Upload
psit-in
View
2
Download
0
Embed Size (px)
Citation preview
2 2
RUNNING THE MACHINE AT NO LOAD
DRYING THE MACHINE IN H2 MEDIUM
DRYING THE STATOR WDG BY CIRCULATING HOT AIR
DRYING OUT BY CIRCULATING HOT WATER (50 DEG C)
DRYING OF WINDING
3 3
Run the machine at no load
Heat generated by windage losses in the machine is utilized for heating
Commission the seal oil system
Admit dry instrument air (pr = 0.2 Ksc)
Purge the moist air periodically through generator drain.
Keep gas driers in service
Regulate gas cooler outlet valve to control the stator winding temperature.
The stator winding temperature should not be greater than 75 degrees
Core temperature 95 degrees
Rotor winding 110 degrees
Measure PI/IR values every three hours
Stop heating when PI = 2
DRYING OF WINDING: RUNNING THE MACHINE AT NO LOAD
4 4
Procedure same as that of air
Keep Hydrogen pressure at 1.15Ksc
Purge out 1 cylinder every two hours to maintain low humidity inside the Generator
DRYING OF WINDING: Using Hydrogen
DRYING OF WINDING: Circulating Hot air
ADMIT HOT AIR AT 65 Degrees
MAINTAIN AIR PRESSURE AT 2-3Ksc
ADMIT AIR BEFORE MAGNETIC FILTER
5 5
Hot water temperature 50 degrees.
Maintain flow at 25m3 an hour
Maintain winding temperature between 65-75 degrees for 72 hours.
Drain water from winding
Blow hot air through winding
Measure IR and PI value
DRYING OF WINDING: using hot water
MEASUREMENT OF IR AND PI
WINDING SHOULD BE COMPLETELY DRY.
NEUTRAL AND PHASE POINT SHOULD BE DISCONNECTED AND EACH WINDING SHOULD BE SEPARATE
WHILE MEGGERING ONE PHASE OTHER TWO PHASE SHOULD BE GROUNDED.
ABSORPTION COEFFICIENT = R60 / R15 > 1.3
POLARISATION INDEX (PI) = R600 / R60 > 2
6 6
IR AND PI MEASUREMENT
TAN DELTA MEASUREMENT
DC WINDING RESISTANCE
HIGH VOLTAGE TEST
ELCID TEST
GAS TIGHTNESS TEST
HYDRO TEST
TEST ON STATOR
7 7
WINDING SHOULD BE COMPLETELY DRY.
NEUTRAL AND PHASE POINT SHOULD BE DISCONNECTED AND EACH WINDING SHOULD BE SEPARATE
WHILE MEGGERING ONE PHASE OTHER TWO PHASE SHOULD BE GROUNDED.
ABSORPTION COEFFICIENT = R60 / R15 > 1.3
POLARISATION INDEX (PI) = R600 / R60 > 2
TEST ON STATOR: IR AND PI MEASUREMENT
8 8
Evaluation of stress grading, dielectric loss and homogenity of the winding.
The insulator cannot be made 100% pure. Also due to ageing of insulator the impurities like, dirt and moisture enter into it. These impurities provide conductive path to the current. Consequently, leakage electric current flowing from line earth through insulator has also resistive component.
In other way the healthiness of an electrical insulator can be determined by ratio of resistive component to capacitive component. For good insulator this ratio would be quite low. This ratio is commonly known as tanδ or tan delta. Sometimes it is also referred as dissipation factor.
TEST ON STATOR: TAN DELTA MEASUREMENT
9 9
In the vector diagram above, the system voltage is drawn along x-axis. Conductive electric current i.e. resistive component of leakage current, IR will also be along x-axis.
As the capacitive component of leakage electric current IC leads system voltage by 90°, it will be drawn along y-axis.
Now, total leakage electric current IL(Ic + IR) makes an angle δ (say) with y-axis.
Now, from the diagram above, it is cleared, the ratio, IR to IC is nothing but tanδ or tan delta.
10 10
Detects poor connection and conductor short circuit
DC resistance value is measured. After temperature correction, it is compared with factory value. Variation with in 2% is considered as normal
TEST ON STATOR: DC WINDING RESISTANCE
TEST ON STATOR: HIGH VOLTAGE TEST
At 2.5 kv, for one minute for a new rotor at site. Value may be reduced for old rotor. Generally carried out only when any repair is done on the rotor winding.
2 times the rated voltage +1 kv for first time
80% of the previous value for the second time
80% of the previous value for the subsequent times
11 11
Electromagnetic Core Imperfection Detection Test.
Detects healthiness of stator core and lamination insulation
It is a non destructive test
TEST ON STATOR: ELCID TEST
TEST ON STATOR: GAS TIGHTNESS TEST
Keep air inside generator casing at 3.5Ksc for 24 hours.
Leakage should not be more than 1% of internal volume of stator alone and 5% in case of completely assembled generator.
Volume (H2) / Volume (air) = 3.2
12 12
HYDRAULIC TEST FOR THE STATOR WINDING IS CONDUCTED AT
5 KG/ cm2 FOR 24 HOURS USING FILTERED DM WATER.
NO DROP IS ALLOWED.
PROBABLE LEAK POINTS ARE:
TEFLON HOSES AT THE TURBINE END
THE CONNECTING PIPES OF THE TERMINAL BUSHINGS
THE CONNECTING PIPES AT THE EXCITER END
TEST ON STATOR: HYDRO TEST OF STATOR WINDING
14 14
PURGE TEST OF TG ROTOR.
GAS TIGHTNESS TEST OF ROTOR.
DYE PENETRATION TEST OF ROTOR.
D.C. WINDING RESISTANCE TEST.
IR AND PI MEASUREMENT.
TEST ON ROTOR
TEST ON ROTOR: PURGE TEST
Pressure of 3. 0 ± 0.1KG/cm2 GAUGE SHOULD BE APPLIED AT THE VENTILATING CANALS OF SLOT THROUGH THE ADOPTER.
While carrying out test on overhang, a static pressure of 50 mm of water column should be maintained under retaining ring.
The average velocity pressure in the canals of slot portion should not be less than 15 mm of water column for each zone and 21 mm of water column for each slot.
The minimum value of static pressure in individual canals of over hang portion should not be less than 15mm of water column.
Fully closed canals are not allowed in the over hang portion of rotor winding.
Ensure that all the ventilation canals/ ducts are properly sealed after the purge test.
16 16
Dye penetration test
Ultra sonic test
These tests are carried out to check the surface of the retaining ring for any sub surface crack
TEST ON ROTOR: TEST ON ROTOR RETAINING RING
TEST ON ROTOR: AC IMPEDENCE MEASUREMENT
This is carried out at different speeds of the rotor.
To detect any displacement of winding in the slot.
To detect the presence of short circuited turns.
17 17
Dye penetration test :
It is a non destructive testing technique to detect surface breaking defects in a non porous material.
The surface is cleaned and prepared for inspection.
Liquid penetrant is applied to the surface and is drawn into cracks and porous by capillary action
After the dwell time the liquid penetrant is wiped off and surface is dried.
A developer is sprayed on the surface n order to extract the liquid penetrant from possible defects.
After the proper time for development of indications, visual inspection is carried out in order to revel defects.
Final cleaning if the surface.
Dye Penetration Test
18 18
The generator is rotated at the rated speed,
• all the terminals are disconnected from loads,
• the field current is set to zero first.
• Next, the field current is increased in steps and the phase voltage (whish is equal to the internal generated voltage EA since the armature current is zero) is measured.
Since the unsaturated core of the machine has a reluctance thousands times lower than the reluctance of the air-gap, the resulting flux increases linearly first. When the saturation is reached, the core reluctance greatly increases causing the flux to increase much slower with the increase of the mmf.
Open-Circuit Characteristic is the graph of generated voltage
against field current with the terminals open-circuited
and running at synchronous speed
Maintain the machine at its rated speed.
Vary the rotor current.
Measure the rotor voltage and the stator voltage.
OCC
19 19
The generator is rotated at the rated speed, with the field current is set to zero first, and all the terminals are short-circuited through ammeters.
Next, the field current is increased in steps and the armature current IA is measured as the field current is increased.
The plot of armature current (or line current) vs. the field current is the short-circuit characteristic (SCC) of the generator.
The SCC is a straight line since, for the short-circuited terminals, the magnitude of the armature current is
SCC
20 20
TESTING OF RELAYS
TESTING OF STATIC EXCITATION SYSTEM
CHECKING OF ANNUNCIATIONS
CHECKING OF GT COOLING SYSTEM
RUN UP OF TEST
CHECKING OF VIBRATION
SEAL OIL DRAIN TEMPERATURE AND BEARING METAL
TEMPERATURE
OPERATION OF ISOLATORS AND BREAKERS
SYNCHRONISING AND HOURLY CHECKS
STARTING OF GENERATOR
21 21
MODE OF OPERATION – Auto & Manual
SUPPLY ARRANGEMENTS
LIMITER CARDS
BRIDGE FAILURE CONDITION
OPERATING PRINCIPLES
STATIC EXCITATION SYSTEM
22 22
INITIAL ASSEMBLY
PREPARATION OF OIL
FILLING AND CIRCULATION OF OIL
TESTING OF OIL
TRANSFORMER TESTING
BACK CHARGING OF TRANSFORMER
CHECKING THE COOLING SYSTEM
CHECKING THE RELAYS AND ANNUNCIATIONS
GENERATOR TRANSFORMER