41
Soft Landings a persuasive case [email protected]

Soft landings - A persuasive case

  • Upload
    bsria

  • View
    558

  • Download
    0

Embed Size (px)

DESCRIPTION

Rod Bunn provides a case study on how to succeed with a Soft Landings project

Citation preview

Page 1: Soft landings  - A persuasive case

Soft Landings a persuasive case

[email protected]

Page 2: Soft landings  - A persuasive case

Once upon a time…

There was a project …

And this project had a visionary client . . .

Visionary client

…who pulled together a great team of designers to devise a low carbon, award-winning building.

Page 3: Soft landings  - A persuasive case

3 Making buildings better

Visionary client

The architect had loads of experience with passive solar design…

The engineers had loads of experience with renewable energy systems

Architect who knows the

importance of a North symbol

Low Carbon Consultant

Page 4: Soft landings  - A persuasive case

4 Making buildings better

The client appointed a sustainability consultant…

…And an external BREEAM assessor….

Many of the right ingredients for a sustainable building were in place…

Page 6: Soft landings  - A persuasive case

6 Making buildings better

The budget was tight…

The client chose a design and build procurement on a guaranteed price

The scheme design was passed to the contractor and the contractor’s design team did the detail design..

Page 7: Soft landings  - A persuasive case

7 Making buildings better

The tender returns were too expensive by about £500K. This affected some key design details

Value engineering cut out non-critical items, and brought the project back on budget

Cost of Unnecessary

design

Unnecessary costs of

components

Unnecessary costs of

materials

Unnecessary cost of

buildability

Unnecessary life cycle cost

The VE vision

Page 8: Soft landings  - A persuasive case

8 Making buildings better

Negative consequences of VE saw the controls system re-engineered to a cheaper system

Cost of Unnecessary

design

Unnecessary costs of

components

Unnecessary costs of

materials

Unnecessary cost of

buildability

Unnecessary life cycle cost

Systems that lost critical components, or which needed some re-design, were never checked for integrity…

Design subtleties

engineered out

Cheaper components sourced by contractors

Loss of robustness in

fittings

Not enough attention to

commissioning

Life-cycle considerations abandoned for

lowest price

The VE vision The VE reality

Page 9: Soft landings  - A persuasive case

9 Making buildings better

Time and cost issues trumped quality…

The lack of a commissioning strategy saw commissioning rushed and unfinished at PC

Stresses and strains in the project team led to a break down in communication and trust

Commissioning

Practical completion and

move in

Page 10: Soft landings  - A persuasive case

10 Making buildings better

Client left the contractor and project manager in

charge and didn’t provide leadership

Client-side designers watched from afar and couldn’t influence what they couldn’t see or be

invited to comment upon

Packaged sub-contractors often

in charge of critical details

M&E contractor and novated design team

reported to main contractor

Occupants wait for the move in date, but had

minimal support, training and

guidance

Page 11: Soft landings  - A persuasive case

11 Making buildings better

Design detailing was poor, and the controls unmanageably complex

Page 12: Soft landings  - A persuasive case

12 Making buildings better

When the building opened, the staff were ill-prepared, the energy metering didn’t work properly, and the energy use was much higher than the client expected

The contractors only attended site to deal with

defects

It took 9 months to get the O&M manuals…

The gas boilers were set up on the BMS to take the lead on heating, not the GSHP….

Page 13: Soft landings  - A persuasive case

13 Making buildings better

The as-built EPC was a B…but the DEC became an E

Page 14: Soft landings  - A persuasive case

14 Making buildings better

A BUS occupant survey 12 months later showed the occupants didn’t like the building

Although it won an architectural award and

occupants thought it looked quite good…!

Page 15: Soft landings  - A persuasive case

15 Making buildings better

Everyone set out with great intentions, but they foundered on over-ambitous targets, poorly informed cost-cutting, over-complex systems, inadequate commissioning, rushed handover, minimal end-user training, and a lack of post-handover support.

That would normally be

~THE END ~

But the client had another project planned, and the

consultants said “we need to learn from experience…”

Page 16: Soft landings  - A persuasive case

16 Making buildings better

…So they said… ….why don’t we adopt the BSRIA Soft Landings process to make the next building better…?

So they did…

Page 17: Soft landings  - A persuasive case

17 Making buildings better

• The lead designers gave the client a copy of the Soft Landings Core Principles

• The client liked what it read

• “Will it cost me more, it asked?”

• “Much less than the cost of failures, time wasted, and energy bills being far higher than you intended,” said the designers

• “OK, I’m interested, said the client…”

• …What do we do next?

Page 18: Soft landings  - A persuasive case

18 Making buildings better

• Adopt the Soft Landings Framework as the primary approach to managing the project

• Use the BSRIA guidance How to procure Soft Landings to embed Soft Landings in the Client’s Requirements and the contract using the proposed clauses

• Invite tenders on willingness to do Soft Landings (not their price)

• Make sure at least one of the primary designers joins the BSRIA Soft Landings User Group to gain insights

• Commit to a period of professional aftercare and POE

Page 19: Soft landings  - A persuasive case

19 Making buildings better

Everyone on the project team focused on actual operational outcomes

Page 20: Soft landings  - A persuasive case

20 Making buildings better

• Existing programme management processes were developed to accommodate Soft Landings

• There was no need to reinvent the wheel. They made use of existing meetings and tools

• They found what they could for free, what could be achieved from modifying existing project activities, and what was extra and needed to be paid-for

• Soft Landings Champions were appointed on the client and project teams

Page 21: Soft landings  - A persuasive case

21 Making buildings better

Soft Landings Process Map – stage-by-stage

Page 22: Soft landings  - A persuasive case

22 Making buildings better

Page 23: Soft landings  - A persuasive case

23 Making buildings better

• The project team adopted reality-checking at key stages of the project

• They checked energy, usability and maintainability issues

• This informed commissioning, training, fine-tuning and a CIBSE TM54 energy model

• It ensured risky and innovative systems got more attention beyond design reviews

Page 24: Soft landings  - A persuasive case

24 Making buildings better

Page 25: Soft landings  - A persuasive case

25 Making buildings better

More attention to performance metrics – energy and occupants

Page 26: Soft landings  - A persuasive case

26 Making buildings better

Page 27: Soft landings  - A persuasive case

27 Making buildings better

A through commissioning plan was set early on

Staged commissioning proved insightful: thermography surveys and pressure tests

Page 28: Soft landings  - A persuasive case

28 Making buildings better

Page 29: Soft landings  - A persuasive case

29 Making buildings better

The move-in, and training and support was well-planned

Page 30: Soft landings  - A persuasive case

30 Making buildings better

User guides were simple, updatable, and accessible

Page 31: Soft landings  - A persuasive case

31 Making buildings better

Far more effort was put into end-user guidance

Page 32: Soft landings  - A persuasive case

32 Making buildings better

Professional support in the aftercare period paid dividends

Page 33: Soft landings  - A persuasive case

33 Making buildings better

Page 34: Soft landings  - A persuasive case

34 Making buildings better

The occupants liked this building a lot more

Page 35: Soft landings  - A persuasive case

35 Making buildings better

A process that focuses on identifying operational risks before they become ingrained

and irredeemable problems

A method of managing those risks during briefing, design, construction, handover and

initial operation

Support for those risks during the first few operating seasons

The application of experience and feedback from earlier projects to eliminate or

reduce risks, and focus on ways to enhance performance

Soft Landings help you manage performance risks

Page 36: Soft landings  - A persuasive case

36 Making buildings better

Final observations

Page 37: Soft landings  - A persuasive case

37 Making buildings better

What clients and industry need now is a helpful degree of convergence

On processes and procedures On training and technical support On terminology, on the cost benefits, on the contractual requirements In reporting procedures and risk management methods (in BIM) On definitions of operational outcomes and performance requirements On metrics for measuring success – both quantitative and qualitative

Government Soft Landings and BIM

from 2016

Page 38: Soft landings  - A persuasive case

38 Making buildings better

Technical criteria

…To many clients, the CONTEXTUAL CRITERIA are much more important than the technical criteria in judging the success of a building

Which means we need to find ways of assessing them – a big challenge

Contextual criteria

Quality of work

environment, space use, resource efficiency,

health and well-being, productivity – zero FM

complaints

?

Page 39: Soft landings  - A persuasive case

39 Making buildings better

Soft Landings Challenges and opportunities

Q: How can you make Soft Landings work on your projects?

Is there really any alternative?

Page 40: Soft landings  - A persuasive case

40 Making buildings better

The Soft Landings Framework Includes all the procedures for applying Soft Landings, plus checklists and generic work plans Soft Landings Core Principles The main requirements for defining a full Soft Landings project Soft Landings for schools The case for Soft Landings 1: Energy cost variations BREEAM 2011 and Soft Landings

Download from www.softlandings.org.uk

Free guidance to get you started

Page 41: Soft landings  - A persuasive case

More information from

[email protected]