation. The shortage of
funds for Police accommodation has always been highlighted in the Ministerial
Policy Statement (MPS) as presented to Parliament. The response from MoFPED
despite recommendations from Parliament to increase funding for Police
accommodation has not been positive. They further explained that staff
accommodation is being considered under the wider scope of Public Private
Partnerships for delivery of Police infrastructure.
I advised the Accounting Officer to mobilize funds by liaising with the responsible
Ministry and other stake holders to provide accommodation for the officers.
10.7 Construction of Yumbe Police Station
Construction of Yumbe Police Station started in Janury 2014 and was to be
completed by May, 2014. However, physical inspection undertaken on
31/01/2015 observed that eight months after the estimated completion date, the
project was estimated at 77% of completion. The construction had been at stand
still for six months since August 2014 when the building had just been roofed but
not plastered as shown in the photos below.
197
Roofed building but not yet platered
Above: Floor finishes not yet done Ceiling not yet finished
Management attributed delayed completion to inadequate funding. Ministry of
Finance Planning and Economic Development had promised to release funds to
complete the project in the 4th quarter of 2014/15.
I advised management to liaise with Ministry of Finance, Planning and Economic
Development and ensure that the funds are released.
10.8 Manafwa Police Station
The construction of the Police station was abandoned in June 2014 when it had
been roofed and ceiling casted. Windows, doors and their frames were not fitted
and the ceiling finishes and floor screed were not done. Besides, the station has
no provision for staff accommodation forcing the officers to rent outside the
barracks. The photos below show the structure:
198
Lack of good working environment impacts on the morale of the officers thereby
affecting the effectiveness and efficiency of the services delivered.
Management explained that the funding of this project was in phased manner.
Funding for the FY 2013/14 could only take the structure to the roofing level.
Although funds for completion were expected in 3rd Quarter of FY 2014/15, to date
no release had been effected which may further delay the completion.
I encouraged the Accounting Officer to continue requesting for funds and have the
Police station completed.
10.9 Olilim Police Training School (PTS)
(i) Inappropriate use of the Olilim PTS classroom block
A classroom block was constructed at Olilim PTS however; the block was turned
into accommodation for staff, an Armoury, a clinic and office. The workmanship
looked poor as evidenced by cracked floor which needed to be redone as seen in
the photo below:
Cracked floor
199
The building was not provided with the lightening arrester to guard against
lightening, and the rain gutters were not fitted to protect the building walls and
verandah from rain water. The staff provide accommodation by themselves and
use pit water for bathing and washing, which is hazardous for their health and
may negatively affect their effectiveness in providing police services. See photos
below:
Accommodation Accommodation bathing facilities
Management explained that lack of funds to urgently construct structures to house
the staff pushed the school administration to temporarily accommodate the
personnel in the classroom block. Plans to construct staff quarters are already
underway. The cracks in the classroom block were majorly attributed to the
vibrations resulting from explosive training conducted by Counter Terrorism
Directorate. The plan to supply safe water system to the training school has also
delayed due to lack of funds.
I advised management to plan accordingly and have the staff accommodated.
Efforts to have water supplied to the school is also awaited.
(ii) Delayed completion of the Administration block
The construction of the administration building was started in 2009 under Force
Account arrangement. The works have since stalled as the door shutters and
window glasses were not fitted, the floor screed was not done; only electricity
conducting was done while the ceiling had big cracks. The photo below shows the
incomplete administration block:
200
Incomplete administration block
Management attributed delayed completion to inadequate funding. The ceiling
cracks in the Administration block was a result of vibrations from the explosive
blasts during counter terrorism training that caused slight movements in the
ceiling.
I advised management to prioritize completion of the administration block.
10.10 Buliisa Police station and barracks
(i) Police station
The office block was constructed at an estimated cost of UGX.450million using
Force Account. The construction was to be completed within 10 months effective
December 2013, but this was not achieved due to late release of funds. Although
UGX.250 million was released within the first six months, completion of works was
delayed. Out of the balance required of UGX.200 million, UGX.137 million was
released in the second quarter of 2014/2015 while the remaining UGX.63 million is
yet to be released.
There was commendable work in progress by the time of the visit. The works
under execution included ceiling works, plumbing and block production. The
building however awaits fixing of steel doors, windows, plastering, floor screeding
and painting. The photos below refer:
201
It was also noted that the uniports being used need proper maintenance works
especially on the floor slabs for the officers to continue occupying them. Refer to
photos below:
In response, management indicated that funds for completion were expected in 3rd
Quarter of FY 2014/15, but these funds have not been released to date. Because
of insufficient budget, repairs of uniports have not yet been undertaken.
I advised management to mobilize the required funds from the responsible
Ministry and complete the building and also renovate the uniports.
10.11 Kabalye Police Training School (PTS)
Audit inspection of Kabalye PTS was carried out on 19thJanuary 2015. There were
three on-going construction projects:
a. A four (4) storeyed classroom block contracted by a local company.
b. An eight (8) unit accommodation block under Force Account.
c. Three dormitory (108 heads) blocks being constructed using hydra foam
technology.
202
A review of the construction works revealed the following:
a) Delayed completion of Four (4) Storeyed Classroom block
A contract for the construction of a Four-Storeyed Classroom Block for
UGX.4,324,964,501 was signed on 25th January 2011 between the Government of
Uganda represented by Ministry of Internal Affairs, Uganda Police Force and a
local company. The work was to be completed within 4 calendar months ending
24thMay 2011. However, despite various extensions of completion periods to 6th
March 2014 the Classroom Block had not been completed by 19/01/2015 when I
visited the site. I noted that delay in completion was partly contributed by late
clearance of contractor‟s certificates which has denied the trainees the benefits of
studying from a conducive environment, the objective for which the project was
started.
I advised management to intensify supervision and ensure that the works are
completed without delay.
b) Eight (8) Unit staff accommodation block by Force Account
Construction of the accommodation block begun in June 2014 and was to be
completed within eight months (end of February 2015). However, at the time of
inspection in January 2015, the project construction was behind schedule (as per
the photo below) with a few workers currently on site being assisted by four (4)
Korean expatriates under the supervision of the foreman and the engineer in
charge of the project. Labourers were sent on temporally leave due to lack of
funds to pay them.
203
Stage of completion of the accommodation block
Management attributed the slow progress to funding gaps which resulted into
phased construction.
I advised management to liaise with the responsible authorities for funding and
have the works completed.
c) Delayed completion of the Dormitory (108 heads) blocks being
constructed using hydra foam technology
The construction of the three dormitory blocks was started in May 2014 and
expected to be completed by October 2014. By January 2015 three months after
the expected completion date, one block was at the roofing stage, another one at
wall plate level, while the third was at slab level as shown in the photos below:
204
Construction dormitories under Hydra form technology
Management explained that insufficient funding led to some delays which affected
the contractors‟ cash flows, payment of labour costs and securing the building
materials and hence overall completion of the project works.
I advised management to prioritize the completion of the whole construction
project at the training school by allocating funds for the completion of the project.
10.12 Poor working conditions at Kanara Police Station
The station operates in a unipot and police officers lack accommodation facilities,
which negatively impact on staff morale. The OC Station informed the team that
the area local council offered land for use to the Police station but there is need
for lands department to formalize the details of titling. The photo below shows the
accommodation facilities:
205
Management explained that due to inadequate budget, funds have not yet been
earmarked for construction of the station and staff accommodation. It further
explained that the process of titling all Police lands is ongoing although the speed
was hampered by inadequate budget.
I encouraged management to continue engaging the MoFPED for appropriate
funding to improve its infrastructure. The Directorate of Engineering and Logistics
is also advised to follow up the acquisition of land title for the offered spaces.
10.13 Ishasha Police Post
The Police Post operates in a unipot. The Post is policed by seven officers; each
with one pair of uniform that was received in 2011. There is only one motor cycle
in good working condition and a bicycle that was grounded. I noted that policing
in the area poses a big challenge given the long distances involved. I informed
management that lack of adequate facilities negatively affects officers‟ morale and
hampers proper service delivery.
206
Uniports providing accommodation for staff
Management responded that funds have not yet been earmarked for construction
of the station and staff accommodation.
I advised the Accounting Officer together with the engineering directorate to
improve on the officers‟ welfare by constructing both the administration and
accommodation blocks, provide a vehicle and at least two pairs of uniform for
staff.
10.14 Fleet management
During audit inspection of Busia, Tororo, Mbale and Olilim, it was noted that some
fleet were not well maintained and their condition was deteriorating. Whereas
some vehicles were scrap and ought to have been boarded off, some lacked
spares and were grounded. The fleet has continued to lose value through
deterioration. It was further noted that although the Force has a draft fleet
management policy, it has not been approved to properly guide the fleet
management. The table and the photos below show the part of the deteriorating
fleet:
Police Station
Motor vehicle No. Make State
Busia UP 0284 Land Rover scrap
Tororo UP 1032 Lacks spares
Tororo UP 2611 Toyota Hilux Lacking Battery
Mbale No number Toyota Hilux scrap
207
Police Station
Motor vehicle No. Make State
Mbale UP 12299 Toyota Land cruiser Lacks spares
Mbale UP 2343 Lacks spares
Mbale UP 2819 Motor cycle Lacks spares
Mbale UDL 380R Motor cycle Lacks spares
Mbale Motor cycle Lacks spares
Olilim PTS UP 1038 Toyota Land cruiser Lacks spares
Amuria UP 2078 Motor cycle Lacks spares
Grounded vehicles
I advised the Accounting Officer to expedite the process of having the draft policy
approved. In addition, the Force should liaise with the Ministry of Works and
Transport to have the old fleet evaluated for possible boarding off to avoid further
loss of value.
10.15 Failure to complete evaluation for the purchase of the helicopters
Following the 2014 amendments to the PPDA regulations, post qualification
evaluation is mandatory under the Technical Compliance Selection evaluation
methodology. It was noted that the entity did not conduct post qualification as
required under the Reg. 15 (d) of the PPDA (Evaluation) Regulations, 2014.
Without post qualification the Entity risks awarding a contract to a bidder without
capacity to complete the contract.
Management explained that for the complex procurement such as procurement of
helicopters, the entity did a due diligence on manufacturers who were invited to
bid and did not envisage the need of carrying out a post assessment in this case.
208
The requirement was however noted and the entity will always comply in
subsequent complex procurements
The procurement and disposal Unit was advised to ensure that all stages of
evaluation are completed as established per evaluation methodology.
10.16 Lack of a policy on creation, development & maintenance of Police
Stations and Barracks
The Force lacks a policy on creation, development and maintenance of Police
Stations and Barracks in Uganda. This has been evidenced by the appalling state
of sanitation, poor/illegal electricity connection, limited safe and water access,
dilapidated and illegal state of infrastructure in the various police stations and
barracks. The barracks sampled and found to be in this state of affair include:
Masaka Police Station and Barracks, Kiboga Police Station and Barracks, Masindi
Police Station and Barracks and Nebbi Police Station and Barracks. Due to lack of a
policy, issues such as the required thresholds for in-house vs. outsourced
construction works and maintenance works, standard designs, details and
specifications procedures will not be clearly identified.
Management admitted to having no approved strategic investment plan and policy
guidelines on infrastructure. However, an accommodation master plan has already
been drafted together with the Construction Policy that is to address the key
issues pertaining to development and maintenance of infrastructure in the UPF.
The draft is yet to be presented to the Policy and Advisory Committee of UPF for
approval.
I await the approval and implementation of the policy.
10.17 Lack of adequate documentation of assets and other properties
There is inadequate documentation of assets and other properties of the Uganda
Police Force. Most of the RPCs and DPCs do not keep inventory of buildings, Land
and other Police properties. For instance, Atiak Police Station and Barracks lacks
an inventory register. In addition, the OC station complained of lack of uniforms.
209
Other stations & barracks without documentation of assets and other properties
are in Kiboga, Hoima, Masindi, Buliisa, Nebbi, Arua, Yumbe, Gulu, Lira and Apac.
There is a risk of loss of Police property.
I advised management to ensure that inventory of all police assets including land
and buildings is maintained at district and regional levels, while a central data
base for all the police assets is maintained at the directorate of logistics and
engineering.
10.18 Welfare issues
(i) Staff housing and accommodation
Due to old and inadequate houses, staff live in make shift structures (manyatas)
and dilapidated old buildings with leaking roofs, cracked walls and broken
windows/doors which expose occupants to hostile weather. Some Police Stations
and Barracks with poor accommodation include: Kiboga, Masindi, Bushenyi, Gulu,
Lira, Jinja, Kamuli, Iganga, Tororo, Mbale, Soroti, Moroto, Mityana, Mubende,
Kyenjojo, Sembabule, Masaka, Bushenyi and Hoima Police Station.
There is also a shortage of accommodation in Arua despite the renovation of 24
blocks. About 64 of the staff are not provided with accommodation and are renting
outside the barracks. In Yumbe, out of 51 staff at the headquarters, only 38 were
housed in the barracks and the rest were renting while some sleep in „manyatas‟.
In Atiak police station and barracks there is congestion in the four blocks meant to
house two families now housing four families. Poor accommodation negatively
affects staff morale and output.
Management explained that renovations and maintenance works have been
carried out in various barracks including Gulu, Arua, Atiak and Jinja Barracks.
However the rate of maintenance and reconstruction of staff accommodation is
very slow owing to budgetary limitations.
I advised management to consider regular renovation of the old police stations
and barracks and also construct new ones in districts without barracks as a means
of improving staff wellbeing.
210
(ii) Lack of Electricity connection
Many police stations and barracks do not have access to electricity. The electricity
connections to a number of Police stations and barracks is old and defective
causing electric shocks and damages to appliances. There is rampant irregular
connections of power to illegal structures (manyatas) which have become a threat
to the lives and properties of the officers and their families. Cases in point include:
Kiboga Police Barracks, Hoima Police Station, Nebbi Police Barracks, Lyantonde
Police Barracks, Mubende Police Station and barracks, Atiak Police Station and
Barracks.
In Jinja and Bushenyi Police Barracks, the electric wires were too old and exposed
on the wall surface. Some stations and barracks like Yumbe, Atiak, Kyenjojo, and
Kamwenge did not have electricity while Ibanda experienced unstable power
supply and the electrical circuit breaker and some of the electrical items are of low
gauge.
Management indicated that the Force is undertaking disconnections of all
substandard mains supply and replacing them with standard service cables.
Inadequate funding is however limiting the pace of executing the exercise.
I urged management to continue with the disconnections but also consider
providing electricity to all police stations and barracks throughout the country and
carry out routine inspection exercises for electricity connections on a quarterly
basis by a team of officials from Welfare, Logistics and Engineering together with
UMEME officials in order to ensure adequate connections and safety of the lives of
the police officers.
(iii) Lack of clean and safe water access
A number of Police Stations and Barracks especially in the recently created
Districts do not have access to clean and safe water. Atiak Police Station &
Barracks did not have water at the barracks and the nearest water source
“borehole” is about 300 meters away from the barracks. Arua Police Station and
211
Barracks is connected to tap water but water access is still a problem due to the
broken water taps. Other stations and barracks without water sources are in
Kiboga, Apac and Kamwenge. Safe water is essential for human life lack of which
negatively affects staff morale and output.
Management indicated that supply of clean piped water has been achieved in
many areas for example in Arua, Kyenjojo and Apac. Inadequate funding is
however limiting the pace of execution of this crucial activity.
I informed management that access to clean water is a right to life. I encouraged
it management to connect water to all the Police barracks and stations.
(iv) Poor sanitation
The sanitation condition in most barracks is appalling. There are no functioning
toilets since the old ones are filled up. The drainage systems are blocked and the
wastes spill onto the compounds. The barracks‟ compounds are very dirty, bushy
and have a bad odor. The conditions pose a health problem and lead to serious
outbreak of diseases if not attended to. The most affected barracks include:
Masindi Police Barracks, Arua Police Barracks, Gulu Police Barracks, Jinja Police
Barracks, Kamuli Police Barracks and Lwakhakha Police Barracks.
In Kamuli Police Barracks there was poor garbage and waste management.
Garbage piled up in heaps and some was scattered in the compound, while in
Lwakhakha Police Barracks, flashing toilets were not functioning well as manholes
had been blocked and sewage flows into the nearby river.
Poor sanitation, coupled with lack of safe water and accommodation have adverse
consequences on staff morale and output.
I advised management to consider carrying out total overhaul of the sewerage and
drainage systems in the affected barracks to avoid possible out breaks of diseases.
Regular inspection for cleanliness should be done by a team of officers from
welfare and the OC stations and barracks throughout the country. Funds should
be budgeted for quarterly maintenance of the stations and barracks.
212
10.19 Budget Performance
A review of the budget showed that UGX.369.85bn was released against an
approved budget of UGX.375.35 bn. A review of the budget performance for the
year 2013/2014 revealed that some planned activities and targets were partially or
not achieved at all. Details are as per the table below:
Activities Details Budgeted
activity
Achieved Out put Remarks
Output
125602
Criminal
Investigations
Enhanced response and
investigation of violent
crime.
Increased crime
detection.
Reduced CIID case
workload.
Improved case
management
40,900 violent
crimes to be
investigated
and passed on
to DPP
26,548 cases
investigated &
passed on to DPP
14,352 not
concluded.
Purchase 16
double cabin
pickups for
regional CIID
offices.
13 double cabin
pickups purchased
3 double
cabin pickups
not purchased
Setup AFIS
system for
KMP
Not done AFIS system
for KMP not
set up
Output
125603
Counter
Terrorism
Improved public
awareness on terrorism.
-Increased capacity of
personnel to identify and
respond to terrorism
threats/Incidents
To ensure a
proportion of
69% public are
aware of signs
of terrorism
35% proportion of
public are aware of
signs of terrorism.
34% are not
aware.
It is also
unclear the
methodology
used to
determine the
proportion of
the public that
are aware of
terror threats.
Output
125610
Police
Administration
and Support
Services
-Enhanced Information
sharing and investigation.
-Enhanced participation in
UN peace keeping
operations.
-Enhanced cooperation
180 cases of
international
criminals to be
repatriated.
156 cases of
international
criminals
repatriated.
24 cases not
handled.
213
Activities Details Budgeted
activity
Achieved Out put Remarks
with partner states on
transnational/crime.
Output 1256
Police
services
Recruit and train 2000
PPCs and 500 cadets.
Recruit and
train 2000
PPCs and 500
cadets.
3,500 PPCs and
Cadets recruited
and undergoing
training
Output 1256
Police
services
Start Implementation of
PPP.
PPP
implementation
PPP Program not
implemented.
PPP Program
not
implemented
apart from
forming the
Negotiation
team.
Complete
pending
constructions
Police headquarters
CIID wing
completed.
Police Stations:
Natete (Phase II)
completed.
Kiira Div. hqtrs
completed.
Mukono Police
completed.
Output
125677
Contractual obligation on
Public Order Management
bill fulfilled.
Contractual
Obligation on
Public order
Management
bill fulfilled.
Fulfilled the
contractual
obligation on Public
Order Management
equipment.
Payment
completed.
Output
125609
Police,
Command,
Control and
Planning.
Strategic Policing
finalized.
Strategic
Policing
finalized.
Five year strategic
Policing Plan
developed.
Awaiting
implementatio
n.
Unimplemented activities hamper service delivery, and the appropriating
authority‟s objectives may not be met.
214
Management explained that some activities could not be implemented because of
inadequate funding.
I advised management to ensure adequate planning and implementation of
approved activities.
11.0 UGANDA PRISONS SERVICES
11.1 Mischarged Expenditure
Parliament appropriates funds annually in accordance with the needs of each MDA.
This appropriation is implemented through the budget in which funds are tagged
to particular activities and outputs using account and MTEF codes. A review of the
entity expenditures revealed that UGX.637,537,384 was charged on wrong
expenditure without authority for the reallocation. This practice does not only
distort the intentions of appropriating authority but also results into incorrect
reporting of the financial statements balances.
Management explained that some of the outputs like construction and renovation
had no related budgets such as allowances spent on their implementation as such
funds had to be reallocated from other expenditure codes. Management regretted
the anomaly and promised to address the issue in the next budgeting process.
I advised management to streamline the budget process to ensure that adequate
funds are allocated to each account code, and utilize the budget as appropriated.
Authority should be sought before any reallocations are made.
11.2 Increased Payables Position
A review of the Statement of Financial Position revealed outstanding payables of
UGX.46,597,708,858. Payables worth UGX.18,028,999,698 were disclosed in the
statement of financial position as at 30th June 2014, implying that there has been
an increase in domestic arrears by UGX.28,568,709,160 (158%) from the closing
position of the previous year. It is evident that management has continued to
incur arrears without establishing sufficient mechanisms to monitor and control
215
them. There is a risk of loss of reputation and litigation due to non settlement of
creditors.
Management explained that the increase in payables was as a result of demand
for food items, electricity and water consumed during the year and not paid
accompanied by insufficient funding for these items.
I advised Management to clear the outstanding commitments as a first call on the
budget as guided by Accountant General. I also advised Management to liaise with
the relevant Government authorities for adequate funding.
11.3 Under performance of letters of credit
Statement of Financial Position had receivables of UGX.2,437,182,189 as at 30th
June 2014 which relate to outstanding letters of credit as at the end of year. Out
of this figure, LCs worth UGX.677,451,776 relate to the previous year in respect of
maintenance-civil, non-residential buildings and residential buildings. It was
observed that non-residential buildings and residential buildings LCs‟ performance
was quite low while maintenance civil did not perform at all. UGX.203,868,135 was
as a result transferred back to consolidated fund as shown below:
Activity
Balance
01/07/23
Paid
2013/2014 Balance C/F
Additions
2013/14
Transfer to
UCF
Balance
30/06/201
4
Maintenanc
e -civil 203,227,415 - 203,227,415 - 203,227,415 -
Non –
Residential
Building
207,691,509 146,196,986 61,494,523 - - 61,494,523
Residential
Building 886,931,752 474,201,914 412,729,838 1,590,798,548 640,720
2,002,887,6
66
Total 1,297,850,676 620,398,900 677,451,776 1,590,798,548 203,868,135
Underperformance of the letters of credit negatively affects the achievements of
the intended entity objectives.
216
Management explained that the letters of credit were still performing by the close
of the financial and some had fully performed awaiting payment of retention fees.
I advised management to continue supervising the projects that had not fully
performed and ensure that they are concluded.
11.4 Un-surveyed Land
The prisons service has a lot of un-surveyed land which needs formalization. Out
of 240 prisons, only 49 had land titles, 112 prisons land was not surveyed and 79
prisons are on either Kingdom or District land. Most of the untitled land is either
customary or mailo land under the Sub-county, Public/Mailo land under District
Land Boards or Mailo land under Buganda Kingdom. This poses a risk of
subdividing and allocating to private developers, and losing some of it to land
encroachers.
Management explained that the process of surveying prisons land where the entity
has control is underway. Negotiations to acquire kingdom land have also started.
Surveying and titling of land for the 60 prisons under Buganda Kingdom and 19
under District Local Government will only be possible after acquiring them.
UGX.1.12bn is required to survey the 112 un-surveyed prison land but only
UGX.100 million was provided. Due to budget constraints, survey of land will be
done in phases.
I advised Management to follow up with relevant stakeholders for purposes of
securing the required funding so that all the land owned by government is
surveyed and secured.
11.5 Congestion in prisons
Uganda Prisons Service has experienced an increase in the prisoners‟ population
since the merger and takeover of 174 Local Administration Prisons in 2006, from a
daily average of 19,179 prisoners in 2006 to 39,844 prisoners by January 2014. In
June 2014, Prisoner populations had risen to 41,516 prisoners. According to
management the current housing capacity is at 16,040 prisoners only. Compared
217
to the current prisoners‟ population (41,516), 25,476 prisoners cannot be
accommodated now. See the table below.
Categories Males Females Total
Convicts 17,382 720 18,102
Remands 22,136 1,038 23,175
Debtors 203 36 239
Total 39,722 1,794 41,516
Percentage (%) 95.7 4.3 100
Approved Capacity 16,040
Occupancy Rate (%) 258.8
Not accommodated 25,476
Increase in congestion of prisoners was associated with the following challenges:-
Overcrowding: I noted that 5 prisons that had occupancy rate of above
500% as indicated below. Space has become a challenge with the
growing numbers.
Prison Occupancy rate
Gulu 508%
Ntungamo 720%
Kisoro 906%
Kabale 651%
Rukungiri 530%
Low staff Numbers: With the increase of prison population, more staff
are needed to exploit production potential of prisons farms, match the
challenging profiles of offenders, monitor prisoners and reduce escape
routes. This has not been fully achieved because of a ban in recruitment.
Provision of basic necessities of life to both prisoner and staff:
These include uniforms, beddings and staff accommodation. This has been
a challenge due to the limited funding of the entity.
218
Increased food budget: The required annual prisoner‟s food budget for
the next financial year has been provided at UGX.50.006bn. However, the
budget MTEF provision has been set at UGX.23.298bn thus creating a
shortfall of UGX.26.708bn.
Increased utility costs: Initially, 36 stations were connected to electricity
power but currently 77 stations are connected. A total of 63 prison stations
are connected to water compared to 32 formerly connected as a result of
reduction of the bucket system. The water and electricity tariffs have thus
gone up from UGX.1,912 in 2006 to UGX.2,353 in 2013 and UGX.426/kwh to
UGX.525/kwh respectively.
The numbers have caused congestion of the prisons thus increasing the risks
of prisoners‟ escape, poor hygiene, diseases and rampant strikes as the
prisoners continue scampering for the little resources.
Despite the increase in the number of prisoners and utility connections,
accommodation and utility facilities have not increased proportionately.
Management attributed the problem of prisons congestion to the high prisoner
population growth of 10% per annum which is not matched with accommodation
requirements. The majority of prisons require expansion, major overhauls,
renovations, and re-construction but the prisons service lacked sufficient funds. A
proposal for renovation of prisons was submitted to Ministry of Finance, Planning
and Economic Development and a phased approach over a period of 5 years was
proposed. Ministry of Finance, Planning and Economic Development promised to
handle the renovation of prisons over a medium term.
I advised management to continue lobbying for additional resources to improve
the accommodation facilities of the inmates.
11.6 Budget Performance
A review of the budget performance for the year 2013/2014 revealed that some
targets were not achieved despite receiving 99% of the approved budget. Details
219
are as per table below: Unimplemented activities hamper service delivery, and the
appropriating authority‟s objectives may not be met.
The Accounting Officer explained that some activities were not completed within
the year, and spilled over to the subsequent year. The delay was attributed to late
Key activities Performance/Achieved output
Survey and title 9 Prisons &
open boundaries for 4 Prisons
09 prisons land surveyed, 06 land titles
obtained and only 02 boundaries opened.
62% performance
Development and installation of
irrigation system at Ruimi
Prison Farm; Setup irrigation
system at Ruimi Prison Farm.
Technical study design and development of
irrigation system at Ruimi, Ibuga and Mubuku
on-going; Schematic designs completed but
Irrigation system not developed yet.
Renovation of Rwimi Prison Plumbing and electrical installations not done
yet
Construction of Kaabong prison Contractor secured, works not yet completed
Construction of Amur Prison Irrigation system not developed yet.
Construction of a second Twin
prisoner's ward at Ruimi Prison
Fixing of water tanks, connecting water and
electricity is ongoing. At roofing level by
January 2015
Construction of a cotton farm
store at Mobuku
Work on the super structure is ongoing,
currently at foundation stage; expected date
of completion is December 2014. Not
completed.
Estimated at 80% by January 2015
Construction of 14 blocks of
staff houses at Muinaina,
Kiyunga, Ruimi and Kapchorwa
Prisons.
All the building materials have been procured
and delivered on site. Kapchorwa is at roofing
stage and expected completion date for all
sites is December 2014, Muinaina nearing
completion.
500 staff to benefit from Duty
Free Shop
343 staff benefitted from Duty Free Shop.
31% did not benefit
220
acquisition of land from the districts, heavy rain at the beginning of some of the
projects and lengthy procurements among others. The Accounting Officer however
indicated that the activities were ongoing.
I advised the Accounting Officer to ensure that all planned activities for which
funds are released are carried out as planned.
11.7 Field inspections
A) Mbale Main Prison
During field inpection, it was observed that the prisons wards were leaking, some
prisoners uniforms were were old and some had got torn. The perimeter fence
was damaged and needed repair. The pictures below refer.
Leaking roof
Torn inmates‟ uniforms damaged fence
221
The inmates are living in poor health condition with a possibility of inmates
escaping because of the damaged fence. The inadequate clothing undermines the
status of Uganda prisons.
Management in their response indicated that the majority of prisons structures
were constructed in 1920s aimed at a smaller population. The structures have not
had major overhaul, renovation and maintenance. The Prison is among those
identified to be upgraded through renovation and new construction in the strategic
investment plan III (2012/13 – 2016/17), while the prisoner‟s uniforms will be
addressed soon.
I advised management to expedite the renovations of the prison to ensure that
prisoners‟ rights are not denied.
b) Ruimi Prisons Farm - Delayed construction of a twin ward
The construction worth UGX.618,909,737 commenced on 27th March 2014 and
was expected to be completed by 27th Sept 2014. The completion date was later
extended to 30th December 2014 with a variation of UGX.24,976,180 due to
changes on the ground beam and filling murram due to its location (earthquake
prone area). Delayed construction has negatively impacted on the intended
objective of availing accommodation for prisoners. By January 2015, the building
was at roofing level as shown in the photo below:
Construction on-going
Management attributed the delays to the heavy rains at the start of the project.
222
The contractor has been given up to April 2015 to have all the activities completed
and the wards handed over for occupation.
Management action on the matter is awaited.
c) Mubuku Prisons Farm - Delayed completion of the construction of
a cotton store
Construction of the cotton store at Mubuku Prison was contracted by a local
company at a contract price of UGX.149,982,339. The project that started on 26th
May 2014 was to be completed by 15th.January 2015 after an extension of two
months. However, during audit inspection in January 2015, the cotton store had
just been roofed and plastered outside but the doors had not been fixed and the
floor was yet to be casted and screed. The construction has been delayed, and
this has had a negative impact on storage of produce. Details are as shown in the
photos below:
Plastered outside walls
223
Inside walls not yet plastered Floor not yet casted
Management in their response attributed the delay to heavy rains at the start of
the project. Management promised that the works will be completed by end of
March 2015.
I advised the Accounting Officer to compel contractor to complete the construction
of the store on the agreed timelines.
12.0 JUDICIARY DEPARTMENT
12.1 Arrears of rent
It was noted that out of the payables of UGX.6,834,553,806 reflected in the
financial statements, UGX.3,010,447,187 comprised of sundry creditors (landlords)
who have not been paid rent due from use of their premises by Courts. Delayed
payment of rent may lead to reputation risk and eviction of the Courts to the
embarrassment of the Judiciary.
The Accounting Officer explained that rental bills accumulate because of the
increasing demand for Judicial Services yet the Judiciary lacks self-owned premises
across the country. Further, the funds released for rent are inadequate leading to
delayed payment to the landlords. The Accounting Officer further indicated that
the entity has requested for a supplementary from Ministry of Finance, Planning
and Economic Development to settle the arrears.
224
I await the results of management efforts. It is also advisable that in the long run
Judiciary should consider to construct its premises to minimize funds incurred in
rent.
12.2 Deposit of third party funds on operations account
In the miscellaneous application number 44 of 2012, the honourable commercial
Court delivered a judgment and awarded damages of UGX.494,990,000. The
amount was deposited on the entity operational account in the court of appeal
despite the fact that the Judiciary has an account in Bank of Uganda where
deposits are paid. I explained to the management that the risk of utilizing these
funds for court operations was high. A review of the bank statement indeed
revealed that the court had borrowed these funds for its day to today operations.
The Accounting officer explained that the deposit was as a result of a court order
and could not change until another order is issued after disposal of the case.
I advised the Accounting Officer to relate with the court and ensure that the funds
are deposited in the appropriate bank accounts.
12.3 Human Resource Management
a) Staffing Gaps
According to the staff establishment, 297 posts within the Judiciary had remained
vacant during the year. These included among others 8 Justices of Court of
appeal, 4 Justices of the Supreme Court and 8 High court Judges. Lack of staff in
vital positions affects the performance and overall achievement of organization‟s
goals and objectives. This could also be a contributory factor to case backlogs.
The Accounting Officer explained that the vacant posts were declared to the
Service Commissions and management await its decision.
I advised the Accounting Officer to liaise with the relevant stakeholders and
ensure that vacant posts are filled.
225
b) Performance Management- Absence of Appraisal system for
Judges
Section (A-m) 3 of the Public Service Standing Orders requires all responsible
officers to manage the performance of their Ministry or department to ensure that
the performance of organizations and individuals directly contribute to improved
service delivery and attainment of national development objectives.
However, it was noted that this mechanism did not exist in Judiciary. The entity;
Does not have annual performance plans developed at the beginning of every
financial year for Judicial Officers.
Does not hold performance review meetings to review the performance of the
Judicial Officers.
Does not monitor and evaluate performance of the department and individual
staff.
Does not prepare annual performance reports for both Judicial and non-
Judicial staff.
Does not carry out staff appraisals of both Judicial and non-Judicial staff.
In absence of a performance management system, staff will not have focus on the
organizational goals and priorities, show commitment to their work and also
improve on their competences through constructive feedback.
The Accounting Officer responded that Judicial Officers on the lower bench and
the non-Judicial Officers are appraised through the normal Public Service Appraisal
System. However this appraisal system appeared not appropriate for the Judges
and Justices. As a result of this, an appraisal tool that covers all officers within the
Judiciary has been developed by a consultant and is now being piloted.
I urged the management to have the appropriate tool finalised for implementation.
12.4 Department structure and issues of strategy
a) Operations of the High Court Circuits
Following the 1997-1998 post Constitution Judicial restructuring report, Judicial
services were decentralized to now twelve (12) High Court circuits. This was
226
intended to improve delivery of justice to all Ugandans. It was noted that whereas
the High Court circuits were supposed to be replicas of the High Court, the
concept of divisions at the High Court has not been rolled out to the High Court
circuits. This sometimes leads to some cases being transferred from High Court
circuits to the respective divisions at High Court in Kampala. This does not only
make justice expensive for the litigants, but can be a burden to the divisional
judges at the High Court hence leading to case backlogs. It may also cause
redundancy of the resident judges.
The Accounting Officer responded that by resolution of Parliament, the Judges of
the High Court are to be increased to 82. This will enable additional Judges to be
recruited to facilitate creation of additional High Court Circuits. The creation of
divisions at circuit level is a long term strategy which will be debated by the
Judiciary. In the meantime, the Resident Judges in the High Court circuits have
unlimited original jurisdiction and therefore handle all types of cases.
I advised that management considers the concept of High court circuits for
implementation.
b) Narrow Structure of the Court of Appeal
The Court of Appeal has jurisdiction to hear appeals from the High Courts. These
appeals come from court rulings of the High Court circuits and the High
Court divisions-including Civil division, Criminal division, Commercial division, Anti-
corruption division and Land division. A narrow structure of the court of appeal
was noted in as far as the handling of cases from the High Courts is concerned.
The eight divisions of the High Court and the High Court circuits all feed into the
Court of Appeal. This does not allow smooth flow of cases.
The Accounting Officer responded that Management agrees with the need to
expand the structure of the Court of Appeal. However, this is to be preceded with
a business study to determine the wage and non-wage requirements, the
infrastructure and case load.
227
I advised that there is need to broaden the structure of the Court of Appeal to
match with the High Court structure. This may go along in solving the case
backlog in the court.
c) Independence of the Judiciary
Article 128(1) of the Constitution of the Republic of Uganda states that in the
exercise of judicial power, the courts shall be independent and shall not be subject
to the control or direction of any person or authority. However, contrary to
legislation, the Judiciary has failed to assert its independence as it is treated as a
Department rather than an arm of Government and has no financial independence
and cannot recruit its own staff.
The Accounting Officer responded that the Draft Administration of Judiciary Bill
2013 was presented to Cabinet. Further discussion of the Bill was deferred until
Article 172 of the Constitution is amended to allow for the delinking of certain
cadres from the Public Service to the Judiciary.
I advised that effort should be made to delink the Judiciary from the main stream
Public Service in order to achieve autonomy in the management of its financial
and human resources in a bid to achieve its strategic objectives.
d) Absence of a Client Service Charter
Good practice requires that the judicature formulates Client Service Charter
showing commitment to provide quality service and how to work best with general
public. Over the years, the Judiciary has been in the spotlight on issues regarding
the integrity of both Judicial and non-judicial officers. Despite the negative
publicity, the Judiciary has not developed a client service charter.
The Accounting Officer responded that a draft Client Charter for the Judiciary has
been developed and will be operationalized in FY 2015/2016.
I advised the Accounting Officer that there is a need for the Judiciary to expedite
the implementation of the client charter that reflects its commitment to providing
a high quality service, and how the Judiciary can work hand in hand with the
general public to improve services.
228
12.5 Mischarge of Expenditure
The Parliament of Uganda also appropriates funds annually in accordance with the
needs of each MDA. This appropriation is implemented through the budget in
which funds are tagged to particular activities and outputs using account and
MTEF codes. A review of the payments for the Judiciary revealed that payments
amounting to UGX.423,909,500 were not charged under the appropriated and
rightful codes. These payments were made without requisite authority. The
practice does not only undermine the budgeting process and the intentions of the
appropriating authority but also leads to financial statements misreporting.
The Accounting Officer explained that the Judiciary has endeavoured to streamline
the budget in order to minimize mischarge of expenditure.
I advised that Management should allocate enough funds to budget lines in
accordance with priorities and reallocations should be undertaken whenever there
is need in accordance with the regulations.
12.6 Budget Performance
Although the Judiciary received 98% of its budget, there was notable under
performance on the planned activities for the period under review. The table
below refers:
Planned
Activity
Planned Output Actual
Output
Variance Planned
Output
Cost
Actual
Output
Cost
Budget
Spent%
Disposal of
appeals and
suits in High
court
3,094 Criminal
suits
1,857
Criminal
suits and
391
criminal
appeals
disposed of
-846 21.154bn 21.696bn 102.6%
3,056 Family suits 2,186
family suits
disposed of
-870
388 Anti- 145 cases -243
229
Planned
Activity
Planned Output Actual
Output
Variance Planned
Output
Cost
Actual
Output
Cost
Budget
Spent%
corruption cases disposed of
3,070 Civil suits 2,558
Civil suits
and 234
Civil
appeals
disposed of
-278
1,297 Commercial
suits
1,754
Commercial
suits
disposed of
+457
1,546 Land Cases 1,413 land
cases
disposed of
-133
Disposal of suits
and appeals in
Magistrate
Courts
109,261 cases
disposed of
63,297
cases
disposed of
-45,964 15.899bn 15.942bn 100.3%
Construction
and
rehabilitation of
Judicial Courts
Commence
construction of
Lugazi and
Mayuge
Magistrate courts
No output The two
courts not
constructed
1.175bn 2.006bn 170%
The underperformance escalated the case backlogs and negatively impacted on
the achievement of the Judiciary mandate.
The Accounting Officer explained that the planning was ambitious and furthermore
the funds allocated were not only meant for court sessions but for other attendant
activities like visiting locus in quo, vehicle maintenance, fuel, rent and general
supplies of goods and services.
230
I advised the Accounting Officer that the Management team should make realistic
plans and ensure that all planned activities for which funds are released are
completed to enable the department deliver its mandate.
12.7 Field inspections - Books of Accounts and other operational concerns
Field inspections revealed the following;
No Court Observations
1 Jinja High Court and
Chief Magistrate‟s
Court
The High Court has a Senior Accounts Assistant
appointed as the substantive cashier. The cashier had last posted the books in March
2011.
Similarly at the Chief Magistrates court (which has
an Accounts Assistant), the books were last posted
in July 2009.
2 Kyegegwa Grade 1
Court
The Court is in rented premises and the space is not
adequate for Court operations.
This court has a wider coverage with distant places
in cases of visiting locus but it has no office vehicle thus making it costly to use public means.
3 Iganga Chief
Magistrate‟s Court
The court does not maintain an assets register.
The computers are not connected to CCAS System.
Revenues collections are done in the bank after
assessments by the Ag. Cashier, but it was noted
that the cashier does not issue general receipts. The court has no substantive cashier and all
accounts related functions are carried out by
records assistant. The cashbook is wrongly posted
for example bank charges which are expenses were recorded on the debit side of the cash book.
4 Kaliro GR I Court
There are no books of accounts maintained at this
court. This is because the Ag. Cashier lacks the competence to perform accounts related functions.
The Court has no exhibit store and the exhibits are
not recorded in the register. Exhibits are kept in the
registry. The returns are not submitted in time due to laxity
by the clerk.
5 Mbale High and Chief
Magistrate‟s Court
The mandatory books of Accounts such as Revenue
Collectors cash book, Bail deposit cash book,
Operational cash book, were in place but not updated.
Cases registers are in place but not properly posted.
Although there are many clerical officers, the team found out that there is no single officer responsible
for each register. There are gaps left in between the cases registered.
231
No Court Observations
The Magistrates do not sign in the case registers, especially cases registered as complete to confirm
the results recorded in the registers.
Magistrates do not regularly supervise the Clerks to
confirm that, whatever is recorded in the register is a true picture of what inspired in the court.
Case returns are prepared but not submitted on
time. There were also cases of use of white wash to
correct mistakes in the registers. This is very risky in
that anybody can tamper with the information in the register.
Document filing was also found to be poor.
Though the court had an exhibit stores, it was
leaking and the floor is peeling off.
6 Sironko GR 1 Court The cashier does not issue general receipts to the
litigants, there were no monthly bank reconciliations.
Accountabilities for funds advanced for March 2014
were unavailable.
Case registers were not properly posted, there are
many blank spaces left in between the cases registered. The magistrates do not sign against the
results recorded by the clerks in the registers. Document filing was poor, files having loose
papers which are not numbered according to their
order.
7 Kabale High Court and
Chief Magistrate Court
Case registers are poorly posted, there is no specific
staff to record cases. There are gaps left in between cases registered. Mistakes are corrected by
overwriting, crossing and use of white wash. The Magistrates also do not sign the results for
completed cases entered in the registers by the
Clerks. Access to the Registry is not restricted. Document filing is not properly done. The
documents are not are not numbered and they are
just loose in the files. The exhibits register is in place but exhibits are not
regularly recorded when received.
It was also noted that, there is a dilapidated store
constructed with old iron sheets. The door does not even lock properly, risking exhibits to theft. It was
established that in January 2014, thugs broke into
the store and stole two bicycles and ten plastic chairs.
8 Nakasongola C/M
Court
Cases registers are in place but are not properly
posted: Criminal cases are mixed up with Juvenile
cases; there are gaps left in between the cases registered. The complete cases are not signed off in
the register by the chief magistrate The court has got enough space for the existing 9
staff. The offices are fairly furnished but there is no
232
No Court Observations
photocopier, filing cabinet, and Solar system/ Generator because they do not have stable power.
Nakasongola court makes returns on a monthly
basis as required, but the reports submitted in most
cases are inaccurate for instance in February 2014, 46 criminal cases were reported and yet the actual
cases registered were 49. In January 2014, they reported zero civil cases and yet 2 were registered,
in March 2014, they registered 28 civil and reported 30.
9 General observation
across the Courts
In the courts where there is electricity and water, it
was noted that, the Office Supervisors do not
maintain utility ledgers. They did not even know the meter numbers and account numbers for their
respective courts. The bills were submitted for
payment as received by the courts. It was therefore not easy to verify these bills when the
courts submitting them have not given assurance that they are genuine.
The weak record keeping is likely to lead to inaccurate reporting on cases
reported and handled, loss of revenue, misuse of assets and, poor accountability.
The Accounting Officer explained that Management has put in place mechanisms
to address the weaknesses identified above through; training of staff, recruitment
and re-assignment of responsibilities
I await the results of management efforts.
12.8 Loss of motorcycle
Motorcycle Registration No. UG0311J attached to Commercial court Division was
stolen at Senate Building Makerere University on Monday 6th February, 2012 from
a Process Server who had gone to serve a ruling notice. The circumstances
surrounding the theft of this motorcycle were not clear. The place the motorcycle
was stolen from is not where the server notice was to be delivered. In addition,
the time the officer claims the motorcycle was stolen (2.00 p.m.) differed from the
police reports (12:46 p.m). These inconsistencies in reporting were suspicious.
The Principal Human Resource Officer was requested by the Transport Officer to
take action against the Officer but there was no report to show whether
233
disciplinary action was taken against him. Failure to impose strong regulations on
officers upon any irregularity may lead to loss of Government resources.
The Accounting Officer explained that the case was reported to Police and
investigation is on-going.
I advised management to follow up the matter to conclusion.
12.9 DANIDA UGANDA GOOD GOVERNANCE PROGRAMME (UGOGO) –
SUPPORT TO THE JUSTICE, LAW AND ORDER SECTOR 2011-2016 31ST
DECEMBER, 2014
Use of out-dated Financial Policy and Procedures Manual
The Project has been using the Financial Policies and Procedures Manual
developed as far back as 2001 for the Judiciary Danida Support to discharge its
accountability function to DANIDA and the Government of Uganda. At the
beginning of the third phase of the Danida Support to Judiciary in March 2006, the
Registrar Planning and Development in consultation with the Project Director was
to propose amendments to these financial procedures to the Technical Committee
and facilitate the introduction of new instructions. I noted that no amendments
have since been made to these policies.
Management responded that they have been aware of the need to update its
Financial and Procurement Guidelines and stated that a consultant has already
been engaged to update the guidelines in close consultation with programme
management and the Royal Danish Embassy.
I await the out come of management efforts to update the Manual.
Non Compliance with Steering Committee meetings
The Programme policy document provides that a Steering Committee composed of
the Chief Justice and members of the Judiciary Planning and Development
Committee, and the Royal Danish Embassy would be the forum for the overall
234
coordination at policy level and was required to meet twice a year. However, it
was noted that during the year, the Steering Committee met only once. There is a
risk that the project may not have obtained the required guidance of the steering
committee.
Management explained that the infrequency of meetings was partly due to the fact
that for more than two years there was no substantive Chief Justice and the
Project was not clear as to whether the Acting Chief Justice can also fulfil the role
of the Chairperson of the Steering Committee.
I advised Management to organize regular meetings for the effective
implementation of the work plans.
Absence of Approved List of Suppliers
Section 7.2.2 of the Daninda Judiciary Support Project Financial Policies and
Procedures Manual states that; for all general stores items, an approved list of
suppliers will be maintained. These suppliers should have verifiable premises, be
registered for VAT purposes and issue valid tax invoices. It also states that the list
will be reviewed and updated regularly by the Technical Committee. However
during the audit it was observed that the Project did not maintain such a list.
Management explained that the Project uses a list of suppliers that consists of;
Firms from the PPDA Register of providers‟ website; Judiciary‟s list of prequalified
suppliers; and firms that were successfully used under the HUGGO phase and
have shown high quality service.
I advised Management to ensure compliance with the procedures Manual.
Repair of X-TRAIL Motor Vehicles
A contract for the repair of three x-trail motor vehicles- UG 290J, UG O271J, and
UG 274J of UGX.51, 170,000 was awarded to ACE Motors. It was noted that the
motor vehicles were not assessed before and after the repairs by mechanical
235
engineer. There are risks that the repairs where over costed or not completely
done as per the proforma invoices indicated leading to loss of programme funds.
Management responded that they had taken note and will in future ensure that an
independent assessment is done before and after repair of the vehicles. The
updated Financial Management Manual will also include clear policies regarding
the repair of vehicles.
I advised Management to source for technical support from competent individuals
in future.
Non-Deduction of Withholding Tax (WHT):
It was observed that WHT totalling to UGX.75,955,526 was not deducted whilst
effecting some payments in contravention of the Income Tax Act.
Failure to withhold tax could lead to penalties as stipulated in the Income Tax Act.
Management admitted the shortcoming and explained that they will endeavour to
recover WHT from the listed suppliers. Management further indicated that
clarification on tax exemptions and their applications will be sought from the Royal
Danish Embassy and URA. Respective provisions will thereafter be included in the
updated Financial Management Guidelines.
I advised Management to consult with Royal Danish Embassy and URA regarding
the Income Tax Act provisions.
i. Non-Deduction of PAYE:
The Income Tax Act, 1997 (as amended) section 117(1) states that; every
employer shall withhold tax from a payment of employment income to an
employee as prescribed by the regulations. During the year, the project paid
UGX.32,150,000 as monthly allowances to; the Project Administrator, Office
236
Attendant in charge of Resource Centre and the Driver. The project however did
not deduct and pay to URA PAYE of UGX.9,645,000.
This is contrary to the Income Tax Act requirement and could lead to penalties
from URA.
Management admitted the shortcoming and explained that they will recover the
PAYE from the employees. Management further stated that with effect from
January 2015 PAYE is deducted from all employees.
I advised Management to have consultations with the Royal Danish Embassy and
URA in respect of the tax provisions.
ii. Work plans and budgets
Budget Shortfall
I noted a shortfall of funding of the approved work plans of the Programme. The
total budget funding for the year under review stood at UGX.3,052,299,861 and
only UGX.2,075,513,072 was received resulting into a budget shortfall of
UGX.976,786,789.
The funding shortfall may in turn affect the implementation of the planned
activities.
Management explained that the commitments made by the Embassy towards the
project remain valid for the entire programme period. However, as part of due
diligence, the Embassy only disburses funds to the project on a needs basis that
is; according to the approved work plan/budget and upon receipt of satisfactory
progress and financial reports as well as evidence of reduced balance on the
project account.
I advised Management to undertake realistic budgeting in order to implement the
activities in accordance with approved work plans.
237
Physical Budget performance-Non-Partial implementation of planned
activities
UGOGO Project is component 2 of Sector Investment Plan III (SIP III) and is
aimed at promoting the rule of law as its overall strategic goal. In order to achieve
this goal, strategic objectives and activities are designed and medium term plans
are prepared in form of approved annual work plans and budgets.
A review of the Project's performance as per DANIDA 4th progress report (Work
plan IV) revealed that a number of activities remained un-implemented during the
year while others were partially implemented. The table below refers.
Targeted
outputs
Planned
activities to
achieve the
targeted out put
Budget
(UGX.)
Expenditu
re(UGX)
Status Remark
1 IMPLEMENTATION OF THE STRATEGIC INVESTMENT PLAN
1.1 JSIP 111
achievements
and challenges
in
implementation
identified
Conduct
consultancy for
mid-term review of
JSIP 111
(inclusive of
coordination costs)
84,800,000 1,360,000 Not
completed
(98%
under
performan
ce)
Terms of
reference for the
consultancy have
been drafted and
circulated for
review. Funds
reallocated to
cater for 3
trainings; one in
customer care
and another in
human rights.
PERFORMANCE ENHANCEMENT
2.2 Staff ownership
and adoption of
developed
appraisal tool
promoted
Conduct 3
sensitization
workshops for
Judiciary staff on
the use of the
developed
135,000,000 -- Not done
(100%
under
performan
ce)
Pending
completion of
development of
the Judiciary
performance
enhancement
238
Targeted
outputs
Planned
activities to
achieve the
targeted out put
Budget
(UGX.)
Expenditu
re(UGX)
Status Remark
performance
enhancement &
appraisal tool (100
pax per workshop)
tool.
3 CASE BACKLOG REDUCTION
4 REFORMS IN JUDICIARY TO ENHANCE ACCESS TO JUSTICE.
4.1 Information on
Judiciary
policies, cause
lists and
procedures
readily available
to the Public
Procure and install
one computer set
(monitor,
CPU,UPS, printer &
software) on 26
information desks
in Central and
Eastern regions
130,000,000 28,686,000 Not
completed
. (78%
under
absorption
/performa
nce)
14 Computers
procured pending
installation.
4.4 Adoption of
standard
punishment
measures for
criminals
Conduct two
sensitization
workshops on the
developed
Sentencing
Guidelines
90,000,000 -- Not
done.(100
%%
under
absorption
/performa
nce)
A proposal was
made for these
funds to be
reallocated
towards the roll
out of Plea
bargaining.
Management explained that the failure to fully implement planned activities
occurred due to various challenges faced during the year such as; dependence on
out-dated Procurement and Financial Management guidelines, increased backlog
of activities due to implementation of activities from previous work plans,
dependence on various departments and officers in implementation who were also
engaged in other Court business, some activities being reliant on the completion
of others, and uncertainties that occurred during the period regarding the
continuity of the Project.
239
I advised Management to ensure commitment to the execution of project activities
to enable timely attainment of the Programmes strategic objectives, by addressing
the above short comings.
Audit inspections
Field inspections were carried out at Jinja, Gulu and Mbarara High Courts. The
objectives of the inspections were to establish supply of recording equipment,
confirmation of installation and functioning of recording equipment in the courts,
and, existence and functioning of the small claims procedure whose subject matter
does not exceed UGX.10,000,000.
The equipment was supplied and installed and the small claims procedures were
implemented in the courts. However, the following exceptions were noted:
(i) Mbarara High Court - Court Recording Equipment:
The court recording equipment was supplied by the Project, comprising of; 8 micro
phones, Dell monitor, key board, CPU and mouse, PA Amplifier, Timer, D-Link easy
smart switch, Head phones, 4 Speakers, Recorder, and the transcription set that
including a CPU (Lenove) Monitor, Key board, Mouse and headphones.
However, it was noted that whereas the Court recording set was functioning and
was being put to use, the transcription set was not being utilized due to the
challenges below;
At the time of delivery, the CPU (Lenovo) power cable was not delivered with
the rest of the equipment. The IT personnel who installed the equipment
explained to the staff at the Mbarara High Court that the CPU uses a different
cable from those used by other brands and that meant they would have to
wait for it to be delivered. This has not happened to date. Therefore, another
computer is used for transcription and this takes place after the court session
is done.
Mbarara High Court lacks a transcriber. When the equipment was supplied and
installed, it required two personnel; a recorder and a transcriber so that during
a court hearing, the recording and transcription activities can take place
simultaneously. This is not possible at the Court, as the position of the
240
transcriber is not filled. Therefore the recorder ends up typing what has
transpired after the court session is done.
Management explained that they had not received any official communication
regarding the missing power cable. However, Management has taken note of the
issue and will follow up.
I advised Judiciary ICT Department to follow up the matter and ensure that the
equipment can be put to use.
13.0 DIRECTORATE OF PUBLIC PROSECUTIONS
13.1 Mischarged Expenditure
A review of the Directorate‟s expenditure revealed that the entity charged wrong
expenditure codes to a tune of UGX.454,431,122. The practice of mischarge of
expenditure violates the TAI, undermines the importance of the budgeting process
as well as the intentions of the appropriating authority and leads to misreporting.
The Accounting Officer explained that he was challenged with budget ceilings
within the Medium Term Expenditure Framework (MTEF), where only a few
priority areas could be funded. That left out a number of important areas either
under-funded or completely un-funded. Further, there arose a number of cases
that required the co-opting of a wide range of experts and staff at a scale that was
not anticipated during the budgeting process. However, the Accounting Officer
indicated that the Directorate has taken administrative measures to improve on
Budget discipline.
I advised management to streamline the budget process to ensure that adequate
funds are allocated to each account code and utilize the budget as appropriate.
Authority should be sought before any reallocations are made.
13.2 Staffing gaps
241
It was noted that the Directorate had 31 vacant posts which were not filled. These
include a key post of the Assistant Director of Public Prosecutions. The Table
below refers. Inadequate staffing affects the timely implementation and delivery
of services which may adversely impact in the achievement of the entity strategic
objectives.
Post Title Scale No. of Vacancies Status
Ass. Director of Public
Prosecutions UISE 1 Vacant
Secretaries U5-U7 30 Vacant
Total 31
The Accounting Officer explained that the post of Assistant Director of Public
Prosecutions fell vacant as a result of the promotion of the then Deputy Director of
Public Prosecutions in December 2014. The recruitment process to fill the post of
Assistant Director of Public Prosecutions has however been initiated. The positions
of Secretary (U7-U5) have been vacant for some time as a result of transfers
within the Public Service. These vacancies have been declared to the Line Ministry
to have them filled.
I await the results of management efforts in having the posts filled.
13.3 Advances to Individual Personal Accounts - Non Compliance with
Treasury Accounting Instructions
Sections 227, 228 and 229 of the Treasury Accounting Instructions (TAIs), provide
that all payments should be made by the Accounting Officer directly to the
beneficiaries. Where this is not convenient, an imprest holder should be appointed
by the Accounting Officer with the approval of the Accountant General. On the
contrary, UGX.68,730,000 was advanced to Directorate staff through their
personal bank accounts to undertake direct procurements and other activities of
the Directorate. Such a practice of depositing huge funds on personal accounts
exposes Government funds to risk of loss, since the Ministry does not have any
control over such funds deposited on personal accounts.
242
The Accounting Officer responded that the Directorate recognizes the inherent
risks that are associated with advances and has tried to minimize this type of
payments. These payments relate to operational advances for office running
mainly to the Secretarial staff for newspapers, tea and refreshments.
I advised the Accounting Officer to avoid the practice and ensure strict adherence
with the requirements under the Treasury Accounting Instructions.
13.4 Budget Performance
A review of the budget revealed that UGX.16,276,902,823 was released against
an approved budget of UGX.17,252,411,052, representing 94% of the budget
performance. Due to the budget shortfall, office and machinery and ICT
equipment together with its software estimated at UGX.876,295,000 was not
procured. Unimplemented activities hamper service delivery, and the appropriating
authority‟s objectives may not be met.
The Accounting Officer explained that part of the Development budget was not
released by the end of the financial year. This led to the non-implementation of
the planned ICT infrastructure. He further responded that the Directorate shall
continue to liaise with the MoFPED to have it honor the approved budget.
I advised the Accounting Officer to continue liaising with MoFEP for adequate
funding and effective implementation of the planned activities and service delivery.
14.0 NATIONAL CITIZENSHIP AND IMMIGRATION CONTROL
14.1 Mischarged expenditure
A review of the entity expenditures revealed that wrong expenditure codes were
charged to a tune of 5,906,786,217 without authority contrary to chapter IV
section 156 of the TAIs. This practice does not only distort the intentions of
appropriating authority but also results into misreporting in the financial
statements.
243
Management explained that the mass enrolment exercise had one output of
registering citizens. Some expenses like allowances to staff on the exercise were
budgeted and charged on contract staff salaries (211102) thus indicating a
mischarge whereas not. In some instances, funds for allowances would delay and
the Directorate charged equipment to pay allowances. However whenever funds
for allowances would come, equipment item would be refunded thus showing
mischarges. It was therefore inevitable that certain items were used to fund
critical activities at a time resulting into mischarges.
I advised management to streamline the budgeting process to ensure that
sufficient funds are allocated to each account code and to seek for authority
whenever there is need for extra funding before any reallocations are made.
14.2 Procurements of NSIS equipment
In accordance with Section 39 of the PPDA Act, 2003 and Regulations 62 (1)
(b)(1), 75(b), 78(1)(d), 79, and 80 of the PPDA Regulations 2003, the
Accounting Officer DICC delegated the procurement of additional machinery and
equipment for the National Security Information System (NSIS) to Internal
Security organization (ISO). The procurement of the machinery and equipment
was worth UGX.83,358,464,749 and USD.6,637,239 and reportedly delivered to
ISO. Information relating to the above transaction had just been received by
management of DICC at the time of concluding this report in March, 2015. As such
I was unable to conclude on the verification of this procurement before the
statutory reporting deadline.
14.3 Payables
Included in payables of UGX.39,750,093,409 is rent due to Civil Aviation Authority
of UGX.780,949,138; Property rent due to UPPC UGX.874,264,954 and a
contractual obligation to Mulbuaer of UGX.16,420,383,768 which have been
outstanding for more than a year. Delayed settlement of the outstanding
obligations can result into wasteful expenditure in form of litigation costs.
244
Management attributed accumulation and non-clearance of domestic arrears to
budget constraints which has been brought to the attention of Ministry of Finance,
Planning and Economic Development.
I reminded the Accounting Officer that accumulation of domestic arrears is in
contravention of the commitment control system and advised him to liaise with the
MoFPED for extra funding to clear the outstanding arrears.
14.4 Renting of premises from Ministry of Defence at Kololo ceremonial
grounds
The Directorate entered into a tenancy agreement with the Ministry of Defence
(MoD) to let the premises at Kololo ceremonial grounds to the Directorate at a
monthly rent of UGX.56m. The Building was to be used as a warehouse, offices,
issuance place for the National Identity cards and related activities under the
National Security Information System (NSIS) Project. Under the contract, MoD was
required to make NSIS Project specific modifications to put in a tenantable
condition at the cost of the Directorate. The cost of project specific modifications
was estimated by the Ministry of Works and Transport at UGX.947,089,983. The
following were observed:
a) Lack of costed Bills of Quantities and a schedule of materials
The Directorate paid a sum of UGX.1,619,089,983 to the Ministry of Defence. The
payment comprised of rent charge of UGX.672,000,000 for 12 months and
project specific modifications of UGX.947,089,983. However, the Bills of Quantities
were not costed to support the amount of UGX.947,089,983. I informed
management that in the absence of the costed BOQs it was difficult to establish
whether the funds paid were for the actual amount billed by the contractor.
Management explained that the works were done by MOD and promised to
communicate to the Ministry Accounting Officer over the matter.
245
I advised management to follow up the matter with Ministry of Defence and have
the necessary documentation provided for future use.
b) Payments to MOD account instead of Consolidated Funds
The rented premises (Kololo Cerebration Grounds) are owned by the Government
of Uganda and managed by the Ministry of Defence, a Government entity. Equally
the tenant is a Government entity both of which draw funds from the Consolidated
Fund. However, rent of UGX.672,000,000 was paid to the MoD account held in
Bank of Uganda. The justification for not paying directly to the Consolidated Fund
was not provided.
Management explained that the payment was in accordance with the tenancy
agreement with the MOD.
I await confirmation from MOD that the funds were transferred to the
Consolidated Fund.
14.5 Renovation works on the rented premises
On 26th July 2013, the Directorate entered into a contract with UPPC for the
renovation of the allocated premises for a contract sum of UGX.2,869,960,881.
The Directorate was to renovate blocks 1, 2 and 3 and demolish block 4 to
construct a new one in its place. The civil works were to last for 10 calendar
months from the commencement date 24th October, 2013 and completed on 24th
August 2014.
However, by the time of writing this report (March 2015), five months after the
expected completion date, the contractor had not completed the works. The last
certificate of work done was prepared on 24th April 2014 with the value of work
done put at UGX.434,084,280, implying that the works were at a level of 15% to
completion. Besides, the renovation works on Block 1 (see figure 1) had not
started.
246
Figure 1- Block 1: UPPC has declined to hand over Block 1 over a debt owed to it by
DCIC
Figure 2; Block 2 was still far from completion.
Figure 3: Block 3 was not yet completed.
247
Figure 4: Interior works at Block 3 were not yet completed.
According to management, Uganda Printing and Publication Corporation did not
hand over block 1 to DCIC as DCIC had failed to pay rent arrears of
UGX.874,264,954 owing to the Corporation. I noted that at this rate, the
Directorate may have to extend its rent with the Ministry of Defence as the UPPC
project is still behind schedule.
Management explained that funds for clearing the rent arrears have been secured
but the Solicitor General has declined to give legal advice on how to settle the
obligation because it was an oral contract between UPPC and Ministry of Internal
Affairs.
I advised management to regularise the contract and also expedite the payment of
arrears to the Corporation to allow the contractor renovate the block.
Management was further advised to liaise with the contractor to speed up the civil
works and complete the renovation of the buildings in order to accommodate the
project as its tenure at Kololo Ceremonial Grounds has ended.
14.6 Non-tax revenue not retained as Appropriation-In-Aid
According to Section 3 of the Uganda Citizenship and Immigration Control
amendment Act, Non-Tax Revenue collected by the entity should be retained and
treated as appropriated in Aid (A.A). To the contrary, UGX.68,778,391,313 was
collected as Non-Tax Revenue through the Uganda Revenue Authority system and
automatically remitted to the Consolidated Fund. The Ministry of Finance, Planning
and Economic Development has not authorised the Directorate to utilise the funds
248
at source in accordance with the Act. This has impacted on the Directorate in
implementation of its mandate.
The Accounting Officer explained that efforts by the Directorate to have the
sections of the law implemented have been futile. A number of meetings have
been held with Ministry of Finance but to no success. Management further
indicated that they are yet to consult with Solicitor General for interpretation of
the law.
I advised management to keep advocating for the operationalization of the section
of the Act to be able to improve on its service delivery.
14.7 Human Resource matters
a) Inadequate structure
The Directorate has an approved structure however, the structure does not have
certain key functions of administration and human resources. It relies on the
support of the Ministry of Internal affairs for some very critical and important
services. For example, DCIC does not have a Personnel and Administration
positions like the Under Secretary Finance and Administration, Principal Assistant
Secretary, Senior Assistant Secretary/Transport Officer, Principal Human Resource
Officer, Human Resource Officers, Principal Policy Analyst and Statistician in its
staffing structure. Whereas Management has taken efforts to have an adequate
structure in place, these efforts are yet to yield results. The Directorate
performance in terms of Human Resources Management and general
administration is currently being stifled.
Management explained that the Directorate is still awaiting the outcome of the
study carried out by Ministry of Public Service in regard to the structure.
I encouraged management to continue pursuing the matter with the Ministry of
Public Service for approval of the proposed structure.
b) Staffing gaps
249
A review of the Ministerial Policy Statement revealed that the Directorate has an
establishment of 375 post in the current structure out of which 32 posts are
vacant. This is in-spite of having an inadequate structure. These include key posts
of: Assistant Commissioners (3), Principal Immigration Officer (2), Principal
Procurement Officer, Senior Immigration Officer and the Internal Auditor. The
Table below refers:
PROGRAMME AFFECTED POST/TITLE APPROVED VACANT POSTS
Finance &
Administration
(F&A)
Principal Procurement
Officer
1 1
Internal Auditor 1 1
Records Officer 1 1
Personal Secretary 2 1
Stenographer Sec 5 1
Senior Accounts Assistant 5 2
Principal Stores Assistant 1 1
Office Typists 10 9
Driver 5 2
Inspectorate
and Legal
Services
Assistant Commissioner 2 1
Drivers 2 1
Citizenship and
Passport Control
Assistant Commissioner 2 1
Immigration Officer 26 1
Immigration
Control
Assistant Commissioner 2 1
Principl Immigration Officer 11 2
Senior Immigration Officer 32 1
Immigration Officer 107 1
Immigration Assistants 35 1
Office Typists 3 3
GRAND TOTAL 375 32
Inadequate staffing affects the timely implementation of the Directorate's activities
and adversely impacts on the Directorate in the achievement of its strategic
objectives.
250
Management explained that the recruitment process is on-going and was
optimistic that the vacant positions will be filled.
I advised management to closely follow up the matter to ensure that the vacant
posts are submitted to the Public Service Commission for further action.
14.8 Inspectorate and Legal Services
a) Lack of a Custody Centre
The Department deals with legal compliance. However, it lacks custody centres for
the suspects arrested from the field. Although the Uganda Citizenship and
Immigration Control (Establishment of Immigration Custody Centres) Regulations,
2012 is in place, the Directorate does not have this facility. Lack of such a facility
impacts on the operations of the Directorate as it cannot ably carry out its
mandate effectively and efficiently. The remedy has been to release the suspects
on immigration bond, pending removal/deportation/investigations into their cases
and this leads to delays in deporting or concluding investigations regarding the
suspects. Some suspects have ended up jumping immigration bond which
culminates associated costs in terms of searching for the culprits and time wasted.
Management explained that works on the custody Centre were temporarily
stopped due to administrative reviews on the project. Work will commence as
soon as the reviews are completed.
I advised management to expedite the administrative reviews and complete the
custody centre for temporary custody of immigration offenders pending
deportation and/or investigations to be concluded.
b) Inadequate Enforcement structure
The department has a Skeleton structure of 24 personnel with basically 15 officers
to carry out field activities across the country; that is; 3 Principal Immigration
Officers, 2 Senior Immigration Officers and 10 Immigration Officers. The structure
251
has been the same since 2007 despite the growing number of illegal entrants in
the country. The table below shows the staffing:
PROGRAMME POST APPROVED STRUCTURE
Legal an
Inspectorate
Services
Commissioner 1
Assistant Commissioners 2
Principal Immigration Officers 3
Senior Immigration Officer 2
Immigration Officer 10
Personal Secretary 1
Office typist 1
Driver 1
Office Attendant 1
TOTAL 24
Although the structure is fully filled, it is inadequate to cover the whole country
and as such, there is no proper presence of legal enforcement officers in the 8
regional offices. According to the Commissioner Inspectorate and Legal, each
regional office would minimally require a work force of 15 immigration/Legal
enforcement officers.
Lack of necessary staff limits supervision of the border points. This could lead to
increase in illegal immigrants.
In their response, management explained that the Ministry of Public Service
carried out human resource needs assessment in various votes across Government
including DCIC. The Directorate‟s concerns were duly captured and the
Directorate still awaits the outcome of the exercise. Management further stated
that the recruitment of 150 Immigration Officers and 150 Assistant Immigration
Officers is on-going, and hoped this will help bridge the staffing gap as it awaits
approval of the proposed staff structure by Ministry of Public Service.
252
I encouraged management to continue engaging the Ministry of Public Service for
an improved and adequate structure. Meanwhile the outcome of the recruitment
exercise is awaited.
c) Lack of connectivity of border entry points
The border posts are not interlinked to one another. Data on entrants, how long
they are to stay, where they are to stay and from where they can be picked in
case of overstay is not interlinked to all border posts for ease of coordination and
follow up. Currently enforcement officers do random checking which is not only
inconveniencing the public but is also costly in terms of fuel and time.
Management indicated that connectivity of border posts was included in the
budget for FY 2015/2016.
I advised management to ensure that they secure the necessary funds and install
a system that connects all the entry points with the headquarters to effectively
coordinate, monitor and verify persons entering the country and those staying in
the country illegally.
d) Inadequate funding and transport
The Department receives approximately UGX.200,000,000 per year for inspections
and investigations of illegal immigrants in the whole country. This includes funds
for fuel and allowances for the officers undertaking the activities. In addition the
department currently has only one pickup and two Mini buses one of which is in a
poor mechanical condition. Lack of sufficient funds and transport coupled with
inadequate structure practically renders the department inactive which make
monitoring entry points difficult.
Management explained that it has been liaising with Ministry of Finance for more
funding to secure adequate transport to facilitate the operations but with limited
success.
I advised management continue liaising with the relevant Ministry for additional
funds to cater for inspections, investigations and monitoring of entry points. The
253
Accounting Officer is encouraged to liaise with development partners to facilitate
movements and enable improve on the inspections, investigations and monitoring
of all entry points.
14.9 Passport Control Office
a) Inadequate infrastructure
The Passport Control Office is expected to receive, expeditiously process, issue
and deliver Passports in appropriate quantum to the diverse beneficiaries with
considerably less duress and excessive fatigue for efficient and effective delivery
of service. Inspection of the Citizenship and Passport Control Department revealed
that there is lack of sufficient infrastructure and conducive working conditions as
necessary prerequisite to deliver satisfactory services. The Passport Officers are
squeezed in dilapidated small rooms and other activities like receiving application
forms, interviewing applicants and issuing passports are carried out from the
improvised tents. The photos below refer:
Above: Applicants in the queue under the tents for interviews.
254
Above: Sometimes the numbers of applicants exceeds the capacity of the tents
and have to stand outside the tents:
Above: Ready passports stacked in boxes being delivered to the public under the
shade
255
Above: A clear view of the shade where passports are delivered/received from.
Management explained that they will continue liaising with the Ministry of Finance
for infrastructural funding to secure adequate office space. In the meantime, DCIC
is implementing a passport centre in Gulu this FY 2014/2015 and another centre in
Arua next FY 2015/2016 in a bid to decongest the centre.
Management is advised to liaise with the responsible Ministry to seek for funding
to secure proper accommodation for the Directorate. In the meantime, the
Directorate is encouraged to continue pursuing the decentralization of passport
centres to reduce on the congestion at headquarters.
b) Inadequate staffing
The Department is aggressively pursuing decentralization of Passports issuance
not only in Uganda but also in the earmarked areas of the Diaspora (Beijing,
Brussels and New Delhi) in addition to the existing issuance centres. This is done
in consideration of the demand and overall contribution of the saleable documents
to Non-Tax Revenue collection in the country.
However, the Department lacks human capacity to carry out this drive
notwithstanding the infrastructure and technological gaps. For instance,
decongesting the centre requires setting up alternative service centres within
256
Kampala district and opening up more regional offices (in addition to the existing
Mbarara and Mbale).
Currently, there are six (06) officers who receive, interview and process
approximately 450-600 applications daily, an average of 80 applications per officer
per day. The ideal situation for one Receiving Officer is an average of 50
applications a day. This is obviously a high ratio that impacts negatively on
performance.
Management indicated that they will liaise with Ministry Public Service to resolve
staffing problems.
I encouraged management to continue engaging the Ministry of Public Service for
an improved and adequate structure in the Directorate.
c) Delays in Passport delivery
The ideal turn-round time for Passport delivery is eight (08) working days.
However the increasing numbers in Passport applications averaging 450-630 files
daily inclusive of Renewal applications seriously threatens the status quo and has
pushed passport delivery period to between twenty (20) to thirty (30) or more
days. The continued reliance on one Passport Control Officer and his Deputy for
signing more than 600 files a day is rather a toll order.
Management explained that in the established Client Charter, the lead period to
issue a passport is 10 working days. In the meantime, the delays at approval
processes have been addressed by deploying two (2) more officers to make it four
(4) at the Kampala Office.
I advised management keep engaging the Ministry of Public Service more staff to
reduce on the lead time to at least an allowance level.
d) Lack of Inter connectivity of Passport Issuing System
257
In consideration of Clients interests and pursuant to Government Decentralization
program, the Department upgraded Mbarara and Mbale Passport offices into fully
fledged One-Stop Passport Personalization and issuance centres. The Department
of Citizenship and Passport Control also operates Passport Personalization and
issuance Centres in Pretoria, Washington and London.
However, all the passport systems at Regional and Mission issuance centres and at
the Headquarters are not interlinked. In such situations, details of the passports
issued at the missions and regions cannot be retrieved at the head quarter for
ease of information flow. In the absence of a system interlinking activities and
information of all the passport issuance centres, there is a risk of one person
processing more than one passport from different centres.
Management explained that the local remote sites in Mbale and Mbarara are
securely data linked with the Kampala Passport Office server and no possibility of
an applicant obtaining more than one passport by using different centers. The
abroad centers in Pretoria, Washington and London are not linked to Kampala but
are only meant for renewing/replacements already vetted passport applications.
No new passport applicants are handled by these centers. Management is
budgeting for connectivity of the three centres above in the FY 2015/2016.
I encouraged management to secure funds and procure and install an interlinking
system to avoid possibilities of people getting more than one passport from
different centres.
e) Records section/Registry
The department processes an average of 500 hundred files each day from
applicants. However, there is no proper system of keeping these files. In most
cases, people‟s files get misplaced during processing and when they are under
custody. The filling system is manual, and un-systematic and tracing or retrieving
files for renewal is a night mare and sometimes the files are lost which leaves the
258
public frustrated with the passport office. The problem is made worse with the
limited space as can be seen in the photo below:
I advised management to secure funds for establishing an adequate registry and
automate the record keeping system at the Directorate to improve on record
keeping and reduce the lead time to locate individual files.
14.10 Inspection of the strong room
Passports are processed in the strong room. The processes include but are not
limited to personalization of passports which is basically transferring of applicants‟
information from the file to the passport, capturing data into the system and
printing, quality assurance, passport signing and dispatch. The following were
observed:
a) Security/Physical control
The door to the control room is made of wood and enforced with metallic burglars.
However, the metallic burglar both on the door and windows are not strong
enough to match the importance of the strong room and to stop any serious
criminals interested in its access. There is need to replace the wooden door with
259
the metallic one and replace the weak metallic burglar with stronger ones to guard
against any unauthorized intended access to the strong room.
Management noted the recommendation and promised that funds to replace the
weak doors and burglar proofs will be budgeted for in the financial year
2015/2016.
I await management commitment on the matter.
b) Limited space
A discussion with the Commissioner Passport Control and Citizenship revealed that
the Directorate is supposed to migrate to E-Passport by close of the year 2015 in
accordance with ICAO‟s requirements. However, the Directorate has no suitable
space where to install the machines that process electronic passports. The
machines need a specious room with certain level of aeration due to high
technology that does not allow dust among others.
Currently, the department has been using the same strong room since 1998
despite the increase in the volume of passports processing that match with the
increased population. By 1998, 40-50 passports were processed a day compared
to an average of 300-400 processed currently. The working space in the strong
room is small and not enough for the volume of work involved. The sitting space is
small and congested which impacts on the effective processing of passports.
Management explained that the issue of limited space remains a challenge but the
Ministry of Finance has authorized the DCIC to engage the Private Developer
under the PPP arrangement in the implementation of e-passport. The office space
issue will be part of these negotiations.
I advised management that in the meantime, there is need to have an organized
bigger space where the data entrants are separated from quality assurance,
passport printing and passport signing, recording and dispatch. This would go a
long way in improving the working conditions of staff; reduce on time wastage
260
due to congestion and damage of passports through human error in the strong
room.
c) Labour shortage
The labour force is not enough to handle the current volume of work in the strong
room. On average, 350 passports are processed daily using 7 work stations. Staffs
in the strong room work through lunch break and over the weekends in order to
reduce on the workload. There is need to double the workstations and staff to be
able to handle the passport processing effectively.
Management acknowledged the increased demand for travel documents by
Ugandans and the need to gear up the production capacity and the Strong Room
Staff strength to equate the task. The future plan of e-passport is to double the
Strong Room capacity in terms of workstations and human resources.
I await management action on the matter.
14.11 Citizenship section
Citizenship section deals with receiving, processing and delivery of Citizenship
documents after consideration by the National Citizenship and Immigration Board.
It also handles and prepares for delivery Certificates of Identity and Conventional
Travel Documents (CTDs) issued out to refugees.
A quick look at the operations of the section for January 2015 revealed that the
section handled a number of documents as summarized below:
Type of documents handled Number of documents handled
Certificate of Identity 77
Number of Dual Citizenship applications 121
Record of Dual Citizenship granted 119
Number of Naturalized foreigners Still pending
Registered as Citizens 30
Dual Certificates issued 87
261
Type of documents handled Number of documents handled
Deferred applications 11
Like any other section, the section operates under harsh conditions, more so that
it deals with foreigners. This leaves the image of the country tainted. Below is one
of the offices the section operates from:
I advised management to allocate some funds to renovate the office to improve the
working environment.
Management took note of the recommendation of renovating the office and pledged
to continue requesting for funds to carry out renovations of office premises despite
limited releases from Ministry of Finance.
14.12 National Information Security Sysytem (NSIS) project
On 1st November 2013, Cabinet approved the NSIS strategy, which included the
roadmap, budget and governance structure. A countrywide Mass Enrolment was
launched on 13th April, 2014 by H.E. the President and on 14th April, 2014 enrolment
started across the country. The implementation was undertaken using a Multi
262
sectoral/Multi-Institutional approach, which was coordinated by the Ministry of
Internal Affairs. The implementation was guided by a roadmap (detailed
Implementation Plan) and managed by an organization structure that was approved
by Cabinet. The target was to register 18 million citizens who are 16 years and
above during mass enrolment and the continuous enrolment.
a) Update on the mass registration/enrolment exercise
Registration of citizens to facilitate issuance of national identity cards and for other
purposes started at Parish level on 11th April 2014. This went on up to 11thAugust
2014 when registration shifted to the sub-county level.
During the four months of registration of persons (April-August 2014), over
14.8million persons were registered, a performance of 82%. On the 12th August
2014, registration at sub-county level started and over 1.1million citizens were
registered. In view of the projected 18million target of those with 16 years and
above, about 2,424,000 are yet to be registered. A total of 15,970,000 (88.7 %)
based on the 18 million target was registered by 11th Jan 2015 both in Mass and
Continuous Registration exercise.
It was however noted that the Uganda Bureau of Statistics released Provisional
results of the 2014 National Population and Housing Census exercise, indicating
that 15,958,595 people out of the 34,900,000 are aged 16 years and above. In
case the statistics are correct, this would mean that 97.6% was registered, leaving
2.3% yet to be registered.
b) NSIS Equipment maintenance plan
The National Security Information system acquired various equipment (hardware
and software) that were deployed to capture, process and establish a national
information register, produce national IDs and issue the ID cards. These include
8,000 registration kits, a data processing centre with over 300 desktop computers,
a set of secure central equipment comprising of high end computer servers that
include Automated Fingerprint Identification System (AFIS), Facial Recognition
263
System (FRS), high end database systems to store the captured data, and a setup
of a card personalized centre with four high end personalization machines that
produce 60,000 ID cards per day.
A review of the documents pertaining to the purchase of the equipment revealed
that the personalization machines consist of many movable parts that are prone to
breakages. The contract with the suppliers provided for a 6 months‟ free
maintenance in the first six months of production. The machines have been
producing cards since October 2014. The six months free period of maintenance
end on 31st March 2015 before the exercise is completed. An interaction with the
information technology team revealed that to maintain all the equipment for a
period April-June 2015 when the registration exercise is expected to be completed,
the project will require an estimated cost of UGX.5,542,700,000. The project
however has neither funds nor a budget to maintain these machines.
I advised management to properly justify the estimated maintenance costs and
liaise with relevant for funding to avoid equipment breakdowns.
14.13 Other observations
a) Board of Survey recommendations
A review of the board of survey report of 30/06/2014 noted that various
recommendations were made for implementation by DCIC management. These
include the following:
To create more space for storage of the assets and other items especially at
the border posts.
Equip the boarder offices with adequate furniture to enable the staff perform
their duties well.
Engrave all the assets at the border posts.
To submit a list of assets due for disposal indicating their locations and giving
reasons for their disposal.
Proceeds from the disposal of assets to be transferred to the consolidated
funds.
264
However, by the time of audit, all the above recommendations had not been
implemented.
Management explained that the Directorate is apparently faced with a challenge of
space not only at the border points but also at the headquarters. However,
construction at various border points of Bunagana, Cyanika, Goli, KIzinga, Vura,
Amudat, Lia, Swan River, and Ntoroko is on-going and some sites are already
complete. This will help reduce the problem of space.
It was further explained that funds for purchase of furniture for a few border
stations were provided in the FY 2014/15 both in the MTEF budget and the JLOS
and the Procurements process are on-going. Meanwhile a team from various stake
holder MDAs has been assembled to handle the process of asset disposal and all
the proceeds from the sale will be deposited to the consolidated account as guided
by the financial regulations and the Office of the Auditor General.
I await the implementation of the Board of Survey recommendations.
b) Maintenance and servicing of Passport issuing system
The Directorate signed a contract with an International Company to maintain and
service of passport issuing Machines at the Headquarters, Washington, London
and Pretoria for a period of three years from 1st February 2011 to 31st January
2014. Unfortunately, by the time of audit inspection, the contractor had not
rendered material maintenance services to the three missions as provided for in
the contract and yet there were indications that the systems were about to break
down especially in Washington DC.
Regarding the operations at the Headquarters, it was observed that there was no
prompt technical support response from the supplier which adversely affects the
business process and service delivery to the community due to system break
down.
265
Management acknowledged the observation and the Commissioner Citizenship and
Passport Control promised to work together with the Legal Department on
modalities of periodic review of the service contract.
I advised management to follow up the provisions in the maintenance contract
and ensure that the service provider renders satisfactory services. Payments to the
service provider should be based on actual performance supported by certified
reports from the Missions and user department at the Head quarter and this
should clearly be included in the maintenance contract. In future, the concerned
Missions should submit quarterly service provider`s performance reports to enable
management to monitor the performance.
c) Training of Staff at the Missions
Staff at the Missions do issue out VISAs and Passports however they have never
had formal training or instruction from the Immigration and passport departments
about the issuance of Uganda passports and VISAs. In addition, the concerned
Missions have no Immigration officers to handle the above functions. This may
result into obtaining inadequate information from the applicants. Errors and
omissions may not be ignored especially when printing passports.
Management explained that training clinics for Foreign Service Officers are
organized as funds may permit. One such training was organized in the 1st
Quarter of this FY 2014/2015. Funds to deploy Immigration Officers at Missions are also
being budgeted for in FY 2015/2016.
I advised management in consultation with Ministry of Foreign Affairs to organise
refresher courses for the staff handling VISAs and Passports at the Missions.
Training should be done regularly to update them with the new changes.
d) Implementation of Dual citizenship Act
The mission staff indicated that the implementation of the Dual citizenship Act is
unclear to them at the Missions. It is unclear as to what documents an applicant is
266
supposed to fill and whether they can officiate at the swearing of the Oath of
Allegiance. Management acknowledged the observation and promised to handle
the matter during the subsequent trainings
I advised management to regularly organize training for the Mission staff to enable
them acquire the necessary skills and handle their work diligently.
14.14 Budget Performance
Public Finance and Accountability Regulations, 2003, section 2.10 (b) entrusts the
Accounting officer with ensuring that all controls such as those contained in the
approved estimates and warrants are strictly observed. Budget estimates are
based on outputs to be achieved for the financial year and during implementation,
effort is required to be made to achieve the agreed objectives or targets of the
entity within the availed resources.
During the year, all the appropriated budget plus the supplementary totalling to
UGX.178,686,460,900 was released representing 100% release. A review of the
Department‟s budget performance for the year 2013/2014 revealed that some
targets were not achieved. The table below refers:
Planned Activities Expected Outputs Actual outputs(As per end of FY 2013/14 report)
Comments
Office of the Director Develop National Immigration Policy
National Immigration Policy
3rd draft of the National Immigration Policy prepared, pending a final meeting with stakeholders and costing of the policy
Costing of the Policy is pending
Finalize Development of the National Migration Policy
National Migration Policy National Migration Policy pending stakeholder consultation
Development of National Migration Policy stalled
Develop a 5 Year Strategic Plan for the Directorate
5 Year Strategic Plan Strategic Plan not developed
Strategic Plan Task Force Team is yet to be reconstituted. The Minister lifted the ban he had imposed on development of the strategic plan
Inspection and Legal Services Carry out inspections and investigations
Aliens arrested and investigated
1,114 suspected immigration offenders
No specific/quantifiable
267
Planned Activities Expected Outputs Actual outputs(As per end of FY
2013/14 report)
Comments
arrested and/or investigated. Out of these 329 illegal immigrants, representing 29.5% of those apprehended were removed from the country.
targets/ performance indicators against which to evaluate performance
Support to National Citizenship and Immigration
Procure passport issuance system for Gulu
Issuance System in place System not procured Funds diverted to Mbarara and Mbale passport centers that were under budgeted for.
Construct Kaiso Tonya
and Segaboro border posts
Kaiso Tonya Commissioned Not constructed The contracts
committee declined to approve the procurement due to lack of proof ownership of land.
Construct Busunga border post
Busunga border commissioned
Not constructed
Construct Kaiso Tonya and Segaboro border posts
Kaiso Tonya Commissioned Not constructed The contracts committee declined to approve the procurement due to lack of proof ownership of land.
Procure system for electronic visa issuance
Visa issuance software Not procured The system was not procured.
Citizenship and Passport Control
Grant dual citizenship Aliens and former Ugandans granted dual citizenship
Granted 234 dual citizenship certificates of which 58 foreigners and 176 Ugandans in diaspora.
No specific performance indicators against which to measure performance
Immigration Control
ICT Master plan developed
ICT Master plan ICT Master plan not developed
ICT Master plan not developed
Management explained that the activities were not implemented because of
various challenges like land ownership and inadequate funding.
I informed management that unimplemented activities hamper service delivery
and the appropriating authority‟s objectives may not be met.
268
PUBLIC SECTOR MANAGEMENT
15.0 MINISTRY OF LOCAL GOVERNMENT
a) Mischarge of Expenditure
A review of the Ministry of Local Government‟s expenditures revealed that the
entity charged wrong expenditure codes to a tune of UGX.2,497,433,465. This
constituted 8% of total expenditure for the Ministry. Mischarges undermine the
importance of the budgeting process as well as the intentions of the appropriating
authority and lead to misreporting.
Management explained that this was caused by quarterly release limitations which
forced management to charge items with cash balances to fund urgent and critical
activities. Management further explained that insufficient budget allocations and
severe cuts in consumptive areas by MOFPED led to this situation.
I advised management to liaise with the relevant authorities to streamline the
budget process to ensure that sufficient funds are allocated to each account.
Further, authority should be sought for any reallocations.
b) Unaccounted for remittance to Uganda Police Force – UGX.137,542,000
It was observed that UGX.137,542,000 was remitted by the Ministry to UPF to
cater for training of Police Fire and Rescue personnel on Fire fighting equipment
but this payment was not supported with a Memorandum of Understanding
between the two parties specifying the outputs, responsibilities and accountability
framework. Furthermore, I could not confirm whether the activity was undertaken
as no accountability documentation or report was availed for verification.
Management explained that UPF had been contacted to furnish them with the
accountabilities.
269
I advised management to ensure funds are accounted for in time and also have
the MoU in place before any remittance of funds to third parties is effected in the
future.
c) Advances to Individual Personal Accounts –UGX.4,623,642,146
(i) Non-Compliance with Treasury Accounting Instructions
UGX.4,623,642,146 was advanced to Ministry staff through their personal bank
accounts to undertake direct procurements and other activities of the Ministry
contrary to Sections 227,228 and 229 of the Treasury Accounting Instructions.
Such a practice of depositing huge funds on personal accounts exposes
Government funds to risk of loss, since the Ministry does not have any control
over such funds deposited on personal accounts.
Management explained that the advances mainly related to activities and
workshops undertaken upcountry with staff from other Ministries/Local
Governments. Management further explained that staff from the Ministry acted as
Team leaders who were responsible for allowances and other facilitations for the
team members. All activities were carried out and activity reports filed.
I advised management to ensure strict adherence with the requirements of the
Treasury Accounting Instructions.
d) Payments for beautification of Kampala
A local Company entered into a contract with Ministry of Local Government for
beautification of the Clock-Tower-Nsambya-Gaba/Munyonyo Road corridor in 2007
ahead of the CHOGM activities and final certification of works was issued in May
2008. A review of the payments to the contactor revealed several issues as
follows;
(i) Nugatory Expenditure:
It was noted that UGX.107,989,414 has been outstanding since issuance of a
completion certificate by the consultant in May 2008. Because of that, interest
accrued on late payment rose to UGX.371,748,822 as at February 2012 (an
increment of 344%) leading to a payable sum of UGX.479,738,236. At the time
270
of reporting, the payable had been made good. The interest paid is considered
nugatory.
(ii) Interest computation basis:
Clause 43.1 and 43.2 of the contract provided for interest on late payment by the
client to the Contractor from the date by which the payment should have been
made up to the date when the late payment is made at the prevailing rate of
interest for commercial borrowing.
It was noted that the basis for the contractors interest rate was unknown since the
clause did not specify the Bank for “prevailing commercial interest” purposes. The
contractor seems to have exploited the loophole to compute interest using his own
banks interest rate that might have been higher than Bank of Uganda rate.
Without providing the schedule for interest computation, I could not confirm the
accuracy of the amount and whether the right rate was used in the computation.
Management explained that the transaction was incurred during the CHOGM and it
was inevitable that the payment had to be settled although it was not included in
the domestic arrears. The Ministry of Finance, obligated votes to settle
outstanding claims under their votes the basis upon which the payment was later
made.
I advised management to avoid such losses in future by putting in place adequate
risk management controls, and paying suppliers and contractors promptly.
e) Motor vehicles and office equipment
a) Motor vehicle repairs and servicing
UGX.560,453,690 was spent on repairs and servicing of the Ministry‟s motor
vehicles during the year. However the following issues were noted which require
management attention;
Payment for grounded vehicles
UGX.13,869,979 was spent on four vehicles that were confirmed as having been
grounded throughout the year and were ineligible for any repairs.
271
Cash payments
Cash payments to the tune of UGX.5,000,000 was paid to a staff for onward
remmittance to a pre-qualified supplier being funds to cater for repairs and
servicing Ministry motor vehicles instead of using direct EFT payment. This is
contrary to the financial regulations.
Management explained that the grounded vehicles were earmarked for disposal
but the Ministry failed to acquire a new fleet and the same vehicles remained in
use for the time the expenditure was incurred. Management also explained that
there was an emergency activity and garages had refused to offer services without
settlement of outstanding dues which led to the utilization of cash to undertake
the repairs.
I advised management to liaise with Ministry of Works and Transport and have
uneconomical motor vehicles boarded off.
b) Non-serviceable motor vehicles
An inspection of the Ministry‟s stores and motor vehicle yard revealed that there
were a number of un-serviceable motor vehicles and office equipment which were
occupying valuable space. There was no evidence of any initiated process for
disposal. Some of the vehicles were found abandoned in privately owned service
garages where they were exposed to risk of vandalism and further loss of value.
Non-disposal of un-serviceable motor vehicles and office equipment may lead to
loss in value through vandalization or theft and creates shortage of valuable
storage space.
Management explained that the Ministry through an Auctioneer carried out the
process of disposing off all the old vehicles last year. Unfortunately the fleet
continues to depreciate and more vehicles became unserviceable. The Ministry has
again initiated the process to dispose them off.
I await management‟s effort in the disposal process.
c) Nugatory payment of parking fees
272
As noted in my previous year report, it was observed that during the year under
review, UGX.33,040,000 was again paid to a parking space service provider as
parking fees for 16 Ministry motor vehicles parked in the basement of Uganda
House contrary to Chapter 7, paragraph 705 of the Treasury Accounting
Instructions part 11-Stores that requires compilation of lists of unserviceable
vehicles for onward submission to the Accountant General requesting for their
disposal. The payments relate to the period January to June 2013
(UGX.15,292,800) and July to December 2013 (UGX.17,747,200). Inspection of
the parked vehicles in the basement revealed that these vehicles were grounded
and therefore expenses incurred on them are nugatory. There is risk of loss of the
vehicles given the incomplete vehicle register and vandalism which will reduce the
disposal value.
Management explained that the process of boarding off was in advanced stages.
I advised management to expedite the boarding off of grounded motor vehicles so
that wasteful funds paid for parking space is saved.
f) Non-deduction of Withholding tax
Section 120(1) of the Income Tax Act requires all Ministries to withhold tax from
supplies of any services of an amount or amounts in aggregate exceeding one
million shillings to any person in Uganda at the rate of 6% of the aggregate sums.
Further, section 124(1) of the Act requires a withholding tax agent to remit the tax
within fifteen days after month end.
Contrary to the above, I noted that withholding tax to the tune of UGX.93,970,920
from two payments was not deducted for onward remittance to URA. See the
table below;
S/N Description Gross amount (UGX.) 6% WHT
1 Rental payments to NSSF 1,354,050,785 81,243,047
2 Stationery purchases 245,453,819 12,727,873
Total 93,970,920
273
The Ministry risks fines and penalties from URA that may be imposed for non-
adherence to the laws.
Management in response regretted the anomally and pledged to withhold tax from
the suppliers subsequent payments.
I advised management to ensure that due taxes are deducted and remitted to URA
as required by the Income Tax law.
g) Anomalies in Procurement
A sample of procurement files were selected to enable me audit the various stages
of the procurement process from initiation to contract management and a number
of observations ranging from undervaluation of taxes, bid and evaluation
manipulation, non-compliance to specifications in bid documents, defiance of
Public service authority, contract payments and limitation on bidders were noted.
Details are as below;
a) Limitation on bidders on procurement of energy packages
PPDA regulations 142(1), (2) and (3) requires a shortlist to include sufficient
bidders to ensure effective and real competition. Further, it requires a PDU to use
information from four sources i.e. PPDA register, entity prequalified list, any other
PDU list and market knowledge.
Three bidders were invited using market knowledge and two submitted bids for
the above mentioned procurements worth UGX.123,679,500. However, it was
noted that there was limitation as the PPDA register had at least four providers for
the service who would have been invited to bid and widen competition. As such
there was no adequate competition in this respect.
b) Non-compliance to specification
Review of the evaluation worksheets revealed that a company that bided for
supply of vehicles and motor cycles was non-compliant on the 4WD station wagon
of 3000cc with regard to “minimum dimensions” as the company was silent on
ground clearance that was required of 0.22m and fell short on the required length
274
of 4.9m by submitting a bid of 4780mm. The company should have been
eliminated at this stage. The company however went on to win the contract.
Further, Government procedure requires authority from the Minister of Public
Service for procurement of vehicles. Authority on the procurement from the
Minister of state dated 31/3/2014 specified two double cabin pick-ups not
exceeding 2800cc; however the supplier was awarded to provide 3000cc vehicles.
Management explained that PDU‟s knowledge of the market was one of the
recognized databases under Rule 142(2) (d) for development of provider shortlist
and that three providers on the shortlist were considered sufficient. Management
further explained that registered providers will be accorded priority in future.
With regard to non-compliance to specifications, the evaluation and review of
specifications offered by providers involved expertise from MoWT and that certain
non-conformity could be waived under R178 (4), (5).
I advised management to ensure that the Procurement and Disposal Unit and
Contracts Committee adhere to the PPDA Act and regulations are strictly adhered
to.
h) Local Government Sector Investment Plan (LGSIP) Account
The Ministry operates a Bank Account “Local Government Sector Investment Plan”
with Bank of Uganda. At the end of the financial 2012/2013 the Ministry had a
balance of UGX.852,593,754 and during the financial year 2013/2014
management made several transfers totalling to UGX.440,697,837 from Treasury
Single Sub Account (TSSA) to this account for onward remittance to clearing firms.
Audit review of receipts and expenditures on this account revealed the following;
Rationale for maintenance of Bank account:
It was noted that the account has no project funding but rather receives transfers
from the Ministry Treasury Single Sub Account (TSSA) for onward remittance to
suppliers and Ministry staff which activities should have been effected from the
TSSA. It should also be noted that the Project closed some years back but
275
Management did not close the account. This is contrary to Treasury Accounting
Instructions (TAIs). Such accounts are easily susceptible to irregular activities.
Financial reporting:
The balance brought forward of UGX.852,593,754 and spent during the year was
not reflected in any performance report for the year since it was neither project
funding nor appropriated by Parliament.
Management explained that Local Government Sector Investment Plan was a
Project and as such its expenditure could not be reflected in the statement of
financial performance but rather end of year balances are disclosed in the
schedule of Project balances. I explained to management that projects have
timelines, financing agreements, project appraisal documents and annual audit
reports which was not the case.
I advised management to consider closing the account in line with Accountant
Generals guidelines.
i) Payments for domestic arrears
Treasury Accounting Instructions 2003 Part 1 chapter IV section 188 specifies that
an officer authorized to incur expenditure will ensure that no payments due in any
financial year remain unpaid at the end of that year. Further, the established
commitment control system requires management to commit the Ministry only
when funding is appropriated and has been confirmed.
A review of the financial statements of the Ministry for the year ended June 2013
revealed that the Ministry had outstanding commitments of UGX.51,037,123.
However I noted that UGX.799,619,907 was paid to several companies for
settlement of arrears incurred in the previous financial years. This was a clear
indication of non-disclosure of full arrears. Summary of payments is as below;
S/N Description Amount (UGX)
1 Beautification – M/s Omega construction 479,738,236
2 Vehicle repairs 186,545,356
276
S/N Description Amount (UGX)
3 Clearing and forwarding 133,336,315
799,619,907
The Ministry misrepresented their indebtedness in the previous financial
statements. Furthermore, the Ministry did not budget and neither did it have a
provision for item 321605 (domestic arrears) besides, supplementary funding was
not requested instead management mischarged already budgeted items. Under
the circumstances funds for planned activities appropriated by Parliament were
diverted to settle domestic arrears.
I advised management to adhere to the commitment control system and ensure
that verified domestic are verified, budgeted for and paid using the appropriate
expenditure account codes and are appropriately disclosed in the financial
statements.
j) Vacant Posts in the Establishment
Ministry of Local Government has an approved establishment structure of 165
staff. However a review of the established structure revealed that 16 posts were
not yet filled representing ten (10%) vacancy gap. Service delivery is hampered by
delays in filling the vacancies especially at senior management level and staff may
be overworked which may adversely affect their morale.
Management explained that some of the posts fell vacant because some staff were
interdicted while others were promoted to higher posts. Management further
explained that a submission had been made to Public Service Commission to have
the vacant posts filled.
I await management‟s effort in filling the vacant posts.
k) Budget Performance
Public Finance and Accountability Regulations 2.10(b) entrusts the Accounting
Officer with ensuring that all total controls such as those contained in the
approved estimates, warrants and others are strictly observed. Budget estimates
277
are based on outputs to be achieved for the financial year and during
implementation, effort is required to be made to achieve the agreed objectives or
targets of the entity within the availed resources.
Review of the budget performance for the year under review revealed that some
targets were partially or not achieved despite release of funds to the vote
functions. Details are in the table below:
Vote function output
Item description
Planned outputs/ Quantity
Amount (UGX) budgeted
Amount released (UGX)
Actual output/ Quantity
Remarks
Project 1089a-LGSIP Support to District Development
132172-government building and administrative infrastructure
Construction of Sub-county headquarters at Nabweru Wakiso district
300,000,000 113,400,000 No construction has started
37% of the funds were received but construction has not started
Project 1089b-LGSIP Support to local councils development
132272-Government buildings and administrative infrastructure
Construction of Local government offices supported pledges
200,000,000 130,400,000 None No construction has started
Project 1089d-LGSIP Support to policy, planning and support
134975-Purchase of Motor Equipment and other Transport Equipment
Procurement of Motor vehicle
200,000,000 133,400,000 None -No vehicle was procured despite receiving 67% of the funds
Service delivery is hampered and the appropriating authority‟s objectives are not
met.
Management explained that funds were transfered to Mubende Town Council and
District for completion of a sanitation site and office block at district headquarters
respectively. Management further explained that funds for procurement of a
vehicle were used on vehicle maintenence.
I advised management to ensure that all activities are undertaken as planned.
15.2 UGANDA GOOD GOVERNANCE (UGOGO) PROGRAMME
a) Compliance with the Financing Agreement and GoU Financial
Regulations
278
It was noted that the Programme management had complied material with
Financing Agreement Terms and Government of Uganda Financial Regulations
except in the following matters;
b) Lack of an Annual Procurement Plan
Procurements under the Uganda Good Governance Project were carried out
without a procurement plan contrary to the PPDA provisions Section 58. Annual
procurement plans help to rationalize procurements and ensure economy while
avoiding split procurements made on adhoc basis. This also enables subsequent
comparisons of planned implementation against actual procurements.
Management explained that the project did not have major procurements apart
from routine maintenance of vehicles and equipment plus a few stationery items
which were mainly done through the three quote system.
I advised management to put in place a procurement plan to ensure compliance to
Public Procurement and Disposal of Public Assets Act provisions.
c) Vacant Position of the Program Officer
It was noted that the position of Uganda Good Governance Program Officer was
vacant. This implied that some members of staff were overstretched since they
were taking activities beyond what was stipulated in their job description.
Management explained that the Unit recruited a Program Officer who lasted for 3
months only and considering the remaining period for the program and the time it
would take to recruit and orient the officer, it was decided that the work be
distributed among the different officers within the Unit and outputs are being
achieved through other officers within the Unit.
I advised Management to liaise with relevant government bodies to ensure that
the project achieves full establishment.
d) Procurement Irregularities
279
The Public Procurement and Disposal of Public Assets (PPDA) Act 2003, and the
Local Government PPDA regulations 2006 require that all public procurement of
goods services and works comply with the procurement law. However services
worth UGX.8,800,000 were procured without following Public Procurement
Regulations and guidelines. The details of the transactions are in the table below:
Voucher No Date Payee Item procured Amount Remarks
358 12/09/2013 Paper
Capito Ltd
Supply of
stationery
1,800,000 Requisition from user
department made on 10/09/2013
Request for
quotations 12/09/2013
Proforma invoice
raised on 09/09/2013
Evaluation report
done by Nakasi Esperanza not dated.
393 The Leading Edge Printing
Services
7,000,000 One Proforma invoice
dated 05/08/2013, 8days before the
request for quotations
was sent on 13/08/2013
Evaluation report
signed by only one person and not dated
No receipt on file
from The Leading
Edge for the monies received.
Total 8,800,000
There is a risk that value for money might not have been obtained.
I advised management ensure compliance with the PPDA Act, Regulations and
Guidelines to strengthen the procurement processes.
e) General Standard of Accounting and Internal Control
A review was carried out on the system of accounting and internal control. It was
noted that management had instituted adequate controls to manage project
resources except in the following areas;
280
f) Unacknowledged Payments
It was noted that payments in respect of Pay As You Earn, WHT and National
Social Security Fund lacked acknowledgment by respective statutory bodies. From
the sample payments reviewed UGX.87,549,248 was not supported with
acknowledgement receipts. Further, UGX.6,913,290 in respect of purchase of
stationery was not accounted for by way of receipts. I could not therefore
ascertain with reasonable accuracy as to whether those payments were actually
received by the intended beneficiaries.
Management explained that for tax deductions they were in the process of making
sure that tax payments were acknowledged through the monthly return system.
I advised management to ensure that the person responsible for making returns
should always endeavor to pick acknowledgement receipts and certificates as
proof of payment.
g) Missing voucher
Examination of accounts revealed that payment records amounting to
UGX.14,940,000 were missing from the expenditure files. The payments were in
favor of Joint Monitoring team –UGOGO activities. Missing documents indicate a
weakness in the projects records keeping function which could lead to loss of vital
records. In the absence of documentation, I could not verify whether the amounts
had been regularly withdrawn from the project accounts and applied for the
intended purposes.
Management explained that there was already restricted access to financial
information. They further explained that the voucher could have been misfiled and
they promised to trace it.
281
I advised management to institute controls like restricted access to records to
ensure proper safeguard of the projects accounting documentation, and also to
trace the missing voucher for verification.
h) Students Complaints
According to demand notes issued by training institutions, the fees charged relate
to lecture costs, revision and study materials. During the head count exercise it
was noted that students complained that they do not get all the benefits as the
sponsoring program states, the program claims to be paying tuition fees, study
materials and revision for students but it was noted in some training centre‟s that
students pay for themselves revision fees and study materials.
Management explained that each student knows exactly what is being sponsored
by the Ministry and they have avenues of reporting to the respective personnel
departments of the respective local governments for the ministry to follow up with
the respective centre‟s and training colleges.
I advised management to investigate those complaints and ensure that students
obtain the required benefits and to always comply with the guidelines and
principles of local government sponsorship of students to pursue professional
courses.
i) Failure to Comply with Sponsorship Guidelines
According to the guidelines for sponsorship signed by the program and the training
centers a student is allowed to sit for a paper for a maximum of two sittings
failure to do so the student pays for him or herself for the third sitting. However it
was observed that this guideline is not being complied with as was noted from one
of the students of College for Professional Development from Gulu center who sat
for papers 6, 10 and 11 for three sittings and the program paying for him for all
the sittings. Non compliance with guidelines implies a risk of mismanaging the
program funds.
282
Management explained that the guideline was revised in the program meeting
considering that usually it is the finalists who repeat papers. They further stated
that it would be a great loss not to support the finalist until when they finally pass
the papers because they are likely to fall out.
I advised management to comply with the guidelines in place and always review
student‟s database to avoid such anomalies.
j) Review of Previous Year‟s Audit Issues
The status of implementation of previous recommendations as reviewed and the
table below provides the update.
Issue Managements
comments
Status
Accounting System
During the previous audit, it
was noted that the
programme support
team unit maintained a
manual accounting
system (excel spread
sheet) to record all its
accounting ledger
books. This rendered
accounting including
the preparation of Fund
Accountability
Statements is Laborious
and prone to errors.
Acknowledged. The
programme is
ending in a
year‟s time and
it is not one of
those that have
been prioritized
to be included
on the IFMS by
MoFPED due to
its remaining
life and size. For
the remaining
life, the Project
team has no
During the audit of the
period under review,
the audit team
noted that the
Programme is not
yet integrated to
IFMS.
283
Issue Managements
comments
Status
choice but to
continue with
manual
accounting
system.
Diversion of programme
funds
During the previous audit, we
observed that a staff of
the Ministry of Local
government was loaned
UUGX.14,270,000 from
UGOGO Funds to cater
for his tuition for a
course on sustainable
Local Economic
Development in
Netherlands on 19th
March 2013 Voucher
No. 219
Acknowledged. The
Ministry is
committed to
paying back this
debt. The
Ministry is
intending to
settle this debt
from the third
quarter release
from MoFPED .
During the review of the
current period there
was no evidence
that the money
talked of above had
actually been
refunded.
Internal Audit function
During the previous audit, we
noted that internal
audit function was
lacking.
The internal audit
team‟s report
was still being
processed by
the time of the
audit. It is now
ready and
available for all
stake holders.
During the audit of the
period under review,
the audit team
observed that the
internal audit team
made reviews but
there was no report
of the findings.
However, the report was
not availed for
284
Issue Managements
comments
Status
inspection.
Lack of Memorandum of
Understanding
(MOU) with
professional training
institutions
During the previous audit, we
observed that there
was no memorandum
of Understanding
(MOU) between the
Uganda Good
Governance (UGOGO)
Programme and the
Training institutions to
govern their
relationship and
accountability
arrangements.
Acknowledged. The
programme is in
its final life
stages so it did
not warranty to
start recruiting
the institutions
afresh for a
continuing
program. The
Ministry
continues to
issue operating
guidelines
which the
already
recruited
institutions use
until when the
project ends.
No MOU is in place.
285
15.3 COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT
PROGRAMME – PROJECT 1 (CAIIP 1)
a) Compliance With Financing Agreement And Government Of
Uganda Financial Regulations
It was noted that management had complied in all material aspects of the
financing agreement and GoU financial regulations except for the matters below;
b) Un-remitted Pay-As-You-Earn
UGX.188,840,643 was deducted and withheld as PAYE from salaries of Programme
staff during the year under review. However, these funds were not remitted to
URA. Furthermore PAYE arrears of UGX.147,392,099 noted in last year‟s audit
report remained unremitted. Non remittance of deductions is a violation of the tax
law which may lead to penalties and fines being imposed on the programme.
Management explained that the bilateral agreements with the Donors prohibit the
use of donor funds to meet the above obligations. GOU funds should have been
used to cater for both the PAYE and the NSSF Contributions. However, during the
year, remittance for PAYE was not done because counterpart funding of
UGX.53,000,000 was not enough to cater for all outstanding obligations.
I advised management to liaise with the relevant Government authorities and
ensure that the funds are released and remitted to the rightful authorities as
required by the law.
c) Failure to deduct 6%Withholding tax (WHT) from Service
providers
It was observed that Management did not withhold tax amounting to
UGX.304,715,889 on payments for services provided by non-exempt companies
contrary to the requirements of the tax law under Section 120(1) of the Income
286
Tax Act. Non-deduction of withholding tax may result in to penalties and fines
being imposed on the Programme by the tax body.
Management explained that the Project is being financed using Loan funds from
the African Development Bank (ADB) whose bilateral Agreement with Government
precludes the use of the loan funds for the payment of taxes relating to goods and
services required for the execution of the Project. Therefore deduction and
subsequent remittance of WHT under this Loan funding constitutes ineligible
expenditure which are grounds for suspension of disbursements of loan funds to
the Project.
I advised management to engage the Ministry of Finance, Planning and Economic
Development to ensure that withholding tax from outstanding payments to eligible
service providers is done and remitted to the tax body as required by the Income
Tax laws.
d) General Standards Of Accounting And Internal Control
(i) Spending at source
Project Operations Manual Part Two Paragraph 3.1 (Sub-sections 111 Flow of
funds) requires all project funds including GoU counterpart funding to be
deposited to special account held with Bank of Uganda.
However, it was noted that GoU contribution amounting to UGX.53,000,000 was
released by Ministry of Finance, Planning and Economic Development to the
project through the Ministry of Local Government Treasury General Account,
where these funds were spent on non project activities. Spending Project funds
by the Ministry does not only deny Project Management control over the funds but
also poses a risk of diverting the funds to activities outside the project.
Management explained that with the migration of Government accounting system
to the IFMS system, all the GOU project accounts were closed hence counterpart
funds for the project were transferred to the Ministry General account.
287
I advised management to ensure strict adherence to controls of project accounts
such as authorization and purpose of the expenditure for proper monitoring and
control.
e) Field Inspections
Field inspections were undertaken with a view of establishing among others,
Physical progress of civil works on district feeder roads and community access
roads; construction of rural markets and agro processing shelters. The extent of
supervision and monitoring by the respective District Local Governments were also
considered. The following matters were observed during inspections:-
Agro Processing facilities
(i) Apparent project overload to the contractor
A construction company was awarded a contract to construct Agro Processing
facilities in the three sub-counties of; Nagongera (2 rice hullers), Merikit (2 rice
hullers) and Nabuyoga (1 maize mill and 2 rice hullers) all in Tororo District at a
total cost of UGX.227,594,063. All agro processing facilities were to be executed
and completed within the same period. It was however noted that the contractor
lacked capacity to execute the contracts within the contract period and as a result
works had stalled for over three years. This led to the delayed completion of the
project hence a breach of contract. Refer to the pictures of Agro-Processing plants
shown below:
Incomplete rice hullers in Nagongera and Merikit sub-counties for over 3 years
The delayed works deprive the beneficiary community of intended services.
288
Management explained that the contractor had financial challenges after the
contracts had been signed. However, the construction of the shelters was
completed and agro process facilities were installed. Management further
explained that it had now downsized on the number of shelters being handled by
a single contractor in order to avoid work overload and ensure that the
construction of the shelters is completed in time to allow for the installation and
operationalization of the machines scheduled to ensure maximum benefit to the
communities.
I await the outcome of management‟s efforts.
(ii) Missing components for Agro process equipment
It was noted that some of the equipment for the agro processing plants in various
districts and sub counties visited lacked vital components like mortars, gear
switches and foundation bolts causing a delay in the installation process. Details
are shown below;
District/Sub county Missing components
Tororo, Katajula sub-county,
Nagongera
Mortars for the rice hullers were stolen
Kapchorwa The rice hullers lacked main gear
switches, tool boxes and foundation
bolts. The site engineers stated that
most of the missing components were
apparently not delivered by the
supplier
Pallisa, Agule Sub-county The milk cooler lacked a Lactometer
while the rice mill lacked a weighing
scale and stitching needle.
Failure to fully install the agro processing equipment and safeguard the project
assets denies the beneficiary communities services which would improve their
livelihood.
289
Management explained that due to the delays in the completion of the shelters,
the Ministry decided to deliver the equipment to the respective beneficiary sub
counties for safe custody as a measure of reducing on the accumulation of the
storage costs charged by the suppliers and during the process some of the
equipment components went missing after delivery to the respective beneficiary
sub counties. However management is working hand in hand with the district,
police and affected sub counties to ensure that all the missing accessories are
replaced so that machine installation can be completed.
I await the outcome of management‟s efforts on this matter.
(iii) Supply of the wrong type of generators
It was noted that some districts were supplied with low capacity generators which
could not operate the Agro processing equipment. The faulty generators were
replaced with higher capacity generators in some districts like Kapchorwa, Sironko
and Pallisa. However, the new generators had not yet been installed, while the
rejected generators had been abandoned at the agro-processing facilities. Refer to
the pictures below;
Rejected generators abandoned at Patete and Agule sub-counties in Pallisa district
The suppliers of the faulty equipment alleged that the equipment was damaged
due to poor storage as deliveries were made before construction of agro
processing shelters. At the time of inspection, the suppliers had issued an
intention to sue the Ministry of Local Government for neglecting payment of
outstanding balance and damages totalling to USD. 1,081,059 (M/s Capital
Venture Ltd USD 529,830 and Ms Charm Ltd USD 551,229
290
Supply of generators with wrong specification and delayed replacement of these
generators denies the community of the benefits of improving the household
livelihood.
Management explained that delivery and installation of new generators at the
respective affected sites has now been done. Management further explained that
it is working hand in hand with the office of the Solicitor General to address the
pending litigation to ensure that there is no financial loss to Government.
I await the outcome of management‟s efforts.
(iv) Non-operational Agro–processing facilities at various district
An inspection of Agro–processing facilities revealed that while the facilities had
been completed, some remained non-operational. The Agro processing facilities
affected include those in the districts of Kapchorwa, Sironko, Iganga, Pallisa
districts. The communities are therefore being denied the benefits of the Project
meant to improve household income.
District Sub-
County
Pictorial Facility remarks
Kapchorwa Ngege
Rice huller By June 2014 the Agro
processing facility had
been completed however
the facility was not
operational because the
Local government had not
yet recruited Private
Operator and Farmer
management committee
had not yet been formed.
291
Kapchorwa Kawowo
Coffee
huller, milk
cooler
By June 2014 the Agro
processing facility had
been completed however
the facility was not
operational because the
Local government had not
yet recruited Private
Operator and Farmer
management committee
had not yet been formed.
Kapchorwa Kaptanya
Milk cooler By June 2014 the Agro
processing facility had
been completed however
the facility was not
operational because the
Local government had not
yet recruited Private
Operator and Farmer
management committee
had not yet been formed.
Sironko Zesui
Maize mill The Agro processing
facility was to be
completed by September
2012.
By June 2014 the Agro
processing facility had
been completed however
the facility was not
operational because the
Local government had not
yet recruited Private
Operator and Farmer
management committee
had not yet been formed.
292
Sironko Buteza
Milk cooler,
maize mill
The Agro processing
facility was to be
completed by September
2012.
By June 2014 the Agro
processing facility had
been completed however
the facility was not
operational because the
Local government had not
yet recruited Private
Operator and Farmer
management committee
had not yet been formed.
Pallisa Agule
Milk cooler The Agro processing
facility was to be
completed by September
2013
By June 2014 the Agro
processing facility had
been completed however
the facility was not
operational because the
Local government had not
yet recruited Private
Operator and Farmer
management committee
had not yet been formed.
Pallisa Patete
Rice huller The Agro processing
facility was to be
completed by September
2013.
By June 2014 the Agro
processing facility had
been completed however
the facility was not
operational because the
Local government had not
yet recruited Private
Operator and Farmer
293
management committee
had not yet been formed.
Iganga Namugalwe
Coffee
huller
The agro processing
facility was to be
completed by September
2013
By June 2014 the Agro
processing facility had
been completed however
the facility was not
operational because the
Local government had not
yet recruited Private
Operator and Farmer
management committee
had not yet been formed.
Iganga Nakigo
Coffee
huller
The agro processing facility
was to be completed by
September 2013.
By June 2014 the Agro
processing facility had
been completed however
the facility was not
operational because the
Local government had not
yet recruited Private
Operator and Farmer
management committee
had not yet been formed
Management explained that the listed Agro-processing facilities were not
operational mainly due to lack of private operators to run and manage the facilities
on behalf of the respective Sub counties. Management indicated that they are
working closely with the affected Sub counties to expedite the process of
identifying the suitable private operators to operate and manage the facilities
sustainably.
I await the outcome of management‟s efforts.
294
(v) Poor storage facilities for Agro processing equipment
It was observed that the agro processing equipment in Kawowo Sub-county,
Kapchorwa district was kept in an open place without any proper safe guards. The
equipment may be damaged or stolen which may result in to a financial loss to the
project.
Management explained that the affected machine had been transferred to a
completed shelter and was currently undergoing installation.
I await the outcome of management‟s efforts.
f) Non-operational markets in the districts
Audit inspection revealed that some markets that had been completed were not
operational. For instance the market in Kaptanya Sub-county contracted at
UGX.364,993,230 and Kawowo Sub-county contracted at UGX.392,752,964 in
Kapchorwa District, was completed but there were no locks in place and the
contractor abandoned work before fixing the locks. In Sironko, Tororo and Pallisa
Districts, the unutilized markets were being occupied by idlers. Management
stated that these markets were handed over to the Sub Counties and it was the
responsibility of the Sub-counties to allocate the stalls to the vendors. Refer to the
pictures shown below:
Abandoned market in Kaptanya and Kawowo Sub-counties Kapchorwa District
The community is not benefiting from the project infrastructure.
295
Management explained that the non-operationalization of markets was due to
among others poor location, lack of enforcement of the Market Act by the Local
Governments, political interference in the running of markets, reluctance to pay
market dues by the vendors, inadequate produce/commodities to sell in the
market during the off-season. However the aforementioned issues were being
addressed jointly by the affected Local Governments and positive results were
being realized.
I await the outcome of management‟s efforts.
g) Rehabilitation of Community and Access Roads (CAR)
1. Delayed completion of road works UGX.392,009,451
During the financial year 2010/2011, Masaka District Administration awarded a
contract worth UGX.392,009,451 to a local contractor to rehabilitate community
roads under CAIIP-1 batch B. However, the CAIIP-1 project ended before the road
works were completed and at the time of project closure four certificates
amounting to UGX.170,662,000 had been paid. Refer to the schedule of roads
below
b
e
l
o
w
:
Roads Length
Nkuke-Minyinya-Kitoma road
4.8 km
4.8km
Bbuliro-Kitunga road
4.2 km
Kaswa-Kibbe-Butosi road
3.2 km
Manzi-Bukunda road
2.5 km
2.5 km
Biyinja-Kyembazi road
6.0 km
TOTAL 21.3 km
296
The delay in contract performance increases administration costs. It also denies
the community access to good roads meant to improve peoples livelihoods.
Management explained that Masaka District Local Government was notified and
advised several times by the project management to improve on contract
management of this contract or have it terminated. However by the time remedial
action was taken, the donors had closed the window for fresh procurements.
Currently the roads had been opened and were motorable save for the sections
that needed raising the swampy areas. To address the challenge the district used
counterpart funding from Government and force on account. I explained that the
funds advanced to the contractor earlier with no partial works done could be a loss
to government.
I advised management to follow up and ensure that the road works are fully
completed.
2. Lack of routine maintenance of roads by the Districts
Most of the roads in the Districts under CAIIP 1 (Batch A and B) Project were
completed. However, the districts are not maintaining these roads and
consequently some roads have narrowed as a result of growth of grass. During
inspection of Lyantonde and Ssembabule districts, the District Engineers explained
that the districts do not get enough funds to maintain the roads. Refer to the
pictures below:
Districts Remarks
Lyantonde
Buyaga-Keishango-Rwamyongo road
10.5 km
The road was rough due to lack of
maintenance
Ssembabule
297
Lugusulu-Kanjunju road
10.0km contracted to M/S PRIBERA
CIVIL
A section of the road had narrowed due to
overgrown grass.
Due to non-maintenance, the roads may not last to their expected life span.
Management explained that a list of all rehabilitated roads was submitted to the
Uganda Road Fund to harmonize the periodization of the community roads in the
Project Sub-Counties for maintenance. However, management promised to closely
liaise with the Road Fund and the Project Districts to ensure that the rehabilitated
roads are maintained.
I await the outcome of management‟s efforts.
h) Status of Project Implementation
3. Project performance against the logical frame work
According to the project five year implementation plan and annual progress
reports, the performance of the project as at 30th June 2014 was noted as below;
Project
Activity
Target as
per
project
Appraisal
document
Achieved
as per
draft
Annual
report
%age
achieved
as per
draft
Annual
report
Amount (UGX) Audit Remarks
Rehabilitation of
CARs
4680Km 4447Km 95%
110,156,252,767
All completed roads have been
dully handed over to the
respective LGs. However there
is lack of routine road
maintenance.
Some roads in Masaka district
contracted had not been
completed.
Rehabilitation of
District Feeder
Roads
520 Km 578 Km 111% 21,244,312,717 All completed roads have been
dully handed over to the
respective LGs. However, there
is lack of routine road
298
Project
Activity
Target as
per
project
Appraisal
document
Achieved
as per
draft
Annual
report
%age
achieved
as per
draft
Annual
report
Amount (UGX) Audit Remarks
maintenance.
Construction of
rural markets
78 markets 77
markets
98.70% 10,456,057,439 All markets have been handed
over to the respective LGs.
However some markets are not
being utilized by the beneficiary
communities.
Construction of
APF Shelters
117 123 105% 4,090,876,965 There were 3 uncompleted agro
processing facilities in Tororo
district.
It was also noted that some
agro processing facilities
especially in Eastern Uganda
were not being utilized by the
beneficiary communities.
Supply and
installation of
APF machines
117 123
assorted
APF
machines
105 5,560,049,800 It was noted that some Agro
processing equipment especially
in Eastern Uganda lacked some
essential components which
affected their use for example
milk coolers in Pallisa lacked
Lactometers while in Kapchorwa
and Tororo districts rice mullers
lacked gear switches and
mortars.
Extension of HEP
grid to APF sites
52 Km to
67 APF
sites
5,002,089,182
Supply,
installation and
commissioning of
generators
40 KVA
generators
40 KVA
generators
100% 1,894,002,500 Wrong type generators had
been supplied and later replaced
with new ones however some
areas in Eastern Uganda had
not received the new
generators.
Services and
operations
15,549,356,915 The project had not completed
the following activities;
completion report, RIMS Follow-
up study, financial impact
assessment and environmental
299
Project
Activity
Target as
per
project
Appraisal
document
Achieved
as per
draft
Annual
report
%age
achieved
as per
draft
Annual
report
Amount (UGX) Audit Remarks
audit.
Total 173,952,998,285
Management explained that the pending activities include operationalization of the
markets and the agro facilities. Management further explained that since the
project was implemented in Local Governments, it will ensure that all the
completion activities are fully implemented under its supervision.
I await the outcome of management‟s efforts.
15.4 COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT
PROGRAMME – PROJECT I1 (CAIIP I1)
(a) Compliance w
(b) .ith Financing Agreement and Government of Uganda Financial
Regulations
i) Budget Performance-Low Absorption Capacity
The approved Project expenditure estimates for the financial year amounted to
UGX.89,898,531,239. However, only UGX.40,035,310,967 was spent during the
year, representing an absorption capacity of 45%.
Low absorption capacity denies the beneficiary communities services which would
have improved their livelihood. There is also a risk that Management may not
meet project objectives within the agreed project period.
Management explained that 83% of the total budget was earmarked for the
rehabilitation of 1,533 km of Batch B and C community access roads, rehabilitation
of 230.4km of District roads, and the construction of shelters for agro processing
facilities, however implementation was delayed because of procurement
challenges. The procurement processes for the last batch of community access
300
roads were concluded during the year under review and project implementation
has now been rolled over to the financial year 2014/15.
I advised management to ensure that the implementation is carried out as planned
and within the agreed project timelines.
ii) Failure to deduct 6%withholding tax (WHT) from service providers
It was observed that Management did not withhold tax amounting to
UGX.1,792,568,024 on payments for services provided, contrary to Section 120(1)
of the Income Tax Act. Non-deduction of withholding tax from civil works was a
violation of the tax laws which may result into penalties and fines being imposed
on the Project by the tax body.
Management explained that the Project is being financed using Loan funds from
the African Development Bank (ADB) whose bilateral Agreement with Government
precludes the use of the loan funds for the payment of taxes relating to the goods
and services required for the execution of the Project therefore deduction and
subsequent remittance of WHT under this Loan funding constitutes ineligible
expenditure which are grounds for suspension of disbursements of loan funds to
the Project.
I advised management to engage the Ministry of Finance, Planning and Economic
Development to ensure that withholding tax from outstanding payments to eligible
service providers is deducted and remitted to the tax body as required by the
Income Tax law.
iii) General Standards Of Accounting And Internal Control
i) Vacant post of Financial Management Specialist
The project‟s approved organization structure requires the project to employ a
Financial Management Specialist who is responsible for establishing and
maintaining a financial management system which is in line with the GoU
Regulations and Donor Procedures and ensuring that sound internal controls are in
place. However, it was noted that the project operated without a Financial
301
Management Specialist for over a year. Absence of a financial management
specialist may hinder proper and prompt implementation of project activities.
Management explained that the recruitment process for the post was initiated and
the successful candidate was submitted to African Development Bank for approval.
I await the outcome of the management initiation.
iv) Field Inspections
An audit inspection was carried out in September 2013 and the following issues
relating to the implementation of the Project were noted;
(i) Abandonment of Community access road under Batch B
Terms and conditions of Project civil works contracts stipulate that the contractors
should complete the work and correct any defects within six months from the
contract substantial completion date. It was however noted that some road works
had not been completed while other sites had been abandoned. Specifically
during the inspection in Lango region, it was observed that Agwata Atidi-Kachung
road in Agwata Sub County in Dokolo District constructed by Sefkon (u) Ltd had
been abandoned. The road was contracted at a sum of UGX.428,915,399 and as
at 30th June 2014 a sum of UGX.55,759,002 had been paid to the contractor.
There is a risk that extra administrative costs will be incurred as a consequence of
delayed implementation.
Management explained abandonment of site for a continuous period of 28 days is
a substantial breach of contract. When this occurred, management through the
District Local Government took immediate action by terminating the
aforementioned contract. The works have been re-packaged for procurement to a
new contractor and the accrued retention shall be used to meet additional
administrative costs.
I advised management to urgently recruit the new contractor and have the
contractual works concluded.
302
(ii) Delayed completion of contracts for Agro–processing facilities
According to Terms and conditions of Agro Processing facilities contracts, the
contractors were to execute, complete the works and remedy any defect therein,
in conformity with all aspects in the contract within a period of six months from
the date the contract comes in force. During inspection, it was noted that the
Agro-processing shelter at KYAMULIBWA in Masaka district constructed at a cost
of UGX.103,499,045 had been completed, however there was no electricity
connected to the facility hence the facility was not being utilized. Refer to photos
below. At the time of inspection, the transformer had not been installed.
Agro processing facility at Kyamulibwa not functional
Poles with no transformer to supply electricity to the facility
The community is being denied the benefits of the Project meant to improve
household income and livelihood.
Management explained although the construction of the shelter was completed,
the contract for the extension of the grid, supply and installation of the agro-
processing facility and the transformer were still on-going. Management also
explained that supervision and monitoring of on-going works throughout the
beneficiary districts had been intensified to ensure that activities are completed by
December 2014.
303
I await the outcome of management‟s efforts.
v) Status of Project Implementation
(i) Project performance against the logical Frame Work
According to the project five year implementation plan and annual progress
reports, the project had not achieved the following targets by the time of audit,
despite the fact that the project is set to close in December 2014:
Component Planned Activity Status as at 30th June
2014
Remarks
Rural
Infrastructure
Improvement
Completion of
pending Batch A contracts
1418.4km (97.5%) out
1454.1Km of Batch A CARs have been
completed.
Civil works on the
remaining 8.2 km in Kapchorwa district still
on-going. 3 non performing
contracts in Katakwi,
Kitgum, Kibale, were
terminated and re-advertised under
Batch C and 1 contract in Pader (Lot 80) with
works on-going under
Batch B.
Complete all
pending works-
642.6km of Batch B and
27.9kms of
district feeder roads
91.4% (1096.75km)
out of 1,198.2km of
Batch B have been completed and handed
over to the respective
district Local Governments
All the 230.4 km of
230.4km of District Feeder roads have
been completed.
All pending civil works
of 101.45km Batch B
CARs are expected to be completed during
the financial year
2014/15.
Complete
construction of 80 agro-shelters,
2 produce stores and
procurement of
contractors for the 15 re-
advertised agro-shelters.
Civil works on the 12
re –advertised lots commenced while the
3 contracts in Dokolo and Pader have been
re-advertised and at
evaluation stage
Pending civil works on
agro-shelters and stores were expected
to be completed during the next
financial year.
Civil works on the re-
advertised agro-shelters commenced
and works are on-going at all sites
304
Component Planned Activity Status as at 30th June
2014
Remarks
Rehabilitate
about 600km of Batch C CARs
10 contracts of batch
C CARs have been granted a no objection
by the bank and the rest of the contracts
will be considered for
re-advertisement in the next quarter.
Civil works for the
cleared lots were expected to
commence by in the first quarter of
2014/15
Deliver 95 APFS
to the respective
districts
All the 95 assorted
APFs have been
delivered. Overall 30 assorted APFs have
been installed including 5 milk
coolers, 2 coffee hullers, 15 maize mills,
5 grain mills and 3 rice
hullers.
Installation of APFs is
still on going through
out the project area where the APF
shelters have been completed.
Complete works
for the extension
of 54 km of grid
to 57 APFs sites
Progress on works for
extension of 54Km of
Hydro Electric power
grid to 57 APF sites averages at 85% with
completed extension of conductors and
installation of transformers.
Installation of energy
meters and opening of
accounts will be done
in the first quarter of 2014/15
Community
Mobilisation
Follow up
districts on
issues of formation and
training of IMCs,
engagement of private
operators, identification /
formation of farmer‟s
cooperatives and
on issues of security of
tenure for all investments.
Out of the 14 districts
so far visited only 12
(86%) have confirmed formation and
presence of farmers‟
co-operatives for APFs. The remaining
ones are in process. IMCs for Batch A&B
are in place formed
and trained
There is need to
sensitize the districts
about sustainability of the project‟s
investments such as
roads and Agro-processing facilities.
Complete
formation and
training of IMCS for batch C CARs
Formation of IMCs
completed and training
is on-going.
Training was
completed
305
Component Planned Activity Status as at 30th June
2014
Remarks
Component
Coordination
Carry out
Monitoring and Supervision
The project
participated in one Support Supervision
mission conducted by the Bank towards the
beginning of the
quarter. The mission emphasized the need
to expedite implementation of on-
going civil works to
ensure that they are all completed before
project closure in December 2014
Technical support
supervision, monitoring and
guidance offered to all
districts and lower local governments.
It was noted that
some works had been abandoned and some
agro processing facilities were not in
operation thus there
was need to intensify monitoring and
supervision of project activities in order to
increase their benefit
to the communities.
Management has not fully achieved targets in the loan agreements.
Management explained that although the Project is set for closure at the end of
December 2014, an extension is anticipated for effective completion. Management
further explained that most of the road works had been completed while the
progress on construction of agro-shelters averages 54% of the works and besides
all the 95 assorted Agro-Processing facilities had been delivered and installation
was on-going.
I advised management to intensify the supervision and monitoring and ensure that
the project implementation is fully undertaken within the agreed timelines.
306
15.5 COMMUNITY AGRICULTURAL INFRASTRUCTURE IMPROVEMENT
PROGRAMME – PROJECT I1 (CAIIP III)
(a) Compliance With Financing Agreement And Government Of Uganda
Financial Regulations
It was noted that management had complied in all material aspects of the
financing and GoU financial regulations except for the matters below;
i) Budget Performance-Low Absorption Capacity
The approved Project expenditure estimates for the financial year amounted to
UGX.45, 015,592,384. However, only UGX.2,249,801,651 was spent during the
year, representing an absorption capacity of only 5%.
Low absorption capacity denies the beneficiary communities services which would
have improved their livelihood. There is also a risk that Management may not
meet project objectives within the agreed project period.
Management explained that the bulk of the budget was earmarked for
rehabilitation of 1,318.9Km of the first batch of community access roads, selection
of subsequent priority infrastructure, carrying out needs assessments towards
identification and prioritization of agro processing facilities including designs and
carrying out of a project baseline study. However the project performance was
affected by procurement challenges of the community access roads which was the
major cost driver. Management however indicated that a number of contracts
have now been awarded and major civil works will commence in 2014/15.
I advised management to undertake procurements early enough and ensure that
budget implementation is carried out as planned and in agreed time period.
(b) General Standards of Accounting And Internal Controls
i) Spending at source
Project Operations Manual PART two Paragraph 3.1 (sub-sections 111 Flow of
funds) requires all project funds including GoU counterpart funding to be
deposited to special account held with Bank of Uganda. However, it was noted
that GoU contribution amounting to UGX.199,728,000 was released by Ministry of
307
Finance, Planning and Economic Development to the project through the Ministry
of Local Government Treasury General Account, where funds were spent on non
project activities contrary to the Project‟s operations manual. Spending Project
funds by the Ministry does not only deny Project Management control over the
funds but also poses a risk of diverting the funds to activities outside the project.
Management explained that with the migration of Government accounting system
to the IFMS system, all the GOU project accounts were closed hence counterpart
funds for the project were transferred to the Ministry General account.
I advised management to ensure strict adherence to controls of project accounts
such as authorization and purpose of the expenditure for proper monitoring and
control.
ii) Vacant post of Financial Management Specialist
The project‟s approved organization structure requires the project to employ a
Financial Management Specialist who is responsible for establishing and
maintaining a financial management system which is in line with the GoU
regulations and Donor procedures and ensuring that sound internal controls are in
place.
It was noted that the project operated without a Financial Management Specialist
for over a year. Absence of a financial management specialist may hinder proper
and prompt implementation of project activities.
Management explained that the recruitment process for the post was initiated and
the successful candidate was submitted to African Development Bank for approval.
I await the outcome of the recruitment process.
(c) Status of Project Implementation
i) Project performance against the logical frame work
The Project was expected to commence in 2011 and run for 5 years, however,
operations begun in April 2012. A review of the project implementation plan and
308
project progress reports revealed delays in the implementation of activities as
indicated below;
Activity Targets Progress as at 30th June 2014
Rehabilitation of Community
Access Roads
3,060km 3 contracts for lots 22, 62 and 77 in
the districts of Sheema, Luwero and
Busia are ongoing and physical
progress averaged 70% as of 30th June 2014. In addition, civil works
for 43 lots under the re-advertised Batch A CARs commenced in May
2014 and 31 non-responsive lots were retendered
Rehabilitation/Construction of
Markets
68 Markets Rehabilitation of rural markets was
deferred until there is improved
performance of markets under CAIIP-1
Construction of shelters for 78
Agro Processing Facilities
78 shelters Needs Assessment and design of 78
Assorted APFs completed. However
construction had not yet started.
During inspection of beneficiary some districts, it was observed that operational
funds had been received to cater for needs assessment, training and construction
of community access roads among others. However, activities had not yet started.
Delay in implementation of planned activities denies beneficiaries the benefits of
the project, besides, project objectives may not be achieved.
Management explained that measures had been put in place to ensure that all
activities are undertaken in time and these included expediting the procurement of
the remaining batches of roads, design of agro processing facilities and training
staff in contract and environmental management.
I advised to expedite the planned project activities in order to meet project
objectives within the agreed time frame.
309
15.6 MARKETS AND AGRICULTURAL TRADE IMPROVEMENT PROJECT 1
(MATIP 1)
(a) Compliance With Financing Agreement, Government of Uganda
Financial Regulations And Statutory Obligations
i) Under-Performing Loan from Arab Bank for Economic Development
in Africa (BADEA) - US$ 10,000,000
According to the loan agreement signed on 16th July 2009 between Government of
Uganda and the Arab Bank for Economic Development in Africa (BADEA), the loan
amount of USD 10million was for construction of five markets at Kasubi, Busega,
Kansanga (Kampala City), Kimaka (Jinja District) and Nyendo (Masaka District).
The executing Agency was required to acquire land for construction of the markets
in the above mentioned locations before disbursement of funds. The agreement
indicated that the borrower shall pay interest at the rate of one per cent (1%) per
annum on the principal amount of the loan withdrawn and outstanding from time
to time. The loan was declared effective on 21st January 2010 with the last
disbursement expected on 30th March 2013. It was however noted that only
UGX.112,428,671 was disbursed during the year under review.
The funds were spent on consultancy services for developing architectural designs
and supervision of the construction of the five markets. The commitment fees and
interest that has accrued on this loan account since its effective date is estimated
at US$500,000. Under-utilization of the loan may result into a financial loss to
Government. Delays in accessing funds have a negative effect on service delivery
to communities as the period for the construction of the above five markets has
since overlapped the agreed date of last disbursement of 30th March 2013.
Management explained that the performance of the loan was mainly affected by
lack of evidence of ownership of land in Kansanga, Kimaka and Kasubi, a major
condition for the design of the markets of the town councils. However following
the confirmation of availability of land for Nyendo and Busega, detailed designs
were completed and submitted to BADEA and approved. To date, the bids for the
construction of Busega and Masaka markets have been evaluated and sent to
BADEA for approval after which construction will commence for the two markets.
310
I advised management to acquire land in Kansanga, Kimaka and Kasubi as
required to enable the smooth utilization of the loan fund.
ii) Budget Performance-Low Absorption Capacity
The approved Project expenditure estimates for the financial year amounted to
UGX.61,349,873,640. However, only UGX.40,449,178,104 was spent during the
year, indicating absorption capacity of 66%.
Low absorption capacity denies the beneficiary communities services which would
have improved their livelihood. There is a risk that Management may not meet
project objectives within the agreed project period.
Management explained that the shortfall in absorption capacity was mainly due to
the failure of Government to contribute towards the tax component which affected
the performance. However, communication had been made to Ministry of Finance,
Planning and Economic Development, and the taxes are expected to be cleared in
the 2014/15 financial year.
I await the outcome of management‟s efforts.
iii) Counterpart funding
According to the Provisions of the Loan Agreement, GOU is required to contribute
funds towards the implementation of Programme activities. A review of the project
budget revealed that a total of UGX.10,395,482,191 was budgeted as GOU
counterpart funding, however according to the Project‟s records, only
UGX.1,273,934,149 was released for Project activities resulting into a shortfall of
UGX.9,121,548,042 (88%). Failure to provide counterpart funding as budgeted for
is in violation of the project Financing Agreement. Besides, underfunding hinders
the smooth implementation of the project activities.
Management explained that the Ministry was aware of the constraints caused by
inadequate funding and had already communicated to the Ministry of Finance,
Planning and Economic Development to ensure sufficient releases are made in the
financial year 2014/15.
311
I advised management to continue liaising with the Ministry of Finance, Planning
and Economic Development to ensure all budgeted funds are released to allow
smooth implementation of the project activities.
iv) Outstanding VAT on certified works and consultancy
The contract agreements signed between the Line Ministry and the contractors for
civil works for the construction of markets quoted the prices inclusive of Value
Added Tax (VAT). The project had VAT payable and accumulated interest of
UGX.12,767,665,608 at the close of the financial year. It was noted that the
contractors for civil works at the seven sites were threatening to sue Ministry of
Local Government for the unpaid VAT including interest. The delayed payments
may result in to a nugatory expenditure in terms of legal costs to the Project.
Management explained that VAT was not paid to a number of service providers
due to insufficient Government counterpart funding. Management further stated
that supplementary funding was sought to cover the outstanding amounts which
will be catered for in the financial year 2014/2015.
I wait the outcome of management‟s efforts on the matter.
(b) General Standards of Accounting And Internal Control
i) Spending at source
Project Operations Manual PART two Paragraph 3.1 (sub-sections 111 Flow of
funds) requires all project funds including GoU counterpart funding to be
deposited to special account held with Bank of Uganda.
A review of the Ministry of Local Government development expenditure records
revealed that GoU contribution amounting to UGX.995,300,408 released by
Ministry of Finance, Planning and Economic Development to the project through
the Ministry of Local Government Treasury General Account, was spent by the
Ministry on behalf of the Project on non project activities which was contrary to
the Project‟s operations manual.
312
Spending Project funds by the Ministry does not only deny Project Management
control over the funds but also poses a risk of diverting the funds to activities
outside the project.
Management explained that with the migration of Government accounting system
to the IFMS system, all the GOU project accounts were closed hence counterpart
funds for the project were transferred to the Ministry General account.
I advised management to ensure strict adherence to controls of project accounts
such as authorization and purpose of the expenditure for proper monitoring and
control.
ii) Vacant post of Financial Management Specialist
The project‟s approved organization structure requires the project to employ a
Financial Management Specialist who is responsible for establishing and
maintaining a financial management system which is in line with the GoU
regulations and Donor procedures and ensuring that sound internal controls are in
place.
However, it was noted that the project operated without a Financial Management
Specialist for over a year. Absence of a financial management specialist may
hinder proper and prompt implementation of project activities.
Management explained that the recruitment process for the post was initiated and
the successful candidate name was submitted to African Development Bank for
approval.
I await the outcome of the recruitment process.
(c) Status of Project Implementation
i) Delayed implementation of project activities
A review of the project implementation plan and progress reports revealed that
the project had not achieved planned targets in the agreed timeframe. The
following activities should have been undertaken by the end of the year under
review;
313
Component Activity Progress as at 30th June 2014
Market
Infrastructure
Development.
Complete and handover all
the remaining 4 markets
namely; Lira, Jinja, Gulu and
Hoima.
Works are still on-going on all the
4 markets.
The Progress of work was
affected by delayed VAT payment
to contractors and civil works
consultants.
Complete designs of Busega
and Nyendo markets under
BADEA loan.
Detailed designs were produced,
reviewed and approved by
relevant authorities, including
urban authorities and the funding
agency (BADEA).
Initiate procurement of
contractors for Nyendo and
Busega markets under the
BADEA loan
Construction of the Busega and
Nyendo markets is currently
under procurement with bid
closure slated for 1st September
2014.
Market
Management and
Trade
Enhancement
Complete the re-location of
vendors back to the
completed markets
The process of resettling vendors
in Mbale and Hoima markets is
still on-going. A total of 1,753
vendors had already resettled in
Mpanga and Wandegeya
markets. Registered vendors are
given first priority in the
allocation process and any other
remaining facilities will be given
out on a competitive basis as per
the laws that govern
Procurement and Disposal of
Public Assets. However there is
need to carry out sensitization of
market vendors in Hoima, Gulu,
Jinja and Lira markets regarding
market facilities management
guidelines in order to enable
sustainability of project
objectives.
Complete the establishment
of the Market and
Management Information
System
The process of establishing the
Market Management and
Information System is still on-
going.
Programme
Management and
Coordination
Undertake monitoring and
supervision
The construction work continues
to be supervised by respective
consultants with oversight
guidance from the Programme
314
Component Activity Progress as at 30th June 2014
Facilitation Team (PFT) of the
Ministry.
Conduct a progress review
workshop
No review workshop was held
during the reporting period.
Delay in implementation of activities denies beneficiaries the benefits of the
project, besides, project objectives may not be achieved due to the delays.
Management explained that the project is in its fourth year of implementation and
is expected to close in 2015. By then, the indicated project milestones will have
been achieved.
Management is advised to expedite the planned project activities in order to meet
project objectives within the agreed time frame.
15.7 DISTRICT LIVELIHOODS SUPPORT PROGRAMME (DLSP) – MINISTRY OF
LOCAL GOVERNMENT (MOLG)
(a) Compliance With Financing Agreement And Government of Uganda
Financial Regulations
A review of the Programme implementation records revealed that generally there
was compliance with the financing agreement and Government of Uganda
financial regulations, except for the following:
(i) Government of Uganda (GOU) counterpart funding
A sum of UGX.296,008,000 was received as GOU counterpart funding during the
year out of the approved budget estimates of UGX.399,883,115. The receipts were
credited to the Ministry of Local Government (MoLG) General Treasury Account.
The following were noted during the audit;
Non-incorporation of the GOU counterpart funding into the
Consolidated Annual budget of DLSP
According to the Project Financial Guideline 1.32, all budgets are required to be
associated with codes which identify the funding source, budget categories,
315
budget components, sub components, and activities as indicated in the budget
plan chart and analysis. However a review of the Annual work plan and budget for
the programme revealed that GOU counterpart funding budget and work plan was
not incorporated in the project consolidated work plan and budget as required.
Failure to incorporate the GOU funding budget estimates in the Project
consolidated work plan and budget may result into the entity spending funds on
unplanned activities.
Management explained that the Annual Work Plan Budget (AWPB) will be adjusted
to incorporate the GoU Component in the subsequent year, however, the GOU
component had been incorporated in the Ministerial Policy Statement as a starting
point.
I await management implementation on the matter.
Low absorption Capacity
The approved budget for the financial year 2013/2014 was UGX.49,301,833,686.
Although UGX.24,430,141,921 was actually released during the year, only
UGX.23,769,033,103 was spent representing an absorption capacity of only
48.2%. It is worth noting that the Project is in the second last–year of
implementation. Low absorption capacity denies the community services ability to
uplift their livelihoods. Furthermore Project objectives may not be achieved within
the stipulated time frame leading to extra administrative costs.
Management explained that all the funds were committed in contracts and that the
Programme Coordination Unit had put in place mechanisms to complete planned
activities by December 2014.
I advised management to ensure that budget implementation is carried out as
planned before activity closure.
Status of the loan disbursement
A review of the financial statements revealed that out of the total IFAD loan of
USD 52,000,000, Management had only utilized USD 38,951,348 resulting into an
316
estimated unlimited loan balance of USD 13,048,652 (25% of the total loan) yet
the project completion date is set for 31st December 2014. This assertion was
supported by the project Aid memoire dated 7th-31st October,2014 where it was
revealed that pending road works and other activities amounted to USD 12.1m
while un disbursed funds on the IFAD account amounted to USD 12.2m as at that
date. There is a risk that management may not fully utilize the loan by the project
closure date if activities are not completed in time. Administrative costs are also
likely to escalate.
Management explained that all the undisbursed funds were already committed to
on-going road works. Management further explained that although the project
completion scheduled for end of December, 2014, the project will continue
processing payments even after the project completion date provided the
payments relate to works which were performed before the project completion
date.
Management is advised to expedite the implementation of the activities to ensure
that the loan is fully utilized to allow the project achieve its objectives.
(b) General Standards of Accounting And Internal Control
(i) Wasteful expenditure on purchase of „„TOMPRO‟ Accounting
Software
According to the Supervision and Implementation Support Mission report: (16-27
July, 2012), ''TOMPRO'' Accounting Software was procured at USD 50,000 and
installed at both the districts and the Project Coordination Unit in Kampala. The
Accounting software was intended to harmonize the financial, monitoring and
reporting for the project team. The software has modules for system parameters;
financial accounting, reports analysis, budget control, fixed assets management,
credit management, procurement management and disbursement reports.
It was noted that the software had not been put to use at the Project Coordination
Unit (PCU) and the districts despite further recommendation by the IFAD mission
in the Aide memoire (8th-19th July 2013) to fully implement “TROMPO” by 31st July
2013. Therefore the objective of introducing the software to capture transactions
317
at Project Coordination Unit and Programme districts has not been achieved
wasteful expenditure of USD 50,000 to the project.
Management explained that the software could not be used at PCU since data
capture had failed at the district level and it needed reconfiguration which was
expensive and would not yield value for money since the programme was left with
only one year to operate before project closure. Management further explained
that the time was not sufficient to allow the procurement of the consultant to
reconfigure and allow it operate at both PCU and district level.
I advised management to always carry out a study on the use and benefit of such
procurements before undertaking implementation decisions.
(ii) Spending at source
A review of records revealed that GoU contribution amounting to UGX.296,008,000
was released by Ministry of Finance, Planning and Economic Development to the
project through the Ministry of Local Government Treasury General Account,
where funds were spent on behalf of the Project on non-project activities which
was contrary to the Project‟s operations manual. Spending Project funds by the
Ministry denies Project Management control over the funds.
Management explained that with the migration of Government accounting system
to the IFMS system, all the GOU project accounts were closed hence counterpart
funds for the project were transferred to the Ministry General account.
I advised management to ensure strict adherence to controls to allow project
management full control of the project funds.
(iii) Un accounted for advances
The project had outstanding advances of UGX.183,219,506 as at 30th June 2014 as
indicated in the table below.
The delays in accountability affect project implementation and intended objectives
may not be achieved within the stipulated project timelines.
318
District/PCU Outstanding advances as at 30th June,2014
Apac 76,430,000
Bundibugyo 4,728,000
Kamwenge 55,614,834
Luwero 997,000
Busia 15,119,400
PCU 30,330,272
Total 183,219,506
Management explained that they had instituted measures to recover the
outstanding advances in line with the project guidelines.
I await the outcome of Management‟s efforts.
(c) Audit Field Inspections
Field inspection to assess progress on implementation of DLSP activities was
undertaken and the findings were noted:
i) Poor workmanship
Section vii sub sec 1.23.1 General condition of the contract specifies that the
contractor shall construct and install the works in accordance with specifications
and drawings.
During inspection of the rehabilitated roads works in Apac and Oyam districts, it
was noted that although the works had been completed, there was evidence of
poor workmanship on some roads. For example there were no headwalls at the
culvert ends, culverts were not properly installed while some of the headwalls built
were already cracked and lacked wing walls. Details are in the pictures below:
319
Olelpek-AbapirinAbei Border
Road, 22.8km, Batch 2 in
Apac district constructed at a
Contract price UGX.
563,264,970
Silted culverts blocked the road
drainage channel.
The culverts should have been
lifted up.
Alira-Oder Swamp-Abwongo H/C, 12.2 km, Apac district Batch 3 constructed at a cost of UGX. 333,117,310 Cracked headwall along the road.
Arocha market-Tolkoling-owalo trading center 7.2km in Apac district ,Batch 3 constructed at cost of UGX 167,255,691 Head walls were built without wing walls
320
Otwal railway-Ojwii road 12.7km in Oyam district constructed at a contract price of UGX. 344,396,456 Headwalls were built without wing walls.
The poor workmanship affects the lifespan of the roads.
Management explained that the beneficiary districts and contractors had been
notified to correct the defects.
I await the outcome of management‟s efforts.
ii) Under scope of work
Clause 36 of the conditions of contract for the rehabilitation of Community Access
Roads (CARs) states that the Bills of Quantities (BOQs) shall contain items for the
construction, installation, testing and commissioning of the work to be done by the
contractor. It is also used to calculate the contract price and the contractor is paid
for the quantity of work done at the rate in the BOQs for each item.
Furthermore for quotations to be made, the bidder is required to inspect the
project sites with a view of establishing the bills of quantities and develop proper
bid quotations. The consultant is required to inspect the site to come up with
standard costing upon which the projection valuation will be based while the
Project Support Officers (District Engineers), and Infrastructure Engineers are
required to carry out comprehensive assessment of requirements of works in order
to come up with accurate bids.
During inspections in Oyam district, it was noted that some projects had design
gaps which could not be covered using the amount quoted. This was because the
contractors made quotation based only on the paper project design provision
resulting into significant mismatches with actual road bottle necks.
321
Engineers stated that some of the BOQ provisions were below the desired
requirements, given the levels of road bottlenecks observed on the road. Some
contractors have requested for contract variations in order to cover the design
gaps. One of the examples is sited below:
The under scope of work led to delayed completion of the project, sub-standard
works and resulted into increased administrative costs. It is also evident that the
contractors, consultants, Project Support Officers and Infrastructure Engineers did
not carry out comprehensive assessment of the requirements of works on the
ground.
Management stated that measures will be taken to improve on the quality of
designs by undertaking due deligence in validating designs. Management further
stated that the bidding process will compel intending bidders to inspect works
prior to bidding.
I await the outcome of management‟s efforts.
Camnono road –Teogali TC,
11km: Constructed at a contract
price of UGX.374,616,650 was
poorly designed as the road had low
filling which resulted into big
depression that causes water
lodging during the rainy season.
The district engineers amended the
road design as requested by the
project and quoted a contract
variation of UGX.46,055,863 for
additional works on 8th October
2013, however Project Management
had not yet responded to the
quotation.
322
iii) Delayed completion of road works
During inspection of DLSP Batch C Community Access Roads in Bulisa and Masindi
districts, it was noted that some road works had delayed and lacked signposts
contrary to the agreement. It was also noted that in some cases culverts were
poorly installed, particularly the road works done in Bulisa district. In one instance,
the contractor had abandoned works and another construction company
contracted but this time at a higher cost. Details are in the table below;
Batch3 MASINDI District Management
Response
Rehabilitation of Biraizi-
Kuhuuba road (3.2km)
Inspection team noted
that although the works
had progressed well,
the contractor did not
construct headwalls
around swampy areas.
This leaves the road
surface prone to
erosion.
At the time of
inspection the head
and wing walls were
not yet constructed to
allow for settlement
of the fill material.
Otherwise the head
and wing walls may
crack when there is
substantial settlement
after construction.
This was part of the
snags that the
Monitoring Unit
enlisted to be done.
Katagurukwa-Kibbali
Balyegoma Road (13.6KM)
323
Batch3 MASINDI District Management
Response
It was noted that
although the works had
progressed well, the
contractor did not
construct headwalls
around swampy areas.
This left the road
surface prone to
erosion.
The bill boards have
been installed.
Kyagamoyo-Kaikuka-Ntoma
Raod 28.9KM
It was noted that
although the works had
progressed well, the
contractor did not
construct headwalls
around swampy areas.
This left the road
surface prone to
erosion.
The issue was noted
and brought to the
attention of the
contractor.
BULISA DISTRICT
Wanseko-Murchison falls Park
road-18.6 km rehabilitated
under DLSP Batch 2.
324
Batch3 MASINDI District Management
Response
This site was
abandoned by the first
contractor M/S PATROV
International Ltd who
started work in April
2012 at
UGX.559,378,600 and
was paid
UGX.196,684,120 after
doing 35% of the
works. It is now
contracted to M/S
PEKASA Enterprises at a
contract cost of
UGX.874,963,793.
There was no signpost
for the works.
The bill boards have
now been installed.
St. Mary‟s Kalengeija Primary
school- Bubwe road-5.2 km
rehabilitated under DLSP
Batch 3.
This site was contracted
to M/S SINAI General
Merchandise and
Supplies Co. Ltd at a
combined cost of
UGX.913,280,340 which
also covers other road
sections with total
distance of 14.3 km. It
was observed on roads
all done by M/S SINAI
that the culverts were
poorly installed creating
steep humps which may
hinder the benefits of
the services to the road
users.
Management has
instructed the
contractor on the
defects.
325
Batch3 MASINDI District Management
Response
Angolyero-Akollo-Garasoya
road 2.6 km rehabilitated
under DLSP Batch 3.
It was contracted to
M/S SINAI General
Merchandise and
Supplies Co. Ltd at a
combined cost of
UGX.913,280,340 which
also covers other road
sections with total
distance of 14.3 km. It
was observed on all
roads done by M/S
SINAI that the culverts
were poorly installed
creating very steep
humps which may
hinder the benefits of
services to the road
users.
Management has
instructed the
contractor on the
defects.
The delay in contract performance and poor workmanship increase construction
and administration costs and it denies the community access to good roads which
are meant to improve their livelihoods.
I advised management to regularly monitor activities in the districts to ensure
quality and timely completion of road works. Management is further advised to
invoke the penalty clauses within the contract agreements for delayed completion
of works.
(d) Status of Project Implementation
i) Project performance as per logical framework
According to the Project seven year implementation plan and progressive reports,
the project had not achieved some of the following targets despite the fact that
the project closure date was set for 15th December 2014:
326
Activity Targets Progress as at 30th/June/2014
Community infrastructure
Community
Access roads
-Construction of
2,400 Kms of
community access
roads.
-Training 300 road
user committees
- The civil works for the first batch of roads
measuring 313.5 Kms were completed
and the roads are now under routine
maintenance by the districts.
- The construction of the second batch
measuring 640.1 kms has been
completed.
- The construction of the 3rd batch (418.25
km) community access roads is near
completion and about 85% construction
work has been completed.
- The construction of the fourth batch of
community access roads totaling to 766.8
km is in progress and only 55%
construction was has been completed.
COMMUNITY DEVELOPMENT
-Train and facilitate
1,872 community
volunteers
(household
mentors and FAL
instructors)
-Enroll 46,800 FAL
learners
-Train 15,600
farmers in group
organization and
leadership skills.
-Mentor 17,280
poor house holds
- Trained 1,232 Community volunteers (FAL
instructors and house hold mentors) and
empowered them to conduct 572 FAL
classes aimed at mentoring the targeted
17,280 poorer households in all the 13
districts.
- Identified and trained 680 groups in
group dynamics and leadership skills.
- Mentored a cumulative total of 18,172
poorer households to enable them
participate in development initiatives
through identifying and developing their
own path ways out of poverty.
- A total of 24,283 FAL learners were
enrolled to improve their literacy and
numerical skills. Consequently, over
327
Activity Targets Progress as at 30th/June/2014
14,067 FAL learners did proficiency tests
and were able to apply their numerical
and literacy skills. There was a shortfall
about 50% of the planned enrolment.
Agriculture Development And Land Tenure
-Establish 312 on
farm
demonstration.
- 251 on farm demonstrations were
established focusing on different
agronomic practices in management of
Upland rice, bananas, and cassava (Akena
variety). (80%)
District And Sub-County Execution
- Refurbishment of
5 district
headquarters.
2 district headquarters Refurbished (40%).
Management stated the audit observations were appreciated and they were to
ensure that all the remaining activities are completed in time.
I wait the outcome of management‟s efforts towards timely implementation of
project activities.
15.8 MILLENNIUM VILLAGES PROJECT (MVP) PHASE II
(a) Expenditure on project activities
USD 577,239 was expended by the Millennium Villages Phase 11 Project between
22nd May and 31st October 2013 as shown in the table below:
Project Component Amount Spent
(USD)
Increased Agricultural Production and Enhanced Nutrition 48,655
Business Development and Micro-Finance 29,231
Promoting Universal access, Retention and Quality Education 43,874
Strengthening Health Service Delivery Systems for Improving
access to Basic Health Care
223,088
328
Infrastructural Development and Innovation Promotion 32,775
Water for Domestic Consumption, Production and Sanitation. 36,344
Project Implementation Unit Management 163,273
TOTAL 577,239
It was noted from the review of expenditure records that USD 359,393.17 which
represents 62% of the expenditure for the five months period was spent on
wages, salaries and top-up allowances to staff in the seven components and yet
the workplan and budget for the thirteen months period from 22nd May 2013 to
30th June 2014 provided for a total of US $230,000 on the staff costs. This limited
funding to other vital project activities to just 37.5%. This practice could constrain
effective implementation of other project activities in the long run.
Furthermore, the project employs 200 staff to implement activities in 8 villages of
Isingiro district. The organization structure appeared too big for the project
considering that major activities are executed in Ruhiira village, Isingiro district.
Refer to table showing staff numbers and categories below:
Staff categories Total Number
Coordinators 8
Operations 13
Facilitators 17
Technicians and assistants 12
Data staff 13
Radio presenters 3
Community Education worker 11
Medical workers 31
Support staff 27
Community Health workers 65
TOTAL 200
329
The huge number of staff will lead to excessive staff costs and hamper
implementation of planned project activities, since funds are likely to be drawn
from other programmes to cater for staff costs.
Management explained that Millennium Promise Alliance (MPA) was in the process
of streamlining the project personnel to a structure that suites the task although
the existing team which implemented Millennium Villages Project (MVP) Phase I
kick-started Millennium Villages Project Phase II.
I advised Management to expedite the process of streamlining the Project staffing
structure.
(b) Lack of Government of Uganda (GoU) counterpart funding
Article 7.1 of the loan agreement between Government of Uganda and IDB
requires the borrower to promptly fund the Project in accordance with the lender‟s
terms and conditions. Accordingly, Government of Uganda was required to
contribute USD 980,000 to the project over three years in addition to secondment
of health workers and teachers to the Project and other non-monetary support.
However, no funding was received from Government of Uganda for the period
under review.
Failure by Government to meet its funding obligations negatively affects the
project activities.
Management explained that the Project agreement was signed on 22nd May when
the financial year 2012/13 was ending and that a provision for GOU co-funding
was made in the budget for the financial year 2014/15.
Management should follow up the matter with the Ministry of Finance, Planning
and Economic Development to ensure that Government meets its funding
obligation to the project.
(c) Non-compliance with procurement guidelines
Section 7.2 (iv) of the of the loan agreement between the Republic of Uganda and
Islamic development bank (IDB) requires all procurements of civil works,
330
equipment and supplies, computers and related technologies and training
materials whose estimated cost are above ID 25,000 (approximately equivalent to
USD 16,66.26) to be carried out via national competitive bidding.
It was noted that two contracts were awarded through the direct procurement
method contrary to the IDB procurement guidelines. Refer to the table below;
Name of
contractor
Contract Contract
sum
Remarks
Joint Medical Stores
Supply of
Medicine and
medical supplies
48,308,664
No procurement files for
the contract.
Joint Medical Stores owed
the project a balance UGX.1,270,560 from the prior
supplies made but this was not deducted from the final payment.
J & K Technical
Services
Construction of
Staff house at
Ruhiira H/C
67,000,000 Whereas the procurement
documents (evaluation committee
minutes) indicated that 3 companies bidded for the
construction of the Staff house,
there was no evidence of bid documents and bid submission for
the other companies involved in the bidding process.
Non-compliance with procurement procedures denies competition which may lead
to procurement of lower quality services at unfavorable costs.
Management explained during the period under review, the project had not
received funding from either GOU or IDB. Therefore MPA procurement procedures
were consistently applied and not IDB procurement guidelines. Management
further stated that when the project received funds from IDB loan, the
procurement was streamlined with Ministry of Local Government where big items
are centrally purchased using PPDA procedures which cover IDB guidelines.
Management also indicated that the project recruited a procurement specialist to
assist the project in the procurement of goods and services.
I advised Management to follow the procurement guidelines in place.
331
(d) General Standard of Accounting and Internal Controls
It was noted that management had instituted adequate controls to manage project
resources.
(e) Field Inspections
Inspection of the project site in Ruhiira was undertaken. The objective of the
inspection was to assess the extent of implementation of the project, its impact on
the community and compliance with contract agreements. The major findings from
the inspection are below:
i) Lack of Sign Posts
Bills of Quantities provided for a sign post for identification of the sub projects
undertaken by MVP II in the area which the project is located. The bill board is
required to clearly specify the project, the project funders, Sub County, District
and contractor. It was observed that some project investments lacked the
required sign posts.
In absence of sign posts, it becomes difficult to ascertain whether all projects
inspected were actually genuine as there were similar projects being implemented
by Isingiro District Local Government and other Non-Government Organizations
(NGOs).
Management explained that all sign posts for completed and on-going projects will
be installed at the projects sites.
I await the outcome of management‟s efforts.
ii) Delayed completion of staff house at Ruhiira Health Centre III
According to the contract agreements for the construction works, the contract
period for works of the staff house at Ruhiira Health Centre III was three months
ending 27th March 2013. It was however observed that construction had stalled for
over a year. Refer to the picture below;
332
Construction of
Ruhira Health
Centre III staff
house by J&K
Technical
Services
Delay in implementation of planned activities could lead to unnecessary extra costs
in form of administration, monitoring and supervision.
Management explained that the construction of the health centre staff house was
under Millennium Village Phase I which could not be completed due to insufficient
funds. However, the project had included the finishing works of the project in the
Annual work plan 2014/2015 of Millennium village phase II in order to complete
the construction of the health centre staff house.
I await the outcome of management‟s efforts.
iii) Poor Storage of drugs at Ruhiira Health centre
The drugs at the Health centre were poorly stored and as such I was not able to
differentiate between drugs delivered by the project and those from the district.
Poor storage of drugs may lead to losses as the drugs are exposed to undesirable
conditions.
Management has promised to ensure that there is proper storage of drugs at the
Health centre.
I await the outcome of management‟s efforts.
16.0 OFFICE OF THE PRIME MINISTER
333
16.1 Mischarge of Expenditure
The Parliament of Uganda appropriates funds in accordance with the needs of the
country and this appropriation is implemented through the budget in which funds
are tagged to particular activities and outputs using account codes and MTEF
codes. A review of the Office of the Prime Minister‟s expenditures revealed that
the entity charged wrong expenditure codes to a tune of UGX.5,564,282,629. This
constituted 6% of total expenditure for the Office of the Prime Minister. This
practice undermines the importance of the budgeting process as well as the
intentions of the appropriating authority and leads to misreporting.
Management explained that the Ministry of Finance Planning and Economic
Development (MoFPED) advised them to utilize funds that had been released and
were not performing to cater for emerging priorities that included refugee influx
and drought emergencies.
I advised management to streamline the budget process to ensure that sufficient
funds are allocated to each account and budget line codes. Authority should
always be sought before any reallocations are made.
16.2 Advances to Individual Personal Accounts
Non Compliance with Treasury Accounting Instructions
Sections 227, 228 and 229 of the Treasury Accounting Instructions (TAIs),
provides that all payments should be made by the Accounting Officer directly to
the beneficiaries. Where this is not convenient, an imprest holder should be
appointed by the Accounting Officer with the approval of the Accountant General.
UGX.3.6 billion was advanced to Ministry staff through their personal bank
accounts to undertake direct procurements and other activities.
Although the funds were accounted for, such a practice of depositing huge funds
on personal accounts exposes Government funds to risk of loss, since the entity
does not have any control over such funds deposited on personal accounts.
Management explained that most of the activities undertaken by the office are
field based and involve working with other stakeholders in the Districts who are
334
not usually known at the time the requisitions for funds are made, necessitating it
to advance funds to individuals to execute field based activities. In the meantime,
management has engaged the Permanent Secretary/Secretary to the Treasury,
who has authorized OPM to process an impest warrant through the Accountant
General which decision will hopefully go a long way in addressing the problem.
I advised management to ensure strict adherence with the requirements of the
Treasury Accounting Instructions. Meanwhile management effort to resolve the
issue is awaited.
16.3 Refund to NUSAF 2 for PRDP expenditure
A review of the Ministry‟s expenditures revealed that the entity irregularly paid
funds to a tune of UGX.271,193,000 to NUSAF 2 project account as refunds to the
project for ineligible expenditure under the World Bank portfolio. The funds were
for start up activities and fuel paid to PRDP in 2010. The accounting officer
charged sub-programme 0932-130306 item 224001 (Medical and Agricultural
Supplies) for the refund. These funds were not appropriated in the Appropriation
Act. It was also noted that neither virements warrant nor supplementary funding
was requisitioned and approved for the expenditure. This practice undermines the
importance of the budgeting process, suffocates the approved programmes and
also hampers service delivery. Further, the practice leads to misreporting.
Management explained that at the time, there was no budget provision for
preparatory activities for the design of NUSAF2 (counterpart funding). World Bank
insisted that there should be a commitment on part of Government to meet the
initial preparatory costs.
I advised the Accounting officer to ensure adherence to the financial regulations
and apply for supplementary provisions where unforeseen circumstances arise
which may not be postponed without detriment to public interest.
16.4 Quarterly Staff allowances
The Ministry paid quarterly allowances to Ministers, staff, police officers, home
guards and political assistants for the year under review to a tune of
335
UGX.1,269,305,000. The payments were not provided for in the standing
instructions.
Payment of irregular allowances affects the entity cash flows and results into
diversions of government funds.
Management promised to streamline payment of these allowances.
I await management‟s efforts in streamlining the payment process.
16.5 Gross payment tax
a) Budgeting
Budget estimates provide a basis for the Ministry commitment and represents the
Ministry‟s understanding of the scope and expense of what needs to be done, and
the amount required to settle in taxes. The Ministry budgeted for a total of
UGX.16,413,653,190 to cater for gross tax payments and only UGX.5,100,000,000
was released by Treasury. Out of the release only UGX.3,539,828,278 was spent
reflecting 31% budget release and 69% release utilization. Allocating funds for
activities/expenses whose likelihood of occurrence is remote provides avenues for
diversions as well as large budgetary slacks which provide for future unfair
budgetary variations.
Management explained that the gross tax budget was a non-resource item and not
tied to the ceiling of Vote 003. Due to the withdraw of donor support to OPM, a lot
of anticipated procurements which would have consumed much of the gross tax
were not procured creating a huge variance between the budgeted and the actual
outturn. Management further explained that the gross tax component is also used
to pay taxes on imports donated by Non-Governmental Organizations (NGOs) to
the Sector which in most cases are not known at the time of budgeting.
I advised Management to always ensure that reasonable budgetary estimates are
made.
b) Tax obligations by the Ministry
336
The Office of the Prime Minister entered into several Memoranda of Understanding
with Non-Governmental Organizations and provided for tax settlement on their
behalf within these MoUs for goods acquired by them. As such, the Ministry had to
meet tax obligations on behalf of these NGOs arising out of the agreements made.
The following were observed:
Article 7 of the MOU‟s signed before 2013/14 financial year regarding taxes
and duties was open ended as it did not limit the type of imports, e.g. vehicle
capacities, luxurious goods etc.
It should be noted that upon paying, the Ministry has no control in regard
to the final destination of the goods implying that there is a risk that such
goods may end up in the open market.
This practice exposes the Ministry to the risk of payment for non-beneficial
commodities which may end up on the open market and undermine the tax
planning efforts of Government.
Management explained that the MOU with all NGOs partnering with OPM and
those intending to do so has been reviewed to address the gaps identified. These
include among others the kind of imports that are eligible for tax clearance,
verification of imports in the presence of OPM internal auditors and the NGO
before goods are distributed to intended beneficiaries. In addition it is now a
requirement that the Head of Department or a senior officer appointed by the
Head of Department monitors the utilization of donated items by the beneficiaries
in accordance with the provisions of the MOU. The officer will be required to make
a report to the accounting officer at the end of the distribution detailing the items
received and how they were finally utilized.
I urged management to implement the action points in the process of streamlining
the tax payment process.
16.6 Lack of verifiable database for Kasiimo Project
The Ministry through the department of Luwero Affairs is charged with the
mandate of paying gratuity to non-combatant War (civil) veterans. To expedite the
337
process, the Ministry transfers funds to Centenary Bank equivalent to moneys due
to the veterans verified by the Luwero triangle war debt verification committee.
The Bank then pays individual veterans by crediting bank accounts opened with
them.
During the year, UGX.6,140,000,000 was transferred to the bank for onward
transfer to the beneficiaries. However as mentioned in my previous years report,
neither the committee responsible nor the Office of the Prime Minister has a
comprehensive verifiable database of the combatants who have been paid and
those who are pending six (6) years after the onset of the scheme. The Ministry
has schedules that have been remitted to Centenary bank for payment since
inception of the programme but not all the beneficiaries in the schedules were
paid as reconciliations have proved because of the manual environment. The
Ministry may lose funds given that under the circumstances, cases of duplication
and inclusion of non-entitled beneficiaries cannot be ruled out.
Management explained that the Verification Committee is compiling a complete
data base on those who have not been paid and those who did not get the
verification forms during the first verification exercise. To streamline the process
further, a consultant to develop a computerized web based database has been
procured. This will resolve the manually managed payment process.
I advised management to ensure that a comprehensive database is developed that
should be able to capture all payments to individuals and be reconciled to total
remittances to the bank since project inception. In the meantime, management is
urged to expedite the implementation of the computerized web data base.
16.7 Execution of Unenforceable performance securities on Procurement for
Construction of Education Infrastructure in Karamoja
The Office of the Prime Minister signed contracts with several firms for the
construction of Education Infrastructure in Karamoja District under three lots with
lot 3 being awarded to a Construction company at a contract sum of
UGX.1,073,713,920 to construct semi- detached houses at Moroto High School.
Special Conditions of contract 52.1 and 52.3 required the contractor to execute a
338
performance security of ten percent (10%) contract price in form of a bank
Guarantee.
Contrary to the above requirement, no performance security in form of a bank
guarantee was availed by the contractor. The firm provided a performance
security from Mercantile Credit Bank Ltd which is a credit institution and licensed
to conduct credit institution business (Tier II) and as such is not a Commercial
Bank. Absence of performance security puts the entity at a risk of losing funds in
the event of non-compliance.
Management explained that they had communicated to the contractor to provide
the Performance Security that is consistent with the provision of the contract.
I advised management to always carry out due diligence on securities prior to
contract commitment.
16.8 Dormant Accounts
Guidance from the Accountant General provides that all Government accounts held
with Bank of Uganda are automatically blocked if they are inactive for a period of
six months. Accountant General should advise of any alternative action on these
accounts. It was noted that three project bank accounts held in local currency
were found to be dormant for a period of twenty four (24) month with a total
credit balance of UGX.375,662,268 as at 30th November 2014 as indicated below:
ACCOUNT NUMBER ACCOUNT TITTLE AMOUNT (UGX.)
000030088000009 DFID SUPPORT TO THE NATIONAL
INEGRATED MONITORING AND EVALUATION
STRATEGY
326,397,167
000030088000027 NORTHERN UGANDA DATA CENTRE-GIZ
COMPONENT
46,710,876
000030088000038 PEACE RECOVERY AND DEVELOPMENT PLAN
(PRDP) NORTHERN UG&A
2,554,225
TOTAL 375,662,268
339
Dormant accounts are risky as they provide an avenue for perpetuating illegal
activities through concealment.
Management explained that these accounts were for donor funded programmes
and projects which were suspended following the financial impropriety that
occurred in OPM and other MDAs. Negotiations are on-going between Government
and the Development partners to have these accounts unfrozen and release the
monies to complete the outstanding activities. In the meantime, management has
written to Accountant General to justify the continued existence of these Accounts.
I advised management to continue liaising with the Accountant General to ensure
that the Accounts are maintained in line with financial regulations.
16.9 Budget performance
Public Finance and Accountability Regulations 2.10(b) entrusts the Accounting
Officer with ensuring that all total controls such as those contained in the
approved estimates, warrants and others are strictly observed. Budget estimates
are based on outputs to be achieved for the financial year and during
implementation, effort is required to be made to achieve the agreed objectives or
targets of the entity within the availed resources.
Review of the budget performance for the year under review revealed that some
targets were partially or not undertaken despite release of funds to the vote
functions as below;
Vote function
output
Item
description
Planned
outputs/
Qty
Amount
(UGX)
budgeted in
billions
Amount
released
(UGX) in
billions
Actual output/
Quantity
Remarks Mgt response
Project 1235-
ressetlement of
landless persons
and disaster
victims
130275-
purchase of
motor vehicle
-Purchase of
one trailer
-Purchase of
two (2)
tonne tipper
0.83 0.83 Three pickups
were
procured
instead of
trailer and 2
tippers
100% of
funding was
got but no
budgeted
activity/outp
uts were
Procurement
for trailer and
trucks not
done yet there
was increased
demand for
340
Vote function
output
Item
description
Planned
outputs/
Qty
Amount
(UGX)
budgeted in
billions
Amount
released
(UGX) in
billions
Actual output/
Quantity
Remarks Mgt response
trucks procured
instead
management
procured
pickups
rather than
tippers and
one trailer
emergency
response
Programme 18-
Disaster
preparedness
and management
130203 IDPS
returned and
resettled
-Construction
of 100 more
permanent
houses for
landslide
victims
-Finishes on
50 of the
first 101
houses
2.0 2.146 Finishes on
50 of the first
-100% of the
funds were
released but
100 more
permanent
houses were
not built
As a result of
global
warming and
climate
change,
disaster
challenges
have increased
and this led to
increased
demand for
relief.
130374-
major bridges
-Construction
of major
bridges
3.0 1.5 -NO bridges
constructed
-Bridges
were not
built despite
release 50%
of the funds
The funds
were non-
resource
which were
managed and
controlled by
MOFPED and
earmarked for
imports.
Programme 06 –
Luwero Rwenzori
Triangle
Output
130302 –
payment of
gratuity and
coordination
of war debts
clearance
-4500 to be
paid
6.133 6.133 -3064 civilian
veterans paid
Despite full
release, 70%
of planned
veterans
were paid
-
Project 0932 –
Post war
recovery and
presidential
pledges
130375 –
pacification
and
development
-Purchase of
vehicles (3)
procured for
Gulu office
-Purchase of
0.810 0.810 -Three double
cabins for
Gulu office
procured
-one vehicle
and tippers
were not
procured
Procurement
for vehicles
was not
finalised and
instead ten
341
Vote function
output
Item
description
Planned
outputs/
Qty
Amount
(UGX)
budgeted in
billions
Amount
released
(UGX) in
billions
Actual output/
Quantity
Remarks Mgt response
two tipper
trucks
-purchase of
vehicle for
coordinator
(10) hydra
foam
machines were
procured
Service delivery is hampered and the appropriating authority‟s objectives are not
met.
Management explained that the underperformance on the specified areas was
attributed to other emerging pressures and priorities that cropped up in the course
of the financial year necessitating reallocations and Virement for which authority
was sought from PS/ST.
I advised management to always undertake activities as planned.
16.10 NORTHERN UGANDA SOCIAL ACTION FUND (NUSAF 2)
(a) COMPLIANCE WITH THE MEMORANDUM OF UNDERSTANDING
AND GOU REGULATIONS
i) Unaccounted for Subproject Disbursements UGX. 58,826,655,271
Section 2.2 of NUSAF II Operational Manual requires that at least 80% of previous
disbursements are accounted for before replenishment to a subproject. The policy
also requires that all funds to subprojects should be accounted for within six
months.
It was noted that UGX.58,826,655,271 (25.8%) out UGX.227,844,706,768
disbursed to subprojects remained unaccounted for as at 30th June 2014. Out of
the UGX.58 billion unaccounted for, UGX.41,547,079,004 relates to disbursements
which have been outstanding for over six months. The table below refers;
342
AGE DISBURSED ACCOUNTED
%
ACCOUNTED UNACCOUNTED
% UN-
ACCOUNTED
Above 12
Months 142,994,940,365 124,511,969,492 87.1% 18,482,970,872 12.9%
9-12 Months 24,756,699,087 17,209,507,363 69.5% 7,547,191,724 20.6%
6-9 Months 40,914,262,109 25,397,345,701 62.1% 15,516,916,408 36.5%
Sub-Total (≥
6Mths) 208,665,901,560 167,118,822,557 80.1%
41,547,079,004 19.9%
3-6 Months 5,047,535,125 1,208,680,407 23.9% 3,838,854,718 72.6%
0-3 Months 14,131,270,083 690,548,534 4.9% 13,440,721,549 94.4%
Sub-Total
(0-6Mths) 19,178,805,208 1,899,228,940 9.9%
17,279,576,268 90.1%
Overall
Status 227,844,706,768 169,018,051,497 74.2%
Under the circumstances, I was unable to establish whether the unaccounted for
funds were used for intended purposes. Further, the delays in accounting for
subproject funds affects Project implementation as the activities are not completed
within project timelines.
Management explained that the delay in project accountability is a result of many
factors which include; the Community Infrastructure Rehabilitation (CIR) and
Public Works Program (PWP) which take 4-6 weeks before project implementation,
delays by contractors due to limited capacity to execute contracts on time and
fiduciary requirements that require at least 80% accountability for the previous
disbursement to sub projects and overall outstanding community accountabilities
above 6months in the district to be below UGX.50m. Management further
explained that the District Financial Tracker clean up exercise and Rapid Results
Initiative to clean up subproject accountabilities at the district had been carried
out and as a result unaccounted for funds had gone down.
I advised management to ensure that all project funds are fully accounted and
within the project timelines.
ii) Discrepancy between approved budget estimates by project
funders and the estimates approved by Parliament
343
The approved estimates by Parliament for the year under review were indicated as
UGX.41,648,920,000 while the approved budget by the World Bank amounted to
UGX.169,189,150,568 creating a variance of UGX.127,540,230,568. Management
stated that the variance was as a result of committed funds as at 30th of June
meant to implement the backlog of subprojects. However, according to the
NUSAF-World Bank work plan, the committed funds for the backlog sub project
amounted to only UGX.102,903,898,568 hence creating an outstanding variance of
UGX.24,636,332,000.
There seems to be a mismatch between the work plans and the Appropriation Act.
Management explained that the discrepancy was due to the project
implementation design where projects for Community Infrastructure and Public
works once approved receive only 50% of funds in the first tranche to commence
the implementation and receive the last 50% as second tranche subject to a
satisfactory report and accountability of not less than 80% of the funds released.
Management further indicated that the approved funding that is not released to
subprojects is retained by the project and reflected as committed funds and rolled
over to the subsequent financial year and that the difference observed was
planned to offset the accumulated outstanding 2nd tranche demands of the
community projects which were rolled over.
I advised management to harmonise project annual estimates submitted to
Parliament and those of the World Bank. This will also facilitate smooth
performance measurement.
iii) Low absorption capacity
The Annual work plan and budget for NUSAF II activities stood at
UGX.169,189,150,568. During the year, a total of UGX.91,783,256,891 was
received by the project in addition to the bank balances of UGX.49,084,796,298
meant for subprojects which were rolled over from the prior year.
UGX.104,683,883,524 was utilized during the year representing an absorption
capacity of only 62% of the approved budget, despite the Project being in its fifth
344
year of the six–year implementation plan. This implies that a number of planned
activities are likely not to be implemented.
Non-implementation of planned activities in the stipulated timelines does not only
lead to spillover of activities to the next planning period but may also lead to non-
achievement of the desired outputs, subsequently hampering fulfillment of Project
objectives. This could also lead to extra administrative costs in case of project
extension.
Management explained that the rate of absorption against IDA Credit is 100%
based on planned withdrawals versus actual withdrawals. Management further
explained that the project planned for 10,042 subprojects at the onset of NUSAF2
programme and to date 9619 projects had been funded.
I advised management to carry out adequate planning to enable full
implementation. Management should also ensure that planned activities are
completed before the project closure date (31st August 2015).
(b) General Standard of Accounting and Internal Controls
A review was carried out of the project system of financial management and the
following matters were observed;
i) Failure to insure Project vehicles
Section 4.4 (ix) of the NUSAF2 administrative hand book requires all Project
vehicles to be comprehensively insured with a reputable insurance company in
Uganda. This was not the case as all the project vehicles had not been insured at
the time of audit.
Failure to insure Project vehicles may lead to Project incurring unwarranted costs
in form of replacements and repairs in case any of the programme vehicles got
involved in accidents.
Management explained that the Process for procurement of Non-consultancy
services for insurance of NUSAF2 Vehicles was initiated, proposals received and
evaluated but the process could not proceed further because of Government‟s
345
policy which does not provide for insurance of government vehicles. Management
further explained that NUSAF2 being a main-streamed project had all its vehicles
registered under the ownership of OPM and therefore could not operate in
exception regarding insurance of government vehicles.
I advised management to liaise with the relevant authorities to ensure that the
matter is resolved so as to comply with the guidelines.
(c) General Implementation of Workplan and Activity Component
An Audit inspection of subprojects was carried out to assess the progress of
implementation. The following issues were observed:
Absence of sign posts at the sub-project sites
Bill of Quantities- provided for a sign post for identification of the sub projects
undertaken by NUSAF2 in the area which the project is located. The bill board
should clearly specify the Ministry, the project, the subproject name Sub County,
District and contractor. However, it was observed that all sub-projects in Karamoja
Region (Kaboong and Kotido) and many in areas of Acholi and Lango regions
inspected lacked sign posts for identification with the exception of Dokolo District.
In absence of the sign posts, it becomes difficult to ascertain whether all the
projects inspected were actually the right ones as there were other similar projects
run by Non-Governmental Organizations. There was also a financial loss for the
project as the item was budgeted for in the BOQs but not adhered to by the
contractors.
Management explained that a written communication had been made to all the
districts to prioritize the installation of sign posts at sub project sites.
I await management‟s efforts to ensure that installation of sign posts by the
contractors in all the sub-projects is done for easy sub project identification.
(d) Status of Sub Project Implementation
i) Project performance per annual work plan and Budget 2013/14
346
NUSAF II Project Management planned for implementation of various activities
during the year. A review of the annual work plan vis-à-vis actual implementation
and outputs for the year revealed that while a number of activities had been
completed, some activities were partially implemented. The table below refers:
S/No Activities for
the year
Targets for the
year
Amount
(UGX)
Progress during the year
1. Subprojects
completed
10,042
subprojects
completed
A total of 6,503 subprojects
(HISP-5,047 CIR-1,377 and
PWP-79) are completed out of
the 8,719 funded subprojects
giving a completion rate of
75%.
2. Accountability for
grants mobilized
99% of funds
disbursed
The project disbursed a total
of UGX.227,828,905,089 and
UGX.185,294,319,134 have
been accounted which is
81.3% of disbursed amount.
3. Implementation
support and
guidance offered
to districts
Reaching 55
districts – two
visits per district
65,000,000 One support supervision visit
was conducted reaching 11
districts (7 in Karamoja, 2 in
Elgon, 1 in Teso and 1 in
Lango sub-regions).
4. Training district
staff on
environment and
social safeguards
110 (55 Dist.
Env. Officers and
55 DCDOs)
160,000,000 3 regional trainings were held
in Gulu for participants from
Acholi, Lango and West Nile
districts; Mbale for
participants from Elgon,
Bukedi and Teso districts and
Moroto for participants from
Karamoja districts.
5. Technical support
on environment
and social
safeguards
55 districts 33,229,840 3 technical support visits were
done reaching 42 districts
(76% coverage).
6. Radio talk shows
and broadcasts
5 radio talk
shows per region
20,000,000 1 radio talk show on
commissioning of NUSAF2
subprojects held in Sironko
and 4 radio broadcasts in
Karamoja on NUSAF2 status
updates.
7. Support
supervision and
backstopping of
district staff on
3 visits to 55
districts
20,000,000 Backstopping of 34 districts
done on documentation of
best practices and record
keeping (62%).
347
S/No Activities for
the year
Targets for the
year
Amount
(UGX)
Progress during the year
documentation
Delay in implementation of planned activities denies beneficiaries the intended
benefits of the Project. Besides, Project objectives may not be achieved.
Management explained that the decision to extend the project life by one year was
made after the preparation of the 2013/14 work plan and the targets that were
made under the assumption that the project would end in August 2014.
Management further explained that a new road map had been made providing
new targets for the project close in August 2015.
I advised management to expedite the planned Project activities in order to meet
Project objectives within the agreed time frame.
ii) Project Performance as per Logical Framework
According to the Project five year implementation plan and progressive reports
reviewed from management, the Project had in some instances (Public Works
Programme) not progressed well despite the fact that its closure date was set for
August 2015:
Component
Sub Projects Funding
Planned Approved
%
Achieved
against
5 yr
target
Planned
(US$)
Approved
(UGX)
Community
Infrastructure
Rehabilitation
(CIR)
1,915 2,533 132% 57,450,000 182,070,857,306
Household
Income Support
Projects (HISP)
7,236 6,716 93% 36,180,000 72,737,780,326
Public Works
Programme
(PWP)
891 370 42% 17,820,000 11,977,982,373
TOTAL 10,042 9,619 96% 111,450,000 266,786,620,005
348
Delays in implementing activities could result into extra administrative costs.
Management explained that the project was set to meet the planned target once
the project is extended for another year.
I wait the outcome of management‟s efforts towards implementation of project
activities within the agreed timelines.
349
17.0 MINISTRY OF PUBLIC SERVICE
17.1 Unspent Balances Due to the Consolidated Fund – UGX.262,479,735
The Public Finance and Accountability Act, 2003, requires that any unspent funds
as at the 30th of June that were obtained from the Consolidated Fund (UCF), be
returned to the Fund. It was noted that at the close of the financial year under
review, a balance of UGX.262,479,735 was still on the PSRP project account and
had not been remitted to the UCF account. I was not given an explanation on the
fate of the amount in question, given that the project closed in 2014.
In response, the Accounting Officer stated that these funds could not be remitted
to the UCF account, nor transferred back to the Ministry account as they were
meant to procure IPPS equipment whose procurement process was on-going. I
was however, not presented with documentary evidence to this effect. I advised
the Accounting Officer to always remit unspent balances to the Consolidated Fund
Account or else seek authority of the PS/ST as provided for under the Act.
17.2 Domestic Arrears – UGX.1,187,512,043
A review of the financial statements revealed that the ministry‟s domestic arrears
position increased by 281% from UGX.311,659,924 at the start of the year to
UGX.1,187,512,043 as at 30th June, 2014. This is an indication that the ministry
continues not to fully comply with the commitment control system introduced by
the Ministry of Finance Planning and Economic Development.
The Accounting Officer explained that the bulk of the arrears incurred during the
year (i.e. Ugx.680,700,719) related to validated monthly pension invoices which
remained unpaid on the system as at 30th June 2014, but were settled in July
2014.
I advised the Accounting Officer to always adhere to the commitment control
system of government and only commit her ministry to the extent of availed
funds.
350
17.3 Mischarges of Expenditure – UGX.1,721,329,414
The GOU Chart of Accounts defines the nature of expenditure for each item code,
with the intention of facilitating better and consistent classification of financial
transactions and tracking budget performance per item.
It was noted that expenditures totalling to UGX.1,721,329,414 were charged on
items which do not reflect the nature of the expenditure. Such a practice impacts
on the credibility of the financial statements, since the figures reported therein do
not reflect true amounts expended on the affected expenditure items. In addition,
the practice distorts budget performance review on an item by item basis.
I advised the Accounting Officer to avoid such a practice and always ensure strict
budgetary discipline.
17.4 Imprest not Accounted For – UGX.108,336,942
Section 227 to 229 of the Treasury Accounting Instructions (TAI), 2003, provides
for retirement of all imprest by the close of the financial year, failure of which
recovery measures should be instituted against the concerned officers‟ (imprest
holder‟s) emoluments.
During the year under review, the Ministry paid cash imprest totaling to
UGX.260,718,300 of which UGX.108,336,942 had not been accounted for by the
time of concluding the audit. In addition, it was found that, contrary to provisions
of section 226 of the TAIs, there were no Imprest cashbooks maintained
throughout the year. The poor record keeping coupled with delayed accountability
further raise doubts as to whether the funds were properly utilised.
Given the circumstances, I was unable to establish whether the amount in
question was expended for the intended purposes. I advised the Accounting
Officer to follow up this matter and have the concerned staff account for the funds
and to always ensure full compliance with the requirements of the TAIs.
351
17.5 Refunds to the PSRP-UPSPEP Project – UGX.66,872,000
Paragraph 156 of the Treasury Accounting Instructions (TAIs), 2003 Part 1,
prohibits expenditure from being charged to an item/sub-item merely because
funds are available under that item/sub-item. In addition, funds available on one
vote may not be transferred to another vote without parliamentary approval.
Contrary to the above requirement, the ministry paid a total of UGX.66,872,000 to
the PSRP-UPSPEP project, being a refund of project funds borrowed by the
ministry during the year. I was not availed with the details of the borrowings
made and the activities involved to ascertain their genuineness, and whether they
related to the financial year under review. I was also not availed the requisite
authority to borrow the project funds.
Although the Accounting Officer indicated that the documentation in question was
available, this had not been availed to me at the time of concluding this report. I
advised the Accounting Officer to always seek for proper authority for such
borrowings with a justification.
17.6 Non Deduction of 6% Withholding Tax - UGX.38,087,253
Section 117-1 of the Income Tax Act (ITA), Cap 340 (as amended), requires a
withholding agent to deduct and remit a withholding tax on payment of
employment income. During the year under review, the ministry made payments
to various service providers for goods and services supplied without deducting 6%
withholding tax totaling to UGX.38,087,253. According to the ITA, failure to remit
the amount withheld constitutes an offence for which the Accounting Officer, as a
withholding agent, is personally liable. In addition, it further exposes the ministry
to the risk of penalties/fines imposed by URA.
The Accounting Officer stated that the anomaly resulted from a failure to activate
the With-holding tax function at the time of setting up the suppliers on the IFMS,
and that a letter had been written to the Accountant General, requesting him to
activate the function of withholding the 6% tax. I advised the Accounting Officer
352
to follow up this mater and ensure that in future, withholding tax is always
deducted before making any payments above the threshold prescribed in the Act.
17.7 Unaccounted For Funds For Various Activities – Ugx.193,681,503
Section 212 of the Treasury Accounting Instructions (TAI), 2003 provides for
temporary imprest advanced to staff to be recorded in the General Ledger until
they are accounted for. Thereafter they are expensed to respective expenditure
items.
Examination of payments however revealed that a total of UGX.193,681,503 either
advanced to staff or deposited directly with service providers in respect of
workshops/conferences conducted by the Ministry remained unaccounted for at
the end of the year. There was no supporting documentation availed for audit
examination in respect of the amounts advanced/deposited. Under the
circumstances, I was unable to confirm whether the amount involved was applied
for the intended purposes.
Although the Accounting Officer indicated during my concluding meeting with her,
that the documentation in question was available, this was not availed to me. I
advised the Accounting Officer to ensure full adherence to the TAI and have all
advances accounted for.
17.8 Payments to Foreign Pensioners – UGX.113,324,176
A review of pension records revealed that the ministry pays pension to foreign
pensioners through account number 0196000236505 in Stanbic Bank, and that
during the year, the ministry paid to this account, a sum of UGX.113,324,176.
However, I was not availed with records to establish the authenticity of these
foreign pensions. Although the Accounting Officer indicated that the files in
question would be availed to me, these had not yet been availed by the time of
concluding my report. I advised the Accounting Officer to ensure that all records
pertaining to pension payments are always properly kept and filed, to facilitate
their retrieval in case of need, say for audit purposes. In the meantime, the files in
question ought to be obtained and provided for audit examination.
353
17.9 Payment of Pensioners Beyond The Pensionable Period–
Ugx.12,755,933,531
It is a requirement under Section 18(1) of the Pensions Act, Cap 286, that every
pension or other allowance granted under the Act, should cease upon the death of
the person to whom it is granted. For the avoidance of doubt, it is declared that a
pension granted under this section be payable for a period not exceeding in
aggregate, fifteen years from the date of retirement of the deceased pensioner.
Pursuant to the above therefore, all pensioners must furnish the Ministry of Public
service with annual life certificates after the expiry of their 15 year pensionable
periods as proof that they are still alive.
Contrary to above, a total of 19,135 pensioners who had attained the maximum
pensionable period of 15 years were still on the ministry‟s payroll and earning
monthly pension yet they had not furnished the ministry with life certificates. As
such, a total of UGX.12,727,686,849 paid in respect of their monthly pensions
during the year under review could not be justified in the absence of life
certificates. In addition, a total of UGX.28,246,682 was paid to administrators of
estates of pensioners whose cause of retirement was death and had earned
pension beyond the stipulated period of 15 years. Under the circumstances, the
audit could not confirm that the said pensioners were still eligible. There is a risk
that the ministry continues to pay pension to ineligible or non-existent pensioners
and thus occasioning loss to government.
The Accounting Officer explained that according to the Pension Act, Cap 286 all
pensioners who are over 75 years should furnish the Ministry with Life Certificates,
but that the Ministry cannot just delete them off the payroll unless it is confirmed
that they are dead. I advised the Accounting Officer to institute a mechanism that
tracks pensioners so that they do not get paid beyond the lawful pensionable
period. In addition, the ministry should enforce the requirement of pensioners,
specifically those that have attained the maximum pensionable period of fifteen
years, to avail life certificates.
354
17.10 Pension Payments To Group Associations – Ugx.956,803,416
A total of UGX.953,803,416 was paid to various pension groups as both gratuity
and monthly pension of group members. However, it was noted that these groups
did not furnish the Ministry with accountability records/evidence of
acknowledgements to show that the funds reached the bona-fide beneficiaries.
There is no evidence that the ministry has a mechanism to track the pensioners
under these groups to ascertain whether the pensioners were still alive and
eligible for pension as there were no life certificates on file for the beneficiaries
under these groups. Absence of the monitoring measures may lead to payment of
non-existent/ineligible pensioners and thus occasioning loss to government.
In response, the Accounting Officer stated that the Ministry has instituted
mechanisms to ensure that each pensioner or beneficiary is unique. However, at
payment, the pay code can be to a group as in the above cases. Where a
pensioner has not been paid, the ministry is always notified, and no complaint to
this effect has ever been received. I advised the Accounting Officer to update all
data in respect of group pensioners and institute a monitoring mechanism to
ensure payments are made to genuine pensioners.
.
355
SECURITY SECTOR
18.0 MINISTRY OF DEFENCE
18.1 Outstanding commitments
A review of the Statement of Financial Position revealed outstanding payables of
UGX.81,928,017,200 as at 30th June 2014. Payables worth UGX.57,385,245,362
were disclosed in the statement of financial position as at 30th June 2013, out of
which UGX.26,037,671,862 was paid implying an increase in domestic arrears by
UGX.50,580,443,700 (88%) from the closing position of the previous year. It is
evident that management has continued to incur arrears without establishing
sufficient mechanisms to monitor and control them. There is a risk of loss of
reputation and litigation due to non settlement of creditors.
The Accounting Officer attributed this problem to increased activities, emergencies
widening operations and escalation of food and other essential commodity prices
without corresponding increase in funding.
I advised management to liaise with Ministry of Finance, Planning and Economic
Development for improved funding for the Ministry.
18.2 Borrowings
It was established that at the beginning of the financial year, the Ministry had an
outstanding interest bearing loan worth UGX.136,781,479,167 and no repayment
was done during the year. Further, this loan attracted a fixed interest of
UGX.80,506,679,188 for the period March 2010 to June 2011.
The Accounting Officer explained that this resulted from procurement of classified
equipment‟s undertaken by the Ministry in the financial year 2009/2010 by a
drawdown on foreign reserves of Bank of Uganda. The loan interest has not
attracted any interest since then as per the funding arrangement.
356
I advised the Accounting Officer to engage Ministry of Finance, Planning and
Economic Development to have this amount budgeted for so that the loan can be
cleared.
18.3 Avoidable expenditure
It was established that on 18th December, 2013 the Ministry of Defence entered
into a lump sum agreement/contract with a motor company to supply 109
different types of brand new motor vehicles at an agreed total price of
USD.5,578,094.80 and corresponding spare parts at USD.248,900.20, leading to a
total contract price of USD.5,826,995.00. The terms of payment were 40% deposit
with a signed contract/order confirmation and the balance of 60% upon transfer of
ownership of the vehicles (before delivery). The contract also required the Ministry
to pay by an irrevocable Letter of Credit.
However, instead of opening up an irrevocable Letter of Credit with Bank of
Uganda, the Ministry opened up a Deferred Letter of Credit Facility (LC Facility)
with Stanbic Bank of USD.6,273,438.40 payable in 13 quarterly instalments with a
commission of USD 31,367.19 payable every quarter. This resulted into excess
payment of USD.446,443.40 equivalent to UGX.1,104,947,415. In addition, the
Ministry intends to pay another of 13 quarterly instalments of USD.31,367.19
which will also result into an extra cost of USD.407,773.47 equivalents to
UGX.1,009,239,338.
The Accounting Officer explained that BoU issues irrevocable letters of credit on
deposit of full LC value yet the Ministry did not have the entire contract amount of
US$.5,826,995 to open this type of Letters of Credit.
I advised that management should have consulted with the Accountant General
regarding the Letters of Credit prior to execution.
18.4 Sub-constructed works of NSIS project at Kololo
Engineering Brigade made a payment of UGX.560,000,000 to a local company to
partition the offices and provision of other necessary facilities under the National
357
Security Information system (NSIS) project at Kololo. However, no contract was
availed to enable me evaluate the sub-contracted works. The Accounting Officer
presented copies of the acknowledgement receipts for the money paid without
details of works done. I explained to the Accounting Officer that carrying out
works without a formal agreement may result into shoddy or abandoned works. I
was therefore unable to review the works undertaken for purposes of compliance.
The Accounting Officer explained that the arrangement was entered into in order
to speed up the works.
I urged the Accounting Officer to always ensure that formal agreements are
entered into for all Ministry contracts.
18.5 Un-reconciled Government of Uganda debt with UMEME and Ministry of
Defence
Government of Uganda entered into an agreement with UMEME in which the latter
was required to offset government bills that remained outstanding for a period of
more than 60 days. A review of the available documents indicates that total
Government debt as at 31st January, 2013 amounted to UGX.62,771,404,221, of
which UGX.30,303,286,732 relate to Ministry of Defence. At that date UMEME set
off UGX.31,717,538,490 from the debt leaving a balance of UGX.31,053,885,731
as total outstanding. However, it was not clear of what amount offset relates to
the ministry of Defence.
Furthermore, it was noted that during the year Ministry of Defence did not
reconcile with UMEME to ensure that the amount off set is deducted before
making payment.
The Accounting Officer explained that information on the outstanding debt was
communicated to PS/ST who will ensure that when paying the debt, all offset
amount will be taken into consideration and deducted.
I advised management to liaise with the Ministry of Finance, Planning and
Economic Development to have the position reconciled.
358
18.6 Un-reconciled National Water and Sewerage Corporation Bills
UGX.3,102,169,373 was paid to NWSC for water supplied to the Ministry.
However, the Ministry did not have updated ledgers for all the water accounts to
keep track of the bills paid and what was outstanding. The Ministry did not include
any amount outstanding at the end of the year despite the fact that April 2014
bills were the last to be paid in the financial year. Further, no reconciliation was
done at year end to establish what was owed to NWSC. The Ministry therefore
understated the outstanding commitment for the year.
The Accounting Officer explained that water payment ledgers are not up-to-date
due to un-concluded process for verification of water bills of the Ministry. The
verification is underway and expected to be completed in the financial year
2014/15.
I urged the Accounting Officer to follow up the verification process and ensure
that it is completed.
18.7 Intended Sale of Kiseka Hospital
Some time back in 2007, a decision was taken by management of the Ministry of
Defence to have the premises and land comprised of the former Kiseka Hospital
sold. However, to date this property has not been sold off. The property is
dilapidated, abandoned and is losing value as time passes. There is also a risk that
this property could easily be encroached. By the time it is sold, the Ministry may
not get the expected value from the sale.
The Accounting Officer explained that effort was made to have this property sold
off through competitive bidding but the highest bidder was found to be below the
reserve price. A decision was then taken to revalue the property but the highest
bidder sued the Ministry where Court ruled in favour of the Ministry. The ruling
was appealed against and management of the Ministry is still waiting for the
outcome.
359
I advised the Accounting Officer to follow this case and also liaise with Uganda
Land Commission and ensure the safety of the land and property.
18.8 Audit Inspections
a) Inspection of Schools and Colleges
i. Under-funding of Kimaka
The budget of Senior Command and Staff College, Kimaka has remained at the
same level since 2004 at UGX.1,532,905,096 and cannot meet all the
requirements of the college. During the financial year under review, the approved
budget was not adjusted against UGX.2,972,117,000 that was required. As a result
of inadequate funding the college is facing a number of challenges which include:
The lagoon that serves the Senior Command and Staff College was
degenerating and may in the end fail to serve the purpose for which it was set
up.
The place is surrounded by garbage which has reached too close to the fence.
Cattle were found grazing within the fence. A piggery with 46 pigs was
adjacent to the lagoon presumed to belong to someone who is not a member
of Uganda Peoples‟ Defence Forces.
The screen that sieves the spillage into the lagoon together with the three
metallic electrical poles which were meant to provide light have been
removed.
The continued lack of adequate funding will hamper the achievement of planned
activities and the long term objectives of the college.
The Accounting Officer attributed the current situation to budgetary constraints
faced by the Ministry.
I advised the Accounting Officer to liaise with the responsible authorities to ensure
the College is funded to meet the objectives for which it was established.
b) Junior Command and Staff College
Un-surveyed land
360
Land measuring about 697.721 acres belonging to the College is not surveyed and
as a result most of the training areas in Bugungu, Buikwe District have been
encroached on by people in the area. The Ministry is at a risk of losing this land to
the encroachers and as such in future it may be difficult to undertake trainings at
the college.
I advised management to have the land surveyed to avoid costs associated with
evictions.
Amber court Market
This market is situated on Kimaka Road on army land which was established in
conjunction with the Jinja Municipality with a specific aim of improving the welfare
of the spouses of soldiers within the Gaddafi Garrison. Correspondences about this
subject are dated as back as July 2002. The available records indicate that the
accruing revenue from the market was to be shared between Municipality and
welfare of solders in the ratios of 60 to 40. It was established that to-date, these
instructions have never been honoured. The records further called for
empowerment of the soldiers‟ spouses to be able to bid and run the market. This
has also been persistently ignored.
At the time of this audit inspection (October, 2014), this market was being
operated by a third party at a monthly rent of UGX.2,330,445. This translates into
UGX.27,965,340 a year and for the last five years, a total of UGX.139,826,700
should have been paid. Because of laxity in the implementation of the
instructions, the soldiers‟ welfare fund has lost UGX.55,184,937 which is
equivalent to 40% of UGX.139,826,700.
I advised the Accounting Officer to follow up the matter to ensure that the army
benefits from the facility.
18.9 Bugema barracks in Mbale
a) Barracks land
This barracks which is the 3rd Division Headquarters, occupies an area of
approximately 600 acres located within Mbale Municipality. It was however noted
that land owned by the barracks is not in the inventory of the Ministry‟s lands.
361
Information available indicates that this barracks has existed since the days of
African Rifles (the first Ugandan Army). There were reports that some people have
started claiming ownership of the same land. The Ministry is at a risk of losing this
land if no action is taken immediately.
I advised the Accounting Officer to follow up the matter with authorities with a
view of resolving land ownership of the facility.
b) UPDF maize mill project at Mbale
The Military Maize Mill at Mbale Industrial area was contracted out to an individual
to manage and run it on behalf of 3rd Infantry Division of the UPDF for a period of
30 months commencing from 1st June 2014, at an agreed total consideration of
UGX.92,910,000. Out of the total consideration, UGX.62, 910,000 was to settle all
the outstanding debts incurred by the milling project and UGX.1,000,000 was to
be paid to the Division on a monthly basis up to the end of the period. The
following issues were however noted:
The individual who hired the mill is one of the long-time suppliers of maize
flour to Ministry of Defence, an indication of conflict of interest.
The outstanding amount of UGX.62,910,000 was not verified by an
independent person at the time when it was forming part of the consideration.
It was also not clear as to whether 3rd Division has mandate to commit the
UPDF assets for that period.
The revenue of UGX.6,000,000 (period of 6 months) was not verified as no
document was availed for verification at the time of inspection.
It was also noted that the individual who hired the mill was the land lord of
the maize mill project, an indication that insider dealing with this supplier was
possible as no advertising was made at the time of soliciting the services of
the contractor.
The agreement signed was never cleared by the Solicitor General as per the
requirement of government agreements.
The Ministry is therefore at a risk of losing the entire maize mill if no follow up is
made on this project.
362
I advised management to review the contract in consultation with the Solicitor
General.
18.10 Moroto Barracks
a) Encroached Land
This land which was surveyed during the time when the Uganda Army was
referred to as Uganda Rifles has a number of encroachers. Keeping these
encroachers on Ministry land is in contravention of Commander in Chief directive
which required all people to vacate Ministry land. The latest report on opening of
the boundaries dated 30th July 2014 revealed that some key military installations
are outside the surveyed land and recommended annexure of the same before
scrupulous people take advantage. At the time of this report no action to the
effect had been taken.
Delays in implementing the directives to have all encroachers off the Ministry land
will expose the land to unscrupulous people with intention to own it.
The Accounting Officer explained that Military Land Board was following up the
issue of encroachers of the Ministry/UPDF land. A report on the outcome is
awaited.
b) Generator at Oliver Thambo training school
The standby generator of 250hp at Oliver Thambo is degenerating due to
inadequate maintenance. It was not possible to establish when it was last serviced
because the service card was worn out. Besides, it could not be used during
power blackout because the changeover control panel fixed is for a single phase
yet the generator is of a bigger capacity. At the time of audit inspection, there was
no power and lectures were being conducted on a very small generator of 5hp.
Lack of funding is causing vital assets of the school to degenerate and as such the
Accounting Officer was advised to secure further funding for maintenance of the
assets.
I advised the Accounting Officer to secure funds to service the generator.
363
18.11 Motorised infantry workshop-Nakasongola
The motorized infantry workshop under construction at a cost of UGX.1,
507,894,518 appeared abandoned after building it to shell level. The same applied
to the toilet and the septic tank. There was no documentation at the site to assess
whether the work was on schedule. Besides, the contract records were not
provided for review.
18.12 5th Division Acholi Pii
a) Land occupied by the division headquarters
According to records, the land occupied by the Division Headquarters is estimated
at 1,388 hectares for the Acholi Pii (Arum Site) and the Agago Ranch 3,429 acres
formerly belonged to the Office of Prime Minister supposed to accommodate
refugees but has since been converted to Army use. At the time of inspection, the
users (the army) were not aware of the boundaries of the land. It is also believed
that the land is heavily encroached. The Military Land Board asserts that the
formalization of acquisition from Office of the Prime Minister and Pader District is
on-going.
Delay in streamlining ownership credentials increases encumbrances on the land
with the attendant litigation costs as result of encroachment.
The Accounting Officer explained that arrangements for the acquisition of the land
are in advance stages and a final decision is awaited from the Office of the Prime
Minister.
I urged the Accounting Officer to ensure that the process of finalising the
acquisition of the land is expedited.
18.13 Masaka armoured brigade
a) Land Encroachments
With the exception of Masaka armoured brigade land, the army land at Lukaya
and Lake Nabugabo is heavily encroached. Whereas administratively this land
belongs to the Uganda Peoples Defence Air Force as users, the land has been
364
encroached on. The encroachment on the land appears to be due to lack of
effective use.
The Accounting Officer explained that the Ministry contested the encroachment
and several meetings have been held between ULC, Lukaya Town Council
Authorities and UPDF to have the matter resolved.
I urged the Accounting Officer to continue pursuing the above action and ensure
that the matter is resolved.
b) Financial loss due to termination of contract
During the audit inspection; a site that was for the flat lets which was abandoned
by a construction company after payment of UGX.474,576,271 had been
completely abandoned and preserved as exhibit. The new flats built by another
construction company were now complete under a completely new contract and
new site.
The choice of a new site and contractor resulted into a financial loss of
UGX.474.5Million which was not reported in the financial statements in accordance
with financial regulations.
I advised the Accounting Officer to undertake due diligence prior to award of
contracts.
18.14 2nd Division Mbarara
a) Encroachment of 2nd division headquarters‟ land
Records obtained from the Military Land Board revealed that the land
accommodating the 2nd Division Headquarters measured 600 acres. The barracks
land has been encroached on and there is no evidence of action taken by
management. Besides, there was nothing on the ground like a copy of the land
title to indicate the extent of the barracks premises.
The Accounting Officer was advised to take interest on the matter and ensure that
the land is secured.
365
b) Abandonment of rehabilitation works at School of Military
Intelligence, Muhoti Baracks
An inspection of the contract for rehabilitation of the School of Military Intelligence
revealed that the contactor had only done progress work on nine (9) blocks out of
twenty two (22). At the time of audit inspection, the keys to the nine blocks were
still retained by the contractors and could not therefore be used to alleviate the
acute accommodation problem at the school. Records obtained from the
Engineers‟ Brigade indicated that the contract sum was UGX.2, 274,831,418 and
by the time of this report, UGX.1,901,206,927 had been paid representing a
payment of 83% against a performance of 41% or less. Besides, the contract
period was for 2008-2010 which indicated that it was five years behind schedule.
I advised the Accounting Officer to follow up on the delayed works to ensure
accommodation issues are resolved.
c) Hima Barracks 305 Brigade Headquarters
It was observed that all buildings at the brigade headquarters had developed
cracks while these structures appeared recently renovated. These included the
administration block, hospital and barracks quarters. This may be an indicator that
the design and execution of the contract was not undertaken properly.
I advised management to follow up on the defects noted.
18.15 Mubende Rehabilitation Centre
a) Maize mill
The Chieftaincy entered into a tenancy agreement to operate the maize mill
belonging to Uganda Peoples‟ Defence forces at an annual rent of
UGX.18,000,000. The contract indicates that on signing of the contract (1st May
2014) the tenant had paid the annual rent in advance. However in absence of a
general receipt, bank slip and bank statements, we were unable to certify
ourselves on the authenticity of the payment. Besides, the legal capacity of the
Chieftaincy to contract on behalf of Ministry of Defence was not properly
demonstrated. It was also noted also that the income was not recognised as Non-
366
tax Revenue. There is a risk that the Ministry did not carry out enough due
diligence about this contractor.
The Accounting Officer explained that management is to review the contract in
consultation with the Solicitor General with a view to addressing the anomalies in
it.
This action is awaited.
19.0 OFFICE OF THE PRESIDENT
19.1 Cumulative outstanding commitments
Office of the President had arrears of UGX.8,816,941,731 at the beginning of
financial year 2012/2013 comprised of domestic arrears of UGX.4,527,940,977 and
pension liabilities of UGX.4,289,000,977. By the end of the financial year
2013/2014 the arrears had accumulated to UGX.24,944,370,718 comprising of
domestic arrears of UGX.11,182,915,772 and pension liabilities of
UGX.13,761,454,946. Accumulation of arrears is in contravention of the
commitment control system and the entity also risks loss of reputation and
litigation due to non settlement of the obligations.
The Accounting Officer explained that outstanding commitments were a result of
insufficient funding of the Security Agencies and that the resultant arrears have
been brought to the attention of Parliament and the Ministry of Finance, Planning
and Economic Development. MoFPED provided UGX.7,240,894,000 in the budget
and a supplementary of UGX.6,335,942,636 to clear the reported arrears under
financial year 2014/2015 which reduced the arrears to UGX.11,367,534,082.
I have advised management to continue following up the matter and ensure that
all the outstanding arrears are cleared.
19.2 Budget performance
367
The financial statements submitted by the Office of the President for the financial
year ended 30th June 2014 indicated that UGX.73,619,648,221 was budgeted,
UGX. 73,561,071,202 released and UGX.73,389,672,977 was spent. Despite the
Ministry having received virtually all the budgeted funds, some activities were not
undertaken as shown in table below:
Output
Code
Planned
Activity
Expected outputs Actual outputs Unimplemented
Output:
160104
Economic
Research
and
Information
Policies reviewed to
identify policy
implementation
weakness with the
aim of generating
actionable
recommendations
for policy
development in
Sectors of
energy (Oil and Gas
sector )
Investment
and taxation and
micro finance
Research
conducted on the
implementation
and performance
of the pension
policy and a report
produced and
submitted to
relevant MDAs for
appropriate action.
Research carried
out to assess the
progress in the
development of
the Energy (oil
and gas) sector,
the report is in
draft form.
Research on
Agricultural
Financing on-
going.
Policies reviews
and actionable
recommendations
for Investment,
taxation finance
not done.
Output:
160201
Cabinet
Support and
Policy
Development
60 Agenda
and Minutes issued
to Ministers and
Ministers of State.
248 draft
cabinet submissions
Reviewed for
adequacy.
4,800
extracts of cabinet
decisions issued to
ministers and PS.
56 Agenda and
Minutes of Cabinet
Meetings issued.
166 Draft Cabinet
Submissions
reviewed for
adequacy.
3951 Extracts of
Cabinet Decisions
Issued to Minutes,
Ministers of State
and Permanent
Secretaries.
4 agenda and
Minutes of Cabinet
meetings not
issued.
82 draft cabinet
submissions not
reviewed for
adequacy
849 extracts of
cabinet decisions
not issued to
ministers and PS
368
Management explained that there were changes in work plans regarding policy
reviews while the anticipated Cabinet business did not take place.
I advised management to ensure that all planned activities are undertaken and
that any changes to the workplans are documented and authorised.
19.3 Delays in completion of construction of RDC`S Office in Otuke District
A Local Company was awarded a contract to construct RDCs office in Otuke
District at a contract sum of UGX.605,221,056. The contract start date was set on
21st March, 2012 and the intended completion date was 20th July, 2012. Works
were later extended to 31st December, 2013. Despite the extension, the contract is
still behind schedule. The technical inspection report dated February 2014
observed that the roofing works had been completed but with some defects. Since
the project had delayed, the Ministry should have enforced the liquidated damage
clause which was not done. This implied that there was loss of revenue let alone
the signed agreement was not enforced.
Management explained that an inspection team from the Office of the President
identified defects for rectification by the Contractor before the works could be
handed over.
I await confirmation that the defects were actually rectified and that liquidated
damages due to delay are claimed before handover exercise.
19.4 High Vehicle Maintenance costs
It was noted that most vehicles in the Office of the President had exceeded 5
years since they started running and almost all of them had mileage beyond the
limit of 250,000 kms. Because of this, the maintenance costs of the fleet have
tremendously increased. Whereas at the end of the financial year the office had
outstanding garage bills amounting to UGX.534,000,000, management managed
to clear bills amounting to UGX.397,000,000 leaving a balance of
UGX.137,000,000. The office is still faced with bills amounting to UGX.565,106,000
for the first half of the year alone and this has created a balance of
UGX.702,106,000 due for payment.
369
With this trend, it is likely that at the close of the financial year the office may
have outstanding garage bills over UGX.1,000,000,000 given the projections.
Management explained that replacement of aged vehicles is constrained by the
inadequate budget and the Office has raised the matter of the need for additional
resources with the Ministry of Finance, Planning and Economic Development but
no positive response has been received.
I advised management to continue liaising with Ministry of Finance, Planning and
Economic Development and have the outstanding debt cleared to avoid eventual
litigation from garage owners. Plans should be put in place to address the aging
fleet.
19.5 PPDA Audit observations
a) Procurements not in the entity`s procurement plan
The entity conducted five procurements worth UGX.64,037,000 outside the
procurement plan during the financial year contrary to Regulation 3 (2) and (3) of
the PPDA (Procuring and Disposing Entities) Regulations, 2014. Conducting
procurements outside the plan may lead to domestic arrears.
Management explained that the procurements were undertaken as emergency
requirements which had not been foreseen at the time of consolidating User
Department‟s procurement plans.
I urged the Accounting Officer to always ensure that that the user departments
prepare comprehensive work plans and all intended items should be included on
the procurement plan in accordance with the Regulations.
20.0 STATE HOUSE
20.1 Outstanding commitments incurred during the year
Contrary to the commitment control system which requires the Accounting Officer
to commit the Ministry to the extent of funds available, State House incurred
370
outstanding commitments worth UGX.529,849,725 during the year under review.
This practice is contrary to the financial regulations and could lead to litigation
costs due to non-settlement of outstanding obligations.
Management explained that these were utility bills for the month of June which
were received after the financial year had ended and were settled in the first
quarter of financial year 2014/2015.
I advised management to always settle the utility arrears as and when they fall
due.
20.2 Non reconciliation of Government of Uganda debt with UMEME and
State House
Government of Uganda entered into an agreement with UMEME in which the latter
was required to offset government bills that remained outstanding for a period of
more than 60 days. A review of the available documents indicates that total
Government debt as at 31st January, 2013 amounted to UGX.62,771,404,221, of
which UGX.495,904,662 relate to State House. At that date UMEME set off
UGX.31,717,538,490 from the debt leaving a balance of UGX.31,053,885,731 as
total outstanding. However, it was not clear of what amount offset relates to State
House
Furthermore, it was noted that during the year State House did not reconcile with
UMEME to ensure that the amount off set is deducted before making payment.
Management explained that State House was not informed of the deductions and
as such could not undertake the reconciliation.
I advised management to liaise with the Ministry of Finance, Planning and
Economic Development to have the position reconciled.
371
AGRICULTURE SECTOR
21.0 MINISTRY OF AGRICULTURE, ANIMAL INDUSTRY AND FISHERIES
21.1 Land issues
The Ministry has land located in Kampala, Entebbe and various parts of the
country. An inspection was undertaken with a view to establish ownership and
status of use. The following observations were noted;
a) Land not surveyed and titled
A significant portion of the Ministry land especially up country is not surveyed and
therefore not titled making it vulnerable to encroachment. I noted that some of
the land has been encroached on and the issues have not been resolved so far. I
further noted that most of the land especially the up country land has been idle for
a long time and this could have contributed to this challenge.
I was not availed with documents pertaining to occupancy, utilization and transfer
of ownership. I explained to management that the unclear status makes MAAIF
land and assets more vulnerable to waste, encroachment and grabbing. (Details in
table below).
Current Owner Location Size Title
Status
Extent Of
Encroachment
Nyakashashara Holding
Ground
Kiruhura 287 Hectares/717.5
acres
Surveyed The originals plot
has been
subdivided into
43.2 ha and
leased to a
private individual
while 244 ha is
what remains for
the holding
ground
Nshaara Kiruhura 27.3 Sqm17472a Surveyed 5 Square Miles
encroached
372
Current Owner Location Size Title
Status
Extent Of
Encroachment
Kabagore holding
ground
Kiruhura 4 Hectares/10 acres Surveyed -
Kazo Veterinary Centre Kiruhura 10 Hectares/25 acres Surveyed -
Sanga Kiruhura 2.5 Sqm/1600 acres Partly titled 1.5 Square Miles
encroached
Ruhengyere Kiruhura 21 Sqm/13440 acres Titled Kayonza trading
centre 5-10 acres
Katikara in Nalweyo Kibaale 3 sq m/1280 acres Surveyed, a
bsentee
landlord -
Mame
Sabagabo
area (3
sq.m/276
acres)
Missing
Kasenene Tsetse
control
Hoima 10 Acres Encroached -
South Bururuma Kabale 250 ha/625 acres surveyed -
Mbarara zonal
Agricultural Research &
Development Institute
Mbarara 520 ha/1300 acres NARO in the
process of
resurveying,
titled (Title
with Uganda
Land
Commission
)
32 hectares
encroached
Kirimirire Ibanda 8 ha/ 20 acres Not
surveyed
Approximately
1/3 is
encroached on
Nyabikurungu Coffee
Demonstration
Ibanda 4 ha/10 acres Surveyed -
Coffee Demonstration
Centre/House
Mushunga
Nyarushanje sub
county
4 ha/10 acres Not
surveyed
-
Hoima class 111 Hoima 8 acres according to
MAAIF record
Surveyed -
Ibanda farm class II Hoima Estimated 4 Acres Surveyed -
373
Current Owner Location Size Title
Status
Extent Of
Encroachment
W/S
Kitegana Coffee/Cocoa
nursery
Kagadi 2 ha/ 5 acres Surveyed -
Ibanda workshop class
II
Ibanda town 1.2 ha/3.0 acres Not
surveyed
Approximately
1/10 of it has
been encroached
on
Kagadi TVC Kagadi town 2 ha/5 acres Surveyed -
Kakumiro TVC
&Agricultural farm
Kakumiro 2 ha/5 acres Surveyed Whereas MAAIF
intervened
initially, the sub
county through
ULC &DLB got a
land title 7
demarcated plots
for private
developers
Kitagasa coffee
demonstration/nursery
Hoima 1.6 ha/4 acres Surveyed -
Buseruka house of DAO
near L.Albert
Hoima - Not
surveyed
-
Ijamirembe group farm Masindi 1.546 ha/3.87 acres No evidence
of survey
-
Kigumba sub county Masindi 4 sq miles/2560a surveyed -
Dyanga Tsetse control
Unit on Gulu road
Masindi 201 ha/502.5 acres Surveyed
area is 209
ha, I/SE
0148
-
Pakanyi- Kihonda Masindi 560 ha/1625 acres surveyed -
Kihihi class II
workshop
Kanungu - Difficult to
estimate extent
encroached
Kibimbiri cotton
growing farm
Kanungu 320 ha/800 acres Not
surveyed
-
Kihihi fish pond Kanungu 4 acres Surveyed -
Bugangari Coffee
Demonstration Centre
Rukungiri 1.2 ha/3 acres Surveyed -
374
Current Owner Location Size Title
Status
Extent Of
Encroachment
Ntoroko fisheries house Bundibugyo - Not
surveyed
-
Ntoroko meteorological
Equipment and
Fisheries Officer‟s
Residence
Bundibugyo - Not
surveyed
-
Ruhadagaza fish fry
centre
Bushenyi 5 acres Surveyed -
Kicwamba Fisheries
regional hqtrs
Bushenyi 13.63 ha/34.1 acres Surveyed -
Omunyole Livestock
Market, KisokO
Kisoko, Gwaragwara,
Omunyole
Tororo
Approx. 3 Acres - -
Obukuru Holding
Ground, Kayolo
Tororo, Approx. 3 Acres - -
Nyakanysi-Nsongezi Isingiro - - -
Rwivoro Kisoro 300 acres Not
surveyed
-
Rwerere Kisoro - - -
Kyanika Kisoro - Not titled -
Bunagana Kisoro 100 acres Not
surveyed
-
Birere Mbarara - - -
Nalugamba, Busujju Mubende 4.2 acres Surveyed -
Kakuto Class II W/S Kakuto 2 acres Not
surveyed-
Residential by
private people
Kyotera Class II W/S Kyotera 2 acres Not
surveyed -
Private
developments
National semi arid
resources research
institute
Soroti 1,768 acres Survey
process
currently
going on
There is an issue
of the technology
verification
centres, where
encroachment
has been realized
to a large extent
Kidetok Vet Centre Soroti 0.5 acre
375
Current Owner Location Size Title
Status
Extent Of
Encroachment
Odapakol, Pingire
Agu night stop Kumi - Not titled -
Obotia Holding Ground Kumi 50 Acres Not titled -
Alodi Akism, Kadir Kumi Not titled -
Alamaka Mukura sub
county,
Kumi - Not titled -
Oyinuku Koburu, Ngora
subcounty,
Kumi - Not titled -
Bukedea Livestock
Market
Kumi Approximately 2.5
Acres
Omatenga Kajamaka
parish, Kanyum sub
county
- Not titled -
Akuoro parish, Bukedea
sub county kumi
Kumi - Not titled -
Ogirai parish, Kanyum
sub county, Kumi
Kumi - -
Okunguro
Demonstration Farm
Abilakim, Bukedea
Kumi Approx. 7 Acres
Kumi Boma parish,
Kumi Trading centre
Kumi 6 acres - -
Ngora Nyamongo, Kumi 1 acre - -
Karamoja district farm
show ground
Moroto - - -
Atumkat Moroto 937.5 - -
Kihole Katakwi 177 acres
Kuju Katakwi - - -
Nawaikoke agicultural
workshop
Tororo - - -
Masafu Tororo - - -
Omunyole Livestock
Market
Tororo Approximately 3 a Heavily
encroached
Tororo Class I Tractor
Workshop
Tororo Approximately 3 a
Okukuru Holding Tororo Approximately 3 a Heavily
376
Current Owner Location Size Title
Status
Extent Of
Encroachment
Ground Encroached by
the Ringtho
Family
Kisoro sub county TVC Tororo - - -
Malaba Kwapa road, Tororo 2 acres - -
Osukuru Tororo 100 acres - -
Okille Quarantine
Okille, Kobulubulu,
station/Ranch
Kaberamaido Okille Quarantine
Okille, Kobulubulu,
station/Ranch
Kaberamaid
o
Okille Quarantine
Okille,
Kobulubulu,
station/Ranch
Ikulwe Research
station
Mayuge 214 acres On going 1 acre
Bugiri 3335 acres Registered
under plot
9, block 7
(Bukoli)
95%
Sironko Cattle Holding
Ground Buwalasi
Sironkho
173 Acres (surveyed
by Sironko DLG)
Registered
under
Sironko DLG
Wholly taken
Bugusege Experimental
Station, Budadiri
Sironkho Approx. 20 Acres - -
Nalugugu Tractor
Workshop, Bukisa
Sironkho Approx. 2 Acres - -
Nabbongo Variety Trial
Centre
Sironkho Approx. 50 Acres - --
Bulegeni (ARDC) Sironkho 47.82 Process of
securing a
land title in
the names
on NAORO
is on-going
On the side of
the trading
centre the local
authority
constructed part
of the market on
the land
Nakaloke Holding
Ground, Mbale
Mbale Approx. 13 Acres - -
Kidetok Kasilo,Pingire Soroti 0.5 acres - -
Aswa ranch/Acholi
branch
Pader 62 ha,11 ha Leased
expired
-
377
Current Owner Location Size Title
Status
Extent Of
Encroachment
Agricultural VTC Patongo, Pader - Un-surveyed -
Maruzi Apac 64 sq miles Titled Extent not yet
determined
Management attributed the encroachment to inadequate funding of the survey
process and the lengthy process of acquiring a title. Management indicated that
efforts have been made to survey and secure titles of some of the land that
include plots 16-18 station road Entebbe and Fisheries department land. On idle
land, this was attributed to the reforms whereby government divested, itself from
direct production.
I advised management to pursue the matter further with the relevant Authorities
and have the title and land secured.
b) Land usage changed from MAAIF to entities affiliated to the Ministry
During the review, I noted that some land usage changed from MAAIF to other
entities affiliated to the Ministry under various mandates, however ownership
status remained unchanged. For example Sanga Ranch in Mbarara of size 2.5sq.
Miles currently under the stewardship of an affiliate Organisation - NAGRC was
handed over to NAGRC by the Ministry but ownership remained unchanged as
evidenced by the Ministry giving out 30 acres to Sanga Town Council while 1 sq.
mile was reported grabbed by an individual.
Management explained that some land was handed over to MAAIF statutory
agencies and that the recipient agencies are processing transfer of the titles to
their names.
I advised management to liaise with the responsible stakeholders to facilitate the
survey process and have all its land titles acquired. Management should also
consider handing over ownership of the land to affiliated entities for close
supervision and security.
378
21.2 Under performance
A review of the Ministry‟s performance showed that the Ministry had total
operating revenue of UGX.68,986,685,103 including NTR of UGX.824,106,174
during the year. As at 30th June, 2014 I noted that funds worth
UGX.8,663,443,218 remained un-utilized reflecting under absorption capacity of
12.7%. As a result, a number of activities planned for the year were not
implemented as indicated below:
Vote
Function/out
put
Planned/Perfo
rmance
Indicators
Achieved
Target
Perfor
mance
gap
Review
Comments
Management Responses
010103
(The total
output budget
was 2,601bn
and
2,850bn was
spent under
various
activities of
the output)
Purchase of 20
tractors for
distribution as
grants to
farmers.
16
delivered
4 not
delivere
d (80%)
Management
should explain
the cause of
failure to
deliver the
balance of 4
tractors.
The suppliers attempted to
supply 4 tractors of a
different specification and
this was not acceptable to
the ministry foreseeing a
lengthy process for
clearance by Chief
Mechanical Engineer, the
Solicitor General and
approval by contracts
committee without strong
justification. Administrative
arrangements are being
made to ensure that the
four tractors of the same
make as the 16 are
delivered to MAAIF.
010103
Crop
production
technology
promotion:
22 Irrigation and
water harvesting
demonstrations
made in the
various districts.
9
Installed.
Gulu,
Kitgum,
Pader,
13 not
installed
No reasons
given for the
failure to
install the 13
water
This was due to absence of
Extension Staff in Districts:
The success of this activity
was dependent on the ease
with which MAAIF could get
379
Vote
Function/out
put
Planned/Perfo
rmance
Indicators
Achieved
Target
Perfor
mance
gap
Review
Comments
Management Responses
Lira
,Oyam,
Nebbi,
Buliisa,
Maracha
and
Rubirizi
harvesting
demonstration
s yet the item
was overspent.
the list of selected
beneficiaries from the
Districts. Almost all districts
on average have only two
members of staff in the
District Production
Department who are over
loaded with limited
facilitation to traverse the
sub-counties identifying
suitable candidates. This
affected the critical
processes of project
implementation.
010103
Crop
production
technology
promotion
Establish an
Agricultural
Mechanization
Resource
Centre for
training of
machine
operators,
technical
information
generation,
referral
workshops and
testing/evaluatio
n of agricultural
machinery
Not
implemen
ted.
Not
impleme
nted.
No activity was
done.
Management
should explain
the reasons.
It is true the bills of
quantity for rehabilitation
works were not completed
during the financial year
and the works were not
undertaken.
010105
Food and
35 districts to be
assessed for
25
assessed.
10 not
assesse
Management
should explain
This was due to unforeseen
increase in operational
380
Vote
Function/out
put
Planned/Perfo
rmance
Indicators
Achieved
Target
Perfor
mance
gap
Review
Comments
Management Responses
nutrition
security.
food and
nutrition
security
d the cause of
underperforma
nce
expenses which would not
allow undertaking training
in all the 35 districts.
010109
Control of pest
and diseases
in priority
commodities.
(Total output
Budget was
1,600bn and
1,553bn was
Spent (97.1%)
under various
activities of
the output)
Soil fertility
knowledge
management
enhanced 300
soil testing kits
procured and
distributed to
districts.
Procured
100
200 not
procure
d
Management
should explain
the reasons for
under
performance.
There was change in plan
because the kits are to be
used by trained extension
staff and these had not
been recruited, since the
consumables in the kits
expire, had to procure
those that can be used by
available trained staff. The
rest were carried over to
2014/15, to be procured as
more staff are recruited
and trained to use them.
010204
Promotion of
sustainable
fisheries.
(Total output
Budget:
9,121bn
and 6,824bn
(74.8%) was
spent under
various
activities of
the output)
Fishing capacity
controlled
through
licensing all
fishers on all
water bodies.
Not
reported
on.
All
fishers
not
licensed.
No reasons
given for non-
performance.
It is true that not all fishers
were licensed. Delays in
implementing the new
licensing strategy was
caused by delays in the
procurement of the Fishing
Vessel Identification Plates
(FVIPs); because it was a
new innovation requiring
standardizing the vessel
plates, structure,
numbering and their reflect
ability. These new
innovations hampered the
licensing activities on all
381
Vote
Function/out
put
Planned/Perfo
rmance
Indicators
Achieved
Target
Perfor
mance
gap
Review
Comments
Management Responses
water bodies. However
from September 2014 to
date; 3,809 FVIPs have
been issued out as follows:-
Lake Victoria-2759
Lake Albert-350
Lake Kyoga-450
Lakes
Edward/George-240 Other water bodies-10
010204
Promotion of
sustainable
fisheries.
Fishing capacity
controlled
through direct
support to
districts to fund
licensing
activities.
Not
implemen
ted.
Activity
not
carried
out.
Districts are
not supported
by the Ministry
yet.
It is true that districts are
not yet directly supported
by the Ministry to fund
licensing activities. The
mandate of direct support
to districts awaits clearance
of a MOU by the office of
the Solicitor General. The
Ministry is however
pursuing the
operationalization of the
Fisheries Fund to support
grass root activities.
010204
Promotion of
sustainable
fisheries.
5,000
aquaculture
structures
established.
Only 820
structures
establishe
d.
Perform
ance
gap of
4180
No reasons
given for the
underperforma
nce
The Directorate does not
establish but promotes
establishment and adoption
of cage culture enterprises
in aquaculture.
Achieved were 820 cages
setup in various locations.
Response by private sector
has remained low; however
the PPP law was put in
place in 2014; and the
382
Vote
Function/out
put
Planned/Perfo
rmance
Indicators
Achieved
Target
Perfor
mance
gap
Review
Comments
Management Responses
situation is bound to
change. MAAIF is currently
developing a
comprehensive aquaculture
policy to provide an
enabling environment for
aquaculture development.
Failure to utilize the available funds translates into failure to achieve the targeted
short-term objectives which has a negative effect on the mandate of the Ministry.
I advised management to enforce monitoring and supervision of its operations to
ensure all the planned activities are implemented.
21.3 Procurement issues
a) Un planned procurement
During the review, I noted that procurement worth UGX.59,659,384 for extra
works for Entebbe office premises renovation was not included in the procurement
plan contrary to the PPDA Regulations. I explained to management that unplanned
procurements could lead to diversion of funds as well as wastage of financial
resources.
Management responded that the procurement became emergent due to the
instructions received in the middle of the financial year for the Ministry to shift
from Kampala to Entebbe.
I advised management that emergencies should also be handled in accordance
with specific regulations in the PPDA Act.
383
21.4 Incomplete renovation works
A construction company was contracted to undertake renovation of the Ministry
office premises in Entebbe. The renovation works included; plastering, painting
walls and ceilings, replacement of faulty roofing materials, electrical repairs,
installation of sanitary appliances and others. By the end of the financial year;
payments worth UGX.144,214,834 had been made to the contractor. A
review of bills of quantities (BOQ) and the extent of works carried out so far
indicated that the quality of work performed by the contractor was lacking. I noted
that the contractor mostly painted the buildings other than doing the above listed
jobs. Hanging cables, unrepaired ceiling boards and broken locks were not fixed as
illustrated in some of the photographs below:
Loose absolute telephone cables. Ceiling board not replaced /repaired.
There is a possibility that the contractor was not properly supervised.
I also noted that some offices that were equally in need of renovation such as the
Department of Crop Protection, Project office and stores were not included in the
renovation plan. The pictures below show the state of the buildings not yet
renovated;
Department of Crop Protection block. Below is the project Office surrounded by
squalid shacks in which scrap
stationery is piled
384
Below; MAAIF Stores.
I explained to management that the state of affair reflects a bad image of the
Government Ministry.
Management explained that the exclusion of other buildings like the store and the
Crop Protection block was due to limited funding.
I advised management to prioritise and liaise with ministry of Finance for adequate
funds to enable completion of repair works.
21.5 Delayed Supply of 4 tractors
A Local Company was contracted to supply 20 (4 wheeled) tractors with
implements under mechanization/Labour saving technologies each at a cost of
US$.34,336. The contract was signed on the 17th June 2013 and the delivery date
had been slated for end of March 2014. The tractors were a grant to farmer
groups engaged in the production of strategic commodities. A review of this
procurement revealed the following anomalies:
Records availed showed that at the time of reporting, only 16 tractors had
been delivered, inspected and received at Namalere leaving 4 tractors
385
undelivered with no clear reasons. There was no evidence as to when the
balance of 4 tractors would be supplied and delivered to the beneficiaries.
I also noted that there was equally no information pertaining to the
deliveries of the tractors to the targeted beneficiaries.
It was further noted that the performance security was waived under the
general conditions and Ministry is not covered in case the supplier fails to
supply all the tractors which could end up in prolonged litigation process
denying citizens‟ benefits. The Ministry also risks losing resources in re-
starting up the procurement process.
The Accounting Officer explained that the supplier supplied 16 tractors with
implements in accordance with the contractual specifications and the request to
supply 4 tractors of different specifications was not acceptable and hence it was
likely that the procurement of the 4 tractors will be re-advertised.
I advised the Accounting Officer to revisit the issue and take appropriate action.
21.6 Non Tax Revenue
a) Lack of statistical data
The Ministry has various revenue sources under three major directorates; the
Directorate of Crop Resources, Directorate of Animal Resources and Directorate of
Fisheries Resources. However; I noted that the Ministry does not have statistical
data on its revenue sources and as a result, revenue forecasts are not realistically
made which continues to affect the NTR collections. I explained to management
that lack of reliable data and performance targets makes it difficult for the Ministry
to appraise revenue performance.
I advised the Accounting Officer to allocate the necessary resources to facilitate
the directorate towards the process of data collection in order to make realistic
revenue estimates.
b) Failure to revise the Fisheries rates
386
During the review of NTR collected from fisheries, I noted that the license/permit
rates have never been reviewed ever since they were set under Statutory
Instrument No 33 of 2010. I explained to management that the economy has
since then grown and the volume of fishing activities increased hence application
of the same rates could only lead to loss of revenue to Government which further
translates into under performance in collection of NTR.
Management acknowledged that the rates have never been revised since 2010
when the Fishing rules were formulated and passed. Nonetheless, several aspects
of this law have already been identified for revision. Several internal meetings
have been done as part of the procedures for the review of the 2010 fishing rules
and relevant steps will be taken to operationalize the revisions into law.
I await the outcome of management commitment.
21.7 Neglect of stores
In my previous year‟s report, I reported the issue of the state of MAAIF stores but
no action has since been taken and instead the situation is getting worse. Physical
inspection of stores indicated that they are in a deplorable condition. I further
noted that the stores department operates a manual system which has also not
been updated. I explained to management that failure to update the stock ledgers
regularly could result into failure to detect irregularities like theft of stores.
Management explained that the Ministry undertook a phased approach renovation
of the stores which includes installation of vital facilities. The stores renovation
plan was however interrupted by the directive to revert the Ministry to Entebbe
premises which expanded the renovation requirements. The apparent neglect of
stores is attributed to inadequate funding under maintenance-civil amidst
competing renovation requirements.
I advised management to prioritise the stores section so as to enforce good stores
management practices.
387
21.8 Misuse of Government assets and illegal tenants
As part of the audit; inspection of Wandegeya premises which is a prime land that
accommodates an affiliate Organisation - COCTU offices was carried out. I noted
that part of the premises has been turned into residential quarters, food kiosks,
restaurants and some offices are occupied by unauthorised tenants such as
Kampala Capital City Authority Veterinary Officer and Walimi Fish Farmers
Cooperative Society (WAFICOS).
I noted that there were no tenancy agreements hence no evidence that the
tenants have ever paid rent. Further, COCTU which is an affiliate entity under the
MAAIF sector is in shortage of office accommodation and yet the unauthorised
persons continue to occupy government premises without even paying rent,
including some tenants rearing chicken near the offices an activity that is not
rational near offices. Failure to collect rent from the tenants translates into causing
financial loss and misuse of government assets. The pictures below describe part
of the situation at the Wandegeya premises:
Above shacks structures converted to residential
quarters.
Food kiosks/restaurant without designated
toilet facilities.
388
Food preparation is done from the open spaces within the compound in front of some COCTU
offices.
I also noted that one of the Ministry‟s old vehicles parked at the premises was
burnt from the parking lot under unclear circumstances. As at the time of
reporting (February, 2015), there was no police investigation report in place.
The above situation puts the premises to several risks including insecurity, fire
outbreak and health related issues. I explained to management that there is a risk
that this prime land could easily get grabbed by the current squatters if no
controls are put in place to secure the premises.
Management explained that the Ministry has already taken steps to notify the
illegal occupants to vacate the premises.
The outcome of management action is awaited.
21.9 Department of Crop Production
a) Staffing gaps (10)
During the review, I noted that the Ministry has not yet filled some vital vacancies
under the department of Crop production as provided for within its establishment
as summarised below:
No Position Number of vacant posts
1 Mobile Workshop Mechanic 1
2 Grader Operator 2
3 Drivers 4
4 Turn-Man 3
TOTAL 10
I explained to management that the current staffing gaps could affect the
Department‟s performance hence failure to operate efficiently.
389
Management explained that staffing gaps exist because there were no adequate
funds to fill all the positions. Management however indicated that in the next
financial year, a provision has been made to fill all the vacant positions.
I await the outcome of management‟s commitment.
21.11 Plan for Modernization of Agriculture
a) Vacant posts (11)
During the review, I noted that the department lost up to 11 employees who had
literally resigned. Although this department is small; I noted that it is a very crucial
department such that a big number of staff resigning is a cause to worry. Below is
a summary of staff who resigned since 2004:
Numbers Title Date of Resignation
1 Director 2006
2 Director 2012
3 Accountant/Administrator 2004
4 Gender Specialist 2007
5 Accountant/Administrator 2005
6 Accountant/Administrator 2012
7 Office Attendant 2009
8 Driver 2007
9 Driver 2007
10 Driver 2010
11 Research Assistant 2012
I was not availed with any report about the possible causes of resignations. I
explained to management that there is a possibility of failure to implement the
planned activities which could lead to failure to attain the project objectives.
390
I advised management to consider filling the gaps for effective service delivery.
21.11 Loss of a motor cycle UG 2125A-Suzuki.
During the review, I noted that a motor cycle valued at UGX.9,000,000 was stolen
from an officer by unknown people around his home in Kigaga Zone Salama parish
Makindye Division Kampala. I was not availed with appropriate documentation
permitting the officer to use the motor cycle and permission to ride it home. At the
time of reporting (February 2015),the motorcycle had not been recovered. In the
circumstances, it is highly likely that the motorcycle may not be recovered and
besides, the loss was not captured in the financial statements.
Management explained that the case of the stolen motorcycle was reported at
Katwe Police station, arrests were made and the Police are still handling it and
management is still waiting for the conclusion of the case by Police, then a
decision will be taken against the officer.
I outcome of the above action is awaited.
21.12 Motor vehicle UAA 718E-pick up
Motor vehicle UAA 718E –Pick up got involved in an accident in Jinja and was
taken to a Garage in Mengo. During the review, I noted that the vehicle had
stayed in the garage for close to 3 years without being repaired. I further noted
that there was no police report and the circumstances under which it got involved
in the accident and its status before it was taken to the garage could not be
established. There is a possibility of vandalism and further loss of value of the said
car if it is not retrieved out of the garage immediately.
Management explained that the vehicle was inspected by Police and the process of
repairing the vehicle has been initiated pending conclusion. I advised management
to endeavour to repair the vehicle and put it to proper use.
21.13 Delayed establishment of Agriculture Police.
391
A review of the correspondences available revealed that MAAIF has been in the
process of creating an Agriculture Police Force to boost its enforcement effort. I
noted that the process has been rather slow and as at the time of reporting
(February 2015), the deployment had not yet started. I explained to management
that delays in deployment of the police force is likely to increase illegal fishing and
fish trafficking which puts to risk the lives of Fisheries personnel and Beach
Management Unit (BMU) members. Lack of adequate enforcement may also lead
to loss of revenue and gradual depletion of fish stock.
Management explained that the delays in establishment of Agriculture Police were
due to the process and deployment which is beyond MAAIF‟s control. The Ministry
made a follow up and the Police have now been secured awaiting deployment.
I advised management to deploy the police without any further delay.
21.14 Inspection of fish landing sites
As part of the review, inspections of a sample of some fish landing sites was
carried out and below were the findings:
Landing Site Observation/Remarks
Kalangala
In Kalangala,
Mwena, and
Lutoboka fish
landing sites
were inspected
MAAIF‟s Insufficient revenue mobilization strategy
a) Lack of personnel I noted that MAAIF does not have personnel in the districts to
monitor revenue collection despite the re-centralization of
revenue collection. The fishing rules recognize the District
Fisheries Officers and Beach Management Unit (BMU) members
as authorized officers under the rule 26 however; because of
lack of facilitation from MAAIF the officers cannot carry out
enforcement activities.
I explained to management that failure to deploy personnel and
392
Landing Site Observation/Remarks
build capacity in the districts will continue to affect revenue
collection and thereby impact negatively on the general
performance of the Ministry.
Management explained that MAAIF has no personnel in the
districts but supports District Fisheries Officers (DFOs) and BMU
leaders to mobilize, vet and approve fishermen to acquire
licenses in fishing for all NTR. Management further indicated
that the Ministry is undertaking the following to improve
revenue collection.
Transformation of the Department of Fisheries Resources into now a fully-fledged directorate will have more recruitments
Under the single spine agriculture system provision is on for each district to have a District Fisheries Officer and also at Sub-counties with lake Fisheries Pursuing the operationalization of a Fish Levy Fund for a plough back mechanism to ensure sustainable financing.
I await the outcome of the management planned actions.
b) Failure to license boats
Most fishing boats operating in the water bodies were not
licensed contrary to the Fishing Rules. Whereas the Ministry
developed the concept of Vessel Identification Plates (VIP)
around 2011, the introduction of the same took off at a very
slow pace during the financial year under review. I noted that
the majority of the boats operating in the lakes have not yet
been licensed and issued with certificate of vessel ownership
and vessel identification plates as required under Rule 16 (1-3).
Kalangala district received only 60 plates whereas it has about
393
Landing Site Observation/Remarks
64 landing sites with approximately 3,000 boats implying that a
balance of 2,940 boats would still not be issued with the plates.
The revenue loss accruing in respect of application fees of
10,000 and fishing license of 100,000 per annum for the 6
years was UGX.1,940,400,000 (UGX.323,400,000 per year) since
MAAIF recentralized revenue collection.
One of the sites visited; Mwena has a fleet of 66 boats and out
of these only 10 boats were licensed (15%) meanwhile
Lutoboka landing site has a fleet of 59 boats out of which only
17 (29%) were licenced. I explained to management that
Failure to license boats causes loss of revenue to Government.
Management explained that Kalangala district has so far
received more than 1,387 FVIPs and the current deployment of
the Agriculture police and Fisheries Inspectors at border posts
will strengthen enforcement compliance to improve licensing of
boats and other NTR obligations.
I advised management to expedite the registration of fishermen,
issuing of licenses and VIPs backed by an effective enforcement
and supervision so as to improve on revenue collection.
c) Use of un authorized fishing gears
I noted that illegal fishermen use prohibited fishing gears
contrary to the Fishing Rule 3 (1)-(3) which leads to depletion of
fish stock given that illegal fishing is carried out at the lake
shores which are the fish breeding grounds. In the entire fish
landing sites visited, it was reported that the catch has reduced
by over 50%. Lack of adequate monitoring and supervision by
the Ministry could accelerate this challenge leading to loss of
revenue to Government and lack of employment to citizens.
394
Landing Site Observation/Remarks
Management explained that the Ministry has an appropriate
enforcement strategy which it has been using to tackle the use
of unauthorized fishing gears. The expansion of the Regulation
Unit into a Department will go a long way to strengthen the
enforcement strategy in place. The Ministry also has a strategy
to implement cage fish culture/aquaculture development that is
being implemented to boost fish production.
I advised management to roll out an effective enforcement
strategy to curb illegal fishing and promote cage fishing and
aquaculture.
d) Dormant fish landing facilities
Despite the huge investment of up to UGX.2,803,549,835
invested on Mwena Landing Site; the facilities have been
dormant since its completion and hand over in 2007. Refer to
pictures below:
Some of the reasons advanced were that the facility was handed
over to the district for management without operational funds. I
could not establish the clear reasons for failing to utilize the new
structures yet a significant amount of funding was spent on it.
395
Landing Site Observation/Remarks
The Accounting Officer explained that the districts are managing
the facilities with challenges due to the unforthcoming revenues
from the proposed sources attributed to the general decline in
the stocks of Nile perch and Tilapia fish, the species for which
the landing sites were designed to handle. With the positive
trend in the fish stocks registered last year at 1.2%, coupled
with other fisheries management measures put in place, the
challenges noted in the Audit report shall be overcome and the
fisheries infrastructures will be cost effectively operated.
I advised the Accounting to plan adequately and ensure the
facilities are put to use.
Kashanga
Landing site
At this site the following challenges were noted:
Bad fishing methods brought about by usage of unauthorized
fishing gears. I further noted that some of the BMU members
who are supposed to check illegal fishing methods are
sometimes engaged in fishing of premature fishing themselves
due to the fact that the Ministry has not yet put in place a
rigorous vetting methodology for electing members of the
BMUs.
Inadequate toilet facilities which could lead to sanitation
challenges.
The above challenges have continued to affect the operations of
the fisheries sector translating into poor performance during the
year.
Management explained that regular routine sensitization against
the use of illegal gears has been on-going and with the help of
Agriculture Police and deployed border fisheries inspectors‟
396
Landing Site Observation/Remarks
compliance surveillance will be intensified. The BMU guidelines
and statute of 2003 is in its final stages of being revised and
BMU leaders will now be vetted before they are elected by the
fishing communities. Promotion of use of suitable sanitary
facilities at fish landing sites is part of the fisheries infrastructure
development which is a continuous process to support
communities.
The outcomes of the above management actions are awaited.
Lambu Lambu landing site had 120 boats on site but only 34 (29%)
were registered. It is estimated that revenue amounting to
UGX.79,200,000 from the boats application fees and license has
not been collected from them for the last 6 years. Lack of
controls such as Issuing Vessel Identification plates affected the
collection of revenue abetting illegal fishing in which premature
fish is targeted.
Other challenges at this site included;
- Landing of fish in un designated places, - Lack of capacity to carry out law enforcement. - Failure to register all the fishermen. I noted that the Ministry embarked on the process of registering the fishermen and created a data bank of about 1,857. Out of these, 358 were approved by MAAIF after they paid a registration fee of 10,000 each. - Lack of personnel for law enforcement and equipment; the fish landing facility was privatized and it is difficult for government to prescribe measures to the private business man.
Management explained that the exercise is in many cases
dodged by the community that find it easier to operate against
the national laws. This is now being addressed through the
current procurement of FVIPs and enforcement equipment and
agriculture police.
397
Landing Site Observation/Remarks
I advised management to enforce the law in place.
Majanji Inspection of the above landing site revealed that the ice plant
was non-functional due to lack of power and low fish production
yet Government invested up to UGX.3,703,694,777. The landing
site has 35 registered fishermen but none of them had paid the
application fee, the fishing licence and permit translating into
loss of revenue to government. I noted that no revenue has
been collected from this landing site for the last 6 years implying
an estimated revenue loss of UGX.23,100,009 (110,000 x 35 x
6) in application fees of UGX.10,000 each and license fee of
UGX.100,000. The other challenge was un-authorized cross
boarder illegal fishing at the border.
Management explained that the landing site was handed to the
district in July 2012, and is connected to the national grid. The
non-functionality of the structure is largely due to management
issues in the district and lack of fish due to cross border trade. A
senior Fisheries Inspector has been deployed at Busia Boarder
to provide effective monitoring and supervision of the fishing
activities. I advised management to strengthen monitoring and
supervision of the fishing activities.
Kakyanga Kakyanga landing site had 50 registered fishermen from which
no revenue has been collected for the last 6 years implying
revenue loss of about UGX.33,000,000. I noted that all the
boats operating at this landing site are doing so illegally contrary
to the Fishing Rule No 12 of the Statutory Instrument No 33 of
2010. Whereas MAAIF introduced Vessel Identification Plates
(VIP) for the purpose of easy identification of noncomplying
Vessels, such controls have not been embraced at this landing
site. There is a possibility that the Ministry could lose more
revenue in uncollected fees if controls are not strengthened.
398
Landing Site Observation/Remarks
Management explained that the distribution of FVIPs is ongoing
and will solve the anomaly. I advised management to
strengthen controls so that all boats are licensed before they are
allowed to operate.
21.16 General observation affecting operations of landing sites.
Fish landing facilities in the rest of the water bodies are faced with similar
challenges as stated above. A review of monitoring and evaluation report of the
Ministry for year revealed the following weaknesses:
No Location Cost(U) UGX Status Review comments Management Response
1 Mwena in
Kalangala
2,803,549,8
35
Non-
Operational
No electricity for
operation of the heavy ice plant
machinery
Not connected to the
national grid, but provided with 2
generators
2 Kitobo in
Kalangala
2,545,934,7
18
Operational
but with
challenges
Operational with
power challenges of
running the generator. It is not
cost effective
3 Bwondha in Mayuge
2,711,582,225
Operational but with
challenges.
Being managed by the BMU. The ice
plant is not functional because there are no
cold room facilities. It was not handed over.
The insulated store for ice storage
rooms is provided and the landing site
was handed over to the district.
4 Bugoto in
Mayuge
2,798,302,6
71
Operational No power and
running water but use a generator
which is not cost
effective.
Not connected to the
national grid, a generator is
provided and there
is installed water pump and treatment
system
5 Majanji in Busia 3,703,694,7
77
Operational
but with
challenges.
Fully operational but
it was never handed
over officially. The facility does not have
power.
Handed over to the
district, connected to
the national grid and provided with
standby generator
6 Gorofa Island in Bugiri
3,635,593,299
Not operational.
Not commissioned, not handed over and
no power supply.
Provided with 2 generators, persons
nominated by the
399
No Location Cost(U) UGX Status Review comments Management Response
district to operate
the installed facilities trained, not
operating due to challenges (power
and management).
7 Namasale in Amolatar
District
3,926,810,760
Operational It is incomplete, i.e. incomplete plumbing
work and there is no
electricity on site. It was not officially
handed over although fishermen are using
it.
Fully completed, provided with a
generator and
managed by the district together with
the BMUs
8 Kiyindi in Buikwe
2,105,834,438
Non Operational
Incomplete power house and there is no
electricity on site.
Connected to the national grid,
provided with a stand by generator.
There are items in
the design to be completed
9 Bukungu in Buyende
1,741,977,155
Non Operational
Construction of the jetty for the boat
landing is not
complete and there is no electricity on site
Not connected to the national grid,
provided with a
generator, jetty completed. There
are items in the design to be
completed
10 Butyaba in Masindi
2,162,380,394
Operational but with
challenges.
It is operational however there is no
water and electricity.
11 Lwampanga in Nakasongola
2,199,538,421
Non Operational
with challenges.
There is no power at the landing site and
no running water. The constructions are
also incomplete
Not connected to the national grid,
provided with a generator, water
treatment system
provided. There are items in the design
to be completed
12 Busia TC- Fish market
Operational Fully operational however, there was
no official hand over.
Officially handed over
13 Tororo
Municipality-
Fish Market
Operational Operational however,
there is no fridge and
cold room, there is no water and electricity
Electricity and water
provided. Fridge and
cold room was not in the scope of the
facilities to be provided
14 Iganga TC-Fish
Market
Non
Operational
Facility was
abandoned due to
Officially handed
over, was connected
400
No Location Cost(U) UGX Status Review comments Management Response
lack of running water
and electricity. There is also encroachment
on the land.
to electricity and
water but ownership wrangles within the
district is affecting operationalization.
15 Mukono TC Operational Operational however,
there is no water and electricity
Electricity and water
was provided.
16 Mityana TC Non
Operational
There is no
electricity, vandalized.
Officially handed to
the district with all facilities fitted.
District is getting ready to use it.
17 Nyendo in
Masaka
Operational Operational however
there is no cold room and electricity.
Electricity was
connected. However, cold room
was not part of the
design.
18 Mbarara
Municipality
Non
Operational
Incomplete- need to
install the breeding machinery
for the fish, need to
install electricity
Officially handed to
the district with all facilities fitted.
electrical repaired by
district.
19 Kabale
Municipality
Operational Operational however
there is no running
water and no cold room
Water was provided,
cold store was not
part of the design.
20 Ishasha Broader market
in Kasese
Demolished and
constructed a
new one
21 Mpondwe
Boarder Market
in Kasese
Demolished
and
constructed a new one
A new structure was
put up by Belgium
Technical Cooperation. There
was no communication
allowing them to
demolish
22 Kagadi TC-
Market
Functional It is operational but
there is no fridge, latrine and never
handed over officially.
Officially handed
over. Fridge and latrine was not in
the scope of the
facilities to be provided.
23 Lira TC-Market Non
functional
Reconstructed
24 Gulu TC-Market Demolished
and constructed a
new one
Incomplete. The
machinery was delivered but not
installed, hatchery
Reconstructed
401
No Location Cost(U) UGX Status Review comments Management Response
was not installed, fish
ponds and other buildings not
completed.
25 Soroti TC Non Operational
Officially handed to the district with all
facilities fitted
26 Luwero TC Operational Operational however there is no running
water and no cold room. The
administration block was not Constructed
yet it was on the
original plan
Cold room and administration block
was not in the scope of the works
27 Masindi TC Non
Operational
It is operational
however there is no
running water and electricity. There are
no cold room facilities
Electricity and water
was provided. Cold
room facilities was not in the scope of
the design.
28 Paidha TC Operational Operational however
there is no cold room
and electricity.
Cold room facilities
was not in the scope
of the design
29 Bushenyi TC-
aquaculture
center
Non
Operational l
Incomplete- need to
install the breeding
machinery for the fish, need to install
electricity.
Installation of the
Hatchery equipment
in progress
30 Kajansi Operational Fully Operational
31 Mbale TC
Non
Operational
The infrastructure
was abandoned when it was incomplete.
The hatchery
machineries were not installed
Process of having it
completed in progress
Sub-total 30,335,198,
693
SUMMARY OF COSTS
Sub –total as shown above 30,335,198,693
Construction of Fish Market stalls in the North East zone.
605,328,438
Construction of Fish Market stalls in Central
zone and extension of fish quality control laboratory at Entebbe.
1,118,625,475
Construction of fish market stalls in the North
East zone.
Rehabilitation and Construction of Fish
Markets stalls in South West.
833,856,897
Total 32,893,009,503
402
Despite the heavy investment put in fisheries sector as summarised above; the
Ministry has not yet put up mechanisms to maximise revenue collection. There is a
risk that the assets could depreciate before they are put to proper use and thereby
fail to meet the intended objectives.
I advised management to put in effort to collect revenues from fisheries and
emphasize law enforcement on water/landing sites operations.
21.17 Inspection of Small Scale Irrigation/water harvesting demonstration sites
MAAIF entered into a framework contract on the 21st November, 2013 for the
establishment of Small Scale irrigation/harvesting demonstration sites. The
objective was to reduce rain dependent Agriculture and to cope with the rainfall
variability due to climate changes.
a) Lira district
The project is located in Adekokwok S/C in Angweta-ngwet Parish.
One of the criteria of locating the demonstration site was existence of water
source however I noted that the site did not have any water source. The
farmer was dependent on rain water since the supply from NWSC was
unreliable and costly. A trial garden of about an acre with tomatoes planted
therein was inspected. I noted that a 5,000 litre water tank was installed, the
garden is connected with perforated plastic pipes for water sprinkling but due
to absence of water, the garden is almost drying up as the water tank had no
water.
A water pump that was supplied was not found on site as the farmer reported
that the same had been borrowed by a nearby farmer since it was basically
idle. I noted that lending equipment supplied to unknown people under the
403
project was not provided for and the possibility that the pump could have been
sold could not be ruled out.
I noted that the site had been faced with drought for the last three months, an
indication of poor choice contrary to the selection criteria. There is a possibility
that the investment may turn out to be wasteful leading to loss of value for
money benefits.
Management explained that rainfall is the principle source of water. The only
viable option at this site was rainwater harvesting and the facility was installed at
the peak of the dry season. Therefore the farmer will only have water in the
reservoir for demonstration of supplementary irrigation after the coming rains. The
names of the beneficiary farmers‟ of the demo sites were given to MAAIF by the
Districts in order of priority, and they were representative of the area in terms of
water scarcity. The technology is intended for farmers in water stressed areas to
take-up rainwater harvesting because it is the cheapest to replicate at the
smallholder farmer level.
I advised management to ensure the project is closely monitored so that the
farmers benefit from the support and the project objectives achieved.
b) Oyam district
I noted that this site was chosen due to the fact that it had already demonstrated
transformative farming methods among the community with a major objective of
improvement of household income. The site did not have a nearby water source
and the pump that was meant for pumping water from surface water was found
idle as shown below;
404
The perforated pipes for sprinkling and water pump supplied under the project
were not yet put to use (still in the store). The reason for this was that the
pump was designed to draw water from the surface sources which is not
available ; instead, the proprietor is using water from a deep well which he
had before the project was initiated, an indication that this investment too has
not added any value to the farmer. The other challenge reported was that the
perforated watering pipes seemed fragile and the farmer prefers to use water
bottles for sprinkling. This showed that some farmers need sensitisation on
handling which is not yet done. A tour of the farm showed a lot of fruits rotting
due to various diseases and failure to access the market.
In spite of the above challenges, there was no evidence that the project was
effectively monitored. There is a possibility that the project objectives will not be
achieved.
Management explained that at the time of site identification and beneficiary
selection the farmer had no water source. However, the farmer is enterprising and
had drilled a production well for home use and the nearby planned poultry unit by
the time the contractor was deployed and after discussions with the farmer an
agreement was reached to retain the surface water pump to extend water to his
Orchard and fodder garden a distance away where water would not reach by
gravity from his system. He pledged to construct a small pond (collection sump)
where the surface pump would lift the water from the primary source further away
to the Orchard.
I advised management to enforce monitoring and sensitization to farmers.
21.18 BUKALASA AGRICULTURAL INSTITUTE
i) Inappropriate College Structure
During the review, I noted that the College structure was designed and approved
in 2003 when the College was administering only two courses/programs (Animal
Production and Management & Crop Production and Management). However,
currently the College offers six programs as follows; Animal Production &
405
Management, Crop Production & Management, Human Nutrition & Dietetics, Agri-
Business and Horticulture and Management. I noted that the structure of the
College is inappropriate for its current size and operations which could affect the
delivery of services to various stake holders.
Management explained that Public Service cleared the review of the structures of
training institutions and requested MAAIF to provide the plan and logistical support
for the exercise. MAAIF has already provided a budget for review of structure and
arrangements have been made to finalize the plan and to provide logistics to
enable the Ministry of Public Service undertake a review of the structures.
I await the outcome of management action.
ii. Academics - Admission of students
I noted that the College admits both Government sponsored and private students
and in the two types of admissions, the list of successful students is normally
approved. However, during the review I noted that out of the 485 students
admitted, 93 private students‟ supplementary admission list for all courses
including in-service students who do their studies during holidays was not
approved as shown below:
Course Gov‟t
A-Level
Private
A-Level
Private
F/S
Sub
Total
Private
Supplementary
Total
Animal
Production
25 28 12 65 15 80
Crop Production 25 52 13 90 18 108
Agri-business 10 37 5 52 16 68
Human Nutrition 10 15 5 30 09 39
Horticulture 10 8 4 22 05 27
In-service animal - NA NA 65 15 80
In-service crop - NA NA 68 15 83
Total 80 140 39 392 93 485
406
There is a risk that revenue generated from the students whose admission was not
approved by the Council may not be disclosed and could get misappropriated.
In response, management explained that the Universities and Other Tertiary
Institutions Act, 2001 gives the College powers to admit students on Private
Programme through the Admissions Committee made of Heads of Departments
and the Academic Board normally sits to admit all the students that are on Private
Sponsorship. Management has taken steps to regularize the supplementary
admission and minutes.
I await the outcome of management‟s commitment.
22.0 NATIONAL AGRICULTURAL ADVISORY SERVICES (NAADS)
22.1 Compliance with the Financing Agreement
Component 3 of the financing agreement focussed on the provision of advisory
services. However, Government changed the implementation of this component to
free input distribution which led to disagreements with the development partners
that resulted in their suspension of funding for the component.
The change in implementation to provision of free inputs to farmers implies that
the expenditure of UGX 84,823,360,000 recorded under component 3 of the
ATAAS project is ineligible for funding by the participating partners and
achievement of the ATAAS project intended objectives for component 3 may have
been compromised.
Management explained that discussions were held with development partners
during the mission of August 2014 and it was agreed that GOU funds should solely
be used to input purchase for distribution to farmers. As such the development
partners agreed to fund other components excluding component 3.
I advised management to ensure that project activities are implemented as agreed
with the development partners to avoid suspension of funding to the project.
407
22.2 Monitoring and Evaluation of interventions by NAADS secretariat
NAADS is involved in implementation of strategic government interventions in the
agricultural sector for enhancement of household income. The interventions
include the distribution of farm inputs across the country. To assess the impact of
the intervention and to further focus government efforts on priority areas in the
sector, it is necessary to establish a strong and functioning monitoring and
evaluation function. However, it was noted that the existing monitoring and
evaluation function at NAADS is lacking in aspects such as;
(i) Beneficiaries are not identified and documented before procurement of inputs
which creates the risk of diversion of inputs.
(ii) There is no data base of farmers supported by NAADS to track their progress
and success of the interventions.
The absence of a strong monitoring and evaluation mechanism leads to ad-hoc
implementation of the interventions and this may lead to failure to achieve
intended objectives.
Management explained that NAADS Secretariat provided technology inputs to
beneficiaries to address strategic and special demands usually identified at the top
political and policy leadership level. Management further explained that the
support would therefore normally be provided to clearly defined target groups
known well before procurement and initiation and approval of the procurements of
technology inputs for such support would require evidence of the source of
demand.
I advised management to establish a well-functioning monitoring and evaluation
department to measure performance of government‟s interventions. Further a
well-documented process should be developed to identify beneficiaries prior to
distribution of farm inputs.
22.3 Procurement Management
408
In implementing ATAAS project and other programs, NAADS makes various
procurements for supplies and services. However, my review of procurement
procedures and controls revealed the following anomalies;
(i) The procurement plan was not approved by the World Bank contrary to the
provisions of the financing agreement.
(ii) The department does not maintain procurement complaints register where
bidders can register their complaints.
(iii) There is no procurement notice board for publicity.
Failure to ensure approval of the procurement plan by the participating partners
implies non-compliance with the financing agreement provisions which may lead
to the partners‟ refusal of funding procurements under the ATAAS project. Further,
absence of a notice board does not only compromise transparency in the
procurement process but also violates established standard government
procurement procedures.
In these circumstances, procurements are not done in accordance with approved
plan which impacts adversely on the implementation of various activities.
Management explained that the procurement plan was approved by the Board and
submitted to the World Bank which never responded. Management further
informed me that indeed they don‟t have a specific procurement notice Board but
are using a general notice board at NAADS Secretariat on the Ground floor at the
reception area and will put in place a specific notice board for procurement
I advised management to ensure that a procurement plan is prepared and
approved in accordance with the Project financing agreement provisions. Further,
a procurement notice board and a complaints register should be put in place to
ensure transparency and accountability within the process of procurement.
22.4 Framework contracts
A framework contract with an Estates firm was signed on 20th February 2014 to
supply 80 motorised Knapsack Sprayers at a price of UGX 1,850,000 per sprayer.
409
However, the call-off order made to the company on 23rd March 2014 was for 250
units. The additional 170units of motorised Knapsack Sprayers were in excess of
the contracted quantity of 80 units and therefore supplied without being subjected
to the procurement rules and regulations.
Management explained that this was due to the tremendous increased demand for
motorised Knapsack Sprayers following a successful demonstration stage of the
efficient technology in the control of pests and diseases of fruit trees crops notably
citrus, mangoes and coffee. As such, more of the knapsacks were urgently
required.
I advised management to ensure full compliance with procurement rules and
regulations to obtain value for money at competitive prices.
22.5 Distribution of farm inputs
During the year, the secretariat incurred UGX 3,953,424,825 on the purchase and
distribution of inputs to farmers that was not supported by lists of beneficiaries or
acknowledgement by the beneficiaries. Further still the distribution of the inputs is
not properly planned because the procurement of the inputs was done before
determination of the beneficiaries.
As a consequence the expenditure on farm inputs was not adequately supported
and there is a risk that some of the inputs did not reach the targeted beneficiaries
implying that the intervention may not achieve the intended objectives.
Although Management explained that all support documents required for payment
as per the financial procedures were attached to the payment vouchers and were
availed and reviewed during the audit process, I was not availed with the required
documentation.
I advised management to properly plan the distribution of the farm inputs by
inspecting the intended beneficiaries to confirm their requirements and readiness
before procurement of inputs is done. Further, management should ensure that
410
deliveries are monitored, properly documented and the beneficiaries should
acknowledge receipt of the inputs which acknowledgement should be used to
support the payment.
22.6 Tea Intervention Project
Expenditure amounting to UGX 18,555,353,908 was incurred on the purchase and
distribution of 38,168,367 tea seedlings mainly in the Kigezi region. In the course
of the audit i noted irregularities in the procurement, distribution, delivery and
payment for the tea seedlings as elaborated below;
(i) Suppliers of Tea seedlings
It was observed that contracts for the supply of tea seedlings were made after
supplies had taken place. This was contrary to the established government
procurement laws and regulations which require contracts to be signed after a due
procurement process.
Management explained that this was an innovation after failing with the
conventional procurement process which had revealed that nearly 60% of the
seedlings were lost mainly due to mismatch in funds availability, completion of the
procurement process and the agricultural/growing season and as a result of the
delay most beneficiary farmers would abandon the tea on road sides thus
negating the tea intervention efforts and wastage of funds. As a remedial
measure, the District Authorities together with Kinkizi Development Company who
are implementers of the project devised an innovative approach –the “garden
store approach”. Under this approach farmers who wish to plant tea in a given
season do receive supplies directly from the supplier before completion of the
procurement process and it was found to reduce the mortality rate of the tea
plantlets from nearly 60% to 10% with adequate measures in-built in the
approach to mitigate against risk of paying for undelivered supplies.
I advised management to adhere to the procurement regulations.
(ii) Lead agencies
411
The tea intervention in Kigezi area is implemented in collaboration with three lead
agencies. These companies signed Memorandum Understanding (MOUs) with
NAADS to provide services such as mobilizing farmers provide market outlets,
training and field extension services, identify nursery operators, transport and
distribution of plantlets and to facilitate farmers to form cooperatives.
The initial MOUs signed in April 2013 did not provide any payment basis to the
lead agency. Subsequently, an addendum was signed in April 2014 providing a
30% payment to the lead agency on the value of tea seedlings procured and
planted.
During the year payments amounting to UGX 3,659,524,377 were made to the
project lead agencies. Issues of concern with this arrangement are;
The MOU does not clearly justify the 30% payment of the value of tea
plantlets to the lead agency.
Payments to the lead agency are not supported by evidence of extension
services provided.
Management explained that the lead agency‟s responsibilities are stipulated in the
Memorandum of understanding and payment is effected upon meeting the
conditions there in and the lead agency provides periodic reports on activities
carried out on basis of which payments are effected. I advised management to
document activities undertaken to enable proper justification of the payments.
(iii) Distribution/delivery of tea seedlings to farmers
A field inspection was conducted to confirm existence of tea seedlings distributed.
Four (4) farms were inspected and it was noted for the selected sample that tea
was planted on farms but we were not provided with acreage planted except for
one farm. Generally tea seedlings deliveries to the farms as recorded in the
payment records do not appear to match farm acreage planted. For the farm
where acreage was provided, there was a big discrepancy between the tea
seedlings recorded as delivered and the tea plants that can be accommodated on
the farm. The specific cases are noted below;
412
A farm for a religious parish
The tea garden was established in March 2012 and has received tea seedlings
from NAADS from start to date. I requested for information on tea seedlings
supplied for the years 2012 and 2013 but this was not availed. For the year 2014
deliveries of 1,836,000 in May 2014 were noted. We were informed at the time of
the audit (11/12/2014) by the farm manager that in September 2014, additional
1,460,000 tea seedlings were delivered to the farm. There was no information
availed on the garden acreage.
An individual‟s Farm
The farm is located in Busengo Parish Nyarubuye Sub-county Kisoro. Acreage
planted is unknown. Planting of tea in the garden started in March 2012. I was
informed that the farm received seedlings in the subsequent tea seasons of
September12, March 2013, September 2013, March 2014 and September 2014.
In May 2014, the farm received 360,000 tea seedlings. Information on tea
seedlings delivered in the other seasons was not availed.
A Farm for Community Based Organisation
The farm is located in Rubuguri and Ntenko parish in Kisoro district. It is adjacent
to Bwindi National park. Farming commenced in 2012 with an initial delivery of
650,000 tea seedlings supplied. I was informed by the chairman of the community
that these seeds were not planted and dried up on the road side. The actual
acreage planted is unknown. A delivery of 1,793,793 tea seedlings was made to
the farm on 20/05/2014 and received by the chairman. The farm has also received
other tea seedlings over the years but information on these deliveries was not
availed.
An individual‟s Farm
The farm called green valley dairy farm is located in Nyamasizi Kabale district. The
total acreage of the farm was not availed. It is recorded that the farm received
3,006,640 tea seedlings on 02/04/2014. I was informed by the farm manager that
he had also received an additional 1,000,000 million tea seedlings in September
2014.
413
The procurement processes and procedures in the tea intervention project are not
transparent and contravene procurements rules and regulations. In absence of
clear acreage planted, it was not known how the supplies to particular farms are
determined and there is a risk that some of the recorded deliveries of tea plants
are not actually supplied to the farms/ gardens. Furthermore, I was not certain
that the payments to lead agencies were for actual services rendered.
Management admitted to the need to have records on acreage for tea planted but
observed that tea growing areas in Kigezi sub region require experts to be able to
determine contour acreage as opposed to horizontal acreage on which traditional
land measurement systems are based. As such management promised to engage
the services of an expert and aim to have the process completed by June 2016.
22.7 Commitments through local letters of credit at the year-end
Funds amounting to UGX 13,892,716,461 were transferred to Bank of Uganda as
commitments to open local letters of credit between 19th June and 27th June 2014.
Included in the funds transferred was UGX 137,551,648 as commission for the
letters of credit. It was further observed that 6 months later after the commitment
of the funds for the local purchases, UGX 6,977,959,526 remain unperformed local
letters of credit. This is made of mainly commitment to the suppliers of citrus
seedlings amounting to UGX 3,640,513,000.
The transfer of these funds to Bank of Uganda in form of local letters of credit was
done to retain unutilised funds at the year end and the additional cost of UGX
137,551,648 in form of the local letters of credit commission paid to Bank of
Uganda was considered wasteful. Such avoidable costs reduce funds meant for
service delivery in this case farm input distribution.
Management explained that the funds transferred were for purposes of retaining
unutilised funds which were for the contracts signed at the end of the year but
had not yet performed due to the fact that the funds amounting to UGX. 30 billion
were received in April towards the closure of the financial year and the
414
procurement procedures had not been concluded. Management further explained
that some of the supplies depend on the season/weather and being a dry season,
it was advised that some supplies be put on hold for the dry season to end.
I advised management to implement planned activities timely to avoid such year –
end funds retention schemes that result in wastage of resources. Further,
management should not enter into contracts without forecasting and analysing
weather conditions.
22.8 Fixed Assets
It was observed that the fixed asset register is not properly maintained. It lacks
most of the details of assets stipulated in the treasury accounting instructions.
Some assets do not have date of purchase, cost and right location. Further, some
of the motorcycles recorded this year appear twice in the register and one UAA
338F sold during the year was still maintained in the asset register. It was also
noted that the organisation started a disposal process of eight vehicles in 2012
when bids were received but to date, only one vehicle had successfully been
disposed off with the rest still parked at Ministry of Agriculture Offices.
The absence of a comprehensive, accurate and up to date Assets Register implies
that there is a risk that asset losses and misuse may not easily be detected.
Further, failure to timely dispose of assets further diminishes the realisable
amount from the assets because of the continuous waste of these assets that
reduces their value.
Management explained that although some assets in the register lack details,
efforts had been made in subsequent verifications to ensure that gaps of that
nature and others are filled. Management further explained that during their
quarterly financial back stopping to districts, reviewing the maintenance and
updating of asset register of NAADS assets is always done.
I advised management to ensure that there is an updated asset register showing
all details as per the Treasury Accounting instructions.
415
22.9 Unaccounted for funds
In the course of the audit I noted the following unaccounted for funds amounting
to UGX 499,008,800.
s/n Description Amount Remarks
1 Advance to PMA 352,000,000 Unaccounted for six months
after advance
Advance to Buginyanya
Zardi
147,008,800 Training workshops for 44
SNCs and 88 AASPs from
Mbale and Sironko Districts
at a cost of UGX.
29,040,000.
Payment to service providers
totalling UGX.17,528,800
paid out on 30th June 2014.
There are no lists of
workshop participants.
Missing payment details
amounting to
UGX.59,749,000 payment
references 395327,477805
and 477814.
Excessive cash drawn on
cheque no 477816
amounting to UGX
40,691,000 for joint training
Workshop with NARO.
Accountability not sufficiently
supported.
In absence of support documents on payments I was unable to confirm that the
funds were used for intended purposes.
416
Management explained that it was following up the above accountabilities and
failure to obtain satisfactory accountability would result into instituting recovery
measures.
I advised Management to expeditiously follow up the matter and institute recovery
measures from responsible officers where misuse is confirmed.
22.10 Summary issues from inspection of Districts and sub-counties
A review was carried on the programmes system of accounting and record keeping
including implementation of programme activities. The review was undertaken in
761 sub counties/town councils in the 112 districts spread across the country and
the following matters were observed. Details of the matters are attached in the
management letters appendix to this report.
(a) Unaccounted for Funds – UGX 4,007,686,846
These are funds for which we were not availed accountability documents by the
accounting officers. It includes expenditure for sub counties/town councils which
did not avail their books for audit, missing payment vouchers and supporting
documents and unbanked co-funding receipts. Further details are included in the
District/sub county management letters.
(b) Ineligible Expenditure – UGX 47,296,801
It was observed that some districts/sub counties incurred ineligible expenditure
under the ATAAS project by spending outside the approved annual budget or by
failing to comply with ATAAS project procurement procedures. Further details are
included in the respective district/sub county management letter.
(c) Un-remitted Statutory Deductions – UGX 179,906,634
In almost all the districts/sub counties audited, it was noted that withholding tax,
PAYE and NSSF were either not deducted or where deducted, remittance to URA
and NSSF was usually beyond the stipulated time.
(d) Record Keeping
417
I noted instances where the sub counties and districts financial reports amounts
differed from the amounts in the underlying records, the cash books and payment
vouchers implying that these reports are not derived from underlying records.
These are noted in the respective district and sub county management letters.
(e) Fixed assets and financial records
I noted that the fixed assets of NAADS were not properly handed over for safe
custody to the Chief Administrative Officers as per instructions during the
transition period. NAADS‟ Motor vehicles and motorcycles in many districts and sub
counties continued to be used in activities unrelated to NAADS programme. Some
of the former NAADS coordinators were still in possession of financial records like
receipt books, cash books and payment vouchers in their homes at the time of the
audit.
(f) Project implementation Manual (PIM)
Many of the districts and sub counties audited had diverted from the PIM. For
instance the food security component was not fully supported. Funds meant for
this component were in most cases diverted to market oriented component
without approval. More still, the top ceiling of the market oriented farmers support
of UGX.750,000 had been overridden thus supporting fewer farmers than planned.
I advised management to make a follow up on the above matters.
22.11 VEGETABLE OIL DEVELOPMENT PROJECT
(a) Compliance with financing agreement provisions and GOU
financial regulations
A review was carried out on the project compliance with the loan agreement
provisions and GoU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and applied
GoU regulations except in the following matters:
i) Under absorption release of funds
418
During the year under review, a total of UGX.12,477,320,546 out of
UGX.35,215,199,674 budgeted for the year was not released to the Project.
UGX12.3bn of the unreleased funds was meant to have been released by the
IFAD. However, it was noted that out of the released funds, UGX.6,240,584,580
remained unutilised at the end of the year. The under absorption capacity of the
available funds translates into underperformance for year. As a result, the
following activities were not implemented as planned:
Delayed delivery of 2 station wagons and motor cycles;
Delayed construction of a fertilizer store in Kalangala and
Uncompleted Environmental impact assessment that delayed trainings and
workshops.
The Accounting Officer explained that the under performance of the work plan was
a result of delayed procurement process and failure to conclude the MoUs with the
implementing districts.
I advised management to expedite the pending processes and have the activities
implemented.
ii) Review of the Operations of KOPGT
Un-utilized recoveries from the farmers
Article 3 (h) of the agreement signed on the 28th April 2006 between OPUL and
KOPGT, provides that it is the Trustee‟s obligation to refund to the Government
the resources of the Scheme repaid by the smallholders and out growers within
one year of receipt, or utilise such resources as may otherwise be agreed upon by
the Government, the Trustee and IFAD.
I noted that loan recoveries worth UGX.3,257,536,892 had accumulated on the
Loan Recovery Account and the Trustee declared the resources to Ministry of
Agriculture but no action has been taken on the utilisation of the funds. I
explained to management that this contravenes the agreement and denies
farmers and the Trustee in general a chance to grow further and enhance
achievement of the project objectives.
419
Management explained that GOU and IFAD agreed under Schedule 3 of the
Financing Agreement for the second phase of VODP to have the repayments made
by KOPGT on Bugala Island re-cycled to finance loans for new smallholder oil palm
growers in Kalangala and other areas during the second phase of the project.
Also during the Mid Term Review (MTR), GOU and IFAD agreed that the
recoveries be utilized to finance oil palm activities on the outlying islands and
Buvuma where activities are planned to start in early 2015.
Management actions on the matter are awaited.
Outstanding loans from KOPGT Small holders
At the reporting date, a total of UGX.33,728,757,674 had been disbursed as cash
and input loans to KOPGT farmers for oil palm activities. However, I noted that
UGX.3,257,536,892 only has been recovered from the farmers as loan repayments
to-date leaving the balance of UGX.30,491,220,782 yet to be recovered. I
explained to management that the recovery rate was slow.
Management explained that the loans for oil palm cultivation by smallholder
farmers are supposed to be fully recovered 15 years after planting according to
the oil palm model. Since Oil palm planting in Kalangala started in 2006, the last
loans are anticipated to be fully recovered in 2030. The repayment schedule was
proposed to enable farmers have a reasonable take-home income and also enable
the farmer invest in maintaining the oil palm garden.
I advised management to come up with a payback schedule indicating how much
has been recovered and what is anticipated to be recovered over the remaining
period. This will enable me assess the performance of the loan portfolio.
Untitled land
In 2006, the registered farmers agreed to purchase a plot of land on which the
KOPGT secretariat was to be constructed. The farmers contributed UGX.50,000
each collecting a total of UGX.24,000,000 that was used specifically to buy land in
Kalangala Town Council in 2007. However, as at the time of reporting, I noted
that management had not yet acquired the land title. I also noted that there are
some capital developments currently undergoing on the land. The Secretariat had
420
invested UGX.182,283,547 to construct an official building and UGX.1.6bn to
construct fertilizer store. I explained to management that this is risky due to the
uncertainty of the legal rights on the same land.
Management explained that KOPGT Management submitted forms for land transfer
to Masaka Land Registry and the district is in the process of transferring the title
into the name of Kalangala Oil palm Growers Trust (KOPGT).
I advised management to expedite the process of securing the land tittle.
(b) General Standard of Accounting and Internal Control
A review of the system of accounting and internal control was carried out and in
all material respects, the internal control system and measures to ensure proper
accountability for the project funds put in place by management was satisfactory.
(c) Status of Project Implementation
A review of the status of project implementation revealed the following;
i) Inspection of Oil seeds component hubs
As part of the audit, inspections of the Oil Seeds Component hubs was carried out
and below are the findings:
a) Staffing at Mbale Hub
A review of the operations at Mbale Hub that comprises of 20 districts in Eastern
Uganda indicated that it is currently managed by only one staff yet the hub is too
big. I explained to management that farmers may not get the guidance they need
and in time.
Management explained that the project design document did not provide for extra
staff at hub level however, the concern of low levels of staffing was noted and
raised with IFAD and accordingly, the September 2014 IFAD Support Mission Aide
Memoire recommended recruitment of a hub driver and another staff to manage
the regional office. Further, the Mid Term Review has recommended another
421
private service provider for the hub in addition to the two that are already on
ground and it is anticipated that this will enable the farmers to access extension
services they need.
I advised management to expedite the recruitment process.
b) Inspection of oil palm component - Buvuma Palm Oil Project
The Oil Palm Component of the project covers the districts of Kalangala and
Buvuma.
(i) Acquisition and hand over of 4,000 hectares to BIDCO (U) Ltd
(BUL)
According to VODP 2 work plan and budget for the financial year under review,
the project was to consolidate all the acquired land, identify more, survey, process
and hand over 4,000 hectares of this land to BUL for nucleus estate out of the
total planned and agreeable 6,500 hectares of land. I noted that the project has
not handed over the planned hectares of land. This has made the hand over
difficult since. I explained to management that this is likely to affect the progress
of the project.
Management responded that there was delay in land acquisition but the required
6,500ha have now been acquired, which is the amount required by BIDCO. The
delays were a result of unclear land titles, squatters, lengthy valuation, hostile
tenants and conflicts in ownership which are being resolved systematically.
I advised management to expedite the process and have the handover concluded.
(ii) Establishment of Buvuma Oil Palm Growers Trust
According to the VODP 2 work plan and budget for the financial year under
review, the project was supposed to have started the establishment of Buvuma Oil
Palm Growers Trust and the recruitment process of the skeleton staff should have
taken off. However at the time of inspection, it was noted that no such Trust had
been established. I explained to management that failure to establish the Trust as
422
agreed makes it difficult for the project to set off, dragging behind all the planned
activities for implementation.
The Accounting Officer explained that according to the Financing Agreement, the
project can only establish Buvuma Oil Palm Growers Trust after BIDCO starts
implementation of nucleus activities in Buvuma. It was indicated that currently,
the project is working with the Buvuma District Local Government in handling oil
palm activities on the Island with emphasis on land acquisition.
I advised management to address all the issues hindering progress of the project
activities for successful implementation of planned activities.
23.0 NATIONAL AGRICULTURAL RESEARCH ORGANISATION (NARO)
23.1 Mischarge of expenditure-UGX.206,704,980
The Parliament of Uganda appropriates funds in accordance with the needs of the
country and this appropriation is implemented through the budget in which funds
are tagged to particular activities and outputs using account codes and MTEF
codes. During examination, it was noted that expenditure worth UGX.206,704,980
was charged on wrong expenditure codes contrary to GOU chart of accounts.
Mischarge leads to misallocation and diversion of resources to non-planned
activities contrary to appropriation by Parliament. The practice also leads to
misrepresentation of facts in the financial statements and undermines the
importance of the budgeting process.
The Accounting Officer explained that they have on several occasions written to
the PS/ST and the Accountant General seeking for a research code to over-come
the budgeting anomaly without any response. The research activities include;
client priority setting and planning, experimental site visits and maintenance,
surveys and other data collection activities; which require much of the budget and
the amount involved cannot be accommodated on the related codes like travel
inland because of restricted budget line allocations.
423
I urged the Accounting Officer to continue pursuing the matter with the
Accountant General to have it resolved.
23.2 Budget Performance
a) Under funded budget
Management budgeted to receive UGX.41,867,739,709 in order to carry out its
activities for the financial year under review. However, only UGX.35,027,197,017
(79.9%) was received leaving a balance of UGX.6,840,542,692 un released as
summarized below:
Funding category Budgeted Released variance
Recurrent releases 27,737,246,147 27,614,680,851 122,565,296
Development releases 6,130,493,562 4,597,870,172 1,532,623,390
Gross tax 8,000,000,000 2,814,645,994 5,185,354,006
Total transfer from
Govt.
41,867,739,709 35,027,197,017 6,840,542,692
The shortfall in releases affected the research works and a number of activities.
These activities included; data collection on farm performance trials, data
collection on pests & diseases, training of rural artisans, assessment of economic
impact of management of fruit flies, nursery activities & field trials monitoring,
data collection on plant bio diversity, monitoring of project activities, field activity
on vector specimens, identification of termite specimens, monitoring, purification
of cultures experiments and data collection on plant bio diversity purification of
cultures and experiments.
The Accounting Officer explained that the bulk of the unreleased funds relate to
gross tax that could not be utilised because of the length of the procurement
process. He further explained that there was underfunding from Government as
the Organization did not receive its 4th quarter release.
424
I advised management to pursue the matter of funding with MoFPED with a view
of ensuring that in future all the resources for all the planned activities are
accordingly released to enable implementation.
b) Un-collected NTR - UGX.2,734,758,542
NARO‟s approved NTR budget for year was UGX.5,815,021,500 but I noted that
UGX.3,080,262,958 was realised leaving UGX.2,734,758,542 un collected. This
translates into underperformance of 47% of the budgeted revenue collections.
Compared to the previous year, performance declined by UGX.298,081,719 (9%).
The declining performance could be attributed to poor collection strategies and or
weak revenue collection controls.
The Accounting Officer attributed the under collection to compensation from
UEDCL of over UGX.2bn for land occupied by electricity line sub-station at NARL-
Kawanda Institute which did not materialize due to land wrangles between NARO
and the veterans. However, the matter was reported to the courts of law under
suit no. 434/2014.
I advised management to follow up the matter with a view of having the
compensation settled.
23.3 Un recovered car loan-UGX.22,910,000
Sect. 16.2.3 of the NARO human resource manual requires NAROSEC and PARIs
management to recover any outstanding amount from its members by deducting
such amount from gratuity if it cannot be recovered from the salary. Besides,
according to condition b (5 & 6) of the car loan agreement, a staff is under
obligation to pay the loan whether he/she is in full employment with NARO or not.
However, I noted that NAROSEC terminated the services of its two staff after the
expiry of their employment contracts without recovering the outstanding loans.
The other staff is on a study leave whose loan is not being settled. Details in the
table below:
425
Name Designation Terms of service Outstanding
Loan
Last date of
recovery
Staff Principal
Research Officer
Quality
Assurance
Still employed by
NARO but on Study
Leave
6,910,000 30th June,2013
Former staff Senior
Procurement
Officer
Contract terminated
in June 2013
8,000,000 31st
October2013
Former staff Civil Engineer Contract terminated
in June 2013
8,000,000 30th June 2013
Total 22,910,000
I explained to management that failure to recover outstanding loans from the
former staff translates into financial loss to government.
The Accounting Officer explained that the matter of the affected former staff was
brought to the attention of the governing council and have written to them to
have the outstanding amounts settled. The staff on study leave promised to pay in
2 installments and so far US $ 1,200 has been recovered.
I urged management to pursue the affected staff and ensure that their
outstanding loans are recovered.
23.4 Internal Audit Function
a) Operations of Internal Audit
NARO has twenty (20) internal audit staffs and out of these; 4 are based at
Headquarter while the rest are based at the Institutes spread across the country.
During the audit, I noted that the Institutes of ABI –Arua and Mukono ZARDI did
not have internal auditors.
I explained to management that a review of the structure of operations of internal
audit needs to be carried out to ensure the available staff can offer services to the
426
Institutes. Strengthening the internal audit is very essential as it will empower the
unit to handle the ever growing responsibilities at all the Institutes country wide.
The Accounting Officer explained that the internal auditors for ABI and Mukono
ZARDIS resigned from NARO service and the process of replacing them was in
advanced stages. In the meantime, the internal audit staffs at NAROSEC were
reportedly providing internal audit services to these institutes.
I advised management to expedite the recruitment process with a view of
strengthening the internal audit department for effective service delivery.
b) Inadequate staffing –NARL –Kawanda
A review of the Institute‟s internal control environment showed that NARL has one
internal auditor responsible for all internal audit assignments including carrying out
verification of monthly reconciliation statements of over 65 bank accounts. I noted
that during the year, the auditor‟s key role at the institute was to carry out pre-
audits however, there were no internal audit reports, an indication that there was
limited review of the systems and processes at the Institute. I explained to
management that lack of a strong internal audit could result into non-detection of
errors and therefore misstatements of the financial statements.
The Accounting Officer explained that the recruiting process was on-going. I await
the outcome of management‟s commitment.
23.5 Audit Inspections
a) Continued illegal encroachment on MBAZARDI Land
I previously reported that an individual had encroached on MBAZARDI land.
During the year under review, management carried out eviction of some
encroachers on this land. However during inspection, I noted that more land is
being encroached on by the same person earlier evicted. An estimated 31.8 acres
had been encroached on by this person.
It was also noted during the eviction exercise that a staff of NARO was assaulted
by the same encroacher and the case is before the courts of law. However, after a
427
period of more than 5 months, the case has not been put to mention. The
organisation‟s land is at more risk of encroachment.
The Accounting Officer explained that the case is in court suit no. 070 of 2014. I
urged management to pursue the matter and strengthen measures against land
encroachers.
b) Rwebitaba ZARDI
a. Lack of official hand over report of properties
NAROSEC received land and other properties from Kabarole local Government.
Rwebitaba ZARDI then shifted to Kyembogo station as its administration centre.
However, I was not availed with the hand-over report/list of assets to NAROSEC
from Local Government for verification and the land title to confirm ownership.
Furthermore, I noted that the institute has not fenced off its boundaries putting
the assets at more risk as evidenced by a public road passing through the institute
as illustrated in the pictures below:
Office block without a gate/Fence
The public road that passes through the
compound.
I explained to management that this could cause thefts due to open access of the
facility.
The Accounting Officer explained that the hand over is being done in phases and
has not been completed, a complete report is expected after the exercise and will
be availed as soon as it is received.
428
I advised management to ensure that a proper hand over is done and also ensure
that the administration block is fenced off. Acquisition of ownership of the land
should be expedited.
b. Dilapidated properties
The institute buildings where the staffs are accommodated are roofed with
asbestos that was internationally condemned. Furthermore, I noted that some
structures (staff quarters) and a toilet in the compound were very old and
inhabitable and some blocks within the compound were not completed as shown
in the pictures below:
The building with asbestos sheets
One of the public toilets in the compound
Un completed block
Dilapidated structure at staff quarters
I explained to management that the poor state of structures affects the operations
of the institute and reflects a bad image of the organisation.
Management explained that NARO inherited the infrastructure from Kyembogo
Local Government and that some rehabilitations are being done gradually. Once
funds are available, the unroofed blocks will be roofed.
I advised management to plan and have the renovations completed. Meanwhile
the asbestos which is a health hazard to staff should be replaced.
c. Security at the station
429
It was noted that the security at the station is inadequate; there are four
contracted security guards of Reserve Protection Services (RPS) and one locally
employed. Two guards at night and others during the day. I noted that the two
guards deployed at night were not enough to provide the required protection for
the institutes assets and resources that are scattered on approximately 500 acre
piece of land.
Information gathered at the station indicated that the institute experienced thefts
of research materials in the cassava fields and fire out breaks by the outsiders
during the year but the guards could not do much to prevent such occurrences. I
explained to management that those were clear signals that the institute‟s security
is not enough hence putting the assets at high risk of theft and destruction.
Management explained that provision of security to such a wide area including
experimental gardens is a challenge. However costs of recruiting local based
guards to support those deployed by RPS were considered in the budget estimates
of 2015-2016.
I advised management to plan for adequate security and ensure the institute land
is fenced off.
c) MBAZARDI Land encroachment by a Company
Inspection of MBAZARDI land indicated that other encroachers have installed an
illegal structure and a container on the institute land but management has not
taken any action to have them evicted. Below is a picture of the illegal structures:
Discussion with management indicated that the case is now before the courts of
law.
430
Containers and a structure illegally erected on the institute land.
I further noted that there were a number of encroachers on the institute land
along Kasese road. These encroachers have started operating on the institute‟s
land, an indication that there are no strong safeguards set up by management to
stop them. There is a possibility that the entity land could all be grabbed in the
near future thereby affecting the research activities of the organisation.
I advised management to pursue the matter with relevant authorities and ensure
that the government land is recovered from the encroachers. Meanwhile, strong
measures should be put in place to counter any further encroachment.
d) Un compensated land - MBA ZARDI Institute
During the inspection, I noted that the current construction of Mbarara by–pass by
China Railway Seventh group (CRSG) contracted by UNRA affected the activities of
the Institute on approximately 22.670 acres of land on plot 4 & 4a along Kabale
road. It was evident that the water pipes had been destroyed, water troughs had
been affected, EAAPP cassava garden destroyed, trees for animal shades and
pasture for animals destroyed as indicated in the pictures below:
The by-pass that crosses the NARO land
Part of the cassava that remained
undestroyed
431
A review of correspondences available revealed that the Institute was to be
compensated for the development structures and crops destroyed to the tune of
UGX.1,836,545,630 broken down as below;
Item Valued Amount
Land 1,586,900,000
Development 5,786,200
Crops 4,310,000
Sub-total 1,596,996,200
Disturbance allowance 239,549,430
Total 1,836,545,630
However, at the time of reporting (December 2014), no compensation had been
received. I noted that there was lack of adequate follow up of this claim with the
relevant authorities.
The Accounting Officer explained that a follow up with UNRA to have the funds
paid has not yet yielded results. I advised management to pursue the matter
further and have the compensation resolved.
e) Coffee Research Centre (COREC)-Kituza
i) Outstanding fuel arrears-UGX.24m
A review of the institution‟s documents revealed that there were outstanding fuel
arrears worth UGX.24m to an oil company that were consumed during the year.
However, there was no documentation detailing the outstanding fuel bill. Only fuel
statements were availed for review but these lacked the purpose for which the fuel
was consumed. I explained to management that payment of such claims without
supporting documents could lead to misappropriation of funds.
The Accounting Officer explained that the bill was received after the financial year
and its accuracy was being assessed. I advised management to verify the claim
before settlement is made.
432
f) National Forestry Resources Research Institute (NAFORRI)
i) Use of the Guest House
Inspection of the Institute‟s Guest house was carried out as a follow up of the
issues raised in the previous audit. I noted that the 10 bed roomed Guest House
requires renovation as its roof top, some walls and parts of the floor had
developed cracks. In my previous report, I advised management to maintain the
building to avoid further deterioration however, no action has been taken since the
previous audit and the asset continues to deteriorate. This has affected the
collection of revenue to the Institute.
The Accounting Officer explained that NARO engineer was asked to inspect the
guest house and prepare technical reports and BOQs so that the estimates for
renovation are included in the 2015-2016 budget, however the process has
delayed.
I advised management to ensure that the repairs are carried out urgently and the
assets put to use.
ii) Destruction of property at Bulegeni Satellite Station
Bulegeni Satellite station was attacked by a riotous mob of local people on the 27th
February 2014. The Institute property was burnt to ashes that included buildings,
office property, dormitory property, livestock, and crops. It was also indicated that
the attackers stole UGX.1,500,000 (One million five hundred thousand shillings)
which was in the cash box. Two people were reported dead during the incident;
one a security guard hired from RPS to guard the Institute and another person
who had come to graze animals on the Institute land.
Furthermore, I noted that staffs who were residing at Bulegeni also lost their
property which included motor cycle, beddings, utensils, furniture, documents and
clothes. As at the time of inspection (August 2014), it was reported that
management was still compiling the list of the lost property. I noted that
management delayed to compile the list.
433
There was also no evidence that management has taken steps to have the lost
assets valued with a view of quantifying the loss for subsequent reporting to
appropriate authorities and financial statements. The Police report was also not
availed for review.
The Accounting Officer explained that the list of destroyed property was available
and that the government valuer would soon cost the property lost. It was further
explained that the case was in Mbale High court and that the satellite was
earmarked for renovation while Police is keeping guard of the property.
I advised management to quantify the loss in compliance with the regulations for
subsequent action and reporting.
23.6 EAST AFRICA AGRICULTURAL PRODUCTIVITY PROGRAM (EAAPP)
a. Compliance with financing agreement provisions and GOU
financial regulations
A review was carried out on the project compliance with the credit agreement
provisions and GOU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and applied
GoU regulations.
b. General Standard of Accounting and Internal Control
A review of the system of accounting and internal control was carried out and it
was noted that management had instituted controls and measures to ensure
proper accountability for the project resources except in the matter below;
i) Arbitrarily determined labour rates
It was noted that all the Institutes implementing EAAP Project activities do not
have uniform labour rates for similar activities. As a consequence supervisors
were paying differing rates for the same activity in the same period. Examination
of records/payments related to labour revealed that the rates were arbitrarily
determined or were dependent on the bargaining ability of the activity supervisor
434
and labourers. Absence of standard or uniform rates at the institutes may lead to
misuse of project funds. Besides, it makes it difficult to draw a realistic
comprehensive work-plan/budget for a year.
The Accounting Officer explained that a uniform rate policy is being formulated to
have this issue resolved.
I advised the Accounting Officer to expedite the process of formulating the policy
to avoid eventual consequences.
c. Status of Project Implementation
A review of the status of project implementation revealed the following matters;
i) Under absorption of funds
It was noted that the total project budget for the year was US $ 12,633,896
(32.8bn) against the total expenditure of US $ 9,007,795 (UGX.23.4bn). This
resulted into under absorption of US $ 3,626,101 (UGX.9,426,703,017)
representing 51% of the total receipts for the year of UGX.19,199,442,787. As a
result, some of the project activities were partially implemented at the Institutes
as summarized below;
Agency Budget ($) Actual
Expenditure
($)
Variance
($)
% Of
Absor
ption
Pending/Uncompl
eted Activity
NACRRI
CASSAVA
4,905,304 4,078,723.89 826,580 83 Delayed civil works
on office block
construction.
NACRRI
RICE
329,650 312,963.29 16,687 95 Delayed construction
works & Rice
research initiatives
BUGI ZARDI
WHEAT
380,416 235,633.83 144,782 62 Supply of tractors &
implements
NALIRRI 783,930 390,681.76 393,248 50 Installation of
435
Agency Budget ($) Actual
Expenditure
($)
Variance
($)
% Of
Absor
ption
Pending/Uncompl
eted Activity
DAIRY
RESEARCH
livestock unit, water
reservoir.
NARL VAC 767,340 641,370.11 125,970 84 Rehabilitation of
food nutritional lab.
NAGRIC &
DB
1,760,561 1,360,704.49 399,857 77 Embryo transfer lab
nearing completion
and installation of
equipment.
MAAIF
DAPM
251,327 76,648.11 174,679 30 Supply of office
consumables,
support Research on
rice varieties.
PCU 1,006,000 977,482.55 28,517 97 Capacity building in
Procurement.
In view of the expected project closing date of 30th June 2015, I explained to
management that the project is behind schedule which is likely to cause
unnecessary project extension costs. Besides, failure to absorb the available
project funds translates into under-performance that may lead to failure to achieve
the project intended objectives in the scheduled time frame which could affect
agricultural development in the country.
The Accounting Officer explained that the cause of this under absorption arose
from delayed procurements due to the rigorous procurement procedures involved.
However, a no cost project extension of six months has been applied and it is
anticipated that the pending activities will be finalised.
I advised the Accounting officer to ensure all the planned activities are
accomplished as scheduled.
436
23.7 AGRICULTURAL TECHNOLOGY AND AGRIBUSINESS ADVISORY
SERVICES (ATAAS)
(a) Compliance with financing agreement provisions and GOU
financial regulations
A review was carried out on the project compliance with the credit agreement
provisions and GOU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and
applicable GOU regulations except in the following matters:
i) Mischarge of expenditure
A review of the project expenditures for the year revealed that expenditure to the
tune of UGX.215,925,820 was wrongly charged on budget lines to fund activities
that were not meant to be paid from the affected budget lines. The practice
resulted into misrepresentation of expenditure balances in the financial statements
and a diversion of project funds from the intended activities.
The Accounting Officer explained that since 2012, management has been
requesting for a research code from Treasury to take care of all the research
activities that are provided for in the Project Implementation Manual (PIM) and
not appropriately aligned to the GOU chart of accounts but this request has not
been fruitful.
I advised management to continue following up the matter with the Accountant
General with a view of obtaining research code.
ii) Un-realized GOU Counter-Part funding
A review of the project agreement indicated that out of the total project cost of US
$ 665.5 million, GOU was supposed to finance the major share of the project costs
of US $ 497.3M (US $ 166M applicable to NARO) over a 5 year project period from
22nd June 2010 to 30th June 2015. However, I noted that since project inception to
date, there has not been any contribution from GoU to the project. This
contravenes the signed agreement and fulfillment of obligations. I explained to
management that non fulfillment of the funding obligations affects the
437
implementation of the planned activities and the attainment of the overall project
objectives.
The Accounting Officer expressed commitment to continue in dialogue with the
responsible authorities to have the funds released.
The outcome of the above commitment is awaited.
(b) General Standard of Accounting and Internal Control
A review of the system of accounting and internal control was carried out and in
all material respects, the internal control system and measures to ensure proper
accountability for the project funds put in place by management was satisfactory
except for the following matter:
i) Delayed delivery of Project Vehicles
A motor company was awarded the contract to supply 37 vehicles worth
$1,109,593 in January 2013. However, as at the time of reporting (December,
2014) only 20 units had been delivered leaving a balance of 17 units yet to be
delivered. Delay in delivery has exceeded the delivery deadline of 12 weeks from
contract date as required. There was no evidence that management had started
charging liquidated damages as required. I explained to management that Failure
to charge the liquidated damages amounts to non-adherence to procurement
procedures and may lead to loss of revenue.
The Accounting officer explained that the delay was caused by the late release of
funds to cater for taxes for the 17 pickups. However, the taxes have since been
paid and the registration process is ongoing.
I advised management to expedite the registration process and have the vehicles
delivered.
(c) Status of Project Implementation
A review of the status of project implementation revealed the following:
i) Project Socio – economic impact assessment of Research
438
The mandate of NARO is to carry out research and come up with improved
varieties and disseminate the technologies by way of offering demonstration and
advisory services to the farmers, carry out multiplication and distribution of seeds,
implements and others. However, I noted that the socio-economic impact of
research output on the stake holders especially farmers has not been evaluated
and reported on so that it is shared or communicated to the stake holders.
NARO has not adequately documented and publicized the extent to which their
research success has greatly contributed to the improvement of the incomes and
life standards of the general population. There is a possibility that resources are
spent on activities that may not have generated socio-economic benefits to the
stakeholders and the citizens and therefore not realizing value for money benefits.
I advised management to ensure that a socio-economic impact assessment report
is prepared for the benefit of all stakeholders.
ii) Under absorption capacity
It was noted that the Project did not utilize funds worth UGX.26,287,401,192
during the year. This reflects a 71% increase in under-absorption capacity
compared to last year‟s unutilized funds of UGX.15,371,395,463. As a result, a
number of activities were partially implemented as summarized below:
Institute Annual
budget
Total release Budget
balance
%
performance
Uncompleted projects
NACRRI 1,807,190,971 1,516,355,457 290,835,514 84 The rehabilitation of storied
office block and screen house is
still on going. Supply of pick up
motor vehicle not done.
NAFIRRI 890,739,460 785,741,351 104,998,109 88 Staffing gaps still exist. Only 10
technicians available.
NAFORRI 839,671,451 649,780,150 189,891,301 77 The specialized machinery &
equipment for research
activities were not acquired.
The digital and bench meter
was not procured.
NaSARRI 952,481,291 798,733,427 153,747,864 84 The specialized machinery &
equipment for research
439
Institute Annual
budget
Total release Budget
balance
%
performance
Uncompleted projects
activities were not acquired.
Supply of pick up motor vehicle
not done.
NARL 1,734,394,795 1,432,965,648 301,429,147 83 Infrastructure & equipment
were not procured and mobile
applications. Supply of pick up
motor vehicle not done.
ABI ZARDI 475,912,628 404,050,087 71,862,541 85 Construction of screen house.
Still on going
BULINDI 497,151,128 472,635,723 24,515,405 95 Construction of screen house
not completed yet.
NGETTA 523,274,128 427,023,208 96,250,920 82 Construction of screen house on
going. Supply of pick up motor
vehicle not done.
NABUIN 526,052,466 503,398,244 22,654,222 96 The rehabilitation of office block
Still on going.
MBARARA 463,346,128 455,183,515 8,162,613 98 Development of ICT
infrastructure and equipment
not yet fully done.
BUGINYANYA
465,985,628
368,822,170
97,163,458
79 Training and recruitment of
ICT specialists were not done
Construction of screen house
not yet done.
RWEBITABA
485,794,091
461,285,729
24,508,362
95 ICT infrastructure and
equipment not fully developed.
9,661,994,165 8,275,974,709 1,386,019,456
From the table, it is noted that most of the planned civil works involving
renovation of office blocks at all Institutes and building of laboratories were not
carried out during the year as planned. I explained to management that failure to
absorb the available funds may disrupt the achievement of the project objectives
in the scheduled time frame leading to unnecessary project extension costs.
The Accounting Officer explained that there were unnecessary delays in
procurement process but procurement contracts for civil works have now been
awarded.
440
I advised management to increase the supervisory role and ensure that the civil
works are concluded within the stipulated period.
iii) Delayed strengthening of Human Resource
Under this project sub component the targeted staff establishment was 995 where
830 has been filled and 165 is still vacant. Of the un filled positions, I noted that
out of the planned 268 scientists, 242 were filled leaving 26 un filled while out of
274 targeted staff technicians, 199 staff were filled leaving 75 gaps. I explained to
management that this affects research work, one of the core activities of the
project.
The Accounting Officer explained that for the last 2 years, NARO wage bill has not
been increased and this has had a direct effect on the staffing levels. This was
not in line with the plan which should have been fully actualized by July 2014.
I advised management to take up the matter with the responsible authorities and
ensure that the staff gaps are filled as planned.
441
ENERGY SECTOR
24.0 MINISTRY OF ENERGY AND MINERAL DEVELOPMENT
24.1 Mischarge of expenditure
Paragraph 400 (a) of the Treasury Accounting instructions (TAI), 2003, requires
that all Government transactions shall be recorded in the books of account
applying the Government of Uganda Chart of Accounts as prescribed by the
Accountant General. In addition, Accounting Officers shall ensure that all financial
transactions are properly coded.
Contrary to the above provision, the Ministry, charged UGX.3,038,506,327 on
expenditure codes other than those for which funds had been appropriated.
Mischarging expenditure is a sign of weaknesses in budgetary controls and leads
to misstatement of the financial statements.
Though the practice of mischarging expenditure is declining at the Ministry, further
budgetary discipline is required.
The Accounting Officer explained that additional measures will be put in place to
further streamline the budget implementation process so as to avoid the practice
of mischarging expenditure.
I have advised the Accounting Officer to strengthen supervision of the budget
implementation and where necessary, re-allocation warrants should be sought.
24.2 Non Compliance with the Provisions of the Mining Act
a) Unremitted Royalties
By law, mineral royalties collected by the Ministry are shared between the Central
Government (80%) through the UCF, and other stakeholders who include:
districts, urban councils and individual land owners where mining takes place
(20%) through Bank account No.000170148000002 in the Bank of Uganda.
442
It was noted that UGX.5,659,692,377 was collected as mineral royalties through
URA during financial year 2013/2014 but the 20% share was not distributed to the
other stakeholders. This could have had a negative effect on the implementation
of activities by district and urban councils whose budgets may have factored in the
anticipated royalties.
The Accounting Officer explained that the royalties are collected through URA
which is expected to transfer 80% and 20% of the collections from mineral
royalties to the UCF and; the mineral royalties Sharing Fund Account, respectively.
The latter portion, which was supposed to be distributed to the beneficiaries by
the Ministry was not received on the Fund account.
I advised the Accounting Officer to expedite the distribution of mineral royalties to
the bonafide beneficiaries to enable them execute their planned activities.
b) Failure to Collect Royalties and Surface Rentals from Former
Holders of Exploration Licenses
Section 105 of the Mining Act, 2003 states that, the assessed royalty on any
mineral shall be due within thirty days from the date of assessment, and delay in
payment shall attract an interest on the unpaid royalty at the rate of 2% per
annum above the commercial bank lending rate as established by the Bank of
Uganda.
Section 104 (1) of the same Act states that where the holder of a mineral right
fails to pay any royalty payable by him or her on or before the due date, the
Commissioner shall, by notice served on the holder, prohibit the holder from
disposing of any mineral obtained or mined by him or her from the mining area
concerned, or from any other mining area held by that holder, until all outstanding
royalties have been paid or until an arrangement has been made, acceptable to
the Commissioner, for the payment of the royalties, and the holder shall comply
with the notice.
443
It was however noted that 174 companies whose exploration licenses had expired
had arrears of royalties and surface rent amounting to UGX.850,246,000 not
collected by the Ministry. There was no evidence to show that the Ministry had
made any attempts to collect the debts. Failure to collect the outstanding fees may
result into a loss of revenue to the Government.
The Accounting Officer explained that collection of outstanding debts had not been
done, but the Ministry was planning to collect the debts in accordance with the
provisions of the Act.
I advised the Accounting Officer to take appropriate measures and collect the
outstanding debts, and in future, to ensure that all royalties and surface rent due
are collected in a timely manner.
c) Mining Lease Holders Failing to Submit Audited Financial
Statements
Section 50 (2) (a) and 2 (c) of the Mining Act, 2003 obligates the holder of a
mining lease to maintain and submit monthly to the Commissioner of the DGSM
complete and accurate records of operations relating to his/her lease including a
copy of his or her audited financial report showing the profits or loss for the
financial year, and the state of the financial affairs of the lease within 90 days of
the end of each financial year.
Contrary to the above provision, it was noted that the companies holding the
licences listed in the table below had not submitted the required records and
audited financial statements to the department for the past three years.
Mining Lease No. Compliance with section 50 (2) (a)
Compliance with section 50 (2) (c)
4651 Not Submitted Not Submitted
61 Not Submitted Not Submitted
127 Not Submitted Not Submitted
593 Not Submitted Not Submitted
594 Not Submitted Not Submitted
444
I
n
t
h
e absence of audited financial statements, Management had no information on the
profit or loss made by the lease holders, on which assessment for royalties
payable is based. There is a risk that essential data is deliberately withheld and
therefore the Ministry may not be able to make appropriate decisions regarding
such licences.
Management indicated that it had noted the anomaly and undertook to start
implementing the provisions of the Mining Act.
I advised the Accounting Officer to ensure that the companies submit the required
records and accounts for the DGCM to be able to assess the royalties payable.
24.3 Budget Performance
Out of the appropriated sum of UGX.1,305,566,104,201 the Ministry received only
UGX.189,656,857,225 resulting into a short fall of UGX.1,115,909,246,976 (85%),
as indicated in the table below;
Budget Revised Budget
(UGX)
Releases (UGX) %
Relea
s
e
Funds not released
(UGX)
% not
released
Recurrent 6,917,210,169 6,278,124,062 91% 639,086,107 11.6
702 Not Submitted Not Submitted
248 Not Submitted Not Submitted
762 Not Submitted Not Submitted
842 Not Submitted Not Submitted
4063 Not Submitted Not Submitted
4064 Not Submitted Not Submitted
4128 Not Submitted Not Submitted
4227 Not Submitted Not Submitted
4474 Not Submitted Not Submitted
4478 Not Submitted Not Submitted
4603 Not Submitted Not Submitted
1110 Not Submitted Not Submitted
445
Budget Revised Budget
(UGX)
Releases (UGX) %
Relea
s
e
Funds not released
(UGX)
% not
released Development 1,298,648,894,032 183,378,733,163 14% 1,115,270,160,869 90.4
Totals 1,305,566,104,201 189,656,857,225 15% 1,115,909,246,976 85%
A review of the implementation of Ministry projects indicated that due to the
insufficient release, a number of projects were not adequately funded, for
example, Karuma hydro power project received only 3% of the appropriated
amount, Mbarara- Nkenda/Tororo – Lira transmission line, Opuyo-Moroto
interconnection and Kampala – Entebbe Expansion projects received no funding at
all. Non-financing of the projects may lead to failure to fully implement them
within the planned timelines.
In his response, the Accounting Officer explained that the low budget performance
was due to less release of capital development funds which were intended for the
development of large hydropower projects such as Karuma and Isimba, whose
procurement processes had delayed to be completed. He further indicated that the
Ministry would continue to liaise with the Ministry of Finance, Planning and
Economic Development (MoFPED) to ensure that funds are released as planned.
I have advised the Accounting Officer to always implement all planned activities as
intended so as to achieve the set targets and objectives of the Ministry.
24.4 Delayed Compensation of Project Affected Persons for the Oil Refinery
Land
The Government of Uganda through MEMD is undertaking an Oil Refinery Project
in Kabaale, Buseruka Sub - County, Hoima District. Accordingly, a consultant was
engaged to provide consultancy services for the implementation of the
Resettlement Action Plan (RAP) for the project affected persons (PAP) living in the
affected area.
The Chief Government Valuer (CGV) approved the RAP report and cleared 2,708
PAPs for compensation at an estimated cost of UGX.70,915,217,225.12 to pave
way for the construction of the Refinery. However, by the end of the financial year
446
2013/14, only 1,836 (68%) PAPs had been compensated with a total of
UGX.32,208,516,443. I explained to the Accounting Officer that delayed
compensation of land owners may delay the commencement of project works.
The Accounting Officer attributed the delays to; PAPs delaying to sign off the
consent forms after valuation and verification, while others initially contested the
valuation rates, and; Delays in the process, for example procuring land to resettle
PAPs who opted for relocation, and renewal of the consultant‟s contract. He
however indicated that all the issues had been addressed and the compensation
exercise was moving on smoothly, and it was expected that the activity would be
concluded by the end of June, 2015.
I await the outcome of Management„s commitment in this regard.
24.5 Staff Matters
a) Failure to Appraise Staff Performance
Section A-m (14)(a) and (C) of the Public Service Standing Orders provides that a
staff performance appraisal report form shall be completed for each pensionable
and non-pensionable officer and a copy submitted to the Responsible Permanent
Secretary.
However, review of a sample of personnel files revealed that 12 officers had not
been appraised for at least two financial years. Failure to appraise staff hinders
assessment of their performance, identification of training gaps and
commendation of good performance, which ultimately renders staff development
difficult.
The Accounting Officer attributed the anomaly to the officers‟ reluctance to
complete the appraisal forms although they had been reminded in several
meetings. He indicated that the officers had been reminded about the same.
I advised the Accounting Officer to ensure that the human resource department
follows up with all the officers and ensure that they are appraised.
b) Irregular Extension of Probation Period
447
Section A –d (1), (12) and (13) of the Public Service Standing Orders provides
that, probationary appointment shall last six months, and may be extended only
once for a period not exceeding six months, upon the responsible officer making a
submission to the relevant Appointing Authority for the extension.
It was noted however that 15 staff had been on probation for more than a year
without evidence that their probationary period had been extended. A prolonged
probationary period has the effect of reducing staff morale, and may result into
inefficient performance by the affected staff.
The Accounting Officer attributed the delay to the officers, who had delayed to
complete their appraisal forms. He further explained that a number of submissions
had been made to the Public Service Commission (PSC) seeking confirmation of
officers who had completed their appraisal forms.
I advised Management to appraise all the staff whose probationary period had
expired and take appropriate action in accordance with the Standing Orders.
24.6 Management of Fixed Assets
a) Lack of a Comprehensive Fixed Assets Register
Paragraph 805 of the TAI requires all purchases of plant and tools to be charged
to a plant and tools item in the ledger and a fixed assets register to be maintained
to show the location of plant and tools, furniture and equipment. It was observed
however that the Ministry did not comply with this provision, as explained below:
A review of the Board of Survey Report for the MEMD for the financial year
2013/2014 revealed that although the asset register was in place, it did not
meet all the requirements of the TAI. Some items did not have cost prices and
values such as the buildings of the DGSM and the Petroleum Exploration and
Production Department (PEPD), and land in Moroto. The report further
revealed that the asset register did not indicate the location, cost and/or users
of various assets in the categories of computers, office equipment and
vehicles, but only indicated the department.
The inspection of the DGSM laboratory further revealed that a number of the
laboratory equipment were not included in the asset register and were not
448
part of the Board of Survey Report for the FY 2013/2014. Although an
inventory list of the equipment was provided, it was not possible to ascertain
the cost of the equipment as it was not indicated.
Without a complete asset register for all the Ministry assets and complete
information such as user and location, there is risk of loss of assets without a
trace.
The Accounting Officer indicated that the Ministry had started the process of up-
dating the assets register as required by the TAI. I await the outcome of
Management‟s action.
b) Property Without Certificates of Title
The Ministry lacked certificates of title to its property in Entebbe, plot 21-29
Johnstone road, on which the departments of PEPD and GSMD are housed and for
the land on which the regional offices in Gulu, Kabale, Tororo, Moroto,
Kabarole and Mbarara are situated.
Documents available at the Ministry show that there were individuals who claimed
to have titles of ownership, and a case of land grabbing involving plot 10a located
on Hill Road and plot M26 Kibira Road (Mirza Road) were reported to the Police.
In the absence of land titles, the Ministry faces the risk of losing the land.
Management explained that significant efforts had been made to secure the land
titles of Plot 21-29 Johnstone Road Entebbe, and a request was made to the
Commissioner Land Registration to cancel the forged titles for the pieces of land
that had been grabbed and issue titles to the Ministry.
I advised the Accounting Officer to expedite the process of obtaining the
certificates of ownership/ land titles for the land so as to avert the risk of losing
the land.
c) Assets Handed Over From Exploration Area 4B and 5
449
The provisions of the Production Sharing Agreements (PSAs) require that all
equipment and other assets, whether fixed or movable acquired and owned by the
licensee for use in petroleum operations shall become the property of the
Government upon ceasing operations.
Review of documents showed that in February 2013 and August 2013, two
companies, handed over assets worth USD.1,521,687, (NUL- USD.85,815 and DUL
– USD.1,432,869) to the Government. The following matters were noted;
a) Although the Ministry acknowledged receipt of the assets, the assets were not
added to the fixed assets register, and their physical location could not be
ascertained during the audit.
b) Three pick-up trucks (UAK 724C, UAK 772C and UAK 697C) and a motorcycle
(UDE 115H) handed over to the Government had not been registered with
Government number plates, rendering their ownership uncertain.
I informed Management that there is a risk of misappropriation of the assets.
The Accounting Officer explained that, the items in good condition were
distributed for use in the respective departments, while the obsolete ones were
boarded off and disposed of as per the PPDA procedures.
I advised Management to ensure that all the assets handed over are clearly
marked for identification, registration and entered into the assets register of the
Ministry.
24.7 Funds Not Accounted For
a) Allowances and Workshop Expenses
Paragraph 217 of the TAI requires advances to be accounted for without delay. It
was observed that UGX.98,566,501 paid to staff of the Ministry to undertake
official activities remained unaccounted for by the time of audit. In the absence of
the relevant accountability documents, it was not possible to confirm that the
funds were used for the intended purposes.
I advised the Accounting Officer to ensure that advances are accounted for by the
concerned staff.
450
b) Travel Abroad
UGX.24,323,000 was paid to facilitate officers to travel to Denver, USA to
participate in the Unconventional Resources Technology Conference. However the
expenditure was not adequately supported with invitation letters, back to office
reports and copies of boarding passes for passports.
In the absence of such documentation it was not possible to ascertain that the
trips were beneficial to the Ministry.
I advised the Accounting Officer to ensure that the funds are properly accounted
for.
24.8 ELECTRICITY SECTOR DEVELOPMENT PROJECT – MEMD
a) GoU Counterpart Funding
During the year under review, the Government of Uganda released
UGX.11,530,031,689 (USD.4,612,012.68) in respect of counterpart funding for the
project out of which UGX.11,420,000,000 was expended. Examination of the
expenditure records revealed the following matters;
UGX.7,523,718,204 was reflected on the Integrated Financial Management
System (IFMS) payments file as having been expended on the project
activities. The expenditure for the balance of UGX.3,896,281,796 could not be
traced to payments for the project. In the circumstances, the funds remain
unaccounted for.
Whereas management explained that the said funds were not expended
directly through IFMS but rather transferred to UETCL for implementation of
RAP activities, there was no documentary evidence to this effect.
In my report to parliament for the year ended 30th June 2013 I indicated that
UGX.5,133,052,162 was expended on non project activities and reported
project expenditure was overstated in this regard. No adjustment to the
financial statements has been made.
Additionally out of the UGX.7,523,718,204 spent directly by the Ministry,
UGX.1,650,707,968 was again spent on non project activities. Therefore,
451
cumulatively the project financial statements are misstated to the tune of
UGX.6,783,760,130.
The practice of expending project funds on non-qualifying activities amounts
to diversion of project funds and negatively impacts on the achievement of
the overall project objectives. In addition, the reported expenditure is
overstated in this regard as the diverted funds did not contribute to the
performance of the project.
The counterpart funds released by the Government of Uganda amounting to
UGX.11,530,031,689 (USD.4,612,012.68) for funding for the project activities
were not deposited on the project account. In the circumstances, the funds
are prone to being diverted to other activities and monitoring their utilization is
rendered difficult.
Management in response explained that Treasury had been requested to activate
the project account to facilitate deposit of funds but approval was not granted and
undertook to follow up the matter with Treasury.
I have advised management to;
account for the funds and in future ensure that funds meant for the project
are transferred to and expended through the project account,
restore the diverted funds to the Project Account for utilisation on planned
activities, and adjust the financial statements accordingly, and
ensure that all counterpart funds are deposited on the project account as
required under the project agreement.
b) Under absorption of funds
The project commenced in January 2012 and is expected to close in February
2017. It was noted that there is slow implementation of the project activities. For
example, while USD.614,150.26 remained unutilised during the previous financial
year and was available for utilisation during the current financial year on a number
of activities, it was noted that by 30th June, 2014, only USD.343,192.82 had been
absorbed, leaving a balance of USD.270,957.43. In the circumstances, there is a
452
risk that the overall project objectives may not be achieved. In addition,
management risks funding sanctions from the Development Partners.
Management explained that most of the project activities were at the procurement
stage with all Consultants already engaged to support the procurement of
contractors. Management anticipated that the absorption of the funds would
improve when the major activities of the project commence. I have advised
Management to strengthen its internal capacity to implement the project planned
activities and allow substantial disbursement of funds by the bank.
c) Manual Financial Management System
Section II (B)(4) of the Projects‟ financing Agreement states that the “Recipient
shall, not less than six (6) months after the effective date install or cause to be
installed within the Ministry a computerized accounting and financial management
system satisfactory to the Association”. However, it was noted that the accounts
department has continued to generate accounts manually using excel spread
sheets. I informed management that, this may lead to inaccuracies in financial
reporting.
Management undertook to seek approval from the World Bank to procure an
Accounting package with a view to improving the security and accuracy of the
accounting records. I await management‟s commitment in this regard.
d) Role of Internal Audit Function
According to the PAD, it is very important that internal audit unit conducts a risk
based audit on project internal controls periodically, such that appropriate
corrective actions are taken to address any weaknesses found. It was noted that
no transactional and systems audits had been conducted on the Project activities
by the internal audit. In the circumstances, there is a risk of ineffective internal
controls not being identified for corrective measures to be taken.
Management explained that the Internal Audit Department had been conducting
reviews of project operations and periodically advising management on measures
to improve project operations without formal documentation. However,
management undertook to advise the department to document their findings. I
453
have advised the project management to ensure that internal audits are carried
out and reports issued on a regular basis as required in the Project‟s financing
agreement.
24.9 MBARARA-NKENDA & TORORO-LIRA POWER TRANSMISSION LINES
PROJECT – 31ST DECEMBER 2012
a) Delays in acquisition of Rights of Way
It is a requirement under best practices that a Right of Way (ROW) is acquired
under the Resettlement Action plan (RAP) to allow implementation of works
without interferences.
It was however noted that works on a number of locations on the transmission
lines had not started at the time of audit due to delays in obtaining Rights of Way
from the Project Affected Persons. Delays in obtaining Rights of Way impact
negatively on the timely completion of the project.
Management acknowledged the delays which they attributed to delayed approval
of RAP reports by Chief Government Valuer (CGV), disputes with Landowners,
family disputes, absentee landlords, and speculation among landowners. They
further explained that all efforts were being made to address the causes of the
delays for instance through frequent follow-ups with the CGV to expedite the
process of approval.
I have advised the Project Management to devise means of coming to terms with
the project affected persons in order for them to give Rights of Way for the
transmission lines to be erected.
24.10 MBARARA-NKENDA & TORORO-LIRA POWER TRANSMISSION LINES
PROJECT – 31ST DECEMBER 2013
a) Delays in construction of PAP Houses
M/S Lamba Enterprises, the contractor who undertook the construction of houses
for the Project Affected Persons (PAP), failed to complete the construction works
due to financial problems. The last construction works were done in January 2013
454
and as of 31st December 2013, only 3 of the 50 planned houses had been
constructed.
Although management was in the process of procuring another firm to complete
the construction works, this had not been done by the time of the audit. Delays to
construct houses for the affected persons are likely to delay the completion of the
project. The project is also exposed to a risk of loss of the unrecovered money
advanced to the Contractor, (USD.15,193).
Management explained that a new contractor had been procured and a kick-off
meeting held. In addition, UETCL wrote to the PPDA to ban the previous
contractor for abandoning site. It was further stated that out of UGX.474,445,180
advanced to the previous contractor, the outstanding balance of UGX.41 million
was being pursued through legal mechanisms.
I advised the Project management to ensure that the new contractor mobilizes
and starts the construction works to enable completion of the project in time.
Meanwhile, I await the outcome of the legal proceedings aimed at recovering the
balance.
b) Delays in processing PAPs‟ Land Titles
As part of the requirements of the project resettlement and compensation
program, Project Affected Persons (PAP‟s) were required to deposit their land titles
with UETCL in order for the project to curve out land acquired for Transmission
Lines. Whereas the payments had been made to the PAPs, it was noted that most
of the land titles had not yet been returned to them at the time of the audit. In
the circumstances, disputes may arise with the PAP‟s leading to legal actions being
taken against the project.
Management explained that the process of land acquisition and transfers required
authentication, proof of ownership and the involvement of several stakeholders‟
right from the Parish Land Committees (PLCs) to the Land Offices. The team
further stated that UETCL was in possession of the said titles for mutation
purposes. The process of mutation & transfers was affected by the delays in the
land office.
455
I advised management to take up the matter with the relevant authorities and
Ministry of Lands with a view to expediting the transfers by the Lands Office.
24.11 INTERCONNECTION OF ELECTRICAL GRIDS OF NILE EQUATORIAL
LAKES COUNTRIES (NELSAP) UGANDA – 31ST DECEMBER, 2012
a) Review of formal Enterprise wide risk management policy,
procedure and plan
During the review of risk management policy and procedures, the following were
observed:
It is not extended to various projects implemented by UETCL
There is no formal reporting structure (Risk committee, Risk department)
whereby the risk related activities are executed by internal audit.
Management was advised to consider making the various projects implemented by
UETCL part of risk management policies and procedures.
Further management was advised to amend the policy and procedures such that
they include appropriate and regular reporting structures.
Management explained that the risk is done internally by the project managers
through the Head of Department who Reports to Management and Board on a
Quarterly basis.
b) Review of Audit Committee Charter:
It was observed that:
The Audit committee charter was not reviewed and formally approved by
audit committee since 2008, though charter requires review, revision and
approval every 3 years.
Management charter has not been reviewed and approved since 2008, though
charter requires review every 5 years.
456
Management explained that the management charter was not yet due for reivw by
the end of the financial year under audit. However, it was scheduled to be
reviewed after 2013.
Management was advised to thoroughly review, revise and approve the audit
committee charter in order to strengthen the monitoring controls required to
address various risks associated with current operations.
c) Delay in implementation of the Resettlement Action Plan (RAP)
In addition to the observation identified, it was also observed that the RAP which
was supposed to have been approved by January 2011, was not yet approved by
the end of 2011.
The delayed approval of the (RAP) within the timelines has subsequently lead to
the late implementation of the RAP.
Management explained that the RAP report approval is an external process
because the approval is vested in the office of the Chief Government Valuer (CGV)
in the Ministry of Lands. The CGV handles all infrastructure projects in the country
and the delays have been noted by various parties. However, the approval was
later achieved and the process of compensation is on-going and currently more
than 79% and 78% are compensated for Bujagali-Tororo and Mbarara-Mirama
respectively.
Management was advised to ensure that RAP is implemented in time as required
by the developments partner‟s guidelines.
d) Delay in handover of sites to the contractor
During the field visits and interviewing the contractors, it was observed that there
is significant delay in handing over the sites to contractors as a result of either
delay in approval of plans or settling the claims of PAP and RAP.
The compensation progress report as on December 31, 2012 is as under;
457
Compensation progress Percentage (%)
LOT A - Mbarara - Mirrama 49%
LOT B - Bujagali - Tororo 48%
Management explained that the delay to hand over sites is due to a number of
factors such as delays to approve the RAP report by CGV, disputes with
landowners, family disputes, processing delays, absente land lords, speculation
which leads to landowners selling to new persons leading to new claimants.
Management was advised to expedite the RAP implementation.
e) Inappropriate handling of source documents
During the review of expenses, it observed that;
i. PAP Compensations
It was noted from the sample of PAP files for verification, many PAP files were
misplaced/disorganized and were not availed in time.
Management explained that it is important to note that the Audit exercise
coincided with an on-going exercise to digitise the RAP processes and records into
the Way Leaves Information Management System. The Exercise required files to
be assembled to the scanning teams at different locations, (Jinja, Lugogo and
Hannington) therefore their timely retrieval when instantly required posed a
challenge.
Management further explained that the process of Land Acquisition and transfers
is not instantaneous. The process requires Authentication, proof of ownership and
the involvement of several stakeholders right from the PLCs to the Land Offices.
Most of the paid land is customary owned and therefore the process of transfer is
handled at a later stage as long as clearance for construction of the transmission
line is achieved. Registration of transfer forms is done after the mutation process
has been completed.
Management was therefore advised to develop a strong control over maintenance
and safeguarding the physical files that is periodical physical verification of number
458
files and accurate records for movements in files.
i. Lack of transfer of ownership to of NELSAP acquired land
From the reviewed samples, it was noted that;
a) PAP land transfer forms were not signed by appropriate authority of UETCL,
yet payments were made in full.
b) PAP land transfer forms have not been registered with land office.
Both the above are contrary to the provision of the Project Implementation
manual, where the land titles are supposed to be obtained before full payment to
the PAP.
Management explained that approval is given to the professional staff whose CVs
are documented in the Bid of the Lead consultant. These are evaluated and
approved accordingly. However, the mentioned staff belonged to a sub consultant
engaged by the main consultant as clerk of works, although they are engineers.
Management was advised to ensure that the process of transfer of title of land into
UETCL names is expedited.
Further management was also advised to keep in mind the disbursement process;
which should be in line with project implementation manual.
Further still it was noted that non compliance with the conditions stated in the
manual, may create a future financial loss to the NELSAP.
ii. Lack of approval of key field engineers
We have not received the evidence of below missing approval for change of
professional field engineers:
Missing documented apporvals Consultant
Edward Byaruhanga AECOM/ RSW
Paul Kasozi AECOM/ RSW
459
Management was advised to make sure that any change in approved staff must be
approved by a consultant.
iii. Project fixed assets monitoring:
It was noted that the projects fixed assets are were not engraved/tagged, labeled
with NELSAP project identification codes and there was no evidence of regular
verifications.
Management explained that the UETCL assets are engraved and managed through
the main Corporate Assets Management arm. However, improvements to add
inscriptions to identify project assets will be implemented.
Management was advised that project assets be tagged/labeled with NELSAP
identification codes and periodic counts should be performed and reviewed for all
assets, with count results reconciled to the fixed asset register by individuals.
iv. Non compliances to withholding tax provisions
As per Section 119 of the Income Tax Act Cap 340, UETCL is liable to deduct
withholding tax @ 15% on each payment made to any resident.
However, UETCL did not remit the deducted WHT @ 15% on payments made to
RSW International (AECOM) to URA by the time of this audit.
Management explained that deduction of WHT for RSW International (Acecom) is
provided for but awaits cash release from the same treasury (MoFPED) so that it
can be paid to URA, the collecting arm of the same Treasury.
Management further explained that for all donor based payments, the taxes are
part of counterpart funding and therefore a GoU obligation.
Management was advised that non-deducted WHT from previous payments should
be deducted from subsequent payments and paid to URA at the earliest. Moreover
in future, it should be fully complaint to the provisions of the income tax act.
24.12 INTERCONNECTION OF ELECTRICAL GRIDS OF NILE EQUATORIAL
LAKES COUNTRIES (NELSAP) UGANDA – 31ST DECEMBER, 2012
460
a) Review of formal Enterprise wide risk management policy,
procedure and plan
During the review of risk management policy and procedures, the following were
observed:
It is not extended to various projects implemented by UETCL
There is no formal reporting structure (Risk committee, Risk department)
whereby the risk related activities are executed by internal audit.
Management explained that risk management in projects is assessed during
feasibility study as well as Environment Assessment/Resettlement Action Plan
(RAP) preparation. In addition, the risks are identified and assessed during the
preparation of the Project Implementation Manual (PIM).
Management explained that the risk is done internally by the project managers
through the Head of Department who Reports to Management and Board on a
Quarterly basis.
Management was advised to consider making the various projects implemented by
UETCL part of risk management policies and procedures.
Further management was advised to amend the policy and procedures such that
they include appropriate and regular reporting structures.
b) Review of Audit Committee Charter:
It was observed that:
The Audit committee charter was not reviewed and formally approved by
audit committee since 2008, though charter requires review, revision and
approval every 3 years.
Management charter has not been reviewed and approved since 2008, though
charter requires review every 5 years.
Management noted the audit comment and said that the Audit Committee Charter
is in the process of being reviewed accordingly.
461
Management further explained that the management charter was not yet due for
review by the end of the financial year under audit. However, it promised that the
Charter was scheduled to be reviewed after 2013.
Management was advised to thoroughly review, revise and approve the audit
committee charter in order to strengthen the monitoring controls required to
address various risks associated with current operations.
c) Delay in implementation of the Resettlement Action Plan (RAP)
In addition to the observation identified, it was also observed that the RAP which
was supposed to have been approved by January 2011, was not yet approved by
the end of 2011.
The delayed approval of the (RAP) within the timelines has subsequently lead to
the late implementation of the RAP.
Management explained that the RAP report approval is an external process
because the approval is vested in the office of the Chief Government Valuer (CGV)
in the Ministry of Lands. The CGV handles all infrastructure projects in the country
and the delays have been noted by various parties. However, the approval was
later achieved and the process of compensation is on-going and currently more
than 79% and 78% are compensated for Bujagali-Tororo and Mbarara-Mirama
respectively.
Management was advised to ensure that RAP is implemented in time as required
by the developments partner‟s guidelines.
d) Field Visits
i. Delay in handover of sites to the contractor
During the field visits and interviewing the contractors, it was observed that there
is significant delay in handing over the sites to contractors as a result of either
delay in approval of plans or settling the claims of PAPs and RAP.
462
The compensation progress report as on December 31, 2012 and 2013 is as
under;
Compensation Progress Percentage (%)
LOT A – Mbarara - Mirrama 49%
LOT B – Bujagali - Tororo 48%
Management noted the audit comment and explained that the delay to hand over
sites is due to a number of factors such as delays to approve the RAP report by
CGV, disputes with landowners, family disputes, processing delays, absente land
lords, speculation which leads to landowners selling to new persons leading to new
claimants.
Management was advised to expedite the RAP implementation.
ii. Inappropriate handling of source documents
During the review of expenses, the following was observed;
a) PAP Compensations
It was noted from the sample of PAP files for verification, many PAP files were
misplaced/disorganized and were not availed in time.
Management explained that it is important to note that the Audit exercise
coincided with an on-going exercise to digitise the RAP processes and records into
the Way Leaves Information Management System. The Exercise required files to
be assembled to the scanning teams at different locations, (Jinja, Lugogo and
Hannington) therefore their timely retrieval when instantly required posed a
challenge.
Management further explained that the process of Land Acquisition and transfers
is not instantaneous. The process requires Authentication, proof of ownership and
the involvement of several stakeholders right from the PLCs to the Land Offices.
Most of the paid land is customary owned and therefore the process of transfer is
handled at a later stage as long as clearance for construction of the transmission
463
line is achieved. Registration of transfer forms is done after the mutation process
has been completed.
Management was therefore advised to develop a strong control over maintenance
and safeguarding the physical files that is periodical physical verification of number
files and accurate records for movements in files.
b) Lack of transfer of ownership to NELSAP acquired land
From the reviewed samples, it was noted that;
PAP land transfer forms were not signed by appropriate authority of UETCL,
yet payments were made in full.
PAP land transfer forms have not been registered with land office.
Both the above are contrary to the provision of the Project Implementation
manual, where the land titles are supposed to be obtained before full payment to
the PAP.
Management explained to the audit team that the process of Land Acquisition and
transfers is not instantaneous. The process requires Authentication, proof of
ownership and the involvement of several stakeholders‟ right from the PLCs to the
Land Offices. Most of the paid land is customary owned and therefore the process
of transfer is handled at a later stage as long as clearance for construction of the
transmission line is achieved.
Registration of transfer forms is done after the mutation process has been
completed.
Management explained further that for titled Land, UETCL is in possession of the
said Titles for mutation. In cases titles are not available, 70% of the funds is paid
so that the PAPs allow construction activity to take place and when titles are
presented, the 30% is cleared. All this is done through memorandums of
understanding between land owners and the company. The process of transfers is
also affected by the delays in the land office such as the recent computerisation
when all land offices in the country closed, and even after opening, the process
has not resumed smoothly.
464
Management was advised to do the following;
To ensure that the process of transfer of title of land into UETCL names is
expedited.
Payment authorities should keep in mind the disbursement process; which
should be in line with project implementation manual.
Non compliances with the procedural manual, may create a future financial
loss to the NELSAP.
c) Lack of approval of key field engineers
We have not received the evidence of below missing approval for change of
professional field engineers:
Missing documented apporvals Consultant
Edward Byaruhanga AECOM/ RSW
Paul Kasozi AECOM/ RSW
Management explained that the approval is given to the Key professional staff
whose CVs are documented in the Bid of the Lead consultant. These are evaluated
and approved accordingly. However, the mentioned staff belonged to a sub
consultant engaged by the main consultant as clerk of works, although they are
engineers.
Management was advised to make sure that any change in approved staff must be
approved by a consultant.
d) NELSAP Physical implementation
During the time of audit, the following was noted;
a) There was a lot of pending work with an estimated delay of about 1 year on
Lot B and 6 months on both Lots A and C.
465
There is a risk that the funding period will expire before full project
implementation and all unclaimed funds will attract a surcharge in form of interest
expense to the Government.
The UETCL management promised that it will strive to expedite the process of
handing over the corridor to the contractor as soon as it acquires the remaining
portions.
b) It was also noted that the earthing resistance of the foundation installation
was not measured after back filling as provided for in the contract.
Management explained that the tower foundation installations were still in work in
Progress and all criteria for finalising them will be met.
Management further explained that the earthing of the foundation installations is a
quality conformity requirement by all known electrical installations. It will be done
after tower erection. After foundation back filling and tower erection, extra
earthing is applied on two tower legs on a diagonal (Lattice tower), It is at this
point that earthing resistance is measured and a comparison made against the
recommended standard. The Project Manager will ensure that the measurements
are done once all erection and leg earthings are complete.
Management was advised to do the following;
Ensure that the earthing resistance of the towers is measured and improved
upon through extra earthing pits before stringing of the conductors can be
done and;
Ensure that in rocky places, soil for backfilling be brought from other areas for
good earthing of the system.
c) It was also noted that the number of supervisors on the consultant‟s team
were not adequate. For example a stretch of LOT A with five Gangs operating
at the same time was being supervised by one consultant engineer and LOT B
which had over three Gangs was also being supervised by one consultant
engineer.
466
It was noted that there may be a risk of not attaining the agreed tower
foundation.
Management explained that earlier in the contract, the Consultant was requested
to submit a proposal for enhanced supervision. This was received, reviewed and
forwarded to the Financier for a no-objection which was declined. However,
UETCL.
Management was advised to consider increasing the number of supervisors for
adequate supervision.
Contractor does not maintain accurate and reliable quantitative records for the
movements, use and balance of stocks.
In the absence of the accurate records, there is a risk of not ensuring that all
inventory items purchased are appropriately used for the project and no frauds
have taken place.
Management was advised to maintain the appropriate stock records and
consultant the consultant should periodically review and verify the physical stock
and directly report to the UETCL management.
No test results to ascertain grade of steel being used.
Management was advised to ensure that a sample for each batch is tested to
ascertain the correctness of the steel used.
No toilet facilities at field active sites.
Management was advised to ensure that waste disposal is well managed by the
contractor at all active sites.
d) Unrecorded liquidated obligations
It was observed that NELSAP follows a modified cash basis of accounting where by
expenses are recorded when paid modified by accruing for un-liquidated
obligations at the reporting period
467
However, we observed that un-presented cheques which was paid to PAPs was
not recorded in the books of NELSAP and still showing under reconciliation of
Stanbic Bank account.
Management was advised to disclose these obligations in their quarterly/yearly
financial reporting to the development partners and other reporting authorities.
e) Project fixed assets monitoring:
It was noted that the projects fixed assets were not engraved/tagged, labelled
with NELSAP project identification codes and there was no evidence of regular
verifications.
Management was advised to label all the project assets with the project NELSAP
identification codes and periodic counts should be performed and reviewed for all
assets.
f) Unremitted withholding tax
It was observed that following amount withheld from suppliers yet not remitted to
the Uganda Revenue Authority:
Supplier Date deducted Amount (US$)
AECOM Jan 2013 97,340
AECOM Feb 2013 97,340
Management was advised that withholding tax deducted on payment should be
promptly remitted to URA to reduce the future penalty.
24.13 ENERGY FUND
a) Lack of Operational Guidelines for the Fund
In my report to parliament for the year ended 30th June, 2013, I pointed out that
the Fund lacks operational guidelines for implementation of its activities and
financial reporting. By close of the current year‟s audit the issue remained
outstanding. Under the circumstances, there is risk of uncoordinated operation of
the Fund resulting into sub-optimal decision making.
468
Management explained that the matter had been communicated to the Accountant
General and that interactions between the Ministry of Energy and Mineral
Development and the Office of the Accountant General were ongoing.
I advised management to expedite the process of developing the guidelines
without further delay.
b) Unauthorized Expenditure
Reg. 4 (2) of the Energy Fund Regulations, 2008 provides that monies shall not be
withdrawn from the Fund unless the withdrawal has been duly authorised for a
specific purpose of the Fund. In addition, section 9 (6) of the Public Finance and
Accountability Act, 2003 provides that no expenditure shall be incurred by a
special Fund except under the authority of a warrant signed by the Minister of
Finance and addressed to the Accounting Officer.
Contrary to the above provisions, UGX.10,432,195,553 was paid out of the Energy
Fund without evidence of the requisite authorisation by the Minister responsible
for Finance. I pointed out a similar scenario in my report for the previous year.
Payment without authority exposes the money in the Fund to the risk of
misappropriation which would undermine the objectives for which the Fund was
established.
Management explained that that it had running contracts whose obligations had to
be met using proceeds of the Energy Fund in anticipation that authority to utilize
the proceeds of the Fund would ultimately be granted by the Minister.
I have advised management to always ensure that all withdrawals from the Fund
are authorised by the Minister as required by law.
c) Direct Payments from the Energy Fund
A sum of UGX.11,218,827,049 was paid out of the Fund directly to Energy Infra
tech Ltd, a service provider providing consultancy services for the supervision of
469
construction of Karuma Hydropower project instead of making transfers to the
Hydro power development unit of the Ministry for subsequent disbursement. It
was noted that in the previous year UGX.7, 070,240,250 had been paid out in the
same manner. The practice of making direct payments from the Energy Fund
Account turns it into an ordinary operational account. A similar matter was pointed
out in my report for the previous year.
I informed management that the practice undermines the strategic intent of the
Fund.
Management explained that, a request to the Accountant General to open an
operational account for the Energy Fund had not been cleared by the end of the
financial year. It was further stated that the Hydro power development unit has
since been absorbed into Uganda Electricity Generation Company Limited
(UEGCL).
I advised management to follow up the matter of an operational account with the
Accountant General without further delay.
d) Unimplemented Activities
The Ministry policy statement provided for implementation of the following
activities using the Energy Fund;
S.No Activities Estimated Costs (UGX
Bn)
1 132 KV transmission line from
Kabulasoke to Hoima, including
substations.
70.2
2 132KV transmission line from Lira to
Gulu to Agago, including
substations.
50.7
3 Nyagak 111 hydro power project. 22.425
470
S.No Activities Estimated Costs (UGX
Bn)
4 MW Maziba small power plant. 7.397
Total 150.722
It was however noted that none of the activities was implemented. Non
implementation of the planned activities undermines the intentions of the Fund.
Management explained that the necessary Funds were not released by the Ministry
of Finance.
I advised management to continue liaising with the Ministry of Finance, Planning
and Economic Development together with relevant stakeholders to have the Funds
released.
24.14 STRENGTHENING THE MANAGEMENT OF OIL AND GAS SECTOR IN
UGANDA PROGRAMME (SMOGP)
a) Inconsistencies in the Accounting and budgeting periods
Section 8.0 (3) of the programme document requires that annual financial
statements and budget should be submitted to Norway (Ministry of Foreign
Affairs) within three weeks before the Annual Meeting each year to give complete
and detailed information on the financing of the Programme.
However, it was noted that whereas the Programme follows a calendar year
budget cycle, the financial statements are prepared for the period July to June in
accordance with the Government of Uganda fiscal year. In the circumstances,
analysis of the programme's trends in performance is rendered difficult.
Management explained that quarterly expenditures were made against approved
quarterly budgets for the calendar year as provided for in the annual meeting and
the four (4) quarters that make a financial year were analysed. However,
management indicated that in the event of new programmes, exemptions would
471
be made so that the financial statements follow the Donor period. I have advised
management to align the budget and the GoU financial reporting periods.
472
HEALTH SECTOR
25.0 MINISTRY OF HEALTH
25.1 Mischarge of Expenditure
Paragraph 156 of the TAI prohibits transfer of funds available on one item or sub
item of expenditure to another save, on the authority of a virement warrant. It
also prohibits charging expenditure to items merely because funds are available on
a particular item.
However, It was noted that out of the appropriated expenditure of
UGX.45,794,208,890, a total of UGX.2,644,401,389 (5.7%) was charged on codes
other than those for which funds were appropriated. Though there was an 80%
decrease from UGX.13,431,161,682 mischarged in the previous year, there is need
for further measures to stop the practice, as it contravenes budgetary controls and
distorts the intentions of the appropriating authority.
Management indicated that further controls in budget implementation would be
undertaken to reduce the mischarge. I await the results of Management‟s efforts.
25.2 Payables
Included in the payables balance of UGX.10,815,916,944 in note 26 to the
financial statements are long outstanding liabilities in respect of UMEME
(UGX.3.131 billion), NMS (UGX.3.77 billion), JCRC (UGX.1.1billion), UTL
(UGX.127 million) and NWSC (UGX.61 million) which may result in
discontinuation of essential services to the Ministry.
In response, the Accounting Officer stated that he was liaising with MoFPED to
settle the liabilities to enable sustainability of services.
I advised Management to ensure that resources are set aside to settle the
liabilities without further delay.
25.3 Expired Letters of Credit
473
The Ministry of Health had expired letters of credit amounting to UGX.696,965,456
in respect of settlement of liabilities with various construction companies at the
end of the financial year. There was however no evidence of renewal of the LCs or
a mechanism of settling the liabilities which may result in litigation.
The Accounting Officer indicated that a request to MoFPED for renewal of the LCs
was not responded to. I advised Management to continue liaising with MoFPED to
ensure that resources are set aside to settle the liabilities without delay.
25.4 Nugatory Expenditure
A local Construction firm was contracted by the Ministry to undertake various
projects between 1997/1998 and 2005/2006 at a total cost of UGX.4,419,818,390.
The projects included;
i. Reconstruction of the Ministry of Health Headquarters;
ii. Rehabilitation of Jinja Hospital;
iii. Rehabilitation of sewerage, water reticulation and plumbing installation for
Entebbe Hospital, and
iv. Construction and equipping of Health Centres in Kamuli and Kisoro Districts.
However, owing to delayed settlement of the contractual sum, interest of
UGX.2,116,126,197 was charged to the Ministry. The expenditure is considered
wasteful, since it would have been avoided if the bills were settled promptly.
Besides, the interest charge continues to accumulate with further delays in
settlement of the bills.
In response, the Accounting Officer explained that the entire contract was being
reviewed by the Internal Audit section of the Ministry, after which a final position
would be communicated to all stakeholders.
I advised the Accounting Officer to expedite the review process and liaise with the
Ministry of Finance, Planning and Economic Development (MoFPED) to settle the
bills without further delay to save public funds from wastage.
25.5 Budget Performance
474
a) Revenue Performance
Out of the budgeted revenue of UGX.473.99 billion, the Ministry received only
UGX.291.62 billion, resulting into a shortfall of UGX.182.37 billion (39%). It was
noted that the component supported by Development Partners suffered the
biggest shortfall amounting to UGX.171.7 billion (41%) as shown in the table
below;
Particulars GoU (billions) Donor (billions) Total (billions)
Approved budget 57.32 416.67 473.99
Released funds 46.70 244.92 291.62
Shortfall 182.37
% shortfall 38.48
As a result, various planned activities were not implemented such as construction
of the Central vaccine store, District vaccines stores and staff houses in the hard
to reach areas. Failure to construct stores for vaccines and staff houses has the
effect of constraining immunisation programmes and motivation of staff in hard to
reach areas respectively.
In response, the Accounting Officer explained that the funds were carried over to
the FY 2014/2015 and would be applied to the planned activities.
I advised the Accounting Officer to continue liaising with MoFPED and other
stakeholders to ensure that appropriated revenue is realized in a timely manner to
be able to meet the MoH and sector objectives.
b) Low Absorption Capacity for Global Alliance for Vaccines
Initiatives (GAVI)
The Global Alliance for Vaccines Initiatives (GAVI) was launched in 2000 to
improve access to immunisation services for children in Uganda. The Project‟s
main objective is to contribute to strengthening Uganda‟s health system to deliver
the National Minimum Health Care Package (NMHCP), including immunization in
an efficient, equitable and sustainable manner for reduced morbidity and mortality
in Uganda. The first phase of the Project is expected to end in June 2015.
475
A review of the Financial Performance Analysis of the GAVI Project for the period
ended 31st June 2014, revealed that out of the disbursement of
UGX.54,862,533,887, only UGX.1,512,757,372 (2.76%) was expended on Project
activities, leaving a balance of UGX.53,349,776,515.3, as indicated in the table
below;
Grant Rolling Budget Disbursement for
FY 2013/14 (a) Expenditure by 30th June 2014(b)
Variance (c)=(a)-(b)
%Expenditure
Health Systems Strengthening Grant
46,180,800,936 46,180,800,936 223,878,800 45,956,922,136 0.5
Immunisation Support Services one grant
2,046,059,631 860,950,281.3 169,139,020 691,811,261.30
20
Immunisation Support Services Two grant
6,358,853,680 6,358,853,680 605,206,500 5,753,647,180
9.5
Vaccine introduction Grant
3,384,276,000 1,461,928,990 514,533,052 947,395,938
35.2
Total 57,969,990,247 54,862,533,887 1,512,757,372 53,349,776,515.3
Under absorption of funds hinders achievement of immunisation goals.
The Accounting Officer attributed the low absorption capacity for the Global
Alliance for Vaccines Initiative (GAVI) to procurement delays resulting from
administrative reviews of various procurements. He further explained that,
consequently the top Management of MoH together with the GAVI alliance had
resolved to use the delegated procurement method, using international agencies
such as UNICEF, USAID and Catholic Relief Services (CRS).
I advised the Accounting Officer to ensure that procurement systems within the
Ministry are strengthened so as to minimize administrative reviews and gain the
confidence of financiers.
c) Review of the Annual Health Sector Performance Reports
476
A review of the annual health sector performance reports for the period 2006 -
2014 revealed that there was stagnation towards achievement of the Sector set
targets and goals as indicated in the table below;
The Health impact indicators against the MDGs and the HSSIP 2010/2011-2014/2015 targets Health Impact Indicator
MDG/HSSIP
2015 target
2006 2011 2012 2013 2014 Audit Remarks
Maternal
mortality ratio (per 100,000 live
births)
131 435 438 438 438 438 Declining/stagna
ted trend
Neonatal mortality rate
(per 1000 live births)
23 29 27 27 27 27 Stagnated trend
Infant mortality
rate (per 1000 live births)
41 76 54 54 54 54 Stagnated trend
Under 5 mortality
rate (per 1000 live birth)
56 137 90 90 90 90 Stagnated trend
The low performance ratios were attributed by Management to various factors
including; health service communication breakdowns, lack of blood products,
supplies and consumables, Health staff non-action, staff misguided action, staff
lack of expertise, inadequate Human Resource (HR) numbers and skills at the
health facility level at only 69% of the required positions. It was noted that the
general Government funds allocation to the Health Sector as a percentage of the
total Government budget had averaged about 8% from 2010/2011 to 2013/20141
which is 1.8% short of the HSSIP target of 9.8%.
The Accounting Officer explained that the impact indicators had been measured by
UDHS in 2011 and the following interventions have since been undertaken:
Increasing funding for reproductive health commodities from USD.3.3 million
to USD.6.9 million, thus reducing stock outs;
1 In 2013/2014 the total government budget allocation to the Health Sector increased from
UGX.852,200,000,000 allocated in the previous year was UGX1, 127,480,000,000.
477
Setting up regional blood banks at Mbale, Mbarara, Fort Portal, Arua, Gulu and
Soroti Regional Referral Hospitals;
Recruitment of health workers to operate Health Centre (HC) IVs thus
increasing HC IVs offering comprehensive emergency obstetric care from 17 %
- 35%;
Mentoring health workers to carry out emergency obstetric care and other
reproductive health services;
Procuring and distributing of equipment to health facilities;
Using Village Health Teams to mobilize, register and refer mothers and their
babies to health facilities, and;
Carrying out maternal and prenatal death reviews as a quality improvement
tool.
I await the results of Management‟s action in this regard.
25.6 Funds Not Accounted For
a) Administrative Advances
Paragraph 215 (a) of Part I of the TAI, 2003 requires advances to be accounted
for within sixty days of disbursement. It was however noted that
UGX.121,360,800, advanced to various Ministry staff during the financial year for
implementation of official activities, remained outstanding.
In the absence of the necessary accountability documents, it was not possible to
confirm whether the funds were put to intended use.
The Accounting Officer explained that the concerned individuals had been notified
and reminded of the need for timely accountability.
I advised the Accounting Officer to ensure that the outstanding advances are
accounted for by the various beneficiaries or else, the funds are recovered.
b) Advances to Staff Personal Bank Accounts
UGX.15,644,667 advanced to Ministry staff through their personal bank accounts
for purchase of fuel while on official activities remained outstanding. I explained to
478
the Accounting Officer that the practice contravenes paragraph 228 of the TAI,
2003 which exposes the funds to the risk of mismanagement.
In response, the Accounting Officer explained that further consultations with
MoFPED are to be undertaken to enable staff carry out field activities without
paying funds to personal accounts.
I advised the Accounting Officer to consider providing staff with fuel cards for use
during field activities. Meanwhile, the funds should be accounted for or recovered.
25.7 Wasteful Expenditure
The Ministry contracted a hotel for four (4) days from 23rd to 26th September,
2013 to provide hotel services for the Joint Health Review Mission. However, it
was noted that whereas 1,600 participants were paid, only 1,284 attended,
resulting into wasteful expenditure of UGX.27,047,783. In response, the
Accounting Officer stated that the Ministry paid the hotel on the understanding
that all invited guests would attend.
I advised the Accounting Officer to always ensure prior confirmation of
participation by invited guests before booking the services, since the Joint Review
Mission is a regular and planned event.
25.8 Implementation of Procurement Audit Recommendations
Review of the implementation status of the PPDA Authority audit recommendation
for the year 2012/2013 revealed various outstanding matters as indicated in the
table below;
Ser. no. Procurement area. Current status
1. Preparation of solicitation documents Not implemented
2. Signing of all contracts by the Accounting Officer. Not implemented
3. Reporting; Donors funded projects with an estimated
value of UGX 380,000,000 not reported to PPDA
Not implemented
4. Performance of Accounting Officer –
- Take responsibility of the Nugatory expenditure
- Ensure delays in procurement processes are avoided
Not implemented
479
Ser. no. Procurement area. Current status
at the various stages and timelines in the bid notice.
5. - Performance of the procurement and disposal Unit
staff for failure to seek contract committee approvals
of some mentioned procurements
Not implemented
6. Performance of user departments – Caution in writing an
officer for usurping the role of the procuring and disposal
unit.
Not implemented
Failure to implement the procurement audit recommendations may result in
recurrence of the anomalies. The Accounting Officer stated that out of the 13
recommendations, 7 had been implemented and plans were underway to
implement the outstanding 6 matters.
I advised the Accounting Officer to ensure that all procurement audit
recommendations are implemented by the Ministry so as to improve its
performance.
25.9 UGANDA GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA
PROJECT – HEALTH SYSTEMS STRENGTHENING COMPONENT IN THE
MINISTRY OF HEALTH
25.10 Delayed Release of Project Funds
The review of the Portfolio Disbursement Release (PDR) document for the financial
year 2013/2014 revealed that Global Fund released a total grant of USD.2,272,147
on 20th June 2014 through the Principal Recipient - Ministry of Finance
Planning and Economic Development (MoFPED). However, the funds could not
be transferred to the Project account since they had been released towards the
end of the financial year. As a result, the planned activities could not be
implemented during the period thus affecting the project completion timelines and
the attainment of the overall project goals and objectives.
480
The delayed release of funds was attributed to the delayed recruitment of the
Regional Performance Monitoring Teams (RPMTs).
The Accounting Officer explained that the Management of the Fund together with
the Global Fund (GF) Secretariat team had put in place measures to unblock
roadblocks and expedite the implementation of the grant activities.
I have advised the Project management to ensure timely release of funds to
enable implementation of planned activities, thus ensuring attainment of project
objectives.
25.11 Global Fund GoU counterpart funding
A review of the Project work plan and Government of Uganda (GoU) Global Fund
schedule of releases from IFMS system revealed that management had
budgeted for GoU funding of UGX.4,000,000,000, but only UGX.3,277,112,100
(82%) was actually released as co-funding to the Project.
Failure to fully fund the Project stifles the project cash flows thereby constraining
the implementation of the planned activities and the attainment of Project
objectives.
Management explained that they were in negotiations with MoFPED to ensure that
all budgeted counterpart funds are released early in the financial year according to
work plans.
I have advised management to always liaise with MoFPED to plan properly for the
release of funds to ensure proper implementation of all planned project activities.
25.12 Un-updated asset register and Un-engraved assets
The Specific Terms and Conditions, Para 2 of the Project Grant Agreement (Annex
2) require the Principal Recipient to provide an up-to-date, complete asset register
(including, without limitation, the location of the fixed asset, the owner of the
fixed asset, specific fixed asset identifier code or reference). It was however noted
that the fixed asset register for Global Fund was not updated with all the details of
the assets.
481
Review of the asset register also revealed that a number of assets which were
distributed up-country such as microscopes, laptop computers, printers, desktop
computers, Laboratory Refrigerators, Drawer filing cabinets, Round conference
tables and standard office chairs had not been engraved. Failure to update the
asset register and to engrave the assets is an indication of weaknesses in the
internal controls which exposes the Project assets to misuse.
Management acknowledged the anomaly and pledged to endeavour to engrave
the assets, and update the fixed asset register.
I have advised the Project Management to ensure that all assets are engraved and
that the asset register is updated with all the details of the assets.
25.13 Un-utilized Funds for Regional Planning and Monitoring Teams
UGX.2,889,664,406 was released for operational funds for the component of
Health Systems Strengthening for the period Jan - June 2014. Audit noted that
UGX.1,783,007,073 was properly utilized and accounted for while the balance of
UGX.1,106,657,333 meant for Regional Performance Monitoring Teams (RPMTs)
was not utilized. This was attributed to the late release of funds to the regional
offices (i.e on 14th May 2014). Management was given a no cost extension up to
December 2014, to implement the activities of RPMTs. However, at the time of
writing this report (March 2015), there were no further details regarding the
matter.
The Accounting Officer explained that the delay to release the implementation
funds for RPMTs was due to the time it took for the host districts to include them
in the district system - because they had to be approved as supplementary funds
by the respective district councils. He further stated that implementation was on-
going and once completed, the funds would be fully accounted for.
I have advised the Accounting Officer to ensure that the implementation of the
RPMTs activities is duly expedited and fully monitored to ensure proper utilization
of the funds.
482
25.14 Review of implementation of recommendations
i. Status of conditions precedent and/or other special conditions
It was observed that the Principal Recipient had three conditions precedent and/or
other special conditions to be fulfilled before and after the first disbursement could
be made. While one condition had been met, the other two remained outstanding.
Failure to fulfil these conditions could result into delayed or withholding of further
disbursement.
In their response, the Project Management committed to continuously liaise with
the stakeholders to fully address the work in progress of the issues noted.
I have advised management to expedite the implementation of the outstanding
conditions in order not to frustrate further disbursement of funds.
ii. Follow up of Local Fund Agent (LFA) findings and
recommendations
The Local Fund Agent (LFA) raised a number of issues during the year on the
Grant. While some actions had been taken by Management to address the
recommendations, a number of them remained outstanding and this could affect
grant disbursements.
In their response, Management promised to continuously work towards providing
remedial actions/measures for the above issues.
I have advised the Project Management to ensure that it fully addresses the
outstanding issues raised by the LFA.
25.15 UGANDA GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA
PROJECT – MALARIA COMPONENT ROUND 4 – MOH
a) Un-utilised Funds by Sub Sub-Recipients (Districts)
In October 2012, a number of district Global Fund accounts were credited with
funds under the Round 4 (AMFm) Project meant for Project activities with the
understanding that these funds would be spent by 31st December, 2012. Districts
483
which were unable to spend these funds within the given timeline were to refund
the unspent funds to the Ministry of Health. However, by the end of the previous
financial period, 19 districts holding UGX.261,505,730 had not made the refund.
By the time the Grant came to an end on 31st December, 2013, 14 districts still
held UGX.119,652,304 (USD.46,126).These funds had not yet been refunded by
the districts despite a directive from the Permanent Secretary, Ministry of Health to
do so.
These balances are being eroded by the charging of bank charges, besides the
Project‟s objectives are not being enhanced because these funds were not used
for what they had initially been planned for.
Management noted the observation and explained that the recovery of these funds
is being carried out as part of the closure activities for this Grant.
I advised Management to pursue the recovery of these funds and ensure they are
recovered and refunded to the Global Fund since the Project has come to an end.
b) Undistributed Torches and Batteries
In the previous period‟s audit report, I noted that a number of districts had not
been able to distribute the torches and batteries procured under the AMFm
funding round. Following up on this observation, we noted that this condition had
persisted in some districts like Tororo. Also observed that some of these batteries
were now damaged which could have discouraged the intended recipients from
picking them up from the district stores.
Unutilised torches and batteries affect service delivery and could result in financial
loss especially when the batteries expire or get damaged.
Management regrets the holding of torches and batteries at district level, as the
distribution point was supposed to be at the sub-county level, for onward
transmission to the beneficiaries Village Health Teams (VHTs). Management
promised to follow up with the districts to ensure that this anomaly is rectified and
report by the next audit period.
484
I advised Management to ensure that the intended beneficiaries are identified and
given the torches, batteries and nets.
c) Long Outstanding Invoices from the National Medical Stores
The National Medical Stores (NMS) is an autonomous public corporation
established under the National Medical Stores Act, CAP 207 and mandated to
procure, store and distribute pharmaceutical products to health institutions in the
Public Sector in Uganda. The MoH pays NMS a handling fee of 8.5% of the Cost
Insurance Fright (CIF) value of goods and services.
Included in AMFm (Round 4) Project‟s commitments are unpaid amounts to the
NMS totalling up to USD.1,007,758, of this, USD.825,827 (82%) relates to services
and invoices that NMS provided before the reporting period.
Long outstanding invoices could result in errors like the inclusion of invoices which
have already been paid for. In other instances, legal proceedings could be initiated
by the aggrieved third party resulting in financial and/ or reputation loss.
Furthermore, the service provider, NMS may institute punitive conditions for
handling Global Fund Projects‟ deliveries (like asking for 100% payment before
they allow the goods into their stores).
Management noted the observation and explained that this has however changed
and payment to the National Medical Stores is on-going following NMS‟ opening of
an account with the Bank of Uganda, which was a requirement by the GoU.
I advised Management to expeditiously review the NMS invoices received and
settle them timely.
d) Refund of Advance for Consultancy Services
A local firm and its consortium were contracted in 2012 to provide consultancy
services for private sector training in ACT medicines for affordable medicine facility
at a contract sum of USD.867,624. 80% of the contract amount was advanced in
two tranches; 50% of the contract amount (USD.433,812) in September 2012 and
30% of the contract amount (USD 260,287) in June 2013. The terms and
conditions of the Contract Agreement require accountability of the advance
485
payments before the final payment is made. However, contrary to the General
Conditions of the Contract (GCC), the firm did not submit the required
accountability when they submitted the detailed report on the training. Although
the Accounting Officer followed up the matter with the firm there was no response
from the firm.
It was also noted that the Ministry could not effect the final payment of
USD.173,525 because of non-accountability for the advance payments. Instead,
the Ministry of Health has sought the guidance of the Solicitor General to recover
in full the advanced amount of USD.694,099 from the firm.
Without the financial accountability, the Ministry of Health may not be able to
ascertain whether the firm actually carried out the activities which might impede
Project objectives.
Management explained that it will proceed to recover the money from the firm
once the Solicitor General has given guidance on the matter.
I have advised that at the highest levels, the Ministry proactively engages the firm
to ensure that the money is accounted for.
e) Lack of a Fixed Asset Register
The Implementation Letter dated 26th July 2013 from the Global Fund requested
that by no later than 30th June 2013, the Recipient should have provided an up-to-
date and complete asset register. SC3 provides that the PR shall ensure that:
i. The asset register is updated regularly and submitted to the Global Fund on a
semi-annual basis;
ii. An annual verification and fixed assets inspection report shall be submitted on
an annual basis.
The existing fixed asset register does not capture all the information regarding the
assets. Although the PR procured accounting software, Navision, with a fixed asset
register module, the software has not been installed, pending purchase of a server
to host it.
486
With an asset register maintained in MS Excel, errors of omission or commission
may occur without being detected.
Management explained that they were in the final stages of installing and
implementing the upgraded Accounting Software, from Navision 2009 to Navision
Serenic Navigator 2013.
I advised Management to expeditiously complete the installation of Navision so
that they can make use of the asset module.
25.16 UGANDA GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA
PROJECT – MALARIA COMPONENT ROUND 7 – MOH
a) Unaccounted for Funds
Review of the status of the Special Condition Account from Malaria round 7 phase
1 revealed that USD.518,614 remained un-accounted for from the advances paid
out from Phase 1 of the Grant, contrary to Section 5 of the Malaria round 7 PR
Special Conditions (SCs). In an interview with the Focal Coordinator, it was
established that the matter was being investigated by the Police and had not been
resolved. A further delay on the resolution of the matter is likely to jeopardise
Project funding and implementation.
Management explained that they were waiting for the finalization of the Police
investigation and report for appropriate action to be taken.
I have advised the Program Management to proactively follow up with the Police
and ensure that the investigation is concluded and appropriate action taken
against the culprits.
b) Lack of Reconciliations for Purchases Made Under the VPP
Mechanism
The Voluntary Pooled Procurement (VPP) mechanism is a strategic initiative
established as a result of the Global Fund Board decision B5/DP151 aimed at
ensuring a cost-effective and cost-efficient procurement process focusing on the
three key principles of:
487
• Efficient, timely and reliable procurement.
• Stringent quality standards for procured products.
• Attractive pricing for key health products.
Through the VPP mechanism, Principal Recipients (PRs) can procure health
products through the VPP pre-qualified Procurement Services Agents (PSAs):
Step 8 of the 8-step VPP procurement process states that the PSA shall reconcile
the PR‟s account based on updates about procurements and deliveries made and
submit the final invoices to the PR. These invoices bear the price and quantity of
the health products procured. However it was noted that the Program
Management did not receive these invoices to carry out reconciliations.
There is a risk that in case of any errors, they may not be identified and corrected
in time.
The PR noted the observation and undertook to continue to work with the PSAs to
get all the necessary documentation.
I have advised the Program Management to always obtain the final invoices from
the PSA and carry out the necessary reconciliations.
c) Lack of a Fixed Asset Register
The Implementation Letter dated 26th July, 2013 from the Global Fund requested
that by no later than 30th June, 2013, the recipient should have provided an up-to-
date and complete asset register. SC3 states that the PR shall ensure that:
i. The asset register is updated regularly and submitted to the Global Fund on a
semi-annual basis;
ii. An annual verification and fixed assets inspection report is submitted on an
annual basis.
It was noted that the existing fixed asset register does not capture all the
information regarding the assets. Although the PR procured an accounting
software, Navision, with a fixed asset register module, the software has not been
installed pending purchase of a server to host it. With the current asset register
488
maintained in MS Excel, errors of omission or commission may occur without being
detected.
Management explained that they were in the final stages of installing and
implementing the upgraded Accounting Software, from Navision 2009 to Navision
Serenic Navigator 2013.
I have advised the Program Management to expeditiously complete the installation
of the upgraded Navision so that they can make use of the asset module.
d) Supervising and Monitoring of Sub Sub-Recipients (SSRs)
In the previous year‟s report it was observed that monitoring, supervision and
progress reports were not available to enable assessment. This finding persisted in
the current period. Management inquiries revealed that in November 2013, the
Ministry set up Regional Performance Monitoring Teams (RPMT) to provide direct
assistance to the SR‟s in the field through quarterly stakeholder meetings and
trainings. The RPMTs also help improve the quality of the data prepared by the
SRs before it is shared with other stakeholders. Without progress reports,
weaknesses may not be identified for corrective actions to be taken.
Management noted the observation and explained that the SR periodic reports had
started coming in.
I have advised the Grant Management that, in addition to the critical role played
by the RPMTs, reports should be obtained from all the SRs.
25.17 UGANDA GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA
PROJECT – MALARIA COMPONENT ROUND 10 – MOH
a) Lack of Reconciliations for Purchases Made Under the VPP
Mechanism
The Voluntary Pooled Procurement (VPP) mechanism is a strategic initiative
established as a result of the Global Fund Board decision B5/DP151 aimed at
ensuring a cost-effective and cost-efficient procurement process focusing on the
three key principles:
489
Efficient, timely and reliable procurement
Stringent quality standards for procured products
Attractive pricing for key health products
Through the VPP mechanism, Principal Recipients (PRs) can procure health
products through the VPP prequalified Procurement Services Agents (PSAs):
Step 8 of the 8-step VPP procurement process states that the PSA shall reconcile
the PR‟s account based on updates about procurements and deliveries made and
submit the final invoices to the PR. These invoices bear the price and quantity of
the health products procured. However it was noted that the program
management did not receive these invoices to carryout reconciliations.
There is a risk that in case of any errors, they may not be identified and corrected
in time.
The PR noted the observation and undertook to work with the VPP team to get all
the necessary documentation.
I have advised the Program Management to always obtain the final invoices from
the PSA and carryout the necessary reconciliations.
b) Lack of a Fixed Asset Register
The Implementation Letter dated 26th July, 2013 from the Global Fund requested
that by no later than 30th June, 2013, the recipient should have provided an up-to-
date and complete asset register. SC3 states that the PR shall ensure that:
a. The asset register is updated regularly and submitted to the Global Fund on a
semi-annual basis;
(j) An annual verification and fixed assets inspection report is submitted on an
annual basis.
It was noted that the existing fixed asset register does not capture all the
information regarding the assets. Although the PR procured an accounting
software, Navision, with a fixed asset register module, the software has not been
installed pending purchase of a server to host it. With the current asset register
490
maintained in MS Excel, errors of omission or commission may occur without being
detected.
Management explained that it was in the final stages of installing and
implementing the upgraded Accounting Software, from Navision 2009 to Navision
Serenic Navigator 2013.
I have advised Management to expeditiously complete the installation of the
upgraded Navision so that they can make use of the asset module
25.18 GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA PROJECT
– HIV COMPONENT
a) Expired Drugs
An audit inspection carried out in various hospitals and Health Centres revealed
expired drugs that were still being kept in the stores. It was further noted that in
some cases, the expired drugs were kept together with the useful ones thereby
risking contamination and the possibility of dispensing improper drugs to patients .
The table below refer;
Ser. No/
Health
facility
Particulars Expiry date Audit remarks
Dokolo HC IV 251 packets of Atazanavir
+Ritonavir
(300mg/100mg)
capsules
Jan 2015 All the items were still
on shelf of the
time of the
inspection
Dokolo HC IV 1400 pieces of Determine
(HIV test kits).
Jan 2015 -do-
Kyabugumbi
HCIV,
70 bottles of Efavirenz HIV
capsules 50mg for
children
31/Jan/2015 Items were still on the
store shelves.
Kiwoko Hospital 336 strips of 28RHZE tablets
75/150/275/400mg
31/12/2014 The drugs were received
on 19/11/2014,
one month to
expiry.
491
Expired drugs were also found in Lyantonde Hospital and in Lukoki HC IV and
Bwera Hospital in Kasese. It was further noted that registers for expired drugs
were not maintained at various health facilities which hindered proper tracking and
destruction of the drugs. There is a risk of expired drugs being channelled to
private clinics.
In response the Accounting Officer explained that, as part of inventory
management, before medicines and other health commodities are removed from
the shelf, they undergo a systemic review to identify and ascertain the remaining
shelf life to determine those that are to be retained, replenished, or removed for
disposal. He indicated that this was an on-going process in conformity with the
WHO guidelines to guard against medicines falling in un-authorized persons‟
possession. He further indicated that on a monthly basis there was a stock taking
exercise to enable replenishment and removal for disposal of expired drugs. He
also promised to follow up the issue of expired drugs with the respective Health
Centers.
I advised the Accounting Officer to ensure that the managers of the health
facilities together with the district health officers institute proper disposal
measures for the expired drugs.
b) Inadequacies in Stores Records Management
Inspections of stores in the sampled Health Centers revealed various challenges in
stores management which included inadequate records, lack of qualified
personnel, inadequate space and poor record keeping, as indicated in the table
below:
Health Center Observations
Atiak HC IV - The store lacks substantive stores personnel. It was being
manned by a nursing assistant.
Dokolo HC IV - Incomplete ARV & PMTCT medicines order forms and patient
reports.
- Stock cards were not updated a case in point
Tenofovir/Lamivudine/Efaverenz Tabs physical stock was 908
the card reflected 2089 units.
Naguru China - The store lacks store shelves.
492
Health Center Observations
Friendship
Hospital
- The store is not equipped with firefighting equipment.
Lyantonde Hospital - The hospital has a very small compact store.
- The store has inadequate ventilation (most drugs in the store
require storage below 20 degrees but the store lacks windows
and ventilators.
Kyabugimbi Health IV - The stock cards were not updated hence making it hard to track
drug usage.
- The store lacks adequate space and thus the boxes of HIV and
malaria drugs were lying on the store floor.
- The HMIS form 017, district requisition and issue voucher forms
for the period 2013/2014 were never authorized by the
departmental supervisors or the health unit in-charge as
required by the HMIS regulations.
Bushenyi HC IV - Un-authorized issue and requisition vouchers by the in-charge
(sample of vouchers for the period 10/06/14 to 31/12/14
reviewed indicated that none had been authorized).
- The stores in-charge does not verify the dispensing logs to
confirm stock-outs from the different departments before
replenishments.
- Inadequate storage space hence boxes of medicines were lying
on the floor.
- The store is not fitted with shelves.
Kasese town HC IV - Some items were not posted to stock cards. A case in point
were 13 boxes of stat-pak test kits and 158 tins of nevirapine
200mg.
Kyamuhunga HC III - The expired/spoiled medicines register was not maintained. For
example 2,300 Vactainer tubes and needles had expired but
there was no record in place.
Rukoki Health Center
III
- The unit lacked dispensing logs hence drugs picked from the
stores were not recorded at the dispensing area.
- The HMIS form 17-requisition and issue vouchers were not
authorized by the in-charge. The requisitions were made directly
to the stores in-charge.
- The unit has a small compact store for HIV and malaria drugs
therefore some medical supplies are kept on the floor in a
separate room.
Kiganda HCIV-Mubende
district
- Un-authorized issue and requisition vouchers by the in-charge. A
sample of vouchers, serial numbers 1571802-1571884 and
10781101-1078158 in 2013/14 were un-authorized
- The health facility lacked the expired/spoilt drug registers,
therefore there was no record of the current expired drugs.
- The store space is inadequate.
Kataraka HC IV-
Kabarole
- Unauthorized issue and requisition vouchers by the in-charge.
- The unit lacked dispensing logs which made it difficult to carry
493
Health Center Observations
district out confirmation of genuine stock outs at the dispensing areas
- The HIV/Malaria drug store was small and compact without
enough shelves. Some drugs were kept in boxes which may
affect their durability.
- Due to inadequate space, expired drugs were kept in the open
at the residence of the in-charge.
Mukono HC IV - The stores recording system was manual and could not
separately record and file Global Fund deliveries from GoU and
other sources.
- Orders made for drugs were general and it could not be
ascertained whether all Global Fund drugs ordered for were
actually delivered.
Mpoma HC II - Mukono
District
- The HC II did not order for drugs delivered and deliveries could
not be verified against orders made since a push system of
delivery was used by NMS.
- Global Fund drugs received at the health facility could not easily
be distinguished from drugs from other sources since general
delivery notes were used by NMS.
Buwenge HC IV - Jinja
District
- Poor filing system. A case in point was the Delivery notes for 95
packets of contrimoxale 120 mg tablets delivered on 27th July
2013. Delivery records were not availed for review and thus
deliveries could not be confirmed.
- Storage space was inadequate for large consignments.
- The health facility had a manual system of store record keeping
and Global Fund drugs could not be identified from drugs from
other sources.
Bulesa HC III - Bugiri
District
- Delivery notes for the months of February and April 2013 were
not availed for review.
- Delivery notes from NMS were general and Global Fund
deliveries could not easily be identified. Thus, comparisons of
orders versus actual deliveries could not easily be done.
Soroti Hospital - The store records system was manual and inadequate to
capture orders for drugs and other essential medical items,
deliveries, distributions and expiries of drugs.
- Although a list of expiry drugs was availed, it lacked values of
expired drugs and due to poor filing system, it could not be
ascertained which drugs were from Global Fund.
Pallisa Hospital - Delivery notes from NMS were general and Global Fund
deliveries could not easily be identified. Thus, comparisons of
orders versus actual deliveries in respect to Global Fund could
not easily be done.
- Stores returns/reports as per delivery cycles were not prepared.
Pallisa Town Council HC
III
- Delivery notes from NMS were general and Global Fund
deliveries could not easily be identified. Thus, comparisons of
orders versus actual deliveries in respect to Global Fund could
494
Health Center Observations
not easily be done.
- Stores returns/reports as per delivery cycles were not prepared.
Kamuli Police HC II - The health facility‟s system of record keeping was inadequate as
delivery notes reviewed were note well fastened in file folders.
They were loosely kept in a box and these could easily be
misplaced.
- Global Fund drugs and sundries could not be identified among
those from other sources.
The weaknesses mentioned above hinder delivery of medical services to the grass
root population.
The Accounting Officer explained that the health delivery system was designed to
serve smaller populations in the rural areas which have now expanded together
with the administrative units. As a remedial action, the Health delivery System was
being reviewed with a view to carrying out the necessary expansion.
I advised the Accounting Officer to ensure that standard record keeping forms are
distributed and utilized at the Health Centres. In addition, the Ministry of Health
should liaise with the Health Service Commission and District Service Commission
to improve on staffing in the Health Centres. Expired drugs should be stored
separately from drugs still in use. Besides, efforts should be enhanced to minimize
expiry of drugs.
c) Review of prior year audit issues
Below is the implementation status of the issues raised in the prior year:-
No Finding Recommendation Status of Implementation
1 Non-availability of
records in
relation to
Procurement
of health
products and
Management was
advised to
obtain and
avail the
records
relating to
All health Products and health equipment,
medicines & pharmaceutical
products are procured through
mechanisms called Voluntary Pooled
Procurement (VPP). The VPP agent
is tasked to deliver the above
495
supply
management
costs.
UGX.116,310,
182,000
the
procureme
nt and PSM
costs for
audit
scrutiny.
referred to health and medicine
products after undergoing a
tendering competitive process. All
transactions are made by the Global
fund secretariat on behalf of the PR
with consent/concurrence of the PR.
Audit queries regarding these
procurements have been ironed out
through convening meetings
between the OAG and GF country
mission as well as holding
teleconferences and all information
provided to the audit team.
Matter Addressed
The Procurement process was clearly
narrated during a
teleconferencing and records
submitted.
2 Non-Refund of Un-
utilized funds
from Sub-
Recipients.
UGX.107,872,
000
Management was
advised to
enforce the
requiremen
t of Sub-
Recipients
(SR)
refunding
the un-
utilized
balances to
the
Principal
recipient
(PR)
PR‟s has continued to recover un utilized
funds from SRs. Total of
UGX.107,909,265 has been
additionally refunded within this
current year and the process is still
on going.
All funds were refunded by the SRs.
3 Low Absorption of
Funds (funds
were
awaiting the
presentation
and
verification of
PSM costs
from NMS) –
USD.4,391,17
6
Management was
advised to
liaise with
NMS and
hasten the
process so
that the
funds are
used to
implement
the
planned
Verification of PSM cost from NMS was
carried out by PSM expert in
collaboration with Pharmacy. A
payment of funds totaling
USD.3,149,249.54 was effected to
NMS on 2nd September 2014. The
process of verification of NMS
invoices is continuous. Absorption
rate has reached 97%
496
activities.
4 Ineligible Expenditure
in respect of
individual
consultants‟
fees and
newspaper
adverts –
UGX.214,990,
000
Management to
stop
comminglin
g funds on
the Project
account
and to
include the
counterpart
funds in
the Project
budget
This has since stopped. All funds under
different Grants are spent
independently of other Grants.
Matter addressed
5 Status of Global fund
closed Grants
(HIV/AIDS)
Round I and
II closed but
no closure
procedures
were carried
out.
Management was
advised to
ensure that
the closure
procedures
are
undertaken
This was noted and has seen been effected
as advised. This is illustrated under
closure of the Affordable Medicines
Facility For malaria Grant (AMFm)
Matter addressed
6 Conditions to the grant agreement
i) By not later than
30th June
2012, the
principal
Recipient
(PR) shall
deliver to
the Global
Fund an
operations
Manual
Management was
advised to
expedite
the
Fulfillment
of the
outstanding
conditions
This was done and the approved operations
manual is in place.
Matter addressed
ii) The fixed asset
register is
updated
regularly and
submitted to the
global fund
An annual
verification and
inspection of the
fixed asset
register shall be
conducted and a
report of the
Management was
advised to
expedite
the
Fulfillment
of the
outstanding
conditions.
Currently, the PR maintains and updates the
fixed assets register. Additionally, the
Asset register is annually updated
with the condition of the Assets in the
various locations after the verification
exercise has been carried out.
Issues addressed
497
inspection shall
be submitted to
the GF
iii) The PR represents
and
acknowledg
es that the
regional
performanc
e
monitoring
teams will
be
subsumed
within
MOH. By
not later
than 31st
Dec 2012,
the PR shall
submit to
GF a
transition
plan
acceptable
to GF with
detailed
actions and
timelines of
how the PR
will take
over the
RPMTs
Management was
advised to
expedite
the
Fulfillment
of the
outstanding
conditions
Negotiations are still on-going between MoH,
MoFPED and Min. of Public Services.
Global fund to handle up to June 2015
In response, Management promised to continuously work towards providing
remedial actions/measures for the above issues. They indicated that by the end of
the current financial year, all the matters will have been resolved. I await the
outcome of Management‟s resolve to address the audit recommendations
25.19 UGANDA GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA
PROJECT - TUBERCULOSIS COMPONENT
a) Lack of Quarterly Progress Reports
498
In May 2014, the Ministry of Health through the Global Fund component on
Tuberculosis entered into a Memorandum of Understanding (MoU) with Makerere
University School of Public Health to carry out a National Tuberculosis Survey for
three quarters covering April 2014 to December 2014. Consequently, an advance
payment of USD.968,352.32 was made to the University for the activity. It was
noted that although the MoU stipulated that quarterly progress reports would be
submitted to assess the progress of the activity, no reports were produced. This
contravened the provisions of the MoU and could have hindered monitoring of the
results of the survey.
The Accounting Officer acknowledged and regretted the anomaly but added that
Management had communicated to the School of Public Health requesting for
quarterly reports in accordance with the MoU requirements.
I have advised the Accounting Officer to follow up the matter and ensure that
quarterly progress reports are prepared and submitted to enable proper
monitoring of the activity.
b) Un Implemented Activities
The Project Management planned a number of activities to be implemented during
the financial year under review. A review of the Global Fund TB component budget
performance reports revealed that while many of the planned activities were
implemented, a number of others remained outstanding. Management advanced
various reasons for the non-implementation as indicated in the table below:-
Code Activity Budgeted amount
USD
Management response
3.17 Provide
incentiv
es to 45
health
67,500 The activity did not go through the procurement
process because it involves payment of
allowances to incentivize the health
499
Code Activity Budgeted amount
USD
Management response
workers
in 5
PMDT
treatme
nt Units
workers working in the Programmatic
Management of Multi-Drug Resistance TB
Treatment units.
The requisition process commenced. However,
MDR health facilities had increased from 5
to 14 at the implementation. It therefore
required approval from GF Secretariat,
Geneva to pay all the 14. This has not
been secured yet.
3.8 Support TB
specime
n
referral
system
for
routine
surveilla
nce of
Drug
resistant
TB
36,468 All the invoices are processed for payment as they
are submitted.
Going forward, we shall advise Posta Uganda to
submit invoices on a bi-monthly basis to
ease processing payments
5.1.1 Support salaries
of
Uganda
Stop TB
Partners
hip
Staff-
4Staff
108,600 The MoU between TASO and the partnership fund
expired in June 2014. The process to get
an MoU between the MoH and USTP
commenced in July 2014 and its now in
the final stages at the Solicitor General‟s
Office.
5.1.3 Facilitate USTB
Monthly
and
quarterl
y
meeting
s
9,232.53 Implementation awaiting an approved MoU
between MoH and USTP which is at the
Solicitor General‟s Office.
5.1.4 Rents and Costs
for
USTP
24,712.48 Implementation awaiting an approved MoU
between MoH and USTP which is at the
Solicitor General‟s office
5.1.5 Insurance costs
for 3
vehicles
6,456.75 The vehicles to be insured were MOH Program
vehicles.
500
Code Activity Budgeted amount
USD
Management response
of USTP
5.1.6 Maintenance
costs for
3
vehicles
of USTP
1,485.13 The three vehicles to be maintained were MoH TB
program Cars.
There is a risk that non-implementation of planned activities may hinder the
achievement of the overall objective of the project.
I have advised the Project Management to address the causes of delays in
implementing project planned activities
25.20 EAST AFRICAN PUBLIC HEALTH LABORATORIES NETWORKING PROJECT
(EAPHLNP)
a. Funds not accounted for
Contrary to section 217 of the Treasury Accounting Instructions 2003, which
requires public officers to account for funds advanced to them within a period of
60 days, audit noted that UGX.20,520,000 out of the UGX.95,761,200 advanced to
various staff to undertake various project activities, remained un-accounted for.
Failure by staff to account for advances was attributed to management‟s failure to
enforce accountability procedures. Accordingly, I could not ascertain whether the
money was used for the intended purpose.
I have advised the project management to strengthen and enforce controls related
to accounting for funds and should ensure recovery of the outstanding amounts.
b. Doubtful Expenditure
UGX.10,857,000 was paid out to a local Hotel in January 2014 to provide hotel
services, but the expenditure was doubtful owing to the fact that the supporting
attendance list was a photocopy and had inconsistent dates on the payment
documents. While some documents indicated that the workshop was held for five
days from 23rd to 27th September 2013, the activity report attached to the
payment voucher indicated the activity was undertaken from 8th to 14th September
501
2013 (8 days). In such circumstances, there is a risk of expending funds for
services that were never supplied.
I advised the Accounting Officer to investigate the circumstances surrounding the
event with a view of ensuring that the intended objective was met. I further
advised him to always ensure that original documents are used whilst making
payments.
c. Un-acknowledged Statutory Remittances
i. Non deduction of Tax
A foreign firm was paid USD.116,152 for supply of medical laboratory equipment,
without deducting 15% withholding tax of USD.17,422 (Equivalent2 to
UGX.48,261,156), contrary to section 85(2) of the Income Tax Act, 1997, (as
amended). There is a risk of the project being subjected to penalties and fines
which will occasion loss of funds.
I have advised the Accounting Officer to endeavor to recover the tax and to
ensure that withholding tax is always deducted from suppliers of goods and
services to avoid penalties and fines from URA.
ii. Un-acknowledged remittances to NSSF
UGX.20,244,025 that was purportedly remitted to NSSF in respect of employee
contributions lacked acknowledgement receipts and in the absence of which audit
could not ascertain whether the said funds were actually remitted.
I have advised management to provide the necessary documentation for audit and
to always obtain official acknowledgement receipts for proper documentation and
accountability.
d. Status of Implementation of Project Activities
i. Loan Performance
A review of the loan status revealed that the loan whose closing date is projected
to be 30th March 2016 has had a low disbursement rate. Of the loan amount of
USD.10,100,000, only USD.5,919,345.74 (58.6%) had been disbursed by end of
2 Exchange rate as at 23rd Dec 2014 1USD = 2,770
502
the current financial year. It was also noted that USD.1,414,175.01 remained
unutilized from the funds disbursed for the year under review.
The low disbursement rate coupled with big unutilized balances does not only
affect the project implementation and attainment of the targets set, but may also
be an indication of prior project planning before the loans are disbursed.
The Accounting Officer explained that the bulk of the unexpended funds were in
relation to the Construction of the National TB Reference Laboratory at
USD.2,200,000, Renovation of Mbale & Lacor satellite sites estimated to cost
USD.650,000 and Operational Research, USD.455,100. The activities under
performed due to the delays to complete the Architectural Designs by the
Consultant and other procurement procedures. He further stated that the activities
had since commenced and will be completed within the Project life.
I have advised the project management to expedite the implementation of the
outstanding activities so as to improve on funds absorption and thus disbursement
rates, so as to attain the project objectives.
ii. Delayed Implementation of Project Activities
A review of the five year project work plan revealed that a number of civil works
had delayed, including;
Consultancy Services for design and Supervision for National T.B Reference Lab
and satellite labs (Including a laboratory infrastructure consultant). This was
supposed to be implemented between 2010 and 2013, however the project
progress report of March 2014 indicated that the construction started on
11/03/2014, many months after the intended timeline;
Consultancy Services for design and Supervision for 5 satellite Labs (Including a
laboratory infrastructure consultant). This was also supposed to be
implemented between year 2010 and 2013, but the progress report of March
2014 indicated that the architectural plans of the satellite sites had not yet been
finalized.
The project management team attributed the delays in execution of project
activities to long and slow procurement processes. The failure to timely implement
503
the project activities may hinder attainment of project objectives. The Accounting
Officer acknowledged the delay and explained that work was on course and will be
completed before Project closure.
I have advised the project management to expedite the works so as to ensure that
the implementation is in accordance with the project work plans.
e. Lack of Proper Authorization for use of Motor Vehicles
Best practices in the management of project assets call for proper authorization
before an asset such as a motor vehicle is released for official activities/work. This
strengthens internal controls over the project assets/vehicles. However, for the
year under review it was noted that such internal control measures were not being
implemented by the project.
Absence of formal authorizations may lead to mismanagement of project motor
vehicles and is an indicator of internal control weakness. The Project Management
acknowledged the anomaly and committed to institute authorization measures.
I have advised the Project management to institute asset management
measures for proper accountability of project assets.
f. Inspection of supply and delivery of the Gene X-pert machine
The project procured and distributed equipment for high drug resistant testing in a
number of hospitals including Jinja, Mbale, Lacor, Mbarara, Mulago and the
headquarters on Buganda Road. However, it was noted that, the equipment in
Mbale had failed and was non-functional.
Interview with management revealed that there were a number of samples that
had been stored in the queue pending processing and pressure was mounting as a
result of delayed release of results due to delayed testing. Delayed release of test
results may cause delays it treatment of patients which may be fatal.
Management explained that they were aware of the defects and arrangements
with World Health Organization (WHO) through which the equipment was
procured were underway to rectify the defects. In the short term, the Project was
arranging to procure a spare compartment to be delivered to Mbale site.
504
I have advised the Project Management to liaise with the respective stakeholders
to ensure that the equipment is repaired.
25.21 UGANDA HEALTH SYSTEMS STRENGTHENING PROJECT (UHSSP)
a) Funds not accounted for
i. Preparation of a long term family planning mentorship
UGX.33,532,000 was expended on the preparation of a long term family planning
mentorship activity for health workers in Jinja regional Referral hospital. However,
UGX.8,800,000 paid out to eight (8) purported participants as allowances through
their respective personal bank accounts was not accounted for, contrary to section
217 of the Treasury Accounting Instructions, 2003. In the circumstances, I could
not ascertain whether the expenditure was genuinely used for the intended
purpose.
Management acknowledged the anomaly which was attributed to a Circular from
the Office of the Permanent Secretary and Secretary to Treasury (PS/ST)
instructing Accounting Officers to transfer funds to participants‟ bank accounts.
This had a challenge of individuals who may not attend at all or attend fewer days
than paid for, but pledged to recover the funds through the officer who managed
the training.
I have advised the Accounting Officer to recover the funds from the concerned
officers and in future strengthen and enforce controls related funds accountability.
ii. Advances to staff
Regulation 65(1) of PFAR, 2003, requires all imprest funds to be retired as soon as
the necessity for their use ceases or on the last working day of the financial year,
however, UGX.10,515,333 (equivalent to USD.4,177.14) remained unaccounted
for.
In response, management stated that reminders had been sent to the concerned
officers but to no avail and was thus planning to recover the funds.
I await management‟s action in this regard.
iii. Vehicle Maintenance and Repairs
505
A total of UGX.7,692,154 (equivalent to USD.3,071.49) was incurred on repairs
and servicing of project motor vehicles during the year under review, however,
contrary to best practice, the repairs were not supported with post vehicle
inspection reports. In the absence of inspection reports, it was not possible to
ascertain whether the repairs and maintenance were satisfactorily done. I have
advised management to ensure that motor vehicle repairs and maintenance are
undertaken after pre-inspections have been carried out and post inspection reports
availed before effecting payments.
b) Donor Funding
i. Funds Disbursement
According to the Loan Agreement, the UHSSP project‟s funding is supposed to be
SDR 85.7 million (equivalent to USD.130 million) from the International
Development Association (IDA) of the World Bank and USD.14.4 million from the
Government of Uganda (GoU) over a 5 year period (2011-15). A review of the
project income and expenditure revealed that the cumulative project disbursement
as at 30th June 2014 was USD.70,456,145.82, representing about 54% of the total
expected project funding.
Given the low rate of funds disbursement and activity implementation, it is
doubtful whether the project will meet its intended objectives within the agreed
project period. Project Management acknowledged the low funds absorption given
the life on the Project left. I have advised the project management to strengthen
project implementation so as to increase disbursement of funds for better project
implementation and attainment of set objectives before the end of the project life.
ii. Delayed implementation of project activities
It was noted that a number of project activities that had not been undertaken
despite the project winding up in one year‟s time. The delayed implementation of
the planned activities may lead to failure to achieve the project objectives.
Management in response acknowledged the state of affairs and undertook to
ensure that all activities are executed before project closure. I have advised the
506
project management to expedite the implementation of project activities in order
to achieve the intended objectives.
c) Delivery of Equipment to General Hospitals and Health Centre IVs
Physical inspection of the various health facilities revealed the following anomalies:
i. Failure to replace medical equipment and Hospital Furniture
After the distribution of general, specialized medical equipment and instruments
under health infrastructure component was finalized, the National Committee on
Medical Equipment (NACME) pointed out some medical equipment that did not
meet specifications and had to be replaced; including: defibrillators, Ear Nose and
Throat (ENT) instrument sets, delivery and adult patient beds with mattresses;
bed side lockers, bowl stand, cupboard, instrument, cupboard, steel, lockable,
examination couch (gynaecology), filing cabinets and patient trolleys.
However, a physical inspection carried out in a number of Health facilities including
Iganga Regional Referral Hospital, Budaka HCIV, Kibuku HCIV and Budondo HCIV
revealed that the faulty equipment had not been replaced but were instead
repaired.
Failure to replace the equipment may result in constant breakdown of equipment
resulting in high repair costs. In the long run it may result in failure to achieve
value for money and thus compromising attainment of project objectives.
In response, the Accounting Officer explained that the Supplier had been tasked to
replace the equipment that did not meet the specifications and so far the patient
Trolleys had been replaced for all health facilities and modalities for replacement
of the remaining items were on course. I have advised the Accounting Officer to
ensure that the contractor replaces all the equipment that did not meet the
specifications.
d) Delivery of equipment to a non-operational General Hospital
Whereas management had resolved to deliver the equipment to operational health
facilities and that each delivery coincides with completion of civil works and
handover period, dispatch was made to one of the health facilities in Jinja District -
507
Buwenge General Hospital, whose buildings had not been completed. Because the
hospital was non-existent, the equipment was delivered to Buwenge Health Centre
IV. The equipment is being kept at the Centre‟s theatre.
Audit further noted that the works at Buwenge General Hospital have since been
abandoned, with the contractor‟s supervisor last visiting the site in December
2012. Through inquiries, it was also revealed that the abandonment of the site
was due to financial constraints arising from cost under estimation by the
contractor. The delivery of equipment to non-operational health units may result in
loss of funds and the project failing to achieve the intended objectives.
In response, the Project management stated that the Ministry of Health had
instituted a Team to analyse the usage, storage, condition and availability of
trained Staff for the Medical Equipment distributed under the Project and come up
with recommendations. I have advised management to ensure that the equipment
is reallocated to other eligible health facilities, to avoid obsolescence.
e) Non recording of equipment in the facilities‟ records
It was noted that equipment was delivered to health centres as allocated, however
all the health centre IVs that were visited had not recorded the equipment in their
stores books. Records such as stock cards and ledgers for the equipment were not
maintained. This was evident in Soroti General Hospital, Kibuku HC IV, Budaka HC
IV, Mbale Regional referral Hospital, among others. There is risk of loss of
equipment.
In response, the Project Management stated that a letter would be drafted for the
Accounting Officers instructing the health centres to dully record the equipment in
their books. I have advised the project management to enforce the recording of
equipment in the books in all the beneficiary health centres and hospitals so that
assets are safeguarded.
f) Un-used equipment
Most equipment delivered were not in use, for reasons ranging from lack of power
(since some health centres are not connected to the grid), lack of trained
personnel to operate lab and theatre equipment, manuals not issued to users, lack
508
of spare parts or accompanying items like oxygen, items delivered to wrong units,
theatres not operational. These were noted in Budondo HCIV, Buwenge HCIV,
Bugembe HCIV and Kumi HCIV among others. This state of affairs affects service
delivery.
In response, management stated that the Ministry has instituted a team to analyse
usage of medical equipment distributed by the Project and come up with
recommendations. I have advised management to ensure that all facilities
delivered to health centres are put to use so as to improve service delivery to the
populace.
g) Un-fitted equipment in some health facilities
Some health centre theatres were not operational; cases in point were Kumi
Health Centre and Apapai Health Centre, which were still under construction.
There were many incidences of equipment not installed for use, for example at
Princess Diana Health Centre, in Soroti. The new beds had not been fitted since
being delivered six months before.
In Serere Health Centre, there was no storage space and the equipment was being
kept along the corridors and in Iganga equipment like anaesthesia units,
autoclaves, incubators and lab equipment had not been fitted. Also noted were
instances of poor storage of equipment e.g in Budondo HC IV, where equipment
had gathered dust and had starting to rust. In Buwenge Health Centre IV, termites
had destroyed paper boxes in which the equipment had been wrapped.
Management in response stated that the Ministry had instituted a team to analyse
the usage and condition of the medical equipment distributed by the Project and
come up with recommendations. I have advised the project management to
ensure that all equipment is fitted/installed in all the beneficiary health centres so
that they can be utilised for health service delivery in order to realise the project
objectives.
509
26.0 UGANDA BLOOD TRANSFUSION SERVICES
26.1 Mischarge of Expenditure
Paragraph 40 of the Treasury Accounting Instructions, 2003, requires all virements
to be approved in advance by the Minister who may choose to delegate such
powers to the Secretary to Treasury. It was noted that UGX.27,880,704 in respect
of various activities was charged wrongly to item codes meant for other activities
resulting in misstatement of amounts expended on the affected item codes. This
implies that the financial statements are misrepresented with regard to the
mischarged amounts and the practice renders the budgeting process redundant.
The Accounting Officer explained that the mischarge of expenditure occurred in
the fourth quarter when the remaining funds of the financial year had already
been received and yet the Treasury Accounting Instructions do not provide for
seeking virement retrospectively once funds are received.
I have advised the Accounting Officer to streamline the budgeting process and to
subsequently ensure that payments are correctly charged on the item codes to
enable proper implementation of the entity‟s programmes.
26.2 Staffing Gaps
A review of UBTS‟ establishment records revealed that out of the establishment of
116 staffing gaps, only 98 were filled, leaving 16 vacancies as shown in the table
below. The four Regional Blood banks of Gulu, Fort portal, Arua and Mbale were
greatly affected by this understaffing. For example; Arua Regional Blood Banks in
particular lacked a Laboratory Technician and Nurse to carry out day to day
operations.
Staffing gaps in the regional blood banks may result in inefficiencies in operations
thus affecting performance and service delivery of the Blood Bank. The table
below refers;
Post Title Salary
Scale
Establishment Filled
Posts
Vacant
Posts
Principal Medical U2 6 5 1
510
Post Title Salary
Scale
Establishment Filled
Posts
Vacant
Posts
Officer
Blood Donor
Recruiter
U4 14
12 2
Donor Clerk U7 18 17 1
Lab Assistant U7 24 22 2
Medical Records
Assistant
U7 11
9 2
Driver U8 40 33 7
Receptionist U8 1 0 1
Total 114 98 16
The Accounting Officer explained that the Health Service Commission was in the
process of recruiting the staff to fill the vacant positions.
I have advised the Accounting Officer to follow up with the Health Service
Commission to ensure that the recruitment process is concluded expeditiously.
26.3 Boarding off Obsolete Assets
Paragraph 705 of the TAI, 2003 requires that where it is considered that
inventories, vehicles, plant, equipment have reached the end of their useful life,
and are beyond economical repair or are unserviceable for any other reason such
items should be recommended for boarding off.
However, an audit inspection carried out at the UBTS yard revealed a number of
old vehicles in a state of disrepair that had not been boarded off. Although the
Transport Officer had brought the matter to the attention of the Accounting
Officer in April 2013 and the Contracts Committee considered it in August 2013,
no action was taken thereafter to have the vehicles disposed off. There is risk of
further deterioration in value of the vehicles.
The Accounting Officer explained that an adhoc board of survey committee was
constituted to carry out the physical inspection and evaluation of the old vehicles
and obsolete stores for purposes of boarding off. The committee met in June 2014
511
and agreed on activities and the facilitation required for undertaking the physical
inspections. The committee was scheduled to complete this task in quarter three
of the financial year 14/15.
I have advised the Accounting Officer to expedite the process of disposal of
obsolete assets to avoid further loss in value.
26.4 Shortage of Storage Space
It was noted that there was shortage of storage space for inventories at UBTS.
Some inventories were kept in space that was earlier designated as washrooms.
There is a risk of inventories getting spoilt due to poor storage. Pictures below
illustrate.
Inventories blocking the ventilation
space.
Inventories stored in place
earlier designed for toilet use
The Accounting Officer explained that management would continue to liaise with
MoFPED for additional funding to commence the construction of the centralised
medical store at Nakasero Blood Bank Headquarters in the next financial year
(2015/2016).
I await the outcome of management‟s actions towards improving the storage
problem at the Blood Bank.
512
26.5 Status of Implementation of the planned activities
A review of implementation of activities revealed that although the Blood Bank
received 100% of its budgeted funds, a number of activities detailed in the table
below were partially implemented.
Activity Summarized
Status
Cause of Non
Implementation
Expand Blood Transfusion Infrastructure;
Partly
Implemented
Lack of Funding
Furnish and equip the newly constructed
Gulu and Fort Portal Regional blood
banks;
Partly
Implemented
Lack of Funding
Procure four vehicles for blood collection
and continue construction of central
stores at the Headquarters
Partly achieved
Vehicles – Delays in
Procurements
Stores – Inadequate
Funds
Operate an active nationwide quality
assurance program that ensures blood
safety –from vein to vein by; testing all
blood for transfusion –transmissible
infections (TTIs) – HIV; Hepatitis B; C;
and Syphilis in addition to blood
grouping;
Partly achieved A Programme to
Accredit UBTS Blood
Products has been
embarked upon –
Quality Assessment
On-going to identify
quality gaps. Initial
Funding is provided by
Donors (PEPFAR)
Strengthen the organizational capacity of
UBTS to enable efficient and effective
service delivery; through mentoring and
training of UBTS staff
Partly achieved On – going/ continuous
process.
Some CPD Conferences
for staff are funded
513
It was further noted that UBTS had unfunded priorities which included;
Creation of 2 additional blood collection teams.
Procurement of office furniture and equipment for the newly constructed
Regional Blood Bank (RBB).
Construction of a RBB in Moroto.
Accreditation of UBTS, Rent for office space at Arua RBB and;
The shortfall of UGX1.2bn to National Medical Stores to procure adequate
supplies and cover handling charges.
The newly constructed library building lacked furniture. This hindered the
utilization of the facility.
The Accounting Officer explained that management would continue to negotiate
for additional funding from MoFPED so that furniture and fittings are procured for
the newly constructed regional blood banks and the construction of new regional
blood facilities at identified sites, including a centralized Medical Store at Nakasero
Headquarters.
I await the outcome of management‟s actions towards negotiating for more
funding for the identified unfunded priorities.
Non-funding of priorities may lead to failure by UBTS to perform its functions and
eventually not achieving its objectives.
514
26.6 SUPPORTING NATIONAL BLOOD TRANSFUSION SERVICE IN THE
IMPLEMENTATION AND STRENGTHENING OF BLOOD SAFETY
ACTIVITIES IN UGANDA
a) Compliance With The Financing Agreement And Gou Financial
Regulations
It was noted that management had in all material respects complied with the financing
agreement provisions and Government of Uganda financial regulations.
b) General Standard of Accounting And Internal Control
c) Exceeding Budget lines
The cooperative agreement requires the project management to implement activities
within the budget lines that have been provided and approved. Audit however noted
that the expenditure budget line for Fringe benefits had been exceeded during the
budget implementation. This was as a result of inadequate reviews and monitoring of
the actual expenditure against the budget which also led to some activities not being
implemented as planned. The Table below refers.
Expenditure Item
Actual
Expenditure
Budget Variance
USD USD USD
Fringe benefits 37,353.83 27,152 10,201.83
In their response, management atttributed the over expenditure on the fringe benefits
on insufficient allocation at the time of budgeting.
I have advised management to adhere to the approved budget lines during
implementation of project activities.
d) Employee Personnel Files
It is good management practice to have up to date and complete performance
appraisal records for all employees prior to renewal of employment contracts. Audit
515
noted that personnel files of eight (8) PEPFAR project employees lacked authentic or
up to date staff performance evaluations.
This was caused by failure by management to enforce the requirement of periodic
performance evaluation. This leads to inadequate or inappropriate assessment of
employee contribution towards the success of project activities.
I have advised management to ensure that proper and complete performance
appraisals are undertaken for all project employees and that documentary evidence is
maintained on the individual staff files.
e) Late Income Tax (PAYE) remittance
The Income tax Act of the Republic of Uganda requires employers to remit income tax
charged on employees by the 15th day of the following calendar month to which it
relates. Audit however noted that UBTS made late remittances of the Income Tax
(PAYE) returns for the months below;
Month Amount (USD) Deadline Date Date Remitted
October 2012 816.27 15th Nov 2012 6th May 2014
November 2012 795.95 15th Dec 2012 24th Sept 2013
December 2012 795.95 15th Jan 2012 24th Sept 2013
January 2013 795.95 15th Feb 2012 9th Oct 2013
February 2013 800.75 15th Mar 2012 10th Sept 2013
March 2013 821.07 15th Apr 2012 10th Sept 2013
April 2013 821.07 15th May 2012 10th Sept 2013
May 2013 821.07 15th June 2012 31st July 2013
June 2013 821.07 15th July 2012 24th July 2013
Delays in remittances of the statutory obligations could result in fines and penalties
being imposed by the tax Authority. Management explained that the remittances were
made at the time of salary payment and that the obligations were remitted within the
516
statutory deadlines, however there were delays in filing returns and obtaining
acknowledgement receipts.
I have advised management to adhere to statutory deadlines when remitting statutory
deductions and to timely file returns.
27.0 BUTABIKA MENTAL REFERRAL HOSPITAL
27.1 Mischarge of Expenditure
Treasury Accounting Instructions require that transactions should be recorded in
the books of account using the Government of Uganda Chart of Accounts as
prescribed by the Accountant General. The detailed explanations for each account
prescribe what expenditures should be charged on the account.
It was noted that out of the total hospital operating expenditure of
UGX.8,718,327,417, UGX.74,863,427 (0.9%) was charged on codes other than
those under which it was appropriated leading to mischarge of expenditure on
these accounts. The financial statements are misrepresented to the extent of the
mischarge.
The Accounting Officer regretted the anomaly and attributed it to under/over
estimation of some items during the budgeting process. However, during the
bidding process, actual costs varied from the estimates leading to deficits and
surplus on some items. It was not possible to obtain authority for a virement from
Permanent Secretary/Secretary to the Treasury, as the funds had already been
released and uploaded on IFMS.
I have advised management to streamline the budgeting process and, ensure that
payments are correctly charged on the item codes to enable proper
implementation of the Hospital‟s programmes.
27.2 Un authorised additional funding above contractual figures
517
Regulation 105(1)(c) of PPDA Regulations, 2003 prohibits procuring and disposing
entities from initiating any procurement proceedings or activities for which funds
are neither available nor adequate, except where the Permanent
Secretary/Secretary to Treasury (PS/ST) has confirmed in writing that the required
funding shall be made available.
Review of the procurement records and the consolidated procurement plan
revealed that the Hospital estimated to buy a dental chair at a cost of UGX.40M
and to fence a football pitch and private wing of the hospital at a cost of
UGX.60M. It was however noted that the cost of the dental chair was
UGX.67,200,000 while that of fencing the football pitch and private wing was
UGX.115,969,990. I was not provided with evidence of confirmation of additional
funding.
In response, the Accounting Officer explained that the purchase of these items
was under budgeted in comparison with the actual contract values, while the
transport equipment – Ambulance, was over budgeted. Given the need to fence
off the football pitch to secure land from encroachment and the high numbers of
both in and out patients demanding for dental services, the savings from the
Ambulance were used to top-up the under budgeted items.
I advised the Accounting Officer to ensure that the Hospital operates within the
accounting warrant or else seek for authority to spend over and above the
budgeted amounts in a timely manner.
27.3 Staffing gaps in Butabika NMRH
Butabika National Mental Hospital staffing was restructured in 1999/2000 as part
of the overall restructuring of Government and the Ministry of Health resulting
into the current establishment of 433 staff of which 346 positions are filled
leaving 87 vacancies. Analysis of the current patient load revealed a need for
filling of the vacancies and further review of the staffing structure given the nature
of patients who require dedication of more time by the medical staff. The table
below refers;
518
S.no Nature of
clinic
Planned
average No of
patients
Current average
No of patients
Increase in
average No of
patients
Period
1. In patients 550 800 250 Daily
2. out-patients
clinic
27,500 40,000 12,500 Annually
3. mental clinic 16,875 27,000 10,125 Annually
Understaffing and inadequate staff establishment may result into deterioration of
delivery of medical services to the patients.
Management indicated that a proposal for a new structure of 762 staff had been
forwarded to the Ministries of Health and of Public Service.
I have advised the Hospital Management to follow up with the line Ministry and
other stake holders to ensure that the staffing requirements of the Hospital are
addressed.
28.0 UGANDA CANCER INSTITUTE
28.1 Mischarge of Expenditure
Paragraph 400 (a) of the Treasury Accounting Instructions 2003 stipulates that all
government transactions shall be recorded in the books of account applying the
Government of Uganda chart of Accounts as prescribed by the Accountant
General. The accounting officers shall ensure that all financial instructions are
properly coded.
It was however noted that out of the total payments of UGX.7,141,831,790 for the
financial year, an amount of UGX.656,275,672 was charged on codes other than
those for which the funds were appropriated resulting into unauthorized diversion
of funds. The practice is an indication of breakdown of controls in the budget
implementation process.
519
In response, the Accounting Officer explained that funds were diverted to outreach
activities, patients‟ food, non medical sundries and detergents in order to ensure
continuity of service since the appropriated amounts were inadequate.
I advised the Accounting Officer to always liaise with the Ministry of Finance,
Planning and Economic Development and ensure adequate allocation of funds to
the essential items.
28.2 Nugatory Expenditure
The institute incurred nugatory expenditure of UGX.448,408,158 as follows;
a) Idle charges
Idle Charges amounting to UGX.320,924,000 were paid to M/s Ambitious
Construction Company Limited vide payment voucher number DB02/2/14 and EFT
No. 363329 on 10th February 2014 as a result of delayed handover of the site
because of a disagreement between Uganda Cancer Institute and Mwanamugimu
Nutrition Unit over location of the building. This occurred when the contractor‟s
materials, equipment and labour had already been mobilized and availed at the
site.
The expenditure would have been avoided if proper identification of the site had
been done by the Institute prior to signing of the contract.
In response management stated that the change of construction site was directed
by the Ministry of Health after an appeal by Mwana Mugimu Unit.
I advised the Accounting Officer to always make adequate consultations with all
stakeholders before embarking on projects that may have costly financial
implications.
b) Interest Costs
520
A sum of UGX.127,484,158 was paid to M/s Ambitious Construction Co. Ltd as
interest charges due to delayed payment on interim certificates 1-6 and 6-8 for
construction of the Cancer Ward.
This expenditure could have been avoided if realistic payment terms and
confirmation of availability of funds were made before contracting the firm.
In response, the Accounting Officer explained that the interest accumulated
between the period of closure of the financial year 2012/2013 and the beginning
of financial year 2013/2014 when the funds for the new year had not yet been
realised.
I advised the Accounting to ensure that in future, realistic payment terms are
included in the contract agreements and commitments are made only when funds
are available.
28.3 Expired drugs
An inspection conducted in the Institute‟s drug store revealed that an assortment
of drugs worth UGX.425,825,877 had expired. Expired drugs represent a loss to
the public and further loss may be incurred in the process of their destruction.
The expiry was attributed to long procurement processes and short shelf lives of
some of the drugs.
In response, the Accounting Officer explained that the procurement of medicines
was a function of National Medical Stores (NMS) and some medicines were
supplied in large quantities that could not be consumed rapidly.
The Accounting Officer further explained that National Drug Authority had been
contacted to have the expired medicines incinerated.
I advised the Accounting Officer to streamline liaison with NMS so as to minimize
expiry of drugs.
28.4 Budget Performance
521
a) Under collection of Non-Tax Revenue (NTR)
Whereas the Institute had estimated to raise UGX.900,000,000 from its Non-Tax
Revenue sources only UGX.580,670,600 was actually raised resulting into under
collection of UGX.319,329,400. It was further noted that all financial transactions
relating to NTR were recorded manually and bank reconciliation statements were
not prepared regularly.
The weaknesses above make the process not only tedious but also prone to
inaccuracy and errors in the revenue collection.
Management attributed the under collection of NTR to failure to operationalize
medicine sales in the private wing. It was further stated that a computerized
system of revenue collection and recording would be procured.
I advised the Accounting Officer to ensure that bank reconciliations are prepared
monthly and reviewed by a senior staff in addition to procuring appropriate
accounting software for revenue collection and recording.
28.5 Non Tax revenue not receipted
Regulation 49(1) of the PFAR 2003 requires a receipt in the prescribed form to be
issued immediately for any public moneys received; and when the payer presents
himself or herself in person, the receipt must be handed to him or her at once.
It was however noted that, direct bank deposits amounting to UGX.45,495,600
lacked acknowledgement receipts.
There is a risk of understatement of revenue collections.
In response, the Accounting officer stated that some institutional clients remitted
funds to the bank directly for their staff and there was delay in reconciling the
payments with actual clients.
I advised the Accounting Officer to ensure the said revenue is receipted to
safeguard the revenue.
28.6 Irregular Amendment of contract
522
Regulation 262 (1) of the Public Procurement and Disposal of Public Assets
Regulations, 2003 defines an amendment to a contract as a change in the terms
and conditions of an awarded contract. Sub-regulation (5) states that no individual
contract amendment shall increase the total contract price by more than fifteen
percent of the original contract price or cumulatively by more than 25%.
It was however noted that the entity amended the contract referenced as
UCI/WRKS/09-10/00081 entered into with M/s Ambitious Construction Co. Ltd for
the Construction of the 5 – Level cancer building at an original contract price of
UGX. 5,783,789,753 to 6-Level Cancer Ward Building with an additional cost of
UGX. 2,197,609,659. The total contract price was thus increased by 37.9% of the
original contract price contrary to the aforementioned regulation. The practice
contravenes regulations and distorts procurement planning. It also disadvantages
other service providers who were not offered opportunity to bid for the entire
works thereby undermining the principle of transparency and competitiveness.
In response, the Accounting Officer explained that guidance was sought from
PPDA and the Solicitor General. However, the retrospective approval sought from
PPDA was rejected.
I advised the Accounting Officer to always follow PPDA regulations in relation to
variations.
28.7 Failure to operationalize the New Cancer ward
It was noted that despite official handover of a new Ward, there was no
observable evidence that the Cancer Institute had put it to use.
Physical inspection revealed overcrowding of patients in the existing wards as
indicated below.
Ward Planned Capacity Current Capacity
Lymphoma Treatment Centre (LTC) 32 Over 50 patients
Solid Tumor Centre (STC) 24 Over 30 patients
Private ward 10 Over 15 patients
523
In response, the Accounting Officer explained that the use of the new ward was
dependent on installation of diagnostic equipments and furnishing which shall be
acquired in a phased manner with effect from 2014/2015 financial year.
I advised the Accounting Officer to liaise with relevant stakeholders and expedite
the process of equipping the new Cancer Ward in order to alleviate the problem of
overcrowding of patients.
28.8 Repair of Motor Vehicles
The Institute carried out repair of vehicles at a total cost of UGX.19,486,696 of
which Motor Vehicle UG 4016M was allegedly repaired at a cost of
UGX.15,470,600. The following anomalies were noted;
There were no pre -inspection reports before the vehicles were referred to the
garage
There were equally no post-inspection reports provided after the alleged
repairs.
Without pre and post repair reports, there was a possibility of inflation of repair
costs.
In response, the Accounting Officer explained that vehicle UG 4016M was grabbed
by security personnel on its way to the Institute after which it was involved in an
accident while still under their care.
I advised the Accounting Officer to ensure the pre-and post inspection reports
from the Ministry of Works together with the police report are submitted for
verification.
524
29.0 UGANDA HEART INSTITUTE
a) Outstanding Payables
Included in the payables under Note 26 was a sum of UGX.207,840,052 for goods
and services, and UGX.197,576,992 for equipment all of which amounted to
UGX.405,417,044. It was noted that the payables accumulated during the year in
contravention of the Commitment Control System. The Institute risks litigation and
a bad reputation over failure to settle obligations in a timely manner.
Management attributed the accumulation of payables to an increase in the
quantities of sundries and equipment required to meet the growing number of
heart patients.
I advised management to always make realistic budgets taking into account the
demographic factors and disease prevalence rates.
b) Short fall in Non-Tax Revenue Collection
Out of the budgeted NTR of UGX.2,850,000,000 only UGX.2,461,193,370 was
received resulting in a shortfall of UGX.388,806,630. As a result, planned activities
such as intensive care admissions were limited. There is a risk of increase in
deaths of patients requiring intensive care who are not adequately cared for.
The Accounting Officer attributed the NTR shortfall to limitation in admissions in th
pravate wing due to inadequate space. Shortfall in NTR negatively impenges on
the effective delivery of Health care services.
I advised management to expedite the process of expanding facilities for
admission of patients.
c) Physical Performance of the Institute
Review of the Institute‟s workplan for 2013/2014 revealed significant variances
between planned and actual physical performance regarding clinical, diagnostic
and surgical services as indicated in the table below:
525
Clinical Services
Activity Planned Output Achieved Comments/ Remarks
Outpatient attendances 10,000 13,561 Increased number of patients
General Admissions 1,000 1,372 Increased number of patients
Intensive Care Unit Admissions 180 107 Minimal bed capacity
Coronary Care Unit Admissions 500 495 Increased number of patients
Endoscopy 80 0 Machine break down
Stress Test 260 0 Inadequate Specialist skills
Diagnostic services
Echocardiography (ECHO) 12,000 8,028 Machine failure, (A new machine
bought in the mid-year)
Increased activities
Electrocardiography (ECG) 11,000 6,599 Inadequate number of machines
and increased activities
Holter Monitoring 180 Increased number of patients
Surgical services
Closed Heart and Thoracic
Surgeries
240 174 Most children required
operations, less costly
Open Heart Surgeries 100 37 Very costly to be done yet
required highly skilled
personnel
Cath-Lab Procedures 172 Limited by sundries
Outreache to RRH 14 13 Need for clinics in RRH
Outreache to facilities 10 9 More public awareness needed
Research publications 4 5 Including PhD Thesis
526
The increase in patient numbers coupled with inadequate facilities impaired the
effectiveness of service delivery.
Management indicated that a new Heart Institute would be built under the Cardio
Thoracic diseases Project to be funded by the Islamic Developement Bank (IsDB).
This is expected to address the shortage of facilities.
I advised the Accounting Officer to ensure implementation of the project without
delay to enable improvement in service delivery
30.0 MULAGO REFERRAL HOSPITAL COMPLEX
30.1 Mischarge of Expenditure
Paragraph 400 (a) of the Treasury Accounting Instructions (TAI), 2003, requires all
transactions to be recorded in the books of account applying the Government of
Uganda chart of Accounts as prescribed by the Accountant General. In addition,
paragraph 156 of TAI, 2003 require expenditure to be charged in accordance with
the appropriation of funds to the items by Parliament. It was however, noted that
UGX.1,756,710,500 out of the total actual expenditure of UGX.47,774,796,289 was
not charged under the correct item codes leading to mischarge of expenditure.
Mischarge of expenditure is an indication of a breakdown in budgetary control and
leads to misrepresentation of information in the financial statements.
I have advised the Accounting Officer to streamline the budget implementation
process to ensure expenditure is charged in accordance with the appropriation by
Parliament.
30.2 Non-Disclosure of Receivables
The Accounting Officer is responsible for the preparation of financial statements in
accordance with the Financial Reporting Guide, 2008, issued by the Accountant
General. Section 2.5.18 (viii) of the Guide - Statement of arrears of revenue,
requires the Hospital to disclose revenue billed but not collected by the end of the
financial year, so as to provide additional information to the users.
527
A review of the Private Patients Scheme records revealed that funds totalling
UGX.1,256,811,309 that were receivable by year end were not disclosed in the
financial statements (memorandum statement of Arrears of Revenue).
Also noted was that no efforts were being made to collect the debts. The debtors‟
ageing list was also not availed for audit.
Failure to disclose revenue billed but not collected, exposes the Hospital to a risk of
loss of revenue and the financial statements are misstated to the extent of
undisclosed receivables. The non-disclosure of Revenue is also contrary to the
Financial Reporting Guide, 2008 while absence of the aging list makes it difficult to
follow debts that are overdue.
The Accounting Officer explained that the services were rendered to the clients who
did not pay their dues during the financial year and that in line with the prudence
concept, the recognition of revenue is done when the funds are received and not
when services are rendered. He hastened to add that the Non-Disclosure of
Receivables was to avoid overstatement of assets.
I advised the Accounting Officer to follow the prescribed Reporting Guide, and in
case of any significant departure to seek the Accountant General‟s approval.
30.3 Inadequate Control over the utilisation of Utility Services
Section 8 (2) and (3) (a) of the Public Finance and Accountability Act, 2003 state
that the Accounting Officer shall have control and be personally accountable to
Parliament for the regularity and propriety of the expenditure of money applied by
an expenditure vote and shall ensure that adequate control is exercised over the
incurring of commitments.
The Hospital reported payables of UGX.8,901,380,582 at the end of the financial
year which was a significant increase from UGX.1,704,626,602 reported in the
previous year. The biggest portion of these payables constituted of unpaid utility
bills of UGX.8,539,720,698 (water UGX.4,779,837,982 and Electricity
UGX.3,759,882,716).
528
It was noted that other independent institutions such as Makerere University College
of Health Sciences, Infectious Diseases Institute (IDI), Uganda Heart Institute,
Uganda Cancer Institute, Baylor College, Dental School, Makerere University John
Hopkins University (MUJHU), The AIDS Support Organisation (TASO), Makerere
Joint AIDS Programme (MJAP) and others including banks, churches, canteens and
restaurants were connected to the Hospital utility meters and yet there was no
evidence that they contributed to settlement of the bills.
The cause of the anomaly was lack of Memoranda of Understanding (MoU) with
these institutions and independent utilities‟ meters, to enable separate billing by the
utility companies.
The accumulation of utility arrears by the Hospital is reaching unprecedented levels
which may be difficult to settle within the Hospital‟s current budget settings. There
are also risks associated with the disconnections by the utility companies.
I advised the Accounting Officer to make adequate provisions in the budget to pay
the outstanding arrears. I have also advised him to separate the various
independent institutions from the Hospital‟s meters so as to reduce on the hospital‟s
utility bills.
30.4 Un-acknowledged statutory deductions
Section 123(1) of the Income Tax Act CAP 340 of the laws of Uganda, 2000,
requires a withholding tax agent to pay to the commissioner any tax that had been
withheld or that should have been withheld within fifteen days after the end of the
month in which payment subject to withholding tax was made.
A review of the payment records revealed that, UGX.1,867,853,563 comprising of
withholding tax of UGX.1,060,315,674 and Pay As You Earn (PAYE) of
UGX.807,537,889 lacked evidence of receipt by the Uganda Revenue Authority
(URA).
The anomaly was attributed to laxity by management to make follow up on
acknowledgement receipts for the payments made. There is a possibility that the
529
funds may not have been remitted to the tax authority and the Hospital may be
exposed to risk of penalties due to non-compliance with the law.
I advised the Accounting Officer to ensure that the remittances reached URA and
that the acknowledgment receipts are obtained from URA as evidence that the
money reached.
30.5 Staffing Gaps
A review of the approved establishment of the Hospital revealed that out of the
approved posts of 1,477 only 1,290 (88%) were filled leaving 187 (12%) vacancies.
It was also noted that the approved staff establishment was at variance with the
payroll for the month of June 2014 which indicated 1,842 staff were paid.
Inadequate staffing makes it difficult for the Hospital to achieve its strategic
objectives and also affects the quality of service delivery. The rate at which the
vacancies are being filled doesn‟t match the current requirements and developments
at the hospital.
Management explained that during the Financial Year 2013/14, the hospital made
efforts to fill some of the vacancies basing on the available wage bill budget. A total
of 89 positions were filled. The remaining vacancies with an estimated wage
requirement of UGX.1,646,623,656 could not be filled within the medium term
because of the constrained wage budget. The vacancies therefore remain a non-
funded priority.
I advised the Accounting Officer to liaise with the Ministry of Public Service and the
Health Service Commission to consider recruitment of more staff to fill the existing
vacancies to enable the Hospital attain its objectives.
30.6 Inadequately Funded Commitment on Construction of 100 Units of Staff
Houses (2 Flats) at Mulago Hospital
Section 59 (2) of the Public Procurement and Disposal of Public Assets Act, 2003
states that procurements or disposals shall only be initiated or continued on the
530
confirmation that funding, in the full amount over the required period is available or
will be made available at the time the contract commitment is made.
Contrary to the above, the Hospital entered into a contract with a Local Construction
firm to construct 100 Units of Staff Houses at a contract sum of
UGX.17,453,287,500 with a commencement date of 24th October 2013 and
completion by 18th October 2015. However, review of the approved budget for the
financial year under review revealed that only UGX.3,000,000,000 was provided for
residential buildings. By the time of the audit, UGX.2,980,809,498 had been paid to
the contractor for the certified works, leaving UGX.14,472,478,002 outstanding
pending subsequent interim payment certificates. There was no evidence to show
that there was commitment for funding of the project over the three years. There is
a risk of failing to settle the interim payment certificates submitted by the
contractor.
There is also a risk of accumulation of domestic arrears contrary to commitment
control policy.
The Accounting Officer explained that management had ring fenced all available
capital budget allocation on Medium Term Expenditure Framework (MTEF) of UGX.5
billion in the two financial years 2014/15 and 2015/16 to this project and also hoped
that Ministry of Finance, Planning and Economic Development (MoFPED) would
agree to increase the MTEF capital budget provision by UGX.4 billion in the two
financial years, so as to have this project completed.
I advised the Accounting Officer to source for adequate funding for the project well
in time, to avoid accumulation of domestic arrears.
30.7 Payment of Advances to Individual Employees Personal Bank Accounts
Paragraphs 227, 228 and 229 of the TAI, 2003, state that all payments should be
made by the Accounting Officer directly to the beneficiaries. Where this is not
convenient an imprest holder shall be appointed by the Accounting Officer with the
approval of the Accountant General. It also requires that the imprest funds must be
accounted for promptly.
531
It was noted that UGX.1,099,484,885 was advanced to various staff through their
personal bank accounts to implement a number of activities. Though the funds were
accounted for, the practice is susceptible to abuse and can easily lead to loss of
public funds. This anomaly was attributed to a weak internal control system.
I advised the Accounting Officer to always make payments directly to service
providers procured in accordance with the prescribed regulations. Official advances
should be paid to designated cash agents for ease of accountability.
30.8 Direct Procurements
Section 46 of the PPDA Act 2003, requires all procurement and disposal to be
conducted in a manner that maximizes competition and ensures attainment of value
for money. It was noted that UGX.504,358,000 was paid to various staff to procure
items and provide services instead of using pre-qualified suppliers. Value for money
and benefits of competition might not have been achieved.
This could be attributed to disregard of procurement legislation by management and
inadequate planning by the user departments and the PDU.
I advised the Accounting Officer to always engage prequalified providers in order to
encourage transparency and competition.
30.9 Irregular Procurements
Section 29 of the Public Procurement and Disposal of Public Assets Act, 2003 gives
powers to the Contracts Committee to authorize:-
the choice of a procurement and disposal procedure;
solicitation documents before issue;
award of contracts in accordance with applicable procurement or disposal
procedures as the case may be.
It was noted that contracts worth UGX.128,956,377, were awarded to various
service providers without approval of the procurement method by the Contracts
Committee. In certain cases, evidence of quotations from at least three prequalified
service providers were not available. In one case regarding the contract awarded for
532
supply of a warmer machine worth UGX.53,100,000, the Solicitor General‟s approval
was lacking.
Failure to abide by the procurement Laws makes the procurements irregular and
could negatively impact on the quality of goods or services procured.
Management explained that the payments were made to staff in the emergency
situations that required urgent fixing which included; maintenance and repairs of the
Hospital‟s dilapidated structures and machinery like sewage lines and leakages.
I advised the Accounting Officer to ensure that the Contracts Committee is always
involved in all procurements.
30.10 Procurement of Parking Management Services
Sec. 58 of the PPDA Act, 2003 requires a PDE to plan its procurements and disposals
in a rational manner. A review of the procurement of parking management services
at the hospital revealed the following anomalies;
a) The requirement for parking management services was not included in the
Hospital‟s Annual Procurement plan for the financial year 2013/2014 and was
instead treated as an emergency procurement.
b) The contracted firm was required to pay to MNRH a monthly fee of
UGX.31,300,000 for three years effective July 2013, of which the hospital would
reimburse the contractor UGX.5,727,900 per month, to recover costs of park
construction. However, no record of receipts or re-imbursements was provided
for audit review.
c) There was no evidence of monitoring and evaluation of the contract
performance.
Without proper records of revenue and re-imbursements, there is a risk of under
declaration of funds and possible misrepresentation of financial statements.
Management acknowledged the anomaly and explained that it was no longer
necessary to have a provider charging parking fees given the anticipated
renovations funded by ADB. However, because of safety requirements during this
533
period when vehicles are parked outside the hospital premises, management opted
to have a provider setting up a parking for safety of the vehicles.
I advised the Accounting Officer to ensure that the Hospital effectively plans for all
procurements to avoid emergency situations in future.
30.11 Inadequate Accounting Software for Private Patients Scheme
Paragraph 219 of the TAI, 2003, requires Accounting Officers to account for all
revenues received in form of Appropriation in Aid, by maintaining a separate ledger
account for each item of revenue in accordance with the chart of accounts.
It was however observed that the quick books software used by the Hospital in the
collection of Non Tax Revenue (UGX.6,997,363,939 during the financial year) did
not code the various transactions in accordance with the GoU chart of accounts.
This led to manual interventions to code the transactions outside the system which
is susceptible to error. The users of the software were not adequately trained to use
the software for the purpose of revenue collection. Meanwhile UGX.1,256,811,309
reported in the financial statements as receivables was not supported with a list of
invoiced patients who had not paid at the year end.
Failure to follow the GoU chart of accounts may result in mischarge of revenue and
thus inaccurate disclosures in the financial statements. The anomaly could have
been caused by inadequate specifications to the vender which led to acquisition of a
system not compatible to the GoU chart of accounts.
Management explained that the Treasury Department at MoFPED was in the process
of acquiring a module to link the system with IFMS for proper management of NTR.
They were meanwhile using quick books for their record keeping purposes.
I advised the Accounting Officer to ensure that the software is upgraded to ensure
that revenue collections are properly coded and limit the human intervention in the
process.
30.12 Non-disposal of unused Hospital Beds
534
Regulation 2(1) of the Public Procurement and Disposal of Public Assets (Disposal of
Public Assets) Regulations, 2014 requires an Accounting Officer in each financial
year to cause the public assets of a procuring and disposing entity to be reviewed,
to identify the public assets for disposal in the following financial year.
It was noted that when the hospital acquired 100 new hospital beds and 1000
mattresses, the old beds and mattresses were piled up in the open and exposed to
severe weather conditions, as seen in photographs below;
A review of the Procurement & Disposal plan for the year showed that no provision
had been included either to repair the beds or dispose of them.
Management explained that they were in the process of boarding off the old beds
and mattresses.
I advised the Accounting Officer to either have the beds repaired for further Hospital
use or have them disposed of expeditiously to avoid deterioration in value.
535
30.13 Lack of a Strategic Plan
Contrary to best practice, it was noted that the Hospital did not have a strategic plan
to guide management in the operations and implementation of its activities, after
the expiry of the 2008/9-2012/13 version. This means the Hospital operated without
medium and long term plans to guide its management and operations during the
financial year. The budget was therefore not linked to any strategic objectives.
Lack of a strategic plan implies that implementation of activities aimed at achieving
the entity„s mission and long term objectives may not be properly guided. This
practice might expose the allocated resources to waste.
This was attributed to laxity and inadequate planning by management to embark on
the process of developing a new strategic plan in time.
The Accounting Officer explained that a draft of a 30 year Master Plan and a 5 year
strategic and Investment Plan had been developed awaiting final approval by the
Board. I advised the Accounting Officer to expedite the process of approval and
have the strategic plan in place to guide management in their operations.
30.14 Bed Occupancy
Audit also noted that the hospital had about 2,000 beds, with occupancy rate of
119% compared to the planned 90%. The high patient population notwithstanding,
the tendency of many attendants for patients also contributes immensely to the
congestion in the hospital and overstretches the available facilities.
Management acknowledged the fact that the bed occupancy in the hospital was
higher than expected throughout the year and attributed it to the weak referral
systems and limited functional health facilities in Kampala Metropolitan area. They
explained that a plan for decongesting MNRH was designed and would be achieved
through the following strategies;
Construction of other referral hospitals in the Kampala Metropolitan area.
Linking the three hospitals in Kampala to Mulago Hospital through Telemedicine
to allow tele-consultations.
Remodelling and renovation of Mulago Hospital to restrict visitors.
536
Increase in the number of theatres from 7 to 16 and the number of beds in
ICU from 12 to 26, to help increase the number of surgical operations hence
reducing the average length of stay for surgical patients.
Construction of a 320 bed Women‟s hospital was slated to begin in February
2015 to reduce on the congestion in the current facility.
I advised the Accounting Officer to devise measures to control the number of
caretakers, so as not to overstretch the hospital facilities, given the high
maintenance and utility costs.
30.15 Adequacy of Dialysis Machines
It was noted that the Hospital had a total number of twenty one (21) Haemodialysis
Machines, of which four (4) had broken down and needed repairs, while the other
seventeen (17) were functional. Although management explained that seven (7)
more machines were expected, it was noted that the Renal Unit on average received
80 patients daily who required the dialysis services. Each machine has a capacity to
handle three (3) patients each day.
Due to staffing gaps in the unit and in the hospital generally, the unit operated more
or less as an outpatient unit and the machines therefore handled 2 patients per day,
per machine, indicating 34 patients per day leaving out an average of 46
unattended to. Failure by the hospital to offer desired services timely may lead to
loss of lives.
It was also noted that the hospital did not have any Peritoneal Dialysis, machines,
which would serve mainly child patients below the age of 10 years and it was not
clear how such child patients were being attended to.
Management explained that the Hospital had entered into a contract through
National Medical Stores for a supplier to provide sundries and/or consumables
for dialysis to enable attendance to additional sixty (60) patients twice a week.
Management further stated that whereas patients ought to be dialysed three times a
week, this is being done only two times a week because of limited funding.
537
I advised the Accounting Officer to liaise with the respective Ministries so as to
acquire optimal number of dialysis machines with the associated staffing levels, for
improved service delivery.
30.16 IMPROVEMENT OF HEALTH SERVICE DELIVERY IN MULAGO HOSPITAL
AND IN THE CITY OF KAMPALA PROJECT (MKCCAP)
a) Funds disbursement
According to the Loan Agreement, the MKCCAP project whose total funding is Unit
of Account (UA) 56 million3 is supposed to run for a period of 5 years (2012 -
2016), with the last (disbursement expected by 31st December 2016). However, a
review of the project income and expenditure revealed that the cumulative project
expenditure as at 30th June 2014 was USD.7,977,440 representing 14% of the
total expected project funding. Given the low rate of funds disbursement and
activity implementation, it is highly doubtful that the project will achieve its
intended objectives within the remaining project period.
Management attributed the delays to the fact that most of the project resources
(about 86%) were allocated to civil works and procurement of hospital equipment
and furniture, and the hospital civil works had to go through elaborate African
Development Bank (ADB) and GoU procurement processes to identify contractors
before funds could be disbursed. Management explained that the disbursement of
funds would soon greatly improve.
I have advised management to hasten the implementation of activities so as to
improve the disbursement of funds and thus attainment of the project objectives
within the remaining project period.
b) Delays in development of Master Plan for Mulago Hospital
A Contract to develop a 30 year master plan for Mulago National Referral Hospital
was awarded to a consultant at a cost of USD.369,900. A payment of USD.73,980
was made during the year.
3 African Development Fund loan of UA 46 million and Nigeria Trust Fund loan of UA 10 million
538
A review of the Aide Memoire of July 2014 showed that the initial contract for the
consultancy expired on 30th November 2013 and a-no-cost extension was granted
up to 30th April 2014. The contractor however, could not produce the final report
by the due date but only submitted a final draft in July 2014. However, by the
time of this report December 2014, not all deliverables of the consultancy had
been concluded. There is a risk that the consultants may not be able to deliver on
all the aspects of the contract.
Management attributed the delays to the consultant and the delayed feedback
from clients because of the many stakeholders that had to be consulted.
Management further explained that the Bank Supervision Mission had advised GoU
to seek for No Objection for the extension of completion time.
I have advised project management to review the progress of the consultant and
ensure that the process is expedited to ensure completion of the task. Meanwhile I
await the action of management as far as seeking for a No Objection is concerned.
c) Failure to meet the Bank‟s conditions
i. Uganda legislation and public policy concerning public private
partnerships
A review of the project documents and the Aide Memoire of July 2014 showed that
the project did not meet a number of the conditions as specified in the Loan
Agreement. These include:-
Submitting a Memorandum by the Ministry of Health (MoH), Mulago Hospital
and Makerere University in form and substance acceptable to the Fund,
clarifying roles and responsibilities of the three institutions by 31st December
2012”.
Submitting to the Fund for review and approval, prior to execution, any
contract that is entered into by the MoH and the selected service provider, for
the management of the Ambulance referral system in the city of Kampala and
provide written confirmation that any contract entered into by MoH for the
purposes of the ambulance referral system in the city of Kampala, is in
539
accordance with the Republic of Uganda‟s legislation and public policy
concerning public private partnerships by 31st July 2013.”
The above conditions which had not been met by the time of audit could result in
withholding of funding for the project and thus lead to stalling of implementation
of the project activities.
Management acknowledged the anomaly and explained that Work on the MOU
had already started and a draft had been prepared. Management added that since
the time of the loan agreement, GoU had realized that it needed to prepare one
MoU between MoH, the 5 Universities with Medical Schools and the respective
teaching hospitals. The above process was on-going and was expected to be
finalized by March 2015. Due the wider stakeholder consultations, the process had
taken longer than expected.
I have advised the project management to address the impediments so that the
Bank‟s condition as of developing legislation and public policy concerning public
private partnerships is met.
d) Status of Implementation of Mission Recommendations
A review of the project documents and the Aide Memoire of 18th-24th July 2014
revealed that the activities below were still pending implementation due to
procurement technicalities.
Issue Recommendation Actions Expected Implementation
time line
Procurement of 10
Ambulances
Review specifications and re-
advertise tenders for Ambulances
By 31st July 2014
Referral and
Ambulance system
Submit proposal and budget
details from IFC to the Bank
31st July 2014
Procurement of the
project vehicle
Submit request for the bank
consideration
Immediately requested for
The failure to act upon the recommendations of the Bank Supervision Mission may
have a negative impact on attainment of the overall project objectives.
540
I have advised management to always implement the recommendations of the
Bank Supervision Mission as agreed for better and smooth project implementation.
e) Land dispute at Kawempe
A review of the Aide Memoire and other project documents indicated that the
project was undertaking construction of a General Referral Hospital in Kawempe
but on a disputed piece of land.
The Accounting officer explained that the Banks Compliance review and Mediation
Unit (CRMU) undertook a fact finding mission in Uganda to meet all the relevant
stakeholders, including KCCA, Minister of Health, the Permanent Secretary MoH,
Solicitor General and the complainants. It was however noted that at the time of
this report (December 2014), the matter had not been fully addressed. The
progress of the works was likely to be interrupted should the complainants opt to
take legal action.
The project management explained that the matter was being handled amicably
with the claimant in order to have it resolved and enable the hospital construction
works to continue. Two meetings attended by key stakeholders had been held
with the claimants. The Ministry of Lands had provided documents from the Land
Registry that clearly showed KCCA as the rightful owner of the Land on which the
hospital was being constructed.
I await the outcome of the on-going actions towards resolving the land dispute.
f) Asset Management
i. Marking/ engraving of Assets
Regulation 101 of the Public Finance and Accountability Regulations 2003 (PFAR)
requires all assets to be appropriately marked or engraved to ensure that they are
easily identifiable as Government assets. It was however noted that the project
owns a number of assets such as furniture, computers and office equipment
valued at UGX.67,450,000 and USD.45,644.05 respectively that have not been
engraved. Failure to engrave the assets exposes them to a risk of loss without
trace.
541
Management acknowledged the anomaly and committed to engrave all project
assets by January 2015.
I await management‟s actions on the commitment of engraving all the project
assets by January 2015.
30.17 SUPPORT TO THE DEVELOPMENT OF A SPECIALIZED MATERNAL AND
NEONATAL HEALTH CARE UNIT IN MULAGO NATIONAL REFERRAL
HOSPITAL (MULAGO III) PROJECT
a) Delay in procurement activities
During a meeting held on 17th July 2014, between the Project Management Unit
(PMU) Mulago National Referral Hospital and the Islamic Development Bank (IsDB)
Project Implementation Assessment and Support (PIAS) Mission, it was agreed
that the procurement of a consultant for the supervision of works, contractor for
civil works were to be completed by December 2014 and the civil works for the
project to commence by January 2015.
By the time of audit (November 2014), the agreed upon activities had not been
implemented and a letter of no objection for the shortlisted service providers had
not been obtained from the Bank. The delay may impact negatively on the project
implementation and attainment of project objectives.
The project management explained that the procurement of the supervision
consultant was underway and the technical evaluation of the bids had been
completed, awaiting a no objection from the Bank and there after financial
proposals would be opened. The contract was expected to be signed by end of
February 2015.
I have advised management to ensure that the project implementation timelines
are adhered to for the attainment of project objectives.
542
30.18 UGANDA SANITATION FUND
a) Outstanding Fuel Deposits
Fuel worth UGX.10,162,425 was deposited with M/s. Shell Kumi Petrol Station
during the financial year 2012/2013, however fuel worth UGX.6,698,607 was
consumed, leaving a balance of UGX.3,463,818 worth of fuel unutilized.
It was explained that the operators of the station closed business before the
project could consume all the fuel. Although the dealers acknowledged the debt
and showed willingness to pay the outstanding amount, the District had not
recovered the money by the time of audit.
In his reponse, the Accounting Officer plegded to take necessary steps to
recoverthe funds.I await the action of theAccounting Officer to recover the money.
b) Under-utilization of funds
A review of the financial statements revealed that out of a total of USD.544,338
received by USF during the 15 months period, USD.386,820.20 was utilized
leaving a balance of USD.157, 517.80 unutilized. Failure to utilize funds within the
planned timeframe slows down project implementation and may hinder attainment
of project objectives.
The Accounting Officer attributed the delay to slow rate of the procurement
processes in the Ministry and the delay to recruit project staff. I have advised him
to always ensure that the project activities are carried out according to the project
work schedules.
c) Project Asset Management
a. Non-maintenance of Asset inventory
According to the Grant Support Agreement between the UNOPS and the
Government of Uganda for the Global Sanitation Fund Programme in Uganda
(Annex A - General Condition for the Grant Support Agreement 9.2), the recipient
is expected to maintain records of non-expendable equipment with an acquisition
value of USD.500 or more purchased with project funds. The recipient is expected
543
to submit an inventory of such equipment to UNOPS, indicating descriptions, serial
Nos, date of purchase, original cost, present conditions, location of each item
attached to each yearly progress report.
Similarly,Regulation 101 of the Public Finance and Accountability Regulatios, 2003
requires that a register, in a form prescribed by the Accountant General shall be
maintained for all assets, and all such assets shall also be appropriately marked or
engraved to ensure that they are easily identifiable as Government assets.
However, it was noted that the project assets such as vehicles, computers and
Cameras procured using the project funds were not recorded in the inventory
register. Additionally, assets were not appropriately marked or engraved.This
complicates their identification, management and reporting.The Accounting Officer
explained that the ministry had embarked on the process of engraving the project
assets.
I have advised Project management to maintain an asset inventory and ensure
that all project assets are engraved as required for ease of asset identification,
management and reporting.
544
REGIONAL REFERRAL HOSPITALS
31.0 ARUA REGIONAL REFERRAL HOSPITAL
31.1 Unaccounted for funds
a) Unsupported Cash withdraws
Regulation 60(1) of the Public Finance and Accountability Regulations, 2003 states
that all disbursements of public moneys shall be vouched on payment vouchers.
However, a review of the cashbook and the Bank statements of the Operational
account of Hospital revealed that UGX.253,556,250 was withdrawn in cash from
the bank without payment vouchers or any supporting documents rendering the
expenditure incompletely vouched. In the circumstance, the payments are
doubtful.
I advised the Accounting Officer to investigate the matter and ensure recovery.
b) Funds not accounted for
Paragraphs 214(a) and 215(a) of the Treasury Accounting Instructions, 2003
require an Accounting Officer prior to approving an advance to staff to ensure that
the concerned staff has settled any old advances and that the advance must be
accounted for without delay. However, UGX.105,574,390 remained unaccounted
for by the time of audit. Consequently, I was unable to confirm that the funds
were utilized for the intended purposes.
I advised the Accounting Officer to obtain the accountability or else enforce
recovery from the responsible officers.
b. Non-Tax Revenue shortfall
Regulation 44(1) of the Public Finance and Accountability Regulations, 2003 states
that an Accounting Officer is personally responsible for ensuring that adequate
safeguards exist and are applied for the prompt collection of, and proper
545
accounting for, all Government revenue and other public moneys relating to their
departments.
However, the Hospital budgeted to collect UGX.70,000,000 from Non-Tax Revenue
source. However, only UGX.27,308,825 was realized leading to a shortfall of
UGX.42,691,175, representing 61% of the budgeted Non tax revenue.
Management attributed the poor performance to the renovations that were on-
going at the private wing of the maternity ward.
I advised the Accounting Officer to ensure that all budgeted revenue is collected.
31.2 Understaffing
The hospital has a staff establishment structure of 354 posts. However, out of the
354 approved posts, only 301 posts had been filled leaving 53 posts vacant. It was
observed that some of the vacant posts are the key positions which include Senior
Consultant Surgeon, Senior Consultant Physician, Senior Consultant Paediatrician,
Senior Consultant Obs/Gyn, Principal Dental Surgeon, Nursing officers which are
so fundamental in the operations of the Hospital.
Understaffing undermines service delivery.
Management explained that the hospital operates within the staffing policy of
Government. In liaison with the Ministry of Health and Ministry of Public Service
the hospital developed a recruitment plan, vacant positions were advertised and
interviews to secure staff to fill the vacant positions on replacement basis are
under way.
I advised the Accounting Officer to liaise with Ministry of Public Service and
Ministry of Health to expedite the recruitment exercise to fill the vacant posts.
546
32.0 MBALE REGIONAL REFERRAL HOSPITAL
32.1 Funds not accounted for
a) Unaccounted for Advances
Paragraph 120 of the Treasury Accounting Instructions (TAI) Part 1 requires that
funds be properly accounted for with appropriate documents. However, it was
observed that a sum of UGX.9,319,000 advanced to staff remained unaccounted
for at the time of audit contrary to the regulations. Consequently, I could not
confirm that the funds were utilised for the intended purposes.
The Accounting Officer was advised to obtain the accountabilities or else recovery
be made from the responsible officers.
b) Incompletely Vouched Expenditure
Paragraph 120 of Part I of the TAI, 2003 requires all payment vouchers to be
properly supported with appropriate documents or sub-vouchers before they are
passed for payment. However, it was observed that expenditure amounting to
UGX.14,207,000 lacked the necessary supporting documents, contrary to the
regulations.
I advised the Accounting Officer to ensure that the accountability is obtained and
presented for audit verification.
32.2 Wasteful expenditure
Ms Ambitious Construction Company limited was contracted to construct an
accommodation block for staff under procurement reference number
MRRH/WORKS/09-10-/00034 at a contract price of UGX.3, 885,939,190 in the FY
2009/2010.
However, the hospital failed to pay interim certificates in time which resulted into
the contractor claiming interest payment/penalties for delayed payments of
UGX.146,883,559. By the time of audit UGX.127,700,000 had already been paid
leaving a balance of UGX.19,183,559 as shown below;
547
Invoice
Number
Invoice
Date
Description/Pu
rpose
EFT/
Cheque
Number
Distribution
Amount
Supplier
Account
Name
DB13/09/
113
27-Sep-13 Payment of
Interest accrued
from delayed
Payments.
2919322
45,900,000
Ambitious
Construction
Company Ltd
DB13/12/
183
23-Dec-13 Payment of
Interest on
delayed
payment.
98944
81,800,000
Ambitious
Construction
Company Ltd
Total 127,700,000
The Accounting Officer admitted the shortcoming and attributed it to the delay by
Ministry of Finance to release funds on time.
I advised the Accounting Officer to ensure compliance with the commitment
control procedures.
32.3 Outstanding Commitments
Section 198 of Treasury Accounting Instructions Part I Finance, requires all
purchases of goods or services to be subject to the commitment control system
procedures issued by the Accountant General from time to time. Commitment
control system requires that commitments are not made in excess of cash limits
project for the period. By the end of the financial year, the entity had
accumulated outstanding commitments amounting to UGX.266,412,236 these
comprised of the balance brought forward from last 2012/13 of UGX.252,252,984
and commitments incurred during the F/Y under review of UGX.14,159,252.
Failure to settle the outstanding commitments may lead to litigation and penalties.
The Accounting Officer admitted the shortcoming and explained that these
commitments could not be cleared because of insufficient funds. He however
indicated that Ministry of Finance Planning and Economic Development cleared the
hospital to settle the commitments from the current budget.
548
The Accounting Officer is advised to ensure that commitments are made within the
cash limits available in accordance with the regulations.
32.4 Supply of Medical equipment by Crown Health Care
The hospital awarded a contract for supply of medical equipment worth
UGX.163,215,950 to Crown health care under contract MBH/SUPLS/13-14/00044
during the year under review. It was however, observed that some of the items
supplied had defects. The internal auditors inspection report dated 15/5/2014,
recommended return of some of the items on the basis of either being poor
quality and not conforming to the specifications.
The Accounting Officer explained that defective items were replaced and that
there was an internal Audit report confirming the deliveries. However, the report
was not availed for verification.
The matter requires urgent attention.
32.5 Understaffing of PDU
The approved staffing structure requires the procurement and disposal unit (PDU)
to have three staff. However, the department is manned by only one officer. It
was also observed that while the department was expected to be headed by a
senior procurement officer, it is headed by a procurement officer.
Failure to adequately staff the PDU undermines the level of performance of the
unit.
The Accounting Officer explained that the matter had been brought to the
attention of the Ministry of Finance Planning and Economic Development
(MOFPED).
I advised the Accounting Officer to follow up the matter with MOFPED to ensure
that the PDU is adequately staffed.
549
32.6 Service Delivery
a) Dental Clinic/ Department (Masaba Wing)
Para 2.1.1 (D) of the LGMSD program operational manual, sets out health service
delivery packages or minimum standards for proper functioning of health centres.
Inspection of the dental clinic revealed the following shortcomings:
Limited supplies of dental cements (amalgam) one of the major items required
in the clinic.
X-ray board was not functional. It was established that absence of this board
makes it hard for the dentist to read the x-ray for better results.
The available dental chairs were not functioning properly. It was observed
that they could not rotate as expected.
Dental trimmers in the theatre were not in use due to lack of a technical
person to operate them
The X-ray monitor was not functional at the time of inspection.
No protective wall for the x-ray machine making it risky for the operator
The Accounting Officer attributed the failure to use the dental X-ray machine to
absence of a protective wall / shield for the operator and that the X-ray viewing
board does not light properly.
He further explained that the dental chairs were also malfunctioning and required
an expert dental technologist.
I advised the Accounting Officer to liaise with the line Ministry of Health to address
the issue and ensure that the dental clinic is fully operational.
33.0 KABALE REGIONAL REFERRAL HOSPITAL
33.1 Irregular Payment of VAT
Section 19, paragraph (a a) of the Value Added Tax (VAT) Act 2009 (amended)
stipulates that supply of civil works related to health sectors were exempt from
VAT.
550
It was observed that the Hospital paid a total of UGX 7,594,636 as VAT to GESES
Uganda Ltd in respect paving and fencing works of the Nurses hostel which was
VAT exempt. The VAT payment was irregular.
The Accounting Officer explained that he had written a letter to Geses (U) Limited
advising the firm of the intended recovery.
I advised the Accounting Officer to follow up the matter and ensure recovery.
33.2 Un spent balances
Section 19(1) of The Public Finance and Accountability Act, 2003 require that
every appropriation by Parliament of public moneys for the services of a financial
year, shall lapse and cease to have any effect at the close of that year and the
unexpended balance of any moneys withdrawn from the Consolidated Fund shall
be repaid to the Consolidated Fund. However, UGX.462,821,812 in respect of
unspent balances that remained on the Hospital bank accounts at the year-end
was never returned to the consolidated fund.
The Accounting Officer explained that the request to retain the committed funds
had been submitted to the Permanent Secretary/Secretary to Treasury, Ministry of
Finance, Planning and Economic Development but a response had not been
obtained.
I advised the Accounting Officer to follow up the matter with the PS/ST to ensure
that authority for retention is obtained or else the funds should be returned to the
consolidated as required under the law.
33.3 Lack of Hospital Board
Part III section 5 (3) of the Ministry of Health National Hospital Act 2006, require
hospitals to have hospital management boards.
However, it was observed that for the year under review the hospital did not have
a board. Consequently, the strategic and operational decisions lack the requisite
scrutiny and guidance of a board.
551
The Accounting Officer explained that they had communicated the matter to the
Ministry of Health and were still awaiting response.
I advised the Accounting Officer to follow up the matter with the Ministry of Health
and ensure that the hospital management board is appointed.
33.4 Understaffing
The approved staff structure of the hospital had 350 positions. However, out of
the 350 approved positions, only 227 are filled, leaving 123 vacant positions,
representing 35% of the establishment.
Staff shortages undermine service delivery.
The Accounting Officer explained that the matter had been brought to the
attention of relevant authorities.
I advised the Accounting Officer to follow up with the relevant authorities to
ensure that vacant positions are filled.
34.0 LIRA REGIONAL REFERRAL HOSPITAL
34.1 Non-Disclosure of Project balances in the Cash and Cash Equivalents
The cash and cash equivalent of UGX 123,929,499 reported in the statement of
financial positions is understated by the project balances of UGX 107,583,155
which were not disclosed as part of the Cash and Cash equivalents for the year.
The Accounting Officer indicated that they were not guided on the accounting
treatment of project funds. Therefore they needed to consult Ministry of Finance,
Planning and Economic Development in order to adjust the financial statements.
I advised the Accounting Officer to follow up the matter with the Ministry of
Finance, Planning and Economic Development for the necessary guideline.
34.2 Unaccounted for Funds
552
Section 43(2) of the Local Governments Financial and Accounting Regulation, 2007
requires administrative advances to be accounted for within a period of one
month. In addition, paragraph 2.2.1 (6) of the Local Government Financial and
Accounting Manual, 2007 requires the Head of Finance to ensure that all payment
vouchers are supported by relevant documents. However, UGX.106,394,580 paid
to staff and service providers was either unaccounted for or lacked supporting
documents at the time of audit. Consequently, I was unable to confirm that the
funds were utilised for intended purposes.
I advised the Accounting officer to obtain the accountabilities or else recovery be
made from the responsible officers.
34.3 Non Deduction Withholding Tax
Section 124 (1) states that a withholding agent who fails to Withhold Tax is
personally liable to pay to the commissioner the amount of tax which has not been
withheld but the withholding agent is entitled to recover this amount from the
payee.
However, it was observed that UGX 29,094,551 in respect of withholding tax was
not deducted from service providers contrary to Income Tax law.
Non-compliance with the tax law may attract fines and penalties from the tax
body.
I advised the Accounting Officer to comply with the tax law to avoid fines and
penalties.
35.0 GULU REGIONAL REFERRAL HOSPITAL
35.1 Un-vouched Expenditure
Regulation 60(1) of the Pubic Finance and Accountability Regulations 2003,
requires all disbursements of public monies to be properly vouched on payment
vouchers prescribed by the Accountant General. However, expenditure totalling
553
UGX 219,224,118 lacked expenditure vouchers, rendering the authenticity of the
expenditure doubtful.
The Accounting officer explained that the vouchers had been kept in Sustain Office
in Kampala. By the time of writing this report, the vouchers had not been
presented for audit verification.
Management was advised to obtain the accountabilities and present them for
audit verification.
35.2 Stores not Taken on Charge
The Treasury Accounting Instructions (TAIs) 2003 paragraph 203 requires stores
receipts taken on charge to be recorded in the stores ledger.
Management procured stores worth UGX 105,779,182 but the items were not
recorded on the store ledger. In the circumstances I could not confirm that the
items were delivered.
The Accounting officer attributed the anomaly to understaffing.
I advised the Accounting officer to ensure that the stores are recorded in the
ledgers and accountability rendered for audit verification.
35.3 Unutilised Line of Credit
The Ministry of Health of Uganda allocated UGX.949,000,000 for medical supplies
to Gulu Regional Hospital under the credit line allocation for the year 2013/14. It
was further noted that under the Hospital credit line there was unutilised balance
of UGX.374,408,533 leading to a total of UGX.1,323,408,533 funds available for
the year under review.
However, the hospital utilised only UGX.863,279,300 out of UGX.1,053,859,302
worth drugs ordered leaving a balance of UGX.190,580,000 with drugs ordered
not delivered by NMS as shown in the table below:-
Hospital Records
554
Cycle Order Value Per Cycle Delivery Value Per Cycle Variance
Cycle 1 181,285,506.00 124,955,029.38 56,330,477
Cycle 2 156,602,842.00 148,050,035.59 8,552,807
Cycle 3 154,264,205.00 110,334,127.33 43,930,078
Cycle 4 150,051,355.00 124,683,255.66 25,368,100
Cycle 5 150,059,055.00 123,499,302.22 26,559,753
Cycle 6 261,596,341.00 231,757,552.97 29,838,789
TOTAL 1,053,859,302 863,279,300 190,580,004
The Accounting officer explained that National Medical Stores did not fulfill all the
orders made due to non-availability of some drugs, although the hospital made
orders for their entire line of credit.
I advised the Accounting Officer to engage National Medical Stores and the
Ministry of Health to ensure that line of credit is fully supplied.
36.0 MBARARA REGIONAL REFERRAL HOSPITAL
36.1 Goods not Taken on Charge
Paragraph 203 of the Treasury Accounting Instructions, Part II, requires all stores
receipts to be taken on charge in the stores ledger. However, a review of Stores
records revealed that purchases totalling to UGX.10,164,220 were not taken on
charge in stores.
There is a risk that the goods may not have been supplied.
The Accounting Officer explained that the goods were taken on charge, however,
the stores records were not availed for verification.
I advised the Accounting Officer to ensure that all the items presented are
properly recorded in the records of the stores.
36.2 Understaffing
The approved Staff establishment of the hospital had 620 positions. However, out
of the 620 approved positions, only 437 were filled, leaving 183 posts vacant,
555
representing 30% of the establishment. Understaffing negatively affects service
delivery.
The Accounting Officer explained that advertisements for the vacant positions had
been placed in the media and recruitments were under way.
I advised the Accounting Officer to follow up that matter and ensure that the
vacant positions are filled.
36.3 Lack of an Information and Communications Technology Policy
The Public Finance and Accountability Act requires the Chief Executive to
designate an officer to ensure that adequate information and communication
technology policies are established and are applied to enable adequate security
and protection over computers and of data held on computers or information
systems operated by a government department.
However, there were no proper procedures formulated to guide the use of the
equipment.
This could be attributed to the hospital staff structure that does not provide for
information technology personnel. Misuse of computer equipment and loss of vital
data may not be ruled out in the prevailing circumstances.
The Accounting Officer acknowledged the shortcoming and promised to liaise with
the Ministry of Information Communication Technology (ICT) to establish an IT
policy.
I await the outcome of the Accounting Officer‟s commitment.
37.0 FORT PORTAL REGIONAL REFERRAL HOSPITAL
37.1 Understaffing
The approved staffing establishment for the hospital is 421 positions. Out of the
approved 421 positions only 310 were filled, leaving 111 vacant positions,
representing 26% of the establishment, as shown below.
556
Positions Approved Posts
Filled
Posts
Vacant
Posts
%age of
Gap
Doctors 42 12 30 71
Nurses 152 122 30 20
Paramedics 89 61 28 31
Administration 33 17 16 48
Support Staff 105 98 7 7
Total 421 310 111 26
Understaffing undermines service delivery.
According to the Accounting Officer staffing challenges have persisted for so long
yet the number of patients continue to increase and the hospital is also expanding
in terms of structure and function. It was difficult to attract and retain the critical
cadres at the current terms and conditions of service.
I advised the Accounting Officer to engage the Ministries of Health and Public
Service to ensure that the vacant positions are filled.
37.2 Vehicle Repairs
Section 199 of TAI provides that payment vouchers for the purchase of stores
must be supported with all the relevant documents, including requisitions,
purchase orders, supplier„s invoice, delivery notes and an inspection/goods
received note.
However, repair services totaling UGX.36,420,396 were carried out without
requisitions from user departments, LPOs and Job Completion Certificates. There
is a risk of paying for no work done.
According to the Accounting Officer, the workshop follows a work-plan, routine
maintenance, but also respond to emergency breakdowns. They do not have to
wait for complete breakdown of equipment in order to repair them. There is need
for periodic service of machines and equipment.
557
I advised the Accounting Officer to abide by the laid down repairs procedures.
37.3 Unutilized Equipment
In January 2014 the hospital received Anaesthetic Machines, Datex-Ohmeda
9100C, Autoclaves and Delivery Beds from M/s. SIMED International, the supplier
of ENONC equipment under Uganda Health System Strengthening Project; IDA CR
No. 47420. However, audit inspection revealed that the Anaesthetic machine was
not working because its accessories were not supplied. Similarly, the Autoclaves
and Delivery Beds were also not being used.
According to the Accounting Officer, the Anaesthetic machine was supplied by
Ministry of Health. The anaesthetic machine can be used but require oxygen
under high pressure which can only be obtained by using cylinders which are not
readily available in the HCIVs. However, for further details the Ministry of Health
can be contacted for a better position of choice of the equipment.
I advised the Accounting Officer to liaise with the Ministry of Health for necessary
action to ensure that the equipment‟s are put to use.
38.0 JINJA REGIONAL REFERRAL HOSPITAL
38.1 Service delivery
a) Expired Drugs
The expired drugs are required to be returned to National Medical Stores (NMS)
for destruction.
However, it was observed that some drugs worth UGX.15,884,100 had expired
and had not been returned to NMS for destruction. Besides, the expired drugs
were not properly kept as shown in the photograph below;
558
The expired drugs may be misused.
I advised management to ensure that expired drugs are isolated and disposed off
urgently.
b) Understaffing
The staff structure of the hospital had 417 approved posts. However, out of the
approved posts 364 were filled, leaving 53 vacant which represent about 13% of
the establishment.
Management explained that the hospital requests for recruitment were submitted
to relevant authority and some posts were cleared for filling.
I advised management to follow up the matter with the authorities and ensure
that the vacancies are filled.
c) Department of Obstetrics and Gynaecology
An inspection of the above department revealed the following:-
The department lacks 5 B/P machines and a weighing scale.
Gynaecology ward was in a sorry state, some doors were broken. It lacked
evacuation set, stethoscopes, thermometers, wheel chairs, oxygen heads and
sterilizer/boiler.
The patients‟ toilets lack water.
The building housing the Family Planning/Association of voluntary Surgical
Contraceptives was dilapidated.
Expired Neverapine still in the shelf mixed
with drugs with active drugs.
Expired kaletra oral suspension still
kept in the fridge with other
medicines.
559
Management agreed with the observation.
I advised the Accounting Officer to engage the relevant stakeholders to address
the matter.
38.2 Lack of Land Titles
Treasury Accounting Instruction 2003, Part I 400 (h) requires the particulars of the
fixed assets acquired shall be recorded and kept in a fixed assets register
(Treasury form 89).
It was observed that the hospital did not have land titles for some of its land on
which its properties are located namely plots 31-39, Nile Avenue, Plot 26-32,
Nalufenya road, Plot 34-40 Nalufenya road, Plot 52 Gabula road and Plot 47 Nile
Garden.
Lack of land titles creates a risk of encroachment.
Management explained some of the land plots were under dispute.
I advised the Accounting Officer to ensure that the disputes are resolved and land
titles secured.
38.3 Management of Information and Communication Technology
Review of the IT general and application controls revealed that the hospital has
not formulated an IT policy and there was no evidence of any effective measures
that had been taken to create awareness regarding IT security amongst staff
despite having a number of desk top computers and laptops.
The Hospital has also installed IT systems like Personnel management system,
Health management information system and the procurement information system
but all this systems run without a fully-fledged IT steering committee that among
other functions will incorporate IT issues in the hospital strategic plan and
budgets, and these committee is also vital in instituting internal controls to
safeguard against data usage and loss.
560
The implication is that misuse of computer equipment, loss of vital data and
information and theft may not be ruled out. This could be due to lack of
awareness of computer use.
The Accounting Officer is advised to formulate an IT steering committee and
maintenance policy in order to safe guard IT resources at the Hospital.
Management acknowledged the findings.
The Accounting Office should also liaise with the Ministry of Information
Communication Technology (ICT) to formulate IT policies, to guide in
management of IT resources, and with the Ministry of Public Service with a view
of recruiting an IT staff.
39.0 SOROTI REGIONAL REFERRAL HOSPITAL
39.1 Unaccounted for Funds
Section 215 (a & b) of Treasury accounting instructions requires advances to be
accounted for without delay. However, it was observed that advances totalling to
UGX. 23,466,678 remained unaccounted for at the time of audit.
This was attributed to laxity on the part of the management to enforce controls
regarding accountability. Consequently, it was difficult to ascertain whether the
funds were utilised for the intended purposes.
I advised the Accounting Officer to obtain the accountabilities or recover from the
responsible officer.
39.2 Understaffing
The approved hospital establishment has 344 posts. However, out of the 344
approved posts only 259 posts had been filled leaving 85 vacancies representing
25%.
According to management under staffing was caused by retirement, transfers and
the ban on recruitment by the Ministry of Public Service.
Understaffing undermines service delivery.
561
I advised the Accounting Officer to liaise with the Ministries of Finance, Planning
and Economic Development and Public Service to address the matter.
39.3 Non Disposal of Expired Drugs
The inspection of the hospital store in November 2014 revealed that several drugs
had expired and had not been disposed.
Expired drugs if not destroyed can end up on the market. The Accounting officer
explained that most of the expired drugs were a cumulative effect over a number
of years from donors and projects.
I advised the Accounting Officer to ensure that the expired drugs are disposed off.
40.0 MASAKA REGIONAL REFERRAL HOSPITAL
40.1 Operation of a dollar account without authority
Regulation 327 of Treasury Accounting Instructions (TAI‟s) 2004, states that no
bank account shall be opened or closed without the prior authority of the
Accountant General. However, management opened and operated a dollar account
under account name CDIC without authority of the Accountant General. There
was no disclosure of the operations of this account in the Hospitals financial
statements. Besides, management did not avail accountability documents for the
transactions on this account for audit verification.
The Accounting Officer explained that the Hospital Director Masaka Referral
Hospital is the chairperson of the steering committee and one of the signatories to
the account. The account is not for the hospital but for Ministry of health although
it benefits from the project which covers the whole country.
I advised the Accounting Officer to obtain the Accountant General‟s authority for
opening the account and ensure that the funds are appropriately accounted for.
40.2 Construction of the maternity and children complex
562
The BOQs provided for iron bars of 4x25 on the outside columns and 4x16 on the
inside columns; it was observed that instead of using 4x25 as per BOQs, 4x16
column bars were used for the section of the outside wall. The difference in
column size as per specifics in the BOQ could affect the substructure and lead to
the collapse of the building as these were not erected and strong enough to hold a
3 storeyed maternity complex as shown below;-
4x16 iron bars on the outside columns that are weak
The Accounting Officer explained that this was caused by the record in the
structural plans which provided for 4x16 iron bars on the outside columns which
were installed, varying from the BOQs which provided for 4x25. The 4x16 columns
appeared weak and may crumble under the weight of 3 storeys. The issue of the
variance of the outside columns between the BOQs and the structural plans
remains a sticky issue as it will affect structure of the building. Since the bars
constitute part of the foundation level for the base beam installations, it is
paramount that they are of a considerable strength and promised to investigate
the variance between the columns sizes, the number of columns to be erected and
have it rectified.
I advised the Accounting Officer to investigate the anomalies and have them
rectified.
40.3 Lack of a Hospital Board
563
Guideline 1.1.1 (e) of the Governance structure guidelines issued by Ministry of
Health January 2013; provides that at a referral hospital, the board shall provide
the oversight role for effective functioning of hospital in order to deliver quality
services.
However, the hospital did not have a board.
It was observed that during the year, these roles were performed by hospital
managers yet they are the implementers of the annual work plans and the hospital
budget. This grossly compromised the quality of services at the hospital.
The Accounting Officer admitted the shortcoming and explained that the old
board‟s term of office expired in December 2013 and a new board had been
appointed.
I advised the Accounting Officer to show proof of the new board appointment and
evidence of the oversight role by the board.
41.0 MUBENDE REGIONAL REFERRAL HOSPITAL
41.1 Lack of Vehicle Log Books
Section 801 of the Treasury Accounting Instructions on Stores provides that
vehicle log books are maintained for each vehicle to show details of dates,
purpose of journey or works performed, the signature of the officer authorising
them, details of fuel, oils, and spares used, dates and nature of servicing and
repairs and lists of tools, spare wheels and other equipment carried on or
associated with the vehicle, launch or equipment.
However, management did not maintain vehicle movement log books contrary to
the regulations. Consequently, it becomes difficult to monitor and control vehicle
movements and fuel.
The Accounting Officer has promised to establish the vehicle movement registers.
I advised the Accounting Officer to establish the vehicle movement log books.
564
42.0 MOROTO REGIONAL REFERRAL HOSPITAL
42.1 Use of Non-Prequalified Suppliers
Regulation 125 (1) (b) of the PPDA Regulations (2003), requires a procuring and
disposing entity to send the solicitation documents to a number of bidders
appropriate for effective competition from among the providers who submitted
pre-qualification submissions or expressions of interest and who meet the
prequalification criteria.
It was however, observed that procurements worth UGX. 31,600,500 were
solicited from non-prequalified suppliers, contrary to the regulations. In the
circumstances the hospital may not have achieved value for money.
The Accounting officer was advised to ensure that only prequalified suppliers are
invited when soliciting for quotations.
42.2 Inspection of Hospital Facilities
a) Wards
Most wards were noted to be in a poor state with lack of enough beds, non
functioning water system and dilapidated structures, among others, as shown
below:
Childrens Ward
Dilapidated Childrens Ward with Patients on floor, no enough beds and
ward congested
Medical Ward
565
Falling ceiling, no running water with a few Drip stands in the ward.
The Accounting Officer explained that the beds appear to be insufficient because
there are too many patients in the hospital.
I advised the Accounting Officer to priortise the renovation and equiping of the
hospital.
b) Hospital Mortuary
The Hospital does not have a functional mortuary. The building that is used as the
mortuary is dilapidated with broken window panes and without any cold storage
facility. According to management, the Hospital Mortuary is planned to be
constructed in the second phase of Uganda Health Services Support Porject/World
Bnak Project.
I advised the Accounting officer to liaise with the Ministry of Health for the release
of project funds to have a functional mortuary.
42.3 Non-Deduction of Taxes
Section 123 of the Income Tax Act, 1997, requires a withholding agent to pay
URA any tax that has or should have been withheld within fifteen days after the
end of the month.
It was observed that 6% Withholding tax of UGX 17,686,200 was not recovered
from a payment a local firm contracted to construct a staff houses.
Non-compliance with the Tax Law may attract fines and penalties from URA. The
Accounting Officer promised to recover the taxes from the subsequent payments
to the contractor.
566
I advised the Accounting Officer to comply with the tax law.
42.4 Fixed Assets Register
Paragraph 801 of Treasury Accounting Instruction 2003 part II-public stores
requires an entity to maintain a Fixed Assets register showing the location of plant
and tools in daily use. However, the hospital purchased fixed assets amounting to
UGX 35,713,000 but were not recorded in the asset register, contrary to the
regulations.
I advised the Accounting Officer to ensure that the fixed assets register is regularly
updated.
42.5 Human Resources
a) UnderStaffing
The approved staff structure of the Hospital has 386 posts. However, out of the
approved 386 posts only 153 were filled leaving 233 positions vacant representing
60% of the establishment. Understaffing undermines service delivery.
This was attributed to the ban on recruitment by Ministry of Public Service and
difficulty to retain staff in the region as it is a hard to reach and staff.
I advised the Accounting Officer to liaise with the Ministries of Health and Public
Service to ensure that the vacant posts are filled.
43.0 HOIMA REGIONAL REFERRAL HOSPITAL
43.1 Funds not Accounted for
Paragraph 217 of Part 1 of the Treasury Accounting Instructions (TAI) 2003
requires advances to be accounted for within 60 days and there after deductions
to be made from the monthly salary of the debtor and no new advance to be given
before accounting for the previous advance.
It was however, observed that UGX 12,520,753 remained unaccounted contrary to
the regulation as shown below;
567
Unaccounted for funds
Date Vr No. Particulars Payee Amount remark
3.10.13 3.'1 Refund to the MOH MOH
7,395,755
Funds not
acknowledged
27.2.14 67.2
Repair and servicing of
computers
Computers and
beyond Africa
5,125,000 No job cards
12,520,755
Delays in submission of accountability may lead to falsification of documents.
Consequently, I could not ascertain whether the funds were used for the intended
purposes.
I advised the Accounting Officer to ensure that funds are accounted for or else
recovery be made in accordance with Section 217 of Treasury Accounting
Instructions.
43.2 Mischarge of Expenditure
Paragraph 156 of Treasury Accounting Instructions provide that funds available
under one item or sub item of expenditure may not be transferable to another
item without the authority of a virement. UGX.35,875,900 paid for various
services were charged on items which do not reflect the nature of the expenditure.
This was done to disguise expenditure as per the approved estimates.
Management took note of the anomaly and promised to desist from this practice in
the future.
I await to see the outcome of management promise.
43.3 Under Staffing
The hospital has an approved structure of 401 staff, however only 209 (55%)
were filled; leaving a staffing gap of 192 representing 45% of the establishment.
The staff shortage includes critical staffs like consultants, medical officers,
surgeons, gynaecologist, radiographers, nurses and Laboratory Technicians were
568
inadequate. This man power shortage hampers delivery of service to the
community.
The Accounting Officer admitted the shortcomings and explained that there is
need for the Central Government to ensure that key critical staff are recruited in
order for the hospital to be able to deliver on its mandate.
I advised the Accounting Officer to liaise with Ministry of Health to address the
matter.
44.0 CHINA-UGANDA FRIENDSHIP HOSPITAL NAGURU
44.1 Transfers from Treasury General Account
A review of the bank statements for the referral hospital revealed that funds
totaling to UGX.1,500,129,768 were transferred from the Treasury General
Account to a Sub Treasury Single Account as indicated below;
NO Date. Document No. From Amount (UGX).
1. 18/10/13 9911FN132910118 Q336TSA Naguru Referral Hospital 1,057,785,926
2. 30/01/14 991SIS03132940077 00376 Naguru Referral Hospital 86,833,440
3. 10/06/14 991SIS0132940077 00376 Naguru Referral Hospital 290,724,060
4. 16/06/14 991SIS0132940077 00376 Naguru Referral Naguru 64,786,342
Total 1,500,129,768
I was not availed with documentation on how the funds were eventually spent. In
the circumstances, it was not possible to ascertain the purpose for which the
money was used.
Although the Accounting Officer indicated that management was taking measures
to provide the documents, these were not availed by the time of writing this
report.
I advised the Accounting Officer to avail the necessary accountability or enforce
recovery of the above funds.
569
44.2 Revenue performance
The Hospital had an appropriated budget of UGX.9,548,296,000 for the year under
review but received only UGX.7,187,921,785 resulting into a shortfall of
UGX.2,498,998,215 (26%). As a result, the following activities were not
implemented:
Medical waste management to handle organic medical waste,
Construction of incinerator,
Hospital expansion by an additional floor,
Oxygen supply to essential units of the Hospital,
Provision of food to patients and staff motivation through allowances.
Failure to implement planned activities impedes the Hospital from achieving its
objective. There is also a risk that the initial government intentions of improving
the referral system in Kampala and decongesting Mulago Hospital Complex may
not be achieved in the short run.
I advised the Accounting Officer to liaise with the Ministry of Finance Planning and
Economic Development and other stakeholders, to ensure that the Hospital‟s
budget is always fully funded to enable it achieve its objectives and the
government intentions of improving the referral system in Kampala.
44.3 Purchase of Land for Staff Houses
During the year under review, UGX.993,000,000 was paid to an individual for
measuring 0.776 hectares, and Block 230 plot 1471 measuring 0.034 hectares
under procurement reference number CUFH/SUPLS/13-14/00016. The following
anomalies were observed:
While the purchase was meant for block 230, plot 1472 and part of plot 1471,
the contract signed with the vendor and the certificate of title showed the land
details as to be for block 230, plot 1473 and part of plot 1472. Plot 1473 had
not been valued by the Chief Government Valuer and therefore the price for it
had no basis. This could cause unnecessary land wrangles.
570
The certificates of title had not been transferred into the names of the Hospital
by the time of audit. The transfer of ownership had been halted by the
Principal Registrar, Wakiso district, pending clarification on the Hospital names
since the Hospital interchangeably uses the names of China Uganda Friendship
Hospital and Naguru Referral Hospital.
The Accounting Officer explained that the differences in plot numbers were not
attributed to Naguru as an entity but to Wakiso lands office as they indicated that
the initial plots were “re-numbered due to double plotting”. This was not in any
way likely to cause any confusion in future. He also indicated that management
was making all efforts to transfer the titles in the Hospital names following
clarification in the Hospital‟s name by the Permanent Secretary, Ministry of Health.
I advised the Accounting Officer to obtain clarification regarding the details on the
land title and also expedite the transfer process.
44.4 Construction of a Drug Store
The Hospital procured a local construction firm to construct a three level office
structure and a drug store at a contract sum of UGX.769,240,009. During the year
under review, a total of UGX.223,077,200 was paid to the firm on Voucher number
NR310/06/2014, vide EFT 1239859, however the following anomalies were noted:
Non Public bid opening
There was no public bid opening contrary to Regulation 62 (1) of the PPDA
Regulations 2014 (Rules and Methods for Procurement of Supplies, Works and
Services) which requires bids submitted under the open bidding method or the
restricted bidding method to be opened at a public bid opening session.
Raising a bid advertisement before contracts committee approval
A bid Advertisement was raised on 3rd January 2014 before the Contracts
Committee approved the procurement method, Bid document and Advert which
was done on 17th March 2014. This contravenes regulation 12 of the PPDA (PDE)
regulations 2014.
571
Lack of approval of plan by KCCA
The plan for the offices and stores was not approved by the Area Planning
Authority (KCCA). It was noted that the Directorate of physical planning in KCCA
gave a notice of deferment of development permission sighting among other
reasons the encroachment by the drug store on the planned road reserve and the
confusion relating to the developer‟s name. This has stalled construction which
may lead to escalation of construction costs and delayed completion.
In response, the Accounting Officer explained that, Plans for the drug store were
submitted to KCCA as required by law. However, KCCA deferred the development
permission for the Project. Efforts were made to address all the concerns raised.
I advised the Accounting Officer to follow up with KCCA and ensure that the
development plans are approved. In future, bid documents should always be
approved by the Contracts Committee before an advertisement is placed.
44.5 Medical waste Treatment Machine
A review of the hospital medical waste disposal process revealed that the hospital
has a medical waste treatment machine bought locally at UGX.250m for
incinerating solid medical waste materials. The hospital however does not have
the capability to handle medical waste like placentas and is locally disposing off
such waste.
Whereas the hospital is commended for acquiring the medical waste treatment
plant, the absence of a placenta pit, makes it difficult to handle and dispose the
non solid waste matter. The Accounting Officer explained that the recommendable
manner could not be achieved because the Hospital was financially constrained as
this activity was among the unfunded priorities.
I advised the Accounting Officer to put in place maintenance procedures for the
equipment to ensure its sustainable use and to also institute other necessary
measures for disposal of other waste matter.
44.6 Demurrage Charges
572
A review of the documents revealed that during the year funds totaling
UGX.20,700,916 were paid to a clearing firm for clearing medical equipment
donated by the Republic of China. However, it was noted that 40%
(UGX.8,054,900) of the payment was wasteful as it was paid as demurrage for
delay in clearing the equipment.
The Accounting Officer attributed the delay to absence of the TIN for the Hospital
at the time and explained that the Hospital had before delivery of the said
equipment initiated the process of acquiring a TIN online, which process was
delayed due to uncertainty of ownership of the Hospital by URA.
I advised the Accounting Officer to put in place mechanisms of expediting specific
processes whose delays could lead to such wasteful expenditure.
573
EDUCATION SECTOR
45.0 MINISTRY OF EDUCATION AND SPORTS
45.1 Mischarge of Expenditure
Paragraph 156 of the TAIs prohibits the transfer of funds available on one item or
sub-item of expenditure to another, save on the authority of a virement warrant.
It also prohibits charging expenditure to an item/sub-item merely because funds
are available under that item/sub-item.
On the contrary, it was noted that out of the total expenditure of
UGX.97,566,221,002 (excluding transfers to other organisations),
UGX.4,395239,994 (4%) was charged on expenditure codes meant for other
activities possibly because funds were available on these item codes.
Mischarge of expenditure is a weakness in budgetary controls and results into
misrepresentation of balances in the financial statements.
Management explained that funds were not released as budgeted, warranting the
accounting officer to use the available limited resources to deliver services.
I advised the Accounting Officer to ensure that transactions are correctly charged
on the right expenditure item codes or else seek reallocations before loading the
releases on the system.
45.2 Unreconciled Position of Payables
A schedule of payables obtained from from the MoFPED (Treasury) indicated that
the Ministry had submitted payables of UGX.20,412,601,005 as at 30th June, 2014.
This position differed from that reported in the financial statements of
UGX.1,608,017,001 by UGX.18,804,584,004. The conflicting positions pose a risk
of settling bills that are not supported with underlying transactions.
574
The Accounting Officer explained that a fresh verification by Internal Audit had
been instituted to establish the true position of the payables. I await the outcome
of Management‟s action in this regard.
45.3 Under-Funding of Examination Boards
During the year, Uganda Allied Health Examination Board (UAHEB), Uganda
Business and Technical Examinations Board (UBTEB) had a and Uganda Nurses
and Midwives Examinations Board (UNMEB) revenue budget of
UGX.20,674,619,576 expected from Government. However, the Board received
only UGX.16,655,471,933, resulting into a shortfall of UGX.4,019,147,643. This
could have greatly affected the performance of the boards. The Table below
refers:
Board Budgeted Revenue from
Government (UGX)
Received (UGX) Shortfall (UGX)
UAHEB 3,990,255,000 2,509,379,167 1,480,875,833
UBTEB 9,000,000,000 6,901,365,226 2,098,634,774
UNMEB 7,684,364,576 7,244,727,540 439,637,036
Total 20,674,619,576 16,655,471,933 4,019,147,643
Management attributed the shortfall to stagnant non-wage allocations within the
sector ceiling, which could not allow allocation of additional funding to the boards.
I advised the Accounting Officer to liaise with MoFPED to ensure that the boards
are adequately funded to facilitate implementation of their planned activities.
45.4 Redundant Teachers SACCO Fund
During the year, the Government offered UGX.25bn to the teachers‟ SACCO fund
to be contributed in 5 years with the objective of enabling teachers access
affordable credit financing. A total of UGX.4,317,423,564 was released to Micro
Finance Support Centre during the year under review. However, by the time of
writing this report, the funds had not yet been accessed by the beneficiary
teachers. Besides, the fund management had become a source of conflict between
UNATU and the Ministry. In the circumstances, the objectives of funding the
teachers SACCO may not be achieved.
575
Management attributed the delay in operationalization of the fund to the long
procurement process of a fund manager, and the process of developing the
necessary guidelines. Management further indicated a fund manager was
eventually procured and the process of disbursements was underway.
I advised Management to ensure operationalization of the fund so that the
intended objectives are achieved.
45.5 Funds Not Accounted For
a) Advances to Schools, Colleges and Technical Institutions
Funds amounting to UGX.559,122,789 were advanced to various primary schools
for construction activities during the year under review. However, it was noted
that the Ministry neither received accountability returns nor progress reports for
the funds. In the circumstances, there is a risk that the funds were not utilized as
intended.
The Accounting Officer indicated that reminder letters had been sent to the Head
Teachers of the affected schools demanding for accountability of the funds.
I advised the Accounting Officer to ensure that funds advanced to schools for
various activities are accounted for in a timely manner. In the alternative the funds
are recoverable.
b) Other Advances
UGX.314,636,968 was advanced to various institutions and individuals outside the
Ministry to undertake various activities such as teachers training and subventions.
However, contrary to paragraph 217 of the Treasury Accounting Instructions,
there were no accountabilities to show utilization of the funds. In the
circumstances, I was unable to ascertain whether the funds were utilized for the
intended purposes.
I advised the Accounting Officer to ensure that all the funds are accounted for by
the respective beneficiaries to give assurance that the money was used for the
576
intended purposes.
45.6 Budget Performance
Out of the budgeted revenue of UGX.197,562,361,139 only UGX.186,558,729,377
was received resulting into a shortfall of UGX.11,003,631,762 (6%). As a result a
number of activities were not implemented which hinders the Ministry from
achieving its objectives. The table below shows the activities that were not
implemented;
Output Name Description of
Performance Planned outputs Status and
reason for
variations
Pre primary and
Primary
education
Instructional
materials for
primary schools
The department planned
to complete procurement
of P5 -P7
textbooks as rolled over contracts for the
2,378,829 pupils books
and 325,000 teachers' guides for P5 and P7
Reprint curricula for P1
and P2;
Pay for consultancy of
Needs assessment for SNE;
Procure hearing Aids for
assessed learners of SNE;
Procure instructional
materials for PTCs; Conduct prequalification
workshop for P1 and P2 instructional materials
The evaluation of
bids for P1
and P2 was a spill-over activity from
FY 2012/13. -Final payment for
the supply
and delivery for P5-P7 textbooks in
favor of M/S Longhorn
Publishers combined the two
final tranches (60%
upon presentation of shipping
documents; 20% upon
Verification of
deliveries.) -Funds for the
procurement of assorted textbooks
to support implementation of
revised PTE
curriculum were processed but not
paid. Therefore, the Procurement
process and
monitoring requisition could
not be
577
Output Name Description of Performance
Planned outputs Status and reason for
variations
accomplished by the end of the
Financial Year.
Secondary School Education
Instructional materials for
Secondary schools
Books and periodicals
procured; Computer and ICT
services
provided; 4th cycle of 50 schools
under Digital Science
Cyber handled;
Text books for science
and mathematics for the
UPOLET government and PPP schools procured;
Computer laboratory of
Bukoyo SS; Iganga equipped with 80
Computers.
Under the APL project by the
end of Q4, the supplier had not yet
delivered the
science kits to the beneficiary schools
Secondary School Education
Monitoring and Supervision of
Secondary
Schools
425 site meetings
attended at 56 institutions to, monitoring
of 43
institutions by ADB IV;
Funds were transferred to item
70201 to offset a
funding shortfall
Secondary
School Education
USE Tuition
Support
East African essay
competitions
carried out
- The East Africa
Essay competition in Secondary
schools was not facilitated because
money was
transferred to offset a funding shortfall.
-Funds were defrayed from
training of
secondary teachers to follow up trained
teachers.
Secondary School Education
Provision of furniture and
equipment to secondary
schools
Furniture supplied to 100
beneficiary schools in
Phase III Under world bank
project.
The process is being financed by
donor funds.
Quality and
Standards
Inspection
(Primary Secondary
BTVET) and monitoring of
Inspection of 1,900
secondary
schools, 500 BTVET
Institutions 10 NTCs, 20
PTCs
-The targeted
number of 8 vehicles was not
tenable because of price variations at
578
Output Name Description of Performance
Planned outputs Status and reason for
variations
construction works in PTCs
the time of procurement.
-Activities for the relocation of
Shimoni project did
not proceed due to contractual
problems which are being sorted out.
Management explained that the Ministry of Finance, Planning and Economic
Development (MoFPED) only released 94% of the appropriated budget which
consequently affected the performance of MoES.
I advised Management to always liaise with the MoFPED to ensure that all
appropriated funds are released.
45.7 Government of Uganda Payroll Validation Exercise
I appointed Ernst & Young to undertake a payroll audit and to validate and
capture the biometric details of all Government of Uganda Employees.
In a press release dated 4th April, 2014, I reiterated that employees who failed to
present themselves for validation and have their biometric data captured face the
risk of being deleted from the Government payroll.
However, it was noted that 37 staff of MoES never presented themselves for
validation. There is a risk of being deleted from the Government payroll, if at all
the affected employees do exist. Management explained that by the time of Audit
some staff had not been validated but since then, they have been validated
however verification could not confirm management response.
I advised the Accounting Officer to ensure that the affected employees are
validated or deleted from the payroll as appropriate.
579
45.8 Unreconciled UMEME Arrears
In his communication to various accounting officers dated 7th October, 2014 (Ref.
ISS 49/137/01, the PS/ST indicated that UGX.26.193 billion due to Uganda
Electricity Distribution Company (UETCL) had been withheld by UMEME on account
of Non-payment of bills in the MoES by Government of Uganda for the period June
2013 to June 2014. Previously another UGX 18.34 billion had been withheld in a
similar manner for the previous period
In the case of the MoES, the letter indicated that UGX.20,187,950 was outstanding
as at 30th June 2014. However, the list of payables indicated that the outstanding
UMEME bill was UGX.1,513,523,108 as at 30th June, 2014.
Although the Accounting Officer was requested to confirm and reconcile with
UMEME the arrears position, there was no evidence that this was done. There is a
risk that the Ministry continues to settle bills that had already been offset from
payments to UEDCL. .
Management explained that the ministry had not paid any arrears on outstanding
UMEME bills cause they had not received any cash limits for it and that
management was in contact with MoFPED to provide the ministry with
information regarding funds withheld owed by government to UMEME.
I have advised the Accounting Officer to reconcile UMEME bills with the Ministry
balances to avoid multiple settlement of the same bills.
45.9 Consultancy Services for Undertaking Assessment of Learners with
Disabilities/Special Needs-Hearing Aid Assistive Devices-MOES/12-
13/SRVCS/0233/C0737
a) Delayed Procurement Process
It was noted that the Ministry planned to procure consultancy services to
undertake Assessment of Learners with Disabilities/Special Needs in the Financial
year 2012/13. Significant delays were however noted in this procurement from the
580
time it was initiated up to the time of contract signing as shown in the table
below:
Activity Date when action was taken
Procurement Requisition was raised by the user department
on PP Form
25th October, 2012
Confirmation of funding was approved by US/FA at Estimated
Cost of UGX. 200,000,000.
20th February,2013
An Advert run on in the Daily Monitor included a Schedule of activities which stated that implementation start date was
22nd July, 2013
10th May, 2013
Contract Agreement Signing at Contract Price of UGX.413,082,200
1st November, 2013
Delays in the procurement process greatly affect procurement planning and lead
to delayed service delivery.
The Accounting Officer attributed the delay to major staff transfers in the PDU
during the year under review which impacted negatively on performance.
I advised Management to ensure that procurements are always initiated and
implemented in the planned time period.
45.10 Supply of Textbooks and Instructional Materials (MOES/Supplies/11-
12/0013)
a) Delayed Delivery of Instructional Materials by Contractors
Regulation 260 (1) (b) of the PPDA Regulations, (2003) requires a contract
manager to ensure that the service provider performs the contract in accordance
with the terms and conditions specified in the contract. During the year under
review, the Ministry engaged various private firms to supply and deliver
instructional materials to various schools in the country. However, delays were
noted in the execution of the contracts well beyond the agreed 120 days. Besides,
there was no documentary proof that the liquidated damages clause was evoked.
Contractor and contract
details
Contract
sum (UGX)
Contract
date
Expected
date of discharge
(120 days)
Actual
date of discharge
Varianc
e
M/S Longhorn publishers.(supply of p.5,p6&
p.7 text books)
7,057,673,400 30/5/2013 30/9/2013 16/10/2014 381 days
581
Contractor and contract details
Contract sum
(UGX)
Contract date
Expected date of
discharge
(120 days)
Actual date of
discharge
Variance
M/S East Africa Educational
publishers. (supply ofP.5 Swahili text books)
519,135,760 30/5/2013 30/9/2013 13/10/2014 378 days.
M/S St.Bernard
publishers.(supply of p.5 math text books)
500,916,000 30/5/2013 30/9/2013 23/5/2014 223 days.
M/S Fountain Publishers.
(Supply of p.5, p.6 & p.7 text books).
2,588,953,878 30/5/2013 30/9/2013 03/02/2014 123 days
M/S M.K Publishers Ltd,
(supply of p.5,p.6 & p.7 text books)
3,433,484,300 31/5/2013 30/9/2013 14/04/2014 194 days.
In the circumstances, the objectives of the procurement were undermined. I
explained to Management that there could be change of curriculum before
utilization of the said books. The delays could also affect the intended beneficiaries
especially the candidate classes.
The Accounting Officer attributed the anomaly to delays in issuing of clearance
certificates to contractors for mass printing.
I advised Management to always ensure that terms and conditions of a contract
are complied with to ensure effective and efficient service delivery.
b) Lack of Contract Management Records
Regulation 259(1) of the PPDA Regulations, (2003) requires the Accounting Officer
to appoint a contract manager for each contract/procurement, who will inter alia
draw a contract management plan and keep a record of performance of the
contract. However, it was noted that no contract management plan for the
procurement of instructional materials was drawn, and contract management
records such as progress reports, field reports, copies of payments made, among
others, were not maintained on file.
I explained to Management that absence of contract management records makes
it difficult to confirm whether supervision and monitoring of the contract was
carried out in accordance with the specified terms of the agreement.
582
Management explained that the contract manager had limited human resource
capacity to effectively implement the Regulation and promised to build capacity in
contract management.
I advised Management to always ensure compliance with the Regulations in this
regard.
45.11 MUNI UNIVERSITY
a) Budget Performance
Whereas the University budgeted to receive revenue amounting to
UGX.5,000,000,000 from government grants, only UGX.4,459,251,381 was
received through the MoES, thereby registering a shortfall of UGX.540,748,619
(10.8%). The shortfall constrained Management in implementing planned capital
development projects at the University.
Management explained that MoES received 94% of its appropriated budget which
consequently affected the performance.
I advised Management to always liaise with the Ministries of MoFPED and MoES to
ensure all budgeted funds are released.
b) Implementation of Unapproved Strategic Plan
It was noted that the Management of the University has been implementing a 5-
year draft Strategic Plan covering the period 2010/11 to 2014/15. Lack of an
approved strategic plan may lead to implementation of activities that are not
strategic to the University.
Management explained that the draft Strategic Plan was submitted to the Council
for consideration.
I advised Management to follow up the matter and ensure that the Strategic Plan
is approved to give proper direction to the University when it is still at its formative
stage.
583
c) Land Ownership
The University owns various pieces of land totaling to 3,690.3746 acres. All the
land was donated by the local communities and agreements of offer are in place,
except for 0.4446 acres along post office Road. By the time of writing this report,
only one title for the land measuring 2973.13 acres had been secured, with the
rest of the pieces of land without ownership titles. There is a risk of the university
losing the land to encroachers. The table below refers;
Location Sub- county District Land size Status
Muni Oluko Arua 130.054 acres Lease process ongoing
Paroketo Pakwach Nebbi 147.166 acres Lease process ongoing
Bidibidi Romogi Yumbe 439.58 acres Lease process ongoing
Madiokello Okollo Arua 2973.13 acres Land title obtained
Along Post
Office rd,
Arua
Municipality
Arua 0.4446 acres Process of opening
boundaries
3,690.3746
Management explained that most of the leases were in the final stages of
processing, and the parcel of the land along post office road in Arua Municipality
had just been donated. The process of re-opening the boundary had also begun.
I advised Management to liaise with the relevant authorities and expedite the
transfer processes.
45.12 SUPPORT TO THE POST-PRIMARY EDUCATION TRAINING EXPANSION
AND IMPROVEMENT (EDUCATION IV) PROJECT
a) Compliance With Financing Agreement Provisions And Gou
Financial Regulations
i. Government of Uganda Counterpart Funding
The African Development Fund Project Appraisal Document required the
Government of Uganda to contribute 10% of the total project cost and partially
584
finance the categories of expenditure for works (10%), services (10%) and
operating costs (80%), all to the tune of UA 5,780,000 (Approx. USD 9.36 Million).
However, with 92% of the project time elapsed as at 30 June 2014, the GoU
contribution stood at UA 4,170,776, equivalent to USD 6.76 Million (72% of the
agreed amount). There is a risk that the project will close without the government
making its full contribution to the project. This can also lead to accumulation of
unpaid bills thereby affecting completion of all agreed and planned activities.
The Accounting Officer explained that the pace at which the counterpart funds
were released to the Ministry on a quarterly did not match the rate at which the
contractors‟ requests for interim payment certificates came in. I have advised the
Accounting officer to liaise with the Ministry of Finance Planning and Economic
Development to ensure that GOU obligations are met to enable the
implementation of the agreed activities.
ii) Slow Progress in Project Implementation
Review of the project implementation records showed clusters I, II and III were
due to have been completed in September 2013. However, it was noted that some
of the cluster I, II and III activities were still outstanding. Also noted was that the
works under cluster IV whose contracts were signed in September 2013 and
expected to be completed in September 2014 were behind schedule.
Delays in the completion of works would call for unnecessary variations and
increase in contract administrative costs in terms of inspection. In addition, the
specific activities may be affected if they are still incomplete at the time the
project ends.
The Accounting officer explained that time contract extensions had been site-
specific and they did not result into a change in contract price variations hence no
additional cost. Out of the 68 targeted beneficiary institutions under the Project,
44 (65%) had been completed and 17 (25%) had attained a rate of completion of
75-95% and above. Management further indicated that measures had been put in
place to address civil works challenges and intensify site supervision and
monitoring.
585
I await the outcome of management‟s intervention in this regard.
iii) Recruitment of Teachers for Seed Schools
Under the project 12 new seed secondary schools are to be constructed and be
fully furnished and equipped. It was noted that out of the 12 schools, 4 schools
namely; Mella SSS, Atutur SSS, Kanara SSS and Wakyato had been completed,
handed over by the contractors and students enrolled. However, no teachers were
posted to these schools to teach the enrolled students. It was further noted that
the schools were operating with the support of a few community volunteer
teachers who were not on government payroll. Lack of committed and facilitated
teachers may compromise the project objective of accessing equitable and quality
education.
Management explained that the Executing Agency had made attempts to deploy
Teachers to the new seed secondary Schools but the majority had not reported for
duty citing relocation challenges arising from location of the seed secondary
schools. They stated that a formal request for approval of recruitment of teachers
for the seed schools had been sent to the Ministry of Public Service.
I await the outcome of management‟s action in this regard.
b) General Standards of Accounting And Internal Control
It was noted that management had in all material respects, put in place a
satisfactory internal control system and measures to ensure proper accountability
for all project funds.
45.13 UNIVERSAL POST PRIMARY EDUCATION AND TRAINING PROJECT
a) Compliance With Financing Agreement Provisions And Gou
Financial Regulations
It was noted that management had in all material respects complied with the
covenants contained in the Financing Agreement and the Government of Uganda
Financial Regulations except for the following matters:
586
i) Funds not accounted for
The Treasury Accounting Instructions, paragraph 181 and the Public Finance and
Accountability Act Reg. 63(4) require all vouchers to contain full particulars of each
service or goods procured and such supporting documents as may be required to
enable checking without reference to any other documents.
Furthermore, Guideline 4.18 of the School Based Procurement and Implementation
Manual for Civil Works 2012 requires the accountability returns to be submitted to
the Ministry of Education and Sports (MoES) within one month after utilization of
funds.
A sum of UGX.225,472,952,772 was advanced to schools for UPPET activities
under phase 1 and phase 2. However at the time of audit, only
UGX.215,464,635,286 had either been accounted for after utilisation or refunded
by various schools leaving an outstanding balance of UGX.10,008,317,486.
The funds were advanced between May 2011 and December 2013 as summarized
in the table below:
No of
s
c
h
o
o
l
s
Advanced
(UGX)
Accounted
(UGX)
Refunded
(UGX)
Total Accounted
for and refunded
(UGX)
Total
Outstanding
Balance (UGX)
Phase
1
215 59,523,373,232 49,872,017,510
6,233,577,706
56,105,595,216 3,417,778,016
Phase
2
422 165,949,579,540
155,889,800,45
2
3,469,239,618
159,359,040,070 6,590,539,470
Total 637 225,472,952,772 205,761,817,962 9,702,817,324 215,464,635,286 10,008,317,486
Failure to account for the funds in a timely manner could lead to their misuse by
the respective schools.
Management explained that they had intensified financial accountability
requirements and the status continued to change as more accountability returns
587
were being submitted by the schools. In addition management had requested the
PS/ST to consider attaching accounts of schools with big outstanding balances.
I have advised the Accounting Officer to follow up the long outstanding
accountabilities and ensure that the respective schools comply with the
accountability requirements.
iii) Terminated contracts without recovery of Performance Securities
Section 232 (5) & (6) of the PPDA Regulations state that where a provider is
required to provide a performance security, a bid security from that provider shall
not be released until a satisfactory performance security is received by a procuring
and disposing entity. A performance security shall not be released by a procuring
entity until all the provider's obligations have been fulfilled.
A number of firms were engaged to undertake civil works at 35 schools for an
aggregate contract sum of UGX.9,099,561,449. At the time of audit, a sum of
UGX.3,894,801,294 had been paid to the contractors in respect of certified works.
However, the contractors failed to execute the contracts to completion culminating
into termination. At the time of termination most of the performance securities had
expired and as such they could not be cashed. This could lead to loss of funds
where particular contractors fail to perform their contracts.
Management explained that during the project implementation, a number of
challenges arose such as inflation, delayed release of funds to schools, low
quotations; and these resulted into slow progress and un-recorded time
extensions. Whereas the schools were advised to terminate non-performing
contracts, delays in termination resulted into expiry of performance securities
making it impossible to cash them.
I have advised management to always ensure proper contract management and to
consider legal action against the errant contractors.
iv) Refund of ineligible Expenditure to IDA 4570-UG USD 1,124,755
588
Funds amounting to UGX.2,868,124,565 (USD.1,124,755) was validated as
ineligible contrary to the loan agreement according to the validation exercise of
accountability reports. Consequently the PS/ST by way of a virement effected a
refund of UGX.2,958,105,650 equivalent of USD.1,124,755 to IDA Bank in New
York.
I explained to the Accounting officer that there is a risk that project activities were
not implemented as planned and management risks funding sanctions from the
Bank due to noncompliance with the loan agreement. The virement in the current
budget to refund the money implies that the planned activities in the current
budget could not be implemented.
Management explained that the ineligible expenditure was caused by individual
head teachers who chose to spend project funds outside the guidelines. These
head teachers were interdicted and some were being investigated by CIID and as
a result, some of the head teachers were paying back and the names of the errant
ones had been submitted to MoFPED to tag the funds on their retirement benefits.
I have advised the Accounting officer to ensure full recovery of the outstanding
ineligible expenditure from the errant head teachers. Future programmes of same
nature should also include detailed sensitisation of head teachers on the
procedures of implementation and utilisation of programme funds.
v) Government obligation arising from Delayed procurement process
The construction of 44 Schools (19 new and 25 for completion) were turned down
by the World Bank on the basis that the computations contained errors and they
were late as there was insufficient time to correct the errors and sign the contracts
to get the work completed by Project closure date of 31st July 2014. The amount
spent on the 25 incomplete Schools was UGX.1,454,214,518 and the estimated
cost up to completion is UGX 15,727,562,518 which gives rise to immediate
government obligation to implement the construction of the incomplete schools.
Management explained this was brought about by failure by the schools to
account for disbursed funds and that Government has committed to provide
resources to complete the unfinished activities in the financial year 2015/16.
589
I have advised the Accounting officer to pursue the matter urgently so as to avoid
further deterioration of the unfinished structures.
vi) Cancelled Schools
A total of 48 schools were cancelled during the IDA Implementation Supervision
Mission of the UPPET/APL1 project in April 2014 on grounds of having outstanding
issues with their financial records with possible interdiction of some head teachers
who were also still reluctant to terminate contractors contrary to technical advice
provided. It was noted that work resumed on six of them and two had been
completed as detailed in the table below:
School Status
Jubilee SS On Going
Nyakinoni SS On going
Puranga SS Completed
St Kizito SS Nakibano On Going
Nyabiteete SS Completed
Kiyeyi High School On going
The remaining 42 Schools were still un-attended to after a total of
UGX.6,140,261,629 was incurred on them. It was also noted that no measures had
been put in place to safeguard the developments which may result into their
destruction and therefore loss of the money spent so far. There is also the risk
that the intended project targets may not have been met.
The Accounting officer indicated that the cancelled schools were to be budgeted
for and constructed in the FY 2015/16 using GoU funds. I await the outcome of
management action.
b) Project implementation status
By June 30, 2014, USD.140,924,633.55 (94.04%) of the credit had been disbursed
and later the project closed on 31st July 2014. However, the status report showed
that some project component activities had not been completed and by the time
590
of Audit (November 2014), the following components had not achieved 100%
status of implementation. There is a risk that with the project closure, the
components may not be implemented fully.
Project
Component
Purpose (Sub components) Status (Nov 2014)
Increasing
equitable
access to
lower
secondary
schools
On-going construction of
Classrooms
87%
Improving
quality for
lower
secondary
education
Revised Curriculum framework for
lower secondary
95%
Supply of lockable metallic
bookshelves
90%
Management attributed the delay in project implementation to strict adherence to
procurement processes and preliminary activities such as need to adequately
prepare and train the different categories of actors involved in the project
implementation.
I have advised management to ensure steps are taken so as to ensure attainment
of the intended project objectives.
i) Incomplete and Delayed supply of School Furniture
By the close of June 30, 2014, 131 out of the 573 completed schools did not have
furniture of which 122 schools‟ furniture had been centrally procured. It was noted
that 30% of the centrally procured furniture contract were to be executed by 31st
July, 2014. This implies that 94 schools will not have furniture, (85 of the 122
schools will not be furnished from the project, and additional 9 complete schools
whose bills of quantities did not include furniture supply but were identified at
completion).
Although Management explained that Furniture for 122 schools has been delivered
to the central stores in the Ministry and is yet to be distributed to the beneficiary
schools, I was unable to verify the delivery to the central stores.
591
iii) Delayed Delivery of Procured Motor Vehicles
On 29th November. 2013, the Ministry signed a contract with M/S Toyota U Ltd to
supply 2 motor vehicles - Toyota Land cruiser (station wagon) at a cost of
USD.241,654,000.
Examination of payments revealed that the Ministry paid a total of
UGX.397,093,223 in 2 instalments vide Invoice No. UPPET124 of 30th April, 2014
(UGX.199,649,223) and Invoice No. R 730/Jun (UGX.197,444,000). However, by
the time of writing this report in December 2014, the vehicles had not yet been
delivered to the Ministry (project closed on 31st July 2014).
I explained to management that Delayed delivery defeats the purpose for which
the vehicles were required. Full payment for the vehicles amounted to pre-
financing the supplier.
The Accounting Officer explained that the vehicles were with the supplier and
were to be delivered to the Ministry. I have advised management to follow up with
the supplier and have the vehicles delivered.
46.0 MAKERERE UNIVERSITY
a) Mischarge of Expenditure
Paragraph 156 of the TAI provides that funds available under one item or sub-item
of expenditure may not be transferred to another item or sub-item save on the
authority of a virement warrant, nor may expenditure be charged to an item/sub
item merely because funds are available under that item/sub-item.
It was noted that UGX.969,917,237 was wrongly charged on item codes meant for
other activities other than those for which the expenditure was incurred.
Mischarge of expenditure is an indication of weaknesses in budgetary controls and
results into misrepresentation of balances in the financial statements to the extent
of the mischarged expenditure.
592
I advised the Accounting Officer to strengthen controls over budget execution to
avoid mischarge of expenditure codes.
b) Payment for Extra Load Allowance
During the year under review, the University spent a total of UGX.308,857,850 as
allowances for the extra lectures taught and work done during the weekends and
evenings. However, the basis of computation of individual payments, including
information relating to the total number of hours lectured above the standard
hours by each lecturer and rates were not availed to support the payments.
There was also no evidence of monitoring and supervision of teaching staff, who
taught outside the normal working hours. In the circumstances, the authenticity of
the payments could not be ascertained.
Management explained that at the time of the audit, some staff had not been
confirmed in the University service but this was later rectified. However, the
relevant supporting documents were not availed during the verification exercise.
I advised the Accounting Officer to:
ensure that payments for extra load allowances are properly supported with
evidence of having carried out the extra load activities.
ensure that the appointments are approved by the Appointments Board as
required.
formulate and institute a proper mechanism of monitoring and ensuring that
payment for extra load activities are undertaken.
c) Delayed and Non Deduction of NSSF Contribution
Section 11(1) of the National Social Security Fund Act, Cap 222 of the Laws of
Uganda, 2000 requires that every contributing employer shall, for every month
during which he or she pays wages to an eligible employee, pay to the fund,
within fifteen days following the last day of the month for which the relevant
wages are paid, a standard contribution of 15 percent calculated on the total
wages paid during that month to that employee. However, it was noted that the
University remitted UGX.1,256,828,654 to NSSF more than 15 days after the due
dates.
593
Also noted was that the University did not make deductions amounting to
UGX.338,830,110 as 5% employee contribution from staff salaries. This could
lead to loss of staff earnings in form of interest,in additionto exposing the
University to the risk of penalties by NSSF. The reported payables in the financial
statements are misstated in this regard.
Management explained that the affected staff had not yet been allocated NSSF
numbers which were later given and the University was in the process of remitting
the money to NSSF.
I advised the Accounting Officer to ensure that the deduction in respect of NSSF is
always effected and remitted in a timely manner.
d) Pension Liabilities
The University had outstanding pension liabilities of UGX.30,406,365,541 at the
close of the financial year. The following observations were made:
a) Unremitted DAP Arrears contributions
The University runs its own Retirement Scheme, Deposit Administration Plan
(DAP)where the staff contribute 5% deducted from their individual salaries while
the University contributes 10%.Included in the balance of pension liabilities is a
sum of UGX.10,632,082,369 in respect of deductions and contributions that
Management had not been deposited on the DAP Account by close of the year. In
the circumstances, the fund‟s ability to grow to cater for members‟ interest
earnings is limited and its sustainability is curtailed.
The Accounting Officer attributed the state of affairs of the DAP to underfunding of
the University which leads to payment of net accounts and leaving the
contributions to DAP as payables.
I advised Management to ensure timely remittance of contributions in accordance
with the provisions of the Fund to ensure its sustainability.
594
b) Unremitted NSSF Contribution Arrears
Section 11(1) of the NSSF Act, requires every contributing employer every month
during which he or she pays wages to an eligible employee to pay to the fund,
within fifteen days a standard contribution of 10 percent calculated on the total
wages paid during that month to that employee. On the contrary, it was noted
that the University did not remit UGX.601,706,641 for financial years ending June
2007 and June 2008 to the Fund. Non-remittance of contributions to the Fund
impacts on the staff savings inform of interest and could also attract penalties
from the Fund.
The Accounting Officer attributed the non-compliance to underfunding of the
University but indicated that they had started remitting the outstanding balances.
I advised the Accounting officer to engage the key stakeholders and ensure that all
the outstanding balances are remitted to NSSF to enable members earn interest
on their contributions and also avoid possible penalties.
e) Accumulation of Payables
Contrary to the Commitment Control Policy of Government, there was an increase
of UGX.14,412,306,708 (126%) in the reported payables from
UGX.11,409,981,432 (FY 2012/2013) to UGX.25,822,288,140 in FY 2013/2014.
There is a risk that the University may not be able to settle the creditors given the
current level of funding. It was also irregular for the University to continue to
accumulate domestic arrears without adequate funds to settle them.
The Accounting Officer explained that payables accumulated due to underfunding
of the University but efforts were being made to ensure that they are settled.
I advised the Accounting officer to adhere to the Government‟s Commitment
Control Policy and ensure that the outstanding payables are settled.
f) Unauthorized Over Expenditure
Paragraph 152 of the TAIs Part I, 2004 and section 17 of the Public Finance and
Accountability Act (PFAA), 2003 requires that expenditure not provided for in the
approved estimates of any financial year may not be incurred without the authority
595
of a Supplementary Estimates Warrant, a Virement Warrant or a Contingencies
Fund Advance Warrant. It was noted that the University incurred excess
expenditure of UGX.4,037,303,551 on the two items shown below without the
necessary approval.
Expenditure
Item
Budget Actual Expenditure Variance
Other operating
expenses
14,561,400,379 17,114,067,918 2,555,667,539
Domestic Arrears 780,000,000 2,261,636,012 1,481,636,012
TOTAL 15,341,400,379 19,375,703,930 4,037,303,551
I explained to the Accounting Officer that this practice suffocates other planned
activities whose budgeted funds are diverted.
The Accounting Officer attributed the anomaly to increased prices for students‟
food, unfavourable exchange rates for invoices that were quoted in foreign
currency and pressure to pay the domestic arrears as some creditors threatened
the University with court action.
I advised Management to ensure proper budgeting for all expenditure items to
avoid diverting funds meant for other activities. Furthermore, the Accounting
officer should always seek relevant authority prior for spending over and above
the budget.
g) Revenue Shortfall
Out of the budgeted Internally Generated Revenue of UGX.122,590,439,007 for
the year under review, the University collected UGX.103,076,996,162, resulting
into a shortfall of UGX.19,513,442,845 (16%). Failure to collect budgeted revenue
hindered the University from achieving its planned activities and also accumulating
domestic arrears.
In response, Management attributed the shortfall to the University tuition policy at
the time which gave room for students to pay 60% of fees and the 40% was
carried forward to subsequent years. It however indicated that the University had
taken corrective action and the current policy on tuition is such that all students
must pay100% tuition before sitting for the semester examinations.
596
I advised Management to enforce the fees collection policy to avoid accumulating
receivables which may eventually become uncollectable.
h) Management of Receivables
During the year, Receivables increased from UGX.630,545,566 to
UGX.4,914,675,690, indicating an increase of UGX.4,284,130,124 (680%). A
review of the supporting schedules revealed that a significant proportion of the
debts was in respect of tuition fees (UGX.3,706,164,617) not collected during the
year under review. There was laxity in enforcement of debt collection as there
were students who sat exams without settling the tuition fees contrary to the
University policy.
I explained to Management that accumulation of receivables hinders availability of
cash to finance University operations. There is also a risk that the debts may
eventually become uncollectable.
Management explained that a new unit called Makerere University Revenue
Services Unit had been created and mandated to ensure that fees collection is
enhanced. I advised Management to ensure enforcement of the fees collection
policy.
i) Staffing Gaps
A review of the University staff establishment revealed discrepancies between the
establishment structure and the filled positions. Out of the 2,780 approved
positions, only 1,484 (53.4%) positions were filled leaving 1,296 (46.6%)
vacancies.
I explained to the Accounting Officer that understaffing leads to work overload on
the existing staff and limits the ability of the University to effectively deliver and
achieve its mandate. There is also a risk that optimum teaching is not achieved,
which may affect the University products (students).
597
Management explained that the University had tried to uplift the staffing levels to
an optimal level, but the University Council could not handle the wage bill since it
caters for only 42% of the total wage bill annually.
I advised the Accounting Officer together with the University Governing Organs to
liaise with other stakeholders and address the matter of understaffing by recruiting
more staff to ensure effective service delivery.
j) Government of Uganda Payroll Validation Exercise
The Auditor General appointed Ernst & Young to undertake a payroll audit and to
validate and capture the biometric details of all Government of Uganda
Employees. It was noted that 95 members of MUK staff did not turn up for the
exercise. There is a risk of these employees being deleted from the Government
Payroll if at all they exist.
The Accounting Officer explained that the University was in touch with the Ministry
of Public Service to ensure that the affected staff are validated. It also indicated
that, 22 of the queried staff could not be traced and had been deleted from the
payroll, and the University Security Department was spearheading efforts to trace
and recover the money from the affected staff.
I advised the Accounting Officer to ensure that the traceable employees are
validated. I also await the outcome of the action being taken with regard to the 22
employees.
k) Non-Deduction of Taxes
Section 120 of the Income Tax Act, 1997, requires a withholding agent to pay
withholding tax to Uganda Revenue Authority (URA) within fifteen days after the
end of the month in which the payment for goods and services in excess of UGX.1
million was made. However, UGX.457,214,062 was paid to various suppliers
without deducting withholding tax at 6% and remitting it to URA. Failure to deduct
and remit taxes may attract fines and penalties from URA.
Whereas Management indicated that taxes had been deducted and remitted to
URA, no details of payment were availed for examination.
598
I advised Management to recover the un-deducted taxes from the respective
suppliers for onward remittance to URA in accordance with the Act.
l) Incompletely Vouched Expenditure
Paragraph 181 of the TAI requires all vouchers to contain full particulars of each
service or good and be accompanied by such supporting documents as may be
required so as to enable them to be checked without reference to any other
documents. However, UGX.76,742,813 paid in respect of various activities
including teaching and internship workshops and placements lacked the relevant
supporting documents like attendance registers and minutes.
In the absence of supporting documents, I was unable to confirm that the
expenditure was correctly incurred.
Whereas Management indicated that the supporting documents were available,
they were not provided for audit examination.
I advised the Accounting Officer to ensure that all expenditure incurred is
appropriately vouched and accounted for.
m) Under Utilization of the Integrated Tertiary System for Revenue
Collection
The University procured a computerized integrated tertiary software system (ITS)
in 2004 as a major part of the University‟s wide initiative to improveFinancial and
Human Resource management, and maintenance of Academic Records. The
system is constituted of three Modules, the ARIS (Academic Register Information
System), the FINIS (Financial Information System) and the HURIS (Human
Resource Information System).
It was noted that despite the expected benefits, all three modules were notfully
operationalized to reap the benefits of automation.
The following table summarizes the module components that are functional and
those that are not.
599
MODULES FUNCTIONAL MODULES NON FUNCTIONAL
ARIS
Registration Application and Admission Time table
Study Records Graduation
FINIS
Revenue Collection Assets ,Budgeting Procurement, Sundry
Debtors, Student debtors Code structure and General Ledger
Payroll, Cash Book
HURIS Non functional
This implies that the University is not deriving value for money from the
procurement and installation of the ITS.
Management explained that the system was acquired under donor funding but
later the University was meant to take it up. Due to the financial constraints the
University was faced with, it failed to maintain all the modules as earlier planned.
However, the Ministry of Finance, planning and Economic Development (MoFPED)
is introducing the Centralised Educational Management and Accounting System
(CEMAS) which is expected to replace all the modules with new ones.
I await the outcome of Government‟s intervention in this regard.
n) Failure by the System to Generate Reports
A review of the ITS revealed that the system was notable to generate a number of
reports which are considered important at Management level and for audit
purposes. Examples of reports that the system could not generate include the
following:
S/N Detail
1. Transaction of bank statement
2. Cost center Report for Revenue collections
3. Revenue & Expenditure Statement report
4. Report for Student Biographical Information
Failure by the ITS to generate certain reports implies that the system is not being
used by the University Management to make important decisions.
600
Management acknowledged the challenge but indicated that the Ministry of
Education and Sports (MoES) and MoFPED were planning to implement the
CEMAS, an IT platform for all Public Universities. I wait the outcome of
Government intervention in this regard.
o) Land Ownership
Review of documents of ownership of land belonging to the University revealed
the University owns various pieces of land in different locations with unspecified
acreage. While some of it is registered in the name of Makerere University Council,
other pieces of land are not. It was noted that in most cases there was delayed
renewal of lease agreements and land encroachment on University land by various
individuals claiming ownership of the land. Without evidence of ownership, it was
difficult to confirm that the land actually belongs to the University. There is a risk
of the University losing the land if not transferred into its name or having the
expired leases renewed. The table below refers;
Location Plot No. Acres Audit comment
Action taken
Kasangati 2.97 No lease agreement
The land is clearly fenced off and there is no illegal settlement. Boundaries have been opened and the process of obtaining the
lease title on-going.
Katalemwa F-N, BC, CD-CZ,DE-DL
43 No title Katalemwa covers total acreage of 82 and the University has 31 acres of land titled.
The boundary opening for this land was done
A formal land search at the Ministry of Lands, Housing and Urban Development was done.
Investigation of encroachment was being handled by the Police Land Protection Unit.
Makerere North
77, 88,103-119, 156-159,350,364
20 No title Boundary mark stone pillars were installed and a land search commenced for these plots before
further action could be taken.
Buyana 350 No title An instruction was issued to Surveyors on a frame work contract to process the title and work wason-going.
Lira Municipality
7-9 1.49 Expired lease The process of renewing the lease title was in the final stages, all necessary fees were paid and alease agreement signed and forwarded to the External
601
Location Plot No. Acres Audit comment
Action taken
Lawyers for final execution.
Katanga 1-47 31.73 Alterations made on the land title.
The land ownership dispute in Court and awaiting final ruling on this case.
Makerere North
239 1.08 Title is under the names of Amos KaluleSempa
The transfer forms for this land were obtained and a search issued to the land office to ascertain ownership before further action could be taken.
Makindye 14, 45, 57 14 Land encroachers
A court injunction was issued against the encroachers for trespass on the land and the matter was in court.
A caveat had been registered on
the land and the court hearing was due in February 2015.
Management explained that in order to address the land issues which were
inherited from past years, the University had engaged a surveyor to handle
cadastral issues and a law firm for legal issues, both on framework contract basis.
I await the outcome of Management‟s actions on the matter.
p) Lack of Staff Performance Plans
Staff performance appraisal is part of the performance management system that is
used as a management tool for establishing the extent to which set targets within
the overall goals of the organization have been achieved. It also helps identify
performance gaps and development of training needs of individual employees.
However, a review of the staff personal files revealed that they lacked annual
performance plans which would have been the basis for appraisal at the end of
the appraisal period. I explained to Management that there is a risk that staff
performance was not being properly planned, monitored and measured through a
staff performance management and appraisal system. This can lead to non-
performing staff being rewarded at the expense of those who are performing.
Management explained that the University was reviewing its Human Resource
Manual, and among the areas under review was performance management.
602
I advised the Accounting Officer, together with the Human Resource Department
to ensure that the University has a proper mechanism for staff performance
management and appraisal.
q) Operations of Makerere University Guest House
a) NSSF Remittances
Section 11(i) of the NSSF Act, Cap 222 of the Laws of Uganda, 2000requires every
contributing employer to pay to the fund, within 15 days next following the last
day of the month for which the relevant wages were paid, a standard contribution
of 15% calculated on the total wages paid during that month to that employee.
It was noted that whereas the Guest House was deducting NSSF contributions at a
rate of 5% from staff, there was no evidence to show that deductions amounting
to UGX.49,789,874 were remitted to NSSF together with the 10% employers‟
contribution.
Besides, most of the employees lacked NSSF Numbers and no effort had been
made by Management to have this matter addressed. Failure to remit NSSF
contributions exposes the Guest House and the University as a whole to penalties
and fines by the Fund.
Whereas Management indicated in their response that all arrears had been
subsequently cleared, I was not availed with evidence to this effect.
I advised Management to have all employees registered with NSSF and their
contributions (arrears and future) remitted to avoid penalties by the Fund.
b) Unremitted PAYE
Section 123 (1) of the Income Tax Act requires a withholding agent to pay to the
Commissioner any tax that has been withheld or that should have been withheld
within fifteen days after the end of the month in which the payment subject to
withholding tax was made by the agent.
603
However, it was noted that UGX.43,131,990 in respect of PAYE deductions from
staff salaries was not remitted to the tax body. This omission attracts penalties in
form of interest which the Guest House may have to pay.
Whereas Management indicated in their response that all arrears had been
subsequently cleared, I was not availed with evidence to this effect.
I advised the Accounting Officer to have all the money that was deducted from
employees as PAYE remitted to URA and also to ensure that all future deductions
are remitted in the stipulated statutory period to avoid possible penalties.
c) Failure to Disclose VAT
The Value Added Tax (VAT) Act, Cap 349 of the Laws of Uganda, 2000 requires
that all persons registered for VAT levy it on all transactions which are vatable and
that a VAT return is filed every month.
However, it was noted that Management of the Guest House did not furnish its
VAT returns to URA and yet the issued invoices were inclusive of VAT.
The Guest House Management‟s failure to declare VAT charged on supplies could
lead to penalties by the tax authority.
I advised the Accounting Officer to ensure that the Guest House Management
submits the required returns to URA.
r) Outstanding Debtors
It was noted that despite the fact that the Guest house is struggling to remain a
going concern, it had accumulated debtors to the tune of UGX.227,802,294 as at
30th June, 2014.
A review of the list of debtors revealed that the University departments were
among the biggest debtors for the services provided by the Guest House, to the
tune of UGX.133,042,055.
604
Whereas Management indicated that the debts had since been cleared, I was not
availed with evidence to this effect.
I advised the University Accounting Officer to ensure that the debts owed by the
various departments are settled to enable the Guest House settle its own
obligations.
s) Profit and Loss Account of the University Bakery
It was noted that the bakery has been making losses for the last two consecutive
financial years. The prior year loss was UGX.24,003,919, while a loss of
UGX.36,633,600 was incurred in the year ended 30th June, 2014. I explained to
the Accounting Officer that those are indications of the bakery becoming a non-
going concern.
Management attributed the huge losses to increasedcosts of production for the
Bakery and the fixed price of selling bread to the Halls. They further indicated that
the Bakery had been taken over by Makerere University Holdings Company which
is expected to turn it into a viable commercial unit. I await the outcome of
Management‟s intervention in this regard.
t) ECONOMIC POLICY RESEARCH CENTRE -MUK
a) Unacknowledged receipt of funds
A sum of UGX 62,020,000 was paid to enumerators to undertake research during
the year under review. However, it was noted that receipt of the funds was not
acknowledged by the beneficiaries. This practice leads to gaps in the
accountability process of the money involved which can result into
misappropriation of the funds.
Management explained that the funds were paid to 84 enumerators through their
Bank accounts whose details were provided and confirmed by the beneficiaries.
The payments to bank are always followed with notification to pay and these
payments are clearly indicated on the Bank statement.
605
I have advised management to ensure that payees acknowledge receipt of funds
received.
b) Adjustments made through journal vouchers
Best practice requires that any adjustments made in the accounts be supported by
properly authorized adjustment vouchers. It was noted that three journal entries
totaling to UGX.16,749,605 passed in the accounting system to correct book
keeping errors were not approved by management. There is a risk of intentional
misrepresentation of transactions on account balances going undetected.
Management acknowledged the anomaly and undertook to take action in future. I
await management‟s commitment in this regard.
u) NORWEGIAN PROGRAMME FOR CAPACITY DEVELOPMENT IN HIGHER
EDUCATION AND RESEARCH FOR DEVELOPMENT (NORHED) FUNDED
PROJECTS - MUK
a) Delayed Project implementation
It was observed that the implementation of projects was delayed especially the
signing of partnership contracts for collaboration to enhance capacity building
programs at the Universities. Consequently, a balance of USD.1,240,793
remained unutilized for the 7 month period ended 30th June 2014. The delay in
project implementation may affect the enrolment of new students under the
program in Higher Education Institutions.
In their response, management acknowledged the state of affairs which it
attributed to the following factors:-
delayed disbursement of funds by the donor
Inadequate descriptive financial information of the first disbursements which
did not synchronize with project details hence delaying access to the funds.
Some programme partners had not opened their respective accounts, making
it difficult for Makerere University to disburse institutional funds on individual
accounts.
606
NORHED was a unique programme involving not only many programmes, but
many distant partners, with different financial management systems, therefore
there was initial problem to study these systems and harmonize the different
procedures.
South Sudan became politically insecure making it insecure for staff to conduct
business with the Universities there.
A bigger proportion of the balances held on the A/C is for Tuition and Stipends
of the Ph.D. and Masters Students whose process of identification took longer
than anticipated especially from the partner institutions of University of Juba,
South Sudan and University of Agder, Ethiopia.
Delays in the procurement processes for items such as Computers and other
specialized scientific equipment.
Management undertook to provide the necessary support to all projects with
implementation of programme activities with a view to harmonizing and increasing
efficiency in budget performance. I await management‟s commitment in this
regard.
b) Funds not properly accounted for
i) Incompletely Vouched Expenditure
A sum of USD 12,247 was expended in respect of various project activities.
However, it was noted that the payment vouchers lacked appropriate supporting
documents like receipts, air ticket bookings, transfer slips, and schedule of
beneficiaries. Delayed accountability may lead to falsification of documents.
Management explained that at the time of Audit, some receipts and other
accountabilities were separately filed. In addition, the doctoral students to whom
funds had been advanced to procure laptops were still in Oslo, Norway. However,
management undertook to provide the accountability documents as soon as they
are available.
I have advised management to always ensure that payment vouchers are
supported with the necessary accountability documents.
607
v) MAKERERE UNIVERSITY: ADAPTATION OF SMALL SCALE BIOGAS
DIGESTERS FOR USE IN RURAL HOUSEHOLDS IN SUB SAHARAN AFRICA
PROJECT FOR THE 16 MONTHS PERIOD ENDED 31ST MARCH 2014
a) Compliance With Financing Agreement Provisions and
Government of Uganda Financial Regulations
It was noted that management had in all material respects complied with the
financing agreement provisions and Government of Uganda financial regulations
except for the following matters:
i. Funds not accounted for
A sum of Euros 137,326.624 advanced to 9 partners to carry out project activities
lacked relevant supporting documents contrary to Articles 2.1, 16.2 & 16.3 (Annex
II) of the Grant Contract. Unsupported expenditure may result into misuse of the
project funds thereby hindering implementation of the project.
Management explained that the funds disbursed to all partners were based on the
submitted funding requests and bank information that served as supporting
documents. Management undertook to ensure that other supporting documents
are obtained and kept by the Lead Applicant.
I have advised management to ensure that in future, all partners submit periodic
accountability returns in respect of the funds disbursed to them.
ii. Irregular Expenditure
Comparison of the approved budget and the actual expenditure for the financial
year under review revealed that the expenditure exceeded the budget on a
number of items by a total of Euros 10,758.54 without the relevant authority.
Activities whose funds were encroached upon may not be fully implemented.
Management acknowledged the anomaly which they attributed to posting of
figures to wrong budget lines. However, management undertook to ensure that
partner institutions correctly post report figures in the appropriate budget lines.
I await management‟s action in this regard.
608
iii. Unauthenticated Bank Documents from Partners
During the first year of payment, it was noted that most of the bank statements
submitted by partners apart from Cameroon were not authenticated by their
respective bankers thereby rendering them doubtful.
Management in response acknowledged the anomaly and undertook to
communicate the same to all partner institutions.
b) General Standards of Accounting and Internal Control
It was noted that management‟s control structure environment, accounting system
and policies and control procedures were generally adequate to ensure prudent
use of, and accountability for all project expenditure except in the following
instances:
i. Unabsorbed Funds
During the year under review, a sum of Euros 61,311.06 was disbursed to several
Project Partners to undertake various activities. However, the funds remained
unutilized by end of the period under review. There is a risk of delayed completion
of project activities and/or diversion of funds which may result in funding
sanctions.
Management attributed the state of affairs to low burn rates for some partners
due to a delay in project start time yet some partners‟ activities depended on
others‟ output. I have advised management to ensure that all funds are absorbed
in accordance with the workplan.
c) Status of Project Implementation
During the year under review a total of Euros 258,161.37 was disbursed to various
African Union Commission Project partners implementing the project. Field
inspections were carried out in a selected number of beneficiary homes in Uganda
in the Districts of; Luwero, Kiboga, Mpigi and Buikwe among others to review the
status of project implementation and the following anomaly was noted:
i. Project Monitoring Costs
609
A review of the project documents revealed that no provision was made for the
principal investigator or an independent person to undertake monitoring and
inspections of project implementation. Without proper monitoring and inspection,
there is a risk that any deviation may not be detected and corrected in a timely
manner.
Management explained that this matter was communicated to African Union
Commission to permit budget re- allocation to include monitoring costs. I await
the outcome of management‟s action in this regard.
46.1 SUPPORT TO RESEARCH ACTIVITIES AT MAKERERE UNIVERSITY
FUNDED BY THE SWEDISH INTERNATIONAL DEVELOPMENT
COOPERATION AGENCY (SIDA)
I. COMPLIANCE WITH FINANCING AGREEMENT PROVISIONS AND
GoU FINANCIAL REGULATIONS
It was noted that the Project complied in all material respects with the Financing
Agreement provisions and Government of Uganda Regulations except for the
following matter:
I.1 Unauthorized over expenditures
A number of budget lines were overspent to the tune of UGX.2,483,197,182 (Refer
to table below) without the necessary approval in the form of
virement/reallocation warrants. In the circumstances, the expenditures are
deemed ineligible.
Management attributed the anomaly non revision of budget allocations since 2010
and consequently, allowing researchers to continue with their activities without
sufficient funding on the items so long as the central account still had funds.
610
Expenditure Item Budget
(Ugx)
Actual
(Ugx)
Over
(Ugx)
Travel abroad 876,643,694 1,226,395,691 349,751,997
Machinery &
Equipment
477,274,593 589,605,277 112,330,684
Scholarships-
fieldwork
1,094,481,724 1,644,799,380 550,317,656
Scholarships-
unforeseen
31,570,754 152,785,205 121,214,451
Scholarships-
subsistence
2,011,125,531 3,360,707,925 1,349,582,394
Total 4,491,096,296 6,974,293,478 2,483,197,182
I have advised the project management to always revise their budgets in
accordance with the level of activities to be undertaken.
I.2 Irregular procurement of goods
It was noted that procurement of goods worth USD.56,106(UGX.147,839,310) for
E-Resources from M/S International Network for the Availability of Scientific
Publications(INAP) was not approved by the Solicitor General as required by the
PPDA Act 2003. In the circumstances there is a risk of being party to unfavourable
contractual obligations.
611
Management in response indicated that the transfer of USD 56,106 was a
subscription fee for E-resource, a research site negotiated between the University
and the supplier through an agreement which is reviewed every three years.
I have advised management to always seek approval of the Solicitor General for all
procurements in excess of UGX.50 million as required under the PPDA Act.
II. GENERAL STANDARDS OF ACCOUNTING AND INTERNAL CONTROL
II.1 Project funds not accounted for
A sum of UGX.567,731,120 that was spent on various project activities during the
financial year lacked appropriate supporting accountability documentscontrary to
the Project operational guidelines. In the absence of such documentation, I could
not ascertain the correctness of the expenditure.
Management attributed the delayed accountabilities to circumstances beyond the
control of some researchers such as conditions that had to be fulfilled before they
could proceed with other funded activities on a given research. I have advised
management to always ensure that project funds are promptly and properly
accounted for.
II.2 Inappropriate application of Exchange Rates
The application of exchange rates during the year under review was inconsistent
with generally accepted accounting practice. The project used exchange rates at
the dates when remittances were received from the SIDA and such rates would
remain operational until the subsequent remittance. In the circumstances, there is
a risk of misrepresentation of the operating results of the project as they may not
have been translated into the functional currency (UGX) at the correct rates.
Management in response explained that it was viable to use set rates at given
periods to avoid frequent fluctuations which worsen at the time of the
transaction.I have advised management to ensure that rates applicable on the
date of transactions are used.
II.3 Mischarge of expenditure
Procurement of computers worth USD.13,100(UGX.34,518,500) from a local firm
was wrongly classified under Scholarships subsistence budget line thereby
distorting the operating results of the Project.
612
Management explained that the equipment was charged on scholarship because
all moneys received on exchange gains and interest earned is accumulated under
scholarships as it is received unexpectedly. However I have advised the project
management to always budgetand spend such windfall gains in accordance with
the existing budget provisions.
III. STATUS OF PRIOR YEAR AUDIT RECOMMENDATIONS
I reviewed the implementation of the previous year audit recommendations and
the following table summarises the status of those still outstanding.
Observation Status
Inadequate management of fixed assets
(incompletefixed assets register, some assets
not engraved and lack of a maintenance
schedule for assets like heavy duty Photocopier
and Lab testing Machines which have
manufacturers‟ recommendation of usage and
service)
Partially addressed
I have advised management to address all the audit issues and recommendations
made in the previous reports as they are intended to enhance efficiency of
operations, accuracy of financial reporting and compliance with the applicable
legislation
47.0 MAKERERE UNIVERSITY BUSINESS SCHOOL
a) Outstanding Payables
Section 1.1.5 of the School Accounting Manual 2012 requires settlement of
outstanding dues within 30 days from the date of receipt of invoice. However, a
review of payables revealed that a balance of UGX.5,081,938,136 remained
outstanding at the close of the year under review. By the time of writing this
report, a total of UGX.3,562,439,292 had been settled leaving a balance of
UGX.1,519,498,844 unsettled. This is contrary to the commitment control system
613
which prohibits entities from entering into commitments unless funds are
available.
Management explained that the School largely depends on NTR which is normally
received between mid-May and June when students are to sit their final exams. I
have advised management to comply with the commitment control system.
b) Unauthorised Excess Expenditure
Section 2.5.1 of the MUBS Finance and Accounting Manual 2012 requires
management to effect re-allocations between expenditure line items, within the
same vote, only after approval by the Secretary to Treasury in accordance with the
Public Finance and Accounting Regulations, 2003.
During the year under review, the School sought for a virement /reallocation of
funds amounting to UGX.3,592,572,343 to enable the School cater for additional
staff recruitment and the need to enhance the welfare of science staff. It was
noted that although the request was granted by the PS/ST, the school still
incurred UGX.1,936,187,681 over and above the approved estimates on various
expenditure line items without the necessary approval. Incurring expenditure
without the requisite approval of any amendments to the budget was irregular.
Management in response attributed the anomaly to some challenges faced with
respect to four items namely employee costs, professional services, travel and
transport, and maintenance of grounds and buildings.
I have advised management to always follow the prescribed procedures prior to
incurring excess expenditure.
c) Unapproved ICT Policy
Section 40(2)(b) of the Universities and Other Tertiary Institutions Act, 2001
outlines the formulation of the general policy of the Public University (School) as
one of the responsibilities of the University Council.
614
The purpose of an Information and Communications Technology (ICT) Policy is to
streamline the management of an Organization‟s ICT activities with regard to
acquisition, utilization, development and sustainability. However, it was noted that
the Draft ICT Policy was never approved by the School Governing Council although
management had been using it since 2010. The lack of Council‟s approval makes it
difficult to enforce the provisions in the Policy.
Management explained that the draft policy was being reviewed and expected to
be submitted to Council for approval by the end of financial year 2014/2015.
I await management‟s action in this regard.
d) Student Records
Section 9.4.4 (f) of the School‟s Human Resource Manual 2009 states that it is the
responsibility of the School Registrar to liaise with the School Bursar to maintain
and update the students‟ database including registration and examination records.
On the contrary, management did not maintain a comprehensive record of
students during the year under review. The records lacked vital information such
as nationality and sponsorship (Private or Government). In the circumstances,
proper management of student affairs is rendered difficult. Additionally, there is a
risk of misstating the revenue collected from privately sponsored students.
Management explained that the School maintained a comprehensive record in the
form of a nominal role. I have advised the Accounting Officer to ensure that a
student database is maintained as required under the Manual.
e) Transfer of Staff Loan Recoveries
The School operates a loan account with Bank of Africa- Jinja road, Kampala out of
which low-interest loans are extended to staff and recoveries deposited back on
the same account. During the year under review, a total of UGX.1,179,009,120
was recovered from staff loans. However, it was noted that recoveries for the
months of May and June 2014 amounting to UGX.222,832,405 had not been
deposited on the designated loan account. I explained to management that this
negatively impacts on the would-be interest income accruing from the loans.
615
Management explained that the delay to deposit the money on the loans account
was caused by challenges in cash inflows.
I have advised management to ensure timely transfer of loan recoveries to the
designated account to enable other staff also benefit from the loan scheme.
f) Contract not cleared by the Solicitor General
Regulation 225 (2) (f) of PPDA Regulations, 2003 stipulates that a contract
document, purchase order, letter of bid acceptance or other communication in any
form conveying acceptance of a bid that binds a procuring and disposing entity to
a contract with the provider, shall not be issued prior to approval by all relevant
agencies, including the Attorney General.
Management hired office space at MTAC at a contract sum of UGX.152,707,104
without approval of the contract by Solicitor General which was attributed to
inadequate Government valuer‟s report:
Failure to have the contract cleared by the Solicitor General exposes the School to
a risk of financial loss in the event that there are disagreements with MTAC.
I have advised management to get clearance from the Solicitor General‟s Office
and heed the legal advice provided.
Management explained that although the contract had delayed to be cleared by
the Solicitor General, they relied on the relationship already established with MTAC
supported by an earlier contract cleared by the Solicitor General. They further
explained that any further delays to pay would have resulted into MTAC
terminating the relationship.
48.0 UGANDA MANAGEMENT INSTITUTE
a) Accumulation of Payables
Payables increased from UGX.2,630,011,183 to UGX.6,831,472,117 representing
160% increment from the previous financial year. Accumulation of payables
exposes the Institute to a risk of litigations and the attendant costs.
616
Besides, there was no payables management policy to enable the Institute monitor
and pay its creditors.
Management acknowledged the lack of payables management policy and
undertook to take measures to reduce the risk exposure.
A Payables Management Policy should also be instituted to enable timely
settlement of obligations.
b) Receivables
The Institute Debt Management policy requires all trade debtors to be allowed a
grace period of 30 days from the date of the invoice. It was noted however that
receivables increased from UGX.5,607,228,689 to UGX.7,642,135,737 representing
an increase of 36.29%. Included in these receivables is „other accounts receivable‟
comprising mainly student debtors of UGX.7,332,342,516 of which
UGX.3,577,080,183 relates to the period 2010-2012 and UGX.818,900,355 to
earlier periods.
I informed management that an inadequate cash position undermines settlement
of liabilities as they fall due. The accumulation of the receivables is attributed to
laxity of management in enforcing the debt management policy of the Institute.
The analysis below refers;
Analysis of Debtors
Bal b/f F/Y 2010/11 F/Y 2011/12 F/Y 2012/13 F/Y 2013/14 TOTAL
818,920,355.79 1,048,794,675.36 734,006,846.04 1,793,630,660.93 3,246,783,199.52 7,642,135,737.64
Management undertook to enforce the debt collection policy more consistently. I
have advised the Accounting Officer to consistently enforce the debt management
policy, so as to improve the cash position and subsequently settle the Institute‟s
payables.
c) Delayed contract Execution
617
The Institute engaged an international construction firm in March 2012 to
construct a new Classroom and Office Block, at a contract sum of UGX.
21,324,058,054. The completion date of the works was September 2013. However
by the time of the audit, in February 2014, the works had stalled at structural
level. It was also noted that the performance security had expired. Without
renewal of the performance security, there is a risk of financial loss in the event of
failure to execute the contract to its completion.
Management attributed the delayed execution of works to cash flow challenges
and indicated that the construction would be completed using funds from AfDB
under the HEST project. I advised the Accounting Officer to ensure that adequate
funds are provided to complete the works. The performance Security should also
be renewed.
d) Rehabilitation of the Hostel
A local construction firm was awarded a contract for rehabilitation of a hostel at
UGX.2,543,323,798 (including a variation of UGX.163,931,252). By the time of the
audit, UGX.1,589,061,770 had been paid representing 67% of the value of work
done. Whereas the completion date was October 2013, inspections carried out in
November 2014 revealed that the works were incomplete and had since stalled.
Delay to execute the rehabilitation works to completion may lead to escalation of
c
o
s
t
s
Left: Three completed blocks Right: Three hostel blocks which stalled
Management explained that the works stalled because of cash flow challenges and
that construction would resume when funds are collected from the debtors.
I advised the Accounting Officer to enforce debt collection strategies and finalize
the construction as envisaged.
618
e) Understaffing at the Institute
The Uganda Management Institute has an approved establishment structure of
219 posts, out of which only 182 (83%) were filled leaving 37 vacancies. The most
affected departments were the Quality Assurance, Procurement, Planning, M&E,
Projects and Monitoring, SDL and IT, Research center, which lacked Heads of
Department and staff.
Failure to fill all approved posts impacts negatively on the effective delivery of
services by the Institute. Management undertook to fill the vacant positions in
phases and in accordance with the existing recruitment Plan.
I await the outcome of management undertaking.
49.0 MBARARA UNIVERSITY OF SCIENCE AND TECHNOLOGY
a) Unauthorized Excess Expenditure
The University incurred excess expenditure of UGX.680,036,286 over and above
the appropriated amount on Research, Consultancy, Publication and
Administration and support services without relevant authority.
Management attributed the anomaly to excess revenue collections and inability to
obtain authority to spend during the year under review. In the circumstances, the
intentions of the appropriating authority are undermined.
I have advised management to always seek the necessary approval prior to
incurring expenditure in excess of the approved amounts.
b) Outstanding Commitments
The University reported in its financial statements payables UGX.5,404,564,479 as
at 30th June 2014. Included in the reported balance is UGX 4,442,293,176 in
respect of salary arrears due to non-teaching staff, out of which UGX
4,185,159,868 had been settled by the time of audit. Also noted was that the
payables included NSSF arrears of UGX.245,306,319 and a long-outstanding
obligation of UGX.420,000,000 due to the former owners of the University Inn.
619
I explained to management that accumulation of domestic arrears contravenes the
Government Policy on commitment control and may attract litigation from long
outstanding creditors. The NSSF obligation could attract fines and penalties as
well.
Management explained that requests had been made to MoFPED to provide funds
to settle the obligation. I have advised management to ensure that the
outstanding obligations are settled to avoid possible litigations and their attendant
costs.
c) Management of Receivables
Management reported a receivables balance of UGX.698,323,077 in the statement
of financial position as at 30th June 2014. A sum of UGX.478,105,350 had been
collected by the time of audit, thereby leaving a balance of UGX.220,217,727. A
review of the supporting schedule revealed that the debts were owed by sponsors
of private students. Also noted was that some students sat exams without settling
tuition fees contrary to the existing University policy. This is an indication of laxity
on the part of the University administration to enforce debt collection policy.
Accumulation of receivables hinders availability of funds for University operations.
Management explained that the University had introduced mechanisms for
tracking defaulters which was expected to mitigate the problem. I await the
outcome of management‟s intervention in this regard.
d) Budget Performance
The University received a total of UGX.22,656,019,762 during the year under
review, against an annual appropriated budget of UGX.21,817,082,000
representing a percentage performance of 103.8%. However, it was noted that
whereas the University realized revenue over and above the bulk of the
appropriated funds during the year, some key planned activities were not
implemented as detailed in the table below:
620
KEY OUTPUT PLANNED OUTPUT ACTUAL VARIANCE
Research Consultancy and
Publication
Conduct 35 Research studies, make 16
Publications, Hold 4 public lectures 8
Research workshops and 1 research
Dissemination
Conference
Conducted 28 research studies,
made 7 publications, held 3 public
lectures,11 research workshops and 1
research
dissemination conference
7 Research studies not held,9 Publications not
made,1 public lecture not held
Purchase of
Office and ICT Equipment
including software
Networking of 1 level
of science block,40 desk top computers
for laboratories,2 wireless outdoor
points, Network equipment, website
camera
Procured 40 Desktop
computers for laboratories,1CISCO
Switch for ICS, Wall network cabinet for
FoM, completed networking of 4TH
floor science block
The procurement
process for network fiber switches,
bandwidth optimization tool and
server was at evaluation stage.
Failure to implement planned activities undermines the University objectives.
Management attributed the state of affairs to the long procurement process that
was still in progress by the end of the year under review. I have advised the
accounting officer to always ensure that procurement processes are properly
planned and undertaken early enough to enable management implement planned
activities.
e) Investment in Shares
During the audit, it was noted that management invested in bank of Baroda with
5000 shares equivalent to UGX.3,000,000 in 2002. However, contrary to Treasury
Accounting Instructions, the following anomalies were noted:
The University did not have an investment policy in place.
There was no due diligence report showing the viability of the investment.
There was no revaluation carried out at the end of the financial year since
2002, this leaves the investment presented at the nominal value in the
financial statements hence misrepresenting the value of the investment to
date.
Management does not maintain any investment ledgers that are meant to
indicate the nominal amount of investment, income received, actual cash paid
representing the capital invested and duration of the investment.
621
In the absence of the above, I could not confirm the justification of the
investment.
Management in response explained that the shares were bought as one of the
initiatives of income generation for the University. I have advised management to
formulate policy guidelines on investment proposals.
f) Incomplete Fixed Assets Register
It was noted that the University did not maintain an updated fixed assets register.
I explained to the management that failure to maintain the register renders the
monitoring and tracking of the University assets difficult.
Management in response attributed the anomaly to posting of values, to a number
of assets. However, an adhoc Valuation Committee had been established to come
up with asset values whose work is yet to be completed. I await the outcome of
management action in this regard.
g) Outstanding Advances
A sum of UGX.17,407,000 advanced to various staff for official activities remained
outstanding contrary to paragraph 217 of the Treasury Accounting Instructions
2003, which requires accountabilities to be submitted within 60 days from the date
of payment. Delayed accountability may result into falsification of accountability
documents.
Management explained that the concerned staff had been advised to submit the
accountabilities for verification. I have advised management to ensure that
advances are accounted for or else recovered.
622
50.0 KYAMBOGO UNIVERSITY
a) FINANCIAL STATEMENTS
i. Misstatements in the Financial Statements
A review of the financial statements presented for audit revealed the following
misstatements;
The statement of financial performance reflects total expenditure of
UGX.66,995,757,620 which excludes accrued expenditure of
UGX.4,619,832,348, as shown in the statement of outstanding commitments
as at 30th June 2014.
Whereas the Appropriation Statements reflect total expenditure of
UGX.66,995,757,620, the statement of Expenditure reconciliation reflects total
expenditure per appropriation account as UGX.64,528,959,341, leading to an
unexplained variance of UGX.2,466,798,279.
The receivables figure of UGX.4,983,181,359 includes a total of
UGX.4,716,181,435 related to outstanding students‟ fees. However this figure
is not supported and analysed by management to indicate the details of the
debtors such as students‟ name, programme/year of study and the respective
faculties where such amount is due. Besides the bulk of this amount (i.e.
UGX.3,343,584,532) is not allocated to any specific faculty, but is shown as
due from „Revenue collection stanbic‟ with no proper justification.
The above errors imply that the financial statements are misstated. Although the
Accounting Officer committed to having them corrected, this had not been done
by the time of concluding this report in March 2015.
ii. Lack of budget provisions for domestic arrears - UGX.959,827,755
A total of UGX.959,827,755 was paid to suppliers in respect of unpaid invoices
relating to previous years. However, a review of the University records revealed
that although the University budgeted for settlement of domestic arrears, these
particular arrears had not been reflected in the financial statements for the
preceding year and accordingly, had not been budgeted for in the year under
623
review. Under the circumstances, I could not confirm whether the arrears and the
corresponding payments were genuine transactions. Payments for unbudgeted
expenses, tantamount to unauthorized expenditure and also leads to diversion of
funds meant for other planned activities.
The Accounting Officer explained that the University paid the above amount of
domestic arrears without adequate budget provision in the FY 2013/14, but also
indicated that going forward, the University shall endeavor to minimize arrears,
and when they occur, will be adequately budgeted for in the subsequent financial
year.
I have advised the Accounting Officer to always ensure that only budgeted for
expenditures are incurred by the University, or else use the options available
under the Budget Act, 2001, to request for a supplementary estimate to cater for
such unplanned expenditures.
iii. Failure to adhere to the Commitment Control System
Contrary to the commitment control system which requires Accounting Officers to
commit the entity to the extent of funds availability, a review of the statement of
financial position revealed that the entity has continued to incur domestic arrears.
It was noted that the University payables increased by 49% from
UGX.2,549,415,022 as at 30th June 2013 to UGX.4,983,181,359 as at 30th June
2014. Failure to adhere to the commitment control system leads to delays in
settlement of supplier invoices, which can lead to loss of goodwill as well as
imposition of interest charges on outstanding amounts.
In his response, the Accounting Officer explained that the increment in the
payables figure was mainly due to the salary arrears arising from the failure by the
Ministry of Finance, Planning and Economic Development (MOFPED) to remit on
time UGX.2,860,377,118 for staff salaries and gratuity for the month of June,
2014.
I advised the Accounting Officer to always adhere to the regulations and ensure
that commitments are only allowed to the extent of the available funds.
624
iv. Management of Receivables
The University reported receivables and prepayments of UGX.1,695,217,227 by
the close of the year. Of this amount, UGX.1,428,217,303 relates to student‟s fees
while UGX.266,999,924 relates to other debtors. The University has a policy which
requires full settlement of fees before students are allowed to sit for exams. Strict
implementation of the policy would mean that no debtors would arise from unpaid
fees. The presence of significant balances of unpaid fees is an indication of laxity
on the part of management to implement the University policy. This increases the
risk of non-payment of fees by students, thus denying the University the much
required funding.
In his response the Accounting Officer explained that the fees arrears related to
State House. Statehouse requested the University to allow the sponsored students
to sit their examination before paying fees pledging to pay later. It was further
noted during scrutiny of correspondences between State House and the University
on the matter, that State House owed the University UGX.1,298,349,081 and by
30th January, 2015, it had paid a sum of UGX.1,251,270,988 leaving a balance of
UGX.47,078,093 outstanding. Considering the above development, receivables
amounting to UGX.129,868,222 relate to other students other than those
sponsored by State House. I advised the Accounting Officer to consider fully
implementing the set policies of the University regarding payment of University
dues.
b) REVENUE
i. Failure to collect Revenue from staff rentals – UGX.180,966,472
For the period under review, the University let out 120 units of its houses to staff
for accommodation at a monthly rental fee agreed upon in the individual contracts
with staff, which was recovered at source from staffs‟ monthly salaries. It was
noted however that the University had outstanding rental dues totaling to
UGX.180,966,472 as at 30th June 2014.
The Accounting Officer explained that the failure to effect rental deductions was
due to a problem of payroll management during the FY 2013/14 when Ministry of
625
Public service was shifting to IPPS. He explained that for the period from July to
September, 2013, deductions were made by MoPS, whereas from October, 2013
to April, 2014 no deductions were made due to the transition process from Legacy
to IPPS. However, although he indicated that the amount has since been
recovered, I was not provided with sufficient documentation to confirm recovery
of the amount involved apart from a schedule indicating indebtedness by staff. I
have advised the Accounting officer to recover the amounts due from staff and
provide proper accountability.
ii. Failure to collect outstanding rental fees from private businesses - UGX.42,457,276
The University hired out spaces to private businesses and the National Council for
Higher Education (NCHE) from which it collects rent. At the close of the year, it
was noted that unpaid rental fees had accumulated to UGX.42,457,276 over the
years. There is no evidence that the University has taken adequate steps to
recover the outstanding rental dues. Further noted was that this amount was not
included in the receivables balance as at 30th June 2014, implying that the
receivables balance was misstated.
The Accounting Officer acknowledged that the University did not fully collect the
rent due, but was making progress towards recovery of the outstanding amounts.
I have advised the Accounting Officer to institute mechanisms to recover all
outstanding rental dues and in future, consider putting in place strong controls to
prevent accumulation of unpaid rental dues. In addition, the amount in question
needs to be reflected in its books of accounts.
iii. Unpaid Hall Fees - UGX.62,560,000
Privately sponsored students housed in the University halls are required to pay
UGX.920,000 per annum (UGX.460,000 per semester) as accommodation fees.
The fee is payable to halls of residence A/c No:9030005812444 in Stanbic
bank, which is the sole recipient of hall accommodation payments.
A comparison of the nominal roll sheets for all privately sponsored students
accommodated in the University‟s halls, with the Halls of residence account bank
626
statement, revealed that 68 students appeared on the nominal sheets but had no
corresponding payments on the halls of residence account bank statement. This
translated into a possible loss of UGX.62,560,000 to the University in uncollected
revenue.
The Accounting Officer explained that many students normally reside in the halls
of residence in one semester and leave in the next at will. He requested to
reconcile the figures and report back. However, by the time of writing this report
(in March 2015), I had not yet received any feedback in regard to this matter.
I have advised the Accounting Officer and the University Bursar to expedite the
reconciliation and ensure that the amounts due are fully recovered from the
students and properly accounted for.
iv. Non collection of rent from businesses operating illegally in the
University
In my special audit report to Parliament of October 2014, I noted that a number of
businesses were operating illegally within the University. By January, 2015 a
number of these businesses had neither been regularized nor discontinued from
operating within the University. In addition, several of these private businesses
were operating without valid contracts and were not paying rent for the spaces
occupied, and for the utilities, such as water and electricity consumed.
The Accounting Officer explained that the University through the Chief
Government Valuer, appointed a technical committee which identified and
assessed all small businesses in the University. A report was prepared and
submitted to the contracts committee to guide the tendering process. The
contracts committee completed the award process and contracts are to be signed
soon. In addition, he appointed an implementation committee which among other
things is to ensure that the recommendations of the technical adhoc committee
are implemented.
I advised the Accounting Officer to expedite the process of contract signing by all
business operating within the University. In the meantime, I await the outcome of
management‟s commitment.
627
v. Banks operating in the University premises without paying rent and/or valid contracts
Kyambogo University has got three banks operating within the University premises
namely; Stanbic Bank, Eco Bank and Crane Bank. The University invited and
contracted Eco Bank and Crane Bank for provision of banking services. Audit
review established the following;
Although the banks modified University premises, I was not availed evidence
of authorization by the University. Besides, it was not clear as to what was the
cost of such modifications, as well as who was to bear the associated costs.
The tenancy agreement with Stanbic bank expired on the 31st September
2007 and has since not been renewed.
The contracts between the University, Eco Bank and Crane Bank did not have
special conditions of service attached and they were open ended with no
contractual period.
There is no record of payment of rent by these banks for the use of University
premises with the exception of Stanbic bank which last paid rent in the FY
2012/2013.
In the absence of valid tenancy agreements and comprehensive contracts, I was
unable to ascertain the actual rent due from Eco Bank and Crane Bank and the
minimum service standards expected by the University.
In his response the Accounting Officer stated that University procured two Banks
(ECO Bank and Crane Bank) to provide the University with banking services
through a procurement process. The cost of renovation was to be met by each of
the said banks. The University recently contracted valuers to value the said
premises for the purpose of contracting and that the report had just been
received. The legal section was drawing up tenancy agreements between the
University and the banks. He further explained that the contracts will address the
issue of special conditions of contract, their comprehensiveness and the recovery
of arrears of rent due to the University from the date of commencement of
operations at the University.
628
I have advised the Accounting Officer to expedite the process of securing
comprehensive contracts and tenancy agreements with the banks and ensure
recovery of arrears of rent.
i. Revenue from the University Farm: Outstanding credit sales to
departments – UGX.15,571,150
The University owns a dairy farm as one of its income generating ventures. By the
time of the audit, the farm had 87 heads of cattle and 27 pigs. The farm generates
revenue from credit sales of milk, mainly to University departments who pay into
the University farm account. An analysis of the records availed revealed that for
the period under review, the farm made total credit sales of UGX.24,029,650 to
various departments. However only UGX.8,458,500 was received from the
departments leaving a balance of UGX.15,571,150 unpaid.
In his response the Accounting Officer indicated that the actual recoveries were
UGX.12,113,700 and not UGX.8,458,500. However, scrutiny of the additional
payments revealed that they were made during the period from July, 2014 to
January, 2015 and there was no evidence to show that they were related to the
amounts in question. Failure to effect the full remittances implies that the farm
may be denied of revenue to implement all its planned activities.
I have advised the Accounting Officer to follow up this matter and ensure that the
departments clear their indebtedness to the University farm.
c) EXPENDITURE
i. Unauthorized Over Expenditure – UGX.5,135,749,119
Contrary to Section 17 of the PFAA, 2003, as well as, the University and other
Tertiary Institutions Act, 2001, an analysis of budget estimates and the actual
expenditure of the University for the financial year under review revealed that the
budget lines on Teaching and Training, Research, consultancy, and outreach
students‟ welfare were overspent by UGX.5,135,749,119. I was not availed any
evidence of authorization by way of approved reallocation or virement warrants,
as is required by the PFAA.
629
Overspending on one budget item suffocates the implementation of other planned
activities. Notable among them was the planned renovation of buildings where
actual expenditure was a meagre 25% of the approved budget. This explains why
many of the University buildings are in a sorry state. Besides, the practice of over
spending on certain budget lines undermines the intentions of the University
Council on specific University objectives.
The Accounting Officer explained that the over expenditure was due to under
budgeting in regard to this important sector of the University. I have advised the
Accounting Officer to always ensure adherence to budgetary discipline and where
circumstances do not permit, to always seek Council approval before incurring
such expenditures.
ii. Mischarge of expenditure – UGX. 978,727,963
The University uses the Government of Uganda Chart of accounts, which defines
the nature of expenditure for each item code. The Chart of accounts is intended to
facilitate better and consistent classification of financial transactions and also track
budget performance per item in line with the approved budget. During budgeting,
funds are tagged to particular activities and outputs using account codes and are
appropriated accordingly.
Contrary to the above, in the financial year under review, it was noted that
Expenditure totaling to UGX.978,727,963 was wrongly charged on budget lines to
fund activities that had not been provided for under those budget lines. This
practice undermines the importance of budgeting process, as well as the
intentions of the appropriating authority to instil budget discipline. The practice
further leads to misleading reporting and affects the credibility of the financial
statement figures, since they do not reflect the true amounts expended on the
respective items. It also undermines the budgeting process and it is a violation of
the principle of proper accountability as stipulated in the TAI and gives avenues
for diversion of funds.
The Accounting Officer explained that items were wrongly classified and they were
to be re-classified in the final accounts. However, I was not provided with
630
evidence of re-classification of the items in question. I advised management to
ensure adherence to approved budget provisions unless proper authority for
reallocation is obtained from Council.
iii. Unexplained deductions - UGX.239,465,087
A review of bank statements, bank reconciliation and cash books of Faculty of Arts
account No:9030005812975 and School of Management account
No:903005705044, revealed that Stanbic bank made deductions unknown to the
University management totaling to UGX.239,465,087 with unclear descriptions
including: ATM cash withdrawals, Fee-Coin Deposit, among others. When
contacted, the University accounts staff explained that the deductions were
unknown to them and that the Accounting Officer had written to the bank seeking
for details and explanations. However, there was no documentary evidence to that
effect and by the end of the audit, the issue had not yet been resolved between
the banks and the University.
I have advised the Accounting Officer to closely follow up these transactions with
the banks and ensure that the amounts irregularly deducted are recovered from
the banks.
Payment of Allowances
The Uganda Public Service Standing Orders, 2010 Section (E-a) defines an
allowance as a payment in cash additional to salary, that is payable to an officer to
facilitate the proper execution of an assignment or duty. The allowance should be
regulated and properly explainable. For the period under review the University
paid a number of allowances to its staff, some of which had no justification and/or
were not provided for in the Terms and Conditions of Service for Members of Staff
of Kyambogo University. The details are discussed in the following paragraphs;
a) Extra Load Allowance - UGX.40,145,000
According to Section 27 (b) of the Terms and Conditions of Service for Members of
Staff of Kyambogo University, the normal working hours for full time staff is
8.00AM to 5.00PM. Section 16 (3) of the same Terms and Conditions states that,
“Extra load allowance” shall be paid to full time staff who are authorized and carry
631
out extra duties in addition to their official normal duties and/or work outside the
normal hours.
For the period under review, the University paid a sum of UGX.40,145,000 to full
time staff as extra load allowance. Scrutiny of the payment vouchers, teaching
timetables and signed attendance sheets revealed that these payments majorly
applied to day assignments for which the staff earned a salary, thus not
warranting the payments. Such payments are irregular as they translate into a
double benefit to such employees since allowances will be paid for hours already
covered by their contractual obligation.
The Accounting Officer explained that the University Council made an exception
for academic staff who teach in excess of the normal teaching load during the
normal working hours. However, I found this explanation not satisfactory, given
that a staff cannot justifiably be expected to have excess load during the normal
working hours.
I advised the Accounting Officer to correct the anomaly and consider recovering
the funds that have been paid out irregularly.
b) Doubtful Payment of Teaching Allowance - UGX.17,957,500
Teaching allowance is paid to Lecturers and Tutorial Assistants for lecturing
students basing on the number of lectures and tutorials undertaken, respectively.
The number of lectures is stipulated in the time table at the beginning of each
semester. The time table provides the basis for payment of teaching allowance.
This is further supported by the Lecturers‟ appointment letters which requires
them to sign an attendance register in the departmental office, which must be
counter signed by the head of department confirming that the lecturer conducted
the lecture.
However, contrary to the above set procedures, the University paid a sum of
UGX.17,957,500 as teaching allowance to Lecturers and Tutorial assistants for
lectures that did not appear on the timetable and were not signed for in the
attendance register and confirmed by the head of department. Under the
632
circumstances, it is likely that the allowances were paid for lectures which were
not conducted. In the absence of proper supporting documentation, I could not
confirm that the expenditure was properly incurred by the University.
Further scrutiny of the payment of lectures‟ teaching allowances, revealed that
lecturers claimed payments using wrong payment rates. Lecturers‟ contracts with
the University stipulates the rates per contract hour of; UGX.45,000 for evening
lectures, UGX.25,000 for day lectures, UGX.20,000 for tutorials, and UGX.55,000
for masters programs. These rates form the basis for the lecturer‟s claims. It was
however noted that some lecturers claimed teaching allowances using evening
program rates yet the lectures were conducted during the day resulting into an
over payment of UGX.43,260,000.
The Accounting Officer promised to look into the matter and recover the amount
from the concerned lecturers. I advised the Accounting Officer to correct the
anomaly and consider recovering the funds that have been paid out irregularly
from the affected staff members.
i. Un-presented Payment Vouchers – UGX.504,161,513
Regulation 60 of the PFAR, 2003 requires all disbursements of public monies to be
properly vouched on payment vouchers prescribed by the Accountant General.
However, contrary to the requirements of the Public Finance Act, 2003 and the
National Audit Act, 2008, payment vouchers and supporting documents for
transactions totaling to UGX.504,161,513 were not presented for audit. In the
absence of the payment vouchers together with their supporting documentation, I
cannot provide assurance as to whether the funds were rightfully expended.
The Accounting Officer explained that most of payment vouchers had been mixed
up in other documents due to big volumes of files and promised to avail them. By
the end of my audit exercise, payment vouchers to the tune of UGX.504,161,513,
were still missing. I advised the Accounting Officer to always ensure that all
expenditure vouchers are properly filed as required by the financial regulations.
633
ii. Advances not accounted for - UGX.66,335,791
Section 217 of the Treasury Accounting Instructions requires accountabilities for
the amount advanced to be submitted within 60 days. However, for the period
under review, a total of UGX.66,335,791 advanced to several staff remained
unaccounted for at the time of concluding the audit. The Accounting Officer
explained that a number of accountability submissions faced filing problems after
being verified by the internal audit department and that any staff who will not
have accounted for the funds advanced will have the money recovered from their
salaries. I await the outcome of this management commitment.
iii. Statutory Deductions
a) Non remittance of taxes to URA - UGX.382,901,835
Section 119 of the Income Tax Act, Cap 340, as amended, requires an agent to
withhold on the gross amount a payment at the rate provided in the third schedule
of the Act and remit it to URA by the 15th day of the next month from which it was
deducted. I noted that PAYE totaling to UGX.382,901,835 was deducted from
lecturers‟ allowances in the Faculty of Sciences and was not remitted to URA. Non
remittance of withholding tax deductions is a violation of the tax law and may lead
to imposition of penalties on the University by URA. Besides, this amount is not
reflected in the University payables. This implies that the payables position is
understated.
I advised the Accounting Officer to always adhere to the requirements under the
Act. In addition, the outstanding amount needs to be recognized in the books of
account.
b) Un-deducted NSSF – UGX.315,232,550
According to Section 11(1) of the NSSF Act, Cap 222 and Solicitor General
Guidance to the University on payment of NSSF, dated 24th April 2013, every
contributing employer shall, for every month during which he/she pays wages to
an eligible employee, pay to the fund, within fifteen days a standard contribution
of 15% calculated on the total wages paid during that month to that employee.
On the contrary, it was noted that the University did not deduct NSSF amounting
to UGX.315,232,550 from a reviewed sample of payments of allowances for part
634
time teaching and course work marking, from the faculty of arts and Sciences.
Non remittance of NSSF deductions is a violation of the law and may lead to
imposition of penalties on the University by NSSF. In addition, it denies employees
of their future benefits.
In his response the Accounting Officer stated that the University sought legal
advice from the Solicitor General in respect of deduction and payment of NSSF on
allowances, with an objective of ensuring that the University pays the correct
NSSF. Subsequently, the University signed a deed of settlement of the NSSF
arrears. The instalment payment of the above arrears as per the deed of
settlement ends in May 2015. However, the above amount has not been included
in the University payables.
I advised the Accounting Officer to always adhere to the NSSF Act and also ensure
that the amounts in question are deducted from the staff concerned and
accordingly remitted to NSSF, without further delay. In addition, the outstanding
amount needs to be reflected in the University‟s books of accounts.
c) Undetailed Procurement work plan
According to PPDA Regulations 70 and 97(a), a combined work plan for the
procuring and disposing entity shall include a detailed breakdown of activities of
works, services or supplies to be procured. It was noted that the consolidated
procurement work plan of the University for the FY 2013/14 was not detailed. The
items planned to be procured were generalized and the plan did not indicate the
specific procurement needs of the various units of the University. The failure to
prepare a detailed procurement plan contravened the PPDA Act, 2003.
The Accounting Officer explained that the Procurement Plan for 2013/14 was not
adequately detailed and pledged to continuously improve and comply with the Act.
I await the outcome of this commitment.
635
d) PROJECT ACCOUNTS
a) Child To Child Project
The University received a total of UGX.96,146,599 for empowering children with
disabilities. It was noted that UGX.95,995,000 was spent under the project with
UGX.45,807,000 withdrawn on the same day (2/07/2013) in three equal
instalments and another UGX.50,188,000 was also withdrawn on the same day
(25/07/2013), again in three instalments for running workshops in various schools.
During a review of the accountabilities submitted, it was found that the
accountabilities appeared doubtful. They contained numerous inconsistencies and
some of the expenditure was found ineligible. There is a risk that these funds may
not have been properly utilised. In the absence of proper accounting records and
accountabilities, I cannot confirm whether the funds were used for the intended
purpose. I have advised the Accounting Officer to institute further investigations
into these transactions with an aim of ruling out possible misuse.
e) HUMAN RESOURCE MANAGEMENT
a) Staffing gaps
A review of the approved University staff establishment revealed that out of the
approved 1,550 posts, only 830 (54 %) were filled leaving 720 (46 %) posts
vacant. A further review of the structure revealed that the category of academic
staff was the most affected. Out of 530 required academic staff, only 270 posts
were filled. This implies that the University does not have the requisite number of
teaching staff, despite the fact that teaching is its core activity. Most affected
positions were those above lecturer position, implying that the university is facing
challenges of supervising academic work at a senior level which impacts negatively
on the university‟s research initiatives. Inadequate staffing undermines the
achievement of strategic objectives and affects the level and quality of service
delivery at the University.
The Accounting Officer explained that he had so far engaged several stakeholders
to address this matter without a positive response yet. I have advised the
University management to continue liaising with the relevant authorities to ensure
636
that this challenge is brought to their attention and addressed with the urgency it
deserves.
f) MANAGEMENT OF ASSETS
i. LAND
a) Failure to record land in the Fixed Assets Register
Regulation 101 of the Public Finance and Accountability Regulations and the
Treasury Accounting Instruction, 2003, Part 11 Public Stores (Paragraphs 804-806)
require maintenance of an assets register for all assets in a form prescribed by the
Accountant General to ensure that the assets are easily identifiable. The Register
should show the asset code, description, and serial number, date of acquisition,
value, condition, and location.
Scrutiny of the University assets register however revealed that, land comprised in
FRV 461 Folio 13 also known as plot M902 situated at Kampala-Kyambogo
measuring 137.51 Hectares and various pieces of land in Kyagwe comprised in
Block 87 plots: 150, 30, 146, 123, 113, and 151 situated at Namasiga-Mukono
were not registered in the Assets register. Absence of a complete fixed asset
register is a critical internal control weakness that exposes the University land to a
risk of loss.
The Accounting Officer explained that this was an omission and that the register
was to be updated accordingly. However, at the time of concluding the audit, the
register had not yet been updated. I have advised the Accounting Officer to
update the fixed asset register to include all university assets.
b) Failure to transfer land titles into the names of Kyambogo
University
Kyambogo University was established by Instrument No.37 of 2003 as a result of a
merger of three institutions; Teachers Education Kyambogo (ITEK), Uganda
polytechnic Kyambogo (UPK) and the National Institute of Special Education
(UNISE). Consequently, the three institutions ceased to exist. It was however
noted that the University land in Namasiga has never been transferred into the
names of Kyambogo University, but was still in the names of a non-existent
637
institution (i.e. Institute of Teachers Education). Failure to transfer University land
into its names exposes the land to a risk of being encroached or even grabbed by
unscrupulous individuals.
The Accounting Officer explained that the process of transferring the Land at
Namasiga into the names of the University had started. I have advised the
Accounting Officer to expedite this action accordingly.
c) Unabated Land Encroachment
Inspection of the University land during audit revealed that encroachment on the
University Land was rampant. The encroachers have constructed permanent
houses, established agricultural farmlands with perennial crops, while others are
engaged in fabrication and selling of charcoal stoves along Mackay road,
Kyambogo Road, Kigobe Road, junior staff quarters and near UNISE. Failure to
evict the encroachers may lead to loss of University land and/or the University
may suffer high costs of compensating the encroachers if not evicted earlier.
The pictures below illustrate the level of encroachment on the University land
along Mackay,Kigobe and Kyambogo roads.
Encroached sections of the University land
In his response the Accounting Officer stated that the land encroachers settled on
Kyambogo many years ago and that it was not easy to remove them without a
due process of the law. However, the University employed land valuers under the
guidance and instructions of the Chief Government Valuer. The valuation process
has just been concluded and the University is to embark on the process of
compensating and removing the said people from the University land.
638
I have advised the Accounting Officer to ensure that all University property and
land in particular is properly safeguarded from illegal encroachment.
d) Un-demarcated University Land
The University fenced off most of its land to protect it from encroachment and
grabbing. However during inspection, it was revealed that along Mackay road, the
land above Kyambogo primary school staff quarters was not fenced as shown in
the photographs below;
Un-demarcated University land along Mackay road
Management stated that they were considering swapping the land in issue with
Buganda Kingdom because of its proximity with the kingdom palace. However,
audit noted that the land was being taken over by encroachers.
I have advised the Accounting Officer to fence off the land and legitimately
expedite the process of the land swap if considered appropriate by the University
Board.
g) STATUS OF HALLS OF RESIDENCE AND INSTITUTIONAL HOUSES
The Universities and Other Tertiary Institutions Act, 2006, requires the University
Council within a period of three months before the end of each financial year, to
submit to the Minister for approval, the income and expenditure estimates of the
Public University for the next ensuing year. These annual estimates should include
639
among others charges for the maintenance of the buildings and other assets of
the University.
It was noted however that for the period under review, the University did not
budget for renovations and repairs of halls of residences and as a result the status
of the halls of residence and houses was appalling. During inspection of Mandela,
Kulubya, Africa, Nanziri and Pearl halls of residences, the following was observed:-
a. Dilapidated East end Kitchen (Mandela Hall)
It was noted that the status of the Kitchen at the East end dining hall was
appalling and needs immediate renovation. It is not safe and hygienic to serve its
purpose as a dinning and Kitchen for the students in its current status as indicated
in the photographs below;
Dilapidated Kitchen at the East end Dinning hall
The Accounting Officer explained that the University has been repairing a number
of its buildings including some of the Halls of Residence. However, due to limited
resources, the renovation process is done in phases. In the financial year under
review, the University renovated West end kitchen, which was in a worse
condition. In the next financial year, maintenance work on the dining, hall, stores
640
and kitchen will be put before the University Council for consideration. In the
meantime, minor maintenance work on the said buildings is being done.
I have advised the Accounting Officer to appropriately prioritize and budget for
renovation of University buildings.
b. Non-functioning CCTV cameras
The University installed CCTV cameras to improve the security at the East end
Kitchen and Mandela Hall. However, it was observed that management has failed
to utilize and operate the CCTV cameras. As a result, the purpose of their
installations was not being served. In his response, the Accounting Officer
explained that the non-functionality was a temporary problem and that the
process of repairing them was ongoing.
I have advised the Accounting Officer to expedite this process and ensure that the
CCTV cameras are functional at all times.
c. Failure to install proper burglar proofing at the East End Dining stores
The burglar proofing at the food stores in the East End dining hall was not
satisfactory to protect the University property from theft. As a result, it was
explained during inspection, that burglary was becoming rampart at these stores.
This was aggravated by the fact that the CCTV cameras installed were not
functional.
The Accounting Officer explained that the University was in the process of making
repairs on these structures. However, due to limited resources the process was
moving on slowly.
d. Broken water pipes and dilapidated Lavatory facilities in Halls of residences
Inspection of the lavatory facilities in Mandela, Kulubya, Nanziri and Pearl halls of
residences revealed that the plumbing system in the bathrooms and lavatories had
broken down and as a result, there was uncontrolled water flow in some of the
bathrooms. The state of hygiene was poor and some of the laundry rooms had
been turned into dumping rooms for unwanted materials as shown in the
photographs below;
641
Dilapidated Lavatory facilities in Mandela, Nanziri and Pearl halls
The Accounting Officer explained that the broken water pipes had been repaired.
The dilapidated lavatory facilities require a big budget and will be renovated
accordingly when a new budget is provided.
I advised the Accounting Officer to ensure that renovation works are prioritized
and budgted for accordingly.
h) MOTOR VEHICLES
Failure to dispose grounded vehicles
Regulation 295 (1) of the PPDA requires an Accounting Officer to carry out regular
annual reviews of assets for purposes of identifying those which are obsolete and
those that should be disposed. Good practice also requires that the assets that are
no longer of economic value to the organization be disposed and the profits or
losses that accrue from such sales subsequently disclosed in the financial
statements. Furthermore, a procuring and disposing entity may use a board of
survey to identify assets to be disposed off, on a periodic basis.
642
During inspection of the University, it was revealed that a number of University
vehicles had been abandoned at; Kyambogo University police station, security
office, UNISE and other parking lots, and had not been boarded off. The vehicles
were in a bad state and were deteriorating in value. Examination of the Assets
register revealed that the vehicles were recorded as those belonging to Kyambogo
University though most of them had Ministry of Education number plates.
There is a risk of further deterioration in the value of the assets if no immediate
action is taken to board off and dispose the vehicles. In his response, the
Accounting Officer stated that the vehicles in bad condition belong to the MoES,
and that he had written to the ministry to obtain authority to either dispose them
off or to have them taken by MoES.
I have advised the Accounting Officer to follow up this matter with MoES until an
amicable solution is obtained. Details in the photographs below;
Pictures showing some of the grounded motor vehicles
Some of the University vehicles not included in the asset register, but grounded and
parked for over 2 years
Kyambogo University vehicles, some with Ministry of Education registration numbers,
grounded and parked for over two years recommended for disposal in the BOS 2013/14, but have not been disposed off by management.
643
i) SPECIAL INVESTIGATION INTO THE AFFAIRS OF KYAMBOGO
UNIVERSITY
I instituted an investigation into the affairs of Kyambogo University in January
2014 following a Parliamentary resolution and a letter from the University
Secretary (Accounting Officer). In addition, I received several allegations from
whistle blowers which included mismanagement of funds, fraud in the collection
and utilization of fees, asset mismanagement and human resource
mismanagement.
The investigation focused on the period from July 2009 to June 2012 and was
conducted with specific terms of reference. However, earlier and later periods
were included in instances where this provided clarity. Below are the highlights of
the key findings;
644
1. Observations on general governance of the University
My investigation revealed that the University Council lacks a charter
governing the activities of the Council and only has guidelines for Council
meetings. This creates uncertainty in so far as the operations of the
University Council are concerned.
I observed that the University lacks salient policies on recruitment and
promotion of staff, research and projects, financial management among
others and only relies on Council decisions that are passed from time to
time.
I observed that the University is currently grossly understaffed. The
University is currently operating under an establishment approved by the
University Council in 2004, which was made at a time during which it had a
population of 8,000 students compared to the current total of over 23,000. I
observed that of the 2,351 positions in the said establishment for both
teaching and non-teaching staff, only 1,102 are filled. This in effect means
that the university is operating at a 47% capacity.
The Academic Registrar was negligent in so far as she failed to detect and
stop the irregular admission of 10,486 students, during the period under
review, who did not apply for admission.
2. General observations on the Human Resource Management
Contrary to the National Social Security Fund Act, the University failed to
remit NSSF contributions for staff totaling to UGX.1,119,515,189 and as a
result, also attracted a penalty of UGX.3,021,399,729.
There was irregular recruitment of support staff and part time lecturers
without being interviewed and being appointed by the Appointments Board.
According to the Public Service Standing Orders, the University Terms and
Conditions of Service of Staff, all academic, administrative and support staff
645
of the University shall be appointed by the Appointments Board on terms
and conditions that may be determined by the University Council.
A total of UGX.653,963,329 was paid as headship allowance yet it is not an
approved allowance. An additional UGX.688,352,000 was also paid to non-
academic staff as extra load allowance without the necessary board
approval.
A total of UGX.48,564,124 was also paid to top management as domestic
allowance despite the fact that this allowance was abolished by Public
Service in 1995 and is also not provided for in the University Terms and
Conditions of Service. A further UGX.81,166,251 was also paid to the top
management in form of salary increment contrary to their employment
contracts.
UGX.373,364,544 was paid to staff after they had reached the retirement
age of 60 according to the Terms and Conditions of Service
I established that several members of staff that were arrested for criminal
offences were never suspended and continued to receive their full salaries,
contrary to the Public Service Standing Orders and the Terms and Conditions
of service.
3. Observations on revenue and expenditure
A total of 10,486 students were admitted by the University without applying
and consequently UGX.532,825,000 was not collected as application fees
during the period under review. This was a loss to the University.
The University has huge debtors as a result of admitting students who are
sponsored by other government agencies. For example a total of
UGX.2,615,298,661 for the academic years 2009/10 to 2013/14 remains
outstanding. I have received written assurances that this particular debt will
be settled.
646
The University lacked cash books and a students‟ ledger which should have
contained a comprehensive list of all students admitted into the university as
well as details of how they have cleared all their fees.
I noted several internal weaknesses in the fees banking process and receipt
issuance by the bursar‟s office. I observed that the entire process was
manual in nature with the use of manual receipt books and in several
instances the amounts recorded in the receipts was more than the amounts
deposited per the bank statement.
I noted a discrepancy in revenue accountability of UGX.8,928,814,082 as
only a total of UGX.71,913,461,494 was recorded as collected compared to
UGX.80,842,275,576 that should have been collected as per the number of
students that sat for examinations.
An analysis of the receipted revenue and bankings for the year 2010/11
revealed an amount of UGX.4,343,299,348 that was receipted by the desk
officers in the various faculties which is not supported by corresponding
bankings onto the University bank accounts.
The University does not have a complete tenancy Register and as such
cannot easily track all the tenants and their respective payments. It also
lacks clear guidelines for determining the amount of rent payable by the
tenants.
In the period between 01st January 2010 and 24th March 2014, the University
spent a total of UGX.3,720,720,373 on fuel. I observed that the university
lacks a policy to regulate the distribution and use of fuel. A total of 295 total-
plus fuel cards had been issued to staff. A total of UGX.83,328,998 was
consumed from fuel stations outside the Kampala area especially on
weekends.
647
4. General observations on Asset Management
There has been laxity and negligence on the part of management in failing
to curtail the massive encroachment and illegal activity on the University
land in Kyambogo by unknown persons.
I also noted several irregularities in so far as the management of the
University farm in Nakagere, Mukono is concerned. Only 7 out of 187 acres
of this land is being utilized by the University thereby leaving the rest of the
land susceptible to encroachment by squatters who have erected permanent
structures on the land. The University could stand to lose part of the land.
The University farms lack animal registers. In fact some of the animals are
not tagged for identification purposes and so are prone to theft
I found that there were several irregularities and control weaknesses in the
management of the University mechanical and production workshop. This
could be attributed to lack of clear guidelines and policies, lack of proper
documentation and record keeping making it difficult to verify the revenues
received from the workshop.
There was poor maintenance of the University staff houses as most of them
are in a state of disrepair despite the fact that the University has always
budgeted for their repair and several Council resolutions have been passed
to that effect.
The University lacks tenancy agreements with some of the occupants of its
houses contrary to the Public Standing Orders. Those that had been issued
had provisions that were unlawful as they were contrary to the Housing
Policy (basically state the specific policy) which required the tenancies to be
held for a term of not more than three years. The agreements were to run
for 10 years.
I discovered several irregularities in the management of the cricket oval. I
noted that Uganda Cricket Association (UCA) had erected structures and let
out the premises to a third party contrary to the initial MOU that was signed
648
between UCA and the former UPK. I further established that there is
currently no binding MOU between KYU and UCA regarding the usage of the
cricket oval.
Inspections of the University vehicles revealed that 13 of them are
grounded. They are in a deplorable state, were being vandalized and
therefore need to be disposed off.
I tested for the completeness of the asset register by tracing the vehicles log
books in the motor vehicle register. I noted that there were 14 vehicles
whose registration books were in the custody of the University Secretary but
the same were not recorded in the vehicle register. I sought to verify the
existence of the said vehicles but the transport officer failed to avail the
same for physical inspection.
Whereas the University had annual budgetary provisions for insurance of its
motor vehicles, for the financial years 2010/2011, 2011/2012 and 2012/2013
respectively, only six (6) vehicles had been insured and 40 had their
insurance cover expired.
General Recommendations
The following general recommendations have been proposed:-
a. Governance
The University Council is advised to formulate a charter that will guide and
govern its operational modalities.
The University Council is further advised to ensure that policies on
recruitment and promotion of staff, financial management, research and
projects among others are developed, approved and complied with in the
day to day operations of the university.
The current University structure needs to be reviewed to allow for an
optimum level of staffing that can adequately manage the current student
levels and other University responsibilities.
The Academic Registrar is advised to always follow the laid down admission
procedures while admitting any student.
649
b. Human Resource Management
The University Bursar is advised to always ensure that statutory deductions
on staff pay such as contributions to the National Social Security Fund are
always effected and remitted promptly as required by the law.
The Director Human Resource is advised to always ensure that recruitment
of staff is done in accordance with the law and laid down procedures.
Allowances that are not provided for in the University Terms and Conditions
of Service of Staff and the Public Service Standing Orders should not be paid
by the University.
c. Revenue and Financial Management
The University Bursar is advised to exercise close supervision to staff in his
office that are charged with revenue collection, safe custody of accountable
stationary and also ensure regular reconciliation of financial records.
The University Bursar is further advised to always ensure proper
maintenance and recording of all books of accounts such as cash books,
student ledgers among others as per the Generally Accepted Accounting
Principles.
The University Management is advised to always ensure that all fees payable
by students during the admission process such as applications fees under
the private sponsorship scheme are collected and accounted for.
The University Management should institute stringent and robust debt
collection mechanisms in order to ensure prompt payment of fees by the
various student sponsors.
The Accounting Officer is advised to establish a mechanism through which all
audit findings contained in the annual audit reports are to be followed up
and actioned upon.
d. Asset Management
The University Accounting Officer is advised to ensure that all University
Assets are recorded in an Assets Register which ought to be periodically
650
updated to reflect an up-to-date status of the assets owned by the
University.
The University Accounting Officer is further advised to ensure that all
University land is secured and all activity on the said land is authorized and
monitored by the University Authorities.
The University management is also advised to develop guidelines that will
govern the running and management of all University workshops and ensure
adherence to the same.
51.0 BUSITEMA UNIVERSITY
a) Receivables
Included in the receivables are student debtors that increased from
UGX.333,193,785 to UGX.426,591,128 implying an increment of UGX.93,397,343
(28%). The increment may be attributed to laxity in enforcing the fees collection
policy. Accumulation of student debts may result into bad debts.
Management explained that the University has a debtor‟s policy which requires
students to clear their tuition and functional fees to zero balance before the
examination date and that efforts would be made to fully implement the policy.
I advised management to strengthen mechanisms of enforcing collection of debts.
b) Payables
Payables increased from UGX.192,279,917 to UGX.313,777,260 indicating an
increase of 63%. Included in the payables is a sum of UGX.114,774,856 payable
to National Social Security fund (NSSF), UGX.27,758,768 (withholding tax) and
UGX.9,135,284 (PAYE) payable to Uganda Revenue Authority (URA).
The University is exposed to the risk of penalties and fines from NSSF and URA.
Management stated that arrangements to settle the obligations were underway.
I advised management to ensure settlement of obligations in a timely manner to
avoid penalties and fines.
651
c) Land ownership
The University owns various pieces of land at different campuses totalling to
2,840.77 acres. While some of it is registered in the names of Busitema University
Council other pieces of land are not. Without evidence of ownership, it was
difficult to confirm whether the land actually belongs to the University. There is a
risk of loss of the land if it is not transferred appropriately.
In response management stated that the process of titling the land is underway.
The table below refers;
LOCATION AREA ( Acres)
STATUS OWNERSHIP
Busitema campus
1,309.658 530 hectares titled Busitema University Council
Namasagali 187 50.2 acres titled.
Namasagali University &Namasagali College.
Pallisa 27.804 11.252 hectares titled Busitema University Council
Nagongera 584.775 228.62 Hectares. titled Busitema University Council
Arapai 679.54 275 Hectares. titled Uganda Land Commission.
Mbale 52 0 Title not availed, therefore could not confirm ownership.
TOTAL 2,840.777
d) Non -implementation of planned activities
Comparison of the University‟s budget and Policy Statement for the year with
milestones attained revealed that the following planned activities and acquisitions
were not achieved;
The table below refers;
S/No. Item Estimated Cost (UGX)
1 Rehabilitation works at Mbale Campus. 100m
652
S/No. Item Estimated Cost (UGX)
2 Procurement of Identification Unit. 30m
3 Procurement of Conference Table for Council Hall.
28m
4 To Establish LAN (Local Area Network) in 2 campuses.
100M
5 Preparation of the quarterly progress and NTR reports and submission to the MoFPED and MoES respectively.
No estimates
6 Development of a consolidated Human Resource Policy.
No estimates
7 Procurement of 50 computers. Only 21 computers were purchased.
No estimates
8 Conducting a Training Needs Assessment exercise. No estimates
9 Planting trees around the boundaries of the University land at all campuses.
No estimates
Management attributed the shortfalls in the performance to inadequate funding.
I advised management to continue liaising with the Ministries of Finance, Planning
and Economic Development (MoFPED) and of Education and Sports (MoES) so as
to attain necessary funding for implementation of planned activities.
In addition all planned activities should be properly costed for ease of analysis of
the funding gaps.
e) Lack of Revenue collection procedures for Guest Houses
The University owns guest houses at Busitema University campus, Arapai Campus
and Namasagali Campus. However, the University lacks proper revenue collection,
recording and reporting procedures for the guest houses. In the circumstances
there is a risk of loss of revenue.
653
Management stated that arrangements are underway to put in place revenue
management mechanisms. I advised the Accounting Officer to strategize the
revenue management without further delay.
f) Inconsistencies in the recruitment regulations
Regulation 2.5.4 of the University Terms and Conditions of service require that the
Accounting officer makes part-term appointments for non-academic staff on
recommendation of the recipient Unit. On the contrary regulation 11(d) of the
recruitment and promotion policy requires appointments of non-Academic staff to
be made by the Vice chancellor on recommendation of the recipient Unit.
I explained to management that vesting of recruitment powers in different centres
may result into conflicting recruitments. Management stated that the regulations
and policy would be harmonized.
I await management action on the matter.
52.0 GULU UNIVERSITY
a) Doubtful Payment for Extra Load Allowance
In my previous report to Parliament, I qualified my audit opinion on the basis of
doubtful payments for extra load allowance, amounting to UGX.728,758,584. In
the report, I indicated that the basis of computation for the payments, including
information relating to the total number of hours lectured above the standard
hours by each lecturer rates and evidence of occurrence were not availed to
support the payments.
Management has indicated that controls surrounding the payment of extra load
allowances have been strengthened. However, I was still not availed with evidence
to satisfy myself that the payments were authentic.
b) Un-discharged Statutory Obligation
Section 14(1) of the National Social Security Fund, 1985 requires that every
contributing employer shall, for every month during which he or she pays wages
654
to an eligible employees, pay to the Fund, within fifteen days, next following the
last day of the month for which the relevant wages are paid, a standard
contribution of 15 percent calculated on the total wages paid during that month to
the employee.
However, contrary to the above requirement NSSF arrears stood at
UGX.577,709,906 as at 30th June 2014. Included in this figure is UGX.283,146,154
for the period July 2009 to June 2010, with interest of UGX.105,306,471. I
explained to management that there was a possibility of litigation and this could
put the University assets at risk.
Management explained that when staff salaries were enhanced, the employer‟s
contribution (10%) was not catered for and this contributed to the accumulation of
NSSF arrears. They further indicated that, a request for settlement of domestic
arrears which include NSSF obligations had been submitted to the MoFPED for
consideration.
I await the outcome of management‟s action in this regard.
c) Management of Receivables
Receivables relating to student debtors increased by UGX.266,567,004 from
UGX.2,098,511,984 to UGX.2,365,078,988 reported in 2012/13 and 2013/14
financial years respectively. There is laxity in enforcement of fees collection which
affects the implementation of planned activities.
Management undertook to enforce the policy on fees management which requires
students to pay all tuition fees and other University dues within 8 weeks after
commencement of the semester. I await management‟s commitment in this
regard.
d) Ownership of Land
The University owns five pieces of land, all totaling to 812.452 acres. However, the
University lacks certificates of title to show ownership. Without evidence of
ownership, it was not possible to confirm whether the land actually belongs to the
University. I explained to the accounting officer that there was a risk of the
655
University losing land to encroachers and other developers, if not transferred into
the University‟s name.
Management indicated that a lease offer had been granted for the 100 acres at
Latoro in Nwoya District and all efforts were being made to secure all the
University land.
I advised management to follow up the matter with the concerned authorities and
have all the University land secured and certificates of title transferred into the
University‟s names.
e) Direct Procurements
Regulation 94 (1)(a) of the Public Procurement and Disposal of public assets states
that a contracts committee or a holder of delegated authority shall approve the
choice of a procurement method prior to commencement of the procurement
process. On the contrary, goods and services worth UGX.34,444,000 were
procured by way of advancing funds to university staff and other non-prequalified
firms for purposes of purchasing various items directly. I explained to the
accounting officer that the use of such unconventional methods in acquisition of
goods and services lacked transparency and may not have achieved value for
money.
Management explained that the University had approved framework contracts for
regularly required items to limit advances. I advised the Accounting Officer to
streamline the procurement of the routinely purchased items to avoid possible
misuse of advances.
f) Understaffing in Internal Audit Department
It was noted that Internal Audit Department is understaffed and is currently
headed by a Senior Auditor. In the absence of a substantive Chief internal
auditor, the department‟s capacity to deliver on its mandate is not effective, given
the size and nature of the operations of the University.
656
Management explained that their submission to the Ministry of Public Service
authorization, to recruit both academic and non-academic staff especially for key
positions had not been responded to.
I advised management to follow up the submission made to Ministry of Public
Service and ensure that all key positions are filled to avoid operational
inefficiencies. The internal audit function should be appropriately staffed.
g) Absence of Fraud Control Policy
Best practice and good corporate governance require that organizations should
institute policies and procedures to detect, control and minimize occurrence of
fraudulent actions. It was noted that the University did not have any fraud control
policies and procedures to guide staff in the event that they encounter fraudulent
activities in the day-to-day operations within the University. In absence of such
procedures, it is difficult to mitigate occurrence of fraud and may create a
conducive environment for staff to commit fraud.
Management explained that the Audit Committee of Council in its meeting of 14th
October 2014 tasked management to table a fraud control policy at its next sitting
in February 2015. I await the outcome of this process.
h) Grounded Motor Vehicles
Regulation 2(1) of the Public Procurement and Disposal of Public Assets (Disposal
of Public Asset) Regulations, 2014 requires that the Accounting Officer shall, in
each financial year, cause the public assets of a PDE to be reviewed to identify the
public assets to be disposed of in the following financial year.
Audit noted that a number of motor vehicles belonging to the University had been
grounded for a long time without reviewing them for purposes of disposing them.
There is a risk that the vehicles are deteriorating further and therefore reducing
scrap value.
Management explained that the assets were recommended for boarding off by the
Board of Survey and approved by University Council and that the disposal process
was in progress.
657
I have advised the Accounting Officer to expedite the disposal process and in
future ensure that annual reviews are undertaken to identify any assets for
disposal in the next financial year as required by the PPDA – Disposal Regulations.
658
GENDER AND LABOUR SECTOR
53.0 MINISTRY OF GENDER, LABOUR AND SOCIAL DEVELOPMENT
a) Payables
Audit of Financial Statements for the period under review revealed that the
Ministry had liabilities of UGX.4,771,858,282, broken down as follows:
No Item Amount
1 Trade Creditors 220,000
2 Sundry Creditors 4,730,824,170
3 Withholding Tax Payable 40,814,112
Total 4,771,858,282
The sundry creditors arose out of outstanding claims for workman‟s compensation,
dating back to 2003/2004 financial year. Meanwhile, the withholding tax liabilities
may attract penalties from Uganda Revenue Authority as provided for in the
Income Tax Act, 1997 (as amended). The delay in paying renders the claims
redundant.
In response, management stated that requests to MoFPED for funds to settle the
liabilities had not been responded to positively.
I advised the Accounting Officer to continue liaising with the MoFPED and other
stakeholders to ensure prioritization of funding for the items to avoid litigations
and other costs that may arise.
b) Mischarge of Expenditure
Paragraph 400 (a) of the Treasury Accounting Instructions (TAI), 2003 states that
all government transactions shall be recorded in the books of account applying the
Government of Uganda Chart of Accounts as prescribed by the Accountant
General. In addition, Accounting Officers shall ensure that all financial transactions
are properly coded. It was noted that out of the total actual expenditure of
UGX.27,871,419,382, a total of UGX. 66,982,475 were mischarged. The practice
is a sign of a breakdown in controls over the budget implementation process.
659
Management explained that more adherences to the charge codes in line with the
Chart of Accounts is now being emphasized.
I have advised the Accounting Officer to streamline the budgeting process so that
available funds are properly allocated to the planned activities.
c) Advances not accounted for
A sum of UGX.25,000,000 advanced to three Districts for purchase of toolkits for
PCY activities lacked accountability contrary to TAI and MoU which requires
accountability within 60 days. The table below refers:
Document
No
Date Details Amount Paid
(UGX)
1139107 4/10/2013 Payment to CAO - Arua district to
purchase toolkits for Youth
trained
16,000,000
1216325 4/12/2013 Payment to CAO Gulu for
purchase of tool kits for training
and coordination of PCY project
4,000,000
1216321 4/12/2013 Payment to CAO Lira for
purchase of tool kits for training
and coordination of PCY project
5,000,000
Total 25,000,000
In the circumstances, I could not confirm whether the funds were used for the
intended purposes.
In response, management explained that letters reminding the respective Chief
Administrative Officers had been dispatched.
I advised the Accounting Officer to ensure submission of accountability or recovery
of the funds.
660
d) Staffing Gaps
I noted that the Ministry was grossly understaffed. Out of 609 posts in the
approved structure, only 276 were filled leaving 333 posts unfilled. Among unfilled
posts were; the Director Social Protection and Director Labour Employment
(Occupational Safety & Health), which are key posts in the management structure
of the Ministry.
Management indicated that submissions were made to the Ministry of Public
Service and Public Service Commission to ensure that the staffing challenge is
addressed.
I advised management to follow up the matter and fill the positions in a phased
manner beginning with the critical ones.
e) Non-Disposal of Obsolete Assets
Section 295 (5) of the PPDA Regulations, 2003 requires a procuring and disposing
entity through the board of survey to identify assets for disposal on a periodic
basis. A review of the Ministry‟s Asset register revealed a number of old and
obsolete assets due for boarding off and these included; motor vehicles, desktop
computers, laptops, furniture, tyres and books among others. I also noted that the
recommendations of the Board of Survey for disposal in the Financial Year
2011/2012 were not implemented.
Management indicated that it is in the process of updating a Disposal Plan and will
dispose of obsolete items in FY 2014/15.
I advised the Accounting Officer that failure to timely dispose of these assets
results in further physical deterioration and diminution in value. I await results of
management actions.
f) Lack of Performance Appraisals for some Staffs
Sec. A-m (14) of The Uganda Public Service Standing Orders, 2010 states that “A
staff performance appraisal report form shall be completed for each pensionable
and non-pensionable officer and a copy submitted to the Responsible Permanent
Secretary.
661
It was however noted that 25 staff out of a sample of 45 staff of the Ministry were
not appraised during the year under audit. The Accounting Officer explained that
strict guidelines and deadlines have been put in place for those that do not
comply.
I await results of management actions in this regard.
g) Repayments into the Revolving Fund
According to the YLP Programme Document dated December 2013, the revolving
nature ensures sustainability through the cash and kind refunds and re-
disbursement. This is further amplified in Part 4.0 of the YLP Project Funds Access
Criteria document which requires YLP to be administered as interest-free
Revolving Funds to ensure sustainability of the Programme.
I observed that out of 27 districts that had received the funds, only 6 had opened
the special collection accounts.
Management indicated that the outstanding 21 districts had been reminded.
I advised the Accounting Officer to ensure that the remaining Districts comply with
the regulatory requirements for YLP.
h) General Challenges faced in the Implementation of Youth Livelihood
Programme:
58.h.1.1.1.1 Determination of the age of the group members
According to YLP Project Funds Access Criteria part 2.2 (i) (Beneficiary Selection
Criteria) paragraph and program document chapter 2 section 2.4, all intended
beneficiary Youths should be persons within the age bracket of 18-30 and
evidence was to be provided through birth certificates, immunization cards,
passports, baptism cards, marriage certificates, National Identity Cards or
community knowledge of the youth.
During the period under review, audit noted that birth certificates for beneficiaries
on a number of project files were missing, rendering confirmation of the
qualification by age difficult.
662
Management indicated that a number of potential beneficiaries did not have
documentary evidence for their ages. The Selection Committees relied on the
judgement and decision of the community members under the leadership of LC I
Chairpersons as provided in the Programme Guidelines.
I advised the management to use the National identity cards in determining age of
beneficiaries in the successive following phases of the programme.
58.h.1.1.1.2 Inadequate monitoring of the projects
It was noted that the Districts were not closely monitoring the activities of the
approved youth projects due to inadequate staffing. For example, there were no
monitoring reports for the 16 districts inspected out of the 27 pilot districts. The
respective CAOs and the District Focal Point Persons indicated that there is low
human resource capacity as opposed to the number of approved projects to allow
closer monitoring to take place.
Management explained that the low staffing levels especially of Extension Staff in
the Local Governments still remains a challenge. Furthermore, the Accounting
Officer indicated that the Chief Administrative Officers have been advised to
rationalize the deployment of the available staff to ensure that the youth groups
financed under YLP receive technical support.
I await results of management actions on this matter.
58.h.1.1.1.3 Lack of sign posts for respective Projects
It was observed that a majority of the YIG Projects that were inspected did not
have sign posts. Those that had sign posts did not have YLP identity. It was
therefore not possible to easily identify them with YLP funding.
In response, management stated that all the new projects are being advised to
provide for the signposts in their budgets. Furthermore, YLP has concluded the
Geographical Information System (GIS) mapping for all the projects financed
under Phase-I as a strategy of enhancing accountability, transparency and to avert
a possibility of using one project site for multiple accountabilities to various
663
agencies or persons. In the meantime, I await the results of management effort in
this regard.
58.h.1.1.1.4 Inadequate training of the 3 committees in a group
The YLP Programme Document requires each YIG to have at least 3 committees
namely; Youth Project Management Committee (YPMC), Youth Procurement
Committee (YPC) and Social Accountability Committee (SAC).
Audit revealed that the trainings received by the members of these committees
were so general and did not address the specific roles that each committee is
supposed to play in a group. Furthermore, the trainings were conducted under
limited time frame.
Management explained that any gaps identified during monitoring visits are
documented and addressed as part of the routine continuous support to the
groups.
I advised management to ensure that trainings to the committee members are
conducted to enable them appreciate their roles on the committees so as to avert
conflicts and failure of groups‟ businesses.
58.h.1.1.1.5 Record Keeping
It is good practice for any type of business/project to keep proper books of
account, management records among others. I noted that most of the groups
visited did not maintain/keep such records including minutes and procurement
details.
Management indicated that the varied literacy levels of the beneficiaries supported
under YLP affects record keeping. However, the Sub-county Community
Development Officers (CDOs) have been advised to provide support to weak
groups on regular basis as part of their overall mandate in community mobilization
and development.
I await the results of management efforts in this regard.
664
53.1 EXPANDING SOCIAL PROTECTION PROGRAMME 2011/2012
a) Lack of National Social Protection Policy
It was noted during audit that the program still lacked an approved policy,
contrary to the recommendation contained in Expanding Social Protection (ESP)
Quarterly report of July to September 2011, requiring an approved policy
framework to be in place within the financial year 2011/12. In the circumstances,
there is no formal framework to guide the activities of Social Protection in the
country. There is also a risk of having social disharmony between the societies
that have benefited and those that have not.
Management explained that at the inception of the programme, the design
foresaw the development of a Social Protection “framework” which would have
simply defined the scope of social protection services in Uganda. However, during
the course of the programme, management realized that a full National Social
Protection Policy was required along with a comprehensive costed plan of
Interventions (PPI) to cover social assistance, social insurance and social care
services. Management further stated that according to the revised log-frame, the
policy and PPI are due to be finalised by December 2014.
I have advised management to engage the stakeholders involved and expedite the
discussions to have the policy finalised and approved.
b) Co-funding
Section 2 of the Joint Financing Arrangement requires the Government of Uganda
(through the MoGLSD) to provide an agreed level of funding to the programme. It
was however noted that GoU, which had committed to provide USD.20,030 (about
UGX. 70,105,000), did not fulfill its obligation in the period under review. This
could have hampered the implementation of the planned activities and may affect
the overall attainment of the programme objectives.
Management explained that they were continuing to engage the Ministry of
Finance, Planning and Economic Development to fulfill the government obligations
towards the programme.
665
I have advised management to continue with the engagement of the Ministry of
Finance Planning and Economic Development so as to ensure that Government
fulfills its commitment towards the programme for better implementation.
c) Un-accounted for Funds
UGX.227,301,091 (equivalent to USD.49,778.45) was transferred to ESP
operational account in the MoGLSD, to facilitate older persons day celebrations
and orientation of Members of Parliament. Audit noted that a total of
UGX.106,618,500 was utilized for the celebrations and orientation of MPs, leaving
a balance of UGX.120,682,591 unaccounted for.
Although management explained that the balance was retained in the MoGLSD
ESP operations account for other ESP activities, no documentary evidence was
availed to confirm this and how it was utilised.
I have advised management to ensure
53.2 EXPANDING SOCIAL PROTECTION PROGRAMME 2012/2013
a) Co-funding
Section 2 of the Joint Financing Arrangement requires the Government of Uganda
(through the MoGLSD) to provide an agreed level of funding to the programme. It
was however noted in the year under review that GoU allocated only
UGX.40,000,000 million as opposed to the FY 2012/13 counterpart commitment of
UGX.500,500,000. This could have hampered the implementation of some planned
activities and may affect the overall attainment of the programme objectives.
I advised management to engage Ministry of Finance Planning and Economic
Development so as to ensure that Government fulfils its commitment towards the
programme for better implementation.
b) Doubtful contract award
Regulation 90 (g, h & i) of the Public Procurement and Disposal of Public Assets,
2013, stipulates the procurement records that should be maintained by a
procurement and disposal unit. However it was noted that a total of
UGX.191,666,376 was paid to Property Development Company Ltd for rent, but
procurement documents were not maintained, contrary to the requirements of the
regulations. In the circumstances, audit could not ascertain whether the
procurement was fairly competed for and that there was value for money.
666
I advised management to ensure that all procurement records are in future
maintenance for all procurements undertaken on behalf of the programme.
c) Un-vouched Expenditure
Audit noted that out of a total of UGX.135,369,238 transferred to Kyenjojo District
to fund SAGE activities in the months of January and June 2013, a total of
UGX.116,152,804 was spent without preparing payment vouchers. The
authenticity of the expenditures relating to all the missing vouchers could not be
ascertained.
I advised management to ensure that the funds are accounted for.
d) Mischarged expenditure items
A total of UGX.11,976,000 was charged wrongly on expenditure items other than
those under which it was supposed to have been spent, contrary to the
requirements of section 3.1 of the overview of the financial management of SAGE.
Failure to comply with the requirements portrays a breakdown of controls in the
budget implementation process and it affects the implementation of some planned
activities.
I advised management to streamline the budgeting process and ensure that
payments are correctly charged on the item codes to enable proper
implementation of the programme.
e) Un Accounted for Funds
Funds totaling UGX.56,178,500 advanced to various officers in Katakwi district to
implement programme activities remained un-accounted by the time of writing this
report. In the absence of the necessary accountability, audit could not confirm
whether the funds were put to intended use.
I advised management to recover the funds from the officers
667
53.3 EXPANDING SOCIAL PROTECTION PROGRAMME 2013/2014
a) Irregular payments to Deceased Persons
The Social Assistance Grants for Empowerment (SAGE) comprise two sub-
components namely; Senior Citizen‟s Grant (SCG) and Vulnerable Families Support
Grant (VFSG).
Chapter six (6) of the Implementation Guidelines for SAGE, SCG and VFSG provide
that „In the event of the death of an older person, households benefitting from the
SCG will cease to be eligible immediately‟. An older person refers to one who has
attained the age of sixty five (65) years and above. In addition, the third
paragraph of chapter 6.1 of the same guidelines states that „The death of a
registered beneficiary of the SCG will result in termination of payments. Death of a
beneficiary must be reported by the next of kin to the Village Chairperson as soon
as possible and an SCG Beneficiary Death Notification Form (Annex X) should also
be completed by the next of kin with the support of the village chairperson‟.
A review of the SCG component, beneficiary payrolls and files in 14 Districts
inspected revealed that names of deceased beneficiaries were neither reported as
required nor deleted from payrolls after they had passed on. In the circumstances,
payments totalling UGX.36,950,000 made in respect of deceased persons were
made irregularly.
In response, management explained that a team of staff had been constituted to
work on improving the system of capturing information on deaths.
I advised management to strengthen mechanisms for timely reporting of deaths
under the SCG component so as to ensure the programme meets its intended
objective of assisting Senior Citizens
b) Suspected SAGE Fraud in Kole District
Review of an investigation report prepared by a contracted Auditor revealed
suspected fraud on beneficiary payments for the month of December 2013 in Kole
District amounting to UGX.132,268,500. The suspected fraud was attributed to
lack of a documented policy over SIM card management and collusion between
the MTN Mobile Money Agent and SAGE staff.
668
In response, management stated that disciplinary hearing with SAGE staff had
been held and efforts were being made to have criminal prosecution of the staff
together with the MTN Mobile Money Agent. In addition, training on SAGE Policy
on fraud, complaints and whistle blowing would be undertaken for all SAGE and
local government staff.
I await results of management actions.
c) Lack of Procurement Plan
Regulation 6 (2) of the PPDA Regulations, 2003 requires an entity to prepare a
consolidated procurement plan. However, Expanding Social Protection Programme
(ESPP) carried out procurements without a procurement plan. It was observed
that departmental procurement work-plans were also not prepared. There is
possibility of sub-optimal procurement.
Management indicated that the procurement activities for different programmes
have now been integrated into programme work plan for the implementation in
the next period.
I await the results of management action.
d) Governance Weaknesses
1.d.1 Lack of approved Human Resource Manual
A human resources manual, guides staff recruitment, appointments and is a vital
tool in management of staff of any organization. It was however noted that
the Programme lacks a human resources manual. There is a risk that the
Programme‟s human resource operations are not well guided.
It was also noted that a draft manual has now been developed and is awaiting
approval by the Programme Steering Committee.
I advised management to expedite approval of the manual to enable proper
management of staff.
1.d.2 Lack of Internal Audit Function
669
The internal audit function helps to regularly conduct reviews on entity risk
management, monitor and provide assurance on internal controls. It was however
noted that ESPP operated without an internal audit function during the period
under review. There is a risk of weaknesses in internal control remaining
undetected over long periods.
Management stated that a proposal to establish the function will be tabled before
the Steering Committee for approval.
I await management action in this regard.
1.d.3 Lack of approved Finance and Procedures Manual
The Finance and procedures manual helps guide management of finances in an
organization. Audit however noted that ESPP did not have an approved accounting
and financial procedures manual.
Management indicated that a draft manual was in place and it would be updated
before approval by the Steering Committee.
I advised management to expedite the process.
e) Inadequate Management of Inventories
Paragraph 203 of the Treasury Accounting Instruction, 2003 requires all stores
receipts to be posted in the ledger as soon as they have been examined in
accordance with the receiving procedure. All issues of inventories will be posted in
the stores ledger daily but if on any occasion, daily posting of vouchers proves
impracticable, the vouchers will be posted with the least possible delay, and the
circumstances will be notified by the Storekeeper to the Head of his Department
or Accounting Officer.
During audit, it was noted that all procured items were not taken on charge and
were not issued using bin cards and issue vouchers. Weaknesses in the inventory
management may result in loss/misappropriation of programme assets.
Management indicated that the purchases are normally made in small and
irregular quantities which did not require detailed recording.
I advised the Accounting Officer to ensure proper record keeping of stores in
compliance with the accounting instructions.
670
f) Incomplete Transition Plan
According to part 9.1 of the ESPP 2010 - 2014 Programme Document, capacity
was to be progressively built in government over the first 3 years so that full
responsibility for funds and management of the ESPP can be handed over to the
Government of Uganda. During the course of the 3 year existence of ESPP, certain
budgets and other areas of the programme were to be transferred to GoU. It was
however noted that the transition plan, in terms of capacity building, had not been
achieved as envisaged, even after contracting an Institutional Development
Specialist in the first quarter of 2011/2012 to operationalize the plan. This was
attributed to the freezing of the donor funding in December 2012, where money
initially channelled through the Chief Administrative Officers for this purpose was
stopped and the management agent was introduced. There is a risk that the
programme may collapse after the current arrangements cease.
Management indicated that consultations are underway to have new transition
arrangements in place.
I advised management to ensure that the transition work plan is implemented and
re-aligned with the current level of implementation to ensure that the programme
is able to operate sustainably.
g) Long distances travelled by beneficiaries to Mobile Money Pay
Points
To effectively deliver payments, an extensive and reliable distribution network is
required to reduce the cost of access for recipients. Through interviews with some
of the beneficiaries during audit inspection, it was noted that many of them had to
travel on average four (4) kilometres to pay points to access payments. In some
extreme cases, such as Nebbi, Kole, Amudat and Napak districts, some
beneficiaries travelled distances as far as seven (7) kilometres to pay points. This
was partly attributed to weak signal strength of the Mobile Money service provider
(MTN Uganda) at some places.
The resultant effect of the above is that beneficiaries incur high transportation
costs, which erodes the value of the grant transferred and the overall benefits to
671
the beneficiaries. The attainment of the initial objective of improving the
livelihoods of the beneficiaries is therefore undermined.
Management indicated that the payment service provider (MTN) would be
engaged to improve on signal strengths.
I await results of management action.
h) Replacement of lost SIM cards
Interviews conducted with the OPG beneficiaries in the Districts revealed instances
of loss of SIM cards by the beneficiaries. It was further noted that it took up to
two months or more for lost SIM cards to be replaced. Failure to replace lost SIM
cards in a timely manner hinders accessibility to the payments thereby impairing
achievement of the programme objectives.
Management explained that the replacement process for the lost cards takes long
due to the fact that the service provider imports the cards.
I advised management to liaise with MTN with a view of ensuring that the time
taken to replace lost SIM cards is reduced, so as to ensure uninterrupted monthly
payments to beneficiaries.
i) Selection criteria for Vulnerable Families Support Grant (VFSG)
According to the programme document, Social Assistance Grants for
Empowerment enrols people who are in vulnerable families. Vulnerable families
are defined as those which have majority of orphans, do not have any bread
earner and are living in poverty conditions.
Interviews conducted with some beneficiaries and Community Development
Officers in Kiboga and Kyenjojo Town Councils revealed that some of the selected
beneficiaries did not meet the criteria as defined in the ESPP selection criteria. This
practice denies the genuine vulnerable families the opportunity to benefit from the
VFSG program.
Management explained that the VFSG programme was a pilot study alongside the
SCG to identify the best method of targeting the families. Going forward VFSG
method will be phased out and an alternative method developed. I advised
management to put in place rigorous beneficiary selection procedures and carry
672
out post selection reviews to ensure that rightful persons benefit from the
programme
WATER AND ENVIRONMENT SECTOR
54.0 MINISTRY OF WATER AND ENVIROMENT
a) Mischarge of expenditure
The Parliament of Uganda appropriates funds in accordance with the needs of the
Country and this appropriation is implemented through the budget in which funds
are tagged to particular activities and outputs using account codes and MTEF
codes.
A review of the Ministry‟s expenditure revealed that the entity charged
UGX.1,545,058,115 a decline of 84% from previous year‟s amount of
UGX.9,438,526,861 on expenditure codes other than those for which funds had
been appropriated. There was no evidence of authority under which the
mischarges were allowed while executing the budget.
Though the practice of mischarging the expenditure is on the decline at the
Ministry, further budgetary discipline is required.
The accounting officer explained that additional measures would be put in place to
further streamline the budget implementation process, so as to avoid the practice
of mischarging expenditure.
I advised the Accounting Officer to strengthen supervision of the budget
implementation and where it is inevitable re-allocation warrants should be sought
from the Ministry of Finance, Planning and Economic Development before release
of funds.
b) Payables
The Ministry had domestic arrears and other payables amounting to
UGX.3,019,492,303 at the close of the financial year as presented in note 26 to
the financial statements. Included in this amount were long outstanding debts
673
such as; PAYE (UGX.1,348,649,448), contributions to international organizations
(UGX.291,740,137), and UMEME (UGX.41,900,648).
It was noted that Tax liabilities attract fines in accordance with the Income Tax
Act, 1997 (As amended). Failure to contribute to international organizations may
result into forfeiture of corresponding rights and benefits. There is also a risk of
disconnection of electricity to the Ministry by UMEME.
Management attributed the outstanding payables to failure by the Ministry of
Finance, Planning and Economic Development (MoFPED) to release necessary
funds for their settlement.
I advised management to continue liaising with MoFPED to ensure that resources
are set aside to settle these payables.
c) Nugatory expenditure
The Ministry paid UGX.1,120,908,971 to A Construction company being interest
charges on delayed payments for the contract of reconstruction of water supply
and sanitation facilities in Sironko, Soroti and Kaberamaido districts under contract
No DWD/WORKS/04-05/00140. It was further noted that UGX.223,694,883
relating to the interest was paid in error. Payment of interest charges is
considered wasteful expenditure as it could have been avoided with proper project
planning.
Management attributed the nugatory costs to delayed release of advance payment
to the contractor, unscheduled public holidays, scope changes and additional
work. It was also stated that efforts to recover UGX.223,694,883 relating to
interest paid to the contractor in error were underway.
I advised the Accounting Officer to always ensure timely settlement of obligations
to save public funds from wastage. Meanwhile, I await evidence of recovery of
interest paid in error.
d) Administrative advances
Paragraph 217 of Treasury Accounting Instructions requires that administrative
advances be accounted for within 60 days from the date of payment or else be
674
deducted from the monthly salary of the official. Contrary to the above
requirement however, UGX 90,073,333 advanced to staff for official activities
lacked supporting documents. In addition, review of accountability documents
submitted by the Ministry staff revealed improper accountability for
UGX.112,817,000 thereby bringing the total sum of outstanding funds to
UGX.202,890,333. Failure to ensure proper accountability and/or enforce recovery
may result into loss of public funds. Though the Accounting Officer indicated that
supporting documents were available, the outstanding sum was not supported.
I advised the Accounting Officer to ensure proper accountability or recovery of the
funds from the concerned staff.
e) Delays in the procurement evaluation process
According to the Ministry‟s approved procurement plan, procurement of works
service should take a maximum of 38 days from the date of bid opening to the
date of evaluation. I however observed that procurement of consultancy services
funded under the donor component lasted up to 91 days. The table below refers;
Subject Of Procurement Provider Contract Value Start date No of
Days
Consultancy Services for
Feasibility Studies, Detailed
Designs and Construction
Supervision of Water Supply
Systems Under Lot3: for
Namulonge-Kiwenda-Busiika
and Kiwoko, Butalanga and
Rehabilitation of Katuugo and
Improvement of Kakooge and
Migeera Water Supply
Systems.
MS M&E
Associates
Ltd
UGX.1,213,300,000 25-Nov-13 91
Consultancy Services for
Feasibility Studies and
Detailed Designs Under Lot2:
for Busaana
Kayunga,Kabembe-Kalagi-
Naggalama and Kakunyu-
Kiyindi and Construction
Supervision for Rehabilitation
MS Seureca
Consulting EA
In
Association
With Warner
Consultants
€ 512,288 25-Nov-13 91
675
of Buvuma
The Accounting Officer attributed the delays to the time that was taken to seek for
no objection from the donor. Delayed procurement of service providers affects
timely delivery of services to the population.
I have advised the accounting officer to ensure that procurement planning takes
into account donor requirements so as to attain timely delivery of services to the
population.
f) FARM INCOME ENHANCEMENT & FOREST CONSERVATION PROJECT
Under absorption of project funds
The Government of Uganda obtained funding from the African Development Bank
(ADB) Group and the NDF to support the FIEFOC Project which was designed to
support the Government of Uganda‟s (GoU‟s) Plan for Modernisation of Agriculture
(PMA) aimed at increasing incomes and improving the quality of life of poor
subsistence farmers and their households through market-oriented agricultural
production. The financing requirements provide for a refund of any funds not
absorbed.
It was noted that by 30th June 2014, UGX.911,108,559 and UGX.337,799,685 from
the African Development Bank and the Nordic Development Fund respectively had
not been absorbed and therefore the amounts were refunded.
As a result, planned activities such as; capacity building of farmer based
organizations for efficient management of Doho, Mubuku and Agoro irrigation
schemes and establishment of contour hedgerows on 10,000 km of slopes were
not undertaken.
676
The accounting officer attributed the under absorption to delay of civil works while
the irrigation component was under the Ministry of Agriculture, Animal Industry
and Fisheries.
I advised the Project Management to ensure that in future, bottlenecks to project
implementation should be timely resolved so as to ensure timely and proper
implementation and thus improved funds absorption.
54.1 BRIDGING SUPPORT TO CLIMATE CHANGE UNIT PROJECT
a) Project Bank Account
Best practice requires each project to have a separate bank account for ease of
tracking and accounting for any project transactions at any particular time. Audit
noted that there was no separate bank account maintained for the project making
it difficult to track inflow and outflow of the project funds. There is also a risk of
project funds being utilized on activities of other projects and vice versa.
Management attributed the anomaly to the communication from Ministry of
Finance Planning and Economic Development of minimizing the opening of
Government accounts but hastened to add that an application had been lodged
with the Accountant General‟s Office to obtain clearance to open a separate
account for the project.
I have advised management to hasten the opening of a separate bank account for
the project.
b) Implementation of activities
Accordance to the approved project agreement and approved work plan, Bridging
support project was to run for a period of two years, up to the end of the year
2013. Consequently, 75% of the activities ought to have been implemented by the
year end (i.e. 30th June 2013).
Audit noted that by the end of the financial year, most activities had not been
implemented. For example the activities under the climate change coordination
mainstreaming and capacity enhancement at national and district level had not
been implemented. This may affect the attainment of the overall project
objectives.
677
I have advised management to ensure that project implementation is carried out
as planned so as to meet set objectives
54.2 CLIMATE CHANGE INITIATIVE PROJECT
a) Non-Compliance with the terms of the standard project agreement
During the year, the Government of Uganda (GoU) contributed UGX.787,260,833
to the project. However the funds were not banked on a Climate Change Unit
Account, contrary to the requirements of Section 14.1 of the Standard Project
Agreement. This was a violation of the Standing Agreement. In the circumstances,
management of the project cannot be able to control the expenditure of the funds.
Management explained that the funds for the project were maintained on a
different account and managed by the Ministry of Water and Environment.
This matter was reported in my previous report (30th June 2013) and although
management had explained that it was an oversight that would be corrected, no
action was taken.
I have advised management to liaise with the Ministry of Water and Environment
so as to ensure that the Standing Agreement provision pertaining to banking in a
project account is complied with.
b) Delay in accounting for funds
UGX.32,151,743, which was advanced for the National Conference on Climate
Change Policy on 7th August 2012 was accounted for on 27th February 2013,
together with a refund of UGX.3,208,243 on the same day (a delay of 205 days).
The financial monitoring and internal control is thus inadequate.
Management acknowledged the anomaly but attributed the delay to the busy
schedule of the concerned officers who had engagements of developing the
National Climate Change Policy.
I have advised management to ensure that project staff timely account for funds
advanced to them to enable effective financial monitoring.
c) Local Service Tax
Section 80 (1b) of the Local Governments Act states that a local service tax is to
be levied on all persons in gainful employment or who are practicing any
678
profession or on business persons and commercial farmers producing on a large
scale.
A review of the project monthly payrolls revealed that the local service tax was not
withheld for onward remittance to Local Councils.
Defaulting on local service tax exposes the project to risks of penalties.
Management regretted the anomaly and pledged, with effect from January 2015
to deduct Local Service Tax fees from all the Climate Change Department‟s staff
salaries and remit to the respective Local Councils, as per the requirements of the
Act.
I await management‟s action in this regard.
54.3 JOINT WATER SANITATION SECTOR PROGRAMME SUPPORT (JWSSPS)-
AfDB FUNDED COMPONENT
a) SECTOR PROGRAM SUPPORT-COMPONENT
a. Under absorption of donor funds
Sector program support budgeted and received UGX.4,240,000,000 from AfDB but
audit noted that only 50% (UGX.2,115,000,000) of the funds released were
utilised. Failure to absorb all the released funds does not only affect performance
but may also affect future cash flows.
Management attributed under absorption to the delay in finalizing the joint
financing agreement for the Joint Water and Environment Sector Support
Programme (JWESSP) and delays in opening of the fund and operational bank
accounts.
I have advised the program coordinator to closely monitor the performance of the
activities experiencing slow progress in implementation and ensure that corrective
actions are undertaken to bring those activities back on course.
b) RURAL WATER AND SANITATION SUPPLY-COMPONENT
i. Budget performance
The component budgeted for revenue of UGX.36.818 billion to implement agreed
activities but only UGX.19.171 billion was released resulting in a variance of
UGX.17.647 billion. Failure to release all the budgeted funds constrained the
679
implementation of the core component activities hence greatly affecting the
component performance. Management attributed this to the delay in finalizing the
Joint financing agreement for the JWESSP.
I have advised the Accounting Officer to always conclude the signing of project
funding agreements well in advance and allow for adequate time to enable smooth
release of funds allocated in each financial year.
ii. Accounting for Staff Advance
The project management advanced UGX.22,485,000 to an employee on Voucher
No.13-0509 to undertake a training of Iganga district local government staff in
appropriate sanitation promotion approaches. Review of the accountability
revealed some anomalies as indicated below;
JPF operations manual requires a log book to be maintained for every vehicle
and to be filled by a driver for each trip, which should be counter signed by the
officer. Furthermore, JPF manual requires drivers to submit monthly vehicle
reports showing summary of mileage covered and technical performance of the
vehicles. Contrary to these requirements, it was noted the activity holder fuelled
vehicles registration Nos. UG 1739S and UG 1733S with fuel worth
UGX.729,200 from various fuel stations without adhering to the mentioned
requirements. Although management in its response stated that the log books
were available, however, they were not provided for verification.
The activity holder paid Canaan Resort Hotel Ltd and Shelter Guest House
UGX.4,000,000 and UGX.10,675,000 respectively for hotel services, however,
withholding tax of UGX.880,500 was not deducted. Management in its response
pledged to recover the tax from the activity holder. I await the outcome of
management‟s action in this regard.
I have advised the Accounting Officer to ensure that vehicle movements are
adequately documented in log books to enhance management of vehicle fleet.
g) WATER AND SANIATION DEVELOPMENT FACILTY-CENTRAL REGION
i. Absorption of donor funds
680
Review of the budget performance for the facility revealed AfDB committed to
finance agreed facility activities with a total of UGX.26,361,540,000 and this
money was duly transferred from JPF operations account to the facility in the year
under review. However, audit noted that only UGX.24,374,999,000 was absorbed
leaving a balance of UGX.1,986,541,000 un-utilized.
This was caused by delays in the approval and implementation of some
construction works in rural growth centres which negatively affected the overall
performance of the facility.
I have advised the facility manager to enhance monitoring, supervision of
procurement processes and construction works to avoid unnecessary delays.
ii. Procurement from Non Prequalified Service Providers
Regulation 94(1) (a) of the public procurement and disposal of public assets, 2003
stipulates that a contracts committee or a holder of delegated authority shall
approve the choice of a procurement method prior to commencement of the
procurement process.
However, review of payment vouchers revealed that UGX.520,649,524 was paid to
un-prequalified firms for hotel services without proper justification or contracts
committee approval. This practice undermines the purpose of prequalifying firms
and it is likely that the facility did not obtained value for money from the
expenditure incurred.
Management explained that the facility operates in Rural Growth Centres where
there are no pre-qualified service providers to offer the required Hotel Services
and thus uses the “National Shopping Procurement Method” as provided for in the
funding agreement between AfDB and GoU. A review of the funding agreement
however showed that the purported procurement method is not providing for.
I have advised the Accounting Officer to prevail over the procurement officer and
ensure that procurement procedures are adhered to when incurring public funds.
iii. Fuel Management
Public Procurement and Disposal of Public Assets Authority gave the Facility
authority to procure fuel advantage card facilities from M/s Shell (U) Ltd and M/s
681
Total (U) Ltd. The two service providers were selected due to their geographical
spread. A review of fuel payment vouchers however revealed that the facility‟s
management disregarded the authority and deposited UGX.140,000,000 with Shell
Nansana as opposed to M/s Shell (U) Ltd and M/s Total (U) Ltd. Failure to adhere
to the authority granted by PPDA does not only undermine its mandate but also
makes management‟s actions suspect.
Management in its response explained that the funds were deposited with Shell
Nansana, because it‟s located near the Facility. Management further explained that
it was an interim measure undertaken when the previous credit card system by
Standard Chartered Bank was terminated.
I have advised the Accounting Officer to always carry out transactions in
accordance with the authority granted by PPDA, and in case of need for
divergence, to seek for PPDA approval.
iv. Consultancy services for feasibility studies, design review and
detailed engineering design for lot 1: Kiganda, Kakumiro, Kagadi
and Kiboga
Water and Sanitation Development Facility signed a contract No. MWE/SRVCS/11-
12/1292/1 dated 10th October 2012 with COWI (U) Ltd for consultancy services for
feasibility studies, design review and detailed engineering design for lot 1:
Kiganda, Kakumiro, Kagadi and Kiboga at a contract price of UGX.176,077,984.
The project commenced on 1st November 2012 with expected completion date of
30th June 2013. It was however, noted that contrary to Paragraph 18.1 of the
general conditions to the contract agreement, requiring the contractor to complete
the feasibility studies of the 4 schemes within 8 months (1st Nov 2012 to 30th June
2013); the contractor delayed to complete the project by 5 months (completed in
November 2013).
Failure to timely complete feasibility studies delayed the implementation of the
water schemes in the above mentioned towns, hence affecting service delivery.
Management attributed the delay to the failure to identify adequate water
resources in the towns of Kiboga, Kagandi and Kakumiro.
682
I have advised the facility manager to always expedite test drills to allow sufficient
time for the consultants to finalize detailed designs within the agreed contract
period.
v. Consultancy services for feasibility studies and detailed designs
for Busaana Kayunga, Kabembe-Kalagi-Naggalama and Kakunyu-
Kiyindi and feasibility studies, detailed designs and construction
supervision for rehabilitation of Buvuma
WSDF- Central contracted Seureca Consulting Engineers in Association with
Seureca EA Ltd and Warner Consultants on 13th May 2014 to carry out feasibility
studies and detailed designs for Busaana Kayunga, Kabembe-Kalagi-Naggalama
and Kakunyu-Kiyindi and feasibility studies, detailed designs and construction
supervision for rehabilitation of Buvuma at a contract price of Euros.512,288.
I noted that contrary to regulation of 239(2) of PPDA, which requires a procuring
and disposing entity to pay a service provider for the actual cost of the works, as
evidenced by receipts and other appropriate documentation, management paid
Euros.53,324 for reimbursable expenditure to the consultant under certificate 1
without adequate supporting documents.
Management in its response indicated that communication had been made to the
consultant to submit supporting documentation for the re-imbursable expenditure
for certificate one.
I await the outcome of management‟s action in this regard; else the Accounting
Officer will have to deduct the funds from the subsequent certificates of the
consultant.
54.4 JOINT WATER AND SANITATION SECTOR PROGRAMME SUPPORT
(JWSSPS) – SOUTH WESTERN
a) COMPLIANCE WITH THE PROGRAMME FINANCING AGREEMENT
AND THE GOU FINANCIAL REGULATIONS
Compliance review was undertaken on the programme operations, however there
was no material breach of compliance issues that came to my attention during the
audit that would warrant reporting.
683
b) GENERAL STANDARD OF ACCOUNTING AND INTERNAL CONTROL
i. Inefficient Accounting System
WSDF-SWB is required by the Joint funding partnership operations manual to
process financial transactions and maintain books of accounts using a Computer
Financial Management System (CFMS).
It was observed that there was poor connectivity between the central server at
Luzira and the facility office at Mbarara. As a result officers had to travel to
headquarters in Kampala to enter data in the system and process transactions.
The poor connectivity does not only defeat the purpose for which the system was
installed but has also caused delays in the processing financial transactions,
increased operational costs and can affect the branch performance of the project.
Management explained that a new web-based system had been adopted and that
the IT department was working on its connectivity. I await the outcome of
management‟s action in this regard.
ii. Unbudgeted for expenditure
Paragraph 152 of the Treasury Accounting Instructions (TAI), 2003 requires that,
expenditure not provided for in the approved estimates of the current financial
year may not be incurred without the authority of a supplementary estimates
warrant, a virement warrant or a contingencies fund advance warrant.
It was however observed that the facility paid out UGX.234,239,258 to URA as
withholding tax and PAYE arrears relating to the previous financial years yet the
expenditure had not been provided for in the approved estimates for the period
under review. In the circumstances, management is constrained in implementing
the planned activities. Management explained that the amount was deducted in
the previous FY but was not remitted to URA due to lack of funds. I have advised
management to always seek approval from the sector working group for any
expenditure outside the approved budget.
iii. Management of the Facility Assets
Grounded Facility Vehicles and Motorcycles
684
Section 6.3 of the Joint Partnership Fund, Phase 2 operations manual, requires the
facility to efficiently and effectively manage the vehicles and assets under its
control in order to maximize the future economic benefits. This required
management putting in place an organized system of planned preventive
maintenance that provides for scheduled maintenance before an asset breaks
down.
It was noted that seven motor vehicles and two motorcycles belonging to the
facility broke down and had been grounded and needed boarding off. However,
the boarding off process had not been initiated. The failure to timely board off the
grounded assets is bound to result in further loss of realisable value.
Management acknowledged the anomaly and explained that the assets had
become costly to maintain. I have advised the facility management to liaise with
the Ministry‟s Accounting Officer and commence the disposal process of grounded
vehicles and motorcycles.
Ownership of plot of land on Mbarara - Kabale road
It was observed that WSDF-SWB occupies Plot Number one on Mbarara - Kabale
road, which lacked a land title. In the circumstances, the facility is exposed to a
risk of forfeiture of the piece of land in the event that the Municipal Authorities
decide to re-allocate the land to other developers.
Management explained that it was in the process of obtaining the land title and
that the surveying process had been concluded and deed plans secured. The
conclusion of the matter was still pending offer by the District Land Board. I await
the outcome of the process initiated by the facility management.
iv. Construction of Kyempene Town Water Supply and Sanitation
Scheme in Ntungamo District
Ministry of Water and Environment, Directorate of Water Development, Water and
Sanitation Development Facility-South Western Branch signed a contract with a
685
construction firm in August 2013 for the construction of Kyempene Water Supply
and Sanitation Scheme in Ntungamo District at a cost of UGX.1,582,646,835.
Paragraph 104(2) of the PPDA regulations, 2003 requires the procuring and
disposing entity to ensure that engineers‟ estimates are realistic and are based on
up-to-date information. It was noted that the project was designed with estimated
cost of UGX.1,369,003,298. However the submissions to the Contracts Committee,
had an amount UGX.1,586,684,122, which lacked details of how the estimates
increased from the original amount of UGX.1.369 billion.
Although management explained that there were supporting documents to justify
the increment, these documents were not availed for examination. I have advised
the Accounting Officer to investigate the cause of the increment in the engineers‟
estimates in the above matter and to ensure that any changes in estimates are
always properly documented.
54.5 KAMPALA WATER – LAKE VICTORIA WATER AND SANITATION PROJECT
a) Low budget utilization rate
Our review of Article 3, 3.2 of the financing agreement between KfW and the
Government of Uganda, revealed that KfW has a right to refuse to make
disbursements towards the project after 31st December 2017.
A comparison between the planned and the actual funds utilization for the financial
year 2012/2013 showed that the project was behind schedule in implementation
of some activities. A low absorption capacity rate could lead to the project not
meeting its set objectives in the Common Partnership Terms Agreement (CPTA), in
the stipulated time frame. Table below refers;
Description Budget for the
year ended 30
June 2013-
Euros
Actual utilization
for the year
ended 30 June
2013-Euros
Budget
utilization as a
percentage
Direct
disbursements
made 3,934,049 2,065,282 52%
686
Total Uses of Funds 7,134,049 4,205,489 59%
Management acknowledged the slow progress of the project but attributed it to
the delays in attaining the initial/prerequisite conditions for disbursement like the
development and approval of the operating manual, development of the
implementation/works packaging strategy and its consequent approval.
I advised the project management to hasten the implementation of various project
activities in order to meet the set project targets and objectives.
54.6 JOINT WATER AND SANITATION SECTOR PROGRAMME SUPPORT
(JWSSPS)- WATER AND SANITATION WATER DEVELOPMENT FACILIY
EAST
a) Compliance with Project Agreement, Government Regulations and
Operations Guidelines and Internal Controls
i. Information System Security and Disaster Preparedness
Audit noted that the project lacked an external hard drive for backing up sensitive
finance and procurement information. Also noted was that all the IBF grant
information was saved on the hard drives of the computers which are kept at the
office premises, hence the project risks losing all project information in case of
computer damage, fire outbreaks, theft or computer crash. Furthermore, there
was no risk management plan (disaster preparedness) to ensure early risk
identified and to sufficiently manage risks in all the project activities.
Management regretted the oversight and promised to initiate the process of
acquiring external hard drives and start the process of risk identification as a
prelude to establishment of a risk management plan.
I advised management to hasten the;
Acquisition of hard drives for the accounts and procurement department to
enable regular data back-up which should be kept offsite to facilitate
information restoration in case of damage or loss of the computers.
687
Creation of risk awareness so that potential risks at the facility are ably
identified, assessed and mitigation measures put in place.
ii. Internal Audit Function
It is expected that quarterly internal audit reviews are undertaken for the facility.
Audit however was availed only one report, implying that for the other three (3)
quarters, no internal audit review was undertaken, signifying a weak internal
review function thus increasing risk of non-compliance with policies and
agreement provisions. The project‟s internal control systems are weakened under
the circumstances. Management in its response acknowledged lack of an audit
function in the facility to complement the Ministry‟s internal audit.
I advised the facility management to lobby for the creation of an Internal Auditor
position so as to strengthen the control environment at the facility.
iii. Human Resource Capacity Development
The project injects a lot of funds for implementation of activities and yet there
were non-finance personnel involved in the implementation. Audit noted that the
said personnel were neither conversant with financial management nor trained.
There was therefore a training gap. Management acknowledged the shortcoming
and stated that it was arranging to have the non-finance project staff trained in
financial management.
I advised management, in consultation with the relevant stakeholders, to hasten
to arrange the training so that project funds are well managed during project
implementation.
iv. Accounting Controls
Audit noted that same cheques were being used to settle several payments. Cases
in point were cheque numbers 763 and 777, which were used to pay out funds for
10 and 12 payment vouchers respectively, hence complicating filing based on
cheque numbers.
688
Secondly, there were instances of delayed implementation of activities after the
funds had been advanced to staff. For example funds released on 25th April 2014
for surveying the additional distribution line of Kaliro Town Water Supply System,
were utilised in the period 2nd to 9th June 2014. The funds are susceptible to
misuse and/or teaming and lading.
Management acknowledged the anomaly and promised to use one cheque for
each payment or to provide a comprehensive schedule of payments in instances
where one cheque has been used to pay various payments.
I advised management to ensure that;
Cheques are used for each individual payment relating to specific planned
activity to facilitate record filing and review by management.
Funds are requisitioned by the implementing staff after the necessary
preparations have been undertaken for the execution of the project activity.
v. Use and Management of Vehicle
At the time of the audit, it was noted that the vehicle journey log book system was
in place, however, the one for Vehicle No. UG 1894S was not counter signed by
the officers who made the trips, implying non-compliance with the Operation
manual requirement under section E.4 Vehicle operations and management (E.4.4
Vehicle records). Management regretted the omission of the procedural
requirement but indicated that the signing of the vehicle log books was always
done by both drivers and officers.
I have advised management to ensure that the procedural requirement is adhered
to so as to facilitate tracking and ease the general management of vehicles.
b) General Standard of Construction Works and accountability
i. Poor Quality Ecosan Toilet Construction Works
During the inspection of the sampled Construction Works for 2013/14, audit noted
satisfactory quality of works by the contractors, with the exception of works done
by a local engineering firm at a cost of UGX.43,641,000, on institutional toilets at
689
Kibuku Primary School, where low quality materials were used for doors and
roofing. The structure had no ring beam, the finishing and works on the walkway
stairs were poorly done. Also noted was lack of facial boards, the poor quality
timber used for roofing, none galvanised low gauge iron sheets and the peeling off
of rough cast towards the roof. Picture refers.
Picture showing the poor quality works of the Institutional Ecosan
Toilet (FY 2013/14) at Kibuku Primary School in Kibuku Town
Council
Audit noted that the contracted firm signed a contract agreement in January 2014
to construct eight (8) Institutional Ecosan Toilets at an overall cost of
UGX.349,128,010; and works in seven (7) of the sites was in initial stages. Given
the poor quality work noted in Kibuku Primary School, there was a likelihood of the
contractor replicating the same in the other 7 sites.
Management stated that the contractor had been notified of the defects and
corrective action is being taken.
I have advised management to ensure that the construction works are closely
supervised by the WSDF-E contract manager to ensure implementation of quality
works in all the facility sites.
ii. Inappropriate and Insufficient Expenditure Accountabilities
690
Audit noted that UGX.19,417,500 relating to software was unaccounted by the
project staff, contrary to the Operation manual section E.1.4, requiring staff
advances to be accounted for and retired within 60 days. Further noted were
inadequacies in the activity reports, payment sheets and attendance lists that had
been attached as part of the accountabilities.
Management in its response stated that the concerned officers had been engaged
to account for the funds and that the accountabilities were in place. On the issue
of inadequacies in the accountability documents, management undertook to
address the anomalies in the subsequent period.
I advised management to;
Ensure adequate follow-up on the officers who do not timely furnish the
necessary accountabilities after the implementation of facility activities.
Develop a formal system of communicating to staff who delay to account for
funds advanced within the stipulated 30 days period and administrative
sanctions taken on the non-responsive officers.
Avoid advancing more funds to staff who have not accounted for previous
funds.
Ensure completeness and clarity of accountability documents for ease of audit
trail and for proper stewardship.
54.7 LAKE VICTORIA ENVIRONMENT MANAGEMENT PROJECT II
a) Project Implementing Partners
The management of LVEMP signed memoranda of understanding (MoUs) with two
Ministries of Agriculture Animal Industries and Fisheries [MAAIF], Works and
Transport) in August 2011, 9 districts (Mubende, Masaka, Kalangala, Namayingo,
Mityana, Gomba, Rakai, Mpigi and Kalungu) in April 2012, and 4 other
organizations (National Water and Sewerage Corporation, NARO-Kawanda,
Makerere University and NaFIRRI) in August 2011 to implement specific project
activities.
Documents relating to the Implementing Partners (IPs) however revealed that all
the signed MoUs did not specify the amount of money each entity was supposed
691
to receive and the timing of remittances. From July 2012 to April 2014, the two
ministries and the four other organizations had not received any project funding
and the districts on the other hand took 24 months (ie April 2012 to April 2014) to
receive funding. This was a prolonged delay for a project whose initial
implementation period was from 29th Oct 2009 to 30th June 2013. As a result of
such delays the project was extended for two years up to 30th June 2015.
Management attributed the delays to the long lead time from signing of MoUs to
disbursement of funds, as a number of processes had to be completed before
disbursement.
Article II and III of the signed MoUs requires the IPs to prepare work plans and
submit to the National Coordination Office for approval. Although the work plans
were prepared and submitted, audit was not provided with the minutes for the
meetings in which they were approved. I therefore cannot rule out the use of non-
approved work plans. Although management indicated during exit meeting that
the documents were available, they were not provided for verification.
A review of work plans and remittances to the IPs revealed disparities ranging
from IPs getting more funds than had been planned, while some that had not
been planned for received funding. Management did not provide evidence to
confirm that the work plans were amended.
Although management attributed the variances to the fact that funds for the
subprojects were budgeted under the respective implementing partner overseeing
the implementation of subprojects in the districts, no documentary evidence was
availed in support of that explanation.
I have advised the project coordinator to develop a new implementation plan, fast
track it and closely monitor its implementation so as to be able to meet the new
deadline of 30th June 2015.
b) Low absorption of funds by the Implementing Partners (IPs)
The project, which started on 29th Oct 2009 was supposed to close on 30th June
2013, however due to the delayed implementation of the agreed activities the
project was extended for two more years from 1st July 2013 to 30th June 2015.
692
Despite the extension, low absorption of funds by IPs was noted, which casts
doubt on whether all the planned activities would have been implemented by the
end of the extended period. A total of UGX.3,880,599,296 was released to the IPs
but only UGX.439,868,485 (11%) had been utilized by the end of the financial
year, leaving a balance of UGX.3,533,295,929 (89%) un-utilized. Table refers. I
further noted that by the time of audit (September 2014), all the un-spent
balances had not been accounted for.
Agency Voucher No. /
Disbursement
date
Amount
Disbursed
Amount
Spent
Unspent
balance at
30/06/2014
%
Perform
ance
Ministry of
Works
875/February 14 80,000,000 0 80,000,000 0%
Ministry of
Agriculture
876/February 14 404,800,000 158,100,754 246,699,246 39%
NARO –
Kawanda
877/February 14 127,100,000 12,735,231 114,364,769 10%
NWSC 878/February 14 69,900,000 0 162,465,118 0%
Makerere
University
879/February 14 87,300,000 86,449,350 850,650 99%
NaFIRRI 944/April 14 304,000,000 182,583,150 121,416,850 60%
Local
Governments
May –June 14 2,807,499,296
0 2,807,499,296
0%
Total 3,880,599,296 439,868,485 3,533,295,929
As a result of low absorption, most of the planned activities for the year under
review were not implemented and is likely to result in another request for project
extension. Consequently, this lowers Uganda‟s chances of benefitting from the
second project phase (APL3 (FY13-FY18), which is already overdue.
Management attributed the delay in disbursement of funds to the delay by the
Districts to open up LVEMP designated bank accounts and also the delay by some
implementing partners to submit progress reports and accountabilities.
I have advised the Project Coordinator to enhance planning, monitoring and
reporting systems with the view of ensuring that all planned activities are carried
out within the stipulated time frames.
693
c) Unaccounted for funds
i. Personal Advances
UGX.30,758,200 paid out for various activities remained unaccounted for, contrary
to Chapter 1V section 217 of the Treasury Accounting Instructions (TAI) 2003,
which requires public officers to account for funds advanced to them within 60
days. This was caused by the laxity of management to adequately enforce the
internal controls relating to accountability of advances.
I have advised management to recover the funds from the concerned officers.
ii. Project counterpart fund Account
Section 4.1.2(IV) of the Financial Management Manual (FMM) required the project
to operate a separate account in Bank of Uganda for the purposes of receiving and
managing the government‟s counterpart funds. Contrary to this, it was noted that
the project used one operational account for both donor and counterpart funding,
resulting in co-mingling of funds.
This may result in the use of donor funds to pay for disallowed expenses, improper
accountability and misstatement of financial statements. This arose due to laxity of
the project management. Management acknowledged the anomaly and promised
to take corrective action by ensuring that a separate account is opened.
I await management‟s action on this matter.
d) Human Resource Management
i. Annual Leave
Section C-a (2) and section C-b (1 & 5) of the Uganda Public Service Standing
Orders, Jan 2010, stipulate that annual leave is a right applicable to public officers
employed on full time basis and when due, should be obligatory. A review of the
employee personal files revealed that some officers had not taken leave, right
from time of recruitment. This was attributed to management‟s failure to prepare
a leave roaster and to encourage officers to go on leave. Although management in
its response stated that a leave roster was in place, it was however not provided
for audit verification.
694
I have advised management to always prepare annual leave roasters and to
encourage officers go for leave.
ii. Incomplete Personal Files
A review of staff personal files revealed lack of academic papers and appraisal
forms, contrary to section (P-d) sub sections 4 and 5 of the Uganda Public Service
Standing Orders, Jan 2010, requiring all documents which affect the official record
of a public officer to be properly kept.
This is an indication of poor record keeping by the human resources department
(HRD). In the absence of these records, the competences/abilities and
performance gaps cannot be determined and thus the appraisal of the HR is made
cumbersome.
Although management attributed the anomaly to the centralization of the main
staff files at the Ministry‟s Headquarter, by the time of this report, the files had not
been updated.
I advised management to always update public officer‟s personal files for proper
human resource management.
e) Motor Vehicle Records
A review of the asset‟s register revealed that the project owned a number of
vehicles however, contrary to paragraph 818 of the TAI, Part 2 (public stores), it
did not maintain log books or operating records for eleven motor vehicles. In the
circumstances, it was not possible to ascertain whether the vehicles were properly
maintained and/or carrying out project activities.
Management explained that the vehicles in question were being used by the
implementing partners and promised to urge them to maintain logbooks.
I advised the project management to always maintain log books or operating
records to ease the management of the vehicle fleet.
695
54.8 JOINT PARTHNERSHIP FUND
a) Accounts receivable
Review of note 4.8 revealed that a total amount of UGX.120,438,000 relating to
sundry debtors had been outstanding since the previous year without any efforts
at recovery. Included in the amount is UGX.52,188,892 relating to withholding tax
paid in error, which URA advised the project in 2011 to deduct from subsequent
remittances, an offer the Ministry has not adequately taken advantage of. There
is a risk of loss of funds under sundry debtors.
The accounting officer indicated that instructions had been given to the accounts
department to follow up the matter.
I wait for the outcome of management action in this regard. Meanwhile,
management is advised to take up the offer of offsetting WHT remittances from
subsequent payments to URA.
b) Under absorption of component funds
The JPF components received a total funding of UGX 17,365,514,880 however
only UGX 10,818,999,000 was utilized resulting into under absorption of UGX
6,546,515,880. The table below refers:
Component Amount received Expenditure Variance % variance
Rural water 11,100,000,000 12,420,206,000 -1,320,206,000 -11.9
Water for production 3,170,350,000 2,914,000 3,167,436,000 99.9
Water resource management
2,463,000,000 4,543,280,000 -2,080,280,000 -84.5
Regulation unit 500,000,000 542,522,000 -42,522,000 -8.5
Climate change 1,000,000,000 305,901,000 694,099,000 69.4
696
Component Amount received Expenditure Variance % variance
Sector programme
support and PMS
6,955,000,000 4,750,000,000 2,205,000,000 31.7
Urban water supply
and sanitation
component
3,900,000,002 1,931,485,000 1,968,515,002 50.5
Water management zones
3,791,508,880 1,786,806,000 2,004,702,880 52.9
Water and sanitation
development facility-
North
11,560,000,000 8,644,370,000 2,915,630,000 25.2
Improved hygiene and
sanitation
1,600,006,000 307,361,000 1,292,645,000 80.8
Environment and natural
resources
414,000,000 80,462,000 333,538,000 80.6
Total 17,365,514,880 10,818,999,000 6,546,515,880 37.7
Management attributed low absorption of funds to the delayed signing of JPF
phase II agreement and operationalization of the new accounts for phase II that
only became possible 6 months after the start of the Financial Year.
Non-implementation of planned activities is likely to hinder the project from
achieving its overall objective of “providing sustainable safe water supply and
sanitation facilities based on management responsibility and ownership by the
users within reach of 77% by the year 2015 with 90% effective use and
functionality of services”.
I advised the Accounting Officer to institute adequate measures that will ensure
timely implementation of planned project activities to avoid future extensions.
c) Un-authorized excess expenditure
Section 4.6 of the JPF III operational manual permits the project management to
make budget variations of up to a maximum 20% (plus or minus) on every
component‟s expenditure budget line items.
Audit however noted that under Rural Water component, a total amount of UGX.
1,320,206,000 was spent in excess of the budgeted line items amount of
697
UGX.11,100,000,000. Included in the amount of excess expenditure among others
was UGX.414,172,440 (92.04%) spent above the initial budget of 450,000,000
under procurement of vehicles budget line item.
On the other had a total sum of UGX 2,080,280,000 (99.9%) was incurred above
the line item budget allocation of UGX.2,463,000,000 under Regulation Unit
component without obtaining necessary approvals.
In the management‟s response the Accounting Officer attributed spending above
the approved budget to changes in the market price, failure to realize
Government‟s contribution and need to give extra training and capacity building
support to the newly created districts. The Accounting Officer further explained
that the anticipated mid-year budget revision to re-align component budgets/work
plans did not take place as planned.
Incurring funds over and above the approved budget without obtaining necessary
authorisation does not only contravene budgetary controls but also impacts
negatively on the implementation of activities from which funds were re-allocated.
I advised the Accounting Officer to always operate within the budget allocations
and where it is unavoidable seek for the necessary approvals for budget
variations.
d) Construction of structure & protective house at Jinja pier
Regulation 4 of the PPDA (Force Account Mechanism), 2014, requires the
procuring and disposing entity to use procurement rules and methods in the PPDA
Act, 2003 when procuring equipment and supplies required while undertaking
works using the force account mechanism.
Contrary to the above requirement audit noted that supplies worth
UGX.16,629,500 were procured under force on account arrangement for the
construction of structure & protective house for telemetry hydrological station at
Jinja pier without following force on account procurement procedures. As a result
withholding tax amounting to UGX.997,770 was not deducted from the suppliers
as required by income Tax Act, 2012 (As amended) .
The Accounting Officer explained that materials procured were obtained from the
informal sector which would have been hard to get through the normal
procurement process. This explanation however was not satisfactory as
698
accountability receipts attached show that the materials were procured from hard
ware shops.
I advised the Accounting Officer to remit the taxes involved to Uganda Revenue
Authority and ensure strict adherence to the force on account regulations in
subsequent transactions of similar nature.
e) Non deduction of WHT from Payment of Contractors
Section 119 (1) of the Income Tax Act, 2011 requires any government entity
paying for the supply of goods or services exceeding one million shillings, to
deduct 6% of the amount paid, as withholding tax and remit it to the tax
authority. Contrary to this requirement, UGX.18,566,648 was not withheld from
the payments amounting to UGX.309,44,125 made to various suppliers as shown
below:
Vr No Payee Details Memo Amount WHT
deduc
tible
V16/03 Sumadhura
Tech. Ltd
Construction Certificate No.6
for Adjumani TC
217,679,396 13,060,764
V36/03 Palm Construction
Ltd
Construction Certificate No.6-
Paidha TC.
91,764,729 5,505,884
Total 309,444,125 18,566,648
The facility management attributed the anomaly to the fact that the contractors
presented premature withholding tax exemptions on which the decision not to
deduct the tax was based. However, failure to make the deductions may result in
penalties being levied by the tax body.
I have advised the accounting officer to recover the money from the subsequent
payments to the contractors.
f) Unsupported payables
A sum of UGX.6,793,000 was reported as accounts payable in the statement of
financial position however, the amount was not supported with schedules or
699
claims to justify its authenticity. Unsupported balances may result into payment
for bills without authorised underlying transactions.
In response the Accounting Officer indicated that documents were available
however, they were not submitted for audit verification.
I advised the accounting officer to ensure that adequate documentation
supporting the above figure is submitted for verification.
54.9 NYABYEYA FORESTRY COLLEGE
1. Budget short fall
Out of the appropriated grant of UGX.842,455,000 only UGX.719,973,455 was
released by the Treasury resulting in a shortfall of UGX.122,481,545. As a result
the College was unable to undertake planned activities such as, construction of a
lecture block and renovation of old College buildings.
The accounting officer indicated that recurrent funds for the fourth quarter were
not released and there was no explanation to that effect.
I advised management to follow up the matter with Ministry of Water and
Environment (MWE) and Ministry of Finance, Planning and Economic Development
(MoFPED) to ensure releases are in tandem with appropriated amounts.
2. Extra Budgetary funding
UGX.401,012,695 brought forward from the previous year and UGX.82,203,500
received from African Network for Agroforestry and Natural Resources Education
(ANAFE) were not supported with necessary appropriation and supplementary
estimates respectively. Unauthorised extra budgetary funding contravenes
budgetary controls and undermines the responsibility of the appropriating
authority.
Management indicated that it was an oversight to spend without appropriation and
that ANAFE funds were received unexpectedly when the budgeting process was
already complete.
I advised management to always ensure that extra funds are properly
appropriated by relevant authority.
700
3. Unauthorised reallocation
Review of the budget revealed that UGX.277,973,324 was spent over and above
certain budget line items without obtaining the necessary approval as shown in
the table below.
Expenditure
item
Budget (UGX) Actual (UGX) Variance (UGX) Variance
(%)
Students welfare 238,000,000 271,296,037 33,296,037 14
Allowances 175,000,000 289,150,300 114,150,300 65.2
Vehicle operation &
maintenance
55,000,000 118,300,575 63,300,575 115.1
Staff welfare 25,500,000 38,733,500 13,233,500 51.9
Consumables 60,000,000 87,708,330 27,708,330 46.2
Other goods and
services
93,930,105 118,769,527 24,839,422 26.4
Bank charges 5,500,000 6,945,160 1,445,160 26.3
652,930,105 930,903,429 277,973,324
The un-authorized expenditure was due to management‟s failure to seek for re-
allocation from the finance committee. This practise does not only undermine the
principles of budgeting but also renders the expenditure unauthorized.
Management promised to streamline the budget preparation and implementation
processes.
I have advised the Accounting Officer to ensure that budget procedures and
controls are adhered to.
4. Governance Matters
4.1 College Governing Council
Section 77 (1) of the Universities and Other Tertiary Institutions Act, 2001,
requires any Public Tertiary Institution to establish a Governing Council. Audit
however noted that the College has since July 2011 operated without a Governing
701
Council. Operating without a Governing body is irregular and effects the effective
operation of the College.
The Accounting Officer explained that the names of proposed members of the
Governing Council were forwarded to the Permanent Secretary MWE in September
2014 and the College awaits his response.
I have advised the Accounting Officer to continue pursuing the matter with the
Permanent Secretary of the MWE so that the process of establishing a Governing
Council for the College is concluded without further delay.
4.2 Absence of a Strategic Plan
Nyabyeya Forestry College is mandated to offer practical oriented technical
forestry training by offering diploma and certificate courses. To effectively carry
out its functions; good practice requires that the college prepares a strategic plan
which identifies key objectives, resource mobilisation, coordination of activities and
application of resources among others. However, it was noted that the College has
continued to operate without a strategic plan.
In response, the Accounting Officer explained that the College lacks adequate
financial resources to prepare a strategic plan but further indicated that
management is in close contact with the MWE to ensure that funds are provided
for this activity in the subsequent budget period.
I have advised the Accounting Officer to expedite the consultations and consider
using internally generated revenue to kick-start the process.
4.3 Internal Audit Function
Regulation 27(2) of the Public Finance and Accountability Regulations, 2003 states
that in order to discharge his or her responsibilities, an Accounting Officer should
maintain an effective internal audit function throughout the Ministry, department
or agency or other reporting unit of the Government for which he or she is
responsible.
Audit however noted that, in the year under review, the College lacked an internal
audit function. As a result, management was not provided with oversight over the
accounting, financial and operational Controls.
702
Management indicated that it would liaise with MWE‟s Internal Audit Department
for provision of internal oversight role to the College.
I await the outcome of management‟s liaison with MWE.
5. Staffing Gaps
Out of the College establishment of one hundred seven (107) staff, only 20
positions (19%) were filled, leaving 87 vacancies (81%). Notable among the
unfilled positions were the posts of Senior Lecturers, Lecturers and Assistant
Lecturers.
It is evident that with this level of staffing, the students‟ training needs may not be
satisfactorily met, which impedes on the attainment of the College‟s set objectives.
The Accounting Officer explained that qualified staff keep leaving the College due
to low remuneration and that the staff shortage was reported to MWE.
I advised management to liaise with relevant stakeholders to improve the working
environment of the staff.
6. Failure to bank Revenue
Paragraph 339 of the Treasury Accounting Instructions, 2003 requires all
government revenue collected to be banked intact on the same day of collection
or the day following that of collection or the next banking day. Contrary to the
above, audit noted that the College failed to bank UGX.34,019,872 internally
collected from the Sawmill and Guest House. This exposes the funds to risk of
misappropriation.
The accounting officer attributed the anomaly to emergencies that come up when
one of the principal signatories is not at the duty station. Management further
indicated that they have initiated the imprest system.
I advised management to operationalize the accountable imprest system so as to
meet the College cash requirement in a transparent manner and ensure that
revenue collected is banked intact.
7. Non-submission of monthly Procurement Reports to PPDAA
703
Paragraph 20 (1) of PPDA regulations, 2014 requires a procuring and disposing
entity to submit to the Authority, by the fifteenth day of the following month, a
report on the procurement activities undertaken by the procuring and disposing
entity in the month. On contrary, procurements worth UGX.777,354,347
undertaken by management during the year were not reported to PPDA.
In response, management indicated that the institution lacked substantive
procurement staff and only a procurement assistant (Trainee) had been recruited
to perform procurement activities.
I advised management to liaise with MWE to ensure that the College recruits a
procurement officer who will be charged with the duty of ensuring that
procurement reports are prepared monthly and submitted to PPDA
54.10 WATER MANAGEMENT AND DEVELOPMENT PROJECT
a) Low funds absorption
During the year under review the project received USD.3,660,353 for the
implementation of the planned activities, however only USD.690,457.85 (18.9%)
was utilized (absorbed) leaving a balance of USD.2,969,895.15 (81.1%) unutilized.
This implies that the activities for which the funds were provided were not fully
implemented and this distorts the project implementation schedule and may result
in requests for project extension, which is not only costly but also affects future
rating of the country‟s similar projects by the World Bank.
Management acknowledged that there was unrealistic (over-ambitious) budgeting
for the first year of implementation which did not adequately take into account the
actual duration of the respective procurements for supply of goods, and
consultancy services. Therefore, the under-expenditures arose because most of
the planned procurements were still not finalized during the year.
I have advised management to revisit project implementation strategies to ensure
that funded activities are implemented on time, and all unspent funds for the year
under review are absorbed in the subsequent period.
704
b) Excess Expenditure
The Ministry of water and Environment prepared and submitted the project work
plan for the financial year under review to World Bank and was duly approved.
Best practice requires management to implement the agreed work plan activities
in accordance with the activity ceilings.
Review of the project work plan however, revealed that management budgeted to
spend USD.353,992 on certain specific activities but instead spent
USD.570,573.83, hence creating an excess expenditure of USD.216,581.83
(61.2%). No evidence for approval of the excess expenditure was provided. There
is a risk of the funders demanding for a refund of money spent over and above
the budgets.
Management explained that over expenditure on the specific budget lines was as a
result of under estimating the amounts that would be spent on contracts for goods
and services at the time the work plan was made, in October 2013. However, the
contracts for the goods and services to which the expenditures relate were signed
in February 2014 after getting the World Bank “No Objections.”
I have advised management to obtain retrospective approval of the excess
expenditure from the funders to avoid future penalties.
c) Late Submission of Financial Statements
Water Management and Development Project is managed following GoU financial
management and accounting procedures. Paragraph 441 of the Treasury
Accounting Instruction, 2003 requires the Accounting Officer to submit the
financial statements within 3 months after the end of the financial year, to the
Minister and the Auditor General, with a copy to the Accountant General.
The project management however did not submit the financial statements, within
the stipulated time, as the financial statements were submitted on 4th December
2014 (5 months after the statutory deadline).
I have advised the Accounting Officer to ensure that financial statements are
prepared and submitted in time for audit and for other purposes.
705
54.11 SECOND NATIONAL COMMUNICATION PROJECT
a) Under absorption of funds
Out of the budget of USD 317,600, for the Second National Communication
Project for the period January 2013 to June 2014 only USD.144,423.04 was
utilised by 30th June 2014 resulting into under absorption of USD.173,178. It was
further noted that USD.168,408.54 was withheld by donors pending submission
and approval of the first draft report on climate change adaptation. Among the
activities that were not fully implemented were: strengthening of the National
capacities on climate change, training of staff adaptation of international practices,
establishment of a website and collection of baseline data.
Management attributed partial implementation of agreed activities to delayed
approval of the draft climate change report by the funders, a requirement
necessary for execution of the remaining activities. Management further indicated
that UNEP remitted the remaining funds in July 2014 and January 2015 to
implement the remaining activities.
There is a risk that untimely implementation of the project activities may affect
future project funding arrangements.
I advised the accounting officer to expedite the implementation of the pending
activities and in future ensure that adequate monitoring mechanisms are put in
place to allow timely completion of agreed project activities.
55.0 MINISTRY OF TRADE, INDUSTRY AND COOPERATIVES
a) Mischarges-UGX.592,962,823
The Parliament of Uganda appropriates funds in accordance with the needs of the
country and this appropriation is implemented through the budget in which funds
706
are tagged to particular activities and outputs using account codes and MTEF
codes. A review of the Ministry of Trade, Industry and Cooperatives expenditures
revealed that the entity charged wrong expenditure codes to a tune of
UGX.592,962,823. This constituted 4% of total expenditure for the Ministry. This
practice undermines the importance of the budgeting process as well as the
intentions of the appropriating authority and leads to financial misreporting.
I advised management to streamline the budget process to ensure that sufficient
funds are allocated to each account. Authority should be sought for any
reallocations.
b) Irregular payment of monthly consolidated allowances -
UGX.483,678,941
It was observed that the Ministry paid UGX.483,678,941 to staff as entitled
monthly allowances in form of night subsistence allowance ranging from two to
three days and lunch for the various categories of staff. This allowance paid in
form of night subsistence was paid irregularly because it was not supported with
any administrative circulars/standing order instructions approving it from Ministry
of Public Service.
Management explained that the payments were a composition of field trip
allowances based on departmental work plans tagged to activities that the Ministry
undertook during the year. I explained to management that staffs in U8 are office
support cadres and are not field based. I also explained that there are no standard
field days undertaken monthly by staff. Where the need arises, subsistence
allowances are requisitioned and paid separately.
I advised management to liaise with the Ministry of Public Service to have the
monthly allowance regularized or work within the regulations and pay for
approved allowances such as mileage.
c) Unaccounted for Funds
A review of the expenditure records for the Ministry revealed that funds worth
UGX.51,338,990 were spent on various activities but lacked accountability
707
documents such as bills, evidence of travels, minutes of meetings, attendance
lists, boarding passes and activity reports. Details are as below;
S/N Description Amount (UGX)
1 Advances to personal accounts 8,194,000
2 Travel abroad 26,400,000
3 Temporary advances 16,744,990
Total 51,338,990
In this regard, I was unable to confirm whether the amount involved was applied
for the intended purposes.
I advised management to enforce recovery measures from responsible officers.
d) Unsupported utility payments
It was noted that several transactions worth UGX.163,771,216 made with utility
organizations and other service providers were not supported with adequate
documentation to evidence the accuracy and completeness of the amounts paid to
the companies i.e. consumption statements and receipts.
Management explained that they had requested the service providers to avail the
documentation.
I await management‟s efforts on the matter failure of which recovery measures
should be instituted.
e) Contributions to International Organizations
a) Transfers to World Trade Organisation-UGX.172,765,620
Government of Uganda is a member and participates in the proceedings of World
Trade Organisation Ministerial Conferences which requires the country to make an
annual contribution to the World Trade Organisation budget. A statement of
708
account for the Ministry indicated that Swiss Francs 40,803 was outstanding for
the year 2012 while Swiss francs 43,010 was outstanding for the year 2013.
During the year, the Ministry made a payment of UGX.172,765,620 as annual
contribution to WTO which was acknowledged with a receipt of Swiss francs
20,000 leaving a balance of Swiss francs 63,811 outstanding as at October 2013.
However some issues were noted as below;
Delays in remittance of the Contribution (two years) impacts negatively on the
image of the nation.
The contribution for the year 2014 was not paid by the time of audit.
Management explained that they indeed acknowledge the negative impact of the
delays in remittance and attributed the problem to Ministry of Finance, Planning
and Economic Development (MoFPED) inability to release funds on the budget
line.
I advised management to liaise with the MoFPED and ensure that the contributions
are prioritised and paid.
b) Contributions to the regular COMESA budget
The Ministry paid a total of UGX.2,536,957,800 USD.975,754 to settle arrears of
contributions for 2012 and 2013. However the following issues were observed;
Out of the arrears paid, there is a component of interest on arrears of COMESA
Dollars 1,281.30 COMESA Dollars accumulated as at 2nd May, 2013. The
interest component incurred could have been avoided had the management
complied with Section 166(6) of COMESA. This is considered as nugatory
payment.
Delays in remittance of the Contribution (two years) impacts negatively on the
image of the nation.
The contribution for the year 2014 was not paid by the time of writing this
report.
Management explained that though the funds had been budgeted for, it was
treated by MoFPED as unfunded priority and the funds were released under a
supplementary budget and by then it had incurred interest. Management further
709
explained that funds for the year 2014 were being processed through a
supplementary budget that was before Parliament at the time of writing this
report.
I advised management to liaise with the MoFPED and ensure that the contributions
are prioritised for the Ministry releases to avoid nugatory payments in form of
interest.
f) Review of procurements
A sample of procurements undertaken by the entity were reviewed and the
following were noted;
a) Un implemented activities in the procurement plan
A review of the procurement plan and the procurements undertaken revealed that
nine procurements worth UGX.1,866,080,000 were not undertaken during the year
as planned. Failure to undertake all the planned procurements could have affected
the operations of the Ministry. The needs of the user departments were not met
since the procurements were not fulfilled.
Management explained that procurements that were not undertaken due to failure
by the MoFPED to release funds for their implementation.
I advised management to liaise with the MoFPED and ensure that budgeted funds
are promptly released and utilized as planned.
b) Un supported procurement
Section 56(1) of PPDA Act 2003 requires a PDE to maintain detailed records of all
proceedings, preserve and safe guard all relevant documents it issues and
receives.
During the year, a sum of UGX.45,900,000 was spent on procurement of air
ticketing services, however the procurement file with full documentation
confirming that the procurement procedures and regulations were followed in
obtaining the services was not provided for review. This casts doubt as to whether
the PPDA regulations were adhered to.
710
I advised Management to avail the file for confirmation of adherence to
regulations.
g) Inspections of stores management
An inspection of the stores revealed that the store is not ventilated or air-
conditioned to make it environmentally usable. Exposure of the store keeper to
such conditions is not only a health risk but may also affect his efficiency. Further,
damage or deterioration of the inventories due to dumpiness may not be ruled
out.
Management explained that the Ministry has a very small storeroom which is
poorly ventilated but that the storekeeper had been allocated accommodation in a
safe working environment as his alternative office.
I advised management to consider relocating the stores to a more conducive
environment.
h) DISTRICT COMMERCIAL OFFICERS SERVICES SUPPORT (DICOSS) – 31ST
DECEMBER 13
a) Compliance with Financing Agreement Provisions and GoU
Financial Regulations
A review was carried out on the project compliance with the credit agreement
provisions and GoU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and applied
GoU regulations except in the following matter:
i. Unapproved addendum
The project was approved on 7th June, 2011 and was to expire on 31st December
2013. Any extension of the duration of the project was subject to the beneficiary
writing a request with supporting justifications to UNOPS at least three (3) months
before the memorandum ends for Enhanced Integrated Framework (EIF) board
approval. The project management through an addendum No.1 to DICOSS
memorandum of implementation dated 4th April 2013 sought for an amendment
711
extending the contractual period. This period has since expired and the project
has continued to operate without the requisite approval.
Management explained that Government had contracted UNOPS on the financing
of the project and an amendment had been sought to extend the operational
period to December 2014.
I urged management to expedite the approval process and have the activities
implemented on time.
b) General Standard of Accounting and Internal Control
i. Unaccounted for procurements for Districts
A total of USD.654,630 was transferred to UNDP account for the procurement and
delivery of furniture and equipment by 31st August 2012. The procurement
included 81 office desks, 81 chairs, 208 chairs for round tables, 52 book shelves,
26 safes, 26 round tables, 300 notice boards, 79 desk computers, 28 laptops, 26
printers, 26 scanners, 26 photocopiers, 25 mobile phones, 1 pick-up double cabin,
51 motor cycles and 79 UPSs.
However, it was noted that the procurement file together with the accountability in
form of delivery notes, invoices, and receipts were not submitted to the project
management. In addition, information on the balances of funds as stipulated in
the Memorandum was not availed. I was therefore unable to verify whether all the
items were procured for the funds advanced.
Management explained that the donors preferred this particular procurement to be
handled by UNDP.
I advised management to liaise with UNDP with a view of retrieving the
accountabilities for audit verification.
ii. Refurbishment and repair of District Commercial Offices
According to the records availed, the funders were to refurbish and repair District
Commercial Offices in the 23 districts country wide out of the 25 implementing
districts. This expenditure was valued at USD 104,043. According to the records,
712
the procurement of contractors was the responsibility of the respective districts
and work was to start at the end of December 2012. At the close of 2013, USD
106,185 had been paid out to various contractors. This resulted in unexplained
overpayment of USD 2,142. I was also not availed the procurement files to
ascertain how the procurement was undertaken and the extent of refurbishing and
repair of the district offices.
Management explained that procurement of contractors was a responsibility of
Districts and hence the documentation in lieu of the procurements remained with
the Districts.
I advised management to liaise with the beneficiary Districts and have the original
documents submitted to provide me an assurance that the refurbishment and
repairs were actually undertaken.
c) Status of Project Implementation
i. Low absorption of project funds
According to the Memorandum of Understanding, a total of US $ 2,232,311 should
have been received by 31st December 2013 however only US $ 873,540 was
received leaving a balance of US $ 1,358,772. Various activities remained
unimplemented as a result implying that only 39% of the projected funds were
absorbed. For instance, funding of the items listed below was not realised at all:
Activity Amount Budgeted (UGX)
Funding of District work plans 625,000,000
Radio programs 165,000,000
Insurance 49,000,000
Compensation and motivation
allowance
243,000,000
The failure to fund the activities as planned hinders the project from achieving its
intended objectives.
713
Management explained that the low absorption was occasioned by delay in
recruitment of project implementation team and delayed procurements.
I urged management of the project to fast track the activities to enable
achievement of project objectives.
i) SECOND TRADE CAPACITY ENHANCEMENT (TRACE) PROJECT 31ST DEC
2013
a) Compliance with Financing Agreement Provisions and GoU
Financial Regulations
A review was carried out on the project compliance with the credit agreement
provisions and GoU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and applied
GoU regulations.
b) General Standard of Accounting and Internal Control
A review of the system of accounting and internal control was carried out. It was
noted that management had put in place measures to ensure proper
accountability for the project funds.
c) Status of Project Implementation
A review of the status of project implementation revealed the following;
i. Project performance
During the year under review, the project budgeted for USD 302,809 and received
only USD 100,000 towards the close of the financial year (October 2013) resulting
into a shortfall of USD 202,209. As at the end of the financial year, USD 63,769
had been spent leaving a balance of USD 36,231 on the account. As a result,
some activities that had been planned were not undertaken. These include among
others procurement of equipment, conducting professional services and
communication and publicity of entity activities to the stakeholders. The intended
objectives may not be realized within the project life time.
714
Management explained that three quarters of the period was operated under no
cost extension and the funds were received in the last quarter. This affected the
absorption capacity.
I urged management of the project to always liaise with the development partners
to ensure that funds are released timely to enable early implementation of the
project activities.
j) QUALITY INFRASTRUCTURE AND STANDARDS PROGRAM (QUISP)
a) Revenue performance
UGX.9,737,388,600 was budgeted to undertake project activities but only
UGX.3,136,178,649 (23%) was received from the development partners leaving a
funding gap of UGX.6,601,209,951. Of the funds received UGX.2,207,960,878 was
spent leaving a balance of UGX.928,217,771 on the project account in the Bank of
Uganda. Failure to realise the total funds budgeted for implies that almost all the
planned activities of the project could not be undertaken. This may result in non-
attainment of the project objectives.
Management explained that the work plan for the financial year was negatively
affected because of the funding suspension from the development partners. The
development partners only released funds for activities that did not require
lengthy procurements and the balance will be disbursed after signing contracts
with service providers.
I urged management to liaise with the development partners and have all the
budgeted funds released and ensure that all funds released are utilised as
planned.
b) Unpaid Creditors
It was observed that a sum of UGX.332,401,737 remained unpaid for works and
services rendered to the project. Failure to clear debts is likely to result into
unforeseen litigations and waste of government funds.
715
Management explained that the PDU office is in the process of arranging for the
payments once the office is satisfied that works were properly undertaken and
delivered.
I advised management to expedite the payment process and have the creditors
cleared.
c) Non-remittance of WHT
It was noted that funds worth UGX.18,823,505 were deducted in form of WHT but
were not remitted to the tax body as required by the law. Non remittance of
statutory deductions may result in payment of penalties which could have been
avoided.
I advised management to remit the outstanding statutory deductions without
delay.
d) Funds not fully utilized as per work plan
UGX.712,198,500 was disbursed by QUISP to UNBS to facilitate the
implementation of various planned activities such as assistance of SMEs in
implementing standards, awareness and publicity, development of harmonization
of standards, training on Technical Barriers to Trade (TBT) on line notification and
for the facilitation of the UNBS 27th meeting of the National TBT/SPS. However,
part of the funds totalling UGX.257,179,644 representing 36% of the total funds
released were not utilized.
Failure to absorb the limited funds available may lead to failure to implement the
activities for which they are meant which results in non-attainment of project
activities.
Management explained that because of the delayed approval of the work plan,
funds were availed to UNBS in April, 2014 which was so short a time to implement
the activities. The planned activities were carried forward in the revised work plan
from July to December, 2014 to ensure that all the activities are implemented and
the funds utilized. The Ministry will further discuss with UNBS management to
ensure adequate manpower is provided to implement QUISP activities.
716
I advised management to liaise with the development partners to ensure that
funds are released are fully utilized as planned.
56.0 MINISTRY OF TOURISM WILDLIFE AND ANTIQUITIES
a) Mischarge of expenditure
The Parliament of Uganda appropriates funds in accordance with the needs of the
country and this appropriation is implemented through the budget in which funds
are tagged to particular activities and outputs using account codes and MTEF
codes. During the year, management of the Ministry of Tourism, Wildlife and
Antiquities charged wrong expenditure codes to a tune of UGX.115,112,418. This
constituted 1.5% of total expenditure for the Ministry. This practice undermines
the importance of the budgeting process as well as the intentions of the
appropriating authority and leads to misleading reporting.
Management explained that these funds were balances of savings made on rent,
consultancies and subscriptions and they could not be technically re-allocated for
funding the emerging needs.
I advised management to streamline the budget process to ensure that sufficient
funds are allocated to each account and budget line codes should be in
accordance with the Government of Uganda chart of accounts for uniformity in
reporting and understanding by users of the statements. Authority should be
sought for any reallocations.
b) Grounded old vehicles
The Ministry has two old vehicles that are no longer in use and have been
grounded for sometime. The vehicles are at a risk of being vandalized as detailed
below;
Vehicle no Type
UG 0190T Nissan Terrano
717
UG 0299T Mitsubishi Pajero
Management explained that the vehicles are adequately secured at Uganda
Museum and the process to have them boarded off is in progress. Management
further explained that vehicle no. UG 0299T has already been inspected by the
chief mechanical engineer and the other is yet to be inspected.
I advised management to expedite the disposal process to have value for money
obtained before total loss in value of the vehicles.
c) Lack of land titles
The Ministry is in charge of a number of museums and historical sites. It was
however noted that the historical sites and museums listed below had no land
titles:
Name Location Size Structures Status
Kapir Ngora 12 acres
Rock art paintings,
foot prints land surveyed
Kakoro Rock
paintings Pallisa 15 acres Rock art paintings land surveyed
Karamoja
Museums Moroto 6 acres Museum building no title
Soroti
Museum Soroti 4 acres
Administration
block land surveyed
Sir Samuel
Fort, Patiko Gulu 10 acres
Monuments,
dilapidated office
and shade no title
Katasiha Fort Hoima 1/2 acres monuments no title
Bigo by a
Mugenyi Ssembabule
334.4
hectares
Monumental Trench
System land surveyed
Ntusi Female
mounds Ssembabule
0.23
hectares
Archaeological
Female mound land surveyed
Ntusi male Ssembabule 0.16 Archaeological male land surveyed
718
Name Location Size Structures Status
mounds hectares mound
Ntusi basin Ssembabule
10.51
hectares
Archaeological
basin and mounds land surveyed
Barlonyo Lira 1/2 acres Monuments land surveyed
Lokudi Gulu 23 acres Monuments land surveyed
Pabbo Camp Amuru 0.75 acres Huts land surveyed
Kabale
Museum Kabale 1 acre
Museum, cultural
village and craft
shop land surveyed
Dufile Moyo 12 acres Monuments no title
Bweyogerere
Capital site Mbarara 5 acres Empty no title
There is a risk that the land may be encroached on by the neighbouring
communities.
Management explained that despite limitation of resources, the program of
acquisition of land titles by the department of museums and monuments is on-
going to ensure that all heritage sites are properly preserved. I advised
management to liaise with Ministry of Finance to fund this activity to enable the
acquisition process concluded.
d) Inadequate staffing
An analysis of the staff establishment and the staff for the Ministry indicated a
staffing gap of 43. Included among these are one position for Director and 5
positions at Assistant Commissioner level. The vacant positions are likely to limit
the ability of the Ministry to effectively deliver on its mandate.
Management explained that due to wage bill limitations, only 7 of the 43 posts
have been cleared for filling by Ministry of Public Service. Management further
explained that they had gone ahead and written to Permanent Secretary/Secretary
719
to the Treasury to consider an increment in the Ministry‟s wage bill so as to fill the
critical positions.
I advised management to keep following up on the matter with Finance and Public
Service and have the situation resolved.
e) Budget performance-Funding gap
The Ministry budgeted to receive UGX.13,612,395,000 for the period under review
but only received UGX.12,309,697,806 resulting into an underfunding of
UGX.1,302,697,194. Included in the underfunding is a sum of UGX.1,050,000,000
for non-resource gross tax and UGX.252,697,000 for taxes on capital purchase
and activities under hotel establishment classification respectively.
A review of the performance report revealed the following issues:
i. Budgeting
Budget estimates though not accurate enough provide a basis for the Ministry
commitment and represents the Ministry‟s understanding of the scope and
expense of what needs to be done. The Ministry budgeted for a total of
UGX.1,300,000,000 for gross tax but only UGX.250,000,000 was released by
Treasury out of which a sum of UGX.147,430,768 was spent reflecting 19%
budget release and 59% release utilization. Allocating funds for activities/expenses
whose likelihood of occurrence is remote provides avenues for diversions as well
as large budgetary slacks which provide for future unfair budgetary variations.
Management explained that the released amount was sufficient for taxes on
capital purchases.
I advised Management to always ensure that reasonable budgetary estimates are
provided.
ii. Unimplemented activities
A review of the budget performance revealed that activities in the table below
were not implemented:
720
Activity/ indicator Planned Actual output
Classification of accommodation
establishments. 200 63
Regional & international meetings. 9 6
Non implementation of planned activities may affect the Ministry in achieving its
short-term and long-term objectives and performance of its mandate.
Management explained that the above unimplemented activities were due to
Ministry of Finance release adjustments which were necessitated by the need to fit
within the revenue performance of Government.
I advised management to continuously liaise with the Ministry of Finance, Planning
and Economic Development for funding and ensure that all activities are
undertaken as planned.
721
LAND SECTOR
57.0 MINISTRY OF LANDS, HOUSING AND URBAN DEVELOPMENT
a) Mischarge of expenditure - UGX.543,519,621
Expenditure worth UGX.543,519,621 was inappropriately charged on budget lines
to fund activities that were not planned without authority. I explained to
management that mischarge of expenditure translates into misrepresentation of
expenditure balances in the financial statements and it also undermines the
purpose for which the funds were appropriated by Parliament.
Management explained that mischarges arose out of necessity because the budget
did not support critical expenditure like payment of entitlements. This called for
sourcing for funds across the board thereby creating imbalances in the budget and
hence the mischarges. However this situation has now been addressed in the
Ministry budget proposal for the year 2014/15.
I advised management to streamline the budget process to ensure that sufficient
funds are allocated to significant account areas and should there be need for
reallocation, authority for the virement should be sought.
b) Funding gap
A review of the budgeted revenue against the actual revenue realized for year
revealed that management had budgeted to receive UGX.17,277,762,153
however; UGX.15,256,559,842 (88.3%) was received, leading to a shortfall of
UGX.2,021,202,311 representing 11.7% of the expected release. I noted that due
to the budget shortfall, some planned activities were not performed and others
were partially undertaken as summarized in the table below:
722
S/N Activities to be achieved Target Status of implementation
No. implemented
%age of implementation
Under Land Administration
And Management
1. Dissemination of national land policy and
implementation guidelines
40 districts Not achieved 0%
2. Registration of land transactions
300,000 transactions
37,878 Registered
13%
Physical Planning And
Urban Development
3. Dissemination of national
housing policy and
guidelines
25 Not achieved 0%
Government Land
Administration.
4. Processing of lease applications
600 leases 309 processed and issued out
52%
Management explained that this was a long standing problem. The Ministry does
not influence Ministry of Finance, Planning and Economic Development (MoFPED)
on release of funds to the Ministry.
I advised management to continue pursuing the matter with the MoFPED to
ensure all the budgeted funds are always released to accomplish the planned
activities.
c) Irregular payment of transport and lunch allowances
Expenditure worth UGX.283,314,333 was paid out to staff during the year as
transport and lunch allowance. However, the basis upon which the allowances
were paid and how the rates were determined could not be ascertained. Besides,
there was no authority from Public Service to allow such payments. In the
circumstances, I could not confirm the regularity of these payments.
Management explained that the allowances were paid as a motivation for the
Ministry staff that are required to work beyond normal working hours.
I advised management to make sure these allowances to staff are regularised by
Ministry of Public Service.
723
d) Staffing gaps- 496 Vacant Posts
Out of 839 approved staffing positions for the Ministry, only 343 (40.9 %)
positions had been filled as at the end of the financial year leaving 486 (59.1%)
unfilled. This position was over the half way mark. With this current staffing gaps,
performance of the Ministry may be affected and may result into failure to achieve
the entity‟s mandate.
Management explained that the filling of vacancies has been done in a phased
manner starting with the six (6) operational Ministry Zonal Offices; however that
notwithstanding all vacancies cannot be filled at once due to limitations of the
budget. The Ministry has so far submitted 109 vacant posts to the Public Service
Commission for filling which include some of the vital posts.
I await the outcome of management efforts.
e) Un-serviceable stores due for disposal
During the review; I noted that some items were kept in store and others kept at
the parking yard without any record or order of arrangement as evidenced by the
photographs below:
Interview with management and inspection of the stores showed that some items
had become unserviceable and are due for disposal as illustrated below;
Items Quantity
1 Computer sets 4
2 Photocopying Machines 3
3 Steel Filing Cabinets 4
724
Items Quantity
4 Swing chairs 3
5 Telephone switchboard 1
6 Used Vehicle Tires of different sizes 40
7 Wooden Chairs 8
I noted that the unserviceable stores had no records and items have overstayed
and continue to lose value. There is a risk that the items in the stores could easily
disappear through theft or negligence without detection.
Management explained that a Board of Survey has been constituted that will guide
the disposal of all unserviceable stores in the Ministry by the close of the financial
year.
I await the outcome of management‟s action.
f) Vehicles due for boarding off
A physical inspection carried out on the Ministry assets revealed that there were
12 vehicles grounded in the Ministry Parking yard as listed below;
Vehicle Registration Number Make.
1 UG 0010L Toyota Land Cruiser
2 UG 0019L JEEPGRAND CHEROKEE
3 UG 0020L JEEPGRAND CHEROKEE
4 UG 0053L NISSAN HARD BODY
5 UG 0025L TOYOTA HILUX
6 UG 0073L ITSUBISH
7 UG 0079L FORD RANGER
8 UG 0034L FORD RANGER
9 UG 0022L NISSAN HARD BODY
10 UG 0032L FORD RANGER
11 UG 0007L TOYOTA LAND CRUISER
12 UG 0072L NISSAN PATROL
The vehicles seemed to have been packed for a long time in the Ministry parking
yard as reflected in the pictures below:
725
Some two pickups ready for disposal packed in the Ministry parking yard.
UG 0019L JEEPGRAND Cherokee
Interview with management revealed that the vehicles became uneconomical to
run because of constant repairs due to old age. Further analysis showed the
following anomalies:
Although the transport officer had written to the responsible officers
recommending the vehicles for boarding off; no action had been taken by
management.
The vehicles were parked in the Ministry parking yard which has continuously
congested the already limited parking space.
Management explained that a Board of Survey has been constituted that will guide
the disposal of all old vehicles in the Ministry by the close of the financial year
2014/15.
I advised management to expedite the disposal process and have the vehicles
disposed off to avoid any eventual deterioration of value due to weather and other
factors.
g) Ministry Zonal Offices
A review of the Ministry staff establishment revealed that the Ministry is supposed
to have 21 zonal offices throughout the country and these were planned to start in
June 2012. However, inspection of the zonal offices carried out in January 2015
revealed that only 6 Zonal offices were established and are operational. These
were Kampala (KCCA building), Wakiso, Mukono, Jinja, Masaka and Mbarara Zonal
offices. Below is a summary of inspection findings:
726
a) Congested offices and corridors
According to the Principal Lands officer in charge of Wakiso zonal office, the Zonal
office had 45 staff members occupying 11 offices. Physical inspection revealed
that the offices were very congested and some staff did not have chairs to use.
The most affected section was the strong room with 5 staff members who had
only one table with two chairs placed in the corridor to the strong room.
According to the hand over report dated 18/08/2014 by the outgoing Principal
Lands Officer, the entire first floor of the building was supposed to be occupied by
the Ministry Zonal Office but it was noted that most of the offices of the first floor
were still occupied by the District staff. I explained to management that the
current state reflects a bad image of the Ministry. Moreover; the congested offices
hinder the smooth progress of work and could seriously affect individual
performance and the Ministry at large.
Management explained that Wakiso zonal office is the largest of the zonal offices
with a total of 160,000 titles hence the heavy human traffic. Works are underway
to control unauthorized access by land agents as an initial measure by creating
access control systems. Management further explained that in the long run, the
Ministry is considering creating another Ministry Zonal Office out of Wakiso either
in Entebbe or Kira to further decongest Wakiso.
The outcome of management‟s effort is awaited.
h) Ownership of Buildings
Century house plot 13/15 Kampala and survey and mapping plot 1-3A, 3B, 3C
Entebbe were the only buildings captured in the assets register. It was observed
that both office buildings were too old, over 50 years and maintenance was not
being done periodically to control wear and tear. It was also observed that
acquisition date of the buildings was not captured in the fixed assets register and
this made it difficult for the audit team to assess the value of the buildings. The
ownership was also not ascertained.
727
Management indicated that some officers were assigned to handle the issues
mentioned. The buildings have not been adequately maintained over a period
of time due to lack of a budget. However the Ministry through USMID project has
commenced on an initiative to renovate part of the buildings in a phased manner.
The outcome of management initiatives is awaited.
i) Zonal offices
a) Arua zonal office
a. Procurement of office furniture
Public procurement and Disposal of assets Act 2003 Section 58, requires that
entities plan its procurements in a rational manner and this is done to guide the
Government expenditure so that the entity acquires what it needs at the right time
given resource constraints Government is faced with.
It was observed that the furniture procured for all zonal offices was done without
plan and were therefore not reconciled to the time line of implementing
operationalization of zonal offices. As a result, the furniture got damaged through
use by the district staff.
I advised management to contact the district offices to make good of the damaged
furniture.
(k) Maintenance of the building
Although this is still a new structure, I noticed that maintenance was not being
done. The strong room was heavily infected by termites that had built ant hills as
a result; some of the files were found with some getting damaged by termites.
Poor maintenance of the building results into quick deterioration. I recommended
that management should direct the District to make routine maintenance as a
condition of occupying the building.
b) Lira Zonal Building
a. Building maintenance
728
The inspection of the building revealed that the building is inadequately
maintained as stated below:
The once white paint is now dirty in most parts of the building both inside and
outside;
The cob webs are a common site inside and outside the building.
The building has water born toilets however; most of these toilets are now out
of use resulting from poor usage. They require major plumbing work.
The compound was found bushy;
The building is also at risk in case of fire outbreak. The fire extinguisher in the
building has service which expired on 1/10/2010.
I advised management to consider renovating and improving the zonal building.
j) LEVERAGING MUNICIPAL INFRASTRUCTURE IMPROVEMENT
INVESTMENT (LMIII) PROJECT – 2012/2013
a) General Standards of Accounting and Internal Control
A review of the system of accounting and internal control was carried out and in
all material respects, the internal control system and measures to ensure proper
accountability for the Grant funds put in place by management was satisfactory.
b) Compliance with Financing Agreement Provisions and GoU
Financial Regulations
A review was carried out on the project compliance with the grant agreement
provisions and GOU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and applied
GOU regulations except in the following matter:
i) Delayed submission of Project Expenditure Report and accounts
It was noted that management did not submit the project expenditure report and
accounts in time to allow me review the report and the accounts yet the Grant
agreement became effective way back in July 2012. Management submitted the
expenditure report one (1) year later after the end of the financial year. Further,
the accounts were submitted 2 years later. The delay affected the audit of the
729
project for the 2012/13 implying that the report could not be prepared and availed
to the various stakeholders at the required time.
I advised management to ensure that the expenditure report is submitted in time
to facilitate timely reporting on the Project financial performance.
c) Status of Project Implementation
i) Delays in concluding the Consultancy on Environmental Impact
assessment and Resettlement Framework
On the 17th January 2011, the Ministry entered into an agreement with a
consulting company to carry out environmental impact assessment and
resettlement framework in the fourteen (14) Municipalities country wide at a price
of US $ 104,621. According to the special conditions of contract, the
commencement date was supposed to be 7 days after the date of the contract
becoming effective and the time period was supposed to be 45 days for the
environmental and social impact assessment and 35 days for the resettlement
frame work while two additional weeks were to cater for the approval of the final
report.
It was noted that the contract for provision of consultancy services was signed in
January 2011 while the grant agreement was signed in July 2012; 18 months
before the LMIII grant agreement came into existence. The final consultancy
report had not been concluded at the time of reporting. I explained to
management that without a report, I could not establish whether the funds were
put to proper use and whether the report will be useful to the users at the end of
the exercise.
Management explained that the World Bank provided US $ 85,000 to pay a
consultant to come up with the Environment & Social Management Framework
under a different management. The consultant quoted US $ 104,000 and informed
the Bank management about the financing gap. The Ministry of Finance was
accordingly required to make a formal request for additional funds however the
Ministry delayed and the Grant closed before the Consultant was fully paid.
Management further explained that when the LMIII Grant came on board, the
730
Consultant‟s balance was included in the LMIII work plan which was okayed by the
funders since it well fit in the LMIII Grant objectives.
I advised management to follow up on the report and ensure that the contents are
still useful and applicable to the users.
k) LEVERAGING MUNICIPAL INFRASTRUCTURE IMPROVEMENT
INVESTMENT (LMIII) PROJECT – 2013/2014
a) General Standards of Accounting and Internal Control
A review of the system of accounting and internal control was carried out and in
all material respects, the internal control system and measures to ensure proper
accountability for the Grant funds put in place by management was satisfactory
except in the following matter;
i. Delays to disburse funds to the Municipal Councils
During the financial year under review, UGX.317,186,100 was remitted to nine
Municipal Councils as indicated in the table below:
Municipality. Voucher Number Amount
Entebbe MC 001052014 35,242,900
Fort Portal MC 002052014 35,242,900
Gulu MC 003052014 35,242,900
Hoima MC 004052014 35,242,900
Lira MC 005052014 35,242,900
Masaka MC 006052014 35,242,900
Moroto MC 007052014 35,242,900
Soroti MC 008052014 35,242,900
Tororo MC 009052014 35,242,900
Total Funds sent 317,186,100
I noted that funds to finance the activities of the Municipal Development Forum
(MDF) for the financial year were remitted on 20th May 2014, one month and 10
days to the end of the financial year although the funders released the second
installment early on the 4th October, 2013. Delays by project management to
disburse funds to Municipal Councils on time impacted negatively on the
731
implementation of the planned activities in municipalities. There is a risk that the
project may be extended leading to extra administrative costs.
Management explained that the delays were occasioned by the delay in concluding
with the work plans by the Municipalities but committed that in future,
disbursement of the project funds to the project beneficiaries will be timely.
Management was advised to always remit the project funds to avoid another
project extension.
b) Compliance with Financing Agreement Provisions and GoU Financial
Regulations
A review was carried out on the project compliance with the grant agreement
provisions and GOU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and applied
GOU regulations.
c) Status of Project Implementation
Inspection of the Municipal Councils.
Inspection of the nine Municipal Councils that benefited from the grant was carried
out and the following were observed;
i. Failure to utilize the disbursed funds
Whereas UGX.317,186,100 was remitted to nine selected Municipal Councils at the
time of inspection, eight (8) of the nine (9) municipalities had not utilized the
funds except Gulu Municipal Council which had utilized just UGX.2,058,500 of the
total funds remitted. The funds utilization status has been summarized in the table
below;
Table: Funds utilization status
Municipality Amount sent Utilized Unutilized
Amount % age of
funds
utilized.
Amount. % age of
funds
unutilized
Entebbe MC 35,242,900 00 00 35,242,900 100%
732
Municipality Amount sent Utilized Unutilized
Amount % age of
funds
utilized.
Amount. % age of
funds
unutilized
Fort Portal MC 35,242,900 00 00 35,242,900 100%
Gulu MC 35,242,900 2,058,500 5.8 33,184,400 94.2
Hoima MC 35,242,900 00 00 35,242,900 100%
Lira MC 35,242,900 00 00 35,242,900 100%
Masaka MC 35,242,900 00 00 35,242,900 100%
Moroto MC 35,242,900 00 00 35,242,900 100%
Soroti MC 35,242,900 00 00 35,242,900 100%
Tororo MC 35,242,900 00 00 35,242,900 100%
Total 317,186,100 315,127,600
Management explained that the Municipal Council funds were sent to their
respective General Funds Account towards the close of the financial year, a period
that was considered to be too short to utilize the funds. It was further indicated
that the funds were sent without guidelines on how to utilize them. I explained to
management that delayed utilization of funds denies citizens timely benefits of the
Grant which could frustrate the purpose for which the grant was accepted.
I advised management to ensure guidelines for the utilization of funds to the
municipal councils are issued immediately to avoid further delays.
ii. Memorandum of Understanding between LMIII Project &
Municipal Councils
During the review, it was noted that the disbursement of funds to other Agencies
(municipal councils) was not supported by a memorandum of understanding
(MOU) between the Municipal Councils and the Project management. I explained
to management that without the MoU, it may not be easy to enforce binding
obligations on both parties a situation that could pose challenges on effective
implementation of the project activities. Besides, funds could easily get diverted
into non project activities.
In response, management explained that after the Municipalities signing the
Project Participation Agreement under the USMID Program, it was anticipated that
this would suffice because; the intercalations between the Municipal Councils and
733
the MDF‟s were clearly pointed out in the Program Operational Manual to which all
parties are bound.
I advised management to ensure that the MoUs are in place that defines the
obligations of each party for successful implementation of the project activities.
l) TRANSFORMING SETTLEMENTS OF THE URBAN POORIN UGANDA
(TSUPU)
a) Compliance with the Financing Agreement and Government of
Uganda Provisions
A review was carried out on the project compliance with the Grant agreement
provisions and GOU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and applied
GOU regulations.
b) General Standard of Accounting and Internal Control
A review of the project financial management system was carried out and it was
noted that management had instituted adequate controls to manage project
resources except for the following matters;
i. Delayed adoption of National Urban policy (NUP)
A contract for provision of consultancy services to finalize the development of
National Urban Policy was awarded to a consulting firm in October 2012 at a
contract price of USD.442,633. The consultant was required to specifically come
up with:-
15 year strategic Urban Development Plan
Creation of an Urban Indicators Data base and
Preparation of the Information, Education and Communications (IEC)
strategy).
At the time of reporting, the consultant had received all the contract amount.
According to the National Consultant Workshop held in May 2014, the stakeholders
were satisfied with the consultant deliverables. However, it was noted that the
734
policy had not yet been submitted to cabinet for approval and adoption.
Implementation of the Policy is delayed.
Management explained that the NUP draft policy is currently before an editor to
remove the editorial mistakes before submitting to cabinet.
I advised management to expedite the process to ensure the policy is submitted to
Cabinet for approval.
ii. Inspections of Project activities in Municipal Councils
During the year, TSUPU project was implemented in five Municipal Councils of
Kabale, Mbarara, Jinja, Arua and Mbale where funds worth UGX.2,162,487,369
were remitted. As part of the audit, inspection was carried in all the five Municipal
Councils to establish the extent of implementation of project activities. The
following were observed:
KABALE MUNICIPAL COUNCIL
i. Unutilized funds-UGX.413,159,381
During the financial year, the Council received UGX.413,159,381 from the Ministry
for TSUPU activities. The funds were disbursed in two instalment of
UGX.234,787,170 and UGX.178,372,211 on 23/09/2013 and 20/06/2014
respectively.
At the time of inspection (September 2014) all the funds were still held on the
Municipal account. These funds had therefore not been put to use in implementing
planned activities.
Management explained that the delay to utilise the funds arose from late
disbursement of funds from the development partners.
I advised management to always liaise with the financiers for timely release of
funds.
JINJA MUNICIPAL COUNCIL
i. Unutilized funds -UGX.4,481,863
735
Jinja Municipal Council received UGX.491,511,798 for implementation of TSUPU
activities. As at 30th June 2014 UGX.4,481,863 was still held on the Municipal
account. Non utilization of all funds received implies that the intended project
activities were not fully implemented.
Management explained that these funds still on the account were retention for the
CUF projects to cater for the defect period.
I advised management to avoid comingling of TSUPU project funds with other
project funds as this is likely to cause diversions.
MBARARA MUNICIPAL COUNCIL
i. Unutilized funds – UGX.15,553,957
During inspection, it was discovered that the Municipal Council had
UGX.15,553,957 unutilized at the close of the financial year on TSUPU Bank
Account in Crane Bank.
Management explained that the Ministry had formally written to the Town Clerk to
respond to the issue.
I advised management to ensure adequate follow up on the matter to enable
proper accountability.
ARUA MUNICIPAL COUNCIL
i. Delayed release of TSUPU funds from General Fund Bank A/C
The Ministry remitted UGX.423,162,659 to Arua Municipal Council for TSUPU
activities for the financial Year 2013/2014. The funds were remitted in two
instalments of UGX.234,787,170 and UGX.188,375,489. However, I noted that the
last instalment of UGX.188,375,489 was not transferred from the General Funds
Account until 19/07/2014. Delayed release of project funds affected the project
performance during the financial year.
I advised management to ensure that project funds are remitted in time to allow
project implementation of planned activities.
736
57.1 UGANDA SUPPORT TO MUNICIPAL INFRASTRUCTURE DEVELOPMENT
PROGRAM (USMID) PROJECT
1.1 Compliance with the Financing Agreement and Government of
Uganda Provisions
A review was carried out on the project compliance with the credit agreement
provisions and GOU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and applied
GOU regulations fairly except in the following;
1.1.1 Unutilised funds at Project Headquarters
The project received all the budgeted funds expected (UGX.66,542,389,583) but
only UGX.51,874,220,299 (78%) was spent leaving UGX.14,668,169,284 (22%) un
utilized as summarized in the table below:
Expenditure
budget line
allocation
Allocated
funds
Spent
amount
Unutilized
funds
Unutilized
funds as
%age to the
allocated
funds
1 Municipal
Developm
ent Grant
41,826,946,37
7
41,826,946,37
7
Nil 0
2 Municipal
Capacity
Building
6,139,735,248 6,139,735,248 Nil 0
3 MLHUD Capacity
Building
Grant
13,381,200,82
9
3,907,538,673 9,473,662,156 71%
737
4 IFMS Installation
in 12
Municipalit
ies
5,194,507,129 Nil 5,194,507,129 100%
Grand Total 66,542,389,583 51,874,220,299 14,668,169,284 22%
All the funds due to Municipal Councils of UGX.41,826,946,377 and
UGX.6,139,735,248 for Municipal Development Grant (Infrastructure development)
and Municipal Capacity Building respectively, were remitted to the Municipal
Councils. However, it was noted that management did not deliver as expected
under MOLHUD capacity building grant and installation of IFMS.
Failure to implement all the planned activities for year implies underperformance
and could result into failure to attain the project intended objectives in the
scheduled period.
Management explained that generally there was time constraint and the project
had to start late. The loan became effective in September 2014 and initial
disbursement started thereafter.
On procurement of IFMS implementation firm, management procured a service
provider and installation of IFMS in the 12 municipal councils are in the final
stages.
With regard to capacity development programme, management had entered into
agreements with contractors to supply vehicles, furniture and equipment.
I advised management to expedite the procurement processes and have the
implementation kick-started.
738
1.2 General Standard of Accounting and Internal Control
A review of the project financial management system was carried out and it was
observed that management had instituted adequate controls to manage project
resources except for the matter below:
1.2.1 Training Abroad
The project spent US $ 8,814 and UGX.16,930,780 on training of six officers in
South Africa and India.
The following anomalies were noted:
The project had no training guidelines to guide the project staff on training.
Training was therefore done haphazardly.
All the individuals trained were MoLHUD officials and not project staff. It was
not clear under what project budget item the Ministry officials were trained.
The project funds were therefore diverted.
There was no evidence of training needs assessment carried out to confirm
that the individual‟s needs were assessed as necessary and beneficial to both
the individuals trained and the project. There is a possibility that Project funds
could have been spent on non-beneficial trainings.
I advised management to endeavor to put in place a training policy that will guide
the project management and staff in training so as to benefit from the project.
Management should also account for the funds not supported.
1.3 Status of project implementation
A review of the status of project implementation revealed the following:
1.3.1 Unutilized funds remitted to Municipal Councils
An inspection carried in August 2014 of some of the Municipal Councils revealed
the following:
1.3.2 Unutilized funds for capacity building-UGX.4,723,244,616
The project head office remitted a total of UGX.6,139,752,416 to 14 Municipal
Councils. However, it was noted that as at the close of the financial year
739
2013/2014, only UGX.1,416,507,800 (23%) had been utilized implying that
UGX.4,723,244,616 (77%) remained unspent as indicated in the table below:
Municipal Amount released Amount spent
%age spent to the
amount
released
Un spent
bal.
%age of un spent to
the amount
released
Arua 438,553,744 61,977,050 14% 376,576,694 86%
Entebbe 438,553,744 18,835,250 4% 419,718,494 96%
Fort Portal 438,553,744 24,293,244 6% 414,260,500 94%
Gulu 438,553,744 24,665,015 6% 413,888,729 94%
Hoima 438,553,744 209,805,895 48% 228,747,849 52%
Jinja 438,553,744 39,921,493 9% 398,632,251 91%
Kabale 438,553,744 95,716,701 22% 342,837,043 78%
Lira 438,553,744 75,237,743 17% 363,316,001 83%
Masaka 438,553,744 260,814,754 59% 177,738,990 41%
Mbale 438,553,744 29,980,300 7% 408,573,444 93%
Mbarara 438,553,744 134,622,798 31% 303,930,946 69%
Moroto 438,553,744 248,104,708 57% 190,449,036 43%
Soroti 438,553,744 59,462,688 14% 379,091,056 86%
Tororo 438,553,744 133,070,161 30% 305,483,583 70%
Total 6,139,752,416 1,416,507,800 23% 4,723,244,61
6 77%
At the time of inspection, the Municipal council‟s management had not come up
with the capacity building implementation reports. Further, the annual report for
the first year of program implementation by the project headquarters did not
provide details of the Municipal Council capacity building implementation status.
Underutilization of capacity building funds (some below 10%) affects
implementation of planned activities and ultimate attainment of overall project
objectives.
Management explained that the Municipalities received the funds barely 4 months
and had not fully completed the procurement process for consultants and supplies.
740
The Municipal Council also needed support from the Ministry to ensure that quality
tools were procured. Further, the Municipal Councils had started on the process of
coming up with capacity building plans and the reports will be produced
accordingly.
I urged management to support the municipal councils and ensure that the
procurements are done on time and activities implemented.
1.3.3 Un-utilised fund for Infrastructure Development
The project head office remitted a total of UGX.41,826,946,392 to 14 Municipal
Councils as budgeted. During inspection, it was noted that at the close of the
financial year, a total of UGX35,018,760,442 (84%) remained unspent as per the
details in the table below:
Municipal Bank Amount sent Closing Balance
1 Arua Orient Bank 2,598,140,991 8,765,460
2 Entebbe Bank of Baroda 2,689,196,081 2,724,879,781
3 Fort Portal Housing Finance
Bank 1,660,797,443 1,691,167,821
4 Gulu Bank of Africa 8,162,894,235 8,162,755,481
5 Hoima Crane Bank 3,511,992,326 3,521,915,938
6 Jinja Crane Bank 3,193,079,981 3,202,039,427
7 Kabale Bank of Baroda 1,535,126,450 1,532,367,451
8 Lira Bank of Africa 4,967,344,540 4,967,190,552
9 Masaka Crane Bank 3,041,414,632 3,045,632,403
10 Mbale Crane Bank 2,911,814,550 851,962,587
11 Mbarara Crane Bank 2,687,417,388 2,698,862,531
12 Moroto Crane Bank 446,244,780 475,868,980
13 Soroti Crane Bank 2,482,947,571 1,240,434,155
14 Tororo Crane Bank 1,938,535,424 894,917,875
TOTAL 41,826,946,392 35,018,760,442
741
By the close of the financial year, municipalities in cluster 2 (Mbale, Soroti and
Tororo) had just signed contracts for works and at the time of inspection; contract
execution was ongoing.
I could not rule out lack of commitment by municipalities on the implementation of
project activities which may hinder the achievement of project objectives.
Management explained that 10 Municipal Councils signed contract agreements at
the end of the financial year and in the course of the first quarter of 2014/15
financial year. The other 4 Municipal Councils are still in negotiation stage.
Management however promised to fully utilize the funds in the subsequent year.
I urged management to liaise further with management of the municipalities to
ensure that infrastructure development activities are successfully implemented
57.2 DEVELOPMENT OF NATIONAL URBAN SOLID WASTE MANAGEMENT
STRATEGY - 2012/2013
a) General Standards of Accounting and Internal Control
A review of the system of accounting and internal control was carried out. It was
noted that in all material respects, management had put in place adequate
controls to ensure proper accountability for the Grant funds.
b) Compliance with Financing Agreement Provisions and GoU
Financial Regulations
A review was carried out on the project compliance with the Grant agreement
provisions and GOU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and applied
GOU regulations except for the following matters;
i. Delayed submission of Financial Statements
It was noted that management submitted financial statements one (1) year later
after the end of the financial year contrary to sect.2.04 (c) of article II of the
742
Grant agreement. Failure to submit the financial statements limited my ability to
undertake the audit and report within the prescribed timeline. Furthermore, this
impacts negatively on the decision making process of stakeholders.
I advised management to prepare accounts in time to enable the audit and timely
reporting on the Project financial statements.
ii. Lack of Project work plan
It was noted that the project management did not prepare a project work plan to
guide in the utilization of the grant funds despite a total budget of USD.547,000. I
explained to management that a work plan guides the project in achieving its
intended objectives. Without the work-plan, ineligible expenditures could occur
and make it difficult to assess performance.
I advised management to ensure that a work plan is put in place and all
expenditures of the project is in accordance to the plan.
iii. Lack of interim unaudited financial reports
Sect. 2.04 (b) of the project document provides that the recipient shall ensure
interim unaudited financial reports are prepared and furnished to the World Bank
not later than forty five (45) days after the end of each calendar quarter. During
the review, I noted that management did not produce the interim financial
reports. I explained to management that failure to provide Interim Financial
Reports hinders the assessment of financial stewardship and performance of the
project.
I advised management to ensure that the interim un-audited financial reports are
in place to guide the financial stewardship and performance of the project.
57.3 DEVELOPMENT OF NATIONAL URBAN SOLID WASTE MANAGEMENT
STRATEGY - 2013/2014
a) General Standards of Accounting and Internal Control
A review of the system of accounting and internal control was carried out. It was
noted that in all material respects, management had put in place adequate
743
controls to ensure proper accountability for the Grant funds put in place by
management was satisfactory.
b) Compliance with Financing Agreement Provisions and GoU
Financial Regulations
A review was carried out to the project compliance with the Grant agreement
provisions and GoU financial regulations and it was noted that the project
complied in all material respects with the provisions in the agreement and applied
GoU regulations except for the following matters:-
i. Lack of project work plan
It was noted that the project management did not prepare a project work plan to
guide in the utilization of the grant funds despite a total budget of US$.547,000. I
explained to management that a work plan guides the project in achieving its
intended objectives. Without the work-plan ineligible, expenditures are likely to
occur. This issue was raised in 2012/13 report to Parliament.
I advised management to ensure that a work plan is put in place and all
expenditures of the project is in accordance to the plan.
ii. Lack of interim unaudited financial reports
Sect. 2.04 (b) of the project document states that the recipient shall ensure
interim unaudited financial reports are prepared and furnished to the World Bank
not later than forty five (45) days after the end of each calendar quarter. During
the review, I noted that management did not produce the interim financial
reports. I explained to management that failure to provide Interim Financial
Reports hinders the assessment of financial stewardship and performance of the
project. This issue had earlier been raised in 2012/13 report to Parliament.
I advised management to ensure that the interim unaudited financial reports are in
place to guide the financial stewardship and performance of the project.
iii. Operating beyond the agreed project closing date
744
Sect. 3.03 of the grant agreement indicated that the project closing date was 31st
December 2013 but operations of the project continued beyond 31/03/2014 when
the last payments were made. I noted that the extension was not granted by the
IDA. Further, the last tranche was not received. I explained to management that
failure to officially close the project in compliance with the project closing
guidelines is against the financial agreement provisions and project operations
guidelines.
Management explained that there was a delay in seeking for an extension.
Management was supposed to undertake study tours, exchange visits,
benchmarking best practices and training of officers but the activities were not
undertaken because the last tranche was not received. The balance of the
Consultancy fees had to be partly settled by World Bank having exhausted all the
funds on the Project account.
I advised management to always operate within the agreed period or seek
extension in time in case there is need.
c) Status of Project Implementation
i. Development of the National Urban Solid Waste Management
Strategy - Status of implementation
One of the major objectives of the project was to develop a Solid Waste
Management Strategy to ensure a cleaner and less polluted environment and have
it disseminated to different stakeholders. At the time of reporting, the strategy had
not been submitted to cabinet for adoption although a consultant contracted to
develop the policy had been paid all his dues amounting to US$377,600 for the
services rendered. I explained to management that in case of any suggested
changes, there is a risk that the consultant may not revisit the strategy and have
the changes effected.
Management explained that the policy was validated at a national stakeholder‟s
workshop in May 2014 and the delegates adopted it with some few amendments.
Management took it up to harmonize positions relating to the Ministerial mandate
745
of Water, Environment, Health and NEMA. It was indicated that there were issues
that the Ministers in charge of Health, Water and Environment had to agree on
and when finalized, the relevant Minister will table it to Cabinet for adoption and
to Parliament for final approval.
I advised management to expedite the approval process and have the strategy
implemented by stakeholders.
INFORMATION AND COMMUNICATION SECTOR
58.0 MINISTRY OF INFORMATION AND COMMUNICATIONS
TECHNOLOGY
a) Mischarge of Expenditure
The Parliament appropriates funds in accordance with the needs of the country
and this appropriation is implemented through the budget in which funds are
tagged to particular activities and outputs using account codes and MTEF codes. A
review of the Ministry‟s expenditures revealed that the entity charged wrong
expenditure codes to a tune of UGX.193,053,197. This constituted 4% of total
expenditure for the year of UGX.4,960,480,667.
Mischarges undermine the importance of the budgeting process as well as the
intentions of the appropriating authority and lead to misreporting.
Management explained that the mischarge of expenditure was a result of
insufficient budgetary allocations and severe cuts in respect of items referred to as
consumptive items by the MOFPED.
I advised the Accounting Officer to streamline the budgeting process to ensure
that sufficient funds are allocated to each account. Furthermore, authority should
be sought for any reallocations.
746
b) Outstanding Payables
A comparison of the payables balances for the financial year 2012/13 and 2013/14
revealed a significant increase in domestic arrears of UGX.356,261,608 (39.6%)
from UGX.900,856,821 in the financial year 2012/13 to UGX.1,257,118,429 during
the year under review. I explained to management that the entity risks litigation
and payment of nugatory expenditure arising out of litigation costs.
Management responded that the increase in payables was as a result of rent
arrears of UGX.350,732,722 which remained unpaid for the period ending 30th
June, 2014. The Ministry had budgeted UGX.516,000,000 exclusive of Value
Added Tax (VAT) for rent for the period because the Landlord M/s NSSF had not
earlier indicated that they are VAT registered. Management further explained that,
later in the year, the Landlord submitted a claim for VAT which increased the rent
amount beyond the budgeted funds.
I advised management to liaise with Ministry of Finance Planning and Economic
development and ensure that the rental arrears are cleared.
c) Un-approved Corporate Strategic Plan
The strategic plan is an important tool in steering any organization towards its
vision, mission and its overall mandate. Annual activities undertaken by any
organization should be derived from the strategic plan. However, it was noted that
the Ministry does not have an approved strategic plan in place. Delays in having a
strategic plan approved may adversely impact on the Ministry in the achievement
of its objectives.
Management explained that the Ministry‟s draft Strategic and Investment Plan
(ICT-SIP) was submitted to the Ministry of Finance Planning and Economic
Development for a certificate of financial implications so as to enable the Minister
of ICT submit it to Cabinet for approval.
I await the outcome of management‟s efforts in having an approved strategic plan
in place.
747
d) Staffing Gaps
A review of the Ministry‟s organizational structure revealed that out of the
available 93 posts, 76 posts were filled leaving 17 positions vacant. Some of the
vacant positions include vital positions below;
Vacant Position Vacancies Scale
Principal Information Scientist 01 U2U
Principal Communications Officer 01 U2 U
Senior Systems Analyst 01 U3SC
Senior Information Technology
Officer 01 U3SC
Information Technology Officer 01 U4SC
Information Scientist 01 U4SC
Staffing gaps affect the performance and overall achievement of organizational
goals and objectives.
Management explained that the recruitment of staff is constrained by the budget
ceiling. Management further explained that the Ministry is faced with the challenge
of uncompetitive salaries in the labour market thus there is a high staff turnover
in technical ICT positions yet the Ministry may not be able to attract suitable
applicants due to lack of competitive wage offers.
I advised management to continue liaising with Ministry of Public service with a
view of ensuring that the vacant posts are filled and possibilities of staff retention.
e) Budget Performance
Review of the budget performance for the year revealed that one targeted key
activity was not undertaken despite release of funds worth UGX.32,162,000 to the
entity to perform. The activity was in respect of start up activities for construction
of the Ministry of ICT.
748
Management explained that the Ministry budgeted for UGX.32,162,000 for
surveying the land for the Technology Park. However because the land had not
yet been fully secured from the Uganda Investment Authority this activity could
not be undertaken.
I advised management to follow up the matter with UIA to secure the land.
749
PUBLIC ADMINISTRATION SECTOR
59.0 MINISTRY OF FOREIGN AFFAIRS
a) Receivables
Included in the statement of financial position and Note 21 of the financial
statements for the period under review are receivables totalling to
UGX.3,343,141729 an equivalent of USD.1,464,363.81. These receivables relate to
the money advanced to Imperial Royale Hotel Ltd for the provision of conference
facilities and room accommodation during the CHOGM in 2007.
However, details show that the hotel was not ready for occupation between 26th
October, 2007 and 18th November, 2007 when CHOGM activities took place.
Although this matter has been referred to the Courts of Law, the outcome cannot
be predicted. There is a risk that Government may lose this money which has
been outstanding for more than 7 years.
The Accounting Officer explained that the court hearing of this case commenced
on 12th August 2014 and after several adjournments.
I advised management to follow up the matter and also provide an update of the
current status.
b) Retrospective approval of contracts
Contract agreements in the sum of UGX.965,470,474 were signed and activities
undertaken before award of contracts by the Contracts Committee contrary to
Regulation 225 (2) of the PPDA Regulations, 2003 and Regulation 7(1) of the
PPDA Regulations, 2014.
The practice negates the role of the Contracts Committee in the procurement
process and exposes the Ministry to the risk of contracting sub-standard
contractors.
The Accounting Officer explained that these were emergency procurements arising
from directives given at short notice to host International summits. The contracts
Committee was informed of the procurements afterwards.
750
I advised the Accounting Officer to consider using framework contracts for
repetitive services and ensure the Contracts Committee performs its duties in
accordance with the Regulations.
c) Failure to submit progress Reports on Waivers and Deviations Given by
PPDA
During the course of the financial year, the Ministry hosted a number of summits
which included the AMISOM Summit, Tripartite Summit, ICGLR summit and IGAD
summit among others. Due to the perceived time constraint the Ministry sought
and was given permission to use emergency procurement method.
However, though the Ministry was required to submit progress reports to the PPDA
within 10 (ten) working days after contract award and signing as per referance to
corresponces PPDA/M11/000 for the Tripartite Summit, PPDA /M07/000 for the
Amisom summit, PPDA/M11/000 for the ICGLR Summit, there was no evidence
that management submitted the progress reports to the Authority.
The Accounting Officer explained that the progress reports on waivers and
deviations were usually presented in the monthly procurement reports to the
Authority. Evidence to this effect was not availed.
I advised management to ensure that the required reports are always submitted
for review.
d) Donation to a Foundation
A total of UGX.746,659,035 was disbursed to a Foundation A/C no 1000043346052
in February 2014 on the basis of a letter by the Ministry‟s Accounting Officer.
However, the donation had not been budgeted for during the period under
review. The payment also lacked an acknowledgement receipt from the
beneficairy. Unauthorised reallocation of funds distorts the intentions of the
appropriating authority and contravenes budgetary controls.
The Accounting Officer explained that the PS/ST gave authority to re-prioritize
contributions to International Organisations so as to accommodate this donation.
751
I advised the Accounting Officer to always ensure that additional funding
requirements are properly planned through reallocations and supplementaries to
avoid distortions in the budget implementation.
e) Accomodation for ICGLR
The contract for provision of hotel services during the ICGLR which took place
from 3rd to 5th September, 2013 was awarded to Munyonyo Comonwealth Resort
Limited at a sum of UGX.594,142,019. However the Hotel was paid
UGX.682,708,283 VAT inclusive.
A reveiw of the procurement file revealed the following matters:
There was an over expenditure on the contract sum of UGX.594,142,019 by
UGX.88,566,264. It was further observed that the extra costs were not
approved by the Contracts Commitee as a variation to the original contract
contrary to Regulation 262 (3&5) of the PPDA Regulations, 2003.
A record of bid opening dated 1/8/13 was not witnessed by a member of the
Contracts Commitee. In addition, whereas the price quoted and approved by
the Evaluation Commitee was UGX.333,729,487, the contract sum was UGX.
UGX.594,142,019 and this eventually rose to UGX.682,708,283. No
explanation for the variances was provided.
The contract number on the contract agreement for non consultancy services
was changed to read MOFA/SRVCS/13-14/00091 instead of MOFA/SRVCS/13-
14/00051 by hand. There was no explanation for this change.
The attendance list of participants was not availed for verification and
confirmation of room occupancy.
In response the Accounting Officer explained that the extra expenditure of
UGX.88,566,264 arose as a result of the additional guests and facilities which were
not budgeted for.
I advised the Accounting officer to investigate the causes of the variances, provide
neccessay supporting documents and ensure that emergency procurements meet
the criteria for such procurements.
752
60.0 EAST AFRICAN COMMUNITY AFFAIRS
a) Irregular tenure of Office in acting capacity
Paragraph 9 of Section (A-C) of the Uganda Public Service Standing Orders
requires that an appointment on acting basis is expected to last not more than six
months and is subject to direction by the Appointing Authority. The Section further
provides that any extensions shall not exceed twelve months in total.
A review of personnel files revealed that two officers had been in Acting Positions
for a period exceeding twelve months contrary to the provisions in the standing
orders. Keeping officers in acting positions for a period longer than the period
provided for in the standing orders is irregular.
Management explained that the post of Commissioner Political and Legal Affairs
had been internally advertised by the Public Service Commission while the
Ministry had continually requested the Ministry of Public Service to deploy a Senior
Office Supervisor without success.
I have advised the Accounting Officer to let the officers revert to their substantive
positions in accordance with the standing orders as the outcome of the
recruitment process is awaited.
b) Irregular probationary period of service
Examination of personnel files revealed that an Office Attendant at the Ministry
had been on probation since first appointment in 2008 contrary to section (A-d)
(1) of the public service Standing Orders. There was no evidence of performance
appraisal on the personnel files nor efforts made to confirm the Officer. This may
negatively affect computation of the officer‟s terminal benefits.
Management ackowledged the anomaly and indicated that a submission
recommending the confirmation of the Officer had been made to Public Service
Commission. I await the outcome of management‟s action in this regard.
753
SOCIAL DEVELOPMENT SECTOR
61.0 MINISTRY OF GENDER, LABOUR AND SOCIAL DEVELOPMENT
a) Payables
Audit of Financial Statements for the period under review revealed that the
Ministry had liabilities of UGX.4,771,858,282, broken down as follows
No Item Amount
1 Trade Creditors 220,000
2 Sundry Creditors 4,730,824,170
3 Withholding Tax Payable 40,814,112
Total 4,771,858,282
The sundry creditors arose out of outstanding claims for workman‟s compensation,
dating back to 2003/2004 financial year. Meanwhile, the withholding tax liabilities
may attract penalties from Uganda Revenue Authority as provided for in the
Income Tax Act, 1997 (as amended). The delay in paying renders the claims
redundant.
In response, management stated that requests to MoFPED for funds to settle the
liabilities had not been responded to positively.
I advised the Accounting Officer to continue liaising with the MoFPED and other
stakeholders to ensure prioritization of funding for the items to avoid litigations
and other costs that may arise.
7.2 Mischarge of Expenditure
Paragraph 400 (a) of the Treasury Accounting Instructions (TAI), 2003 states that
all government transactions shall be recorded in the books of account applying the
Government of Uganda Chart of Accounts as prescribed by the Accountant
General. In addition, Accounting Officers shall ensure that all financial transactions
are properly coded. It was noted that out of the total actual expenditure of
UGX.27,871,419,382, a total of UGX. 66,982,475 were mischarged. The practice is
a sign of a breakdown in controls over the budget implementation process.
754
Management explained that more adherences to the charge codes in line with the
Chart of Accounts is now being emphasized.
I have advised the Accounting Officer to streamline the budgeting process so that
available funds are properly allocated to the planned activities.
7.3 Advances not accounted for
A sum of UGX.25,000,000 advanced to three Districts for purchase of toolkits for
PCY activities lacked accountability contrary to TAI and MoU which requires
accountability within 60 days. The table below refers:
Document
No
Date Details Amount Paid
(UGX)
1139107 4/10/2013 Payment to CAO - Arua district to
purchase toolkits for Youth
trained
16,000,000
1216325 4/12/2013 Payment to CAO Gulu for
purchase of tool kits for training
and coordination of PCY project
4,000,000
1216321 4/12/2013 Payment to CAO Lira for
purchase of tool kits for training
and coordination of PCY project
5,000,000
Total 25,000,000
In the circumstances, I could not confirm whether the funds were used for the
intended purposes.
In response, management explained that letters reminding the respective Chief
Administrative Officers had been dispatched.
I advised the Accounting Officer to ensure submission of accountability or recovery
of the funds.
7.4 Staffing Gaps
I noted that the Ministry was grossly understaffed. Out of 609 posts in the
approved structure, only 276 were filled leaving 333 posts unfilled. Among unfilled
755
posts were; the Director Social Protection and Director Labour Employment
(Occupational Safety & Health), which are key posts in the management structure
of the Ministry.
Management indicated that submissions were made to the Ministry of Public
Service and Public Service Commission to ensure that the staffing challenge is
addressed.
I advised management to follow up the matter and fill the positions in a phased
manner beginning with the critical ones.
7.5 Non-Disposal of Obsolete Assets
Section 295 (5) of the PPDA Regulations, 2003 requires a procuring and disposing
entity through the board of survey to identify assets for disposal on a periodic
basis. A review of the Ministry‟s Asset register revealed a number of old and
obsolete assets due for boarding off and these included; motor vehicles, desktop
computers, laptops, furniture, tyres and books among others. I also noted that the
recommendations of the Board of Survey for disposal in the Financial Year
2011/2012 were not implemented.
Management indicated that it is in the process of updating a Disposal Plan and will
dispose of obsolete items in FY 2014/15.
I advised the Accounting Officer that failure to timely dispose of these assets
results in further physical deterioration and diminution in value. I await results of
management actions.
7.6 Lack of Performance Appraisals for some Staffs
Sec. A-m (14) of The Uganda Public Service Standing Orders, 2010 states that “A
staff performance appraisal report form shall be completed for each pensionable
and non-pensionable officer and a copy submitted to the Responsible Permanent
Secretary.
It was however noted that 25 staff out of a sample of 45 staff of the Ministry were
not appraised during the year under audit. The Accounting Officer explained that
strict guidelines and deadlines have been put in place for those that do not
comply.
I await results of management actions in this regard.
756
7.7 Repayments into the Revolving Fund
According to the YLP Programme Document dated December 2013, the revolving
nature ensure sustainability through the cash and kind refunds and re-
disbursement. This is further amplified in Part 4.0 of the YLP Project Funds Access
Criteria document which requires YLP to be administered as interest-free
Revolving Funds to ensure sustainability of the Programme.
I observed that out of 27 districts that had received the funds, only 6 had opened
the special collection accounts.
Management indicated that the outstanding 21 districts had been reminded.
I advised the Accounting Officer to ensure that the remaining Districts comply with
the regulatory requirements for YLP.
7.8 General Challenges faced in the Implementation of Youth Livelihood
Programme:
7.8.1 Determination of the age of the group members
According to YLP Project Funds Access Criteria part 2.2 (i) (Beneficiary Selection
Criteria) paragraph and program document chapter 2 section 2.4, all intended
beneficiary Youths should be persons within the age bracket of 18-30 and
evidence was to be provided through birth certificates, immunization cards,
passports, baptism cards, marriage certificates, National Identity Cards or
community knowledge of the youth.
During the period under review, audit noted that birth certificates for beneficiaries
on a number of project files were missing, rendering confirmation of the
qualification by age difficult.
Management indicated that a number of potential beneficiaries did not have
documentary evidence for their ages. The Selection Committees relied on the
judgement and decision of the community members under the leadership of LC I
Chairpersons as provided in the Programme Guidelines.
I advised the management to use the National identity cards in determining age of
beneficiaries in the successive following phases of the programme.
757
7.8.2 Inadequate monitoring of the projects
It was noted that the Districts were not closely monitoring the activities of the
approved youth projects due to inadequate staffing. For example, there were no
monitoring reports for the 16 districts inspected out of the 27 pilot districts. The
respective CAOs and the District Focal Point Persons indicated that there is low
human resource capacity as opposed to the number of approved projects to allow
closer monitoring to take place.
Management explained that the low staffing levels especially of Extension Staff in
the Local Governments still remains a challenge. Furthermore, the Accounting
Officer indicated that the Chief Administrative Officers have been advised to
rationalize the deployment of the available staff to ensure that the youth groups
financed under YLP receive technical support.
I await results of management actions on this matter.
7.8.3 Lack of sign posts for respective Projects
It was observed that a majority of the YIG Projects that were inspected did not
have sign posts. Those that had sign posts did not have YLP identity. It was
therefore not possible to easily identify them with YLP funding.
In response, management stated that all the new projects are being advised to
provide for the signposts in their budgets. Furthermore, YLP has concluded the
Geographical Information System (GIS) mapping for all the projects financed
under Phase-I as a strategy of enhancing accountability, transparency and to avert
a possibility of using one project site for multiple accountabilities to various
agencies or persons. In the meantime, I await the results of management effort in
this regard.
7.8.4 Inadequate training of the 3 committees in a group
The YLP Programme Document requires each YIG to have at least 3 committees
namely; Youth Project Management Committee (YPMC), Youth Procurement
Committee (YPC) and Social Accountability Committee (SAC).
Audit revealed that the trainings received by the members of these committees
were so general and did not address the specific roles that each committee is
758
supposed to play in a group. Furthermore, the trainings were conducted under
limited time frame.
Management explained that any gaps identified during monitoring visits are
documented and addressed as part of the routine continuous support to the
groups.
I advised management to ensure that trainings to the committee members are
conducted to enable them appreciate their roles on the committees so as to avert
conflicts and failure of groups‟ businesses.
7.8.5 Record Keeping
It is good practice for any type of business/project to keep proper books of
account, management records among others. I noted that most of the groups
visited did not maintain/keep such records including minutes and procurement
details.
Management indicated that the varied literacy levels of the beneficiaries supported
under YLP affects record keeping. However, the Sub-county Community
Development Officers (CDOs) have been advised to provide support to weak
groups on regular basis as part of their overall mandate in community mobilization
and development.
I await the results of management efforts in this regard.
b) EXPANDING SOCIAL PROTECTION PROGRAMME 2011/2012
f) Lack of National Social Protection Policy
It was noted during audit that the program still lacked an approved policy,
contrary to the recommendation contained in Expanding Social Protection (ESP)
Quarterly report of July to September 2011, requiring an approved policy
framework to be in place within the financial year 2011/12. In the circumstances,
there is no formal framework to guide the activities of Social Protection in the
country. There is also a risk of having social disharmony between the societies
that have benefited and those that have not.
Management explained that at the inception of the programme, the design
foresaw the development of a Social Protection “framework” which would have
simply defined the scope of social protection services in Uganda. However, during
759
the course of the programme, management realized that a full National Social
Protection Policy was required along with a comprehensive costed plan of
Interventions (PPI) to cover social assistance, social insurance and social care
services. Management further stated that according to the revised log-frame, the
policy and PPI are due to be finalised by December 2014.
I have advised management to engage the stakeholders involved and expedite the
discussions to have the policy finalised and approved.
g) Co-funding
Section 2 of the Joint Financing Arrangement requires the Government of Uganda
(through the MoGLSD) to provide an agreed level of funding to the programme. It
was however noted that GoU, which had committed to provide USD.20,030 (about
UGX. 70,105,000), did not fulfill its obligation in the period under review. This
could have hampered the implementation of the planned activities and may affect
the overall attainment of the programme objectives.
Management explained that they were continuing to engage the Ministry of
Finance, Planning and Economic Development to fulfill the government obligations
towards the programme.
I have advised management to continue with the engagement of the Ministry of
Finance Planning and Economic Development so as to ensure that Government
fulfills its commitment towards the programme for better implementation.
h) Un-accounted for Funds
UGX.227,301,091 (equivalent to USD.49,778.45) was transferred to ESP
operational account in the MoGLSD, to facilitate older persons day celebrations
and orientation of Members of Parliament. Audit noted that a total of
UGX.106,618,500 was utilized for the celebrations and orientation of MPs, leaving
a balance of UGX.120,682,591 unaccounted for.
Although management explained that the balance was retained in the MoGLSD
ESP operations account for other ESP activities, no documentary evidence was
availed to confirm this and how it was utilised.
I have advised management to ensure
760
c) EXPANDING SOCIAL PROTECTION PROGRAMME 2012/2013
i. Co-funding
Section 2 of the Joint Financing Arrangement requires the Government of Uganda
(through the MoGLSD) to provide an agreed level of funding to the programme. It
was however noted in the year under review that GoU allocated only
UGX.40,000,000 million as opposed to the FY 2012/13 counterpart commitment of
UGX.500,500,000. This could have hampered the implementation of some planned
activities and may affect the overall attainment of the programme objectives.
I advised management to engage Ministry of Finance Planning and Economic
Development so as to ensure that Government fulfils its commitment towards the
programme for better implementation.
ii. Doubtful contract award
Regulation 90 (g, h & i) of the Public Procurement and Disposal of Public Assets,
2013, stipulates the procurement records that should be maintained by a
procurement and disposal unit. However it was noted that a total of
UGX.191,666,376 was paid to Property Development Company Ltd for rent, but
procurement documents were not maintained, contrary to the requirements of the
regulations. In the circumstances, audit could not ascertain whether the
procurement was fairly competed for and that there was value for money.
I advised management to ensure that all procurement records are in future
maintenance for all procurements undertaken on behalf of the programme.
iii. Un-vouched Expenditure
Audit noted that out of a total of UGX.135,369,238 transferred to Kyenjojo District
to fund SAGE activities in the months of January and June 2013, a total of
UGX.116,152,804 was spent without preparing payment vouchers. The
authenticity of the expenditures relating to all the missing vouchers could not be
ascertained.
I advised management to ensure that the funds are accounted for.
iv. Mischarged expenditure items
761
A total of UGX.11,976,000 was charged wrongly on expenditure items other than
those under which it was supposed to have been spent, contrary to the
requirements of section 3.1 of the overview of the financial management of SAGE.
Failure to comply with the requirements portrays a breakdown of controls in the
budget implementation process and it affects the implementation of some planned
activities.
I advised management to streamline the budgeting process and ensure that
payments are correctly charged on the item codes to enable proper
implementation of the programme.
v. Un Accounted for Funds
Funds totaling UGX.56,178,500 advanced to various officers in Katakwi district to
implement programme activities remained un-accounted by the time of writing this
report. In the absence of the necessary accountability, audit could not confirm
whether the funds were put to intended use.
I advised management to recover the funds from the officers.
762
MISSIONS
62.0 UGANDA EMBASSY, ABU DHABI
a) Wasteful Expenditure
The Embassy incurred costs totaling AED 2,900 (approximately UGX.2,048,822) as
bank charges for failure to maintain a minimum bank balances on the account.
This expenditure is considered wasteful as it would have been avoided by
maintaining the minimum balance.
Though the Accounting Officer explained that he had communicated to the bank
to stop the monthly deductions on non-maintenance of a minimum balance since
this was an operational account and not a savings account, there was no action
taken by the Bank. As a result the Embassy opened a new bank account that
allows minimal bank balance with the authority of the Accountant General.
I have advised Management to recover the money from the bank.
63.0 UGANDA HIGH COMMISSION, ABUJA
a) Non Tax Revenue (NTR) Collections
Regulation 46 of Public Finance and Accountability Regulations states, in all cases,
the gross amount of moneys received shall be accounted for and any charges
against the revenue received shall require appropriate authority as expenditure
incurred by the Government and shall appear as a charge on public funds in the
books of accounts, duly supported by proper voucher.
It was noted that for the period between November 2013 and June 2014, the
mission collected and banked NTR of NGN 26,888,703.75 and USD 42,315,
however only NTR of NGN 14,637,890 was transferred to the consolidated fund
leaving a balance of NGN 12,430,412= unaccounted for contrary regulations. It
was also noted that the mission borrowed NGN 9,033,408.5 and USD 41,776.78 at
763
source to cater for various commitments but did not provide evidence of refund as
shown in the table 1 below.
Period Amount (NGN) Borrowed (NGN)
Repayment (NGN)
Amount transferred to
BoU (NGN)
October 1,457,395 0 0
November 804,475 0 0
December 1,328,035 2,922,227 0
January 4,029,283 522,625 0
February 6,298,647.47 0 0
March 2,169,304.66 1,272,735 6,889,588
April 1,428,927 2,414,082.5 0
May 5,362,763.98 256,450 0
June 2,508,670 1,645,289 7,748,302
Closing balance
1,501,202.64 0 0
TOTAL 26,888,703.75 9,033,408.5 14,637,890
Extracted from bank statements for NTR account November 2013 to June 2014
Furthermore there were no records for NTR cash collections to reconcile with
actual banking‟s to confirm that all NTR collected was banked intact in accordance
with the requirements of the public finance and accountability Act
I have advised The Accounting officer to remit the outstanding NTR balances to
the consolidated fund as required by the regulations and also provide the
necessary supporting documentation for NTR cash for verification.
b) Payments made outside Navision
The Accountant General introduced the Navision accounting system in the mission
to strengthen the internal controls systems and improve financial reporting.
It was noted that during the month of March 2014, payments totaling to NGN
437,330 (Details in table 2) were made outside the Navision system contrary to
the Treasury directives. Payments made outside the Navision financial system
render the accuracy and reliability of the financial statements uncertain as such
amounts not captured in the ledgers have an effect of understating the
expenditure reflected in the system generated financial statements.
764
Table 2: Payments made outside the system
Voucher Amount Payee
PV-1781 16,000 Amb. Maurice Kagina Kiwanuka
PV-1782 14,000 Amb. Maurice Kagina Kiwanuka
PV-1783 19,200 Joseph Koufionou
PV-1784 55,000 Sundry persons
PV-1785/3 5,000 Abuja electricity distribution company
PV-1786/3 30,000 Katherine Sati
PV-1787/3 14,100 Sundry persons
PV-1788/3 9000 Katherine Sati
PV-1789/3 50,000 Isaac Onali
PV-1790/3 68,000 KKONTech
PV-1791/3 11,050 Goodness International
PV-1792/3 91,000 Sundry persons
30,000 Musa Gimba
PV-1794/3 6,000 Jide Sholotan
PV-1795/3 16,000 Sundry persons
PV-1796/3 2,980 Cash account
Total 437,330
In his response the Accounting Officer acknowledged this anomaly and attributed
it to a system failure in February 2014 which lasted for a period of one and a half
months. I advised the Accounting Officer to have that the necessary adjustments
effected in the accounting system to ensure accurate and reliable financial
reporting of mission expenditures.
c) Unauthorized Over expenditure
A review of financial statements revealed that the Mission incurred
UGX.232,895,267 in excess of the approved budget of UGX. 1,017,000,072.
However, there was no evidence to show that the necessary approval in the form
765
of virements/reallocation warrants was granted by the Permanent
Secretary/Secretary to the Treasury contrary to section 17 of the Public Finance
and Accountability Act, 2003. Under the circumstances, the expenditure is
considered not a proper charge to government funds.
I advised the Accounting Officer to always adhere to the approved budget and
where necessary liaise with treasury for supplementary appropriation in
accordance with the public finance and accountability Act 2003.
d) Non Compliance with the PPDA Act regulations
The PPDA Act and regulations require every Procurement and disposal unit to
amongst other requirements;
Prepare and submit to PPDA an Annual procurement plan based on the annual
approved budget for that respective financial year;
Prepare and submit to PPDA quarterly procurement and disposal reports;
Produce a list of prequalified goods and service providers for the next three
years.
Contrary to the above requirements the mission did not prepare an annual
procurement plan and quarterly procurement and disposal reports nor a list of
prequalified service providers.
I advised the Accounting Officer to comply with the PPDA regulations and observe
the above requirements.
e) Progress report on implementation of the Mission Charter
The mission was issued a Charter covering a three year period 2011/12 to
2013/2014 setting out key outputs, performance targets and performance
indicators; however I was not availed with quarterly progress reports on the
implementation of the Mission charter. In the absence of progress reports, it was
difficult to establish the extent to which the mission achieved its set objectives
I advised the Accounting Officer to prepare and submit quarterly progress reports
on implementation of the Mission Charter to enable its performance to be
assessed.
766
f) Office Imprest
During the year it was observed that the mission on a regular basis drew various
amounts of dollars from the operational account which was then converted to
Naira for office imprest.
Examination of returns revealed that N 2,441,620 and USD 36,990 was drawn
as petty cash for the period.
Treasury Accounting Instructions Chapter IV, Payments 227 requires that there
should be an imprest holder duly appointed by the Accounting Officer and
approved by the Accountant General. However, there was no evidence to that
effect.
Treasury Accounting Instructions Chapter IV, Payments 214 requires that before
replenishing an imprest, the previous one should be properly accounted for and
retired. It was noted that all imprest advances drawn as petty cash were not
supported with requisitions prepared by the beneficiaries which meant that the
basis for the advances could not be substantiated and in other instances petty
cash was paid as refunds for activities that had not been sanctioned by the
Accounting Officer.
In his response the Accounting Officer acknowledged this anomaly and attributed
it to the operating environment in Nigeria where most suppliers and service
providers of routine office consumables only accept cash as a medium of
exchange.
The Accounting Officer was advised to have imprest holders properly appointed in
accordance with the Treasury Accounting Instructions and also ensure that for any
petty cash payment effected; the user department should express the need
through properly approved requisitions.
g) Project Account and Chancery land
In the Permanent Secretary‟s letter to the Uganda High Commission – Abuja dated
28th February 2014; four (4) officers from Inter-ministerial Property Management
767
Committee were sent to Abuja to carry out technical study on the mission land
earmarked for the construction of a Chancery. The 3 officers were to be facilitated
from the funds which remained on the project account. However, there were no
clear terms of reference for this exercise and the technical report which was the
major deliverable from the exercise was not availed for audit to support this
payment. It was also noted that UGX 145,695,932 spent on this exercise was not
from the mission‟s approved budget has since been capitalized under Consumption
of property, plant and equipment in the financial statements without any
justification.
I advised the Accounting Officer to avail the technical report for verification and
also provide a justification why this payment was capitalized in the financial
statements yet it was extra budgetary.
h) Payment of electricity for staff
According to the Uganda Public service Standing Orders 2010 governing housing
of officers in the foreign service (H - e) para 9(a) , every public officer at the
mission shall be responsible for the cost of lighting and water consumed in any
house allocated to him or her.. It was however observed that the mission was
reimbursing staff 80% of the bills incurred by them contrary to the instructions. A
total of N51,120= was paid as per details in table 3 below:
Table 3: reimbursment made for staff electricity bills
Voucher Payee Description
Amount
(NGN)
pv1179 Agnes Achen being refund of 80% electricity bills 14,400
pv1237 John Nuamanya being refund of 80% electricity bills 3,600
pv 1487 Kalinaki Hadijah being refund of 80% electricity bills 6,400
pv1518 john Nuamanya being refund of 80% electricity bills 3,600
pv1609 Agnes Achen being refund of 80% electricity bills 8,000
pv1710 John Nuamanya being refund of 80% electricity bills 4,000
pv1829 John Nuamanya being refund of 80% electricity bills 5,200
pv1937 Agnes Achen being refund of 80% electricity bills 5,920
768
Voucher Payee Description
Amount
(NGN)
51,120
I advised the Accounting officer to recover the amounts paid and in future ensure
compliance with the requirement of the standing orders.
64.0 UGANDA, EMBASSY ADDIS ABABA
a) Exchange Rate Table in Navision not updated daily
It is a requirement for all embassies to update exchange rates daily in the exchange
rate table in Navision. The rates are obtainable from the Bank of Uganda (BoU)
website. A review of the Embassy‟s Navision system however revealed that the
exchange rates were not updated on a daily basis. The anomaly was attributed to
the intermittent internet connectivity at the Embassy. This casts doubt on the
authenticity of the foreign exchange gain reported of UGX.4,927,333 in the financial
statements of the Embassy.
The Accounting Officer acknowledged the anomaly and stated that the matter had
been rectified as the exchange rates were now being updated daily before
transactions on the system are undertaken. The Accounting Officer however
hastened to add that there was still a challenge of the BoU exchange rates being
updated on the system 2 or 3 days late.
I have advised the Accounting Officer to ensure that the exchange rates are updated
on a daily basis, as required and to follow up the issue of delayed updates of the
exchange rates on the system with the Navision Support Group at the Ministry of
Finance, Planning and Economic Development (MoFPED).
b) Unauthorized Over Expenditure
Regulation 37(b) of Public Finance and Accountability Regulations, 2003, requires
the Accounting Officer to ensure that the provision for services as authorized by
accounting warrants are not exceeded, and is held personally and pecuniary
responsible for any excess expenditure that is incurred without proper authority.
769
A review of expenditure of the Embassy revealed that there was over expenditures
on various expenditure budget line items amounting to Birr 1,068,046
(UGX.142,915,235) without seeking appropriate authority in form of reallocations or
virement warrants. This contravenes the intentions of budgeting.
The Accounting Officer attributed the occurrence to shortfalls on some budget items
for which authority to make reallocations within the same accounting warrant was
sought but had not been responded to.
I have advised the Accounting Officer to always ensure that payments are only
made when authority for reallocations has been granted.
c) Unfunded Priorities
The Addis Ababa Embassy is strategic and handles both bilateral and multilateral
matters which require adequate funding. The capital budget and the Peace and
Security budget for the year under review were not funded. Consequently the
Embassy was not able to:
Replace the ageing automobiles in the vehicle fleet. The vehicles for the Head
of Mission, Deputy Head of Mission and the staff utility van were more than five
(5) years old and often broke down. This constrained mobility at the Embassy
and consequently the ability to effectively facilitate high level official delegations
visiting Addis Ababa regularly to attend meetings at African Union, United
Nations Economic Commission for Africa (UNECA) and IGAD.
Renovate the official residence in Mugenagna that was purchased by the
Government of Uganda in 2012. The structure was old and required renovation
but the available funds were insufficient. There is a risk of the authorities
demolishing the structure.
Facilitate an extra officer to deal with the Peace and Security matters where
Uganda is serving in the Peace and Security Council for the period 2013 - 2015.
This curtails the implementation of peace and security activities.
Management explained that they had requested the responsible authorities severally
to address the issues but to no avail. They also stated that though they had
budgeted for the activities in the year, funding was not obtained.
770
I have advised the Embassy management to continue liaising with the responsible
authorities with a view to ensuring that the unfunded priorities are considered in the
subsequent financial periods.
d) Failure to acquire Plot of Land in Lebu
In 2005, Uganda was allocated a plot of land in Lebu by the Ethiopian Government,
which land was to be paid for and developed. Audit noted that although the
Embassy had been budgeting for this activity, no funds had been released to enable
it conclude the purchase and start on the construction. It is worth noting that most
of the other countries that had also been allocated land had developed theirs. There
is a risk of the said land being withdrawn and reallocated to other interested
developers.
In view of the terror threat in the region, coupled with Uganda‟s involvement in
peace and security initiatives, the Chancery may become a terror target given the
current location in a poorly lit area, off Bole Road.
Management explained that they had engaged the relevant authorities and in the
Financial Year (FY) 2014/15, some money was released towards the purchase of the
land leaving a funding gap of UGX.417 million which the Ministry of Foreign Affairs
(MoFA) had promised to secure and allocate to the Embassy during the financial
year 2015/16. Once the land is fully paid for, plans then will be developed for the
construction to commence.
I have advised management to continue engaging the relevant authorities so that
funds are secured for the purchase and eventual development of the land to house
the Chancery.
e) Unpaid Education Allowances
In June 2011, the Ministry of Public Service communicated to the Ministry of Foreign
Affairs concerning the standardization of the Education Allowance to USD.2,000 per
child per year for Group B Missions, which includes Addis Ababa. The allowance is
payable for a maximum of four biological or legally adopted children between the
ages of 4 and 18.
771
Audit however noted that the Education Allowance was not being paid to the
Foreign Service Officers deployed at the Addis Ababa Embassy ever since it was
approved in 2011 and this has the effect of demotivating staff.
Management stated that it had already engaged MoFA and MoFPED in this regard
and hastened to add that for the FY 2014/15, a supplementary was provided to
cover this item. Consequently for the FY 2015/16, the Embassy budgeted for the
allowance and is hopeful that the entitlement shall be honoured.
I await the implementation of management‟s proposals.
65.0 ANKARA EMBASSY
a) Representation Car
The commentary to the financial statements indicated that the Embassy did not
have a representation car for the Head of Mission. Lack of such a suitable
representation vehicle portrays a negative image for the country. Management
explained that the car had been budgeted for purchase in the Financial Year
2015/16.
I advised management to liaise with MoFA and MoFPED to ensure that necessary
resources are put aside to acquire the vehicle.
b) Local Staff
Section (A-a) (10) (f) of the Public Service Standing Orders states that “The power
to appoint, confirm, discipline and remove officers from office in the public service
is vested in the Head of a Mission, subject to delegation in writing, in the case of
locally recruited staff for the Embassy.
During the year under review, a sum of TL.79,828 was paid in respect of social
contributions for local staff. However, appointment contracts for the staff were not
availed for verification. In the circumstances, I could not ascertain the
genuineness of this expenditure.
772
Whereas management acknowledged the expenditure, the necessary
documentation was not availed at the time of writing this report.
I have advised Management to avail copies of appointment contracts and appraisal
forms for staff to enable verification of the payments.
66.0 UGANDA, EMBASSY BEIJING
a) Outstanding commitments from prior years
It was observed that the consulate had outstanding commitments amounting to
UGX.398,313,217 at the end of the financial year under review. The commitments
were in respect of utilities and rent in the Mission. Long outstanding commitments
could result into halting of provision for services due to non payment.
Management explained that they had budgeted for and included the outstanding
rent arrears in the Mission budget proposals submitted to the Ministry of Finance,
Planning and Economic Development for the financial year 2014/15. However,
funding to the outstanding commitment was not provided in the Missions
approved budget for FY 2014/15. Nevertheless, management has requested
MoFPED for a supplementary in order to offset the overdue settlement and is
awaiting further guidance.
I advised management to ensure that the outstanding commitments are prioritized
for settlement.
b) Idle motor vehicle
It was observed that mission purchased a motor vehicle (Van) in the year 1996.
However over time the use of the vehicle had been outlawed due to its inability to
comply with the emission standards in China. As such the vehicle remained un-
used for over a year.
There is a risk that the vehicle would deteriorate further attracting eventually
lesser value.
773
Management explained that the motor vehicle in question was uninsurable and
declared unfit for usage in China and therefore attracts no value; except as a
scrap. I advised Management to consider commencing on the disposal process for
the vehicle to avoid further loss.
c) Staffing at the Mission
The mission is categorized as 1+3 for purposes of the structure at the mission.
However currently the mission is staffed at 1+5, which is beyond the approved
structure. The current staffing position implies that the mission is overstaffed and
may not access adequate resources to manage the existing staff.
Management explained that they had engaged with Ministry of Foreign Affairs and
had made recommendations and sought approval from the Ministry to upgrade the
Mission to category A for reasons of the growing volume of engagements with
China and enhancing the Missions capacity to effectively cover the whole of China
and the four other countries (North Korea, Vietnam, Cambodia and Laos) to which
it is also accredited. The response of the Ministry is being awaited.
I advised management to further follow up with the Ministries of Foreign Affairs
and that of Finance, Planning and Economic Development to review the structure
so that corresponding resources are provided.
67.0 UGANDA EMBASSY, BERLIN
a) Unauthorized Over expenditure
A review of financial statements revealed that the Embassy incurred 21,874,544 in
excess of the approved budget of UGX. 2,536,000,000. However, there was no
documentary proof to the effect that the necessary approval in the form of
virements/reallocation warrants was granted contrary to section 17 of the Public
Finance and Accountability Act, 2003. Under the circumstances, the expenditure is
considered not to be a proper charge to government funds.
774
Management acknowledged the anomaly and indicated that they will liaise with
treasury to regularize this expenditure . I have advised management to always
ensure that approval is obtained prior to spending.
b) Mission Charter
It was noted that the Berlin mission charter was issued to H.E. the Ambassador in
February 2014 by the Minister of Foreign Affairs; however the following
inconsistencies were noted
The charter mentions only 2 countries which is Germany and Austria. The fate
of other countries that have hitherto been under the jurisdiction of the Berlin
mission which include the Czech Republic, Poland, Hungary, The Holy See
(Vatican), Slovakia, Bulgaria, Romania plus UN Organizations in
Bonn(Germany) and Austria is not known.
Although all the Letters of Credence for the countries and bodies mentioned
above were signed by HE the President in August 2013, the Current
Ambassador has only presented Credentials to Germany, The Holy See
(Vatican) and the International Atomic Energy Agency (IAEA) in Vienna.
These conflicting objectives undermine the embassy‟s efforts of fulfilling its
mandate. Delays or failure to present Letters of Credence to the respective
countries denies Uganda formal representation.
Management explained that upon realizing the omission of most countries in the
mission charter the issue was reported to the concerned authorities and is being
looked into. Management attributed the non-presentation of letters of credence to
insufficient funding.
I have advised management to liaise with the Ministry of Foreign Affairs to
harmonize the Mission charter so that it‟s consistent with the strategic objectives
of the embassy. Efforts should also be made for presentation of outstanding
letters of credence to the related countries in order to foster the embassies
operations in those jurisdictions.
c) Over Expenditure on Telephone Expenses
775
Section (H-e) regulation 14 of the Public Service Standing Orders, 2010 states that
“All calls at residences, official or otherwise, of Heads of Mission should not exceed
USD 500 per month”. However examination of the payment vouchers revealed
that a total of USD 6,870 (5,056 Euro) (details in appendix 1) was spent over and
above the stipulated limit contrary to public service standing orders. This implies
that funds were diverted from some budget lines to finance the expenditure and
this negatively impacted on the implementation of some of the planned activities.
Management in response undertook to comply henceforth. I await the outcome of
management‟s commitment in this regard.
d) Overpayment of Foreign Service Allowances
Section (E-e The Public Service Standing Orders 2010) states that, each Foreign
service Officer is entitled to a Foreign Service Allowance. The rates payable to
each Foreign Service officer are clearly spelt out in the Permanent Secretary‟s
communication of reference COM 95/100/01 dated 16th June 2011.
However examination of the payment vouchers revealed that some officers were
paid Foreign Service allowance at a rate higher than the rate stipulated in the
permanent secretary‟s communication hence causing unauthorized Foreign Service
allowance totaling USD 40,784.1, this is considered irregular and hence
recoverable.
Management explained that this anomaly arose because of the standardization of
the exchange rate between a Euro and Dollar.
I have advised management to recover the unauthorized amounts paid in respect
of Foreign Service allowance and in future ensure that payments are based on the
dollar equivalent at the time of payment.
776
68.0 UGANDA EMBASSY BRUSSELS
a) Budgeting and funding
The Ugandan Embassy in Brussels covers Belgium, the Netherlands, Luxemburg,
as well as the European Union and the International Court of Justice (ICJ). For the
financial year 2013/14, a sum of UGX.3,278,099,906, was released to implement
planned activities in the above areas as per the approved budget.
However, during discussions with Her Excellency the Ambassador, it was noted
that due to many special assignments handled by the Mission, this ultimately leads
to more frequent travels abroad, which eventually implies that the budgeted funds
are always not adequate.
I advised management to bring this matter to the concerned stakeholders,
including the ministries of Foreign Affairs as well as that of Finance, Planning and
Economic Development, so as to have their budget amounts improved upon.
b) Unauthorised Over Expenditure – UGX.390,437,807
Regulations 39 and 40 of the Public Finance and Accountability Regulations, 2003,
require the Accounting Officers to adhere to the budgetary allocation per vote or
obtain prior permission before an over expenditure is incurred.
Contrary to the above, a review of the financial statements for the year under
review revealed that actual expenditure on goods and services exceeded the
budgeted amount by UGX.390,437,807. There was no evidence provided to show
that authorization for the over expenditure was sought from, and granted as
provided for by the regulations. Further noted was that, a sum of
UGX.150,514,718 was diverted from capital development budget to cater for travel
expenses, which had not been budgeted for under the recurrent budget at the
beginning of the financial year. The act may have hampered the implementation
of capital development activities.
The Accounting Officer stated that the above was due to unforeseen/unplanned
need for foreign travels for which the Embassy had no control over, and that in
777
future, the proper procedure would be followed by first seeking authority from the
Permanent Secretary/Secretary to Treasury.
c) Non Tax Revenue (NTR) reconciliation:
Lack of a Visa Issue Ledger
A review of Visa stationery was carried out to determine the accuracy of the
reported NTR of UGX.283,680,935 collected during the year. Whereas the total
NTR collections reconciled with used visa counterfoils, the review revealed that no
Visa issue ledger exists to record the movement of the visa stationery, which
comprise of Single entry, Multiple, Gratis and Transit visa stickers, and Emergency
Travel documents. The only records availed were in respect of receipts of Visas
during the year. Under the circumstances, I could therefore not determine the
opening stock balances of visa stationery at the start of the financial year as well
as the closing balances. Although a board of survey was constituted at the close of
the year, there was no report submitted to confirm the closing balances of visa
stationery as at 30th June 2014. There is a risk of un-accounted for revenue arising
from issuance of unrecorded visa stationery.
In his response, the Accounting Officer regretted this anomaly and indicated that a
Visa Issue Register has been opened effective 2014/15 financial year.
d) Irregular payments under Foreign Travel
The Embassy sought the services of an Architect from the Ministry of Works and
Transport to assess the status of embassy buildings on an understanding that it
could cater for travel and other allowances for the officer abroad. I noted that,
during his first visit, the officers‟ stay was extended for a further seven (7) days,
which was not authorized by the Permanent Secretary, Ministry of Foreign Affairs.
Similarly, the same officer was again invited on a second visit to finalize the work
and as a result the embassy further catered for the officer‟s stay for another three
(3) days, including transport refund on train ticket and an additional allowance for
two (2) days while travelling from Copenhagen, Denmark.
A review of expenditure documents in respect of the above visits revealed that a
sum of Euros.4,469.18 (UGX.15,038,567) was irregularly paid to the officer from
778
the Ministry of works and Transport, since the visits lacked clearance from the
Accounting officer of the Ministry of Foreign Affairs in Kampala. Details of the
payments are indicated in the table below;
Voucher
number
Purpose Amount
in Euros
Comments
PV1707/12/13 Extra per diem for 7 days 2,135.59 Extension not authorized by
MoFA
PV2381/06/14 2 days per diem and train
ticket to Brussels from
Paris
709.17 Travel to Brussels not
authorized
PV2335/06/14 3 days per diem in
Brussels from Paris
1,624.42 Travel to Brussels not
authorized
TOTAL 4,469.18
In his response, the Accounting officer regretted that authority for the stay and
subsequent visit by the Ministry of Works official was not obtained, and stated that
in future, authority would first be sought before extending the stay or inviting
technical officials from MDAs.
e) Human Resource Management matters
A review of staff records and interviews held with management revealed the
following;
a. Undisclosed contingent liability
An interview with the Head of Mission revealed that one of the Embassy drivers
had reached his retirement age of 65 years (May 2014) towards the end of the
financial year under review. According to the Belgian laws, the driver is entitled to
a gratuity covering his entire service period to the Embassy, which amounts to
thirty two (32) years. This amount is payable by the Belgian Social Security Fund,
to which, according to the Accounting Officer, is equivalent to the employee‟s
monthly salary payable throughout the employment period.
However, I noted that the Embassy had only made contributions for the last seven
years, implying that the driver is entitled to gratuity for only seven years. This is a
contingent liability which should be recognized and settled by the Embassy to
779
avoid being sued by the driver, as well as payment of a heavy fine to the Social
Security Fund for the period defaulted.
Management explained that it decided to retain the driver as it handles the matter
with the Social security fund through the Embassy lawyers, so as to mitigate the
heavy fines associated with the circumstance. The Accounting officer stated that
he had written to the relevant authorities requesting for funds to cover the
outstanding amounts under domestic arrears. I have advised that this action be
expedited, to avoid further exposure by the Mission and to also compute and
recognise this contingent liability in the financial statements.
b. Absence of employment contracts for local staff
An interview with the Accounting Officer revealed that Belgian laws provide for a
person to be employed on contract for one year, renewable once, or a non-
renewable contract running for two years.
An interview with the local staff revealed that none of the five local staff (including
the retired driver) had an employment contract. This implies that they are illegally
employed and being paid, with a possibility that some have exceeded the
contractible periods.
In addition, it was noted that, according to Belgian laws, a driver is contracted to
drive a particular type of car, which should be stated in the contract. However, to
the contrary, one driver was switched from driving the official car to a utility van,
which necessitated a new contract. This was not duly implemented, exposing the
Embassy to the risk of a law suit, as the driver has already notified of his
intentions to sue.
The Accounting officer stated that they were discussing with the lawyers on how
to resolve the issues raised. I have advised the Accounting Officer to always
ensure that all efforts are made to abide by the local laws so as to avoid
imposition of penalties and fines.
c. Lack of performance plans at the start of the appraisal period
780
Management of staff performance requires the appraisees to agree with their
supervisors at the start of the period, the activities, key performance indicators,
and outputs/target for the appraisal period. The agreed outputs together with the
activities constitute staff performance plans, which should form the basis of
appraising staff at the end of the appraisal period.
However, it was noted that staff at the Embassy did not have performance plans
agreed with the supervisors at the beginning of the period. As a result, there were
cases of appraisees not agreeing with the performance appraisal results at the end
of the financial year. Lack of performance plans with clear outputs/targets limits
the full attainment of the objectives of performance appraisals at the end of the
period.
In response, the Accounting officer stated that management was following up on
the performance plans to ensure that they are discussed and appraisals submitted
at the end of the financial year. I await the outcome of this management
commitment.
f) Inspection of Government properties
The Uganda Government owns three mission properties in Brussels which consist
of the Chancery, official residence and a vacant plot on 35 Clos Des Lauriers
Woluwe St Pierre, which formerly housed the official residence that was later
demolished due to continued non maintenance. Physical inspection of the embassy
properties revealed the following;
a. Chancery building
During inspection of the chancery building, situated at Avenue de Tervuren 317 in
Brussels, it was revealed that the building had not had major renovations of recent
and as a result, it was in a state of disrepair requiring substantial provision of
money to have it renovated. There was complete lack of routine and periodic
maintenance activities required because of the weather conditions. The structure
continued to deteriorate with water leakages from the roof destroying the walls
and ceiling, the basement floors were in a sorry state and inhabitable, some walls
in the building had developed mould which is considered to be toxic and a health
781
hazard, while most of the walls and the ceiling had developed major cracks putting
the lives of the users at great risk.
Given the current state of the building, it is not insured, exposing Government to a
risk of potential loss should it get seriously damaged, say by fire. Management
explained that an assessment of the status of the buildings had been undertaken
and recommendations made by the property management team from Ministry of
Foreign Affairs. Accordingly, a sum of UGX.450 million was released during the
year, out of a budget of UGX.1.18billion to start the renovation works. However by
the time of inspection, no major renovations were noted on the plots, except on
the current official residence.
The Accounting Officer concurred that the building was not insured because of its
state, and commencement of renovations had been delayed by the procurement
process, but is expected to start soon. I advised the Accounting Officer to expedite
this process so as to have the renovations undertaken.
b. Official residence
An audit inspection of the Official residence revealed that some renovations had
been undertaken mainly on the heating, electric system and paintwork. There
were notable defects on the building with mortar peeling off the walls on the
outside and heat insulation. The heating system, though improved, still had
defects like poor insulation, leading to substantial heat loss during winter. There
are also faulty plumbing systems in the bath rooms. There is a risk that the facility
may deteriorate further if no major renovations are undertaken.
In his response, the Accounting officer stated that the renovations of the official
residence was on going, and funds to pay for them were being awaited.
c. Redevelopment of plot of land formerly occupied by official
residence
Following the demolition of the former official residence at 35 Clos Des Lauriers
Woluwe St. Pierre, the asset (plot) was stripped of its diplomatic immunity, which
was granted to the current residence occupied by the Ambassador. Consequently,
782
the City Authorities have asked the Embassy to redevelop the plot as soon as
possible. There is a risk that if the redevelopment is not undertaken within the
time frame given, the plot which is located in a very prime area, will be forfeited,
as its current state has made the neighbouring properties lose value.
The Accounting officer stated that Ministry of works officials inspected the plot and
proposed construction of two houses, and accordingly management submitted the
construction estimates to the Ministry of Foreign Affairs for appropriate action, and
budgeted for them in the financial year 2015/16. I advised that this matter be
followed up to avoid the risk of forfeiture of the plot in question.
69.0 UGANDA HIGH COMMISSION, BUJUMBURA
a) Unacknowledged Remittances
Included in the statement of financial performance for period ending 30th June
2014 is a transfer to treasury amounting to UGX.13,833,381. However, the
transfer was not supported with acknowledgement receipts from Accountant
General. The Accounting Officer explained that a bank statement was available to
support the transaction.
I advised the Accounting Officer that the Bank statement is not adequate since it
lists down various transfers. The acknowledgement receipt corresponding to the
transfer should be availed for verification.
b) Failure to translate transactions
Included in the statement of financial position are receivables amounting to
UGX.3,966,456. However, the details/ schedules for the receivables were not
translated into English as required by Section (P-b) (7) of the Public Service
Standing. Though the Accounting Officer explained that the receivables were tax
refunds from Burundi Revenue Authority, verification could not be done since the
language used was French.
I advised the Accounting Officer to submit details in the reporting currency for
verification.
783
c) Arrears of Revenue
Included in the statement of arrears of revenue is a total of UGX.3,994,965 being
arrears of revenue as at 30th June 2014. However, there was no evidence to show
that management made efforts to recover the arrears. Accumulation of revenue
arrears may result into bad debts. The Accounting Officer explained that the
arrears of revenue were tax refund claims made to Burundi Revenue Authority and
the claims would be followed up.
I await management‟s action on this matter.
d) Refund of Medical Expenses
A total of BIF.3,361,296 (UGX.6,344,068) was refunded to various officials of the
Embassy in respect of medical bills because management did not register with a
health insurance scheme contrary to sections (M-a) (14) and (F-a) (3) of the
public service standing orders. This practice is bound to be abused because it is
difficult to verify the correctness of receipts obtained from the various health units.
Though the Accounting officer explained that the medical services in Burundi are
in a poor state, this was not brought to the attention of the Permanent Secretary
Ministry of Foreign Affairs as provided in the standing orders.
I advised management to liaise with the Permanent Secretary Ministry of Foreign
Affairs and the Director General of Health Services in Uganda for an appropriate
remedy.
e) Irregular Power Refunds
Section (H-e) (9) of the public service standing orders requires every public officer
at the Embassy to be responsible for the cost of lighting and water consumed in
any house allocated to him or her. However, BIF.534,000 (UGX.1,007,865) was
incurred on electricity bills for residences of staff of the Embassy making this
expenditure irregular and therefore recoverable.
The Accounting Officer stated that Burundi was situated in or near the subtropical
dry forest biome with a pronounced dry season and long periods of drought that
necessitated incurring costs of cooling for officers.
784
I advised management to liaise with MoFA and MoFPED to consider regularizing
the expenditure.
f) Vehicle Maintenance
The Embassy spent BIF.7,284,164.81 (UGX.13,748,041) in respect of vehicle
maintenance and equipment repair. However, the payment vouchers were not
supported with documents such as requisitions, purchase orders, receipts, pre
and post maintenance reports and quotations from at least three garages. The
prequalified list of suppliers and minutes of the contract committee were also
missing. Unsupported expenditure could lead to misappropriation of funds.
The Accounting Officer explained that public procurement processes were under
developed in the country and transactions were basically cash basis.
I advised management to ensure internal procurement processes are adhered to,
and all the relevant supporting documents are submitted for verification.
70.0 UGANDA EMBASSY, CAIRO
a) Budget Performance - Recurrent
The activities and operations of the Mission are financed through budget support
by Government of Uganda. In the financial year under review, the mission
received a sum of UGX.1,321,748,000 against an approved budget of
UGX.1,321,749,000, which constituted 99.9% budget performance level. However,
comparing this performance with previous year, the mission‟s budget declined by
UGX.52 Million in recurrent budget support as indicated in the table below;
Analysis of budget performance-Recurrent
Financial Year Initial Budget
(UGX)
Revised
Budget
(UGX)
Actual
Release
(UGX)
Budget
performance
(%)
FY 2012/13 1,662,518,484 1,373,748,679 1,373,748,679 100%
FY 2013/14 1,321,749,000 1,321,749,000 1,321,748,000 99.9%
Variance 51,999,679 52,000,679
785
With the increased responsibilities of the mission as described in its Mission
Charter, the reduction in its budget may negatively affect its capacity to effectively
deliver its mandate.
I advised the Accounting Officer to liaise with the responsible authorities, to
ensure that the identified priorities in the Mission Charter are adequately funded
during the budgeting process.
b) Budget Performance-Capital development
In the FY 2013/14, a sum of UGX.250 Million was budgeted and released to the
Mission to cater for capital development expenditure. However, I noted that out of
the funds released, only UGX.140,133,583 was spent on renovation of the
Chancery. The balance of UGX.109,866,417 remained unspent at year end. I was
not availed any evidence to show that authority was granted to the Mission by the
PS/ST to retain the unspent funds as is required under the TAI, 2003.
The Accounting officer explained that the Mission received a directive from the
Ministry of Foreign Affairs, to stop the ongoing works at the residence until further
notice and this was at the beginning of a new financial year, when funds had
already been committed to the said activity. However, Management will ensure
that it seeks authority to retain unutilized funds at the close of every financial
year. I advised the Accounting Officer to ensure that authority to retain unutilized
funds at the close of the year is always sought and obtained as required by the
TAIs.
c) Non-Tax Revenue
The Mission collects its NTR from administrative fees and miscellaneous revenue,
which mainly includes proceeds from the issuance of Visas, and travel documents.
In the financial year under review, a total of UGX.115,291,861 was collected.
However, scrutiny of NTR transactions revealed the following irregularities;
a. Unbudgeted NTR
Paragraph 2(c) of the third schedule of the Public Finance and Accountability Act
2003, requires the Accounting Officers to submit to the Accountant General a
786
statement of revenue received during the year, showing the amount contained in
the estimates of revenue for each source of revenue, the amount actually
collected, with explanation for any variation between the revenues collected and
estimated.
Contrary to the above provision, the mission did not provide an estimate of
revenue to be collected under NTR in its annual budget for the year under review.
As a result, management could not assess and monitor its revenue performance,
and submit accurate revenue returns to the Accountant General. This poses a high
risk of misuse of such funds.
The Accounting Officer explained that the mission collects Non tax revenue only in
the form of Visa fees, Endorsements and Emergency travel documents. These are
variable fees and very hard to estimate, however, the mission would seek further
guidance on the issue from the concerned departments. I advised the Accounting
Officer to start budgeting for NTR as per the provisions of the Public Finance and
Accountability Act, 2003 to enable the Mission assess and monitor NTR
performance.
b. Non remittance of NTR to the Consolidated Fund
Paragraphs 98 – 102 of the TAI, 2003 specify how Accounting Officers should
account for revenue collected. Included in the specifications is the requirement to
transfer money to BoU on an account designated by the Accountant General from
which such revenue is periodically transferred to the Uganda Consolidated Fund
(UCF) Account. On Transfer of the revenue to the UCF, both the Accountant
General and the Accounting Officer are notified by BoU.
I noted that at the closure of the financial year under review, the Accounting
Officer did not transfer all the collected revenue to the UCF as required by TAIs,
hence leading to the creation of unnecessary arrears of revenue, which stood at
UGX.93,194,267. The failure by the Accounting Officer to remit monies to the UCF
denies government of the revenue required to implement its programmes, thus
affecting service delivery. In addition, it increases the risk of misuse of the funds if
787
strict adherence to regulations prohibiting utilization of funds at source is not
observed.
The Accounting Officer attributed this anomaly to the political situation in the
country and the fact that the Central Bank put restrictions and a limit to the
foreign exchange out flow. I advised the Accounting Officer to liaise with the
PS/Ministry of Foreign Affairs and the PS/ST to find out a solution to this
challenge.
d) Irregular Payment of Staff rent - USD.66,500
Examination of payment vouchers revealed that staff were directly paid monies in
respect of their rent totaling to USD.66,500 (Approximately UGX.186,200,000)
instead of the amounts being paid to the landlords. In addition, the monies were
being paid to staff in cash, thus increasing a risk of misuse by staff through
fraudulent activities, such as paying for less expensive and unbefitting
accommodation, and irregularly saving on the balance of the amount claimed. I
further noted that some staff were paid for rent periods that did not fall in the
respective financial years being charged without declaring the source of the funds
in the budgets.
Scrutiny of the lease agreements further revealed the following irregularities;
The lease agreements were drawn in English by the Mission staff and not
translated in Arabic (official language of the host country), thus standing a risk
of limited legal enforcement, especially in a foreign country.
Some lease agreements had no dates of expiry indicated, thus leaving them
open for unspecified periods. Although they contained a provision of automatic
renewal in case the occupant continued using the premises, it is important that
the start and end dates be specified in the agreements.
The lease agreements required landlords to furnish the client with a
list/inventory of household items, but in most of the agreements reviewed the
lists were not provided.
Some agreements lacked the telephone contacts of the landlords, although this
was specifically provided for.
788
Given the above mentioned irregularities in the agreements and the method of
cash payment to the landlords, the rent transactions are susceptible to abuse.
The Accounting Officer explained that;
In the near future the mission shall ensure that contracts are drawn up by a
law firm and also translated to Arabic. Regarding the lease period, they had
assumed that in the absence of notification from either party, the rent for the
next period becomes automatic as stated in the agreement.
The Mission always recommends that all officers rent fully furnished apartments
to avoid purchasing of house hold items by the Mission hence all inventory for
the officer‟s apartments are available in their respective places of residence. We
shall get a copy and attach it on the new agreements accordingly.
Telephone contacts for the various landlords will be added to each agreement.
I advised the Mission Management as follows;
The Accounting Officer should desist from paying cash to landlords and all
payments to landlords should be by bank.
The Head of Mission should ensure that legally binding lease agreements
are drawn by a reputable law firm in the country to avoid undesirable
circumstances that may occur in future.
e) Payment of Child Education Allowances
Section E-e (Foreign Services Allowances) Paragraph 12-20 of the Public Service
Standing Orders, 2010 (Revised), prescribe the preconditions for the payment of
Child Education Allowance to mission staff. In particular, Paragraph 19 provides
for the payment of education allowance directly to the school and reimbursement
from the officer for his/her personal share should be made at source.
Furthermore, Paragraph 20 of the same Standing Orders provides for each
application for an education allowance to be approved by the Responsible Officer
and must be accompanied by a certification by the Head of Mission confirming;
The circumstances provided by the officer are correct;
The period of education to be carried;
The date of birth of the child; and
The evidence of child parenthood/adoption.
789
During the period under review, child education allowance totaling USD.14,000
(Approximately UGX.39,200,000) was paid to staff of the mission. However it was
noted that the allowances were paid to the individuals (Mission staff) without
evidence on staff personal files of approval of the prescribed conditions by the
HoM, and there were no receipts from the schools acknowledging payment of the
amounts.
In the absence of certification by the HoM and the relevant supporting
documentation, the possibility that allowances were not paid for the intended
purposes cannot be ruled out.
The Accounting Officer explained that Payment of child education allowance was
standardized by the Ministry of Public Service and it was advised that for all
officers who have children between the ages of 4 and 18 must be paid a uniform
amount of money (i.e. Us$.2,000) per child every year irrespective of how much
the officer is actually paying.
I noted that although the circular standardized the amount to be paid per child
every year, it remained silent on the provisions in the Public Service Standing
Orders that prescribe how child allowance should be paid and accounted for. I
advised the Accounting Officer to liaise with PS/MoFA and PS/MoPS to ensure that
the circular directives are harmonized with the Public Service standing orders.
f) Staff Insurance and Medical Refunds
Section M-a (Medical Attention) Para.14 of the Public Service Standing Orders,
2010 (Revised) requires a Foreign Service officer to be fully covered by a medical
insurance. I noted, in accordance with the above provision, that the mission was
paying for medical insurance to a few staff and had incurred a sum of EGP.6,845
(Approximately UGX.2,590,000) in the period under review.
However, I further noted that the mission was spending heavily on staff medical
refunds and as a result, a sum of EGP.120,489 (Approximately UGX.45,590,360),
which was almost eighteen times more than what was paid in staff medical
insurance scheme. Those payments were found irregular, given the fact that the
790
staff were supposed to send their medical claims to the insurance companies for
settlement. Notable incidents included the following;
The treatment of one staff, who is said to be terminally ill, is drawing a
significant proportion of staff medical refunds. Given the officer‟s current
health condition, the mission cannot continuously sustain payment of his
medical bills without suffocating the payment of other financial obligations.
The treatment of HoM, when he was involved in a motor accident in Kampala,
has also exerted financial pressure on the mission budget. A sum of
USD.6,000 had been spent on his treatment and was still undergoing
treatment at the time of the audit (November, 2014). An outstanding claim for
medical bills incurred in Kampala of UGX.5,427,160 had not been settled by
the Accounting Officer as directed by the PS/Ministry of Foreign Affairs.
The treatment of Administrative Attaché also significantly drained the mission
resources.
The above cases and many others, cannot be sustained by the mission‟s meager
resources, hence the urgent need for a comprehensive insurance scheme for all
mission staff.
The Accounting Officer explained that the above matter was being looked into but
it has been difficult to find an insurance company with 100% comprehensive
coverage. She further explained that she had written to different insurance
companies and was still looking around to make sure this issue is resolved
notwithstanding the ailments that are not covered. I advised the Accounting
Officer to take up the matter with the relevant authorities to ensure that a
sustainable solution is reached.
g) Repair of Vehicles
A sum of EGP.139,082 (Approximately UGX.52,625,621) was spent on repair of
the two utility vehicles and one representation car in the year under review.
However, the following anomalies were noted;
Although there used to be a sound vehicle repair system, it has currently
broken down, whereby drivers do not report vehicle repair requirements in
791
writing; vehicles are not inspected before and after repairs; and garages are
being paid in cash other than by cheques or bank transfers.
The representation vehicle has been involved in a series of accidents more
than the other two vehicles since its acquisition in 2005. However the major
accident, which cost the Embassy heavily, occurred at Cairo International
Airport whereby a substantial amount of EGP.84,370 (Approximately
UGX.31,923,783) was paid to a repairing firm. Although the vehicle was
comprehensively insured, the insurance company refunded the Embassy only
EGP.32,978 (39.1% of the cost incurred), due to the fact that the car was
improperly handled by the driver right after the accident. According to the
insurance company, the driver tried to drive the car immediately after the
accident instead of putting it on a car carrier, thus causing more significant
damage than what was caused by the accident itself. Through negligence, the
driver occasioned a financial loss of EGP.51,392 (Approximately
UGX.19,445,621) to government.
Although the payments were supported by receipts, invoices and other
supporting documents, I could not fully rely on them because of the
weaknesses in the vehicle management system.
The Accounting Officer explained that the Mission was in the process of putting up
a tightly controlled fleet management system as recommended. I advised the
Accounting Officer to restore the vehicle management system to oversee vehicle
repairs, fuelling and movements. In addition, all vehicle repair bills should be paid
through the bank.
h) Management of Imprest
Paragraph 20 of the TAIs requires Imprest holders to be appointed by the
Accounting Officers on specific approval by the Accountant General. Paragraph 23
of TAIs further specifies that all appointments of Imprest holders must be notified
to the Accountant General, Auditor-General and the officer to whom the Imprest
Holder is to account. Para 24.of TAIs require that in fixing the amount of the
imprest, Accounting Officers appointing Imprest holders will have regard to the
792
facilities available to them for the safe keeping of money, and will not authorize
the holding of sums larger than those for which suitable accommodation is
available.
I noted that the Accounts Assistant also doubled as the Mission‟s Imprest holder,
but contrary to the above provisions in the TAIs, he was not duly appointed. I
further noted that large amounts of money would be drawn ranging between
UGX.1 million to UGX.50 million as imprest and there was no imprest limit set by
the Accounting Officer. I further noted that although the Accounts Assistant
properly maintained the imprest cash book and accounted for the imprest
advances, some ineligible expenses, such as: vehicle repairs (notably EGP.84,370,
which was paid to a garage when the representation vehicle was involved in an
accident); staff medical claims and telephone expenses-international VOIP that
would be charged from the Mission‟s operation account, were charged on imprest.
In his response, the Accounting Officer acknowledged the anomaly and indicated
that an imprest holder would be appointed going forward. I advised the
Accounting Officer to expedite this action and also ensure that imprest
management is in accordance with the provisions under the Treasury Accounting
Instructions, 2003.
i) Procurement
a. Absence of a Procurement Plan
Regulation No.96, sections (1) to (3) of the PPDA Regulations, 2003 requires a
user department to prepare and submit to the PDU a multi-annual rolling work
plan for procurements based on approved budget. The procurement plan should
enhance financial predictability, accounting and control over procurement budgets.
In addition, the plan should facilitate the entity to plan, organize, forecast and
schedule its procurement activities.
A review of the mission‟s procurement files and records showed that the mission
did not have a comprehensive procurement plan in a format prescribed by the
above regulation. Although the Accounting Officer explained that the Mission had
a procurement Plan, the plan availed was a listing of the items to be procured with
793
no details such estimated amounts, procurement method and timing. In addition,
there was no evidence to indicate that the mission prepared and filed procurement
returns with PPDA Authority.
I advised the Accounting Officer to ensure that procurement plans are always
prepared in accordance with the PPDA regulations, to effectively guide the
mission‟s procurement activities. In addition, procurement returns should be
prepared and filed with PPDA authority.
b. Absence of Evaluation Committee
Regulation No.169, Section (1) of the PPDA Regulations, 2003, requires an
evaluation to be conducted by an Evaluation Committee (EC). Section (2) of the
same regulation requires the Procurement and Disposal Unit (PDU) to recommend
the membership of the EC to the Contracts Committee (CC) for approval.
According to Section (3) of the Regulation, the number of members will depend on
the value and complexity of the procurement requirements, but shall not be less
than three. Section (4) further requires that the members should be of an
appropriate level of seniority and experience depending on the value and
complexity of the procurement.
A review of the procurement files for the mission revealed that all awards by the
Contracts Committee (CC), were not backed by recommendations of an evaluation
committee contrary to PPDA regulations. In some instances, the CC would
irregularly constitute itself into an Evaluation Committee in the same meetings of
tender award, thus adapting the name “Evaluation/Contracts Committee”.
However, during discussions with the mission staff, it was noted that with the
appointment of the CC, the other remaining staff (i.e. HoM, A/O and Accounts
Staff) by nature of their duties, would automatically not qualify to serve as
members of the EC. I noted the leanness of the Mission staff structure and found
out that it hinders the separation of the EC from CC. The absence of a technical
evaluation committee not only contravened the PPDA regulations, but also
resulted into various irregularities being committed by the CC as discussed in the
subsequent paragraphs.
794
The Accounting Officer explained that the Mission will seek guidance from relevant
authorities regarding the above aspect and also conduct training for staff involved.
I await the outcome of this management commitment.
c. Botched Renovation of the Official Residence
Two companies were invited to tender for renovation works at the official
residence. However the following anomalies were noted;
No evidence was availed to indicate that the works were advertised and
request for bids sent to bidders. The method of direct procurement as
explained by management, was not appropriate given the nature of the
contract and the procurement threshold prescribed by PPDA regulations.
The two companies each quoted for works in different currencies. It was
noted that without an evaluation report, the CC went ahead to award the
contract to one of the companies.
The scope and magnitude of renovation works were not first ascertained by
the Mission and as a result, each bidder visited the official residence to
determine for themselves what the works would entail. This implied that there
could not be an effective comparison of the two bids since there was no
common stand on the scope of works.
Due to the threat to sue by the other company which lost the tender, and the
decision by H.E the Ambassador to stop the contractor, the CC on its sitting
on 8th July, 2014, under minute 1/07/2014, decided to defer the renovation
works. However, there is no evidence on the procurement file indicating that
the decision was duly communicated to the company that had been awarded
the contract.
In its effort to rectify the situation, management requested for the works to
be assessed and sought assistance from government engineers from the
Ministry of Works and Transport (MoW&T), who were facilitated by the
embassy to the tune of EGP.13,500 (UGX.5,108,108) in air tickets. However,
at the time of the audit (November, 2014), the Engineers had not provided
795
the Mission with an assessment report and as a result the procurement
process had stalled.
Government had released a sum of UGX.250,000,000 for capital development,
but as at closure of the financial year, only UGX.109,866,417 had remained
unapplied. There is a risk that the funds may continue being applied on other
mission activities if the tender process is not expedited.
The Accounting Officer explained that the Mission will send a reminder to the
officials from Ministry of Works to furnish management with a proper works
assessment report to allow the procurement process to commence. I advised the
Accounting Officer to expedite this action, and ensure that proper procurement
procedures are observed in accordance with the PPDA regulations.
d. Procurement of Office Laptops
Three firms were sourced by the mission through direct physical contact, to supply
four office laptops. The following anomalies were noted;
Although the CC opted for the direct method of procurement, there is no
evidence that the technical specifications, such as: storage memory,
processing speed, monitor size, etc, had been specified, to allow for easy
comparison during evaluation. Although the awarded firm had quoted lower
than others, the comparison was not done on standard technical
specifications.
There was no technical evaluation report on file to back the decision of the
CC, despite the complex nature of the procurement.
According to the quotation from one of the firms, it indicated that it was
authored on the 17th June, 2014. Comparing this date with the date of CC
sitting on 18th June, 2014, it was revealed that the procurement was hurriedly
concluded, thus posing a risk that the mission may not have obtained value
for money in the procurement due to the opted procurement method.
The Accounting Officer explained as follows;
796
The late award of the tender was as a result of administrative issues in terms
of interference in the work of the contracts committee. The committee was
not independent hence the delay.
As long as there is no interference in the activities of the contracts committee
all future procurements will be concluded according to the plans set in the
PPDA regulations.
I advised the Accounting Officer to ensure that future procurements are concluded
according to the procurement plan and in accordance with the PPDA regulations.
e. Redesigning of the Chancery Reception
Three firms were invited for redesigning of the chancery reception and the
contract was awarded to one of the firms for USD.10,000. It was noted that the
redesign of the chancery reception has improved the general appearance of the
Embassy. However, the following anomalies were noted;
There was no evidence on the procurement file to indicate that the evaluation
committee report was prepared before the award by the CC.
One firm quoted in a different currency and there is no evidence to show that
the CC committee made a currency conversion to enable equitable
comparison.
There was no evidence on file to indicate that specifications for the works
were prepared and communicated to all firms.
The work of the redesign of the reception was so technical, thus needed a
fully constituted technical evaluation committee.
The procurement method used was beyond the PPDA permitted threshold of
such works.
No designs were obtained from the other two companies apart from the one
that won the tender.
The Accounting Officer acknowledged the above anomalies and indicated that all
mission procurements will in future be conducted in accordance with the PPDA
regulations. I await the outcome of this commitment by the Accounting Officer.
797
j) Mission Charter and Performance Reporting
The Embassy prepared a mission charter to facilitate its service delivery by
focusing on three thematic areas: Economic/Commercial diplomacy;
Regional/International peace and security; and the well-being of Ugandans. In
order to further streamline its focus on the thematic areas, the Embassy
developed eight (8) strategic objectives, with clearly defined key outputs,
performance indicators, and performance targets, as indicated in paragraph 3.0
above.
In his letter referenced MFA/X/16 of 16th April, 2014, the Hon. Minister of Foreign
Affairs, further gave guidance to the HoM to give priority attention to the following
specific actions and report on them on a quarterly basis;
a) Engage Egypt to be supportive of various peace building
initiatives/processes on interest to Uganda and Great Lakes Region;
b) Lobby Egypt‟s understanding and appreciation of Uganda‟s position on
various important issues, particularly the Nile and regional geo-politics;
c) Facilitate promotion of at least USD.200M worth of Uganda exports to
Egypt annually;
d) Lobby for inward transfer of at least USD.300M worth of investment from
Egypt per year;
e) Facilitate attraction of at least 150,000 tourists from Egypt per year;
f) Handle at least 600,000 requests for Consular services annually;
g) Identify and facilitate of appropriate technology from Egypt;
h) Engage Ugandan Diaspora in Egypt to actively contribute to development
at home; and
i) Identify and facilitate acquisition, development and maintenance of at least
one Government property in Cairo annually.
A review of the 3rd quarter performance report of the FY 2013/14 submitted to
PS/Ministry of Foreign Affairs on 6th May, 2014, indicated promising results and
achievements by the mission. Notable achievements included;
Increased coordination of mission activities, including allocation of duties to
staff;
798
Followed the geo-politics in the countries of accreditation;
Coordinated UPDF and Police trainings in Egypt
Issued 225 visas; and
Received company profiles of firms interested in renewable sources of energy,
gas supply and oil refinery.
I did not review the 4th quarter report as it was not availed to me. However,
comparing the mission charter strategic objectives, key outputs, performance
indicators and targets, with the mission quarterly performance report, the
following areas of improvement are suggested;
Staff activity reports should be prepared in line with their allocated duties,
which should also be linked to the strategic objectives of the mission charter.
The quarterly performance report by the HoM should be linked to staff activity
reports.
The Quarterly performance report should, to a large extent, focus on the key
outputs, performance indicators and targets.
The Accounting Officer has committed to ensure that the Staff activity and
quarterly performance reports are improved and adjusted accordingly.
k) Cash payments of staff salaries
Paragraph 268 of the TAIs and Section B-a 9 of the Public Service Standing
Orders, 2010 (Revised), provide for payment of staff salaries into the individual
bank accounts of staff. I noted that in most occasions, staff salaries were being
paid in cash by the Accounts Assistant, after drawing lump sum amounts from the
bank. Such a practice exposes the mission to a risk of loss, given the risks
associated with cash. Besides, some officers had financial obligations (loan
repayments) with their banks. This implies that payment of salaries in cash may
hinder the recovery efforts by banks, which may in turn cause diplomatic
embarrassments.
The Accounting Officer explained that the payment method was adopted due to
the fact that only two officers hold bank accounts. Since the revolution in the
country, the Egyptian fiscal policies tremendously changed. For example, it takes a
799
lot of scrutiny just to cash the mission cheques. However, officers without bank
accounts have been advised to follow up with the various banks in order to get
bank accounts. She further explained that management would make all efforts to
minimize cash transactions. I advised the Accounting Officer to ensure that this
practice is stopped henceforth and that all salary payments are made through the
bank.
l) Staff Performance
Management of staff performance requires the appraisees to agree with their
supervisors on the activities, key performance indicators, and outputs/targets for
the appraisal period. The agreed outputs together with the activities constitute
staff performance plans, which should form the basis for appraisal of staff at the
end of the appraisal period.
However, there was no evidence on staff personal files, to indicate that the staff
prepared and discussed performance plans with their supervisors at the beginning
of the appraisal period, and that they were appraised at the end of the year. The
absence of performance plans, with clear outputs/targets, limits the effective
supervision and monitoring of staff activities, which eventually frustrates the
objectives of performance appraisals at the end of the period. In addition, this
affects the attainment of the objectives in the Mission Charter.
Further noted was that staff activity reports were not specific and did not, on
many occasions, contain measurable outputs or targets. They were so narrative
and could not be aligned back to the objectives of the Mission Charter. I advised
the HoM to ensure that staff performance plans, with measurable targets which
link to the objectives of the Mission Charter, are drawn at the beginning of the
appraisal period to form the basis of staff appraisal at the end of such periods.
m) Physical Inspection of Mission Properties
a. Chancery Building
The first phase of the renovation of the chancery building had just been completed
at the time of audit. The contractors for both the general renovation and redesign
800
of the chancery reception appear to have exhibited good workmanship skills.
Below are some of the photographs taken during inspection;
Photographs taken during inspection of the chancery building
Photograph Remarks
Photograph showing the front view of the newly redesigned chancery reception
Photograph showing the behind view of the newly redesigned chancery reception.
The photograph showing the recently renovated staff boardroom with new furniture.
b. Official Residence
The general condition of the official residence was generally appalling. The
residence is comprised of a storeyed building with servant quarters on the roof
top. The following conditions were observed;
The paint on the walls was peeling off;
The roof top was leaking whenever it rains;
The kitchen facilities including the cookers, fridges require urgent attention;
801
Electrical switches and sockets were found broken and the wires were
exposed, posing safety risk to the occupants; and
Water heaters were not functioning.
The Accounting Officer explained that the Mission was awaiting the MoW&T
engineers to finalize the assessment report in order to embark on the renovation
works.
I advised the Accounting Officer to liaise with the PS/Ministry of Foreign Affairs to
ensure that the MoW&T engineers finalize the assessment report, to enable the
commencement of the procurement process for the renovation works without
further delay.
n) Financial Statements
a. Staff Arrears and Other Commitments
A review of the financial statements (Statement of outstanding commitments)
revealed that, of the total outstanding commitments as at the beginning of the
year under review amounting to UGX.158,679,788, the Mission was only able to
pay UGX.2,644,082 during the year, leaving a balance of UGX.156,035,706
outstanding for more than a year. It is apparent that the Mission‟s efforts towards
settlement of outstanding arrears are minimal. Also noted was that a significant
portion of the outstanding commitments is staff social benefits of
UGX.106,912,112, which accrued due to failure by the mission to pay the „„13th
month‟‟ for the local staff. There is an increased risk of the mission being taken to
courts of law if the obligations are not settled and this may tarnish the diplomatic
image of the country.
The Accounting Officer explained that the matter was brought to the attention of
the Permanent Secretaries in the Ministries of Foreign Affairs and that of Finance
Planning and Economic Development. However, although these arrears have been
budgeted for in the past financial years, the funds in question have not been
availed to the Mission. I advised the Accounting Officer to continue following up
this matter until the obligations are settled.
b. Prepaid Rent
802
It was noted that rental payments totaling to USD.9,000 were made in respect of
periods straddling in the ensuing financial year, but were not recognized as
prepayments in the financial statements as prescribed in the accounting policies
Details as per table below;
Prepaid Rent not disclosed in the financial statements
DATE PVR.NO. CHQ.NO. DESCRIPTION AMOUNT (USD)
15/06/2014 PV-2479 CH.1177 Rents for (July-sept14) 4,500.00
15/06/2014 PV-2480 CH.1178 Rents for (July-sept14) 4,500.00
Total 9,000.00
Although the Accounting Officer explained that adjustments to recognize prepaid
rent would be effected in the financial statements, by the time of concluding this
audit, this had not been effected.
I advised the Accounts Assistant to recognize the amount of prepaid rent in
accordance with the prescription in the basis of preparation of accounts.
71.0 UGANDA HIGH COMMISSION, CANBERRA
a) Unspent Balances
Section 19 (1) of the Public Finance and Accountability Act(PFAA), 2003 require
unspent balances at the end of the financial year to be returned to the Uganda
Consolidated Fund (UCF). A review of the statement of financial position for the
year under review revealed unspent balances of UGX 107,200,862.60 at the year
end. Included in this amount was UGX 43,544,449.10 that remained unexpended
on the expenditure account which was not returned to the consolidated fund as
required. The authority for retention was not availed for audit.
The balance of UGX 63,656,334.20 related to Not Tax Revenue (NTR) that had not
been remitted to the treasury. It was explained that it was remitted on 3rd of July
2014 but the acknowledgement receipt from the Accountant General was not
presented for audit verification.
803
The Accounting Officer explained that the balance on expenditure account was
retained to finance bank standing orders and to cater for a new officer posted to
the mission but had not arrived. Regarding the lack of acknowledgement receipt
of the NTR remitted to the treasury, the Accounting Officer explained that the
mission had sent a reminder to the Accountant General‟s Office.
The Accounting officer was advised to seek authority for retention. Meanwhile the
acknowledgement receipt from the Accountant General for the remitted NTR
should be obtained and should be presented for audit verification.
b) Excess Expenditure
The statement of appropriation account (based on nature of expenditure for
services voted) revealed excess expenditure as follows:
Nature of expenditure
Initial budget (UGX)
Revised Budget(UGX)
Actual (UGX) Excess expenditure (UGX)
1 Employee costs
844,410,903.10 807,555,125.00 844,410,903.10 36,855,778.00
2 Goods and services consumed
838,338,427.70 838,338,427.70 842,643,386.60 4,304,958.90
Total 1,682,749,330.80 1,645,893,552.80 1,687,054,289.70 41,160,736.90
The Accounting Officer explained that excess expenditure was occasioned by
insufficient budget allocations on the items namely, medical expenses, electricity
and gas, computer supplies and welfare and entertainment.
The Accounting Officer was advised to seek authority from the Secretary to the
treasury whenever such shortfalls in the budget occur so that the necessary
budgetary revisions are undertaken.
c) Procurement of Goods
The statement of appropriation of account reported a sum of UGX 842,643,386.60
incurred on goods and services. Included in the sum was UGX 62,567,529.34
(AUD 25,424.55) incurred on procuring assets for the mission as shown below:-
804
Month Purpose Cheque Amount
(AUD)
1 July 2013 Furniture 2776 5,584.00
2 October 2013 Various Assets 2875 4,823.85
3 do 2858 939.00
4 do 2846 480.00
5 April 2014 do 3073 7,122.70
6 May 2014 do 3129 5,000.00
7 do 3110 1,475.00
Total 25,424.55
However, procurement files were lacking. Hence it was not possible to confirm
that proper procurement procedures were complied with. The Accounting officer
explained that the anomaly arose due to absence of the required procurement
structures and as such procurement files could not be maintained. She further
explained that the mission had only two home based staff and therefore it was
difficult to constitute the contract committee and procurement and disposal unit
under the circumstances.
However, the Accounting Officer had written to the Permanent Secretary/Secretary
to the Treasury regarding the matter.
Management was advised to ensure that the requisite Procurements structures are
instituted, staff trained and procurement files kept.
d) Renting of Property
It was observed that the mission does not own any residential property
.Accordingly the chancery, the official residence and other residences for staff are
rented at an annual cost of AUD equivalent to AUD 208,882.80 (UGX
514,039,999.50). Details are as follows:
Rented property Rent per
month(AUD)
Annual rent
(AUD)
1 Official residence 7000.00 84,000.00
805
Rented property Rent per
month(AUD)
Annual rent
(AUD)
2 chancery 3,823.81 45,885.72
3 Accounting Officer 2715.77 32,589.24
4 Posted foreign service
officer
1,868.45 estimated 22,421.40
5 Administrative attaché‟ 1998.81 23,985.72
Total 17,406.84 208,882.08
This cost would be saved in the long run if an attempt to acquire own property is
undertaken.
The Accounting Officer explained that the Head of Mission was following up the
matter with the Ministry of Foreign Affairs initially to provide funds for purchase of
land being offered by the Australian Government and thereafter source for funds
for putting up the chancery and official residence.
The Head of Mission was urged to follow up the matter and source for the
requisite funding.
e) Foreign Service Allowance
It was noted that the Foreign Service allowance (FSA) paid to the home based
staff to cater for their cost of living has never been reviewed by the ministry of
foreign affairs and public service for a long time. The FSA has now been eroded by
the expensive market prices in the economy. As a result management explained
that it is becoming increasingly difficult for the staff to live an affordable life. This
impacts on staff morale and hence productivity.
It was observed that management is engaging the MOFA to review the grading of
the mission so that it is placed in the appropriate category A for purposes of
enhancing the FSA to match the price index.
Management should continue engaging the relevant authorities for the possibility
of appropriately regarding the mission.
806
f) Review of the Inventory
A review of the inventory of the chancery in the board of survey and verification
on a test check basis revealed old furniture and other stores that require
replacement. During discussions the Accounting officer explained that capital
development funds to enable replacement of the items have started flowing in
although minimal. The old items would require boarding off.
The Accounting Officer explained that a board of survey had been formed to carry
out the boarding off exercise in the month of October 2014. Management was
urged to ensure that the boarding off exercise takes place in accordance with the
Public procurement and disposal of assets regulations.
g) Under Staffing
According to the Ministry of foreign affairs categorization of missions, Canberra
mission is categorized as 1 +2 mission whose structure should have one Head of
mission and two Foreign Service officers.
It was observed that the mission has the Head of mission and one Foreign Service
officer occasioning one vacancy. The Accounting officer explained that the arrival
of the officer to fill the vacancy that had been delayed due to entry visa issues.
Management was advised to follow up the matter with the Ministry of Foreign
Affairs so that the vacancy is filled.
72.0 UGANDA EMBASSY, COPENHAGEN
a) Performance Report
The Accounting Officer under section 14 of PFA is supposed to carry out regular
review of embassy operations and establish whether the operations are being
carried out as planned for the year. The end of year performance report was not
presented for audit verification.
In the absence of the performance report, it was difficult to establish whether the
mission activities had been implemented as planned.
807
In addition, it was difficult to link the mission, financial performance to the
planned activities and outcomes.
The Accounting Officer explained that the at the time of audit, the Embassy had
only complied separate activity reports from Q1-Q4 respectively that have been
integrated into a comprehensive performance report in line with the Copenhagen
Mission Charter 2014.
I advised the Accounting Officer to ensure that performance reports are regularly
conducted and presented for audit verification.
b) Lack of a Procurement Plan
Section 6 of the PPDA 2007 guidelines for mission refers that entities shall prepare
annual procurement plans based on the approval budgets and work plans in
accordance with PPDA regulations and submit them to the Authority before the
end of the first quarter of the financial year.
The procurement plan is supposed to allow the mission to enjoy economies of
scale and to reduce procurement costs.
It was observed that the procurement plan was not submitted to PPDA contrary to
the regulations.
The Accounting Officer admitted the shortcoming and explained that whereas
Form PP 20 is used to support expenditure on procured goods and services, the
Mission requires a proper management plan in line with the PPDA regulations.
Accordingly, the mission will be merging digital online shopping to conform with
PPDA regulations
I advised the Accounting Officer to ensure that procurement plans are prepared
and submitted to the Authority in accordance with the regulations.
c) Assets Management
Section 14(c) of the PFA 2003 required the accounting officer to ensure that
property and resources are properly managed and safeguarded.
808
It was observed that all the fixed assets owned by the mission had not been
labelled with any unique identification mark. This implies that the items may not
be easily identified in case of loss.
The Accounting Officer explained that steps have been taken to engrave all the
Embassy assets both at the Chancery and residential quarters.
73.0 UGANDA HIGH COMMISSION, DAR ES SALAAM
a) Irregular Procurements
Paragraph 2 of the Public Procurement and Disposal of Assets guidelines for
Uganda Missions abroad requires the Missions to pre-qualify providers who shall
be maintained on the list for three years. It was observed that the Mission did
not have a list of prequalified service providers. Consequently, procurements
worth TUGX.116,645,135 were undertaken in contravention of the PPDA
regulations as shown below:-
Service Provider Category of Service Amount (TUGX)
Viliproma Investment Ltd Fuel, oil and lubricants 29,374,868
Security Group (T) Ltd Security of chancery and residences
60,433,100
Aichi Supplies Stationery 4,133,400
Meridianna Africa Airline Ai tickets 8,488,767
Naska Lubricant Service Vehicle repairs and maintenance
9,215,000
TOTAL 116,645,135
The Accounting Officer explained that the Mission used per-qualified service
providers of other diplomatic missions in Dar es Salaam.
I advised the Accounting Officer to comply with the PPDA law.
809
b) Understaffing
The Uganda Public Service standing orders (A - a) 15 (a & f) states that the
Responsible Permanent Secretary shall determine the terms and conditions of service
and the structures of the Public Service in consultation with the Secretary to the
Treasury. Accordingly the mission had 15 approved posts and only 11 posts were
filled leaving 4 vacant posts.
Inadequate staffing adversely affects service delivery.
The Accounting Officer explained that the Head of Mission has engaged the
Ministry on the issue and recently an Officer was posted to the Mission. The
Mission still awaits replacement of former Head of Mission by appointing
authority.
I advised the Accounting Officer to follow up the matter with the relevant
authorities to ensure that the vacancies are filled.
c) Inspections
An inspection was carried on the mission properties located in the Diplomatic
Enclave of Dar as Salaam revealed the following shortcomings;
Official Residence Plot 65/12 Yasser Arafat Road
The building is dilapidated and
requires renovations of the roof
and the external walls.
810
The fence of the wall has a huge
crack that requires immediate
attention.
Other Residence
Plot 10 Kaunda Drive, WARD: Msasani, Street Oyesterbay House no 328
This residence is dilapidated and
requires major rehabilitation.
.
I advised the Accounting Officer to ensure renovation of the properties.
74.0 UGANDA HIGH COMMISSION, WASHINGTON
a) Outstanding Advances
Included in the outstanding advances is a sum of USD 40,000 that was
contributed to the Uganda North American Association in 2010 and 2012, and USD
55,000 that was incurred on transfer of two Foreign Service officers in 2006. Long
outstanding advances represent idle assets and may not be recoverable.
Management explained that the expenditure was incurred on behalf of the Ministry
of Foreign Affairs and the refunds were therefore expected.
I have advised the Accounting officer to liaise with the Ministry of Foreign Affairs
and the Treasury to either have the amounts refunded or written off in accordance
with financial regulations.
b) Dilapidated state of Buildings
Inspection of the Mission buildings namely: 5909, 16th St., NW and 5911, 16th St.
NW revealed water leakages in the foundation and in the ceiling. The air-
conditioning facility for the later was also noted to be mal-functioning. Owing to
811
the usual extreme weather conditions in the Washington area, there is risk of
rapid deterioration of the buildings and a harsh working environment for staff.
Management indicated that requests made to the Ministry of Finance, Planning
and Economic Development for capital funds to carry out renovations had not
been responded to.
I have advised the Mission to involve the Ministry of Foreign Affairs in seeking the
necessary resources for renovation of the properties and air-conditioning.
c) Irregular payment of Mileage Allowances
Section (E-e) of the Public Service Standing Orders, 2010 outlines the different
categories of allowances to which Foreign Service officers are entitled. This is
further amplified by Circular Standing Instruction No.4 of 2008, which clearly
indicates revised standard rates of allowances payable to all public officers.
It was noted that whereas mileage allowance does not fall under the above
section, a sum of USD 5,520 was paid to various officials of the mission in this
respect. This was therefore not a proper charge on public funds.
Management explained that this was a decision of the Finance committee arising
from the use of personal vehicles by staff and that the practice shall be halted
with immediate effect.
I advised the Accounting Officer to seek authority from the Ministry of Foreign
Affairs and the Ministry of Public Service before payment of undesignated
allowances.
d) Non-remittance of social Security and Medical Insurance for local staff
The mission employs a number of locally based staff who are entitled to a monthly
salary in addition to medical insurance and contributions to a Social Security Fund.
Examination of payment vouchers revealed that medical insurance and Social
Security Contributions were paid to staff personal accounts instead of remitting to
the relevant authorities. This practice is irregular because the social contributions
constitute their terminal benefits after the end of their employment contracts.
There is also a risk that the staff may not remit their contributions to the
812
regulatory agencies contrary to the law and this may attract penalties and related
fines against the Embassy.
I advised management to ensure deductions are remitted directly to the
concerned regulatory agencies.
e) Mission Charter
The mission charter provided to the Embassy by the Ministry of Foreign Affairs
comprises broad goals achievable over a period of time. The charter was not
broken down into targets, performance indicators and key result areas for each
year.
In the circumstances, it is difficult to assess the annual performance of the
Embassy in achieving its broad goals.
The Accounting Officer explained that the mission would liaise with the Ministry of
Foreign Affairs and break down the objectives into specific targets and
performance indicators by January 2015.
I await the results of this liaison.
75.0 THE PERMANENT MISSION OF THE REPUBLIC OF UGANDA TO THE
UNITED NATIONS AND OTHER INTERNATIONAL ORGANIZATIONS
IN GENEVA
a) Contingent Liabilities reported in the Financial Statements;
The Mission provided for Contingent Liabilities of UGX.811,269,801 representing
provisions for two pending court cases of unpaid rent plus repair costs and a claim
by a dismissed local staff. The following were noted with regard to the cases;
a) Documents indicated that the contract with the landlord was never terminated
since the Mission‟s relationship had ceased in 2007 when the home based
staff left the house and it was allocated to the local staff who started paying
the rent by herself. There was no justification for this anomaly.
813
b) Documents further indicated that the head of Chancery at the time allegedly
received CHF.7,800 from the local staff purportedly to pay the landlord the
equivalent of three months‟ rent as security deposit. This was never done
since the tenancy agreement between the Mission and the land lord was not
terminated and the security deposit initially paid was neither claimed by the
Mission nor used by the landlord for any necessary repairs. There were no
details to show that the money received by the Head of Mission was recorded
in the Mission books of account. There is a possibility that this money was put
to personal use by the recipient.
c) The locally based staff, who was later dismissed from her engagement with
the Mission later left the house without paying five months‟ rent of Cf.14,330
with a number of spoilt items that needed repairs. The security deposit which
the Mission had deposited was deemed by the landlord as insufficient to cover
the repair costs which required an additional amount of CF.7,981. The
additional attendant court costs have not been determined given that the
Mission has been sued by the landlord.
d) The staff in the above observation was hastily dismissed, but delegations from
Uganda continued to work with her as a staff of the Mission. As a result, the
Mission has been sued by this staff for unpaid salaries and general damages
totalling to CHF.251,839.77.
In the above circumstances, the officers appear to have acted outside the normal
Public Service practices. The likely payments to the landlord, the staff and the
attendant legal costs, in addition to suffering reputational risk by the Mission,
could have been avoided had the officers acted within the limits of the Uganda
Public Service Standing Orders.
Meanwhile the GoU through the Ministries of Foreign Affairs and Justice and
Constitutional Affairs had not assigned a legal counsel to represent Government in
court in Switzerland which poses a risk of the cases being determined without any
submissions from the GOU side.
814
The Accounting Officer explained that the Mission had communicated to the
Ministry of Foreign Affairs and copied to the former Head of Mission drawing his
attention to the matter. He also stated that he had communicated to the Ministry
of Justice and Constitutional Affairs requesting it to assign a legal officer to handle
the cases.
I have advised that;
the former Head of Mission refunds CHF.7,800 he is alleged to have obtained
from the Local staff and also be held accountable for the outcome of the case
regarding the allocation of the house to an ineligible staff in unclear
circumstances.
Government through the Ministries of Foreign Affairs and; Justice and
Constitutional Affairs takes up the matter and assigns legal representatives to
handle the cases in Switzerland.
b) Lack of segregation of duties
It was noted that the Mission is using a staff employed as a receptionist
/Secretary/translator to at the same time manage the finance affairs of the
Mission, prepare and sign the Financial Statements as the Mission Accountant. In
addition to not being qualified for the Accountant‟s job, the officer was found to be
handling a number of other tasks. Performing many tasks including the
Accountant‟s role may eventually render the staff ineffective.
Management took note of the matter and explained that they had written to the
Accountant General requesting for a qualified accountant to be posted to the
Mission.
I await the outcome of management‟s action in this regard.
c) Procurements and disposals
a) Roles of different parties in the procurement process
Procurements regulations require that different roles in the procurement cycle be
segregated to enhance transparency in the procurement process. It was however
noted that the Mission‟s Contract Committee was performing conflicting functions
during the procurement process. For example, identification of the need,
815
Evaluations/negotiations, approvals and communication of the Contracts
Committee‟s decision to the best evaluated bidders, were all undertaken by the
member(s) of the Contracts Committee. This is not only irregular but could lead to
undertaking procurements where the independence of the Contracts committee
members may be eroded.
I have advised the Accounting Officer that notwithstanding the limitations of the
Mission in terms of staff numbers, efforts should be made to segregate the roles
of the Contracts Committee from other roles in the procurement process in order
to preserve the Committee‟s independence.
b) Non disposal of Assets:
Review of the list of the Assets owned by the Mission revealed a number of old
equipment that had been in use for a number of years, most of them for over ten
years. Although the list indicated that many of them were still in a good state,
others were indicated as either old (procured as far back as 1996), broken, not
good or incomplete. These include furniture and fittings and, other household
equipment for both the residences and the Chancery. The list had two old vehicles
that were bought in 2005 and 2006 but whose costs of maintenance and repair
were high compared to others owned by the Mission. A negative image is
portrayed about the country by use of old equipment, furniture and other fittings.
Management explained that the Mission got funds for replacing the furniture and
fittings in the staff residences in the FY 2014/15 budget and had submitted a
budget to have the Deputy Permanent Representative‟s (DPR) car replaced in the
FY 2015/16.
I have advised the Accounting Officer to constitute a board of survey to inspect
the assets and recommend those that should be disposed of.
d) Non-disclosure of Security deposits in the Financial Statements
During the year, the Mission entered into a tenancy agreement with a new
Landlord for the residence of the Deputy Permanent Representative and paid
CHF13,500 as security deposit. It was however noted that this deposit was
816
expensed instead of treating it as a receivable in the financial statements.
Similarly, all the previous deposits (whose details could not be established) had
been expensed at the time of payment and they are equally not reported in the
financial statements. The interests earned from the banks were also not reported.
There is a risk that these deposits and their related interest earned could be
misused when the tenancy agreements end. I have advised the Accounting Officer
to ensure that the security deposits are appropriately disclosed in the financial
statements and that they are only expensed when the tenancy agreements end
and the money is to be used by the Landlords to renovate/repair their houses.
e) Payment of Rent for two properties for the Deputy Permanent
Representative
It was noted that the Mission procured rental services of a house located at de la
Majonne 2, 1293 Bellevue in September 2013 when the beneficiary was still
occupying another house at Rue de Ferney Grand Sacornex. While CHF.29,400
(4,900 X 6 months) was paid for the new house at de la Majonne 2, 1293
Bellevue, another CHF.25,800 (4,300 X 6 Months) was also paid for the premises
at Rue de Ferney Grand Sacornex. This was attributed to the stringent legal
regime governing tenancy in Switzerland. The double payment amounts to
wasteful expenditure as the second house was not occupied until February 2014
and could have been avoided if there was proper planning and the funds could
have been used to finance other priorities of the Mission.
The Accounting Officer explained that Management took note and had put in place
a proper plan for procuring accommodation for the staff. I have advised the
management of the Mission to ensure that there is proper planning for
procurement of accommodation to avoid overlapping payments for the same
officers.
f) Staff matters
a) Lack of performance plans
It was noted that there are no performance plans for the staff against which
performance should be measured at the time of appraisal. This is contrary to the
817
current Public Service Appraisal system which requires identification of key
activities and Key Performance Indicators at the start of the appraisal period,
management of the staff performance during the appraisal period and an appraisal
based on the performance at the end of the period.
Lack of performance plans therefore makes it difficult to manage staff
performance and carry out objective appraisals in accordance with the current
Public Service requirements.
I have advised the Management of the Mission to ensure that each staff of the
mission has an approved performance plan at the start of every appraisal period to
enable and ease staff performance management.
b) Non appraisal of staff
It was also noted that most of the Mission staff had not been appraised for the
preceding appraisal period. This does not only limit management from monitoring
staff performance and staff competencies but also makes it difficult to help staff
develop as their areas of improvement are not timely identified.
I have advised management to ensure that the Mission staff are appraised at the
end of each appraisal period to help the Mission monitor staff performance and
also help them to develop.
g) Payments
a) Insufficient description of payment details on the payment
vouchers
Paragraph 181 of the Treasury Accounting Instructions (TAIs) requires that all
vouchers will contain full particulars of each service or goods and will be
accompanied by such supporting documents as may be required so as to enable
them to be checked without reference to any other documents. It was however
noted that the payment vouchers for 2013/14 did not have description/details of
the payments. Given that all documents attached are in French, it made it difficult
to understand why certain payments, especially the non-routine payments, were
being made.
818
I have advised Accounting Officer to ensure that the payment vouchers contain full
description of payments to allow for understanding of the payments by other
stakeholders.
b) Double payments for insurance
The Accounting Officer is expected to design and implement internal controls to
assist him/her detect and minimise any errors of omission or commission. Review
of the payment files and the expenditure records revealed that the Mission made
double payments for three staff insurance amounting to CHF 5,016.
The circumstances under which the second payment was made for the same
period were not properly explained. There is a risk that the Mission could lose
huge amounts of money through such schemes where double payments can be
effected without being detected by internal mechanisms.
Although management stated that they had taken note of the matter and
promised to submit a report on the matter, this had not been done by the time of
writing this report.
I have advised the Mission Management to investigate the circumstances under
which the double payments were effected and institute recovery measures. I have
also advised them that the internal controls/mechanisms should be strengthened
to ensure that such double payments do not reoccur.
c) Compilation and settlement of outstanding bills
It is good practice to compile all unpaid bills and plan to settle them as and when
funds are available. This practice enables proper management of the budget and
planning cash flows. It was noted that the outstanding bills are not compiled and
approved for inclusion in the financial statements at the end of the financial year.
Instead the practice is that the officers stay with their individual claims/bills and
submit them later during the following financial year to be considered and paid by
819
the Accounting Officer. The practice is irregular, prone to abuse as it can be used
to sneak in fictitious bills and, distorts implementation of the planned activities.
The Accounting Officer was advised to ensure that all outstanding bills/claims at
the year-end are approved, compiled and planned for payment in the following
year. Bills submitted outside this arrangement should not be considered for
payment.
76.0 UGANDA PERMANENT MISSION TO THE UNITED NATIONS, NEW
YORK
a) Failure to revise Budget
Examination of the statement of appropriation Account based on the nature of
expenditure for services voted revealed excess expenditure of UGX.321,435,728
on the consumption of property, plant and equipment. Though management
indicated that the excess expenditure had been authorized by the Permanent
Secretary/Secretary to Treasury, the budget was not revised and uploaded
accordingly.
Management is advised to liaise with the Treasury to ensure that the revised
budget is uploaded in the system for proper presentation of financial statements.
b) Outstanding receivables
Included in the receivables is a sum of USD.37,825.87 attributed to a foreign
mission. Long outstanding receivables represent idle assets which impair the
Mission‟s non-tax revenue collections.
The Accounting Officer explained that the debtor had been reminded of the
obligations and a commitment letter for settlement of debt was subsequently
obtained.
In addition, the mission had instituted a late payment charge of 5% on the
monthly instalments to discourage late payments.
I await results of the action taken by the Accounting Officer.
820
c) Staffing Structure
Whereas the Mission is approved staffing structure is 1+3, the actual staffing is
1+8. The structure comprises the Permanent Representative to the United Nations
and his/her officers. It was pointed out that the funding of the Mission was not in
tandem with the increased staffing. The Accounting Officer further indicated that
the required level of staffing is 1+10 in view of the workload at the United
Nations.
In my report for the previous year I advised that close liaison with the Ministries of
Foreign Affairs, Public Service and Finance, planning and Economic Development
should be undertaken to rationalize the staffing position. Evidence of the results of
the liaison was not availed for review. Respective stakeholders are urged to
expedite resolution of the matter to enhance performance of the Mission.
d) Motor vehicle management
The Public Service standing orders require proper management of government
vehicles including use of vehicle movement logbooks to ensure monitoring of
utilization and fuel usage. The practice also ensures that the vehicles are used for
authorized official purposes and that they can be accounted for at any one time.
It was however, noted that the Mission last used log books for the vehicles in
2011. Though management explained that vehicle movement guidelines have
been put in place, it is noted that these are general procedures that do not serve
the purpose of monitoring efficient utilization of the vehicles.
The Accounting Officer indicated that use of log books shall be instituted with
effect from January, 2015.
I await evidence of the action taken.
77.0 UGANDA CONSULATE, GUANGZHOU, CHINA
a) Mission Charter
821
It was observed that the consulate operated without a Charter. Ideally the ministry
would formulate a foreign policy through which missions were to contribute by
way of well defined charters. In absence on one it became difficult to measure
performance of the consulate and as such there was a risk of implementing
uncoordinated activities that might not have achieved the objectives of the foreign
policy.
Management explained that the Consulate and the Ministry of Foreign Affairs were
engaged in the discussion and formulation of the Mission Charter which was only
finalized and sent to the Consulate in April 2014, and accordingly the Consulate
prepared a detailed work/activity plan and is being used in the current financial
year.
I await management action to implement the Charter in the subsequent year.
78.0 UGANDA EMBASSY JUBA
a) Improper payments
A total of USD.15,439 paid to individuals was supported with accountabilities from
recipients other than the contracted parties contrary to Regulation 254 (1) (2) of
the PPDA Regulations, 2003. Payments to unauthorized recipients may result into
loss of public funds. Though the management stated that the relevant
authorization had been obtained from the contracted parties, there was no
evidence to this effect.
I advised management to obtain and submit evidence of authorization for review.
In future all payments should be made to the contracted party.
b) Procurement shortcomings
In accordance with section 97 of the PPDA Act, 2003, the authority issued
guideline referenced 1/2007 to missions for use in their procurement activities.
However, the following weaknesses were noted at the Embassy in the
procurement function;
822
Lack of designated procurement set up in terms of staff.
Absence of procurement plan.
Lack of contracts committee and evaluation committee.
Unauthorized direct procurements worth USD.13,049.
Absence of key procurement documents such as LPOs, delivery notes, goods
received notes, inspection reports, job cards and acknowledgement receipts
for payments.
Unplanned and unsupported procurements expose public funds to abuse.
Management indicated that the shortcomings would be addressed in the next
financial year with the help of the PPDAA.
I advised management to seek technical guidance from the PPDAA on the setting
up of a functional procurement system, so as to operationalize and integrate the
relevant regulations in their procurements.
c) Mischarge of Expenditure
A total of USD.10,165 was charged on codes other than those under which it was
appropriated leading to mischarge of expenditure contrary to paragraph 400 (a) of
the TAI 2003.
The practice indicates abuse of budgetary controls and leads to misrepresentation
in the financial statements. Management explained that the Embassy had faced
inadequate funding since 2011 when it was elevated from a consulate to Embassy.
I advised management to always liaise with MoFPED to ensure adequate funds are
allocated to the budget items. In the event of need to reallocate funds, necessary
authority should be sought from the Treasury prior to release of funds.
d) Transfers received from other Government Units
A total of UGX.479,166,667 was indicated in the Cash Flow Statement as Transfers
received from other government units. However, Note 5 of the financial
823
statements, which records transfers received from other government units
indicated a nil balance. Management in response indicated that an adjustment
would be made, which however was not done.
I advised management to adjust Note 5 of the financial statements in this regard.
e) Over Expenditure without authority from the Accountant General
Comparison between Approved budget and Actual Expenditure revealed that
management of the Embassy over spent by UGX.1,282,122,285 on two line items
namely employee cost and Goods and Services Consumed without authority from
the Accountant General as per details below.
Item Budgeted (UGX) Actual (UGX) Variance (UGX)
Employee Costs 531,000,000 757,576,224 226,576,224
Goods And Services 734,500,000 1,790,046,061 1,055,546,061
Total 1,265,500,000 2,547,622,285 1,282,122,285
Management explained that expenditure was incurred in anticipation of
supplementary funding warrant which was however not provided.
I advised management that excess expenditure should only be incurred after
authorization by Treasury. In the circumstances there is need for evidence of the
supplementary warrant.
79.0 UGANDA EMBASSY, KHARTOUM
a) Cash and Cash Equivalents
Included in the statement of financial position is cash and cash equivalents totaling
UGX.183,248,063 which comprises the following;
Item Amount (UGX)
Cash at Bank 51,305,881
824
Item Amount (UGX)
Cash in transit 80,935,889
Cash at hand 51,006,293
Total 183,248,063
However, I could not confirm the accuracy of this figure (UGX.183,248,063)
because cash at Bank was not supported with the certificate of bank balances and
the bank reconciliation statement for the month of June 2014. In addition, cash in
transit and the cash at hand were not supported with electronic transfer document
and board of survey report respectively.
I advised the Accounting Officer to submit the missing documents for verification.
80.0 UGANDA HIGH COMMISSION, KIGALI
a) Failure to reconcile receipts in the General Ledger (GL) and the Bank
A review of the process of posting of the visa receipts into the system revealed
that monthly collections were posted lump sum instead of being entered
individually. I was therefore unable to reconcile the individual collections to the
bank. It was further noted that the Visa fees collections and TMPS deposits on
bank 3 (USD Account) and bank 5 (Local Account) respectively could not reconcile
with manual collection ledgers prepared at the High Commission by USD 900.00 in
bank 3 and FRW 103,900 in bank 5.
Management attributed this to posting of receipts to cash in transit instead of
posting to the bank directly. Management further explained that they had sought
assistance from the Navision Support Team to guide the Consular Officer on how
to post individual collections to enable a smoother reconciliation.
I advised management to always post the individual collections to the bank to
enable reconciliation.
b) Non approvals of payments within Navision
825
According to the commission cash books generated by the system, payments
worth USD 152,191 and FRW 43,970,383 from a local and dollar accounts were
not approved by the Accounting Officer even when there was evidence that these
payments were actually manually approved before payment was effected.
Management could not explain this anomaly and referred this matter to Navision
experts at Treasury for further consultation.
I advised management to continue liaising with Navision Support Team at
Treasury and have the system issue resolved once and for all.
c) Construction of the proposed chancery at Kacyiru Kigali
i. Irregular use of VAT refunds
According to one of the (PS/ST) communication dated 11th December 2013, the
High commission in Kigali was authorized to utilize VAT refund amounting to USD
101,332 on project activities. The Accounting Officer was also requested to
provide a revised implementation schedule showing details of the remaining
activities and the cost to end of the project.
At the time of audit, USD 290,172.53 had been refunded indicating that USD
188,836.53 was utilized without the requisite approval by the Permanent
Secretary/Secretary to the Treasury. I was also unable to confirm whether the
activities on which these funds were spent on had been budgeted for. A revised
implementation schedule showing details of the remaining activities and the cost
to end of the project was not provided at the time of writing this report.
Management explained that the refund had been utilised in line with Project
activities. These included air travel and allowances for the Construction
Management Team related to the regular Site Chancery meetings between the
Client (Uganda High Commission, the Contractor and the Consultant), Contracts
Committee meeting costs related to the various procurement procedures for
furniture and security equipment. Management promised to submit a full report
on the implementation schedule of VAT refund to the PS/ST once the Chancery
construction is completed.
826
I advised management to ensure that approvals are sought prior to utilizing the
VAT funds.
d) Irregularities in the payments to a Supervisor
In June 2009, a supervising company was contracted by Government to undertake
consultancy services and supervision of the proposed construction of the
Chancellery building at Kacyiru-Kigali at a contract price of UGX.448,400,000 (VAT
inclusive). At the time of audit, UGX.369,930,000 (USD 155,644.23) had been paid
leaving a balance of UGX.78,470,000. According to special conditions of the
contract (page 23), payments should have been effected as per the following
schedule;
Table 1: Payment schedule as per the special conditions
Activity to be carried out
Comments Fees UGX
Provision of inception report
20% Paid against payment request No. 1 and No 2. Ref MoFA 01 dated 13/11/2010
89,680,000
Feasibility Design 15% Paid against payment request No. 1 and No 2. Ref MoFA 01 dated 13/11/2010
67,260,000
Scheme Design 15% Paid against payment request No. 3. Ref MoFA 01 dated 31/05/2011
67,260,000
Final Design and Tender documents
15% Paid against payment request No. 3. Ref MoFA 01 dated 31/05/2011
67,260,000
Construction supervision
30% Determined at the date of commencement of construction on 28/03/2013. They had supervised for 7 months as at 4/12/2013 and billed for 7 months. UGX 78,470,000 has been paid based on the assessment.
78,470,000
End of defects liability period
5% 0
Total payment 369,930,000
The following were noted;
827
i. Non adherence to special conditions in the agreement
According to GCC 8.1 of the special conditions of the agreement the period within
which the services may have commenced is June 2010. GCC 18.1 also stipulated
that the period within which the services shall have been completed following
commencement of the services is 2 years. The above conditions imply that the
contract should have expired in 2012. It was however noted that even after the
expired contract, the firm went ahead and billed UGX.78,470,000, being
construction supervision for the 7 months period supervised (from the date of
commencement of construction on 28/03/2013 to 4/12/2013) without an
addendum/revised contract terms. At the time of writing this report, the bill had
been settled. Ideally, the supervision costs should have been settled after
finalization of the construction.
Management explained the procurement process for an addendum to the contract
had commenced in consultation with the parent Ministry of Foreign Affairs.
Management effort on the matter is awaited.
ii. Failure to Claim for the Tax Refunds
No taxes were claimed from payments to the firm worth UGX.148,353,991 thus a
loss of government funds.
Management explained that the withholding tax of 6% would be recovered from
the firm at the time of effecting the final payment due to them.
I advised management to always deduct taxes considering that embassies are
exempted from paying taxes.
iii. Failure to trace one of the payments to the firm worth USD 68,288
in the system
USD 68,288 paid to the firm being engineering and feasibility design was not
posted as a payment in the Navision system. I could not establish how the funds
were paid. I explained to management that if this problem is not resolved, double
payment cannot be ruled out on future transactions.
828
Management explained that they had sought an explanation from the Navision
Support Unit regarding the anomaly as to why the payment is not reflected in the
system.
I advised management to investigate this anomaly with Navision experts and have
it resolve.
e) Performance of the Mission
i. Incomplete Mission Charter
At the time of writing this report, the mission charter was in a draft form. The
Charter outlines the road map that the Mission intends to follow in the future to
enable the achievement of its mandate. In the absence of the approved mission
charter, there is a risk that the Mission activities are not in tandem with the
Uganda Government Foreign Policy. In addition, it becomes difficult to review the
performance of the Mission with regard to its strategic goals.
Management explained that in conjunction with the line department of the Ministry
of Foreign Affairs, SMART targets had been drawn up in January 2015 reflecting
more achievable performance targets. They stated that the draft Mission Charter
is pending approval and signature of the Honorable Minister of Foreign Affairs.
I advised management to expedite the approval process and have the charter in
place.
81.0 UGANDA EMBASSY, KINSHASA
a) Non Tax Revenue
a. Unbudgeted Non -Tax Revenue (NTR) – UGX.53,562,240
Paragraph 2(c) of the third schedule of the Public Finance and Accountability Act
2003, requires the Accounting Officer to submit to the Accountant General a
statement of revenue received during the year, showing the amount contained in
the estimates of revenue for each source of revenue, the amount actually
collected, with an explanation for any variation between the revenues collected
and estimated.
829
A review of the Embassy financial statements for the year ended 30th June, 2014
(Statement of appropriation account) revealed that the mission collected NTR
totaling to UGX.53,562,240 from Passport and Visa entry fees. However, the
amount had not been budgeted for by the mission as indicated by the zero
amounts in the approved budget column of the Statement of appropriation
account. This rendered it impossible to assess the revenue performance of the
mission in respect of the NTR and may potentially provide an avenue for misuse of
NTR collected.
Although management explained that the Mission budgeted for UGX.41,000,000 as
indicated in the work plan (Performance Form A) submitted to Permanent
Secretary/Secretary to Treasury, the Work Plan could not be accepted as a
substitute for the approved budget. I have advised the Accounting Officer to
ensure that all NTR sources are always included in the Mission budget submitted
for approval.
b. Usage of Visa stickers
An analysis of the usage of visa stickers during the year was undertaken during
the audit. The comparison of the number of visa stickers issued by the mission
and those received from headquarters, showed that there appears to have been
an over requisition of visa stickers as shown in the table below;
Table showing analysis of Usage of Travel Documents during the year
Visa Stickers Single Entry Multiple
Entry
Gratis Emergency
Document
s
Balance b/f 287 0 230 0
Received during the year 1,000 1,450 550 100
Available in the year 1,287 1,450 770 100
Used during the year 357 24 136 4
Cancelled visas 16 3 1 0
Balance 914 1,423 643 96
830
The Mission appears not to have properly analyzed its annual visa requirements,
thus posing a risk of misuse of a significant number of unutilized visa stickers at
year end. I have advised management to always ensure that realistic estimates
are always made.
c. Poorly maintained visa records
A review of visa records revealed that they were poorly maintained as summarized
below:-
For instance, a gratis visa number 16263 issued on 25th April 2014 reflected a
sum of USD.15 whereas it should be issued free.
There were cases of cancelled visas, whose cancellation dates appeared
earlier than their issue dates, while some visas appeared to have been issued
on two different dates.
Some visas posted several cancellations and re-issuances while most of them
lacked details of applicants, passport numbers and nationality.
It was observed that there was lack of regular reconciliation of revenue
collections and visa stickers.
Under the circumstances, there is a risk of miss postings and/or understatement of
nontax revenue collection for the year. The Accounting officer attributed the
mistakes to the officer who acted in the absence of the Visa Clerk, but that these
were rectified, hence the numerous cancellations noted.
b) Unauthorized Expenditure - UGX.22,758,031
The Public Finance and Accountability Regulations 2003 (Regulation 39 & 40)
require that Accounting Officers adhere to the budgetary allocation per vote or
obtain prior permission before an over expenditure is incurred.
However, a review of the financial statements for the year revealed that actual
expenditure on employee costs and, goods and services during the period under
review exceeded the budget for the two line items by UGX.22,758,031. There was
no evidence on file to indicate that authority to overspend was sought from the
Accountant General, besides the source of extra funding was not indicated to me.
The details are as indicate in the table below:-
831
Item Budgeted - Ugx Actual - Ugx Variance - Ugx
Employee Costs 959,328,000 963,833,422 4,505,412
Goods & Services 727,398,000 745,650,609 18,252,609
Total 1,686,726,000 1,709,484,031 22,758,031
The Accounting Officer explained that this was due to increased feeding and
repatriation expenses in respect of released Ugandans in the absence of
alternative means of action. However, the over expenditure on items still exists
and remains unauthorized.
The Accounting Officer added that high bank charges and budget shortfall due to
exchange rate also contributed to this, and that the Mission had requested for a
supplementary funding which was not provided.
c) Doubtful Refund of Medical Expenses - UGX.15,841,267
Foreign services Standing Order M-a 14 provides that officers serving with a
mission should register with a local National Health Insurance Scheme.
However, there is no evidence that management solicited the services of any
medical service provider and consequently, medical refunds totaling USD.6,094.60
(Ugx.15,841,267.158) were made to various mission staff, based on claims that
could not be verified due to lack of supporting documents, such as receipts. In the
absence of contracted service provider(s) and supporting documents, I could not
confirm the correctness and genuineness of the medical refunds.
The Accounting Officer explained that there is no National Health Insurance
Scheme in DRC or a credible medical Insurance provider in DRC, and consequently
the Mission opted for reimbursement of monies spent on medical services by the
various officers, and the Mission had subsequently procured the services of one
provider for the Local staff. He added that the Mission has finally contracted an
Insurance company during the financial year 2014/15.
The Accounting Officer‟s response that all the claims were accompanied by
payment receipts could not be substantiated as the documentation availed did not
reflect the payment receipts.
832
d) Unspent Balances at the closure of the Financial Year –
UGX.761,106,632
Section 54 of the PFAA, 2003 provides that unspent balances at the end of the
financial year should be returned to the Uganda Consolidated Fund within 60 days.
However, Note 20 to the balance sheet revealed that a balance of
UGX.761,106,632, was reflected as cash and cash equivalent at the end of the
financial year and verified as follows:-
Revenue account UGX.16,725,811
Expenditure account UGX.633,725,258
Cash at hand UGX.110,655,563
According to the Accounting Officer, these were committed funds in respect of the
renovation of the chancery building at Tombalbaye Street, which was ongoing, till
the end of October, 2014.
However, there was no authority from the PS/ST allowing the embassy to withhold
the unspent balances as explained by the Accounting Officer. In addition, there is
a high risk of holding big volumes of cash at hand, given the inherit risk associated
with cash, which is highly susceptible to misappropriation.
The Accounting officer explained in his response that keeping large sums of cash
at hand was unavoidable, given the fluid security situation in DR Congo, and that
the UN had accordingly advised foreign nationals to be on high alert and have
adequate cash at all times.
e) Unsupported Payments for Education Allowances
Section E-e para. 19 of the Public Service standing orders 2010 provides that
education allowance be paid direct to the school and reimbursement from the
officer for their personal share be made at source. Para 20 of the same standing
orders provides for each application for an education allowance to be approved
by the Responsible Officer, accompanied by a certification by the Head of Mission
in respect of the children‟s details.
833
During the period under review, education allowance totaling USD.17,500.00
(Approximately UGX.45,412,500) was paid to staff of the mission. However it was
noted that the allowances were paid to the individuals (Mission staff); the period
of education to be covered was not stated; and there were no receipts from the
schools.
In the absence of the relevant supporting documentation, the possibility that
allowances were not paid for the intended purposes cannot be ruled out.
The Accounting Officer explained that the education allowance paid was for the
year 2013 and to the two officers who had eligible children whose details were
attached. However, whereas details in respect of children were verified, details of
school acknowledgment and period of coverage were not indicated.
f) Non submission of Quarterly Reports on Procurements and Disposals
Section 3.1 of the guidelines for procurements and disposals by missions abroad
provides for missions to submit quarterly reports on procurement and disposal to
the Authority by the 15th day of the following month using PP Forms 200 and 202
on the micro procurements and DPA Form 201 on disposals. Copies of minutes of
the Contracts Committee should also be attached to the quarterly reports.
However, it was noted that management did not comply with the above provision.
Failure to prepare and submit the above reports hinders the PPDA from
performing its regulatory work over the mission‟s procurements and disposals.
The Accounting Officer explained that the monthly returns had always been
submitted promptly and consistently and that the mission was finalizing its annual
procurement & disposal report for submission. However there was no evidence
availed to support the explanation of the Accounting Officer.
g) Inspection of Mission Properties
An audit inspection of the mission properties on 15th August 2014 revealed that
Uganda has two properties in Kinshasa, which included a residence currently
hosting the chancery at Avenue De L‟ouganda, Q/Petit Pont, commune de la
Gombe, and the former chancery at 17 Avenue Tombalbaye.
834
Plot 17 Avenue Tombalbaye
This was the former chancery built in the 1970s. It is a storeyed building
comprising four apartments and an office space. The building was vandalized
during an attack by the security forces of the Democratic Republic of Congo at the
helm of the severe relationship between the DRC and Uganda in 1997. The
structure is dilapidated with a leaking roof, shattered floor, and services, such as:
electricity, water, and fire-fighting and warning system are all broken down
requiring a major overhaul.
At the time of inspection, the property was undergoing renovation and
refurbishment, at an estimated cost of USD.1,438,333, inclusive of tax. The works
were expected to last 12 months from 8th October, 2013 to 7th October 2014, but
this date was revised to 31st December 2014. A total of USD.453,653.47 had been
paid to the contractors as summarized in the table below:
Description Activities Cost in USD Percentage
FY2012/13 Procurement Process 48,506.06 11%
FY 2013/ 2014
Advance payment paid 247,,988.40 55%
Contractor s bills 80,809.98 18%
Administrative costs 76,349.03 16%
TOTAL COST TO 30 JUNE 2014 453,653.47 100%
Inspection of the building revealed that works were at wall plate level, which
represented a 60% progress, according to the project report dated 15th May 2014,
and payment progress stood at 22.9%. Given the reported progress, there is a
high possibility that the project will not be completed within the estimated time.
Property at Avenue De L‟ouganda-Gombe
The premise currently accommodates the Chancery, but is supposed to be the
official residence of the Ambassador. The Ambassador is currently being
accommodated in rented premises. It is proposed that, with the completion of
renovations, the chancery will relocate to its former premises, which will also
accommodate the mission staff, and the Ambassador relocates to his official
residence.
835
However this may expose the mission to the following risks as the premises are in
a commercial area:-
It is dangerous and risky for all staff to be under one roof in case of a terrorist
attack or accident.
Mixing office and staff residences may infringe on staff privacy.
In response, the Accounting officer explained that management had proposed to
the Ministry that the Mission stays at its current location, secures land for
construction of official residence elsewhere and rent out part of the premises at
Avenue Tombalbaye, to generate revenue.
h) Un-Disclosed Outstanding Debt Obligation – UGX.5,957,614
A review of the financial statements revealed payables of UGX.131,225,090 as at
30th June 2014. These are gratuity arrears in respect of the former mission staff.
Further review of documents revealed that a local workers‟ social security fund
organization (INSS) and a local professional workers body (RPS) were demanding
a sum of USD.2,291.39 (UGX.5,957,614) being workers‟ contributions as indicated
in the table below:-
GRATUITY OF FORMER STAFF-INSS
NAME INSS-3.5% RPS-10% NET AMOUNT DUE
Mukendi Mbuyi 153.33 428.26 14,513.90
Mbikayi Katshimuena 102.52 282.66 9,77.07
Senkunja James 109.35 301.51 6,577.00
Ditina Matondo 84.80 233.61 5,614.39
Bofoyo Eyenga 49.21 135.67 4,804.86
Muhunda Mudiwa 30.74 84.76 3,524.81
Bantoka Mafuta 35.57 98.08 2.33.31
Moboti Jean 24.23 66.81 1,877.15
Michel 18.17 50.11 1,461.65
TOTAL 609.92 1,681.47 USD 50.486.14
N.B: 2,595* USD.50,486.14= UGX.131,225,090
The failure to provide for the omitted staff contributions and their eventual
settlement exposes the mission to the risk of litigation by the workers‟
organizations.
The Accounting officer explained that the staff gratuity had been erroneously
computed, omitting the above obligations, hence their omission from the Balance
836
sheet. He added that the deductions of USD.1,681.47 due to RPS cannot be
remitted as the union ceased to exist, and that USD.609.92 due to INSS will be
budgeted for in 2015/16.
82.0 UGANDA HIGH COMMISSION, LONDON
a) Utilization of NTR at Source
Paragraph 94 of Part I, of the Treasury Accounting Instructions, 2003, prohibits
collectors of revenue from utilising cash collected for any purpose whatsoever unless
otherwise authorised in writing by the Accountant General. The High Commission
utilized at source GBP 141,547.06 (UGX.627,335,154) out of the Non-Tax Revenue
(NTR) collection to renovate the Official Residence and to rent an apartment (GBP
30,266.43) for the High Commissioner for a period of five months, during
renovations.
The utilization of NTR at source lacked the requisite authority and was therefore
irregular.
Management stated that urgent renovations were required at the Official Residence
of which funds had been requested from the Ministry of Finance, Planning and
Economic Development (MoFPED) without success.
I advised the Accounting Officer to always seek authority before spending NTR at
source.
b) Unauthorized Over Expenditure
Regulation 37(b) of Public Finance and Accountability Regulations, 2003, requires
Accounting Officers to ensure that the provision for services as authorized by
accounting warrants are not exceeded, and they are held personally responsible
for any excess expenditure that is incurred without proper authority.
A review of expenditure of the High Commission revealed that there was over
expenditure of GBP.104,024.91 (UGX.461,037,361) on various budget line items
without seeking appropriate authority in form of reallocations or virements. The
practice undermines the intentions of the appropriating authority.
837
Management indicated that requests for reallocation of funds to MoFPED were not
responded to.
I advised the Accounting Officer to always ensure that the operations of the High
Commission are within the accounting warrant or else authority to spend over the
budget is sought before release of funds.
c) Assets of the High Commission
The High Commission possesses buildings namely the Chancery, Official Residence
and 189 Wardour Street, whose conditions were as follows;
a) Chancery – Uganda House
The Uganda House, 58-59 Trafalgar Square WC2N 5DX was renovated prior to
inspection. The building is occupied by the Chancery and partly let out to other
tenants. The inspection of the Chancery revealed the following;
Although the Chancery was in a habitable state, it required furnishing of the
reception area which lacked furniture.
The Chancery requires security locking systems, given the terror threats
around the world.
I have advised management to plan and budget for furnishing of the reception
and installation of security systems at the Chancery.
b) Official Residence
The Official Residence, at 30 Ingram Avenue, whose roof had been repaired
during the financial year, was in a fair condition, relatively habitable although the
following issues were noted during inspection:
The carpet was in poor condition following the previous water leakages into the
house.
The residence lacked security systems like Closed-Circuit Television (CCTV)
cameras to improve on security around the residence.
The furnishing at the residence was old and inadequate especially at the
kitchen area.
The water, drainage and heating systems were not functioning properly.
838
Through interaction with the staff at the High Commission, it was observed that
the renovations were being carried out in phases without taking into account the
interconnection of various systems of the structure. This resulted in deterioration
of the renovated parts requiring repeat repairs in the same areas within a short
time. The status of the building portrays negatively the image of the High
Commission and the country at large.
Management explained that they had already notified the property committee in
the Ministry of Foreign Affairs of the required works and repairs.
I have advised management of the High Commission, to continue engaging the
relevant Ministries and plan for the holistic renovation of the Official residence as
opposed to piecemeal works.
c) Property at 189 Wardour Street
The High Commission owns a commercial property at 189 Wardour Street, housing
two tenants. A review of the tenancy documents indicated that the High
Commission earns rent of GBP.70,000 per annum, payable in quarterly instalments
of GBP.17,500. The High Commission was scheduled to undertake a tenancy
review in March 2014, however by the time of audit (October 2014), it had not
been undertaken. The High Commission is likely to be charging lower rates in
comparison with the market rates.
Management explained that the rent review process, was already underway and all
parties had been notified. The process was expected to be concluded by end of
March 2015.
I have advised management to expedite the tenancy review process so as to
ensure improved NTR collections for the High Commission.
83.0 UGANDA EMBASSY, MOSCOW
a) Receivables
Included in the reported receivables of UGX.166,819,839 is UGX.46,827,823
(Euros 13,608.72) that was advanced to UPDF students during the year under
839
review. It was noted that the students‟ money had been remitted to a separate
bank account operated by the Defence attaché. A refund was not made to the
Embassy‟s Account to enable it execute the planned activities by the end of the
financial year. As a result, the money was regarded as unspent balances and
returnable to the Consolidated Fund. Meanwhile payables of UGX.8.6million
remained outstanding.
The payables would have been cleared by 30th June, 2014 if the UPDF students
had been paid using the funds meant for them.
The Accounting Officer explained that the funds were remitted by the Ministry of
Defence to the Defence Attaché‟s account to urgently facilitate the students‟ travel
back to Uganda after graduation. She attributed the anomaly to the Defence
Attaché‟s failure to transfer the funds to the Embassy‟s account on time.
I advised Management to ensure proper planning for the students‟ facilitation to
avoid similar scenarios in future.
b) Unplanned Procurements
Paragraph 6 of the Procurement Guidelines for Missions, 2008 requires missions to
prepare annual procurement plans based on the approved budgets and work plans
in accordance with PPDA Regulation 96 of the PPDA Regulations and submit them
to the Authority before the end of the first quarter of the Financial Year.
On the contrary, RUB. 746,686.25 (Approx. UGX. 55,553,457) was paid for
procurement of assorted items during the financial year without a procurement
plan. Adhoc procurement activities expose the Embassy to the risk of acquisition
of non-priority items.
Management indicated that the Embassy used a procurement guide for the year
under review. However, due to the unique market environment in Russia, it was
rather difficult to attach prices to the items in advance.
I advised Management to always prepare procurement plans in accordance with
the budget.
840
c) Failure to Translate Documents
It was noted that a number of key supporting documents availed for verification
had not been translated from Russian to the English language contrary to Section
(P-b) (7) of the Public Service Standing Orders which states that “If an officer
receives documents written in a language other than English and it is necessary to
refer such documents to other departments or officers, he or she should arrange
for the documents to be translated by a designated translator or professional and
for such translations to be available to other interested departments and officers”.
This therefore rendered understanding of the expenditure and the supporting
documents difficult.
Management acknowledged the language challenge, and indicated that the
Embassy recruited a translator who doubles as a front desk officer but he is
overwhelmed with the volume of translation work.
I advised management to ensure that key supporting documents are always
translated into English.
84.0 UGANDA HIGH COMMISSION, NAIROBI
a) Lack of audited accounts for Uganda House
Clauses 2(k) and 9 (f) of the 3-year Property Management Contract with a local
property management agent requires the maintenance of proper books of
accounts and the audit thereof for Uganda House Ltd. However, audited Financial
Statements for the period to 30th June 2014 were not available for review at the
time of audit of the High Commission. In the circumstances, there is a risk of
under declaration of rental income by the property manager.
Management explained that the High Commission was in the process of procuring
an audit firm to carry out the audit of Uganda House Ltd.
I have advised management to ensure that the terms and conditions of the
Management Contract are enforced.
841
b) Old Utility Van
The Mission owns a 2006-Model Mercedes Benz Utility Van which was acquired in
2010. At the time of audit inspection, the vehicle had been in use for over 5 years
and had an Odometer reading of 327,083 Km.
Using the vehicle for more than five years and beyond the recommended 200,000
Km does not only make it uneconomical to maintain, but also exposes the Mission
to reputational risk.
Management in reponse explained that purchase of the van was provided for in
the budget for the financial year 2014/15 as part of capital development, but the
funds were not provided.
I have advised management to take up the matter with the Line Ministry with a
view to replacing the Van.
c) Outstanding Staff Advances
The reported receivables of UGX.44,644,765 represent funds advanced to staff in
the financial statements as far back as 2009/10 financial year. However, the funds
had not been recovered by the time of audit. There is a risk that the money may
never be recovered.
Management indicated that they had communicated to the concerned officers with
a view to recovering the funds.
I have advised the Accounting Officer to recover the advances from the officials‟
salaries and allowances.
d) Non-submission of Quarterly Procurement Reports to PPDA
Paragraph 3.1 of the Mission Procurement Guidelines, 2008 require Missions to
submit quarterly reports on procurement and disposal to the PPDAA by the 15th
day of each month for the previous month on macro procurements, the micro
procurements and disposals using appropriate forms with copies of minutes of the
Contracts Committee attached thereto. However, no reports were submitted to the
842
PPDAA during the year under review. In the circumstances, the Authority is denied
vital information necessary for the proper planning of periodic compliance
inspections.
Management in response acknowledged the anomaly and undertook to comply
with the PPDA laws and guidelines by submitting the reports as required.
I await management‟s action in this regard.
85.0 UGANDA HIGH COMMISSION, NEW DELHI
a) Advances
Through a review of the financial statements- Note 21: Receivables, it was noted
that UGX 2,409,158 related to staff advances- in the form of their share of utilities
bills. This amount however should have been retired by the end of the financial
year as is the case for all advances given.
Management acknowledged this weakness and indicated that the staff advances
were cleared in the next financial year (2014/15).
I await evidence of the action taken by management
b) Procurements
A procurement plan was not prepared. In addition, all the procurements during the
year under review were not requisitioned on a PP Form 20. In the absence of a
procurement plan, there is a risk of making unplanned and procurements not
based on the needs of the Embassy.
In addition, management did not prepare quarterly reports on procurement and
disposal as is required by the PPDA guidelines.
Management acknowledged these observations and promised to prepare the
reports regularly as required by the PPDA Regulations.
I await evidence of the action taken by management.
843
c) Contracts Committee
Although the Mission had a Contracts Committee and had requested the PS/ST as
is required of the Public Procurement and Disposal of Public Assets (PPDA)
Regulations to formally appoint this committee, there was no evidence that the
proposed committee had been formally approved by the PS/ST. In addition, the
contracts committee was also doubling as the evaluation committee which is
contrary to the procurement regulations.
I advised the Mission to follow up with the PS/ST regarding formal approval of the
Contracts Committee and segregate the contracts committee from the evaluation
committee.
d) Fixed asset register
The Mission does not maintain a comprehensive fixed assets register. Fixed asset
register should show item, date of purchase, value, location, condition,
identification number and status for ease of identification and decision making.
Although the register maintained included some details like date of purchase,
quantity, description, amount, it was not regularly filled. The absence of a
comprehensive fixed assets register exposes the Embassy‟s assets to the risk of
their loss without detection.
Management acknowledged these weaknesses and promised to have the ledger
properly maintained.
I await evidence of the action taken by management.
86.0 UGANDA HIGH COMMISSION, OTTAWA
a) Performance Report
The Accounting Officer under section 14 of PFA is supposed to carry out regular
review of embassy operations and establish whether the operations are being
carried out as planned for the year. The end of year performance report was not
presented for audit verification.
844
In the absence of the performance report, it was difficult to establish whether the
mission activities had been implemented as planned.
In addition, it was difficult to link the mission, financial performance to the
planned activities and outcomes.
The Accounting Officer regretted the failure to avail the end of year performance
report for audit verification but promised to ensure that the performance reports
are in future prepared in a timely manner and presented for audit verification.
I advised the Accounting Officer to ensure that performance reports are regularly
produced and presented for audit verification.
b) Official Residence
It was observed that work for the renovation and improved security at the official
residence had not yet commenced despite the promise from the accounting Officer
that civil works would commence during the year under review. This is an
indication that the Mission activities may not have been under taken on schedule
and according to work plans.
The Accounting Officer explained that the pre-renovation works did commence
with the technical team undertaking necessary analysis/ measurements and
preparing a report specifying the specific courses of action to guide the official
renovation project. In accordance with the Canadian regulation, Peterson Group
Inc. Consulting Engineers firm was contracted to undertake the detailed study to
determine the presence of designated substances such as asbestos containing
materials like lead paints which are harmful to human and the study report
revealed presence of designated substances which are hazardous to humans. In
addition, the land at 235 Mariposa Avenue was surveyed and the report submitted
to the Ministry of Foreign Affairs to facilitate the preparation of the draft
architectural drawings.
The draft architectural drawings prepared by Government of Uganda Technical
Team were subsequently submitted to a Canadian Architectural firm for review in
compliance with the Canadian building guidelines that require all architectural
845
designs prepared by non-Canadian Architects to be endorsed by Canadian
Architects before submission to relevant authorities for approval. This firm has
advised Mission that the “working budget for renovation is Canadian Dollars CAD$
2.2 million and CAD$ 3.0 Millions for construction of a new building including
landscaping, fencing, hard surface, pool and pool house”. This working budget
estimate leaves a funding shortage of more than Canadian Dollars CAD$ 1.8
Million for renovation and CAD $ 2.7 million for construction of a new building for
the official residence.
After analyzing Canadian laws and historical changes I construction industry , the
three levels of laws that govern environment and standards of structures in
Rockcliff Village Park as well as the structural state of the Official Residence,
LineBox Studio recommended that demolition and reconstruction of the residence
was more viable. The cost of demolition and construction of a new building is
almost the same as that of renovation. Renovation could end up being even more
costly because of the unknown conditions that may be discovered after renovation
has started. Should renovation be chosen as the preferred option, there are high
chances of ending up with an increment in the funds spent and loss of opportunity
to build a residence where government shall save costs in the long term.
Given the preliminary technical advise on the cost-benefits analysis implications by
the firm, the Mission is liasing with Ministries of Foreign Affairs and that of
Finance, Planning and Economic Development with a strong recommendation that
it is in our strategic interest to demolish and redevelop the current official
residence building to minimize on spending additional resources for renovation in
the long-term.
The matter requires urgent attention.
87.0 UGANDA EMBASSY, PARIS
a) Inadequate Funding for the Embassy activities
The Uganda Embassy in Paris is accredited to France, Spain, Portugal as well as
Permanent Mission to UNESCO, OECD, and BIE. It was also observed that on a
846
number of occasions, the Embassy received state guests who had to be catered
for in terms of transport as well as facilitating the Embassy staff to perform extra
activities during such visits. Review of the budget ceilings and releases to the
Embassy revealed that over the past five years, a total of UGX.14.146 billion had
been released to the Embassy (average of UGX 2.8 billion per year). This is
against the management of the Embassy regarded as adequate to cover all
planned activities at UGX.20,722,200,967 over the same period. The following
were noted;
i. Inadequate Budget Provisions
The Embassy annual budget ceilings were observed to be grossly inadequate
compared to the planned activities. For example, the level of funding during
the financial year only allowed the embassy to partially cover routine payments
without adequate provisions to facilitate the officers to implement planned
activities especially those that involved traveling to other countries. During the
financial year, the routine payments which include allowances, salaries,
medical insurance, utilities and rent consumed UGX.2.567 billion (90%) out of
the UGX.2.853 billion received by the Embassy. This may lead to ineffective
representation of the country by the Embassy in the three countries and other
organisations.
ii. Unpaid Salaries
Salaries for the month of June 2014 were not paid until the release of first quarter
of 2014/15 financial year was received. This continued to affect the subsequent
payments because at the time of audit in mid-September 2014, there was no
money to pay September salaries and Foreign Service allowances.
Non-payment of salaries on time may affect the staff performance due to the high
cost of leaving experienced in France.
iii. Unfunded Priorities
A number of priorities remained unfunded:
Renovation of the chancery;
Procurement of representation car;
Replacement of the utility car;
Furnishing the official residence;
847
Security installations at the chancery.
Inadequate provision of funding to the Embassy to finance priorities affects the
achievement of Embassy objectives. Security installations at the chancery were of
great concern given the location of the Chancery and the current worldwide terror
threats. Review of payment records also revealed that there were frequent
disconnections of communication (Wi-Fi, TV, and phones) due to non-payment
which inconveniences the users.
The Accounting Officer explained that the Embassy had received funds for
replacement of the vehicles and budgets for other priorities had been submitted
for consideration during the following financial year.
I have advised management to liaise with the Ministry of Finance and provide
adequate funds to finance the Embassy‟s priorities and to facilitate officers to
effectively perform their duties in all the accredited countries and organisations.
b) Routine Payments not supported with schedules
The Embassy makes routine payments in respect of salaries, rent, insurances and
medical expenses. It was noted that contrary to the provisions of paragraph 181
of the TAI which requires all payment vouchers to be accompanied by supporting
documents, the payment vouchers for all routine payments made during the year
lacked the required supporting documents, such as approved schedules and
payrolls. There is a risk of duplicating the payments.
The Accounting Officer explained that the Embassy had started on preparation of
payment schedules that are approved by the Finance Committee before any
payments are effected.
I have advised the Accounting Officer to ensure that payment vouchers for routine
payments are always fully supported with the necessary supporting documents.
c) Approval of Contracts Committee composition
Section 27 (2) of the PPDA Act, 2003 states that the members of the Contracts
Committee shall be nominated by the Accounting Officer and approved by the
848
Secretary to the Treasury. However, it was noted that the term of old Committee
had expired and communication for constitution of a new committee made in July
2014.
At the time of audit, the approval by the Secretary to the Treasury had not been
granted but the proposed members were conducting procurement business. This
was irregular and the decisions of these members could be challenged.
The Accounting Officer explained that management would continue to follow up
with the PS/ST for approval of the committee.
I await the outcome of the Accounting Officer‟s action.
d) Non-remittance of Non-Tax Revenue (NTR)
It was noted that the Embassy collected a total of UGX.269,280,450 in form of
Non-tax Revenue during the financial year. However audit of the same revealed
that contrary to the Government Standing Policy that requires all NTR to be
remitted to the Uganda consolidated fund account, there were no transfers to the
UCF. Although in some cases the Embassy management wrote requesting to use
the funds, citing pressures of inadequate releases and effects of loss on poundage,
there were no responses.
There are associated risks of not remitting the money such as spending the money
by the Embassy.
I advised the Accounting Officer to follow up with the PS/ST and ensure that
request to utilise NTR at source is properly authorised.
e) Staff Matters
a) Absence of ideal staff structure for the Embassy
The Embassy is accredited to three countries of France, Spain and Portugal and as
well as Permanent Mission to UNESCO, OECD and BIE. Effective representation in
these countries and organisations requires a number of staff to be deployed at the
Embassy. However, it was noted that the current structure of 1 + 3 officers,
849
Accountant and Administrative Attaché is not adequate to allow effective
representation.
There is a risk that the Country may not be well represented in the three countries
and the three organizations under the jurisdiction of the Embassy.
The Accounting Officer explained that consultations were on going with the
Ministry of Foreign Affairs to improve the staffing levels of the Embassy but that
this was limited by the budget constraint. I await the outcome of the consultations
with the Ministry.
b) Lack of staff performance plans and appraisal
The Public Service Standing Orders paragraph 12 of section A-M states that the
performance appraisal system shall involve:
a) Performance planning
b) Continuous performance monitoring
c) Performance assessment/evaluation and
d) Performance improvement.
However, it was noted that;
There were no performance plans for the Embassy staff for the year under
review.
There was no evidence of staff performance monitoring, and
Review of staff personnel files at the Embassy revealed that the staff were not
being appraised/assessed annually.
Appraisals that are conducted long after the required dates and not linked to the
annual performance of staff cannot be used for staff performance improvement.
I have advised the Head of Mission to ensure that staff performance management
is undertaken for all staff of the Embassy.
f) Status of Government assets
a) State of the Chancery
An audit inspection revealed that the Chancery building has neither had routine
and periodic maintenance, or major renovations in the recent past. As a result, it
850
was in a poor state requiring substantial provision of funds to have it repaired.
Periodic and routine maintenance activities are required because of the weather
conditions which affect buildings, absence of which leads to faster deterioration of
the structure and facilities.
There is a risk that continued lack of routine and periodic maintenance activities
coupled with delayed renovations will make the building inhabitable and be
condemned by city authorities.
The Accounting Officer acknowledged the poor condition of the chancery and
explained that, a request to utilise the rental income paid by the Tanzanian
Embassy to renovate and prepare the premises for a new tenant had been made.
I have advised management to provide for adequate funds in the Embassy‟s
budget for maintenance and renovations and to follow up their request to utilise
the rental income for urgent interventions on the building.
b) Lack of Furniture and fittings for the official Residence
The Public Service Standing Orders, under Section 11-e, provides for provision of a
fully furnished Official Residence for the Head Mission. It was however noted that
the rented official residence was not furnished contrary to the requirements of the
Public Service Standing Orders. Instead the Ambassador had provided herself with
most of the household requirements (furniture, fittings and other equipment) but
with visible lack of others or use of old ones.
The Accounting Officer stated that they were going to follow-up the matter with
relevant authorities and ensure that the furnishing of the official residence is done.
I have advised management to budget for the required furnishings and ensure
that the follow up is done.
88.0 UGANDA HIGH COMMISSION, PRETORIA
a) Rent
851
The mission incurs a monthly rent of R 43,200 ($ 43,200) for renting
accommodation for the home based staff as follows:
Landlord Accommodation rented for Amount per month
1 Catherine Susanne Administrative attaché R 7400
2 Broadways Accounting officer R 11,500
3 Dream works Financial attaché R 8600
4 Ditto Third secretary R 9200
5 Ron mark Second secretary R6500
Total R 43,200
This translates into an annual rent 0f R 518,400 ($51,840) equivalent to UGX
126,577,728 would have been saved if efforts are undertaken to acquire own
residential properties.
In a written response the Accounting Officer explained that the Mission has
engaged the Ministry of Foreign Affairs (MOFA)on the issue.
I have advised management to follow up the matter with the Ministry of Foreign
Affairs to ensure that the mission acquire its own residences for its staff.
b) The Chancery
a) Condition of the Building
Documentary review file regarding the chancery revealed that it was acquired on
25th January 2001 at R, 1,424,000 equivalent to UGX 347,698,080. However since
that time its maintenance has been minimal due to lack of sufficient funds in the
annual budget allocations.
Its condition requires repair and renovation to save it from further deterioration.
For example some of the floor and roof tiles are getting off and the interior wall
require painting.
In a written response the Accounting Officer stated that the Ministry of Foreign
Affairs was aware of the condition of the chancery and has indicated that funds
will be availed in the financial year 2015/16 for its renovation.
852
I urged the Accounting officer to follow up the matter with the Ministry Of Foreign
Affairs so that the requisite funds are provided for in the budget.
b) Security
Although the chancery has electric steel gates at the staff and visitors entrances
and the building fitted with an alarm system there are no CCTV cameras, provision
of access control readers and other devices that enhance security. There is a risk
that sophisticated security threats may not be adequately prevented and handled.
It was observed that the mission has raised the matter with Ministry of foreign
affairs to be allocated funds so that the security at the mission can be
strengthened.
In a written response the Accounting Officer promised to follow up the matter with
the Ministry Of Foreign Affairs and Ministry Of Finance, planning and Economic
Development.
I urged the Accounting officer to follow up the matter with Ministry of foreign
Affairs (MOFA) and Ministry of finance planning and economic development
(MOFPED) for financial support so that the chancery is adequately secured.
c) Renovation of the Official Residence
There is a commitment to pay for renovation works going on at the official
residence amounting to R 7,261,116.92(UGX 1,772,946,918) and consultancy fees
of R 508,098 (UGX 124,062,289) that will fall due in September when the works
are expected to be completed. So far R 2,241,163.67(UGX 547,224,933) has been
paid leaving a balance of R5, 448,391.25(UGX 1,330,333,692). According to the
site meeting held on 20 August 2014 the contractor is committed to complete on
the scheduled date of 18 September 2014.
It was observed that the mission has only R 3,071,235.99(UGX 749,903,692)
available which is not enough to clear the obligation when it falls due. Unless
853
funds of R 2,378,155.26(UGX 580,674,170) are provided this may result in a
domestic arrear.
According to the Accounting officer the renovated residence will also require
furniture befitting it, rebuilding of the perimeter wall and strengthening of security
which have not been provided for.
In addition, reply the Accounting Officer explained that the Mission was following
up the matter with the Ministry Of Foreign Affairs and the Ministry Of Finance,
Planning and Economic Development.
I urged the Accounting officer to follow up the matter accordingly.
89.0 UGANDA EMBASSY, ROME
a) Over Release of Funds by EURO 39,562.96
EURO 39,562.96 was credited on the embassy operational account on 18/09/2013
and was drawn 18 days later (03/10/2013) without the knowledge of either the
Accounting Officer or Head of Mission, the substantive signatories to the account.
The source and the purpose for which the funds were released could not be
disclosed at the time of writing this report.
Management explained that when this anomaly was discovered, the Accounting
Officer notified the Head of Mission as well as the Accountant General seeking
guidance on the purpose of the funds. As due diligence was on-going, the funds
were removed from the Embassy account and made available to the account of
the agriculture attaché without the knowledge of the accounting officer or the
Head of Mission.
I advised management to establish the source of the funds and how these funds
were eventually utilized.
b) Navision System Issues
The procedure under the Navision system requires that before any payment is
made in Navision, the Accountant posts the invoice details of a vendor and
854
payment details for the Accounting Officer initial approval. The Accountant then
pays the invoice either by cash or bank. The payment is then resent to the
Accounting Officer for final approval. At this level the payment is posted to the
General Ledger from which the cash book is generated. A review of the cash book
generated from the system revealed the following anomalies;
a) Lack of Vendor/payee details
The cash book generated from the system lacked a vendor/payee yet these details
are posted at the time of entry of the document. This gap hindered the audit
process as it required me to drill the particular payment within the system one at
ago.
Management explained that the system cashbook in Navision was limited in detail
and could not show certain entries. Management promised that in the upcoming
Navision training at the Ministry of Finance, the Mission will raise this anomaly and
many more related to Navision. I await the outcome of management effort.
b) Non approvals of payments within Navision
According to the cash book generated by the system, 61 payments worth EURO
31,026.66 were indicated as having not been approved by the Accounting Officer
even when there was evidence that these payments were actually approved
before payment was effected. Management could not explain this anomaly and
promised to liaise with Navision support team at Treasury.
I advised management to continue liaising with Treasury and have the system
issue resolved once and for all.
c) Legal fees
a) Former Accounts Assistant
A former Accounts Assistant who misappropriated petty cash of EURO 5,185 and
unbanked NTR funds of EURO 2,456 all totaling EURO 7,641 (refer to the report to
Parliament for the year ended 30th June 2011) was terminated and the officer
proceeded to court for wrongful dismissal. In 2012, the court ruled in the
Embassy‟s favour and ordered that the funds earlier misappropriated be refunded.
855
In 2013, the officer took the embassy to court again this time for unpaid
retirement package (Severance package) and the court awarded her EURO
9,527.47. This was based on the fact that once a local staff has been terminated,
Severance package has to be paid regardless of the reason of termination. The
embassy legal officer claimed EURO 4,700.00 as legal fees. At the time of audit,
this case was yet to be resolved. A follow up of the misappropriated funds is also
awaited.
b) Former Cook for the Ambassador
A former cook of the Ambassadors official residence was hired in February 2010
and services terminated shortly on grounds that she had not been cleared by
security from Kampala. The former cook sued the Embassy for non-payment of
severance pay and INPS for the entire period of her service. At the time of writing
this report, this case had not been resolved.
c) Accident vehicle
It was further noted that one of the embassy car attached to the Agricultural
Attaché while being driven by a temporary driver (not an official driver) was
involved in an accident. At the time of the accident, this car lacked a 3rd party
insurance and therefore should not have been on the road. The insurance had
expired 3 months prior to the accident. At the time of inspection, the embassy had
been sued for involvement in the accident and failure to pay 3rd party insurance of
EURO 712. EURO 400 had been paid to the embassy lawyer as legal fees to
handle the case whose outcome had not been established at the time of writing
this report.
Management explained that in all the above instances, Ministry of Finance and that
of Foreign Affairs have been notified of the cases. Management promised to follow
up on all the legal matters to conclusion.
Management follow up on the legal matters is awaited.
d) Embassy space
856
An inspection of the embassy offices and ambassador‟s residence revealed that
there was limited space and or store to accommodate a number of procurements
undertaken during the year. The corridor to the accounting office and the
Agriculture Attaché office serves as a store (see picture below), similarly, the
Accounting Officers office served as a store to stationary and other promotional
items. There was no board room to facilitate a number of meetings with business
community. There was a small reception that could only accommodate two visitors
at a time. In the process, the corridor was used to accommodate the extra
visitors. There was also no car packing space for the embassy cars as the embassy
staffs were competing with the local population for packing space on the street.
An inspection of the ambassador‟s residence further revealed that the procured
items worth EURO 3,015.50 mostly furniture for the ambassador‟s office (Sofa set,
Meeting table and chairs, functions chairs etc.) were being stored at the
ambassador‟s residence garage (see the picture below); Since the assets are not
being secured in an ideal environment, the risk of loss of value is evident.
Corridor serving as a store
Accounting officers office serving as a stationary store
Furniture stored at ambassador‟s
residence
Furniture stored at ambassador‟s
residence
857
Management explained that the Embassy identified suitable premises for the
Chancery in August 2014 but was informed that there were no funds to effect the
move. Management promised to continue to engage Ministry of Finance with a
view of securing funding for this purpose.
I advised management to continue liaising with Ministry of Finance, Planning and
Economic Development with a view of securing a good working environment
befitting the status of an embassy.
e) INPS Arrears
INPS is a social contribution paid by the embassy on behalf of the non-diplomatic
staff. EURO 62,824.81 was appropriated and released to cater for this
contribution. During the year under review, a sum of EURO 62,686 was paid to the
INPS office to cater for the above expenditure. At the time of inspection, INPS for
the month of May and June 2014 worth EURO 7,982 (UGX 28,735,200) had not
been paid and were still outstanding. Management risks paying fines and penalties
if the outstanding INPS is not cleared on time.
Management explained that the two (2) months arrears will be paid in Q2 of
2014/15 financial year.
I advised management to ensure that the arrears are paid to the INPS office to
avoid eventual penalties.
f) Ambiguous targets
I noted that almost all the targets set in the mission charter appeared ambiguous
and could therefore not be achieved. See the comments in the table below:
Comments
1 Promote at least US$ 50m worth of
Uganda exports to Italy
This target cannot be achieved
because a number of exhibitions
intended to be carried out could
not be achieved because of the
limited budget.
858
Comments
2 Lobby Italy‟s annual inward investment
of at least US$ 100m
Statistics at Ministry of Trade
indicate that very few investors
were attracted from Italy. A lot
more has to be done to achieve
this target.
3 Facilitate attraction of at least 30,000
tourists from Italy.
Only 504 Visas were issued by
the embassy during the year
under review.
4 Lobby for at least US$ 20m worth of
budget support from Italy.
Interactions with investors were
therefore limited because of the
resources.
5 Lobby for at least 20 Rome scholarships
for Uganda students annually.
Can only be achieved if inland
travel, fuel and allowances are
up graded.
6 Handle at least 50,000 requests for
consular services annually
Management could not explain
how this target can be achieved.
7 Identify and facilitate acquisition,
development and maintenance of at
least one Government property in
Rome annually.
This target is likely not to be
achieved considering the capital
development budget of only
UGX 150,000,000 only during
the year under review.
I also noted that the Ministry responsible in setting the targets did not consult the
mission on the set targets. Besides, the activities of the 9 (nine) countries and 3
(three) Organizations accredited to the embassy were not included in the mission
charter. The excluded countries and Organizations include; Malta, Greece, Serbia
and Montenegro, Macedonia, Croatia, Cyprus, Slovenia, Albania, Bosnia and
Herzegovina FAO, WFP and IFAD.
Management took note of the challenges involved in attracting inward investment,
promoting exports and lobbying for budget support and many others with limited
funds. Management however promised to continue engaging Ministry of Finance,
859
Planning and Economic Development to enhance the ceiling of the Mission.
Management also indicated that with only EURO 30,000 remaining (after
deducting rent, FSA, Salaries for local staff, INPS (NSSF)), it is almost difficult to
achieve the above set targets.
I advised management to liaise further with the responsible Ministry and have
achievable targets revised in consultation with the mission management.
90.0 UGANDA EMBASSY TOKYO
a) Mission Charter
The Mission Charter shows the strategic direction of the Embassy. At the time of
inspection in October 2014, the approved charter availed was dated 16th Apr
2014. The charter for the part of the period under audit that is July 2013 to April
2014 was not seen. It was also noted that although the charter had key outputs,
performance indicators, and targets and required the Embassy to make quarterly
progress reports, the quarterly reports availed did not include a measure of the
extent of achievement of the output targets as indicated in the charter though
they indicated the activities the Embassy had undertaken in the respective
quarters.
In the absence of progress being reported in line with the measurable targets, it
may not be possible to monitor and assess progress on the strategic objectives of
the embassy.
I have advised management to report in line with the mission charter and indicate
extent of achievement of the strategic objectives so as to aid in monitoring the
performance of the charter.
b) Unspent Balances
Regulations require that all unspent balances should be returned to the Uganda
Consolidated Fund (UCF) at the end of the financial year. Through a review of the
financial statements, it was noted from the Statement of Financial Position, that
860
the Mission had an unspent balances of UGX. 604,281,310. Of this, UGX
590,002,808 had been remitted back to the Treasury on 30th June 2014, but still
recognized in the financial statements as part of Cash in Transit. I was not provide
with evidence of the remittance done by the Embassy.
I have advised management to accordingly adjust the financial statements upon
confirmation of the remittance.
c) Collection & Accounting of Non Tax Revenue
During the year, the embassy received JPY 6,660,812 (equivalent of UGX
169,140,355) as NTR. It was noted that the embassy receives this money in cash
and in many cases, there were delays in banking it. For example, although there
were NTR transactions between 11th Dec 2013 and 31st Jan 2014, there were no
bankings made in this period. The bankings also made in some cases were in
portions. With this practice, the likelihood that the NTR is used at source and later
reimbursed (teeming and lading) cannot be ruled out and this may lead to
misappropriation of embassy funds.
Management explained that to ensure proper accountability, the Accounting
Officer reconciles the actual NTR with the NTR on the system before banking and
in some cases because the Accounting Officer is attending to other Embassy
matters, the reconciliation and banking had been delayed.
I advised management to put in place checks and balances to ensure the NTR is
banked intact and immediately as required.
d) Procurements
A procurement plan was not prepared. In addition, all the procurements during the
year under review were not requisitioned on a PP Form 20. In the absence of a
procurement plan, there is a risk of making unplanned and procurements not
based on the needs of the Embassy.
In addition, management did not prepare quarterly reports on procurement and
disposal as is required by the PPDA guidelines.
861
Management acknowledged these observations and promised to prepare the
reports regularly as required by the PPDA Regulations.
I await evidence of the action taken by management.
e) Fixed asset register and stores ledgers
The Embassy does not maintain a comprehensive fixed assets register and a
stores/inventory records/ledger. Fixed asset register should show item, date of
purchase, value, location, condition, identification number and status for ease of
identification and decision making. Although the register maintained included some
details like date of purchase, quantity, description, amount, it was not regularly
filled. The absence of a comprehensive fixed assets register exposes the Embassy‟s
assets to the risk of their loss without detection.
Management acknowledged these weaknesses and promised to have the ledger
properly maintained.
I await evidence of the action taken by management.
91.0 UGANDA EMBASSY, TRIPOLI
a) Rent
A total of EUR.113,586 paid to various land lords as rent for residences and
chancery lacked copies of the tenancy agreement from land lords contrary to
section (H-b) (1) of the public service standing orders. Though the Accounting
Officer stated that the tenancy agreements for all the properties rented apart from
the official Residence/Chancery in Tripoli were availed for verification, audit
revealed that the attachments were merely rent payment forms but not tenancy
agreements.
There is a possibility that such expenditure could have been incurred without
following proper procedures.
I advised management to avail the tenancy agreements for verification.
862
b) Transfers to Treasury
A total of UGX.15,778,349 was indicated in the Statement of Financial
Performance as a transfer to Treasury during the period. However, Note 18 to the
Financial Statements indicated UGX.8,494,854 as a transfer to Treasury resulting
into a variance of UGX.7,283,495, which was not explained. There is a risk of
overstating the excess of revenue over expenditure and the net worth of the
Embassy for the year under review.
I advised the Accounting Officer to explain the variance and adjust the financial
statements accordingly.
c) Lack of Segregation of duties
A best practice requires separation of key duties as a measure of effective internal
controls. It was however noted that for any Embassy activity that took place, the
requisition for funds was always made by the Ambassador to the Accounting
Officer. The practice impairs checks and balances within the Embassy and may
result into anomalies remaining undetected over a long period. Also noted was
non-availability of accountability reports for allowances totaling EUR.32,431
contrary to paragraph 181 of Treasury accounting instructions.
Though the Accounting Officer submitted the reports for verification, the reports
availed were not signed rendering their authenticity doubtful.
I advised management to ensure Key functions of the Embassy are performed by
different staff to ensure checks and balances in the system. Properly signed
accountability reports should be availed for verification.
92.0 UGANDA HIGH COMMISSION, TEHRAN
a) Lack of a list of prequalified suppliers
Paragraph 2.1 of the PPDA guidelines for Uganda Missions abroad requires the
Accounting Officer to prequalify service providers for three years.
863
However, the Mission did not have a list of pre-qualified service providers and
procurements worth Rail 320,843,000 (UGX.32,084,300) were direct
procurements from non-prequalified service providers as shown in the table
below;
Documents reference No
Date Payee Details Amount (IRR)
Remarks
PV -641 11/07/2013 Bridget Safari Co.
Servicing Fire Extinguisher
5,200,000 No Quotation from service providers, or written permission from accounting officer or contracts committee
PV -630 07/07/2013 Sadaf Supermarket
Consumables 11,285,000 No Quotation from service provider, or written permission from accounting officer or contracts committee
PV -709 07/07/2013 Sadaf Supermarket
Consumables 12,024,000 No Quotation from service provider, or written permission from accounting officer but there is a loose minute
PV -707 27/08/2013 Donyaye Stationary
Purchase of stationary
11,050,000 No Quotation from service provider, or written permission from accounting officer but there is a loose minute
PV -659 22/08/2013 Naeeb Restaurant
Food for Ambassadors and their drivers
23,000,000 No Quotation from service provider, or written permission from accounting officer, Payment voucher names is different from cheque names, payment cheque has the names Mr. Alavi Ali which can lead to payment of wrong person
PV -776 29/10/2013 Naeeb Restaurant
Food for African Diplomatic Ladies Group
12,140,000 No Quotation from service provider, or written permission from accounting officer, Payment voucher names is different from cheque names, payment cheque has the names Mr. Alavi Ali which can lead to payment of wrong person
PV -756 30/09/2013 Iran Sport Spare tyre for utility Car ( Santafei)
14,000,000 No quotations from the service providers and no permission from the contracts committee to undertake the procurement
PV -800 04/12/2013 Dey Computers
Making DVD's on investments
5,400,000 No quotations from the service providers so as to assess the cheapest supplier
PV -797 03/12/2013 Dey Computers
Making DVD's on investments for seminar
4,400,000 No quotations from the service providers so as to assess the cheapest supplier
864
Documents reference No
Date Payee Details Amount (IRR)
Remarks
PV -850 25/12/2013 Chalak Parvaz co.
Air ticket for Brian and Cissy for A/O conference
56,993,000 No evidence of prequalification or a request of quotations from various service providers. This therefore puts the embassy at a risk of over payment for a service
PV -849 25/12/2013 Chalak Parvaz co.
Air ticket for Brian and Ambassador on New A/c issues
165,351,000 No evidence of prequalification of service provider or a request of quotations from various service providers. This therefore puts the embassy at a risk of over payment for a service
320,843,000
The Accounting Officer explained that initiative has been taken to advertise and
prequalify the firms for the mission.
I advised the Accounting Officer to comply with the guidelines and ensure that a list
of prequalified service providers is in place.
93.0 UGANDA EMBASSY IN RIYADH
a) Refund of Medical Expenses
SAR.24,351.86 (approx. UGX.16,729,728) was refunded to various officials of the
Embassy in respect of medical bills, while M/S Tuwinaya Health and Rasan Medical
Clinic were paid SAR.8,555.21 (approx. UGX.5,877,429) for treatment of staff
contrary to Section M-a (14) of the Public Service Standing Orders which requires a
Foreign Service Officer serving in an Embassy abroad to be covered by full medical
insurance. This practice is bound to be abused because it is difficult to verify the
correctness of some of the receipts submitted when requesting for refunds and
accounting for advances.
Though the Accounting Officer explained that the insurance policies did not provide
full coverage for treatment, the list of services not covered by the policies was not
availed for verification.
865
I advised Management to liaise with the Permanent Secretary MoFA and the
Director General of Health Services to provide an appropriate solution to the
matter.
b) Payment of Bonus
Allowances paid to Foreign Service Officers are regulated by section E of the Public
Service Standing Orders. Bonus payments are not part of the said allowances. It
was however noted that SAR 2,200 (approx. UGX.1,511,400) was paid to various
staff as bonus in respect of the Eid Il fitr holidays during the financial year
2013/2014, contrary to the Standing Orders.
In response, the Accounting Officer stated that it is a custom in Saudi Arabia to pay
the bonus.
I advised the Accounting Officer that such payments ought to be authorised under
the Government of Uganda regulations if deemed necessary. Otherwise, I consider
them irregular.
94.0 UGANDA EMBASSY IN MOGADISHU
a) Lack of Mission Charter
The Ministry of Foreign Affairs is required to provide every Embassy with a charter
spelling out its goals, objectives and activities to enable the Embassy set annual
goals and also design strategies to achieve them. However, it was noted that the
Embassy operated without a charter. The performance of the Embassy and its staff
could not be assessed objectively without key performance indicators. Besides,
there is a risk of implementation of uncoordinated activities.
The Accounting Officer explained that a draft copy of the Embassy charter was
submitted to the Ministry of Foreign Affairs for review and subsequent approval.
866
I advised management to follow up the matter and have the charter approved, and
disseminated to all concerned staff for implementation.
b) Poor Filing of Documents
It was noted that the payment vouchers submitted for audit were not sequentially
numbered and filed, making it difficult to match the payments to the source
documents contrary to paragraph 419 of the TAIs.
The Accounting Officer acknowledged the anomaly and explained that ,this was
partly attributed to the operating environment which has limited amenities and
new staff.
The Accounting Officer is advised to always number and file payment vouchers
sequentially for ease of accountability.