Upload
detourgold
View
8.922
Download
1
Tags:
Embed Size (px)
Citation preview
Building Canada’s Largest Gold MineProduction Early 2013
Corporate Presentation July 24, 2012
© 2011 Detour Gold All Rights Reserved. 2
This presentation contains certain forward-looking information as defined in applicable securities laws (referred to herein as “forward-looking statements”). Specifically, this presentation contains forward-looking statements regarding the reserve and resource estimates, ore grade, expected mine life, anticipated gold production, gold recovery, cash operating costs and other costs, capital costs, sensitivity to metal prices and other sensitivities, financial analysis of the project, commencement of operations, potential expansion opportunities, plans for organic growth and expected drilling activities. Forward-looking statements involve known and unknown risks, uncertainties and other factors which are beyond Detour Gold’s ability to predict or control and may cause Detour Gold’s actual results, performance or achievements to be materially different from any of its future results, performance or achievements expressed or implied by forward-looking statements. These risks, uncertainties and other factors include, but are not limited to, gold price volatility, changes in debt and equity markets, the uncertainties involved in interpreting geological data, increases in costs, environmental compliance and changes in environmental legislation and regulation, interest rate and exchange rate fluctuations, general economic conditions and other risks involved in the gold exploration and development industry, as well as those risk factors discussed in the section entitled “Description of Business - Risk Factors” in Detour Gold’s 2011 AIF and in the continuous disclosure documents filed by Detour Gold on and available on SEDAR at www.sedar.com. Such forward-looking statements are also based on a number of assumptions which may prove to be incorrect, including, but not limited to, assumptions about the following: the supply and demand for gold, and the level and volatility of the price of gold; the availability of financing for exploration and development activities; the estimated timeline for the development of the Detour Lake gold project; the expected mine life; anticipated gold production; gold recovery; the development schedule; cash operating costs and other costs; the financial analysis for the project; capital costs; sensitivity to metal prices and other sensitivities; the accuracy of reserve and resource estimates and the assumptions on which the reserve and resource estimates are based; the receipt of necessary permits; market competition; ongoing relations with employees and impacted communities; and general business and economic conditions. Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking statements contained herein are made as of the date hereof, or such other date or dates specified in such statements. Detour Gold undertakes no obligation to update publicly or otherwise revise any forward-looking statements contained herein whether as a result of new information or future events or otherwise, except as may be required by law. If the Company does update one or more forward-looking statements, no inference should be drawn that it will make additional updates with respect to those or other forward-looking statements.
Forward Looking Information
© 2011 Detour Gold All Rights Reserved. 3
Information Concerning Estimates of Mineral Reserves and Resources
The mineral reserve and resource estimates reported in this presentation were prepared in accordance with Canadian National Instrument 43-101Standards of Disclosure for Mineral Projects (“NI 43-101”), as required by Canadian securities regulatory authorities. For United States reporting purposes, the United States Securities and Exchange Commission (“SEC”) applies different standards in order to classify mineralization as a reserve. In particular, while the terms “measured,” “indicated” and “inferred” mineral resources are required pursuant to NI 43-101, the SEC does not recognize such terms. Canadian standards differ significantly from the requirements of the SEC. Investors are cautioned not to assume that any part or all of the mineral deposits in these categories constitute or will ever be converted into reserves. In addition, “inferred” mineral resources have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian securities laws, issuers must not make any disclosure of results of an economic analysis that includes inferred mineral resources, except in rare cases.
On January 31, 2011, Detour Gold announced an updated mineral resource and reserve estimate. The following QPs participated in this update: Michel Dagbert, Eng., Senior Geostatistician and André Laferrière, P. Geo., Senior Geologist of SGS Canada Inc. (mineral resources); and André Allaire, Eng., Director Mining and Metals and Patrice Live, Eng., Mining Manager of BBA Inc (mineral reserve). The NI 43-101 compliant Technical Report for this update was filed on SEDAR on March 15, 2011.
On January 25, 2012, Detour Gold announced a mineral resource and reserve update. The following QPs participated in this update: Michel Dagbert, Eng., Senior Geostatistician of SGS Canada Inc (mineral resources) and Patrice Live, Eng., Mining Manager of BBA Inc (mineral reserves).
NI 43-101 Disclosure
© 2011 Detour Gold All Rights Reserved. 4
Focus on a world-class asset – Detour Lake Canada’s largest pure gold play with 15.6 M oz in reserves
(@ US$ 850/oz gold price) Construction progressing on schedule (75% as of June 30)
One of the best cash flow/share opportunities Gold production starting in Q1 2013 Excellent organic growth potential (5 year plan) Potential expansion of mill throughput
Invest in Detour Gold
© 2011 Detour Gold All Rights Reserved. 5
Issued and Outstanding:
112.6 M
Options & FN Share Commitments:
8.7 M =Fully Diluted:
134.3 M
Market cap: C$2.4 Billion Cash position: C$576 Million Major shareholders:
Convertible Notes:13.0 M
Paulson & Co. 15%
Fidelity Mgmt 8%
Detour Gold Mgmt <2%
Institutions total >90%
Share Capital
Detour LakeDetour Lake
+ +
Note: Share data and cash position as of June 30, 2012.
© 2011 Detour Gold All Rights Reserved. 6
Strong Share Performance
Osisko (239%)
Yamana
Randgold
Eldorado
Buenaventura
NewcrestIMG
KinrossAndina
HeclaGabriel
Anglo Gold AshantiAEM
GoldfieldsCG
NEM
AGI
Aurizon GABX
GSC
DGC11/09DGC11/09
DGC07/10DGC07/10
Jan. 2007 to Present % Change in Shares Outstanding100
150
0 50 200
Share Issuance vs. Performance
Source: BMO, June 2012
IPOIPO
DGC07/09DGC07/09
DGC04/08DGC04/08
DGC08/11DGC08/11
Ja
n.
20
07
to
Pre
se
nt
Tota
l R
etu
rn
400%
300%
200%
100%
0%
-100%
500%
600%
700%
800%
900%
1000%
500% total return since IPO
DGC01/12DGC01/12
DGC equity financings
AuRicoEco Oro
Great Basin (209%)
© 2011 Detour Gold All Rights Reserved. 7
DETOUR LAKE: RECORD TIMING FROM “DISCOVERY” TO PROJECTED PRODUCTION
6 years
Acquisition/Discovery
2007
Pre-feasibility Study2009
Feasibility Study & Permitting
2010
Development2011-2012
Production 2013
Successful Focused Approach
© 2011 Detour Gold All Rights Reserved. 8
Mineral reserves/resources update for 2011 year-end Top up of $277 million to complete the project and working capital Second 45 km segment of transmission line complete 230 kV transmission line connection in Q3 Updated mine plan & operational forecast in Q3 Ore stockpile of 3 Mt available in Q4 for processing Process plant commissioning in Q4 Manpower ramp-up to 400 (now 277 employees at site and Cochrane) Delivery of 12 haul trucks and 2 cable shovels
Detour Gold 2012 Objectives
© 2011 Detour Gold All Rights Reserved. 9
2005-05
2006-09
Date AccumulativeDGC Drilling Resources/Reserves (M oz) Inferred M&I 2P
Growing Reserve/Resource Base
RESOURCE GROWTH EXCEEDING 750% SINCE IPO
2007-12 50,000m
2008-06 123,000m
2012-01 523,000m $850/oz 15.6
2011-01 430,000m $850/oz 14.9
2010-06 334,000m $850/oz 11.4
2009-09 249,000m 8.8
Estimated by Pelangio
DGC due diligence
10M 20M 30M
© 2011 Detour Gold All Rights Reserved. 10
As at Dec. 31, 2011
@ US$850/ozTonnes
(millions)Grade(g/t)
Contained Gold(‘000 oz)
Reserves (1)
Proven 101.6 1.29 4,222
Probable 368.4 0.96 11,351
P&P 470.0 1.03 15,573
Resources (2)
Measured 124.5 1.36 5,424
Indicated 554.3 1.00 17,836
M&I 678.8 1.07 23,261
Inferred 208.5 0.86 5,785
1. After a 95% mining recovery rate; Mining dilution factor of 15.5%.2. Inclusive of mineral reserves.
DISCOVERY COST < $10/oz OF RESERVES
Detour Lake Reserves & Resources
© 2011 Detour Gold All Rights Reserved. 11
Detour Lake Profile (@ US$850/oz)
>1.0 g/t Au
0.5 - 1.0 g/t Au
<0.5 g/t Au
20,600E
16,500E
700 m
Open pit@ 0.5 g/t cut-off
Detour LakeJanuary 2012
update
Production start Q1 2013
OP reserves (M oz) 15.6
Mill throughput (tpd) 55,000
Strip ratio (waste:ore) 3.6
Gold recoveries 91%
Average grade (g/t) 1.03
Estimated mine life (yrs) 22
Avg. production (oz/yr)(1)(2) 657,000
Initial Capex (C$ B)(3) 1.45
1. After full commissioning in Yr 1.2. Based on March 2011 TR.3. Initial capex revised in November 2011.
© 2011 Detour Gold All Rights Reserved. 12
2012E Cash Cost Profile (US$/oz)*
JuniorProducers
SeniorProducers
IntermediateProducers
$ 796
$ 706 $ 706
$ 800
$ 700
$ 600
$ 500
*Source: BMO Equity ResearchSeniors Producers include: Agnico-Eagle, AngloGold Ashanti, Barrick, Gold Fields, Goldcorp, Kinross, Newcrest, Newmont, Polyus and Yamana.Intermediate Producers include: African Barrick, Alacer, AuRico, Centamin Egypt, Centerra, Eldorado, Harmony, IAMGold, New Gold, Osisko, Petropavlovsk, Randgold and SEMAFO.Junior Producers include: Alamos Gold, Aurizon, Avion, Avocet, CGA Mining, Cluff Gold, Dundee Precious Metals, Golden Star, Great Basin Gold, Kingsgate, Lake Shore, OceanaGold, Perseus, Primero, Resolute, San Gold and Teranga.
Total Cash Costs
Since 2010 (release of Feasibility Study), inflationary pressure seen in operating costs
25%
14%
13%13%
7%
4%
24%Maintenance Consumables
Royalty(2%
NSR)G&A
DieselPower
Labour
Approx. % of total cash cost/oz in FS1
1. Total estimated cash cost of US$543/oz based on March 2011 TR using cost parameters from feasibility study, including US$850/oz gold price and US$80/barrel oil.
© 2011 Detour Gold All Rights Reserved. 13© 2011 Detour Gold All Rights Reserved. 13
Mine Site ConstructionProgressing on Schedule
© 2011 Detour Gold All Rights Reserved. 14
2010 2011 2012 2013
Construction Schedule Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Award of Engineering Contract
Award of PCM Contract
Detailed Engineering
Construction camp (1,200 people)
Power line (Phase 1&2) – Electrification
Equipment purchase/delivery & assembly
Pre-stripping
Process plant – Commissioning start-up
Tailings dam construction (first cell)
Provincial Permits/Aboriginal IBAs
Federal Permits
Start production and ramp-up
Detour Lake: We are on ScheduleDetour Lake: We are on Schedule
1 2
GOLD PRODUCTION PROJECTED IN 1Q 2013
© 2011 Detour Gold All Rights Reserved. 15
Capital Expenditures (C$ M)
Description
SpentJune 30,
2012
CommittedJune 30,
2012
Project Control Estimate
(as of 11/2011)
Mining Fleet and Facilities 142 181 203
Crushing and Processing (P&E) 421 610 565
Tailings and Water Mgmt 16 45 65
Infrastructure and Power line 139 150 156
Other Indirect 167 206 310
EPCM 84 100 101
Contingency (10%) - 1 50
Total (pre-production) 969 1,294 1,450
PROJECT CONSTRUCTION 75% COMPLETE
Detour Lake: We are on Budget
© 2011 Detour Gold All Rights Reserved. 16
2012 Pre-Stripping
Feasibility Study
PCE(11/2011)
Status (06/30/2012)
Overburden/Till 16 Mt 21 Mt 7.0 Mt
Waste - 10 Mt 2.4 Mt
Ore 3 Mt -
Estimated Cost C$30 M C$78 M -
PROJECT CHANGE OF SCOPE
= A BENEFIT
Ore available for processing in 2012
Ore ready to be processed by the fourth quarter of 2012 Pre-production capital costs include $78 M for pre-strip activities 10 Mt mined to date with daily rates >100,000 t Plan to have up to 3 Mt of ore ready for process
2012 Operational Readiness Plan
© 2011 Detour Gold All Rights Reserved. 17
Mining is Ramping Up
© 2011 Detour Gold All Rights Reserved. 18
Mining is Ramping Up
© 2011 Detour Gold All Rights Reserved. 19
8 CAT 795F trucks operational + 6 assembled (includes 2 supplied by CAT);
2 CAT 6060FS shovels in operationShovel CAT 7495 (48 m3) to be ready
late summer
Initial Mining Fleet at Site
Loading Units3 X Hydraulic CAT6060 (25 m3)2 X Electric cable shovels (48 m3)
Haulers
23 X CAT 795F trucks (320 t);30-35 at peak of operation
© 2011 Detour Gold All Rights Reserved. 20
135 km
Powerline45 kmPowerline
Detour Lake Development Progress
Gravel (34 km)135 km
Powerline
Paved road (151 km)
45 kmPowerline
Detour Lake
Second 45 km segment of powerline complete
Pre-stripping program ongoing Installation of mill equipment
underway (first grinding line mechanical installation is 90% complete)
Installation of equipment in gold room underway
Commissioning with water started for leach tanks
Truck wash facilities complete Permanent camp construction
completed
© 2011 Detour Gold All Rights Reserved. 2121Note: Open pit reserves using US$850/oz goldNote: Open pit reserves using US$850/oz gold
Detour Lake Mining FacilitiesDetour Lake Mining Facilities
© 2011 Detour Gold All Rights Reserved. 22
12-06-08
Overview Detour Lake Facilities
Truck Wash
Truck Shop & Warehouse
Mine Offices
Processing Plant
© 2011 Detour Gold All Rights Reserved. 23
Overview Detour Lake Facilities
12-07-13
Primary Crusher
Stockpile Reclaim
Secondary Crushers
Geodesic Dome
© 2011 Detour Gold All Rights Reserved. 24
Gyro is 9 m high
Primary Crusher (up to 100,000 tpd capacity)
35 m
Surface
12-07-13
© 2011 Detour Gold All Rights Reserved. 25
Stockpile Reclaim
12-07-13
Geodesic Dome for Stockpile Reclaim
Secondary and Pebble Crushers
12-06-08
© 2011 Detour Gold All Rights Reserved. 26
SAG Mills
12-06-08
Ball Mills
Processing Plant Building
© 2011 Detour Gold All Rights Reserved. 27
Processing Plant Building
Hydrocyclones
CIP Tanks
12-06-08
Pumps
© 2011 Detour Gold All Rights Reserved. 28
Conventional gravity and CIP plant 55,000 tpd (=92% availability of 60,000
tpd capacity) 2 parallel lines (each with 1 secondary
cone crusher + 1 SAG and 1 ball mill)
A
A
Simple Process Plant
Estimated gravity recovery: 30-40% Estimated overall gold recovery: 91.0% Leach time 29 hours Leach feed size 80% passing 95 μm
© 2011 Detour Gold All Rights Reserved. 29
Detour Lake Employees & Contractors
Construction Phase >1,550 workers (currently) Ramping up DGC team (277)
Operation Phase (Starting 2013) 400-500 employees Rotation 1 week in /out New modern camp facilities with
400 en-suite rooms completed
© 2011 Detour Gold All Rights Reserved. 30
Focus: Hiring Local First
28%
24%
43%
3%2%
CochraneCochrane AreaNorthern OntarioRest of Ontario
Professional are: MGMT, Eng., Geo., Supt. Front Line are: Operators, Admin, Support Continuing focus on hiring local/regional 25% of employees are Aboriginals
24%
76%
ProfessionalFront Line
Yr-end 2012 Employment Objective:
301/400 as of June 30, 2012*
* Includes Corporate office.
© 2011 Detour Gold All Rights Reserved. 31© 2011 Detour Gold All Rights Reserved. 31
Planning for Organic GrowthUnder-explored Greenstone Belt
© 2011 Detour Gold All Rights Reserved. 32
Large prospective land position of approx. 540 km2
Land position increased with acquisition of Trade Winds properties Two main gold structures with total strike length of >80 km Continue focus on Detour Lake deposit extension (northern structure) Test targets on structure south of Detour Lake
Future Objectives Grow reserve base to +20 M oz (@ US$850/oz) Increase mill throughput to above 75,000 tpd for gold production
output of +800,000 oz/yr Find high-grade ore near-surface within trucking distance to
supplement mill
5 yr plan for successful organic growth
Planning for Organic Growth
© 2011 Detour Gold All Rights Reserved. 33
Priority #1 on Block A Area between Block A open pit resource (M-Zone) and the
underground QK Zone discovered by Placer in mid-90’s Drilling program of 50,000 m in 1H 2012 Start pre-feasibility study for small open pit (Block A resource) Advance exploration of QK underground zone
Priority #2 on Lower Detour Deformation Zone (+40 km) 5,060 m of diamond drilling completed: N-S drill fence on high-grade drill
hole intercepts (53 g/t Au / 3 m & 22.6 g/t Au / 1 m) 115 km of IP geophysical survey completed Geological and structural mapping; data compilation
2012 Plan for Successful Organic Growth
© 2011 Detour Gold All Rights Reserved. 34
*Not updated with TWD Dec. 30th PR. On Dec. 1, 2011, Detour Gold announced the acquisition of TWD.
Planning for Organic Growth
Deposit open to the west and at depth +50,000 m of drilling for 2012 (Block A open pit above QK Zone)
2012 target
© 2011 Detour Gold All Rights Reserved. 35
Block A near-surface resource
Detour Lake 2011 year-end reserves = 15.6 M oz
Priority # 1 - Block A Target
DH included in 2011 year-endreservesDH not included in 2011 year-endreserves
2012 proposed DH2012 extension DH
Historical DH
© 2011 Detour Gold All Rights Reserved. 36
Priority # 1 - Block A Target
July 14, 2012
2012 proposed DH2012 extension DH2012 completed DHHistorical DHCancelled or not accessible
2011 year-end reserves = 15.6 M oz
Block A2012 Drilling Program
•HQ geotechnical drill core (Golder and Ass.) is being stored on pallets at the McAlpine Camp until we can free up manpower to log it and prepare it for shipment.
© 2011 Detour Gold All Rights Reserved. 37
Existing DDHGold occurrence (OGS)DDH intersection >1g/2mDDH intersection >1g/10m
*Note: Excludes drilling around Detour Lake and M zone (Block A).
+80 km of favourable geology
Insert- see next slide
MMI Survey Coverage
MMI Au Anomaly
Planning for Organic Growth
Sunday Lake Option
15.6 M oz in Reserves
© 2011 Detour Gold All Rights Reserved. 38
Planning for Organic Growth
Completed drilling
© 2011 Detour Gold All Rights Reserved. 39
?
?
Planning for Organic Growth
© 2011 Detour Gold All Rights Reserved. 40
2013
2012
2014
Best scenario is throughput increase from 55,000 to 75,000 tpd @ US$1,200/oz
Start pre-feasibility on Block A
Complete feasibility study and assess technical feasibility and resultant project economics
At >US$1,000/oz and after successful commercial production is achieved, proceed with plant expansion
Complete expansion in 2 years
Evaluating Expansion Opportunities
© 2011 Detour Gold All Rights Reserved. 41
Focus on a world-class asset – Detour Lake Canada’s largest pure gold play with 15.6 M oz in reserves
(@ US$ 850/oz gold price) Construction progressing on schedule (75% as of June 30)
One of the best cash flow/share opportunities Gold production starting in Q1 2013 Excellent organic growth potential (5 year plan) Potential expansion of mill throughput
Invest in Detour Gold
© 2011 Detour Gold All Rights Reserved. 42© 2011 Detour Gold All Rights Reserved. 42
Additional Information
© 2011 Detour Gold All Rights Reserved. 43
Detour Lake – Surface Plan
2011 Year-end reserves = 15.6 M oz
DH included in the 2011 year-endreserves
DH not included in the 2011 year-endreserves
Pre 2007 DH
© 2011 Detour Gold All Rights Reserved. 44
QK Zone
Looking 20,070 N
Detour Lake – Long Section
DH included in the 2011 year-endreserves
DH not included in the 2011 year-endreserves
Pre 2007 DH
© 2011 Detour Gold All Rights Reserved. 45
1,600
1,400
1,200
1,000
800
600
400
200
0
Oun
ces
(000
’s)
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 3.0
Cut-off BINs
OK (oz Au)ID3 (oz Au)
Approx. 3 M oz. between 0.3-0.5 g/t Au
Block Model - Gold Distribution
© 2011 Detour Gold All Rights Reserved. 46
Directors
Peter CrossgroveLouis DionneRobert E. Doyle
Ingrid HibbardMichael KenyonAlex G. Morrison
Gerald PannetonJonathan RubensteinGraham Wozniak
Management Gerald Panneton, Founder, President &
CEO, Director Michael Kenyon, Chairman Paul Martin, CFO Pierre Beaudoin, Sr. VP Capital Projects Pat Donovan, VP Corporate Development Julie Galloway, VP General Counsel &
Corporate Secretary James Mavor, VP Finance Rachel Pineault, VP HR & Northern
Affairs James Robertson, VP Environment &
Sustainability
Derek Teevan, VP Aboriginal & Government Affairs
Eric Josipovic, Controller Drew Anwyll, Director of Operations Andrew Croal, Dir. Technical Services Laurie Gaborit, Dir. Investor Relations Jean-François Métail, Director Reserves
and Resources Greg Miazga, Dir. Construction &
Engineering Bill Snelling, Director Corporate Systems
and Controls Christian Brousseau, Project Manager Patrik Gillerstedt, Mine Manager
Management & Directors
© 2011 Detour Gold All Rights Reserved. 47
© 2011 Detour Gold All Rights Reserved. 47
Gerald Panneton, President & CEO Email: [email protected] Ph: 416 304 0800
Laurie Gaborit, Director Investor RelationsEmail: [email protected] Ph: 416 304 0800
www.detourgold.com
Contact Information