FONDA
HDB LIFT UPGRADING PROGRAM
D&B OF UPGRADING PROJECTS FOR G8B
ARCHITECTURAL
DESIGN
ARCHITECTURAL DESIGN
- PROJECT BRIEF
- DESIGN APPROACH
- LIFT PROPOSAL
- PRIVACY
- DESIGN CONSIDERATION
- CONSTRUCTION
- HOME IMPROVEMENT PROGRAMME
(HIP)
- SITE MANAGEMENT
- DESIGN PROPOSAL
PRECINT A
PRECINT B
PRECINT C
PRECINT D
PRECINT E
PRECINT F
STRUCTURAL DESIGN
DESIGN CRITERIA & LIFT SHAFT DESIGN
M&E DESIGN
FONDA
HDB LIFT UPGRADING PROGRAM
DESIGN & BUILD LUP + HIP FOR
HOLLAND CLOSE PRECINT
INTRODUCTION DESIGN SCOPED&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAMINTRODUCTION DESIGN SCOPE
PROJECT BRIEF
The Design and built proposal for G8 involves Lift
upgrading Program (LUP) for the following Precinct;
Precinct A
Bedok North Avenue 3 Blocks 401 to 404
Precinct B
Ang Mo Kio Avenue 4 Blocks 108 to 111
Precinct C
Ang Mo Kio Avenue 1 /3 Blocks 221, 222, 229 to 235
Precinct D
Ang Mo Kio Avenue 3 Blocks 301, 302, 322 to 327
Precinct E
Commonwealth Avenue West Blocks 410 to 412
Precinct F
Holland Close / Avenue / Drive Blocks 6, 9 to 13, 40 to 43, 45 to 47 and;
(HIP) Home Improvement program for
Precinct G
Holland Close Blocks 31 and 32
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAMINTRODUCTION DESIGN SCOPE
1.0 DESIGN APPROACH
1.1 The solution derived for the project is a result of close co-ordination and integration of the expertise of the various professional disciplines, focusing on achieving a most optimal ‘value engineering’ solution meeting all fundamental requirements, standards set by HDB. Most importantly, to ensure design is meets stringently to all mandatory building bylaws set by the relevant authorities, and also be able to address security and privacy issues thru well integrated design features.
1.2 The LUP’s proposal consists of new lift shaft constructed primarily of steel structure and cladding panels. Fundamentally, the choice of construction methodology is to achieve speedier and neater construction process. Due consideration is also given to environmental friendliness thru usage of material selection which are recyclable and deriving good detailing for ease of construction, as well as mitigating future maintenance cost.
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAMINTRODUCTION DESIGN SCOPE
2.0 LIFTS PROPOSAL
2.1 The location for the new lifts, shutting down of existing lifts and replacement of new lifts, generally shall complies with the given design brief.
2.2 Each new lift locations shall be designed within it’s specific site constraint, such that ventilations and setback meets the requirement stipulated by FSSD.
2.3 Ramps of not more than 1:12 shall be provided to bridge differences in levels or to replace existing steps where occurred, in comply with the barrier free accessibility code stipulated by BCA.
2.4 Careful studies and planning shall be make to each individual blocks to ensure disruption to existing infrastructure and inconveniences to the resident are minimize.
3.0 PRIVACY
3.1 This is an important design consideration, which fundamentally, the new lift position must not open within the sight of the dwelling units windows and doors compromising the resident’s privacy. The lift shaft should also be strategically plan such that views and ventilation to the dwelling units are nit affected.
3.2 Where there is occurrence of angled view into the window of the dwelling units, design features like vertical louvers screen/fins wall shall be strategically placed to cut off visibility, yet maintaining cross air flow through the new lift lobby.
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAMINTRODUCTION DESIGN SCOPE
3.3 PROTECTION FROM KILLER LITTER
Generally, this is to mitigate risk of falling litter to any existing facilities or amenities that is located within close proximity to new lift lobbies. As a rule of thumb, such amenities within 5m radius of the lift lobbies shall be relocated.
4.0 CONSTRUCTION
4.1 The use of mainly steel materials and aluminiumcladding shall contribute to a speedier and neater construction process, being that most work will be fabricated and constructed offsite and installed on site. Upon the installation of the new steel frame, the cladding shall follow consequentially, to avoid the image of the incomplete steel frame of the lift shaft. The proposed construction methodology will result in a reduced time frame for the construction period, and also entail a more efficient and safe working environment within the estate.
4.2 Existing trees will be required to be pruned or removed, where affected by the new lifts. However, every attempt will be make to minimize tree felling, where possible.
4.3 Survey shall be conducted on underground Services, and shall be diverted at the first phase of the work, if determined to affect the new lift position.
.4.5 Detailed Planning and Construction Phasing shall be planned to run concurrently within the dwelling units to reduce the construction period. Proper co-ordination and close liaison with the residents during the execution of the work shall be the primary focus by the contractor’s management team.
5M5M
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAMINTRODUCTION DESIGN SCOPE
5.0 HOME IMPROVEMENT PROGRAMME (HIP)
5.1 materials specification + Quality
Essentially, Materials and products proposed for the HIP shall comply with the specification stipulated under the contract and the requirement set by HDB.
Material’s selection should also consider high durability and easy maintenance. The followings are a summary of items included under HIP;
1) PVC sliding or Bi-fold door to toilet
2) Sanitary Ware and sanitary pipes replacement
3) Ceramic wall and floor tiles (HDB approved type)
4)Aluminium Glass louvers window
5) New aluminium clothes drying racks
6) Replacement of pipe socket
7) Aluminium refuse chute hopper
.
6.0 SITE MANAGEMENT
A well managed site shall be the key success to the
project execution, and minimising inconvenience and
disturbance to the resident.
The use of mainly prefabricated steel structure will
contribute to a neat and tidy site, as such materials are
fabricated off site and will have very quick installation on
site. Where possible, prefab components will be
encouraged to reduce on site casting works. Proper
hoarding shall be maintained at all time to allow a safe
pedestrian routes at all time.
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
SITE LAYOUT PLAN
BEDOK NORTH AVENUE 3 block 401- 404DESIGN PROPOSAL
PRECINT A
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 401 & 402TYPICAL GROUND FLOOR PLAN
BLOCK 403 & 404TYPICAL GROUND FLOOR PLAN
BEDOK NORTH AVENUE 3 block 401- 404DESIGN PROPOSAL
PRECINT A
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
TYPICAL GROUND FLOOR PLAN
BEDOK NORTH AVENUE 3 block 401- 404DESIGN PROPOSAL
PRECINT A
D&B OF UPGRADING PROJECTS FOR G8B
TYPICAL UPPER FLOOR PLAN
ELEVATION OF LIFT
Entrance Canopy and canopy will be provided
Privacy fins and ledge to be provided on the upper floors
Full wall tiles on ground floor up to the edge of staircase
Tile bands to typical floor lift lobbies and entrance canopy will be provided
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 404
BEDOK NORTH AVENUE 3 block 401- 404DESIGN PROPOSAL
ARTIST IMPRESSION
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
SITE LAYOUT PLAN
ANG MO KIO AVE 4 blocks 108 - 111DESIGN PROPOSAL
PRECINT B
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 108TYPICAL UPPER STOREY FLOOR PLAN
BLOCK 111TYPICAL GROUND FLOOR
ANG MO KIO AVE 4 blocks 108 - 111DESIGN PROPOSAL
PRECINT B
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 109TYPICAL UPPER STOREY FLOOR PLAN
BLOCK 110TYPICAL GROUND FLOOR PLAN
ANG MO KIO AVE 4 blocks 108 - 111DESIGN PROPOSAL
PRECINT B
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
TYPICAL GROUND FLOOR PLAN
DESIGN PROPOSAL
PRECINT B
D&B OF UPGRADING PROJECTS FOR G8B
TYPICAL UPPER FLOOR PLAN
ELEVATION OF LIFT
Entrance Canopy and canopy will be provided
Privacy fins and ledge to be provided on the upper floors
Full wall tiles on ground floor up to the edge of staircase
Tile bands to typical floor lift lobbies and entrance canopy will be provided
ANG MO KIO AVE 4 blocks 108 - 111
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 111
ANG MO KIO AVE 4 blocks 108 - 111DESIGN PROPOSAL
ARTIST IMPRESSION
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
SITE LAYOUT PLAN
ANG MO KIO AVE 1/3 blocks 221,222, 229 to 235DESIGN PROPOSAL
PRECINT C
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 221 & 222TYPICAL UPPER STOREY FLOOR PLAN
BLOCK 229 & 231TYPICAL UPPER STOREY FLOOR PLAN
ANG MO KIO AVE 1/3 blocks 221,222, 229 to 235DESIGN PROPOSAL
PRECINT C
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 234TYPICAL UPPER STOREY FLOOR PLAN
BLOCK 230TYPICAL UPPER STOREY FLOOR PLAN
ANG MO KIO AVE 1/3 blocks 221,222, 229 to 235DESIGN PROPOSAL
PRECINT C
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 232, 233 & 235TYPICAL UPPER STOREY FLOOR PLAN
ANG MO KIO AVE 1/3 blocks 221,222, 229 to 235DESIGN PROPOSAL
PRECINT C
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
TYPICAL GROUND FLOOR PLAN
DESIGN PROPOSAL
PRECINT C
D&B OF UPGRADING PROJECTS FOR G8B
TYPICAL UPPER FLOOR PLAN
ELEVATION OF LIFT
Entrance Canopy and canopy will be provided
Privacy fins and ledge to be provided on the upper floors
Full wall tiles on ground floor up to the edge of staircase
Tile bands to typical floor lift lobbies and entrance canopy will be provided
ANG MO KIO AVE 1/3 blocks 221,222, 229 to 235
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 233
ANG MO KIO AVE 1/3 blocks 221,222, 229 to 235DESIGN PROPOSAL
ARTIST IMPRESSION
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
LUP B7 ANG MO KIO AVE 3 blocks 301,302,322 TO 327DESIGN PROPOSAL
SITE LAYOUT PLANPRECINT D
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 301 & 302TYPICAL UPPER STOREY FLOOR PLAN
LUP B7 ANG MO KIO AVE 3 blocks 301,302,322 TO 327DESIGN PROPOSAL
BLOCK 324 & 325TYPICAL UPPER STOREY FLOOR PLAN
PRECINT D
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 326TYPICAL UPPER STOREY FLOOR PLAN
LUP B7 ANG MO KIO AVE 3 blocks 301,302,322 TO 327DESIGN PROPOSAL
BLOCK 327TYPICAL UPPER STOREY FLOOR PLAN PRECINT D
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 322TYPICAL UPPER STOREY FLOOR PLAN
LUP B7 ANG MO KIO AVE 3 blocks 301,302,322 TO 327DESIGN PROPOSAL
PRECINT D
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 323TYPICAL UPPER STOREY FLOOR PLAN
LUP B7 ANG MO KIO AVE 3 blocks 301,302,322 TO 327DESIGN PROPOSAL
PRECINT D
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 302
LUP B7 ANG MO KIO AVE 3 blocks 301,302,322 TO 327DESIGN PROPOSAL
ARTIST IMPRESSION
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
SITE LAYOUT PLAN
COMMONWEALTH AVENUE WEST blocks 410 to 412DESIGN PROPOSAL
PRECINT E
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 410, 411 & 412TYPICAL UPPER STOREY FLOOR PLAN
COMMONWEALTH AVENUE WEST blocks 410 to 412DESIGN PROPOSAL
PRECINT E
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 410
COMMONWEALTH AVENUE WEST blocks 410 to 412DESIGN PROPOSAL
ARTIST IMPRESSION
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
SITE LAYOUT PLAN
HOLLAND CLOSE blocks 6, 9 to 13, 40 to 43, 45 to 47DESIGN PROPOSAL
PRECINT F
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 6 & 9TYPICAL GROUNDFLOOR PLAN
HOLLAND CLOSE blocks 6, 9 to 13, 40 to 43, 45 to 47DESIGN PROPOSAL
PRECINT F
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 11TYPICAL GROUNDFLOOR PLAN
HOLLAND CLOSE blocks 6, 9 to 13, 40 to 43, 45 to 47DESIGN PROPOSAL
PRECINT F
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 12TYPICAL GROUNDFLOOR PLAN
HOLLAND CLOSE blocks 6, 9 to 13, 40 to 43, 45 to 47DESIGN PROPOSAL
PRECINT F
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 13TYPICAL GROUNDFLOOR PLAN
HOLLAND CLOSE blocks 6, 9 to 13, 40 to 43, 45 to 47DESIGN PROPOSAL
PRECINT F
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
BLOCK 47TYPICAL GROUND FLOOR PLAN
HOLLAND CLOSE blocks 6, 9 to 13, 40 to 43, 45 to 47DESIGN PROPOSAL
PRECINT F
BLOCK 10TYPICAL UPPER STOREY FLOOR PLAN
D&B OF UPGRADING PROJECTS FOR G8B
FONDA
HDB LIFT UPGRADING PROGRAM
HOLLAND CLOSE blocks 6, 9 to 13, 40 to 43, 45 to 47DESIGN PROPOSAL
PRECINT F
D&B OF UPGRADING PROJECTS FOR G8B
Existing 3 steps located at the upper
storey does not allow for barrier free
access to the common corridor as well
as does not allow a new lift opening to
be created at one of the existing lift
shaft. The creation of a single ramp to
replace the steps proves to be too long
and will also stretch beyond the
nearest main door opening of the
nearest dwelling unit. Our proposal is
to raise the floor level of the existing
corridor landing leading in front of the
new lifts and create ramps on both
sides of the common corridor so as to
shorten the length of ramps created for
better barrier free accessibility.
Lift Upgrading Proposal
EXISTING 3 STEPS TO BE REMOVED
TYPICAL UPPER STOREY PLAN
NEW STEPS
RAISED FLOOR LEVEL
FONDA
HDB LIFT UPGRADING PROGRAM
HOLLAND CLOSE blocks 6, 9 to 13, 40 to 43, 45 to 47DESIGN PROPOSAL
PRECINT F
D&B OF UPGRADING PROJECTS FOR G8B
Existing 3 steps located at the upper
storey does not allow for barrier free
access to the common corridor as well
as does not allow a new lift opening to
be created. The creation of a single
ramp to replace the steps proves to be
too long and will also stretch beyond
the nearest main door opening of the
nearest dwelling unit. Our proposal is
to raise the floor level of the existing
corridor landing leading in front of the
existing lifts, and create ramps on both
sides of the common corridor so as to
shorten the length of ramps created for
better barrier free accessibility.
Lift Upgrading Proposal
PROPOSED
RAISING OF
FLOOR LEVEL
NEW RAMP
NEW LIFT
NEW LIFT
EXISTING
STEPS TO
CONVERT
TO RAMP
TO RECTIFY THE EXISTING BEAM TO MEET
THE MINIMUM HEADROOM CLEARANCE
REQUIREMENT OF 2 METERS
FONDA
HDB LIFT UPGRADING PROGRAM
HOLLAND CLOSE blocks 6, 9 to 13, 40 to 43, 45 to 47DESIGN PROPOSAL