Upload
independent
View
0
Download
0
Embed Size (px)
Citation preview
Linking objective and subjective modelling
for landuse decision-making
Nathaniel C. Bantayana,*, Ian D. Bishopb
a Institute of Renewable Natural Resources, College of Forestry and Natural Resources, University of the Philippines,
Los BanÄos College, Laguna, Philippinesb Centre for GIS and Modelling, The University of Melbourne, Parkville, Vic., Australia
Received 22 May 1998; received in revised form 16 July 1998; accepted 16 July 1998
Abstract
This paper describes a landuse modelling approach developed for the Makiling Forest Reserve in the Philippines. The process
includes application of the analytical hierarchy process (AHP) but extends this approach to include objective process based
modelling ± in the form of the universal soil loss equation (USLE) ± in the subjectively oriented framework of AHP. A
geographic information system was used for data assembly and to de®ne decision zones and a PC based interface developed to
accommodate interactive application of the AHP and USLE models. Having successfully combined the objective and
subjective elements for evaluation of landuse alternatives, the paper explores the options for landuse allocation based on the
suitability assessments of a participating decision group. # 1998 Elsevier Science B.V. All rights reserved.
Keywords: Landuse; GIS; Analytical hierarchy process (AHP)
1. Introduction
Decision-making is a complex process. It usually
involves multiple objectives, multiple alternatives and
multiple social interests and preferences. Since the
early 1970s, researchers have focused their attention
on multi-objective situations and their simultaneous
treatment. This period saw the emergence of multi-
objective programming models applied to landuse
planning problems. One example is the interactive
linear multi-objective programming model by Nij-
kamp and Rietveld (1976). The model allowed the
decision-maker to express his/her relative preference
with respect to certain provisional ef®cient solutions.
The speci®cation of preference is repeated a number
of times until a best compromise solution is deter-
mined. Similar works include those by Barber (1976),
Dane et al. (1977), Ridgley (1984), Ridgley and
Giambelluca (1992) and Rehman and Romero (1993).
Likewise, decision-making involves multiple alter-
natives. Several alternatives exist that will satisfy the
objectives of the problem to varying degrees (Batty,
1979). The decision-maker has to choose the best
alternative without having a ®rm knowledge of the
effect of each alternative on the objectives. It is
important, in the ®rst instance, to generate a complete
set of alternatives and to use appropriate models to
predict the probable effect of each choice. These
models may be either wholly quantitative and objec-
Landscape and Urban Planning 43 (1998) 35±48
*Corresponding author. Tel.: +63-049-536-2557; fax: +63-049-
536-3206; e-mail: [email protected]
0169-2046/98/$19.00 # 1998 Elsevier Science B.V. All rights reserved.
P I I : S 0 1 6 9 - 2 0 4 6 ( 9 8 ) 0 0 1 0 1 - 7
tive (for example the Universal Soil Loss Equation
(USLE)) or they may involve subjectivity and expert
judgment (e.g. the analytical hierarchy process
(AHP)).
Finally, any landuse planning activity involves
multiple social interests and preferences. Usually,
the ®nal decision on an alternative depends on the
consensus of a group of decision-makers. Saaty (1980)
de®nes consensus as `̀ improving con®dence in the
priority values by using several judges to bring the
results in line with majority preferences.'' Thus, the
decision model must be able to accommodate these
varied and often con¯icting points of view. More
importantly, an aggregation procedure that gives
results which are representative of group opinion is
desirable.
There is considerable work reported in the literature
dealing with the several aspects of the decision process
and systems and procedures for decision support. This
paper reports a case study in the Makiling Forest
Reserve, Philippines which combines the work of
several authors (Fig. 1). Most importantly it presents
an approach to the combination of objective and
subjective modelling. Seldom has the use of both
approaches been reported in combination. There has
been little attempt to develop a systematic procedure
for combination such that an objective/quantitative
model may be used when available and considered
reliable while fuzzier/subjective/expert judgments are
employed to important decision parameters for which
no objective model exists (Bantayan, 1996).
2. A systematic approach to the decision-makingprocess
Complexity necessitates a systematic approach to
the decision-making process to accommodate the
multiplicity and multi-dimensionality of the problem.
A systematic approach is also useful to gain a thor-
ough understanding of the issues affecting the problem
(Jankowski, 1989, 1995). An example of a systems
approach to solving a complex landuse planning
problem is multi-criteria evaluation (MCE). MCE
techniques try to investigate a number of alternatives
(or choice possibilities) in the light of multiple objec-
tives (or criteria) and con¯icting preferences (or prio-
rities) (Voogd, 1983). An extension of MCE is multi-
criteria decision-making (MCDM). MCDM models
go beyond MCE techniques in seeking to establish
preferences and trade-offs among competing objec-
tives which may have been separately evaluated using
MCE (Bantayan and Bishop, 1993a, b).
Engendering preferences presents uncertainties.
These uncertainties point to the fuzziness or the
imprecision of human decisions (Xiang et al.,
1992). Until recently, the exclusion of intangible
information from planning exercises has been com-
mon practice because, `̀ . . . knowledge of human
beings involves the apprehension of qualities, which
in their very nature escape the net of numbers''
(Leitner et al., 1985). But as the same authors argue,
`̀ . . . a reduction of some phenomenon to a set of
measurable variables, to the exclusion of `unmeasur-
ables', provides a necessarily biased representation of
the phenomena at issue and often falls short of depict-
ing what is really important.'' In addition, Blin and
Whinston (1973) point out that problems which
involve expressions of preferences of individuals or
groups are more appropriately solved through the
theory of fuzzy sets. This realisation led to the devel-
opment of models integrating fuzzy set theory into the
decision-making process. Such models are referred to
collectively as subjective models.
Fuzzy set theory ®nds application in systems where
human judgment, perceptions and emotions play a
central role (Zadeh, 1977). It is a `̀ body of concepts
and techniques aimed at providing a systematic frame-
work for dealing with the vagueness and imprecision
inherent in human thought processes'' (Gupta, 1977).
The theory extends the classical two-valued logic (true
and false) of set membership towards a third region ±
between true and false (Brule, 1992). For more details
about fuzzy set theory, numerous references are avail-
able. Notable are those by Gupta (1977), Kaufmann
and Gupta (1985), Zimmermann (1991) or the tutorial
by Brule (1985) which is available on the Internet.
3. Subjective modelling for decision-making
Subjective models for decision-making can be
described as integrating the theory of fuzzy sets with
the concepts of multi-criteria decision-making mod-
els. This provides a coherent process for incorporating
subjective views into an explicit decision process
36 N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48
(Nijkamp and Voogd, 1985). In addition, the view-
points of interested individuals and groups can be
aggregated. The de®ciency of this approach in many
cases is that it does not allow the ¯exibility of treating
quantitative and qualitative information simulta-
neously. Our proposed mechanism for dealing with
objective and subjective models is introduced later in
this paper.
Fung and Fu (1975) made one of the ®rst attempts at
subjective modelling for group decision-making.
According to them, the preference pattern of an indi-
vidual decision-maker is represented by a fuzzy set. In
evaluating several alternatives, the degree of member-
ship of an alternative corresponds to the individual's
degree of acceptability of that alternative. The mem-
bership values are entered into an evaluation matrix
representing the decision-maker's preference pattern
(Fig. 2). The evaluation matrices of all decision-
makers are then aggregated to arrive at a group
opinion (see Section 6).
Other works in decision-making under uncertainty
include those by Sobral et al. (1981), Takeda (1975),
Fig. 1. Location map of the Makiling Forest Reserve, Philippines.
N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48 37
Hipel (1982), Mendoza and Sprouse (1989), Jan-
kowski (1989), Banai-Kashani (1990), Hall and Wang
(1992), Xiang et al. (1992), Carver (1991), Smith
(1992), Mendoza et al. (1993), Whitley et al.
(1993), Xiang (1993), Bantayan and Bishop (1993a,
b), Jankowski and Richard (1994), Bantayan (1996),
among others.
Initially, the preferences usually take linguistic
form. These are then assigned their corresponding
numerical values based on a pre-determined rational
measurement system. A rational measurement system
is a numerical system representing the preference
pattern of an informed individual (Fung and Fu,
1975). For example, the subjective model developed
by Xiang et al. (1992) contains the following fuzzy
linguistic labels: very high, high, moderate, low and
very low. These labels correspond to the evaluation
values 1.0, 0.7, 0.5, 0.3 and 0.0, respectively. Such a
rational assignment is not unique. It is merely neces-
sary that the values are linearly ordered. As Fung and
Fu (1975) note, a rational assignment should be able
`̀ to preserve the basic properties of the individual's
qualitative preference structure on a numerical scale.''
In rational decision-making, the following assump-
tions are important (adapted from Saaty, 1980):
1. Quanti®cation or the use of mathematics is
necessary to produce numerical scales of judg-
ments and other comparative measurements; and
2. Such a scale must be able to discriminate between
human emotions and feelings. The values must
have some kind of regularity so that a correspon-
dence between qualitative judgments and values in
the scale is evident.
Using the same example, a list of alternatives are
evaluated based on a set of criteria. A value of 1.0
indicates perfect suitability of the alternative based on
a particular criterion or criteria while for another
alternative a value of 0.0 indicates that it is absolutely
unsuitable. Values in-between 0 and 1 denote varying
degrees of preference.
3.1. The analytic hierarchy process
A subjective model which is gaining wide applica-
tion in landuse decision-making is the analytic hier-
archy process (AHP). AHP had its beginnings in the
early 1970s when Thomas L. Saaty, its developer, was
involved in several decision-making projects. By its
name, every problem is treated in terms of hierarchies
± a system of strati®ed levels, each consisting of
several elements. AHP utilises the systems approach
to decision-making. It views the problem as a system
and decomposes it into its elements. The approach
moves from the general concept to the particular and
more detailed elements of the system. It involves
pairwise comparisons of decision variables (e.g.,
objectives, alternatives) according to some attribute
they share or a criterion they should meet. Preference
is denoted by a vector of weights following an AHP
scale of relative importance ranging from 1 to 9 (see
Table 1). Reciprocal relationships are denoted by
reciprocal values. For instance, if a decision-maker
feels strongly that soil stability is more important than
recreation, he/she gives a rating of 5. Reciprocally,
comparing recreation with soil stability would denote
a score of 0.20. Eventually, a relative weight for each
decision variable is calculated.
How the process accommodates qualitative infor-
mation lies in its hierarchical approach. More infor-
mation is considered in the analysis as the hierarchy is
unveiled in more detail. Furthermore, inconsistent
comparisons are addressed by means of an internal
procedure which detects inconsistencies according to
an arbitrary consistency ratio of �10%. As Saaty
(1980) illustrates, `̀ if apples are preferred to oranges
and oranges are preferred to bananas, then apples must
be preferred to bananas. Moreover, if apples are twice
as preferable as oranges and oranges are three times as
preferable as bananas, then apples must be six times as
preferable as bananas.'' If the inconsistency ratio is
greater than the chosen threshold Saaty (1980) sug-
Fig. 2. Structure of evaluation matrices.
38 N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48
gests re-evaluation of the comparisons. The proce-
dure, however, is limited by the number of factors
which can be compared. An individual cannot simul-
taneously compare more than nine objects without
being confused (Saaty, 1980; Banai-Kashani, 1989).
Thus, comparison of objects beyond nine will not give
reliable results.
3.2. Generating the subjective measure
The ®rst step in the analytic hierarchy process
(AHP) is to de®ne the hierarchy, each representing
a level in the system. Illustrated below are the three
identi®ed levels of hierarchy for landuse decision-
making in our case study area in the Mt Makiling
Forest Reserve, Philippines (Table 2).
Consider the goal as choosing the landuse that is
most suited for the Reserve. This is based initially on a
comparison of the importance of the objectives. This
assessment can be based in consideration of the
Reserve as a whole. However, as the Reserve is not
uniform in its bio-physical characteristics it would be
inappropriate for a decision-maker to determine the
relationship between alternatives and objectives holi-
stically. In order to make informed and valid assess-
ments, the area should be divided into zones with
relatively homogenous characteristics. To this end, the
study area was divided into ten decision zones based
on similarities of slope and soil type. This classi®ca-
tion was deemed appropriate for the purpose. While it
was possible to include more factors in the homo-
genization process, these decision factors were
assumed to come into play in the application of the
subjective model. This was done using the SAGE
raster GIS (Itami and Raulings, 1993a, b) into a
number of pertinent map layers (elevation, soils,
existing land cover, rainfall, roads).
A computer program to assist in the application of
AHP to the Makiling reserve has been developed for
PC using VISUAL BASIC. Each stage of the analysis is
presented to the decision-maker as a series of prompts
seeking a comparison ratio. The program also com-
putes the consistency ratios and returns to the appro-
priate point in the AHP if a consistency threshold is
exceeded. The user may also display the GIS-based
maps at any time to check on the location of a decision
zone or some aspect of the underlying data.
3.3. Pairwise comparison of objectives
The analysis proceeds by conducting a pairwise
comparison of the objectives ± considered for the
reserve as a whole. The assumption taken is that
Table 1
Ratio scale of comparison (from Saaty (1980), p. 54)
Intensity of importance Definition Explanation
1 Equal importance Equal importance or indifference
3 Weak importance of one over another Experience and judgment slightly favour one activity
over another
5 Essential or strong importance Experience and judgment strongly favour one activity
over another
7 Very strong or demonstrated importance An activity is favoured very strongly over another; its
dominance is demonstrated in practice
9 Absolute importance The evidence favouring one activity over another is of
the highest possible order of affirmation
2, 4, 6, 8 Intermediate values between adjacent scale values
Table 2
Hierarchical classification of the study
Level 1 Goal Choose best landuse
Level 2 Objectives 1. Soil stability (SS)
2. Recreation (RV)
3. Employment (EO)
4. Sustainable/potable water (PW)
5. Food production (FP)
6. Education and research (ER)
7. Pollution abatement (PA)
Level 3 Alternatives 1. Cultivated areas (C)
2. Forested areas (F)
3. Built-up areas (B)
4. Park and botanic garden areas (P)
N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48 39
the objectives should be independent of the internal
variation in the land characteristics. Any differences
would be the result of decision-makers beginning to
prejudge what are suitable landuses. Each decision-
maker is asked independently to establish the relation-
ships among the objectives using the ratio scale of
measurement (see Table 1). For each decision-maker,
therefore, a square objectives matrix is generated (see
Table 3). Next, the matrices are normalised. This is
done by adding the column elements and dividing
each element by the respective column sum. The
rows of the normalised matrix of objectives are aver-
aged to yield the relative weights. The relative
weights (or objective weightings !i) are considered
representative of the degrees of preference of the
decision-maker.
To check for consistency in the decision-maker's
subjective assessments, the next step in the process
involves calculation of the column vector. It is derived
by multiplying the matrix of objectives by the relative
weights. In equation form:
vk � Mk � !ki (1)
where vk is the column vector for kth decision-maker,
Mk the matrix of objectives for kth decision-maker and
!ki the relative weight of ith objective for kth decision-
maker.
With the column vector of weights, the maximum or
principal eigenvalue (denoted by �max) is computed.
The closer the principal eigenvalue is to n, the more
consistent are the subjective assessments (Saaty,
1980). It is derived by taking the average of the
sum of the ratios of the column vector and relative
weights. The preferences of the decision-maker are
then subjected to a test of consistency of judgment.
The index of consistency (CI) is the difference
between the maximum or principal eigenvalue and
the number of objectives (n) divided by n ÿ 1. In
equation form it can be represented as
CI � �max ÿ n
nÿ 1(2)
where CI is the consistency index, �max the principal
eigenvalue and n the number of objectives.
CI is then compared to a random consistency index
(RI) of values as shown in Table 4. A consistency ratio
of 10 percent or less is usually considered acceptable.
Beyond this threshold, the decision-maker's judg-
ments are considered too inconsistent to be useful
for decision-making.
3.4. Setting priorities
The preceding calculations relate to the pairwise
comparison of the objectives at level 2 of the hier-
archy. The next step in the process relates to the
derivation of the priorities of the alternatives with
respect to each objective at level 3 of the hierarchy.
The relative weights of the alternatives based on each
objective are calculated in the same manner.
Table 3
Pairwise comparison of objectives for decision-maker 1
SS RV EO PW FP ER PA !i
Soil stability (SS) 1.00 2.00 0.25 0.50 1.00 3.00 2.00 0.12
Recreation (RV) 0.50 1.00 0.25 0.20 0.17 1.00 0.50 0.05
Employment (EO) 4.00 4.00 1.00 4.00 3.00 5.00 4.00 0.35
Sustainable/potable water (PW) 2.00 5.00 0.25 1.00 0.25 3.00 2.00 0.14
Food production (FP) 1.00 6.00 0.33 4.00 1.00 6.00 4.00 0.24
Education and research (ER) 0.33 1.00 0.20 0.33 0.17 1.00 1.00 0.05
Pollution abatement (PA) 0.50 2.00 0.25 0.50 0.25 1.00 1.00 0.07
�max � 7.32, CR � 0.07.
Table 4
Consistency random index (RI) values (from Saaty (1980), p. 21)
Order of matrix (n) 1 2 3 4 5 6 7 8 9 10 11 12
Average RI 0.00 0.00 0.58 0.90 1.12 1.24 1.32 1.41 1.45 1.49 1.51 1.48
40 N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48
The ®nal ranking of the alternatives (denoted by !i)
is calculated by performing a matrix multiplication of
the relative weights of the alternatives per objective
(denoted by Mij) and the relative weights of the
objectives (denoted by !i). It is calculated using the
equation:
!j � Mij � !i (3)
where Mij takes the form
Mij �!11 : !1p
: : :!n1 : !np
24 35 (4)
and !11 is the relative weight of alternative 1 for
objective 1, p is the number of alternatives and n is
the number of objectives.
The procedure is repeated in each decision zone,
until all decision zones are evaluated. Accordingly,
each decision zone will have its own set of relative
weights. From the standpoint of the decision-maker,
making all these assessments becomes very tiring as
the number of decision zones increase. The PC-based
computer model makes it easier for the decision-
maker to input all these subjective assessments.
4. Merging objective and subjective modelling
There is no accepted term for a procedure combin-
ing objective and subjective models in a single para-
digm. As the objective models relating to landuse are
typically physical models we have adopted the term
physico-subjective modelling. The approach uses
AHP subjective modelling process as its starting
point. The difference is that whenever an objective
approach to the estimation of matrix values is possible,
and deemed reliable, that approach is adopted and
replaces the subjective relationship between alterna-
tive and objective which would otherwise have been
used.
In this case study, soil stability (SS) is objectively
determined (see Fig. 3) using a physical model that
generates values showing erosion susceptibility (Ban-
tayan, 1997). The model has also been implemented
on PC using VISUAL BASIC. It draws on the same GIS-
based data on soils, slope and rainfall described above
and adopts the universal soil loss equation (USLE) by
Wischmeier (1959) in generating the erosion poten-
tials. These values are normalised and included as the
appropriate matrix column for the landuse option and
decision zone in question.
If, for example, an objective model for food pro-
duction was available (and reliable), the FP column
could be replaced by normalised values generated by
this model.
The physico-subjective approach used normalises
the output of the physical model on a scale of 0 to 1 to
create a common measure from the objective (or
physical) and subjective models to allow for mean-
ingful comparison.
Fig. 3. Value determination of relative weights.
N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48 41
In the case of one decision-maker, the analysis is
straightforward and no aggregation is necessary. But,
in this case, where a group of decision-makers is
involved, an aggregate set of objective and alternative
weightings needs to be established. Thus, for kth
decision-maker (d � k, . . . , q) and jth objective
(o � i, . . . , n), a mapping of the relative weights
for all Aj alternatives (a � j, . . . , p) is established.
These weights represent the preference pattern of the
individual decision-maker (or interest group). The
®nal ranking of the alternatives is calculated by per-
forming a matrix multiplication of the relative weights
for all Aj alternatives per objective (denoted by!kij) and
the relative weights for all Oi objectives (denoted by
!i).
A procedure is necessary to test the variation in
response of the decision-making group. It may be that
variability is due to distinct variation in viewpoints
among the members of the group or it may be simply
that scaling process has been applied in slightly
different ways. One available procedure is a non-
parametric test called the Friedman (Q) statistic (Leh-
mann and D'Abrera, 1975). This test rests on the
assumption that there is no difference among the
objective weightings for the individual members of
the group.
The procedure starts with an ordering (ranking) of
the objective weightings. Responses which differ
widely among each other will be re¯ected in large
differences among the average ranking. If this is the
case, the statistic will be large. Otherwise, when the
average ranking are all equal, the statistic is zero.
Friedman's statistic is given by:
Q � 12
Ns�s� 1�Xs
i�1
R2i ÿ 3N�s� 1� (5)
where N is the number of decision-makers, s the
number of objectives and R2i the square of the rank
sum associated with the ith objective.
This equation is used in situations where there are
no ties among the responses for any objective. A more
complex variation on the equation exists to deal with
equal rankings and generates a statistic Q*.
If the hypothesis of no intra-group difference in
weightings is accepted, the median may be used to
represent group response. An aggregate set of objec-
tive weightings is derived to represent group judgment
for the study area. Table 5 is a summary of the
objective weightings for the eight decision-makers
who participated in this study.
The result of the difference analysis for these
weights was:
Q � 7.28, d.f. � 6, p � 0.297.
Q* � 7.35, d.f. � 6, p � 0.290 (adjusted for ties).
Thus, the probability P(Q* � 7.35) that a �2-vari-
able with 6 degrees of freedom exceeds 7.35 is seen to
be 0.290. It can be concluded that the variation in
weightings is not signi®cant at the 5% con®dence
level. Table 6 shows the consequent aggregate objec-
tive weightings (estimated median).
Table 5
Summary of objective weightings for all decision-makers (dk)
Objective d1 d2 d3 d4 d5 d6 d7 d8
SS 0.12 0.25 0.22 0.14 0.023 0.26 0.16 0.08
RV 0.05 0.03 0.11 0.09 0.05 0.09 0.33 0.15
EO 0.35 0.04 0.02 0.08 0.25 0.03 0.08 0.20
PW 0.14 0.25 0.19 0.22 0.13 0.23 0.19 0.12
FP 0.24 0.03 0.06 0.11 0.14 0.03 0.04 0.21
ER 0.05 0.14 0.22 0.13 0.12 0.19 0.09 0.19
PA 0.07 0.26 0.18 0.23 0.08 0.17 0.11 0.05
Table 6
Aggregate objective weightings
Objective Estimated median
Soil stability 0.19
Recreation value 0.10
Employment opportunities 0.09
Sustainable/potable water 0.20
Food production 0.09
Education and research 0.14
Pollution abatement 0.16
42 N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48
5. Ranking of alternatives
To illustrate the computation of the ®nal ranking
consider the case of decision-maker 1 in decision zone
1. Thus, the weights for the four landuse alternatives
are:
therefore,
!11 � �0:07� 0:19� � �0:10� 0:10� � �0:49� 0:09�� �0:13�0:20� � �0:46�0:09� � �0:16�0:14�� �0:16� 0:16� � 0:21
similarly !12 � 0:38; !1
3 � 0:11; !14 � 0:30.
Table 7 shows the summary of the relative weights
for all Aj alternatives for all dk decision-makers in
decision zone 1, for example.
6. Combination of measures
A combination procedure indicating an overall
position for each decision zone needs to be estab-
lished. There are several ways to aggregate the pre-
ference patterns of individual decision-makers. Using
operations in fuzzy set theory, the dominant alterna-
tive can be determined. The form of aggregation may
be optimistic, pessimistic, or mixed (Fung and Fu,
1975). Optimistic aggregation takes the maximum
membership value from all the evaluation matrices
relative to the alternative in question. The calculation
is accomplished by performing a union operation. This
approach is essentially conservative and has the dis-
advantage of including inferior alternatives. For
instance, consider eight decision-makers (dk. . .q),
seven objectives (oi. . .n) and four alternatives (aj. . .p).
The fuzzy union for, say, alternative 1, is:
!11 [ !2
1 [31 [ . . . [ !8
1 � max�!11; !
21; !
31; . . . ; !8
1�� �
(6)
where !kj -preference (or membership value) attributed
to jth alternative by kth decision-maker.
Pessimistic aggregation, on the other hand, attempts
to minimise risk by taking the smallest membership
value. This is calculated by performing a fuzzy inter-
section operation. Finally, mixed aggregation is a
compromise between the optimistic and pessimistic
preferences. Initially, a reference value is determined
which is usually the midpoint (x) in the preference
scale. If all decision-makers agree on the acceptability
of an alternative based on an objective (ie., pre-
ference � x for all decision-makers), a pessimistic
aggregate is used to minimise risk. Otherwise, an
optimistic aggregate is used (i.e., preference � x for
all decision-makers). In case of disagreement on
acceptability, the compromise value x is used (Fung
!1j �
0:07 0:10 0:49 0:13 0:46 0:16 0:16
0:42 0:22 0:09 0:51 0:33 0:41 0:50
0:09 0:08 0:27 0:12 0:12 0:08 0:09
0:42 0:60 0:15 0:25 0:25 0:35 0:25
�����������������
0:19
0:10
0:09
0:20
0:09
0:14
0:16
��������������
��������������
Table 7
Summary of relative weights for all Aj and dk
Landuse Decision zone 1 Average Standard deviation
d1 d2 d3 d4 d5 d6 d7 d8
C 0.21 0.28 0.15 0.23 0.08 0.16 0.2 0.16 0.18 0.06
F 0.38 0.4 0.42 0.36 0.44 0.42 0.44 0.48 0.42 0.04
B 0.11 0.12 0.07 0.09 0.11 0.1 0.08 0.08 0.1 0.02
P 0.3 0.2 0.36 0.32 0.37 0.32 0.28 0.28 0.3 0.05
N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48 43
and Fu, 1975; Znotinas and Hipel, 1979; Hipel, 1982;
Xiang et al., 1992). The method is more likely to be
generally satisfying in the sense that it takes the
middle ground between the conservatism of the pes-
simistic approach and the looseness of the optimistic
approach. In cases where the judgments are too limit-
ing, it takes the maximum. In cases where the judg-
ments are too generous, it takes the minimum.
In cases where at least one is limiting and at least
one is generous, a value x (typically the median) is
used. The advantage of using median, rather than the
mean, is that it is less affected by polarised viewpoints.
Considering the whole group the compromise
relationship between the ith objective and jth alter-
native is determined as shown in Table 7. For instance,
for decision zone 1, the decision-making group con-
siders forestry (F) and park and botanic garden (P) as
the most important as far as the objective on soil
stability (SS) is concerned (i.e. preference � 0.42).
Similarly, for the objectives on recreation value (RV),
sustainable/potable water (PW), education and
research (ER) and pollution abatement (PA), forestry
landuse (F) is considered the most appropriate. In
terms of employment opportunities (EO) and food
production (FP), cultivation (C) receives the highest
rating (Table 8).
In deriving the aggregate set of relative weights of
the alternatives, the matrix for each decision zone
MIX!k1 � min�!1
1; !21; !
31; . . . ; !8
1�� �
; if �!k1� � x for all decision-makers
MIX!k1 � max�!1
1; !21; !
31; . . . ; !8
1�� �
; if �!k1� � x for all decision-makers
MIX!k1 � x if at least one or more �!k
1� � x and at least one or more �!k1� � x
(7)
Table 8
Mixed aggregate ratings for all decision zones
Landuse SS RV EO PW FP ER PA Landuse SS RV EO PW FP ER PA
Decision zone 1 Decision zone 2
C 0.07 0.08 0.33 0.09 0.47 0.15 0.09 C 0.06 0.16 0.32 0.13 0.53 0.15 0.14
F 0.42 0.42 0.25 0.52 0.25 0.47 0.52 F 0.41 0.37 0.28 0.53 0.17 0.38 0.54
B 0.09 0.07 0.15 0.07 0.15 0.08 0.08 B 0.12 0.08 0.21 0.08 0.15 0.08 0.10
P 0.42 0.39 0.22 0.26 0.13 0.31 0.30 P 0.41 0.28 0.15 0.27 0.11 0.32 0.28
Decision zone 3 Decision zone 4
C 0.03 0.05 0.35 0.08 0.56 0.11 0.11 C 0.00 0.07 0.27 0.15 0.29 0.10 0.09
F 0.45 0.50 0.14 0.61 0.26 0.39 0.55 F 0.46 0.52 0.25 0.53 0.26 0.48 0.55
B 0.06 0.08 0.28 0.06 0.13 0.07 0.06 B 0.00 0.10 0.16 0.07 0.15 0.08 0.07
P 0.46 0.30 0.22 0.27 0.11 0.39 0.28 P 0.54 0.31 0.20 0.25 0.16 0.35 0.27
Decision zone 5 Decision zone 6
C 0.13 0.12 0.26 0.11 0.47 0.11 0.10 C 0.05 0.12 0.18 0.09 0.40 0.14 0.10
F 0.34 0.37 0.19 0.44 0.17 0.37 0.47 F 0.46 0.40 0.22 0.47 0.21 0.40 0.52
B 0.17 0.17 0.20 0.15 0.17 0.12 0.10 B 0.06 0.09 0.21 0.08 0.20 0.10 0.08
P 0.34 0.36 0.28 0.29 0.20 0.30 0.30 P 0.46 0.35 0.28 0.33 0.20 0.30 0.29
Decision zone 7 Decision zone 8
C 0.01 0.10 0.27 0.07 0.34 0.10 0.06 C 0.00 0.06 0.22 0.11 0.58 0.06 0.07
F 0.47 0.32 0.20 0.54 0.27 0.41 0.51 F 0.46 0.38 0.13 0.51 0.20 0.42 0.56
B 0.01 0.09 0.21 0.07 0.22 0.11 0.07 B 0.01 0.11 0.25 0.06 0.13 0.10 0.07
P 0.51 0.33 0.28 0.27 0.18 0.35 0.33 P 0.52 0.39 0.27 0.27 0.13 0.28 0.27
Decision zone 9 Decision zone 10
C 0.00 0.07 0.21 0.12 0.48 0.06 0.07 C 0.05 0.11 0.25 0.13 0.50 0.09 0.09
F 0.46 0.39 0.26 0.52 0.23 0.43 0.52 F 0.41 0.29 0.21 0.49 0.17 0.34 0.54
B 0.00 0.09 0.30 0.07 0.18 0.11 0.09 B 0.12 0.16 0.14 0.05 0.10 0.09 0.07
P 0.54 0.38 0.26 0.26 0.16 0.30 0.29 P 0.41 0.31 0.21 0.30 0.14 0.29 0.25
44 N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48
above is subjected to Eq. (7) using the estimated
median as the objective weightings (!i). This results
to the following values as shown below: Table 9.
Analysis of the above values indicate a clear dom-
inance of forestry with built-up landuse as the least
preferable alternative. Predictably, the group of deci-
sion-makers prefer to maintain the forest cover within
the study area. In addition, the group would not likely
endorse any form of construction and as much as
possible, cultivation should be limited. These ®ndings
can be veri®ed by subjecting the decision matrices to a
separate analysis.
7. Sensitivity analysis
To ascertain the results of mixed aggregation, the
overall position is derived from the pairwise compar-
ison of the alternatives along each of the objectives
(i.e., level 3 in the problem hierarchy) without appli-
cation of the objective weightings. Thus, the objective
weightings are implied from the subjective assess-
ments of the alternatives along each of the objectives.
Such an approach guarantees the independence of the
objectives in the analysis and avoids the danger of
prejudgment mentioned earlier.
The analysis utilises the dominance concept (Sobral
et al., 1981; Hipel, 1982). This involves pairwise
comparison of the alternatives weightings in consid-
eration of the aggregate scores for each objective. The
degree to which one alternative dominates the others is
calculated and entered in a dominance matrix (D), in
the form:
D �djj : djp
: : :dpj : dpp
24 35 (8)
For instance, for decision zone 1, C dominates F
twice (refer to Table 7; employment opportunities
(EO) and food production (FP)). In contrast, F dom-
inates C ®ve times which should give a total equal to
the number of objectives n (�7). This is not necessa-
rily always true particularly in cases where the aggre-
gate scores are equal. In addition, if the aggregate
score is the same across all Aj alternatives for ith
objective, that particular objective can be removed
from further analysis.
The column sums indicate the number of times jth
alternative dominates all the others. While the row
sums indicate the number of times jth alternative is
dominated by the others. Thus, preference is given to
the alternative with relatively high column sums and
low row totals. For instance, for all the decision zones,
the djj entries are: Table 10.
The values deriving from the dominance approach
con®rm the results of the weighted mixed aggregation.
In general, the same conclusions may be arrived at
regarding the dominance of forestry landuse. For all
decision zones, forestry consistently garners the high-
est column totals and the lowest row sums except for
decision zone 5. In contrast, built-up landuse gets the
least column totals and the highest row sums except
for decision zone 9. In order of preference, forestry is
followed by park and botanic garden, cultivated and
built-up landuses. A majority of the decision zones
mirrored the results of the weighted mixed aggrega-
tion. However, in decision zone 5, park and botanic
garden appeared to be the most preferred. For decision
zone 7, forestry and park/botanic garden landuses
received the same preference score. For decision zone
8, highest preference shifted to park/botanic garden
with cultivated landuse receiving the lowest value. For
decision zone 9, the lowest preference shifted to
cultivated landuse.
Table 9
Relative weights of alternatives using mixed aggregation
Landuse Decision zones
d1 d2 d3 d4 d5 d6 d7 d8 d9 d10
C 0.15 0.17 0.14 0.12 0.13 0.13 0.10 0.12 0.11 0.14
F 0.42 0.40 0.44 0.45 0.35 0.40 0.41 0.04 0.42 0.37
B 0.19 0.11 0.09 0.07 0.14 0.10 0.09 0.08 0.10 0.09
P 0.29 0.27 0.30 0.31 0.29 0.32 0.33 0.31 0.32 0.28
N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48 45
8. Conclusions
We have offered a different approach to the problem
of combining objective and subjective approaches to
land suitability assessment. Our basic premise is
that an objective model should be preferred if avail-
able and reliable in the context, and if the necessary
data sets for model implementation are also available
and reliable. In other situations it is frequently neces-
sary to take a more subjective approach. The analytical
hierarchy process provides a basis for effective com-
bination of the two types of models. This research has
also demonstrated the potential facility of the
approach by implementing both the USLE and the
AHP on the same PC with a common geographic
information system available to both modelling
procedures.
In applying the new process and software to the case
of Makiling Forest Reserve we have further concluded
that:
� The output of the individual applications of the
AHP process can be successfully combined, in this
case, to generate a group view on the value of
landuse options.
� A geographic information system (GIS) provides
the user with a greater sense of control, than the
AHP implemented in isolation, by providing
immediate access to underlying maps and decision
zone information.
Table 10
Dominance matrices for all decision zones for mixed aggregation
Landuse C F B PP
Landuse C F B PP
Decision zone 1 Decision zone 2
C 0 5 1 5 11 C 0 5 1 5 11
F 2 0 0 0 2 F 2 0 0 0 2
B 6 7 0 6 19 B 6 7 0 5 18
P 2 7 1 0 10 P 2 6 2 0 10
10 19 2 11 10 18 3 10
Decision zone 3 Decision zone 4
C 0 5 2 5 12 C 0 5 1 5 11
F 2 0 0 2 4 F 2 0 0 1 3
B 5 7 0 5 17 B 5 7 0 7 19
P 2 5 2 0 9 P 2 6 0 0 8
9 17 4 12 9 18 1 13
Decision zone 5 Decision zone 6
C 0 5 4 6 15 C 0 6 2 6 14
F 2 0 1 2 5 F 1 0 0 1 2
B 2 5 0 7 14 B 5 7 0 6 18
P 1 4 0 0 5 P 1 5 0 0 6
5 14 5 15 7 18 2 13
Decision zone 7 Decision zone 8
C 0 5 2 6 13 C 0 5 4 6 15
F 2 0 1 3 6 F 2 0 1 3 6
B 3 6 0 6 15 B 2 6 0 6 14
P 1 4 1 0 6 P 1 4 0 0 5
6 15 4 15 5 15 5 15
Decision zone 9 Decision zone 10
C 0 6 4 6 16 C 0 5 2 5 12
F 1 0 1 1 3 F 2 0 0 1 3
B 2 6 0 5 13 B 4 7 0 7 18
P 1 5 2 0 8 P 2 4 0 0 6
4 17 7 12 8 16 2 13
46 N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48
Acknowledgements
We wish to thank the staff of the University of the
Philippines, Los BanÄos College of Forestry and Nat-
ural Resources who supplied the data for this research.
Special thanks are due those who participated in the
workshop.
References
Banai-Kashani, A.R., 1990. Dealing with uncertainty and fuzziness
in development planning: a simulation of hightech industrial
location decision-making by the analytic hierarchy process.
Environment and Planning A 22, 1183±1203.
Banai-Kashani, R., 1989. A new method for site suitability
analysis: the analytic hierarchy process. Environ. Manage.
13(6), 685±693.
Bantayan, N.C., 1997. GIS-based estimation of soil loss. In: The
Pterocarpus, vol. 9. pp. 1, 24±35.
Bantayan, N.C., 1996. Participatory Decision Support Systems:
The Case of the Makiling Forest Reserve. Ph.D. Thesis, The
University of Melbourne, Australia.
Bantayan, N.C., Bishop, I.D., 1993a. The role of GIS in
integrating fuzziness and modelling in landuse planning. In:
Proceedings of the 21st Annual International Conference and
Technical Exhibition, AURISA 93. Aurisa, Adelaide, South
Australia.
Bantayan, N.C., Bishop, I.D., 1993b. An approach to combine
fuzziness with a physical model for landuse planning using
GIS. In: Proceedings of the Land Information Management and
Geographic Information Systems (LIM & GIS) Conference.
University of New South Wales, Sydney, Australia.
Barber, G.M., 1976. Land-use plan design via interactive multi-
objective programming. Environment and Planning A 8, 625±
636.
Batty, M., 1979. On planning processes. In: Goodall, B., Kirby, A.
(Eds.), Resources and Planning. Pergamon Press, Oxford, pp.
17±45.
Blin, J.M., Whinston, A.B., 1973. Fuzzy sets and social choice. J.
Cybernetics 3(4), 28±36.
Brule, J.F., 1992. Fuzzy systems ± a tutorial. From baechte-
[email protected] Newsgroup: comp.ai. 11 pp.
Carver, S.J., 1991. Integrating multi-criteria evaluation with
geographical information systems. Int. J. Geographical Infor-
mation Syst. 5(3), 321±339.
Dane, C.W., Meador, N.C., White, J.B., 1977. Goal programming
in land-use planning. J. Forestry (June), 75(6) 325±329.
Fung, L.W., Fu, K.S., 1975. An axiomatic approach to rational
decision-making in a fuzzy environment. In: Fuzzy Sets and
Their Applications To Cognitive and Decision Processes.
University of California, Berkeley, California, pp. 227±257.
Gupta, M.M., 1977. `Fuzzy-ism', the first decade. In: Gupta, M.,
Saridis, G., Gaines, B. (Eds.), Fuzzy Automata and Decision
Processes, Elsevier North-Holland, New York, pp. 5±10.
Hall, G.B., Wang, F., et al.1992. Comparison of Boolean and fuzzy
classification methods in land suitability analysis by using
geographical information systems. Environment and Planning
A 24, 497±516.
Hipel, K.W., 1982. Fuzzy set methodologies in multicriteria
modelling. In: Gupta, M.M., Sanchez, E. (Eds.), Fuzzy
Information and Decision Processes. North-Holland, Amster-
dam, pp. 279±287.
Itami, R.M., Raulings, R.J., 1993a. SAGE Introductory Guidebook.
Digital Land Systems Research, Melbourne, 106 pp.
Itami, R.M., Raulings, R.J., 1993b. SAGE Reference Manual.
Digital Land Systems Research, Melbourne, 113 pp.
Jankowski, P., 1995. Integrating geographical information systems
and multiple criteria decision-making methods. Int. J. Geo-
graphical Information Syst. 9(3), 251±273.
Jankowski, P., Richard, L., 1994. Integration of GIS-based
suitability analysis and multicriteria evaluation in a spatial
decision support system for route selection. Environment and
Planning B: Planning and Design 21, 323±340.
Jankowski, P., 1989. Mixed-data multicriteria evaluation for
regional planning: a systematic approach to the decision-
making process. Environment and Planning A 21, 349±362.
Kaufmann, A., Gupta, M.M., 1985. Introduction to Fuzzy
Arithmetic ± Theory and Applications. Van Nostrand Reinhold,
New York, 351 pp.
Lehmann, E.L., D'Abrera, H.J.M., 1975. Nonparametrics: Statis-
tical Methods Based on Ranks. Holden-Day, San Francisco,
CA, 458 pp.
Leitner, H., Nijkamp, P., Wrigley, N., 1985. Qualitative spatial data
analysis: a compendium of approaches. In: Nijkamp, P.,
Leitner, H., Wrigley, N. (Eds.), Measuring the Unmeasurable.
Nijhoff (Martinus), Dordrecht, pp. 1±28.
Mendoza, G.A., Sprouse, W., 1989. Forest planning and decision-
making under fuzzy environments: an overview and illustration.
For. Sci. 35(2), 481±502.
Mendoza, G.A., Bruce Bare, B., Zhou, Z., 1993. A fuzzy multiple
objective linear programming approach to forest planning
under uncertainty. Agric. Syst. 41, 257±274.
Nijkamp, P., Voogd, H., 1985. A survey of qualitative multiple
criteria choice models. In: Nijkamp, P., Leitner, H., Wrigley, N.
(Eds.), Measuring the Unmeasurable. Dordrecht, Martinus
Nijhoff Publishers, 425±427.
Nijkamp, P., Rietveld, P., 1976. Multi-objective programming
models. Regional Science and Urban Economics 6, 253±274.
Rehman, T., Romero, C., 1993. The application of the MCDM
paradigm to the management of agricultural systems: some
basic considerations. Agric. Syst. 41, 239±255.
Ridgley, M.A., Giambelluca, T.W., 1992. Linking water-balance
simulation and multiobjective programming: land-use plan
design in Hawaii. Environment and Planning B: Planning and
Design 19, 317±336.
Ridgley, M.A., 1984. Water and urban land-use planning in the
developing world: a linked simulation-multiobjective approach.
Environment and Planning B: Planning and Design 11, 229±242.
Saaty, T.L., 1980. The Analytic Hierarchy Process ± Planning,
Priority Setting, Resource Allocation. McGraw-Hill, New York,
287 pp.
N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48 47
Smith, P.N., 1992. Fuzzy evaluation of land-use and transportation
options. Environment and Planning B: Planning and Design 19,
525±544.
Sobral, M.M., Hipel, K.W., Farquhar, G.J., 1981. A multi-criteria
model for solid waste management. J. Environ. Manage. 12,
97±110.
Takeda, E., 1975. Interactive identification of fuzzy outranking
relations in a multicriteria decision problem. Paper read at
Fuzzy information and decision processes.
Voogd, H., 1983. Multiple Criteria Evaluation for Urban and
Regional Planning. Pion, London, 367 pp.
Whitley, D.L., Xiang, W.-N., Young, J.J., 1993. Use a GIS `Melting
Pot' to assess land use suitability. GIS World 6 (7).
Wischmeier, W.H., 1959. A rainfall erosion index for a universal
soil loss equation. Soil Sci. Soc. Am. 23, 246±249.
Xiang, W.-N., Gross, M., Gy Fabos, J., MacDougall, E.B., 1992. A
fuzzy-group multicriteria decision-making model and its
application to land-use planning. Environment and Planning
B: Planning and Design 19, 61±84.
Xiang, W.-N., 1993. A GIS/MMP-based coordination model and its
application to distributed environmental planning. Environment
and Planning B: Planning and Design 20, 195±220.
Zadeh, L.A., 1977. Fuzzy set theory: a perspective. In: Gupta, M.,
Saridis, G., Gaines, B. (Eds.), Fuzzy Automata and Decision
Processes. Elsevier North-Holland, New York, pp. 3±4.
Zimmermann, H.J., 1991. Fuzzy set theory and its applications.
Norwell, Massachusetts, Kluwer Academic Press.
Znotinas, N.M., Hipel, K.W., 1979. Comparison of alternative
engineering designs. Water Resources Bull. 15(1), 44±59.
48 N.C. Bantayan, I.D. Bishop / Landscape and Urban Planning 43 (1998) 35±48