NOVA IVI FERTILITY
AHMEDABAD
Problem : Finishing issues are there as the gap between the two doors of the lift is only 3MM. Solution : One lift door needs to be opened for a human hand to get in
3MM Gap
3MM Gap Only
Problem : Vinyl is not finished properly as there is no space on top as wellSolution : Needs to remove the doors and paste again
NO Space
Problem: Bubbles in the vinyl as the glass doors are cleaned daily with ColinSolution: Pl do not use water/colin on the etching.
Problem: Bubbles in the vinyl as the glass doors are cleaned daily with ColinSolution: Pl do not use water/colin on the etching.
Problem : No creative on the back side.Solution : New Creative on the back side needed. Was not there before.
THANK YOU