FOCUS on

Powering Bangladesh’s Future

Page 2: Powering of bangladesh- Vision 2021

Investment Requirements Generation & Transmission

PARTICULARS TOTAL VALUE (billion in USD)TRANSMISSION $ 7.53RENEWABLE ENERGY $ 4.5HYDRO & RE $ 0.5DIESEL $ 0.56FURNACE OIL $ 5.89NATURAL GAS $ 7.63IMPORTED COAL $ 12.47DOMESTIC COAL $ 13.92

$7.5

3

$4.5

0

$0.5

0

$0.5

6 $5.8

9

$7.6

3 $12.

47

$13.

92

TOTAL VALUE (billion in USD)

TOTAL VALUE (billion in USD)

Page 3: Powering of bangladesh- Vision 2021

The government of Bangladesh has set a target to bring the whole country under

electricity coverage by 2021.

Bangladesh requires multibillion dollar investments in the power sector.

Bangladesh government is increasingly diversifying the sources of investment.

Innovative funds- Export Credit Agency (ECA) financing is one of the big innovative

ways.

Power Infrastructure is the backbone of development for a country.

Key Points

Page 4: Powering of bangladesh- Vision 2021

12, 071MW

CURRENT INSTALLED CAPACITY

6, 431MW

Current Average Demand

34,000MW

Projected Energy Demand (2030)

42% Of Electricity

Is supplied by the Private Sector

63%Of Electricity Fuel

Is supplied by Natural Gas

62% Of the Population

Have access to Electricity

Powering Bangladesh’s Future

Page 5: Powering of bangladesh- Vision 2021

Present Installed Generation Capacity (MW) as on 01 January, 2017.

Public Sector Installed Generation Capacity (MW)  BPDB 4650APSCL 1200EGCB 622

NWPGCL 440RPCL

BPDB-RPCL JV77

149

Subtotal 7138 (54%)Private Sector

IPPs 3025SIPPs (BPDB) 99SIPPs (REB) 25115 YR. Rental 169

3/5 YR. Rental 1869Power Import 600

                        Subtotal 6,013 (46%)                        TOTAL 13,151 *

* Including Captive Power Total Installed Capacity (13,151 + 2,200) = 15,351 MW

Page 6: Powering of bangladesh- Vision 2021

Present Installed Generation Capacity (MW) as on 01 January, 2017.

MAXIMUM DEMAND SERVED FAR 9,036 MW 30-06-2016

TRANSMISSION LINES (400 kV) 221 Ckt. K.M FY-2016

TRANSMISSION LINES (230 kV) 3185 Ckt. K.M FY-2016

TRANSMISSION LINES (132 kV) 6487 Ckt. K.M FY-2016

GRID SUB-STATION CAPACITY (400/230/132 kV) 520 MVA FY-2016

GRID SUB-STATION CAPACITY (230/132 kV) 9625 MVA FY- 2016

GRID SUB-STATION CAPACITY (132/33 kV) 15,133   MVA FY- 2016

DISTRIBUTION LINES (33 KV & BELOW) (only BPDB)41,919 K.M FY-2016

CONSUMER NUMBER 34,57,178 FY-2016

Page 7: Powering of bangladesh- Vision 2021

21.11

8.052.1

4.211.94

62.59

CURRENT FUEL MIX

FURNACE OILDIESELCOALPOWER IMPORTHYDRONATURAL GAS

DIESEL FURNACE OIL LNG IMPORTED COAL IMPORTED POWER DOMESTIC GAS

25.9

17.9

5

12.2

8.1

6.2

2.57

COST OF GENERATION (TK/UNIT)

CURRENT FUEL MIX & COST OF GENERATION (TK/UNIT)

Page 8: Powering of bangladesh- Vision 2021

PRIMARY GRID SYSTEM OF BANGLAESH

Page 9: Powering of bangladesh- Vision 2021

You can find:Mukhlasur Rahman

THANKS TO ALL