PMO/HRZ/DR/001 1
HORIZON VILLAS CONSTRUCTION PROGRESS REPORT
PMO/HRZ/DR/001
EMPLOYER: FAWAZ ABDULMEJEED M AL YAHYA
CONTRACTOR: PMO MÜH VE ERNJ YON. DAN LTD STİ
DATE OF THE REPORT: 05.07.2014 PROGRESS REPORT NO: PMO/HRZ/DR-001
KÖRFEZ TATİL
HORIZON VILLAS CONSTRUCTION STATUS REPORT
PMO/HRZ/DR/001 2
INDEX:
1. INTRODUCTION ...................................................................................................................... 3
2. ON GOING CONSTRUCTION ACTIVITIES ..................................................................... 4
2.1. RETAINING WALLS .................................................................................................................... 4
APPENDIX A – PROGRESS STATUS REPORT ANALYSIS
PMO/HRZ/DR/001 3
1. INTRODUCTION
This report cover the progress of the construction Works for Horizon Villa Project located in Sapanca Ilmiye village.
The construction activites started on site on 09.06.2014. The activities started are
• Mobilisation • Preparation of the site • Excavation and backfill Works • Natural Stone retaining walls.
As per the dicsussion and the approval of the employer, some of the villa levels are changed compare to its original level on the municipality drawings.
• A;B;C;D;E;N villas will be build as the project.
• F;L;M:L villas foundations will be raised and the raised parts will be filled with sands.
• F and G villas will be raised 2,00 meters.
• M villa will be raised 0,75 meters.
• L villa will be raised 1,50 meters.
• H;I;J;K villas will be raised and not filled with the sands instead the raised parts
• will be used as hobby rooms, storerooms or other useful areas.
• H villa will be raised 2,60 meters.
• I villa will be raised 3,35 meters.
• J villa will be raised 3,00 meters.
• K villa will be raised 2,25 meters.
Details of the progress has been included in the report.
Regards,
Sahin Atila Ozkan, PMP
KÖRFEZ TATİL
HORIZON VILLAS CONSTRUCTION STATUS REPORT
PMO/HRZ/DR/001 4
2. ON GOING CONSTRUCTION ACTIVITIES
2.1. RETAINING WALLS The construction of retaining walls have been commenced at the bottom road which borders the land. At this side the retaining walls J1;J2;J3;J4;J5;J6;J7;J8 and J9 have been completed except the edges. At the below there are photos of related to these works.
J1 - J9 RETAINING WALLS
RETAINING WALLS J9 – J8- J7
KÖRFEZ TATİL
HORIZON VILLAS CONSTRUCTION STATUS REPORT
PMO/HRZ/DR/001 5
RETAINING WALLS J9 – J8 - J7 – J6 – J5
RETAINING WALL J3
KÖRFEZ TATİL
HORIZON VILLAS CONSTRUCTION STATUS REPORT
PMO/HRZ/DR/001 6
RETAINING WALL J1
After completion of the retaining walls J1-‐J9, the retaining walls in front of the F and G Blocks have been commenced. In this side some very poor soil structure has detected. To take measures excavation was deepened, filling was made with large rocks and reinforced concrete foundation was build. At the below there are photos of related to these works.
KÖRFEZ TATİL
HORIZON VILLAS CONSTRUCTION STATUS REPORT
PMO/HRZ/DR/001 8
2.2. EXCAVATION-‐BACK FILLING
Excavation works are spread to the entire worksite. Working with two excavators and ten trucks gained momentum.
Our most intensive study area is at the villas located in the top of the land. In this region approximately 10.000 m3 were excavated.
At the below there are photos of related to excavation.
KÖRFEZ TATİL
HORIZON VILLAS CONSTRUCTION STATUS REPORT
PMO/HRZ/DR/001 11
THE APPROXIMATE MEASUREMENT OF WORKS RETAINING WALLS
! J1 – J9 950 m³
! F&G BLOCKS 250 m³
! TOTAL RETAINING WALLS 1.200 m³ EXCAVATION
! F&G BLOCKS 7.000 m³
! A-‐B-‐C-‐D-‐E BLOCKS 7.000 m³
! H-‐I-‐J-‐K-‐L-‐M-‐N BLOCKS 2.000 m³
! TOTAL EXCAVATION 16.000 m³ GRAVEL FOR DRAINAGE
! H-‐I-‐J-‐K-‐L-‐M-‐N BLOCKS 30 m³ INSTALL DRAIN PIPE
! H-‐I-‐J-‐K-‐L-‐M-‐N BLOCKS 40 m
Manhour % Manhour %
01 Excavation-Backfilling 2.970,00 1.249,00 42,05% 1.296,00 43,64% 47,00
02 Retaining Wall 7.308,00 1.476,00 20,20% 1.647,00 22,54% 171,00
03 Reinforced Concrete Works 23.600,00
04 Brick Walls 1.611,00
05 Roofing 849,00
06 Waterproofing 854,00
07 Windows 1.008,00
08 Doors 756,00
09 Facade 5.324,00
10 Finishing Works Mortared 7.814,00
11 Finishing Works 13.312,00
12 Mechanical Works 2.646,00
13 Electrical Works 1.764,00
14 Infrastructure Jobs 997,00
Direct 0 0 15 Garden and Landscaping 2.553,00
Indirect 432 18 9 18 18 18 18 18 117 16 Outdoor Swimming pool 448,00
Direct 1755 198 0 198 198 198 198 198 1188
Indirect 126 18 0 18 18 18 18 18 108
Direct 0 0
Indirect 261 0 0 27 0 27 0 27 81
TOTAL DİRECT 1755 198 0 198 198 198 198 198 1188
Manhour % Manhour %
TOTAL INDIRECT 819 36 9 63 36 63 36 63 306
01 Excavation-Backfilling 2.970,00 369,00 12,42% 369,00 12,42% 0,00
GENERAL TOTAL 2574 234 9 261 234 261 234 261 1494 02 Retaining Wall 7.308,00 1.476,00 20,20% 1.647,00 22,54% 171,00
03 Reinforced Concrete Works 23.600,00
04 Brick Walls 1.611,00
05 Roofing 849,00
06 Waterproofing 854,00
07 Windows 1.008,00
08 Doors 756,00
09 Facade 5.324,00
10 Finishing Works Mortared 7.814,00
11 Finishing Works 13.312,00
12 Mechanical Works 2.646,00
13 Electrical Works 1.764,00
14 Infrastructure Jobs 997,00
15 Garden and Landscaping 2.553,00
16 Outdoor Swimming pool 448,00
73.814,00
HORIZON VILLASCONSTRUCTION STATUS REPORT
Gündoğdu Surveying4.7
.2014 Total
Time % Progress
Aktivite GruplarıCode
10.0
6. /
27.0
6.
Tota
l
Physical % Progress
6,85%
1,04%
3. ANALYSIS OF PROGRESS
PHYSICAL ANALYSIS OF CUMULATIVE PROGRESS
31.5.2015
MANHOUR
TotalPlanned Acquired
Deviation
PROJECT INFORMATION
SAPANCA / HORIZON VILLAS
31.5.2015
10.6.2014
0
25
340
Project
Project Completion Date
Project Start Date
Total Working Days
The Remaining Days
Day of Delay
Planned Completion Date
3.7
.2014
PMO
BadışoğullarıExcavation-Retaining
Walls
Project Management
29.6
.2014
30.6
.2014
DATA MANHOUR 04.07.2014
1.7
.2014
2.7
.2014
Direct/
Indirect
DescriptionCompany
28.6
.2014
ANALYSIS OF PHYSICAL PROGRESS 04.07.2014
Code Aktivite GruplarıTotal
Planned Acquired Deviation
MANHOUR
Excavation-Backfilling
Retaining WallReinforcedConcrete
WorksBrick Walls Roofing Waterproofing Windows Doors Facade
FinishingWorks
Mortared
FinishingWorks
MechanicalWorks
ElectricalWorks
InfrastructureJobs
Garden andLandscaping
OutdoorSwimming
pool
Total 2.970,00 7.308,00 23.600,00 1.611,00 849,00 854,00 1.008,00 756,00 5.324,00 7.814,00 13.312,00 2.646,00 1.764,00 997,00 2.553,00 448,00
PlannedManhour
1.249,00 1.476,00
Planned % 42,05% 20,20%
AcquiredManhour
1.296,00 1.647,00
Acquired % 43,64% 22,54%
0,00
5.000,00
10.000,00
15.000,00
20.000,00
25.000,00CUMULATİVE PROGRESS