It is common knowledge that every project should have mutually agreed upon objectives that are specific, measurable, achievable, relevant, and time-boxed (SMART). Common knowledge does not automatically equal common practice. Often, projects fail simply because there is no mutual understanding of the objectives and stakeholder expectations are not aligned. This paper outlines a simple yet powerful workshop approach that can help realign objectives and stakeholders’ expectations for a project that is behind schedule. It describes the prerequisites and necessary preparation, delineates the key parts of the workshop, and sketches possible outcomes. --- additional information available at www.TheProjectLeadershipPyramid.net
Citation preview
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2008 Permission is granted to PMI for Congress attendee use only
Re-aligning Project Objectives and
Stakeholders’ Expectations
in a Project Behind Schedule
Session #ADV12
Thomas Juli, Ph.D., PMPManaging Director, Thomas Juli Empowerment Partners
Outline of Session
Introduction Workshop Simulation Conclusion
1. Project situation
2. Objective of simulation
3. Purpose of workshop
4. Workshop set-up and parts
5. Workshop simulation
6. Workshop outcomes and take-aways
7. Lessons learned from other workshops
8. Q & A
Project Situation (1/2)
Project objective: Replace the proprietary call center and promotion management applications with a new CRM (customer relationship management) system
Project objectives agreed by CEO and every department head
Project duration: 9 months
Atmosphere: good, high motivation
Today, 2 months later
Key requirements of the marketing department have been captured and documented
Call Center and the Billing departments have not concluded documenting
their requirements due to different opinions about the scope and level of
project involvement of their subject matter experts
=> Project is behind schedule and not in budget
Resolution:• New full-time project manager replaces part-time project
manager
• Project manager reporting directly to project sponsor
Project Situation (2/2)
KEY QUESTION: Can this workshop become the foundation of project success
and if so, how?
Mission: Do whatever is necessary to get projectback on track and finish it on time and in budget
First activity: Interviewing department chairs
Insights after interviews: No common understanding of the project objectives
Next action: Invitation to project alignment workshop
Objectives of Simulation
The simulation will– sketch a simple, yet powerful approach to realign project objectives and
stakeholders’ expectations,– outline proven workshop approach,– describe the prerequisites and necessary preparation activities,– delineate the key parts of the workshop,– and sketch possible outcomes.
With your help and active participation*
* Active participation in the simulation may vary depending on the actual number of session attendants.
1. Refined project objective
statement which is SMART
(specific, measurable, achievable,
relevant, time-boxed)
2. Objective statement
mutually understood and
supported
1. Get a mutual understanding of each
other’s expectations about the project
2. Revisit the official project objectives
statement and
3. align it with
a) the present situation and
b) stated expectations
of attendants
Purpose of Workshop
Expected OutcomesObjectives
o Introductiono Breakouts (5 groups of 2-3
individuals each, everyone has decision making authority)
• Discuss and summarize their needs and expectations of the project and its deliverables
• Prepared set of questions serve as guideline
o Presentation and discussion of results in whole group
Workshop Setup & Parts
Prioritizing presented breakout results - based on SMART and other pre-defined prioritization criteria
Objectives:
o Qualify the existing project objectives
o Align with stakeholders’ expectations
o Meet previously set criteria
o Summary of findings
o Review of remaining open questions
o Outlook of next steps
Part I:Introduction & Breakouts
Part II:Prioritization
Part III:Conclusion
Workshop attendants: All affected department chairs*, sponsor, business and technical track leaders of the project team
Workshop duration: 3+ hours. Simulation duration: 40 minutes
* Affected departments: marketing, customer care, Call Center, accounting / billing, IT
Part I: BreakoutsInstructions:
1. Answer the following questions*
a) Purpose: Why do you and your organization need a new CRM system? - List the most important reason.
b) Value: On a scale from 1 (low) to 5 (high), what priority does the new CRM system have for you and your organization?
c) Other projects: What other project(s) is (are) more important to you and why? On a scale of 1 to 5, what priorities do they have? List up to 2 other projects.
d) Impact of delay: What impact does it have to you and your organization if the project is delayed and/or does not meet your expectations (e.g., limited scope)? How do you measure, i.e., quantify this impact? - List the 2 most important impacts and quantify them.
e) Fallback plan: Do you have a fallback plan / solution in place if the project fails? How much would it cost? – Limit your response to 2 options and quantify them.
f) SMART project objective(s): Based on your answers above, phrase the project objective(s), making sure that it is a) specific, b) measurable, c) achievable, d) relevant and e) time-boxed.
g) Critical success factors: What are the top 2 most important factors that have to be met for the project to be successful?
2. Print each answer on a separate moderation card (e.g. 4x5 inch card)
3. Appoint one member to present results to whole group. Presentation limit for simulation: 2 minutes
* Simulation will cover only select number of questions.
o Every participant has 3 votes for various categories
o Votes can be split evenly or allocated to one or more entries
Top entry of each category discussed in group
Objective: agree on a single entry which everyone or at least the majority can support
In case of tie: sponsor decides
(1) Categories Purpose, Other Projects and Impact of Delay
(2) Collected SMART Project Objectives
(3) Critical Success Factors
Part II: Prioritization
Voting RulesVoting & Discussion
Sequence
Prioritization ………………….........
Part II: Possible Simulation Results
Topic Marketing Votes Customer Care Votes Call Center Votes Accounting / Billing Votes IT Votes
Purpose need single application for planning and managing marketing activities which ensures consistent data throughout
6
need single application for all relevant customer data
7
we don't want a new system; it is all too technical
0
consistent data throughout
8
support warranty for proprietary systems will run out in 6 months
4(1) Need for consistent data (2) Need for single customer view(3) Need for single marketing application
Other projects -> to identify interdependencies
marketing plan 2009: 5
5
N/A
0
new training program (curriculum): 4moving to new facilities in same building: 5
1
roll-out of billing application: 5------------------------------SOX compliance issues: 5
5----7
support for roll-out of billing application: 3
6(1) New billing application(2) SOX compliance issues(3) Marketing plan 2009
Impact of delay Additional effort (and hence costs) for planning and mgt of marketing campaigns.--------------------------------Lack of flexibility, 3 week ahead notice required for new campaigns
1---
5 (10)
Need to train new season staff in old applications is costly; staff not qualified enough => Churn: overall customer service suffers leading to unhappy customers
5 (10)
None, will continue to use old applications
0
Inconsistent data may lead to wrong accounting data: legal implications
----------profit loss
.
5 (2)---
5 (4)
1) maintenance costs of old system skyrocket, need to hire external support
4
(1) Lack of flexible marketing campaigns(2) Churn(3) Profit loss due to inconsistent data.
Note: Initial voting resulted in tie, new round results in brackets. Final priorities decided by sponsor breakting tie b/w (1) and (2).
SMART project objectives
Implementation of new CRM system covering all documented key reqs by originally agreed delivery date
6
Implementation of new CRM system which allows single view of customer data (correct and consistent) within 6 months. 5
assess available CRM systems, pick one most suitable to CC
0
Implementation of CRM system which guarantees consistent and correct data throughout all applications. 8
Implementation of new CRM system out of the box with minimal customization not exceeding 1000 person days in development and testing within 4 months
4
Implementation of new CRM system which(1) ensures consistent and correct data(2) covers all documented key requirements for 1st release(3) creates single customer view
Additional sponsor decisions: a) CRM system will be out-of-the box with minimal customization. b) project end date within 5 months.
Critical Success Factor
joint effort of all departments: consolidated, mutually agreed and documented key requirements within 2 weeks
6
accounting for user friendliness in front end design
2
account for training needs (content, headcount, budget, schedule) in project plan and budget
7
Stand-in for SME who has to support project
5
doc of agreed key requirements for first release
5
(1) All key requirements for 1st release documented for IT to proceed(2) Training needs of CC agents accounted for in project plan and budget(3) Stand-in for accounting / billing SME
Groups (each group casted 5 votes per category. In case of tie, sponsor decided) Resulting Priorities
Part II: Possible Simulation Results
Topic
Purpose(1) Need for consistent data (2) Need for single customer view(3) Need for single marketing application
Other projects -> to identify interdependencies
(1) New billing application(2) SOX compliance issues(3) Marketing plan 2009
Impact of delay
(1) Lack of flexible marketing campaigns(2) Churn(3) Profit loss due to inconsistent data.Note: Initial voting resulted in tie, new round results in brackets. Final priorities decided by sponsor breakting tie b/w (1) and (2).
SMART project objectives
Implementation of new CRM system which(1) ensures consistent and correct data(2) covers all documented key requirements for 1st release(3) creates single customer view
Additional sponsor decisions: a) CRM system will be out-of-the box with minimal customization. b) project end date within 5 months.
Critical Success Factor(1) All key requirements for 1st release documented for IT to proceed(2) Training needs of CC agents accounted for in project plan and budget(3) Stand-in for accounting / billing SME
Resulting Priorities
Part III: Summary of Results
Summary of prioritized project objectives and stakeholders’ expectations
Revisit open issues and/or action items -> assign owners, define due dates
Determine next steps getting project back on track.
Possibly
• Establish functional and non-functional requirements• Review the project governance structure• Adjust the project plan to meet the qualified and re-aligned
project objectives and stakeholders’ expectations
Common definition and understanding of the project objectives= critical to get project back on track and foundation for all consecutive project work
Prioritization guidelines for operational project work
Simple and effective team building exercise
Constructs a learning environment => promotes mutual understanding of all parties involved
Workshop Outcomes & Take Aways
Still: Workshop alone is NOT sufficient to re-align the project
objectives and stakeholders’ expectations
Instead: Workshop and outcomes help build a solid foundation to get the project back on track
Lessons Learned From Other Workshops
Workshop approach applicable to many situations
Minimum duration of workshop: 2-3 hours.
Longer = better (the more complex the longer)
Maximum number of attendees: 20
All key stakeholders attend; all have decision making authority
Experienced facilitator
Prior stakeholder interviews -> build trust and understanding
Thorough preparation and team support
Last but not least, every workshop has its own dynamics
Q & A
Available for additional Q&A after workshop session
Contact Information:Thomas Juli, Ph.D., PMPManaging Director