Upload
kopila
View
3.518
Download
1
Tags:
Embed Size (px)
DESCRIPTION
This is presentation on PPP in Urban Transport Sector for Mumbai Metro
Citation preview
MUMBAI METRO ONEPPP session
Faisal Khan
Presentation Plan
Present Scenario of transport infrastructure in Mumbai
Project DescriptionBidding selectionPPP structure of the ProjectRisk allocation framework
Present Transport Scenario in Mumbai
11 million people travel daily by Public Transport (share of PT more than 90%) Many areas in city and suburbs are not served by rail system Suburban rail traffic increased by 6 times while the capacity increased by only 2.3 times 4500 passengers travel per train against the carrying capacity of 1750 resulting in unbearable overcrowding
Project Description
Consists of three phases Phase I, II, III Phase I – Versova-Andheri-Ghatkopar line with dedicated elevated corridor and of length 11.07 km with 12 stations Rail to have maximum speed of 80kmph with average speed of 33kmph Project will provide East-West rail based connectivity to Central and Western suburbs Total time for journey from Versova to Ghatkopar would be approximately 21 minutes as against 90 minutes by other modes of transport
Bidding Selection Detailed feasibility study carried out under the Indo-
German technical co-operation to the group of TEWET, DE-Consult and TCS during 97-00
Study recommended mass transit corridor from Andheri to Ghatkopar as potentially bankable and economically viable – Government decided to go on PPP basis
Management of transaction process – Consortium of Louis Berger as technical consultants, PwC, Masons and Economic Laws and Practices was appointed to assisst MMRDA
Bids invited in August 2004 and 150 bidders responded to EoI
Bid process: Technical and financial stage
Bidding selection contd.. Technical bids invited in May 05
HCC and RITES Reliance Energy Limited, Veolia Transport, Connex-France Shaktikumar Sacheti Limited and Lingakaran Metro Siemens, L&T, Gammon, BEML IL&FS, ITD Thailand and Unity Infraprojects
Financial bids invited from qualified bidders in January 06 Reliance Energy Limited and Connex-France IL&FS, ITD Thailand and Unity Infraprojects
Bid Won by consortia of Reliance Energy Limited, Veolia Transport, Hong Kong MRT & Connex France
Bidding Selection contd.. Expected IRR of 26% by REL-led consortium
but government negotiated and the consortium agreed to an equity IRR of 15%
Project faced delay in obtaining approval for VGF as its concession agreement was based on MCA of NHAI and only tentative guidelines were in place for PPP agreements
Government gave special grant of 20% and GoM approved grant of 7.5% of project cost
SPV incorporated in December 2006 by the name
‘Mumbai Metro One Private Limited’
Financial Model
Project Cost INR 2356 Crores
Viability Gap Funding INR 650 Crores
Debt:Equity 70:30
Total Equity INR 513 Crores
MMRDA Equity (26%) INR 134 Crores
Reliance Energy (69%) INR 353 Crores
Connex-France (5%) INR 26 Crores
Debt INR 1194 Crores
PPP structure of project
Connex-France & others
Reliance Energy Ltd
Indian Bank, Oriental Bank of
CommerceIDBI,
Corporation Bank
Canara Bank, Karur Vysya Bank
MMRDA
EPC Contractor
s5%
69% 26%MMOPL
Risk Allocation FrameworkRisk Type Sensitivity Risk Period (yrs) Risk Bearer
Land acquisition High 0-5 Government
Financing Risk Medium 0-5 Private sector
Regulatory, Administrative appr.
Low 0-5 Private sector
Design Risk Medium 0-5 Private sector
Construction Risk
Medium 0-5 Private sector
Change in scope risk
Low 0-5 Government
Financing risk Medium 0-5 Private sector
Technology risk Low 0-35 Private/Govt
O&M risk Medium 0-35 Private sector
Market risk High 0-30 Private sector
Performance risk High 0-30 Private sector
Default risk Low 0-35 Defaulting party
Force Majeure Low 0-35 Shared
Thank You for Listening