Page 1: Project for developing the Date Sector in  Jericho and the Jordan Valley

Moon Valley Date Factory

Project for developing the Date Sector in

Jericho and the Jordan Valley

Page 2: Project for developing the Date Sector in  Jericho and the Jordan Valley

Moon Valley Date Factory• It was

established in 2009 by PARC, and it is run by Al Reef Company, which is the commercial arm of PARC.

Page 3: Project for developing the Date Sector in  Jericho and the Jordan Valley

Capacity: 500 kg

per hour.

Page 4: Project for developing the Date Sector in  Jericho and the Jordan Valley

Project area: 12000 m2

Location: JerichoComponents of the

Project: 1. Refrigerators for storing

the dates with a storage capacity of 400 tonnes

2. Filling and packaging lines

3. Sun-drying facilities4. Filling station of 616 m2

5. Lab for quality analysis6. Two vehicles for

distribution

Page 5: Project for developing the Date Sector in  Jericho and the Jordan Valley

Production capacity: 1 ton per hourJob creation: 30 employees (men and women)

Number of farmer beneficiaries: 45 (450 beneficiaries when including the farmers’ families)

Page 6: Project for developing the Date Sector in  Jericho and the Jordan Valley

Capacity of the quantity of dates in the Jordan valley

- 1000 ton medjoul dates

- 1900 ton different varieties like Baladi, Hiyani, Barhi, Zheidi

Note: annual increase from medjoul dates is around 25%

Page 7: Project for developing the Date Sector in  Jericho and the Jordan Valley

Markets

Export medjoul dates to different international markets like Italy, Belgium, France, Britain, new Zealand, USA, UAE, plus the local market.

Page 8: Project for developing the Date Sector in  Jericho and the Jordan Valley
Page 9: Project for developing the Date Sector in  Jericho and the Jordan Valley

Use of the Loan: construction and rehabilitation process in the dates factory in Jericho

• 1. Build 120 meter of offices in front of the factory

Page 10: Project for developing the Date Sector in  Jericho and the Jordan Valley

During Work

Page 11: Project for developing the Date Sector in  Jericho and the Jordan Valley

2. Rehabilitate the walls around the warehouses (fridges) by adding a cement cover.

Page 12: Project for developing the Date Sector in  Jericho and the Jordan Valley

3. Fix the gate of the warehouses (fridges)

Page 13: Project for developing the Date Sector in  Jericho and the Jordan Valley

4. Provide a generator for the factory.

Page 14: Project for developing the Date Sector in  Jericho and the Jordan Valley

5. Rehabilitate a road from the main street to the factory and plant palm trees on the sides.