International Public Bid:
ENERGY SECURITY AND SOUTHERN GAS PIPELINE
ENERGY SECURITY AND SOUTHERN
GAS PIPELINE
CALLED
� Location: Cusco, Arequipa and Moquegua.
� Description: This project comprises the concession to design, finance,build, operate, maintain and transfer a transport natural gas system withthe following components:
� Reinforcement works of pipelines from the Separation Plant ofMalvinas to the Compression Station at Chiquintirca.
� Construction of natural gas pipelines and/or liquid gas pipelinesfrom the existing natural gas transport system (between Malvinasand Chiquintirca) to Anta (Cusco Region) able to supply natural gasto the future thermal plant of Quillabamba and south coast of thecountry.
� Construction of the Southern Gas Pipeline from Anta to south coastof the country.
� Type of concession: Self-sustained
• Estimated Investment (VAT not included): US$ 2,431 Million.
• Competition Factor: The lowest cost per transport services.
� Current status: Enquires to the Bidding Documents.
� Estimated award date: I QT 2014.
ENERGY SECURITY AND SOUTHERN
GAS PIPELINE
PISCOPISCO
LIMA (Lurín)LIMA
(Lurín)
HUMAY
HUANCAVELICA
AYACUCHO
APURIMAC
AREQUIPA
MOQUEGUA
MADRE DE DIOS
TACNA
CUSCO
PUNO
CUSCO
PUNO
CHILECHILE
BOLIVIABOLIVIA
BRASILBRASIL
LAGOTITICACA
LAGOTITICACA
ENERGY SECURITY (Gas Pipeline)ENERGY SECURITY (Gas Pipeline)
AREQUIPA
MALVINAS
TGP (CURRENT SYSTEM + LOOP COAST) Gas and Liquid PipelinesTGP (CURRENT SYSTEM + LOOP COAST) Gas and Liquid Pipelines
JULIACAMARCONAMARCONA
ICA
CONTUGAS (CURRENT SYSTEM)CONTUGAS (CURRENT SYSTEM)
Pampa Melchorita
Pampa Melchorita
PERU LNG (GAS PIPELINE)PERU LNG (GAS PIPELINE)
LoopTGPLoopTGP
CURRENT
PLANNED
LOOP TGP (KM 88 – KM 127)LOOP TGP (KM 88 – KM 127)
SOUTHERN GAS PIPELINESOUTHERN GAS PIPELINE
ANTA
ESPINAR
ENERGY
SECURITY ZONEQUILLABAMBA
CHIQUINTIRCA
ENERGY SECURITY (Liquids Pipeline)ENERGY SECURITY (Liquids Pipeline)
Km 127
Km 88
ABANCAY
PETROCHEMICAL COMPLEX AND
ENERGY NODE LOCATION
Basic Features:
a) Gas Pipeline from the Connection Point to the Current System (CP) up to Mollendo/Ilo.
– Gas Pipeline from the CP to Anta Province (includes connection to Quillabamba).
– Gas Pipeline from Anta Province to Mollendo/Ilo (includes connection to Apurímac, Puno and Tacna).
b) Gas Pipeline and Liquids Pipeline from the Separation Plant of Malvinas to CP.
c) Gas Pipeline and Liquids Pipeline from the CP to the Compression Station at Chiquintirca.
ENERGY SECURITY AND SOUTHERN
GAS PIPELINE
CP
SCHEDULE
Inquiries to the
Terms
Nov 11th
2013
Jan 10th
2014
Answers to the
inquiries to the
Terms
Jan 16th
2014
Qualification
(Envelope N° 1)
Jan 17th
2014
Announcement of
short listed Bidders
Delivery of final
contract version
Feb 13th
2014
Call for tenders and
publication of
Tenders Documents
Feb 24th
2013
Submission of
Envelopes N° 2 and
N° 3
I QT
2014
Award
Closing Date
Nov 04th
2013
Feb 17th
2014
CONTACT INFORMATION
66
Eng. Luis Sánchez Torino Head of Energy Security Projects
Telephone (51-1) 200-1200 extension 1213
[email protected]@proinversion.gob.pe