1
What can we do? What can we do? against inefficient budget executionagainst inefficient budget execution
May. 6, 2014
Seongbak WiMinistry of Strategy and Finance, Korea Secondee to Inter-American Development Bank
4
세계경제 전망 (%)
Object of budget
Budget a bridge and no output
No monitoring, no sanction
1. Raising an issue
Ⅰ. Raising an issue
5
세계경제 전망 (%)
Request a building construction
Cost : US$9 -> US$15 -> US$ 30
1. Raising an issue
Ⅰ. Raising an issue
6
세계경제 전망 (%)
1. Raising an issue
M&E helps projects implemented as planned and budgeted.
- Line ministries and executing entities have desire to increase
the scale of projects or to use money for personal purpose
For M&E to be effective, we need some strong methods, such
as sanctions against bad executions.
Ⅰ. Raising an issue
8
세계경제 전망 (%)
1. External supervision of project Execution
Ⅱ. M&E in Korea and strengthening the method
▶ Project execution is supervised by government
- payment will be done after checking the process and proof.
▶ Administration of Audit and Inspection :
- fire-off, cut in salary, warning, …
▶ Prosecutors ,
- imprisonment, fine
▶ Parliament and people’s monitoring
9
세계경제 전망 (%)
Ⅱ . M&E in Korea and strengthening the method
▶ Existence of output
vs
▶Feasibility and Efficiency
10
세계경제 전망 (%)
2. Re-assessment of Feasibility
Ⅱ. . M&E in Korea and strengthening the method
▶ Projects start after feasibility test,
However, their feasibilities can change after the initiation
▶ Re-assess of Feasibility will be done
- If TPC has increased by more than 20%
- If new demand forecast is smaller by 30% than the initial one
▶ What if a project appears not to be feasible by reassessment?
11
세계경제 전망 (%)
2. Re-assessment of Feasibility
Ⅱ. . M&E in Korea and strengthening the method
▶ Sanctions by Re-assessment of Feasibility (1)
: Example of stopped projects which completed detailed design
- Janghowon~Jumdong national road(BC=0.24)
- Bukmyun~Bugok natinal road(BC-0.26)
- Sungnam~Janghown natinal road(BC-0.83)
- Imchun~Kanhkyung local road(BC=43)
- Boryung new harbour (BC=0.24)
12
세계경제 전망 (%)
2. Re-assessment of Feasibility
▶ Counter action by re-assessment of feasibility (2) : adjustment
of total costsyear # of
Proj.Initial TPC
(A)Reqest
(B)B/A(%)
Adjust(C)
C/A(%)
2010 (36) 8,783 15,829 80.2 13,826 57.4
2011 (22) 10,627 14,264 34.2 13,012 22.4
Ⅱ. . M&E in Korea and strengthening the method
13
세계경제 전망 (%)
3. Total Project Cost Management
Ⅱ. . M&E in Korea and strengthening the method
▶ MOSF watch the execution of projects to prevent excessive increase
in total cost induced by modification of construction size or design .
▶ TPC rule
- Line ministries should report to MOSF and get approval
- difference between designed project cost and the cost in bidding
- changes in total project cost
14
세계경제 전망 (%)
3. Total Project Cost Management
Ⅱ . M&E in Korea and strengthening the method
▶ what if an entity violate TPC rule?
- execution of projects without report of changes project cost
▶ Sanctions, introduced in 2000
- Cut in supplementary expenses of projects
- Cut in operational expenditures of the relevant line ministry
- No budgeting the unapproved increment
15
세계경제 전망 (%)
3. Total Project Cost Management
Ⅱ. . M&E in Korea and strengthening the method
▣ Effect of Introducing Sanctions to TPC Management
TPC requested TPC Adjusted
Before introducing sanctions (1996~1999)
26.4% 11.1%
After introducing sanctions (2000~2003)
4.4% 1.0%
16
세계경제 전망 (%)
4. Budget Waste Reporting System
▶ Concept : On-line monitoring system open to the public
- operating 309 portal sites : 50 in central governments,
246 in local governments, 13 in state-owned enterprises
- Number of reported projects by people are increasing
(2009) 1,390 -> (2012) 3,474
Ⅱ. . M&E in Korea and strengthening the method
17
세계경제 전망 (%)
4. Budget Waste Reporting System
▶ Following actions
- MOSF reviews reported issues,
- reassess feasibility, in-depth evaluation
▶ Possible sanctions
- cut in the project cost, cut in the budget, stop the project
.
Ⅱ. . M&E in Korea and strengthening the method
18
세계경제 전망 (%)
4. Budget Waste Reporting System
Ⅱ. . M&E in Korea and strengthening the method
▶ Case : Reconstruction of national road between Yoju-
Yangpyung
- Projects : from 2 lanes to 4 lanes,
- reported issue :
another road is being built.
- Reassessment of feasibility
- cut in TPC, straightening the lanes
$117 mil. → $ 60 mil.
19
세계경제 전망 (%)
5. Performance Evaluation
Ⅱ. . M&E in Korea and strengthening the method
1. Self- evaluation
▶ concept
- MOSF gives check lists for line ministries to evaluate projects
- Line ministries assess performance of programs
- Considers for the next year’s budgeting
▶ counteractions
- cut in the next year’s budget in case of poor performance
20
Linkage between Self Evaluation and Budgeting
Year
Budget change of Projects(%)
Projects (No.) Poor performance
Projects (No.) Good performance
2008 70 Δ6.8 19 6.7
2009 133 Δ12.5 27 6.32010 132 Δ10.0 33 8.4
Ⅱ. . M&E in Korea and strengthening the method
5. Performance Evaluation
21
세계경제 전망 (%)
5. Performance Evaluation
Ⅱ. . M&E in Korea and strengthening the method
2. In-depth Evaluation
▶ concept
- Evaluate appropriateness, effectiveness, sustainability
- in-depth evaluation on some selected projects
▶ counteractions
- Some cases, if some problems were found, are sent to Reassessment of feasibility test
- cut in the project cost, cut in the next year’s budget, stopping the project
23
세계경제 전망 (%)
Challenges in M&E
Ⅲ. Challenges and remarks
Difficulty in monitoringTetrapod for breakwater
24
세계경제 전망 (%)
Challenges in Sanctions
Ⅲ Challenges and remarks
▶ Limitation on effectiveness
- Once a project was launched, it is hard to stop it.
- it is also hard to restore to the initial condition
▶ Reluctance to sanction
- People want to give favor to someone rather than sanction
▶ Is Restriction always desirable?
25
세계경제 전망 (%)
Concluding Remarks
Ⅲ. Challenges and remarks
▶ Effective M&E is as important as planning and budgeting.
- to secure a project to be realized as planned
▶ M&E requires counteractions to be effective
- Strong counteractions, sanctions, will help feedback
and launching a new efficient project