View
2.472
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Using Porous Pavements and Other Green Technologies to Reduce Urban Runoff and Combined Sewer Overflows. Dan Wible, CH2M Hill (presented March 17, 2011)
Citation preview
Onondaga County’s 2010 Porous Pavement ProjectsMeeting Stormwater Goals while Managing Costs
March 17, 2011Joanne M. Mahoney,
County Executive
Dan Wible, P.E., LEED APSenior Project Engineer
www.SaveTheRain.us
Presentation Outline• Case Studies:
• City Lot #21 (formerly the “Farmer’s Market Lot”
• City Lot #3• Pearl Street Lot (DOT)• Creekwalk
• Case Study Topics:• Design Components / Goals• Pre/Post-Construction Photos• Costs and Metrics Summary• Lessons Learned
Parking Lot #21 (Formerly “Farmer’s Market Lot”)
Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”)
• Design Components• Costs and Metrics Summary• Lessons Learned
Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”)
• Design Components:• 5,000sf infiltration system
• Tree trench (2,000sf) with porous pavers and 36” of CU-Structural Soil
• Aggregate infiltration bed under standard asphalt (31” deep)
• Inlet filter inserts• Entire lot repaved (standard asphalt) and
restriped (6 more spaces)• Two outlet control structures with weirs
(connection to existing storm sewer)• Infiltration testing yielded a rate of 20 in/hr
Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”)
• Design Components:• Impervious area managed: 26,250sf• Infiltration area: 5,000sf (loading ratio of
5.3:1)• Runoff capture goal (1”): 2,190cf• 6 new trees• Total soil: 6,000cf (1,000cf per tree)• Total static storage capacity: 4,200cf
(equates to around 2.1” of runoff capture)
Parking Lot #21 (Formerly “Farmer’s Market Lot”)
Before
After
CSO Area: Clinton
Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”)
• Design Components / Goals• Costs and Metrics Summary• Lessons Learned
Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”)
• Total Project Cost: $188,046• Total Estimated CSO Reduction: 328,000 gal• Cost per CSO Reduction: $0.57 per gal
Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”)
• Design Components / Goals• Costs and Metrics Summary• Lessons Learned
Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”)
• Stormwater Details and Specifications• Concrete structures preferred• Overflow weir plates • Concerns over inlet filter inserts
(maintenance)
Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”)
• Trees and Plantings• Temporary maintenance: emphasize/enforce
temporary irrigation and initial pruning• Species selection and maintenance streamlined
in the future with the City Arborist
Case Study: City Lot #21 (formerly the “Farmer’s Market Lot”)
• Subsurface Materials• Infiltration bed stone availability: NYSDOT #3A
is typically the cleanest, most available stone in the size range desired
• CU-Structural Soil Handling/Acceptance: ensure contractor provides appropriate cover and maintenance, and perform testing if needed
• Porous paver edge termination
Porous Pavement / Infiltration Practices in Onondaga County, NY
• Design Assumptions / Guidelines:• Static storage of first inch of runoff• Maximum loading ratio of 10:1 (impervious
area to infiltration area); 5:1 is preferred• Geotextile liner separating rock from soil
(non-woven or woven… or sand?)• Impervious liner where needed (proximity
to utilities, buildings, etc)• Observation well and cleanouts • Perforated distribution pipe and/or
underdrain
Porous Pavement / Infiltration Practices in Onondaga County, NY
• More Design Assumptions / Guidelines:• Dewater within 72 hours• Level bed/trench bottom• Maximum surface grade change of 1-2 feet;
steeper sloped areas may warrant a change in bottom elevation (via berms or other)
• Upper 3” of the infiltration bed subgrade should be scarified prior to bed installation (if necessary)
• Total facility depth should between 24-31 inches (frost consideration)
• Protect existing utilities
Porous Pavement / Infiltration Practices in Onondaga County, NY
• More Design Assumptions / Guidelines:• Setbacks:
• 10ft to buildings with basements• 3ft to buildings without basements• 3ft from utility structures, vents, poles,
etc
City Parking Lot #3
Lot #3
Porous ConcreteCaptures over 700,000 gallons of stormwater annually
CSO Area: Erie Blvd
Case Study: City Lot #3
• Design Components / Goals• Costs and Metrics Summary• Lessons Learned
Case Study: City Lot #3
• Design Components:• 8,380sf infiltration system
• Tree trench with 36” of CU-Structural Soil• 6” porous concrete / aggregate
infiltration bed (23” deep) • Interior tree plantings• Inlet filter inserts and sumps
• Entire lot repaved (standard asphalt) and restriped
• One outlet control structure with removable weir (connection to existing storm sewer)
• Infiltration testing yielded an average rate of 0.48 in/hr (0.24 in/hr used for design)
Case Study: City Lot #3
• Design Components:• Impervious area managed: 38,507sf• Infiltration area: 8,380sf (loading ratio of
4.6:1)• Runoff capture goal (1”): 3,209cf• 23 new trees• Total soil: 7,650cf (333cf per tree, not
including existing soil volume along edge)• Total static storage capacity: 3,392cf
(equates to around 1.1” of runoff capture)• Dewatering time: 72 hours (100-year
storm)
Case Study: City Lot #3
• Design Components / Goals• Costs and Metrics Summary• Lessons Learned
Case Study: City Lot #3
• Total Project Cost: $239,102• Total Estimated CSO Reduction: 625,000 gal• Cost per CSO Reduction: $0.38 per gal
Case Study: City Lot #3
• Design Components / Goals• Costs and Metrics Summary• Lessons Learned
Case Study: City Lot #3
• Stormwater Details and Specifications• Inlet restoration – check if necessary
• Porous Concrete• Test pad quality control
• Letter to contractor noting concerns with aggregate, water retarder, water content
• Site installation permitted as 2nd “test pad”• Cold weather placement: 7 days curing time
per specified temperature requirements
Pearl Street Parking Lot
Pearl Street Parking Lot
CSO Area: Franklin FCF
Case Study: Pearl Street Lot
• Design Components / Goals• Costs and Metrics Summary• Lessons Learned
Case Study: Pearl Street Lot
• Design Components:• 25,300sf infiltration system
• Porous asphalt (1.5”) on 3” of asphalt treated permeable base (ATPB)
• Aggregate infiltration bed under both standard and porous asphalt (24” deep)
• Inlet filter inserts and sumps• Entire lot repaved (standard asphalt) and
restriped• One outlet control structure with removable
weir (connection to existing combined sewer)• Infiltration testing was variable, but yielded an
average rate of 7 in/hr (2 in/hr used for design)
Case Study: Pearl Street Lot
• Design Components:• Impervious area managed: 73,172sf• Infiltration area: 25,300sf (loading ratio of
2.9:1)• Runoff capture goal (1”): 6,098cf• Total static storage capacity: 10,120cf
(equates to around 1.7” of runoff capture)• Dewatering time: 24 hours (100-year
storm)
Case Study: Pearl Street Lot
• Design Components / Goals• Costs and Metrics Summary• Lessons Learned
Case Study: Pearl Street Lot
• Total Project Cost: $396,772• Total Estimated CSO Reduction: 915,000 gal• Cost per CSO Reduction: $0.43 per gal
Case Study: Pearl Street Lot
• Design Components / Goals• Costs and Metrics Summary• Lessons Learned
Case Study: Pearl Street Lot
• Subsurface Utility Location – coordinate with utilities early; lack of response or delayed response resulted in field directives
• Unforeseen Conditions• Subsurface structure demolition: multiple
building foundations were encountered• Balance research costs with schedule and
field directive costs• Ample public notification
Creekwalk
Creekwalk
Revisit Winter 2011: Pearl Street
Revisit Winter 2011: Pearl Street
Revisit Winter 2011: Lot 3
Winter Revisit Notes
• Pearl Street porous pavement performing well, particularly vs. standard pavement, but is being over-salted
• Lot 3 wheelstops – wheelstops vs. curbs with inlets
• Lot 3 porous concrete performing well• Snow storage areas
64
Thank You!
Questions?
Please Visit:www.SaveTheRain.us
Go Nova!